Online Feedback Management System - Bijan Shrestha (20BCE2904) Page 1

Jul, 11 '22
Task Name Duration Planned Start Date Planned Finish Date Linked From M

1 Brainstorming 2 days 20/07/2022 21/07/2022 Brainstorming

2 Topic Selection 1 day 20/07/2022 20/07/2022 Topic Selection

3 Problem Statement 1 day 21/07/2022 21/07/2022 Problem Statement

4 Requirement Gathering 8 days 22/07/2022 2/08/2022


5 Functional Requirement 3 days 22/07/2022 26/07/2022 1 Function

6 Non functional Requirement 2 days 27/07/2022 28/07/2022 5 No

7 Hardware and Software Requiremnt 3 days 29/07/2022 2/08/2022 6


8 Analysis 9 days 3/08/2022 15/08/2022
9 Discussion 1 day 3/08/2022 3/08/2022 4
10 Literature Survey 8 days 4/08/2022 15/08/2022 9
11 Design 3 days 16/08/2022 18/08/2022
12 Homepage 3 days 16/08/2022 18/08/2022 8
13 About page 2 days 16/08/2022 17/08/2022
14 Database Design 21 days 16/08/2022 13/09/2022
15 Registration Page 10 days 16/08/2022 29/08/2022
16 Login Page 5 days 30/08/2022 5/09/2022 15
17 HOD page 3 days 6/09/2022 8/09/2022 16
18 Faculty Page 2 days 9/09/2022 12/09/2022 17, 16
19 Student Page 3 days 9/09/2022 13/09/2022 17, 16
20 Contact page 2 days 9/09/2022 12/09/2022 17
21 Testing 18 days 13/09/2022 6/10/2022
22 Unit Testing 12 days 13/09/2022 28/09/2022
23 Integration Testing 9 days 13/09/2022 23/09/2022
24 Functional Testing 6 days 13/09/2022 20/09/2022
25 Manual Testing 6 days 29/09/2022 6/10/2022
26 Maintainance 12 days 7/10/2022 24/10/2022
27 Maintaining Testing 12 days 7/10/2022 24/10/2022
28 Documentation 11 days 25/10/2022 8/11/2022
29 Site Installation 4 days 25/10/2022 28/10/2022 26
30 Prototype Feedback 4 days 31/10/2022 3/11/2022 29
31 Backtracking and Report 3 days 4/11/2022 8/11/2022 30