Improvement Team Regristration & Project Charter

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 4

CF-TQM-04 / 01

Date: 20 Junio 2022


HAYCO GROUP
IMPROVEMENT TEAM REGRISTRATION & PROJECT CHARTER
Project Team
PROJECT KPI (关键绩效指标 (可以为一个以上) :
PROJECT TITLE :
SGA-OPEX42 Proyecto de Reduccion de Headcount y reconfiguracion
Productivity, efficiency, security, espacio, STd Time.
de Empaque en la linea de Botella

TEAM NAME (OPTIONAL) ):

TEAM BASICS PROJECT ANALYSIS MEETINGS


FINANCIAL
Name DEPT. PROJECT SELECTION
IMPACT
LEADER Christopher del Rosario ME MEETING
Maycky PD FREQUENCY Two time by week
Jose Japa ME
Gabriel Alemany ME

MEMBERS Sally POSSIBLE CHALLENGES


Robin Jimenez OpEx Wenesday and
MEETING
Friday
TIME 11:00 am to 11:30
am

PROCESS OWNER PROJECT SPONSOR

SIGNATURE:Janny Bernabel SIGNATURE :Tania Mateo


PROGRESS CHARTER
2021
IMPROVEMENT STEPS Month June July Aug.

Week No 24 25 26 27 28 29 30 31 32 33 34

1. Map The current Situation & MeasurableTarget. Plan


P1,P2
研究当前形势并提出可行性目标 Actual
2. Root Cause Analysis Plan
P3
根本原因分析 Actual
3. Develop Solution Plan
P4
提出解决方案 Actual
4. Plan Implemention Of Selected Solutions Plan
D1
即选方案计划执行 Actual
5. Implement Solutions With Measurable Results Plan
D2
执行方案与可测性结果分析 Actual
6. Check and Standardise Actions Plan
C/A
检查和规范行动 Actual
CF-TQM-04 / 01

LEADER SIGNATURE LAST UPDATE Week 29


上次回顾时间
CF-TQM-04 / 01

e: 20 Junio 2022

Project Team

FINANCIAL
IMPACT