Jessore Felicity BigData Data Center Solution - V1.0
Jessore Felicity BigData Data Center Solution - V1.0
164 racks for phase 1 and 328 racks for all phases;
2
Configuration Summary
Item Phase I Phase II
Transformer
2 sets 2000kVA 1 sets 2000kVA
(dry type)
IT: 2*800KVA IT: 2*800KVA
UPS system for IT&CT CT:2*800KVA CT:2*800KVA
2N redundancy 2N redundancy
Single system: 200KVA Single system: 200KVA
Mechanical UPS
1 system, N+1 redundancy 1 system, N+1 redundancy
8 sets TP482000B 8 sets TP482000B
CT Rectifier
2N redundancy 2N redundancy
Data Hall 1: 7 CRAC Cooling(6+1 redundant) Data Hall 1: 7 CRAC Cooling(6+1 redundant)
CRAH
Data Hall 2: 7 CRAC Cooling(6+1 redundant) Data Hall 2: 7 CRAC Cooling(6+1 redundant)
3
All Phases Site Design 3D Overview
Summary:
1. 1728 sqm(71m*24m)for whole data center site.
2. Building area is 1201 sqm for DC
3. 527 sqm for Guard Room, Road and others
4. White Area:1000 sqm (two floor space for white area)
5. 14 m high for DC building
6. 50 Years lifespan for whole building
4
7. Zone 3 seismic protection.
All Phases Site Design 3D Overview
Summary:
1. 1728 sqm(71m*24m)for whole data center site.
2. Building area is 1201 sqm for DC
3. 527 sqm for Guard Room, Road and others
4. White Area:1000 sqm (two floor space for white area)
5. 14 m high for DC building
6. 50 Years lifespan for whole building
5
7. Zone 3 seismic protection.
Site Design Layout for All Phase
Ground Floor: 250 Sqm for
DG & Oil tank; DG: 4*1600kW
Thermal
Parking & Road Area: 527 Sqm Storage Tank
24 m
Chiller
5*825kW
Data Hall Phase 2 Data Hall Phase 1 Auxiliary
86 IT racks & 78 CT racks 86 IT racks & 78 CT racks Function Area
Data Hall
Totally 4 data halls in all
phases.
CT:2 data hall, totally
156 racks
IT: 2 data hall, totally 172
Power Room
racks Totally 5 power rooms, 2N
redundant.
4*800kVA UPS system 7
with 10 mins backup time.
Phase I: Ground Floor Layout
NOC
Phase II Phase I
Reception
Room Experience
Power Power Power
Centre
Room 1A Room 1B Room for
Mechanical
Generator
Room
MMR
BAT. BAT.
ELV
Room 1B Room 1A Toilet
Phase II: Ground Floor Layout
Phase II Phase I
Corridor
BAT.
Room 2A Generator
Room
Power BAT.
Power
Room 2B Room 2B
Room 2A
Phase I: First Floor Layout
Manger Meeting
office Room
Phase II Phase I
Office
MMR
ELV
Toilet
78 Racks
Phase II: First Floor Layout
Phase II Phase I
Corridor
Chiller plant
2 Chillers
78 Racks
Phase I: Second Floor Layout
Thermal
Storage Tank
Corridor
Corridor Corridor
IT: Data Hall 1B
Pump
Room
Reserved in Corridor
Phase II
86 Racks
Phase II: Second Floor Layout
Phase II Phase I
Corridor
86 Racks
Power System Topology
TR A G DG R TR C TR B
G DG 1 G DG 3 G DG 2
TR DB GCB-R TR DB TR DB
UPS UPS UPS UPS UPS ATS Other UPS UPS UPS UPS
Load
Chiller
rectifier AC PDF AC PDF rectifier rectifier AC PDF AC PDF rectifier
CRAC
AC PUMP AC
DC PDF RACK DC PDF DC PDF RACK DC PDF
DC
Phase I & II DC
RACK Mechanical RACK
Phase I Phase II
Power Subsystem | Capacity & Configuration Calculation——Phase I
Total Reactive Apparent
Rated Need Power
Category Devices Quantity Power power(Q) power(S)
Power Facter Factor
(kW) kVAR kVA
IT load 682.5 1 1 0.95 683 224.33 718.42
DCIM load 11.94 1 1 0.95 12 3.92 12.57
IT UPS charging power 68.28 1 1 0.99 68 9.73 68.97
IT UPS loss 31.28 1 1 0.99 31 4.46 31.60
ICT Load IT UPS charging power 68.28 1 1 0.99 68 9.73 68.97
CT UPS loss 28.68 1 1 0.99 29 4.09 28.97
CT Load 620 1 1 0.99 620 88.35 626.26
Rectifier charging power 0 1 1 0.99 0 0.00 0.00
Rectifier loss 31.00 1 1 0.99 31 4.42 31.31
LV system loss
15.42 1 1 0.99 15.41953 2.20 15.58
Total load 1557.37 351.21 1596.48
Reactive compensation 0.00
Capacity after compensation 0.98 1557.37 351.21 1596.48
Main circuit breaker(A) 3200
Transformer Type (kVA) 2000
T&G Final selection Generator Type PRP/DCP(kW) 1600
Transformer Actual Load Rate 80%
Generator Actual Load Rate 97%
Power Subsystem | Capacity & Configuration Calculation——Phase II
Total Reactive Apparent
Rated Need Power
Category Devices Quantity Power power(Q) power(S)
Power Facter Factor
(kW) kVAR kVA
IT load 666.5 1 1 0.95 667 219.07 701.58
DCIM load 0 1 1 0.95 0 0.00 0.00
IT UPS charging power 68.28 1 1 0.99 68 9.73 68.97
IT UPS loss 31.28 1 1 0.99 31 4.46 31.60
ICT Load IT UPS charging power 68.28 1 1 0.99 68 9.73 68.97
CT UPS loss 28.68 1 1 0.99 29 4.09 28.97
CT Load 620 1 1 0.99 620 88.35 626.26
Rectifier charging power 0 1 1 0.99 0 0.00 0.00
Rectifier loss 31.00 1 1 0.99 31 4.42 31.31
LV system loss
15.14 1 1 0.99 15.14013 2.16 15.29
Total load 1529.15 341.99 1566.93
Reactive compensation 0.00
Capacity after compensation 0.98 1529.15 341.99 1566.93
Main circuit breaker(A) 3200
Transformer Type (kVA) 2000
T&G Final selection Generator Type PRP/DCP(kW) 1600
Transformer Actual Load Rate 78%
Generator Actual Load Rate 96%
Power Subsystem | Capacity & Configuration Calculation——ME load
Reactive Apparent
Need Power Total Power
Category Devices Rated Power Quantity power(Q) power(S)
Facter Factor (kW)
kVAR kVA
A/C Power consumption 137.8 1 1 0.9 137.8 66.74 153.11
FAHU 20 1 1 0.85 20 12.39 23.53
dehumidifier 15 1 1 0.85 15 9.30 17.65
Fire damper 1 1 1 0.85 1 0.62 1.18
Chiller 1114.8 1 1 0.9 1114.8 539.92 1238.67
Mechanical Load
Chiller Water Pump 88 1 1 0.85 88 54.54 103.53
Fixed-pressure water refill device 0.5 1 1 0.9 0.5 0.24 0.56
Exhaust fan 3 1 1 0.85 3 1.86 3.53
ME UPS charging power 40.00 1 1 0.99 40 5.70 40.40
ME UPS Loss 17.37 1 1 0.99 17.36842 2.47 17.54
lighting 30 1 1 0.9 30 14.53 33.33
Firefighting 2 1 1 0.8 2 1.50 2.50
Others Sockets 10 1 0.5 0.95 5 1.64 5.26
Otherload(office+gen AUX) 80 1 1 0.9 80 38.75 88.89
LV system loss 15.59 1 1 0.99 15.59468 2.22 15.75
Total load 1570.06 752.43 1741.05
Reactive compensation 300.00
Capacity after compensation 0.96 1570.06 452.43 1633.95
Main circuit breaker(A) 3200
Transformer Type (kVA) 2000
T&G Final selection Generator Type PRP/DCP(kW) 1600
Transformer Actual Load Rate 82%
Generator Actual Load Rate 98%
Delivery time influencing factors
4. Substation ready
5. Electricity acquire ready time
6. Power supply capacity
DCIM
UPS & Battery System UPTIME Tier Certificate
(Monitor system)