Contract: 2084 Job.: 06202 Sheet 1 of 12 Doc. No.: 06202-ELE-SP-000-024 SCOP Doc. No.: –
ADDITIONAL DEVELOPMENT
OF
LUHAIS & SUBBA OIL FIELD
PROJECTS
GENERAL
SPECIFICATION FOR DESALTER TRANSFORMER
(SCOP SPECIFICATION E-1106.1 WITH AMENDMENTS)
06202-ELE-SP-000-024-IF0
ADDITIONAL DEVELOPMENT OF LUHAIS & SUBBA OIL FIELD PROJECTS
GENERAL SPECIFICATION FOR DESALTER TRANSFORMER
06202-ELE-SP-000-024 Sheet 2 of 12 Rev. IF0 -
INDEX
06202-ELE-SP-000-024-IF0
ADDITIONAL DEVELOPMENT OF LUHAIS & SUBBA OIL FIELD PROJECTS
GENERAL SPECIFICATION FOR DESALTER TRANSFORMER
06202-ELE-SP-000-024 Sheet 3 of 12 Rev. IF0 -
PART I INTRODUCTION
1 GENERAL
1.3 Definitions
Project: is the Additional Development of The Luhais & Subba Oil Field Projects
06202-ELE-SP-000-024-IF0
ADDITIONAL DEVELOPMENT OF LUHAIS & SUBBA OIL FIELD PROJECTS
GENERAL SPECIFICATION FOR DESALTER TRANSFORMER
06202-ELE-SP-000-024 Sheet 4 of 12 Rev. IF0 -
Contractor/Buyer: PETREL/MAKMAN JV
Supplier or Vendor: any company who received the Purchase Order from the Buyer
(Manufacturer )
Purchase Order: the Purchase Order placed on the Supplier by the Buyer which shall
incorporate Terms and Conditions of Purchase, the Material
Requisition, drawings, specification, and other documents referred to
in the Purchase Order and any written amendments
Construction Contractor Any Contractor in contract with the Company for the construction
and commissioning of the Additional Development of Luhais &
Subba Oil Field Projects
1.4 Abbreviations
CACW Totally Enclosed, Air Circuit Machine Water Cooled Air Cooler
CT Current transformer
06202-ELE-SP-000-024-IF0
ADDITIONAL DEVELOPMENT OF LUHAIS & SUBBA OIL FIELD PROJECTS
GENERAL SPECIFICATION FOR DESALTER TRANSFORMER
06202-ELE-SP-000-024 Sheet 5 of 12 Rev. IF0 -
LV Low Voltage
MV Medium Voltage
T1 Temperature
06202-ELE-SP-000-024-IF0
ADDITIONAL DEVELOPMENT OF LUHAIS & SUBBA OIL FIELD PROJECTS
GENERAL SPECIFICATION FOR DESALTER TRANSFORMER
06202-ELE-SP-000-024 Sheet 6 of 12 Rev. IF0 -
Ambient Temperature
Maximum : 55°C (in shade) and 83°C (exposed to sunlight)
Minimum : -5°C
Design Temperature:
Outdoor:
Maximum : 55°C (in shade) and 83°C (exposed to sunlight)
Minimum : -5°C
Indoor : +40°C
Relative Humidity
Maximum at 43°C : 95%
Average at 54°C : 60%
1.7 Language
All correspondence, drawings, instructions, data sheets, design calculations or any other
written information shall be in the English Language.
06202-ELE-SP-000-024-IF0
ADDITIONAL DEVELOPMENT OF LUHAIS & SUBBA OIL FIELD PROJECTS
GENERAL SPECIFICATION FOR DESALTER TRANSFORMER
06202-ELE-SP-000-024 Sheet 8 of 12 Rev. IF0 -
PART II AMENDMENTS
GENERAL DOCUMENTS
SUPPLIER DOCUMENTS WHICH SATISFY THE SDRL CODES REQUIRED BELOW SHALL BE LISTED ON THE
SUPPLIER DATA REGISTER – SDRL CODE G01
Abbreviations : A – Award, D – Delivery, „-„ – Before, „+‟ – After, Blank – No Requirement
Example : +4A = four weeks after Purchase Order award, -2D = two weeks before delivery
IOM – Installation, Operations and Maintenance Manual
MDB – Manufacturing Data Book
PURPOSE & TIMING
SDRL With For Databook ()
SDRL – CODE DESCRIPTION
CODE Bid () Revie IOM MDB
w
SUPPLIER DATA REGISTER
List every document drawing, calculation, manual, etc. to be submitted to fulfill the
G01 +2A
requirements of this SDRL. Including submission dates, whether for information or
review and the manual reference. To be updated on a continuous basis.
OUTLINE / GENERAL ARRANGEMENTS
List all items and show arrangement of components for each unit. Give over all
dimensions. Locate foundation supports, anchor bolts and all Buyer termination points
including instrument and electrical. Also show details of shipping splits and/or items
G02 removed during shipping. Plan, evaluation and end views shall be shown. Scale used
+4D
should be indicated. Arrangement drawings shall at least show base plate(s),
equipment, components, drivers, coolers, major values, all instruments, ladders,
platforms/gratings etc
DATA SHEETS
G03 Review and comments on information on Buyer data sheets. +4D
Complete where applicable, and provide all Supplier and Sub-Supplier data sheets.
WEIGHTS AND LOADS
G06 Give weight and C of G positions for dry and normal operations case. +4D
PROJECT PLAN/SCHEDULE
G10 A milestone bar chart of all activities from award though to shipment of +2A
equipment/materials suitable for bid evaluation.
ENGINEERING/PROCUREMENT/FABRICATION SCHEDULE
A network or bar chart developing and confirming the chart in G09 above, containing
G11 complete details of Suppliers and major Sub-Supplier‟s activities. It shall also be suitable
+4A
for Supplier for report progress and Buyer to assess and monitor performance.
G12 SCHEDULE OF SUB-SUPPLIERS +2A
G13 PERIODIC PROGRESS REPORTS +4A
Frequency as specified in Purchase Order
QUALITY CONTROL INSPECTION PLAN
G14 Draft or Typical with Bid complying with Specification. All major Sub-Suppliers shall +2A +4D
submit Quality Control Inspection Plans
G15 HSE PLAN
G16 INDEX OF QA MANUAL/MANUFACTURING QC PROCEDURES +2A
Applicable to Purchase Order Workscope
06202-ELE-SP-000-024-IF0
ADDITIONAL DEVELOPMENT OF LUHAIS & SUBBA OIL FIELD PROJECTS
GENERAL SPECIFICATION FOR DESALTER TRANSFORMER
06202-ELE-SP-000-024 Sheet 9 of 12 Rev. IF0 -
PROCEDURES
SUPPLIER DOCUMENTS WHICH SATISFY THE SDRL CODES REQUIRED BELOW SHALL BE LISTED ON THE
SUPPLIER DATA REGISTER – SDRL CODE G01
Abbreviations : A – Award, D – Delivery, „-„ – Before, „+‟ – After, Blank – No Requirement
Example : +4A = four weeks after Purchase Order award, -2D = two weeks before delivery
PURPOSE & TIMING
SDRL With For Databook
SDRL – CODE DESCRIPTION
CODE Bid () Revie IOM MDB
w
FACTORY ACCEPTANCE TEST (FAT) PROCEDURES
P09 Specific performance, functionality, inspection and test criteria to be +4A
satisfied are defined in Specification No. XXX, Section YYY.
SUPPLIER DOCUMENTS WHICH SATISFY THE SDRL CODES REQUIRED BELOW SHALL BE LISTED ON THE
SUPPLIER DATA REGISTER – SDRL CODE G01
Abbreviations : A – Award, D – Delivery, „-„ – Before, „+‟ – After, Blank – No Requirement
Example : +4A = four weeks after Purchase Order award, -2D = two weeks before delivery
PURPOSE & TIMING
SDRL With For Databook
SDRL – CODE DESCRIPTION
CODE Bid () Revie IOM MDB
w
GENERAL ARRANGEMENT DRAWINGS
Show main dimensions and weights, fixing/mounting sizes and locations, terminal box
E01 locations and cable entries, size of cable entry threads, location and size of earthing
connection. Also show detail of shipping splits and/or items removed during shipping.
ELECTRICAL TERMINATION/ WIRING DIAGRAM
E02 Show details of terminal arrangements, cables, cable glands, etc.
+2A +4D
ELECTRICAL SCHEMATICS +4D
E04 Show full control logic, illustrating component identification legend and setting ranges for +4A
all protective devices.
CIRCUIT SCHEDULE +4D
E05 +4A
Showing installed and absorbed kW ratings of motors, heaters, controls, etc.
ELECTRICAL LAYOUT DRAWING +4D
E06 Show location of electrical equipment, cable trays, junction boxes, etc. Routing of +4A
cables, Buyer cable entry and connection point locations.
06202-ELE-SP-000-024-IF0
ADDITIONAL DEVELOPMENT OF LUHAIS & SUBBA OIL FIELD PROJECTS
GENERAL SPECIFICATION FOR DESALTER TRANSFORMER
06202-ELE-SP-000-024 Sheet 10 of 12 Rev. IF0 -
CERTIFICATION DOCUMENTS
SUPPLIER DOCUMENTS WHICH SATISFY THE SDRL CODES REQUIRED BELOW SHALL BE LISTED ON THE
SUPPLIER DATA REGISTER – SDRL CODE G01
Abbreviations : A – Award, D – Delivery, „-„ – Before, „+‟ – After, Blank – No Requirement
Example : +4A = four weeks after Purchase Order award, -2D = two weeks before delivery
PURPOSE & TIMING
SDRL With For Databook
SDRL – CODE DESCRIPTION
CODE Bid () Revie IOM MDB
w
TYPE TEST/APPROVAL CERTIFICATE +4D
C02 Attesting that equipment has been approved by an independent and internationally
recognized testing authority.
HAZARDOUS AREA CLASSIFICATION SCHEDULE AND +4D
C03 CERTIFICATES
Certificates testifying to suitability of electrical/electronic apparatus for use in Hazardous
Areas.
INGRESS PROTECTION SCHEDULE AND CERTIFICATES +4D
C04 Certificates testifying to suitability of electrical/electronic apparatus for use in Hazardous
Areas.
CONFORMITY CERTIFICATE
C05
Attesting conformance to type approval.
MANUFACTURER‟S STATEMENT OF CONFORMITY/COMPLIANCE
C07 The Supplier shall confirm that the requirements in the requisition for design, +4D
calculations, production, testing, inspection and traceability for all items have been met.
06202-ELE-SP-000-024-IF0
ADDITIONAL DEVELOPMENT OF LUHAIS & SUBBA OIL FIELD PROJECTS
GENERAL SPECIFICATION FOR DESALTER TRANSFORMER
06202-ELE-SP-000-024 Sheet 11 of 12 Rev. IF0 -
06202-ELE-SP-000-024-IF0
ADDITIONAL DEVELOPMENT OF LUHAIS & SUBBA OIL FIELD PROJECTS
GENERAL SPECIFICATION FOR DESALTER TRANSFORMER
06202-ELE-SP-000-024 Sheet 12 of 12 Rev. IF0 -
Rev 0
July 2002
06202-ELE-SP-000-024-IF0