Q4, 2016

Lamprell delivers
jackup rigs to NDC
and Ensco

New major contract win Lamprell wins Daman


Page Page Sports and Social day Page
from ScottishPower award for third
3 13 held by Lamprell 14
Renewables consecutive year
www.lamprell.com

also completed and delivered five more UZ750 modules


P-2 Message from the CEO
for Zadco in December page 9. The remaining modules
P-3 New contract award from ScottishPower and three jackup rigs being constructed in our Hamriyah
facility are all currently on schedule and we expect to
P-4 HSES News Update
deliver as planned.
P-5 NBJU News Update
I would like to take this opportunity to welcome Rony
P-7 Rig Refurbishment Update
Nair who joined Lamprell on 16 October to succeed Alan
P-8 Land Rig Services Update Robson as Director - HSESQ. Alan has decided to take
a well-earned retirement and will depart in mid-January
P-9 Modular Work Update
after a period of transition with Rony who will report
P-10 Engineering & Construction Update directly to me. Rony has almost 20 years’ experience
in the oil and gas industry having held positions with
P-12 Service Businesses Update
a number of industry-leading organisations including
P-13 HR & General News ADNOC, Expro and Baker Hughes as well as spending
time in consulting roles with Serinus Energy, Severn
P-11
P-15 Glossary
Solutions, Saudi Aramco and DuPont. In addition, I would
like to welcome Ian Wilkinson to the Lamprell team who

Message
has joined to head up project controls, commercial and
contracts/risk management. Ian has extensive experience
having worked for the Driver Group, Bechtel and CB&I
from the and he will also report directly to me.

CEO Our safety TRIR currently stands at 0.3 which is a good


achievement given our reducing workload and the
challenging day-to-day working conditions. Throughout
Lamprell celebrated 2016 we made good progress in developing our
its 40th anniversary relationship with Saudi Aramco as we move towards
in 2016 and, in spite the proposed joint venture for the establishment of the
of the challenging Maritime Yard in Ras Al Khair. We now have 12 Lamprell
moments, we can all employees assigned full time in the Kingdom with more
be proud of what we lined up to go in January.
have achieved during
the year to create a Despite the ups and downs of 2016, I feel confident that
solid business capable we can go into next year with cautious optimism. The
of weathering a storm Saudi Aramco relationship has the potential to deliver
that has been caused significant long-term returns for the Company; the East
by the continuing global industry downturn. Anglia contract award has raised our profile in what is a
major UK renewables sector, and we have established an
I was very pleased to take over the reins of leading the overhead cost base that will make us more competitive.
Lamprell team from Jim Moffat on 1 October. As most of Our focus is now on successfully completing and
you know, Jim stepped down as CEO of Lamprell and delivering the NDC 8, NDC 9 and Shelf Krathong rigs as
transitioned to a consulting role in October last year. well as the Hereema project, and to sharpen our focus
We will continue to benefit from Jim’s extensive on winning profitable new work in all of our business
knowledge as he supports us until the end of Q1, after streams.
which time he will move on to enjoy his retirement fully. In
the meantime, on behalf of the Company, I would like to I very much look forward to building on our recent
thank Jim for his significant contributions to the business successes and continuing our focus on safety, quality,
since March 2013. efficiency and cost competitiveness as we develop our
profile and reputation in the global energy industry.
It is sometimes said that a new CEO will use his first 100
days in office to observe the business but, since moving Christopher McDonald
to Lamprell, I am pleased to have already been part of CEO
some exciting and important developments. Only a few
days after joining, we signed a significant contract with
Master Marine for a major vessel upgrade and then later,
in November, we secured a second major contract with
ScottishPower Renewables page 3 for the fabrication of
60 jackets for the East Anglia One offshore wind farm in
the North Sea. During the last four months of the year, we
delivered the NDC 7, Ensco 141 and Shelf 122 rigs and

2
New contract award from ScottishPower

After many months of The East Anglia One modern facilities in Belfast, skills are once again
negotiations, Lamprell project is located in the prior to final delivery to transferrable to other areas
successfully secured UK waters of the southern SPR. Fabrication work in of the energy industry and
a new contract award North Sea and aims to be Lamprell’s Jebel Ali and beyond our traditional
in November from the best value offshore Sharjah yards in the UAE sweet spot in the oil &
ScottishPower Renewables wind farm to go into is scheduled to start in gas sector.”
(SPR) for the fabrication construction anywhere in March 2017, with final
of 60 jackets and piles for the world. It is a large-scale deliveries to be made to Lamprell has a proven
the “East Anglia One” wind project which will utilise the client between March track record of working
farm. As we are all aware, 102 turbines, each with a and October 2018. for clients in the oil & gas
the market continues to capacity of 7 megawatts, space but we have a clear
be very challenging and which is expected to Commenting on the award, goal to expand our footprint
yet Lamprell has been generate power for more Christopher McDonald, into the wider energy
successful in winning this than 500,000 homes Chief Executive Officer, industry. The renewables
strategic award despite every year. Lamprell, said: “We are sector is fast-growing with
fierce competition from proud to be part of this similar, further projects
rival bidders. With an Lamprell’s contract will also flagship project developed expected to be launched
approximate contract create jobs in the UK as in the North Sea. This is in the coming years.
value of US$225 million, we will work closely with a significant award for This project allows us to
Lamprell will fabricate and Harland & Wolff in Belfast Lamprell and represents demonstrate how we can
deliver the 60 foundations on this project. Drawing on a big step forward in provide high quality, safe
to SPR who will then install 150 years of experience servicing the fast growing products in other areas of
them offshore. in marine construction, renewables segment. the energy industry and
Harland and Wolff will This project gives us an gives us a solid platform
perform jacket assembly opportunity to demonstrate to diversify our business
works for Lamprell at their how our fabrication streams.

3
www.lamprell.com

HSES News Update


Bureau Veritas ISO recertification
audits successfully completed
Lamprell is pleased to divisions have now been
report that comprehensive successfully completed.
recertification audits by The Quality team’s efforts
Bureau Veritas on the in updating the relevant
new ISO 9001:2015 documentation was very
and ISO/TS 29001:2010 much appreciated by the
standards for Lamprell’s management team and we
core facilities in Jebel Ali, aim to ensure that all of our
Hamriyah, Sharjah, as certifications remain up
well as our E&C and O&M to date.

Safety stand down held in Hamriyah


working unsafely. Lamprell job. This includes looking
management encourages at their work area before
its workers to stop an starting a task to identify
activity if they witness and remove any risks and
an unsafe act by using a making this part of their
STOP card which has been pre-work routine. The
especially designed for this slogan “see it – own it – fix
purpose. Anybody working it” is regularly used and
in our facility can stop a workers are constantly
task and the management reminded that we all have
team wanted to reiterate a duty of care to make
that and encourage the use sure that our colleagues
of the STOP cards. go home safely to their
In Q4 Lamprell held a purpose of the stand families. At Lamprell
full safety stand down down was to discuss safe Supervisors are tasked we are committed to
in its Hamriyah facility working, stopping any with regularly encouraging creating a culture which
for both the day and unsafe acts as well as workers to follow certain is second to none in safe
night shift workers. The intervening if anybody is steps before starting a project delivery.

New iSupplier initiative rolled out Renewable energy in rig design


Lamprell continues to the “Al Gharbia”. They
assist multiple clients to are powered by solar
reduce the environmental panels with an auxiliary
impact of their rigs by battery to support. Going
incorporating elements of forward, Lamprell will
renewable energy in the continue to engage with
design and engineering a range of stakeholders
aspects of their across its value chain to
projects. New and more roll out similar initiatives
environmentally friendly and help minimise the
iSupplier aircraft warning lights were environmental impacts of
recently fitted onto the the wider industry.
Lamprell’s P&SC and efficiency. It also highlights NDC 7 rig,
Finance Departments have Lamprell’s proactive
been busy engaging with approach to improving
a large number of vendors the environmental
to register their companies sustainability of company
using a new tool called operations across its
“iSupplier” via Lamprell’s supply chain by decreasing
website. The tool allows the need for paper
for web based logging and consumption. Our goal is
processing of invoices to have all our vendors New more environmentally friendly aircraft warning lights, which are
powered by solar panels with an auxiliary battery, were recently fitted
and will help improve registered on the new onto the NDC 7 rig “Al Gharbia”
Lamprell’s organisational system by early 2017.

4
NBJU News Update
Lamprell delivers seventh rig to its biggest client

A small ceremony was held after Lamprell successfully delivered its seventh rig, “Al Gharbia”, to NDC in December 2016

Lamprell successfully higher management and


delivered the jackup the NDC Board of Directors
drilling rig, “Al Gharbia” for their guidance and
to its biggest client NDC continuous support. He
in December. Completion also thanked the Abu
and delivery of the jackup Dhabi Marine Operating
rig, on time and on Company (ADMA-OPCO)
budget, was marked at an for their cooperation and
inauguration ceremony trust and Lamprell for their
held at Lamprell’s distinguished efforts in
Hamriyah facility in the completing the project.
UAE on 22 December. The
contract for the NDC “Al Commenting on the
Gharbia” rig was signed delivery, Lamprell CEO
in November 2014 and Christopher McDonald said
this is the seventh rig in a “I am pleased to announce
series of nine being built the completion and delivery
and delivered by Lamprell of this seventh jackup rig to
to NDC. NDC, as planned. Rig “Al Delegates from NDC greet the “Al Gharbia” rig project team
Gharbia” is the 25th jackup
NDC CEO Abdalla Saeed drilling unit that Lamprell
Al Suwaidi, commented: has delivered since its
“NDC launched this listing in 2006 and is the
strategic project to fourth jackup rig that we
maintain the highest have delivered in as many
levels of reliability and months. This successful
resilience, as well as to project delivery would not
ensure that we provide have taken place without
high-quality, cost-efficient, close teamwork and the
and versatile drilling strong relationship between
services to our clients, the Lamprell and NDC
ADNOC Group companies, project and management
without compromising on teams. We look forward
HSE standards and asset to working with NDC on
integrity.” Mr. Al Suwaidi the remaining two projects
extended his sincere which are both proceeding
appreciation to ADNOC well.” NDC 7 “Al Gharbia” inauguration ceremony
was held in our Hamriyah facility

5
www.lamprell.com

Second jackup rig successfully delivered to Ensco


In early November 2016,
we saw the successful
completion of construction
of the “Ensco 141” jackup
drilling rig and its delivery
to Ensco Intercontinental
GmbH, a subsidiary of
Ensco plc (“Ensco”).
Lamprell CEO Christopher
McDonald commented
on the delivery: “I am
pleased to be marking the
completion and delivery
of this rig to Ensco, one
of our key clients. Our
combined project team has
collaborated effectively
and has performed well
to deliver this project
while at the same time
maintaining an exceptional
safety record. Lamprell has Lamprell delivered its second rig to Ensco Intercontinental GmbH in November last year
demonstrated its capability
to fabricate high quality,
complex products for use the second rig with the alongside its sister rig Hamriyah facility, which are
by leading operators in the LeTourneau Super 116E at Lamprell’s stacking progressing as planned
global energy industry.” (Enhanced) Class design facility in Hamriyah, United and will be delivered over
which Lamprell has Arab Emirates. Lamprell the coming four months.
The contract for the “Ensco delivered to this leading currently has a further
141” rig was signed in drilling operator. The rig three new build jackup rigs
April 2014 and this is has been warm-stacked under construction at its

6
Rig Refurbishment Update
“Emerald Driller” successfully refurbished
We welcomed a new which would meet the
client in September when client’s specifications.
Vantage Drilling brought
their rig, “Emerald Driller” As with all projects, there
to Lamprell’s facility in was a keen focus on safety
Port Khalid for some and we were pleased to
minor upgrades and be working with a similarly
refurbishment works before safety-focused client.
talking up a new contract in Both parties worked well
Qatar. The rig is relatively together and supported
new having been built in each other to ensure the
2008 and was in Lamprell’s project was completed
yard primarily for without incident. The rig
equipment overhauls and departed Port Khalid on
upgrades to the rig engines 1 November 2016 to take
and drilling equipment and up its new contract after
a number of repairs to the successful completion
ballast piping and auger of the works. We believe
ditch. One of the main a good relationship has
work scopes included the been created and we look
removal and replacement forward to working with
of the cement unit with a Vantage Drilling again in
Lamprell successfully completed refurbishment work to the rig newer, upgraded version the future.
“Emerald Driller” which sailed away from our facility in November 2016

Noble “Houston Colbert” Refurbishment of rig “Paragon


refurbished prior to contract award M1162” successfully completed

The Noble rig “Houston Colbert” was refurbished by Lamprell recently

Lamprell’s strong to the cantilever, repairs to


relationship with Noble the legs and refurbishment
continued with the arrival of other equipment. All
of the rig “Houston Colbert” work was successfully
Paragon’s rig “M1162” was successfully refurbished in November 2016
in our Hamriyah facility for completed and the rig took
upgrade and refurbishment up its new contract in early Lamprell welcomed the to the legs, the raw water
work in September 2016. December 2016. The work latest rig into our Sharjah tower and the helideck as
The rig was initially sent to was completed without facility, the “Paragon well as blast and painting
be warm-stacked but was injury or safety incidents. M1162”, for upgrade and to a number of areas
soon awarded a contract This is a great testament refurbishment works around the rig. Following
and the scope of work of how well both Noble and during November 2016. successful completion, the
developed from minor Lamprell worked together The rig refurbishment rig was relocated to the
repairs to a more extensive and the focus on safety is project developed into an breakwater where it was
refurbishment project. paying dividends. upgrade including repairs warm-stacked.
Works included an upgrade

7
www.lamprell.com

Land Rig Services Update


“WDI 878” mud system delivered on schedule
In December Lamprell was completed within
successfully delivered a the four-month schedule.
4,500 bbl mud system and The full package system
high-pressure piping to was delivered to Kuwait,
WDI, one of the leading assembled on site and
international drilling commissioned by Lamprell
contractors in the Middle and WDI.
East region, for their “WDI
878” land rig, on time and This is the 17th mud system
within budget. In addition that Lamprell has built and
to the original contract, successfully delivered in
there was a significant the last three and a A bbl mud system was delivered by Lamprell to WDI for
their “WDI 878” land rig
amount of extra work which half years.

LRS coiled tubing related products delivered


Building on our expertise to the other products
in designing CT towers for designed and built for such
multiple clients, Lamprell applications by Lamprell.
is expanding its product Further solutions for the
offering with the design promising CT operations in
and construction of a the region will follow in due
new rotating table for course so keep reading
CT reels. The product Lamprelltimes to find
is DNV-certified, similar out more.
Lamprell is expanding its product offering with the design and build of
new rotating tables for coiled tubing reels

LRS refurbishes equipment to API standards


Lamprell continues to build on
its portfolio of API licenses and
refurbishment of equipment
according to API’s recommended
practices. A number of our clients
have trusted our mechanical
and QC teams to repair and
inspect drilling and hoisting
equipment on site and in our API
workshop in Hamriyah. In Q4 we
worked with a variety of clients
to repair and inspect drilling and
hoisting equipment. Lamprell’s mechanical and QC teams completed a number of repairs and inspections to drilling
and hoisting equipment in our API workshop in Hamriyah

8
Modular Work Update
Lamprell delivers further modules for UZ750 project and
celebrates safety success

The UZ750 project team delivered five CPARs in December 2016

In early November 2016, has a TRIR of 0.16 which


the Lamprell Jebel Ali is well under the group
project team working on KPI of 0.25.
the Petrofac UZ750 project
successfully completed Also in November,
a major milestone by mechanical completion
reaching five million was achieved on the
manhours without a critical SPAU04 and
DAFWC. In addition to this, NPAU04 modules and
the project team delivered the two PAU’s sailed
over 29,000 safety away to their Abu Dhabi
observation cards which destination. This took the
have greatly contributed overall delivery tally to
to achieve mechanical remaining four units
to the safety performance 36 modules. The project
completion of the next set including one WPAU03
on this project. The project team then moved its focus
of five CPARs which they and three WPAMs modules
successfully completed in which are progressing as
December 2016. These planned. These final four
five modules are expected units are expected to be
to sail away to the Central mechanically complete by
Zakum Island site in mid-January and will sail
early Q1. away to the West Zakum
Island in Q1. This will bring
The current focus is on our total delivery for the
piping erection, piping UZ750 project up to the full
The Petrofac UZ750 project team celebrated reaching over five million hydro-testing and EIT 45 modules.
manhours without a DAFWC in November 2016 erection works for the

9
www.lamprell.com

Engineering & Construction News


EPC of Dugas berth pipeline and marine loading arm
The Dugas berth pipeline and further works have to DEWA utility and
project, a multi-disciplinary since been performed on other services. Lamprell
project which was awarded the pipeline. Lamprell recently completed the
to Lamprell in August worked closely with the installation of the pipeline
2015, consists of marine client and authorities in in full compliance with
loading facilities and a order to agree on the such requirements and
3.2km pipeline within the requirements to comply the commissioning
Jebel Ali Freezone. The
marine loading facilities
with local permits. The
pipeline had to be laid
process has commenced
successfully.
DUGAS
were completed by manually due to the close
Lamprell in May 2016 proximity underground

ENOC project safely completed Lamprell awarded new Horizon


Lamprell safely completed in early November
Terminals contract
multi-disciplinary works 2016 as per our client’s Lamprell was awarded obtained and engineering
for its long-standing requirement. I am very a contract to provide and procurement work
client, Emirates National pleased with the safety ME&I services for the is running to plan. This
Oil Company (ENOC), record on this project and Horizon Terminals project project, which is for a client
within their EPCL Jebel would like to thank the in early 2016. The scope forming part of the ENOC
Ali refinery. A completion team involved for all their of work is spread across group, is scheduled to be
certificate was issued for hard work.” four locations including completed in Q3 2017.
the mechanical works the main terminal, the
completed in the terminal’s quayside and jetty, the
live plant and brownfield pigging station and a fourth
environments. Head of area which is located close
Lamprell’s E&C Division to Dubai International
Darren McDonald said: Airport. Project
“The project started in late construction approvals
2015 and was completed and NOCs have been

Lamprell continues to provide maintenance services to SNOC


The E&C team continues contract. This is a broad across the Sajaa gas
to provide ongoing services scope including project plant, well sites and flow
to Sharjah National Oil management, engineering, lines with some also in
Corporation (SNOC) for procurement, construction the Hamriyah Liquefied
the Saaja gas field as part and maintenance. The Petroleum Gas and
of its annual maintenance ongoing works are spread condensate terminals.

10
ENOC awards best ME&I contractor to Lamprell
ENOC is a client with where we received “Best
whom Lamprell has shared ME&I Contractor” for
a long-standing record for project work completed
successful project delivery. within the ENOC Terminals.
In 2015 Lamprell’s E&C Lamprell remains highly
division accepted an award regarded by ENOC for our
for “Outstanding Project safety, quality and on-time
Performer” and we are execution and we continue
pleased to announce that to deliver site projects for
in October 2016 we were this key client at its
once again recognised, this various facilities.
time in the silver category Lamprell were recognised by ENOC in the silver category as “Best
ME&I Contractor” last October

E&C pressure vessel projects update


Fabrication is in full swing in de-aerator package for the
Lamprell’s Sharjah yard for six Yibal Khuff project in Oman
H2S high-pressure gas scraper has been completed and
vessels being constructed fabrication has commenced.
for the Gasco project in The scope of carbon and
Abu Dhabi. The project is stainless steel vessels and
progressing well with an the supply of process internals
excellent safety record and is are on track for delivery in
on track for delivery in January. Q2 2017. Lamprell is fabricating multiple pressure
vessels in its Sharjah facility
Similarly, the design of the

Kaombo project continues to progress


Ten suction piles left tanks are currently March. One standout
Lamprell’s Sharjah under construction, for this project is the
facility safely in August also in Lamprell’s safety performance.
for Angola, and after Sharjah facility, and are The combined efforts of
a long voyage, all of nearing completion. Lamprell, Heerema and
the piles have been Completion works and Total have produced
safely deployed by load out preparations excellent results as
the Heerema offshore are underway with the the project celebrated
team in the deep first lot expected to two million manhours
water of the Kaombo depart in January, with without a DAFWC in
block 32 project. subsequent load outs early December.
Eighteen buoyancy planned in February and

The Kaombo project team celebrated progress and reaching two million manhours without a DAFWC in December 2016

11
www.lamprell.com

Service Businesses Update


Sunbelt wins new contract awards
Lamprell’s subsidiary to the Halliburton work forward to building a strong
Sunbelt Safety is pleased sites. Sunbelt Safety will working relationship with Sunbelt Safety also
to announce the award provide H2S safety during the Haliburton team. continues to strengthen
of a master purchase Halliburton’s well testing, their relationship with GDI
agreement from Halliburton coil tubing and well logging In addition to the Haliburton in Qatar with the recent
in the Kingdom of Saudi activities. The initial award, Sunbelt Safety award to provide H2S
Arabia (KSA) to provide work order is for two H2S was awarded a H2S safety services on the
H2S safety services to packages of equipment service contract for the GDI jackup rig “Leshat”.
Halliburton’s Rigless however the total “Sagadrill 1” rig, which The contract will run
Services Department. The requirement is expected has been contracted for a from the beginning of
agreement is valid for a to increase in line with one well drilling campaign, January throughout 2017,
four-year period and work Halliburton’s activities. This offshore Abu Dhabi for with a renewable option
will commence in January is an excellent opportunity Bunduq Oil. The work is thereafter. “Leshat” is the
2017 with two packages for Sunbelt Safety to estimated to take place first of three GDI rigs to go
of equipment as well as establish a long-term over a three to four-month to work for Ras Gas in a
a number of technicians partnership with Halliburton period and will commence new drilling programme.
who are being mobilised KSA and the team look in December 2016.

O&M successfully renews ENOC contract for an


additional three years
Lamprell’s O&M division manpower and services
has successfully retained for a period of three years
a contract with one of its with effect from November
major clients, ENOC. In an 2016. ENOC is one of
extensive re-bid exercise, the O&M division’s major
the team secured a letter clients, building on an
of intent for electrical and association which began
instruments maintenance back in 1999.

Quarterly safety awards rolled out by O&M team


In our ongoing efforts quarter. In Q4, the O&M
to improve safety and management team visited
cultivate a safe culture Dubai Petroleum’s Jebel Ali
within our workforce, the onshore facility to attend
O&M team has rolled out their site safety meeting
a new quarterly safety and present awards to the
champion initiative for safety champions of the
its contract employees quarter. Congratulations
working at clients’ sites. go out to Warehouse Clerk
Employees that have Umesh Raj Sasidharan
consistently achieved high Nair, Materials man Ibrahim
HSES standards and have Abdul Rehman
proactively demonstrated and Technical Assistant
Congratulations go out to Warehouse Clerk Umesh Raj Sasidharan
their awareness in Faiyaz Ahmed for winning Nair, Materials man Ibrahim Abdul Rehman and Technical Assistant
accident prevention are the awards. Faiyaz Ahmed for winning the O&M safety awards
awarded with prizes each

12
HR & General News
New CEO holds first town halls
Lamprell’s new CEO started in the US and his his experience, and he
Christopher McDonald experience in the industry encouraged employees to
held a series of mini which has been gained all ensure timely delivery of
town hall talks across all over the world including the current projects which
three facilities located the US, Asia, Australia, would be crucial for clients
in the UAE in order to Europe, UK & the Middle during uncertain times for
introduce himself to East. He also discussed the industry as a whole.
Lamprell employees and the Group’s goals for the The presentations were
provide the team with a future which includes a very well received by all.
general company update. strong focus on business New Lamprell CEO
Christopher explained development, an area of Christopher McDonald introduced
himself to the Lamprell team in
his background which particular strength given October after holding a series
of mini town hall talks

Jebel Ali facility holds sports & social day


On 15 December, a sports winner from a veritable
& social day was held at cast of star performers,
Lamprell’s Jebel Ali facility however there could only
for all staff based there. be one for each division
A number of speed and and the stand out singing
strength competitions act this year was awarded
were held followed by to rigger Mr Hamsa Koya.
the theatrical part of the The dancing competition
day where our budding highlighted the hidden
“Bollywood” stars put on talents of many of our
performances that included workers with the eventual
interesting singing and winner, Mr Rajeev Rajan,
dancing routines. With the taking the stage by storm
standards increasing year and entertaining the crowd
on year it is always tough to almost fever pitch. A fun packed sports and social day was held at Lamprell’s
for the judges to pick one Jebel Ali facility in December

Robin Adhikari Khabir Hamsa Koya Rajeev Rajan Welder’s Team


runner-up Chowdhary Winner Singing Winner Dancing Captain runner-up Scaffolder’s Team Winners – Tug “O” War
100 m Winner 100 m Competition Competition Tug “O” War

Lamprell makes top 10 at Dubai Dash


The UAE’s largest annual to get people out of the Binoy Jacob, Gokuldas
corporate relay race, the workplace and make them Subramanian Thoomat,
Dubai Dash, took place active. Out of a total of Hani Elkurd, Oliver
on 7 December 2016 and 43 teams, Lamprell came Stafford, Joven Manalang,
Lamprell entered a team of in at 9th place beating Lawrence Himsworth
their top 10 runners hoping the previous year’s result. and Piotr Jaworski. The
to beat the previous year’s Thanks go out to our event was followed by a
result, which was 10th Lamprell representatives social evening including
place. The event, which who participated in this a prize giving with DJ and
took place at the Els Club event, namely Steven entertainment as well as Team Lamprell made it to
with stunning views across Wagner, Anees Sulaiman, drinks and snacks. 9th place at the Dubai Dash
the golf course, is designed Darren Macdonald, corporate relay race

13
www.lamprell.com

Lamprell wins Daman award for third consecutive year

Lamprell was delighted to win a Daman sponsored award for improved corporate health and wellness performance for a third successive year

Lamprell were awarded the of a huge number of our welfare, including our service awards and our
Daman-sponsored national workforce, the judges voted extensive employee health improvements in yard
award for improved Lamprell into first place screening, our annual absenteeism in 2016.
corporate health and ahead of Seadrill who heat stress campaign, the
wellness performance for finished runners-up. Other various health education Once again, this award
the third successive year. category award winners and awareness talks quite rightly recognises the
Having won it for the first included companies such that we host for admin efforts of our people not
time in 2014, the 2015 as CH2M Hill, ABB, Al and yard personnel, the only in HSESQ and HR/
judges were looking for Mansoori Engineering, fact that we have DHA- Admin, where many of the
evidence of improvements Mashreq Bank and the approved doctors and initiatives are coordinated
in our achievements Atlantis hotel. clinics in our yards, the but also the cooperation
around employee health medical facilities that we and commitment of all of
and wellness and we won it Lamprell’s repeated provide at our camps, our our employees in helping
again. In 2016 it was even success in receiving this alcohol testing policy, the to maintain such excellent
harder to demonstrate award has arisen from its flu vaccination campaigns, standards.
continued improvement efforts on multiple levels our employee sports and
but thanks to the efforts to improve employee social programme, long

Breast cancer awareness talk held for Lamprell ladies


October was recognised cancer is curable if
globally as breast cancer identified at an early stage.
awareness month and with Regular screening can
this in mind, Lamprell’s help recognise possible
HR department held a warning signs or symptoms
breast cancer awareness helping take adequate
talk hosted by Dr. Heera treatment measures when
Manuel from the Zulekha still at its earlier stages.
Hospital in October. The event was well
Breast cancer is the most attended and attendees
common type of cancer received vouchers for
amongst women worldwide free oncologist and
and with the increased mammogram consultations
global awareness of the at Zulekha Hospital in both
disease, it is common Sharjah and Dubai. Female Lamprell employees were invited to a talk on breast cancer
knowledge that breast which was held in October last year

14
Lamprell showcases at 2016 ADIPEC
Lamprell exhibited at the more than 132 countries. and Procurement took time Hani Elkurd presented
world’s biggest oil and gas In attendance at the event out of their schedules to a paper on coiled tubing
exhibition and conference were current Lamprell CEO represent the company in conjunction with
which took place from Christopher McDonald, at our exhibition stand. Schlumberger which was
7 – 10 November in Abu former CEO Jim Moffat The event marked four well attended. Our stand
Dhabi last year. Some of and many of Lamprell’s days of high-level industry saw good levels of activity
the world’s most influential management team. In discussions that shape including discussions with
energy ministers and addition, representatives policies and strategies for many industry peers and
decision makers opened from departments including the new energy landscape. clients. We were also
ADIPEC 2016 with a series Business Development, Also at the event, honoured with a visit from
of powerful messages for Marketing, HR, Lamprell’s head of LRS NDC CEO Mr Abdalla
the visitors attending from Commercial, Engineering and Rig Refurbishment Saeed Al Suwaidi.

Lamprell’s head of LRS and Rig Refurbishment divisions


NDC CEO Mr Abdalla Saeed Al Suwaidi (centre) visited Hani Elkurd presented a paper on coiled tubing in
Lamprell’s stand at ADIPEC conjunction with Schlumberger at ADIPEC

Glossary of Terms
CEO – Chief Executive Officer IT – Information Technology
COO – Chief Operating Officer KSA – Kingdom of Saudi Arabia
CPAR – Pre-Assembled Racks LRS – Land Rig Services
CT – Coiled Tubing LTA – Long Term Agreement
DAFWC – Day Away From Work Case ME&I – Mechanical, Electrical and Instrumentation
DIP – Dubai Investments Park NDC – National Drilling Company
DNV – Det Norske Veritas O&M – Operations and Maintenance
DPE – Dubai Petroleum Establishment PAM – Pre-Assembled Modules
DUGAS – Dubai Natural Gas Company Limited PAR – Pre-Assembled Racks
DUSUP – Dubai Supply Authority PAU – Pre-Assembled Unit
E&C – Engineering & Construction QMS – Quality Management System
EIT – Electrical, Instrumentation and Telecom SNOC – Sharjah National Oil Corporation’s
ENOC – Emirates National Oil Company SPR – ScottishPower Renewables
EPC – Engineering, Procurement & Construction UAE – United Arab Emirates
EPCL – ENOC Processing Company Limited UWILD – Under Water Survey in Lieu of Dry Docking
HR – Human Resources VP HSESQ – Vice President Health Safety Environment
HSES – Health Safety Environment and Security Security and Quality
HSESQ – Health Safety Environment Security and Quality WDI – Weatherford

15
Certifications:
Bureau Veritas ASME National Board

ISO 9001:2015
ISO/TS 29001:2010
OHSAS 18001:2007 NB, R
ISO 14001:2004 U,S,PP,U2
ISO 27001:2013

Monogram Licenses
2B-0133 4F-0281 16C-0278
2C-0113 7K-0303 16D-0075
4F-0094 8C-0182
4F-0227 16C-0202

API QMS API - Q1 TRACE

Q1-1322
Q1-0633
2427, 0881
R

You might also like