Professional Documents
Culture Documents
Integrity Management - Ii (Pipeline Operation and Maintenance)
Integrity Management - Ii (Pipeline Operation and Maintenance)
Integrity Management - Ii (Pipeline Operation and Maintenance)
Author
Rajib Kumar Dey
General Manager, ONGC Ltd. Uran
Maharashtra, India
Co-Author
Srivatsan K. Iyengar
TD Williamson India Pvt. Ltd.
Vadodara, Gujarat, India
Carbon Composite Application
• Uran Plant has two Gas Sweetening Units that remove acidic components
(CO2 &H2S) from the natural gas received from Western Offshore Fields.
Operation of these units is based on Shell Sulfinol Process.
• Surface was prepared considering the thinned areas LTA1 and LTA2.
Pitted surfaces were applied with filler putty and evenly
scrubbed off on proper curing. HT- 700 Primer was applied on
surface of column circumferentially around 700 mm height above
insulation ring-2 followed by application of RES-Q wrapping 7 layers
on both the repair locations(LTA1&2). Service Provider carried out
the Composite Application. Third Party Inspection was done by M/S
Global Tech Solutions.
Mock up test
Application on Regeneration Column
• On satisfactory clearance on surface preparation (Cleanliness ST-2 and anchor profile 2-4mils)
the primer (HT Primer-700 was applied on the surface of Column circumferentially around
700mm height above insulation ring – 2 (Identified area of interest for repair) followed by
application of RES-Q ® wrapping 7 layers on both the repair locations (i.e. LTA-1 & LTA-2) and
rest of the area, 4layers were applied as per approved procedure No. TDWIL/P-1/RES-Q ®. A
2Inch and 6Inch overlaps were maintained circumferentially and longitudinally to achieve
proper adhesiveness and strength at joints. On satisfactory completion of RES-Q ® and proper
curing a hardness test was carried out and noted as 74 to 85 Shore D hardness. A detailed
RES-Q® applied schematic drawings were made for records which later became a part of the
final document dossier. (TPIA Remarks: Satisfactory)
Inspection post application
• Visual Inspection of the RES-Q ®/Coating applied surface: On successful
completion of RES-Q ® and Coating application, TPIA had a walk through,
along with Service Provider to ensure that the entire scope of work is
completed and the visual inspection was carried out from bottom shell
section to top elevation of the Regeneration Column C-1302 and found
satisfactory.
• Service Provider advised to ensure proper housekeeping and make sure
the entire column is free from dust, loose particles and blasting abrasives.
Column was released for re-instatement of Hot Insulation by ONGC
• Results Tensile Tests: Parameters Composite Tensile Base Metal Tensile