TBL - 31 - E - BV - EP40 - IP - 001 - Factory Acceptant Test Procedure (FAT)

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 33

Space for Stamp: IP/OE

RETURN CODE

Revision History
Rev Revision Created Checked by Approved by Brief Description
Date by
A June 20, 19 Buppha Amrun. M First Information
0 July 25, 19 Buppha Ittichai Amrun. M For Construction

Description of Current Revision:

Owner

Owner’s Engineer: Contractor:

Project
TAMBAK LOROK COMBINED CYCLE
POWER PLANT BLOCK 3 PROJECT
WITH NET DEPENDABLE CAPACITY OF 600 – 850 MW.
SEMARANG – CENTRAL JAVA
Subject:
“Factory acceptant Test procedure (FAT)”
Issue Purpose: For Construction Responsible Dept:
Electrical
Originator:

Originator Document No: VICTRON-TL01-Q-0001 Originator Rev:


B
Project Document No: Rev: Sheet.

TBL/31/E/BV----EP40/IP/001 Page

0 33
System Overview
Product : Tecned UPS Model ONV 230V, 35 kVA x 2 Unit
Configuration : Parallel redundant system ( N+1 )
Battery Autonomy time : 2 x 120 Min
Open Lead Acid Battery (Flood Type)
“Classlic” Model 8 OPZS 800 LA with Recombination Plug Rate 2V/900 AH
Bypass Cabinet with Automatic Voltage stabilizer
Battery Configuration
- 110 Cell/ String ( Connect in Series )
- 1 String / UPS ( Connect in Parallel )
- Total Number of String 2 String
- Total Number of Battery 220 Cell
- Battery for FAT will be used Seal lead acid 12V x 18(216 Cell) Block/String
Group of Critical Load
- WTP&WTTP
- Chlorination plant

Country of Origin
1.) Tecned UPS : The Netherland
2.) Classlic Battery : France
System Single line diagram
Item 3.1.1 and 4.1.1
UPS input Voltgae

Display Rectifier Inverter STB


unit control control control
Input Bypass
1 phase, 230V
Manual LOAD
Bypass

Static
Bypass
Switch

Input DC.Charge Volt


3 phase, 400 V 0 V Static
RECTIFIER INVERTER Inverter
Switch

MCCB F3
OPEN

Measure
Input Voltage

CB.
Battery
Battery Protection
110 Cell
“OPEN”
Item 3.1.2 and 4.1.2 (1)
Rectifier Output Voltgae

Display Rectifier Inverter STB


unit control control control
Input Bypass
1 phase, 230V
Manual LOAD
Bypass

Static
Bypass
Switch

Input DC.Charge Volt


3 phase, 400 V 243V Static
RECTIFIER INVERTER Inverter
Switch

MCCB F3
OPEN

Measure
Rectifier Voltage

MCCB.
Battery
Battery Protection
110 Cell
“OPEN”
Item 3.1.2 and 4.1.2 (2)
Rectifier Output Voltgae

Display Rectifier Inverter STB


unit control control control
Input Bypass
1 phase, 230V
Manual LOAD
Bypass

Static
Bypass
Switch

Input DC.Charge Volt


3 phase, 400 V 243 V Static
RECTIFIER INVERTER Inverter
Switch

MCCB F3
Closed

Measure
Rectifier Voltage

MCCB.
Battery
Battery Protection
110 Cell
“OPEN”
Item 3.1.3 and 4.1.3
Battery supply Voltgae: Float and Boost charge

Display Rectifier Inverter STB


unit control control control
Input Bypass
1 phase, 230V
Manual LOAD
Bypass

Static
Bypass
DC.Charge Volt Switch
Float:247.5 V/Boost 264V

Input
3 phase, 400 V Static
RECTIFIER INVERTER Inverter
Switch

MCCB F3
Closed

Measure
Battery Voltage

MCCB.
Battery Protection Battery
110 Cell
“Closed”
Item 3.2 and 4.2 (1)
UPS Performance/ On start Inverter unit
Test at No-Load
Display Rectifier Inverter STB
unit control control control
Input Bypass
Input Bypass
1 phase, 230V
1 phase, 230V
Manual No-
Bypass LOAD

Static
Bypass
Switch AC.output Volt
230 V

Input DC.Charge Volt


3 phase, 400 V 247.5 V Static
RECTIFIER INVERTER Inverter
Switch

Measure(2) Measure (3)


- Battery Voltage - Output Voltage
- DC. Ripple Voltage - Output Current
Measure (1) - THD V
- Input Voltage - Frequency
- Input Current Battery - Power KW and KVA
110 Cell
- Power factor
Item 3.2 and 4.2 (1)
UPS Performance
Test at Full-Load
Display Rectifier Inverter STB
unit control control control
Input Bypass
Input Bypass
1 phase, 230V
1 phase, 230V
Manual Full-
Bypass LOAD

Static
Bypass
Switch AC.output Volt
230 V

Input DC.Charge Volt


3 phase, 400 V 243 V Static
RECTIFIER INVERTER Inverter
Switch

Measure(2) Measure (3)


- Battery Voltage - Output Voltage
- DC. Ripple Voltage - Output Current
Measure (1) - THD V
- Input Voltage - Frequency
- Input Current Battery - Power KW and KVA
- THD i 110 Cell
- Power factor
Item 3.3.1 and 4.3.1
Battery Mode test

Display Rectifier Inverter STB


unit control control control

Manual Full-
Bypass LOAD

Static
Battery Volt Bypass
216 V Switch AC.output Volt
230 V

Static
RECTIFIER INVERTER Inverter
Switch

Record output voltage


Continuous without loss
voltage to load
“Setting time plot Mode”
Battery
110 Cell
Item 3.3.2 and 4.3.2
Main input return/Rectifier automatic re-start

Display Rectifier Inverter STB


unit control control control
Input Bypass
Input Bypass
1 phase, 230V
1 phase, 230V
Manual Full-
Bypass LOAD

Static
Bypass
Switch AC.output Volt
230 V

Input DC.Charge Volt


3 phase, 400 V 243 V Static
RECTIFIER INVERTER Inverter
Switch

Record output voltage


Continuous without loss
voltage to load
“Setting time plot Mode”
Battery
110 Cell
Item 3.3.3 and 4.3.3
Transfer load to automatic (static)bypass

Display Rectifier Inverter STB


unit control control control
Input Bypass
Input Bypass
1 phase, 230V
1 phase, 230V
Manual Full-
Bypass LOAD

Static
Bypass
Switch AC.output Volt
230 V

Input DC.Charge Volt


3 phase, 400 V 243 V Static
RECTIFIER INVERTER Inverter
Switch

Record output voltage


Continuous without loss
voltage to load
“Setting time plot Mode”
Battery
110 Cell
Item 3.3.4 and 4.3.4
Transfer load to Manual (Maintenance) bypass

Display Rectifier Inverter STB


unit control control control
Input Bypass
Input Bypass
1 phase, 230V
1 phase, 230V
Manual Full-
Bypass LOAD

Static
Bypass
Switch AC.output Volt
230 V

Input DC.Charge Volt


3 phase, 400 V 243 V Static
RECTIFIER INVERTER Inverter
Switch

Record output voltage


Continuous without loss
voltage to load
“Setting time plot Mode”
Battery
110 Cell
Remote Communication
Item 3.5
Item 5.1 Active share load
- UPS 1 & UPS 2 Active Share load 50:50 Percent
- Separate Charging it’s own battery (Float Charge)
- Output Voltage of these 2 UPS are synchronize.
UPS-A UPS-0B
Measure Measure
- Input Voltage - Input Voltage
- Input Current - Input Current
RECTIFIER RECTIFIER
Battery Protection Panel
243 V 243 V
MCCB MCCB

INVERTER INVERTER
Measure Measure
Battery Voltage Battery Voltage

STATIC STATIC STATIC STATIC


BYPASS BYPASS BYPASS BYPASS

BATTERY BATTERY
#A #B
Q9 Q9

Measure Measure
- Output Voltage - Output Voltage
- Output Current - Output Current
- Output Power - Output Power

Common Bus at Bypass Cabinet

Measure
- Output Voltage
- Output Current
Dummy Load
- Output Power
Item 5.2 Battery Operation
- UPS 1 & UPS 2 Active Share load 50:50 Percent
- Output Voltage of these 2 UPS are synchronize.

UPS-A UPS-0B

RECTIFIER RECTIFIER
Battery Protection Panel
216 V 216 V
MCCB MCCB

INVERTER INVERTER
Measure Measure
Battery Voltage Battery Voltage

STATIC STATIC STATIC STATIC


BYPASS BYPASS BYPASS BYPASS

BATTERY BATTERY
#A #B
Q9 Q9

Measure
Measure
- Output Voltage
- Output Voltage
- Output Current
- Output Current
- Output Power
- Output Power

Common Bus at Bypass Cabinet

Measure
- Output Voltage
- Output Current
UPS-DB.
- Output Power

CT Make up Chlorination System


Item 5.3 UPS A Failure
- Simulate UPS A fail
- UPS B Take load 100 % with-out interrupt to load

UPS-A UPS-0B
Measure Measure
- Input Voltage - Input Voltage
- Input Current - Input Current
RECTIFIER RECTIFIER
Battery Protection Panel
243 V 247.5 V
MCCB MCCB

INVERTER INVERTER
Measure Measure
Battery Voltage Battery Voltage

STATIC STATIC STATIC STATIC


BYPASS BYPASS BYPASS BYPASS

BATTERY BATTERY
#A #B
Q9 Q9

Measure Measure
- Output Voltage - Output Voltage
- Output Current - Output Current
- Output Power - Output Power

Common Bus at Bypass Cabinet

Measure
- Output Voltage
- Output Current
UPS-DB.
- Output Power

CT Make up Chlorination System


Item 5.4 UPS B Failure
- Simulate UPS B fail
- UPS A Take load 100 % with-out interrupt to load

UPS-A UPS-0B
Measure Measure
- Input Voltage - Input Voltage
- Input Current - Input Current
RECTIFIER RECTIFIER
Battery Protection Panel
243 V 243 V
MCCB MCCB

INVERTER INVERTER
Measure Measure
Battery Voltage Battery Voltage

STATIC STATIC STATIC STATIC


BYPASS BYPASS BYPASS BYPASS

BATTERY BATTERY
#A #B
Q9 Q9

Measure Measure
- Output Voltage - Output Voltage
- Output Current - Output Current
- Output Power - Output Power

Common Bus at Bypass Cabinet

Measure
- Output Voltage
- Output Current
UPS-DB.
- Output Power

CT Make up Chlorination System


Item 6.2
Bypass Transformer and Automatic voltage Regulator

Input Bypass AC.output Volt


3 phase, 400/230V 230 V +/- 1%
Automatic Load
Voltage Regulator 0 and 100%

Measure (1) Measure (2)


- Input Voltage - Output Voltage
- Input Current - Output Current
Item 6.3.1
Fuction Test by setting output voltage at 240 V

Input Bypass AC.output Volt


3 phase, 400/230V 240 V +/- 1%
Automatic Load
Voltage Regulator 0 and 100%

Measure (1) Measure (2)


- Input Voltage - Output Voltage
- Input Current - Output Current
Item 6.3.1
Fuction Test by setting output voltage at 240 V

Input Bypass AC.output Volt


3 phase, 400/230V 240 V +/- 1%
Automatic Load
Voltage Regulator 0 and 100%

Measure (1) Measure (2)


- Input Voltage - Output Voltage
- Input Current - Output Current
Item 6.3.2
Fuction Test by setting output voltage at 220 V

Input Bypass AC.output Volt


3 phase, 400/230V 220 V +/- 1%
Automatic Load
Voltage Regulator 0 and 100%

Measure (1) Measure (2)


- Input Voltage - Output Voltage
- Input Current - Output Current
UPS FACTORY ACCEPTANT TEST

Project Name :
Customer Name :

Main Contractor :
Owner :

UPS-01
Model :
Rated :
S/N :

UPS-02
Model :
Rated :
S/N :

Bypass Transformer and AVR


Model :
Rated :
S/N :

Place :
Date of Testing :

Standard reference : IEC62040-3

Tecned BV. Customer

Test BY : Withness By (1) :


( ) ( )

Approved BY : Withness By (2) :


( ) ( )

TECNED | Committed to Reliable Energy MADE IN HOLL AND 1


Table content Page

1.) Electrical measuring instrument list 3


2.) Equipment Inspection Check list
2.1 General Data 3
2.2 Visual inspection 4
3.) UPS No.1 Performance Test
3.1 Electrical Pre-Test 5
3.2 UPS Performance Test 5
3.3 UPS Fuction Test 5
3.4 UPS Front Panel LED Alarm and Analog meter 6
3.5 UPS Remote Alarm Test 6
4.) UPS No.2 Performance Test
4.1 Electrical Pre-Test 7
4.2 UPS Performance Test 7
4.3 UPS Function Test 7
4.4 UPS Front Panel LED Alarm and Analog meter 8
4.5 UPS Remote Alarm Test 8
5.) UPS Parallel Function Test
5.1 Active Share Load 9
5.2 Battery Operation 9
5.3 UPS-01 Fail 9
5.3 UPS-02 Fail 9
6.) Bypass Transformer and Automatic Voltage Stbilizer (AVR) Performance Test
6.1 Electrical Pre-Test 10
6.2 AVR Performance Test 10
6.3 AVR Function Test 10
6.4 AVR Analog meter 10

7.) Note 11

TECNED | Committed to Reliable Energy MADE IN HOLL AND 2


Check
Pass/ Not Pass
1.) Electrical measuring instrument list
Digital Multi Meter
(serial number: _________________, calibrated until: _________________)
Digital Clamp Ampere meter and Power Analyzer
(serial number: _________________, calibrated until: _________________)
Digital Clamp Ampere Meter
(serial number: _________________, calibrated until: _________________)

2. Equipment Inspection Check list


2.1 General Data

UPS-serial number:
Power rating:
Power factor:
No. of phase

UPS-serial number:
Power rating:
Power factor:
No. of phase

BYPASS Transformer -serial number:


Power rating:
Power factor:
No. of phase

Battery ( Temporary for Test )


Battery Type:
Number of blocs per UPS : Bloc
Blocks voltage and capacity: V AH
Charging voltage per UPS : V

TECNED | Committed to Reliable Energy MADE IN HOLL AND 3


Check
Pass/ Not Pass

2.2 Visual inspection

2.2.1 UPS-01
Check cabinets and metal parts on damage
Mechanical structure and connectors
Modules and assemblies
Control and power voltage wiring and connectors
Check data type plate/production card/specifications
Check on layout drawing of assemblies
Transformer input , inverter & bypass
Earth connections of assemblies

2.2.2 UPS-02
Check cabinets and metal parts on damage
Mechanical structure and connectors
Modules and assemblies
Control and power voltage wiring and connectors
Check data type plate/production card/specifications
Check on layout drawing of assemblies
Transformer input , inverter & bypass
Earth connections of assemblies

2.2.3 BYPASS TRANSFORMER AND VOLTAGE STABILIZER


Check cabinets and metal parts on damage
Mechanical structure and connectors
Modules and assemblies
Control and power voltage wiring and connectors
Check data type plate/production card/specifications
Check on layout drawing of assemblies
Transformer input , inverter & bypass
Voltage Stabilizer unit
Earth connections of assemblies

TECNED | Committed to Reliable Energy MADE IN HOLL AND 4


Check
Pass/ Not Pass
3. UPS Performance Test "A"

3.1 Electrical Pre-Test


3.1.1 UPS Input Voltage
Apply power to input of UPS and verify proper voltage levels.
Note.
Input Rectifier and Bypass are common

UPS Input Voltage (Main Input)

Line to Line Specification


Actual
Phase U1 – V1 400 V +15%
Phase V1 – W1 400 V +15%
Phase W1 – U1 400 V +15%
Frequency 50 Hz + 5%

3.1.2 Initial Module Energization


DC link voltage verification
Energize voltgae to rectifier / charger and verify proper DC link voltage.
"OPEN" MCCB at Battery Protection Panel locate at Battery room
Measurement DC.link voltage at the battery output terminal or terminal Battery (+,-)

Description (V) DC.

Battery breaker (F3) "Open", 0 V


Battery breaker(F3) "Close"
243 V +/- 1%

3.1.3 Battery Supply

Voltage and Polarity of battery Switch has to be checked before closing


Measurement Battery supply in between Plus(+) pole of battery No.1 to Minus(-) Pole of Battery No.108
o
Temperature C
Verify DC. voltage from UPS charger at battery

Float voltage
Battery voltage Mode No. of cell Nominal Voltage Actual Remark
( 2.25 V/Cell)
UPS-01 Float 108 216 243 V +/-1 % 2.25V/Cell
UPS-01 Boost 108 216 259.2 V +/-1 % 2.4V/Cell

3.2 UPS Performance Test

UPS DATA Record Table


Input Parameter DC. DC. OUTPUT Parameter
( Terminal X3. L1,L2,L3) Voltage (V) Voltage ( Terminal X8. L1,N)
Load Voltage Current Voltage Current THD.V Frequency P S PF.
Termianl Ripple (mV)
(V) (A) (+/-) Termianl (+/-) (V) (A) % Hz. kW kVA
U-V
0% V-W
W-U
U-V
100% V-W
W-U

UPS Input Harmornic (THDi)@Full load 100 % Phase U % Phase W % Phase V %

3.3 UPS Function Test

3.3.1 Battery Mode Test / Record grah from Power analyzer Meter
Simulate Main input Fail by "Open" Main input Circuit Braker supply to UPS/ Load will supply by Battery Load will not OFF
or UPS will change to battery Mode .

3.3.2 Main input Recovery Mode / Record grah from Power analyzer Meter
Simulate Main input return by "Closed" Main input Circuit Breaker supply to UPS/ Both Rectifier will automatic ON

3.3.3 UPS Automatic Bypass Mode ( Press Stop Inverter ) / Record grah from Power analyzer Meter

3.3.4 UPS transfer to Manual Bypass Mode/Record grah from Power analyzer Meter

Note.
Record grah of Output current & voltage from Power analyzer Meter for every step load

TECNED | Committed to Reliable Energy MADE IN HOLL AND 5


Check
Pass/ Not Pass

3.4 UPS Front Panel LED Alarm and Analog meter


Analog Metering
- V1 Input AC.Voltage
- A1 Input AC.Current
- V3 Battery DC.Voltage
- A3 Battery DC.Current
- V8 Output AC.Voltage
- F8 Output Frequency
- A8 Output AC.Current
LED Lamp Status
Rectifier
- Operation
- Boostcharge
- Battery Operation
- General Alarm
- Utility Failure
- General Alaarm
- DC.Voltage High
- DC.Voltage Low
- Rectifier Failure
- Fan Failure
- DC.Ground Fault
Inverter
Operation
Load On Inverter
General
DC Voltage Low
DC Voltage Low
Inverter Failure
Load On Bypass
Manual Bypass ON
Input Bypass Fault
Fan Failure
Over Temparature
- Inverter Not Sync

3.5 UPS Remote Alarm Test and external signal trip


Output Relay Change status

- General Alarm "R1"


- Utility Failure "R2"
- Battery Low "R3"
- Over Temparature "R4"
- Fan Failure "R5"

TECNED | Committed to Reliable Energy MADE IN HOLL AND 6


Check
Pass/ Not Pass
4. UPS Performance Test "B"

4.1 Electrical Pre-Test


4.1.1 UPS Input Voltage
Apply power to input of UPS and verify proper voltage levels.
Note.
Input Rectifier and Bypass are common

UPS Input Voltage (Main Input)

Line to Line Specification


Actual
Phase U1 – V1 400 V +15%
Phase V1 – W1 400 V +15%
Phase W1 – U1 400 V +15%
Frequency 50 Hz + 5%

4.1.2 Initial Module Energization


DC link voltage verification
Energize voltgae to rectifier / charger and verify proper DC link voltage.
"OPEN" MCCB at Battery Protection Panel locate at Battery room
Measurement DC.link voltage at the battery output terminal or terminal Battery (+,-)

Description (V) DC.

Battery breaker (F3) "Open", 0 V


Battery breaker(F3) "Close"
243 V +/- 1%

4.1.3 Battery Supply

Voltage and Polarity of battery Switch has to be checked before closing


Measurement Battery supply in between Plus(+) pole of battery No.1 to Minus(-) Pole of Battery No.108
o
Temperature C
Verify DC. voltage from UPS charger at battery

Float voltage
Battery voltage Mode No. of cell Nominal Voltage Actual Remark
( 2.25 V/Cell)
UPS-01 Float 108 216 243 V +/-1 % 2.25V/Cell
UPS-01 Boost 108 216 259.2 V +/-1 % 2.4V/Cell

4.2 UPS Performance Test

UPS DATA Record Table


Input Parameter DC. DC. OUTPUT Parameter
( Terminal X3. L1,L2,L3) Voltage (V) Voltage ( Terminal X8. L1,N)
Load Voltage Current Voltage Current THD.V Frequency P S PF.
Termianl Ripple (mV)
(V) (A) (+/-) Termianl (+/-) (V) (A) % Hz. kW kVA
U-V
0% V-W
W-U
U-V
100% V-W
W-U

UPS Input Harmornic (THDi)@Full load 100 % Phase U % Phase W % Phase V %

4.3 UPS Function Test

4.3.1 Battery Mode Test / Record grah from Power analyzer Meter
Simulate Main input Fail by "Open" Main input Circuit Braker supply to UPS/ Load will supply by Battery Load will not OFF
or UPS will change to battery Mode .

4.3.2 Main input Recovery Mode / Record grah from Power analyzer Meter
Simulate Main input return by "Closed" Main input Circuit Breaker supply to UPS/ Both Rectifier will automatic ON

4.3.3 UPS Automatic Bypass Mode ( Press Stop Inverter ) / Record grah from Power analyzer Meter

4.3.4 UPS transfer to Manual Bypass Mode/Record grah from Power analyzer Meter

Note.
Record grah of Output current & voltage from Power analyzer Meter for every step load

TECNED | Committed to Reliable Energy MADE IN HOLL AND 7


Check
Pass/ Not Pass

4.4 UPS Front Panel LED Alarm and Analog meter


Analog Metering
- V1 Input AC.Voltage
- A1 Input AC.Current
- V3 Battery DC.Voltage
- A3 Battery DC.Current
- V8 Output AC.Voltage
- F8 Output Frequency
- A8 Output AC.Current
LED Lamp Status
Rectifier
- Operation
- Boostcharge
- Battery Operation
- General Alarm
- Utility Failure
- General Alaarm
- DC.Voltage High
- DC.Voltage Low
- Rectifier Failure
- Fan Failure
- DC.Ground Fault
Inverter
Operation
Load On Inverter
General
DC Voltage Low
DC Voltage Low
Inverter Failure
Load On Bypass
Manual Bypass ON
Input Bypass Fault
Fan Failure
Over Temparature
- Inverter Not Sync

3.5 UPS Remote Alarm Test and external signal trip


Output Relay Change status

- General Alarm "R1"


- Utility Failure "R2"
- Battery Low "R3"
- Over Temparature "R4"
- Fan Failure "R5"

TECNED | Committed to Reliable Energy MADE IN HOLL AND 8


Check
Pass/ Not Pass

5. UPS Parallel Function Test

Step 1. Connect UPS01 & 02 as Parallel Redundnat System ( Common output of each UPS )
Step 2. Connect Power Analizer to the UPS output
Step 3. Turn-on UPS 01 & 02 as Parallel function
Step 4. Apply load Full load as rated of single UPS at the output A

5.1 Active Share Load


Record grah from Power analyzer Meter

UPS DATA Record Table


Input Parameter DC. DC. OUTPUT Parameter
( Terminal X3. L1,L2,L3) Voltage (V) Voltage ( Terminal X8. L1,N)
Load Voltage Current Voltage Current THD.V Frequency P S PF.
Termianl Ripple (mV)
(V) (A) (+/-) Termianl (+/-) (V) (A) % Hz. kW kVA
U-V
UPS-A V-W
W-U
U-V
UPS-B V-W
W-U

UPS-01 & 02 Share equal load


UPS-01 & 02 Output Wave from Synchornize

5.2 Battery Operation


Record grah from Power analyzer Meter
Simulate Main input Failure by "Open" Main input Curcuit Braker suppier to UPS01 &02 / Load will supply by Batery
Load will supply by Batery -01 & 02
UPS-01 & 02 Share equal load
UPS-01 & 02 Output Wave from Synchornize
Return Main input suppier / UPS-01 & 02 automatic Started and share equal load

5.3 UPS-01 Fail


Record grah from Power analyzer Meter
Simulate UPS-01. Fail by switch "OFF" Inverter ,
Load will Supply to UPS-02 / "UPS-02 output current = connected Load"
Return UPS-01 to Normal mode by turn on inverter / UPS-01 & 02 Share equal load

5.4 UPS-02 Fail


Record grah from Power analyzer Meter
Simulate UPS-02. Fail by switch "OFF" Inverter ,
Load will Supply to UPS-01 / "UPS-01 output current = connected Load"
Return UPS-02 to Normal mode by turn on inverter / UPS-01 & 02 Share equal load

Photo.1 LCD Display of UPS. A Show Load Percentage Photo.2 LCD Display of UPS. A Show Load Percentage

TECNED | Committed to Reliable Energy MADE IN HOLL AND 9


Check
Pass/ Not Pass
6. Bypass Transformer and Automatic Voltage Stabilizer (AVR) Performance Test

6.1 Electrical Pre-Test


Input Voltage
Apply power to input of UPS and verify proper voltage levels.
Note.
Input Rectifier and Bypass are common

UPS Input Voltage (Main Input)

Line to Line Specification


Actual
Phase L – N 230 V +15%
Frequency 50 Hz + 5%

6.2 BYPASS and AVR Performance Test


Check AVR Output Voltage

BYPASS Transformer and AVR DATA Record Table


Input Parameter OUTPUT Parameter
( Terminal X1. L,N) ( Terminal X3. L,N)
Load Remark
Voltage Current Voltage Current THD.V Frequency P S
PF.
(V) (A) (V) (A) % Hz. kW kVA
0%
100%

6.3 AVR Function Test

- Setting output Voltage at 240 V


AVR unit adjusted voltage output 240 +/- 2%.

- Setting output Voltage at 220 V


AVR unit adjusted voltage output 220 +/- 2%.

6.4 Bypass Panel Analog meter

- V1 Input AC.Voltage
- V1 Input AC.Current

TECNED | Committed to Reliable Energy MADE IN HOLL AND 10


Check
Pass/ Not Pass

7.Note :