Check List For Civil Defense
Check List For Civil Defense
1 Intake and exhaust shaft car park wall penetration to be closed ASCC
17 Diesel fire pump and electrical pump base to be filled by concret ASCC
20 Fire alarm control panel cable pulling and termination to be completed Voltas
1 Intake and exhaust shaft car park wall penetration to be closed ASCC
STATUS ON
Sl. No. CHECKLIST OF THE PENDING WORK ACTION BY
14/01/2018
14 Voltas
Break glass for access control system to be completed
15 ETS Room Corridor life and safety final fix to be completed Voltas
5 finance ,staff break out , garbage room ,kitchen all false ceilng clearance VOLTAS
18 corewall 2 fire lift lobby and corridor life and safety system should be installed Voltas
STATUS ON
Sl. No. CHECKLIST OF THE PENDING WORK ACTION BY
14/01/2018
1 lift lobby call button Kone
2 emergency light, break glass,push button near lift lobby Voltas
3 fire alarm sounder lift lobby Voltas
4 Idf room fire damper opening to be closed ASCC
3 Disable room toilet mep 3rd fix RCP drawing pending Voltas
3 Disable room toilet mep 3rd fix RCP drawing pending Voltas
4 fire alarm sounder lift lobby Voltas
5 IFU not installed in offices Voltas
6 Emergency exit light missing in corewall 2 Voltas
7 Idf room fire damper opening to be closed ASCC
8 door to be installed in animal exhaust shaft and ftc riser ASCC
9 fire sealant in ftc riser Voltas
12 fire lift lobby and corridor 3rd fix to be completed corewall 2 Voltas
All offices fire fighting butterfly valve and zone control valve interface
30 with FA to be completed Voltas
3 Disable room toilet mep 3rd fix RCP drawing pending Voltas
4 fire alarm sounder lift lobby Voltas
5 IFU not installed in offices Voltas
6 Emergency exit light missing in corewall 2 Voltas
7 Idf room fire damper opening to be closed ASCC
14 fire lift lobby and corridor 3rd fix to be completed corewall 2 Voltas
32 All offices fire fighting butterfly valve and zone control valve interface Voltas
with FA to be completed
33 Door access installation to be done in plant room Voltas
34 unnecessary opening in SE shaft to be closed ASCC
35 fire alarm control panel to be fixed in electrical room and IT room Voltas
7th floor Date-13/01/2018
Sl. No. CHECKLIST OF THE PENDING WORK ACTION BY Status on 14/01/2017
38 gypsum board and studs to be completed for fire hose cabinet box ASCC
12 gypsum board and studs to be completed for fire hose cabinet box ASCC
24 Voltas
water metre room shaft fire sealant in riser to be completed
25 All door closure to installed ASCC
26 All signages to be completed ASCC
9th floor date-13/01/2018
14 gypsum board and studs to be completed for fire hose cabinet box ASCC
26 Voltas
water metre room shaft fire sealant in riser to be completed
27 ASCC
All door closure to installed
28 All signages to be completed ASCC
ROOF AND UPPER ROOF date -13/01/2018
S.NO CHECKLIST OF PENDING WORKS Action By Status on 14/01/2018
1 Exhaust fan duct connection from smoke exhaust shaft duct Voltas