Ul RESTRICTIONS
‘The proponent is stri
ly subject to the following restrictions:
11, No other activities shall be undertaken other than what was stipulated in the EIA document.
Should there be an expansion of the project beyond the project description, construction of
other structures beyond those stated in the EIA document, or any change in the activity, same
shall be made subject to a new Environmental Impact Assessment;
112, Land clearing shall be limited to the project description; and
113, In case of transfer of ownership of this project, the same conditions and restriction shall apply
and the transferee shall be required to notify the EMB Regional Office of such activity within
fifteen (15) days.
Section 2. Applicability
All provisions in this Amendment shall now prevail over the previous conditionalities cited in
ECC No. 010101-120004-0502 issued last January 12, 2001.
Section 3. Effectivity
This Amendment is issued in the interest of all concerned parties and shall take effect
immediately.
Done in the City of San Femando, La Union, Philipines, his O7 MAY 2014
APPROVED:
JOEL G. SALVADOR, CESO IV
Regional Director
Chief, Clearance and\Permitting Division
Amendment Fee: | @ 315.00 O.R.No.: ” 9467739 Date: | 03/25/2014
VALID ONLY IF MARKED WITH DRY SEAL,
‘loneadmen: 2014 ‘ttex