Professional Documents
Culture Documents
116MP2022 Full Petition
116MP2022 Full Petition
Petition under Section 79(1)(b) read with Section 79(1)(f) of the Electricity
Act, 2003 seeking, inter alia, quashing of the purported invoice dated
14.12.2021 raised by the Respondent No. 1 on the Petitioner and for refund of
Rs 59,58,745 wrongfully and illegally deducted by the Respondents
VERSUS
PAPERBOOK
VERSUS
INDEX
PETITIONER
FILED BY
Deepak Khurana
Petition under Section 79(1)(b) read with Section 79(1)(f) of the Electricity
Act, 2003 seeking, inter alia, quashing of the purported invoice dated
14.12.2021 raised by the Respondent No. 1 on the Petitioner and for refund of
Rs 59,58,745 wrongfully and illegally deducted by the Respondents
DB Power Ltd.
Having its registered office at:
Office Block 1A, 5th Floor,
Corporate Block, DB City Park,
DB City, Arera Hills,
Opposite MP Nagar, Zone-I,
Bhopal-462016.
Also at
C-31, Naman Corporate Link
3rd floor, G Block,
Opposite Dena Bank,
Bandra Kurla Complex,
Bandra (East),
Mumbai – 400051
Through its Authorized Signatory
Shri Ajay Kumar Kaithwash ... PETITIONER
VERSUS
Companies Act, 1956. The Petitioner has set up 1200 MW (2 x 600) Thermal
both of its units are presently in operation. The Petitioner is supplying power to
more than one state and has a composite scheme for the generation and sale of
electricity as envisaged under Section 79(1) (b) of the Electricity Act 2003. The
Corporation Ltd. under a long term PPA, 311 MW power to Rajasthan Discoms
through PTC India Ltd. under long term PPA, 5% of the net generated power to
the State of Chhattisgarh under a long term PPA, in addition to the present
under the Indian Electricity Act, 2003, carrying out its trading activities
in the activity of bulk purchase and sale of electricity in Gujarat for & on
behalf of its Distribution Companies and is the ultimate purchaser of the power
in question.
4. The facts and circumstances leading to filing of the present petition are
its rights to substantiate its Petition with further documents and submissions
(i) That in September, 2021, the Respondent No. 2 issued a request for
(ii) That pursuant to the said invitation of bids by Respondent No. 2, the
following tariff:-
(iv) Further to the above, the Respondent No. 2 issued a letter of intent
2”) to the Petitioner for purchase of power from the Petitioner for
agreed between the Petitioner and the Respondent No. 1 whereby the
2. The LOI 2 further mentions that the rest of the terms &
(i.e. the RFP) and e-mail communication between the Petitioner and
(vi) It is pertinent to note that in terms of Clause 24 of the RFP, both the
parties would ensure that actual scheduling does not deviate by more
than 15% of the contracted power (i.e. 100 MW) as per the approved
open access for the monthly basis (for each requisition separately).
The said provision stipulates that in case the deviation from the
Respondent’s No. 2’s side is more than 15% of contracted energy for
is reproduced below:
CAPACITY
and pay for the open access charges to the extent not
availed by the GUVNL.
(vii) That the Respondent No. 1, vide its invoice dated 14.12.2021 raised
01.11.2021 to 30.11.2021.
marked as Annexure-E.
end for the period for which the invoice for compensation was issued
energy (for which open access had been allocated). However, the
11
deviation above the allowed limit of 15%, for raising the said
Clause 24(i) of the RFP is general and provides that both the
power as per the approved open access for the monthly basis. The
said clause nowhere provides for any cumulative deviation from the
Petitioner and the Respondent No. 1, much less the same being a
that the seller i.e. the Petitioner is only liable to pay for deviation if
the deviation from its side is more than 15% of contracted energy
(for which open access has been allocated on monthly basis). Thus,
case there is deviation from its side i.e. Clause 24 (ii) (wrongly typed
deviation of more than 15% from the Petitioner’s side, the Petitioner
(ix) In light of the above, the Petitioner vide its letter dated 15.12.2021,
marked as Annexure-F.
(x) The Respondent No. 1 by its letter dated 16.12.2021 admitted that
alleged that as overall revised quantum (by both the Petitioner and
violating Clause 24(i) of the RFP. Further, the Respondent No. 1 also
stated that owing to the alleged violation, the Respondent No. 2 had
raised the alleged invoice on the Petitioner while taking up the said
marked as Annexure-G.
(xi) That further to the letter dated 16.12.2021, the Respondent No. 1
deviation from the side of the seller i.e. the Petitioner is within the
Annexure-H.
deducted the said amount of Rs. 59,58,745 from the payment made
5. In view of the above clear provisions of the RFP, the Petitioner submits
by the Respondents is in breach of the terms and conditions of the RFP and bad
14
the Petitioner on the pretext of the alleged compensation which has been
imposed in violation of the terms of RFP. The Respondents are thus jointly and
severally liable to refund the said amount of Rs. 59,58,745 to the Petitioner
along with Late Payment Surcharge as per the provisions contained in Clause
23 of the RFP.
6. It is submitted that in light of the above, a dispute has arisen between the
contrary to the terms of the RFP and consequently seeking a direction to the
Respondents to refund the said amount of Rs. 59,58,745 to the Petitioner along
the RFP.
described in Para 2 above. Further, the present matter also relates to inter-state
8. The Petitioner has paid the requisite fees as per the applicable
regulations.
PRAYER
In view of the aforementioned facts and circumstances of the present case it is,
lacs fifty eight thousand seven hundred and forty five) for the period
c. Pass such other and further order or orders as this Hon'ble Commission
may deem fit and proper under the facts and circumstances of the
PETITIONER
Through
Deepak Khurana
(Khaitan & Khaitan)
Advocates for the Petitioner
A-38, Kailash Colony,
New Delhi-110048
Place: New Delhi Tel: 011-49774545
Dated: 01.04.2022 E-mail: deepak.k@khaitanandkhaitan.com
17
DB Power Ltd.
... PETITIONER
VERSUS
AFFIDAVIT
I, Ajay Kumar Kaithwash, aged about 45 years, S/o Sh. R.R. Kaithwash,
working for gain with the Petitioner Company having its Corporate office at C-
31, Naman Corporate Link 3rd floor, G Block, Opposite Dena Bank, Bandra
Kurla Complex, Bandra (East), Mumbai – 400051, presently at New Delhi, do
hereby solemnly affirm and state as under:
DEPONENT
VERIFICATION
I, deponent above named, do herby verify that the contents of the above
affidavit are true to the best of my knowledge and belief derived from the
records of the Petitioner Company, no part of it is false and nothing material
has been concealed therefrom.
DEPONENT