RENCANA ANGGARAN BIAYA

Pembangunan stone Cruser lokasi AIK

NO. URAIAN PEKERJAAN SATUAN HARGA SATUAN JUMLAH HARGA


VOLUME
[Rp.] [Rp.]
A. STRUKTUR
Pekerjaan Pondasi
1. pondasi tiang conveyor
a. besi beton KG 25 15,000.00 375,000.00
b. beton K-250 M3 3 1,950,000.00 5,850,000.00
c. bekesting M2 2.8 255,000.00 714,000.00
d. Baut angkur Buah 8 85,000.00 680,000.00

SUB TOTAL - A 1 7,619,000.00

B. PART STONE CRUSHER


Hopper dan jaws primer
pemasangan hooper stone crusher
1. UNP 200 M 57.2 250,000.00 14,300,000.00
UNP 150 M 9.84 142,000.00 1,397,280.00
UNP 65 M 6 65,000.00 390,000.00
Plat Strip 6 MM M2 5.76 560,000.00 3,225,600.00
PLAT Baja Hitam 10 MM M2 8.64 1,600,000.00 13,824,000.00
Plat Baja 8MM M2 14.09 1,050,000.00 14,794,500.00
Besi Siku 65 MM M 20 100,000.00 2,000,000.00
H-BEAM 300 M 12 2,375,000.00 28,500,000.00
BAUT 3/8 Buah 30 18,000.00 540,000.00
Pengelasan dan Erection Ls 1 25,000,000.00 25,000,000.00

SUB TOTAL - B 1 103,971,380.00

2. pemasangan dudukan jaws primer


a. Besi IWF 300 M 36 785,000.00 28,260,000.00
b. Plat 6 mm M2 11.52 972,000.00 11,197,440.00
c. Baut Buah 48 15,000.00 720,000.00
d. Pengelasan dan erection Ls 1 10,000,000.00 10,000,000.00

SUB TOTAL - B 2 50,177,440.00


3. Pemasangan Rangka dan dudukan conveyor
a. Conveyor 60 cm M 35 245,000.00 8,575,000.00
b. Roller 3 inch Buah 24 190,000.00 4,560,000.00
c. roller 60 cm Buah 4 255,000.00 1,020,000.00
d. Braket Buah 12 265,000.00 3,180,000.00
e. Baut dan mur Buah 24 27,000.00 648,000.00
f. Drum Roller 80 cm Buah 2 575,000.00 1,150,000.00
g. Dinamo 7,5 kw Unit 3 11,500,000.00 34,500,000.00
h. Kabel power 3 phase M 50 1,800,000.00 1,800,000.00
i. Box Panel Unit 1 4,500,000.00 4,500,000.00
f. Plat 6 mm M2 2.88 972,000.00 2,799,360.00
g. Pengelasan dan Erection Ls 1 15,000,000.00 15,000,000.00

SUB TOTAL - B 3 77,732,360.00

Jumlah Total Harga Pekerjaan ( A + B ) Rp 239,500,180.00

ket:
versi Tanpa pondasi beton

Riwang, 28 Juni 2022


Diperiksa Dibuat Oleh

Kurniawan Arif Barandi Nuryanto


Head Off Engineering KTU Manager Tektrans

Disetujui

Dodi Patrawijaya Khairuddin Simatupang


Group Manager AM Area II