Download as pdf or txt
Download as pdf or txt
You are on page 1of 8

We, the Orient Energy Systems (Private) Limited are pleased to present herewith its Offer to Shifa

Internation in response to the enquiry reference mentioned hereinabove. The Offer is based on the
following documents annexed herewith and shall be read and construed as an integral part.

1. Executive Summary
2. Scope Matrix
3. Price Schedule

Sr No. Activity Project Company OES Pak Remarks

1 IMPORTED ITEMS

Supply of Solar PV
1.1 Panels  Mono-PERC PV Panels

Supply of Grid-Tied
1.2  Efficiency>98%
Inverters

Supply of DC Surge
1.3  Inverter built-in option
Arrestors

Supply of remote
1.4 
monitoring system

2 FABRICATED ITEMS

Supply of Solar PV
2.1  
Mounting Structure

Wall Bracket for


2.2 inverter and  
distribution boxes
Supply of AC Breaker
2.3 Box  

Page 1 of 8
3 BREAKERS

Supply of AC Breaker
3.1 
(Local)

4 CABLES & ACCESSORIES

Supply of DC Cables
on site with male and
4.1  Cu/XLPE/XLPE; EN-50618
female MC4
connectors

UPVC Conduit for


4.2 
DC/AC Cables

Supply of AC cable
4.3 from Inverter till LV  Stranded cable
Room

Supply of grounding
4.4  Stranded cable
cable

5 MOUNTING STRUCTURE

Supply of Mounting
5.1 
Structure

Levelling & Flooring


5.2 of location (If  
required)

Area Clearance of
5.3  
location

All tools for


5.4 installation of 
mounting and testing

Page 2 of 8
6 ENGINEERING DRAWINGS

Complete Drawings
Panel placement, civil
and manuals of the
work layout, & SLD will be
6.1 installed system and  
provided after project
equipment - hard
confirmation.
copies

Complete Drawings
Panel placement, civil
and manuals of the
work layout, & SLD will be
6.2 installed system and  
provided after project
equipment - soft
confirmation.
copies

7 MECHANICAL WORKS

Supply of bare
7.1  
copper conductors

Fire system for site


7.2 (fire extinguisher,  
alarm) (if required)

8 ELECTRICAL WORKS

Interconnection of
8.1 inverters for  
monitoring

Electricity
8.2  
connection to site

AC grid voltage
8.3  
stabilization

Page 3 of 8
Supply of Lightning
8.4  
Arrester

9 MISCELLANEOUS WORKS

Provide shade free


area for installation
9.1  
of PV Panels as per
layout

Location to install
Inverters, AC
9.2  
Combiner Box &
other equipment

Site engineer for


9.3  
System Monitoring

Regular Cleaning of
9.4 PV Modules after  
Project handover

Internet facility at
9.5  
site for monitoring

Warehousing and
9.6 Security of Supplied  
items till execution

Furnished Site Office


9.7 (Air  
Condition/Heater)

Page 4 of 8
Electricity, water and
9.8 sanitary facilities in  
site office

Security of site and


9.9  
residential area

Access to works site


9.10 for execution and  
completion of works

Entry gate passes at


9.11 works site for staff  
and workers

10 CIVIL WORKS

Construction of
10.1  
grounding pits

11 PROCUREMENT & TRANSPORTATION

11.1 PI for imported items  

Opening of LC for
11.2  
imported items

11.3 Clearance for goods  

Page 5 of 8
Inland transportation
11.4 of equipment to the  
site

Provide time of
arrival, details of
11.5  
driver and timely
delivery

Offloading of all the


11.6 equipment delivered  
on site

Movement of
Equipment from
11.7  
customer warehouse
to site

In transit Insurance
of equipment from
11.8  
port of discharge to
the site

Inspection of the
11.9 equipment after  
reaching the site

12 COMMISSIONING

Testing of string,
12.1  
Inverter voltages,

Pre-execution
12.2 checklist and  
commissioning form

Page 6 of 8
Complete testing and
12.3 verification of solar  
system

Startup and
12.4 commissioning of  
solar system

Training of complete
solar system to
12.6 customer utility  
manager

Troubleshooting in
12.7  
case of any faults

ARTICLE 3 - PRICE SCHEDULE

Bill of Material (622.935 KW)

3.1 IMPORTED EQUIPMENT/MATERIAL:


Imported Items

S.No Items Make Model Qty


1 Solar Panels Jinko/JA JKM545M-72HL4-V
1,143
2 Spare Solar Panels Jinko/JA JKM545M-72HL4-V
4
3 Inverter Sungrow SG 110CX
5
4 Monitoring Device Sungrow COMM 100
1
5 Environment Ingenieuroburo Weather Station
Monitoring System 1
6 DC Cables Kuka/Jukai/Huldon Tinned CU XLPE/XLPE
5,000

Page 7 of 8
Page 8 of 8

You might also like