This document outlines the tasks and timeline for refurbishing a urea prill tower during a planned shutdown at a chemical plant. It involves several phases including mobilization of 90 days, pre-shutdown preparation over 120 days, scaffolding erection and repair work during an 18 day shutdown period, and post-shutdown activities over 14 days. Key activities include delivering materials, erecting scaffolding, conducting repair work like crack sealing and coating application, and dismantling scaffolding. The refurbishment is scheduled to be completed by December 19th, 2021 after a 152 day duration.
Original Description:
Baseline plan for Civil repair works for Ammonia Prill Tower
This document outlines the tasks and timeline for refurbishing a urea prill tower during a planned shutdown at a chemical plant. It involves several phases including mobilization of 90 days, pre-shutdown preparation over 120 days, scaffolding erection and repair work during an 18 day shutdown period, and post-shutdown activities over 14 days. Key activities include delivering materials, erecting scaffolding, conducting repair work like crack sealing and coating application, and dismantling scaffolding. The refurbishment is scheduled to be completed by December 19th, 2021 after a 152 day duration.
This document outlines the tasks and timeline for refurbishing a urea prill tower during a planned shutdown at a chemical plant. It involves several phases including mobilization of 90 days, pre-shutdown preparation over 120 days, scaffolding erection and repair work during an 18 day shutdown period, and post-shutdown activities over 14 days. Key activities include delivering materials, erecting scaffolding, conducting repair work like crack sealing and coating application, and dismantling scaffolding. The refurbishment is scheduled to be completed by December 19th, 2021 after a 152 day duration.
ID Task Task Name Duration Start Finish Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022
Mode Jun Jul Aug Sep Oct Nov Dec Jan
1 REFURBISHMENT OF UREA 1 PRILL TOWER DURING QAFCO 1 152 days 20-07-21 19-12-21 SHUTDOWN 2 Mobilization Period 90 days 20-07-21 18-10-21 3 Contract mobilization Notification & documents 0 days 20-07-21 20-07-21 20-07 4 Mobilisation specialist manpower from outside Qatar 60 days 20-07-21 18-09-21 5 Gate pass process 14 days 18-09-21 02-10-21 6 Placing material orders [LOCALLY SUPPLIED MATERIALS] 14 days 20-07-21 03-08-21 7 Placing material orders [MATERIALS PURCHASED FROM 90 days 20-07-21 18-10-21 OVERSEAS] 8 Attending induction courses 7 days 02-10-21 09-10-21 9 Site establishment [Mobilization of cabin; stores etc.,] 3 days 09-10-21 12-10-21 10 Pre Shutdown Period 120 days 20-07-21 17-11-21 11 Present scaffolding design drawings and gain approval for erection 4 days 20-07-21 24-07-21 12 Delivery of scaffolding materials 14 days 12-10-21 26-10-21 13 Mobilize scaffolding materials to the top of Melter Floor Area 13 days 26-10-21 08-11-21 and base of Tower 14 Delivery of scaffolding materials at De-dusting level 6 days 26-10-21 01-11-21 15 Erect scaffolding at base of Tower for walls between 0.00m to 4 days 08-11-21 12-11-21 +7.00m [Job # 3] 16 Delivery of Concrete repair materials [Local] 4 days 12-10-21 16-10-21 17 Delivery of Intercrete 4840 for Wall Coating (Sea frieght) 4 days 18-10-21 22-10-21 18 Shifting materials to working platforms 5 days 12-11-21 17-11-21 19 Mobilization complete 0 days 17-11-21 17-11-21 17-11 20 QAFCO Prill Tower Shutdown Period 18 days 17-11-21 05-12-21 21 Washing process Internal of Prill Tower [QAFCO] 1 day 17-11-21 18-11-21 22 Erection of Scaffolding from Raker Plaform to + 11.00m 1.5 days 17-11-21 19-11-21 23 Protection of Fluidizing bed 1.5 days 18-11-21 19-11-21 24 Protection of Deflector Plate above Fluidizing bed 1.5 days 18-11-21 19-11-21 25 Erection of scaffolding for soffit slab 2.5 days 19-11-21 22-11-21 26 Erection of scaffolding for Walls (Internal) & Columns at 2.5 days 19-11-21 22-11-21 Dedusting Floor 27 Erection of suspended scaffolding to 4.0m - 6.0m on Prill 2.5 days 19-11-21 22-11-21 Tower Shaft Wall 28 Erection of scaffolding at lift shaft 2 days 22-11-21 24-11-21 29 Complete scaffolding erection 0 days 24-11-21 24-11-21 24-11 30 Repair of Slab soffit; Columns and Prill Tower Shaft 10 days 22-11-21 02-12-21 31 Provide Hammer Testing & Mark out repair area with 2 days 22-11-21 24-11-21 QAFCO Engineer 32 Demolition & preparation 9 days 22-11-21 01-12-21 33 Crack repairs [Sealing & Injection] 9 days 22-11-21 01-12-21 34 Application of repair mortar 9 days 23-11-21 02-12-21 35 Complete repair of slab soffit: columns and pill rower shaft 0 days 02-12-21 02-12-21 02-12 36 Walls [including base section wall from Raker Platform to 3.5 days 24-11-21 27-11-21 +11.00m] 37 Provide Hammer Testing & Mark out repair area with 0.5 days 24-11-21 24-11-21 QAFCO Engineer 38 Demolition & preparation 3 days 24-11-21 27-11-21 39 Crack repairs 3 days 24-11-21 27-11-21 Page 1 ID Task Task Name Duration Start Finish Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022 Mode Jun Jul Aug Sep Oct Nov Dec Jan 40 Application of repair mortar 2 days 25-11-21 27-11-21 41 Complete repair of Walls [including base section wall from 0 days 27-11-21 27-11-21 27-11 Raker Platform to +11.00m] 42 Base section wall from ground to + 7.00m Raker Platform] 6 days 26-11-21 02-12-21 43 Provide Hammer Testing & Mark out repair area with 1 day 26-11-21 27-11-21 QAFCO Engineer 44 Demolition & preparation 5 days 26-11-21 01-12-21 45 Crack repairs [Sealing & Injection] 5 days 26-11-21 01-12-21 46 Application of repair mortar 6 days 26-11-21 02-12-21 47 Complete repair of Base section wall from ground to + 0 days 02-12-21 02-12-21 02-12 7.00m Raker Platform] 48 Lift Shaft walls 3.5 days 30-11-21 04-12-21 49 Provide Hammer Testing & Mark out repair area with 0.5 days 30-11-21 01-12-21 QAFCO Engineer 50 Demolition & preparation 3 days 30-11-21 03-12-21 51 Crack repairs [Sealing & Injection] 3 days 30-11-21 03-12-21 52 Application of repair mortar 2 days 02-12-21 04-12-21 53 Complete repair of Lift Shaft walls 0 days 04-12-21 04-12-21 04-12 54 Application of Protective Coatings 5 days 30-11-21 05-12-21 55 Slab soffit 1.5 days 02-12-21 03-12-21 56 Slab shaft Walls & Columns 1.5 days 02-12-21 03-12-21 57 Base Section of Walls from 0.00m level to +11.00m 4 days 30-11-21 04-12-21 58 Lift Shaft walls 1 day 04-12-21 05-12-21 59 Complete applicationof Protective Coatings 0 days 05-12-21 05-12-21 05-12 60 Dismantle Scaffolding 2 days 03-12-21 05-12-21 61 Dismantle of scaffolding for columns & Shaft of Prill Tower 1 day 03-12-21 04-12-21 62 Dismantle of scaffolding for soffit / wall 1 day 03-12-21 04-12-21 63 Dismantle protection scaffold at fluidize bed 1 day 04-12-21 05-12-21 64 Complete dismantling scaffolding for columns&shaft, 0 days 05-12-21 05-12-21 05-12 soffit/wall and dismantle protection at fluidize bed 65 Post Shutdown 14 days 05-12-21 19-12-21 66 Dismantle of scaffolding at lift shaft 1 day 05-12-21 06-12-21 67 QAFCO to return Prill Tower for Working Activity 2 days 05-12-21 07-12-21 68 Clearing the debris away from site 7 days 05-12-21 12-12-21 69 Demobilize of plant, equipment & site establishments 7 days 05-12-21 12-12-21 70 Complete demobilization 0 days 12-12-21 12-12-21 12-12 71 Submission and approval of close out report 7 days 12-12-21 19-12-21 72 Project completed 0 days 19-12-21 19-12-21 19-12