Professional Documents
Culture Documents
TCP DR 002 R2 - Dredging and Reclamation Plan
TCP DR 002 R2 - Dredging and Reclamation Plan
PRELIMINARY DESIGN OF WEST BERTH AND EXPANSION OF CONTAINER YARD AT TERMINAL CUENCA
DEL PLATA, MONTEVIDEO-URUGUAY
APRIL 2021
Table of figures
Figure 2-1. Channel Depth Factors_Handbook Quay Walls ....................................................... 5
Figure 2-2. Channel Depth Factors_PIANC 2014 ........................................................................ 6
Figure 2-3. Results of the depth at the berthing area for the design vessel according to the
different design methods ...................................................................................... 7
Figure 3-1. Extent of the scour protection in front of a quay wall PIANC 2014 [ref.6] ............ 10
Figure 3-2. Preliminary design of scour protection of the berthing area (not to scale) .......... 10
Figure 3-3. Open quay wall and shallow rock .......................................................................... 12
Figure 3-4. Open quay wall and deep rock............................................................................... 13
Figure 3-5. Closed quay wall and shallow rock ........................................................................ 13
Figure 3-6. Closed quay wall and rock at great depth.............................................................. 14
Figure 3-7. Areas to be dredged ............................................................................................... 15
Figure 3-8. Cofferdam and retaining wall to protect the southern breakwater ...................... 15
Figure 5-1. Split Hopper barge and backhoe dredger .............................................................. 19
Figure 5-2. Rock levels in berthing area ................................................................................... 19
Figure 5-3. Typical rock core recovered ................................................................................... 19
Figure 5-4. Floating pontoon with drill towers......................................................................... 20
Figure 5-5. Heavy duty rock CSD .............................................................................................. 20
Figure 5-6. Installation of geotextile mats ............................................................................... 21
Figure 5-7. 9,000 m3 TSHD ....................................................................................................... 23
Figure 5-8. Temporary slope at the reclamation fill, open quay .............................................. 24
Figure 5-9. Spreader barge, connected to a floating pipeline.................................................. 25
Figure 5-10. Bulldozers pushing sand in front of the landline releasing the sand mixture ..... 25
The information provided in this document is for Milestone 2 of the project ‘Extension of Cuenca del
Plata Terminal’. The report is compiled to determine feasibility of the dredging and reclamation works
and presents the dredging design for the berthing and terminal area.
This document is intended to provide a level of internal alignment and provide the Client and
Consultants with a starting point for further detailing of the project.
Unless specifically designated by date, the latest edition of each publication shall be used, together
with any amendments/supplements/revisions thereto.
According to the handbook Quay Walls [ref.7], the recommended design depth of the berthing area
depends on the draught of the loaded ship (D), the vertical movement caused by waves, listing and
trim and the required keel clearance. This is presented in the figure below.
As a rule of thumb, 10 % of the maximum draught is taken for the keel clearance. Therefore, the
required Nautical Guaranteed Depth (NGD) is equal to the level design water level (see BoD [ref. X])
minus 1.1 times the maximum draught of the design vessel.
To determine the design depth of the berthing area an extra allowance for sedimentation
(maintenance margin) and dredging tolerances needs to be added to the NGD. According to the
handbook Quay Wallss, the maintenance margin is set equal to 0.50 m for unprotected bottoms and
1.0 m for bottoms with scour protection. In addition, the presence of rocks at the bottom is another
reason to adopt a higher margin (similar to the location where scour protection is installed).
This results in the following formula used for determining the Nautical Guaranteed Depth (NGD) of the
berthing area:
Where: DWL is Design Water Level (see BoD [ref. X]) equal to -0.5 m Wh
The PIANC 2014 [ref.5] is a guideline developed for the design of approach channels (and not for
terminal). Therefore, this method is included for the sake of comparison. According to PIANC 2014,
the recommended design depth of the berthing area is determined by the vessel draught (D), the
design water level and the ship and bottom related factors. This is presented in the figure below.
The ship related factors dominate the design depth. These factors (squat, dynamic heel and wave
response allowance, etc) can be estimated separately or can be combined into one factor (Fs),
according to PIANC 2014. The combined factor (Fs) is obtained by multiplying the design draught by a
coefficient and by adding a constant value. The coefficient depends on ship speed and wave
conditions. Near berthing areas, the ship speed is low, the wave conditions are the dominant factor
for the value of this coefficient. A higher wave height will lead to a higher coefficient. The constant
value depends on the sea bottom type.
The combined factor (Fs) is obtained according to table 2.2 of the PIANC 2014 in combination with the
starting points applied for the design.
This results in the following formula used for determining the combined factor (Fs) and thus the
Nominal Bed Level (NBL) of the berthing area:
Where: DWL is Design Water Level (see BoD [ref. X]) equal to -0.5 m Wh
Note that, in order to define the average dredging depth of the berthing area, an extra allowance
below the Nominal Bed Level needs to be incorporated in the design. This allowance is the bottom
related factors presented in ¡Error! No se encuentra el origen de la referencia..
The results of the depths at the berthing area according to the different design methods are presented
in the figure below:
Figure 2-3. Results of the depth at the berthing area for the design vessel according to the different
design methods
On top of the Nautical Guaranteed Depth an extra allowance is required to accommodate dredging
tolerance and sediment buffer to arrive at the average dredge level. Before we calculate the dredge
level it’s important to mention that there are three different dredging levels distinguished in the
berthing area. These different levels relate to:
2 Areas where the bottom after dredging consists of ‘soft’ or erosion sensitive material, but are not
close to the berthing line. Close to the berthing line there will be a bottom protection
3 Areas where a bottom protection needs to be installed, near the berthing line.
The table below presents the recommended average dredge levels of the berthing area for the design
vessel. After discussions with the Client it was agreed to round these levels to the figures presented in
the column “agreed average dredge level”
Table 2-2. Recommended depth levels at the berthing area for the design vessels
Nautical Guaranteed Average dredge level [m Agreed average dredge
Area Allowances [m]
Depth [m Wh] Wh] level [m Wh]
1 -15.9 1.0 -16.9 -17.0
- The susceptibility to erosion of the subsoil: grain shapes and size, composition and bottom
roughness.
According to handbook Quay Walls [ref.7], the width of the protection in front of the quay wall is
determined by the following criteria:
- Area of the propeller jet load, usually extending 0.75 times the ship’s beam from the front of the
quay.
- The width of the passive wedge of the soil in front of the quay wall, which must be covered by the
bottom protection.
Based on the quay wall design and past project experience, a scour protection composed by quarry
stone with a weight of 10–60 kg grouted with asphalt-bitumen or colloidal concrete is recommended.
The grouting of the stones ensures a better protection against erosion and loss of materials. This type
of scour protection has usually a thickness of 0.5 m. In addition, to prevent the bottom material from
being washed out a good filter structure under the scour protection is required. The filter layer usually
consists of sand-tight geotextile. An accepted method is to use fascine mattresses, which consist of
bundles of fascines attached to a strong geotextile. The mattress is sunk onto the bottom as an
extended carpet. In a further design phase it should be investigated if this design solution is locally
available.
For most conditions, the extent of the protection results in a width smaller than the ship’s width
PIANC 2014 (see figure 3.1). The extent of the protection depends on the influence area of the
propellers and thrusters of the design vessels. This influence area is approximately 0.75 times the
ship’s beam from the front of the quay According to handbook Quay Walls. Given the beam of the
design vessel (see Basis of design) the length of the scour protection from the front of the quay should
be at least equal to 44 m. It is recommended to compute the required passive soil wedge in front of
the quay wall, which must be covered by the bottom protection in a later project stage.
Furthermore, it is advised to increase the protection width with an extra 5 m composed by only rock
material with a weight of 10–60 kg. This extra width ensures a smooth transition between the
protected and the unprotected bottom and functions as a falling apron.
The table and the figure below presents the preliminary design of scour protection of the berthing
area:
Figure 3-2. Preliminary design of scour protection of the berthing area (not to scale)
Slope protection
In case the quay wall structure consists out of a deck on piles with a protected slope below the deck,
it’s important that a smooth transition is created between this slope- and the bottom / scour
protection of the berthing area.
In section 3.4 a (different) solution is presented for the protection of the southern breakwater.
Most of the material in the terminal area, on top of the rock, is very soft silty clay or clayey silt.
Material with a low SPT value (< 5-15 blows) which lies relatively shallow (say 0-8 m below bed level)
should be removed. Removal of deeper layers with very low SPT values can also be removed but this
could become costly and risky. Especially in the southern area towards the breakwater (Escollera
Sarandi) this is relevant since the top of rock is deeper than -30 m Wh at some point. Removing all
material on top of the rock would result in very large dredge volumes but also in risks of instability in
surrounding areas, that will not be dredged.
All material dredged from the terminal area will be disposed in an offshore disposal area at
approximately 30 km distance from the dredging area (see Basis of Design). The disposal area is
determined in cooperation with TCP.
1 High levels of residual settlement after the terminal area has been filled with sand.
2 Instability of the reclamation fill and soft subsoil at the location of the slope under the piled deck
(at the deck on piles alternative).
3 Hight pressures of soft subsoil against a closed quay wall due to the load of the reclamation fill. The
soft soil is pushed towards the closed quay wall, resulting in an extra horizontal load.
Additional soil investigation is required to make proper settlement and stability predictions and
resulting phased construction and measures to shorten the residual settlement period. With these
calculations and predictions several design loops need to be made to find the optimum between
removing a layer of soft material with a certain thickness and phased construction of the reclamation
and measures for speedy settlement.
Four different preliminary dredging design solutions have been developed based on the two base
solutions for the quay wall design. Starting point is that soft material is dredged from the terminal
area up to the rock layer in case the rock layer is less than 10 m below current seabed level. In case
the rock layer is deeper than 10 m, then a layer of approximately 7 m soft material will be removed,
the deeper layers of soft material remain. Near the quay wall construction (both alternatives) deeper
dredging off soft material is necessary to reduce stability risks.
All soft material on top of the rock layer will be removed. In the berthing area the soft material and
rock will be dredged to a level as described in the chapter ‘berthing area design’.
Soft material will be removed to at least a level of -10 m Wh. Soft soil is removed to a maximum level
of -27.5 m Wh near and at the location of the open quay wall structure as shown in the figure below.
All soft material on top of the rock layer is removed. In the berthing area the soft material and rock
will be dredged to a level as described in the chapter ‘berthing area design’. No bottom protection is
required in the berthing area.
The figure below indicates that soft material will be removed up to -10 m Wh. Soft soil is removed to a
level of approximately -20 m Wh near and at the location of the closed quay wall structure as shown in
the figure below. Replacement of the soft soil with sandy material is required to limit the soil pressure
behind the closed quay wall. This -20 m Wh is continued for another 10 m into the terminal area. The
sandy material on both sides of the closed quay wall also results in better balanced passive forces. Soil
improvement to a lower level at this location might be necessary for that reason. Results of additional
soil investigations should be used to determine optimum level.
Extra soil investigations need to be carried out at the locations where stability is critical both for
dredging and also for the reclamation works (at the Escollera Sarandi).
The southern breakwater requires attention with respect to stability when dredging or reclaiming in
its vicinity. The construction of a so called cofferdam and retaining wall to minimize impact of the
dredging and reclamation works on the breakwater could be considered. The picture below (3-8)
shows how this could look like. Three main advantages of suchs a combination of structures are:
- possibility to construct the berthing structure and berthing are up to close proximity of the break
water;
- dredging (up to -27m Wh) for soil improvement under a deck of piles structure to enable a steep
(1:2) slope under the deck on piles;
- dredging the berthing area for soil improvement in close proximity of the breakwater;
Figure 3-8. Cofferdam and retaining wall to protect the southern breakwater
Rock material extends outside the berthing area (50m wide) towards the shipping channel. Removal of
this rock and the soft soil on top of it to a level of -17m Wh might be required. Volumes for these extra
volumes are indicated in the table below.
Dredging works take place at three different locations: the berthing area, the terminal area and the
offshore sand borrow area. All three locations might require different dredging methods and
equipment, possibly some synergy can be achieved. This will be discussed in this chapter.
A choice needs to be made between mechanical and hydraulic dredging. Mechanical dredging is by
means of a grab or backhoe dredger and hydraulic dredging happens with a cutter suction dredger or
a trailing suction hopper dredger.
Water is added to the dredged material to pick it up and transport it in case of hydraulic dredging. The
mixture of clay/silt and water is loaded in the hopper. When the hopper is fully loaded with the
mixture it’s ready to sail. The density of dry particles in the hopper is low at that point in time.
Increasing the density in the hopper by releasing surpless/process water from the hopper is not
possible without also releasing silt/clay particles since the latter will not settle in the hopper but stay
in suspension. So, sailing to the disposal area with a low situ-volume of material in the hopper seems
the only option and is very in-efficient The hopper loading process can be more efficient and the use
of for example a TSHD might be an option in case loading of the very soft soil is possible with only
adding a small volume of process water. The situ volume percentage in the hopper might be sufficient
for an efficient process.
However, mechanical dredging seems a more efficient method in this case. This is best done by a
backhoe dredger accompanied with 2 or 3 split hopper barges. See figures below.
Mobilising a heavy duty CSD for this rock dredging is very costly.
Especially because the CSD does not seem to be a feasibly/efficient
way to dredge the soft soil in the berthing area and the terminal
area.
Before the mats are placed the bottom of the berthing area needs to be levelled. The variation of the
bottom levels should be within a range of -5/+5 cm. This requires accurate levelling by means of a
plow or other device. It might be advisable to replace the soft/clayey sub soil (1 m or so) by sand,
depending on the characteristics of the sub soil.
The geotextile mats are installed with a specially prepared large pontoon. After placing the mats, the
rock material is placed directly on top to stabilise it. A grab-crane or backhoe with grab can be used for
this. After installation of the rock, it will be penetrated with concrete to stabilise the rock.
With extra soil investigations it needs to be determined how close to these structures material can be
dredged and what slopes can best be maintained. If it turns out to risky to dredge close to these
structures then it might be an option to improve the sub soil at these locations after reclamation
works have been carried out. The following could be considered:
- Preloading.
- Vertical drains.
- Soil improvement by removing soft soils and replacing with granular material in a controlled
manner after most of the terminal area is already reclaimed
5.4.3 Disposal
Ones the TSHD arrives at the terminal area it will unload its sand. At the first phase of the reclamation
works the sand will be disposed through a floating pipeline that will be connected to the bow of the
TSHD. The sand on board the vessel will be mixed with water once again and pumped via the bow
coupling through a floating pipeline towards a spreader pontoon. The spreader pontoon will ‘spread’
the sand out over the terminal area in a thin layer (0.5 m). It’s important to not exceed the 0.5 m in
order to slowly and evenly increase the load on the soft sub-soil. This slow increase of loading is
particularly important near the existing southern breakwater. Frequent bathymetric surveys should be
carried out to monitor the filling-in-layers process.
The edge of the reclamation fill area is created at the location of the quay wall. With a spreader barge
it is possible to create a temporary sloop in the berthing area (1:5 / 1:6). This is shown in below
picture.
This method of reclaiming makes it possible to construct the back row and back construction (L-wall)
of the deck on piles quay wall with so called land equipment, standing on the new reclamation. Before
the rest of the pile can be installed the 1:2 slope under the future deck needs to be trimmed and
protected. Maths and rocks are installed in a similar fashion as the bottom protection. Before placing
the armour rock the piles need to be installed from of a barge/pontoon.
A closed quay wall can be constructed completely with dry equipment with this fill method.
Once the quay wall is constructed the remaining sandy material in the berthing area can be dredged
and disposed in the reclamation area.
After the sand fill works reach a level of approximately 1.5 m below water level with the use of a
spreader barge, filling via land and a land line will start. The level of the reclamation area is further
increased up to such a level that sufficient sand has been brought in to also cover for settlement and
possible soil improvement works near the boundaries of the reclamation area.
Below are some pictures of sand fill works, below and above water.
Figure 5-10. Bulldozers pushing sand in front of the landline releasing the sand mixture
The below table shows the required reclamation volume for the terminal area. The gross volume
indicates the estimate volume including allowance for settlement (estimated average 1.5 m). Dredging
volumes area repeated in the table. Volumes of dredging and reclamation are slightly different for the
two alternative quay wall solutions. Since the differences are small (<5%), these are not shown in the
volumes tables.
Phasing of works
Durations as indicated in the table above are net durations, no time is reserved for phasing or waiting.
Especially for the reclamation works it might be necessary to fill in a few phases in order not to
destabilise subsoil, breakwater or existing shore-line (structures). Soil improvement near the existing
shore line or near the breakwater might require fill material first to be placed in temporary stockpiles
after which it is being used to improve the sub soil conditions with land equipment in a controlled
manner near existing shoreline and existing break water.
- Removal of the hard rock material in the terminal area requires specific attention and use of
explosives. Use of explosives near existing structures is a risk for the integrity of these structures.
- The soft sub soil in the terminal area creates a risk for the stability of the quay wall structure. For
the same reason there’s a stability risk when dredging near the existing terminal border, existing
land border/coastline and near the southern breakwater (see also below).
- Leaving soft material in the terminal area will require measures to force the settlement of these
layers and limit residual measurement. The measure that are required take some time and pose a
risk for the planning (see also below).
- Attached to this report is the document named “Dredging and reclamation risks”.
Below are the conclusions on the three risks addressed in this document
It is important to note that the analyses presented in this document are not to be considered as a
proper basis of a design. The purpose of the analyses is to enable the study on feasibility of risk
mitigating measures only. Contractor will be responsible for obtaining and verification of all relevant
starting points, including new information regarding the soil conditions, based on soil surveys which
will be carried out. Based on this information, the Contractor will have to prepare a design. Possibly
the results of this design may result in different conclusions than presented in this report.
Dredging in the proximity of the Sarandí breakwater poses a risk to its stability. Calculations made
based on the available information indicate that a dredging level of -17.5m Wh can only be reached at
a distance of 90m from the centreline of the breakwater (i.e. approximately 80m of its toe) with
negligible impact on the breakwater. As soon as dredging takes place closer to the breakwater, the
stability of the breakwater will be lowered compared to the current situation if no other precautions
are taken. A dredging level of -27.5m Wh, which may be necessary for the soil improvement works,
may only be reached at 130m from the centreline of the breakwater. These distances assume the
bedrock is present at -36m Wh, and may be larger if the bedrock is deeper.
If a deeper bed level is to be reached at a shorter distance to the breakwater, measures need to be
taken. For instance, a large (cofferdam) wall could be built next to the breakwater (port side), reducing
the safe distance between breakwater and berthing pocket.
For the construction of the open berth quay wall, a 1:2 sand slope is to be built. Stability with such
steep slope and a soft subsoil is difficult to achieve. Therefore, to enable the slope of 1:2 the following
construction sequence is proposed:
1. Dredge the area of the proposed container yard and quay wall to the desired level (-27.5m
Wh, due to the required soil improvement);
The indicated slopes and depth correspond to a bedrock at -36m Wh; a deeper bedrock may signify
more demanding requirements (gentler slopes, deeper soil improvement).
We believe this is a robust construction sequence, showing the technical solution is feasible. Future
design stages, when more information is available, may lead to optimisations (such as omitting the
underwater drains).
Calculations indicate that, by using drains and a suitable amount of preload, an acceptable residual
settlement can be achieved within two years, provided the top layers of soft soil are removed. This will
reduce maintenance costs of the container yard substantially. At the location where the bedrock is
present at -36m Wh, dredging down to -17.5m Wh is likely to be sufficient in combination with PVD
and preloading. Where the bedrock is deeper, it is possible that a higher preload and/or more
dredging is necessary, in case the lower layers are formed by soft soil.
It is noteworthy that settlement calculations are mere predictions, and that good monitoring must
take place during construction. Consolidation times may vary.
It’s recommended to carry out additional soil investigations to get a better understanding of the
subsoil and it’s behaviour in the terminal area. This includes investigations to determine whether any
pollutants like chemicals, heavy metals or oil spills are present.
Due care needs to be taken in compiling the tender documents, to address the risks and prepare
requirements that result in proper measures taken by Contractor to mitigate risks and prepare a plan
and work method that matches with the specific challenges of this project. All relevant findings of this
project preparation works should be carefully transferred to the tender documents and the
contractors.
APRIL 2021
2
3
Índice
1. INTRODUCTION................................................................................1
1.1. PROJECT BACKGROUND...................................................................1
1.2. OBJECTIVE ........................................................................................1
1.3. REFERENCES .....................................................................................2
3. CALCULATIONS ................................................................................5
3.1. STARTING POINTS ............................................................................5
3.1.1. Ground conditions ...................................................................5
3.1.2. Water conditions ......................................................................6
3.1.3. Geometry .................................................................................6
3.1.4. Planning ....................................................................................6
3.1.5. Allowable long-term settlement ..............................................7
3.1.6. Safety .......................................................................................7
3.1.7. Software ...................................................................................7
3.2. D-STABILITY CALCULATION: SARANDÍ BREAKWATER (RISK 1).........9
3.3. D-STABILITY CALCULATION: QUAY WALL SLOPE (RISK 2) ..............11
3.3.1. Step 5: Filling to +4.0m Wh ....................................................12
3.3.2. Step 6: Dredging to obtain 1:2 slope......................................13
3.4. D-SETTLEMENTS CALCULATION: RESIDUAL SETTLEMENT (RISK 3)15
4. CONCLUSIONS ................................................................................17
Katoen Natie - Terminal Cuenca del Plata (TCP), through CSI Ingenieros S.A. and its subcontractor
Witteveen+Bos, is developing the preliminary design of an expansion work for its terminal specialized
in container handling, located in the port of Montevideo.
This project comprises the expansion of the container yard and the construction of a 700 m long open
berth (piled deck) to function as a quay wall, between the existing terminal and the Escollera Sarandí.
This is illustrated in Figure 1-1.
1.2. OBJECTIVE
This document starts by describing the most significant risks carried by the dredging works (chapter 2).
It then explains the calculations which were carried out to quantify these risks and investigate possible
mitigation measures (chapter 3). Finally, it draws conclusions and proposes the way forward (chapter
4).
Important: this document is based on limited available site information. Its starting points and
conclusions will need to be updated once a project-specific site investigation takes place.
1. Instability of the Sarandí breakwater, due to nearby dredging works related to the
construction of the quay wall and berthing pocket;
2. Instability of the reclamation during the construction works since thick sand layers need to be
positioned on the existing soft subsoil. Especially the slope to be constructed as part of the
quay wall can be considered to be a critical location;
3. Excessive residual settlement of the container yard caused by slow and high amount of
settlements of the soft subsoil layers not removed by the dredging works.
The west end of the Sarandí Breakwater was built on top of a soil improvement (substitution of clay
by sand and gravel). The below figure shows that soil improvement has been carried out down to -
12m Wh. Given the bedrock level at approximately -36 m Wh, this means that a soft layer of
considerable thickness is to be expected underneath the soil improvement of the breakwater.
Dredging in the vicinity of the Sarandí breakwater will pose a risk to it in terms of significant
displacement and possibly instability, eventually leading to damage and loss of functionality of the
breakwater.
Under the piled deck, a slope needs to be constructed. Currently a steep slope of 1:2 is foreseen to
limit the required deck size, as shown in the drawing below. However, the combination of a steep
sand slope on top of soft subsoil layers may lead to slope instability.
At the container yard area, bedrock may be present below -36m Wh, above which mostly soft soil
layers are encountered. Complete removal of these soft layers by dredging is not desirable given the
large volumes and the risk of instability of surrounding areas (such as the breakwater). Therefore no or
only partial removal of the soft soil layers seems to be the most likely outcome, leaving at least several
meters of soft compressible soil below the reclamation. If no measures are taken this carries the risk
of significant residual settlements during the lifetime of the container yard, leading to high operational
costs.
The project area shows a large variability in the thickness of the soft soil layers on top of the bedrock.
The bedrock level at the location of the proposed quay wall in the area varies between -8m Wh and
deeper than -36m Wh. Close to the Sarandí breakwater, the bedrock is at its deepest at -36 m Wh or
lower. Figure 3-1 shows the top of bedrock level in the area, obtained by seismic profiling (see
references).
Sarandí breakwater
There is limited available site investigation at this area. The closest boreholes to the area with the
deepest bedrock level (and thus the thickest layer of soft soils) are indicated in Figure 3-2 (see also the
references). The numbers between brackets show the year of execution of these boreholes.
It is unknown whether these boreholes represent the subsoil conditions of the entire area well, given
the large variability encountered. Furthermore, the top layers of the boreholes carried out next to the
breakwater are expected to vary substantially at each location. The construction of the breakwater
included soil substitution, and it is likely that during installation the fill mixed with the original soil,
making the conditions potentially very heterogeneous.
For the calculations, borehole P6 was selected because it was the closest one to the critical area. Table
3-1 shows the soil layers and its parameters. These parameters are based on the soil descriptions, in-
situ tests (SPTs and vane tests) and laboratory tests (classification, density and triaxials) made for this
borehole. When necessary, this information was complemented by tests made in nearby boreholes,
and estimations based on engineering judgement.
Parameters are also provided for the non-natural materials in Table 3-2.
A water and groundwater level of 0m Wh is used in the calculations, with hydrostatic porewater
pressures.
3.1.3. Geometry
The geometry of the breakwater used in the stability calculations was based on Figure 2-1. The
required dredging level for vessel navigation and berthing was assumed to be -17.5m Wh.
Other relevant geometric details (such as slope gradient) are presented together with the calculations
in the following sections.
3.1.4. Planning
The reclamation works were assumed to last 2 years for the calculation of settlements.
It was assumed that a long-term settlement (between end of construction and 50 years after) of 10cm
is acceptable. This is an estimation only, no requirements are specified yet.
3.1.6. Safety
The performed calculations were carried out for the purpose of risk assessment only. They are not
design calculations, and no (partial) safety factors were used.
3.1.7. Software
The stability calculations were performed using D-Geo Stability version 17.1, an analytical
macro-stability software, with Bishop failure circles.
The settlement calculations were performed with analytical software D-Settlements version 20.1.
5 SM Very loose silty sand -20.6 4 18 - 22.5 0.1150 0.038 0.0046 10-8
-9
6 ML Soft sandy silt -25.5 3 14 25 - 0.3286 0.1095 0.0131 10
Concrete 25/25 45
The first stability calculation performed has the goal of determining the conditions for which the
stability of the Sarandí breakwater becomes negatively influenced in terms of stability (maximum
allowable dredging level and proximity to the breakwater).
The failure circle for the current conditions is presented in Figure 3-4. The calculated factor of safety
shall be used for comparison purposes only given the uncertain soil conditions under and next to the
breakwater (see section 3.1.1). The actual factor of safety is unknown and difficult to assess, therefore
it is assumed that the current structure is on the edge of failure and any decrease in stability
(reduction of safety factor) needs to be prevented.
Figure 3-5 – Breakwater Stability: failure due to dredging works (-17.5m Wh).
90m
-17.5m Wh
For a dredging level of -27.5m Wh, which may be necessary to carry out a local soil improvement (see
section 3.3), the same 1:4 slope, also starting at approximately 35m from the centreline of the
breakwater, does not have a negative impact on the stability of the breakwater. Following the same
dredging slope and distances, the dredging level of -27.5 m Wh is only reached 130m from the
centreline of the breakwater, see Figure 3-6.
130m
-27.5m Wh
If the berthing pocket is to be positioned closer to the breakwater (i.e. making use of a larger
extension of the quay wall), extra measures need to be taken to ensure the stability of the
breakwater, such as installation of sheetpiles or a cofferdam to protect the stability of the breakwater.
The second stability calculation aims at determining safe conditions for the quay wall construction
sequence.
1. Dredge the area of the proposed container yard and quay wall to the desired level (-27.5m
Wh, due to the required soil improvement);
2. Carefully fill the area of the container yard and quay wall with sand in layers (spraying
pontoon), compacting and finishing in a gentle slope, up to just above water level. This
process must be well-controlled and monitored. Underwater drains could be installed after
the first few metres of sand;
3. Install prefabricated vertical drains (PVD) as soon as fill height is about 1 m above water level;
4. Continue filling the area of the container yard and quay wall with sand in layers, compacting
and finishing in a 1:4 or gentler slope, up until the container yard level, and possibly above
that if preloading is necessary. This process must be well-controlled and monitored.
5. Once the natural soil has reached enough resistance and is consolidated sufficiently, dredge in
front of the quay wall down to desired dredging level (-17.5m Wh), finishing with the 1:2
slope.
For step 6, the increase in undrained shear strength (Cu) on the soft layers due to the additional
weight of the fill, combined with the consolidation due to the drains, was taken into account. This
increase is presented in Table 3-3.
Table 3-3: Soil conditions and derived parameters (P6) - increase in Cu.
Layer Classification Material Description Top Elevation [m Wh] Undrained Shear Strength Cu [kPa]
Step 5 concerns the moment when the container yard has been raised to +4m Wh, but the benefit of
consolidation has not yet been (fully) experienced by the soft layers. The model was set up taking the
soil improvement down to -27.5m Wh into account, as well as a 5m wide 15kPa load at the top of the
slope. The positive effects of settlement and strengthening of the soft layers have not been taken into
account; on the other hand, the negative effect of a potential preload to accelerate consolidation has
not been taken into account either. The calculation shows that a 1:4 slope leads to a stable situation,
with a failure mode as shown in Figure 3-7 (safety factor >1.3). Therefore, a temporary slope of 1:4 or
gentler is considered to be feasible.
Once the subsoil has gained enough strength by consolidation (accelerated by PVD and possibly
preloading), the fill can be dredged to achieve the final 1:2 slope protected by slope protection. The
slope needs to be cut in stages and each stage protected immediately after dredging, since a 1:2
underwater slope consisting of (compacted) sand is not considered to be stable for a long period. The
strength used for the soil in these calculations assumes strength increase due to consolidation, as
presented in Table 3-3.
If no soil improvement was to take place, the slope after dredging would become unstable, therefore
a slope of 1:2 is not feasible without soil improvement (SF<1,0). This situation is presented in Figure
3-8.
For a soil improvement down to -27.5m Wh, the factor of safety is the same as for a full soil
improvement (down to bedrock at -36m Wh). This situation is presented in Figure 3-9. This is why a
soil improvement down to -27.5m Wh (or deeper) is considered necessary and was modelled in the
previous steps.
Figure 3-9 – Stability during construction: step 6 - soil improvement down to -27.5m Wh.
The settlement calculation is set up to model the expected settlements in time to assess the need for
settlement-acceleration measures. Excessive residual settlement may lead to damages in the
container yard, and therefore to high maintenance costs and downtime of the yard due to frequent
repair works.
For the purposes of this calculation, construction is assumed to take two years. The residual
settlement is the settlement which occurs between end of construction and end of the design lifetime
of the container yard (50 years). Spacing and depth of PVD can be varied, in this study a triangular grid
at 1.5m centre-to-centre distance, and tip level of -35m Wh were assumed.
Firstly, the situation without any soil improvement was analysed. The existing subsoil was maintained
at -4.1 m Wh, and the container yard was filled with sand up to +4.0m Wh, without any settlement-
controlling measures being taken. As expected, this leads to very significant (residual) settlement, as
shown in Table 3-4.
Secondly, the situation with soil improvement down to -17.5m Wh was analysed. In this case, only the
natural soil under -17.5m Wh was maintained, and above that level all the way up to +4.0m Wh is
filled with sand. Using the drains and a preload during the construction period of two years leads to a
residual settlement of 10cm.
Lastly, the situation with soil improvement down to -27.5m Wh was analysed. In this case, only the
natural soil under -27.5m Wh was maintained, and above that level all the way up to +4.0m Wh is
filled with sand. Using the drains and a preload during the construction period of two years leads to a
residual settlement of 10cm.
Note: the added preload was just sufficient to achieve the 10cm of residual settlement in each case.
This means more preload was used in the -17.5m Wh case (approximately two additional metres of
sand) than in the -27.5m Wh case (approximately one additional metre of sand).
This information is summarised in Table 3-4. Figure 3-10 presents the evolution of the settlement with
time for each of the analysed situations.
Dredging in the proximity of the Sarandí breakwater poses a risk to its stability. Calculations made
based on the available information indicate that a dredging level of -17.5m Wh can only be reached at
a distance of 90m from the centreline of the breakwater (i.e. approximately 80m of its toe) with
negligible impact on the breakwater. As soon as dredging takes place closer to the breakwater, the
stability of the breakwater will be lowered compared to the current situation if no other precautions
are taken. A dredging level of -27.5m Wh, which may be necessary for the soil improvement works,
may only be reached at 130m from the centreline of the breakwater. These distances assume the
bedrock is present at -36m Wh, and may be larger if the bedrock is deeper.
If a deeper bed level is to be reached at a shorter distance to the breakwater, measures need to be
taken. For instance, a large (cofferdam) wall could be built next to the breakwater (port side), reducing
the safe distance between breakwater and berthing pocket.
For the construction of the open berth quay wall, a 1:2 sand slope is to be built. Stability with such
steep slope and a soft subsoil is difficult to achieve. Therefore, to enable the slope of 1:2 the following
construction sequence is proposed:
1. Dredge the area of the proposed container yard and quay wall to the desired level (-27.5m
Wh, due to the required soil improvement);
2. Carefully fill the area of the container yard and quay wall with sand in layers (spraying
pontoon), compacting and finishing in a gentle slope, up to just above water level. This
process must be well-controlled and monitored. Underwater drains could be installed after
the first few metres of sand;
3. Install prefabricated vertical drains (PVD) as soon as fill height is about 1 m above water level;
4. Continue filling the area of the container yard and quay wall with sand in layers, compacting
and finishing in a 1:4 or gentler slope, up until the container yard level, and possibly above
that if preloading is necessary. This process must be well-controlled and monitored.
5. Once the natural soil has reached enough resistance and is consolidated sufficiently, dredge in
front of the quay wall down to desired dredging level (-17.5m Wh), finishing with the 1:2
slope.
The indicated slopes and depth correspond to a bedrock at -36m Wh; a deeper bedrock may signify
more demanding requirements (gentler slopes, deeper soil improvement).
Calculations indicate that, by using drains and a suitable amount of preload, an acceptable residual
settlement can be achieved within two years, provided the top layers of soft soil are removed. This will
reduce maintenance costs of the container yard substantially. At the location where the bedrock is
present at -36m Wh, dredging down to -17.5m Wh is likely to be sufficient in combination with PVD
and preloading. Where the bedrock is deeper, it is possible that a higher preload and/or more
dredging is necessary, in case the lower layers are formed by soft soil.
It is noteworthy that settlement calculations are mere predictions, and that good monitoring must
take place during construction. Consolidation times may vary.