Cronograma del Proyecto: Construccion e Instalacion del 3er Molino de Bolas y Obras Asociadas

Linea Base 1 Rev. 0 (actualizado al 22-octubre)


Activity ID Activity Name Start Finish Original October 2021 November 2021 December 2021 January 2022 February 2022 March 2022 April 2022 May 2022 June 2022 July 2022
Duration
09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 05 12 19 26 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 02 09 6
06-Apr-21 06:00 A 18-Jun-22 439.00 18-Jun-22 17:00, MC
MCC19 - Cronograma del
d 3er Molino de Bolas y Obras Asociadas - Linea Ba 17:00
06-Apr-21 06:00 A 18-Jun-22 439.00 18-Jun-22 17:00, Co
Contract Milestone
H1000 Award of Contract 06-Apr-21 06:00 A 0.00

H2000 Complete Site Mobilization 13-May-21 0.00


H3000 Commence Site Activities 14-May-21 06:00 A 0.00

H9070 Entrega de area - Contenedores de LB-01 16-May-21 06:00 A 0.00


H9080 Entrega de area - Planta concentradora 17-May-21 06:00 A 0.00
H4000 Main Plant Shutdown Line 1 - Julio 2021 15-Jul-21 07:00 A 20-Jul-21 1 5.90
H5000 Main Plant Shutdown Line 2 - Julio 2021 16-Jul-21 10:30 A 21-Jul-21 2 5.55
H9000 Main Plant Shutdown Line 1 - Febrero 2022 15-Feb-22 06:00* 20-Feb-22 6.00 Main Plant Shutdown Line 1 - Febrero 2022
H9010 Main Plant Shutdown Line 2 - Febrero 2022 18-Feb-22 06:00 23-Feb-22 6.00 Main Plant Shutdown Line 2 - Febrero 2022
H6000 Construction Completion Mill 06-Apr-22 0.00 Construction Completion Mill,
H7000 CO -Mechanical Completion 16-Apr-22 0.00 CO -Mechanical Completion,
H7500 C1 - Dry Commisioning 17-Apr-22 06:00 21-May-22 35.00 C1 - Dry Commisioning
H9050 Mechanical Completion 21-May-22 0.00 Mechanical Completion,
H1010 Fin de desmovilización 18-Jun-22 0.00 Fin de desmovilizació
22-May-22 06:00 18-Jun-22 28.00 18-Jun-22 17:00, De
Demobilization
H1630 Desmovilización de Personal y Equipos 22-May-22 06:00 18-Jun-22 28.00 Desmovilización de P
Procura MCC 06-Apr-21 06:00 A 19-Jun-21 75.00

H9060 Procura 06-Apr-21 06:00 A 19-Jun-21 75.00


Movilización de Personal
Person 07-May-21 06:00 A 08-Jun-21 33.00

A15800 Acuartelamiento y Traslado a Obra (Staff) 07-May-21 06:00 A 08-May-21 2.00


A16130 Inducción Anexo 5 (Staff) 09-May-21 06:00 A 12-May-21 4.00
A16340 Planificación de actividades 13-May-21 06:00 A 15-May-21 3.00
H5700 Inicio de actividades 16-May-21 06:00 A 0.00
Primera Guardia 10-May-21 06:00 A 15-May-21 6.00
A14680 Acuartelamiento y Traslado a Obra (Grupo 1) 10-May-21 06:00 A 11-May-21 2.00
A14690 Inducción Anexo 5 (Grupo 1) 12-May-21 06:00 A 15-May-21 4.00
Segunda Guardia 20-May-21 06:00 A 25-May-21 6.00
A14700 Acuartelamiento y Traslado a Obra (Grupo 2) 20-May-21 06:00 A 21-May-21 2.00
A14710 Inducción Anexo 5 (Grupo 2) 22-May-21 06:00 A 25-May-21 4.00
Tercera Guardia 03-Jun-21 06:00 A 08-Jun-21 6.00
A14720 Acuartelamiento y Traslado a Obra (Grupo 3) 03-Jun-21 06:00 A 04-Jun-21 2.00
A14730 Inducción Anexo 5 (Grupo 3) 05-Jun-21 06:00 A 08-Jun-21 4.00
Movilización de equipos 08-May-21 06:00 A 18-May-21 11.00
A15630 Movilización de camionetas y buses 08-May-21 06:00 A 11-May-21 4.00
A15620 Movilización de equipos mayores Para el Arranque 11-May-21 06:00 A 18-May-21 8.00
16-May-21 06:00 A 09-Feb-22 263.23 09-Feb-22 17:00, Facilidades y Recepción de materiales
Facilidades y Recepción
Recepció de materiales
A15640 Facilidades (Acondicionamiento de taller y oficinas) 16-May-21 06:00 A 12-Jun-21 28.00
A15650 Recepción estructuras y equipos 16-May-21 06:00 A 06-Jun-21 22.00
A15660 Recepción de Materiales Piping existentes 16-May-21 06:00 A 06-Jun-21 22.00
A15670 Recepción de Materiales E&I 16-May-21 06:00 A 06-Jun-21 22.00
A15680 Recepción de Andamios 16-May-21 06:00 A 29-May-21 14.00
A15720 Revisión de planos, identificación de materiales y conteo de andamios par 16-May-21 06:00 A 18-May-21 3.00
A15690 Preservacion de equipos de Estator en LB-01 26-May-21 06:00 A 11-Dec-21 112.16 Preservacion de equipos de Estator en LB-01
A15700 Preservacion de equipos de bombas Warman 26-May-21 06:00 A 09-Feb-22 253.23 Preservacion de equipos de bombas Warman
25-May-21 06:00 A 10-May-22 351.00 10-May-22 17:00, Construction
Construction
Shutdowns 15-Jul-21 07:00 A 22-Feb-22 222.90 22-Feb-22 17:00, Shutdowns
SD-1080 Main Plant Shutdown Line 1 - 102 MH 15-Jul-21 07:00 A 20-Jul-21 1 5.90
SD-1085 Main Plant Shutdown Line 2 - 102 MH 16-Jul-21 10:30 A 21-Jul-21 2 5.55
SD-2980 Shutdown November-2021 02-Nov-21 06:00* 0.00 Shutdown November-2021, 02-Nov-21 06:00*
SD-2960 Main Transition Shutdown Line 1 - Febrero 2022 15-Feb-22 06:00 19-Feb-22 5.00 Main Transition Shutdown Line 1 - Febrero 2022
SD-2970 Main Transition Shutdown Line 2 - Febrero 2022 18-Feb-22 06:00 22-Feb-22 5.00 Main Transition Shutdown Line 2 - Febrero 2022
3rd Ball Mill 25-May-21 06:00 A 10-May-22 351.00 10-May-22 17:00, 3rd Ball Mill
Civil 28-Aug-21 06:00 A 24-Feb-22 181.00 24-Feb-22 17:00, Civil
CX6380 Losa de Concreto entre Molino 2 y Bomba Warman 4 (Actividad ejecutada 28-Aug-21 06:00 A 28-Aug-21 1.00o 2 y Bomba Warman 4 (Actividad ejecutada por otra Contratista)
CX9060 Demolicion de losa en 2do Nivel para Instalacion de rieles 20-Oct-21 06:00 A 28-Oct-21 7.00 Demolicion de losa en 2do Nivel para Instalacion de rieles
CX6390 Pedestales - 2do nivel de la plataforma de molienda 02-Feb-22 06:00 05-Feb-22 4.00 Pedestales - 2do nivel de la plataforma de molienda
CX6360 Losas de mantenimiento entre Ejes 10-11 y C-D (inc. excavacion) 06-Feb-22 06:00 20-Feb-22 15.00 Losas de mantenimiento entre Ejes 10-11 y C-D (inc. excavacion)

Actual Level of Effort Actual Work Critical Remaining Work Page 1 of 20 TASK filter: All Activities
Primary Baseline Remaining Work Milestone © Oracle Corporation
Cronograma del Proyecto: Construccion e Instalacion del 3er Molino de Bolas y Obras Asociadas
Linea Base 1 Rev. 0 (actualizado al 22-octubre)
Activity ID Activity Name Start Finish Original October 2021 November 2021 December 2021 January 2022 February 2022 March 2022 April 2022 May 2022 June 2022 July 2022
Duration
09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 05 12 19 26 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 02 09 6
CX6370 Relleno en el perimetro de la losa de mantenimiento 18-Feb-22 06:00 24-Feb-22 7.00 Relleno en el perimetro de la losa de mantenimiento
Concrete - Plataforma de
d operaciones 3er Molino 17-Nov-21 06:00 17-Feb-22 93.00 17-Feb-22 17:00, Concrete - Plataforma de operaciones 3er Molino
CX9030 Losa colaborante (parte de carga del molino) 17-Nov-21 06:00 29-Nov-21 13.00 Losa colaborante (parte de carga del molino)
CX9040 Losa colaborante (parte de decarga del molino) 30-Nov-21 06:00 14-Dec-21 15.00 Losa colaborante (parte de decarga del molino)
CX1840 Colocación de acero de refuerzo 15-Jan-22 06:00 24-Jan-22 10.00 Colocación de acero de refuerzo
CX1850 Colocación de juntas de cubierta metálica 25-Jan-22 06:00 27-Jan-22 3.00 Colocación de juntas de cubierta metálica
CX2880 Instalación de microclima 28-Jan-22 06:00 29-Jan-22 2.00 Instalación de microclima
CX9050 Losa colaborante (para el sistema de lubricacion de los frenos) 29-Jan-22 06:00 17-Feb-22 20.00 Losa colaborante (para el sistema de lubricacion de los frenos)
CX1520 Colocación de concreto losa colaborante ejes 9 - 9.5 con ejes C-D 30-Jan-22 06:00 01-Feb-22 3.00 Colocación de concreto losa colaborante ejes 9 - 9.5 con ejes C-D
Estructuras 25-May-21 06:00 A 09-Feb-22 261.00 09-Feb-22 17:00, Estructuras
H9012 LLegada de Supervisor de estructuras a Obra (Icluye anexo 5) 20-Sep-21 00:00 A 0.00 Supervisor de estructuras a Obra (Icluye anexo 5), 20-Sep-21 00:00 A
SX6357 Desmontaje de estructuras (eje 10D cuarto nivel) 05-Jan-22 06:00 08-Jan-22 4.00 Desmontaje de estructuras (eje 10D cuarto nivel)
SX6370 Montaje de pasarela 4to nivel (Eje 10 a 11) 09-Jan-22 06:00 14-Jan-22 6.00 Montaje de pasarela 4to nivel (Eje 10 a 11)
Estructuras lado carga del 3er molino 02-Oct-21 06:00 A 16-Nov-21 9.00 16-Nov-21 17:00, Estructuras lado carga del 3er molino
SX6360 Montaje de refuerzo para el chute de alimentación del 3er molino de bolas 02-Oct-21 06:00 A 05-Nov-21 5.00 Montaje de refuerzo para el chute de alimentación del 3er molino de bolas.
SX6400 Rieles para el chute 0310-STP-0102 02-Oct-21 06:00 A 16-Nov-21 4.00 Rieles para el chute 0310-STP-0102
Estructura Plataforma de
d Operaciones 3er Molino 02-Oct-21 06:00 A 09-Feb-22 98.00 09-Feb-22 17:00, Estructura Plataforma de Operaciones 3er Molino
SX7500 Ensamble e Instalación de vigas de amarre ejes 8-7.5 con ejes C1 - D1 (la 02-Oct-21 06:00 A 16-Nov-21 8.00 Ensamble e Instalación de vigas de amarre ejes 8-7.5 con ejes C1 - D1 (lado de carga del molino)
SX7460 Plataforma superior y voladizo de la torre para acceso a Estator 04-Nov-21 06:00 08-Nov-21 5.00 Plataforma superior y voladizo de la torre para acceso a Estator
SX7480 Ensamble e Instalación de Armaduras ejes C2 - D1 09-Jan-22 06:00 13-Jan-22 5.00 Ensamble e Instalación de Armaduras ejes C2 - D1
SX7490 Ensamble e Instalación de vigas de amarre ejes 9-9.5 con ejes C1 - D1 09-Jan-22 06:00 14-Jan-22 6.00 Ensamble e Instalación de vigas de amarre ejes 9-9.5 con ejes C1 - D1
SX7470 Ensamble e Instalación de Armadura y Grating ejes C1 - C2 14-Jan-22 06:00 18-Jan-22 5.00 Ensamble e Instalación de Armadura y Grating ejes C1 - C2
SX7520 Montaje de estructuras sobre la plataforma de operaciones 03-Feb-22 06:00 09-Feb-22 7.00 Montaje de estructuras sobre la plataforma de operaciones
Estructura a la Salida d
del 3er Molino 25-May-21 06:00 A 26-Nov-21 186.00 26-Nov-21 17:00, Estructura a la Salida del 3er Molino
SX7390 Desmontaje de andamios 25-May-21 06:00 A 06-Jun-21 13.00
SX7510 Montaje de estructura en la descarga del MB3 - Entre Columnas existente 29-May-21 06:00 A 16-Nov-21 149.00 Montaje de estructura en la descarga del MB3 - Entre Columnas existentes
SX7530 Acceso al Chute de rechazo de bolas 0310-STP-0106 17-Nov-21 06:00 26-Nov-21 10.00 Acceso al Chute de rechazo de bolas 0310-STP-0106
Instalación del 3er Molino de Bolas 0.00
3BM Mill Mechanical Insta
Installation 06-Jun-21 06:00 A 21-Feb-22 261.00 21-Feb-22 17:00, 3BM Mill Mechanical Installation
MX9220 Montaje de andamios 19-Jun-21 06:00 A 23-Jul-21 1 35.00
Mill - Sole Plates y Base
Bas 06-Jun-21 06:00 A 23-Jul-21 1 48.00
Sole Plate y Base 06-Jun-21 06:00 A 17-Jul-21 1 42.00
MX9230 Desmontaje de Bearing housing (lado carga y descarga) 06-Jun-21 06:00 A 19-Jun-21 14.00
MX9700 Desmontaje de Sole plate (lado carga y descarga) 12-Jun-21 06:00 A 13-Jun-21 2.00
MX9240 Limpieza de Sole Plates (Lado Carga y descarga) 14-Jun-21 06:00 A 17-Jun-21 4.00
MX9250 Instalación planchas de nivelación y Sole Plates 16-Jun-21 06:00 A 15-Jul-21 1 30.00
MX9260 Montaje y Alineamiento de pernos de anclaje 16-Jun-21 06:00 A 17-Jul-21 1 32.00
H9270 Llegada de Grout Epoxico a Obra 16-Jul-21 00:00 A 0.00
Montaje de Bearing 06-Jun-21 06:00 A 23-Jul-21 1 48.00
MX9320 Colocación y ajuste de pernos - Lado Descarga 06-Jun-21 06:00 A 17-Jul-21 1 42.00
MX9290 Colocación y ajuste de pernos - Lado Carga 16-Jul-21 06:00 A 16-Jul-21 1 1.00
CX8990 Vaciado de Grout Epoxico - Lado Carga (inc encofrado,microclima, vaciado 16-Jul-21 06:00 A 16-Jul-21 1 1.00a, vaciado y desencofrado)
CX8980 Vaciado de Grout Epoxico - Lado Descarga (inc encofrado,microclima, vac 19-Jul-21 06:00 A 19-Jul-21 1 1.00 oclima, vaciado y desencofrado)
MX9270 Montaje Bearing housing lado carga 23-Jul-21 06:00 A 23-Jul-21 1 1.00
MX9280 Alineamiento y nivelación de Bearing Housing Carga 23-Jul-21 06:00 A 23-Jul-21 1 1.00
MX9300 Montaje Bearing housing lado descarga 23-Jul-21 06:00 A 23-Jul-21 1 1.00
MX9310 Alineamiento y nivelación de Bearing Housing Descarga 23-Jul-21 06:00 A 23-Jul-21 1 1.00
Mill - Shell x 3 14-Jun-21 06:00 A 20-Aug-21 68.00
MX9340 Izaje y posicionamiento de Shell - Sección Central (Grua de 500 Ton) 14-Jun-21 06:00 A 14-Jun-21 1.00
MX9710 Alineamiento y nivelacion de cuna de elevación 24-Jul-21 06:00 A 30-Jul-21 1 7.00
H9280 Llegada equipos Hidraulicos para gatas ( Ya están en sitio) 28-Jul-21 00:00 A 0.00 io), 28-Jul-21 00:00 A
MX9330 Instalación de Gatas hidraulicas 28-Jul-21 06:00 A 29-Jul-21 1 2.00
H9310 Recepción de Pernos para montaje de Shells 30-Jul-21 0 0.00
H9290 Rigging plan Aprobados 30-Jul-21 17:00 A 0.00
MX9350 Montaje de Shell - Sección Central 01-Aug-21 06:00 A 01-Aug-21 1.00
MX9360 Verificación de ejes del Shell con el eje de operación 01-Aug-21 06:00 A 01-Aug-21 1.00
MX9370 Colocación de arriostres - Fijación del Shell 01-Aug-21 06:00 A 02-Aug-21 2.00
MX9380 Montaje de Shell - Sección Descarga 11-Aug-21 06:00 A 15-Aug-21 5.00
MX9390 Colocación de arriostres - Fijación del Shell 11-Aug-21 06:00 A 15-Aug-21 5.00ell
MX9400 Colocación y ajuste de pernos (25%) entre Shell Medio - Shell Descarga 11-Aug-21 06:00 A 15-Aug-21 5.00 e Shell Medio - Shell Descarga
MX9410 Montaje de Shell - Sección Carga 15-Aug-21 06:00 A 20-Aug-21 6.00
MX9420 Preparación y colocación de arriostres - Fijación del Shell 15-Aug-21 06:00 A 20-Aug-21 6.00s - Fijación del Shell
MX9430 Colocación y ajuste de pernos (25%) entre Shell Central - Shell Carga 15-Aug-21 06:00 A 20-Aug-21 6.00 entre Shell Central - Shell Carga

Actual Level of Effort Actual Work Critical Remaining Work Page 2 of 20 TASK filter: All Activities
Primary Baseline Remaining Work Milestone © Oracle Corporation
Cronograma del Proyecto: Construccion e Instalacion del 3er Molino de Bolas y Obras Asociadas
Linea Base 1 Rev. 0 (actualizado al 22-octubre)
Activity ID Activity Name Start Finish Original October 2021 November 2021 December 2021 January 2022 February 2022 March 2022 April 2022 May 2022 June 2022 July 2022
Duration
09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 05 12 19 26 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 02 09 6
Mill - Tapas de Molino 2x180
2 18-Aug-21 06:00 A 15-Sep-21 31.00 0 A, Mill - Tapas de Molino 2x180
MX9480 Traslado de Tapas a zona de Izaje - Lado Carga 18-Aug-21 06:00 A 28-Aug-21 11.00zaje - Lado Carga
MX9490 Armado de segmentos de tapa - Lado Carga 20-Aug-21 00:00 A 06-Sep-21 16.00 de tapa - Lado Carga
MX9440 Traslado de Tapas a zona de Izaje - Lado Descarga 21-Aug-21 06:00 A 21-Aug-21 1.00 Lado Descarga
H9330 Prestamo de Grua de 220 Ton para traslado de tapas 21-Aug-21 06:00 A 0.00 raslado de tapas, 21-Aug-21 06:00 A
MX9450 Armado de segmentos de tapa - Lado Descarga 22-Aug-21 06:00 A 06-Sep-21 18.00 s de tapa - Lado Descarga
H9300 Rigging plan para montaje de tapas Aprobado 26-Aug-21 0.00 pas Aprobado,
H9014 Llegada de Orejas para izaje de tapas 01-Sep-21 0.00 e de tapas,
MX9460 Izaje y montaje de tapa - Lado Carga 07-Sep-21 06:00 A 08-Sep-21 1.00 pa - Lado Carga
MX9470 Colocación y Ajuste de Pernos de la Platina Circunferencial - Shell y Tapa 07-Sep-21 06:00 A 11-Sep-21 3.00 e de Pernos de la Platina Circunferencial - Shell y Tapa lado Carga (33%)
H9004 Puente grua 80 Ton habilitado 07-Sep-21 06:00 A 0.00 bilitado, 07-Sep-21 06:00 A
MX9500 Izaje y montaje de tapa - Lado Descarga 08-Sep-21 06:00 A 08-Sep-21 1.00e tapa - Lado Descarga
MX9510 Colocación y Ajuste de Pernos de la Platina Circunferencial - Shell y Tapa 08-Sep-21 06:00 A 15-Sep-21 3.00 uste de Pernos de la Platina Circunferencial - Shell y Tapa Lado Descarga (33%)
MX9760 Torqueo de pernos Shell y Tapa lado Carga(66%) 11-Sep-21 06:00 A 12-Sep-21 2.00 nos Shell y Tapa lado Carga(66%)
MX9770 Torqueo de pernos Shell y Tapa lado Descarga (66%) 14-Sep-21 06:00 A 15-Sep-21 2.00 pernos Shell y Tapa lado Descarga (66%)
Mill - Trunnion 28-Aug-21 00:00 A 16-Oct-21 44.00 16-Oct-21 17:00 A, Mill - Trunnion
MX9590 Lift Pad (Preparación y montaje en Bearing) 28-Aug-21 00:00 A 16-Oct-21 15.00 Lift Pad (Preparación y montaje en Bearing)
MX9520 Traslado de Trunnion Carga a zona de Izaje 12-Sep-21 06:00 A 12-Sep-21 1.00 nion Carga a zona de Izaje
MX9550 Traslado de Trunnion Descarga a zona de Izaje 12-Sep-21 06:00 A 12-Sep-21 1.00 e Trunnion Descarga a zona de Izaje
H9005 Liftting plan para montaje de Trunnion 13-Sep-21 06:00 A 0.00montaje de Trunnion, 13-Sep-21 06:00 A
H9006 Aparejos de izaje en campo para montaje de Trunnion 14-Sep-21 06:00 A 0.00 en campo para montaje de Trunnion, 14-Sep-21 06:00 A
MX9560 Montaje de Trunnion Descarga 16-Sep-21 06:00 A 17-Sep-21 1.00 de Trunnion Descarga
MX9570 Ajuste de Pernos Lado Descarga 17-Sep-21 06:00 A 26-Sep-21 2.00 de Pernos Lado Descarga
H16600 Adecuacion del puente grua 80 ton (cambio de ganchos) por kone crane 03-Oct-21 0.00Adecuacion del puente grua 80 ton (cambio de ganchos) por kone crane,
MX9530 Montaje de Trunnion Lado Carga 04-Oct-21 06:00 A 04-Oct-21 2.00Montaje de Trunnion Lado Carga
MX9540 Ajuste de Pernos Lado Carga 05-Oct-21 06:00 A 06-Oct-21 4.00 Ajuste de Pernos Lado Carga
MX9580 Torque de pernos críticos del 33% al 67% ( Shell , Tapas y Trunion) 07-Oct-21 06:00 A 16-Oct-21 2.00 Torque de pernos críticos del 33% al 67% ( Shell , Tapas y Trunion)
Sistema de Lubricación temporal 04-Aug-21 06:00 A 19-Oct-21 73.00 19-Oct-21 17:00 A, Sistema de Lubricación temporal
MX9650 Instalación de Sistema de lubricación temporal ( Lado Carga) 04-Aug-21 06:00 A 16-Oct-21 46.00 Instalación de Sistema de lubricación temporal ( Lado Carga)
MX9660 Instalación de Sistema de lubricación temporal ( Lado Descarga) 04-Aug-21 06:00 A 19-Oct-21 50.00 Instalación de Sistema de lubricación temporal ( Lado Descarga)
H9007 Llegada de Fitting para sistema de lubricación 09-Oct-21 06:00 A 0.00 Llegada de Fitting para sistema de lubricación, 09-Oct-21 06:00 A
Mill - Montaje sobre Bearing
Be 14-Oct-21 06:00 A 30-Oct-21 13.00 30-Oct-21 17:00, Mill - Montaje sobre Bearing
MX9790 Recirculacción de Sistema de lubricación temporal (Presencia de Vendor) 14-Oct-21 06:00 A 19-Oct-21 3.00 Recirculacción de Sistema de lubricación temporal (Presencia de Vendor)
MX9820 Instalación de Orejas para retenida de molino 17-Oct-21 06:00 A 22-Oct-21 3.00 Instalación de Orejas para retenida de molino
MX9600 Posicionamiento molino sobre bearings 20-Oct-21 06:00 A 22-Oct-21 3.00 Posicionamiento molino sobre bearings
MX9800 Alineamiento en frio (no ejecutado) 22-Oct-21 06:00 A 22-Oct-21 4.00 Alineamiento en frio (no ejecutado)
MX10380 Regulación de lift pad (Contacto de trunion con lift pad) lado carga y desca 23-Oct-21 06:00 25-Oct-21 3.00 Regulación de lift pad (Contacto de trunion con lift pad) lado carga y descarga
MX10390 Liberación de gatas de 1000tn 24-Oct-21 06:00 25-Oct-21 2.00 Liberación de gatas de 1000tn
MX9610 Colocar Tapas de Berings 25-Oct-21 06:00 26-Oct-21 2.00 Colocar Tapas de Berings
MX9620 Retiro de Cunas de elevación 27-Oct-21 06:00 30-Oct-21 4.00 Retiro de Cunas de elevación
MX10410 Instalación de Trusth Pack (lado carga) 29-Oct-21 06:00 30-Oct-21 2.00 Instalación de Trusth Pack (lado carga)
Mill - Instalacion de frenos
fren 28-Jun-21 06:00 A 21-Feb-22 239.00 21-Feb-22 17:00, Mill - Instalacion de frenos
MX9720 Montaje de sole plate de freno (Lado izquierdo y Derecho de la descarga) 28-Jun-21 06:00 A 08-Oct-21 82.00 Montaje de sole plate de freno (Lado izquierdo y Derecho de la descarga)
CX9000 Vaciado de Grout en Sole Plate (Lado izquierdo y Derecho), inc encofrado 25-Jul-21 06:00 A 28-Jan-22 59.00 Vaciado de Grout en Sole Plate (Lado izquierdo y Derecho), inc encofrado,microclima, vaciado y desencofrado
CX9020 Vaciado de Grout de bloques de nivelacion, inc. encofrado,microclima, vac 30-Sep-21 00:00 A 05-Oct-21 5.00 Vaciado de Grout de bloques de nivelacion, inc. encofrado,microclima, vaciado y desencofrado
MX9730 Alineamiento de Sole Plate (Lado izquierdo y derecho) 08-Oct-21 06:00 A 10-Oct-21 2.00 Alineamiento de Sole Plate (Lado izquierdo y derecho)
H16620 Llegada de Vendor para el montaje de los frenos (por MMG/Ausenco) 21-Nov-21 0.00 Llegada de Vendor para el montaje de los frenos (por MMG/Ausenco),
MX10610 Inspección y verificación de frenos con presencia de Vendor 22-Nov-21 06:00 22-Nov-21 1.00 Inspección y verificación de frenos con presencia de Vendor
MX9670 Montaje de frenos 23-Nov-21 06:00 23-Nov-21 1.00 Montaje de frenos
MX9680 Alineamiento de frenos 23-Nov-21 06:00 24-Nov-21 2.00 Alineamiento de frenos
MX9690 Ajuste y pre calibracion 25-Nov-21 06:00 25-Nov-21 1.00 Ajuste y pre calibracion
MX8940 Sistema de lubricacion de los frenos (310-R-106) 18-Feb-22 06:00 21-Feb-22 4.00 Sistema de lubricacion de los frenos (310-R-106)
Mill - Otras Actividades 25-Oct-21 06:00 24-Nov-21 31.00 24-Nov-21 17:00, Mill - Otras Actividades
MX9110 Alineamiento del Molino (con presion de aceite) 25-Oct-21 06:00 28-Oct-21 4.00 Alineamiento del Molino (con presion de aceite)
H16710 Presentacion de Plan y Memoria de Calculo para el giro del molino con tirf 25-Oct-21 0.00 Presentacion de Plan y Memoria de Calculo para el giro del molino con tirfor,
MX9100 Retiro de refuerzos del shell 31-Oct-21 06:00 05-Nov-21 6.00 Retiro de refuerzos del shell
MX10650 Retiro de perno engarrotado e intalacion de nuevos pernos 06-Nov-21 06:00 10-Nov-21 5.00 Retiro de perno engarrotado e intalacion de nuevos pernos
H16720 Arribo a obra de tirfors y accesorios para el giro del molino 08-Nov-21 0.00 Arribo a obra de tirfors y accesorios para el giro del molino,
MX10560 Instalacion de tirfors para el giro del molino 09-Nov-21 06:00 10-Nov-21 2.00 Instalacion de tirfors para el giro del molino
MX9120 Giro del molino (con tirfor) 11-Nov-21 06:00 12-Nov-21 2.00 Giro del molino (con tirfor)
MX9130 Torque de pernos criticos al 100% 13-Nov-21 06:00 18-Nov-21 6.00 Torque de pernos criticos al 100%
MX10630 Run Out 19-Nov-21 06:00 21-Nov-21 3.00 Run Out
MX10570 Sellado de juntas en Shell y tapas con silicona 22-Nov-21 06:00 23-Nov-21 2.00 Sellado de juntas en Shell y tapas con silicona

Actual Level of Effort Actual Work Critical Remaining Work Page 3 of 20 TASK filter: All Activities
Primary Baseline Remaining Work Milestone © Oracle Corporation
Cronograma del Proyecto: Construccion e Instalacion del 3er Molino de Bolas y Obras Asociadas
Linea Base 1 Rev. 0 (actualizado al 22-octubre)
Activity ID Activity Name Start Finish Original October 2021 November 2021 December 2021 January 2022 February 2022 March 2022 April 2022 May 2022 June 2022 July 2022
Duration
09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 05 12 19 26 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 02 09 6
MX10580 Aplicación de sikadur 52 en las tapas 23-Nov-21 06:00 24-Nov-21 2.00 Aplicación de sikadur 52 en las tapas
Mill - Engomamieno del Molino 20-Nov-21 06:00 01-Dec-21 12.00 01-Dec-21 17:00, Mill - Engomamieno del Molino
H16590 Llegada de SC engomado 20-Nov-21 0.00 Llegada de SC engomado,
MX9140 Engomado localizado 25-Nov-21 06:00 28-Nov-21 4.00 Engomado localizado
MX9150 Engomado trunnion 29-Nov-21 06:00 01-Dec-21 3.00 Engomado trunnion
Mill - Instalación de liners
line 13-Nov-21 06:00 23-Dec-21 41.00 23-Dec-21 17:00, Mill - Instalación de liners
MX9830 Verificacion y control de calidad de liner a instalar 13-Nov-21 06:00 03-Dec-21 21.00 Verificacion y control de calidad de liner a instalar
MX10590 Trazo y perforaciones para el anclaje del winche y poleas 13-Nov-21 06:00 17-Nov-21 5.00 Trazo y perforaciones para el anclaje del winche y poleas
H16730 Llegada a obra de montacarga y plataforma para traslado de liner 13-Nov-21 0.00 Llegada a obra de montacarga y plataforma para traslado de liner,
MX8980 Traslado de liners 14-Nov-21 06:00 28-Nov-21 15.00 Traslado de liners
MX9090 Instalación de frame para montaje de Winche 18-Nov-21 06:00 21-Nov-21 4.00 Instalación de frame para montaje de Winche
H16640 Finalizacion de trabajos previos (estructuras y civil lado de carga del molino 29-Nov-21 0.00 Finalizacion de trabajos previos (estructuras y civil lado de carga del molino),
H16610 Llegada de winches de 20 ton a obra 30-Nov-21 06:00* 0.00 Llegada de winches de 20 ton a obra, 30-Nov-21 06:00*
MX9810 Instalacion y pruebas de winche de 20 ton de giro y retencion 30-Nov-21 06:00 07-Dec-21 8.00 Instalacion y pruebas de winche de 20 ton de giro y retencion
H16630 Llegada de sub contratista para Liner 03-Dec-21 0.00 Llegada de sub contratista para Liner,
MX8990 Instalacion de liners Shell 3-2-1 07-Dec-21 18:00 13-Dec-21 6.00 Instalacion de liners Shell 3-2-1
MX9000 Instalacion de liners -Tapa Carga 12-Dec-21 06:00 14-Dec-21 3.00 Instalacion de liners -Tapa Carga
MX9010 Instalacion de liners -Tapa Descarga 15-Dec-21 06:00 17-Dec-21 3.00 Instalacion de liners -Tapa Descarga
MX9160 Torqueo de Liner de shell y tapas 15-Dec-21 06:00 21-Dec-21 6.00 Torqueo de Liner de shell y tapas
MX10540 Instalacion de trunnion liners carga y descarga 21-Dec-21 06:00 23-Dec-21 3.00 Instalacion de trunnion liners carga y descarga
Mill - Trunnion Magnetico
Magnetic y Chute de Descarga 17-Nov-21 06:00 07-Jan-22 52.00 07-Jan-22 17:00, Mill - Trunnion Magnetico y Chute de Descarga
MX10640 Montaje chute 0310-LAL-070 17-Nov-21 06:00 20-Nov-21 4.00 Montaje chute 0310-LAL-070
MX9170 Montaje chute de descarga 0310-STP-105 y 0310-STP-104 21-Dec-21 06:00 24-Dec-21 4.00 Montaje chute de descarga 0310-STP-105 y 0310-STP-104
MX9180 Montaje de magneto segmento inferior 25-Dec-21 06:00 25-Dec-21 1.00 Montaje de magneto segmento inferior
MX9190 Montaje de cilindro trunnion magneto 26-Dec-21 06:00 27-Dec-21 2.00 Montaje de cilindro trunnion magneto
MX9200 Montaje de magneto segmento lateral superior 28-Dec-21 06:00 28-Dec-21 1.00 Montaje de magneto segmento lateral superior
MX9210 Alineamiento y torque 28-Dec-21 06:00 30-Dec-21 3.00 Alineamiento y torque
MX6360 Montaje de chute de alimentacion 0310-STP-0102 31-Dec-21 06:00 03-Jan-22 4.00 Montaje de chute de alimentacion 0310-STP-0102
MX6370 Montaje de chute de rechaso de bolas 0310-STP-0106 04-Jan-22 06:00 07-Jan-22 4.00 Montaje de chute de rechaso de bolas 0310-STP-0106
3BM Electrical e Intrumen
Intrumentation Installation (Estator) 23-Oct-21 06:00 06-Apr-22 166.00 06-Apr-22 17:00, 3BM Electrical e Intrumentation Installation (Estator)
Estator - Placa base del
de estator 19-Nov-21 06:00 01-Apr-22 134.00 01-Apr-22 17:00, Estator - Placa base del estator
MX-0500-7693 Retiro de soleplate y pernos del estator (ambos lados) 19-Nov-21 06:00 19-Nov-21 1.00 Retiro de soleplate y pernos del estator (ambos lados)
MX-0500-7703 Limpieza de soleplate del estator (ambos lados) 20-Nov-21 06:00 22-Nov-21 3.00 Limpieza de soleplate del estator (ambos lados)
MX-0500-7713 Instalacion de pernos para el soleplate del estator (ambos lados) 23-Nov-21 06:00 24-Nov-21 2.00 Instalacion de pernos para el soleplate del estator (ambos lados)
MX-0500-7683 Instalación de Placa base de estator 25-Nov-21 06:00 27-Nov-21 3.00 Instalación de Placa base de estator
MX-0500-7673 Alineamiento y nivelación de las Placas Base del Estator 27-Nov-21 06:00 28-Nov-21 2.00 Alineamiento y nivelación de las Placas Base del Estator
CX-0500-3510 Vaciado de grout en placa Base (inc encofrado,microclima, vaciado y dese 28-Mar-22 06:00 01-Apr-22 5.00 Vaciado de grout en placa Base (inc encofrado,microclima, vaciado y desencofrado)
Estator - Roller Track 13-Nov-21 06:00 22-Dec-21 40.00 22-Dec-21 17:00, Estator - Roller Track
MX9630 Izaje y limpieza de Roller Track 13-Nov-21 06:00* 15-Nov-21 3.00 Izaje y limpieza de Roller Track
MX10620 Instalación de Placa base de Roler Track 10-Dec-21 06:00 11-Dec-21 2.00 Instalación de Placa base de Roler Track
MX9011 Instalación y alineamiento final de Roler Track 12-Dec-21 06:00 15-Dec-21 4.00 Instalación y alineamiento final de Roler Track
MX9640 Vaciado de Grout en roller track (Lado izquierdo y Derecho), inc encofrado, 16-Dec-21 06:00 22-Dec-21 7.00 Vaciado de Grout en roller track (Lado izquierdo y Derecho), inc encofrado,microclima, va
Estator - Trabajos preliminares
prelim 23-Oct-21 06:00 19-Dec-21 58.00 19-Dec-21 17:00, Estator - Trabajos preliminares
H9002 Coordinaciones con el vendor en sitio 23-Oct-21 06:00* 0.00 Coordinaciones con el vendor en sitio, 23-Oct-21 06:00*
MX8332 Limpieza mecanica del estator (trabajos previos) 12-Dec-21 06:00 15-Dec-21 4.00 Limpieza mecanica del estator (trabajos previos)
MX8342 Megado del estator (trabajos previos) 16-Dec-21 06:00 16-Dec-21 1.00 Megado del estator (trabajos previos)
Traslado de Estatore
Estatores S1 y S3 29-Nov-21 06:00 11-Dec-21 13.00 11-Dec-21 17:00, Trasla do de Estatores S1 y S3
MX8352 Instalación de galpones de preservación de equipos 29-Nov-21 06:00 06-Dec-21 8.00 Instalación de galpones de preservación de equipos
H16690 Llegada de grua de 300 tn al proyecto 01-Dec-21 0.00 Llegada de grua de 300 tn al proyecto,
MX10550 Traslado de grua 300 ton y sus partes al LB1 02-Dec-21 06:00 03-Dec-21 2.00 Traslado de grua 300 ton y sus partes al LB1
MX10480 Posicionamiento de la grua de 300 tn en LB1 para S2 y S4 04-Dec-21 06:00 04-Dec-21 1.00 Posicionamiento de la grua de 300 tn en LB1 para S2 y S4
MX10130 Movimiento de estatores (S2, S4) 05-Dec-21 06:00 05-Dec-21 1.00 Movimiento de estatores (S2, S4)
MX10140 Instalacion de tacos y Vigas para S2 y S4 06-Dec-21 06:00 06-Dec-21 1.00 Instalacion de tacos y Vigas para S2 y S4
MX10160 Posicionar Estatores S2, S4 a nivel requerido. 07-Dec-21 06:00 07-Dec-21 0.50 Posicionar Estatores S2, S4 a nivel requerido.
MX10420 Termino de techo galpones para S2, S4 07-Dec-21 11:00 07-Dec-21 0.50 Termino de techo galpones para S2, S4
MX10510 Traslado para posicionamiento de la grua de 300 tn en LB1 para S1 y S3 08-Dec-21 06:00 08-Dec-21 1.00 Traslado para posicionamiento de la grua de 300 tn en LB1 para S1 y S3
MX10490 Movimiento de estatores (S1, S3) 09-Dec-21 06:00 09-Dec-21 1.00 Movimiento de estatores (S1, S3)
MX10520 Instalacion de tacos y Vigas para S1 y S3 10-Dec-21 06:00 10-Dec-21 1.00 Instalacion de tacos y Vigas para S1 y S3
MX10150 Posicionar Estatores S1, S3 a nivel requerido. 11-Dec-21 06:00 11-Dec-21 0.50 Posicionar Estatores S1, S3 a nivel requerido.
MX10370 Termino de techo Galpones para S1, S3 11-Dec-21 11:00 11-Dec-21 0.50 Termino de techo Galpones para S1, S3
Trabajos Previos en estatores 10-Dec-21 06:00 19-Dec-21 10.00 19-Dec-21 17:00, Trabajos Previos en estatores
H16670 Llegada de SIEMENS al proyecto 10-Dec-21 06:00* 0.00 Llegada de SIEMENS al proyecto, 10-Dec-21 06:00*
MX10170 Desenvalaje y/o apertura de estator S1, S2, S3 y S4 12-Dec-21 06:00 13-Dec-21 2.00 Desenvalaje y/o apertura de estator S1, S2, S3 y S4

Actual Level of Effort Actual Work Critical Remaining Work Page 4 of 20 TASK filter: All Activities
Primary Baseline Remaining Work Milestone © Oracle Corporation
Cronograma del Proyecto: Construccion e Instalacion del 3er Molino de Bolas y Obras Asociadas
Linea Base 1 Rev. 0 (actualizado al 22-octubre)
Activity ID Activity Name Start Finish Original October 2021 November 2021 December 2021 January 2022 February 2022 March 2022 April 2022 May 2022 June 2022 July 2022
Duration
09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 05 12 19 26 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 02 09 6
S1 y S2 14-Dec-21 06:00 19-Dec-21 6.00 19-Dec-21 17:00, S1 y S2
MX10180 Limpieza mecánica del segmento inferior S1 y S2 14-Dec-21 06:00 15-Dec-21 2.00 Limpieza mecánica del segmento inferior S1 y S2
MX10200 Megado de estator segmento inferior S1 y S2 16-Dec-21 06:00 16-Dec-21 1.00 Megado de estator segmento inferior S1 y S2
MX10230 Instalacion interna del sistema de enfriamiento en el segemento S1 y S2 d 17-Dec-21 06:00 19-Dec-21 3.00 Instalacion interna del sistema de enfriamiento en el segemento S1 y S2 del Estator
S3 y S4 14-Dec-21 06:00 19-Dec-21 6.00 19-Dec-21 17:00, S3 y S4
MX10190 Limpieza mecánica del segmento superior S3 y S4 14-Dec-21 06:00 15-Dec-21 2.00 Limpieza mecánica del segmento superior S3 y S4
MX10240 Megado de estator segmento superior S3 y S4 16-Dec-21 06:00 16-Dec-21 1.00 Megado de estator segmento superior S3 y S4
MX10270 Instalacion interna del sistema de enfriamiento en el segemento S3 y S4 d 17-Dec-21 06:00 19-Dec-21 3.00 Instalacion interna del sistema de enfriamiento en el segemento S3 y S4 del Estator
Estator - Montaje del Estator
Es 19-Dec-21 06:00 04-Jan-22 17.00 04-Jan-22 17:00, Estator - Montaje del Estator
MX10530 Traslado de grúa de 300tn de LB1 a Molino 19-Dec-21 06:00 20-Dec-21 1.00 Traslado de grúa de 300tn de LB1 a Molino
MX10430 Posicionamiento de grúa de 300tn en Molino 20-Dec-21 06:00 20-Dec-21 1.00 Posicionamiento de grúa de 300tn en Molino
H16700 Llegada camion modular de 90ton 23-Dec-21 0.00 Llegada camion modular de 90ton,
MX8970 Traslado de Estator a zona de Izaje -S1 Inferior Eje 8D 24-Dec-21 06:00 24-Dec-21 0.50 Traslado de Estator a zona de Izaje -S1 Inferior Eje 8D
MX10440 Descarga de segmento inferior S1 Inferior Eje 8D 24-Dec-21 11:00 24-Dec-21 0.25 Descarga de segmento inferior S1 Inferior Eje 8D
MX-0500-7573 Volteo y Montaje de Segmento 1 del estator inferior Eje 8D 24-Dec-21 14:30 24-Dec-21 0.25 Volteo y Montaje de Segmento 1 del estator inferior Eje 8D
MX-0500-7723 Montaje y alineamiento de segmento inferior S1 Eje 8D 25-Dec-21 06:00 25-Dec-21 1.00 Montaje y alineamiento de segmento inferior S1 Eje 8D
MX-0500-7633 Traslado de Estator a zona de Izaje -S2 Inferior Eje 9D 26-Dec-21 06:00 26-Dec-21 0.50 Traslado de Estator a zona de Izaje -S2 Inferior Eje 9D
MX10450 Descarga de segmento inferior S2 Inferior Eje 9D 26-Dec-21 11:00 26-Dec-21 0.25 Descarga de segmento inferior S2 Inferior Eje 9D
MX-0500-7583 Volteo y Montaje de Segmento 2 del estator inferior Eje 9D 26-Dec-21 14:30 26-Dec-21 0.25 Volteo y Montaje de Segmento 2 del estator inferior Eje 9D
MX-0500-7733 Montaje y alineamiento de segmento inferior S2 Inferior Eje 9D 27-Dec-21 06:00 27-Dec-21 1.00 Montaje y alineamiento de segmento inferior S2 Inferior Eje 9D
MX-0500-7593 Instalacion de gatas hidraulicas de 100 ton 28-Dec-21 06:00 28-Dec-21 1.00 Instalacion de gatas hidraulicas de 100 ton
MX-0500-7643 Instalación de soporte para la parte superior del estator 28-Dec-21 06:00 28-Dec-21 1.00 Instalación de soporte para la parte superior del estator
MX-0500-7653 Traslado de Estator a zona de Izaje - S3 Superior Eje 8D 29-Dec-21 06:00 29-Dec-21 0.50 Traslado de Estator a zona de Izaje - S3 Superior Eje 8D
MX10460 Descarga de segmento inferior S3 Superior Eje 8D 29-Dec-21 11:00 29-Dec-21 0.25 Descarga de segmento inferior S3 Superior Eje 8D
MX-0500-7563 Volteo y Montaje de Segmento 3 del estator superior Eje 8D 29-Dec-21 14:30 29-Dec-21 0.25 Volteo y Montaje de Segmento 3 del estator superior Eje 8D
MX-0500-7743 Montaje y alineamiento de segmento superior S3 Eje 8D 30-Dec-21 06:00 30-Dec-21 1.00 Montaje y alineamiento de segmento superior S3 Eje 8D
MX-0500-7623 Traslado de Estator a zona de Izaje -S4 Superior Eje 9D 31-Dec-21 06:00 31-Dec-21 0.50 Traslado de Estator a zona de Izaje -S4 Superior Eje 9D
MX10470 Descarga de segmento inferior S4 Superior Eje 9D 31-Dec-21 11:00 31-Dec-21 0.25 Descarga de segmento inferior S4 Superior Eje 9D
MX-0500-7613 Volteo y Montaje de Segmento 4 del estator Superior Eje 9D 31-Dec-21 14:30 31-Dec-21 0.25 Volteo y Montaje de Segmento 4 del estator Superior Eje 9D
MX-0500-7753 Montaje y alineamiento de segmento inferior S4 Superior Eje 9D 01-Jan-22 06:00 01-Jan-22 1.00 Montaje y alineamiento de segmento inferior S4 Superior Eje 9D
MX-0500-7663 Alineamiento y Pre ajuste del Estator 02-Jan-22 06:00 04-Jan-22 3.00 Alineamiento y Pre ajuste del Estator
Estator - Instalación de Polos 05-Jan-22 06:00 03-Mar-22 58.00 03-Mar-22 17:00, Estator - Instalación de Polos
EX16660 Montaje del total de polos Diametrales 05-Jan-22 06:00 19-Jan-22 15.00 Montaje del total de polos Diametrales
MX9020 Desplazamiento del Estator a la zona de Operación (Air Gap) 20-Jan-22 06:00 22-Jan-22 3.00 Desplazamiento del Estator a la zona de Operación (Air Gap)
MX10300 Desplazamiento del Estator a la zona de Mantenimiento 23-Jan-22 06:00 23-Jan-22 1.00 Desplazamiento del Estator a la zona de Mantenimiento
MX-0500-7603 Empaques de Ajuste en uniones de estator y torque 24-Jan-22 06:00 28-Jan-22 5.00 Empaques de Ajuste en uniones de estator y torque
H9001 Llegada de SC AW a Site (inicio de cursos de Anexo 5) 24-Jan-22 06:00* 0.00 Llegada de SC AW a Site (inicio de cursos de Anexo 5), 24-Jan-22 06:00*
EX16670 Devanado del Estator (winding) 29-Jan-22 06:00 27-Feb-22 30.00 Devanado del Estator (winding)
EX16650 Ensamble de las Bobinas de las 4 juntas y pruebas eléctrica 24-Feb-22 06:00 27-Feb-22 4.00 Ensamble de las Bobinas de las 4 juntas y pruebas eléctrica
MX9030 Desplazamiento final del estator a zona de Operación 28-Feb-22 06:00 28-Feb-22 1.00 Desplazamiento final del estator a zona de Operación
MX9040 Inspección del Air Gap 01-Mar-22 06:00 03-Mar-22 3.00 Inspección del Air Gap
Estator - Trabajos Mecanicos
Meca 26-Feb-22 06:00 02-Apr-22 36.00 02-Apr-22 17:00, Estator - Trabajos Mecanicos
EX16690 Anillo de Sello 26-Feb-22 06:00 03-Mar-22 6.00 Anillo de Sello
EX16700 Instalacion de anillo deslizante 04-Mar-22 06:00 09-Mar-22 6.00 Instalacion de anillo deslizante
MX9050 Instalacion del sistema de Enfriamiento (parte externa) 10-Mar-22 06:00 11-Mar-22 2.00 Instalacion del sistema de Enfriamiento (parte externa)
EX16760 Disco ranurado para tacografo 10-Mar-22 06:00 15-Mar-22 6.00 Disco ranurado para tacografo
MX9080 Alineamiento final del estator 12-Mar-22 06:00 15-Mar-22 4.00 Alineamiento final del estator
MX9060 Instalacion de coberturas de estator 16-Mar-22 06:00 27-Mar-22 12.00 Instalacion de coberturas de estator
EX16770 Unidad tacografo 16-Mar-22 06:00 21-Mar-22 6.00 Unidad tacografo
EX16710 Montaje de Escobillas 19-Mar-22 06:00 23-Mar-22 5.00 Montaje de Escobillas
MX9070 Sistema de Sellado (cubiertas de sello) 20-Mar-22 06:00 02-Apr-22 14.00 Sistema de Sellado (cubiertas de sello)
Estator - Trabajos de Electricidad&Instrumentación
El 24-Mar-22 06:00 06-Apr-22 14.00 06-Apr-22 17:00, Estator - Trabajos de Electricidad&Instrumentación
IX7740 Instalación de Instrumentos del estator 24-Mar-22 06:00 27-Mar-22 4.00 Instalación de Instrumentos del estator
EX16680 Instalacion de Tacometro 28-Mar-22 06:00 29-Mar-22 2.00 Instalacion de Tacometro
EX9760 Montaje de seccionador AC y DC 03-Apr-22 06:00 06-Apr-22 4.00 Montaje de seccionador AC y DC
EX9770 Motaje de Panel de control del Estator 03-Apr-22 06:00 06-Apr-22 4.00 Motaje de Panel de control del Estator
EX9780 Acometida y Conexionado de cables de media tensión AC y DC 03-Apr-22 06:00 06-Apr-22 4.00 Acometida y Conexionado de cables de media tensión AC y DC
Electricidad e Instrumentación
Instrumenta 16-Jun-21 06:00 A 06-Apr-22 295.00 06-Apr-22 17:00, Electricidad e Instrumentación
EX6800 Completar canalización, cableado y conexionado para iluminación 16-Jun-21 06:00 A 10-Nov-21 115.00 Completar canalización, cableado y conexionado para iluminación
EX6810 Completar el montaje de Luminarias 22-Jun-21 00:00 A 18-Sep-21 109.00 Completar el montaje de Luminarias
EX6820 Conexionado de sistema de iluminación a sala Electrica - Tie in 31-Jul-21 06:00 A 18-Nov-21 78.00 Conexionado de sistema de iluminación a sala Electrica - Tie in
EX8040 Completar malla a tierra de la extensión del edificio y conexión a malla exis 19-Nov-21 06:00 23-Nov-21 5.00 Completar malla a tierra de la extensión del edificio y conexión a malla existente (Tie In 7017)
EX8050 Instalación de bandeja portacable (Tramo 14) 02-Feb-22 06:00* 21-Feb-22 20.00 Instalación de bandeja portacable (Tramo 14)

Actual Level of Effort Actual Work Critical Remaining Work Page 5 of 20 TASK filter: All Activities
Primary Baseline Remaining Work Milestone © Oracle Corporation
Cronograma del Proyecto: Construccion e Instalacion del 3er Molino de Bolas y Obras Asociadas
Linea Base 1 Rev. 0 (actualizado al 22-octubre)
Activity ID Activity Name Start Finish Original October 2021 November 2021 December 2021 January 2022 February 2022 March 2022 April 2022 May 2022 June 2022 July 2022
Duration
09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 05 12 19 26 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 02 09 6
EX8090 Instalación de bandeja portacable (Tramo 16) 02-Feb-22 06:00 21-Feb-22 20.00 Instalación de bandeja portacable (Tramo 16)
EX8110 Completar montaje bandeja portacable derivación T(Tramo 15) 02-Feb-22 06:00 02-Feb-22 1.00 Completar montaje bandeja portacable derivación T(Tramo 15)
EX8060 Tendido de cable de media tensión (Tramo 14) 22-Feb-22 06:00 03-Mar-22 10.00 Tendido de cable de media tensión (Tramo 14)
EX8100 Tendido de cable de media tension (Tramo 16) 22-Feb-22 06:00 03-Mar-22 10.00 Tendido de cable de media tension (Tramo 16)
EX16730 Tendido de cable y conexionado de cable de fuerza para sistema de freno 22-Feb-22 06:00 26-Feb-22 5.00 Tendido de cable y conexionado de cable de fuerza para sistema de frenos y engrase (desde 0310-MLB-0003 a
EX8120 Completar aterramiento para 3er Molino de Bolas (Tie In 7014) 04-Mar-22 06:00 13-Mar-22 10.00 Completar aterramiento para 3er Molino de Bolas (Tie In 7014)
EX8080 Montaje de tapas para bandejas 14-Mar-22 06:00 23-Mar-22 10.00 Montaje de tapas para bandejas
Instrumentación del 3er molino 09-Oct-21 06:00 A 06-Apr-22 53.00 06-Apr-22 17:00, Instrumentación del 3er molino
IX6391 Pruebas de contrastación de instrumentos 09-Oct-21 06:00 A 26-Feb-22 20.00 Pruebas de contrastación de instrumentos
IX7750 Canalizacion para instrumentos 22-Feb-22 06:00 13-Mar-22 20.00 Canalizacion para instrumentos
IX7760 Tendido de cables para instrumentos 04-Mar-22 06:00 28-Mar-22 25.00 Tendido de cables para instrumentos
IX6370 Paneles de control Local 07-Mar-22 06:00 14-Mar-22 8.00 Paneles de control Local
IX6611 Tendido y conexionado de fibra optica desde sala 3 al COB6 (Panel del es 07-Mar-22 06:00 08-Mar-22 2.00 Tendido y conexionado de fibra optica desde sala 3 al COB6 (Panel del estator)
IX6621 Tendido y conexionado de fibra optica desde COB6 al COB1 (Panel del es 09-Mar-22 06:00 09-Mar-22 1.00 Tendido y conexionado de fibra optica desde COB6 al COB1 (Panel del estator)
IX6380 Sensores y Controladores de temperatura y poscición (inc. conexionado) 15-Mar-22 06:00 22-Mar-22 8.00 Sensores y Controladores de temperatura y poscición (inc. conexionado)
IX6390 Sensores y Controladores de flujo y presión (inc. conexionado) 15-Mar-22 06:00 17-Mar-22 3.00 Sensores y Controladores de flujo y presión (inc. conexionado)
IX6351 Instalar indicadores de presión y proximidad para el Estator (inc. conexiona 18-Mar-22 06:00 30-Mar-22 13.00 Instalar indicadores de presión y proximidad para el Estator (inc. conexionado)
IX6400 Trasmisores de presión e indicadores (inc. conexionado) 18-Mar-22 06:00 30-Mar-22 13.00 Trasmisores de presión e indicadores (inc. conexionado)
IX6410 Valvulas de Control , alivio y solenoide (inc. conexionado) 18-Mar-22 06:00 30-Mar-22 13.00 Valvulas de Control , alivio y solenoide (inc. conexionado)
H9320 Fin de montaje de Molino 06-Apr-22 0.00 Fin de montaje de Molino,
Tests 07-Apr-22 06:00 02-May-22 26.00 02-May-22 17:00, Tests
EX1100 Mill - Empty Test Run of Mill and Motor 07-Apr-22 06:00 02-May-22 26.00 Mill - Empty Test Run of Mill and Motor
Plant outage 03-May-22 06:00 10-May-22 8.00 10-May-22 17:00, Plant outage
SD2360 Main Outage Required (Shutdown of Transition) 03-May-22 06:00 10-May-22 8.00 Main Outage Required (Shutdown of Transition)
Sub-major Areas 29-May-21 06:00 A 31-Mar-22 307.00 31-Mar-22 17:00, Sub-major Areas
Mill Discharge Launders 03-Jun-21 06:00 A 27-Nov-21 175.00 27-Nov-21 17:00, Mill Discharge Launders
H8020 Finalización de Launders 24-Nov-21 0.00 Finalización de Launders,
Mecánica 07-Jun-21 06:00 A 15-Nov-21 156.95 15-Nov-21 06:00, Mecánica
Launder 103 07-Jun-21 06:00 A 10-Nov-21 156.95 10-Nov-21 17:00, Launder 103
MX7390 Instalar Launder N° 103 - Canaleta de descarga 0310-LAL-0103 (Eje 3 a 4 07-Jun-21 06:00 A 03-Jul-21 1 27.00de launder)
MX7440 Instalar Launder N° 103 - Canaleta de descarga 0310-LAL-0103 (Eje 1 a 3 07-Jun-21 06:00 A 21-Jul-21 1 45.00 03 (Eje 1 a 3 de launder)
MX7450 Alineamiento y fijación de launder 103 04-Nov-21 06:00 10-Nov-21 7.00 Alineamiento y fijación de launder 103
Pre Ensamble de 03
0310 - STP - 0065 y Valvulas dardo y cuchilla 26-Jun-21 06:00 A 15-Nov-21 95.00 15-Nov-21 06:00, Pre Ensamble de 0310 - STP - 0065 y Valvulas dardo y cuchilla
Traslado de mater
materiales al area de trabajo 26-Jun-21 06:00 A 02-Jul-21 1 7.00
MX6710 Traslado de secciones de 0310 - STP - 0065 26-Jun-21 06:00 A 01-Jul-21 1 6.00
MX6290 Traslado de Valvulas Darlo y Cuchilla 01-Jul-21 06:00 A 02-Jul-21 1 2.00
Discharge chutes assembly of BM 2 02-Jul-21 06:00 A 15-Nov-21 89.00 15-Nov-21 06:00, Discharge chutes assembly of BM 2
MX6280 Ensamble de 0310 - STP - 0065 - part CP 1, CP 2/ N° drawing 102807 - 0 02-Jul-21 06:00 A 18-Jul-21 1 17.00 02807 - 0310 - M - 123 Rev. 2
MX6860 Ensamble de 0310 - STP - 0065 - part CP 3 - D, CP 4-D 02-Jul-21 06:00 A 18-Jul-21 1 17.00
MX6820 Ensamble de 0310 - STP - 0065 - part CP 4 - I , CP 2-D , CP3-I 12-Jul-21 06:00 A 18-Jul-21 1 7.00
MX6790 Ensamble de valvulas cuchilla 17-Jul-21 06:00 A 18-Jul-21 0 1.00
MX6800 Ensamble de valvulas dardo 17-Jul-21 06:00 A 15-Nov-21 74.00 Ensamble de valvulas dardo
Estrutural 03-Jun-21 06:00 A 27-Nov-21 142.00 27-Nov-21 17:00, Estrutural
SX7435 Desmontaje de arriostres por interferencia 03-Jun-21 06:00 A 04-Jun-21 2.00
Eje 05 - 06 (Launders)
(Launders 17-Jul-21 06:00 A 12-Nov-21 83.00 12-Nov-21 17:00, Eje 05 - 06 (Launders)
SX8100 Completar montaje de pasarelas y escaleras 17-Jul-21 06:00 A 12-Nov-21 83.00 Completar montaje de pasarelas y escaleras
Eje 04 - 05 (Launders)
(Launders 24-Jul-21 06:00 A 20-Nov-21 84.00 20-Nov-21 17:00, Eje 04 - 05 (Launders)
SX7420 Instalar reforzamientos previos al Tie in y montaje de launder descarga MB 24-Jul-21 06:00 A 20-Nov-21 84.00 Instalar reforzamientos previos al Tie in y montaje de launder descarga MB2
Eje 03 - 04 (Launders)
(Launders 06-Jun-21 06:00 A 22-Nov-21 134.00 22-Nov-21 17:00, Eje 03 - 04 (Launders)
SX8050 Instalación de estructuras 06-Jun-21 06:00 A 22-Nov-21 134.00 Instalación de estructuras
SX8060 Instalación de pasarelas y escaleras 06-Jun-21 06:00 A 17-Nov-21 129.00 Instalación de pasarelas y escaleras
Eje 02 - 03 (Launders)
(Launders 06-Jun-21 00:00 A 24-Nov-21 136.00 24-Nov-21 17:00, Eje 02 - 03 (Launders)
SX7450 Instalar pasarela y escaleras sobre Launder N° 103 06-Jun-21 00:00 A 24-Nov-21 136.00 Instalar pasarela y escaleras sobre Launder N° 103
Eje 01 - 02 (Launders)
(Launders 06-Jun-21 06:00 A 27-Nov-21 139.00 27-Nov-21 17:00, Eje 01 - 02 (Launders)
SX7400 Instalar estructuras, pasarela y escaleras sobre le SUL 1 06-Jun-21 06:00 A 27-Nov-21 139.00 Instalar estructuras, pasarela y escaleras sobre le SUL 1
Eléctrica e Instrumentación
Instrumenta 24-Jun-21 06:00 A 11-Nov-21 149.00 11-Nov-21 17:00, Eléctrica e Instrumentación
IX6050 Canalizaciones para el control de válvulas Dardo y Cuchillas( Instalación d 24-Jun-21 06:00 A 02-Nov-21 145.00 Canalizaciones para el control de válvulas Dardo y Cuchillas( Instalación de andamios)
IX6110 Completar cableado de Alimentación desde a Sala electrica N°2 hacia JBA 25-Jun-21 06:00 A 04-Nov-21 146.00 Completar cableado de Alimentación desde a Sala electrica N°2 hacia JBAs
IX6080 Contrastación de Valvulas Dardo y Cuchilla (Vendor - Metso) 24-Jul-21 06:00 A 25-Jul-21 1 114.00 Contrastación de Valvulas Dardo y Cuchilla (Vendor - Metso)
IX6090 Canalización conduit y Cableado de control desde JBA hacia valvulas (Co 24-Jul-21 06:00 A 05-Nov-21 118.00 Canalización conduit y Cableado de control desde JBA hacia valvulas (Conexion en parada)
IX6060 Canalizaciones para los Transmisores de nivel 25-Jul-21 00:00 A 02-Nov-21 114.00 Canalizaciones para los Transmisores de nivel
IX6070 Instalación de sirena 28-Aug-21 00:00 A 03-Nov-21 81.00 Instalación de sirena
IX6100 Terminar la canalización y cableado de control desde JBPs a JBAs 18-Sep-21 00:00 A 04-Nov-21 4.00 Terminar la canalización y cableado de control desde JBPs a JBAs
SX6121 Fabricación de Soporte para tableros JBPs (Lev. Observaciones) 02-Nov-21 06:00 11-Nov-21 10.00 Fabricación de Soporte para tableros JBPs (Lev. Observaciones)

Actual Level of Effort Actual Work Critical Remaining Work Page 6 of 20 TASK filter: All Activities
Primary Baseline Remaining Work Milestone © Oracle Corporation
Cronograma del Proyecto: Construccion e Instalacion del 3er Molino de Bolas y Obras Asociadas
Linea Base 1 Rev. 0 (actualizado al 22-octubre)
Activity ID Activity Name Start Finish Original October 2021 November 2021 December 2021 January 2022 February 2022 March 2022 April 2022 May 2022 June 2022 July 2022
Duration
09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 05 12 19 26 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 02 09 6
IX6120 Montaje de tableros JBPs (Falta liberacion) 02-Nov-21 06:00 04-Nov-21 3.00 Montaje de tableros JBPs (Falta liberacion)
Cyclones 29-May-21 06:00 A 24-Feb-22 272.00 24-Feb-22 17:00, Cyclones
PX6365 Desmontaje de lineas de agua de procesos 21-Jul-21 06:00 A 20-Aug-21 31.00ocesos
PX6376 Desmontaje de linea de lechada de cal 21-Jul-21 06:00 A 20-Aug-21 31.00cal
Civil 16-Oct-21 06:00 A 24-Feb-22 116.00 24-Feb-22 17:00, Civil
CX6366 Vaciado de grout en pedestales y curado de concreto 16-Oct-21 06:00 A 22-Oct-21 4.00 Vaciado de grout en pedestales y curado de concreto
CX6376 Sardineles en Chutes y reparacion de losa (Post SD Julio 21) 01-Nov-21 06:00 04-Nov-21 4.00 Sardineles en Chutes y reparacion de losa (Post SD Julio 21)
H9031 Llegada de sub contratista FH 01-Nov-21 06:00* 0.00 Llegada de sub contratista FH, 01-Nov-21 06:00*
CX6386 Sardineles en Chutes y reparacion de losa (Post SD Febrero 22) 21-Feb-22 06:00 24-Feb-22 4.00 Sardineles en Chutes y reparacion de losa (Post SD Febrero 22)
Ciclon 1 29-May-21 06:00 A 19-Jul-21 0 51.00
Piping 29-May-21 06:00 A 19-Jul-21 0 51.00
PX6470 Completar recorrido de lineas de 2"-0310-WP-06941-C1E2A 29-May-21 06:00 A 18-Jul-21 1 51.00
PX6480 Completar recorrido de lineas de 2"-0310-WP-06942-C1E2A 29-May-21 06:00 A 18-Jul-21 1 51.00
PX6490 Completar recorrido de lineas de 2"-0310-WP-06943-C1E2A 29-May-21 06:00 A 18-Jul-21 1 51.00
PX6500 Completar recorrido de lineas de 2"-0310-WP-06939-C1E2A 29-May-21 06:00 A 18-Jul-21 1 51.00
PX6510 Completar recorrido de lineas de 2"-0310-WP-06940-C1E2A 29-May-21 06:00 A 18-Jul-21 1 51.00
PX6530 Traslado de suministro para soportes estructurales y soporte de tubería 42 01-Jun-21 06:00 A 18-Jul-21 1 48.00 tubería 42"-0310-SL-06716-L1E0VJ
PX6460 Montaje de spool desde linea existente hasta valvula (0310-WP-06914-C1 02-Jun-21 06:00 A 19-Jul-21 0 47.00 -06914-C1E2A)
PX8260 Prueba hidrostatica de tuberias 18-Jul-21 06:00 A 18-Jul-21 1 1.00
Ciclon 2 29-May-21 06:00 A 28-Nov-21 175.00 28-Nov-21 17:00, Ciclon 2
Piping 05-Jul-21 06:00 A 28-Nov-21 108.00 28-Nov-21 17:00, Piping
PX6370 Completar recorrido de lineas de 2"-0310-WP-06725-C1E2A 05-Jul-21 06:00 A 20-Jul-21 2 16.00
PX6380 Completar recorrido de lineas de 2"-0310-WP-06726-C1E2A 05-Jul-21 06:00 A 20-Jul-21 2 16.00
PX6390 Completar recorrido de lineas de 2"-0310-WP-06720-C1E2A 05-Jul-21 06:00 A 28-Nov-21 108.00 Completar recorrido de lineas de 2"-0310-WP-06720-C1E2A
PX6400 Completar recorrido de lineas de 2"-0310-WP-06721-C1E2A 05-Jul-21 06:00 A 28-Nov-21 108.00 Completar recorrido de lineas de 2"-0310-WP-06721-C1E2A
PX6410 Completar recorrido de lineas de 2"-0310-WP-06722-C1E2A 05-Jul-21 06:00 A 28-Nov-21 108.00 Completar recorrido de lineas de 2"-0310-WP-06722-C1E2A
PX6420 Completar recorrido de lineas de 2"-0310-WP-06723-C1E2A 05-Jul-21 06:00 A 28-Nov-21 108.00 Completar recorrido de lineas de 2"-0310-WP-06723-C1E2A
PX6430 Completar recorrido de lineas de 2"-0310-WP-06724-C1E2A 05-Jul-21 06:00 A 28-Nov-21 108.00 Completar recorrido de lineas de 2"-0310-WP-06724-C1E2A
PX6800 Montaje de soportes para linea 42"-0310-SL-06711-L1E0VJ 18-Jul-21 06:00 A 20-Jul-21 1 3.00
PX6450 Traslado de suministro para soportes estructurales y soporte de tubería 42 19-Jul-21 06:00 A 19-Jul-21 2 1.00e tubería 42"-0310-SL-06711-L1E0VJ
PX8270 Prueba hidrostatica de tuberias 20-Jul-21 06:00 A 25-Jul-21 1 6.00
Estructural 14-Jun-21 06:00 A 20-Jul-21 1 37.00
SX5770 Montaje de columna para Refuerzo para viga de Ciclon N°2 (Levantar Inte 14-Jun-21 06:00 A 16-Jun-21 3.00
SX5760 Colocar pernos de anclaje en pedestales para soportes (Levantar Interfere 17-Jul-21 06:00 A 19-Jul-21 1 3.00ntar Interferencia).
SX5780 Recorte de viga para evitar interferencia Ciclon N°2 (Levantar Interferencia 19-Jul-21 06:00 A 20-Jul-21 1 2.00 Interferencia).
Mecanica 29-May-21 06:00 A 17-Jul-21 1 50.00
MX5790 Montaje de unidad hidraulica 0310-ZMH-0050 29-May-21 06:00 A 17-Jul-21 1 50.00
E&I 06-Jun-21 06:00 A 02-Nov-21 167.00 02-Nov-21 17:00, E&I
Unidad Hidraulica e Iluminación 06-Jun-21 06:00 A 02-Nov-21 167.00 02-Nov-21 17:00, Unidad Hidraulica e Iluminación
EX5920 Cableado de 2 circuitos de Iluminación (SE2 - Ciclones) 06-Jun-21 06:00 A 01-Jul-21 1 26.00
EX16740 Montaje de panel de iluminacion 06-Jun-21 06:00 A 01-Jul-21 1 26.00
IX5860 Contrastación y montaje de Válvula 0310-HV-01558 y HV-01559 29-Jun-21 06:00 A 02-Nov-21 141.00 Contrastación y montaje de Válvula 0310-HV-01558 y HV-01559
IX5810 Canalización y cableado desde tablero JBP-0602-03 a Unidad Hidraulica 07-Jul-21 06:00 A 31-Oct-21 136.00 Canalización y cableado desde tablero JBP-0602-03 a Unidad Hidraulica
IX5960 Conexionado de Acometida de 4 circuitos de Iluminación 17-Jul-21 06:00 A 17-Jul-21 1 1.00
EX5970 Tie in - Panel de Iluminación existente en SE 2 17-Jul-21 06:00 A 17-Jul-21 1 1.00
EX5885 Remover instalaciones electricas 17-Jul-21 06:00 A 17-Jul-21 1 1.00
EX5840 Instalación de alimentador de fuerza desde la sala electrica a unidad Hidra 31-Jul-21 06:00 A 26-Sep-21 111.00 Instalación de alimentador de fuerza desde la sala electrica a unidad Hidraulica
IX5820 Canalización y cableado desde Unidad Hidraulica a valvula 0310-HV-0155 18-Sep-21 06:00 A 01-Nov-21 5.00 Canalización y cableado desde Unidad Hidraulica a valvula 0310-HV-01558 y HV-01559
H9015 Llegada de suminitro de cables (Fuerza ) 30-Oct-21 06:00* 0.00 Llegada de suminitro de cables (Fuerza ), 30-Oct-21 06:00*
IX5850 Comisionamiento de la unidad hidraulica ( Presencia del Vendor) 01-Nov-21 06:00 02-Nov-21 2.00 Comisionamiento de la unidad hidraulica ( Presencia del Vendor)
Ciclon 3 05-Jul-21 06:00 A 26-Jan-22 206.00 26-Jan-22 17:00, Ciclon 3
Piping 05-Jul-21 06:00 A 25-Nov-21 144.00 25-Nov-21 17:00, Piping
PX6540 Completar recorrido hasta Valvula Linea de 2"-0310-WP-06728-C1E2A 05-Jul-21 06:00 A 03-Nov-21 135.00 Completar recorrido hasta Valvula Linea de 2"-0310-WP-06728-C1E2A
PX6550 Completar recorrido hasta Valvula Linea de 2"-0310-WP-06729-C1E2A 05-Jul-21 06:00 A 05-Nov-21 137.00 Completar recorrido hasta Valvula Linea de 2"-0310-WP-06729-C1E2A
PX6560 Completar recorrido hasta Valvula Linea de 2"-0310-WP-06730-C1E2A 05-Jul-21 06:00 A 07-Nov-21 139.00 Completar recorrido hasta Valvula Linea de 2"-0310-WP-06730-C1E2A
PX6570 Completar recorrido hasta Valvula Linea de 2"-0310-WP-06731-C1E2A 05-Jul-21 06:00 A 09-Nov-21 141.00 Completar recorrido hasta Valvula Linea de 2"-0310-WP-06731-C1E2A
PX8350 Montaje de soportes para linea 42"-0310-SL-06712 23-Nov-21 06:00 25-Nov-21 3.00 Montaje de soportes para linea 42"-0310-SL-06712
E&I 14-Jan-22 06:00 26-Jan-22 13.00 26-Jan-22 17:00, E&I
IX7780 Canalizacion para valvulas neumaticas a la salida del Ciclon 3 14-Jan-22 06:00 18-Jan-22 5.00 Canalizacion para valvulas neumaticas a la salida del Ciclon 3
IX7790 Cableado para valvulas neumaticas a la salida del Ciclon 3 19-Jan-22 06:00 23-Jan-22 5.00 Cableado para valvulas neumaticas a la salida del Ciclon 3
IX7800 Conexionado para valvulas neumaticas a la salida del Ciclon 3 24-Jan-22 06:00 26-Jan-22 3.00 Conexionado para valvulas neumaticas a la salida del Ciclon 3
Ciclon 4 05-Jul-21 06:00 A 20-Feb-22 231.00 20-Feb-22 17:00, Ciclon 4
Piping 05-Jul-21 06:00 A 17-Feb-22 228.00 17-Feb-22 17:00, Piping
PX6580 Completar recorrido hasta Valvula Linea de 2"-0310-WP-06732-C1E2A 05-Jul-21 06:00 A 30-Nov-21 110.00 Completar recorrido hasta Valvula Linea de 2"-0310-WP-06732-C1E2A

Actual Level of Effort Actual Work Critical Remaining Work Page 7 of 20 TASK filter: All Activities
Primary Baseline Remaining Work Milestone © Oracle Corporation
Cronograma del Proyecto: Construccion e Instalacion del 3er Molino de Bolas y Obras Asociadas
Linea Base 1 Rev. 0 (actualizado al 22-octubre)
Activity ID Activity Name Start Finish Original October 2021 November 2021 December 2021 January 2022 February 2022 March 2022 April 2022 May 2022 June 2022 July 2022
Duration
09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 05 12 19 26 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 02 09 6
PX6590 Completar recorrido hasta Valvula Linea de 2"-0310-WP-06727-C1E2A 05-Jul-21 06:00 A 30-Nov-21 110.00 Completar recorrido hasta Valvula Linea de 2"-0310-WP-06727-C1E2A
PX6600 Prueba de Nueva linea de agua de proceso (0310-WP-06914-C1E2A) 01-Dec-21 06:00 04-Dec-21 4.00 Prueba de Nueva linea de agua de proceso (0310-WP-06914-C1E2A)
PX8360 Montaje de soportes para linea 42"-0310-SL-06715 15-Feb-22 06:00 17-Feb-22 3.00 Montaje de soportes para linea 42"-0310-SL-06715
Mecanica 25-Jan-22 06:00 20-Feb-22 27.00 20-Feb-22 17:00, Mecanica
MX6490 Instalación de chute de alimentación para el 3er Molino 310-STP-0101 25-Jan-22 06:00 03-Feb-22 10.00 Instalación de chute de alimentación para el 3er Molino 310-STP-0101
MX9740 Instalación de chute de alimentación para el 3er Molino 310-STP-0063 18-Feb-22 06:00 20-Feb-22 3.00 Instalación de chute de alimentación para el 3er Molino 310-STP-0063
MX9750 Instalación de chute de alimentación para el 3er Molino 310-STP-0108 18-Feb-22 06:00 20-Feb-22 3.00 Instalación de chute de alimentación para el 3er Molino 310-STP-0108
Estructuras 15-Jan-22 06:00 24-Jan-22 10.00 24-Jan-22 17:00, Estructuras
SX1636 Desmontaje de estructuras (para ampliacion de losa en eje 8-9 del eje D 3 15-Jan-22 06:00 15-Jan-22 1.00 Desmontaje de estructuras (para ampliacion de losa en eje 8-9 del eje D 3er Nivel)
SX1635 Ampliación de losa de ciclones (Estructura Soporte de Chute 0310-STP-01 16-Jan-22 06:00 24-Jan-22 9.00 Ampliación de losa de ciclones (Estructura Soporte de Chute 0310-STP-0101)
Power Systems 17-Jun-21 06:00 A 31-Mar-22 288.00 31-Mar-22 17:00, Power Systems
H8030 Finalización de sistema de potencia 21-Dec-21 0.00 Finalización de sistema de potencia,
H8040 Finalización de cableado y conexionado de Fibra Optica 31-Mar-22 0.00 Finalización de cableado y conexionado de Fibra Optica,
Sala electrica N°1 28-Aug-21 06:00 A 25-Oct-21 34.50 25-Oct-21 17:00, Sala electrica N°1
IX6180 Completar la fibra optica en Chiller COB1 (Actividad ejecutada por otra Co 28-Aug-21 06:00 A 28-Aug-21 1.00hiller COB1 (Actividad ejecutada por otra Contratista)
IX6630 Completar tendido de fibra optica desde 0310-MLB-0003-MCL2 a Chiller ( 28-Aug-21 06:00 A 28-Aug-21 1.00 ica desde 0310-MLB-0003-MCL2 a Chiller (Actividad ejecutada por otra Contratista)
IX6610 Completar tendido de fibra optica desde COB4 (Sala de Lubricacion) a 03 05-Sep-21 06:00 A 09-Oct-21 10.00 Completar tendido de fibra optica desde COB4 (Sala de Lubricacion) a 0310-MLB-0003-MCL2
IX6620 Completar cableado de control desde Sala Electrica 1 (0310-SGM-002) a S 06-Sep-21 06:00 A 25-Oct-21 6.00 Completar cableado de control desde Sala Electrica 1 (0310-SGM-002) a Sala electrica 3
EX6610 Conexionado de panel Chiller - 0310-MLB-0003-MCL2 (Fuerza) 15-Sep-21 06:00 A 15-Sep-21 1.00 nado de panel Chiller - 0310-MLB-0003-MCL2 (Fuerza)
Sala electrica N°2 - Sal
Sala de Lubricacion 17-Jun-21 06:00 A 06-Mar-22 263.00 06-Mar-22 17:00, Sala electrica N°2 - Sala de Lubricacion
EX6040 Instalación de panel para Iluminación LPA-0009 17-Jun-21 06:00 A 22-Oct-21 88.00 Instalación de panel para Iluminación LPA-0009
EX6030 Cableado y Conexionado de LPA-0009 30-Jun-21 06:00 A 22-Oct-21 76.00 Cableado y Conexionado de LPA-0009
IX5870 Montaje de sistema de alimentación ininterrumpida 0310-UPS-0004 01-Jul-21 06:00 A 17-Oct-21 70.00 Montaje de sistema de alimentación ininterrumpida 0310-UPS-0004
IX5930 Cableado y Conexionado desde MCL-0016 a XFL-0011 (Fuerza y control) 01-Jul-21 06:00 A 22-Oct-21 74.00 Cableado y Conexionado desde MCL-0016 a XFL-0011 (Fuerza y control)
EX5880 Montaje de 0310-BAB-0006 05-Jul-21 06:00 A 16-Oct-21 68.00 Montaje de 0310-BAB-0006
EX6020 Cableado y Conexionado de 301-BAB-0006 05-Jul-21 06:00 A 17-Oct-21 73.00 Cableado y Conexionado de 301-BAB-0006
EX5890 Montaje de 0310-DPU-0012 09-Jul-21 06:00 A 22-Oct-21 67.00 Montaje de 0310-DPU-0012
EX5900 Cableado y conexionado 0310-DPU-0012 09-Jul-21 06:00 A 22-Oct-21 65.00 Cableado y conexionado 0310-DPU-0012
EX6010 Cableado y Conexionado de 310-UPS-0004 09-Jul-21 06:00 A 17-Oct-21 68.00 Cableado y Conexionado de 310-UPS-0004
IX5980 Pre comisionamiento del centro de control de motores 0310-MCL-0016 (Ve 24-Jul-21 06:00 A 25-Jul-21 1 2.00 0-MCL-0016 (Vendor - ABB)
H9021 LLegada de equipo de Taggeo para cables 07-Sep-21 06:00 A 0.00 Taggeo para cables, 07-Sep-21 06:00 A
IX1662 Completar equipos auxiliares Para CUA-009 11-Sep-21 06:00 A 11-Sep-21 4.00 auxiliares Para CUA-009
IX7770 Canalizacion interna en la sala ERR-002 11-Sep-21 06:00 A 11-Sep-21 4.00 a en la sala ERR-002
EX5830 Pre comisionamieno de 0310-UPS-0004 16-Oct-21 06:00 A 17-Oct-21 2.00 Pre comisionamieno de 0310-UPS-0004
EX5950 Pre comisionamieno de 0310-BAB-0006 16-Oct-21 06:00 A 17-Oct-21 2.00 Pre comisionamieno de 0310-BAB-0006
EX5910 Pre comisionamieno de 0310-DPU-0012 23-Oct-21 06:00 24-Oct-21 2.00 Pre comisionamieno de 0310-DPU-0012
EX5990 Cableado y Conexionado de 310-CUA-0009 23-Oct-21 06:00 23-Oct-21 1.00 Cableado y Conexionado de 310-CUA-0009
H9019 Llegada de suministro de cables 23-Oct-21 06:00* 0.00 Llegada de suministro de cables, 23-Oct-21 06:00*
H9020 Llegada de suministro de fibra optica 23-Oct-21 06:00* 0.00 Llegada de suministro de fibra optica, 23-Oct-21 06:00*
EX5940 Pre comisionamieno el transformado XFL-0011 24-Oct-21 06:00 24-Oct-21 1.00 Pre comisionamieno el transformado XFL-0011
EX6000 Pre comisionamiento del panel de control 0310-COA-0006 31-Oct-21 06:00 01-Nov-21 2.00 Pre comisionamiento del panel de control 0310-COA-0006
IX6130 Cableado y conexionado de fibra y comunicación desde COB1 a COB4 27-Feb-22 06:00 06-Mar-22 8.00 Cableado y conexionado de fibra y comunicación desde COB1 a COB4
Sala electrica N°3 21-Aug-21 00:00 A 31-Mar-22 223.00 31-Mar-22 17:00, Sala electrica N°3
EX6210 Conexión de acometidas a cicloconvertidores (Tranformadores) 04-Sep-21 06:00 A 16-Dec-21 10.00 Conexión de acometidas a cicloconvertidores (Tranformadores)
EX-3050 Acometida y conexionado de fuerza a equipo 0310-MLB-0003-MCL 11-Sep-21 06:00 A 12-Dec-21 10.00 Acometida y conexionado de fuerza a equipo 0310-MLB-0003-MCL
IX-3040 Completar tendido de fibra optica panel Chiller - 0310-MLB-0003-COB2 (T 24-Nov-21 06:00 08-Dec-21 15.00 Completar tendido de fibra optica panel Chiller - 0310-MLB-0003-COB2 (Tramo 1 Chiller-Sala electrica 3)
IX6360 Conexionado de Fibra Optica (todos los lazos) 09-Mar-22 06:00 11-Mar-22 3.00 Conexionado de Fibra Optica (todos los lazos)
EX-3060 Acometida y conexionado de control, señal y comunicación a paneles de 12-Mar-22 06:00 31-Mar-22 20.00 Acometida y conexionado de control, señal y comunicación a paneles de SE3 (Incluy
Estructuras 28-Sep-21 06:00 A 07-Oct-21 8.00 07-Oct-21 17:00 A, Estructuras
SX6353 Completar montaje de barandas 28-Sep-21 06:00 A 07-Oct-21 4.00 Completar montaje de barandas
SX6366 Desmontaje de andamios 29-Sep-21 00:00 A 07-Oct-21 4.00 Desmontaje de andamios
Mecanica y civil 21-Aug-21 00:00 A 21-Dec-21 123.00 21-Dec-21 17:00, Mecanica y civil
MX6200 Colocación de Parrilla FRP - Debajo de Sala Eléctrica 21-Aug-21 00:00 A 02-Oct-21 34.00olocación de Parrilla FRP - Debajo de Sala Eléctrica
CX6210 Colocación de pernos quimicos 07-Oct-21 06:00 A 08-Oct-21 4.00 Colocación de pernos quimicos
MX6190 Traslado y Montaje de equipo HVAC (Requiere la presencia del Vendor) 17-Dec-21 06:00 21-Dec-21 5.00 Traslado y Montaje de equipo HVAC (Requiere la presencia del Vendor)
Instrumentación 09-Dec-21 06:00 12-Dec-21 4.00 12-Dec-21 17:00, Instrumentación
IX6353 Instalación de CCTV y Sistema de detección de incendios 09-Dec-21 06:00 12-Dec-21 4.00 Instalación de CCTV y Sistema de detección de incendios
Transformadores 24-Jul-21 06:00 A 09-Dec-21 139.00 09-Dec-21 17:00, Transformadores
EX6280 Reemplazo del Transformador de excitación XFC4 (pendiente pruebas en 24-Jul-21 06:00 A 03-Sep-21 42.00 ador de excitación XFC4 (pendiente pruebas en la actividad EX6290)
IX1671 Tendido y conexionado de cables de control 31-Jul-21 06:00 A 09-Oct-21 60.50 Tendido y conexionado de cables de control
EX1661 Completar el sistema de iluminacion 15-Aug-21 00:00 A 09-Oct-21 60.00 Completar el sistema de iluminacion
H9022 Orden de servicio para Llenado de aceite y pruebas 04-Sep-21 06:00 A 0.00enado de aceite y pruebas, 04-Sep-21 06:00 A
EX6620 Instalar tapas de bandeja en patio de transformadores 11-Sep-21 06:00 A 15-Oct-21 5.00 Instalar tapas de bandeja en patio de transformadores

Actual Level of Effort Actual Work Critical Remaining Work Page 8 of 20 TASK filter: All Activities
Primary Baseline Remaining Work Milestone © Oracle Corporation
Cronograma del Proyecto: Construccion e Instalacion del 3er Molino de Bolas y Obras Asociadas
Linea Base 1 Rev. 0 (actualizado al 22-octubre)
Activity ID Activity Name Start Finish Original October 2021 November 2021 December 2021 January 2022 February 2022 March 2022 April 2022 May 2022 June 2022 July 2022
Duration
09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 05 12 19 26 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 02 09 6
H9023 Llegada a obra de sub contrato para lllenado de acite y pruebas 09-Oct-21 06:00 A 0.00 Llegada a obra de sub contrato para lllenado de acite y pruebas, 09-Oct-21 06:00 A
EX6240 Llenado y tratamiento de aceite y pruebas ( Recirculación, Termovacio, Hid 10-Oct-21 06:00 A 20-Nov-21 10.00 Llenado y tratamiento de aceite y pruebas ( Recirculación, Termovacio, Hidrostatica)
EX6250 Pruebas de aceite del Transformador en laboratorio (Lima). 21-Nov-21 06:00 04-Dec-21 14.00 Pruebas de aceite del Transformador en laboratorio (Lima).
IX1681 Reemplazo de manometro y bushing de barra 21-Nov-21 06:00 24-Nov-21 4.00 Reemplazo de manometro y bushing de barra
IX6230 Completar instalación de 03 Cajas de conexionado (Montaje) 25-Nov-21 06:00 27-Nov-21 3.00 Completar instalación de 03 Cajas de conexionado (Montaje)
EX6260 Completar habilitado de conectores P-Fistere en el lado primario y conecto 28-Nov-21 06:00 06-Dec-21 9.00 Completar habilitado de conectores P-Fistere en el lado primario y conectores lado secundario
EX6270 Pruebas eléctricas de transformadores Ciclo convertidores 07-Dec-21 06:00 09-Dec-21 3.00 Pruebas eléctricas de transformadores Ciclo convertidores
EX6290 Pruebas eléctricas del transformador de Exitación 07-Dec-21 06:00 07-Dec-21 1.00 Pruebas eléctricas del transformador de Exitación
Sub Estación Principal 14-Aug-21 00:00 A 02-Nov-21 80.00 02-Nov-21 06:00, Sub Estación Principal
EX6840 Montaje de transformadores Toroidales de corriente en celda de 33KV 14-Aug-21 00:00 A 09-Oct-21 37.00 Montaje de transformadores Toroidales de corriente en celda de 33KV
EX6850 Instalar Tapas de bandejas 15-Aug-21 00:00 A 15-Oct-21 42.00 Instalar Tapas de bandejas
IX6830 Cableado (Control / comunicaciones) - Terminar recorrido 22-Aug-21 00:00 A 09-Oct-21 29.00 Cableado (Control / comunicaciones) - Terminar recorrido
H6860 Conexionado de cables de control y comunicaciones (En parada) 02-Nov-21 06:00 0.00 Conexionado de cables de control y comunicaciones (En parada), 02-Nov-21 06:00
Lube Room 10-Jun-21 06:00 A 20-Dec-21 194.00 20-Dec-21 17:00, Lube Room
H16350 Culminación de Sala de Lubricación 20-Dec-21 0.00 Culminación de Sala de Lubricación,
Eléctrica e Instrumentación
Instrumenta 13-Jun-21 06:00 A 11-Nov-21 151.50 11-Nov-21 11:00, Eléctrica e Instrumentación
Puente Grúa e iluminación
ilumin 13-Jun-21 06:00 A 07-Nov-21 147.50 07-Nov-21 11:00, Puente Grúa e iluminación
EX6110 Canalización, Cableado y Conexionado (SE 2 - Sistema de Iluminación) 13-Jun-21 06:00 A 04-Sep-21 86.00o y Conexionado (SE 2 - Sistema de Iluminación)
EX6150 Canalización y cableado del 3er circuito de iluminación 13-Jun-21 06:00 A 11-Sep-21 86.50 eado del 3er circuito de iluminación
EX16720 Instalacion del disconnect swicht (inc canalizacion, cableado, conexionado 31-Jul-21 06:00 A 11-Sep-21 36.00onnect swicht (inc canalizacion, cableado, conexionado, reubicacion de tableros)
EX6090 Instalar Limit Swich del Puente grua 30-Aug-21 00:00 A 11-Sep-21 7.00 del Puente grua
H6130 Suministro de Limit Swich (IMT) 30-Aug-21 00:00 A 0.00 T), 30-Aug-21 00:00 A
EX6120 Instalación de interruptores y tomacorrientes 31-Aug-21 06:00 A 31-Aug-21 0.50y tomacorrientes
EX6630 Instación de tapas para bandejas (Interior) 05-Sep-21 06:00 A 11-Sep-21 2.00 para bandejas (Interior)
EX6160 Tie In para el 3er circuito de iluminación 14-Sep-21 06:00 A 15-Sep-21 1.00er circuito de iluminación
EX6641 Instación de tapas para bandejas (Exterior) 09-Oct-21 06:00 A 09-Oct-21 2.00 Instación de tapas para bandejas (Exterior)
H16680 Llegada de vendor de puente grua 05-Nov-21 0.00 Llegada de vendor de puente grua,
EX6100 Energizar el puente grua de la Sala de Lubricación (Vendor - Konne Crane 06-Nov-21 06:00 06-Nov-21 1.00 Energizar el puente grua de la Sala de Lubricación (Vendor - Konne Crane)
IX6140 Instalación de señaletica de Entrada/Salida 07-Nov-21 06:00 07-Nov-21 0.50 Instalación de señaletica de Entrada/Salida
Conexionado de Equipos
Equ 26-Jul-21 06:00 A 11-Nov-21 108.50 11-Nov-21 11:00, Conexionado de Equipos
EX6300 Canalizaciones y tendido de cables para equipos de lubricación 26-Jul-21 06:00 A 16-Oct-21 55.50 Canalizaciones y tendido de cables para equipos de lubricación
IX6310 Instalar tableros (Traslado, Fijación conexionado), 4 tableros 01-Aug-21 06:00 A 16-Oct-21 42.50 Instalar tableros (Traslado, Fijación conexionado), 4 tableros
EX6310 Conexionado de equipos de lubricacion 14-Aug-21 06:00 A 09-Oct-21 39.50 Conexionado de equipos de lubricacion
EX6350 Conexionado de Calefactores 15-Sep-21 06:00 A 16-Sep-21 2.00nado de Calefactores
IX6320 Conexionado de equipo COB-102 16-Oct-21 06:00 A 16-Oct-21 1.00 Conexionado de equipo COB-102
IX6330 Conexionado de equipo COB-103 16-Oct-21 06:00 A 16-Oct-21 1.00 Conexionado de equipo COB-103
IX6340 Conexionado de equipo COB-104 16-Oct-21 06:00 A 16-Oct-21 4.00 Conexionado de equipo COB-104
EX6612 Instalación de panel Heat Tracing 07-Nov-21 11:00 11-Nov-21 4.00 Instalación de panel Heat Tracing
Estructuras 17-Jul-21 06:00 A 17-Nov-21 124.00 17-Nov-21 17:00, Estructuras
SX1638 Completar montaje de estrucutras 17-Jul-21 06:00 A 03-Sep-21 49.00 trucutras
SX1639 Realizar desmontaje de estructuras 17-Jul-21 06:00 A 03-Sep-21 49.00 structuras
SX8120 Montaje de barandas y soportes para tuberias 21-Sep-21 00:00 A 02-Oct-21 4.00 ontaje de barandas y soportes para tuberias
SX8130 Montaje porton de acceso 14-Nov-21 06:00 17-Nov-21 4.00 Montaje porton de acceso
Mecánica 10-Jun-21 06:00 A 12-Nov-21 156.00 12-Nov-21 17:00, Mecánica
MX6170 Completar montaje de equipos de lubricación 10-Jun-21 06:00 A 12-Nov-21 156.00 Completar montaje de equipos de lubricación
Civil 28-Aug-21 06:00 A 28-Aug-21 1.00
CX1635 Colocación de pernos quimicos (Actividad ejecutada por otra Contratista) 28-Aug-21 06:00 A 28-Aug-21 1.00s (Actividad ejecutada por otra Contratista)
Piping 07-Dec-21 06:00 20-Dec-21 14.00 20-Dec-21 17:00, Piping
PX7530 Instalación de agua contra incendios - lineas menores a 3" 07-Dec-21 06:00 20-Dec-21 14.00 Instalación de agua contra incendios - lineas menores a 3"
Chillers 17-Aug-21 00:00 A 31-Dec-21 137.00 31-Dec-21 17:00, Chillers
H9260 Culminación de instalación de Chiller 31-Dec-21 0.00 Culminación de instalación de Chiller,
Estructuras 28-Aug-21 06:00 A 28-Aug-21 1.00s
SX7550 Completar el montaje de estructuras y Grout (Actividad ejecutada por otra 28-Aug-21 06:00 A 28-Aug-21 1.00 cturas y Grout (Actividad ejecutada por otra Contratista)
SX7560 Desmontaje de estructuras y andamios (Actividad ejecutada por otra Cont 28-Aug-21 06:00 A 28-Aug-21 1.00 ndamios (Actividad ejecutada por otra Contratista)
Civil 28-Aug-21 06:00 A 28-Aug-21 1.00
CX1634 Montaje de pernos quimicos y vaciado de grout (Actividad ejecutada por o 28-Aug-21 06:00 A 28-Aug-21 1.00 vaciado de grout (Actividad ejecutada por otra Contratista)
Piping 17-Aug-21 00:00 A 08-Dec-21 130.00 08-Dec-21 17:00, Piping
Chiller a Bomba Chiller
Chi 17-Aug-21 00:00 A 24-Nov-21 100.00 24-Nov-21 17:00, Chiller a Bomba Chiller
PX7560 Completar instalación de Linea 8''- 0310-CW-06020 desde Chiller a Bomb 17-Aug-21 00:00 A 09-Oct-21 25.00 Completar instalación de Linea 8''- 0310-CW-06020 desde Chiller a Bomba
PX7580 Completar instalación de Linea 8''- 0310-CR-06117 desde Chiller a Bomba 17-Aug-21 00:00 A 09-Oct-21 25.00 Completar instalación de Linea 8''- 0310-CR-06117 desde Chiller a Bomba
PX7590 Prueba Hidrostatica Linea 8''- 0310-CW-06020 15-Nov-21 06:00 19-Nov-21 5.00 Prueba Hidrostatica Linea 8''- 0310-CW-06020
PX7640 Limpieza (Flushing) Linea 8''- 0310-CW-06020 20-Nov-21 06:00 24-Nov-21 5.00 Limpieza (Flushing) Linea 8''- 0310-CW-06020
Bomba Chiller a Estator
Est del 3er Molino de Bolas 21-Aug-21 00:00 A 08-Dec-21 126.00 08-Dec-21 17:00, Bomba Chiller a Estator del 3er Molino de Bolas
PX7600 Completar instalación de Linea 8''- 0310-CW-06107 desde Bomba Chiller 21-Aug-21 00:00 A 09-Oct-21 51.00 Completar instalación de Linea 8''- 0310-CW-06107 desde Bomba Chiller a Eje B

Actual Level of Effort Actual Work Critical Remaining Work Page 9 of 20 TASK filter: All Activities
Primary Baseline Remaining Work Milestone © Oracle Corporation
Cronograma del Proyecto: Construccion e Instalacion del 3er Molino de Bolas y Obras Asociadas
Linea Base 1 Rev. 0 (actualizado al 22-octubre)
Activity ID Activity Name Start Finish Original October 2021 November 2021 December 2021 January 2022 February 2022 March 2022 April 2022 May 2022 June 2022 July 2022
Duration
09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 05 12 19 26 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 02 09 6
PX7620 Completar instalación de Linea 8''- 0310-CR-06117 desde Bomba Chiller a 21-Aug-21 00:00 A 09-Oct-21 51.00 Completar instalación de Linea 8''- 0310-CR-06117 desde Bomba Chiller a Eje B
PX7601 Completar instalación de Linea 8''- 0310-CW-06107 desde Eje B a Estator 04-Sep-21 06:00 A 10-Nov-21 10.00 Completar instalación de Linea 8''- 0310-CW-06107 desde Eje B a Estator
PX7621 Completar instalación de Linea 8''- 0310-CR-06117 desde Eje B a Estator 04-Sep-21 06:00 A 10-Nov-21 10.00 Completar instalación de Linea 8''- 0310-CR-06117 desde Eje B a Estator
PX7650 Limpieza (Flushing) - Lineas 8''- 0310-CW-06107 y 8''- 0310-CR-06117 25-Nov-21 06:00 29-Nov-21 5.00 Limpieza (Flushing) - Lineas 8''- 0310-CW-06107 y 8''- 0310-CR-06117
PX7630 Prueba Hidrostatica - Lineas 8''- 0310-CW-06107 y 8''- 0310-CR-06117 30-Nov-21 06:00 04-Dec-21 5.00 Prueba Hidrostatica - Lineas 8''- 0310-CW-06107 y 8''- 0310-CR-06117
PX7610 Completar el recorrido de linea 1"-0310-CW-06501 05-Dec-21 06:00 08-Dec-21 4.00 Completar el recorrido de linea 1"-0310-CW-06501
Mecánica 13-Nov-21 06:00 19-Nov-21 7.00 19-Nov-21 17:00, Mecánica
MX7660 Montaje - Chiller #15 0310-CCW-0015 (pendiente verificar observaciones 13-Nov-21 06:00 14-Nov-21 2.00 Montaje - Chiller #15 0310-CCW-0015 (pendiente verificar observaciones por QA/QC y Construccion)
MX7670 Montaje - Chiller #15 0310-CCW-0014 (pendiente verificar observaciones 13-Nov-21 06:00 17-Nov-21 5.00 Montaje - Chiller #15 0310-CCW-0014 (pendiente verificar observaciones por QA/QC y Construccion)
MX7680 Montaje - Bomba 0310-PPC-49 (pendiente verificar observaciones por QA 18-Nov-21 06:00 19-Nov-21 2.00 Montaje - Bomba 0310-PPC-49 (pendiente verificar observaciones por QA/QC y Construccion)
MX7690 Montaje - Bomba 0310-PPC-48 (pendiente verificar observaciones por QA 18-Nov-21 06:00 19-Nov-21 2.00 Montaje - Bomba 0310-PPC-48 (pendiente verificar observaciones por QA/QC y Construccion)
Electricidad e Instrumentacion
Instrume 28-Aug-21 06:00 A 31-Dec-21 126.00 31-Dec-21 17:00, Electricidad e Instrumentacion
Chillers Electrica 28-Aug-21 06:00 A 31-Dec-21 126.00 31-Dec-21 17:00, Chillers Electrica
EX7710 Instalación de cables desde Sala Electrica N° 1 a equipos Chiller (Actividad 28-Aug-21 06:00 A 28-Aug-21 1.00ala Electrica N° 1 a equipos Chiller (Actividad ejecutada por otra Contratista)
EX7740 Conexionado de Chiller #15 0310-CCW-0014 (pendiente verificar observa 16-Oct-21 06:00 A 16-Oct-21 6.00 Conexionado de Chiller #15 0310-CCW-0014 (pendiente verificar observaciones por QA/QC y Construccion)
EX7750 Conexionado de Chiller #15 0310-CCW-0015 (pendiente verificar observa 16-Oct-21 06:00 A 16-Oct-21 7.00 Conexionado de Chiller #15 0310-CCW-0015 (pendiente verificar observaciones por QA/QC y Construccion)
EX7780 Tie in 7013 : Completar aterramiento 16-Oct-21 06:00 A 16-Oct-21 2.00 Tie in 7013 : Completar aterramiento
EX7770 Test Run - Chillers - Energia desde Sala Electrica N° 1 17-Dec-21 06:00 26-Dec-21 10.00 Test Run - Chillers - Energia desde Sala Electrica N° 1
EX7790 Agregar tapas de bandejas 21-Dec-21 06:00 31-Dec-21 11.00 Agregar tapas de bandejas
Chiller instrumentación
instrumentac 25-Nov-21 06:00 16-Dec-21 22.00 16-Dec-21 17:00, Chiller instrumentación
IX6352 Verificar la Instalacion de instrumentos de medición (temperatura , presion 25-Nov-21 06:00 30-Nov-21 6.00 Verificar la Instalacion de instrumentos de medición (temperatura , presion y flujo)
IX7720 Conexionado de Bomba 0310-PPC-49 (pendiente verificar observaciones 04-Dec-21 06:00 08-Dec-21 5.00 Conexionado de Bomba 0310-PPC-49 (pendiente verificar observaciones por QA/QC y Construccion)
IX7730 Conexionado de Bomba 0310-PPC-48 (pendiente verificar observaciones 12-Dec-21 06:00 16-Dec-21 5.00 Conexionado de Bomba 0310-PPC-48 (pendiente verificar observaciones por QA/QC y Construccion)
Ball Charge 05-Jan-22 06:00 20-Feb-22 47.00 20-Feb-22 17:00, Ball Charge
Structural 05-Jan-22 06:00 04-Feb-22 31.00 04-Feb-22 17:00, Structural
SX1631 Desmontaje de estructuras (eje 9-10 del eje D 4to nivel) 05-Jan-22 06:00 08-Jan-22 4.00 Desmontaje de estructuras (eje 9-10 del eje D 4to nivel)
SX1220 Install Cleats for Structural Steel Deck Level 09-Jan-22 06:00 14-Jan-22 6.00 Install Cleats for Structural Steel Deck Level
SX1560 Install Structural Steel Deck Level 12-Jan-22 06:00 16-Jan-22 5.00 Install Structural Steel Deck Level
SX1570 Install Hand Rail and Kick Plates Deck Level 17-Jan-22 06:00 19-Jan-22 3.00 Install Hand Rail and Kick Plates Deck Level
SX1580 Install Grid Mesh Deck Level 20-Jan-22 06:00 22-Jan-22 3.00 Install Grid Mesh Deck Level
SX1590 Install Conveyor frame Deck Level 22-Jan-22 06:00 26-Jan-22 5.00 Install Conveyor frame Deck Level
SX1730 New Ball diversion gate & tie in piping 27-Jan-22 06:00 04-Feb-22 9.00 New Ball diversion gate & tie in piping
Mechanical 22-Jan-22 06:00 08-Feb-22 18.00 08-Feb-22 17:00, Mechanical
MX1230 Installation of New Ball Chute Mill # 3 (0240-STP-0255) 22-Jan-22 06:00 30-Jan-22 9.00 Installation of New Ball Chute Mill # 3 (0240-STP-0255)
MX1600 Prepare Head Pully and Frame 31-Jan-22 06:00 08-Feb-22 9.00 Prepare Head Pully and Frame
Plateworks-1 09-Feb-22 06:00 20-Feb-22 12.00 20-Feb-22 17:00, Plateworks-1
Ball Mill N°2 09-Feb-22 06:00 16-Feb-22 8.00 16-Feb-22 17:00, Ball Mill N°2
MX1480 Chute de alimentación Molino de Bolas N°2 - 0240-STP-0254 (Trabajos pr 09-Feb-22 06:00 12-Feb-22 4.00 Chute de alimentación Molino de Bolas N°2 - 0240-STP-0254 (Trabajos previos)
MX1490 Chute de desvio Molino de Bolas N°2 - 0240-STP-0253 (Trabajos previos) 13-Feb-22 06:00 16-Feb-22 4.00 Chute de desvio Molino de Bolas N°2 - 0240-STP-0253 (Trabajos previos)
Ball Mill N°3 17-Feb-22 06:00 20-Feb-22 4.00 20-Feb-22 17:00, Ball Mill N°3
MX1470 0240-STP-0255: Ball Mill N°3 Ball Feed Chute 17-Feb-22 06:00 20-Feb-22 4.00 0240-STP-0255: Ball Mill N°3 Ball Feed Chute
E&I 22-Jan-22 06:00 07-Feb-22 17.00 07-Feb-22 17:00, E&I
EX-0501 Extension de bandejas portacable 22-Jan-22 06:00 24-Jan-22 3.00 Extension de bandejas portacable
EX-0500-1610 Instalación de nuevo cable de fuerza para motor controlador 25-Jan-22 06:00 28-Jan-22 4.00 Instalación de nuevo cable de fuerza para motor controlador
IX6354 Reubicación e Instalación de instrumentación, transmisores de presión e in 29-Jan-22 06:00 07-Feb-22 10.00 Reubicación e Instalación de instrumentación, transmisores de presión e instrumentos de seuguridad
Slurry Pipeline & Pumps 21-Jun-21 06:00 A 21-Mar-22 274.00 21-Mar-22 17:00, Slurry Pipeline & Pumps
SX6349 Desmontaje de estructuras 15-Feb-22 06:00 16-Feb-22 2.00 Desmontaje de estructuras
EX1637 Trabajos electricos previos 19-Feb-22 06:00 19-Feb-22 1.00 Trabajos electricos previos
H8021 Finalización de tuberias de alimentación a ciclones 21-Mar-22 0.00 Finalización de tuberias de alimentación a ciclones,
Civil 15-Feb-22 06:00 16-Feb-22 2.00 16-Feb-22 17:00, Civil
CX1645 Soporte de tuberías 15-Feb-22 06:00 15-Feb-22 1.00 Soporte de tuberías
CX1646 Base de Bombas 16-Feb-22 06:00 16-Feb-22 1.00 Base de Bombas
Slurry Pipe Line 1 10-Feb-22 06:00 19-Feb-22 10.00 19-Feb-22 17:00, Slurry Pipe Line 1
Civil 10-Feb-22 06:00 10-Feb-22 1.00 10-Feb-22 17:00, Civil
CX1200 Demo Concrete Cut Floor For New Pipe Size 10-Feb-22 06:00 10-Feb-22 1.00 Demo Concrete Cut Floor For New Pipe Size
Piping 11-Feb-22 06:00 15-Feb-22 5.00 15-Feb-22 17:00, Piping
PX1425 Position Support Structural frame 11-Feb-22 06:00 11-Feb-22 1.00 Position Support Structural frame
PX1430 Pre Assembly Pipe line in Construction Zone 12-Feb-22 06:00 12-Feb-22 1.00 Pre Assembly Pipe line in Construction Zone
PX1440 Remove anchors brackets every 2nd bolt 15-Feb-22 06:00 15-Feb-22 1.00 Remove anchors brackets every 2nd bolt
Mechanical 17-Feb-22 13:00 18-Feb-22 1.00 18-Feb-22 13:00, Mechanical
MX1680 Pump Speed Operational Flow 17-Feb-22 13:00 18-Feb-22 1.00 Pump Speed Operational Flow
Estructuras 15-Feb-22 06:00 19-Feb-22 5.00 19-Feb-22 17:00, Estructuras
SX6350 Montaje de plataforma y escalera Linea 1 15-Feb-22 06:00 19-Feb-22 5.00 Montaje de plataforma y escalera Linea 1
Slurry Pipe Line 2 21-Jun-21 06:00 A 25-Nov-21 156.00 25-Nov-21 17:00, Slurry Pipe Line 2

Actual Level of Effort Actual Work Critical Remaining Work Page 10 of 20 TASK filter: All Activities
Primary Baseline Remaining Work Milestone © Oracle Corporation
Cronograma del Proyecto: Construccion e Instalacion del 3er Molino de Bolas y Obras Asociadas
Linea Base 1 Rev. 0 (actualizado al 22-octubre)
Activity ID Activity Name Start Finish Original October 2021 November 2021 December 2021 January 2022 February 2022 March 2022 April 2022 May 2022 June 2022 July 2022
Duration
09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 05 12 19 26 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 02 09 6
Estructuras 17-Nov-21 06:00 23-Nov-21 7.00 23-Nov-21 17:00, Estructuras
SX6362 Montaje de plataforma y escalera 17-Nov-21 06:00 23-Nov-21 7.00 Montaje de plataforma y escalera
Piping 21-Jun-21 06:00 A 25-Nov-21 149.00 25-Nov-21 17:00, Piping
PX6352 Montaje de Spool de 12''-0310-WP-06523 (prueba de vavula en parada d 21-Jun-21 06:00 A 25-Nov-21 149.00 Montaje de Spool de 12''-0310-WP-06523 (prueba de vavula en parada de planta)
Slurry Pipe Line 3 24-Jul-21 06:00 A 02-Dec-21 130.00 02-Dec-21 17:00, Slurry Pipe Line 3
Estructuras 24-Nov-21 06:00 30-Nov-21 7.00 30-Nov-21 17:00, Estructuras
SX6361 Montaje de plataforma y escalera 24-Nov-21 06:00 30-Nov-21 7.00 Montaje de plataforma y escalera
Piping 24-Jul-21 06:00 A 02-Dec-21 116.00 02-Dec-21 17:00, Piping
PX6350 Montaje de Spool de 12''-0310-WP-06524 (prueba de vavula en parada d 24-Jul-21 06:00 A 02-Dec-21 116.00 Montaje de Spool de 12''-0310-WP-06524 (prueba de vavula en parada de planta)
Slurry Pipe Line 4 11-Feb-22 06:00 23-Feb-22 13.00 23-Feb-22 17:00, Slurry Pipe Line 4
Civil 11-Feb-22 06:00 11-Feb-22 1.00 11-Feb-22 17:00, Civil
CX1270 Demo Concrete Cut Floor For New Pipe Size 11-Feb-22 06:00 11-Feb-22 1.00 Demo Concrete Cut Floor For New Pipe Size
Piping 12-Feb-22 06:00 18-Feb-22 7.00 18-Feb-22 17:00, Piping
PX1195 Position Support Structural frame 12-Feb-22 06:00 12-Feb-22 1.00 Position Support Structural frame
PX1200 Pre Assembly Pipe line in Construction Zone 13-Feb-22 06:00 13-Feb-22 1.00 Pre Assembly Pipe line in Construction Zone
PX1210 Remove anchors brackets every 2nd bolt 18-Feb-22 06:00 18-Feb-22 1.00 Remove anchors brackets every 2nd bolt
Mecanica 20-Feb-22 06:00 23-Feb-22 4.00 23-Feb-22 17:00, Mecanica
MX1690 Pump Speed Operational Flow 20-Feb-22 06:00 23-Feb-22 4.00 Pump Speed Operational Flow
Estructuras 18-Feb-22 06:00 22-Feb-22 5.00 22-Feb-22 17:00, Estructuras
SX8110 Montaje de plataforma y escalera - Linea 4 18-Feb-22 06:00 22-Feb-22 5.00 Montaje de plataforma y escalera - Linea 4
Slurry Pump 1 17-Feb-22 06:00 18-Mar-22 30.00 18-Mar-22 17:00, Slurry Pump 1
Civil 24-Feb-22 06:00 06-Mar-22 11.00 06-Mar-22 17:00, Civil
CX-2540 Demolicion de estructuras menores - Slurry Pump #1 24-Feb-22 06:00 28-Feb-22 5.00 Demolicion de estructuras menores - Slurry Pump #1
CX-2550 Colocacion de acero - pedestales 26-Feb-22 06:00 01-Mar-22 4.00 Colocacion de acero - pedestales
CX-2570 Instalacion de microclima 02-Mar-22 06:00 02-Mar-22 1.00 Instalacion de microclima
CX-2580 Vaciado de concreto - Bateas 02-Mar-22 06:00 02-Mar-22 1.00 Vaciado de concreto - Bateas
CX-2590 Encofrado de Pedestales 03-Mar-22 06:00 05-Mar-22 3.00 Encofrado de Pedestales
CX-2600 Vaciado de concreto - Pedestales 06-Mar-22 06:00 06-Mar-22 1.00 Vaciado de concreto - Pedestales
Piping 04-Mar-22 06:00 06-Mar-22 3.00 06-Mar-22 17:00, Piping
MX1491 Prepare 660 Pump and coupling 04-Mar-22 06:00 06-Mar-22 3.00 Prepare 660 Pump and coupling
Structures 17-Feb-22 06:00 15-Mar-22 27.00 15-Mar-22 17:00, Structures
SX6380 Desmontaje de plataforma existente 17-Feb-22 06:00 23-Feb-22 7.00 Desmontaje de plataforma existente
SX1160 Montaje de la nueva plataforma de operaciones 07-Mar-22 06:00 13-Mar-22 7.00 Montaje de la nueva plataforma de operaciones
SX1170 Desmontaje de andamios y limpieza del area 14-Mar-22 06:00 15-Mar-22 2.00 Desmontaje de andamios y limpieza del area
Electrica 04-Mar-22 06:00 18-Mar-22 15.00 18-Mar-22 17:00, Electrica
EX16640 Canalización conduit y cableado para bomba linea 1 04-Mar-22 06:00 18-Mar-22 15.00 Canalización conduit y cableado para bomba linea 1
IX6650 Cotrastacion de valvulas de 12'' 04-Mar-22 06:00 06-Mar-22 3.00 Cotrastacion de valvulas de 12''
Slurry Pump 4 21-Feb-22 06:00 18-Mar-22 26.00 18-Mar-22 17:00, Slurry Pump 4
Civil 28-Feb-22 06:00 10-Mar-22 11.00 10-Mar-22 17:00, Civil
CX4890 Demolicion de estructuras menores - Slurry Pump #4 28-Feb-22 06:00 04-Mar-22 5.00 Demolicion de estructuras menores - Slurry Pump #4
CX2610 Colocacion de acero - pedestales 02-Mar-22 06:00 05-Mar-22 4.00 Colocacion de acero - pedestales
CX2620 Instalacion de microclima 06-Mar-22 06:00 06-Mar-22 1.00 Instalacion de microclima
CX2630 Vaciado de concreto - Bateas 06-Mar-22 06:00 06-Mar-22 1.00 Vaciado de concreto - Bateas
CX2640 Encofrado de Pedestales 07-Mar-22 06:00 09-Mar-22 3.00 Encofrado de Pedestales
CX2650 Vaciado de concreto - Pedestales 10-Mar-22 06:00 10-Mar-22 1.00 Vaciado de concreto - Pedestales
Piping 05-Mar-22 06:00 06-Mar-22 2.00 06-Mar-22 17:00, Piping
PX-0500-1390 Prepare 660 Pump and coupling 05-Mar-22 06:00 06-Mar-22 2.00 Prepare 660 Pump and coupling
Estructuras 21-Feb-22 06:00 17-Mar-22 25.00 17-Mar-22 17:00, Estructuras
SX6390 Desmontaje de plataforma de operaciones 21-Feb-22 06:00 27-Feb-22 7.00 Desmontaje de plataforma de operaciones
SX-0500-1140 Montaje de la nueva plataforma de operaciones 11-Mar-22 06:00 17-Mar-22 7.00 Montaje de la nueva plataforma de operaciones
SX-0500-1150 Armado de andamios para acceder a los trabajos 11-Mar-22 06:00 12-Mar-22 2.00 Armado de andamios para acceder a los trabajos
Electrica 04-Mar-22 06:00 18-Mar-22 15.00 18-Mar-22 17:00, Electrica
EX6640 Canalización conduit y cableado para bomba linea 4 04-Mar-22 06:00 18-Mar-22 15.00 Canalización conduit y cableado para bomba linea 4
EX6650 Contrastacion de valvulas de 12'' 04-Mar-22 06:00 06-Mar-22 3.00 Contrastacion de valvulas de 12''
Line Services 21-Jun-21 06:00 A 19-Mar-22 272.00 19-Mar-22 17:00, Line Services
H7660 Llega de equipo Hidrolavadora y accesorios para pruebas 01-Oct-21 06:00 A 0.00ga de equipo Hidrolavadora y accesorios para pruebas, 01-Oct-21 06:00 A
H16560 Ingenieria de tuberias menores e igual a 3" (recorridos, isometrico y metrad 23-Oct-21 0.00 Ingenieria de tuberias menores e igual a 3" (recorridos, isometrico y metrados),
H16570 Llegada de materiales para tuberia menores a 3" (AI, AP,LOH,LR) 06-Dec-21 0.00 Llegada de materiales para tuberia menores a 3" (AI, AP,LOH,LR),
H9250 Culminación de lineas de servicio 19-Mar-22 0.00 Culminación de lineas de servicio,
Lineas temporales y a remover
r 29-Dec-21 06:00 08-Jan-22 11.00 08-Jan-22 17:00, Lineas temporales y a remover
PX1635 Lineas de servicio temporales (lehada de cal 2pul) 29-Dec-21 06:00 07-Jan-22 10.00 Lineas de servicio temporales (lehada de cal 2pul)
PX1636 Lineas de servicio a remover (Lechada de cal 6 pul) 30-Dec-21 06:00 08-Jan-22 10.00 Lineas de servicio a remover (Lechada de cal 6 pul)
Sistema de agua contra incendios 21-Jun-21 06:00 A 20-Dec-21 183.00 20-Dec-21 17:00, Sistema de agua contra incendios
PX8280 Desmontaje de tuberias de sistema contraincendio 18-Oct-21 06:00 A 21-Nov-21 15.00 Desmontaje de tuberias de sistema contraincendio
Mecanica 16-Oct-21 06:00 A 20-Dec-21 57.00 20-Dec-21 17:00, Mecanica

Actual Level of Effort Actual Work Critical Remaining Work Page 11 of 20 TASK filter: All Activities
Primary Baseline Remaining Work Milestone © Oracle Corporation
Cronograma del Proyecto: Construccion e Instalacion del 3er Molino de Bolas y Obras Asociadas
Linea Base 1 Rev. 0 (actualizado al 22-octubre)
Activity ID Activity Name Start Finish Original October 2021 November 2021 December 2021 January 2022 February 2022 March 2022 April 2022 May 2022 June 2022 July 2022
Duration
09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 05 12 19 26 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 02 09 6
MX-0500-1170 Trabajos previos para los tie in de SCI 16-Oct-21 06:00 A 19-Nov-21 7.00 Trabajos previos para los tie in de SCI
H1180 Culminación de Sistema de agua contra incendios 20-Dec-21 0.00 Culminación de Sistema de agua contra incendios,
Piping 21-Jun-21 06:00 A 10-Dec-21 173.00 10-Dec-21 17:00, Piping
Lineas de 3 07-Aug-21 06:00 A 10-Dec-21 126.00 10-Dec-21 17:00, Lineas de 3
PX6670 Habilitado de tuberia de 3 pul 07-Aug-21 06:00 A 11-Nov-21 44.00 Habilitado de tuberia de 3 pul
PX6720 Completar recorrido de Linea 3"-0310-WF-06552-C1F2A-NI 14-Aug-21 00:00 A 16-Nov-21 42.00 Completar recorrido de Linea 3"-0310-WF-06552-C1F2A-NI
PX6710 Completar recorrido de Linea 3"-0310-WF-06551-C1F2A-WI 15-Aug-21 00:00 A 18-Nov-21 48.00 Completar recorrido de Linea 3"-0310-WF-06551-C1F2A-WI
PX6700 Completar recorrido de Linea 3"-0310-WF-06200-C1F2A-WI 28-Aug-21 00:00 A 21-Nov-21 41.00 Completar recorrido de Linea 3"-0310-WF-06200-C1F2A-WI
PX6690 Completar recorrido de Linea 3"-0310-WF-06119-C1F2A-WI 30-Aug-21 00:00 A 21-Nov-21 39.00 Completar recorrido de Linea 3"-0310-WF-06119-C1F2A-WI
PX6680 Completar recorrido de Linea 3"-0310-WF-06112-C1F2A-WI 11-Oct-21 06:00 A 11-Nov-21 6.00 Completar recorrido de Linea 3"-0310-WF-06112-C1F2A-WI
H9016 Llegada de materiales para tuberia menores a 3" de SCI 30-Oct-21 06:00* 0.00 Llegada de materiales para tuberia menores a 3" de SCI, 30-Oct-21 06:00*
PX8290 Prueba hidrostatica de tuberias de SC 19-Nov-21 06:00 25-Nov-21 7.00 Prueba hidrostatica de tuberias de SC
PX8300 Instalacion de aislamiento de tuberias de SC 04-Dec-21 06:00 10-Dec-21 7.00 Instalacion de aislamiento de tuberias de SC
Lineas de 4 21-Jun-21 06:00 A 28-Nov-21 161.00 28-Nov-21 17:00, Lineas de 4
PX6610 Habilitado de tuberia de 4 pul 21-Jun-21 06:00 A 23-Jul-21 1 33.00
PX6640 Completar recorrido de Linea 4 ''-310-WF-06125-C1F2A 14-Aug-21 00:00 A 16-Oct-21 26.00 Completar recorrido de Linea 4 ''-310-WF-06125-C1F2A
PX6630 Completar recorrido de Linea 4 ''-310-WF-06110- C1F2A 21-Aug-21 00:00 A 16-Oct-21 24.00 Completar recorrido de Linea 4 ''-310-WF-06110- C1F2A
PX6620 Completar recorrido de Linea 4 ''-310-WF-06102-C1F2A 21-Aug-21 06:00 A 17-Oct-21 24.00 Completar recorrido de Linea 4 ''-310-WF-06102-C1F2A
PX6650 Completar recorrido de Linea 4 ''-310-WF-06563-C1F2A 26-Aug-21 00:00 A 16-Oct-21 24.00 Completar recorrido de Linea 4 ''-310-WF-06563-C1F2A
PX6660 Completar recorrido de Linea 4 ''-310-WF-06564-C1F2A 02-Sep-21 00:00 A 17-Oct-21 22.00 Completar recorrido de Linea 4 ''-310-WF-06564-C1F2A
PX8310 Prueba hidrostatica de tuberias 4" de SC 15-Oct-21 06:00 A 16-Oct-21 4.00 Prueba hidrostatica de tuberias 4" de SC
PX8320 Instalacion de aislamiento de tuberias 4" de SC 22-Nov-21 06:00 28-Nov-21 7.00 Instalacion de aislamiento de tuberias 4" de SC
Lineas de 6 01-Sep-21 00:00 A 03-Dec-21 94.00 03-Dec-21 17:00, Lineas de 6
PX8330 Prueba hidrostatica de tuberias 6" de SC 15-Oct-21 06:00 A 17-Oct-21 4.00 Prueba hidrostatica de tuberias 6" de SC
PX8340 Instalacion de aislamiento de tuberias 6" de SC 29-Nov-21 06:00 03-Dec-21 5.00 Instalacion de aislamiento de tuberias 6" de SC
Tuberia de Ace
Acero 01-Sep-21 00:00 A 17-Oct-21 60.00 17-Oct-21 17:00 A, Tuberia de Acero
PX6740 Habilitado Montaje de tuberia de acero 6"-0310-WF-06100-C1F2A-WI 01-Sep-21 00:00 A 16-Oct-21 21.00 Habilitado Montaje de tuberia de acero 6"-0310-WF-06100-C1F2A-WI
PX6750 Habilitado Montaje de acero 6''-0921-WF-06150-C1F2A-NI 16-Oct-21 06:00 A 17-Oct-21 7.00 Habilitado Montaje de acero 6''-0921-WF-06150-C1F2A-NI
Tuberia HDPE 12-Oct-21 06:00 A 11-Nov-21 27.00 11-Nov-21 17:00, Tuberia HDPE
PX6780 Habilitado y Montaje de tuberia HDPE 6''-0921-WF-06650-M2FOH-NI (seg 12-Oct-21 06:00 A 17-Oct-21 2.00 Habilitado y Montaje de tuberia HDPE 6''-0921-WF-06650-M2FOH-NI (segun redline)
PX6790 Habilitado y Montaje de tuberia HDPE 6''-0921-WF-06651-M2FOH-NI (seg 12-Oct-21 06:00 A 17-Oct-21 2.00 Habilitado y Montaje de tuberia HDPE 6''-0921-WF-06651-M2FOH-NI (segun redline)
H16540 Llegada de Sub contratista para termofusion 12-Oct-21 0.00 Llegada de Sub contratista para termofusion,
PX6760 Habilitado y Montaje de tuberia HDPE 6''-0921-WF-06640-M2FOH-NI 06-Nov-21 06:00 11-Nov-21 6.00 Habilitado y Montaje de tuberia HDPE 6''-0921-WF-06640-M2FOH-NI
PX6770 Habilitado y Montaje de tuberia HDPE 6''-0921-WF-06611-M2FOH-NI (inc 06-Nov-21 06:00 09-Nov-21 4.00 Habilitado y Montaje de tuberia HDPE 6''-0921-WF-06611-M2FOH-NI (inc Excavacion)
Lechada de Cal 30-Jun-21 06:00 A 03-Jan-22 188.00 03-Jan-22 17:00, Lechada de Cal
H8010 Culminación de linea de Lechada de Cal 25-Dec-21 0.00 Culminación de linea de Lechada de Cal,
Lechada de Cal - Lin
Linea 1 30-Jun-21 06:00 A 06-Nov-21 130.00 06-Nov-21 17:00, Lechada de Cal - Linea 1
Ciclone 4to nivel 30-Jun-21 06:00 A 06-Nov-21 130.00 06-Nov-21 17:00, Ciclone 4to nivel
PX1820 Insltación de linea 0391-ML-06309 (Plug Valve x 1 TAG : 0391V2130) 30-Jun-21 06:00 A 02-Jul-21 1 3.00
PX1870 Insltación de linea 0391-ML-06416 (Plug Valve x 2 TAG : 0391V2168 / 03 30-Jun-21 06:00 A 05-Nov-21 79.00 Insltación de linea 0391-ML-06416 (Plug Valve x 2 TAG : 0391V2168 / 0391V2216)
PX1830 Insltación de linea 0391-ML-06310 (Plug Valve x 2 TAG : 0391V2072 / 03 02-Nov-21 06:00 06-Nov-21 5.00 Insltación de linea 0391-ML-06310 (Plug Valve x 2 TAG : 0391V2072 / 0391V2073)
Lechada de Cal - Lin
Linea 2 28-Aug-21 00:00 A 28-Nov-21 93.00 28-Nov-21 17:00, Lechada de Cal - Linea 2
Extención del Edificio
Edi 28-Aug-21 00:00 A 28-Nov-21 93.00 28-Nov-21 17:00, Extención del Edificio
PX1840 Instalación de linea 0391-ML-06332 28-Aug-21 00:00 A 20-Nov-21 31.00 Instalación de linea 0391-ML-06332
PX1880 Instalación de linea 0391-ML-06418 (Plug Valve x 2 TAG : 0391V2076 / 0 21-Nov-21 06:00 25-Nov-21 5.00 Instalación de linea 0391-ML-06418 (Plug Valve x 2 TAG : 0391V2076 / 0391V2077)
PX1890 Instalación de linea 0391-ML-06510 (Plug Valve x 2 TAG : 0391V2163 / 0 24-Nov-21 06:00 28-Nov-21 5.00 Instalación de linea 0391-ML-06510 (Plug Valve x 2 TAG : 0391V2163 / 0391V2211)
Lechada de Cal - Lin
Linea 3 28-Aug-21 00:00 A 04-Dec-21 99.00 04-Dec-21 17:00, Lechada de Cal - Linea 3
Extención del Edificio
Edi 28-Aug-21 00:00 A 04-Dec-21 99.00 04-Dec-21 17:00, Extención del Edificio
PX1850 Instalación de linea 0391-ML-06333 28-Aug-21 00:00 A 20-Nov-21 38.00 Instalación de linea 0391-ML-06333
PX1920 Instalación de linea 0391-ML-06514 (Plug Valve x 2 TAG : 0391V2214 / 0 26-Nov-21 06:00 29-Nov-21 4.00 Instalación de linea 0391-ML-06514 (Plug Valve x 2 TAG : 0391V2214 / 0391V2166)
PX1930 Instalación de linea 0391-ML-06515 (Plug Valve x 2 TAG : 0391V2213 / 0 28-Nov-21 06:00 30-Nov-21 3.00 Instalación de linea 0391-ML-06515 (Plug Valve x 2 TAG : 0391V2213 / 0391V2165)
PX1940 Instalación de linea 0391-ML-06517 (Plug Valve x 2 TAG : 0391V2162 / 0 01-Dec-21 06:00 04-Dec-21 4.00 Instalación de linea 0391-ML-06517 (Plug Valve x 2 TAG : 0391V2162 / 0391V2210)
Lechada de Cal - Lin
Linea 4 31-Aug-21 00:00 A 13-Nov-21 75.00 13-Nov-21 17:00, Lechada de Cal - Linea 4
Extención del Edificio
Edi 31-Aug-21 00:00 A 13-Nov-21 75.00 13-Nov-21 17:00, Extención del Edificio
PX1860 Installation of pipe 0391-ML-06407 31-Aug-21 00:00 A 06-Nov-21 47.00 Installation of pipe 0391-ML-06407
PX1900 Installation of pipe 0391-ML-06511 (Plug Valve x 2 TAG : 0391V2215 / 03 07-Nov-21 06:00 11-Nov-21 5.00 Installation of pipe 0391-ML-06511 (Plug Valve x 2 TAG : 0391V2215 / 0391V2167)
PX1910 Installation of pipe 0391-ML-06513 (Plug Valve x 2 TAG : 0391V2164 / 03 10-Nov-21 06:00 13-Nov-21 4.00 Installation of pipe 0391-ML-06513 (Plug Valve x 2 TAG : 0391V2164 / 0391V2212)
Instrumentación 14-Nov-21 06:00 03-Jan-22 51.00 03-Jan-22 17:00, Instrumentación
IX6355 Instalación de Instrumentos - Lechada de cal Linea 1 14-Nov-21 06:00 23-Nov-21 10.00 Instalación de Instrumentos - Lechada de cal Linea 1
IX6371 Instalación de Instrumentos - Lechada de cal Linea 3 05-Dec-21 06:00 14-Dec-21 10.00 Instalación de Instrumentos - Lechada de cal Linea 3
IX6361 Instalación de Instrumentos - Lechada de cal Linea 2 15-Dec-21 06:00 24-Dec-21 10.00 Instalación de Instrumentos - Lechada de cal Linea 2
IX6381 Instalación de Instrumentos - Lechada de cal Linea 4 25-Dec-21 06:00 03-Jan-22 10.00 Instalación de Instrumentos - Lechada de cal Linea 4
Slurry (SL) 18-Jul-21 11:00 A 01-Mar-22 226.50 01-Mar-22 17:00, Slurry (SL)
PX3110 Installation of pipe 0310-SL-06716 (Plug Valve x 5 TAG :0310V2235 /0310 18-Jul-21 11:00 A 22-Feb-22 219.14 Installation of pipe 0310-SL-06716 (Plug Valve x 5 TAG :0310V2235 /0310V2236 / 0310V2237 / 0310V2238 / 0310

Actual Level of Effort Actual Work Critical Remaining Work Page 12 of 20 TASK filter: All Activities
Primary Baseline Remaining Work Milestone © Oracle Corporation
Cronograma del Proyecto: Construccion e Instalacion del 3er Molino de Bolas y Obras Asociadas
Linea Base 1 Rev. 0 (actualizado al 22-octubre)
Activity ID Activity Name Start Finish Original October 2021 November 2021 December 2021 January 2022 February 2022 March 2022 April 2022 May 2022 June 2022 July 2022
Duration
09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 05 12 19 26 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 02 09 6
PX3220 Installation of pipe 0310-SL-06711 (Plug Valve x 1 TAG :0310V2119) - 4hrs 18-Jul-21 20:00 A 22-Feb-22 218.43 Installation of pipe 0310-SL-06711 (Plug Valve x 1 TAG :0310V2119) - 4hrs
PX3130 Installation of pipe 0310-SL-06718 (Plug Valve x 1 TAG : 0310V2118) 19-Jul-21 19:00 A 15-Feb-22 210.46 Installation of pipe 0310-SL-06718 (Plug Valve x 1 TAG : 0310V2118)
PX3230 Installation of pipe 0310-SL-06712 (Plug Valve x 1 TAG :0310V2135) 26-Nov-21 06:00 29-Nov-21 4.00 Installation of pipe 0310-SL-06712 (Plug Valve x 1 TAG :0310V2135)
PX3270 Instalación de densimetro y flujometro sonar linea 0310-SL-06712 26-Nov-21 06:00 26-Nov-21 1.00 Instalación de densimetro y flujometro sonar linea 0310-SL-06712
PX3140 Installation of pipe 0310-SL-06201 15-Feb-22 06:00 15-Feb-22 0.17 Installation of pipe 0310-SL-06201
PX3250 Installation of pipe 0310-SL-06714 15-Feb-22 06:00 15-Feb-22 0.17 Installation of pipe 0310-SL-06714
PX3150 Installation of pipe 0310-SL-06204 15-Feb-22 10:05 17-Feb-22 1.67 Installation of pipe 0310-SL-06204
PX3160 Installation of pipe 0310-SL-06301 17-Feb-22 02:10 18-Feb-22 1.67 Installation of pipe 0310-SL-06301
PX3260 Installation of pipe 0310-SL-06715 (Plug Valve x 3 TAG :0310V2177 / 0310 18-Feb-22 06:00 18-Feb-22 0.17 Installation of pipe 0310-SL-06715 (Plug Valve x 3 TAG :0310V2177 / 0310V2178 / 0310V2179) - 4hrs
PX3170 Installation of pipe 0310-SL-06202 (Plug Valve x 1 TAG : 310V2100) - 24hr 18-Feb-22 18:15 18-Feb-22 0.17 Installation of pipe 0310-SL-06202 (Plug Valve x 1 TAG : 310V2100) - 24hrs SD#7
PX3180 Installation of pipe 0310-SL-06302 18-Feb-22 22:20 20-Feb-22 1.67 Installation of pipe 0310-SL-06302
PX3200 Installation of pipe 0310-SL-06504 (Plug Valve x 1 TAG : 0310V2101) - 4h 19-Feb-22 17:00 19-Feb-22 0.15 Installation of pipe 0310-SL-06504 (Plug Valve x 1 TAG : 0310V2101) - 4hrs SD#7
PX3190 Installation of pipe 0310-SL-06503 20-Feb-22 14:25 22-Feb-22 1.67 Installation of pipe 0310-SL-06503
PX3210 Installation of pipe 0310-SL-06505 20-Feb-22 14:25 22-Feb-22 1.67 Installation of pipe 0310-SL-06505
PX3120 Installation of pipe 0310-SL-06717 (Plug Valve x 1 TAG : 0310V2169) - 4h 22-Feb-22 06:25 22-Feb-22 0.17 Installation of pipe 0310-SL-06717 (Plug Valve x 1 TAG : 0310V2169) - 4hrs
PX3240 Installation of pipe 0310-SL-06713 (Plug Valve x 1 TAG :0310V2176) - 4hrs 22-Feb-22 10:25 22-Feb-22 0.17 Installation of pipe 0310-SL-06713 (Plug Valve x 1 TAG :0310V2176) - 4hrs
Lineas a remover (SL)
(S 26-Feb-22 06:00 01-Mar-22 4.00 01-Mar-22 17:00, Lineas a remover (SL)
PX6353 Lineas de Slurry a remover 26-Feb-22 06:00 01-Mar-22 4.00 Lineas de Slurry a remover
Aire de instrumentación (AI) 21-Jul-21 06:00 A 19-Nov-21 122.00 19-Nov-21 17:00, Aire de instrumentación (AI)
PX1970 Installation of pipe 1.5"-0310-AI-06982 (Ball Valve x 1 TAG: 0310V2114) 21-Jul-21 06:00 A 21-Jul-21 1 1.00 10V2114)
PX1980 Installation of pipe 4"-0310-AI-06983 (Butterfly Valve x 2 TAG: 0310V2152 14-Nov-21 06:00 15-Nov-21 2.00 Installation of pipe 4"-0310-AI-06983 (Butterfly Valve x 2 TAG: 0310V2152 / 0310V2155)
PX1950 Installation of pipe 1"-0310-AI-06980 (Ball Valve x 1 TAG: 0310V2071) 16-Nov-21 06:00 17-Nov-21 2.00 Installation of pipe 1"-0310-AI-06980 (Ball Valve x 1 TAG: 0310V2071)
PX1960 Installation of pipe 1.5"-0310-AI-06981 (Ball Valve x 1 TAG: 0310V2070) 18-Nov-21 06:00 19-Nov-21 2.00 Installation of pipe 1.5"-0310-AI-06981 (Ball Valve x 1 TAG: 0310V2070)
PX1990 Installation of pipe 1.5"-0310-AI-06984 (Ball Valve x 1 TAG: 0310V2150) 18-Nov-21 06:00 19-Nov-21 2.00 Installation of pipe 1.5"-0310-AI-06984 (Ball Valve x 1 TAG: 0310V2150)
Aire de planta (AP) 20-Nov-21 06:00 26-Nov-21 7.00 26-Nov-21 17:00, Aire de planta (AP)
PX2020 Installation of pipe 6"-0310-AP-06901 (Butterfly Valve x 2 TAG: 0310V2067 20-Nov-21 06:00 20-Nov-21 1.00 Installation of pipe 6"-0310-AP-06901 (Butterfly Valve x 2 TAG: 0310V2067 / 0310V2106)
PX2030 Installation of pipe 2"-0310-AP-06950 (Ball Valve x 1 TAG: 0310V2064) 21-Nov-21 06:00 21-Nov-21 1.00 Installation of pipe 2"-0310-AP-06950 (Ball Valve x 1 TAG: 0310V2064)
PX2040 Installation of pipe 2"-0310-AP-06951 (Ball Valve x 1 TAG: 0310V2065) 22-Nov-21 06:00 22-Nov-21 1.00 Installation of pipe 2"-0310-AP-06951 (Ball Valve x 1 TAG: 0310V2065)
PX2050 Installation of pipe 2"-0310-AP-06952 (Ball Valve x 1 TAG: 0310V2066) 23-Nov-21 06:00 23-Nov-21 1.00 Installation of pipe 2"-0310-AP-06952 (Ball Valve x 1 TAG: 0310V2066)
PX2060 Installation of pipe 2"-0310-AP-06954 (Ball Valve x 1 TAG: 0310V2068) 24-Nov-21 06:00 24-Nov-21 1.00 Installation of pipe 2"-0310-AP-06954 (Ball Valve x 1 TAG: 0310V2068)
PX2070 Installation of pipe 2"-0310-AP-06955 (Ball Valve x 1 TAG: 0310V2069) 25-Nov-21 06:00 25-Nov-21 1.00 Installation of pipe 2"-0310-AP-06955 (Ball Valve x 1 TAG: 0310V2069)
PX2080 Installation of pipe 2"-0310-AP-06956 (Ball Valve x 1 TAG: 0310V2244) 26-Nov-21 06:00 26-Nov-21 1.00 Installation of pipe 2"-0310-AP-06956 (Ball Valve x 1 TAG: 0310V2244)
Retorno de lineas de agua
ag fria (CR) 30-Aug-21 00:00 A 06-Mar-22 189.00 06-Mar-22 17:00, Retorno de lineas de agua fria (CR)
PX2190 Instalacion de linea de 8''-0310-CR-06117 (Ball Valve x 1 TAG: 0310V2174 30-Aug-21 00:00 A 02-Oct-21 34.00 stalacion de linea de 8''-0310-CR-06117 (Ball Valve x 1 TAG: 0310V2174)
PX2160 Instalacion de linea de 4''-0310-CR-06101 04-Sep-21 06:00 A 11-Nov-21 6.00 Instalacion de linea de 4''-0310-CR-06101
PX2200 Instalacion de linea de 6''-0310-CR-06118 11-Sep-21 06:00 A 02-Oct-21 2.00 nstalacion de linea de 6''-0310-CR-06118
PX2170 Instalacion de linea de 6''-0310-CR-06103 11-Sep-21 06:00 A 02-Oct-21 2.00 Instalacion de linea de 6''-0310-CR-06103
PX2180 Instalacion de linea de 6''-0310-CR-06104 14-Sep-21 06:00 A 02-Oct-21 2.00 Instalacion de linea de 6''-0310-CR-06104
PX2210 Instalacion de linea de 4''-0310-CR-06401 11-Nov-21 13:00 21-Nov-21 10.00 Instalacion de linea de 4''-0310-CR-06401
PX2640 Limpieza fushing y prueba hidrostatica 21-Nov-21 13:00 26-Nov-21 5.00 Limpieza fushing y prueba hidrostatica
PX2220 Montaje de aislamiento para tuberia de 8''-0310-CR-06117 26-Nov-21 13:00 11-Dec-21 15.00 Montaje de aislamiento para tuberia de 8''-0310-CR-06117
PX2230 Montaje de aislamiento para tuberias de 6 pul 26-Nov-21 13:00 30-Nov-21 4.00 Montaje de aislamiento para tuberias de 6 pul
PX2110 Instalacion de linea de 3''-0310-CR-06001 (Butterfly Valve x 3 & Ball Valve 28-Feb-22 06:00 02-Mar-22 3.00 Instalacion de linea de 3''-0310-CR-06001 (Butterfly Valve x 3 & Ball Valve x 3) (Doble turno)
PX2120 Instalacion de linea de 3''-0310-CR-06002 (Butterfly Valve x 3 & Ball Valve 28-Feb-22 06:00 04-Mar-22 5.00 Instalacion de linea de 3''-0310-CR-06002 (Butterfly Valve x 3 & Ball Valve x 3)
PX2130 Instalacion de linea de 3''-0310-CR-06003 (Butterfly Valve x 3 & Ball Valve 28-Feb-22 06:00 04-Mar-22 5.00 Instalacion de linea de 3''-0310-CR-06003 (Butterfly Valve x 3 & Ball Valve x 3)
PX2140 Instalacion de linea de 3''-0310-CR-06004 (Butterfly Valve x 3 & Ball Valve 05-Mar-22 06:00 06-Mar-22 2.00 Instalacion de linea de 3''-0310-CR-06004 (Butterfly Valve x 3 & Ball Valve x 3)
Lineas de agua fria (CW)
(CW 17-Aug-21 06:00 A 11-Mar-22 207.00 11-Mar-22 17:00, Lineas de agua fria (CW)
PX2240 Instalación de lineas de 8''-0310-CW-06020 (Ball Valve x 1 TAG: 0310V223 17-Aug-21 06:00 A 20-Aug-21 4.00-06020 (Ball Valve x 1 TAG: 0310V2232)
PX2250 Installation of pipe 0310-CW-06107 (Ball Valve x 2 TAG: 0310V2233 / 031 30-Aug-21 00:00 A 02-Oct-21 27.00 stallation of pipe 0310-CW-06107 (Ball Valve x 2 TAG: 0310V2233 / 0310V2175)
PX2270 Instalación de linea 4''-0310-CW-06111 (Butterfly Valve x 4 & Ball Valve x 31-Aug-21 00:00 A 08-Nov-21 42.00 Instalación de linea 4''-0310-CW-06111 (Butterfly Valve x 4 & Ball Valve x 1)
PX2320 Instalación de linea 6''-0310-CW-06138 (Ball Valve x 2 TAG: 0310V2173 / 11-Sep-21 06:00 A 23-Nov-21 1.00 Instalación de linea 6''-0310-CW-06138 (Ball Valve x 2 TAG: 0310V2173 / 0310V2183)
PX2330 Instalación de linea 6''-0310-CW-06141 (Ball Valve x 2 TAG: 0310V2172 / 11-Sep-21 06:00 A 23-Nov-21 1.00 Instalación de linea 6''-0310-CW-06141 (Ball Valve x 2 TAG: 0310V2172 / 0310V2182)
PX2350 Instalación de lineas de 6''-0310-CW-06502 (Ball Valve x 2 TAG: 0310V222 15-Sep-21 06:00 A 23-Nov-21 2.00 Instalación de lineas de 6''-0310-CW-06502 (Ball Valve x 2 TAG: 0310V2220 / 0310V2221)
PX2260 Instalación de linea 4''-0310-CW-06109 (Butterfly Valve x 4 & Ball Valve x 12-Nov-21 06:00 22-Nov-21 11.00 Instalación de linea 4''-0310-CW-06109 (Butterfly Valve x 4 & Ball Valve x 1)
PX2340 Instalación de linea 1''- 0310-CW-06501 (Ball Valve x 2 TAG: 0310V2234 / 23-Nov-21 06:00 24-Nov-21 2.00 Instalación de linea 1''- 0310-CW-06501 (Ball Valve x 2 TAG: 0310V2234 / 0310V2057)
PX2650 Limpieza Flushing y prueba hidrostatica - Lineas de 8 pul 26-Nov-21 13:00 30-Nov-21 4.00 Limpieza Flushing y prueba hidrostatica - Lineas de 8 pul
PX2370 Instalación de aislamiento en lineas de 8''-0310-CW-06020 30-Nov-21 13:00 15-Dec-21 15.00 Instalación de aislamiento en lineas de 8''-0310-CW-06020
PX2380 Montaje de aislamiento para linea 8''-0310-CW-06107 30-Nov-21 13:00 15-Dec-21 15.00 Montaje de aislamiento para linea 8''-0310-CW-06107
PX2290 Instalación de linea 3''-0310-CW-06114 (Butterfly Valve x 5 & Ball Valve x 3 28-Feb-22 06:00 04-Mar-22 5.00 Instalación de linea 3''-0310-CW-06114 (Butterfly Valve x 5 & Ball Valve x 3)
PX2310 Instalación de linea 3''-0310-CW-06116 (Butterfly Valve x 5 & Ball Valve x 3 03-Mar-22 06:00 04-Mar-22 2.00 Instalación de linea 3''-0310-CW-06116 (Butterfly Valve x 5 & Ball Valve x 3)
PX2280 Instalación de linea 3''-0310-CW-06113 (Butterfly Valve x 5 & Ball Valve x 3 05-Mar-22 06:00 06-Mar-22 2.00 Instalación de linea 3''-0310-CW-06113 (Butterfly Valve x 5 & Ball Valve x 3)
PX2300 Instalación de linea 3''-0310-CW-06115 (Butterfly Valve x 5 & Ball Valve x 3 05-Mar-22 06:00 07-Mar-22 3.00 Instalación de linea 3''-0310-CW-06115 (Butterfly Valve x 5 & Ball Valve x 3)
PX2360 Montaje de aislamiento en lineas de 6 pul o menos 08-Mar-22 06:00 11-Mar-22 4.00 Montaje de aislamiento en lineas de 6 pul o menos

Actual Level of Effort Actual Work Critical Remaining Work Page 13 of 20 TASK filter: All Activities
Primary Baseline Remaining Work Milestone © Oracle Corporation
Cronograma del Proyecto: Construccion e Instalacion del 3er Molino de Bolas y Obras Asociadas
Linea Base 1 Rev. 0 (actualizado al 22-octubre)
Activity ID Activity Name Start Finish Original October 2021 November 2021 December 2021 January 2022 February 2022 March 2022 April 2022 May 2022 June 2022 July 2022
Duration
09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 05 12 19 26 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 02 09 6
Lineas de Aceite Hidraulico
Hidrau (HO) 05-Jan-22 06:00 18-Jan-22 14.00 18-Jan-22 17:00, Lineas de Aceite Hidraulico (HO)
PX2390 Installation of pipe 0310-HO-06801 05-Jan-22 06:00 07-Jan-22 3.00 Installation of pipe 0310-HO-06801
PX2410 Installation of pipe 0310-HO-06803 08-Jan-22 06:00 10-Jan-22 3.00 Installation of pipe 0310-HO-06803
PX2400 Installation of pipe 0310-HO-06802 11-Jan-22 06:00 11-Jan-22 1.00 Installation of pipe 0310-HO-06802
PX2610 Limpieza Flushing y prueba hidrotatica - Aceite hidraulico 12-Jan-22 06:00 14-Jan-22 3.00 Limpieza Flushing y prueba hidrotatica - Aceite hidraulico
PX2580 Montaje de aislamiento a linea de aceite hidraulico 15-Jan-22 06:00 18-Jan-22 4.00 Montaje de aislamiento a linea de aceite hidraulico
Aceite de lubricación - A
Alta Presion (LOH) 07-Dec-21 06:00 02-Jan-22 27.00 02-Jan-22 17:00, Aceite de lubricación - Alta Presion (LOH)
PX2420 Installation of pipe 0310-LOH-06602 07-Dec-21 06:00 08-Dec-21 2.00 Installation of pipe 0310-LOH-06602
PX2430 Installation of pipe 0310-LOH-06603 07-Dec-21 06:00 08-Dec-21 2.00 Installation of pipe 0310-LOH-06603
PX2460 Installation of pipe 0310-LOH-06606 07-Dec-21 06:00 09-Dec-21 3.00 Installation of pipe 0310-LOH-06606
PX2470 Installation of pipe 0310-LOH-06607 07-Dec-21 06:00 08-Dec-21 2.00 Installation of pipe 0310-LOH-06607
PX2440 Installation of pipe 0310-LOH-06604 09-Dec-21 06:00 11-Dec-21 3.00 Installation of pipe 0310-LOH-06604
PX2450 Installation of pipe 0310-LOH-06605 09-Dec-21 06:00 11-Dec-21 3.00 Installation of pipe 0310-LOH-06605
PX2480 Installation of pipe 0310-LOH-06608 12-Dec-21 06:00 14-Dec-21 3.00 Installation of pipe 0310-LOH-06608
PX2490 Installation of pipe 0310-LOH-06609 12-Dec-21 06:00 13-Dec-21 2.00 Installation of pipe 0310-LOH-06609
PX2600 Limpieza Flushing y prueba hidrotatica - Aceite a alta presion 14-Dec-21 06:00 18-Dec-21 5.00 Limpieza Flushing y prueba hidrotatica - Aceite a alta presion
PX2500 Installation of pipe 0310-LOH-06702 15-Dec-21 06:00 21-Dec-21 7.00 Installation of pipe 0310-LOH-06702
PX2510 Installation of pipe 0310-LOH-06703 15-Dec-21 06:00 21-Dec-21 7.00 Installation of pipe 0310-LOH-06703
PX2520 Installation of pipe 0310-LOH-06704 15-Dec-21 06:00 21-Dec-21 7.00 Installation of pipe 0310-LOH-06704
PX2530 Installation of pipe 0310-LOH-06705 15-Dec-21 06:00 21-Dec-21 7.00 Installation of pipe 0310-LOH-06705
PX2590 Montaje de aislamiento en linea de alta presion 19-Dec-21 06:00 02-Jan-22 15.00 Montaje de aislamiento en linea de alta presion
PX2630 Instalación de head Tracing 19-Dec-21 06:00 02-Jan-22 15.00 Instalación de head Tracing
Retorno de Aceite de Lubricación
Lu (LR) 18-Jul-21 23:00 A 19-Jan-22 185.00 19-Jan-22 17:00, Retorno de Aceite de Lubricación (LR)
PX2560 Instalación de line de 8''-00310-LR-06861 18-Jul-21 23:00 A 20-Jul-21 1 1.75
PX2540 Instalación de line de 8''-0310-LR-06601 22-Dec-21 06:00 26-Dec-21 5.00 Instalación de line de 8''-0310-LR-06601
PX2550 Instalación de line de 8''-00310-LR-06701 27-Dec-21 06:00 04-Jan-22 9.00 Instalación de line de 8''-00310-LR-06701
PX2620 Limpieza Flushing y prueba hidrotatica - Aceite de retorno 05-Jan-22 06:00 09-Jan-22 5.00 Limpieza Flushing y prueba hidrotatica - Aceite de retorno
PX2570 Montaje de aislamiento para tuberias de 8 pul 10-Jan-22 06:00 19-Jan-22 10.00 Montaje de aislamiento para tuberias de 8 pul
Lineas de Drenaje de aceite
a (WO) 05-Jan-22 06:00 05-Jan-22 1.00 05-Jan-22 17:00, Lineas de Drenaje de aceite (WO)
PX2940 Installation of pipe 0310-WO-06631 05-Jan-22 06:00 05-Jan-22 1.00 Installation of pipe 0310-WO-06631
PX2950 Installation of pipe 0310-WO-06632 05-Jan-22 06:00 05-Jan-22 1.00 Installation of pipe 0310-WO-06632
PX2960 Installation of pipe 0310-WO-06633 05-Jan-22 06:00 05-Jan-22 1.00 Installation of pipe 0310-WO-06633
Lineas de agua de proceso
proc (WP) 20-Jul-21 06:00 A 19-Mar-22 243.00 19-Mar-22 17:00, Lineas de agua de proceso (WP)
PX8170 Instalación de linea 12''-0310-WP-06214 20-Jul-21 06:00 A 11-Nov-21 78.00 Instalación de linea 12''-0310-WP-06214
PX8250 Instalación de linea 6''-0310-WP-06917 17-Aug-21 00:00 A 20-Nov-21 60.00 Instalación de linea 6''-0310-WP-06917
PX8110 Instalación de linea 6''-0316-WP-06916 28-Aug-21 00:00 A 07-Dec-21 66.00 Instalación de linea 6''-0316-WP-06916
PX8440 Instalación de linea 2''-0316-WP-06930 28-Aug-21 00:00 A 14-Nov-21 16.00 Instalación de linea 2''-0316-WP-06930
PX8450 Instalación de linea 2''-0316-WP-06931 28-Aug-21 00:00 A 14-Nov-21 18.00 Instalación de linea 2''-0316-WP-06931
PX8460 Instalación de linea 2''-0316-WP-06932 28-Aug-21 00:00 A 14-Nov-21 20.00 Instalación de linea 2''-0316-WP-06932
PX8470 Instalación de linea 2''-0316-WP-06933 28-Aug-21 00:00 A 14-Nov-21 22.00 Instalación de linea 2''-0316-WP-06933
PX8370 Instalación de linea 3''-0316-WP-06238 02-Sep-21 00:00 A 24-Nov-21 22.00 Instalación de linea 3''-0316-WP-06238
PX8120 Instalación de linea 8''-0316-WP-06915 04-Sep-21 06:00 A 02-Dec-21 5.00 Instalación de linea 8''-0316-WP-06915
PX8130 Instalación de linea 2''-0316-WP-06937 19-Sep-21 00:00 A 13-Nov-21 2.00 Instalación de linea 2''-0316-WP-06937
PX8140 Instalación de linea 2''-0316-WP-06936 19-Sep-21 00:00 A 13-Nov-21 2.00 Instalación de linea 2''-0316-WP-06936
PX8150 Instalación de linea 2''-0316-WP-06935 19-Sep-21 00:00 A 13-Nov-21 2.00 Instalación de linea 2''-0316-WP-06935
PX8160 Instalación de linea 2''-0316-WP-06934 19-Sep-21 00:00 A 17-Nov-21 5.00 Instalación de linea 2''-0316-WP-06934
PX8420 Instalación de linea 2''-0316-WP-06912 25-Nov-21 06:00 29-Nov-21 5.00 Instalación de linea 2''-0316-WP-06912
PX8430 Instalación de linea 2''-0316-WP-06913 25-Nov-21 06:00 29-Nov-21 5.00 Instalación de linea 2''-0316-WP-06913
PX8480 Instalación de linea 2''-0316-WP-06938 29-Nov-21 06:00 30-Nov-21 2.00 Instalación de linea 2''-0316-WP-06938
PX8490 Instalación de linea 2''-0316-WP-06945 03-Dec-21 06:00 04-Dec-21 2.00 Instalación de linea 2''-0316-WP-06945
PX8500 Instalación de linea 2''-0316-WP-06946 05-Dec-21 06:00 06-Dec-21 2.00 Instalación de linea 2''-0316-WP-06946
PX8640 Limpieza Flushing (tuberias 2" en launder) 08-Dec-21 06:00 14-Dec-21 7.00 Limpieza Flushing (tuberias 2" en launder)
PX8650 Instalacion de aislamiento (tuberias 2" en launder) 12-Dec-21 06:00 18-Dec-21 7.00 Instalacion de aislamiento (tuberias 2" en launder)
PX8230 Instalación de linea 12''-0310-WP-06920 (SL-Alimentacion ciclon 01) 15-Feb-22 06:00 17-Feb-22 3.00 Instalación de linea 12''-0310-WP-06920 (SL-Alimentacion ciclon 01)
PX1637 Montaje de tuberias de lineas de agua de proceso 1 1/2" 18-Feb-22 06:00 19-Mar-22 30.00 Montaje de tuberias de lineas de agua de proceso 1 1/2"
PX8200 Instalación de linea 12''-0310-WP-06522 (Warman 04) 18-Feb-22 06:00 19-Feb-22 2.00 Instalación de linea 12''-0310-WP-06522 (Warman 04)
PX8210 Instalación de linea 12''-0310-WP-06848 (Warman 04) 18-Feb-22 06:00 19-Feb-22 2.00 Instalación de linea 12''-0310-WP-06848 (Warman 04)
PX8220 Instalación de linea 12''-0310-WP-06919 (SL-Alimentacion ciclon 04) 18-Feb-22 06:00 19-Feb-22 2.00 Instalación de linea 12''-0310-WP-06919 (SL-Alimentacion ciclon 04)
PX8240 Instalación de linea 6''-0310-WP-06841 18-Feb-22 06:00 27-Feb-22 10.00 Instalación de linea 6''-0310-WP-06841
PX8380 Instalación de linea 3''-0316-WP-06850 18-Feb-22 06:00 22-Feb-22 5.00 Instalación de linea 3''-0316-WP-06850
PX8400 Instalación de linea 2''-0316-WP-06910 18-Feb-22 06:00 22-Feb-22 5.00 Instalación de linea 2''-0316-WP-06910
PX8180 Instalación de linea 12''-0310-WP-06231 (Warman 01) 23-Feb-22 06:00 24-Feb-22 2.00 Instalación de linea 12''-0310-WP-06231 (Warman 01)
PX8190 Instalación de linea 12''-0310-WP-06232 (Warman 01) 23-Feb-22 06:00 24-Feb-22 2.00 Instalación de linea 12''-0310-WP-06232 (Warman 01)

Actual Level of Effort Actual Work Critical Remaining Work Page 14 of 20 TASK filter: All Activities
Primary Baseline Remaining Work Milestone © Oracle Corporation
Cronograma del Proyecto: Construccion e Instalacion del 3er Molino de Bolas y Obras Asociadas
Linea Base 1 Rev. 0 (actualizado al 22-octubre)
Activity ID Activity Name Start Finish Original October 2021 November 2021 December 2021 January 2022 February 2022 March 2022 April 2022 May 2022 June 2022 July 2022
Duration
09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 05 12 19 26 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 02 09 6
PX8390 Instalación de linea 2''-0316-WP-06851 23-Feb-22 06:00 27-Feb-22 5.00 Instalación de linea 2''-0316-WP-06851
PX8410 Instalación de linea 2''-0316-WP-06911 23-Feb-22 06:00 27-Feb-22 5.00 Instalación de linea 2''-0316-WP-06911
Lineas de Drenaje (DP) 20-Jul-21 17:00 A 22-Feb-22 217.00 22-Feb-22 17:00, Lineas de Drenaje (DP)
PX1638 Montaje tuberias de drenaje (area launder) 20-Jul-21 17:00 A 01-Dec-21 65.00 Montaje tuberias de drenaje (area launder)
PX8550 Instalación de line de 6''-0310-PD-06219 02-Feb-22 06:00 03-Feb-22 2.00 Instalación de line de 6''-0310-PD-06219
PX8560 Instalación de line de 6''-0310-PD-06516 04-Feb-22 06:00 05-Feb-22 2.00 Instalación de line de 6''-0310-PD-06516
PX8530 Instalación de line de 12''-0310-PD-06516 18-Feb-22 06:00 19-Feb-22 2.00 Instalación de line de 12''-0310-PD-06516
PX8540 Instalación de line de 12''-0310-PD-06520 18-Feb-22 06:00 19-Feb-22 2.00 Instalación de line de 12''-0310-PD-06520
PX8510 Instalación de line de 12''-0310-PD-06215 21-Feb-22 06:00 22-Feb-22 2.00 Instalación de line de 12''-0310-PD-06215
PX8520 Instalación de line de 12''-0310-PD-06219 21-Feb-22 06:00 22-Feb-22 2.00 Instalación de line de 12''-0310-PD-06219
Otras Lineas 05-Jan-22 06:00 19-Feb-22 46.00 19-Feb-22 17:00, Otras Lineas
PX8590 Instalación de linea 3/4''-0316-FS-06615 05-Jan-22 06:00 06-Jan-22 2.00 Instalación de linea 3/4''-0316-FS-06615
PX8600 Instalación de linea 3/4''-0316-FS-06616 07-Jan-22 06:00 13-Jan-22 7.00 Instalación de linea 3/4''-0316-FS-06616
PX8610 Instalación de linea 1 1/2''-0316-SF-06621 14-Jan-22 06:00 15-Jan-22 2.00 Instalación de linea 1 1/2''-0316-SF-06621
PX8620 Instalación de linea 3/4''-0316-SF-06622 16-Jan-22 06:00 22-Jan-22 7.00 Instalación de linea 3/4''-0316-SF-06622
PX8630 Instalación de linea 2''-0316-WD-06207 06-Feb-22 06:00 08-Feb-22 3.00 Instalación de linea 2''-0316-WD-06207
PX8570 Instalación de linea 1 1/2''-0316-WG-06225 15-Feb-22 06:00 16-Feb-22 2.00 Instalación de linea 1 1/2''-0316-WG-06225
PX8580 Instalación de linea 1 1/2''-0316-WG-06528 18-Feb-22 06:00 19-Feb-22 2.00 Instalación de linea 1 1/2''-0316-WG-06528
Tie In 10-Jun-21 06:00 A 21-Mar-22 285.00 21-Mar-22 17:00, Tie In
H8980 Fin de Tie in - Julio 2021 21-Jul-21 2 0.00
H16550 Fin de Tie in - Noviembre 2021 04-Nov-21 0.00 Fin de Tie in - Noviembre 2021,
H8990 Fin de Tie in - Febrero 2022 25-Feb-22 0.00 Fin de Tie in - Febrero 2022,
Parada de Planta - Julio 2021 10-Jun-21 06:00 A 27-Aug-21 79.00 Planta - Julio 2021
Electricidad 03-Jul-21 06:00 A 17-Jul-21 1 15.00
TI7000-SD1 Trabajos previos a parada de planta julio-2021 (Electricidad) 03-Jul-21 06:00 A 17-Jul-21 1 15.00
TI7008 Tie in 7008: Conexión eléctrica hacia transformador del rectificado de excit 15-Jul-21 17:00 A 16-Jul-21 1 1.00 de excitación (0310-MLB-0003-XFC4)
TI7030 Tie in 7030: Instalación de transformador de corriente 600-200:5 en celda 16-Jul-21 11:00 A 17-Jul-21 0 0.54en celda 16, 0310-SGM-0002
Instrumentación 16-Jul-21 06:00 A 27-Aug-21 43.00ación
TI8018 Tie in 8018: Cambiar la posicion de la tuberia 3-0310-ML-00416-C1E2R 16-Jul-21 06:00 A 27-Aug-21 42.46n de la tuberia 3-0310-ML-00416-C1E2R
TI8019 Tie in 8019: Cambiar la posicion de la tuberia 3-0310-ML-00306-C1E2R 16-Jul-21 06:00 A 27-Aug-21 42.46n de la tuberia 3-0310-ML-00306-C1E2R
TI8000-SD1 Trabajos previos a parada de planta julio-2021 (Instrumentacion) 17-Jul-21 06:00 A 17-Jul-21 1 1.00
TI8006 Tie in 8006: Cables de control e instrumentación, valvulas y sensor de nive 20-Jul-21 11:00 A 21-Jul-21 0 0.54ensor de nivel en SUL-0001
TI8007 Tie in 8007: Cables de control e instrumentación, valvulas y sensor de nive 20-Jul-21 11:00 A 21-Jul-21 0 0.54ensor de nivel en SUL-0002
TI8008 Tie in 8008: Cables de control e instrumentación, valvulas y sensor de nive 20-Jul-21 11:00 A 21-Jul-21 0 0.54ensor de nivel en Drenaje
Piping 22-Jun-21 06:00 A 21-Jul-21 2 30.00
TI6000-SD1 Trabajos previos a parada de planta julio-2021 (Piping) 22-Jun-21 06:00 A 17-Jul-21 1 26.00
TI6026 Tie in 6026: Reubicación de tubería de agua de procesos (3"-0310-WP-06 15-Jul-21 16:00 A 15-Jul-21 1 0.130-WP-06871-C1E2A)
TI6086 Tie in 6086: Conexión de nueva tubería de Descarga (42"-0310-SL-06716 15-Jul-21 16:00 A 16-Jul-21 0 0.33 L-06716-L1E0VJ-NI) de Nido de Ciclones (0310-CSC-0001)
TI6072 Tie in 6072: Reubicación de línea de retorno de lubricante del Molino de B 16-Jul-21 06:00 A 21-Jul-21 2 5.67 l Molino de Bolas N°2, por interferencia con STP-0065
TI6073 Tie in 6073: Reubicación de línea de retorno de lubricante del Molino de B 16-Jul-21 06:00 A 21-Jul-21 2 5.67 l Molino de Bolas N°2
TI6107 Tie in 6107: Reubicación de linea de lubricante por interferencia con valvul 16-Jul-21 06:00 A 21-Jul-21 0 4.75 ia con valvulas dardo y cuchillas de chute 0310-STP-0065
TI6108 Tie in 6108: Reubicación de linea de lubricante por interferencia con valvul 16-Jul-21 06:00 A 21-Jul-21 0 4.75 ia con valvulas dardo y cuchillas de chute 0310-STP-0065
TI6105 Tie in 6105: Reubicación de linea de lubricante por interferencia con valvul 16-Jul-21 06:00 A 21-Jul-21 0 4.75 ia con valvulas dardo y cuchillas de chute 0310-STP-0065
TI6106 Tie in 6106: Reubicación de linea de lubricante por interferencia con valvul 16-Jul-21 06:00 A 21-Jul-21 0 4.75 ia con valvulas dardo y cuchillas de chute 0310-STP-0065
TI6031 Tie in 6031: Reubicación de tubería de agua de procesos (3"-0310-WP-06 18-Jul-21 09:00 A 19-Jul-21 1 1.42 310-WP-06872-C1E2A)
TI6058 Tie in 6058: Reubicación de línea de lechada de cal (3"-0310-ML-06309-C 18-Jul-21 09:00 A 18-Jul-21 1 0.42 L-06309-C1E2R)
TI6059 Tie in 6059: Reubicación de línea de lechada de cal (3"-0310-ML-06416-C 18-Jul-21 09:00 A 18-Jul-21 1 0.42 L-06416-C1E2R)
TI6010 Tie in 6010: Conexión de nueva tubería de Descarga (42"-0310-SL-06718 18-Jul-21 20:00 A 21-Jul-21 0 2.4610-SL-06718-L1E0VJ-NI) de Nido de Ciclones (0310-CSC-0002)
TI6522-T Tie in 6522-T: Retiro de tuberia 2"-0310-WP-04534-C1E2A (existente) por i 20-Jul-21 17:00 A 21-Jul-21 2 1.19xistente) por interferencia con montaje de chute 0310-STP-0065
TI6523-T Tie in 6523-T: Retiro de la tuberia de aire (existente) por interferencia con m 20-Jul-21 17:00 A 21-Jul-21 2 1.19erencia con montaje de chute 0310-STP-0065
Mecanica 10-Jun-21 06:00 A 21-Jul-21 0 41.00
TI5000-SD1 Trabajos previos a parada de planta julio-2021 (Mecanico) 10-Jun-21 06:00 A 17-Jul-21 1 38.00
TI5002 Tie in 5002: Nuevo chute de descarga Bola N°2 (0310-STP-0065), incluye 01-Jul-21 06:00 A 21-Jul-21 0 19.75065), incluye válvulas dardos y de cuchilla.
TI5004 Tie in 5004: Recorte en el chute 0310-STP-0070 cuerpo inferior CP-3 01-Jul-21 06:00 A 21-Jul-21 0 19.75or CP-3
TI5005 Tie in 5005: Modificación de la bandeja de gruesos del nido de ciclones 03 15-Jul-21 06:00 A 21-Jul-21 0 5.75e ciclones 0310-CSC-0002
TI5001 Tie in 5001: Desmontaje de canaleta existente 0310-LAL-0012 y reemplaz 16-Jul-21 10:00 A 18-Jul-21 1 2.06y reemplazo por nueva la canaleta 0310-LAL-0104
TI5003 Tie in 5003: Add new launder 0310-LAL-0103 from new chute 0310-STP-0 17-Jul-21 06:00 A 21-Jul-21 0 4.00 0310-STP-0065 to SUL-0001.
Parada de Planta - Nov
Noviembre 2021 02-Nov-21 06:00 25-Dec-21 53.46 25-Dec-21 17:00, Parada de Planta - Noviembre 2021
Electricidad 02-Nov-21 06:00 03-Nov-21 1.00 03-Nov-21 06:00, Electricidad
TI7028 Tie in 7028: Conexión eléctrica 110 Voltios , celda H16, 0931-SGM-0001ha 02-Nov-21 06:00 03-Nov-21 1.00 Tie in 7028: Conexión eléctrica 110 Voltios , celda H16, 0931-SGM-0001hacia 0310-MLB-0003-COB3
TI7029 Tie in 7029: Conexión de señales de estado y trip interruptor celda H15, 0 02-Nov-21 06:00 03-Nov-21 1.00 Tie in 7029: Conexión de señales de estado y trip interruptor celda H15, 0931-SGM-0001.
TI7031 Tie in 7031: Conexión de señales de estado y trip interruptor celda H16, 0 02-Nov-21 06:00 02-Nov-21 0.50 Tie in 7031: Conexión de señales de estado y trip interruptor celda H16, 0310-SGM-0002.
TI7037 Conexión eléctrica hacia nuevo UPS desde 0310-MCL-0016, ubicados en 02-Nov-21 06:00 03-Nov-21 1.00 Conexión eléctrica hacia nuevo UPS desde 0310-MCL-0016, ubicados en Sala electrica 0310-ERR-0002(No requiere parada)

Actual Level of Effort Actual Work Critical Remaining Work Page 15 of 20 TASK filter: All Activities
Primary Baseline Remaining Work Milestone © Oracle Corporation
Cronograma del Proyecto: Construccion e Instalacion del 3er Molino de Bolas y Obras Asociadas
Linea Base 1 Rev. 0 (actualizado al 22-octubre)
Activity ID Activity Name Start Finish Original October 2021 November 2021 December 2021 January 2022 February 2022 March 2022 April 2022 May 2022 June 2022 July 2022
Duration
09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 05 12 19 26 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 02 09 6
TI7038 Conexión eléctrica hacia nuevos flujometros mágneticos 0310-FIT-01516/0 02-Nov-21 06:00 03-Nov-21 1.00 Conexión eléctrica hacia nuevos flujometros mágneticos 0310-FIT-01516/01615/01611/01612
TI7039 Conexión hacia nuevos flujometros electromágneticos 0310-FIT-01613/01 02-Nov-21 06:00 03-Nov-21 1.00 Conexión hacia nuevos flujometros electromágneticos 0310-FIT-01613/01614/01554/01612, valvula de control 0310-HV-01554
TI7030-1 Completar Tie in 7030 02-Nov-21 06:00 03-Nov-21 1.00 Completar Tie in 7030
TI7008-1 Completar Tie in 7008 02-Nov-21 06:00 03-Nov-21 1.00 Completar Tie in 7008
Instrumentacion 02-Nov-21 06:00 03-Nov-21 1.46 03-Nov-21 17:00, Instrumentacion
TI8006-1 Completar Tie in 8006 02-Nov-21 06:00 03-Nov-21 1.00 Completar Tie in 8006
TI8007-1 Completar Tie in 8007 02-Nov-21 06:00 03-Nov-21 1.00 Completar Tie in 8007
TI8008-1 Completar Tie in 8008 02-Nov-21 06:00 03-Nov-21 1.00 Completar Tie in 8008
TI8021-SD1 Tie in 8021: Instalacion cableado y conexion de valvula cuchilla de 42" (hid 02-Nov-21 17:00 03-Nov-21 1.00 Tie in 8021: Instalacion cableado y conexion de valvula cuchilla de 42" (hidraulicas) 0310-HV-01558 y 0310-HV-01559
Piping 02-Nov-21 06:00 25-Dec-21 53.46 25-Dec-21 17:00, Piping
TI6517-T Tie in 6517-T: Realigment Plant air Pipe (3"-0310-WP-06957) to feed new h 02-Nov-21 06:00 03-Nov-21 1.00 Tie in 6517-T: Realigment Plant air Pipe (3"-0310-WP-06957) to feed new hoose station
TI6086-1 Completar Tie in 6086 02-Nov-21 06:00 03-Nov-21 1.00 Completar Tie in 6086
TI6107-1 Completar Tie in 6107 02-Nov-21 06:00 03-Nov-21 1.00 Completar Tie in 6107
TI6108-1 Completar Tie in 6108 02-Nov-21 06:00 03-Nov-21 1.00 Completar Tie in 6108
TI6105-1 Completar Tie in 6105 02-Nov-21 06:00 03-Nov-21 1.00 Completar Tie in 6105
TI6106-1 Completar Tie in 6106 02-Nov-21 06:00 03-Nov-21 1.00 Completar Tie in 6106
TI6010-1 Completar Tie in 6010 02-Nov-21 06:00 03-Nov-21 1.00 Completar Tie in 6010
TI6026-1 Completar Tie in 6026 02-Nov-21 06:00 03-Nov-21 1.00 Completar Tie in 6026
TI6031-1 Completar Tie in 6031 02-Nov-21 06:00 03-Nov-21 1.00 Completar Tie in 6031
TI6058-1 Completar Tie in 6058 02-Nov-21 06:00 03-Nov-21 1.00 Completar Tie in 6058
TI6059-1 Completar Tie in 6059 02-Nov-21 06:00 03-Nov-21 1.00 Completar Tie in 6059
TI6522-T-1 Completar Tie in 6522-T 03-Nov-21 06:00 04-Nov-21 1.00 Completar Tie in 6522-T
TI6523-T-1 Completar Tie in 6523-T 03-Nov-21 06:00 04-Nov-21 1.00 Completar Tie in 6523-T
TI6027 Tie in 6027: Reubicación de tubería existente de Lechada de cal 6"-0391-M 24-Dec-21 17:00 25-Dec-21 1.00 Tie in 6027: Reubicación de tubería existente de Lechada de cal 6"-0391-ML-00407-C1E2R
TI6030 Tie in 6030: Reubicación de tubería existente de Lechada de cal 6"-0391- 24-Dec-21 17:00 25-Dec-21 1.00 Tie in 6030: Reubicación de tubería existente de Lechada de cal 6"-0391-ML-00407-C1E2R.
TI6022 Tie in 6022: Tubería de Alimentación de Lechada de cal (6"-0391-ML-0633 24-Dec-21 17:00 25-Dec-21 1.00 Tie in 6022: Tubería de Alimentación de Lechada de cal (6"-0391-ML-06332-C1E2R-NI).
TI6024 Tie in 6024: Tubería de Alimentación de Lechada de cal (6"-0391-ML-0633 24-Dec-21 17:00 25-Dec-21 1.00 Tie in 6024: Tubería de Alimentación de Lechada de cal (6"-0391-ML-06333-C1E2R-NI).
TI6023 Tie in 6023: Tubería de Alimentación de Lechada de cal (6 "-0391-ML-0633 24-Dec-21 17:00 25-Dec-21 1.00 Tie in 6023: Tubería de Alimentación de Lechada de cal (6 "-0391-ML-06332-C1E2R-NI).
TI6087 Tie in 6087: Empalme a línea existente 1-1/2"-0391-ML-00411-C1E2R 24-Dec-21 17:00 25-Dec-21 1.00 Tie in 6087: Empalme a línea existente 1-1/2"-0391-ML-00411-C1E2R
TI6088 Tie in 6088: Empalme a línea existente 1-1/2"-0391-ML-00414-C1E2R. 24-Dec-21 17:00 25-Dec-21 1.00 Tie in 6088: Empalme a línea existente 1-1/2"-0391-ML-00414-C1E2R.
TI6089 Tie in 6089: Empalme a línea existente 1-1/2"-0391-ML-00415-C1E2R des 24-Dec-21 17:00 25-Dec-21 1.00 Tie in 6089: Empalme a línea existente 1-1/2"-0391-ML-00415-C1E2R desde línea principal.
TI6090 Tie in 6090: Empalme a línea existente 1-1/2"-0391-ML-00413-C1E2R. 24-Dec-21 17:00 25-Dec-21 1.00 Tie in 6090: Empalme a línea existente 1-1/2"-0391-ML-00413-C1E2R.
TI6091 Tie in 6091:Empalme a línea existente 1-1/2"-0391-ML-00410-C1E2R. 24-Dec-21 17:00 25-Dec-21 1.00 Tie in 6091:Empalme a línea existente 1-1/2"-0391-ML-00410-C1E2R.
TI6102 Tie in 6102:Punto de conexión a línea existente 4"-0391-ML-00327-C1E2R 24-Dec-21 17:00 25-Dec-21 1.00 Tie in 6102:Punto de conexión a línea existente 4"-0391-ML-00327-C1E2R.
TI6503-T Tie in 6503T: Reubicación temporal de tubería de alimentación de lechada 24-Dec-21 17:00 25-Dec-21 1.00 Tie in 6503T: Reubicación temporal de tubería de alimentación de lechada de cal principal ( 3"-0391-ML-00309-C1E2R-NI)
TI6504-T Tie in 6504T: Reubicación temporal de tubería de alimentación de lechada 24-Dec-21 17:00 25-Dec-21 1.00 Tie in 6504T: Reubicación temporal de tubería de alimentación de lechada de cal principal ( 3"-0391-ML-00309-C1E2R-NI)
TI6509-T Tie in 6509T: Reubicación temporal de tubería de alimentación de lechada 24-Dec-21 17:00 25-Dec-21 1.00 Tie in 6509T: Reubicación temporal de tubería de alimentación de lechada de cal principal ( 3"-0391-ML-00416-C1E2R-NI)
TI6510-T Tie in 6510T: Reubicación temporal de tubería de alimentación de lechada 24-Dec-21 17:00 25-Dec-21 1.00 Tie in 6510T: Reubicación temporal de tubería de alimentación de lechada de cal principal ( 3"-0391-ML-00416-C1E2R-NI)
Mecanica 02-Nov-21 06:00 03-Nov-21 1.00 03-Nov-21 06:00, Mecanica
TI5002-1 Completar Tie in 5002 02-Nov-21 06:00 03-Nov-21 1.00 Completar Tie in 5002
TI5004-1 Completar Tie in 5004 02-Nov-21 06:00 03-Nov-21 1.00 Completar Tie in 5004
TI5005-1 Completar Tie in 5005 02-Nov-21 06:00 03-Nov-21 1.00 Completar Tie in 5005
TI5003-1 Completar Tie in 5003 02-Nov-21 06:00 03-Nov-21 1.00 Completar Tie in 5003
No Requiere Parada de Planta 28-Aug-21 00:00 A 25-Feb-22 181.40 25-Feb-22 10:00, No Requiere Parada de Planta
Electricidad 28-Aug-21 00:00 A 18-Feb-22 175.00 18-Feb-22 17:00, Electricidad
TI7013 Conexión de la nueva malla a tierra para los chilllers ( 0310-CCW-3014, 03 28-Aug-21 00:00 A 21-Nov-21 105.00 Conexión de la nueva malla a tierra para los chilllers ( 0310-CCW-3014, 0310-CCW-3015)
TI7019 Sistema de puesta a tierra de la sala de lubricacion será en 3 puntos de la 28-Aug-21 00:00 A 21-Nov-21 105.00 Sistema de puesta a tierra de la sala de lubricacion será en 3 puntos de la nueva malla a tierra
TI7022 Conexión eléctrica para el sistema de iluminación para la sala de lubricació 28-Aug-21 00:00 A 15-Sep-21 105.00 Conexión eléctrica para el sistema de iluminación para la sala de lubricación N° 3 (0310-LPA-0009)
TI7023 Conexión eléctrica en el circuito Nro 04 del tablero de iluminación existente 28-Aug-21 00:00 A 30-Nov-21 114.60 Conexión eléctrica en el circuito Nro 04 del tablero de iluminación existente 0310-LPA-0003
TI7024 Conexión eléctrica en el circuito Nro 08 del tablero de iluminación existente 28-Aug-21 00:00 A 30-Nov-21 114.60 Conexión eléctrica en el circuito Nro 08 del tablero de iluminación existente 0310-LPA-0003
TI7011 Conexión eléctrica en el circuito Nro 30 del tablero de iluminación existente 28-Aug-21 06:00 A 28-Aug-21 1.00o Nro 30 del tablero de iluminación existente 0310-LPA-0004
TI7012 Conexión eléctrica en el circuito Nro 25 del tablero de iluminación existente 28-Aug-21 06:00 A 28-Aug-21 1.00o Nro 25 del tablero de iluminación existente 0310-LPA-0302
TI7016 Puesta a tierra para el nuevo sistema de bombeo de agua de enfriamiento 28-Aug-21 06:00 A 28-Aug-21 1.00 istema de bombeo de agua de enfriamiento para el molino de bolas N° 3
TI7017 Conexión de la nueva malla a tierra de la ampliación de las estructuras de 28-Aug-21 06:00 A 28-Aug-21 1.00 tierra de la ampliación de las estructuras del edificio de molienda
TI7026 Conexión eléctrica en el circuito Nro 02 del tablero de iluminación existente 28-Aug-21 06:00 A 28-Aug-21 1.00o Nro 02 del tablero de iluminación existente 0310-LPA-0303
TI7014 Conexión de la nueva malla a tierra del área del molino de bolas N° 3 será 21-Nov-21 06:00 24-Nov-21 4.00 Conexión de la nueva malla a tierra del área del molino de bolas N° 3 será en 6 puntos de la malla existente de planta
TI7015 Puesta a tierra de la sala eléctrica N ° 3 (E-House) será a traves de la barra 15-Feb-22 06:00 18-Feb-22 4.00 Puesta a tierra de la sala eléctrica N ° 3 (E-House) será a traves de la barra equipotencial existente
TI7018 Conexión de la puesta a tierra de bandejas de la ampliación de la faja tran 15-Feb-22 06:00 18-Feb-22 4.00 Conexión de la puesta a tierra de bandejas de la ampliación de la faja transportadora de bolas
TI7021 Reubicación de motor de faja transportadora de bolas 0240-CVB-0009 15-Feb-22 06:00 18-Feb-22 4.00 Reubicación de motor de faja transportadora de bolas 0240-CVB-0009
TI7025 La Conexión eléctrica para el nuevo circuito de tomacorrientes en 480V pa 15-Feb-22 06:00 18-Feb-22 4.00 La Conexión eléctrica para el nuevo circuito de tomacorrientes en 480V para la plataforma de operaciones
TI7040 Conexión hacia nuevos flujometros electromágneticos 0310-FIT-01613/01 15-Feb-22 06:00 18-Feb-22 4.00 Conexión hacia nuevos flujometros electromágneticos 0310-FIT-01613/01614/01554/01612, valvula de control 0310-H
TI7041 Conexión hacia motor de nueva bomba dosificadora 0392-PPD-0050 desd 15-Feb-22 06:00 18-Feb-22 4.00 Conexión hacia motor de nueva bomba dosificadora 0392-PPD-0050 desde circuito N° 35 del tablero existente 0392-D
TI7042 Conexión hacia motor de nueva bomba dosificadora 0392-PPD-0068 desd 15-Feb-22 06:00 18-Feb-22 4.00 Conexión hacia motor de nueva bomba dosificadora 0392-PPD-0068 desde circuito N° 37 del tablero existente 0392-D

Actual Level of Effort Actual Work Critical Remaining Work Page 16 of 20 TASK filter: All Activities
Primary Baseline Remaining Work Milestone © Oracle Corporation
Cronograma del Proyecto: Construccion e Instalacion del 3er Molino de Bolas y Obras Asociadas
Linea Base 1 Rev. 0 (actualizado al 22-octubre)
Activity ID Activity Name Start Finish Original October 2021 November 2021 December 2021 January 2022 February 2022 March 2022 April 2022 May 2022 June 2022 July 2022
Duration
09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 05 12 19 26 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 02 09 6
Instrumentacion 18-Feb-22 06:00 25-Feb-22 7.40 25-Feb-22 10:00, Instrumentacion
TI8025 Tie in 8025: Integración de nueva válvula 0310-HV-01565 a tablero de con 18-Feb-22 06:00 21-Feb-22 4.00 Tie in 8025: Integración de nueva válvula 0310-HV-01565 a tablero de control 0310-JBP-0302-02
TI8026 Tie in 8026: Integración de nueva válvula 0310-HV-01566 a tablero de con 18-Feb-22 06:00 21-Feb-22 4.00 Tie in 8026: Integración de nueva válvula 0310-HV-01566 a tablero de control 0310-JBP-0401-01
TI8005 Instalación de Fibra Optica para la comunicacion de 0310-MLB-03-COB2 y 20-Feb-22 06:00 22-Feb-22 3.00 Instalación de Fibra Optica para la comunicacion de 0310-MLB-03-COB2 y 0310-COA-006 integración del 3er molin
TI8010 Actualización del SCADA del sistema de control de procesos existente (PC 20-Feb-22 06:00 22-Feb-22 3.00 Actualización del SCADA del sistema de control de procesos existente (PCS)
TI8011 Reubicación de instrumentos de seguridad e Instalación de nuevos instrum 20-Feb-22 06:00 22-Feb-22 3.00 Reubicación de instrumentos de seguridad e Instalación de nuevos instrumentos de seguridad (alarmas y pull cord)
TI8012 Integración del sistema de detección de incendio( 0310-FP-601S, 0310-FP 20-Feb-22 06:00 22-Feb-22 3.00 Integración del sistema de detección de incendio( 0310-FP-601S, 0310-FP-604S, 0310-FP-605S, 0310-FP-606S, 0
TI8013 Integración del sistema de detección de incendio( 0310-FP-602S, 0310-FP 20-Feb-22 06:00 22-Feb-22 3.00 Integración del sistema de detección de incendio( 0310-FP-602S, 0310-FP-603S)
TI8021-SD2 Tie in 8021: Instalacion cableado y conexion de valvula cuchilla de 42" (hid 21-Feb-22 06:00 23-Feb-22 3.00 Tie in 8021: Instalacion cableado y conexion de valvula cuchilla de 42" (hidraulicas) 0310-HV-01556 y 0310-HV-015
TI8014 Instalación, cableado y conexionado del tablero de 031-JBP-601-02 al 031 22-Feb-22 10:00 25-Feb-22 3.00 Instalación, cableado y conexionado del tablero de 031-JBP-601-02 al 0310-COA-003
TI8015 Reubicacion de instrumentos y de paneles campo 0310-PI-012507/11/15/ 22-Feb-22 10:00 25-Feb-22 3.00 Reubicacion de instrumentos y de paneles campo 0310-PI-012507/11/15/19 y 0310-PIT-012530A/B/C/D
TI8016 Instalación de nueva bomba de reactivos - colector primario (0392-PPD-05 22-Feb-22 10:00 25-Feb-22 3.00 Instalación de nueva bomba de reactivos - colector primario (0392-PPD-050) en la red PROFIBUS existente
TI8017 Instalación de nueva bomba de reactivos - colector primario (0392-PPD-06 22-Feb-22 10:00 25-Feb-22 3.00 Instalación de nueva bomba de reactivos - colector primario (0392-PPD-068) en la red PROFIBUS existente
TI8020 Integración con el sistema CCTV existente de la cámara CCTV 0310-YE-0 22-Feb-22 10:00 25-Feb-22 3.00 Integración con el sistema CCTV existente de la cámara CCTV 0310-YE-01247
Piping 15-Oct-21 06:00 A 17-Feb-22 118.00 17-Feb-22 17:00, Piping
TI6055 Tie in 6055: Conexión de nueva tubería de agua de procesos a válvula ac 15-Feb-22 06:00 17-Feb-22 3.00 Tie in 6055: Conexión de nueva tubería de agua de procesos a válvula actuada 0310-HV-01554
Tie Ins - SCI 15-Oct-21 06:00 A 20-Nov-21 29.00 20-Nov-21 17:00, Tie Ins - SCI
TI6513-T TIE-IN 6513T:Cambio de recorrido de tubería (con reemplazo). 15-Oct-21 06:00 A 15-Oct-21 1.00 TIE-IN 6513T:Cambio de recorrido de tubería (con reemplazo).
TI6515-T TIE-IN 6515T:Conexión con tuberia de alimentación de hidrante FH-67. 15-Oct-21 06:00 A 15-Oct-21 1.00 TIE-IN 6515T:Conexión con tuberia de alimentación de hidrante FH-67.
TI6043 Tie in 6043: Reubicación de línea de alimentación de agua contra incendio 17-Oct-21 06:00 A 23-Oct-21 1.00 Tie in 6043: Reubicación de línea de alimentación de agua contra incendio.
TI6040 Tie in 6040:Reubicación de tuberías de agua contra incendio por cambio d 17-Oct-21 06:00 A 07-Nov-21 1.00 Tie in 6040:Reubicación de tuberías de agua contra incendio por cambio de ubicación
TI6039 Tie in 6039: Reubicación de tubería enterrada (6"-0921-WF-00611-M2F0H 17-Oct-21 06:00 A 06-Nov-21 1.00 Tie in 6039: Reubicación de tubería enterrada (6"-0921-WF-00611-M2F0H)
TI6041 Tie in 6041: Reubicación de tuberías de agua contra incendio por cambio 17-Oct-21 06:00 A 06-Nov-21 1.00 Tie in 6041: Reubicación de tuberías de agua contra incendio por cambio de ubicación de manifold N° 1.
TI6044 Tie in 6044: Conexión de línea nueva 4"-0310-WF-06563-C1F2A-WIE. 17-Oct-21 06:00 A 06-Nov-21 1.00 Tie in 6044: Conexión de línea nueva 4"-0310-WF-06563-C1F2A-WIE.
TI6045 TIE-IN 6045: Conexión de línea nueva 4"-0310-WF-06564-C1F2A-WIE. 17-Oct-21 06:00 A 07-Nov-21 1.00 TIE-IN 6045: Conexión de línea nueva 4"-0310-WF-06564-C1F2A-WIE.
TI6038 Tie in 6038: Reubicación de hidrante FH-67 (con reemplazo). 20-Nov-21 06:00 20-Nov-21 1.00 Tie in 6038: Reubicación de hidrante FH-67 (con reemplazo).
Parada de Planta - Febrero
Febr 2022 17-Aug-21 00:00 A 21-Mar-22 217.00 21-Mar-22 17:00, Parada de Planta - Febrero 2022
Electricidad 26-Jan-22 06:00 23-Feb-22 28.00 23-Feb-22 06:00, Electricidad
TI7000-SD2 Trabajos previos a parada de planta febrero-2022 (Electricidad) 26-Jan-22 06:00 14-Feb-22 20.00 Trabajos previos a parada de planta febrero-2022 (Electricidad)
TI7002 Desconexión y reconexión de cables de media tensión que suministran en 15-Feb-22 06:00 19-Feb-22 4.00 Desconexión y reconexión de cables de media tensión que suministran energía al motor (SPS-004)
TI7020 Ampliación del sistema de barras de cobre para la alimentación eléctrica d 15-Feb-22 06:00 19-Feb-22 4.00 Ampliación del sistema de barras de cobre para la alimentación eléctrica de la grúa puente de los molinos de bolas
TI7032 Conexión eléctrica hacia 0310-MLB-0003-MCL1 desde cubiculo de reserva 15-Feb-22 06:00 19-Feb-22 4.00 Conexión eléctrica hacia 0310-MLB-0003-MCL1 desde cubiculo de reserva N° CB-04 del Switchgear 0310-SGL-0004
TI7034 Reubicación de Centro de control de motores 0310-MLB-0001-MCL2, ubic 15-Feb-22 06:00 19-Feb-22 4.00 Reubicación de Centro de control de motores 0310-MLB-0001-MCL2, ubicado en la sala electrica 0310-ERR-0001
TI7035 Reubicación de Centro de control de motores 0310-MLB-0002-MCL2, ubic 15-Feb-22 06:00 19-Feb-22 4.00 Reubicación de Centro de control de motores 0310-MLB-0002-MCL2, ubicado en la sala electrica 0310-ERR-0001
TI7003 Se requiere la desconexión y reconexión de cables de control de la estació 17-Feb-22 06:00 21-Feb-22 4.00 Se requiere la desconexión y reconexión de cables de control de la estación de control local del motor (SPS-004)
TI7004 Se requiere la desconexión y reconexión de cables de media tensión que 17-Feb-22 06:00 21-Feb-22 4.00 Se requiere la desconexión y reconexión de cables de media tensión que suministran energía al motor(SPS-001)
TI7006 Tie in 7006: Conexión eléctrica mediante cables en media tensión entre el 18-Feb-22 06:00 22-Feb-22 4.00 Tie in 7006: Conexión eléctrica mediante cables en media tensión entre el switchgear GIS 33kV (0931-SGM-0001)
TI7001 Reubicar Conduit existentes de alimentación eléctrica de la grúa puente in 18-Feb-22 06:00 22-Feb-22 4.00 Reubicar Conduit existentes de alimentación eléctrica de la grúa puente in la columna de eje 8-D
TI7005 Se requiere la desconexión y reconexión de cables de control de la estació 19-Feb-22 06:00 23-Feb-22 4.00 Se requiere la desconexión y reconexión de cables de control de la estación de control local del motor (SPS-001)
Instrumentación 17-Aug-21 00:00 A 23-Feb-22 190.00 23-Feb-22 06:00, Instrumentación
TI8000-SD2 Trabajos previos a parada de planta febrero-2022 (Instrumentacion) 17-Aug-21 00:00 A 17-Feb-22 185.00 Trabajos previos a parada de planta febrero-2022 (Instrumentacion)
TI8022 Instalacion de la nueva linea de enfriadores para el nuevol molino de bolas 18-Feb-22 06:00 21-Feb-22 3.00 Instalacion de la nueva linea de enfriadores para el nuevol molino de bolas 3
TI8001 Cambio de bomba (SPS-004)Instalar nuevas valvulas y nuevo ruteo condu 19-Feb-22 17:00 22-Feb-22 3.00 Cambio de bomba (SPS-004)Instalar nuevas valvulas y nuevo ruteo conduit y cableado
TI8002 Cambio de bomba (SPS-001)Instalar nuevas valvulas y nuevo ruteo condu 19-Feb-22 17:00 22-Feb-22 3.00 Cambio de bomba (SPS-001)Instalar nuevas valvulas y nuevo ruteo conduit y cableado
TI8003 Instalación, cableado, conexionado, configuración y puesta en operación d 19-Feb-22 17:00 22-Feb-22 3.00 Instalación, cableado, conexionado, configuración y puesta en operación de flujometro Sonar en linea de 36´ Linea
TI8004 Instalación, cableado, conexionado, configuración y puesta en operación d 19-Feb-22 17:00 22-Feb-22 3.00 Instalación, cableado, conexionado, configuración y puesta en operación de flujometro Sonar en linea de 36´ Linea
TI8009 Conexion del 3er Molino de bolas a todos los tableros de control 20-Feb-22 06:00 23-Feb-22 3.00 Conexion del 3er Molino de bolas a todos los tableros de control
Piping 26-Jan-22 06:00 22-Feb-22 27.00 22-Feb-22 06:00, Piping
TI6000-SD2 Trabajos previos a parada de planta febrero-2022 (Piping) 26-Jan-22 06:00 14-Feb-22 20.00 Trabajos previos a parada de planta febrero-2022 (Piping)
TI6012 Tie in 6012: Connection of 42"-0310-SL-06714 of 0310-CSC-0004 to new 15-Feb-22 06:00 19-Feb-22 4.00 Tie in 6012: Connection of 42"-0310-SL-06714 of 0310-CSC-0004 to new Transfer Chute 0310-STP-0101
TI6008 Tie in 6008: Connection in existing pipe of 0310-CSC-0004 with new line 3 15-Feb-22 06:00 19-Feb-22 4.00 Tie in 6008: Connection in existing pipe of 0310-CSC-0004 with new line 36''-0310-SL-06504
TI6001 Tie in 6001: Replace slurry piping 36"-0310-SL-06201 between 0310-SUL- 15-Feb-22 06:00 19-Feb-22 4.00 Tie in 6001: Replace slurry piping 36"-0310-SL-06201 between 0310-SUL-0001 and pump 0310-PPS-0001
TI6002 Tie in 6002: Replacee process water 12”-0310-WP-06231 between 0310-S 15-Feb-22 06:00 19-Feb-22 4.00 Tie in 6002: Replacee process water 12”-0310-WP-06231 between 0310-SUL-0001 and 0310-PPS-0001
TI6005 Tie in 6005: Replace slurry piping 36"-0310-SL-06503 between 0310-SUL- 15-Feb-22 06:00 19-Feb-22 4.00 Tie in 6005: Replace slurry piping 36"-0310-SL-06503 between 0310-SUL-0002 and 0310-PPS-0004
TI6004 Tie in 6004: Connection in existing pipe of 0310-CSC-0001 with new line o 16-Feb-22 06:00 20-Feb-22 4.00 Tie in 6004: Connection in existing pipe of 0310-CSC-0001 with new line of slurry 36”-0310-SL-06202
TI6006 Tie in 6006: Replacee process water 12”-0310-WP-06848 between 0310-S 16-Feb-22 06:00 20-Feb-22 4.00 Tie in 6006: Replacee process water 12”-0310-WP-06848 between 0310-SUL-0002 and 0310-PPS-0004)
TI6085 Tie in 6085: Connection of 42"-0310-SL-06717 from 0310-CSC-0003 to D 19-Feb-22 06:00 22-Feb-22 3.00 Tie in 6085: Connection of 42"-0310-SL-06717 from 0310-CSC-0003 to Distribution Box 0310-STP-0108
TI6052 Tie in 6052: Hose Connection to feed the new pump model 660 (0310-PP 19-Feb-22 06:00 21-Feb-22 2.00 Tie in 6052: Hose Connection to feed the new pump model 660 (0310-PPS-0004)
TI6051 Tie in 6051: Hose Connection to feed the new pump model 660 (0310-PP 19-Feb-22 06:00 21-Feb-22 2.00 Tie in 6051: Hose Connection to feed the new pump model 660 (0310-PPS-0001)
Mecanica 26-Jan-22 06:00 23-Feb-22 29.00 23-Feb-22 17:00, Mecanica
TI5000-SD2 Trabajos previos a parada de planta febrero-2022 (Mecanico) 26-Jan-22 06:00 14-Feb-22 20.00 Trabajos previos a parada de planta febrero-2022 (Mecanico)
TI5012 Tie in 5012: Extensión y conexión la faja transportadora de bolas, 15-Feb-22 06:00 19-Feb-22 4.00 Tie in 5012: Extensión y conexión la faja transportadora de bolas,
TI5010 Tie in 5010: Removal existing launder 0310-LAL-0012 and replacing with la 15-Feb-22 06:00 19-Feb-22 4.00 Tie in 5010: Removal existing launder 0310-LAL-0012 and replacing with launder 0310-LAL-0014

Actual Level of Effort Actual Work Critical Remaining Work Page 17 of 20 TASK filter: All Activities
Primary Baseline Remaining Work Milestone © Oracle Corporation
Cronograma del Proyecto: Construccion e Instalacion del 3er Molino de Bolas y Obras Asociadas
Linea Base 1 Rev. 0 (actualizado al 22-octubre)
Activity ID Activity Name Start Finish Original October 2021 November 2021 December 2021 January 2022 February 2022 March 2022 April 2022 May 2022 June 2022 July 2022
Duration
09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 05 12 19 26 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 02 09 6
TI5006 Tie in 5006: Modification underflow launder of 0310- CSC-0003. Nozzle an 15-Feb-22 06:00 19-Feb-22 4.00 Tie in 5006: Modification underflow launder of 0310- CSC-0003. Nozzle and launder floor are modified
TI5011 Tie in 5011: Extensión y conexión a la faja transportadora de bolas (0240-S 15-Feb-22 06:00 18-Feb-22 3.00 Tie in 5011: Extensión y conexión a la faja transportadora de bolas (0240-STP-0312) reubicación de polea de motriz
TI5015 Tie in 5015: Extensión de la faja de alimentación de bolas requiere nueva 15-Feb-22 06:00 18-Feb-22 3.00 Tie in 5015: Extensión de la faja de alimentación de bolas requiere nueva pieza de faja y ser vulcanizado
TI5007 Tie in 5007: Modification underflow launder of 0310- CSC-0002. Nozzle an 16-Feb-22 06:00 20-Feb-22 4.00 Tie in 5007: Modification underflow launder of 0310- CSC-0002. Nozzle and launder floor are modified
TI5017 Tie in 5017: Replace the existing feed pump to cyclone cluster 4 (0310-PP 18-Feb-22 17:00 22-Feb-22 4.00 Tie in 5017: Replace the existing feed pump to cyclone cluster 4 (0310-PPS-0004
TI5018 Tie in 5018: Replace the pump base plate due of replacement from mode 19-Feb-22 17:00 23-Feb-22 4.00 Tie in 5018: Replace the pump base plate due of replacement from model 650 to 660
TI5019 Tie in 5019: Replace the existing feed pump 0310-PPS-0001 model 650 to 19-Feb-22 17:00 22-Feb-22 3.00 Tie in 5019: Replace the existing feed pump 0310-PPS-0001 model 650 to new pump model 660
TI5020 Tie in 5020: Replace the pump frame due of replacement of pump model 19-Feb-22 17:00 23-Feb-22 4.00 Tie in 5020: Replace the pump frame due of replacement of pump model 650 to 660
Shutdown Febrero-20
Febrero-2022 - Ball Charge 17-Feb-22 06:00 21-Feb-22 4.33 21-Feb-22 14:00, Shutdown Febrero-2022 - Ball Charge
MX-0500-1650 Install Head Pully and Frame (8.0 hrs.) 17-Feb-22 06:00 17-Feb-22 0.33 Install Head Pully and Frame (8.0 hrs.)
TI-0500-1245 TI-014: Modification -Top of Feed Box BM # 2 - Ball Chute Alignment (24.0 17-Feb-22 14:00 18-Feb-22 1.00 TI-014: Modification -Top of Feed Box BM # 2 - Ball Chute Alignment (24.0 hrs.)
TI-0500-1040 TI-006: Remove Milk of Lime Manifold (24.0 hrs) 18-Feb-22 14:00 19-Feb-22 1.00 TI-006: Remove Milk of Lime Manifold (24.0 hrs)
MX-0500-1250 Remove Tension Cut Belt (4.0 hrs.) 18-Feb-22 14:00 18-Feb-22 0.17 Remove Tension Cut Belt (4.0 hrs.)
MX-0500-1630 Remove Head Pully and Frame (6.0 hrs.) 18-Feb-22 18:00 19-Feb-22 0.25 Remove Head Pully and Frame (6.0 hrs.)
MX-0500-1640 Remove Ball Chute Mill # 2 0240-STP-312 (2.0 hrs.) 19-Feb-22 00:00 19-Feb-22 0.08 Remove Ball Chute Mill # 2 0240-STP-312 (2.0 hrs.)
MX-0500-1660 Installation of New Ball Chute Mill # 2 0240-STP-254 (2.0 hrs.) 19-Feb-22 02:00 19-Feb-22 0.08 Installation of New Ball Chute Mill # 2 0240-STP-254 (2.0 hrs.)
MX-0500-1620 Remove Power Drive Motor Deck Level (3.0 hrs.) 19-Feb-22 02:00 19-Feb-22 0.13 Remove Power Drive Motor Deck Level (3.0 hrs.)
MX-0500-1680 Installation New Ball Diversion Gate 0240-STP-0253 & tie in piping (4.0 hrs 19-Feb-22 04:00 19-Feb-22 0.17 Installation New Ball Diversion Gate 0240-STP-0253 & tie in piping (4.0 hrs.)
MX-0500-1670 Connect Power Cables Drive Motor Deck Level (12.0 hrs.) 19-Feb-22 05:00 19-Feb-22 0.50 Connect Power Cables Drive Motor Deck Level (12.0 hrs.)
TI-0500-1590 TI-008: Resolve Pipe Clashes - Process Water (24.0 hrs) 19-Feb-22 14:00 20-Feb-22 1.00 TI-008: Resolve Pipe Clashes - Process Water (24.0 hrs)
MX-0500-1690 Complete Conveyor Transition Frame Deck Level 0240-CVB-009 (6.0 hrs.) 19-Feb-22 17:00 19-Feb-22 0.25 Complete Conveyor Transition Frame Deck Level 0240-CVB-009 (6.0 hrs.)
MX-0500-1710 Relocation of Panel 0330-JBP-0305-01 Deck Level (8.0 hrs.) 19-Feb-22 23:00 20-Feb-22 0.33 Relocation of Panel 0330-JBP-0305-01 Deck Level (8.0 hrs.)
MX-0500-1720 Modifications to Structural Steel Deck Level 20-Feb-22 07:00 20-Feb-22 0.50 Modifications to Structural Steel Deck Level
TI-0500-1680 TI-009: Resolve Pipe Clashes - Air (24.0 hrs) 20-Feb-22 14:00 21-Feb-22 1.00 TI-009: Resolve Pipe Clashes - Air (24.0 hrs)
MX-0500-1700 Installation of Belt & Splicing (4.0 hrs.) 20-Feb-22 19:00 20-Feb-22 0.17 Installation of Belt & Splicing (4.0 hrs.)
H1350 Mechanical Completion - Sistema de alimentación de Bolas 21-Feb-22 0.00 Mechanical Completion - Sistema de alimentación de Bolas,
Transtition Shutdown - Slurry Line 1 15-Feb-22 06:00 17-Feb-22 2.29 17-Feb-22 13:00, Transtition Shutdown - Slurry Line 1
MX1485 Remove spool Cyclone Victolic Flange (3.0 hrs.) 15-Feb-22 06:00 15-Feb-22 0.13 Remove spool Cyclone Victolic Flange (3.0 hrs.)
PX1490 Install new 36" spools Cyclone Launder Floor (3.0 hrs.) 15-Feb-22 09:00 15-Feb-22 0.13 Install new 36" spools Cyclone Launder Floor (3.0 hrs.)
PX1450 Remove Existing Pipe line (12.0 hrs.) 15-Feb-22 17:00 16-Feb-22 0.50 Remove Existing Pipe line (12.0 hrs.)
TI1460 Tie in 8003/8004 :Remove Flow Meter & Nuclear Densimete (3.0 hrs.) 15-Feb-22 17:00 15-Feb-22 0.13 Tie in 8003/8004 :Remove Flow Meter & Nuclear Densimete (3.0 hrs.)
PX1465 Remove Pipe spools Operating Floor (6.0 hrs.) 15-Feb-22 20:00 16-Feb-22 0.25 Remove Pipe spools Operating Floor (6.0 hrs.)
PX1475 Install new 36" spools Operations Floor (8.0 hrs.) 16-Feb-22 02:00 16-Feb-22 0.33 Install new 36" spools Operations Floor (8.0 hrs.)
SX1455 Replace Support Structural frame (8.0 hrs.) 16-Feb-22 05:00 16-Feb-22 0.33 Replace Support Structural frame (8.0 hrs.)
TI1480 Tie in 8003/8004 :Installation of new 36" Flow Meter & Nuclear Densimete 16-Feb-22 10:00 16-Feb-22 0.13 Tie in 8003/8004 :Installation of new 36" Flow Meter & Nuclear Densimete (3.0 hrs.)
PX1470 Installation of new 36" pipe Section (24.0 hrs.) 16-Feb-22 13:00 17-Feb-22 1.00 Installation of new 36" pipe Section (24.0 hrs.)
H1670 Slurry Pipe Line #1 - Mechanical Completion 17-Feb-22 0.00 Slurry Pipe Line #1 - Mechanical Completion,
Transtition Shutdown - Slurry Line 4 18-Feb-22 06:00 21-Feb-22 3.63 21-Feb-22 21:00, Transtition Shutdown - Slurry Line 4
MX1650 Remove spool Cyclone Victolic Flange (3.0 hrs.) 18-Feb-22 06:00 19-Feb-22 1.00 Remove spool Cyclone Victolic Flange (3.0 hrs.)
PX-0500-1220 Remove 4 x Pipe spools Ground Floor (4.0 hrs.) 18-Feb-22 17:00 18-Feb-22 0.17 Remove 4 x Pipe spools Ground Floor (4.0 hrs.)
IX1300 Remove Flow Meter & Nuclear Densimeter (3.0 hrs.) 18-Feb-22 17:00 19-Feb-22 1.00 Remove Flow Meter & Nuclear Densimeter (3.0 hrs.)
SX1240 Excavation under pipe - Install Support Structure (80.0 hrs.) 18-Feb-22 21:00 21-Feb-22 3.00 Excavation under pipe - Install Support Structure (80.0 hrs.)
PX-0500-1225 Remove vertical pipe spools Ground Floor (8.0 hrs.) 18-Feb-22 21:00 19-Feb-22 1.00 Remove vertical pipe spools Ground Floor (8.0 hrs.)
PX-0500-1660 Install new 36" spools Cyclone Launder Floor (3.0 hrs.) 19-Feb-22 06:00 20-Feb-22 1.00 Install new 36" spools Cyclone Launder Floor (3.0 hrs.)
IX1320 Installation of new 36" Flow Meter & Nuclear Densimete (3.0 hrs.) 19-Feb-22 17:00 20-Feb-22 0.50 Installation of new 36" Flow Meter & Nuclear Densimete (3.0 hrs.)
PX-0500-1305 Remove Pipe spools Operating Floor (6.0 hrs.) 19-Feb-22 17:00 19-Feb-22 0.00 Remove Pipe spools Operating Floor (6.0 hrs.)
PX-0500-1315 Install new 36" spools Operations Floor (8.0 hrs.) 19-Feb-22 17:00 19-Feb-22 0.00 Install new 36" spools Operations Floor (8.0 hrs.)
SX1245 Replace Support Structural frame (12.0 hrs.) 19-Feb-22 21:00 20-Feb-22 0.50 Replace Support Structural frame (12.0 hrs.)
PX-0500-1250 Install new 36" spools Ground Floor (8.0 hrs.) 20-Feb-22 01:00 20-Feb-22 0.00 Install new 36" spools Ground Floor (8.0 hrs.)
PX-0500-1248 Install new 36" vertical spools Ground Floor (8.0 hrs.) 20-Feb-22 01:00 21-Feb-22 1.00 Install new 36" vertical spools Ground Floor (8.0 hrs.)
H1671 Slurry Pipe Line #4 - Mechanical Completion 20-Feb-22 0.00 Slurry Pipe Line #4 - Mechanical Completion,
Transtition Shutdown - Slurry Pump 1 15-Mar-22 17:00 21-Mar-22 6.00 21-Mar-22 17:00, Transtition Shutdown - Slurry Pump 1
MX1500 Remove Pump 650 (6.0 hrs.) 15-Mar-22 17:00 16-Mar-22 0.50 Remove Pump 650 (6.0 hrs.)
MX1510 Remove Pump 650 - Motor (8.0 hrs.) 16-Mar-22 05:00 16-Mar-22 0.50 Remove Pump 650 - Motor (8.0 hrs.)
MX1520 Remove Base Plate Pump 650 (6.0 hrs.) 16-Mar-22 17:00 17-Mar-22 0.50 Remove Base Plate Pump 650 (6.0 hrs.)
CX1390 Grout Removal and Packer installation (6.0 hrs.) 17-Mar-22 05:00 17-Mar-22 0.50 Grout Removal and Packer installation (6.0 hrs.)
MX1530 Installation of Base Plate Pump 660 (6.0 hrs.) 17-Mar-22 17:00 18-Mar-22 0.50 Installation of Base Plate Pump 660 (6.0 hrs.)
MX1550 Install Old 650 - Motor (12.0 hrs.) 18-Mar-22 05:00 18-Mar-22 0.50 Install Old 650 - Motor (12.0 hrs.)
MX1540 Install New Pump 660 (8.0 hrs.) 19-Mar-22 17:00 20-Mar-22 0.50 Install New Pump 660 (8.0 hrs.)
MX1560 Complete Alignment Pump 660 (6.0 hrs.) 20-Mar-22 05:00 20-Mar-22 0.50 Complete Alignment Pump 660 (6.0 hrs.)
IX1570 Pump VSD Software Upgrade (4.0 hrs.) 20-Mar-22 17:00 21-Mar-22 0.50 Pump VSD Software Upgrade (4.0 hrs.)
PX-0500-1580 Commissioning (8.0 hrs.) 21-Mar-22 05:00 21-Mar-22 0.50 Commissioning (8.0 hrs.)
CX1400 Grout Base Frame (8.0 hrs.) 21-Mar-22 05:00 21-Mar-22 0.50 Grout Base Frame (8.0 hrs.)

Actual Level of Effort Actual Work Critical Remaining Work Page 18 of 20 TASK filter: All Activities
Primary Baseline Remaining Work Milestone © Oracle Corporation
Cronograma del Proyecto: Construccion e Instalacion del 3er Molino de Bolas y Obras Asociadas
Linea Base 1 Rev. 0 (actualizado al 22-octubre)
Activity ID Activity Name Start Finish Original October 2021 November 2021 December 2021 January 2022 February 2022 March 2022 April 2022 May 2022 June 2022 July 2022
Duration
09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 05 12 19 26 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 02 09 6
Transtition Shutdown - Slurry Pump 4 12-Mar-22 17:00 18-Mar-22 5.50 18-Mar-22 05:00, Transtition Shutdown - Slurry Pump 4
MX-1410 Remove Pump 650 - Motor (8.0 hrs.) 12-Mar-22 17:00 13-Mar-22 0.50 Remove Pump 650 - Motor (8.0 hrs.)
MX1400 Remove Pump 650 (6.0 hrs.) 13-Mar-22 05:00 13-Mar-22 0.50 Remove Pump 650 (6.0 hrs.)
MX1420 Remove Base Plate Pump 650 (6.0 hrs.) 13-Mar-22 17:00 14-Mar-22 0.50 Remove Base Plate Pump 650 (6.0 hrs.)
CX-0500-1370 Grout Removal and Packer installation (6.0 hrs.) 14-Mar-22 05:00 15-Mar-22 1.00 Grout Removal and Packer installation (6.0 hrs.)
MX1430 Installation of Base Plate Pump 660 (6.0 hrs.) 15-Mar-22 05:00 16-Mar-22 1.00 Installation of Base Plate Pump 660 (6.0 hrs.)
MX1440 Install New Pump 660 (8.0 hrs.) 16-Mar-22 05:00 17-Mar-22 1.00 Install New Pump 660 (8.0 hrs.)
MX1450 Install Old 650 - Motor (12.0 hrs.) 16-Mar-22 05:00 16-Mar-22 0.50 Install Old 650 - Motor (12.0 hrs.)
MX1460 Complete Alignment Pump 660 (6.0 hrs.) 17-Mar-22 05:00 17-Mar-22 0.50 Complete Alignment Pump 660 (6.0 hrs.)
IX1470 Pump VSD Software Upgrade (4.0 hrs.) 17-Mar-22 05:00 17-Mar-22 0.50 Pump VSD Software Upgrade (4.0 hrs.)
CX-0500-1380 Grout Base Frame (8.0 hrs.) 17-Mar-22 17:00 18-Mar-22 0.50 Grout Base Frame (8.0 hrs.)
PX-0500-1480 Commissioning (8.0 hrs.) 17-Mar-22 17:00 18-Mar-22 0.50 Commissioning (8.0 hrs.)
21-Jun-21 06:00 A 13-Mar-22 266.00 13-Mar-22 17:00, Harmonic Filter
Harmonic Filter
Hitos 21-Jun-21 06:00 A 13-Mar-22 266.00 13-Mar-22 17:00, Hitos
Generales 21-Jun-21 06:00 A 28-Jun-21 8.00
H16370 KOM 21-Jun-21 06:00 A 0.00
H16380 Firma de Contrato 28-Jun-21 0.00
Procura 23-Oct-21 06:00 20-Jan-22 90.00 20-Jan-22 17:00, Procura
H16390 Inicio de Procura 23-Oct-21 06:00* 0.00 Inicio de Procura, 23-Oct-21 06:00*
H16400 Fin de Procura 20-Jan-22 0.00 Fin de Procura,
Construccion 23-Oct-21 06:00 13-Mar-22 142.00 13-Mar-22 17:00, Construccion
H16410 Inicio de Construccion 23-Oct-21 06:00* 0.00 Inicio de Construccion, 23-Oct-21 06:00*
H16420 Fin de Construccion 13-Mar-22 0.00 Fin de Construccion,

Procura 23-Oct-21 06:00 20-Jan-22 90.00 20-Jan-22 17:00, Procura


H16430 Procura 23-Oct-21 06:00 20-Jan-22 90.00 Procura
Construccion 14-Sep-21 06:00 A 13-Mar-22 181.00 13-Mar-22 17:00, Construccion
Documentacion 17-Nov-21 06:00 01-Dec-21 15.00 01-Dec-21 17:00, Documentacion
H16440 Documentacion (PETS, Procedimientos, Planes) 17-Nov-21 06:00 01-Dec-21 15.00 Documentacion (PETS, Procedimientos, Planes)
Obras Preliminares 23-Oct-21 06:00 13-Mar-22 142.00 13-Mar-22 17:00, Obras Preliminares
H16520 Desmovilizacion (Contratista de Obras Civiles y Estructuras) 23-Oct-21 0.00 Desmovilizacion (Contratista de Obras Civiles y Estructuras),
H16530 Liberacion y transferencia de las Obras Civiles y de Estructuras (por QA/QC 23-Oct-21 06:00 26-Nov-21 35.00 Liberacion y transferencia de las Obras Civiles y de Estructuras (por QA/QC de MCC)
H16450 Movilizacion de Personal 12-Nov-21 06:00 16-Nov-21 5.00 Movilizacion de Personal
H16460 Instalacion de facilidades 17-Nov-21 06:00 26-Nov-21 10.00 Instalacion de facilidades
H16470 Trazo y replanteo 27-Nov-21 06:00 07-Feb-22 73.00 Trazo y replanteo
H16480 Desmovilizacion 10-Mar-22 06:00 13-Mar-22 4.00 Desmovilizacion
Trabajos Electricos 18-Dec-21 06:00 05-Feb-22 50.00 05-Feb-22 17:00, Trabajos Electricos
FX1200 Installation Cable Earthing (equipos) 18-Dec-21 06:00 24-Dec-21 7.00 Installation Cable Earthing (equipos)
FX1240 Installation Cable Tray / Ladde 18-Dec-21 06:00 01-Jan-22 15.00 Installation Cable Tray / Ladde
FX1250 Installation Conduit 22-Dec-21 06:00 26-Dec-21 5.00 Installation Conduit
FX1180 Installation Power < 1000V 02-Jan-22 06:00 16-Jan-22 15.00 Installation Power < 1000V
FX1490 Installation Cable Earthing Term (bandejas) 02-Jan-22 06:00 03-Jan-22 2.00 Installation Cable Earthing Term (bandejas)
FX1190 Installation Power Cable 33kV 21-Jan-22 06:00 27-Jan-22 7.00 Installation Power Cable 33kV
FX1210 Installation Power Cable Term 28-Jan-22 06:00 01-Feb-22 5.00 Installation Power Cable Term
FX1260 Illumination 02-Feb-22 06:00 05-Feb-22 4.00 Illumination
Montaje Electromecanico 28-Nov-21 06:00 11-Feb-22 76.00 11-Feb-22 17:00, Montaje Electromecanico
FX1270 Patio de Filtros - Montaje 28-Nov-21 06:00 17-Dec-21 20.00 Patio de Filtros - Montaje
FX1500 Patio de Filtros - Conexionado y Pruebas 02-Feb-22 06:00 11-Feb-22 10.00 Patio de Filtros - Conexionado y Pruebas
Instrumentacion y Control 14-Sep-21 06:00 A 06-Mar-22 174.00 06-Mar-22 17:00, Instrumentacion y Control
FX1300 Integracion del Sistema - Control y Scada - Montaje y Pruebas 20-Feb-22 06:00 06-Mar-22 15.00 Integracion del Sistema - Control y Scada - Montaje y Pruebas
Instrumentación y Cont
Control General - Suministro, Instalación y pruebas 14-Sep-21 06:00 A 19-Nov-21 67.00 19-Nov-21 17:00, Instrumentación y Control General - Suministro, Instalación y pruebas
FX1350 Verificacion de materiales y equipos 14-Sep-21 06:00 A 23-Sep-21 6.00on de materiales y equipos
FX1360 Traslado y Montaje de tablero 0931-HFM-0004-COB+F8 21-Sep-21 00:00 A 23-Oct-21 4.00 Traslado y Montaje de tablero 0931-HFM-0004-COB+F8
FX1370 Traslado y Montaje de tablero 0931-RTU-0003 21-Sep-21 00:00 A 23-Oct-21 4.00 Traslado y Montaje de tablero 0931-RTU-0003
FX1380 Canalizacion 0931-SGH-0002-H20 hacia 0931-HFM-0004+F8 28-Sep-21 06:00 A 23-Oct-21 2.00 Canalizacion 0931-SGH-0002-H20 hacia 0931-HFM-0004+F8
FX1390 Canalizacion 0931-SGH-0002-H20 hacia 0931-RTU-0003 04-Oct-21 06:00 A 23-Oct-21 2.00 Canalizacion 0931-SGH-0002-H20 hacia 0931-RTU-0003
FX1400 Canalizacion 0931-SGH-0002-H15 hacia 0931-RTU-0003 06-Oct-21 06:00 A 23-Oct-21 2.00 Canalizacion 0931-SGH-0002-H15 hacia 0931-RTU-0003
FX1420 Cableado de control 5/C x 16AWG 0931-SGH-0002-H20 hacia 0931-HFM 12-Oct-21 06:00 A 25-Oct-21 2.00 Cableado de control 5/C x 16AWG 0931-SGH-0002-H20 hacia 0931-HFM-0004+F8 (60 m)
FX1430 Cableado de control 3/C x 14AWG 0931-SGH-0002-H15 hacia 0931-RTU 12-Oct-21 06:00 A 25-Oct-21 2.00 Cableado de control 3/C x 14AWG 0931-SGH-0002-H15 hacia 0931-RTU-0003 (260 m)
FX1410 Cableado de control 10/C x 16AWG 0931-SGH-0002-H20 hacia 0931-HFM 14-Oct-21 06:00 A 25-Oct-21 2.00 Cableado de control 10/C x 16AWG 0931-SGH-0002-H20 hacia 0931-HFM-0004+F8 (60 m)
FX1460 Cableado de control 5C x 14 AWG H-15 hacia 0931-RTU-0003 (50 m) 18-Oct-21 06:00 A 20-Oct-21 2.00 Cableado de control 5C x 14 AWG H-15 hacia 0931-RTU-0003 (50 m)
FX1440 Cableado de patch cord (6 x 3 m) 19-Oct-21 06:00 A 21-Oct-21 1.00 Cableado de patch cord (6 x 3 m)
FX1520 Conexionado y pruebas de cables de control (parte 1) 20-Oct-21 06:00 A 22-Oct-21 4.00 Conexionado y pruebas de cables de control (parte 1)
FX1550 Canalizacion conduit para cable de fibra optica. ( Acometida de tableros) 20-Oct-21 06:00 A 07-Nov-21 1.00 Canalizacion conduit para cable de fibra optica. ( Acometida de tableros)

Actual Level of Effort Actual Work Critical Remaining Work Page 19 of 20 TASK filter: All Activities
Primary Baseline Remaining Work Milestone © Oracle Corporation
Cronograma del Proyecto: Construccion e Instalacion del 3er Molino de Bolas y Obras Asociadas
Linea Base 1 Rev. 0 (actualizado al 22-octubre)
Activity ID Activity Name Start Finish Original October 2021 November 2021 December 2021 January 2022 February 2022 March 2022 April 2022 May 2022 June 2022 July 2022
Duration
09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 05 12 19 26 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 02 09 6
FX1510 Arribo de cables de control faltantes 06-Nov-21 0.00 Arribo de cables de control faltantes,
FX1450 Cableado de fibra optica (3 x 90 m) 08-Nov-21 06:00 11-Nov-21 4.00 Cableado de fibra optica (3 x 90 m)
FX1470 Cableado de control 5C x 14 AWG H-20 hacia 0931-RTU-0003 (60 m) falt 12-Nov-21 06:00 13-Nov-21 2.00 Cableado de control 5C x 14 AWG H-20 hacia 0931-RTU-0003 (60 m) falta suministro
FX1480 Cableado de ethernet 4P+SHx23 AWG H-15 hacia 0931-RTU-0003 (50 m 14-Nov-21 06:00 15-Nov-21 2.00 Cableado de ethernet 4P+SHx23 AWG H-15 hacia 0931-RTU-0003 (50 m) falta suministro
FX1530 Conexionado y pruebas de cables de control (parte 2) 16-Nov-21 06:00 19-Nov-21 4.00 Conexionado y pruebas de cables de control (parte 2)
Precomisionamiento y Com
Comisionamiento 20-Nov-21 06:00 09-Mar-22 110.00 09-Mar-22 17:00, Precomisionamiento y Comisionamiento
FX1540 Precomisionamiento de control SE Principal 20-Nov-21 06:00 24-Nov-21 5.00 Precomisionamiento de control SE Principal
FX1330 Precomisionamiento General 12-Feb-22 06:00 19-Feb-22 8.00 Precomisionamiento General
FX1340 Comisionamiento 28-Feb-22 06:00 09-Mar-22 10.00 Comisionamiento

Actual Level of Effort Actual Work Critical Remaining Work Page 20 of 20 TASK filter: All Activities