Project: Revisi Ms Project Ris Date: June 17, 2022
Project: Revisi Ms Project Ris Date: June 17, 2022
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
1 PEKERJAAN STRUKTUR GEDUNG UPTD 336 days June 1, 2022 May 2, 2023 Rp4,745,706,948
4 1.1. Pondasi Pile Cap 49 days June 8, 2022 July 26, 2022 Rp134,886,045 7/26
5 1.2. Pondasi Tie Beam 49 days June 8, 2022 July 26, 2022 Rp252,806,304 7/26
6 C. PEKERJAAN STRUKTUR LANTAI ATAS 329 days June 8, 2022 May 2, 2023 Rp3,313,833,549
7 3.1. Lantai Dasar Elv. -0.050 98 days June 8, 2022 September 13, 2022 Rp344,588,610
8 3.1.1. Plat Lantai Dasar 49 days June 8, 2022 July 26, 2022 Rp166,619,875
11 3.2. Lantai Dua Elv. +4.150 91 days August 3, 2022 November 1, 2022 Rp587,365,792 11/1
12 3.2.1. Plat Lantai 42 days August 3, 2022 September 13, 2022 Rp195,769,440
14 3.2.3. Kolom 42 days August 31, 2022 October 11, 2022 Rp119,492,059
16 3.3. Lantai Tiga Elv. +8.350 91 days September 21, 2022 December 20, 2022 Rp509,899,996 12/20
17 3.3.1. Plat Lantai 42 days September 21, 2022 November 1, 2022 Rp163,335,417
19 3.3.3. Kolom 42 days October 19, 2022 November 29, 2022 Rp108,015,291
21 3.4. Lantai Empat Elv. +12.550 91 days November 9, 2022 February 7, 2023 Rp509,899,996 2/7
22 3.4.1. Plat Lantai 42 days November 9, 2022 December 20, 2022 Rp163,335,417
23 3.4.2. Balok 42 days November 16, 2022 December 27, 2022 Rp208,746,517
26 3.5. Lantai Lima Elv. +16.750 84 days December 28, 2022 March 21, 2023 Rp509,899,996 3/21
27 3.5.1. Plat Lantai 42 days December 28, 2022 February 7, 2023 Rp163,335,417
29 3.5.3. Kolom 35 days January 25, 2023 February 28, 2023 Rp108,015,291
30 3.5.4. Tangga 35 days February 15, 2023 March 21, 2023 Rp29,802,771
31 3.6. Lantai Atap Elv. +20.850 49 days February 15, 2023 April 4, 2023 Rp480,097,225 4/4
32 3.6.1. Plat Lantai 35 days February 15, 2023 March 21, 2023 Rp163,335,417
33 3.6.2. Balok 35 days February 15, 2023 March 21, 2023 Rp208,746,517
35 3.7. Dak Atap Tangga & Lift Elv. +25.450 35 days March 29, 2023 May 2, 2023 Rp372,081,934 5/2
36 3.7.1. Plat Lantai 35 days March 29, 2023 May 2, 2023 Rp163,335,417
38 D. BIAYA TAK LANGSUNG (BTL) 336 days June 1, 2022 May 2, 2023 Rp900,000,000 5/2
Project: REVISI MS PROJECT RIS Split Inactive Task Duration-only Finish-only Progress
Date: June 17, 2022 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress