ACMV Maintenance Check List
ACMV Maintenance Check List
The Contractor shall be required to carry out inspection, servicing and maintenance
of the equipment / system on campus in accordance to the maintenance schedule.
The Contractor shall adhere to the minimum frequency of the inspection, servicing
and maintenance of the equipment / system stated in the maintenance schedule and
other mandatory requirements, as recommended by the system manufacturers
and/or as required by authorities such as Singapore Civil Defence Force (SCDF),
Ministry of Manpower, local Codes of Practice, etc.
1.2 Chiller
Page | 3
S/No Check Item / Maintenance requirement Frequency
12 Operate and grease associated manual isolating butterfly valves (to Yearly
open and close fully, return to normal position)
13 Conduct oil analysis, eddy current analysis and vibration analysis Yearly
with a specialist report on the findings
14 Shutdown maintenance with manual tube cleaning including cooler Every 2
and condenser tube, check for internal abnormalities and excessive years
wear on gear, service oil pump, recalibration and re-commissioning
Page | 4
S/No Check Item / Maintenance requirement Frequency
Check condition of fan pulley, bearing, bush, shaft, blades and pins,
4 rotation, support frame, fan deck, drum and netting and report any Monthly
defects
5 Check condition of fan blade for corrosion and crack Monthly
6 Check basins and water distribution system for water leaks Monthly
Check condition of ball float, valves, inspect water level and report
7 Monthly
any defects
8 Inspect belts, adjust belt tension and replace belt if necessary (if any) Monthly
Drain or flush out cooling tower. Clean drift eliminator, infills, basins
9 Monthly
and sprinklers
10 Clean, wire brush, touch up and paint all rusty parts Monthly
11 Clean up the unit and surrounding area of the equipment Monthly
Every 3
12 Grease fan bearing sparingly
months
Check condition of fan motor, motor base, motor pulley, key, keyway, Every 3
13
set screw months
Test and record electrical insulation of all motors and wiring with
14 Yearly
megger (7.5 kW and above)
Operate and grease associated manual isolating butterfly valves (to
15 Yearly
open and close fully, return to normal position)
Page | 5
1.7 Water Tank (Includes Make-Up Water Tank and Thermal Energy Storage
(TES) Tanks)
1.8 Pumps
Page | 6
1.9 Pipe Works, Valves and Accessories
1.10 Chilled Water Air Handling Unit (AHU), Fan Coil Unit (FCU), Computer Air
Conditioning Unit (CRAU), Air Cooled Split Type, VRV Air Conditioner
Systems and DX System
General
Page | 7
1.10.1 Chilled Water Air Handling Unit (AHU)
Page | 8
1.10.3 Computer Air Conditioning Unit
Page | 9