PRECOMMISSIONING TARGET DATES

Punch Clearance & Stabilization &


PDB HVAC / ACS / PCS UPS FACP F&G & HSSD RTU (With F&G) METERING SYSTEM RTU (With Metering) SMC MC Walkdown Bypass & Tie-in Gas-In Test Run & Acceptance BISEP Demolition Final Punch Closure Asbuilt PAC
Obtain RFC Ready for Test Run
CRS Start Finish Start Finish Start Finish Start Finish Start Finish Start Finish Start Finish Start Finish Start Finish Start Finish Start Finish Start Finish Start Finish Start Finish Start Finish Start Finish Start Finish Start Finish Start Finish Finish
813 - - - - - - - - - - - - - - - - - - 28-Dec-21 29-Dec-21 30-Dec-21 5-Jan-22 6-Jan-22 12-Jan-22 13-Jan-22 13-Jan-22 15-Jan-22 17-Jan-22 18-Jan-22 24-Jan-22 25-Jan-22 30-Jan-22 31-Jan-22 8-Feb-22 9-Feb-22 15-Feb-22 16-Feb-22 24-Feb-22 24-Feb-22
520 - - - - - - - - - - - - - - - - - - 5-Jan-22 6-Jan-22 8-Jan-22 12-Jan-22 13-Jan-22 19-Jan-22 20-Jan-22 20-Jan-22 22-Jan-22 24-Jan-22 25-Jan-22 27-Jan-22 29-Jan-22 5-Feb-22 6-Feb-22 13-Feb-22 14-Feb-22 19-Feb-22 20-Feb-22 28-Feb-22 28-Feb-22
402 - - - - - - - - - - - - - - - - - - 15-Dec-21 16-Dec-21 18-Dec-21 23-Dec-21 25-Dec-21 30-Dec-21 1-Jan-22 1-Jan-22 2-Jan-22 4-Jan-22 5-Jan-22 8-Jan-22 9-Jan-22 9-Jan-22 10-Jan-22 18-Jan-22 19-Jan-22 25-Jan-22 26-Jan-22 3-Feb-22 3-Feb-22
812 - - - - - - 14-Dec-21 15-Dec-21 16-Dec-21 18-Dec-21 16-Dec-21 18-Dec-21 11-Dec-21 18-Dec-21 16-Dec-21 16-Dec-21 16-Dec-21 16-Dec-21 3-Jan-22 4-Jan-22 5-Jan-22 11-Jan-22 12-Jan-22 18-Jan-22 19-Jan-22 19-Jan-22 20-Jan-22 23-Jan-22 24-Jan-22 26-Jan-22 27-Jan-22 1-Feb-22 2-Feb-22 10-Feb-22 12-Feb-22 17-Feb-22 19-Feb-22 27-Feb-22 27-Feb-22
704 - - 19-Dec-21 26-Dec-21 23-Dec-21 28-Dec-21 22-Dec-21 29-Dec-21 26-Dec-21 30-Dec-21 30-Dec-21 30-Dec-21 29-Dec-21 17-Jan-22 13-Jan-22 16-Jan-22 16-Jan-22 16-Jan-22 18-Jan-22 19-Jan-22 20-Jan-22 26-Jan-22 27-Jan-22 2-Feb-22 3-Feb-22 3-Feb-22 5-Feb-22 7-Feb-22 8-Feb-22 17-Feb-22 19-Feb-22 5-Mar-22 6-Mar-22 14-Mar-22 15-Mar-22 21-Mar-22 22-Mar-22 30-Mar-22 30-Mar-22
708 26-Dec-21 2-Jan-22 27-Dec-21 4-Jan-22 29-Dec-21 3-Jan-22 30-Dec-21 5-Jan-22 2-Jan-22 6-Jan-22 6-Jan-22 6-Jan-22 4-Jan-22 17-Jan-22 13-Jan-22 16-Jan-22 16-Jan-22 16-Jan-22 18-Jan-22 19-Jan-22 20-Jan-22 26-Jan-22 27-Jan-22 2-Feb-22 3-Feb-22 3-Feb-22 5-Feb-22 7-Feb-22 8-Feb-22 14-Feb-22 15-Feb-22 17-Feb-22 19-Feb-22 27-Feb-22 28-Feb-22 6-Mar-22 7-Mar-22 15-Mar-22 15-Mar-22
505 3-Jan-22 9-Jan-22 - - - - 6-Jan-22 11-Jan-22 9-Jan-22 13-Jan-22 13-Jan-22 13-Jan-22 18-Jan-22 29-Jan-22 27-Jan-22 27-Jan-22 27-Jan-22 27-Jan-22 30-Jan-22 31-Jan-22 1-Feb-22 6-Feb-22 7-Feb-22 13-Feb-22 14-Feb-22 14-Feb-22 15-Feb-22 17-Feb-22 19-Feb-22 21-Feb-22 22-Feb-22 24-Feb-22 26-Feb-22 3-Mar-22 5-Mar-22 9-Mar-22 10-Mar-22 19-Mar-22 19-Mar-22
710 - - - - - - - - - - - - 18-Jan-22 25-Jan-22 24-Jan-22 24-Jan-22 - - 26-Jan-22 27-Jan-22 29-Jan-22 3-Feb-22 5-Feb-22 10-Feb-22 12-Feb-22 12-Feb-22 13-Feb-22 15-Feb-22 16-Feb-22 19-Feb-22 20-Feb-22 20-Feb-22 21-Feb-22 1-Mar-22 2-Mar-22 8-Mar-22 9-Mar-22 17-Mar-22 17-Mar-22
403/1440 3-Jan-22 5-Jan-22 5-Jan-22 12-Jan-22 6-Jan-22 11-Jan-22 13-Jan-22 18-Jan-22 16-Jan-22 20-Jan-22 20-Jan-22 20-Jan-22 26-Jan-22 8-Feb-22 6-Feb-22 7-Feb-22 7-Feb-22 7-Feb-22 9-Feb-22 10-Feb-22 12-Feb-22 17-Feb-22 19-Feb-22 24-Feb-22 26-Feb-22 26-Feb-22 27-Feb-22 1-Mar-22 2-Mar-22 8-Mar-22 9-Mar-22 9-Mar-22 10-Mar-22 19-Mar-22 20-Mar-22 26-Mar-22 27-Mar-22 4-Apr-22 4-Apr-22
1470 6-Jan-22 9-Jan-22 13-Jan-22 20-Jan-22 13-Jan-22 13-Jan-22 20-Jan-22 25-Jan-22 23-Jan-22 27-Jan-22 27-Jan-22 27-Jan-22 9-Feb-22 19-Feb-22 17-Feb-22 17-Feb-22 17-Feb-22 17-Feb-22 20-Feb-22 21-Feb-22 22-Feb-22 28-Feb-22 1-Mar-22 7-Mar-22 8-Mar-22 8-Mar-22 9-Mar-22 12-Mar-22 13-Mar-22 15-Mar-22 16-Mar-22 21-Mar-22 22-Mar-22 30-Mar-22 31-Mar-22 6-Apr-22 7-Apr-22 14-Apr-22 14-Apr-22
701/702/709 10-Jan-22 16-Jan-22 22-Jan-22 29-Jan-22 16-Jan-22 19-Jan-22 27-Jan-22 1-Feb-22 30-Jan-22 3-Feb-22 3-Feb-22 3-Feb-22 30-Jan-22 16-Feb-22 14-Feb-22 15-Feb-22 15-Feb-22 15-Feb-22 17-Feb-22 19-Feb-22 20-Feb-22 22-Feb-22 23-Feb-22 26-Feb-22 27-Feb-22 27-Feb-22 28-Feb-22 2-Mar-22 3-Mar-22 16-Mar-22 17-Mar-22 29-Mar-22 30-Mar-22 3-Apr-22 4-Apr-22 9-Apr-22 10-Apr-22 14-Apr-22 14-Apr-22
557 17-Jan-22 23-Jan-22 - - - - - - 6-Feb-22 10-Feb-22 10-Feb-22 10-Feb-22 20-Feb-22 3-Mar-22 2-Mar-22 2-Mar-22 2-Mar-22 2-Mar-22 5-Mar-22 6-Mar-22 7-Mar-22 10-Mar-22 12-Mar-22 16-Mar-22 17-Mar-22 17-Mar-22 19-Mar-22 21-Mar-22 22-Mar-22 24-Mar-22 26-Mar-22 30-Mar-22 31-Mar-22 4-Apr-22 5-Apr-22 9-Apr-22 10-Apr-22 14-Apr-22 14-Apr-22

OEM / VENDOR MOBILIZATION DATES

DISCIPLINE VENDOR CRS-812 CRS-704 CRS-708 CRS-710


PDB
HVAC TSSC Completed 12-Dec-21 13-Dec-21 14-Dec-21 15-Dec-21 16-Dec-21 18-Dec-21 19-Dec-21 20-Dec-21 21-Dec-21 22-Dec-21 23-Dec-21 25-Dec-21 26-Dec-21 27-Dec-21
UPS Gutor Completed 19-Dec-21 20-Dec-21 26-Dec-21 27-Dec-21
FACP Rockwell 14-Dec-21 15-Dec-21 22-Dec-21 26-Dec-21 27-Dec-21 29-Dec-21 3-Jan-22 4-Jan-22
F&G & HSSD Tyco & Honeywell 16-Dec-21 18-Dec-21 23-Dec-21 27-Dec-21 28-Dec-21 30-Dec-21 4-Jan-22 5-Jan-22
F&G & HSSD Honeywell + Tyco
F&G & HSSD Rockwell + Tyco
F&G & HSSD ABB + Tyco
RTU (With F&G) Schneider (Aveva) 16-Dec-21 18-Dec-21 28-Dec-21 5-Jan-22
Metering System Honeywell 13-Dec-21 14-Dec-21 15-Dec-21 16-Dec-21 26-Dec-21 27-Dec-21 28-Dec-21 29-Dec-21 30-Dec-21 2-Jan-22 3-Jan-22 4-Jan-22 5-Jan-22 6-Jan-22 9-Jan-22 10-Jan-22 11-Jan-22 12-Jan-22 26-Dec-21 27-Dec-21 28-Dec-21 29-Dec-21 30-Dec-21 2-Jan-22 3-Jan-22 4-Jan-22 5-Jan-22 6-Jan-22 8-Jan-22 9-Jan-22 10-Jan-22 11-Jan-22 12-Jan-22 13-Jan-22
RTU (With Metering) Schneider (Aveva) 16-Dec-21 10-Jan-22 11-Jan-22 4-Jan-22 5-Jan-22 12-Jan-22
SMC Schneider (Aveva) 16-Dec-21 11-Jan-22 5-Jan-22 12-Jan-22

DISCIPLINE VENDOR CRS-505 CRS-403/1440 CRS-1470


PDB
HVAC TSSC 28-Dec-21 29-Dec-21 30-Dec-21 2-Jan-22 3-Jan-22 4-Jan-22 5-Jan-22 6-Jan-22 8-Jan-22 9-Jan-22 10-Jan-22 11-Jan-22 12-Jan-22 13-Jan-22 15-Jan-22 16-Jan-22 17-Jan-22 18-Jan-22 19-Jan-22 20-Jan-22 22-Jan-22
UPS Gutor - - - - - - - - - 12-Jan-22 13-Jan-22 17-Jan-22 18-Jan-22
FACP Rockwell 6-Jan-22 10-Jan-22 11-Jan-22 13-Jan-22 17-Jan-22 18-Jan-22 20-Jan-22 24-Jan-22 25-Jan-22
F&G & HSSD Tyco & Honeywell 9-Jan-22 12-Jan-22 13-Jan-22
F&G & HSSD Honeywell + Tyco 16-Jan-22 19-Jan-22 20-Jan-22
F&G & HSSD Rockwell + Tyco 23-Jan-22 26-Jan-22 27-Jan-22
F&G & HSSD ABB + Tyco
RTU (With F&G) Schneider (Aveva) 13-Jan-22 20-Jan-22 27-Jan-22
Metering System Honeywell 13-Jan-22 14-Jan-22 16-Jan-22 17-Jan-22 18-Jan-22 19-Jan-22 20-Jan-22 23-Jan-22 24-Jan-22 15-Jan-22 16-Jan-22 17-Jan-22 18-Jan-22 19-Jan-22 20-Jan-22 23-Jan-22 24-Jan-22 25-Jan-22 26-Jan-22 27-Jan-22 29-Jan-22 30-Jan-22 31-Jan-22 1-Feb-22 2-Feb-22 3-Feb-22 6-Feb-22 7-Feb-22 8-Feb-22
RTU (With Metering) Schneider (Aveva) 23-Jan-22 25-Jan-22 26-Jan-22 7-Feb-22
SMC Schneider (Aveva) 23-Jan-22 26-Jan-22 7-Feb-22

DISCIPLINE VENDOR CRS-701/702/709 CRS-557


PDB
HVAC TSSC 23-Jan-22 24-Jan-22 25-Jan-22 26-Jan-22 27-Jan-22 29-Jan-22 30-Jan-22 - - - - - - -
UPS Gutor 30-Jan-22 31-Jan-22 - - - - - - -
FACP Rockwell 27-Jan-22 31-Jan-22 1-Feb-22 3-Feb-22 7-Feb-22 8-Feb-22
F&G & HSSD Tyco & Honeywell 30-Jan-22 2-Feb-22 3-Feb-22
F&G & HSSD Honeywell + Tyco
F&G & HSSD Rockwell + Tyco
F&G & HSSD ABB + Tyco 6-Feb-22 9-Feb-22 10-Feb-22
RTU (With F&G) Schneider (Aveva) 3-Feb-22 10-Feb-22
Metering System Honeywell 29-Jan-22 30-Jan-22 31-Jan-22 1-Feb-22 2-Feb-22 3-Feb-22 6-Feb-22 7-Feb-22 8-Feb-22 9-Feb-22 10-Feb-22 13-Feb-22 14-Feb-22 15-Feb-22 16-Feb-22 9-Feb-22 10-Feb-22 12-Feb-22 13-Feb-22 14-Feb-22 15-Feb-22 16-Feb-22 17-Feb-22 20-Feb-22 21-Feb-22
RTU (With Metering) Schneider (Aveva) 14-Feb-22 15-Feb-22 20-Feb-22
SMC Schneider (Aveva) 15-Feb-22 20-Feb-22

DISCIPLINE VENDOR OEM DAYS


PDB 0
HVAC TSSC 42
UPS Gutor 10
FACP Rockwell 23
F&G & HSSD Tyco & Honeywell 14
F&G & HSSD Honeywell + Tyco 3 403/1440
F&G & HSSD Rockwell + Tyco 3 1470
F&G & HSSD ABB + Tyco 3 557
RTU (With F&G) Schneider (Aveva) 9
Metering System Honeywell 88
RTU (With Metering) Schneider (Aveva) 13
SMC Schneider (Aveva) 9
E&I VENDOR MOBILIZATION SCHEDULE

DISCIPLINE VENDOR CRS-812 CRS-704 CRS-708 CRS-710


HVAC TSSC Completed 12-Dec-21 13-Dec-21 14-Dec-21 15-Dec-21 16-Dec-21 18-Dec-21 19-Dec-21 20-Dec-21 21-Dec-21 22-Dec-21 23-Dec-21 25-Dec-21 26-Dec-21 27-Dec-21
UPS Gutor Completed 19-Dec-21 20-Dec-21 26-Dec-21 27-Dec-21
FACP Rockwell 14-Dec-21 15-Dec-21 22-Dec-21 26-Dec-21 27-Dec-21 29-Dec-21 3-Jan-22 4-Jan-22
F&G & HSSD Tyco & Honeywell 16-Dec-21 18-Dec-21 23-Dec-21 27-Dec-21 28-Dec-21 30-Dec-21 4-Jan-22 5-Jan-22
RTU (With F&G) Schneider (Aveva) 16-Dec-21 18-Dec-21 28-Dec-21 5-Jan-22
Metering System Honeywell 13-Dec-21 14-Dec-21 15-Dec-21 16-Dec-21 26-Dec-21 27-Dec-21 28-Dec-21 29-Dec-21 30-Dec-21 2-Jan-22 3-Jan-22 4-Jan-22 5-Jan-22 6-Jan-22 9-Jan-22 10-Jan-22 11-Jan-22 12-Jan-22 26-Dec-21 27-Dec-21 28-Dec-21 29-Dec-21 30-Dec-21 2-Jan-22 3-Jan-22 4-Jan-22 5-Jan-22 6-Jan-22 8-Jan-22 9-Jan-22 10-Jan-22 11-Jan-22 12-Jan-22 13-Jan-22
RTU (With Metering) Schneider (Aveva) 16-Dec-21 10-Jan-22 11-Jan-22 4-Jan-22 5-Jan-22 12-Jan-22
SMC Schneider (Aveva) 16-Dec-21 11-Jan-22 5-Jan-22 12-Jan-22

DISCIPLINE VENDOR CRS-505 CRS-403/1440 CRS-1470


HVAC TSSC 28-Dec-21 29-Dec-21 30-Dec-21 2-Jan-22 3-Jan-22 4-Jan-22 5-Jan-22 6-Jan-22 8-Jan-22 9-Jan-22 10-Jan-22 11-Jan-22 12-Jan-22 13-Jan-22 15-Jan-22 16-Jan-22 17-Jan-22 18-Jan-22 19-Jan-22 20-Jan-22 22-Jan-22
UPS Gutor - - - - - - - - - 12-Jan-22 13-Jan-22 17-Jan-22 18-Jan-22
FACP Rockwell 6-Jan-22 10-Jan-22 11-Jan-22 13-Jan-22 17-Jan-22 18-Jan-22 20-Jan-22 24-Jan-22 25-Jan-22
F&G & HSSD Tyco & Honeywell 9-Jan-22 12-Jan-22 13-Jan-22 16-Jan-22 19-Jan-22 20-Jan-22 23-Jan-22 26-Jan-22 27-Jan-22
RTU (With F&G) Schneider (Aveva) 13-Jan-22 20-Jan-22 27-Jan-22
Metering System Honeywell 13-Jan-22 14-Jan-22 16-Jan-22 17-Jan-22 18-Jan-22 19-Jan-22 20-Jan-22 23-Jan-22 24-Jan-22 15-Jan-22 16-Jan-22 17-Jan-22 18-Jan-22 19-Jan-22 20-Jan-22 23-Jan-22 24-Jan-22 25-Jan-22 26-Jan-22 27-Jan-22 29-Jan-22 30-Jan-22 31-Jan-22 1-Feb-22 2-Feb-22 3-Feb-22 6-Feb-22 7-Feb-22 8-Feb-22
RTU (With Metering) Schneider (Aveva) 23-Jan-22 25-Jan-22 26-Jan-22 7-Feb-22
SMC Schneider (Aveva) 23-Jan-22 26-Jan-22 7-Feb-22

DISCIPLINE VENDOR CRS-701/702/709 CRS-557


HVAC TSSC 23-Jan-22 24-Jan-22 25-Jan-22 26-Jan-22 27-Jan-22 29-Jan-22 30-Jan-22 - - - - - - -
UPS Gutor 30-Jan-22 31-Jan-22 - - - - - - -
FACP Rockwell 27-Jan-22 31-Jan-22 1-Feb-22 3-Feb-22 7-Feb-22 8-Feb-22
F&G & HSSD Tyco & Honeywell 30-Jan-22 2-Feb-22 3-Feb-22 6-Feb-22 9-Feb-22 10-Feb-22
RTU (With F&G) Schneider (Aveva) 3-Feb-22 10-Feb-22
Metering System Honeywell 29-Jan-22 30-Jan-22 31-Jan-22 1-Feb-22 2-Feb-22 3-Feb-22 6-Feb-22 7-Feb-22 8-Feb-22 9-Feb-22 10-Feb-22 13-Feb-22 14-Feb-22 15-Feb-22 16-Feb-22 9-Feb-22 10-Feb-22 12-Feb-22 13-Feb-22 14-Feb-22 15-Feb-22 16-Feb-22 17-Feb-22 20-Feb-22 21-Feb-22
RTU (With Metering) Schneider (Aveva) 14-Feb-22 15-Feb-22 20-Feb-22
SMC Schneider (Aveva) 15-Feb-22 20-Feb-22

DISCIPLINE VENDOR OEM DAYS


HVAC TSSC 42
UPS Gutor 10
FACP Rockwell 23
F&G & HSSD Tyco & Honeywell 23
RTU (With F&G) Schneider (Aveva) 9
Metering System Honeywell 88
RTU (With Metering) Schneider (Aveva) 13
SMC Schneider (Aveva) 9
PRECOMMISSIONING TARGET DATES
PDB HVAC / ACS / PCS UPS FACP F&G & HSSD RTU (With F&G) METERING SYSTEM RTU (With Metering) SMC MC Walkdown Punch Clearance & Bypass & Tie-in Gas-In Stabilization & Test Run & Acceptance BISEP
Obtain RFC Ready for Test Run
CRS Start Finish Start Finish Start Finish Start Finish Start Finish Start Finish Start Finish Start Finish Start Finish Start Finish Start Finish Start Finish Start Finish Start Finish Start Finish Start Finish
813 - - - - - - - - - - - - - - - - - - 28-Dec-21 29-Dec-21 30-Dec-21 5-Jan-22 6-Jan-22 12-Jan-22 13-Jan-22 13-Jan-22 15-Jan-22 17-Jan-22 18-Jan-22 24-Jan-22 25-Jan-22 30-Jan-22
520 - - - - - - - - - - - - - - - - - - 5-Jan-22 6-Jan-22 8-Jan-22 12-Jan-22 13-Jan-22 19-Jan-22 20-Jan-22 20-Jan-22 22-Jan-22 24-Jan-22 25-Jan-22 27-Jan-22 29-Jan-22 5-Feb-22
402 - - - - - - - - - - - - - - - - - - 15-Dec-21 16-Dec-21 18-Dec-21 23-Dec-21 25-Dec-21 30-Dec-21 1-Jan-22 1-Jan-22 2-Jan-22 4-Jan-22 5-Jan-22 8-Jan-22 9-Jan-22 9-Jan-22
812 - - - - - - 14-Dec-21 15-Dec-21 16-Dec-21 18-Dec-21 16-Dec-21 18-Dec-21 11-Dec-21 18-Dec-21 16-Dec-21 16-Dec-21 16-Dec-21 16-Dec-21 3-Jan-22 4-Jan-22 5-Jan-22 11-Jan-22 12-Jan-22 18-Jan-22 19-Jan-22 19-Jan-22 20-Jan-22 23-Jan-22 24-Jan-22 26-Jan-22 27-Jan-22 1-Feb-22
704 - - 19-Dec-21 26-Dec-21 23-Dec-21 28-Dec-21 22-Dec-21 29-Dec-21 26-Dec-21 30-Dec-21 30-Dec-21 30-Dec-21 29-Dec-21 17-Jan-22 13-Jan-22 16-Jan-22 16-Jan-22 16-Jan-22 18-Jan-22 19-Jan-22 20-Jan-22 26-Jan-22 27-Jan-22 2-Feb-22 3-Feb-22 3-Feb-22 5-Feb-22 7-Feb-22 8-Feb-22 17-Feb-22 19-Feb-22 5-Mar-22
708 26-Dec-21 2-Jan-22 27-Dec-21 4-Jan-22 29-Dec-21 3-Jan-22 30-Dec-21 5-Jan-22 2-Jan-22 6-Jan-22 6-Jan-22 6-Jan-22 4-Jan-22 17-Jan-22 13-Jan-22 16-Jan-22 16-Jan-22 16-Jan-22 18-Jan-22 19-Jan-22 20-Jan-22 26-Jan-22 27-Jan-22 2-Feb-22 3-Feb-22 3-Feb-22 5-Feb-22 7-Feb-22 8-Feb-22 14-Feb-22 15-Feb-22 17-Feb-22
505 3-Jan-22 9-Jan-22 - - - - 6-Jan-22 11-Jan-22 9-Jan-22 13-Jan-22 13-Jan-22 13-Jan-22 18-Jan-22 29-Jan-22 27-Jan-22 27-Jan-22 27-Jan-22 27-Jan-22 30-Jan-22 31-Jan-22 1-Feb-22 6-Feb-22 7-Feb-22 13-Feb-22 14-Feb-22 14-Feb-22 15-Feb-22 17-Feb-22 19-Feb-22 21-Feb-22 22-Feb-22 24-Feb-22
710 - - - - - - - - - - - - 18-Jan-22 25-Jan-22 24-Jan-22 24-Jan-22 - - 26-Jan-22 27-Jan-22 29-Jan-22 3-Feb-22 5-Feb-22 10-Feb-22 12-Feb-22 12-Feb-22 13-Feb-22 15-Feb-22 16-Feb-22 19-Feb-22 20-Feb-22 20-Feb-22
403/1440 3-Jan-22 5-Jan-22 5-Jan-22 12-Jan-22 6-Jan-22 11-Jan-22 13-Jan-22 18-Jan-22 16-Jan-22 20-Jan-22 20-Jan-22 20-Jan-22 26-Jan-22 8-Feb-22 6-Feb-22 7-Feb-22 7-Feb-22 7-Feb-22 9-Feb-22 10-Feb-22 12-Feb-22 17-Feb-22 19-Feb-22 24-Feb-22 26-Feb-22 26-Feb-22 27-Feb-22 1-Mar-22 2-Mar-22 8-Mar-22 9-Mar-22 9-Mar-22
1470 6-Jan-22 9-Jan-22 13-Jan-22 20-Jan-22 13-Jan-22 13-Jan-22 20-Jan-22 25-Jan-22 23-Jan-22 27-Jan-22 27-Jan-22 27-Jan-22 9-Feb-22 19-Feb-22 17-Feb-22 17-Feb-22 17-Feb-22 17-Feb-22 20-Feb-22 21-Feb-22 22-Feb-22 28-Feb-22 1-Mar-22 7-Mar-22 8-Mar-22 8-Mar-22 9-Mar-22 12-Mar-22 13-Mar-22 15-Mar-22 16-Mar-22 21-Mar-22
701/702/709 10-Jan-22 16-Jan-22 22-Jan-22 29-Jan-22 16-Jan-22 19-Jan-22 27-Jan-22 1-Feb-22 30-Jan-22 3-Feb-22 3-Feb-22 3-Feb-22 30-Jan-22 16-Feb-22 14-Feb-22 15-Feb-22 15-Feb-22 15-Feb-22 17-Feb-22 19-Feb-22 20-Feb-22 22-Feb-22 23-Feb-22 26-Feb-22 27-Feb-22 27-Feb-22 28-Feb-22 2-Mar-22 3-Mar-22 16-Mar-22 17-Mar-22 29-Mar-22
557 17-Jan-22 23-Jan-22 - - - - - - 6-Feb-22 10-Feb-22 10-Feb-22 10-Feb-22 20-Feb-22 3-Mar-22 2-Mar-22 2-Mar-22 2-Mar-22 2-Mar-22 5-Mar-22 6-Mar-22 7-Mar-22 10-Mar-22 12-Mar-22 16-Mar-22 17-Mar-22 17-Mar-22 19-Mar-22 21-Mar-22 22-Mar-22 24-Mar-22 26-Mar-22 30-Mar-22

OEM / VENDOR MOBILIZATION DATES

DISCIPLINE VENDOR CRS-812 CRS-704 CRS-708 CRS-710


HVAC TSSC - - - - 19-Dec-21 20-Dec-21 21-Dec-21 22-Dec-21 23-Dec-21 25-Dec-21 26-Dec-21 27-Dec-21 28-Dec-21 29-Dec-21 30-Dec-21 2-Jan-22 3-Jan-22 4-Jan-22
UPS Gutor - - - - 23-Dec-21 26-Dec-21 27-Dec-21 28-Dec-21 29-Dec-21 30-Dec-21 2-Jan-22 3-Jan-22
FACP Rockwell - - - - 22-Dec-21 28-Dec-21 29-Dec-21 30-Dec-21 4-Jan-22 5-Jan-22
F&G & HSSD Tyco & Honeywell - - - - 26-Dec-21 29-Dec-21 30-Dec-21 2-Jan-22 5-Jan-22 6-Jan-22
F&G & HSSD Honeywell + Tyco - - - -
F&G & HSSD Rockwell + Tyco - - - -
F&G & HSSD ABB + Tyco - - - -
RTU (With F&G) Schneider (Aveva) - - - - 30-Dec-21 6-Jan-22

DISCIPLINE VENDOR CRS-505 CRS-403/1440 CRS-1470


HVAC TSSC - - - - - - - 5-Jan-22 6-Jan-22 8-Jan-22 9-Jan-22 10-Jan-22 11-Jan-22 12-Jan-22 13-Jan-22 15-Jan-22 16-Jan-22 17-Jan-22 18-Jan-22 19-Jan-22 20-Jan-22
UPS Gutor - - - - - - - - 6-Jan-22 9-Jan-22 10-Jan-22 11-Jan-22 13-Jan-22
FACP Rockwell 6-Jan-22 10-Jan-22 11-Jan-22 13-Jan-22 17-Jan-22 18-Jan-22 20-Jan-22 24-Jan-22 25-Jan-22
F&G & HSSD Tyco & Honeywell 9-Jan-22 12-Jan-22 13-Jan-22
F&G & HSSD Honeywell + Tyco 16-Jan-22 19-Jan-22 20-Jan-22
F&G & HSSD Rockwell + Tyco 23-Jan-22 26-Jan-22 27-Jan-22
F&G & HSSD ABB + Tyco
RTU (With F&G) Schneider (Aveva) 13-Jan-22 20-Jan-22 27-Jan-22

DISCIPLINE VENDOR CRS-701/702/709 CRS-557


HVAC TSSC 22-Jan-22 23-Jan-22 24-Jan-22 25-Jan-22 26-Jan-22 27-Jan-22 29-Jan-22 - - - - - - -
UPS Gutor 16-Jan-22 17-Jan-22 18-Jan-22 19-Jan-22 - - - - - - -
FACP Rockwell 27-Jan-22 31-Jan-22 1-Feb-22
F&G & HSSD Tyco & Honeywell 30-Jan-22 2-Feb-22 3-Feb-22
F&G & HSSD Honeywell + Tyco
F&G & HSSD Rockwell + Tyco
F&G & HSSD ABB + Tyco 6-Feb-22 9-Feb-22 10-Feb-22
RTU (With F&G) Schneider (Aveva) 3-Feb-22 10-Feb-22

DISCIPLINE VENDOR OEM DAYS


HVAC TSSC 35
UPS Gutor 17
FACP Rockwell 18
F&G & HSSD Tyco & Honeywell 12
F&G & HSSD Honeywell + Tyco 3 403/1440
F&G & HSSD Rockwell + Tyco 3 1470
F&G & HSSD ABB + Tyco 3 557
RTU (With F&G) Schneider (Aveva) 7
Readiness
MC (SAT) SITE (MC) PDB HVAC / ACS / PCS UPS FACP F&G HSSD METERING SYSTEM RTU INERGEN SYSTEM SPS

Maqta 813 Completed Completed Completed Commissioing Balance Completed Completed Completed Completed Completed Completed Completed -

Maqta 520 Completed Completed Completed NA UPSDB : Completed NA Completed NA Completed Completed NA -

Maqta 812 Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed -

Bab/ Buhasa 401 Completed Completed NA NA NA NA Completed NA Completed Completed NA -

Bab/ Buhasa 402 Completed Completed NA NA NA NA Completed NA Completed Completed NA -

Bab/ Buhasa 505 Completed Completed Completed Completed NA Completed Completed Completed Under Punch Closure Completed Completed Completed

Diode to be delivered

SAT Partially
Bab/ Buhasa 602 Completed NA NA NA NA NA NA NA SAT Balance NA Completed
Completed

Commissioing Balance SAT Partially


Ruwais 704 Completed 18-Feb-21 Under Punch Closure & Punch Closure Under Punch Closure Under Punch Closure Under Punch Closure Under Punch Closure Completed SAT Balance Completed -

Out of Scope Punches are


HW - FC Validation Pending 2 days + FC validation
Major

Commissioing Balance Loop & Functional SAT Partially


Ruwais 708 Completed 21-Feb-22 Under Punch Closure Under Punch Closure Under Punch Closure Under Punch Closure SAT Balance Completed -
& Punch Closure test done Completed
Out of Scope Punches are
Major pending work to be closed Vendor Mob Date :

Ruwais 710 Completed 28-Feb-22 Completed NA NA NA NA NA SAT Balance SAT Balance NA -

Bottlenecks Vendor Mob Date : Vendor Mob Date :

Construction, SAT,
Ruwais 701 20-Mar-22 4-Mar-22 Under Punch Closure Commissioing &Punch Completed SAT Balance SAT Balance SAT Balance SAT Balance SAT Balance Pending -

I&C Cable Terminations


Bottlenecks Vendor Mob Date : Vendor Mob Date : Vendor Mob Date : Vendor Mob Date : Vendor Mob Date : Vendor Mob Date : Vendor Mob Date :
Raised Floor

UPSDB : Under Punch


Ruwais 702 Completed 28-Feb-22 Under Punch Closure NA NA SAT Balance NA SAT Balance SAT Balance NA -
Closure

Bottlenecks Vendor Mob Date : Vendor Mob Date : Vendor Mob Date :

Ruwais 709 28-Feb-22 4-Mar-22 SAT Balance NA NA NA SAT Balance NA SAT Balance SAT Balance NA -

Bottlenecks Sub 10B Works Vendor Mob Date : Vendor Mob Date : Vendor Mob Date :

SAT & Commissioing Internal testing


Asab 403 30-Mar-22 3-Apr-22 Completed Completed SAT Balance SAT Balance SAT Balance SAT Balance Pending -
Punch Closure balance Completed
Remaining Cable Modification Completed
Spool Replacement
Bottlenecks Vendor Mob Date : Vendor Mob Date : terminations & Cause and (Termination & Download) Vendor Mob Date : Vendor Mob Date : Mob Date : 22-Mar-22
13-Mar-22 till 3-Apr-22
Effect -21-Mar-22

Asab 1440 Completed 3-Apr-22 NA NA NA NA Pending NA SAT Balance SAT Balance NA -

Bottlenecks Vendor Mob Date : Vendor Mob Date : Vendor Mob Date :

SAT & Commissioing


Asab 1470 Completed Completed Punch Closure balance Completed Completed Completed SAT Balance SAT Balance SAT Balance Pending -

Bottlenecks Vendor Mob Date : Vendor Mob Date : Vendor Mob Date : Vendor Mob Date : Mob Date : 18-Mar-22

Asab 557 SAT Balance NA NA NA SAT Balance SAT Balance SAT Balance SAT Balance NA -

Cable Termination from Sub-Station


Modification Completed
Bottlenecks Pending & Vendor Mob Date : Vendor Mob Date : Vendor Mob Date : Vendor Mob Date :
(Termination & Download)
DB FDn & Earthing Pending
WBS Name CRS Task Name Duration Start Finish OEM Name OEM WBS
CONSTRUCTION &
CONSTRUCTION & COMMISSIONING 71 days 11-Dec-21 3-Mar-22
COMMISSIONING
PRECOMMISSIONING PRECOMMISSIONING 71 days 11-Dec-21 3-Mar-22
CRS-812 812 CRS-812 7 days 11-Dec-21 18-Dec-21
Metering System 812 Metering System 7 days 11-Dec-21 18-Dec-21
Metering System 812 Internal Testing 2 days 11-Dec-21 12-Dec-21 Honeywell Metering
Metering System 812 SAT with Client 4 days 13-Dec-21 16-Dec-21 Honeywell Metering
Metering System 812 Punch Closure 2 days 16-Dec-21 18-Dec-21 Honeywell Metering
FACP 812 FACP 2 days 14-Dec-21 15-Dec-21
FACP 812 SAT with Vendor & Client (Day-1) 1 day 14-Dec-21 14-Dec-21 Rockwell FACP
FACP 812 SAT with Vendor & Client (Day-2) 1 day 15-Dec-21 15-Dec-21 Rockwell FACP
F&G & HSSD 812 F&G & HSSD 2 days 16-Dec-21 18-Dec-21
F&G & HSSD 812 SAT with Vendor & Client (Day-1) 1 day 16-Dec-21 16-Dec-21 Tyco F&G + HSSD
F&G & HSSD 812 SAT with Vendor & Client (Day-2) 1 day 18-Dec-21 18-Dec-21 Tyco F&G + RTU
RTU (With F&G) 812 RTU (With F&G) 2 days 16-Dec-21 18-Dec-21
RTU (With F&G) 812 RTU Communication establishment (with F&G) 1 day 16-Dec-21 18-Dec-21 Schneider (Aveva) + Tyco RTU + F&G
RTU (With Metering) 812 RTU (With Metering) 1 day 16-Dec-21 16-Dec-21
RTU (With Metering) 812 RTU Communication establishment (with Metering System) 1 day 16-Dec-21 16-Dec-21 Schneider (Aveva) + Honeywell RTU + Metering
SMC 812 SMC 1 day 16-Dec-21 16-Dec-21
SMC 812 SMC Communication establishment (with Metering System) 1 day 16-Dec-21 16-Dec-21 Schneider (Aveva) + Honeywell SMC/RTU + Metering

CRS-704 704 CRS-704 25 days 19-Dec-21 17-Jan-22


HVAC 704 HVAC 7 days 19-Dec-21 26-Dec-21
HVAC 704 Internal Testing 5 days 19-Dec-21 23-Dec-21 TSSC HVAC
HVAC 704 Testing with Client 2 days 25-Dec-21 26-Dec-21 TSSC HVAC
UPS 704 UPS 5 days 23-Dec-21 28-Dec-21
UPS 704 Commissioning 4 days 23-Dec-21 28-Dec-21 Gutor UPS
Metering System 704 Metering System 16 days 29-Dec-21 17-Jan-22
Metering System 704 Internal Testing 5 days 29-Dec-21 4-Jan-22 Honeywell Metering
Metering System 704 SAT with Client 8 days 5-Jan-22 16-Jan-22 Honeywell Metering
Metering System 704 Punch Closure 2 days 16-Jan-22 17-Jan-22 Honeywell Metering
FACP 704 FACP 7 days 22-Dec-21 29-Dec-21
FACP 704 Power up (Vendor) 1 day 22-Dec-21 22-Dec-21 Rockwell FACP
FACP 704 Internal Testing (Day-1) 1 day 23-Dec-21 23-Dec-21 -
FACP 704 Internal Testing (Day-2) 1 day 25-Dec-21 25-Dec-21 -
FACP 704 SAT with Vendor & Client (Day-1) 1 day 28-Dec-21 28-Dec-21 Rockwell FACP
FACP 704 SAT with Vendor & Client (Day-2) 1 day 29-Dec-21 29-Dec-21 Rockwell FACP
F&G & HSSD 704 F&G & HSSD 5 days 26-Dec-21 30-Dec-21
F&G & HSSD 704 Power up & Configuration (Vendor) 1 day 26-Dec-21 26-Dec-21 Tyco F&G
F&G & HSSD 704 Internal Testing (Day-1) 1 day 27-Dec-21 27-Dec-21 -
F&G & HSSD 704 Internal Testing (Day-2) 1 day 28-Dec-21 28-Dec-21 -
F&G & HSSD 704 SAT with Vendor & Client (Day-1) 1 day 29-Dec-21 29-Dec-21 Tyco F&G + HSSD
F&G & HSSD 704 SAT with Vendor & Client (Day-2) 1 day 30-Dec-21 30-Dec-21 Tyco F&G + RTU
RTU (With F&G) 704 RTU (With F&G) 1 day 30-Dec-21 30-Dec-21
RTU (With F&G) 704 RTU Communication establishment (with F&G) 1 day 30-Dec-21 30-Dec-21 Schneider (Aveva) + Tyco RTU + F&G
RTU (With Metering) 704 RTU (With Metering) 3 days 13-Jan-22 16-Jan-22
RTU (With Metering) 704 RTU Communication establishment (with Metering System) 2 days 13-Jan-22 16-Jan-22 Schneider (Aveva) + Honeywell RTU + Metering
SMC 704 SMC 1 day 16-Jan-22 16-Jan-22
SMC 704 SMC Communication establishment (with Metering System) 1 day 16-Jan-22 16-Jan-22 Schneider (Aveva) + Honeywell SMC/RTU + Metering

CRS-708 708 CRS-708 19 days 26-Dec-21 17-Jan-22


PDB 708 PDB 6 days 26-Dec-21 2-Jan-22
PDB 708 Internal Testing & Commissioning 6 days 26-Dec-21 2-Jan-22 PDB
HVAC 708 HVAC 7 days 27-Dec-21 4-Jan-22
HVAC 708 Internal Testing 5 days 27-Dec-21 2-Jan-22 TSSC HVAC
HVAC 708 Testing with Client 2 days 3-Jan-22 4-Jan-22 TSSC HVAC
UPS 708 UPS 4 days 29-Dec-21 3-Jan-22
UPS 708 Commissioning 4 days 29-Dec-21 3-Jan-22 Gutor UPS
Metering System 708 Metering System 12 days 4-Jan-22 17-Jan-22
Metering System 708 Internal Testing 3 days 4-Jan-22 6-Jan-22 Honeywell Metering
Metering System 708 SAT with Client 6 days 9-Jan-22 16-Jan-22 Honeywell Metering
Metering System 708 Punch Closure 2 days 16-Jan-22 17-Jan-22 Honeywell Metering
FACP 708 FACP 5 days 30-Dec-21 5-Jan-22
FACP 708 Power up (Vendor) 1 day 30-Dec-21 30-Dec-21 Rockwell FACP
FACP 708 Internal Testing (Day-1) 1 day 2-Jan-22 2-Jan-22 -
FACP 708 Internal Testing (Day-2) 1 day 3-Jan-22 3-Jan-22 -
FACP 708 SAT with Vendor & Client (Day-1) 1 day 4-Jan-22 4-Jan-22 Rockwell FACP
FACP 708 SAT with Vendor & Client (Day-2) 1 day 5-Jan-22 5-Jan-22 Rockwell FACP
F&G & HSSD 708 F&G & HSSD 5 days 2-Jan-22 6-Jan-22
F&G & HSSD 708 Power up & Configuration (Vendor) 1 day 2-Jan-22 2-Jan-22 Tyco F&G
F&G & HSSD 708 Internal Testing (Day-1) 1 day 3-Jan-22 3-Jan-22 -
F&G & HSSD 708 Internal Testing (Day-2) 1 day 4-Jan-22 4-Jan-22 -
F&G & HSSD 708 SAT with Vendor & Client (Day-1) 1 day 5-Jan-22 5-Jan-22 Tyco F&G + HSSD
F&G & HSSD 708 SAT with Vendor & Client (Day-2) 1 day 6-Jan-22 6-Jan-22 Tyco F&G + RTU
RTU (With F&G) 708 RTU (With F&G) 1 day 6-Jan-22 6-Jan-22
RTU (With F&G) 708 RTU Communication establishment (with F&G) 1 day 6-Jan-22 6-Jan-22 Schneider (Aveva) + Tyco RTU + F&G
RTU (With Metering) 708 RTU (With Metering) 3 days 13-Jan-22 16-Jan-22
RTU (With Metering) 708 RTU Communication establishment (with Metering System) 2 days 13-Jan-22 16-Jan-22 Schneider (Aveva) + Honeywell RTU + Metering
SMC 708 SMC 1 day 16-Jan-22 16-Jan-22
SMC 708 SMC Communication establishment (with Metering System) 1 day 16-Jan-22 16-Jan-22 Schneider (Aveva) + Honeywell SMC/RTU + Metering

CRS-710 710 CRS-710 7 days 18-Jan-22 25-Jan-22


Metering System 710 Metering System 7 days 18-Jan-22 25-Jan-22
Metering System 710 Internal Testing 2 days 18-Jan-22 19-Jan-22 Honeywell Metering
Metering System 710 SAT with Client 3 days 20-Jan-22 24-Jan-22 Honeywell Metering
Metering System 710 Punch Closure 2 days 24-Jan-22 25-Jan-22 Honeywell Metering
RTU (With Metering) 710 RTU (With Metering) 1 day 24-Jan-22 24-Jan-22
RTU (With Metering) 710 RTU Communication establishment (with Metering System) 1 day 24-Jan-22 24-Jan-22 Schneider (Aveva) + Honeywell RTU + Metering

CRS-505 505 CRS-505 23 days 3-Jan-22 29-Jan-22


PDB 505 PDB 6 days 3-Jan-22 9-Jan-22
PDB 505 Internal Testing & Commissioning 6 days 3-Jan-22 9-Jan-22 PDB
Metering System 505 Metering System 10 days 18-Jan-22 29-Jan-22
Metering System 505 Internal Testing 3 days 18-Jan-22 20-Jan-22 Honeywell Metering
Metering System 505 SAT with Client 5 days 23-Jan-22 27-Jan-22 Honeywell Metering
Metering System 505 Punch Closure 2 days 27-Jan-22 29-Jan-22 Honeywell Metering
FACP 505 FACP 5 days 6-Jan-22 11-Jan-22
FACP 505 Power up (Vendor) 1 day 6-Jan-22 6-Jan-22 Rockwell FACP
FACP 505 Internal Testing (Day-1) 1 day 8-Jan-22 8-Jan-22 -
FACP 505 Internal Testing (Day-2) 1 day 9-Jan-22 9-Jan-22 -
FACP 505 SAT with Vendor & Client (Day-1) 1 day 10-Jan-22 10-Jan-22 Rockwell FACP
FACP 505 SAT with Vendor & Client (Day-2) 1 day 11-Jan-22 11-Jan-22 Rockwell FACP
F&G & HSSD 505 F&G & HSSD 5 days 9-Jan-22 13-Jan-22
F&G & HSSD 505 Power up & Configuration (Vendor) 1 day 9-Jan-22 9-Jan-22 Tyco F&G
F&G & HSSD 505 Internal Testing (Day-1) 1 day 10-Jan-22 10-Jan-22 -
F&G & HSSD 505 Internal Testing (Day-2) 1 day 11-Jan-22 11-Jan-22 -
F&G & HSSD 505 SAT with Vendor & Client (Day-1) 1 day 12-Jan-22 12-Jan-22 Tyco F&G + HSSD
F&G & HSSD 505 SAT with Vendor & Client (Day-2) 1 day 13-Jan-22 13-Jan-22 Tyco F&G + RTU
RTU (With F&G) 505 RTU (With F&G) 1 day 13-Jan-22 13-Jan-22
RTU (With F&G) 505 RTU Communication establishment (with F&G) 1 day 13-Jan-22 13-Jan-22 Schneider (Aveva) + Tyco RTU + F&G
RTU (With Metering) 505 RTU (With Metering) 1 day 27-Jan-22 27-Jan-22
RTU (With Metering) 505 RTU Communication establishment (with Metering System) 1 day 27-Jan-22 27-Jan-22 Schneider (Aveva) + Honeywell RTU + Metering
SMC 505 SMC 1 day 27-Jan-22 27-Jan-22
SMC 505 SMC Communication establishment (with Metering System) 1 day 27-Jan-22 27-Jan-22 Schneider (Aveva) + Honeywell SMC/RTU + Metering
WBS Name CRS Task Name Duration Start Finish OEM Name OEM WBS

CRS-403/1440 403/1440 CRS-403/1440 32 days 3-Jan-22 8-Feb-22


PDB 403/1440 PDB 3 days 3-Jan-22 5-Jan-22
PDB 403/1440 Internal Testing & Commissioning 3 days 3-Jan-22 5-Jan-22 PDB
HVAC 403/1440 HVAC 7 days 5-Jan-22 12-Jan-22
HVAC 403/1440 Internal Testing 5 days 5-Jan-22 10-Jan-22 TSSC HVAC
HVAC 403/1440 Testing with Client 2 days 11-Jan-22 12-Jan-22 TSSC HVAC
UPS 403/1440 UPS 5 days 6-Jan-22 11-Jan-22
UPS 403/1440 Commissioning 4 days 6-Jan-22 11-Jan-22 Gutor UPS
Metering System 403/1440 Metering System 12 days 26-Jan-22 8-Feb-22
Metering System 403/1440 Internal Testing 3 days 26-Jan-22 29-Jan-22 Honeywell Metering
Metering System 403/1440 SAT with Client 7 days 30-Jan-22 7-Feb-22 Honeywell Metering
Metering System 403/1440 Punch Closure 2 days 7-Feb-22 8-Feb-22 Honeywell Metering
FACP 403/1440 FACP 5 days 13-Jan-22 18-Jan-22
FACP 403/1440 Power up (Vendor) 1 day 13-Jan-22 13-Jan-22 Rockwell FACP
FACP 403/1440 Internal Testing (Day-1) 1 day 15-Jan-22 15-Jan-22 -
FACP 403/1440 Internal Testing (Day-2) 1 day 16-Jan-22 16-Jan-22 -
FACP 403/1440 SAT with Vendor & Client (Day-1) 1 day 17-Jan-22 17-Jan-22 Rockwell FACP
FACP 403/1440 SAT with Vendor & Client (Day-2) 1 day 18-Jan-22 18-Jan-22 Rockwell FACP
F&G & HSSD 403/1440 F&G & HSSD 5 days 16-Jan-22 20-Jan-22
F&G & HSSD 403/1440 Power up & Configuration (Vendor) 1 day 16-Jan-22 16-Jan-22 Honeywell F&G
F&G & HSSD 403/1440 Internal Testing (Day-1) 1 day 17-Jan-22 17-Jan-22 -
F&G & HSSD 403/1440 Internal Testing (Day-2) 1 day 18-Jan-22 18-Jan-22 -
F&G & HSSD 403/1440 SAT with Vendor & Client (Day-1) 1 day 19-Jan-22 19-Jan-22 Honeywell + Tyco F&G + HSSD
F&G & HSSD 403/1440 SAT with Vendor & Client (Day-2) 1 day 20-Jan-22 20-Jan-22 Honeywell + Schneider (Aveva) F&G + RTU
RTU (With F&G) 403/1440 RTU (With F&G) 1 day 20-Jan-22 20-Jan-22
RTU (With F&G) 403/1440 RTU Communication establishment (with Metering) 1 day 20-Jan-22 20-Jan-22 Schneider (Aveva) + Honeywell RTU + F&G
RTU (With Metering) 403/1440 RTU (With Metering) 2 days 6-Feb-22 7-Feb-22
RTU (With Metering) 403/1440 RTU Communication establishment (with Metering System) 2 days 6-Feb-22 7-Feb-22 Schneider (Aveva) + Honeywell RTU + Metering
SMC 403/1440 SMC 1 day 7-Feb-22 7-Feb-22
SMC 403/1440 SMC Communication establishment (with Metering System) 1 day 7-Feb-22 7-Feb-22 Schneider (Aveva) + Honeywell SMC/RTU + Metering

CRS-1470 1470 CRS-1470 38 days 6-Jan-22 19-Feb-22


PDB 1470 PDB 3 days 6-Jan-22 9-Jan-22
PDB 1470 Internal Testing & Commissioning 3 days 6-Jan-22 9-Jan-22 PDB
HVAC 1470 HVAC 7 days 13-Jan-22 20-Jan-22
HVAC 1470 Internal Testing (ACS HVAC) 5 days 13-Jan-22 18-Jan-22 TSSC HVAC
HVAC 1470 Testing with Client (ACS HVAC) 2 days 19-Jan-22 20-Jan-22 TSSC HVAC
UPS 1470 UPS 1 day 13-Jan-22 13-Jan-22
UPS 1470 Commissioning (UPS DB) 1 day 13-Jan-22 13-Jan-22 Gutor Requirement TBC UPS
Metering System 1470 Metering System 9 days 9-Feb-22 19-Feb-22
Metering System 1470 Internal Testing 3 days 9-Feb-22 12-Feb-22 Honeywell Metering
Metering System 1470 SAT with Client 5 days 13-Feb-22 17-Feb-22 Honeywell Metering
Metering System 1470 Punch Closure 2 days 17-Feb-22 19-Feb-22 Honeywell Metering
FACP 1470 FACP 5 days 20-Jan-22 25-Jan-22
FACP 1470 Power up (Vendor) 1 day 20-Jan-22 20-Jan-22 Rockwell FACP
FACP 1470 Internal Testing (Day-1) 1 day 22-Jan-22 22-Jan-22 -
FACP 1470 Internal Testing (Day-2) 1 day 23-Jan-22 23-Jan-22 -
FACP 1470 SAT with Vendor & Client (Day-1) 1 day 24-Jan-22 24-Jan-22 Rockwell FACP
FACP 1470 SAT with Vendor & Client (Day-2) 1 day 25-Jan-22 25-Jan-22 Rockwell FACP
F&G & HSSD 1470 F&G & HSSD 5 days 23-Jan-22 27-Jan-22
F&G & HSSD 1470 Power up & Configuration (Vendor) 1 day 23-Jan-22 23-Jan-22 Rockwell F&G
F&G & HSSD 1470 Internal Testing (Day-1) 1 day 24-Jan-22 24-Jan-22 -
F&G & HSSD 1470 Internal Testing (Day-2) 1 day 25-Jan-22 25-Jan-22 -
F&G & HSSD 1470 SAT with Vendor & Client (Day-1) 1 day 26-Jan-22 26-Jan-22 Rockwell + Tyco F&G + HSSD
F&G & HSSD 1470 SAT with Vendor & Client (Day-2) 1 day 27-Jan-22 27-Jan-22 Rockwell + Schneider (Aveva) F&G + RTU
RTU (With F&G) 1470 RTU (With F&G) 1 day 27-Jan-22 27-Jan-22
RTU (With F&G) 1470 RTU Communication establishment (with F&G) 1 day 27-Jan-22 27-Jan-22 Schneider (Aveva) + Rockwell RTU + F&G
RTU (With Metering) 1470 RTU (With Metering) 1 day 17-Feb-22 17-Feb-22
RTU (With Metering) 1470 RTU Communication establishment (with Metering System) 1 day 17-Feb-22 17-Feb-22 Schneider (Aveva) + Honeywell RTU + Metering
SMC 1470 SMC 1 day 17-Feb-22 17-Feb-22
SMC 1470 SMC Communication establishment (with Metering System) 1 day 17-Feb-22 17-Feb-22 Schneider (Aveva) + Honeywell SMC/RTU + Metering

CRS-701/702/709 701/702/709 CRS-701/702/709 33 days 10-Jan-22 16-Feb-22


PDB 701/702/709 PDB 6 days 10-Jan-22 16-Jan-22
PDB 701/702/709 Internal Testing & Commissioning 6 days 10-Jan-22 16-Jan-22 PDB
HVAC 701/702/709 HVAC 7 days 22-Jan-22 29-Jan-22
HVAC 701/702/709 Internal Testing 5 days 22-Jan-22 26-Jan-22 TSSC HVAC
HVAC 701/702/709 Testing with Client 2 days 27-Jan-22 29-Jan-22 TSSC HVAC
UPS 701/702/709 UPS 4 days 16-Jan-22 19-Jan-22
UPS 701/702/709 Commissioning 4 days 16-Jan-22 19-Jan-22 Gutor UPS
Metering System 701/702/709 Metering System 16 days 30-Jan-22 16-Feb-22
Metering System 701/702/709 Internal Testing 6 days 30-Jan-22 5-Feb-22 Honeywell Metering
Metering System 701/702/709 SAT with Client 8 days 6-Feb-22 15-Feb-22 Honeywell Metering
Metering System 701/702/709 Punch Closure 2 days 15-Feb-22 16-Feb-22 Honeywell Metering
FACP 701/702/709 FACP 5 days 27-Jan-22 1-Feb-22
FACP 701/702/709 Power up (Vendor) 1 day 27-Jan-22 27-Jan-22 Rockwell FACP
FACP 701/702/709 Internal Testing (Day-1) 1 day 29-Jan-22 29-Jan-22 -
FACP 701/702/709 Internal Testing (Day-2) 1 day 30-Jan-22 30-Jan-22 -
FACP 701/702/709 SAT with Vendor & Client (Day-1) 1 day 31-Jan-22 31-Jan-22 Rockwell FACP
FACP 701/702/709 SAT with Vendor & Client (Day-2) 1 day 1-Feb-22 1-Feb-22 Rockwell FACP
F&G & HSSD 701/702/709 F&G & HSSD 5 days 30-Jan-22 3-Feb-22
F&G & HSSD 701/702/709 Power up & Configuration (Vendor) 1 day 30-Jan-22 30-Jan-22 Tyco F&G
F&G & HSSD 701/702/709 Internal Testing (Day-1) 1 day 31-Jan-22 31-Jan-22 -
F&G & HSSD 701/702/709 Internal Testing (Day-2) 1 day 1-Feb-22 1-Feb-22 -
F&G & HSSD 701/702/709 SAT with Vendor & Client (Day-1) 1 day 2-Feb-22 2-Feb-22 Tyco F&G + HSSD
F&G & HSSD 701/702/709 SAT with Vendor & Client (Day-2) 1 day 3-Feb-22 3-Feb-22 Tyco F&G + RTU
RTU (With F&G) 701/702/709 RTU (With F&G) 1 day 3-Feb-22 3-Feb-22
RTU (With F&G) 701/702/709 RTU Communication establishment (with F&G) 1 day 3-Feb-22 3-Feb-22 Schneider (Aveva) + Tyco RTU + F&G
RTU (With Metering) 701/702/709 RTU (With Metering) 2 days 14-Feb-22 15-Feb-22
RTU (With Metering) 701/702/709 RTU Communication establishment (with Metering System) 2 days 14-Feb-22 15-Feb-22 Schneider (Aveva) + Honeywell RTU + Metering
SMC 701/702/709 SMC 1 day 15-Feb-22 15-Feb-22
SMC 701/702/709 SMC Communication establishment (with Metering System) 1 day 15-Feb-22 15-Feb-22 Schneider (Aveva) + Honeywell SMC/RTU + Metering

CRS-557 557 CRS-557 40 days 17-Jan-22 3-Mar-22


PDB 557 PDB 6 days 17-Jan-22 23-Jan-22
PDB 557 Internal Testing & Commissioning 6 days 17-Jan-22 23-Jan-22 PDB
Metering System 557 Metering System 11 days 20-Feb-22 3-Mar-22
Metering System 557 Internal Testing 3 days 20-Feb-22 22-Feb-22 Honeywell Metering
Metering System 557 SAT with Client 6 days 23-Feb-22 2-Mar-22 Honeywell Metering
Metering System 557 Punch Closure 2 days 2-Mar-22 3-Mar-22 Honeywell Metering
F&G & HSSD 557 F&G & HSSD 5 days 6-Feb-22 10-Feb-22
F&G & HSSD 557 Power up & Configuration (Vendor) 1 day 6-Feb-22 6-Feb-22 ABB F&G
F&G & HSSD 557 Internal Testing (Day-1) 1 day 7-Feb-22 7-Feb-22 -
F&G & HSSD 557 Internal Testing (Day-2) 1 day 8-Feb-22 8-Feb-22 -
F&G & HSSD 557 SAT with Vendor & Client (Day-1) 1 day 9-Feb-22 9-Feb-22 ABB + Tyco F&G + HSSD
F&G & HSSD 557 SAT with Vendor & Client (Day-2) 1 day 10-Feb-22 10-Feb-22 ABB + Schneider (Aveva) F&G + RTU
RTU (With F&G) 557 RTU (With F&G) 1 day 10-Feb-22 10-Feb-22
RTU (With F&G) 557 RTU Communication establishment (with F&G) 1 day 10-Feb-22 10-Feb-22 Schneider (Aveva) + ABB RTU + F&G
RTU (With Metering) 557 RTU (With Metering) 1 day 2-Mar-22 2-Mar-22
RTU (With Metering) 557 RTU Communication establishment (with Metering System) 1 day 2-Mar-22 2-Mar-22 Schneider (Aveva) + Honeywell RTU + Metering
SMC 557 SMC 1 day 2-Mar-22 2-Mar-22
SMC 557 SMC Communication establishment (with Metering System) 1 day 2-Mar-22 2-Mar-22 Schneider (Aveva) + Honeywell SMC/RTU + Metering
VENDOR
DAY # ACTIVITY SKID REQUIREMENT REMARKS

CRS-812
Day - 1 Internal Testing Yes
Day - 2 Internal Testing Yes
Day - 3 Internal Testing Yes
Day - 4 Internal Testing Yes
Day - 5 Visual Inspection of Metering Skid Yes
Day - 5 Visual inspection of Metering Control Panel Yes
Day - 5 PLC Redundancy Yes
Day - 5 PLC Digital input test Yes
Day - 6 Valve Control Yes
Day - 6 Automatic run switching Yes
Day - 6 Proving Run Switching Yes
Day - 6 Power failure on SVC, flow computer and PLC Yes
Day - 7 Flow Calculations Yes
Day - 7 Uncertainty Calculation Yes
Day - 7 Flow computer and supervisory computer comparison Yes
Day - 7 Fiscal reporting Yes
Day - 7 Pressure and temperature transmitter input test Yes
Day - 7 PLC Analogue input test Yes
Day - 7 Ultrasonic meter input test Yes
Day - 8 Proving Simulation and Reporting Yes
Day - 8 Low Flow / Pressure Switch Activation Test Yes
Day - 8 Calibration of Pressure Transmitters Yes
Day - 8 RTU communication establishment & test Yes
Day - 8 System Security – OT security compliance test Yes
Day - 8 RTU communication test Yes
Day - 8 Punch Closure Yes
Day - 9 Spare day for Punch Closure Yes

CRS-704
Day - 1 Internal testing Yes
Day - 2 Internal testing Yes
Day - 3 Internal testing Yes
Day - 4 Internal testing Yes
Day - 5 Internal testing Yes
Day - 6 Visual Inspection of Metering Skid 704-ME-701 Yes
Day - 6 Visual Inspection of Metering Skid 704-ME-801 Yes
Day - 6 Visual Inspection of Metering Skid 704-ME-901 Yes
Day - 6 Visual inspection of Metering Control Panel Yes
Day - 6 Visual Inspection of Analyzer Shelter 704-ME-701 Yes
Day - 6 Visual Inspection of Analyzer Shelter 704-ME-901 Yes
Day - 7 Pressure and temperature transmitter input test Yes
Day - 7 Ultrasonic meter input test Yes
Day - 7 Gas composition input test Yes
Day - 7 Flow Calculations Yes
Day - 8 PLC Redundancy Yes
Day - 8 Valve Control Yes
Day - 8 PLC Digital input test Yes
Day - 8 PLC Analogue input test Yes
Day - 8 Automatic run switching 704-ME-701 Yes
Day - 8 Automatic run switching 704-ME-801 Yes
Day - 8 Automatic run switching 704-ME-901 Yes
Day - 8 Proving Run Switching 704-ME-701 Yes
Day - 8 Proving Run Switching 704-ME-801 Yes
Day - 8 Proving Run Switching 704-ME-901 Yes
Day - 9 Flow computer and supervisory computer comparison Yes
Day - 9 Fiscal reporting Yes
Day - 9 Uncertainty Calculation Yes
Day - 9 Power failure on SVC, flow computer and PLC Yes
Day - 9 Sampling Conditioning System & Calibration and Carrier Gas Conditioning System Leak Test 704-ME-701 Yes
Day - 9 Sampling Conditioning System & Calibration and Carrier Gas Conditioning System Leak Test 704-ME-901 Yes
Day - 9 Low Flow / Pressure Switch Activation Test 704-ME-701 Yes
Day - 9 Low Flow / Pressure Switch Activation Test 704-ME-901 Yes
Day - 10 Gas Chromatograph Performance Test 704-ME-701 Yes
Day - 10 Gas Chromatograph Performance Test 704-ME-901 Yes
Day - 10 System Security – OT security compliance test Yes
Day - 10 Software installation list, IP address & disaster recovery procedure Yes
Day - 10 RTU System communication test Yes
Day - 10 CTMMS communication test Yes
Day - 10 Punch Closure Yes
Day - 11 Spare day for Punch closure Yes

CRS-708
Day - 1 Internal testing Yes
Day - 2 Internal testing Yes
Day - 3 Internal testing Yes
Day - 4 Internal testing Yes
Day - 5 Visual Inspection of Metering Skid 708-ME-701 Yes
Day - 5 Visual Inspection of Metering Skid 708-ME-801 Yes
Day - 5 Visual inspection of Metering Control Panel Yes
Day - 5 Visual Inspection of Analyzer Shelter 708-ME-701 Yes
Day - 5 Pressure and temperature transmitter input test Yes
Day - 5 Ultrasonic meter input test Yes
Day - 5 Gas composition input test Yes
Day - 5 Flow Calculations Yes
Day - 6 PLC Redundancy Yes
Day - 6 Valve Control Yes
Day - 6 PLC Digital input test Yes
Day - 6 PLC Analogue input test Yes
Day - 6 Automatic run switching 708-ME-701 Yes
Day - 6 Automatic run switching 708-ME-801 Yes
Day - 6 Proving Run Switching 708-ME-701 Yes
Day - 6 Proving Run Switching 708-ME-801 Yes
Day - 7 Flow computer and supervisory computer comparison Yes
Day - 7 Fiscal reporting Yes
Day - 7 Uncertainty Calculation Yes
Day - 7 Power failure on SVC, flow computer and PLC Yes
Day - 7 Sampling Conditioning System & Calibration and Carrier Gas Conditioning System Leak Test 708-ME-701 Yes
Day - 7 Low Flow / Pressure Switch Activation Test 708-ME-701 Yes
Day - 8 Gas Chromatograph Performance Test 708-ME-701 Yes
Day - 8 System Security – OT security compliance test Yes
Day - 8 Software installation list, IP address & disaster recovery procedure Yes
Day - 8 RTU System communication test Yes
Day - 8 CTMMS communication test Yes
Day - 8 Punch Closure Yes
Day - 9 Spare day for Punch closure Yes

CRS-505
Day - 1 Internal testing Yes
Day - 2 Internal testing Yes
Day - 3 Internal testing Yes
Day - 4 Internal testing Yes
Day - 5 Visual Inspection of Metering Skid 505-ME-801 Yes
Day - 5 Visual inspection of Metering Control Panel Yes
Day - 5 Visual Inspection of Analyzer Shelter 505-ME-801 Yes
Day - 5 Pressure and temperature transmitter input test Yes
Day - 5 Ultrasonic meter input test Yes
Day - 5 Gas composition input test Yes
Day - 5 Flow Calculations Yes
Day - 6 PLC Redundancy Yes
Day - 6 Valve Control Yes
Day - 6 PLC Digital input test Yes
Day - 6 PLC Analogue input test Yes
Day - 6 Automatic run switching 505-ME-801 Yes
Day - 6 Proving Run Switching 505-ME-801 Yes
Day - 7 Flow computer and supervisory computer comparison Yes
Day - 7 Fiscal reporting Yes
Day - 7 Uncertainty Calculation Yes
Day - 7 Power failure on SVC, flow computer and PLC Yes
Day - 7 System Security – OT security compliance test Yes
Day - 7 Software installation list, IP address & disaster recovery procedure Yes
Day - 7 RTU System communication test Yes
Day - 7 CTMMS communication test Yes
Day - 8 Punch Closure Yes
Day - 9 Spare day for Punch closure Yes

CRS-710
Day - 1 Internal testing Yes
Day - 2 Internal testing Yes
Day - 3 Visual inspection of Metering Control Panel Yes
Day - 3 Visual Inspection of Analyzer Shelter Yes
Day - 3 Gas composition input test Yes
Day - 4 Flow computer and supervisory computer comparison Yes
Day - 4 Fiscal reporting Yes
Day - 4 Uncertainty Calculation Yes
Day - 4 Power failure on SVC, flow computer and PLC Yes
Day - 4 Sampling Conditioning System & Calibration and Carrier Gas Conditioning System Leak Test Yes
Day - 4 Low Flow / Pressure Switch Activation Test Yes
Day - 5 Gas Chromatograph Performance Test Yes
Day - 5 System Security – OT security compliance test Yes
Day - 5 Software installation list, IP address & disaster recovery procedure Yes
Day - 5 RTU System communication test Yes
Day - 5 CTMMS communication test Yes
Day - 5 Punch Closure Yes
Day - 6 Spare day for Punch closure Yes

CRS-403/1440
Day - 1 Internal testing Yes
Day - 2 Internal testing Yes
Day - 3 Internal testing Yes
Day - 4 Internal testing Yes
Day - 5 Visual Inspection of Flow meter 556-ME-701 Yes
Day - 5 Visual Inspection of Metering Skid 556-ME-3200-101 Yes
Day - 5 Visual inspection of Metering Control Panel Yes
Day - 5 Visual Inspection of Analyzer Shelter 556-ME-701 Yes
Day - 5 Visual Inspection of Analyzer Shelter 556-ME-3200-101 Yes
Day - 5 Pressure and temperature transmitter input test Yes
Day - 5 Ultrasonic meter input test Yes
Day - 5 Gas composition input test Yes
Day - 5 Flow Calculations Yes
Day - 6 PLC Redundancy Yes
Day - 6 Valve Control Yes
Day - 6 PLC Digital input test Yes
Day - 6 PLC Analogue input test Yes
Day - 6 Automatic run switching 556-ME-3200-101 Yes
Day - 6 Proving Run Switching 556-ME-3200-101 Yes
Day - 7 Flow computer and supervisory computer comparison Yes
Day - 7 Fiscal reporting Yes
Day - 7 Uncertainty Calculation Yes
Day - 7 Power failure on SVC, flow computer and PLC Yes
Day - 7 Sampling Conditioning System & Calibration and Carrier Gas Conditioning System Leak Test 556-ME-701 Yes
Day - 7 Sampling Conditioning System & Calibration and Carrier Gas Conditioning System Leak Test 556-ME-3200-101 Yes
Day - 7 Low Flow / Pressure Switch Activation Test 556-ME-701 Yes
Day - 7 Low Flow / Pressure Switch Activation Test 556-ME-3200-101 Yes
Day - 8 Gas Chromatograph Performance Test 556-ME-701 Yes
Day - 8 Gas Chromatograph Performance Test 556-ME-3200-101 Yes
Day - 8 System Security – OT security compliance test Yes
Day - 8 Software installation list, IP address & disaster recovery procedure Yes
Day - 8 RTU System communication test Yes
Day - 8 CTMMS communication test Yes
Day - 8 Punch Closure Yes
Day - 9 Spare day for Punch closure Yes

CRS-1470
Day - 1 Internal testing Yes
Day - 2 Internal testing Yes
Day - 3 Internal testing Yes
Day - 4 Internal testing Yes
Day - 5 Visual Inspection of Metering Skid 556-ME-3100-101 Yes
Day - 5 Visual inspection of Metering Control Panel Yes
Day - 5 Visual Inspection of Analyzer Shelter 556-ME-3100-101 Yes
Day - 5 Pressure and temperature transmitter input test Yes
Day - 5 Ultrasonic meter input test Yes
Day - 5 Gas composition input test Yes
Day - 5 Flow Calculations Yes
Day - 6 PLC Redundancy Yes
Day - 6 Valve Control Yes
Day - 6 PLC Digital input test Yes
Day - 6 PLC Analogue input test Yes
Day - 6 Automatic run switching 556-ME-3100-101 Yes
Day - 6 Proving Run Switching 556-ME-3100-101 Yes
Day - 7 Flow computer and supervisory computer comparison Yes
Day - 7 Fiscal reporting Yes
Day - 7 Uncertainty Calculation Yes
Day - 7 Power failure on SVC, flow computer and PLC Yes
Day - 7 Sampling Conditioning System & Calibration and Carrier Gas Conditioning System Leak Test 556-ME-3100-101 Yes
Day - 7 Low Flow / Pressure Switch Activation Test 556-ME-3100-101 Yes
Day - 8 Gas Chromatograph Performance Test 556-ME-3100-101 Yes
Day - 8 System Security – OT security compliance test Yes
Day - 8 Software installation list, IP address & disaster recovery procedure Yes
Day - 8 RTU System communication test Yes
Day - 8 CTMMS communication test Yes
Day - 8 Punch Closure Yes
Day - 9 Spare day for Punch closure Yes

CRS-701/702/709
Day - 1 Internal testing Yes
Day - 2 Internal testing Yes
Day - 3 Internal testing Yes
Day - 4 Internal testing Yes
Day - 5 Internal testing Yes
Day - 6 Internal testing Yes
Day - 7 Visual Inspection of Metering Skid 701-ME-701 Yes
Day - 7 Visual Inspection of Metering Skid 701-ME-801 Yes
Day - 7 Visual Inspection of Metering Skid 702-ME-201 Yes
Day - 7 Visual Inspection of Metering Skid 709-ME-501 Yes
Day - 8 Visual inspection of Metering Control Panel Yes
Day - 8 Visual Inspection of Analyzer Shelter 701-ME-701 Yes
Day - 8 Visual Inspection of Analyzer Shelter 702-ME-201 Yes
Day - 9 Pressure and temperature transmitter input test Yes
Day - 9 Ultrasonic meter input test Yes
Day - 9 Gas composition input test Yes
Day - 9 Flow Calculations Yes
Day - 10 PLC Redundancy Yes
Day - 10 Valve Control Yes
Day - 10 PLC Digital input test Yes
Day - 10 PLC Analogue input test Yes
Day - 10 Automatic run switching 701-ME-701 Yes
Day - 10 Automatic run switching 701-ME-801 Yes
Day - 10 Automatic run switching 702-ME-201 Yes
Day - 10 Automatic run switching 709-ME-501 Yes
Day - 10 Proving Run Switching 701-ME-701 Yes
Day - 10 Proving Run Switching 701-ME-801 Yes
Day - 10 Proving Run Switching 702-ME-201 Yes
Day - 10 Proving Run Switching 709-ME-501 Yes
Day - 11 Flow computer and supervisory computer comparison Yes
Day - 11 Fiscal reporting Yes
Day - 11 Uncertainty Calculation Yes
Day - 11 Power failure on SVC, flow computer and PLC Yes
Day - 11 Sampling Conditioning System & Calibration and Carrier Gas Conditioning System Leak Test 701-ME-701 Yes
Day - 11 Sampling Conditioning System & Calibration and Carrier Gas Conditioning System Leak Test 702-ME-201 Yes
Day - 11 Low Flow / Pressure Switch Activation Test 701-ME-701 Yes
Day - 11 Low Flow / Pressure Switch Activation Test 702-ME-201 Yes
Day - 12 Gas Chromatograph Performance Test 701-ME-701 Yes
Day - 12 Gas Chromatograph Performance Test 702-ME-201 Yes
Day - 12 System Security – OT security compliance test Yes
Day - 12 Software installation list, IP address & disaster recovery procedure Yes
Day - 12 RTU System communication test Yes
Day - 12 CTMMS communication test Yes
Day - 12 Punch Closure Yes
Day - 13 Spare day for Punch closure Yes

CRS-557
Day - 1 Internal testing Yes
Day - 2 Internal testing Yes
Day - 3 Internal testing Yes
Day - 4 Internal testing Yes
Day - 5 Visual Inspection of Metering Skid 557-ME-201 Yes
Day - 5 Visual inspection of Metering Control Panel Yes
Day - 5 Visual Inspection of Analyzer Shelter 557-ME-201 Yes
Day - 5 Pressure and temperature transmitter input test Yes
Day - 5 Ultrasonic meter input test Yes
Day - 5 Gas composition input test Yes
Day - 5 Flow Calculations Yes
Day - 5 Inlet & Outlet pressure transmitter test Yes
Day - 6 Valve Control Yes
Day - 6 Flow computer and supervisory computer comparison Yes
Day - 6 Fiscal reporting Yes
Day - 6 Uncertainty Calculation Yes
Day - 7 Power failure on SVC, flow computer and PLC Yes
Day - 7 Sampling Conditioning System & Calibration and Carrier Gas Conditioning System Leak Test 557-ME-201 Yes
Day - 7 Low Flow / Pressure Switch Activation Test 557-ME-201 Yes
Day - 8 Gas Chromatograph Performance Test 557-ME-201 Yes
Day - 8 System Security – OT security compliance test Yes
Day - 8 Software installation list, IP address & disaster recovery procedure Yes
Day - 8 RTU System communication test Yes
Day - 8 CTMMS communication test Yes
Day - 8 Punch Closure Yes
Day - 9 Spare day for Punch closure Yes