Republic of the Philippines

Department of Transportation
MACTAN-CEBU INTERNATIONAL AIRPORT AUTHORITY
Quality Management System
Airport Road, Lapu-Lapu City 6016 Philippines ISO 9001:2015
ID 85465/A/0001/UK/En

July 25, 2022

CHANGE ORDER NO.1


(Adjustment of Quantities)
Project: Supply and Installation of Taxiway Edge Lights
At General Aviation of Mactan-Cebu International Airport

Original Contract Amount: Php 67, 288, 888.09 Revised Contract Amount: Php 69, 546,325.96

VARIATION ORDER NO.1

ITEM NO. 1
(Adjustment of Quantities / Positive Variation)
Total
Item Description Quantity Unit Unit Cost Total Addition Negative
No. (Peso) (Peso) (Peso)
B TAXIWAY CENTERLINE LIGHTS
B-6 Provide and install New Secondary
cable, 600V. (Stranded) in Saw kerf. 870 m. 2, 757.13 2,398,703.10

E CABLE DUCTS, MANHOLE AND


HANDHOLES
E-2 Ductworks 2x110mm dia. PVC pipe in
sand bedding including excavation, 995 m. 2, 487.99 2, 475, 550.05
trenching, backfilling, compaction and
soil restoration.
E-3 Ductworks 4x110mm dia. PVC pipe in
concrete encasement including saw 60 m. 14, 137.08 848,224.80
cutting, asphalt/concrete pavement,
breaking, excavation, re-enforcement
steel bars, warning tape, disposal,
concrete restoration and other
necessary works to complete the work.
E-4 Ductworks 1x63mm dia. PVC pipe in
concrete/sand bedding including 426 m. 1, 848.33 787, 388.58
excavation, trenching, backfilling,
compaction, pavement/soil restoration.
E-6 Manhole Type B- complete with steel
frame and cover, ladder, cable tray 6 ea 242, 443.92 1,454,663.52
support, ground rod, drain pit, water
proofing, end bells, rock excavation,
backfilling, form works, re-enforced
steel bars and other necessary works
to complete the manhole.

Page 1 of 4
E-7 Han dhole Type B- complete with steel 5 ea 37, 337.49 186, 687.45
frame and cover, ladder, cable
support, ground rod, drain pit, end
bells and other necessary works to
complete the handhole.

F POWER SUPPLY CABLING AND


CONTROL SYSTEM
F-3 Provide and install new primary cable
no. 8.0mm² XLPE/PVC, 5KV, DEB, 937 l.m. 424.64 397,887.68
ERP/PCP insulation including
connectors, fittings and cable tags.
F-5 Provide and install new Secondary
Cable no. 4.0mm²x2, EPR/PCP, 600V, 200 l.m. 616.15 123, 230.00
including connectors and kits.

TOTAL POSITIVE VARIATION 8,672,335.18

Page 2 of 4
ITEM NO. 2
(Negative Variation)

Total Negative
Item Description Quantity Unit Unit Cost Total (Peso)
No. (Peso) Addition
(Peso)
B TAXIWAY CENTERLINE LIGHTS
B-1 Supply and Installation of New 8” 5 No. 43,151.73 215,758.65
Shallow base to suit new Lights
B-2 Conduct Core drilling/boring and 5 No. 61,244.43 306,222.15
pouring of Special Rigid Epoxy
Sealant in Asphalt Pavement
B-3 Provide and install new LED Taxiway 8 No. 155, 265.63 1, 242, 125.04
Centerline Lights fixtures (for exit
taxiway).
B-4 Provide and install isolating 14 No. 14, 565.10 203,911.40
transformer 45Watts with grounding.
B-5 Provide and install new inset edge 6 No. 148, 696.85 892, 181.10
light fixtures (for exit Taxiway).
E CABLE DUCTS, MANHOLE AND
HANDHOLE
E-1 Ductworks 1x110mm dia. PVC pipe in 775 m. 2, 064.80 1, 600, 220.00
sand bedding including excavation,
trenching, backfilling, compaction and
soil restoration.
E-5 Ductworks 32mm RSC pipe heavy 475 m. 3, 325.62 1, 579, 669.50
duty including pavement breaking, saw
cutting, chipping, asphalt/concrete
restoration and other necessary works
to complete the work.
F POWER SUPPLY CABLING AND
CONTROL SYSTEM
F-4 Provide and install new secondary 876 l.m. 334.47 292, 995.72
cable no. 5.5mm², 600V, including
connector kits and fittings.
F-6 Provide and install counterpoise earth 455 l.m. 140.25 63,813.75
ing copper wire no. 14mm² stranded
wire, including connector and fittings.
6,369,897.31
TOTAL NEGATIVE VARIATION

TOTAL AMOUNT FOR THIS CHANGE ORDER


TOTAL AMOUNT FOR POSITIVE VARIATION AMOUNT
ITEM NO.1 ADJUSTMENT OF QUANTITIES / POSITIVE VARIATION Php 8,672,335.18
LESS: ITEM NO.2 NEGATIVE VARIATION Php 6,369,897.31
TOTAL AMOUNT FOR CHANGE ORDER NO. 1 Php 2,275,437.87

Page 3 of 4
PREPARED BY: CHECKED BY:

EDUARDO G. GINETE, CE, MPSM


ROBERT A. JUABLAR, REE PMO, Project Manager
Manager, Electrical Division

NOTED:

DR. ACHILLES S. PONCE, PEE


Manager, Engineering Department

APPROVED:

JULIUS G. NERI JR.


General Manager / CEO