University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
Civil Engineering
By
Supervisor:
2019-2020
II
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
DECLARATION
I hereby declare that I carried out the work reported in this report in the Department of
Civil Engineering, University of Sulaimani, under the supervision of (Mr. Zana A. Aziz)
.I solemnly declare that to the best of my knowledge, no part of this report has been
submitted here or elsewhere in a previous application for award of a degree. All sources of
III
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
APPROVAL
This is to certify that the project titled “PREPARATION OF B.O.Q FOR THREE-
STORY BUILDING” carried out by Ahmed Pshtiwan Ahmed and Zhikal Hiwa and
Othman Mohammed Arif
, has been read and approved for meeting part of the requirements and regulations governing
Sulaymaniyah, Iraq.
HEAD OF
Supervisor
DEPARTMENT
Board of examiners
IV
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
DEDICATION
We dedicate our dissertation work to our families and many friends. A special feeling of
gratitude to our loving parents. And We would like to thank (Mr. Bedar Rauf Hassan)
who helped us during the project have never left our side, We also dedicate this
dissertation to our friends who have supported us throughout the process. We will always
appreciate all they have done, We dedicate this work and give special thanks to our best
teacher (Mr. Zana A. Aziz) for being there for us throughout the entire doctorate program.
AKNOWLEGEMENTS
All praises to Allah who helped us to complete this project, we would never able to
1. We would like to express our gratitude to our advisor (Mr. Zana A. Aziz) for his
2. We would like to thank all persons who helped as to complete the project by a word
or a phrase.
3. We would like to thank (Mr. Bedar Rauf Hassan) who helped us during the project.
4. We would like to thank our parents for their helping from start of Study until now.
V
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
Table of Contents
CHAPTER ONE ............................................................................................................................ 1
INTRODUCTION ......................................................................................................................... 1
1.1 What is the estimation? ................................................................................................. 1
1.2 Types of estimation ........................................................................................................ 1
1.3 Objectives of the study ................................................................................................... 2
1.4 Aim .................................................................................................................................. 2
1.5 Report outline ................................................................................................................. 3
CHAPTER TWO ........................................................................................................................... 3
LITERATURE REVIEW ............................................................................................................. 3
CHAPTER THREE ...................................................................................................................... 4
EARTH WORKS .......................................................................................................................... 4
3.1 Excavation:..................................................................................................................... 4
3.1.1 Excavation of Combined Footing:......................................................................... 4
3.1.2 Excavation of Mat foundation:................................................................................... 4
3.2 Filling:............................................................................................................................. 5
CHAPTER FOUR ......................................................................................................................... 7
CONCRETE WORKS .................................................................................................................. 7
4.1Concrete Work of Foundation: ........................................................................................... 7
4.1.1 Concrete for Combined Footing: .......................................................................... 7
4.1.2 Concrete for Mat Foundation: .............................................................................. 7
4.1.3 Lean Concrete under Combined Footings: .......................................................... 7
4.1.4 Lean Concrete under Mat foundation: ................................................................. 8
4.2 Concrete Work of columns: ................................................................................................ 9
4.2.1 Columns of Basement: .................................................................................................. 9
4.2.2 Columns of Ground floor: ..........................................................................................10
4.2.3 Columns of First Floor:...............................................................................................11
4.2.3 Columns of Second Floor:...........................................................................................12
4.3 Concrete Work of Beams:................................................................................................. 13
4.3.1 Beams of Basement: ....................................................................................................13
4.3.2 Beams of Ground Floor: .............................................................................................14
VI
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
VII
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
VIII
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
List of Tables
Table 3. 1 Excavation of combined footing ........................................................................ 4
Table 3. 2 Excavation of Mat Foundation .......................................................................... 4
Table 3. 3 Filling ................................................................................................................. 5
IX
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
X
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
LIST OF FIGURE
1.2 Filling 6
XI
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
XII
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
LIST OF SYMBOLS
D Door
W Window
A Area m2
L Length m
St Stair
SL Stair Landing
XIII
CHAPTER ONE
INTRODUCTION
The eighteenth century is the century that dates back to the history of guessing when
British surveyors found it. Then, during the first half of the twentieth century, other
techniques developed to estimate building materials more and used six methods for
estimating in this century, and are the same methods that engineers use to Estimation
and make a difference only. In prototyping the initial cost.
1.2.1- Approximate Estimation: It is the Estimation of all the building departments based
on the m^2 or m^3 of the construction. This estimate is placed roughly, and we make this
estimate in order for the project owner to know the cost before making a decision to
construct it.
1.2.2- Detailed estimation: This estimation is carried out by contractors before the
important projects to provide the cheapest bids. In this type of estimation estimating
each part separately after knowing the prices of materials, equipment and work fees.
1
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
A-unit quantity: Each item is made separately Measuring its quality and cost, then adding
it.
B-total quantity: We calculate quantities for each type and category of materials and
multiply them according to the cost per unit of material, and also the cost and profit of
the building.
1.4 Aim
This project provide introduction to the principle of construction management with the
focus primarily on cost estimation aspects that govern the effective and timely delivery
of project. In order to further understanding of the above mentioned this case is studied.
And to:
b. Measurement of quantities
c. Cost estimation
d. Change order
2
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
CHAPTER TWO
LITERATURE REVIEW
For the final project which has to be submitted as a requirement for our bachelor degree,
we selected the (Estimation of three story building) project which was proposed by one of
our lectures. Although, many projects have been done on the same subject, but for
different types of buildings, in the past few years by the students of Civil Engineering
Department, we will estimate the martial quantities for a reinforced concrete three story
building. One of projects which has been done in 2019 by Iman Bast , Asht , and Lana,
under the supervision of (Dr.Mahdi Osman ) was project of estimation of commercial
building , they have used detailed method of estimation for measuring of the total
material quantities.
Another, project which has been done in 2018 by Tesho and their group, under the
supervision of ( Mr.Shuaaib A Mohammed ),, was project of quantity and cost estimation
of building, they have used detailed method of estimation for measuring of total material
quantities.
In this project, we will use detailed methods of estimation for measuring of the total
quantities of materials which has been used in the two previously mentioned projects.
3
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
CHAPTER THREE
EARTH WORKS
3.1 Excavation:
3.1.1 Excavation of Combined Footing:
[See Figure (1.1)]
4
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
Figure (1.1)
3.2 Filling:
[See Figure (1.2)]
Table 3. 3 Filling
Length (m) Width (m) Depth (m) Volume (𝐦𝟑 )
9 2.21 2 19.89
Total 19.89
5
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
Figure (1.2)
6
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
CHAPTER FOUR
CONCRETE WORKS
7
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
Figure (2.1)
8
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
Figure (2.2)
9
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
Figure (2.3)
10
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
Figure (2.4)
11
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
Figure (2.5)
12
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
Figure (2.6)
13
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
Figure (2.7)
14
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
Figure (2.8)
15
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
Figure (2.9)
16
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
Figure (2.10)
17
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
Figure (2.11)
18
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
Figure (2.12)
19
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
Figure (2.13)
20
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
TOTAL 19.5456
21
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
Figure (2.14)
4.6. Stairs:
4.6.1 Stairs of Ground floor:
For Stair 1:
No. Steps = 15
Volume of Steps= ½ * 0.3 * 0.2 * 1.1 * 15= 0.495 m3
22
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
Figure (2.15)
23
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
For Stair 2:
[See Figure (2.16)]
No. Steps = 5
Volume of Steps= ½ * 0.3 * 0.16 * 2.2 * 5= 0.264 m3
Figure (2.16)
24
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
No. Steps = 15
Volume of Steps= ½ * 0.3 * 0.2 * 1.1 * 15= 0.495 m3
Figure (2.17)
25
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
CHAPTER FIVE
MASONRY WORK
5.1 Blocks
5.1.1 Blocks for Basement Wall:
[See Figure (3.1)]
26
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
Figure (3.1)
27
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
28
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
Figure (3.2)
29
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
30
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
Figure (3.3)
31
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
32
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
Figure (3.4)
33
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
TOTAL 9.971
34
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
Figure (3.5)
35
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
CHAPTER SIX
FINISHING WORKS
6.1cement Plastering
6.1.1 Basement Cement Plastering
[See Figure (4.1)]
Internal Face:
External Face:
36
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
Deduction:
So, the total area for the Basement Floor = Total area - Deduction (door, window) =
251.488+ 90.74-26.52 = 315.71 m2
Figure (4.1)
37
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
Deduction:
38
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
Figure (4.2)
39
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
Deduction:
So, the total area for the First Floor = Total area - Deduction (door, window) = 255.9
-45.98 = 209.92 m2
40
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
Figure (4.3)
41
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
Deduction:
So, the total area for the Second Floor = Total area - Deduction (door, window) =
175.2 -31.28 = 143.92 m2
42
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
Figure (4.4)
43
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
Figure (4.5)
44
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
Figure (4.6)
45
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
Deduction:
So, the total area for the Ground Floor = Total area - Deduction (door, window) =
622.075 -119.74= 502.335 m2
46
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
Figure (4.7)
47
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
Deduction:
So, the total area for the First Floor = Total area - Deduction (door, window) =
622.075 -119.74= 502.335 m2
48
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
Figure (4.8)
49
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
Deduction:
So, the total area for the Second Floor = Total area - Deduction (door, window) =
236.325 -57.56= 178.765 m2
50
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
Figure (4.9)
51
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
Deduction:
So, the total area for the Ground Floor = Total area - Deduction (door, window) =
218.46-4.5= 213.96m2
52
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
Figure (4.10)
53
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
Deduction:
So, the total area for the First Floor = Total area - Deduction (door, window) =
218.46-4.5= 213.96m2
54
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
Figure (4.11)
55
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
A1 2 6 4 48
A5 1 2 1.05 2.1
D1 4 1 0.2 0.8
Total 106.27
So, the total area for the Second Floor = Total area = 106.27m2
56
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
Figure (4.12)
57
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
Figure (4.13)
58
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
Deduction
Total 2.8
So, the total area for the Ground Floor = Total area - Deduction (door, window) =
24.875 -2.8= 22.075m2
59
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
Figure (4.14)
Deduction
60
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
So, the total area for the First Floor = Total area - Deduction (door, window) =
24.875 -2.8= 22.075m2
Figure (4.15)
61
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
Deduction
So, the total area for the Second Floor = Total area - Deduction (door, window) =
236.325-19.36= 216.965m2
62
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
Figure (4.16)
63
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
64
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
Deduction:
So, the total area for the Ground Floor = Total area - Deduction (door, window) =
255.9 -45.98 = 209.92 m2
65
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
Deduction:
So, the total area for the First Floor = Total area - Deduction (door, window) = 255.9
-45.98 = 209.92 m2
66
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
Deduction:
So, the total area for the Second floor = Total area - Deduction (door, window) =
175.2 -31.28 = 143.92 m2
67
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
68
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
Deduction:
So, the total area for the Ground Floor = Total area - Deduction (door, window) =
622.075 -119.74= 502.335 m2
69
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
Deduction:
So, the total area for the First Floor = Total area - Deduction (door, window) =
622.075 -119.74= 502.335 m2
70
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
Deduction:
So, the total area for the Second Floor = Total area - Deduction (door, window) =
236.325 -57.56= 178.765 m2
71
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
6.9 Ceilings
6.9.1 Ceilings of Ground Floor
[See Figure (4.10)] Page 53
Deduction:
So, the total area for the Ground Floor = Total area - Deduction (door, window) =
216.48-4.5= 211.98m2
72
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
Deduction:
So, the total area for the First Floor = Total area - Deduction (door, window)
=216.48-4.5= 211.98m2
73
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
So, the total area for the Second Floor = Total area = 104.69m2
74
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
CHAPTER SEVEN
7.1 Quantity
Table 7. 1 Quantity
1 Excavation m3 907.2
2 Filling m3 19.89
Lean Concrete of
3 m2 189.1
Foundation
4 concrete wall 𝐦𝟑 19.5456
5 Foundation Concrete 𝐦𝟑 145.34
m3
6 Concrete of Column 27.016
7 Concrete of Slab m3 200.976
8 Concrete of Beam m3 80.986
m3
9 Concrete of Stair 5.463
10 Block (0.2m thick) m3 163.7324
11 Block (0.1m thick) m3 13.079
m2
12 Cement Plastering 1248.59
m2
13 Gypsum Plastering 1183.435
14 Floor Tiles m2 573.19
15 Stairs Tiles m2 30.05
16 Wall Tiles m2 261.115
17 Skirting Tiles m 435.6
18 Exterior Painting m2 932.88
19 Interior Painting m2 1183.435
20 Celling m2 528.65
75
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
76
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
7.3 Tendering.
Table 7. 3 Tendering
1 Earth Works
A) Excavation Works: Excavation in all
types of soils including back-filling and m3 907.2 3500 3175200
compaction .The price includes compacting
of the base of excavation using Viber-roller.
B) Filling Works: Supplying materials and
filling with approved screened sub-base up m3 19.89 5000 99450
to DPC level for the building with
compacting in layers 22 cm thickness.
2 Concrete Works:
77
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
Masonry : Including provision of materials ,pointing ,curing with all necessary work according
3
to section (500) of I.G.T.S & instruction of supervise Engineer.
Finishing: Including provision of all necessary materials.work, curing .The works should be
4 done according to the section 1000,&1400 of I.G.T.S and instruction of site engineer with all
necessary works.
78
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
Total 100,086,049.4
79
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING
CHAPTER EIGHT
CONCLUSION
We learned to read construction drawings, and measuring quantity of material that needed
for a project in our Project, also creating tendering.
The main goals that we achieved from this project is understanding all tasks and their
functions as well as direct and indirect cost of the tasks, and we have learned the importance
of any part of the building.
We learned to read bill of quantity (BOQ) and filling it by using the quantity of material
that measured by quantity estimation and we measured the cost of each item and putted it
into BOQ and determining the total cost of the Project.
The prices are considered based on current labour, workmanship and material and
equipment All the item price is calculated for the unit price in the tender and the total
quantity of that item is obtained.
and the total cost of this building is 100,086,049.4 IQD. This price is good indication to
government directorates to have a value to this building in outskirt areas. In future tenders
the government directorates can use this work as a base for their tender and price.
Recommendations:
The following points is recommended for future work:
1. The tender must update to consider several items for example, new materials used in
market, Ponza block.
2. The prices need competitions and different sources can be used to obtain the price.
3. More detail drawings should be available to get more detail estimation.
80
University of Sulaimani PREPARATION OF B.O.Q FOR THREE-STORY BUILDING