2016-NOV-30__PH-II_OVERALL PROGRESS DASHBOARD LOGO

DATA DATE 30-Nov-16 Area of Concern Major Activities in Nov-2016


Project Details
Owner
Project
Location
Planned COD

Executive Summary

Progress Summary
S.No Description Plan% Actual% Shortfall%
1 Engineering 95.07% 93.54% -1.53%
2 Procurement 86.50% 83.36% -3.14%
3 Construction 62.30% 59.10% -3.20%
4 Commissioning 0.36% 0.36% 0.00%
Overall 74.58% 71.74% -2.84%

Schedule Performance Index =


(Earned Progress / Planned Progress) 0.96

UNIT #3 UNIT #4
Current Date Current Date
Milestones Dates Milestones Dates
(as per actual BL Variance Critical (as per actual BL Variance in Critical
S.No Milestones (as per Baseline fixed on 31- Major Driving factor Impact on COD S.No Milestones (as per Baseline fixed on Major Driving factor Impact on COD
progress till 31- in Days Indicator progress till 31-Dec- Days Indicator

Boiler Unit #4 Erection Status


Oct-2016) 31-Oct-2016)
Dec-2016) 2016)
1 Drum Lifting Completed Nil Nil Nil 1 Drum Lifting Completed Nil
2 Drainable Hydro Test Completed Nil Nil Nil 2 Drainable Hydro Test Completed Nil
3 Chimney for flue gas flow - Nil No 3 Chimney for flue gas flow 28-Feb-17 -42794 days
4 Turbine ready for box-up - Nil No 4 Turbine ready for box-up 0 days
Switchyard ready for Back Switchyard ready for Back
5 - Nil No 5 0 days
energization energization
6 TG ready for turning gear - Nil No 6 TG ready for turning gear 0 days
7 Intake system ready - Nil No 7 Intake system ready 0 days
8 Air compressor ready - Nil No 8 Air compressor ready 0 days
9 Water Treatment ready - Nil Possibly 9 Water Treatment ready 0 days
10 Fuel oil system ready - Nil No 10 Fuel oil system ready 0 days
11 CW & ACW system ready - Nil Possibly 11 CW & ACW system ready 0 days
12 Cooling tower ready - Nil Possibly 12 Cooling tower ready 0 days

Boiler Unit #3 Erection Status


13 Non drainable hydro test - Nil Yes 13 Non drainable hydro test 0 days
14 Boiler Light-up - Nil Yes 14 Boiler Light-up 0 days
15 Chemical Cleaning - Nil Yes 15 Chemical Cleaning 0 days
16 Outfall system ready - Nil Possibly 16 Outfall system ready 0 days
17 Steam Blowing - Nil Yes 17 Steam Blowing 0 days
18 Coal Handling Plant - Nil Possibly 18 Coal Handling Plant 0 days
19 Ash Handling Plant ready - Nil No 19 Ash Handling Plant ready 0 days
20 Synchronization - Nil Yes 20 Synchronization 0 days
21 Full load test - Nil Yes 21 Full load test 0 days
22 COD - Nil Yes 22 COD 0 days

Civil Construction RCC Qty Status