Professional Documents
Culture Documents
Pradip Mehta vs. Sylvanus Propefties LTD
Pradip Mehta vs. Sylvanus Propefties LTD
AT0060000000s2511
JUDG M ENT
1/2r
AT005000000052511
raise grievances that impugned order has not satisfactorily granted the
has remarkable features that developer will provide Golf course with 12
r^,&1 developer had failed to complete the project. Moreover, all amenlties
2/2L
aTo060000000s2611
commitments and therefore the allottees by email dated 6th March 2019
intimated the developer that they have cancelled the booking and
amount paid by the complainants with interest from 2"d July 2014. (iii)
to pay maximum penalty as per the provisions of RERA and (iv) to pay
however, the allottees have failed to do so. The subject flat is still
register the agreement for sale in respect of subject flat. The developer
1/21
4
ATO05000000052611
sate has been executed between the parties. It was fufther contended
developer, but by third party and therefore the allottees cannot claim
that impugned orders dated 24th December 2019 and 20th February
that to lure home buyers, the developer has represented allottees that
project has unique features. The developer will provide Golf-course and
July 2014 to allottees. At the time of booking of the said flat, the
project within stipulated period and therefore allottees vide email dated
6th March 2019 informed the developer that they have cancelled the
s/21
6
4T006000000052611
to obtain occupancy certificate for the said project upto 31st l4arch 2021
and the possession of the subject flat was offered to allottees for the
flrst time on 4th May 2021. However, impugned order traversed beyond
the order that part occupation certificate has been obtained prior to
email dated 6th March 2019 sent to developer for cancellation of subject
flat. These observations would clearly indicate that the impugned order
101 Adv. |\.4r. Manish Gala for appellants has sorely submitted
that allottees have booked flat in June 2014, therefore, developer was
6i21
1
AT005000000052611
portal as lstJuly 2017. The developer in his reply for the first time
3lst lularch 2021. The developer has violated the provisions of RERA.
discharge any other obligations imposed under the Act of 2016 and in
00600000003r7221.
(17) Shree Shakun Realty Pvt. Ltd. Vs. Mr. Vijay Solanki
8/21
9
AT006000000052611
subject flat within stipulated period and even after revised date of
lv'lr. lYanish Gala for appellants prayed to grant reliefs in terms of prayer
application for provisional reservation dated 30th lune 2014. Except this
occupation certificate, and this date governs the parties until execution
whereby the allottees were to pay only 100/0 upfront and the balance
90yo on possession. Since the booking was made much prior to coming
into force of the RERA, law did not require the developer to execute
10121
11
4To06000000052611
booking form, agreed to execute and register the agreement for sale
when called upon, they failed to do so, and thereby allottees have
flat in 2018 but, the allottees did not take action by filing any
proceedings when the said date had passed. The allottees only raked
para-4 of the appeal memo that they have invested in the subject flat
for earning rental income. The allottees are seeking an exit since they
are losing out the rental income. This conduct of allottees clearly
indicates that the allottees are certainly not genuine home buyers, but
investors who are now taking the advantage of the provisions of RERA
ceftificate, the developer called upon the allottees for registering the
1L/21
L2
AT0060000000s2611
agreement for sale and also offered possession of the subject flat.
However, the allottees did not come fonvard to execute agreement for
certificate.
agreement for sale. By email dated 6th N4arch 2019 the allottees
expressed their desire to withdraw from the project for no reason. The
w 181
Order.
to follow :
13/21
14
4To05000000052611
delivering possession of subject flat and (ii) not providing amenities i.e.
sq.ft.
not in dispute that no agreement for sale has been executed by the
occupation certlficate and this date governs the partjes until execution
t4/21
" oroo6ooooooos26ll
for the purpose of worklng out the date of possessjon. However, there
It is not in dispute that after coming into force of RERA 2016, the
the possession of the flat allotted to them and they are entifled to seek
we are awaTe of the fact that when there was no delivery period
15/21
16
AT006000000052.lr
consideration. In the facts and circumstances of the case, a time period
June 2014. In the light of the above ratio laid down by the
Hon,ble
that the date of detivery of possession of the subject flat was 1,t July
2017.
also not in dispute that allottees by email dated 6th March 2019
of delay in possession.
March 2021. The developer has not offered explanation for delay
in
r6/2t
77
4T006000000052611
in this behalf. If the allottee does not intend to withdraw from the
project, he will be paid interest by the promoter for every montht delay
17 /2t
1B
AT006000000052511
case of M/S Newtech Promoters & Anr, Vs. The State Of Uttar
hereunder:
' 25 The urutudlilicd right oj thc alkntee k) seek re/irnd re.ferretl under
Sectian l8(1)(a) and Section l9(1) o/ lhc Act is not dependent on any
contingencies ar stipulati()N lheruo/- It appedrt thttt the legitlature hus
consciously providcd this right of lei)nd on demand as an unconditional
incl ding couipcnsation in tlle manner provided under thr Act \t,ith the
ptoriso that il the allottee Lloes n(rt y'ish to ttithdrav /iom the projecl, he
shall be entitled for intcre.i lL'r lhe periad of delay titt handing otcr
posscssion at the rate prescribed."
in spite of extension of the said period from time to time, the developer
18/21
19
AT0060000000526r1
submitted that any exit by the Allottees from the subject project will
entail huge loss to the developer as allottees have blocked the subject
flat for last eight years and the developer has even in relative terms
on the part of the developer will entail forfeiture of the amount in terms
already observed that the developer has failed to hand over possession
of the subject flat to allottees by due date i.e. 1.t luly 2017 mentioned
L9/21
20
AToo6ooooooosz.ll
developer has utilized the said amount slnce 30th June 2014 till
circumstances of the case, we are of the view that allottees are entiUed
amount paid from 1$ July 2014 till realisation of entire amount, For the
ORDER
ll Appeal No.AT0060000000526L1 of 2O2O is partly altowed.
on the amount paid by the allottees from 1st July, 2014 till
w ivl
the realisation of the entire amount.
)0/)1.
27
AT006000000052611
G'&t
o
\.-'
(sH RIBAM R. JAGTAP)
21/21