DAILY PLAN – 11 April 2022 KINTAP EAST

Senin, 11 April 2022


OB FLEET FLEET SETTING OB
Production HAULER QTY Plan
Distance Dumping Point
No Digger Model Area Pdty (bcm/jam) Plan Fleet Quester Material
Scania Hino 700 HD465 (m)
(Bcm) CWE280T Location
1 HEX3104 PC1250 ST 4 400 4.968 - - - 4 OB 1.708 IPD BC3 RL+6
2 HEX3106 PC1250 ST 4 400 5.768 - - - 4 OB 1.710 IPD BC3 RL+6
3 EX1370 SY500 ST 1 STRIP 220 3.062 6 - - - Top Soil 1.401 IPD BANK SPOIL
4 EX1352 SY500 ST 1 MPP 132 6 - - - Wet Mud 1.411 IPD BANK SPOIL
1.441
5 EX1346 SY500 ST2 LW 220 3.018 6 - - - OB 2.768 IPD BC3 RL+5
6 EX1351 SY500 ST 2 220 3.018 6 - - - OB 2.761 IPD BC3 RL+5
7 EX1369 SY500 ST 2 220 3.062 6 - - - OB 2.722 IPD BC3 RL+5
8 EX1353 SY500 ST 2 220 3.018 6 - - - OB 2.696 IPD BC3 RL+5
9 EX1349 SY500 ST 2 220 3.062 6 - - - OB 2.611 IPD BANK SPOIL
10 EX1348 SY500 ST 2 220 3.062 6 - - - OB 2.609 IPD BANK SPOIL
11 EX1344 SY500 ST 2 220 3.018 6 - - OB 2.762 IPD BC3 RL+4
Total 11 36.501 54 - - 8 2.251

COAL FLEET FLEET SETTING COAL MINING


Productivity Production HAULER QTY Dumping
No Digger Model Area SEAM Distance (m)
Digger (ton/jam) (Ton) FUSO HINO Scania Point
1 EX1368 SY500 PIT KINTAP EAST 220 3.062 7 - - EU1 6.041 CPP
2 EX1347 SY500 PIT KINTAP EAST 220 3.018 7 - - EU1 6.267 CPP
3 EX1379 SY500 PIT KINTAP EAST 220 3.062 - 7 - EU1 6.277 CPP
Total 3 9.145 14 7 - 6.193

Dibuat oleh : Disetujui oleh: Diketahui oleh : Diterima oleh :

Short Term GnG HSE HOS


HOS MED
MED HOD MOD HOS MOD
Alfred/Ilham/Galih Irwan Amrih W A.Ghani
A.Ghani Arofik Anwar Fransisco Y. M/Mas Mawardi/Agus.R
COAL EXPOSE MAP PIT EAST
QUANTITY PLAN QUALITY BASED ON MODEL
PIT SEAM BLOCK STATUS REMARK
TON ASH TS SE
EU1 88 16,000 Ready to getting N
FU3 98 4,000 Ready to getting
11-Apr-22 96 1,000 Expose progress
EU0
90 2,000 Ready to getting Ready to getting
EUOL 90 2,000 Ready to getting
Seam FU3 est.
Ready to getting Ready to getting 24,000
4,000 MT.
PIT EAST 24,000
Mined out
Exposed Exposed -
PIT EAST - Water ponded dan covered by mud
area
Expose progress Expose progress 1,000 FU3
PIT EAST 1,000
Total Coal 24,000 Exclude expose progress & water ponded/covered by mud

Mined out
area EU1 Expose progress
Seam EU0 est. 1,000 MT.

Ready to getting
Seam EU0L est.
2,000 MT.

Ready to getting
Ready to getting Seam EU0 est. 2,000 MT.
Seam EU1 est 16,000 MT.

B86 B87 B88 B89 B90 B91 B92 B93 B94 B95 B96 B97 B98 B99
Keterangan:
= Ready to getting  telah terekspose dan cleaning 1 = Coal cleaning priority
= Expose progress alokasi fleet OB < 2 m to coal roof
= Exposed
GEOTECHNICAL ISSUE - PIT EAST
311700,000000 312600,000000 313500,000000 314400,000000 315300,000000
,000000

9580500,000000
Void AMJ

Stage 2 East
TS02
,000000

9580000,000000
4
2 Stage 2 Creek
3
Void MPP Void Ambalat

MPP_Road Stage 4 6
7
Stage 1
,000000

9579500,000000
TS03
1 8 IPD P9D (Ex PAMA)

Bundwall_HW

IPD BC3
,000000

9579000,000000
Geotech Issue February Week 58
No Area Geotech Issue Tingkat Resiko Rekomendasi
,000000

9578500,000000
1. Reshaping crack
1 Utara LW PIT 9 Meranti Crack longsor busur IPD Menengah 2. Tidak diperbolehkan melakukan dumping /
penambahan material di area ini
Ramp_CoalHaul_KM3 1. Slope sesuai dengan desain
2 Project diversi AMJ Crack pada lereng diversi Menengah
2. RL sesuaikan dengan desain
Longsor pada lereng stage 2 1. Observasi geoteknik rutin dilapangan
3 Stage 2 timur Tinggi
timur 2. Sloping lereng sesuai dengan desain
311700,000000 312600,000000 313500,000000 314400 ,000000 1. Observasi geoteknik rutin
315300 dilapangan
,000000
115°10'0"E 115°20'0"E 4 Stage 2 timur Failure material Tinggi
Mine Engineering Departement 2. Sloping lereng sesuai dengan desain
Pit Geologist & Geotechnical Engineer 1. Observasi geoteknik rutin dilapangan
Aranio 5 Stage 2 timur Bahaya longsor Menengah
2. Tidak membuat double bench pada area ini
0 180 360 720 1.080 1.440
3°40'0"S

meters
Longsor busur (Rembesan air 1. Melakukan peralihan jalan
6 Lereng Jalan Hauling Stage 4 Signifikan
Satui diatas EU1) 2. Tidak dilalui untuk hauling
KALIMANTAN SELATAN
Kintap
Legend :
1. Lakukan penurunan pada RL sesuai dengan desain
Area Kritikal Longsor - Menengah ct_wk58_p9.dxf Polyline 7 HW Stage 1 project jalan Mandalika Bahaya longsor Menengah
2. Observasi geoteknik rutin dilapangan
3°50'0"S

Jorong
Area Kritikal Longsor - Tinggi Block_Eastt_KCP 1. Observasi Geoteknik rutin dilapangan
Bahaya tanggul penyekat
8 Mud Stage 1 Menengah 2. Tidak memotong/meniping lereng tanggul sekatan
Area Kritikal Lonsor - Signifikan PIT_Area lumput hancur
lumpur
115°10'0"E 115°20'0"E
PIT OVERVIEW DAILY (PIT 9 EAST) – 11 April 2022

3
4
8
2

N
Stock Soil 02 1
11

10
9
3

1 7

12 7 Stage 2
5
Divertions Stage 4 8
6
4
Stock Soil 03
2 2
4 Stage 1
1
5 10 9
3 13 IPD P9D
12
EX-PAMA
6 14 3
1b
2
Dumping IPD Pama flat
1 RL +36, elv. aktual +35
IPD BC3
1a
Fleet Allocation Stage 2 – 11 April 2022

PLAN
Activity No Elv
Unit Pit Material Block Dump Dist Plan Hauler
From To
6 EX1351 ST 2 ST 2 B97 IPD BC3 RL+5 2.761 29,2 26 6
7 EX1369 ST 2 ST 2 B94 IPD BC3 RL+5 2.722 29 26 6
8 EX1353 ST 2 ST 2 B95 IPD BC3 RL+5 2.696 23,6 21 6
OB

9 EX1349 ST 2 ST 2 B93 IPD BANK SPOIL 2.611 29,4 26 6


10 EX1348 ST 2 ST 2 B97 IPD BANK SPOIL 2.609 37 34 6
11 EX1344 ST 2 ST 2 B97 IPD BC3 RL+4 2.762 27,6 25 6

Note :
1. 6 x SY500 Steriping OB di area Stage
2
2. Fokus kepada pembuatan akses jalan
to RL 7
3. Segera coal getting seam EU 0 di
area stage 2 timur
Coal Getting EU 0

Setting Unit Support Dozer :


Striping Area 1 x Dozer Shantui Stage 2 East
Create Access to RL 7
1 Setting Unit Support Grader :
Striping Area to
expose 1xGrader CAT 14M stage 2 support to IPD
3
5 BC3
1xGrader XCMG stage 2 support to IPD Ex
Create Access to RL 9 4
Pama
6b 2

1
Fleet Allocation Stage 2 LW – 11 April 2022

PLAN
Activity No Elv
Unit Pit Material Block Dump Dist Plan Hauler
From To
O

5 EX1346 ST2 LW ST2 LW B97 IPD BC3 RL+5 2.768 30 27 6


B

Activity No Unit Pit Seam Blok Dump Dist RL Elv Act Elv Plan Hauler
2 EX1347 PIT KINTAP EAST EU1 B97 CPP 6.267 0 Mineout 7
COAL
3 EX1379 PIT KINTAP EAST EU1 B87 CPP 6.267 0 Mineout 7

Note :
• Pastikan untuk kordinasi terkait keamanan
dengan pihak arutmin saat kegiatan
berlangsung.
• 1 x Stripping OB
• Loading/ expose dengan acuan patok pita
yang sudah ada. Fokus layer by layer untuk
memperluas area expose FU3 sesuai
direct/arah penambangan

Area Coal Getting Area Optimasi

Plan area priority :


Priority 1 : Stripping OB area No 1 ke RL 30
(Ekspose seam FU3), Segera lakukan Coal
Getting apabila terdapat pergerakan dari
PETI
1 7 Priority 2 :
Priority 3 :
Plan Area General Activity :
Fleet Allocation Stage 4 – 11 April 2022

PLAN
Activity No Elv
Unit Pit Material Block Dump Dist Plan Hauler
From To
1 HEX3104 ST 4 ST 4 B96 IPD BC3 RL+6 1.708 30 27 4
OB

2 HEX3106 ST 4 ST 4 B95 IPD BC3 RL+6 1.710 30 27 4

Note :
• Pastikan jalur untuk HD ke area Box Cut
Coal Getting EU 0 Stage 4 sesuai dengan geometri
kebutuhan jalan

1 Setting Unit Support Grader :


1xGrader CAT 14M stage 2 support to IPD
RL 20 BC3
2
1
Fleet Allocation Stage 1 – 11 April 2022

PLAN
Activity No Elv
Unit Pit Material Block Dump Dist Plan Hauler
From To
3 EX1370 ST 1 STRIP ST 1 STRIP B88 IPD BANK SPOIL 1.401 21,5 19 6
OB

4 EX1352 ST 1 MPP ST 1 MPP B97 IPD BANK SPOIL 1.411 0 -3,0 6


Activity No Unit Pit Seam Blok Dump Dist RL Elv Act Elv Plan Hauler
COAL 1 EX1368 PIT KINTAP EAST EU1 B90 CPP 6.267 28 Mineout 7

Stage Plan :
Stripping Top Soil 1. 1x SY 500 mud getting
2. Sidecast material OB ke Barat untuk
1. Sidecast material OB ke Barat blending lumpur
untuk blending lumpur 3. Loading Material yang sudah terblending
2. Loading Material yang sudah dari Loading point mud ke arah selatan
terblending dari Loading point
mud ke arah selatan
Note :
6 • Perhatikan atau selalu monitoring FK dari
jalan yang berpotensi terjadi retakan/sliding
• Buat 2x jenjang & bench di sisi utara stage
area / selatan fast track
• Pastikan area loading aman untuk aktivitas
loading lumpur
• Pengawasan lebih di area lumpur
8

4 Setting Unit Support Dozer :


1xDozer Shantui
Setting Unit Support Grader :
1xGrader CAT 14M stage 2 support to IPD
BC3
WASTE DUMP ALLOCATION IPD BC 3

Key Point:
1. Prioritas dumpingan ke arah no 1 dan 3 (sisi low wall dan high wall) lalu bergeser ke tengah (area no.2)

2. Pastikan pembuatan tanggulan (pad) untuk batas area dumping 10-15 meter dari ujung arah dumpingan

3. Pastikan agar material dumpingan tidak menutupi jalur air/paritan.

4. Selalu periksa/pengecekan secara berkala area bibir/crest dumpingan.

5. Pastikan alat bantu sling dan sackle tersedia di dumpingan

3
2

1
WASTE DUMP ALLOCATION IPD BC 3 – Bank Spoil

Key Point:
1. Prioritas dumpingan ke arah utara, dan lakukan ramp down pada area tersebut
2. Pastikan pembuatan pad pada top ramp
3. Pastikan jarak dumping 10-15 meter dari tp ramp

Ramp down area ini


WASTE DUMP ALLOCATION STOCKSOIL TS02

Act +60

Act +60

Final bdy
Monthly

BM Survey
(Jangan sampai tertutup)

Setting Unit Support Dozer :


1xDozer Class Shantui (untuk 2 Fleet Small)

Setting Unit Support Grader :


1x Grader XCMG front small stage 2 support to TS02
OB Hauling Road Design to Disposal BC3

+16

Bench
RL+25

OB Hauling Road Design to BC3 +22

Grade : 7,7 %
Volume Cut : 13,324 BCM
RE-CONSTRUCT SP 10

4 1

2
Project – Reconstruct SP10

N Key Point:
Line
HDPE • Settpond capacity existing (5,6,7,8,9) = 12.000 m3
• Additional settpond capacity design by AI (1,2,3,4) = 39.216 m3
• Maintenance settpond existing (5,6,7,8,9)
• Material additional settpond design by material non insitu (waste material), with average thickness about 10m.

SP Capacity
Geometry Capacity
SP 10 Location Material Remarks
Width (m) Length (m) Depth (m) Volume (m3)
Kompartemen 1 50 70 5 12,900 Non Insitu New Construct
Control Box Kompartemen 2 30 50 5 4,936 Non Insitu New Construct
Kompartemen 3 30 50 5 4,954 Non Insitu New Construct
Mud Pond Kompartemen 4 40 127 5 16,426 Parsial Non Insitu Pond Widening
Total 39,216

Inlet Debit Max Debit SP Capacity Retention Time


Pump Type Qty Pump WH
N (m3/hr) (m3/day) (m3) (hours)
DnD 200 850 3 20 51,000 52,241 24.6
1 2

5
6
7

8 9

Outlet
Overview

N Summary:
N Total progress 46,45% dari
keseluruhan pekerjaan
reconstruct SP10

Photo: 5 April 2022 Photo: 5 April 2022

Photo: 5 April 2022 Photo: 5 April 2022


Project – Reconstruct SP10
ACTUAL
PROJECT TASK Total UoM Unit PRIORITY START PLAN END % COMPLETE Status
END
Note:
1 Clearing area 1,000.00 BCM SY215 HIGH 2-Mar-22 3-Mar-22 10-Mar-22 100.0% Closed
• Reconstruct SP10 continue widening
Prepare Area
comp 2 & 3
2 Prepare Access 49,338 BCM PR754 HIGH 3-Mar-22 9-Mar-22 100.0% Closed

3 Construct Setpond (Comp 1) 45,000 BCM ZX370 HIGH 3-Mar-22 4-Apr-22 0.0% Open

4 Control Box Construct Setpond (Comp 2) 5,368 BCM ZX370 HIGH 4-Apr-22 8-Apr-22 100.0% Progress

5 Construct Setpond (Comp 3) 4,559 BCM ZX370 HIGH 8-Apr-22 12-Apr-22 38.6% Open

6 Mud Pond Pond Widening 9,024 BCM ZX370 HIGH 12-Apr-22 19-Apr-22 2.2% Progress

11.46%