Professional Documents
Culture Documents
Girder Erection Methodology
Girder Erection Methodology
(
eiekt Lane Access-Controlled Ex
Access-Controlled
Expressway Carriageway from Ranni Village to Miyati
Village of
Construction
tCh.652+720 to 673+770; Design Ch.200+300 to 221+350) Section of Delhi Vadodara
-
ont (NH-148N) on EPC Mode under Bharatmala Pariyojana in the State of Madhya Pradesh
(Package-24)
1. Purpose:
The Purpose of This Methodology for Shifting and Erection of Pre Cast
PSC (Pre-Tensioned Post-Iensioned) and R c -Girders for Major
Bridges and Minor Bridges as well, is to be provided in detailed
procedures to be adopted, materials to be used, resources to be deployed
and moreover, quality assurance and control system/ Procedures.
2. Scope Of Work:
The Scope of this Methodology tor shifting and erection of Pre-cast PSC
(Pre-Tensioned/Post-Tensioned) and RCC 1-Girders for Major Bridges
and Minor Bridges covers the following activities.
31.00MT -
71 Nos.
Page 1|6
Construction of Eight Lane Access-Controlled Expressway Carriageway from Ranni Village to Miyati Village of
Jhabua District (Ch.652+720 to 673+770; Design Ch.200+300 to 221+350) Section of Delhi - Vadodara
oreentield Alignment (NH-148N) on EPC Mode under Bharatmala Pariyojana in the State of Madhya Pradesh
(Package-24)
at site:
Erection of PSC girder
7. duly loaded with the PSC girder
du on
the Trailer
required
7.1 First, place
location.
cranes to
near the loaded trailer to lift the airder
72 Bring the two
from the trailer and let the trailer move off its Dosifion
cranes nearer to the girder and lift the girder on to the niar
7.5 Move the two
till the working radius permits.
Same procedure from points no 7.1 to 7.7 To be repeat to erect all girders.
8. Safety Measures:
.The crane operator should be competent in the scope of work to be
undertaken.
and site
Crane Load chart shall be available with the Crane operator
condition.
engineer also ensure the cranes SLI should be in working
The area of erection shall be cordoned by safety barrier as safet
cone.
All personnel should be outside the drop zone when lifting/tiltingths
panel and rotating it from horizontal to the vertical.
A rigger, who is competent in the work execution that is to D
performed and additional.
Page 3|6
Constructionof Fight
of E Lane Access-Controlled Expressway Carriageway from Ranni
Village Miyati Village of
to
Dictrict (Ch.652+720 to 673+770; Design Ch.200+300 to 221+350) Section
Aliaoment (NH-148N) on EPC Mode under Bharatmala Pariyojana in the StateDelhi-Vadodara
of
Greenfiel of Madhya Pradesh
(Package-24)
Competent labours are required to assist with erection or placement
of element.
.Unauthorized persons & visitor shall not be allowed within the
working area.
10.References:
a. MOR&TH
Page 4 |6