The document discusses various concepts related to project scheduling and management in Primavera. It provides definitions and characteristics of key terms like WBS, EPS, milestones, calendars, and activity types. It also presents true/false and multiple choice questions to test understanding of these concepts. Some key points covered include that the lowest level of a WBS must contain the smallest subdivision of work, EPS allows analysis of project data at multiple levels but is limited to two levels, and resource dependent activities can be performed regardless of resource availability within a timeframe.
The document discusses various concepts related to project scheduling and management in Primavera. It provides definitions and characteristics of key terms like WBS, EPS, milestones, calendars, and activity types. It also presents true/false and multiple choice questions to test understanding of these concepts. Some key points covered include that the lowest level of a WBS must contain the smallest subdivision of work, EPS allows analysis of project data at multiple levels but is limited to two levels, and resource dependent activities can be performed regardless of resource availability within a timeframe.
The document discusses various concepts related to project scheduling and management in Primavera. It provides definitions and characteristics of key terms like WBS, EPS, milestones, calendars, and activity types. It also presents true/false and multiple choice questions to test understanding of these concepts. Some key points covered include that the lowest level of a WBS must contain the smallest subdivision of work, EPS allows analysis of project data at multiple levels but is limited to two levels, and resource dependent activities can be performed regardless of resource availability within a timeframe.
Fill all information Contain smallest subdivision of work General work (*) Incorrect (0/1) Points 2. A hierarchy used to organize projects, that is the definitions of.. EPS (Enterprise Project Structures) (*) Nodes Root OBS (Organizational Breakdown Structures) Incorrect (0/1) Points 3. When you set a date limit on a project schedule using 'Start On or After Constraint', what will be happening? Postpone an activity as long as possible without affecting the next activity. Affect the end date of activity and the end date of subsequent activities. Affect the start date of activity and the start date of subsequent activities. (*) Violate the 'network logic'. Correct (1/1) Points 4. Element represents a deliverable, product, or service and each element contains the activities neede to produce the deliverable: Project OBS EPS WBS (*) Correct (1/1) Points 5. When you add a new WBS element it is automatically added at the same level as the highlighted WBS element. True or False True False (*) Incorrect 6. Which statement about EPS is wrong? It allows project data to be analyzed at multiple levels. It is limited to two weeks. (*) It allows security control at any level. It covers all the projects in the company Incorrect (0/1) Points 7. Which of the following constraints must project management address? Schedule Cost Resources A and B A, B and C (*) Incorrect (0/1) Points 8. In which tab can you specify the automatic numbering of the Activity ID values? Settings General Dates Defaults (*) Correct (1/1) Points 9. Which of the following characteristics is important for a project? Produces unique results It is temporary Complex or consists of many tasks A, B, and C (*) Correct (1/1) Points 10. Threre are three calendar pools, except: Task (*) Resource Global Project Incorrect
11. Which statement about EPS is wrong?
EPS enables security control at every level EPS allows project data to be analyzed at every level EPS activation is only limited to 2 weeks (*) EPS covers all company projects Incorrect (0/1) Points 12. Project duration can be shortened by: Planning a schedule of activity that might overlap Appending resources Changing assignment calender All answers are correct (*) Incorrect (0/1) Points 13. The following statements are true regarding Enterprise Project Structure (EPS), except: EPS enables security control at any level. EPS covers all projects in the company. EPS enables analysis of project data at multiple levels. EPS is limited to only two levels. (*) Correct. (1/1) Points 14. The three main project boundaries are: Time, cost, risk. Cost, scope, risk. Cost, time, human resources. Time, cost, scope. (*) Incorrect (0/1) Points 15. A calendar can include types of work time: Standard day, nonwork, exception and nonwork Exception (*) Standard day and nonwork Standard day, nonwork, exception Standard day, nonwork, exception Correct
16. Here is the meaning of the role, namely:
Something that individuals use to complete activities Activities included in the project Types of work related to resources Job title or skill required to complete an activity (*) Incorrect (0/1) Points 17. The access mode used to allow a project to be accessed and changed by multiple users is called? Read only Shared (*) All in one Exclusive Correct (1/1) Points 18. Which one below that is not included in the company data: EPS Project codes Notebook topic Risks (*) Incorrect (0/1) Points 19. Which does not include roles? Cost (*) Cost Engineer Civil Engineer Engineer Incorrect (0/1) Points 20. The following is one of the steps for analysis of an updated project, except: Perform baseline analysis Perform cost analysis Perform an analysis of used resources Performing role analysis (*) Incorrect 21. The following are things that will be compared when using the baseline project, except.. Data resource Data schedule Data cost Data baseline (*) Correct (1/1) Points 22. You are training a new Primavera user trying to create a project. They navigate to the EPS page. However, they don't see the sub-node where the project should be created. Identify the easiest way for the User to view the sub- nodes on the EPS page. Obtain security assignments at Read Only to all nodes Click on each Node and Expand it to the lowest level (*) Click “Add” button, so that all nodes are expanded, and then cancel. Click on View, Expand All and scroll to locate the sub node Correct (1/1) Points 23. There are several works should be done on Project Time Management (except) Cost control (*) Activity sequencing Activity Resouce Estimating Schedule control Schedule development Incorrect (0/1) Points 24. Which one of the following statements is FALSE? In a relationship, predecessors and successors may run concurrently Successor is an activity that is influenced by the start or finish of another activity
Predecessor is an activity that affects the start or finish of another activity
In a relationship, the predecessor activity is not always starts before the successor starts (*) Incorrect (0/1) Points 25. Level of effort in activity type, means: It will require more resources to complete the activity It will take longer to complete the activity These activities are support activities for the whole project (*) The activity will have the largest total float Correct 26. If activity A with a duration of 3 days starts on August 30, and continues with activity B with a Finish to Start (FS) relationship with a lag of 1 day, what date does activity B start? 3 September (*) 1 September 2 September 4 September Incorrect (0/1) Points 27. The Activity has an Original Duration of 10, and a Duration Remaining of 10. An Actual Start is assigned to the activity. Physical% updated to equal 80%. What is the Time Remaining for this activity? 8 80 2 10 (*) Incorrect (0/1) Points 28. What is Finishing Milestone? The last activity carried out in 1 project (*) The fastest activity completed in 1 project Activities that require the most resources Activities that signal the start of a project Incorrect (0/1) Points 29. The following are examples of enterprise data, except: Risks (*) Notebook topics Roles Risk categories Correct (1/1) Points 30. You need to enter data in the Finish field for which the activity type is a Start Milestone, which has zero duration. True or False True False (*) Incorrect 31. Which one are not common set of project characteristics? Cross organizational participation A target outcome A defined life span New or unique No constraints on time, cost or performance (*) Correct (1/1) Points 32. Which type of activity is used when work must be completed within a certain timeframe, regardless of the availability of the specified resource? Task dependent (*) Resource dependent Level of effort Milestone Correct (1/1) Points 33. Activity A lasted 7 days, activity B lasted 3 days, and activity C lasted 10 days. Activities A and B start at the same time. Activity C can only start when activities A and B are finished. Which array of activities is the critical path? A-C (*) A-B A-B-C B-C Correct (1/1) Points 34. What is lag? Pause between one activity and the next (*) Working time lag between one resource and another When 2 activities overlap each other Pause between one project and another Incorrect (0/1) Points 35. The following are included as levels in the Activities Codes, except: Project Level Global Level WBS Level (*) EPS Level Correct 36. EPS stands for… Enterprise Project System Enterprise Project Share Earning Project Structure (*) Not A and B Correct (1/1) Points 37. Identify the fields that must be unique in Primavera. Project Description Project ID Project manager Project Name (*) Incorrect (0/1) Points 38. If we choose the global calendar, then.. The calendar system will apply to all our projects in the Primavera database (*)
The calendar system will apply only to the projects we specify/select
The calendar system will only apply to some resources All wrong Incorrect (0/1) Points 39. Identify the true statement about EPS. EPS defined and maintained in Optional Client EPS is specified during installation and cannot be changed This is the default filing system for projects Activities represent the lowest level of the hierarchy (*) Incorrect (0/1) Points 40. Project documents can be classified into 2 types, namely: Work plan and Reference document Project documents and reference document Work product and Reference document (*) Linking documents and reference document Incorrect (0/1) Points Previous
41. Generating unique characters is the definition of…
Operation Project (*) A and B Not A and B Incorrect (0/1) Points 42. Identify relevant use cases for implementing a Must Done date on a project. Compare Scheduled Finish with Must Finish By date to negotiate a realistic Finish date (*) Compare Must Done By date with Actual Finish Date to negotiate a realistic Finish date Apply Must Done By date to shorten schedule duration Apply Must Complete On date to build case to request resource Incorrect (0/1) Points 43. A project copy used to update or perform a what-if analysis is the definition of… Summary Project Baseline Reflection Projects (*) Project Plan Incorrect (0/1) Points 44. The following is the proper characteristics for activities in a Task Dependent, namely… Unable to perform role assignment Has a duration of 0 Only has a finish date Can do assignments for roles and resources (*) Incorrect (0/1) Points 45. Every organization has its own variations of what documents are requred to initiate a project. It's importan to identify the project need, stakeholders, and main goals. True or False True (*) False Incorrect 46. Plans that can be compared using the schedule comparison tool are? Revised Plan and Fundamental Plan Based Plan and Schedule Plan Fundamental Plan and Based Plan Based Plan and Revised Plan (*) Incorrect (0/1) Points 47. A picture that represents all the activities in a project as well as the logical (depending on) relationships is the meaning of.. Predence Diagramming Method Logic Diagram Network Diagram Network Logic Diagram (*) Incorrect (0/1) Points 48. OBS stands for… Organizational Based Structure Organizational Broadcaster Structure Organizational Breakdown Structure (*) Correct (1/1) Points 49. There are several important technical skills as Project Manager (except) Scheduling Scoping Empathising (*) Project status reporting Resources allocating Correct (1/1) Points 50. Which of the following is NOT a project? Pasopati flyover construction Procurement of computers at SDN 1 Bandung Teaching and learning activities at the Bandung Institute of Technology (*) Development of the 2022 Digital Village application Incorrect
Principles For Understanding The Seerah (The Biography of The Prophet - Peace Be Upon Him) - Shaykh Saalih Aal Ush-Shaykh - Minister of Islamic Affairs, KSA.