Professional Documents
Culture Documents
Encl. To 17-20128 - Opt
Encl. To 17-20128 - Opt
: 17 – 20128
Visit SAP Doc. – No.:
Power Plant Pangkalan Susu Pangkalan
Place:
4 ID Fans Susu
- Enclosures - Date: 03.10.2017
TLT-Turbo GmbH
Page: 1 von 17
Encl. 1
Machine plate.
(Photo taken by our supervisor Holger Gebauer.)
Report – No.: 17 – 20128
Visit SAP Doc. – No.:
Power Plant Pangkalan Susu Pangkalan
Place:
4 ID Fans Susu
- Enclosures - Date: 03.10.2017
TLT-Turbo GmbH
Page: 3 von 17
Encl. 2
Actuator Plate.
Left photo taken by our supervisor Holger Gebauer.
Right photo taken on 03.10.2017, ID Fan 2B
Report – No.: 17 – 20128
Visit SAP Doc. – No.:
Power Plant Pangkalan Susu Pangkalan
Place:
4 ID Fans Susu
- Enclosures - Date: 03.10.2017
TLT-Turbo GmbH
Page: 5 von 17
Encl. 3
Encl. 4
Encl. 5
Encl. 6
Encl. 7