Professional Documents
Culture Documents
05 Drainage Report
05 Drainage Report
05 Drainage Report
DRAINAGE REPORT
1.0 INTRODUCTION
2.2 Topography
As shown in the Pre-Development Flow Diagram, most of the land is considered gently
slope. However, when comes to the west boundary, the earth level is steeper. The height
difference between the high ground and low ground at western boundary is approximately
1.84m.
DRAINAGE REPORT 1
CONSULTANT COMPANY
3.1 General
The proposed drainage system in this development is by discharging the runoff water into
the nearby earth drain via detention drain.
All internal perimeter drains are designed to cater post-development water runoff of 5
years ARI. Gradients of drains will be aligned as such that the water discharge velocities
are controlled within the range of 0.6m/s and 4m/s, as specified in the Urban Storm water
Management Manual (Malaysia).
For major drainage system, drain functions as detention facility (Detention drain). The
detention drain is along internal road reserve, i.e. in front of residential lots. The drain
will be designed with 50-ARI. Discharge Control Pit (DCP) with orifice will control the
outflow and overflowing weir will serve as emergency spillway.
Final water discharge will be channeled to the road side drain along Jalan Sin On Utara.
Pre-Development
The pre-development catchment is designed by using Linear Reservoir Routing Method. Pervious
and impervious area flow lengths are assumed to be equal. Horton equation is used as infiltration
method.
DRAINAGE REPORT 2
CONSULTANT COMPANY
Catchment A
Flow length = 92.67m
Post-Development
The post-development catchment is designed by using Linear Reservoir Routing Method. Pervious
and impervious area flow lengths are assumed to be equal. Horton equation is used as infiltration
method.
Catchment 1
Overland flow length = Flow length from building roof to house drain leading to detention
drain
= 8.54m
Road Reserve = 346.15m2
Pervious area on Road Reserve = 10% = 34.62 m2
Pervious area of Lot A1 – A12 = 219.57 m2
Total Pervious area = 34.62 + 219.57
= 254.19 m2
DRAINAGE REPORT 3
CONSULTANT COMPANY
Catchment 2
Overland flow length = Flow length from building roof to house drain leading to detention
drain
= 3.66m
Easement Reserve = 317.65m²
Pervious area on Easement Reserve = 10% = 31.77m²
Pervious area of Lot A1 – A12 = 628.54 m2
Total Pervious area = 31.77 + 628.54
= 660.31 m2
Catchment A
ARI 5 ARI 50
Time Qpre Time Qpre
(min) (m3/s) (min) (m3/s)
15 0.044 15 0.139
30 0.049 30 0.152
45 0.070 45 0.155
60 0.069 60 0.146
120 0.040 120 0.098
180 0.022 180 0.045
DRAINAGE REPORT 4
CONSULTANT COMPANY
Catchment 1 & 2 Detention Drain (Please refer to Appendix for Catchment Flow)
ARI 5 ARI 50
Time Qpost Time Qpost
(min) (m3/s) (min) (m3/s)
15 0.123 15 0.222
30 0.122 30 0.211
45 0.118 45 0.198
60 0.109 60 0.184
120 0.075 120 0.129
180 0.032 180 0.054
The water discharged from the post-development catchments will be compared with the pre-
development water discharge to design appropriate detention facilities. Detention facilities will be
designed to cater for post-development 50 years ARI inflow and pre-development 50 years ARI
outflow rate.
The outflows in 5 years ARI and 50 years ARI for post-development are 0.123m3/s and 0.222m3/s
respectively. In this case, pre-development catchment discharge is compared with all post-
development catchment (5-year ARI : 0.070m3/s vs 0.123m3/s; 50-year ARI : 0.155m3/s vs
0.222m3/s).
DRAINAGE REPORT 5
CONSULTANT COMPANY
DRAINAGE REPORT 6
CONSULTANT COMPANY
5-ARI
50-ARI
From Table 11, it can be observed that the total post development outflows are smaller than the
total pre-development outflows after the detention drain is introduced. This complies with the
requirement of Urban Stormwater Management Manual of Malaysia.
In conclusion, the new development will not create catastrophic effect to the drainage system in
the surrounding area as the reduction of the post development peak flow and volume have been
achieved by introducing the water detention facilities.
DRAINAGE REPORT 7
CONSULTANT COMPANY
The mitigation measures, as required by the local authority, during the life span of the drainage
system, include:
DRAINAGE REPORT 8
CONSULTANT COMPANY
5.0 CONCLUSION
In post-development, detention drain with dimension width of 900mm is provided to control the
outflow.
One number of 150mm diameter orifice is provided to discharge control pit (DCP) to limit the
outflow discharge. There will be additional overflow weir above the orifice, designed to discharge
the runoff, in case the orifice is blocked with trash. Meanwhile, trash screen is provided for inlet to
DCP to block of trash from the development entering public drainage system.
Major drainage system is designed for 50 years ARI rainfall events. Minor drainage system is
designed for 5 years ARI rainfall events.
Final discharge of the controlled outflow is channeled to existing earth drain along Jalan Sin On
Utara of the development site through 600mm covered drain.
The total outflow values after detention drain are shown in Table 11. They do not exceed the pre-
development outflows. In other words, there will be no increase in water discharge after this land
has been developed.
DRAINAGE REPORT 9
CONSULTANT COMPANY
The possibility of upper catchment discharge through the development site has been taking into
consideration. The proposed 450mm easement drain will be designed to cater the upper catchment
runoff and discharge from the development site. The final water will be discharge through the
proposed 600mm drain to the existing roadside earth drain at the eastern boundary.
The following table shows the rainfall intensity of several time intervals for 50 year ARI
(Kuamut), taken from Miduss98 estimate:-
Total area of lands is estimated at 4,784 sq.m (1.182 Ac.). Rational Method is used to estimate the
runoff value. The formula is given as
Q = CiA / 3600
The total discharge from the above catchments and part of development site are estimated to be
0.16m³/s. The developer will propose the construction of a 450mm wide RC drain. To calculate the
discharge capacity of the RC drain, Manning’s Formula is used. The formula is given as
Qc = AR2/3 √So
n
DRAINAGE REPORT 10
CONSULTANT COMPANY
The following shows the typical cross-sectional view of the 450mm wide RC drain:-
450m
Existing Ground Level
TWL
0.20m freeboard
450m
v = Velocity of flow
=Q/A
= 0.39 / 0.36
= 1.08 m/s
From the above calculations, it is showed that the 0.45m wide x 1.00m depth RC drain with flow
capacity of 0.39m³/s is sufficient to cater the water from the adjacent land (0.16 m³/s). Also the
velocity of drain flow is between 0.6m/s and 4.0 m/s which are within a safe range.
Qc > Qpeak
v < 4 m/s
Therefore, the proposed RC drain fulfills the capacity requirement of the existing site condition.
DRAINAGE REPORT 11
CONSULTANT COMPANY
The final water will be discharge through the proposed 600mm drain to the existing roadside earth
drain at the eastern boundary.
The following table shows the rainfall intensity of several time intervals for 50 year ARI
(Kuamut), taken from Miduss98 estimate:-
Total area of lands is estimated at 4,784 sq.m (1.182 Ac.). Rational Method is used to estimate the
runoff value. The formula is given as
Q = CiA / 3600
The total discharge from the above catchments and development site are estimated to be 0.19m³/s.
The developer will propose the construction of a 600mm wide RC drain. To calculate the
discharge capacity of the RC drain, Manning’s Formula is used. The formula is given as
Qc = AR2/3 √So
n
DRAINAGE REPORT 12
CONSULTANT COMPANY
The following shows the typical cross-sectional view of the 600mm wide RC drain:-
600m
Existing Ground Level
TWL
0.20m freeboard
600m
v = Velocity of flow
=Q/A
= 0.78 / 0.60
= 1.30 m/s
From the above calculations, it is showed that the 0.60m wide x 1.20m depth RC drain with flow
capacity of 0.78m³/s is sufficient to cater the water from the adjacent land (0.19 m³/s). Also the
velocity of drain flow is between 0.6m/s and 4.0 m/s which are within a safe range.
Qc > Qpeak
v < 4 m/s
Therefore, the proposed RC drain fulfills the capacity requirement of the existing site condition.
DRAINAGE REPORT 13