Professional Documents
Culture Documents
Quantities Report - NAA
Quantities Report - NAA
Quantities Report - NAA
Table of Contents
1.0 INTRODUCTION..............................................................................................................1
2.0 ORGANISATIONAL STRUCTURE:...............................................................................2
FIG 1: ORGANIZATIONAL STRUCTURE..........................................................................2
3.0 CIVIL ENGINEERING MEASUREMENTS...............................................................3
3.1 Introduction to CESSM3....................................................................................................3
3.1.1 General items...................................................................................................................4
3.1.2 Work classification..........................................................................................................4
3.1.3 Coding and numbering....................................................................................................4
3.1.4 Item numbers...................................................................................................................5
3.1.5 Coding of unclassified items...........................................................................................5
3.1.6 Mode of description.........................................................................................................6
3.1.7 Unit of measurement.......................................................................................................6
3.1.8 Additional description rules............................................................................................6
3.2 Introduction to Bill of Quantity (BOQ)..............................................................................6
3.2.1 Purpose of Bill of Quantities...........................................................................................6
3.2.2 Content of Bills of Quantities..........................................................................................7
Section A: List of Principal Quantities........................................................................................7
Section B: Preamble.....................................................................................................................7
Section C: Day Works..................................................................................................................8
Section D: Works items and Classifications................................................................................8
Section E: Grand Summary..........................................................................................................8
FIG 2: SECTIONS OF BOQ....................................................................................................8
3.2.3 Production of Bill of Quantities......................................................................................9
4.0 Taking off 1km Road…………………………………………………………………12
CHAPTER 1
1.0 INTRODUCTION
The Quantities Division is one of the eight divisions of the development department of Ghana
Highway Authority. The division is headed by a director who is assisted by two managers:
Quantities Manager Development and Quantities Manager Maintenance. The Division is charged
with the responsibility of:
During my two months induction training with the Quantities Division I was scheduled to
receive training in the form of lectures and discussions and this was undertaken by surveyors in
the Quantities section. This report elaborates on my experience with the Quantities Division.
CHAPTER TWO
CHAPTER THREE
The civil engineering standard method of measurements (CESMM) helps to secure a more
comprehensive, uniform and rationalized approach to measurement with its standardized
terminology and three levels of description.
Specific requirements-for engineers.ie they are required to facilitate smooth flow of work
Examples
Each class is further sub-divided into three (3) divisions which classify works at successive
levels of detail. Each division comprises a list of 8 descriptive features of work.
An example
Class F (in –situ concrete) contains three divisions of classification. The first classifies different
types of in situ concrete.
The second classifies the strength and location and the third division classifies the aggregate size
and thickness of cross sectioned area.
The letters represent the classes while digits give the position of the item. These positions are in
the first second and third divisions.
An example
Class: E Earthworks
Sometimes the symbol * is used to Indicate all numbers in the appropriate division
An example
Example
Example
Item E120 - where digit 0 is used when the division of classification is open ended.(excavation
by dredging)
An example
High yield steel bar reinforcement to BS 4449 nominal size 20mm not supply, deliver, cut bend
high yield bar reinforcement to BS4449 nominal size 20mm.
A separate item would be given in some instances where additional description is given for
component of work exhibiting different additional features.
Example
Item D310.1 which might be “stump removal 150-500mm diameter and backfill hole with gravel
Item D310.2 which might be “stump removal 150-500mm diameter and backfill hole with clay
material.
It enables all contractors tendering for a contract to price on exactly the same information
with a minimum of effort.
It provides a basis for the evaluation of variations which often occur during the progress
of work.
It gives an itemized list of the component parts of projects, with a full description and the
quantity of each part, and this may assist the successful contractor in ordering materials
and assessing his labour requirement for the contract.
After being priced, it provides a good basis for a cost analysis, which subsequently will
be of use on future contracts in cost panning work.
This list is to precede the preamble to the bill of quantities.The early part of the specification
should describe the nature, magnitude, output or size of the principal components of the works so
that the extent of the works required is defined and readily appreciated. This is also useful if the
cost of the contract is to be of value for cost analysis purposes in the tendering process.
Section B: Preamble
The preamble can be grouped into three items:
Inclusions and narrating of any other standard method of measurement used in measuring
ancillary works on the contract
The standard method has five main divisions or categories of items that can be put in the Class A
preliminaries bill:
Contractual requirements
Specified requirements
The ‘Method-related charges’
Provisional sums
‘Nominated subcontractors’, which include or exclude work on site
Work items Class B-Z:
Section Description
A List of Principal Quantities
B Preamble:
States the edition of CESMM being used and items with measurements
that varies with the CESMM. clauses 5.4 and 5.5
C Day work Schedule
This is a list of labour, plant and material with or without nominal
quantities inserted in the document.
D Works Items
Class A: General Items (preliminaries)
Contractual requirements fixed
Specified requirements fixed, time related, quantity related
Method Related Charges fixed, time related
Provisional Sums
Price cost (PC) items
E Grand Summary
Collection and totaling of Part summaries
General contingency allowance
Adjustment item: Addition to or deduction from the total of complete
works: not adjustable on final certificates – paid or recovered by
proportional installments in interim certificates
Working up
- Squaring
- Abstracting
- Billing
- Editing
- Typing
- Reading over
- Printing
A B C D E A B C D E
A - Binding column
B - Multiplying column
C - Dimension column
D - Squaring column
E - Description column
Length
Width/breadth
Height/depth
10.00 Excavation
Ditto Apron
3.60
0.60
E 532
1.00
Disposal of excavated material
16.32m3
16.32m3
1 m3 16.32
Excavation
2 Disposal of m3 16.32
excavated
material
CHAPTER FOUR
As part of my training, I was guided on how to take off for a one km stretch of a presumed road.
This assignment is completed in the appendix attached to this report.