27-Dec-21 23:48
South Kuwait Excavation Transportation & Remediation
(Zone 3)

Activity ID Activity Name Original Activity % Start Finish


Duration Complete

907.00d 03-Oct-21 19-Nov-24


SKETR Zone 3 South Kuwait Excavation, Transportation & Remediation Project (Zone 3)
0.00d 03-Oct-21 03-Oct-21 03-Oct-21, SKETR Zone 3.1 GENERAL
SKETR Zone 3.1 GENERAL
A1000 Contract Signing 0.00d 0% 03-Oct-21* Contract Signing, 03-Oct-21*
SKETR Zone 3.2 MILESTONES 907.00d 03-Oct-21 19-Nov-24

A1010 Contractual Preliminaries Start 0.00d 0% 03-Oct-21 Contractual Preliminaries Start, 03-Oct-21
A1030 Work Related Preliminaries Start 0.00d 0% 03-Oct-21 Work Related Preliminaries Start, 03-Oct-21
A1060 Portion 1A Commencement 0.00d 0% 03-Oct-21 Portion 1A Commencement, 03-Oct-21
A1020 Contractual Preliminaries End 0.00d 0% 09-Nov-21 Contractual Preliminaries End,
A1040 Work Related Preliminaries End 0.00d 0% 15-Jan-22 Work Related Preliminaries End,
A1052 Mobilisation Finish 0.00d 0% 15-Jan-22 Mobilisation Finish,
A1041 Temporary Works and Enabling Works Start 0.00d 0% 16-Jan-22 Temporary Works and Enabling Works Start, 16-Jan-22
A1042 Temporary Works and Enabling Works End 0.00d 0% 16-Apr-22 Temporary Works and Enabling Works End,
A1070 Portion 1A Finish 0.00d 0% 30-Apr-22 Portion 1A Finish,
A1080 Portion 1B Commencement 0.00d 0% 01-May-22 Portion 1B Commencement, 01-May-22
A1090 Portion 1B Finish 0.00d 0% 31-Aug-23 Portion 1B Finish,
A1570 Completion of Project 0.00d 0% 19-Nov-24
621.00d 03-Oct-21 05-Dec-23 05-Dec-23, SKETR Zone 3.3 PORTION 1A
SKETR Zone 3.3 PORTION 1A
SKETR Zone 3.3.1 CONTRACTUAL PRELIMINARIES 30.00d 03-Oct-21 09-Nov-21 09-Nov-21, SKETR Zone 3.3.1 CONTRACTUAL PRELIMINARIES

SKETR Zone 3.3.1.1 Bonds and Guarantees 30.00d 03-Oct-21 09-Nov-21 09-Nov-21, SKETR Zone 3.3.1.1 Bonds and Guarantees

A1100 Furnish Performance Bond 30.00d 0% 03-Oct-21 09-Nov-21 Furnish Performance Bond
SKETR Zone 3.3.1.2 Insurances 30.00d 03-Oct-21 09-Nov-21 09-Nov-21, SKETR Zone 3.3.1.2 Insurances

A1110 Furnish Erection All Risks Insurance Policy (Optional) 30.00d 0% 03-Oct-21 09-Nov-21 Furnish Erection All Risks Insurance Policy (Optional)
A1120 Furnish General Third Party Liability Policy (Optional) 30.00d 0% 03-Oct-21 09-Nov-21 Furnish General Third Party Liability Policy (Optional)
A1130 Furnish Workmen’s Compensation Insurance Policy 30.00d 0% 03-Oct-21 09-Nov-21 Furnish Workmen’s Compensation Insurance Policy
SKETR Zone 3.3.2 WORK RELATED PRELIMINARIES 621.00d 03-Oct-21 05-Dec-23 05-Dec-23, SKETR Zone 3.3.2 WORK RELATED PRELIMINARIES

44.00d
SKETR Zone 3.3.2.1 Project Plans, Work Method Statements 03-Oct-21 25-Nov-21 25-Nov-21, SKETR Zone 3.3.2.1 Project Plans, Work Method Statements

A1140 Preparation and submission of Project Execution Plan 30.00d 0% 03-Oct-21 09-Nov-21 Preparation and submission of Project Execution Plan
A1160 Preparation and submission of HSE Plan 30.00d 0% 03-Oct-21 09-Nov-21 Preparation and submission of HSE Plan
A1180 Preparation and submission of QAQC & Inspection Test Plan 30.00d 0% 03-Oct-21 09-Nov-21 Preparation and submission of QAQC & Inspection Test Plan
A1200 Preparation and submission of Work Method Statements & Job30.00d
Safety Analysis0% 03-Oct-21 09-Nov-21 Preparation and submission of Work Method Statements & Job Safety Analysis
A1220 Preparation and submission of UXO Risk Assessment Report 30.00d 0% 03-Oct-21 09-Nov-21 Preparation and submission of UXO Risk Assessment Report
A1150 Approval of Project Execution Plan 14.00d 0% 10-Nov-21 25-Nov-21 Approval of Project Execution Plan
A1170 Approval of HSE Plan 14.00d 0% 10-Nov-21 25-Nov-21 Approval of HSE Plan
A1190 Approval of QAQC & Inspection Test Plan 14.00d 0% 10-Nov-21 25-Nov-21 Approval of QAQC & Inspection Test Plan
A1210 Approval of Work Method Statements & Job Safety Analysis 14.00d 0% 10-Nov-21 25-Nov-21 Approval of Work Method Statements & Job Safety Analysis
A1230 Approval of UXO Risk Assessment Report 14.00d 0% 10-Nov-21 25-Nov-21 Approval of UXO Risk Assessment Report
SKETR Zone 3.3.2.2 Mobilisation of labour resources 82.00d 03-Oct-21 12-Jan-22 12-Jan-22, SKETR Zone 3.3.2.2 Mobilisation of labour resources

A1240 Application of Visa quota 14.00d 0% 03-Oct-21 20-Oct-21 Application of Visa quota
A1260 Preparation and submission of Key Personnel for Company approval
14.00d 0% 03-Oct-21 20-Oct-21 Preparation and submission of Key Personnel for Company approval
A1250 Issuance of Visa quota 14.00d 0% 21-Oct-21 07-Nov-21 Issuance of Visa quota
A1270 Approval of Key Personnel 14.00d 0% 21-Oct-21 07-Nov-21 Approval of Key Personnel
A1280 Mobilisation of Key Personnel 40.00d 0% 08-Nov-21 25-Dec-21 Mobilisation of Key Personnel
A1290 Mobilisation of other project personnel 40.00d 0% 08-Nov-21 25-Dec-21 Mobilisation of other project personnel
A1300 Application of personnel gate passes 7.00d 0% 26-Dec-21 04-Jan-22 Application of personnel gate passes
A1320 Worksite Supervisor training and test by Company 7.00d 0% 26-Dec-21 04-Jan-22 Worksite Supervisor training and test by Company
A1330 FirstAider Training by 3rd Party Provider 7.00d 0% 26-Dec-21 04-Jan-22 FirstAider Training by 3rd Party Provider
A1340 Defensive Driving Training by 3rd Party 7.00d 0% 26-Dec-21 04-Jan-22 Defensive Driving Training by 3rd Party
A1310 Receipt of personnel gate passes 7.00d 0% 05-Jan-22 12-Jan-22 Receipt of personnel gate passes
SKETR Zone 3.3.2.3 Mobilisation of non-labour resources 84.00d 03-Oct-21 15-Jan-22 15-Jan-22, SKETR Zone 3.3.2.3 Mobilisation of non-labour resources

Actual Level of Effort Primary Baseline Actual Work Re...


  27-Dec-21 23:48
South Kuwait Excavation Transportation & Remediation
(Zone 3)

Activity ID Activity Name Original Activity % Start Finish


Duration Complete

A1350 Purchase of equipment 60.00d 0% 03-Oct-21 15-Dec-21 Purchase of equipment


A1370 Submission of PPE for approval by Company 7.00d 0% 03-Oct-21 10-Oct-21 Submission of PPE for approval by Company
A1400 Purchase of Tools and Materials 30.00d 0% 03-Oct-21 09-Nov-21 Purchase of Tools and Materials
A1420 Leasing, fabrication & armoring of heavy equipment 70.00d 0% 03-Oct-21 27-Dec-21 Leasing, fabrication & armoring of heavy equipment
A1380 Approval of PPE 14.00d 0% 11-Oct-21 28-Oct-21 Approval of PPE
A1410 Leasing of Vehicles 7.00d 0% 14-Dec-21 21-Dec-21 Leasing of Vehicles
A1360 Arrival and testing of equipment 14.00d 0% 26-Dec-21 12-Jan-22 Arrival and testing of equipment
A1390 Purchase of PPE 7.00d 0% 26-Dec-21 04-Jan-22 Purchase of PPE
A1430 Request for Inspection of armoring 10.00d 0% 28-Dec-21 10-Jan-22 Request for Inspection of armoring
A1440 Inspection and approval of armoring 10.00d 0% 28-Dec-21 10-Jan-22 Inspection and approval of armoring
A1450 Application of vehicle and heavy equipment gate passes 7.00d 0% 28-Dec-21 06-Jan-22 Application of vehicle and heavy equipment gate passes
A1460 Receipt of vehicle and heavy equipment gate passes 7.00d 0% 08-Jan-22 15-Jan-22 Receipt of vehicle and heavy equipment gate passes
SKETR Zone 3.3.2.4 Demobilisation of resources 26.00d 05-Nov-23 05-Dec-23 05-Dec-23, SKETR Zone 3.3.2.4 Demobilisation of resources

A2040 Demobilisation of Personnel, Vehicles and Equipment from Site


26.00d 0% 05-Nov-23 05-Dec-23 Demobilisation of Personnel, Vehicles and Equipment from Site
428.00dGIS Database:
SKETR Zone 3.3.2.5 UXO Project Final Reports including Project 01-May-22 02-Nov-23
For GIS + Geophysical Survey + Clearance 02-Nov-23, SKETR Zone 3.3.2.5 UXO Project Final Reports including Project GIS Data

A1470 Preparation & submission of UXO Final Reports 414.00d 0% 01-May-22 17-Oct-23 Preparation & submission of UXO Final Reports
A1480 Review and approval of UXO Final Reports 414.00d 0% 23-May-22 02-Nov-23 Review and approval of UXO Final Reports
65.00d
SKETR Zone 3.3.4 TEMPORARY WORKS AND ENABLING WORKS 16-Jan-22 09-Apr-22 09-Apr-22, SKETR Zone 3.3.4 TEMPORARYWORKS AND ENABLING WORKS

SKETR Zone 3.3.4.1 Ground Truthing of DOL 65.00d 16-Jan-22 09-Apr-22 09-Apr-22, SKETR Zone 3.3.4.1 Ground Truthing of DOL

A1490 Anomaly Avoidance Team Support for Ground Truthing activities


65.00d 0% 16-Jan-22 09-Apr-22 Anomaly Avoidance Team Support for Ground Truthing activities
A1500 Inspection and approval of 1st batch of GT Report by Company65.00d 0% 16-Jan-22 09-Apr-22 Inspection and approval of 1st batch of GT Report by Company
SKETR Zone 3.3.4.2 Ground Truthing of WOL 65.00d 16-Jan-22 09-Apr-22 09-Apr-22, SKETR Zone 3.3.4.2 Ground Truthing of WOL

A1510 Anomaly Avoidance Team Support for Ground Truthing activities


65.00d 0% 16-Jan-22 09-Apr-22 Anomaly Avoidance Team Support for Ground Truthing activities
A1520 Inspection and approval of 1st batch of GT Report by Company65.00d 0% 16-Jan-22 09-Apr-22 Inspection and approval of 1st batch of GT Report by Company
SKETR Zone 3.3.4.3 Pre-Topographical Survey of OCP 65.00d 16-Jan-22 09-Apr-22 09-Apr-22, SKETR Zone 3.3.4.3 Pre-Topographical Survey of OCP

A1530 Anomaly Avoidance Team Support for Pre-Topo Survey activities


65.00d 0% 16-Jan-22 09-Apr-22 Anomaly Avoidance Team Support for Pre-Topo Survey activities
A1540 Inspection and approval of 1st batch of Pre-Topo Report by Company
65.00d 0% 16-Jan-22 09-Apr-22 Inspection and approval of 1st batch of Pre-Topo Report by Company
SKETR Zone 3.3.4.4 Soil Characterization 65.00d 16-Jan-22 09-Apr-22 09-Apr-22, SKETR Zone 3.3.4.4 Soil Characterization

A1550 Anomaly Avoidance Team Support for Soil Characterization activities


65.00d 0% 16-Jan-22 09-Apr-22 Anomaly Avoidance Team Support for Soil Characterization activities
A1560 Inspection and approval of 1st batch of Soil Characterization Report
65.00dby Company
0% 16-Jan-22 09-Apr-22 Inspection and approval of 1st batch of Soil Characterization Report by Company
SKETR Zone 3.3.3 UXO SURVEY AND CLEARANCE 83.00d 16-Jan-22 30-Apr-22 30-Apr-22, SKETR Zone 3.3.3 UXO SURVEYAND CLEARANCE

83.00d
SKETR Zone 3.3.3.1 UXO Survey and Clearance for Non-Contaminated Soils16-Jan-22 30-Apr-22
(BAC Methodology) 30-Apr-22, SKETR Zone 3.3.3.1 UXO Survey and Clearance for Non-Contaminated Soils (BAC Methodology)

A1580 Setting up and conduct of Detector Prove-out 3.00d 0% 16-Jan-22 18-Jan-22 Setting up and conduct of Detector Prove-out
A1590 Boundary marking with anomaly avoidance 65.00d 0% 16-Jan-22 09-Apr-22 Boundary marking with anomaly avoidance
A1585 Setting up of Instrument Verification TestArea (IVTA) 1.00d 0% 19-Jan-22 19-Jan-22 Setting up of Instrument Verification TestArea (IVTA)
A1600 Battle Area Clearance (Mag & Dig) 65.00d 0% 23-Jan-22 16-Apr-22 Battle Area Clearance (Mag & Dig)
A1610 Retrieval, transportation & storage of safe-to-move UXO 65.00d 0% 23-Jan-22 16-Apr-22 Retrieval, transportation & storage of safe-to-move UXO
A1620 In-situ or Ex-situ disposal of UXO by KMOD 65.00d 0% 23-Jan-22 16-Apr-22 In-situ or Ex-situ disposal of UXO by KMOD
A1630 Internal Quality Control checks 65.00d 0% 26-Jan-22 19-Apr-22 Internal Quality Control checks
A1640 Request for Inspection of Interim Clearance Certificates (ICC) 65.00d 0% 02-Feb-22 26-Apr-22 Request for Inspection of Interim Clearance Certificates (ICC)
A1650 Inspection and approval of ICC by Company 65.00d 0% 07-Feb-22 30-Apr-22 Inspection and approval of ICC by Company
A1660 Backfilling of excavated voids 65.00d 0% 07-Feb-22 30-Apr-22 Backfilling of excavated voids
A1670 Certify Free From Explosives (FFE) and separation of construction
65.00d
and waste debris
0% 07-Feb-22
for disposal 30-Apr-22 Certify Free From Explosives (FFE) and separation of construction and waste debris for disposal
83.00d
SKETR Zone 3.3.3.2 UXO Survey and Clearance for Non-Contaminated Soils16-Jan-22 30-Apr-22
(DGM Methodology) 30-Apr-22, SKETR Zone 3.3.3.2 UXO Survey and Clearance for Non-Contaminated Soils (DGM Methodology)

A2080 Setting up of Geophysical Prove-out (GPO) 7.00d 0% 16-Jan-22 23-Jan-22 Setting up of Geophysical Prove-out (GPO)
A2090 Setting up of Instrument Verification Strip (IVS) 1.00d 0% 24-Jan-22 24-Jan-22 Setting up of Instrument Verification Strip (IVS)
A2085 Submission and Approval of GPO Letter Report by Company 14.00d 0% 24-Jan-22 09-Feb-22 Submission and Approval of GPO Letter Report by Company
A2095 Submission and Approval of IVS Letter Report by Company 14.00d 0% 25-Jan-22 10-Feb-22 Submission and Approval of IVS Letter Report by Company
A2100 DGM Survey 30.00d 0% 12-Feb-22 23-Mar-22 DGM Survey
A2102 Data processing and development of target list 30.00d 0% 13-Feb-22 24-Mar-22 Data processing and development of target list

Actual Level of Effort Primary Baseline Actual Work Re...


  27-Dec-21 23:48
South Kuwait Excavation Transportation & Remediation
(Zone 3)

Activity ID Activity Name Original Activity % Start Finish


Duration Complete

A2104 Submission of processed data and target list for approval by Company
30.00d 0% 16-Feb-22 28-Mar-22 Submission of processed data and target list for approval by Company
A2106 Target Reacquisition 30.00d 0% 10-Mar-22 14-Apr-22 Target Reacquisition
A2108 Intrusive Investigation 30.00d 0% 12-Mar-22 16-Apr-22 Intrusive Investigation
A2110 Retrieval, transportation & storage of safe-to-move UXO 30.00d 0% 13-Mar-22 17-Apr-22 Retrieval, transportation & storage of safe-to-move UXO
A2120 In-situ or Ex-situ disposal of UXO by KMOD 30.00d 0% 13-Mar-22 17-Apr-22 In-situ or Ex-situ disposal of UXO by KMOD
A2130 Internal Quality Control checks 30.00d 0% 15-Mar-22 19-Apr-22 Internal Quality Control checks
A2140 Request for Inspection of Interim Clearance Certificates (ICC) 30.00d 0% 22-Mar-22 26-Apr-22 Request for Inspection of Interim Clearance Certificates (ICC)
A2150 Inspection and approval of ICC by Company 30.00d 0% 26-Mar-22 30-Apr-22 Inspection and approval of ICC by Company
A2160 Backfilling of excavated voids 30.00d 0% 26-Mar-22 30-Apr-22 Backfilling of excavated voids
A2170 Certify Free From Explosives (FFE) and separation of construction
30.00d
and waste debris
0% 26-Mar-22
for disposal 30-Apr-22 Certify Free From Explosives (FFE) and separation of construction and waste debris for disposal
SKETR Zone 3.4 PORTION 1B 823.00d 16-Jan-22 19-Nov-24

SKETR Zone 3.4.1 ENABLING WORKS 823.00d 16-Jan-22 19-Nov-24

SKETR Zone 3.4.1.1 SURVEY OF UTILITIES 71.00d 16-Jan-22 16-Apr-22 16-Apr-22, SKETR Zone 3.4.1.1 SURVEY OF UTILITIES

A1680 Construction Support for Slit Trenching activities 71.00d 0% 16-Jan-22 16-Apr-22 Construction Support for Slit Trenching activities
A1690 Inspection and approval of Services Survey Report by Company
71.00d 0% 16-Jan-22 16-Apr-22 Inspection and approval of Services Survey Report by Company
SKETR Zone 3.4.1.2 POST-TOPOGRAPHIC SURVEY 358.00d 19-Apr-22 26-Jul-23 26-Jul-23, SKETR Zone 3.4.1.2 POST-TOPOGRAPHIC SURVEY

A1700 Post-Topographic Survey 358.00d 0% 19-Apr-22 26-Jul-23 Post-Topographic Survey


A1710 Inspection and approval of Post-Topo Report by Company 358.00d 0% 19-Apr-22 26-Jul-23 Inspection and approval of Post-Topo Report by Company
SKETR Zone 3.4.1.3 UXO Survey and Clearance for Dry Oil347.00d
Lakes (DOL) and10-Apr-22 26-Jun-23
OCP Footprints (BAC Methodology) 26-Jun-23, SKETR Zone 3.4.1.3 UXO Survey and Clearance for Dry Oil Lakes (DOL) and OCP Footprints (B

A1730 Boundary marking with anomaly avoidance 328.00d 0% 10-Apr-22 04-Jun-23 Boundary marking with anomaly avoidance
A1720 Setting up of Instrument Verification TestArea (IVTA) 1.00d 0% 17-Apr-22 17-Apr-22 Setting up of Instrument Verification TestArea (IVTA)
A1740 Battle Area Clearance (Mag & Dig) 328.00d 0% 18-Apr-22 12-Jun-23 Battle Area Clearance (Mag & Dig)
A1750 Retrieval, transportation & storage of safe-to-move UXO 328.00d 0% 18-Apr-22 12-Jun-23 Retrieval, transportation & storage of safe-to-move UXO
A1760 In-situ or Ex-situ disposal of UXO by KMOD 328.00d 0% 18-Apr-22 12-Jun-23 In-situ or Ex-situ disposal of UXO by KMOD
A1770 Internal Quality Control checks 328.00d 0% 21-Apr-22 15-Jun-23 Internal Quality Control checks
A1780 Request for Inspection of Interim Clearance Certificates (ICC) 328.00d 0% 28-Apr-22 22-Jun-23 Request for Inspection of Interim Clearance Certificates (ICC)
A1790 Inspection and approval of ICC by Company 328.00d 0% 08-May-22 26-Jun-23 Inspection and approval of ICC by Company
A1800 Backfilling of excavated voids 328.00d 0% 08-May-22 26-Jun-23 Backfilling of excavated voids
A1810 Certify Free From Explosives (FFE) and separation of construction
328.00d
and waste debris
0% 08-May-22
for disposal 26-Jun-23 Certify Free From Explosives (FFE) and separation of construction and waste debris for disposal
SKETR Zone 3.4.1.4 UXO Survey and Clearance for Dry Oil360.00d
Lakes (DOL) and24-Mar-22 26-Jun-23
OCP Footprints (DGM Methodology) 26-Jun-23, SKETR Zone 3.4.1.4 UXO Survey and Clearance for Dry Oil Lakes (DOL) and OCP Footprints (D

A2210 Setting up of Instrument Verification Strip (IVS) 1.00d 0% 24-Mar-22 24-Mar-22 Setting up of Instrument Verification Strip (IVS)
A2220 Submission and Approval of IVS Letter Report by Company 14.00d 0% 26-Mar-22 11-Apr-22 Submission and Approval of IVS Letter Report by Company
A2230 DGM Survey 310.00d 0% 17-Apr-22 20-May-23 DGM Survey
A2240 Data processing and development of target list 310.00d 0% 18-Apr-22 21-May-23 Data processing and development of target list
A2250 Submission of processed data and target list for approval by Company
310.00d 0% 21-Apr-22 24-May-23 Submission of processed data and target list for approval by Company
A2260 Target Reacquisition 310.00d 0% 14-May-22 11-Jun-23 Target Reacquisition
A2270 Intrusive Investigation 310.00d 0% 15-May-22 12-Jun-23 Intrusive Investigation
A2280 Retrieval, transportation & storage of safe-to-move UXO 310.00d 0% 16-May-22 13-Jun-23 Retrieval, transportation & storage of safe-to-move UXO
A2290 In-situ or Ex-situ disposal of UXO by KMOD 310.00d 0% 16-May-22 13-Jun-23 In-situ or Ex-situ disposal of UXO by KMOD
A2300 Internal Quality Control checks 310.00d 0% 18-May-22 15-Jun-23 Internal Quality Control checks
A2310 Request for Inspection of Interim Clearance Certificates (ICC) 310.00d 0% 25-May-22 22-Jun-23 Request for Inspection of Interim Clearance Certificates (ICC)
A2320 Inspection and approval of ICC by Company 310.00d 0% 29-May-22 26-Jun-23 Inspection and approval of ICC by Company
A2330 Backfilling of excavated voids 310.00d 0% 29-May-22 26-Jun-23 Backfilling of excavated voids
A2340 Certify Free From Explosives (FFE) and separation of construction
310.00d
and waste debris
0% 29-May-22
for disposal 26-Jun-23 Certify Free From Explosives (FFE) and separation of construction and waste debris for disposal
253.00d
SKETR Zone 3.4.1.5 UXO Survey and Clearance for Wet Oil 10-Apr-22
Lakes (WOL) (BAC 28-Feb-23
Methodology) 28-Feb-23, SKETR Zone 3.4.1.5 UXO Survey and Clearance for Wet Oil Lakes (WOL) (BAC Methodology)

A1830 Boundary marking with anomaly avoidance 229.00d 0% 10-Apr-22 26-Jan-23 Boundary marking with anomaly avoidance
A1820 Setting up of Instrument Verification TestArea (IVTA) 1.00d 0% 17-Apr-22 17-Apr-22 Setting up of Instrument Verification TestArea (IVTA)
A1840 Preparation by mixing, displacement and/or trenching 229.00d 0% 17-Apr-22 02-Feb-23 Preparation by mixing, displacement and/or trenching
A1850 Battle Area Clearance (Mag & Dig) 229.00d 0% 24-Apr-22 11-Feb-23 Battle Area Clearance (Mag & Dig)
A1860 Retrieval, transportation & storage of safe-to-move UXO 229.00d 0% 24-Apr-22 11-Feb-23 Retrieval, transportation & storage of safe-to-move UXO

Actual Level of Effort Primary Baseline Actual Work Re...


  27-Dec-21 23:48
South Kuwait Excavation Transportation & Remediation
(Zone 3)

Activity ID Activity Name Original Activity % Start Finish


Duration Complete

A1870 In-situ or Ex-situ disposal of UXO by KMOD 229.00d 0% 24-Apr-22 11-Feb-23 In-situ or Ex-situ disposal of UXO by KMOD
A1880 Internal Quality Control checks 229.00d 0% 27-Apr-22 14-Feb-23 Internal Quality Control checks
A1890 Request for Inspection of Interim Clearance Certificates (ICC) 229.00d 0% 10-May-22 22-Feb-23 Request for Inspection of Interim Clearance Certificates (ICC)
A1900 Inspection and approval of ICC by Company 229.00d 0% 14-May-22 28-Feb-23 Inspection and approval of ICC by Company
A1910 Backfilling of excavated voids 229.00d 0% 14-May-22 28-Feb-23 Backfilling of excavated voids
A1920 Certify Free From Explosives (FFE) and separation of construction
229.00d
and waste debris
0% 14-May-22
for disposal 28-Feb-23 Certify Free From Explosives (FFE) and separation of construction and waste debris for disposal
266.00d
SKETR Zone 3.4.1.6 UXO Survey and Clearance for Wet Oil 24-Mar-22
Lakes (WOL) (DGM 28-Feb-23
Methodology) 28-Feb-23, SKETR Zone 3.4.1.6 UXO Survey and Clearance for Wet Oil Lakes (WOL) (DGM Methodology)

A2360 Setting up of Instrument Verification Strip (IVS) 1.00d 0% 24-Mar-22 24-Mar-22 Setting up of Instrument Verification Strip (IVS)
A2370 Submission and Approval of IVS Letter Report by Company 14.00d 0% 26-Mar-22 11-Apr-22 Submission and Approval of IVS Letter Report by Company
A2380 DGM Survey 216.00d 0% 17-Apr-22 18-Jan-23 DGM Survey
A2390 Data processing and development of target list 216.00d 0% 18-Apr-22 19-Jan-23 Data processing and development of target list
A2400 Submission of processed data and target list for approval by Company
216.00d 0% 21-Apr-22 23-Jan-23 Submission of processed data and target list for approval by Company
A2410 Target Reacquisition 216.00d 0% 14-May-22 09-Feb-23 Target Reacquisition
A2420 Intrusive Investigation 216.00d 0% 15-May-22 11-Feb-23 Intrusive Investigation
A2430 Retrieval, transportation & storage of safe-to-move UXO 216.00d 0% 16-May-22 12-Feb-23 Retrieval, transportation & storage of safe-to-move UXO
A2440 In-situ or Ex-situ disposal of UXO by KMOD 216.00d 0% 16-May-22 12-Feb-23 In-situ or Ex-situ disposal of UXO by KMOD
A2450 Internal Quality Control checks 216.00d 0% 18-May-22 14-Feb-23 Internal Quality Control checks
A2460 Request for Inspection of Interim Clearance Certificates (ICC) 216.00d 0% 25-May-22 22-Feb-23 Request for Inspection of Interim Clearance Certificates (ICC)
A2470 Inspection and approval of ICC by Company 216.00d 0% 29-May-22 28-Feb-23 Inspection and approval of ICC by Company
A2480 Backfilling of excavated voids 216.00d 0% 29-May-22 28-Feb-23 Backfilling of excavated voids
A2490 Certify Free From Explosives (FFE) and separation of construction
216.00d
and waste debris
0% 29-May-22
for disposal 28-Feb-23 Certify Free From Explosives (FFE) and separation of construction and waste debris for disposal
396.00d
SKETR Zone 3.4.1.7 UXO Survey and Clearance for Oil Contaminated 10-Apr-22
Piles (OCP) 31-Aug-23
(BAC Methodology) 31-Aug-23, SKETR Zone 3.4.1.7 UXO Survey and Clearance for Oil Contaminated Piles (OCP) (

A1940 Preparation by laying of soil plots 386.00d 0% 10-Apr-22 20-Aug-23 Preparation by laying of soil plots
A1930 Setting up of Instrument Verification TestArea (IVTA) 1.00d 0% 17-Apr-22 17-Apr-22 Setting up of Instrument Verification TestArea (IVTA)
A1950 Battle Area Clearance (Mag & Dig) 386.00d 0% 18-Apr-22 28-Aug-23 Battle Area Clearance (Mag & Dig)
A1960 Retrieval, transportation & storage of safe-to-move UXO 386.00d 0% 18-Apr-22 28-Aug-23 Retrieval, transportation & storage of safe-to-move UXO
A1970 In-situ or Ex-situ disposal of UXO by KMOD 386.00d 0% 18-Apr-22 28-Aug-23 In-situ or Ex-situ disposal of UXO by KMOD
A1980 Internal Quality Control checks 386.00d 0% 19-Apr-22 29-Aug-23 Internal Quality Control checks
A1990 Request for Inspection of Interim Safety Certificates 386.00d 0% 20-Apr-22 30-Aug-23 Request for Inspection of Interim Safety Certificates
A2000 Inspection and approval of Interim Safety Certificates by Company
386.00d 0% 21-Apr-22 31-Aug-23 Inspection and approval of Interim Safety Certificates by Company
A2020 Certify Free From Explosives (FFE) and separation of construction
386.00d
and waste debris
0% 21-Apr-22
for disposal 31-Aug-23 Certify Free From Explosives (FFE) and separation of construction and waste debris for disposal
823.00d
SKETR Zone 3.4.1.8 Anomaly Avoidance, Construction Support & Escort 16-Jan-22 19-Nov-24
A2030 Provision of Construction Support Teams 71.00d 0% 16-Jan-22 16-Apr-22 Provision of Construction Support Teams
A2050 Provision of Anomal Avoidance Teams 118.00d 0% 16-Jan-22 16-Jun-22 Provision of Anomal Avoidance Teams
A2060 Provision of Escort 823.00d 0% 16-Jan-22* 19-Nov-24

Actual Level of Effort Primary Baseline Actual Work Re...