Lowest level of a WBS must, except:

Most detailed work


Fill all information
Contain smallest subdivision of work
General work (*)
Incorrect
(0/1) Points
2. A hierarchy used to organize projects, that is the definitions of..
EPS (Enterprise Project Structures) (*)
Nodes
Root
OBS (Organizational Breakdown Structures)
Incorrect
(0/1) Points
3. When you set a date limit on a project schedule using 'Start On or After
Constraint', what will be happening?
Postpone an activity as long as possible without affecting the next activity.
Affect the end date of activity and the end date of subsequent activities.
Affect the start date of activity and the start date of subsequent activities. (*)
Violate the 'network logic'.
Correct
(1/1) Points
4. Element represents a deliverable, product, or service and each element
contains the activities neede to produce the deliverable:
Project
OBS
EPS
WBS (*)
Correct
(1/1) Points
5. When you add a new WBS element it is automatically added at the same level
as the highlighted WBS element. True or False
True
False (*)
Incorrect
6. Which statement about EPS is wrong?
It allows project data to be analyzed at multiple levels.
It is limited to two weeks. (*)
It allows security control at any level.
It covers all the projects in the company
Incorrect
(0/1) Points
7. Which of the following constraints must project management address?
Schedule
Cost
Resources
A and B
A, B and C (*)
Incorrect
(0/1) Points
8. In which tab can you specify the automatic numbering of the Activity ID
values?
Settings
General
Dates
Defaults (*)
Correct
(1/1) Points
9. Which of the following characteristics is important for a project?
Produces unique results
It is temporary
Complex or consists of many tasks
A, B, and C (*)
Correct
(1/1) Points
10. Threre are three calendar pools, except:
Task (*)
Resource
Global
Project
Incorrect

11. Which statement about EPS is wrong?


EPS enables security control at every level
EPS allows project data to be analyzed at every level
EPS activation is only limited to 2 weeks (*)
EPS covers all company projects
Incorrect
(0/1) Points
12. Project duration can be shortened by:
Planning a schedule of activity that might overlap
Appending resources
Changing assignment calender
All answers are correct (*)
Incorrect
(0/1) Points
13. The following statements are true regarding Enterprise Project Structure
(EPS), except:
EPS enables security control at any level.
EPS covers all projects in the company.
EPS enables analysis of project data at multiple levels.
EPS is limited to only two levels. (*)
Correct.
(1/1) Points
14. The three main project boundaries are:
Time, cost, risk.
Cost, scope, risk.
Cost, time, human resources.
Time, cost, scope. (*)
Incorrect
(0/1) Points
15. A calendar can include types of work time:
Standard day, nonwork, exception and nonwork Exception (*)
Standard day and nonwork
Standard day, nonwork, exception
Standard day, nonwork, exception
Correct

16. Here is the meaning of the role, namely:


Something that individuals use to complete activities
Activities included in the project
Types of work related to resources
Job title or skill required to complete an activity (*)
Incorrect
(0/1) Points
17. The access mode used to allow a project to be accessed and changed by
multiple users is called?
Read only
Shared (*)
All in one
Exclusive
Correct
(1/1) Points
18. Which one below that is not included in the company data:
EPS
Project codes
Notebook topic
Risks (*)
Incorrect
(0/1) Points
19. Which does not include roles?
Cost (*)
Cost Engineer
Civil Engineer
Engineer
Incorrect
(0/1) Points
20. The following is one of the steps for analysis of an updated project, except:
Perform baseline analysis
Perform cost analysis
Perform an analysis of used resources
Performing role analysis (*)
Incorrect
21. The following are things that will be compared when using the baseline
project, except..
Data resource
Data schedule
Data cost
Data baseline (*)
Correct
(1/1) Points
22. You are training a new Primavera user trying to create a project. They
navigate to the EPS page. However, they don't see the sub-node where the
project should be created. Identify the easiest way for the User to view the sub-
nodes on the EPS page.
Obtain security assignments at Read Only to all nodes
Click on each Node and Expand it to the lowest level (*)
Click “Add” button, so that all nodes are expanded, and then cancel.
Click on View, Expand All and scroll to locate the sub node
Correct
(1/1) Points
23. There are several works should be done on Project Time Management
(except)
Cost control (*)
Activity sequencing
Activity Resouce Estimating
Schedule control
Schedule development
Incorrect
(0/1) Points
24. Which one of the following statements is FALSE?
In a relationship, predecessors and successors may run concurrently
Successor is an activity that is influenced by the start or finish of another activity

Predecessor is an activity that affects the start or finish of another activity


In a relationship, the predecessor activity is not always starts before the
successor starts (*)
Incorrect
(0/1) Points
25. Level of effort in activity type, means:
It will require more resources to complete the activity
It will take longer to complete the activity
These activities are support activities for the whole project (*)
The activity will have the largest total float
Correct
26. If activity A with a duration of 3 days starts on August 30, and continues with
activity B with a Finish to Start (FS) relationship with a lag of 1 day, what date
does activity B start?
3 September (*)
1 September
2 September
4 September
Incorrect
(0/1) Points
27. The Activity has an Original Duration of 10, and a Duration Remaining of 10.
An Actual Start is assigned to the activity. Physical% updated to equal 80%. What
is the Time Remaining for this activity?
8
80
2
10 (*)
Incorrect
(0/1) Points
28. What is Finishing Milestone?
The last activity carried out in 1 project (*)
The fastest activity completed in 1 project
Activities that require the most resources
Activities that signal the start of a project
Incorrect
(0/1) Points
29. The following are examples of enterprise data, except:
Risks (*)
Notebook topics
Roles
Risk categories
Correct
(1/1) Points
30. You need to enter data in the Finish field for which the activity type is a Start
Milestone, which has zero duration. True or False
True
False (*)
Incorrect
31. Which one are not common set of project characteristics?
Cross organizational participation
A target outcome
A defined life span
New or unique
No constraints on time, cost or performance (*)
Correct
(1/1) Points
32. Which type of activity is used when work must be completed within a certain
timeframe, regardless of the availability of the specified resource?
Task dependent (*)
Resource dependent
Level of effort
Milestone
Correct
(1/1) Points
33. Activity A lasted 7 days, activity B lasted 3 days, and activity C lasted 10 days.
Activities A and B start at the same time. Activity C can only start when activities
A and B are finished. Which array of activities is the critical path?
A-C (*)
A-B
A-B-C
B-C
Correct
(1/1) Points
34. What is lag?
Pause between one activity and the next (*)
Working time lag between one resource and another
When 2 activities overlap each other
Pause between one project and another
Incorrect
(0/1) Points
35. The following are included as levels in the Activities Codes, except:
Project Level
Global Level
WBS Level (*)
EPS Level
Correct
36. EPS stands for…
Enterprise Project System
Enterprise Project Share
Earning Project Structure (*)
Not A and B
Correct
(1/1) Points
37. Identify the fields that must be unique in Primavera.
Project Description
Project ID
Project manager
Project Name (*)
Incorrect
(0/1) Points
38. If we choose the global calendar, then..
The calendar system will apply to all our projects in the Primavera database (*)

The calendar system will apply only to the projects we specify/select


The calendar system will only apply to some resources
All wrong
Incorrect
(0/1) Points
39. Identify the true statement about EPS.
EPS defined and maintained in Optional Client
EPS is specified during installation and cannot be changed
This is the default filing system for projects
Activities represent the lowest level of the hierarchy (*)
Incorrect
(0/1) Points
40. Project documents can be classified into 2 types, namely:
Work plan and Reference document
Project documents and reference document
Work product and Reference document (*)
Linking documents and reference document
Incorrect
(0/1) Points
Previous

41. Generating unique characters is the definition of…


Operation
Project (*)
A and B
Not A and B
Incorrect
(0/1) Points
42. Identify relevant use cases for implementing a Must Done date on a project.
Compare Scheduled Finish with Must Finish By date to negotiate a realistic Finish
date (*)
Compare Must Done By date with Actual Finish Date to negotiate a realistic
Finish date
Apply Must Done By date to shorten schedule duration
Apply Must Complete On date to build case to request resource
Incorrect
(0/1) Points
43. A project copy used to update or perform a what-if analysis is the definition
of…
Summary Project
Baseline
Reflection Projects (*)
Project Plan
Incorrect
(0/1) Points
44. The following is the proper characteristics for activities in a Task Dependent,
namely…
Unable to perform role assignment
Has a duration of 0
Only has a finish date
Can do assignments for roles and resources (*)
Incorrect
(0/1) Points
45. Every organization has its own variations of what documents are requred to
initiate a project. It's importan to identify the project need, stakeholders, and
main goals. True or False
True (*)
False
Incorrect
46. Plans that can be compared using the schedule comparison tool are?
Revised Plan and Fundamental Plan
Based Plan and Schedule Plan
Fundamental Plan and Based Plan
Based Plan and Revised Plan (*)
Incorrect
(0/1) Points
47. A picture that represents all the activities in a project as well as the logical
(depending on) relationships is the meaning of..
Predence Diagramming Method
Logic Diagram
Network Diagram
Network Logic Diagram (*)
Incorrect
(0/1) Points
48. OBS stands for…
Organizational Based Structure
Organizational Broadcaster Structure
Organizational Breakdown Structure (*)
Correct
(1/1) Points
49. There are several important technical skills as Project Manager (except)
Scheduling
Scoping
Empathising (*)
Project status reporting
Resources allocating
Correct
(1/1) Points
50. Which of the following is NOT a project?
Pasopati flyover construction
Procurement of computers at SDN 1 Bandung
Teaching and learning activities at the Bandung Institute of Technology (*)
Development of the 2022 Digital Village application
Incorrect