Professional Documents
Culture Documents
M. Lasdoce DRRM Action Plan
M. Lasdoce DRRM Action Plan
CY 2022
1
SPECIFIC STRATEGY AND TIME FRAME PRSONNEL PHYSICAL RESOURCE SUCCESS
OBJECTIVE/S ACTIVITIES INVOLVED REQUIREMENT REQUIREMENT INDICATORS
Q1 Q2 Q3 Q4 AMOUNT SOURCE
100% of activities are Implementation:
implemented very 1. School safety and Principal,DRRM School Supplies Php 50.00 MOOE Activities are
satisfactorily resulting to preparedness Coordinator,Teachers Bond papers implemented very
completed DRRM. assessment. satisfactorily
2. Brigada eskwela Principal,DRRM Forms,cleaning and resulting to
School Coordinator,Teachers, painting completed
Maintenance Parents,Stakeholders materials,garden Php 50.00 MOOE DRRM.
Week. tools
8. Orientation on
2
DRRM. Principal, DRRM DRRM information Php 50.00 MOOE
Coordinator, Teacher,and materials.
Students.
SPECIFIC STRATEGY AND TIME FRAME PRSONNEL PHYSICAL RESOURCE SUCCESS INDICATORS
OBJECTIVE/S ACTIVITIES INVOLVED REQUIREMENT REQUIREMENT
Q1 Q2 Q3 Q4 AMOUNT SOURCE
100% of activities Post-implementation: 1. Principal
are implemented 1. Submission of 2. School 1. Accomplishment
very satisfactorily reports. DRRM reports and Mode of
resulting to Coordinator Php 50.00 MOOE Verifications
completed DRRM . (MOVs) submitted
to the division
office.
Q1: January- March; Q2: April-June; Q3: July- September; & Q4: October- December