ID Task Task Name Duration Start Finish Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022

Mode Jun Jul Aug Sep Oct Nov Dec Jan


1 REFURBISHMENT OF UREA 1 PRILL TOWER DURING QAFCO 1 152 days 20-07-21 19-12-21
SHUTDOWN
2 Mobilization Period 90 days 20-07-21 18-10-21
3 Contract mobilization Notification & documents 0 days 20-07-21 20-07-21 20-07
4 Mobilisation specialist manpower from outside Qatar 60 days 20-07-21 18-09-21
5 Gate pass process 14 days 18-09-21 02-10-21
6 Placing material orders [LOCALLY SUPPLIED MATERIALS] 14 days 20-07-21 03-08-21
7 Placing material orders [MATERIALS PURCHASED FROM 90 days 20-07-21 18-10-21
OVERSEAS]
8 Attending induction courses 7 days 02-10-21 09-10-21
9 Site establishment [Mobilization of cabin; stores etc.,] 3 days 09-10-21 12-10-21
10 Pre Shutdown Period 120 days 20-07-21 17-11-21
11 Present scaffolding design drawings and gain approval for erection
4 days 20-07-21 24-07-21
12 Delivery of scaffolding materials 14 days 12-10-21 26-10-21
13 Mobilize scaffolding materials to the top of Melter Floor Area 13 days 26-10-21 08-11-21
and base of Tower
14 Delivery of scaffolding materials at De-dusting level 6 days 26-10-21 01-11-21
15 Erect scaffolding at base of Tower for walls between 0.00m to 4 days 08-11-21 12-11-21
+7.00m [Job # 3]
16 Delivery of Concrete repair materials [Local] 4 days 12-10-21 16-10-21
17 Delivery of Intercrete 4840 for Wall Coating (Sea frieght) 4 days 18-10-21 22-10-21
18 Shifting materials to working platforms 5 days 12-11-21 17-11-21
19 Mobilization complete 0 days 17-11-21 17-11-21 17-11
20 QAFCO Prill Tower Shutdown Period 18 days 17-11-21 05-12-21
21 Washing process Internal of Prill Tower [QAFCO] 1 day 17-11-21 18-11-21
22 Erection of Scaffolding from Raker Plaform to + 11.00m 1.5 days 17-11-21 19-11-21
23 Protection of Fluidizing bed 1.5 days 18-11-21 19-11-21
24 Protection of Deflector Plate above Fluidizing bed 1.5 days 18-11-21 19-11-21
25 Erection of scaffolding for soffit slab 2.5 days 19-11-21 22-11-21
26 Erection of scaffolding for Walls (Internal) & Columns at 2.5 days 19-11-21 22-11-21
Dedusting Floor
27 Erection of suspended scaffolding to 4.0m - 6.0m on Prill 2.5 days 19-11-21 22-11-21
Tower Shaft Wall
28 Erection of scaffolding at lift shaft 2 days 22-11-21 24-11-21
29 Complete scaffolding erection 0 days 24-11-21 24-11-21 24-11
30 Repair of Slab soffit; Columns and Prill Tower Shaft 10 days 22-11-21 02-12-21
31 Provide Hammer Testing & Mark out repair area with 2 days 22-11-21 24-11-21
QAFCO Engineer
32 Demolition & preparation 9 days 22-11-21 01-12-21
33 Crack repairs [Sealing & Injection] 9 days 22-11-21 01-12-21
34 Application of repair mortar 9 days 23-11-21 02-12-21
35 Complete repair of slab soffit: columns and pill rower shaft 0 days 02-12-21 02-12-21 02-12
36 Walls [including base section wall from Raker Platform to 3.5 days 24-11-21 27-11-21
+11.00m]
37 Provide Hammer Testing & Mark out repair area with 0.5 days 24-11-21 24-11-21
QAFCO Engineer
38 Demolition & preparation 3 days 24-11-21 27-11-21
39 Crack repairs 3 days 24-11-21 27-11-21
Page 1
ID Task Task Name Duration Start Finish Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022
Mode Jun Jul Aug Sep Oct Nov Dec Jan
40 Application of repair mortar 2 days 25-11-21 27-11-21
41 Complete repair of Walls [including base section wall from 0 days 27-11-21 27-11-21 27-11
Raker Platform to +11.00m]
42 Base section wall from ground to + 7.00m Raker Platform] 6 days 26-11-21 02-12-21
43 Provide Hammer Testing & Mark out repair area with 1 day 26-11-21 27-11-21
QAFCO Engineer
44 Demolition & preparation 5 days 26-11-21 01-12-21
45 Crack repairs [Sealing & Injection] 5 days 26-11-21 01-12-21
46 Application of repair mortar 6 days 26-11-21 02-12-21
47 Complete repair of Base section wall from ground to + 0 days 02-12-21 02-12-21 02-12
7.00m Raker Platform]
48 Lift Shaft walls 3.5 days 30-11-21 04-12-21
49 Provide Hammer Testing & Mark out repair area with 0.5 days 30-11-21 01-12-21
QAFCO Engineer
50 Demolition & preparation 3 days 30-11-21 03-12-21
51 Crack repairs [Sealing & Injection] 3 days 30-11-21 03-12-21
52 Application of repair mortar 2 days 02-12-21 04-12-21
53 Complete repair of Lift Shaft walls 0 days 04-12-21 04-12-21 04-12
54 Application of Protective Coatings 5 days 30-11-21 05-12-21
55 Slab soffit 1.5 days 02-12-21 03-12-21
56 Slab shaft Walls & Columns 1.5 days 02-12-21 03-12-21
57 Base Section of Walls from 0.00m level to +11.00m 4 days 30-11-21 04-12-21
58 Lift Shaft walls 1 day 04-12-21 05-12-21
59 Complete applicationof Protective Coatings 0 days 05-12-21 05-12-21 05-12
60 Dismantle Scaffolding 2 days 03-12-21 05-12-21
61 Dismantle of scaffolding for columns & Shaft of Prill Tower 1 day 03-12-21 04-12-21
62 Dismantle of scaffolding for soffit / wall 1 day 03-12-21 04-12-21
63 Dismantle protection scaffold at fluidize bed 1 day 04-12-21 05-12-21
64 Complete dismantling scaffolding for columns&shaft, 0 days 05-12-21 05-12-21 05-12
soffit/wall and dismantle protection at fluidize bed
65 Post Shutdown 14 days 05-12-21 19-12-21
66 Dismantle of scaffolding at lift shaft 1 day 05-12-21 06-12-21
67 QAFCO to return Prill Tower for Working Activity 2 days 05-12-21 07-12-21
68 Clearing the debris away from site 7 days 05-12-21 12-12-21
69 Demobilize of plant, equipment & site establishments 7 days 05-12-21 12-12-21
70 Complete demobilization 0 days 12-12-21 12-12-21 12-12
71 Submission and approval of close out report 7 days 12-12-21 19-12-21
72 Project completed 0 days 19-12-21 19-12-21 19-12

Page 2