Risk Register

probability =1=very low impact=1=very low priority=1 to 10 = green


probability =2= low impact=2=low priority=11 to18 =yellow
probability =3=moderate impact=3=moderate priority=19to 25 =red
probability =4=high impact=1=high
probability =5=very high impact=1=very high

N Risk Category Probability Impact priority Trigger Strategy Response Plan Risk Owner
Breakdown in machine during Technical supervisor
1 Technical 1 2 2 Accept
making the show for machine room
decrease electrical
2 Cut off electrical power Technical 1 4 4 Accept Using generator for electricity Electrical supervisor
energy
Using skilled engineer for the
3 Stage (weak strength) Technical 1 5 5 Accept Stage supervisor
stage
Weather condition celebrating under weather
4 Environment 1 3 3 Accept
(raining,earthquake …) forecast
Ready for fire extinguisher,fire
Occurring accident during
5 Environment 2 5 10 Mitigate engine,fireman,emergency car &
celebrating the show (fire,mine..)
call, Using CCTV
Legal Doing the meeting with team
6 Conflict between membership 1 1 1 Accept Project manager
(team charter) charter & solve
Event Organizer,
Apply first-aid , employ medical
7 Health of performance group social 1 2 2 Accept performance group
team
manager
Invitation (International teams,
8 Management 3 1 3 Accept Event Organizer
Martyr heroes of family)
9 Can get investment from abroad Economical 3 5 15 Accept Abroad Ministry
Can get the international help of
10 Political 4 5 20 Accept Abroad Ministry
rehabilitation of the country
Can reveal Myanmar culture to know
11 the world and can improve travel Economical 5 5 25 Accept Culture Ministry
business
Can build honorary building of
Leaders of the country
12 heroes by using the fund from the Political 3 5 15 Accept
and citizen
show
13 criticism Political 3 1 3 Accept