Anticipated STEPS towards Construction by Zone Enterprise/Zone Developer

Sr.
Activity Responsibility TimeLine Status
No.

Pre-Construction Activities

Issuance of Provisional Allotment Letter by Islamabad Technopolis after


1 STZ Authority
grant of license by approval committee.

Issuance of site plan and approximate demarcation of plot for soil


2 STZA
investigation and Topographic survey by the ZE/ZD.

3 Preliminary EIA report by Environment department. ZE/ZD

4 Design of the building(s) from PEC registered consultant/Architect. ZE/ZD

Detailed Architectural Drawings including external façade, Structural


Drawings, MEP drawings in AUTO CAD format and hard copy along with
geo technical investigation of the plot area; design calculations (Frame
Analysis and design) of all structural members in structural design
5 software’s such as ETABS, SAFE, SAP2000-v12 etc. or manual ZE/ZD
calculations should be from PEC registered consultant/architect;
the architectural firm shall issue a stability certificate that the design is as
per the international standards and the structure will be stable. All will be
at the end of ZE/ZD.

Submission of detailed design stamped and signed by registered


Architect with PCATP (Pakistan Council of Architects and Town Planners)
6 ZE/ZD
and registered engineer with PEC (Pakistan Engineering Council),
registered consulting firm with PCATP and PEC to CDA.

After CDA approval, possession of the site to be given by Islamabad


7 STZ Authority
Technopolis.

NOC by Islamabad Technopolis for construction and for temporary


8 connection of electricity (25 KVa); this connection will be for construction STZ Authority
purposes only.

Construction of the building(s) by the ZE/ZD from PEC enlisted


9 Contractor
contractors.

Construction supervision to be arranged by the ZE/ZD which would be


10 preferably from the designer or any other PEC registered Consultant
consultant/engineer

11 NOC from environment department. EPA

Post - Construction Activities

1 Mobilization ZE/ZD

2 Earth work / Excavation ZE/ZD

3 Construction of Substructure ZE/ZD

4 Construction of Superstructure ZE/ZD

5 Brick Work ZE/ZD

6 Water supply Sanitary and Sewerage / Drainage Works ZE/ZD

7 Plaster ZE/ZD

8 Flooring and Ceiling ZE/ZD

9 Electrificaiton and HVAC System ZE/ZD

10 Paint, Finishing and Allied works ZE/ZD

11 Testing and Commissioning ZE/ZD

Building completion certificate by CDA and stability certificate to be issued


12 by the supervisory consultant/Architect and its submission to Islamabad STZ Authority
Technopolis.

NOC by Islamabad Technopolis for permanent connection of electricity


(this connection will be as per the need of the Zone Enterprise/Zone
13 Developer, water supply for drinking purposes (provision of underground ZE/ZD
water tank is necessary for water supply connection) and sewerage
connections.