Professional Documents
Culture Documents
Basic Electrical Requirements
Basic Electrical Requirements
PART 1 - GENERAL
1.01 SUMMARY
B. Scope of Work
1. Electrical work, unless otherwise specified, includes the supply,
installation, testing and commissioning of the complete electrical
systems, equipment and materials shown on the Drawings and/or
described in the Specification together with all associated ancillary work,
support work and builder’s work in connection.
2. Incoming power supply and connection will be provided by Local Power
Authority at MV to the location shown on the drawings.
Contractor shall coordinate and provide all necessary assistance
required by other trades to complete the installation, and to the entire
satisfaction of the Engineer. Contractor shall be responsible for
providing and installing termination kits in the switchgear.
__________________________________________________________________________________________________
Riyadh Township 26 0500 Page 1 of 13
Kaden Road, Transmission Line and Waterworks
1.02 GENERAL REQUIREMENTS
A. Installations Generally
1. Carry out electrical work in accordance with the Drawings, Specification
and Regulations, ensuring compliance with design and performance
requirements, to provide safe and protected systems with equipment
readily accessible for operation, maintenance and repair.
E. KWh- Metering: liaise with the Local Power Authority and smart and provide
necessary instrumentation, enclosures and accessories required by them to
effect a complete KWh-metering installation.
E. Where design and operating conditions, different from the above are
required for particular equipment, they are described in the specification
sections of the related equipment.
J. Equipment and wiring layouts shown on the Drawings for work not included in
the Electrical Work, such as motor control centers/panels, cables between
motor controllers or motor control centers to motors and other similar
electrically operated equipment are shown for information and reference
only.
__________________________________________________________________________________________________
Riyadh Township 26 0500 Page 4 of 13
Potable Water Transmission Line & Waterworks
E. Factory Assembly: equipment generally is to be supplied in complete factory
assembled units ready for installation on site. Dis-assembly necessary for
transportation or other purposes is to be arranged to limit site work to simple
re-assembly and inter-wiring of control and power cabling.
I. Spare Parts: not later than the date of substantial completion, provide spare
parts required by the Specification, together with suitable means of
identifying, storing and securing same.
J. Tools And Instruments: not later than the date of substantial completion,
provide sets of tools and instruments required by the Specification, together
with suitable means of identifying, storing and securing same.
K. Label and identify all equipment, instruments, control and electrical devices
etc. to indicate duty, service or function, to the satisfaction of the Engineer.
Labels are to be laminated plastic or anodized aluminum discs with black
surface and white core with incised lettering in English. Alternative methods
of labeling may be submitted for approval. Fix labels with non-corrodible
screws to equipment, or to adjacent permanent surfaces or as approved by
the Engineer. Refer to Section ”Identification For Electrical Systems”.
__________________________________________________________________________________________________
Riyadh Township 26 0500 Page 5 of 13
Potable Water Transmission Line & Waterworks
1.05 SUBMISSIONS
A. Increase, by the quantity listed below, the number of electrical related shop
drawings, product data, and samples submitted, to allow for required
distribution plus two copies of each submittal required, which will be retained
by the Engineer.
1. Shop Drawings and Manufacturer’s Literature - Initial Submittal: 1
additional blue- or black-line prints.
2. Shop Drawings and Manufacturer’s Literature - Final Submittal: 1
additional blue- or black-line prints.
3. Product Data: 1 additional copy of each item.
4. List of Manufacturers.
Additional copies may be required by individual sections of these
Specifications.
E. Shop and construction drawings are to demonstrate to the Engineer that the
design requirements are understood by indicating all equipment and
material proposed to be supplied and installed and by detailing fabrication
and installation methods proposed to be used. Shop and construction
drawings are to clearly state the name and location of the work, the names
of the Engineer and Contractor, submission date, cross-references to the
Drawings and Specification and the specific reference number, location,
service and function of each item.
__________________________________________________________________________________________________
Riyadh Township 26 0500 Page 6 of 13
Potable Water Transmission Line & Waterworks
Composite construction drawings fully dimensioned, in metric, showing
locations of cables, conduits, bus ducts, shafts, mechanical and electrical
equipment rooms ceiling spaces and all other critical locations.
J. Spare Parts Schedules: submit with the Tender itemized schedules of spare
parts to be provided, as required by the individual sections of the
Specification, and state against each item the manufacturer’s unit price
including packaging and delivery to site.
K. Tools and Instruments Schedules: submit with the Tender itemized
schedules of tools and instruments to be provided, as required by the
individual sections of the Specification, and state against each item the
manufacturer’s unit price including packaging and delivery to site.
M. Samples: submit samples of all equipment and materials for approval. Major
items of equipment for which samples cannot be submitted are to be
demonstrated in existing installations or by manufacturer’s information, test
certificates and reports.
PART 3 - EXECUTION
3.01 ROUGH-IN
A. Verify final locations for rough-in with field measurements and with the
requirements of the actual equipment to be connected.
B. Refer to equipment specifications in Divisions (2)“Site Work” through (26)
“Electrical Work” for rough-in requirements.
3.02 ELECTRICAL INSTALLATIONS
E. Install systems, materials, and equipment level and plumb, parallel and
perpendicular to other building systems and components, where installed
exposed in finished spaces.
B. Test schedules and procedures are to be submitted for approval and are to
include details of testing equipment to be provided.
E. Insulation Resistance: test the feeders, lighting and power circuits, motors
and other power equipment of low voltage installations with a megger of not
less than 500 V d.c. for installations rated up to 500 V (r.m.s. value of a.c.
supply) and 1000 V d.c. for installations rated above 500 V up to 1000 V,
and as required by the particular Section of the Specification.
H. Operational Tests: carry out operational tests on all equipment and complete
systems to verify proper performance in compliance with the Specification.
Tests are to be carried out under normal operating conditions for not less
than 3 days, and as reasonably required by the Engineer.
__________________________________________________________________________________________________
Riyadh Township 26 0500 Page 10 of 13
Potable Water Transmission Line & Waterworks
I. Specific Tests: carry out specific tests required by the Specification and any
other tests required by the Engineer to verify compliance of the installations
with the Specification.
3.05 RECORDS
A. Generally: not later than the date of substantial completion, provide the
Engineer with four copies of all approved as-installed drawings, test records,
manufacturers’ guarantees and warranties, operating and maintenance
manuals and other records required by the Specification.
D. Test records are to include test certificates of type tests, routine tests, site
tests, commissioning and performance tests and all other tests on
equipment and installations described in the Specification and required by
the Engineer. Information is to include test procedures and results,
conditions under which tests were carried out including set points,
temperatures and the like, dates, location and attendance by authorized
representatives… etc.
END OF SECTION
__________________________________________________________________________________________________
Riyadh Township 26 0500 Page 13 of 13
Potable Water Transmission Line & Waterworks