Download as pdf or txt
Download as pdf or txt
You are on page 1of 9

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/355145876

Developing singly-curved earthen slab system for houses using mud-concrete

Conference Paper · October 2021

CITATIONS READS

0 16

5 authors, including:

R.M.Anjana Rathnayake Rohantha Jayasinghe


University of Moratuwa University of Moratuwa
1 PUBLICATION   0 CITATIONS    6 PUBLICATIONS   2 CITATIONS   

SEE PROFILE SEE PROFILE

Isuru Nanayakkara Rizna Arooz


The University of Sheffield General Sir John Kotelawala Defence University
22 PUBLICATIONS   30 CITATIONS    18 PUBLICATIONS   104 CITATIONS   

SEE PROFILE SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Energy rating system for urban dwellings View project

Engineering and Social Aspects of Ambalam View project

All content following this page was uploaded by Rohantha Jayasinghe on 08 October 2021.

The user has requested enhancement of the downloaded file.


i
8th International Symposium on Advances in Civil and Environmental Engineering
Practices for Sustainable Development (ACEPS – 2021)

Proceedings of the 8th International Symposium on

Advances in Civil and Environmental Engineering


Practices for Sustainable Development
ACEPS - 2021

Developing singly-curved earthen slab system for houses using


mud-concrete
R.M. Anjana Kalindu Rathnayake1, Rohantha Rukshan Jayasinghe1, Rizna Arooz2,
K.I.U. Nanayakkara3, and R.U. Halwatura1
1Department of Civil and Engineering, Faculty of Engineering, University of Moratuwa, Katubedda, SRI LANKA
2Department of Architecture, Faculty of Built Environment & Spatial Sciences, General Sir John Kotelawala Defence University,
Southern Campus, Sewanagala, SRI LANKA
3Department of Civil and Structural Engineering, Faculty of Engineering, The University of Sheffield, Sheffield, UNITED

KINGDOM

ARTICLE INFO ABSTRACT


Available online 07 October 2021 Sustainable practices in construction industry have become a necessity in recent
times, especially in view of the climate emergency. Using earthen materials is one
more prominent solution. Using earthen materials is limited to flooring or walling
systems, although slabs accounts for 60-70% of embodied energy consumption of
conventional building. This paper discusses the development of a singly-curved
earthen slab system using mud-concrete technology by exploring the construction
Keywords: sequence with a prototype of a 1mx 1m slab having a thickness of 100 mm at the
Singly-curved apex. The construction cost of the proposed slab system was compared with that of
Earthen slabs a conventional reinforced concrete slab system, resulting in a 40% reduction in
Mud-concrete labour and material cost. A load test confirmed the structure could withstand the
compression-only design loading of 2kN/m2.

1. INTRODUCTION the reinforcing steel element. However,


earthen materials have low tensile capacity
Many novel construction techniques and when compared with reinforcing steel. Thus,
practices involving earthen materials have to develop a suitable slab system with earthen
been introduced in recent times to achieve material, either a reinforcing material should
sustainability in construction industry. be used or a compression-only structural form
Although there are many new techniques, should be selected. The latter approach is
most of them are limited to applications in adopted here.
walls—e.g. rammed earth walls (Walker et al.,
2005), CSEB block walls (Maïni, 2005), mud- Catalan vaulting is one such slab system
concrete blocks and walls (Arooz, using a compression-only structural form.
2019)(Udawattha et al., 2016a)— or flooring— Catalan vaulting system (also known as
e.g. mud-concrete flooring (Galabada and timbrel vaulting or Guastavino vaulting) is a
Halwatura, 2019). However, when the construction technique mastered by Romans
embodied energy of building elements are and widely used in gothic architectures which
considered, slab systems contribute to 60%- uses thin tiles to build a compression-only
70% of the total (Foraboschi et al., 2014). If an shell structure (Jayasinghe et al., 2019; López
earthen slab system is to be developed, it will López et al., 2014). The use of thin tiles in a
be a significant step towards a fully earthen vaulting system in Sri Lanka has several
structure. drawbacks including production and
transportation of thin tiles, quality issues in
Conventional reinforced concrete slab local binding agents, higher labour cost, etc.
system relies on tensile strength provided by (Jayasinghe et al., 2019).

214
8th International Symposium on Advances in Civil and Environmental Engineering
Practices for Sustainable Development (ACEPS – 2021)

Mud-concrete is a novel development to As an initial trial, a scaled down


the traditional walling techniques. This prototype of 1.0 m span will be studied in the
method is used as an in-situ cast walling remainder of the paper. The scaled down
system (Arooz et al., 2017). In-situ casting prototype is of a 100 mm rise but has the same
systems are labor-intensive and time- minimum vault thickness of 100 mm,
consuming (Löfgren and Kutti, 2001). considering the maximum particle size of the
However, the use of sustainable materials mud-concrete mix.
makes these systems cost-effective.

This paper discusses the possibility of 4. STRUCTURAL ANALYSIS


using mud-concrete in construction of a singly
curved slab system, as a sustainable and a cost- Analysis of this structural form using
effective solution. graphic static has already been done c Here,
analysis of the structural form using a Finite
Element Model is presented. Commercially
2. OBJECTIVES available ANSYS software package was used
for this. Following BS-EN-1991-1, an impose
The work presented in this paper is load of 2kN/m2 is applied on top of the slab.
primarily aimed towards developing an
earthen slab system using mud-concrete. The maximum (compression) and
Thus, the main objectives of this research are minimum (tension) stresses were identified as
to; 0.065kN/m2 (near the supports) and
• determine an appropriate 0.015kN/m2 (near mid-section), respectively
compression-only shell geometry for (see figure 2). With the distribution of stress
an earthen slab system tensors observed in the results, it was
• develop a construction process and identified that crack formation would begin at
construction of a scaled prototype of the centre plane of the bottom surface of the
the proposed slab system slab system (see figure 3).
• assess the construction cost for the
proposed slab system and compare
with that of a conventional reinforced
concrete slab system

3. SHELL GEOMETRY

The geometry of the compression-only


slab system is as given in Figure 1, where the
Figure 2 Stress distribution of the slab
profile is a barrel vault having a length of 3.0 system when the 2kN/m2 applied on top of
m and a rise of 300 mm, and the minimum the surface
vault thickness of 100 mm is at the apex. This
is following the Catalan vault of same
geometry proposed by (Jayasinghe et al.,
2019)).

Figure 3 Vector representation of stress


distribution

Figure 1 Cross-section of the proposed slab


system

215
8th International Symposium on Advances in Civil and Environmental Engineering
Practices for Sustainable Development (ACEPS – 2021)

5. CONSTRUCTION 5.3. Fixing Supports and Sideboards

For the construction, a 1.0 m width of Bamboo props at a 450mm spacing were
vault section was selected. used to support the formwork. 400 mm heigh
sideboards were fixed and levelled, so the
mixture could be poured to achieve the
5.1. Formwork desired floor level. Thereafter, a thick paste of
grease and oil was applied over the curved
Formwork was designed based on the formwork and sideboards, as a release agent.
deflection of the formwork material and the
deflection under the self-weight of the poured
concrete omit the deformations underside of 5.4. Placement of Tie Rods
the slab. Thus, with the calculation formwork
spacing of 330 mm was chosen. The joists were Two tie rods (6mm in diameter) were
cut into arch profile to get the corrected shape placed to resist the horizontal thrust
of the formwork (see Figure (i)). The top generated. To resist the punching load failure
surface was formed with 5mm thick plywood at the wall-tie connection, a 50 mm x 50 mm x
board (see Figure 4 (ii)). 4 mm angle sections were used, and ties were
fixed to the wall with nuts and bolts as shown
in Figure 6.

(i) (ii)
Figure 4 (i) Skeleton of the formwork and
(ii) completed formwork

5.2. Construction of Wall Segments and Figure 6 Placement of tie rods by


Fixing of Formwork nut and bolt method

Two, 1m heigh wall segments were cast


1m apart. For each wall segment, small duct
pipes were placed near slab level to provide 5.5. Preparation of the Mud-Concrete
Mixture
spacing for the tie rods. Two supporting rods
were used to align the formwork in place
An air-dried soil sample was sieved to
before supporting with props and fixing in
obtain the suitable particle size for the mud-
place (see figure 5).
concrete mixture. The required particle sizes of
the soil for the mud-concrete mix is as follows;
• Gravel: particles pass from 19mm
(3/4”) and retained in 4.75mm (No.4)
sieve
• Sand: particles pass from 4.75mm
(No.4) and retained in 0.425mm
(No.40)
• Fine: particles pass from 0.425mm
(No.40)
The mud-concrete mix design for the
proposed slab system was borrowed from
Arooz (2019). The weight batched mix is as
Figure 5 Formwork placement using follows:
supporting rods on the wall sections • Gravel (extracted from the soil) - 45%
• Sand (extracted from the soil) - 50%

216
8th International Symposium on Advances in Civil and Environmental Engineering
Practices for Sustainable Development (ACEPS – 2021)

• Fine (extracted from the soil) - 5% the mud-concrete mixture was poured into the
• Water - 20% mid-section of the formwork (see Figure 8i)
• Cement - 4% and levelled the surface (see Figure 8ii).
To achieve self-compacting concrete
properties, water content is to be kept at 20%
of the dry mix (Arooz, 2019). Additionally, a 5.7. Curing and Removal of Formwork
water-reducing admixture was added (1% by
weight of cementitious materials) to achieve Wet gunny bags were placed on top of the
adequate workability. finished surface when the surface was
Gravel, sand and cement were first mixed hardened enough. Sideboards were removed
thoroughly with half of the water requirement. after 24 hours and curing was carried out for
Then the remaining water and fine particles 21 days, using wet gunny bags and spraying.
were added, along with the water reducing Figure 9 shows the slab system after 24 hours
admixture. Mixture was thoroughly mixed to of casting.
obtain a consistent fluid mud-concrete.
After curing, the structure was kept dry
for another 7 days. As the initial step in the
5.6. Pouring the Mud-Concrete into the formwork removal process, all the props were
Formwork and Levelling the Surface loosened and formwork was decentered
carefully without applying sudden or
The prepared mud-concrete mixture is asymmetric loads. The completed slab system
then poured on top of the formwork. Initially, and bottom face of the slab system are shown
an equal quantity of mixture was poured at the in Figures 10 and 11, respectively.
near supports, and compacted with a tamping
rod. This is to ensure that the stresses
generated during the construction are at a
minimum (see Figure 7).

Figure 9 Slab system 24 hours after casting


ready to be curing

Figure 7 Mud-concrete mixture poured at


the edge of the structure
Also, the tie rods were sequentially
tightened as the filling continued, increasing
the horizontal thrust. After filling the edges,

Figure 10 Completed singly curved slab


system

(i) (ii)

Figure 8 (i) Mud-concrete mixture poured on


top of the formwork and (ii) final finished Figure 11 The bottom face of the slab system
surface

217
8th International Symposium on Advances in Civil and Environmental Engineering
Practices for Sustainable Development (ACEPS – 2021)

5.8. Prototype Load Testing three different structural forms are, (i)
conventional reinforced concrete slab; (ii)
For easy identification of crack formation, singly-curved earthen slab system; (iii) singly
one side of the vault was painted in white. curved mass concrete slab. Total cost was
loading was gradually applied over the calculated to build the above slab systems for
surface to identify whether it satisfy the design 1m x 1m footprint area. All the rates were
criteria. Cement blocks, each weighing calculated from the Building Schedule of Rates
approximately 13.6kg, were used for loading. (BSR-2019/2020) in accordance with CIDA
Each cement block was carefully placed on the regulations in Sri Lanka. Table 1 shows the
slab surface to cover the whole area and cost comparison of the three slab systems. The
gradually increased the loading by stacking labour cost constitutes that for the
cement blocks in layers. construction as well as the material
preparation: e.g., drying and sieving of soil.
Initial crack was observed after stacking
45 blocks: three layers of cement blocks, each
layer consisting of 15 blocks. This corresponds Table 1 Cost comparison of three different
to a uniformly distributed load of 6.08 kN/m2 slab systems
(see Figures 12i and 12ii). The crack was
observed at the bottom mid-span of the vault, Singly- Singly-
where the thickness is minimum. With the R.C.C. curved curved
loading direction, the crack pattern was slab earthe concrete
identified as a tensile crack. system n slab slab
system system

Amount Amount Amount


(LKR) (LKR) (LKR)

Materials
Filling
6424.97 1646.88 6424.97
material
Reinforceme
3321.74 580.00 580.00
(i) nt
Raw
material
N/A 680.00 N/A
Preparation
& Sieving
Formwork 3024.66 3562.85 3562.85
Labour cost 2064.52 2419.72 1599.52
Total cost
14835.88 8889.45 12167.34
per sq.m
Cost 0% 40% 18%
reduction
(ii)

Figure 12 (i) Initial crack was observed Production and construction stage were
when 45 blocks were placed on top of the considered for embodied energy calculations
slab system (ii) Initial tension crack at the (Gibbons and Orr, 2020)(Udawattha et al.,
mid-section 2016b). 25km and 50km distance to source
were assumed for soil and cement
transportation, respectively, considering local
6. COST COMPARISON conditions. (Fay and Raniga, 2000; Jayasinghe,
2011). These may vary based on where the
For three different slab systems, total cost construction was done: Soil was obtained from
and embodied energy were calculated. The

218
8th International Symposium on Advances in Civil and Environmental Engineering
Practices for Sustainable Development (ACEPS – 2021)

immediate vicinity with no transportation cost 8. FUTURE WORKS


for the prototype build discussed in the paper.
This paper presents work in an ongoing
project on developing an earthen slab system.
Table 2 Embodied energy calculations for The current paper focuses only on the
three different slab systems construction sequence of the singly-curved
earthen slab system using mud-concrete.
Embodied
Further research should need to be conducted
Energy in
MJ to identify the behavior of the proposed slab
system under dynamic loading and with an
R.C.C. slab system actual scale model (3mx3m vault section).
Material Also, with the minimum thickness at apex
Reinforced concrete slab 6570.00 being relaxed, the slab geometry may be
optimized to match the loading requirement.
Formwork material
To prevent disproportionate collapse, the slab
Plywood 1184.28 shall fail before the walls failing due to
Total EE 7754.28 horizontal thrust. Another important aspect to
Singly-curved earthen slab system be studied is the ductility of the proposed slab
Material system, and if the steel tie-rods add any
ductility to the system.
Soil 183.75
Cement 1170.00
Transport 10.00 9. CONCLUSIONS
Formwork material
In conclusion;
Plywood board (15mm) 1777.93
• Mud-concrete would be an
Plywood board (4mm) 26.57
appropriate construction material that
Total EE 3168.24 can be used to develop a compression
Singly-curved concrete slab system only shell slab system.
Material • Nearly 40% of cost reduction and 59%
reduction for embodied energy could
Concrete 1:2:4 3993.60
be expected, compared with
Formwork material conventional reinforced concrete slab
Plywood board (15mm) 1422.84 systems having identical footprint
Plywood board (4mm) 26.57 areas.
Total EE 5443.01 • A maximum tensile stress of
0.015kN/m2 at the bottom face of the
slab system was identified when
7. DISCUSSION 2kN/m2 load was applied over the top
surface.
Around 46% of the total cost of the singly
curved earthen slab system is spent on the
formwork system. Plywood formwork was
considered for the prototype design due to the 10. ACKNOWLEDGEMENT
ease of construction. However, a steel
formwork may be ideal for modular The authors would like to acknowledge
construction, considering reusability. the support given by the technical officer,
Tie rods were used to resist the horizontal Ms. W.B.U. Rukma from the Department of
thrust. With proper arrangement of rooms in a Civil Engineering, University of Moratuwa.
dwelling unit or a building, the requirement of
tie rods can be partially omitted. This is by
way of horizontal thrusts being resisted by
walls buttressing other interior walls.

219
8th International Symposium on Advances in Civil and Environmental Engineering
Practices for Sustainable Development (ACEPS – 2021)

11. REFERENCES López López, D., Domènech Rodríguez, M.,


Palumbo Fernández, M., 2014. “Brick-topia”,
Arooz, F.R., Babilegedara, T.D., Halwatura, the thin-tile vaulted pavilion. Case Stud.
R.U., 2017. Effect of aggregate percentage on Struct. Eng. 2, 33–40.
compressive strength of self-compacting in- https://doi.org/10.1016/j.csse.2014.09.001
situ cast Mud - Concrete load bearing walls.
3rd Int. Moratuwa Eng. Res. Conf. MERCon Maïni, S., 2005. Earthen architecture for
2017 271–276. sustainable habitat compressed stabilised
https://doi.org/10.1109/MERCON.2017.798 earth block technology. High Commission of
0494. Ryadh City Development. The Auroville Earth
Institute, Auroville Building Centre INDIA.
Arooz, R., 2019. In-situ Mud-Concrete as a
material for load-bearing walls and Udawattha, C., Arooz, R., Halwatura, R.,
sustainable building practices. 2016a. New earth walling material: Integrating
modern technology into ancient mud wall, in:
Fay, R., Raniga, U.I., 2000. Life-cycle energy 7th International Conference on Sustainable
analysis of buildings: A case study. Build. Res. Built Environment. Kandy, pp. 24–31.
Inf. 28, 31–41.
https://doi.org/10.1080/096132100369073 Udawattha, C., Arooz, R., Halwatura, R.,
2016b. Manufacturing framework and Cost
Foraboschi, P., Mercanzin, M., Trabucco, D., optimization for Building Mud concrete
2014. Sustainable structural design of tall Blocks (MCB), in: 16th Conference of the
buildings based on embodied energy. Energy Science Council of Asia: Science for the People
Build. 68, 254–269. - Mobilizing Technologies for Sustainable
https://doi.org/10.1016/j.enbuild.2013.09.00 Development in Asia. National Science
3. Foundation of Sri Lanka, Colombo.

Galabada, H., Halwatura, R.U., 2019. A Walker, P., Keable, R., Martin, J., Maniatidis,
preliminary study on the use of soil as a floor V., 2005. Rammed earth: design and
finishing material, in: 2019 From Innovation to construction guidelines. Watford: BRE.
Impact, FITI 2019. Institute of Electrical and
Electronics Engineers Inc.
https://doi.org/10.1109/FITI49428.2019.9037
635.

Gibbons, O.P., Orr, J.J., 2020. How to calculate


Embodied Carbon.

Jayasinghe, C., 2011. Embodied energy of


alternative building materials and their impact
on life cycle cost parameters. Int. Conf. Struct.
Eng. Constr. Manag. December 16-18, 2011,
Kandy, Sri Lanka 1–20.
https://doi.org/10.13140/RG.2.1.4852.2321.

Jayasinghe, R.R., Nanayakkara, K.I.., Arooz,


F.R., Halwatura, R.U., 2019. Catalan Vault
Inspired Earthen Slab System for Houses in Sri
Lanka: Form-Finding.

Löfgren, I., Kutti, T., 2001. In-situ concrete


building-Innovations in Formwork, in: The 1st
International Conference on Innovation in
Architecture Engineering and Construction.

220

View publication stats

You might also like