Daily Plan 12 April 2022
Daily Plan 12 April 2022
Mined out
area EU1 Expose progress
Seam EU0 est. 1,000 MT.
Ready to getting
Seam EU0L est.
2,000 MT.
Ready to getting
Ready to getting Seam EU0 est. 2,000 MT.
Seam EU1 est 16,000 MT.
B86 B87 B88 B89 B90 B91 B92 B93 B94 B95 B96 B97 B98 B99
Keterangan:
= Ready to getting telah terekspose dan cleaning 1 = Coal cleaning priority
= Expose progress alokasi fleet OB < 2 m to coal roof
= Exposed
GEOTECHNICAL ISSUE - PIT EAST
311700,000000 312600,000000 313500,000000 314400,000000 315300,000000
,000000
9580500,000000
Void AMJ
Stage 2 East
TS02
,000000
9580000,000000
4
2 Stage 2 Creek
3
Void MPP Void Ambalat
MPP_Road Stage 4 6
7
Stage 1
,000000
9579500,000000
TS03
1 8 IPD P9D (Ex PAMA)
Bundwall_HW
IPD BC3
,000000
9579000,000000
Geotech Issue February Week 58
No Area Geotech Issue Tingkat Resiko Rekomendasi
,000000
9578500,000000
1. Reshaping crack
1 Utara LW PIT 9 Meranti Crack longsor busur IPD Menengah 2. Tidak diperbolehkan melakukan dumping /
penambahan material di area ini
Ramp_CoalHaul_KM3 1. Slope sesuai dengan desain
2 Project diversi AMJ Crack pada lereng diversi Menengah
2. RL sesuaikan dengan desain
Longsor pada lereng stage 2 1. Observasi geoteknik rutin dilapangan
3 Stage 2 timur Tinggi
timur 2. Sloping lereng sesuai dengan desain
311700,000000 312600,000000 313500,000000 314400 ,000000 1. Observasi geoteknik rutin
315300 dilapangan
,000000
115°10'0"E 115°20'0"E 4 Stage 2 timur Failure material Tinggi
Mine Engineering Departement 2. Sloping lereng sesuai dengan desain
Pit Geologist & Geotechnical Engineer 1. Observasi geoteknik rutin dilapangan
Aranio 5 Stage 2 timur Bahaya longsor Menengah
2. Tidak membuat double bench pada area ini
0 180 360 720 1.080 1.440
3°40'0"S
meters
Longsor busur (Rembesan air 1. Melakukan peralihan jalan
6 Lereng Jalan Hauling Stage 4 Signifikan
Satui diatas EU1) 2. Tidak dilalui untuk hauling
KALIMANTAN SELATAN
Kintap
Legend :
1. Lakukan penurunan pada RL sesuai dengan desain
Area Kritikal Longsor - Menengah ct_wk58_p9.dxf Polyline 7 HW Stage 1 project jalan Mandalika Bahaya longsor Menengah
2. Observasi geoteknik rutin dilapangan
3°50'0"S
Jorong
Area Kritikal Longsor - Tinggi Block_Eastt_KCP 1. Observasi Geoteknik rutin dilapangan
Bahaya tanggul penyekat
8 Mud Stage 1 Menengah 2. Tidak memotong/meniping lereng tanggul sekatan
Area Kritikal Lonsor - Signifikan PIT_Area lumput hancur
lumpur
115°10'0"E 115°20'0"E
PIT OVERVIEW DAILY (PIT 9 EAST) – 11 April 2022
3
4
8
2
N
Stock Soil 02 1
11
10
9
3
1 7
12 7 Stage 2
5
Divertions Stage 4 8
6
4
Stock Soil 03
2 2
4 Stage 1
1
5 10 9
3 13 IPD P9D
12
EX-PAMA
6 14 3
1b
2
Dumping IPD Pama flat
1 RL +36, elv. aktual +35
IPD BC3
1a
Fleet Allocation Stage 2 – 11 April 2022
PLAN
Activity No Elv
Unit Pit Material Block Dump Dist Plan Hauler
From To
6 EX1351 ST 2 ST 2 B97 IPD BC3 RL+5 2.761 29,2 26 6
7 EX1369 ST 2 ST 2 B94 IPD BC3 RL+5 2.722 29 26 6
8 EX1353 ST 2 ST 2 B95 IPD BC3 RL+5 2.696 23,6 21 6
OB
Note :
1. 6 x SY500 Steriping OB di area Stage
2
2. Fokus kepada pembuatan akses jalan
to RL 7
3. Segera coal getting seam EU 0 di
area stage 2 timur
Coal Getting EU 0
1
Fleet Allocation Stage 2 LW – 11 April 2022
PLAN
Activity No Elv
Unit Pit Material Block Dump Dist Plan Hauler
From To
O
Activity No Unit Pit Seam Blok Dump Dist RL Elv Act Elv Plan Hauler
2 EX1347 PIT KINTAP EAST EU1 B97 CPP 6.267 0 Mineout 7
COAL
3 EX1379 PIT KINTAP EAST EU1 B87 CPP 6.267 0 Mineout 7
Note :
• Pastikan untuk kordinasi terkait keamanan
dengan pihak arutmin saat kegiatan
berlangsung.
• 1 x Stripping OB
• Loading/ expose dengan acuan patok pita
yang sudah ada. Fokus layer by layer untuk
memperluas area expose FU3 sesuai
direct/arah penambangan
PLAN
Activity No Elv
Unit Pit Material Block Dump Dist Plan Hauler
From To
1 HEX3104 ST 4 ST 4 B96 IPD BC3 RL+6 1.708 30 27 4
OB
Note :
• Pastikan jalur untuk HD ke area Box Cut
Coal Getting EU 0 Stage 4 sesuai dengan geometri
kebutuhan jalan
PLAN
Activity No Elv
Unit Pit Material Block Dump Dist Plan Hauler
From To
3 EX1370 ST 1 STRIP ST 1 STRIP B88 IPD BANK SPOIL 1.401 21,5 19 6
OB
Stage Plan :
Stripping Top Soil 1. 1x SY 500 mud getting
2. Sidecast material OB ke Barat untuk
1. Sidecast material OB ke Barat blending lumpur
untuk blending lumpur 3. Loading Material yang sudah terblending
2. Loading Material yang sudah dari Loading point mud ke arah selatan
terblending dari Loading point
mud ke arah selatan
Note :
6 • Perhatikan atau selalu monitoring FK dari
jalan yang berpotensi terjadi retakan/sliding
• Buat 2x jenjang & bench di sisi utara stage
area / selatan fast track
• Pastikan area loading aman untuk aktivitas
loading lumpur
• Pengawasan lebih di area lumpur
8
Key Point:
1. Prioritas dumpingan ke arah no 1 dan 3 (sisi low wall dan high wall) lalu bergeser ke tengah (area no.2)
2. Pastikan pembuatan tanggulan (pad) untuk batas area dumping 10-15 meter dari ujung arah dumpingan
3
2
1
WASTE DUMP ALLOCATION IPD BC 3 – Bank Spoil
Key Point:
1. Prioritas dumpingan ke arah utara, dan lakukan ramp down pada area tersebut
2. Pastikan pembuatan pad pada top ramp
3. Pastikan jarak dumping 10-15 meter dari tp ramp
Act +60
Act +60
Final bdy
Monthly
BM Survey
(Jangan sampai tertutup)
+16
Bench
RL+25
Grade : 7,7 %
Volume Cut : 13,324 BCM
RE-CONSTRUCT SP 10
4 1
2
Project – Reconstruct SP10
N Key Point:
Line
HDPE • Settpond capacity existing (5,6,7,8,9) = 12.000 m3
• Additional settpond capacity design by AI (1,2,3,4) = 39.216 m3
• Maintenance settpond existing (5,6,7,8,9)
• Material additional settpond design by material non insitu (waste material), with average thickness about 10m.
SP Capacity
Geometry Capacity
SP 10 Location Material Remarks
Width (m) Length (m) Depth (m) Volume (m3)
Kompartemen 1 50 70 5 12,900 Non Insitu New Construct
Control Box Kompartemen 2 30 50 5 4,936 Non Insitu New Construct
Kompartemen 3 30 50 5 4,954 Non Insitu New Construct
Mud Pond Kompartemen 4 40 127 5 16,426 Parsial Non Insitu Pond Widening
Total 39,216
5
6
7
8 9
Outlet
Overview
N Summary:
N Total progress 46,45% dari
keseluruhan pekerjaan
reconstruct SP10
3 Construct Setpond (Comp 1) 45,000 BCM ZX370 HIGH 3-Mar-22 4-Apr-22 0.0% Open
4 Control Box Construct Setpond (Comp 2) 5,368 BCM ZX370 HIGH 4-Apr-22 8-Apr-22 100.0% Progress
5 Construct Setpond (Comp 3) 4,559 BCM ZX370 HIGH 8-Apr-22 12-Apr-22 38.6% Open
6 Mud Pond Pond Widening 9,024 BCM ZX370 HIGH 12-Apr-22 19-Apr-22 2.2% Progress
11.46%