QB0025-F-MST-CIV-030-0016 - Block Works - R0
QB0025-F-MST-CIV-030-0016 - Block Works - R0
QB0025-F-MST-CIV-030-0016 - Block Works - R0
10-POINT EVALUATION
QB0025‐F‐MST‐CIV‐030‐ Contractor
Project Yasmeen City Projects - Buildings MS Ref. No. HCCQ
0016 (MS Owner)
Reviewed Date of
JOJIE GONZALES 07/07/2021 Rev No. 0
by Review
Company Details - Address, Tel & Fax No’s; E-mail, Web? YES
Title - What task(s)? and Ref No. YES
Project Contact Details YES
Location of Works - General & Specific YES
Name of Company Contact + Phone No. YES
Start Date and Duration of Works PART
Page and Paragraph Numbers YES
2. Description
Scope of the block work activity have not
General Scope of Works (new build, refurbishment) PART been mentioned. What is "define the
procedures for Temporary Blockwork"?
1.) Setting-up of temporary works (e.g.
Sequence - Explanation of Operation(s) / Process(es) PART scaffold platforms & etc) have not been
mentioned in the sequence of works.
3. Resources
Names and contact numbers of personnel
No of Personnel - for Task(s) / Operation / Process PART
involved should be included in the permit.
Loading platforms, fall arrest equipment
with designed anchorage systems and
bench & movable stone-cutting machine
Plant / Equipment / Tools to be used PART
have not been identified due to missing
temporary works items in the sequence of
work.
Refer to an updated traffic management
Transportation , Delivery & Collection, Traffic Management Arrangements PART
plan.
Materials storage and location plan should
Materials - Delivery to Area(s) of Work(s) & Storage and Management PART
be included.
4. Control Measures to be used
Pre-task briefing sheet should be included in
Induction Training, Task Specific, Specialised YES
the permit to work.
Permits - Hot Works, Areas of High Risk, etc PART Temporary works permit, work at height
Signage to be used have not been identified
Hazard Signage - Appropriate to tasks PART
in this MS.
Security, access & egress have not been
Access & Egress - Security Measures / Signing In & Out PART
addressed.
5. PPE and Welfare and Temporary Accommodation Facilities
Relevant Safety Data Sheets Method Statements Risk Assessments PART Attach chemicals list with MSDS & COSHH.
Hazardous Substances / Materials / Liquids / Gases PART Not identified and assessed.
Designated Storage for COSHH items and Gas Cylinders YES Refer to HSE Plan
Provide drainage and containment of
Waste Management arrangements and Environmental Protection PART cement sludge generated by bench stone
grinder/s and arrange regular disposal.
10. Monitoring and Compliance
Site engineer and supervisors name &
contact numbers have not been included.
Supervisor - Name, Position + Contact Details NO
Names and contact numbers of personnel
involved should be included in the permit.
Reference to specific standards relevant to the task YES
Contractor should revise and resubmit addressing required items in the remarks section. For future submissions contractor should
consider & address items in this form during the review of MS & RA.
JOJIE GONZALES HSE MANAGER Jojie Gonzales Digitally signed by Jojie Gonzales
Date: 2021.07.07 10:35:40 +03'00'
METHOD STATEMENT
FOR
BLOCKWORK
TABLE OF AMENDMENTS
Amendment Details
Rev. Description of Amendment Reason for Amendment
Page Section
Document No. Rev. No. Issue Date Purpose of issue Revised sections
TABLE OF CONTENTS
1.0 PURPOSE
2.0 SCOPE
3.0 REFERENCES
4.0 MANPOWER & RESPONSIBILITIES
5.0 TOOLS & EQUIPMENTS
6.0 MATERIALS
7.0 WORK METHODOLOGY
8.0 QUALITY CONTROL
9.0 HEALTH, SAFETY & ENVIRONMENT
10.0 ATTACHMENTS
10.1. HSE FORMATS
10.2. RISK ASSESSMENT
10.3 ITP and CHECKLIST
1.0 PURPOSE
The Purpose of this method statement is to describe the method to be followed in detail, identification of hazards
and elimination of the same for Blockwork, while ensuring all related activities within the project scope of work are
carried out safely in strict accordance with Project Specification & Procedures.
2.0 SCOPE
PROJECT NAME: YASMEEN CITY DEVELOPMENT PROJECT PK 14 – BAYTI COMPLEX
SITE LOCATION: LUSAIL, FOX HILLS QATAR
CONTRACTOR: HARINSA CONTRACTING COMPANY QATAR WLL
CONSULTANT : DAR AL HANDASAH CONSULTANTS
The purpose of this method statement is to define the procedures for Temporary Blockwork , to ensure that the
proposed materials and workmanship to be used at the site are complying with the condition & requirements
as stipulated in the specifications.
3.0 REFERENCES
3.1 Yasmeen City, Architectural and Structural Specifications, Section 13 ‐ Masonry works
3.2 Issued For Construction Drawings/shop drawing.
3.3 QCS 2014 Section 13 – Masonry
3.4 Approved Project Quality Plan
3.5 Material submittals for Blocks, Sand cement & Mortar.
4.0 MANPOWER & RESPONSIBILITIES
‐ Project Manager is the overall responsible for planning and implementation of this Method of Statement and
to ensure that the site team are aware of this Method of Statement and all resources such as manpower,
materials, equipment, and tools area available to carry out the works, safely and as planned with respect to
quality.
‐ Construction Manager is responsible for site execution and implementation of the associated work activities
within this Method of Statement. He is also responsible for maintaining the site in a safe working environment
in coordination with his Project and Site Engineer and Safety Engineers.
‐ Technical Manager is responsible for ensuring that all documents are ready or approved, required shop
drawings are available and issued for construction. He also addresses the technical problems on site and comes
up with solutions in liaison with the stakeholders, to ensure smooth workflow.
‐ Project Engineer/Site Engineer is responsible for direct monitoring and executing all associated activities
within this Method of Statement. They directly supervise de execution of works in coordination with the safety
engineer, QA/QC Engineers, Site Supervisors, and Surveyors. During consultant inspection, they will always be
present for them to know the inspection comments for immediate action.
‐ QA/QC Engineer/Inspector ensures that the Method Statement is strictly implemented by the site team, and
ensures all Inspections and tests are done as per the approved ITP. He also ensures compliance of works to the
Method statement, approved shop drawings and specifications prior to inspections.
‐ Safety Coordinator/Safety Officer is responsible for ensuring that implementation of all safety procedures,
safety measures related to the nature of works being carried out in accordance with Project HSE Plan and
finishing the works without any damage to property, accident, or fatality.
5.0 TOOLS & EQUIPMENTS
Masonry hand tools. Plum‐bob.
Trowels. Masonry splitters.
Hammer. Grinders, Actuated Gun
Chisels. Mortar mixer.
Levels. T Crane
Bob cat Survey equipment, Chalk Line
Water Tank and Pumps Wheel Borrow
Scaffolding
6.0 MATERIALS
References: Section 13: Part 04: 4.4 Concrete Masonry Units
QB0025‐D‐MAT‐CIV‐030‐0003/0022
Concrete Solid blocks (400x200x200, 400x200x150, 400x200x100)
Hollow Blocks (400x200x200, 400x200x150, 400x200x100)
Ready‐mix Mortar, washed sand, Aggregate, Cement, Water
7.0 WORK METHODOLGY
7.1 Preparatory works
7.1.1 Delivery and unloading
Material delivered to the site by the supplier and material verified and received by
storekeeper.
Unloading of the material shall be done with crane/forklift in the designated storage
areas and shall be transported from the storage area to the work locations with
Equipment if required.
All Materials delivered to the site shall
be submitted for approval (MIR), prior
to proceeding to installation on the site.
7.1.2 Setting out & Surface preparation
Layout for block work will be marked as per the approved shop drawing.
The following maximum non‐cumulative erection tolerances shall be complied with:
QCS Part 5 Section 13 Table 5.1
7.2 Block work
Setting out shall be done as per section 7.1.2 of this method statement.
Block walls shall be built from undamaged blocks in stretcher bond.
Existing surface to be cleaned well, watered before laying mortar bed for the first
course.
Application of mortar bedding of 25mm thickness (greater than 10mm) to be laid in
the surface for the first row.
For typical walls 10mm head & joints width to be maintained for all masonry walls.
Jambs of all openings, ends, angles, junctions of walls and partitions with columns.
Should be filled with concrete/mortar.
Maximum height of Block wall to be built per day shall not exceed 1.50m.
• When starting or resuming work, loose mortar and foreign materials shall be cleaned
from the top surface of the work. Surfaces of masonry shall be wetted before resuming
work.
• As far as possible, block walls shall be installed with full blocks. However, if it is
required to reduce the size of block, it shall be done with/without grinders.
All the wastage generated shall be segregated, removed with help of skip and crane to
be disposed from the site.
Block work shall be water cured for a minimum of three days.
Ties used are made from galvanized steel, fully embedded in the horizontal mortar
joints at vertical spacings every 3 layers as per shop drawing details.
Coil lath mesh 3’’,4’’.6’’,8’’ should be placed every two courses as per shop drawing
details.
Joints between portions and floor soffits should be as per shop drawing details.
Head restraint shall be provided as per shop drawing and manufacturers
recommendation.
7.3 Installation Lintel Beams
Lintels to be installed as per the shop drawing, usually the door and window openings, to
support the blocks over the openings.
Construct lintels, using concrete and reinforcement specified. Maintain minimum 200mm Bearing on each
side of opening.
Allow lintels to reach maximum strength before removing temporary supports.
The dimension of lintel will be varies depending on the opening, refer shop drawing for
details.
Prefabricated lintel shall be used as per manufacturer recommendations.
lintel dimension and reinforcement shall be
calculated and submitted for Str. approval.
8.0 QUALITY CONTROL
The quality of the blockwork can be defined in terms of the quality of constituent materials, mortar, tiles
and workmanship and the performance of the constructed facility. Quality control measures can be
assured by following the recommended design, construction materials and procedures. Method
statement and sequence for each part of works shall be provided and approved prior to commencing
each part of the works. Following steps and procedure will be followed:
8.1 Coordination
Interface with other subcontractor’s works shall be done during meetings to ensure that all of
the programme and interfacing work is discussed and concluded prior to the initiation of the
works.
8.2 Inspection and Testing
Quality control procedure shall be followed during the all the works stated in this method
statement.in this regard, approved inspection and testing plan (ITP) shall be followed.
Follow up and Evaluation
Each kind of work stated in this method statement shall be in accordance to the inspection and
testing plan.
Non‐conformance may be identified by inspection from site supervisors. The recording of non‐
conformances from initial identification through to eventual resolution will be the
responsibility of the QA/QC inspector. QA/Qc manager shall verify the correction action carry
out, in conjunction with construction manager involved. Take measures to correct adverse
trends.
9.1 RISK MATRIX
Risk Rating (RR) – Severity x Likelihood
RISK LEVEL ACTION AND TIMESCALE
1‐5 QUICK, EASY CONTROLS SHOULD BE IMPLEMENTED IMMEDIATELY AND FURTHER ACTION PLANNED FOR WHEN
Low RESOURCES PERMIT. MONITORING REQUIRED ENSURING CONTROLS ARE MAINTAINED. MANAGE THROUGH
ROUTINE PROCEDURES. GO FOR ECONOMIC IMPROVEMENTS WHERE POSSIBLE. INCIDENT REPORT MUST BE
COMPLETED.
6‐12 AIM TO REDUCE RISKS BUT COSTS OF PREVENTION MAY BE LIMITED. UNDERTAKE A RISK ASSESSMENT OF THE
Mediu SITUATION / TASK AND IMPLEMENT THE APPROPRIATE ACTIONS. ACTIONS SHOULD HAVE A TIMESCALE AND
SHOULD BE MONITORED. WHERE THE RISK INVOLVES WORK IN PROGRESS UNDERTAKE A RISK ASSESSMENT AS
SOON AS POSSIBLE TO ENSURE THE SAFETY OF THE SITUATION OR TASK. WORK SHOULD NOT START UNTIL THE
RISK IS REDUCED TO AN ACCEPTABLE LEVEL. CONSIDERABLE RESOURCES MAY HAVE TO BE ALLOCATED. CONTACT
YOUR MANAGER AND RISK MANAGER BY TELEPHONE ABOUT THE ACTIONS THAT SHOULD BE TAKEN TO REDUCE
THE RISK/S. INCIDENT REPORT MUST BE COMPLETED. INCIDENT MUST BE ADDED TO SERVICE RISK REGISTER.
15‐25 DO NOT COMMENCE THE ACTIVITY UNTIL A RISK ASSESSMENT HAS BEEN COMPLETED TO ENSURE THE SAFETY
High OF THE SITUATION OR TASK. IF IT IS NOT POSSIBLE TO REDUCE OR ELIMINATE THE RISK EVEN WITH UNLIMITED
RESOURCES, WORK MUST REMAIN PROHIBITED. INFORM YOUR RELEVANT DIRECTOR, YOUR MANAGER AND THE
RISK MANAGER IMMEDIATELY BY TELEPHONE. INCIDENT REPORT MUST BE COMPLETED. INCIDENT MUST BE
ADDED TO SERVICE RISK REGISTER.
INSTRUCTION OF RISK COMPUTATION
Risk assessment is the determination of quantitative or qualitative value of risk related to a concrete situation and a
recognized threat (also called hazard). Quantitative risk assessment requires calculations of two components of risk (R): the
magnitude of the potential loss, also termed Severity (S), and the Likelihood, also termed the probability (P) that the loss will
occur.
Risk is computed by multiplying the probability (P) that the loss will occur against the Severity (S). An example can be made by
taking a probability of 4, which is classified as “Very likely to happen”, and multiplying this against a Severity of 2, which is
classified as “Slight effects”, would give you a Risk Rating of 8, which is interpreted as a medium risk.
RESIDUAL RISK COMPUTATION
A residual risk is a portion of the risk that is left after a risk assessment has been conducted and the identified control
measures implemented.
The Residual Risk is computed by reassessing the risk, taking into consideration the effect of the implemented control
measures on the Probability and Severity (Severity remains the same before and after the implementation of the control
measures).
Using the same example above, after the implementation of the control measures, the probability might be reduced in
rate to, let say 1 (instead of the initial 4) but the severity will still be 2, making the Residual Risk Rating to be 4.
HIERARCHY OF RISK CONTROL
Elimination Control: This has to do with the complete removal of the hazard(s) from the work environment.
Substitution Control: This entails substituting the hazardous activity, process or substance with a less hazardous one.
Engineering control: Isolation of the hazard(s) from people who could be harmed. It includes the installation/erection of a
suitable barrier around the hazard to protect the people working around it.
Administrative control: This control includes changing the way people work or preventing people's exposure to hazard(s).
This may be achieved by installing a warning sign, and clearly marking around the hazard(s) to communicate the people of
Personal Protective Equipment (PPE): Provision of the appropriate PPE to cover and protect an individual person from
hazards.
Note: PPE can be used as a temporary control measure until other more effective control measures are provided. In
most cases a combination of other control measures and PPE can effectively control the risks from hazards and protect
those exposed to them.
10.2 RISK ASSESSMENT
nearby. replace with new one.
Supervisor to ensure tools are checked
before being taken from the store into the
site.
HSE team to check and ensure that all
tools are in good condition.
Do not keep tools on access pathways or
abandoned on work platforms. Unused tools
should be kept inside the toolbox.
4. Working at height. Incomplete platforms Falls of workers and 2 4 8 Safe system of work should be in place 1 4 4
and exposed edge. equipment / tools and briefing given to operatives before
from height which proceeding to work at height.
may lead to injuries All work platforms should be complete
and material and have all the fall protection in place before
damage. being used.
All workers working at height must wear a
full body harness and anchor the lanyard
before starting the work.
Close supervision of work force should be
provided.
Equipment/tools Serious injury to 4 4 16 Supervisor to instruct and ensure that 1 4 4
slipping off from the personnel and/or workers use tool strip bags to prevent small
hands of workers from equipment damage. tools from falling off. Damaged tools shall not
height. be used in the operation.
Safe zone shall be created below the floor
where work activity is taking place to ensure
no worker is exposed to the risk of possible
equipment/tools fall.
Tools not in use shall be kept away in their
boxes when not in use and shall be properly
managed when in use.
Workers should ensure they have a firm
grip on the equipment/tools they are
handling.
RISK ASSESSMENT
TITLE OF THE ACTIVITY: BLOCKWORK
RISK ASSESSMENT REF No.: QB0025‐F‐MS‐CIV‐030‐0016 REV. NO.: 0
Undertake manual handling training.
Activity: BLOCKWORK
LIKELIHOOD (L) :- 5 = Certain, 4 = Very likely to happen, 3 = Likely to happen, 2 = May happen occasionally, 1 = Very unlikely
Likelihood
As Low as Reasonably Practicable (ALARP).
Mandatory PPE 1 2 3 4 5
Safety Shoe
Gloves
Goggle / Mask
High Visibility Vest
Prepared by: AKINLOSOYE A. A. Approved by: SAMER AL OREIBI Date of issue: 19 June 2021
HSE COORDINATOR PROJECT DIRECTOR
Date of Next Review: 18 June 2022
Reviewed & Issued by: ODO SIMON AGBO
PROJECT HSE MANAGER
Project No. Document No.
Location LUSAIL, FOX HILLS QATAR / QATAR
QB0025 QB0025-F-MS-CIV-030-0016
Page Rev No.
Title METHOD STATEMENT FOR BLOCKWORKS
0 Rev.
18 of 16 Code
10.3 ITP and CHECKLIST
Activity Inspection
Quality Control point Controlling Document Acceptance Criteria Frequency Verifying Documents
No.
SC/TP HCCQ DAR
1.0 Preliminaries
1.2 Drawing Approvals As per project specs Approved Shop Drawings. once Approved Drawings H H
1.3 Material Submittals As per project specs QB0025-D-MAT-CIV-030-0003, QB0025-D-MAT-CIV-030-0022 once Approved Material Submittals H H
1.4 Material Delivery lnspection As per project specs Compliance Approved Material Submittals every delivery Material Inspection Request H H
Activity Inspection
Quality Control point Controlling Document Acceptance Criteria Frequency Verifying Documents
No.
SC/TP HCCQ DAR
2.5 Curing and protection As per project specs Blockwork shall be cured for a minimum of 3 days and Each area W S
2.6 Final review of documentation Approved QC Documents pertaining this ITP once Approved Inspection Request H R
H- Hold Point: Written notification H/W: Hold Point W - Witness: Written notification S -Surveillance: No notification required but acvtivity may be subjected to DAR R-Review: Records/ Document Review
required Contractor may not proceed initially & required but Contractor may Surveillance Monitoring.
beyond this point without written transfer to proceed, if DAR do not attend.
confirmation of the Engineer. Witness Point,
as per Engineer
Requirements
Grid Drawing Ref
No. Description HCCQ DAR Remarks
1 Submittals
2 Blockwork Setting out
3 Surface Examination and Preparation
4 Cement & Mortar Mixture
5 Installation of Blockwork, Anchoring & Wall Ties
6 Curing of Blockworks
7 Final Cleaning and Protection
NOTES:
CHECKED BY HCCQ QA/QC ENGINEER DATE:
Name: Signature:
APPROVED BY DAR ENGINEER DATE:
Name: Signature: