ID Task Name Duration Start Finish Cost Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
1 PEKERJAAN STRUKTUR GEDUNG UPTD 336 days June 1, 2022 May 2, 2023 Rp4,745,706,948

2 A. PEKERJAAN PERSIAPAN 336 days June 1, 2022 May 2, 2023 Rp144,181,050

3 B. PEKERJAAN SUBSTRUKTUR 49 days June 8, 2022 July 26, 2022 Rp387,692,349

4 1.1. Pondasi Pile Cap 49 days June 8, 2022 July 26, 2022 Rp134,886,045 7/26
5 1.2. Pondasi Tie Beam 49 days June 8, 2022 July 26, 2022 Rp252,806,304 7/26
6 C. PEKERJAAN STRUKTUR LANTAI ATAS 329 days June 8, 2022 May 2, 2023 Rp3,313,833,549

7 3.1. Lantai Dasar Elv. -0.050 98 days June 8, 2022 September 13, 2022 Rp344,588,610

8 3.1.1. Plat Lantai Dasar 49 days June 8, 2022 July 26, 2022 Rp166,619,875

9 3.1.2. Kolom 42 days July 6, 2022 August 16, 2022 Rp148,569,913

10 3.1.3. Tangga 42 days August 3, 2022 September 13, 2022 Rp29,398,822

11 3.2. Lantai Dua Elv. +4.150 91 days August 3, 2022 November 1, 2022 Rp587,365,792 11/1
12 3.2.1. Plat Lantai 42 days August 3, 2022 September 13, 2022 Rp195,769,440

13 3.2.2. Balok 41 days August 3, 2022 September 12, 2022 Rp242,503,562

14 3.2.3. Kolom 42 days August 31, 2022 October 11, 2022 Rp119,492,059

15 3.2.4. Tangga 42 days September 21, 2022 November 1, 2022 Rp29,600,731

16 3.3. Lantai Tiga Elv. +8.350 91 days September 21, 2022 December 20, 2022 Rp509,899,996 12/20
17 3.3.1. Plat Lantai 42 days September 21, 2022 November 1, 2022 Rp163,335,417

18 3.3.2. Balok 42 days September 21, 2022 November 1, 2022 Rp208,746,517

19 3.3.3. Kolom 42 days October 19, 2022 November 29, 2022 Rp108,015,291

20 3.3.4. Tangga 42 days November 9, 2022 December 20, 2022 Rp29,802,771

21 3.4. Lantai Empat Elv. +12.550 91 days November 9, 2022 February 7, 2023 Rp509,899,996 2/7
22 3.4.1. Plat Lantai 42 days November 9, 2022 December 20, 2022 Rp163,335,417

23 3.4.2. Balok 42 days November 16, 2022 December 27, 2022 Rp208,746,517

24 3.4.3. Kolom 42 days December 7, 2022 January 17, 2023 Rp108,015,291

25 3.4.4. Tangga 42 days December 28, 2022 February 7, 2023 Rp29,802,771

26 3.5. Lantai Lima Elv. +16.750 84 days December 28, 2022 March 21, 2023 Rp509,899,996 3/21
27 3.5.1. Plat Lantai 42 days December 28, 2022 February 7, 2023 Rp163,335,417

28 3.5.2. Balok 42 days December 28, 2022 February 7, 2023 Rp208,746,517

29 3.5.3. Kolom 35 days January 25, 2023 February 28, 2023 Rp108,015,291

30 3.5.4. Tangga 35 days February 15, 2023 March 21, 2023 Rp29,802,771

31 3.6. Lantai Atap Elv. +20.850 49 days February 15, 2023 April 4, 2023 Rp480,097,225 4/4
32 3.6.1. Plat Lantai 35 days February 15, 2023 March 21, 2023 Rp163,335,417

33 3.6.2. Balok 35 days February 15, 2023 March 21, 2023 Rp208,746,517

34 3.6.3. Kolom 28 days March 8, 2023 April 4, 2023 Rp108,015,291

35 3.7. Dak Atap Tangga & Lift Elv. +25.450 35 days March 29, 2023 May 2, 2023 Rp372,081,934 5/2
36 3.7.1. Plat Lantai 35 days March 29, 2023 May 2, 2023 Rp163,335,417

37 3.7.2. Balok 35 days March 29, 2023 May 2, 2023 Rp208,746,517

38 D. BIAYA TAK LANGSUNG (BTL) 336 days June 1, 2022 May 2, 2023 Rp900,000,000 5/2

Task Project Summary Manual Task Start-only Deadline

Project: REVISI MS PROJECT RIS Split Inactive Task Duration-only Finish-only Progress
Date: June 17, 2022 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone