Biaya Project PLTS Rooftop
Biaya Project PLTS Rooftop
Biaya Project PLTS Rooftop
Total
DOCUMENT NO TITLE Man Days (MD)
Electrical Civil Drafter
A. ELECTRICAL
A.1 SPECIFICATION
A.1.1 Solar PV Module (Frame and Frameless) 0,5 - -
A.1.2 Inverter & Solar Controller 0,5 - -
A.1.3 AC/DC Combiner 0,5 - -
A.1.4 Low Voltage Panel 0,5 - -
A.1.5 Pyranometer 0,5 - -
A.1.6 Low Voltage Cable (AC/DC) 0,5 - -
A.1.7 Control System 0,5 - -
A.1.8 Lightning protection & Grounding 0,5 - -
A.1.9 Cable Tray & Ladder 0,5 - -
A.2 DRAWING
A.2.1 General Layout 0,5 - 0,5
A.2.2 Overall Single Line Diagram 0,5 - 0,5
A.2.3 Detailed Single Line Diagram for equipment (DC Combiner, AC Combiner, LV Panel) 0,5 - 0,5
A.2.4 Interconection PLTS to Existing grid 0,5 - 0,5
A.2.5 Control System Architecture 0,5 - 0,5
Typical Cable Installation and cable raceway (underground, above ground on
A.2.6 0,5 - 0,5
tray/ladder))
A.2.7 Typical termination drawing LV Cable (at inverter, at AC Combiner, at LV panel) 0,5 - 0,5
Typical termination drawing DC Cable (inter-solar module wiring, termination at DC
A.2.8 0,5 - 0,5
Combiner, termination at Inverter)
A.2.9 Typical Lightning & Grounding system (include protective earthing) installation 0,5 - 0,5
A.2.10 Typical Lightning & Grounding System Schematic 0,5 - 0,5
A.2.11 Lighting Layout 0,5 - 0,5
A.2.12 Typical Lighting Installation Drawing 0,5 - 0,5
A.2.13 Typical Lighting Installation schematic 0,5 - 0,5
A.3 CALCULATION
A.3.1 Solar irradiation and energy yield simulation 1 - -
A.3.2 Protection coordination 1 - -
Equipment Sizing Calculation (DC Combiner, AC Combiner, Inverter, LV Panel (busbar,
A.3.3 1 - -
breakers, fuse, etc))
A.3.4 Cable Sizing Calculation 1 - -
A.3.5 Grounding Calculation 1 - -
A.3.6 Lighting Calculation 1 - -
A.4 LIST
A.4.1 Cable Schedule 1 - -
A.4.2 Equipment list 1 - -
Final Document Revision 6 - 5
Total
DOCUMENT NO TITLE Man Days (MD)
Electrical Civil Drafter
B. CIVIL
B.1 SPECIFICATION
B.1.1 Specification for General Work - 1 -
B.2 DRAWING
B.2.1 General Plot Plan @ Muara Tawar
- Gedung UPMKR - 0,5 0,5
- Gedung CCR - 0,5 0,5
- Gedung Water Intake - 0,5 0,5
- Gudang Utama - 0,5 0,5
- Gedung UPHB - 0,5 0,5
General Plot Plan @ Kantor Pusat
- Gedung A - 0,5 0,5
- Gedung C - 0,5 0,5
- Gudang & GI 20 kV - 0,5 0,5
- Gedung D - 0,5 0,5
B.2.2 Structure & Mounting for PV Module @ Muara Tawar
- Gedung UPMKR - 0,5 0,5
- Gedung CCR - 0,5 0,5
- Gedung Water Intake - 0,5 0,5
- Gudang Utama - 0,5 0,5
- Gedung UPHB - 0,5 0,5
Structure & Mounting for PV Module @ Kantor Pusat
- Gedung A - 0,5 0,5
- Gedung C - 0,5 0,5
- Gudang & GI 20 kV - 0,5 0,5
- Gedung D - 0,5 0,5
B.3 CALCULATION
B.3.1 Roof Structure Assessment for Mounting PV Module @ Muara Tawar
- Gedung UPMKR - 1 -
- Gedung CCR - 1 -
- Gedung Water Intake - 1 -
- Gudang Utama - 1 -
- Gedung UPHB - 1 -
Roof Structure Assessment for Mounting PV Module @ Kantor Pusat
- Gedung A - 1 -
- Gedung C - 1 -
- Gudang & GI 20 kV - 1 -
- Gedung D - 1 -
B.3.2 Foundation/Mounting Calculation For PV Support (Typical) - 1 -
Final Document Revision - 5 5
TOTAL MAN DAYS 25 25 25
No Engineer Jumlah Unit Rate Total
1 Civil Engineer 25 MD 1.000.000 25.000.000
2 Electrical Engineer 25 MD 1.000.000 25.000.000
3 Drafter 25 MD 1.000.000 25.000.000
TOTAL 75.000.000