East India Udyog Limited: REC Quality Monitoring (RQM)
East India Udyog Limited: REC Quality Monitoring (RQM)
RE-DDUGJY-New Project
In State Jharkhand
Location:
S. No.
Description of Defects Picture Location as per Remarks
No. SLD
Distribution Transformer
1. Substation numbering not done Photo 1 DTR 1 Rectification Done
2. Stay found lose Photo 1 DTR 1 Rectification Done
3 DO fuse not proper Photo 1 DTR 1 Rectification Done
4 Oil not found in breather cup Photo 1 DTR 1 Rectification Done
5 Hammering done on Pipe earthing Photo 2 DTR 1 Rectification Done
11 KV Line
6 Stay angle and winding not proper Photo 3 Tapping pole Rectification Done
LT line
7 Pole numbering not done Photo 4 All LT Pole Rectification Done
8 Stay found loose Photo 5 LT 09 Rectification Done
9 Pole found tilted Photo 6 LT 13 Rectification Done
BPL Connection
10 Meter cover not found Photo 7 Meter no. 734547 Rectification Done
11 PVC clamp not found Photo 7 Meter no. 734547 Rectification Done
Total 11
Photo No. 1 Substation numbering not done, Stay found loose, Arc horn alignment not proper, oil not
found in breather cup, HG fuse set not proper
3
Compliance: After Rectification of Photo No 1, Substation No done, stay
tightening done, arcing horn alignment fixed Oil filled in breather cup, DO fuse set
properly. (Note: HG is not our scope).
4
SOR: Photo No 2
5
SOR: HT Line Before Photo No 3
Compliance: After rectification of Photo No 3, Stay angle and winding Done properly.
6
SOR: LINE (Before)
7
SOR: LT Line Photo No 5 before
Photo No. 7 LED bulb not found; meter cover not found.
10
11