BDRRM Plan 2014
BDRRM Plan 2014
The plan will be done thru BDC Meeting with each member will be inform properly regarding the revision and updates of BDRRMC. The Sangguniang
Barangay thru the Punong Barangay and its member will be the responsible in handling the dissemination and implementation of this plan.
Prepared by :
ANITA L. PARANTAR
Barangay Treasurer
Approved by :
ROLLY L. ENCABO
Punong Barangay
1
BARANGAY DISASTER RISK REDUCTION AND MANAGEMENT PLAN
CY 2014
INTRODUCTION :
RA 2011, otherwise known as Philippines Disaster Risk Reduction and Management Act of 2011. Call for the strengthening of the Philippine Disaster Risk
Reduction and Management System at all government level. As the prime implementor of disaster management program at the local government level, the local
government Unit of Barangay San Isidro, Hagonoy, Davao del Sur with its BDRRMC, participated in by the Private Sector and Civil Society Organization has
prepared this Barangay Disaster Risk Reduction Management Plan to built a mechanism that will strengthen the capacity of the LGU and adopt specific measures in
preparing, reducing disaster risk and to manage disaster impacts.
Under Rule 18, Section 1, of RA 10121, the present local calamity fund shall henceforth be known as the local the Local Disaster Risk Reduction and
Management Fund (LDRRMF). Not less than five percent (5%) of the estimated revenue from regular sources shall be set aside as the LDRRMF to support disaster
risk management activities such as but not limited to pre-disaster preparedness programs including training, purchasing life-saving rescue equipment, supplies and
medicines for post disaster activities and for the payment of premiums as calamity insurance and construction of evacuation centers.
For the year 2014,H 5% BDRRM fund is P64,064.60. In order to facilitate expenditures thereby making it operative, proper observance of the mandate of
financial requirements utilization do hereby known as follows:
The utilization of the 70% BDRRM Fund comprises the following programs: 1. Mitigation 2. Preparedness 3. rehabilitation. The total amount appropriated
for these programs is P44,845.00.
2
BARANGAY DISASTER RISK REDUCTION AND MANAGEMENT PLAN
Financial Requirement Utilization of 70% BDRRM FUND FY-2014
I. Mitigation - - - - - P 8,000.00
II. Preparedness - - - P36,845.00
TOTAL P44,845.00
4
II. PREPAREDNESS: Lead: Punong Barangay
Members: SANGGUNIANG BARANGAY MEMBER, DepED, PNP, BNS, BHW, Barangay Tanod.
FUNDING AMOUNT
2.c. Repair of rescue 2.c. Purchase of spare parts and Availability of 2nd quarter 20,000.00 20,000.00
vehicle upholsteries. rescue vehicle
Sub – Total 36,845.00 36,845.00
5
BARANGAY DISASTER RISK REDUCTION AND MANAGEMENT PLAN
Financial Requirement Utilization of 30% BDRRM FUND FY-2014
1. To save lives, 1.a. Mobilization, dispatch of quick response team to 1. Emergency Number of affected Occurrence of 10,000.00 10,000.00
reduce health conduct: Transportation/Mobili population served. emergencies/dis
impacts, ensure -Rapid damage assessment, needs analysis and zation Services aster.
public safety, meet identification of victims.
the basic subsistence -Evacuation of disaster victims and provision of 2. Fuels & Lubricants
needs of the people emergency response.
affected and 1.b. Emergency Relief Operations: 3. Life saving devices
normalized as quickly -Withdrawal of relief food commodities/medicine and 4. Evacuation areas
as possible the other non-food relief supplies. 5. Communication
situation and living -Actual relief distribution of food commodities and Services
conditions of the other relief goods and medical assistance.
people in the areas 1.c. Send disaster reports to higher authorities (initial 6. Food commodities
stricken by disaster & Progress reports) and other non-food
calamities, epidemics, 1.d. Continuous Relief Operation: relief supplies
or complex -Search and rescue, humanitarian assistance, recovery
emergencies. & engineering. 7. Medicine
Total 10,000.00 10,000.00
7
IV. REHABILITATION: Lead : Punong Barangay
Members : Chairman on Committee on Public Works,DepED, PNP, TANODS
FUNDING
AMOUNT
OBJECTIVES PROGRAM/ACTIVITY Resources/Equipm PERFORMANCE TIME
ent/Supplies INDICATOR FRAME MOOE
Needed CO TOTAL
1. To provide food to 1.a. Emergency Cash assistance 1.a. Cash 1.a. Number of After the 9,219.60 9,219.60
distressed/displaced families served. occurrence of
individuals as disaster.
temporary source of
livelihood while
undertaking
restoration and
rehabilitation of own
damage dwelling
units.
Sub-Total 9,219.60 9,219.60
Breakdown/Summary:
1. Response P 10,000.00
2. Rehabilitation P 9,219.60
TOTAL P19,219.60
8
TOTAL FINAL BREAKDOWN SUMMARY
1. Mitigation - - - - - - - - - - - - - - - - - - - - - P 8,000.00
II. Preparedness - - - - - - - - - - - - - - - - - - - P 36,845.00
………………
===========
9
BARANGAY DISASTER RISK REDUCTION AND
MANAGEMENT PLAN
I. Mitigation - - - - - - - - - - - - - P 8,000.00
TOTAL - - - - - - - - - - - P 44,845.00
3
BARANGAY DISASTER RISK REDUCTION AND MANAGEMENT PLAN
Financial Requirement Utilization of 30% BDRRM FUND FY – 2014
TOTAL p19,219.60