This document is a budget plan for the construction of a stone crusher plant at location AIK. It includes 3 sections - structures, stone crusher parts, and conveyor frame and installation. The total budget is Rp 239,500,180,000. Major items include foundations, hoppers, jaws, plates, beams, conveyors, rollers, motors, and installation work. It was prepared on June 28th, 2022 and approved by engineering, project, and area management leaders.
This document is a budget plan for the construction of a stone crusher plant at location AIK. It includes 3 sections - structures, stone crusher parts, and conveyor frame and installation. The total budget is Rp 239,500,180,000. Major items include foundations, hoppers, jaws, plates, beams, conveyors, rollers, motors, and installation work. It was prepared on June 28th, 2022 and approved by engineering, project, and area management leaders.
This document is a budget plan for the construction of a stone crusher plant at location AIK. It includes 3 sections - structures, stone crusher parts, and conveyor frame and installation. The total budget is Rp 239,500,180,000. Major items include foundations, hoppers, jaws, plates, beams, conveyors, rollers, motors, and installation work. It was prepared on June 28th, 2022 and approved by engineering, project, and area management leaders.
This document is a budget plan for the construction of a stone crusher plant at location AIK. It includes 3 sections - structures, stone crusher parts, and conveyor frame and installation. The total budget is Rp 239,500,180,000. Major items include foundations, hoppers, jaws, plates, beams, conveyors, rollers, motors, and installation work. It was prepared on June 28th, 2022 and approved by engineering, project, and area management leaders.
NO. URAIAN PEKERJAAN SATUAN HARGA SATUAN JUMLAH HARGA
VOLUME [Rp.] [Rp.] A. STRUKTUR Pekerjaan Pondasi 1. pondasi tiang conveyor a. besi beton KG 25 15,000.00 375,000.00 b. beton K-250 M3 3 1,950,000.00 5,850,000.00 c. bekesting M2 2.8 255,000.00 714,000.00 d. Baut angkur Buah 8 85,000.00 680,000.00
SUB TOTAL - A 1 7,619,000.00
B. PART STONE CRUSHER
Hopper dan jaws primer pemasangan hooper stone crusher 1. UNP 200 M 57.2 250,000.00 14,300,000.00 UNP 150 M 9.84 142,000.00 1,397,280.00 UNP 65 M 6 65,000.00 390,000.00 Plat Strip 6 MM M2 5.76 560,000.00 3,225,600.00 PLAT Baja Hitam 10 MM M2 8.64 1,600,000.00 13,824,000.00 Plat Baja 8MM M2 14.09 1,050,000.00 14,794,500.00 Besi Siku 65 MM M 20 100,000.00 2,000,000.00 H-BEAM 300 M 12 2,375,000.00 28,500,000.00 BAUT 3/8 Buah 30 18,000.00 540,000.00 Pengelasan dan Erection Ls 1 25,000,000.00 25,000,000.00
SUB TOTAL - B 1 103,971,380.00
2. pemasangan dudukan jaws primer
a. Besi IWF 300 M 36 785,000.00 28,260,000.00 b. Plat 6 mm M2 11.52 972,000.00 11,197,440.00 c. Baut Buah 48 15,000.00 720,000.00 d. Pengelasan dan erection Ls 1 10,000,000.00 10,000,000.00
SUB TOTAL - B 2 50,177,440.00
3. Pemasangan Rangka dan dudukan conveyor a. Conveyor 60 cm M 35 245,000.00 8,575,000.00 b. Roller 3 inch Buah 24 190,000.00 4,560,000.00 c. roller 60 cm Buah 4 255,000.00 1,020,000.00 d. Braket Buah 12 265,000.00 3,180,000.00 e. Baut dan mur Buah 24 27,000.00 648,000.00 f. Drum Roller 80 cm Buah 2 575,000.00 1,150,000.00 g. Dinamo 7,5 kw Unit 3 11,500,000.00 34,500,000.00 h. Kabel power 3 phase M 50 1,800,000.00 1,800,000.00 i. Box Panel Unit 1 4,500,000.00 4,500,000.00 f. Plat 6 mm M2 2.88 972,000.00 2,799,360.00 g. Pengelasan dan Erection Ls 1 15,000,000.00 15,000,000.00
SUB TOTAL - B 3 77,732,360.00
Jumlah Total Harga Pekerjaan ( A + B ) Rp 239,500,180.00