Professional Documents
Culture Documents
Shoring For Deep Excavation in Urban Khartoum, Sudan: February 2008
Shoring For Deep Excavation in Urban Khartoum, Sudan: February 2008
net/publication/292371251
CITATIONS READS
0 3,337
3 authors, including:
6 PUBLICATIONS 71 CITATIONS
University of Khartoum
36 PUBLICATIONS 158 CITATIONS
SEE PROFILE
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Elfatih Ali on 31 January 2016.
87
International Journal of Emerging Technology and Advanced Engineering
Website: www.ijetae.com (ISSN 2250-2459, ISO 9001:2008 Certified Journal, Volume 6, Issue 1, January 2016)
All these conditions led to considering shoring activities Soldier piles with wooden lagging walls are one of the
to address such situations. oldest construction systems. They cannot be used when
water table is encountered unless dewatering is used. This
III. SUBSOIL CONDITIONS system is generally used for narrow temporary excavation.
Geological and geotechnical conditions in the Greater The lagging may need struts and the whole system is
Khartoum Area is dominated by soil layers of clay, silt, generally not very stiff.
sand and mixtures thereof underlain by Nubian sand stone, Sheet piles are of the driven pile types. Vibration and
mudstone and chert . The soil layers extend in depth from 0 noise are main constraints associated with sheet pile
to, about 20 to 30 m depth. The Nubian formation extends construction. In many situations sheet piling may need
from few meters to tens of meters and is underlain by lateral support. Existence of ground water is not a problem
basement complex formation. for use of sheet piles. Sheet pile material is generally
Clays in the Central Sudan are dominated by expansive imported from specialized manufacturers and may incur
soils called Black Cotton Soils. These are generally extra cost. Pile driving equipment availability is also
unsaturated stiff clays that exhibit volume change another constraint.
associated with changes in moisture content. Silt and silty Bored concrete pile wall is the last option. Construction
clays are also frequently encountered. Silty and clayey material i.e. concrete and steel reinforcement as well as
sands as well as sand are also encountered. Fine to medium drilling rigs are available in most places together with
sands as well as coarse sand and gravel also exist. There experienced personnel. For cases of high ground water
are some sand layers that are loose depending on the secant piles are chosen while contiguous piles can be used
deposition process. in other cases.
The ground water depth varies widely in the area.
Depths vary from few meters to more than 20 meters to V. BORED PILE SHORING TYPES
non-existent. Perched ground water may be encountered if A. Contiguous Piles
an impermeable layer exists at shallow depths. Infiltration These are piles that are placed at some spacing between
of water from rain, existing infrastructure, any other them so they do not touch each other. Spacing of one to
surface water used would collect and create what is referred two pile diameters are not unusual. The spacing depends on
to as perched ground water. soil arching and is generally related to clayey nature of
subsoil. For partially saturated clayey soils and when water
IV. EXCAVATION SUPPORT FOR DEEP FOUNDATIONS table is not a factor contiguous piles is an option. For sandy
Many types of excavation support may be considered[7]. soils the stability of the sand in between piles must be
These may include: carefully evaluated. Silty soils must also be considered
a- Retaining walls. carefully. Fig. 1 depict the case of contiguous piles.
b- Diaphragm walls.
c- Sheet pile walls.
d- Soldier piles with timber lagging walls.
e- Pile walls (contiguous, tangent or secant).
The choice of support type is dependent on many factors
such as soil conditions, ground water and/ dewatering
needs, excavation depth, space to nearest structures,
dynamic effects of installation of driven piles, safety Fig. 1: Schematic Plan View of a Contiguous Pile Wall
considerations as well as economic considerations. The
availability of construction equipment, familiarity with B. Secant Piles
their use, availability of materials and their cost are These piles are constructed in two phases. In the first
governing factors. stage female unreinforced concrete piles are constructed.
For urban areas distances between structures are usually Male reinforced concrete piles are then installed so that
small, hence retaining walls are generally excluded. there is an overlap between the adjacent male and female
Diaphragm walls are generally considered too expensive piles. Fig. (2) shows the secant pile setup. Generally female
except for very deep excavations as may be needed for piles are cast using a weaker concrete mix than male piles.
underground transport systems or tunnels.
88
International Journal of Emerging Technology and Advanced Engineering
Website: www.ijetae.com (ISSN 2250-2459, ISO 9001:2008 Certified Journal, Volume 6, Issue 1, January 2016)
Secant piles are chosen in case high water table and/or Design review led to a decision of having two basement
dewatering are in consideration. If the subsoil consists of with a total depth of 6.50 to 7.00 meters. Existing
sandy layers then this type of pile may be considered. neighboring residential building is less than 2.00 m from
the new tower building. Two roads are adjacent to this
structure. Fig. 4 gives a plan of the existing and new
construction.
C. Tangent Piles
Tangent piles are as the name indicates touching each
other. They are used in cases that are considered
transitional between contiguous and secant piles. All piles
are however made of reinforced concrete. Fig. 3
shows tangent pile arrangement. Fig. 4 Map of ACOLID Plot
89
International Journal of Emerging Technology and Advanced Engineering
Website: www.ijetae.com (ISSN 2250-2459, ISO 9001:2008 Certified Journal, Volume 6, Issue 1, January 2016)
TABLE. 1
CONTIGUOUS PILE DESIGN FOR ACOLID TOWER
90
International Journal of Emerging Technology and Advanced Engineering
Website: www.ijetae.com (ISSN 2250-2459, ISO 9001:2008 Certified Journal, Volume 6, Issue 1, January 2016)
2) Subsoil Conditions: Fig. 8 shows the soil profile. Two TABLE 2
stages of Site Investigation (SI) were conducted. The first DESIGN OF CONTIGUOUS PILES FOR TIB TOWER
SI was conducted prior to design while the second SI was Pile Piles Pile Pile
Excavation
carried out at a later stage after excavation began. The Zone Diameter Spacing Length Reinforce/
Depth (m)
owner and consultant worried about the existing office (m) (m) (m) ment
building which began to show some distress. Shoring was 1-2 5.8 0.5 0.5 13.8 8 ɸ 16
then seriously considered at this stage. 2-3 6.8 0.6 0.6 13.8 8 ɸ 16
The boreholes showed similar soil stratification with 3-1 5.8 & 6.8 0.7 0.5 13.8 8 ɸ 20
slight variation in few layers. One borehole indicated very
stiff to hard silty clay layer while the other two boreholes
the clay layer in the top 7.5 m followed by silt layer in the
following 3.00 m [9].
Ground water level was observed in this site at 7.50 m
depth. As the second stage SI was carried out in the river
flood season this is generally the highest level of GWT.
91
International Journal of Emerging Technology and Advanced Engineering
Website: www.ijetae.com (ISSN 2250-2459, ISO 9001:2008 Certified Journal, Volume 6, Issue 1, January 2016)
A complementary SI was carried out to determine design
parameters for shoring of deep excavation. The foundation
for the concrete tanks are to be at a depth of 9.00 m depth.
Fig. 10 shows the map of the SSKN1. The plot is
surrounded by roads on two sides while the other two sides
are covered by institutional municipal buildings.
92
International Journal of Emerging Technology and Advanced Engineering
Website: www.ijetae.com (ISSN 2250-2459, ISO 9001:2008 Certified Journal, Volume 6, Issue 1, January 2016)
Table. 3 gives the design details for this project while Three case studies were given and the choice of support
Fig. 12 shows the construction at the site. system was presented. Cast in-situ concrete pile walls are
TABLE. 3
used. Contiguous and secant piles were used depending on
DESIGN OF SECANT PILES FOR SSKN1 subsoil conditions and ground water situation.
Pile Pile Pile REFERENCES
Excavation Overlap
Pile Type Dia. Length Reinforce/
Depth (m) (m) [1] Thomas Borg and Erik Ulvas "Alternative Foundation Techniques in
(m) (m) ment
Urban Environm nt" MSc thesis, Dept of Civil and Environmental
Secondary 5.5 0.6 0.10 14.0 16 ɸ 20
Eng. Chalmers U of Tech, Sweden 2012.
No
Primary 5.5 0.6 0.10 8.0 Reinforce/m [2] N. Wharmby, B. Perry and H. Waikato "Development of Secant Pile
ent Retaining Wall Construction Urban New Zealand". New Zealand
Concrete Industry Conf. .Wellington, New Zealand 2010.
[3] V.R. Godavarthi, D. Mallavalli, R. Peddi , N. Kartagadda and P.
Mulpuru "Contiguous Pile Wall as a Deep Excavation Support
System" Leonardo Electronic J of Practices and Technologies issu
19, 2011.
[4] I. Jardaneh "Assessment of Local Excavation Support System : A
case Study of Nablus city, Palestine", aN- Najah Uni. J Res. vol. 20,
2006.
[5] F. Murillo et al "Urban SectorStudies and Capacity Building for
Khartoum State" UN- HABITAT, 2009.
[6] E.I.E. Ibrahim "Sustainable Development of the river Nile at Greater
Khartoum" PhD thesis, Uni. of Huddersfield, UK, 2011.
[7] M. Ufuk Ergun , "Deep Excavations", Electronic J. of Geotech.
Engineering , 2008.
[8] ESD, " Soil Investigation for Arab Co. for Livestock Development
(ACOLID) building at Alamarat district in Khartoum". 2008,
Fig. 12 Secant Piles for SSKN1 Khartoum.
[9] ESD, "Report on Shoring study for Al-Tadamon Islamic Bank
VII. CONCLUSIONS excavation in Khartoum" , 2011 , Khartoum.
[10] ESD, " Report on Geotechnical study and Shoring design for Sewage
Urbanisation is a worldwide trend in all countries. The System of Khartoum North Phase 1" 2013, Khartoum.
need for deep excavation is a result of such urbanisation
trend. An overview of different deep excavation support
types is given for various scenarios of loading, subsoil
conditions, adjacent structures, environmental constraints
and equipment and technical expertise availability.
93