Catch Up Plan For Dismantling Tem Bridge CG

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

Catch up Plan 8 9 10 11 12

14th/Aug/2022 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12

STEP Work Item / Hạng mục công việc Unit Q'ty Day 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120

E) Tempoarary bridge
1 Tempoarary bridge 4A 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29

1 T1- T5 Tempoarary remove deck slab pcs 0.5


Op2 Op Content Original New Day %
2 Install add H350 + spacer 10cm Set 8 2.0
Overtime 4hours for Extruction Work
3 Re-Install deckslab pcs 1.0
-20days (60days => 40days) 1 Parallel Work by 15t Boom Truck 17 0 -17 -15%
4 Extract steel sheet pile at abutment A1 pcs 57 2.5
5 Remove Concrete Block A1 pcs 0.5
2 Overtime 4H for Extruction Work 60 40 -20 -17%
6 Cutting mainbeam 1.5m of span T1-T2 pcs 5 0.5 Op3
7 Remove cross beam H400 and cut bracing at T1 Set 1 0.5 Overtime 4hours for Minor Work 3 Overtime 4H for Minor Work 24 16 -8 -7%
8 Extract H-pile, L=42m at T1 Set 5 2.0 -8days (24days => 16days)
9 T5- T7 Tempoarary remove deck slab pcs 0.5 4 Parallel Work P2 PH 8 0 -8 -7%
10 Install add H350 + spacer 10cm (From T1-T3) Set 4 1.0
5 Parallel Work A5 by Barge 13 0 -13 -11%
11 Re-Install deckslab pcs 0.5
12 Remove mainbeam of span T1-T3 pcs 5 0.5
Total 122 56 -66 -57%
13 Remove cross beam H400 and cut bracing pile T2 Set 1 0.5
14 Extract H-pile, L=42m at T2 Set 5 2.0
15 Cutting mainbeam 1.5m of span T3-T4 pcs 5 0.5
Other Point
16 Remove cross beam H400 and cut bracing pile T3 Set 1 0.5
_ NTH clean SSP, H-Piles (High pressure water pump)
17 Extract H-pile, L=42m at T3 Set 5 2.0
_ 499 material is [SSP & Deck slab of 4A,5A] and [3pcs Deck Slab of 6A]
18 Remove mainbeam of span T3-T4 pcs 5 0.5
_ Remove 7A, 80t Crane not stand on Bridge
19 Remove cross beam H400 and cut bracing pile T4 Set 1 0.5
_ Check Piles capacity of P7 Bridge
20 Extract H-pile, L=42m at T4 Set 5 2.0
_ Remain some concrete block
21 Cutting mainbeam 1.5m of span T5-T6 pcs 5 0.5
_ Finishing work for Permanent Structure by Crawler Crane?
22 Remove cross beam H400 and cut bracing of pile T5 Set 1 0.5
_ Calculation for 7A
23 Extract H-pile, L=42m at T5 Set 5 2.0
24 Remove mainbeam of span T5-T7 pcs 5 0.5
25 Remove cross beam H400 and cut bracing pile T6 Set 1 0.5
26 Extract H-pile, L=42m at T6 Set 5 2.0
27 Remove steel sheet pile at abutment A2 pcs 57 2.5
28 Remove cross beam H400 and cut bracing of pile T7 Set 1 0.5
29 Extract H-pile, L=42m + SSP 18m at T7 Set 5 2.0
30 Remove Concrete Block A2 pcs 0.5
31 Transportation H beam to Wharf A or SSP to 499 yard
2 Tempoarary bridge 5A 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

1 T1- T3 Tempoarary remove deck slab pcs 0.5


2 Install add H350 + spacer 10cm Set 4 1.0 Option1 Option1
3 Re-Install deckslab pcs 0.5 Parallel work by 15t Boom Check thickness by UT
4 T3- T5 Tempoarary remove deck slab pcs 0.5 Truck
5 Install add H350 + spacer 10cm Set 4 1.0
6 Re-Install deckslab pcs 0.5
7 Remove steel sheet pile at abutment A1 pcs 32 2.0
8 Cutting mainbeam 1.5m of span T1-T2 pcs 5 0.5
9 Remove cross beam H400 and cut bracing of pile T1 Set 1 0.5
10 Extract H-pile, L=42m at T1 Set 5 2.0
11 Remove mainbeam of span T1-T3 pcs 5 0.5 Option5
12 Remove cross beam H400 & cut bracing of pile T2 Set 1 0.5 Parallel work 5A by Barge
13 Extract H-pile, L=42m at T2 Set 5 2.0 -13days (Except Op1,2)
14 Cutting mainbeam 1.5m at T3 pcs 5 0.5
15 Remove cross beam H400 and cut bracing pile T3 Set 1 0.5
16 Extract H-pile, L=42m at T3 Set 5 2.0
17 Remove mainbeam of span T3-T4 pcs 5 0.5
18 Remove cross beam H400 and cut bracing pile T4 Set 1 0.5
19 Extract H-pile, L=42m at T4 Set 5 2.0
20 Remove steel sheet pile at abutment A2 pcs 58 2.0
21 Remove cross beam H400 and cut bracing pile T5 Set 1 1.0
22 Extract H-pile, L=42m at T5 Set 5 2.0
23 Transportation H beam to Wharf A or SSP to 499 yard
3 Tempoarary bridge 6A 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

1 T1- T3 Tempoarary remove deck slab pcs 0.5


2 Install add H350 + spacer 10cm Set 4 1.0
3 Re-Install deckslab pcs 0.5
4 T3- T5 Tempoarary remove deck slab pcs 0.5
5 Install add H350 + spacer 10cm Set 4 1.0
6 Re-Install deckslab pcs 0.5
7 Remove steel sheet pile at abutment A1 pcs 28 2.0
8 Cutting mainbeam 1.5m of span T1-T2 pcs 5 0.5
9 Remove cross beam H400 and cut bracing pile T1 Set 1 0.5
10 Extract H-pile, L=42m at T1 Set 5 2.0
11 Remove mainbeam of span T1-T3 pcs 5 0.5
12 Remove cross beam H400 and cut bracing pile T2 Set 1 0.5
13 Extract H-pile, L=42m at T2 Set 5 2.0
14 Cutting mainbeam 1.5m at T3 pcs 5 0.5
15 Remove cross beam H400 and cut bracing pile T3 Set 1 0.5
16 Extract H-pile, L=42m at T3 Set 5 2.0
17 Remove mainbeam of span T3-T4 pcs 5 0.5
18 Remove cross beam H400 and cut bracing of pile at T4 Set 1 0.5
19 Extract H-pile, L=42m at T4 pcs 56 2.0
20 Remove steel sheet pile at abutment A2 Set 5 2.0
21 Remove cross beam H400 and cut bracing pile T5 Set 1 1.0
22 Extract H-pile, L=42m at T5 Set 5 2.0
23 Transportation Deck Slab 3pcs to 499 yard, other to Wharf A
4 Tempoarary bridge 7A 1 2 3 4 5 6 7
1 T1- T2 Tempoarary remove deck slab pcs 0.5
2 Replace Beam System Set 5 6.0
3 Re-Install deckslab pcs 0.5
4 Remove deckslab from T1-T2 pcs 0.5
5 Remove concrete block at abutment A1 pcs 0.5
6 Remove mainbeam of span T1-T2 (Remove C Beam) pcs 6 0.5
7 Removecross beam H400 and cutting bracing of pile at T1 Set 1 0.5
8 Extract H-pile, L=42m at T1 Set 6 2.0
9 Remove concrete block at abutment A2 pcs 0.5
10 Remove cross beam H400 and cutting bracing of pile at T2 Set 1 0.5
11 Extract H-pile, L=42m at T2 Set 6 2.0
12 Transportation to Wharf A
5 E) Passenger Hoist P2
1 Remove H-Beam H350 and Counterweight concrete 1.0
2 Remove segment of rail frame 1.3 Option4
3 Remove tie-in bracket 0.3 Parallel work by JO Crawler Crane
4 Remove electric system and Cabin 1.0 -8days
5 Remove base steel plate 0.3
6 Chipping concrete FDN and levelling 0.3
6 G) Other facilities on land
1 Transport pan'nt mat'l office P5 to wharf A Ton 130 2.0
2 Sub JO office P5 m3 7 2.0
7 Tempoarary bridge P7-P8 1 2 3 4 5 6 7 8 9 10 11 12 13

1 T1- T3 Tempoarary remove deck slab pcs 0.5


2 Install add H350 + spacer 10cm Set 4 1.0
3 Re-Install deckslab pcs 0.5
4 Remove steel sheet pile at abutment A1 pcs 44 2.0
5 Remove concrete block at abutment A1 pcs 0.5
6 Cutting mainbeam 1.5m of span T1-T2 pcs 5 0.5
7 Remove cross beam H400 and cutting bracing of pile at T1 set 1 0.5
8 Extract H-pile, L=48m at T1 Set 3 1.5
9 Remove mainbeam of span T1-T3 pcs 5 0.5
10 Remove cross beam H400 and cutting bracing of pile at T2 set 1 0.5
11 Extract H-pile, L=48m at T2 Set 3 1.5
12 Remove steel sheet pile at abutment A2 pcs 38 2.0
13 Remove concrete block at abutment A2 pcs 0.5
14 Remove cross beam H400 and cutting bracing of pile at T3 set 1 0.5
15 Extract H-pile, L=48m at T3 Set 3 1.5
16 Transportation to Wharf A