Detail Structure Section: Line Canal Schedule
Detail Structure Section: Line Canal Schedule
Detail Structure Section: Line Canal Schedule
R
E
SHOULDER
D
L
U
O
H
S
0.15m.THK. CLASS B CONCRETE
Y
WITH 10mmØ VERT.& HOR. BARS A
SPACED @ 0.20m.o.c.EACHWAY W
D
A
O
R
ISOMETRIC DIAGRAM OF
0.10m.thk. GRANULAR BEDDINGS/
FOUNDATION FILL STAGGERED HEADWALL @ LINED CANAL
SCALE : 1 : 40m.
DETAIL OF LINE CANAL
SCALE : 1 : 20m.
PROJECT NAME AND LOCATION: SHEET CONTENTS: DRAFTED: REVIEWED: SUBMITTED: RECOMMENDED: APPROVED: SET NO. SHEET NO.
REPUBLIC OF THE PHILIPPINES
VIRGO I. AUSTRIA
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS DATA CONTROLLER I
"CY -2022"
REGION IV-B
DETAILED ENGINEERING PLAN FOR THE DPWH
KWIN JUVY U. CRUZ GENE RYAN A. ALTEA MELQUIADES H. STO DOMINGO GERALD A. PACANAN, CESO III ROADS
CONSTRUCTION OF MISSING LINKS/ NEW ROADS DETAIL STRUCTURE CY - 2022
PREPARED:
OFFICE OF THE REGIONAL DIRECTOR DR. DAMIAN REYES ROAD (BOAC SIDE)
GODOFREDO S. DAGDAG,Jr.
ENGINEER III OIC- CHIEF, PLANNING AND DESIGN DIVISION OIC - ASSISTANT REGIONAL DIRECTOR REGIONAL DIRECTOR
R-IV-B
08 58
EDSA, DILIMAN QUEZON CITY PACKAGE I DATE: DATE: DATE: DATE:
ENGINEER III
MARINDUQUE