Professional Documents
Culture Documents
WK 7 Projstombaughj
WK 7 Projstombaughj
WK 7 Projstombaughj
Jamie Stombaugh
Walden University
and cybersecurity, is contracting a consulting firm to develop a training program centered around
product liability. This training program must cover both domestic and international liabilities
due to Electron Corporation having plants in 16 countries along with business connections across
the globe. Previously, the legal department within Electron Corporation had created and
delivered a product liability course to its employees. However, the 4-hour course took on a
lecture style with many generalizations, and it failed to achieve the overall training objectives.
The purpose of this training program is to educate employees on product safety, product
liability, and provide a systematic approach of how to handle the day-to-day problems that arise
within the various Electron Corporation facilities. Upon completion of this training program,
liability issue.
Acceptance Criteria
The acceptance criteria for this training program consists of the delivery of a one-day
course that instructs the employees of Electron Corporation on product safety and liability issues
that could result in lawsuits. In addition, employees will learn the proper way to document
3
STATEMENT OF WORK (SOW)
potential product safety or liability issues, how to follow the pre-determined chain of command
to communicate all product safety or liability issues, where to obtain the latest manufacturing
Period of Performance
The first two (2) weeks of the project will be dedicated to preliminary interviews and data
gathering. The third week of the project will be dedicated to the physical creation of the training
program along with consulting the legal department for approval on all content. The fourth week
of the project will be reserved for follow-up interviews and additional data gathering, if needed.
Also, consultation with the legal department and physical creation of the training program will
continue during this time. The fifth week of the project will be used to finalize the content and
prepare for the implementation. The duration of the project from concept to completion will be
Rationale Statement
For my project, I chose to use Case study 21: Craig Gregersen: Balancing a Range of
Stakeholder Interests When Designing Instruction. I chose to stick to the five (5) week timeline
that was presented in the case study. Ideally, I would have pushed for at least eight (8) weeks to
complete a training program of this size. I assumed that more than half of my timeline would be
spent interviewing and gathering data. Given the background of the legal department, I assumed
that two weeks to consult with them on all content was probably a bit tight, but I did not want to
I felt the input from Stan Neuhaus, a senior design engineer for Electron Corporation and
the chair of the Safety Steering Committee, was the most valuable information contained in the
case study. Stan was laser focused on the broken chain of communication within the
organization along with the desperate need for organizational structure and procedures. I agreed
with the items Stan was suggesting. Therefore, I used much of his feedback as the foundation to
my training project. To me, an organization cannot fluidly function and flourish without
Rationale Statement
I developed these charts assuming that the Training Project Manager will be responsible
for ensuring almost all aspects of the project are completed; however, the Lead Designer will
take on the responsibility once it gets to the content creation portion. Senior Management will
ultimately be accountable for most aspects of the project since they are the final say in the
Project Schedule
8
STATEMENT OF WORK (SOW)
To complete the project schedule and resource allocation plan, I made assumptions as to
the wages of each member involved in the project. I also made assumptions at how long it
would take each member to complete their portions of the project. I fully understand these
wages and time allowances could be over/underestimated. When creating my resource allocation
plan, I accounted for two engineers and two members of the legal department to be working on
their portions of the project. Wage estimations are laid out below. The project total is estimated
at $29, 045.
Communication Plan
10
STATEMENT OF WORK (SOW)
Rationale Statement
To complete this portion of the project, I assumed that time was allotted and approved for
preliminary work and post work. However, the preliminary work and post work did not impact
the five-week timeline given for the actual project. The actual project itself was scheduled to
Rationale Statement
For this portion, I followed the basic guidelines for closing out a project. I assumed the
Louise Masoff and Craig Gregersen worked closely with each other throughout the duration of
12
STATEMENT OF WORK (SOW)
the project. Therefore, I found it important for Louise and Craig to act as a team in many of the
project close-out action items. I did struggle in terms of when and where to involve the
engineers from Electron Corporation. Ultimately, they will be the end-users, but their input is
vital to the success of the project from start-up to completion. However, I was mindful of the
fact that the engineers have a day-to-day job that they must complete, so their time could not be
Ertmer, P.A., Quinn, J.A., & Gkazewski, K.D. (Eds). (2019). The ID casebook: Case studies in