1. A hotel housekeeper was observed five times on each of four task elements shown in the
following table.
Compute the Mean Time for each element and the OT, NT, ST, given an allowance job
time of 15%
Compute for the OT,NT and ST assuming and allowance factor of 15% of job time.
1. How many observations would be needed to estimate the mean time for element 2 within
1% of its true value with 95.5% level of confidence?
SD
Z= 95.5%= 2.00
A= 1%= 0.01
2. How many observations would be needed to estimate the mean time for element 2
within .01 minute of its true value with a 95.5% confidence?
Given
Z= 95.5%= 2.00 E= .01 minute S= 0.034 N=(zs/e)^2