Programme for Contract 3310 - North Runway

Modification Works (Rev. B02)


Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
Programme for Contract 3310 - North Runway Modification Works (Rev. B02) 965 1699 07-Jun-21 A 01-Sep-24 29-Nov-21 01-Sep-24 0
----- Contract Dates ----- C01_7 d/w - 10h/d - No HK Hols1183
- No B/O periods
0 (was
07-Jun-21
C1) A 01-Sep-24 29-Nov-21 01-Sep-24 0
Schedule of Significant Date [PS Appendix C1] C01_7 d/w - 10h/d - No HK Hols451
- No B/O periods
0 (was
07-Jun-21
C1) A 01-Sep-22 29-Nov-21 01-Sep-22 1
310.K.EX.A010 starting date [7 Jun 2021] C01_7 d/w - 10h/d - No HK 0 07-Jun-21 A 29-Nov-21
Hols - No B/O periods (was
310.K.EX.A070 Closure Date of Existing North Runway September of 2022 [PS10.2.13, assumed 01 Sep C1)
C01_7 d/w - 10h/d - No HK 0 01-Sep-22* 01-Sep-22 1
2022] Hols - No B/O periods (was
Contract Completion C1)
C01_7 d/w - 10h/d - No HK Hols623
- No B/O periods
0 (was18-Dec-22
C1) 01-Sep-24 18-Dec-22 01-Sep-24 0
Contract Completion Key Dates (Stage 1 to 7) [PS Appendix B] C01_7 d/w - 10h/d - No HK Hols560
- No B/O periods
0 (was18-Dec-22
C1) 30-Jun-24 18-Dec-22 30-Jun-24 0
310.K.EX.A944 [Contract] KD-1 (Stage 1) - Comp AGL Vault D Annex, ABWF, BS, AS, Megger Tests, C01_7 d/w - 10h/d - No HK 0 18-Dec-22* 18-Dec-22 0
provide access to others [18 Dec 22] Hols - No B/O periods (was
310.K.EX.A948 [Contract] KD-2 (Stage 2) - Comp AGL Vault C Annex, ABWF, BS, AS, Megger Tests, C1)
C01_7 d/w - 10h/d - No HK 0 19-Feb-23* 19-Feb-23 0
provide access to others [19 Feb 23] Hols - No B/O periods (was
310.K.EX.A952 [Contract] KD-3(Stage 3) - Comp Comm Rm. CR305 within PBA, ABWF, BS, AS final fix, C1)
C01_7 d/w - 10h/d - No HK 0 26-Feb-23* 26-Feb-23 0
provide access to others [26 Feb 23] Hols - No B/O periods (was
310.K.EX.A956 [Contract] KD-4(Stage 4)-Comp cable duct incl.drawpit along W perimeter C1)
C01_7 d/w - 10h/d - No HK 0 19-Mar-23* 19-Mar-23 0
seawalls,access for CLP cabling[19 Mar23] Hols - No B/O periods (was
310.K.EX.A960 [Contract] KD-5A (Stage 5) - Comp AGL System within 3310/IA/1 [30 Apr 23] C1)
C01_7 d/w - 10h/d - No HK 0 30-Apr-23* 30-Apr-23 0
Hols - No B/O periods (was
310.K.EX.A964 [Contract] KD-5B (Stage 5) - Comp AGL System within 3310/IA/6 [25 Jun 23] C1)
C01_7 d/w - 10h/d - No HK 0 25-Jun-23* 25-Jun-23 0
Hols - No B/O periods (was
310.K.EX.A968 [Contract] KD-5C (Stage 5) - Comp AGL System within 3310/IA/7 [30 Jul 23] C1)
C01_7 d/w - 10h/d - No HK 0 30-Jul-23* 30-Jul-23 0
Hols - No B/O periods (was
310.K.EX.A972 [Contract] KD-5D (Stage 5) - Comp AGL System within 3310/IA/8 [27 Aug 23] C1)
C01_7 d/w - 10h/d - No HK 0 27-Aug-23* 27-Aug-23 0
Hols - No B/O periods (was
310.K.EX.A976 [Contract] KD-5E (Stage 5) - Comp AGL System within 3310/IA/4 [24 Sep 23] C1)
C01_7 d/w - 10h/d - No HK 0 24-Sep-23* 24-Sep-23 0
Hols - No B/O periods (was
310.K.EX.A980 [Contract] KD-5F (Stage 5) - Comp AGL System within 3310/IA/2 [26 Nov 23] C1)
C01_7 d/w - 10h/d - No HK 0 26-Nov-23* 26-Nov-23 0
Hols - No B/O periods (was
310.K.EX.A984 [Contract] KD-5G (Stage 5) - Comp AGL System within 3310/IA/3 [17 Dec 23] C1)
C01_7 d/w - 10h/d - No HK 0 17-Dec-23* 17-Dec-23 0
Hols - No B/O periods (was
310.K.EX.A992 [Contract] KD-6(Stage 6)-Comp comm cabling btw. Comm Rm in ATCT&BATCC on ex. C1)
C01_7 d/w - 10h/d - No HK 0 31-Dec-23* 31-Dec-23 0
Airport and Comm Rm in New ATCT [31 Dec 23] Hols - No B/O periods (was
310.K.EX.A988 [Contract] KD-5H (Stage 5) - Comp AGL System within 3310/IA/5 [14 Jan 24] C1)
C01_7 d/w - 10h/d - No HK 0 14-Jan-24* 14-Jan-24 0
Hols - No B/O periods (was
310.K.EX.A996 [Contract] KD-7 (Stage 7)-Comp modi of ex. N-Runway incl.line marking, T&C ready for C1)
C01_7 d/w - 10h/d - No HK 0 30-Jun-24* 30-Jun-24 0
CAD/AA flight check [30 Jun 24] Hols - No B/O periods (was
Contract Completion Date (Section 1 to 5 & Complete the whole of the works)[Appendix B] C1)
C01_7 d/w - 10h/d - No HK Hols364
- No B/O periods
0 (was03-Sep-23
C1) 01-Sep-24 03-Sep-23 01-Sep-24 0
310.K.EX.A1000 [Contract] KD-8(Section 1)-Comp aviation fuel direct buried pipeline&temp filling point incl C01_7 d/w - 10h/d - No HK 0 03-Sep-23* 03-Sep-23 0
T&C,ready for use[3 Sep 23] Hols - No B/O periods (was
310.K.EX.A1004 [Contract] KD-9 (Section 2) - Comp aviation fuel pipeline through WVT incl T&C, license, C1) C01_7 d/w - 10h/d - No HK 0 30-Jun-24* 30-Jun-24 0
ready for use [30 Jun 24] Hols - No B/O periods (was
310.K.EX.A1008 [Contract] KD-10(Section 3)-Comp wk for all ancillary buildings incl.T&C&stat. appv, C1)
C01_7 d/w - 10h/d - No HK 0 14-Jul-24* 14-Jul-24 0
consents, ready for use [14 Jul 24] Hols - No B/O periods (was
310.K.EX.A1012 [Contract] KD-11 (Section 4)-Comp all works for EVT and WVT incl T&C, stat. appv., C1)
C01_7 d/w - 10h/d - No HK 0 28-Jul-24* 28-Jul-24 0
consents, ready for use [28 Jul 24] Hols - No B/O periods (was
310.K.EX.A1016 [Contract] KD-12 (Section 5)- Comp all works incl. T&C, Stat. appv., licenses incl CAD C1)
C01_7 d/w - 10h/d - No HK 0 25-Aug-24* 25-Aug-24 0
aerodrome licensing [25 Aug 24] Hols - No B/O periods (was
310.K.EX.A1020 [Contract] KD-13 (the whole of the works) - Achieve Completion of the whole of the works C1)
C01_7 d/w - 10h/d - No HK 0 01-Sep-24* 01-Sep-24 0
and vacate the site [1 Sep 24] Hols - No B/O periods (was
Planned Completion C1)
C01_7 d/w - 10h/d - No HK Hols622
- No B/O periods
0 (was17-Dec-22
C1) 30-Aug-24 18-Dec-22 01-Sep-24 2

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:43
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 1 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
Planned Completion Key Dates (Stage 1 to 7) C01_7 d/w - 10h/d - No HK Hols556
- No B/O periods
0 (was17-Dec-22
C1) 25-Jun-24 18-Dec-22 30-Jun-24 5
310.K.EX.A014 [Planned] KD-1 (Stage 1) - Comp AGL Vault D Annex, ABWF, BS, AS, Megger Tests, C01_7 d/w - 10h/d - No HK 0 17-Dec-22* 18-Dec-22 1
provide access to others Hols - No B/O periods (was
310.K.EX.A022 [Planned] KD-3 (Stage 3) - Comp Comm Rm. CR305 within PBA, ABWF, BS, AS final fix, C1)C01_7 d/w - 10h/d - No HK 0 24-Feb-23* 26-Feb-23 2
provide access to others Hols - No B/O periods (was
310.K.EX.A026 [Planned] KD-4 (Stage 4) - Comp cable duct incl. drawpits along W perimeter seawalls, C1)
C01_7 d/w - 10h/d - No HK 0 18-Mar-23* 19-Mar-23 1
provide access for CLP cabling Hols - No B/O periods (was
310.K.EX.A018 [Planned] KD-2 (Stage 2) - Comp AGL Vault C Annex, ABWF, BS, AS, Megger Tests, C1)
C01_7 d/w - 10h/d - No HK 0 29-Mar-23* 19-Feb-23 -38
provide access to others Hols - No B/O periods (was
310.K.EX.A030 [Planned] KD-5A (Stage 5) - Comp AGL System within 3310/IA/1 C1)
C01_7 d/w - 10h/d - No HK 0 17-Apr-23* 30-Apr-23 13
Hols - No B/O periods (was
310.K.EX.A034 [Planned] KD-5B (Stage 5) - Comp AGL System within 3310/IA/6 C1)
C01_7 d/w - 10h/d - No HK 0 24-Jun-23* 25-Jun-23 1
Hols - No B/O periods (was
310.K.EX.A038 [Planned] KD-5C (Stage 5) - Comp AGL System within 3310/IA/7 C1)
C01_7 d/w - 10h/d - No HK 0 22-Jul-23* 30-Jul-23 8
Hols - No B/O periods (was
310.K.EX.A042 [Planned] KD-5D (Stage 5) - Comp AGL System within 3310/IA/8 C1)
C01_7 d/w - 10h/d - No HK 0 14-Aug-23* 27-Aug-23 13
Hols - No B/O periods (was
310.K.EX.A046 [Planned] KD-5E (Stage 5) - Comp AGL System within 3310/IA/4 C1)
C01_7 d/w - 10h/d - No HK 0 28-Aug-23* 24-Sep-23 27
Hols - No B/O periods (was
310.K.EX.A050 [Planned] KD-5F (Stage 5) - Comp AGL System within 3310/IA/2 C1)
C01_7 d/w - 10h/d - No HK 0 21-Nov-23* 26-Nov-23 5
Hols - No B/O periods (was
310.K.EX.A054 [Planned] KD-5G (Stage 5) - Comp AGL System within 3310/IA/3 C1)
C01_7 d/w - 10h/d - No HK 0 13-Dec-23* 17-Dec-23 4
Hols - No B/O periods (was
310.K.EX.A062 [Planned] KD-6 (Stage 6) - Comp comm cabling btw. Comm Rm in ATCT & BATCC on C1)
C01_7 d/w - 10h/d - No HK 0 27-Dec-23* 31-Dec-23 4
ex. Airport and Comm Rm in New ATCT Hols - No B/O periods (was
310.K.EX.A058 [Planned] KD-5H (Stage 5) - Comp AGL System within 3310/IA/5 C1)
C01_7 d/w - 10h/d - No HK 0 13-Jan-24* 14-Jan-24 1
Hols - No B/O periods (was
310.K.EX.A066 [Planned] KD-7 (Stage 7) - Comp modi of ex. N-Runway incl. line marking, T&C ready for C1)
C01_7 d/w - 10h/d - No HK 0 25-Jun-24* 30-Jun-24 5
CAD/AA flight check Hols - No B/O periods (was
Planned Completion Dates (Section 1 to 5 & Complete the whole of the works) C1)
C01_7 d/w - 10h/d - No HK Hols362
- No B/O periods
0 (was03-Sep-23
C1) 30-Aug-24 03-Sep-23 01-Sep-24 2
310.K.EX.A100 [Planned] KD-8 (Section 1) - Comp aviation fuel direct buried pipeline & temp filling point C01_7 d/w - 10h/d - No HK 0 03-Sep-23* 03-Sep-23 0
incl T&C, ready for use Hols - No B/O periods (was
310.K.EX.A104 [Planned] KD-9 (Section 2) - Comp aviation fuel pipeline through WVT incl T&C, license, C1)
C01_7 d/w - 10h/d - No HK 0 15-Jun-24* 30-Jun-24 15
ready for use Hols - No B/O periods (was
310.K.EX.A108 [Planned] KD-10 (Section 3) - Comp works for all ancillary buildings incl. T&C & stat. appv, C1)
C01_7 d/w - 10h/d - No HK 0 26-Jun-24* 14-Jul-24 18
consents, ready for use Hols - No B/O periods (was
310.K.EX.A112 [Planned] KD-11 (Section 4) - Comp all works for EVT and WVT incl T&C, stat. appv., C1)
C01_7 d/w - 10h/d - No HK 0 23-Jul-24* 28-Jul-24 5
consents, ready for use Hols - No B/O periods (was
310.K.EX.A116 [Planned] KD-12 (Section 5) - Comp all works incl. T&C, Stat. appv., consents, licenses C1)
C01_7 d/w - 10h/d - No HK 0 20-Aug-24* 25-Aug-24 5
incl CAD aerodrome licensing Hols - No B/O periods (was
310.K.EX.A120 [Planned] KD-13 (the whole of the works) - Achieve Completion of the whole of the works C1)
C01_7 d/w - 10h/d - No HK 0 30-Aug-24* 01-Sep-24 2
and vacate the site Hols - No B/O periods (was
Option Exercise Date C1)
C01_7 d/w - 10h/d - No HK Hols944
- No B/O periods
0 (was
20-Jul-21
C1) A 18-Feb-24 27-Mar-22 18-Feb-24 0
310.K.EX.A920 Option - Latest Exercise Date for Option 3310/A and 3310/B [within 3 months of the C01_7 d/w - 10h/d - No HK 0 20-Jul-21 A 27-Mar-22
starting date; PS38.1] Hols - No B/O periods (was
Contract Completion Date of Optional Works [PS Appendix B] C1)
C01_7 d/w - 10h/d - No HK Hols567
- No B/O periods
0 (was31-Jul-22
C1) 18-Feb-24 31-Jul-22 18-Feb-24 0
310.K.EX.A1024 [Contract] KD-G1 - Comp all civil wks for HKO Anemometers,incl.power,sys cabling to ex. C01_7 d/w - 10h/d - No HK 0 31-Jul-22* 31-Jul-22 0
ATCX and BATCX, T&C [31 Jul 22] Hols - No B/O periods (was
310.K.EX.A1028 [Contract] KD-G2 - Localizer Bldg C, Glide Path Bldg C & D, HKPF Bldg [8 Oct 23] C1)
C01_7 d/w - 10h/d - No HK 0 08-Oct-23* 08-Oct-23 0
Hols - No B/O periods (was
C1)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:43
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 2 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.K.EX.A1032 [Contract] KD-G3-Civil wks for HKO Runway Visual Range,Forward Scatterer, Ceilometer C01_7 d/w - 10h/d - No HK 0 15-Oct-23* 15-Oct-23 0
& X-Band Radar HKO .... [15 Oct 23] Hols - No B/O periods (was
310.K.EX.A1036 [Contract]KD-G4 - Civil wks for C&ED with associated power&sys cabling incl. T&C, C1)
C01_7 d/w - 10h/d - No HK 0 18-Feb-24* 18-Feb-24 0
approval and consent ..... [18 Feb 24] Hols - No B/O periods (was
Planned Completion Date of Optional Works C1)
C01_7 d/w - 10h/d - No HK Hols565
- No B/O periods
0 (was31-Jul-22
C1) 16-Feb-24 31-Jul-22 18-Feb-24 2
310.K.EX.A200 [Planned] KD-G1 - Comp all civil works for HKO Anemometers, incl. power, system C01_7 d/w - 10h/d - No HK 0 31-Jul-22* 31-Jul-22 0
cabling to ex. ATCX and BATCX, T&C Hols - No B/O periods (was
310.K.EX.A204 [Planned] KD-G2 - Localizer Bldg C, Glide Path Bldg C & D, HKPF Bldg C1)
C01_7 d/w - 10h/d - No HK 0 07-Oct-23* 08-Oct-23 1
Hols - No B/O periods (was
310.K.EX.A228 [Planned] KD-G3 - Civil works for HKO Runway Visual Range, Forward Scatterer, C1)
C01_7 d/w - 10h/d - No HK 0 11-Oct-23* 15-Oct-23 4
Ceilometer and X-Band Radar HKO .... Hols - No B/O periods (was
310.K.EX.A244 [Planned] KD-G4 - Civil works for C&ED with associated power and system cabling incl. C1)
C01_7 d/w - 10h/d - No HK 0 16-Feb-24* 18-Feb-24 2
T&C, approval and consent ..... Hols - No B/O periods (was
Access Dates [PS Appendix C2] C1)
C01_7 d/w - 10h/d - No HK Hols770
- No B/O periods
0 (was
07-Jun-21
C1) A 17-Jul-23 29-Nov-21 01-Sep-24 413
310.A.EX.A300 Access to 3310/1 [7 Jun 21] C01_7 d/w - 10h/d - No HK 0 07-Jun-21 A 27-Jul-22
Hols - No B/O periods (was
310.A.EX.A304 Access to 3310/2 [7 Jun 21] C1)
C01_7 d/w - 10h/d - No HK 0 07-Jun-21 A 10-Jan-23
Hols - No B/O periods (was
310.A.EX.A308 Access to 3310/3 [7 Jun 21] C1)
C01_7 d/w - 10h/d - No HK 0 07-Jun-21 A 13-Aug-22
Hols - No B/O periods (was
310.A.EX.A312 Access to 3310/4 [7 Jun 21] C1)
C01_7 d/w - 10h/d - No HK 0 07-Jun-21 A 26-May-22
Hols - No B/O periods (was
310.A.EX.A324 Access to 3310/6 [7 Jun 21] C1)
C01_7 d/w - 10h/d - No HK 0 07-Jun-21 A 30-Mar-22
Hols - No B/O periods (was
310.A.EX.A348 Access to 3310/8 [7 Jun 21] C1)
C01_7 d/w - 10h/d - No HK 0 07-Jun-21 A 08-Nov-22
Hols - No B/O periods (was
310.A.EX.A376 Access to 3310/13 [7 Jun 21] C1)
C01_7 d/w - 10h/d - No HK 0 07-Jun-21 A 23-Jul-22
Hols - No B/O periods (was
310.A.EX.A328 Access to 3310/6A [4 Oct 21] C1)
C01_7 d/w - 10h/d - No HK 0 04-Oct-21 A 30-Mar-22
Hols - No B/O periods (was
310.A.EX.A368 Access to 3310/11 [9 Aug 21] C1)
C01_7 d/w - 10h/d - No HK 0 28-Oct-21 A 28-Mar-22
Hols - No B/O periods (was
310.A.EX.A366 Access to 3310/10A [9 Aug 21] C1)
C01_7 d/w - 10h/d - No HK 0 28-Oct-21 A 01-Sep-24
Hols - No B/O periods (was
310.A.EX.A332 Access to 3310/6B [3 Jan 22] C1)
C01_7 d/w - 10h/d - No HK 0 27-Mar-22* 03-Jan-22 -83
Hols - No B/O periods (was
310.A.EX.A336 Access to 3310/6C [7 Mar 22] C1)
C01_7 d/w - 10h/d - No HK 0 27-Mar-22* 07-Mar-22 -20
Hols - No B/O periods (was
310.A.EX.A356 Access to 3310/8B [7 Mar 22] C1)
C01_7 d/w - 10h/d - No HK 0 27-Mar-22* 07-Mar-22 -20
Hols - No B/O periods (was
310.A.EX.A364 Access to 3310/10 [31 Jan 22] C1)
C01_7 d/w - 10h/d - No HK 0 27-Mar-22* 31-Jan-22 -55
Hols - No B/O periods (was
310.A.EX.A384 Access to 3310/14 [29 Nov 21] C1)
C01_7 d/w - 10h/d - No HK 0 27-Mar-22* 29-Nov-21 -118
Hols - No B/O periods (was
310.A.EX.A374 Access to 3310/12A [4 Apr 22] C1)
C01_7 d/w - 10h/d - No HK 0 04-Apr-22* 04-Apr-22 0
Hols - No B/O periods (was
310.A.EX.A352 Access to 3310/8A [4 Jul 22] C1)
C01_7 d/w - 10h/d - No HK 0 04-Jul-22* 04-Jul-22 0
Hols - No B/O periods (was
310.A.EX.A372 Access to 3310/12 [4 Jul 22] C1)
C01_7 d/w - 10h/d - No HK 0 04-Jul-22* 04-Jul-22 0
Hols - No B/O periods (was
310.A.EX.A362 Access to 3310/9A [4 Jul 22] C1)
C01_7 d/w - 10h/d - No HK 0 04-Jul-22* 04-Jul-22 0
Hols - No B/O periods (was
C1)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:43
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 3 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.A.EX.A340 Access to 3310/7 [5 Sep 22] C01_7 d/w - 10h/d - No HK 0 05-Sep-22* 05-Sep-22 0
Hols - No B/O periods (was
310.A.EX.A344 Access to 3310/7A [5 Sep 22] C1)
C01_7 d/w - 10h/d - No HK 0 05-Sep-22* 05-Sep-22 0
Hols - No B/O periods (was
310.A.EX.A360 Access to 3310/9 [5 Sep 22] C1)
C01_7 d/w - 10h/d - No HK 0 05-Sep-22* 05-Sep-22 0
Hols - No B/O periods (was
310.A.EX.A380 Access to 3310/13A [5 Sep 22] C1)
C01_7 d/w - 10h/d - No HK 0 05-Sep-22* 05-Sep-22 0
Hols - No B/O periods (was
310.A.EX.A500 Access to Road Tunnel Plant Building B [5 Sep 22] C1)
C01_7 d/w - 10h/d - No HK 0 05-Sep-22* 05-Sep-22 0
Hols - No B/O periods (was
310.A.EX.A504 Access to Road Tunnel Plant Building C [5 Sep 22] C1)
C01_7 d/w - 10h/d - No HK 0 05-Sep-22* 04-Sep-22 0
Hols - No B/O periods (was
310.A.EX.A508 Access to South Section of EVT Tunnel at Existing Airport [5 Sep 22] C1)
C01_7 d/w - 10h/d - No HK 0 05-Sep-22* 05-Sep-22 0
Hols - No B/O periods (was
310.A.EX.A480 Access to Communication Rm CR358 (New Air Traffic Control Tower) [28 Nov 22] C1)
C01_7 d/w - 10h/d - No HK 0 28-Nov-22* 28-Nov-22 0
Hols - No B/O periods (was
310.A.EX.A316 Access to 3310/5 [2 Jan 23] C1)
C01_7 d/w - 10h/d - No HK 0 02-Jan-23* 02-Jan-23 0
Hols - No B/O periods (was
310.A.EX.A320 Access to 3310/5A [6 Mar 23] C1)
C01_7 d/w - 10h/d - No HK 0 06-Mar-23* 06-Mar-23 0
Hols - No B/O periods (was
310.A.EX.A484 Access to Communication Rm CR306 (Aircraft Fuel Dispenser Staging and Staff C1)
C01_7 d/w - 10h/d - No HK 0 27-Mar-23* 27-Mar-23 0
Facilities) [27 Mar 23] Hols - No B/O periods (was
310.A.EX.A488 Access to Data Centre [1 May 23] C1)
C01_7 d/w - 10h/d - No HK 0 01-May-23* 01-May-23 0
Hols - No B/O periods (was
310.A.EX.A492 Access to Communication Room CR308 (Electrical Substation 5) [3 Jul 23] C1)
C01_7 d/w - 10h/d - No HK 0 03-Jul-23* 03-Jul-23 0
Hols - No B/O periods (was
310.A.EX.A496 Access to Communication Room CR78 (Backup IAC) [17 Jul 23] C1)
C01_7 d/w - 10h/d - No HK 0 17-Jul-23* 17-Jul-23 0
Hols - No B/O periods (was
Vacate Dates [PS Appendix C2] C1)
C01_7 d/w - 10h/d - No HK Hols609
- No B/O periods
0 (was25-Dec-22
C1) 25-Aug-24 25-Dec-22 25-Aug-24 0
310.A.EX.A476 Vacate 3310/14 [25 Dec 22] C01_7 d/w - 10h/d - No HK 0 25-Dec-22* 25-Dec-22 0
Hols - No B/O periods (was
310.A.EX.A436 Vacate 3310/7A [25 Jun 23] C1)
C01_7 d/w - 10h/d - No HK 0 25-Jun-23* 25-Jun-23 0
Hols - No B/O periods (was
310.A.EX.A392 Vacate 3310/1 [25 Aug 24] C1)
C01_7 d/w - 10h/d - No HK 0 25-Aug-24* 25-Aug-24 0
Hols - No B/O periods (was
310.A.EX.A396 Vacate 3310/2 [25 Aug 24] C1)
C01_7 d/w - 10h/d - No HK 0 25-Aug-24* 25-Aug-24 0
Hols - No B/O periods (was
310.A.EX.A400 Vacate 3310/3 [25 Aug 24] C1)
C01_7 d/w - 10h/d - No HK 0 25-Aug-24* 25-Aug-24 0
Hols - No B/O periods (was
310.A.EX.A404 Vacate 3310/4 [25 Aug 24] C1)
C01_7 d/w - 10h/d - No HK 0 25-Aug-24* 25-Aug-24 0
Hols - No B/O periods (was
310.A.EX.A408 Vacate 3310/5 [25 Aug 24] C1)
C01_7 d/w - 10h/d - No HK 0 25-Aug-24* 25-Aug-24 0
Hols - No B/O periods (was
310.A.EX.A412 Vacate 3310/5A [25 Aug 24] C1)
C01_7 d/w - 10h/d - No HK 0 25-Aug-24* 25-Aug-24 0
Hols - No B/O periods (was
310.A.EX.A416 Vacate 3310/6 [25 Aug 24] C1)
C01_7 d/w - 10h/d - No HK 0 25-Aug-24* 25-Aug-24 0
Hols - No B/O periods (was
310.A.EX.A420 Vacate 3310/6A [25 Aug 24] C1)
C01_7 d/w - 10h/d - No HK 0 25-Aug-24* 25-Aug-24 0
Hols - No B/O periods (was
310.A.EX.A424 Vacate 3310/6B [25 Aug 24] C1)
C01_7 d/w - 10h/d - No HK 0 25-Aug-24* 25-Aug-24 0
Hols - No B/O periods (was
C1)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:43
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 4 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.A.EX.A428 Vacate 3310/6C [25 Aug 24] C01_7 d/w - 10h/d - No HK 0 25-Aug-24* 25-Aug-24 0
Hols - No B/O periods (was
310.A.EX.A432 Vacate 3310/7 [25 Aug 24] C1)
C01_7 d/w - 10h/d - No HK 0 25-Aug-24* 25-Aug-24 0
Hols - No B/O periods (was
310.A.EX.A440 Vacate 3310/8 [25 Aug 24] C1)
C01_7 d/w - 10h/d - No HK 0 25-Aug-24* 25-Aug-24 0
Hols - No B/O periods (was
310.A.EX.A444 Vacate 3310/8A [25 Aug 24] C1)
C01_7 d/w - 10h/d - No HK 0 25-Aug-24* 25-Aug-24 0
Hols - No B/O periods (was
310.A.EX.A448 Vacate 3310/8B [25 Aug 24] C1)
C01_7 d/w - 10h/d - No HK 0 25-Aug-24* 25-Aug-24 0
Hols - No B/O periods (was
310.A.EX.A452 Vacate 3310/9 [25 Aug 24] C1)
C01_7 d/w - 10h/d - No HK 0 25-Aug-24* 25-Aug-24 0
Hols - No B/O periods (was
310.A.EX.A456 Vacate 3310/10 [25 Aug 24] C1)
C01_7 d/w - 10h/d - No HK 0 25-Aug-24* 25-Aug-24 0
Hols - No B/O periods (was
310.A.EX.A460 Vacate 3310/11 [25 Aug 24] C1)
C01_7 d/w - 10h/d - No HK 0 25-Aug-24* 25-Aug-24 0
Hols - No B/O periods (was
310.A.EX.A464 Vacate 3310/12 [25 Aug 24] C1)
C01_7 d/w - 10h/d - No HK 0 25-Aug-24* 25-Aug-24 0
Hols - No B/O periods (was
310.A.EX.A468 Vacate 3310/13 [25 Aug 24] C1)
C01_7 d/w - 10h/d - No HK 0 25-Aug-24* 25-Aug-24 0
Hols - No B/O periods (was
310.A.EX.A472 Vacate 3310/13A [25 Aug 24] C1)
C01_7 d/w - 10h/d - No HK 0 25-Aug-24* 25-Aug-24 0
Hols - No B/O periods (was
310.A.EX.A458 Vacate 3310/10A [25 Aug 24] C1)
C01_7 d/w - 10h/d - No HK 0 25-Aug-24* 25-Aug-24 0
Hols - No B/O periods (was
310.A.EX.A454 Vacate 3310/9A [25 Aug 24] C1)
C01_7 d/w - 10h/d - No HK 0 25-Aug-24* 25-Aug-24 0
Hols - No B/O periods (was
310.A.EX.A466 Vacate 3310/12A [25 Aug 24] C1)
C01_7 d/w - 10h/d - No HK 0 25-Aug-24* 25-Aug-24 0
Hols - No B/O periods (was
Programme Milestone Dates [PS Appendix C4] C1)
C01_7 d/w - 10h/d - No HK Hols850
- No B/O periods
0 (was27-Mar-22
C1) 23-Jul-24 27-Feb-22 26-Jul-24 3
310.K.EX.A520 PMS06 - Comp ground improvement works in 3310/6A [27 Feb 22] C01_7 d/w - 10h/d - No HK 0 27-Mar-22* 27-Feb-22 -27
Hols - No B/O periods (was
310.K.EX.A500 PMS01 - Comp ground improvement works in 3310/10 [1 May 22] C1)
C01_7 d/w - 10h/d - No HK 0 01-May-22* 01-May-22 0
Hols - No B/O periods (was
310.K.EX.A592 PMS23 - Comp all works for Road Tunnel PBB and stat. apprv, consents, ready for use [4 C1)
C01_7 d/w - 10h/d - No HK 0 04-Dec-22* 04-Dec-22 0
Dec 22] Hols - No B/O periods (was
310.K.EX.A504 PMS02 - Comp West Box Culvert in 3310/10 & 3310/10A (excl. connection with ex. outfall C1)
C01_7 d/w - 10h/d - No HK 0 01-Jan-23* 01-Jan-23 0
no.3) [1 Jan 23] Hols - No B/O periods (was
310.K.EX.A596 PMS24 - Comp all works for Road Tunnel PBC and stat. apprv, consents, ready for use [1 C1)
C01_7 d/w - 10h/d - No HK 0 01-Jan-23* 01-Jan-23 0
Jan 23] Hols - No B/O periods (was
310.K.EX.A532 PMS09 - Comp seawall and ground improvement works in 3310/11 [5 Feb 23] C1)
C01_7 d/w - 10h/d - No HK 0 05-Feb-23* 05-Feb-23 0
Hols - No B/O periods (was
310.K.EX.A544 PMS13 - Comp all civil works for EVT in 3310/6 and 3310/6C (excl. a section of tunnel C1)
C01_7 d/w - 10h/d - No HK 0 06-Feb-23* 05-Feb-23 0
near ex. seawall) [5 Feb 23] Hols - No B/O periods (was
310.K.EX.A604 PMS25 - Comp all works for GSE Vehicle Wash Facility, obtain stat. apprv., consents, C1)
C01_7 d/w - 10h/d - No HK 0 05-Mar-23* 05-Mar-23 0
ready for use [5 Mar 23] Hols - No B/O periods (was
310.K.EX.A534 PMS10 - Comp all cable duct incl. drawpits along W-perimeter seawalls; provide access to C1)
C01_7 d/w - 10h/d - No HK 0 19-Mar-23* 19-Mar-23 0
CLP [19 Mar 23] Hols - No B/O periods (was
310.K.EX.A508 PMS03 - Comp the seawall and land filling works in area 3310/10A [2 Apr 23] C1)
C01_7 d/w - 10h/d - No HK 0 02-Apr-23* 02-Apr-23 0
Hols - No B/O periods (was
310.K.EX.A512 PMS04 - Comp box culvert no.3 and western box culvert in 3310/9 [2 Apr 23] C1)
C01_7 d/w - 10h/d - No HK 0 02-Apr-23* 02-Apr-23 0
Hols - No B/O periods (was
C1)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:43
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 5 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.K.EX.A608 PMS26 - Comp all works for Comm. Equip. Bldg D, obtain stat. apprv., consents, ready for C01_7 d/w - 10h/d - No HK 0 02-Apr-23* 02-Apr-23 0
use [2 Apr 23] Hols - No B/O periods (was
310.K.EX.A536 PMS11 - Comp land filling works in 3310/11 [30 Apr 23] C1)
C01_7 d/w - 10h/d - No HK 0 30-Apr-23* 30-Apr-23 0
Hols - No B/O periods (was
310.K.EX.A924 PMS30 - Comp all civil enabling works in 3310/IA/1 and provide access to Others to C1)
C01_7 d/w - 10h/d - No HK 0 30-Apr-23* 30-Apr-23 0
complete AGL [30 Apr 23] Hols - No B/O periods (was
310.K.EX.A612 PMS27 - Comp all works for GSE Battery Charging B, obtain stat. apprv., consents, ready C1)
C01_7 d/w - 10h/d - No HK 0 04-Jun-23* 03-Jun-23 0
for use [4 Jun 23] Hols - No B/O periods (was
310.K.EX.A548 PMS14 - Comp all civil works for EVT in 3310/7 [4 Jun 23] C1)
C01_7 d/w - 10h/d - No HK 0 04-Jun-23* 04-Jun-23 0
Hols - No B/O periods (was
310.K.EX.A516 PMS05 - Comp all civil enabling works in IA/6 and provide access for others [25 Jun 23] C1)
C01_7 d/w - 10h/d - No HK 0 25-Jun-23* 25-Jun-23 0
Hols - No B/O periods (was
310.K.EX.A616 PMS28 - Comp all works for Screening Facility, obtain stat. apprv., consents, ready for C1)
C01_7 d/w - 10h/d - No HK 0 02-Jul-23* 02-Jul-23 0
use [2 Jul 23] Hols - No B/O periods (was
310.K.EX.A928 PMS31 - Comp all civil enabling works in 3310/IA/7 and provide access to Others to C1)
C01_7 d/w - 10h/d - No HK 0 30-Jul-23* 30-Jul-23 0
complete AGL [30 Jul 23] Hols - No B/O periods (was
310.K.EX.A540 PMS12 - Comp all civil enabling works in IA/8 and provide access for others [27 Aug 23] C1)
C01_7 d/w - 10h/d - No HK 0 27-Aug-23* 27-Aug-23 0
Hols - No B/O periods (was
310.K.EX.A552 PMS15 - Comp all civil works for EVT in Ex. N-Runway [3 Sep 23] C1)
C01_7 d/w - 10h/d - No HK 0 03-Sep-23* 03-Sep-23 0
Hols - No B/O periods (was
310.K.EX.A932 PMS32 - Comp all civil enabling works in 3310/IA/4 and provide access to Others to C1)
C01_7 d/w - 10h/d - No HK 0 24-Sep-23* 24-Sep-23 0
complete AGL [24 Sep 23] Hols - No B/O periods (was
310.K.EX.A524 PMS07 - Comp eastern box culvert in 3310/6 and 3310/6A [1 Oct 23] C1)
C01_7 d/w - 10h/d - No HK 0 01-Oct-23* 01-Oct-23 0
Hols - No B/O periods (was
310.K.EX.A564 PMS18 - Comp all civil works for WVT [1 Oct 23] C1)
C01_7 d/w - 10h/d - No HK 0 01-Oct-23* 01-Oct-23 0
Hols - No B/O periods (was
310.K.EX.A568 PMS19 - Comp Section 1 Aviation Fuel Pipeline and incl. T&C [1 Oct 23] C1)
C01_7 d/w - 10h/d - No HK 0 01-Oct-23* 01-Oct-23 0
Hols - No B/O periods (was
310.K.EX.A528 PMS08 - Comp all civil enabling works in IA/2 and provide access for others [26 Nov 23] C1)
C01_7 d/w - 10h/d - No HK 0 26-Nov-23* 26-Nov-23 0
Hols - No B/O periods (was
310.K.EX.A556 PMS16 - Comp all civil enabling works in IA/3 and provide access for others [17 Dec 23] C1)
C01_7 d/w - 10h/d - No HK 0 17-Dec-23* 17-Dec-23 0
Hols - No B/O periods (was
310.K.EX.A580 PMS20 - Comp all civil enabling works in IA/5 and provide access for others [14 Jan 24] C1)
C01_7 d/w - 10h/d - No HK 0 14-Jan-24* 14-Jan-24 0
Hols - No B/O periods (was
310.K.EX.A620 PMS29 - Comp all works for Security Gatehouse B, obtain stat. apprv., consents, ready C1)
C01_7 d/w - 10h/d - No HK 0 18-Feb-24* 18-Feb-24 0
for use [18 Feb 24] Hols - No B/O periods (was
310.K.EX.A584 PMS21 - Comp Aviation Fuel Pipeline through WVT connect to ex. fuel system, T&C, stat. C1)
C01_7 d/w - 10h/d - No HK 0 30-Jun-24* 30-Jun-24 0
apprv, license [30 Jun 24] Hols - No B/O periods (was
310.K.EX.A560 PMS17 - Comp all works for EVT incl T&C, obtain all statutory approval & consent, ready C1)
C01_7 d/w - 10h/d - No HK 0 22-Jul-24 26-Jul-24 4
for use [28 Jul 24] Hols - No B/O periods (was
310.K.EX.A588 PMS22 - Comp all works for WVT incl T&C, stat. apprv, consents, ready for use [28 Jul C1)
C01_7 d/w - 10h/d - No HK 0 23-Jul-24 26-Jul-24 3
24] Hols - No B/O periods (was
Schedule of Submission Dates [PS Appendix C3] C1)
C01_7 d/w - 10h/d - No HK Hols693
- No B/O periods
0 (was
11-Jul-21
C1) A 04-Jun-23 26-Mar-22 04-Jun-23 0
310.K.EX.A700 01 - Submit - Site layout plan and logistic arrangement [11 Jul 21] C01_7 d/w - 10h/d - No HK 0 11-Jul-21 A 19-Apr-22
Hols - No B/O periods (was
310.K.EX.A720 02 - Submit - Interface Management Plan [11 Jul 21] C1)
C01_7 d/w - 10h/d - No HK 0 11-Jul-21 A 19-Apr-22
Hols - No B/O periods (was
310.K.EX.A724 03 - Submit - Detailed design and method statement of interim security fencing [11 Jul 21] C1)
C01_7 d/w - 10h/d - No HK 0 21-Jul-21 A 08-Jun-22
Hols - No B/O periods (was
310.K.EX.A728 05- Submit - Method statement for construction of ducting and drawpits [8 Aug 21] C1)
C01_7 d/w - 10h/d - No HK 0 07-Aug-21 A 08-Jun-22
Hols - No B/O periods (was
C1)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:43
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 6 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.K.EX.A732 06- Submit - Method statement for construction of taxiway pavement [8 Aug 21] C01_7 d/w - 10h/d - No HK 0 07-Aug-21 A 09-Nov-22
Hols - No B/O periods (was
310.K.EX.A736 07 - Submit - Method statement for construction of runway pavement [8 Aug 21] C1)
C01_7 d/w - 10h/d - No HK 0 07-Aug-21 A 09-Nov-22
Hols - No B/O periods (was
310.K.EX.A740 08 - Submit - Method statement incl. temp work design & ELS for construction of box C1)
C01_7 d/w - 10h/d - No HK 0 30-Aug-21 A 17-May-22
culverts [5 Sep 21] Hols - No B/O periods (was
310.K.EX.A725 04 - Submit - MS for the gnd improvement works under the new parallel taxiway incl C1)
C01_7 d/w - 10h/d - No HK 0 01-Sep-21 A 19-Apr-22
removal armour rock [11 Jul 21] Hols - No B/O periods (was
310.K.EX.A744 09 - Submit - MS incl. temp work design & ELS for rock wedge Gnd improvement, seawall C1)
C01_7 d/w - 10h/d - No HK 0 05-Sep-21 A 08-Nov-22
& land formation [5 Sep 21] Hols - No B/O periods (was
310.K.EX.A748 10 - Submit - Method statement for construction of civil wks for enhanced EVWL, AGL and C1)
C01_7 d/w - 10h/d - No HK 0 05-Sep-21 A 15-Mar-23
its asso. diversion [5 Sep 21] Hols - No B/O periods (was
310.K.EX.A752 11 - Submit - Method statement for land formation at western end of the existing C1)
C01_7 d/w - 10h/d - No HK 0 05-Sep-21 A 19-Apr-22
N-Runway [5 Sep 21] Hols - No B/O periods (was
310.K.EX.A764 14 - Submit - Method statement for construction of WVT [7 Nov 21] C1)
C01_7 d/w - 10h/d - No HK 0 07-Nov-21 A 26-Jul-22
Hols - No B/O periods (was
310.K.EX.A768 15 - Submit - Method statement for construction of EVT and Road Tunnel PBA [7 Nov 21] C1)
C01_7 d/w - 10h/d - No HK 0 16-Nov-21 A 20-Oct-22
Hols - No B/O periods (was
310.K.EX.A756 12 - Submit - Method statement for construction of Stage 1 aviation fuel direct buried C1)
C01_7 d/w - 10h/d - No HK 0 20-Nov-21 A 14-Jun-22
pipeline [7 Nov 21] Hols - No B/O periods (was
310.K.EX.A784 18 - Submit - Method statement for construction of pavement tie-in to ex. Taxiway E&F C1)
C01_7 d/w - 10h/d - No HK 0 06-Dec-21 A 06-Mar-23
incl AGL civil works [5 Dec 21] Hols - No B/O periods (was
310.K.EX.A772 16 - Submit - Method statement for installation and tie-in of various utilities to existing C1)
C01_7 d/w - 10h/d - No HK 0 08-Dec-21 A 26-Jan-23
network [5 Dec 21] Hols - No B/O periods (was
310.K.EX.A796 21 - Submit - Method statement for construction of tie-in of storm water box culvert [6 Mar C1)
C01_7 d/w - 10h/d - No HK 0 15-Dec-21 A 26-Jan-23
22] Hols - No B/O periods (was
310.K.EX.A780 17 - Submit - Method statement for construction of tie-in of box culvert [5 Dec 21] C1)
C01_7 d/w - 10h/d - No HK 0 20-Dec-21 A 26-Jan-23
Hols - No B/O periods (was
310.K.EX.A800 22 - Submit - Method statement for construction of Airport Authority ancillary buildings [6 C1)
C01_7 d/w - 10h/d - No HK 0 25-Feb-22 A 19-Apr-22
Mar 22] Hols - No B/O periods (was
310.K.EX.A788 19 - Submit - shop drawings and method statement for pre-cast unit of EVT and WVT [6 C1)
C01_7 d/w - 10h/d - No HK 0 27-Mar-22* 26-Mar-22 0
Mar 22] Hols - No B/O periods (was
310.K.EX.A792 20 - Submit - Method statement for installation works of Airport/Airfield Systems and C1)
C01_7 d/w - 10h/d - No HK 0 01-Apr-22* 01-Apr-22 0
equipment [6 Mar 22] Hols - No B/O periods (was
310.K.EX.A760 13 - Submit - shop drawings for interim fence and permanent fence C1)
C01_7 d/w - 10h/d - No HK 0 16-Apr-22 07-Jun-22 52
Hols - No B/O periods (was
310.K.EX.A808 24 - Submit - Method statement for construction of Stage 2 aviation fuel pipeline through C1)
C01_7 d/w - 10h/d - No HK 0 25-May-22* 25-May-22 0
WVT [5 Jun 22] Hols - No B/O periods (was
310.K.EX.A804 23 - Submit - Method statement for demolition of North Eastern Loading Quay and sloping C1)
C01_7 d/w - 10h/d - No HK 0 01-Jun-22* 01-Jun-22 0
seawall reinstatement [5 Jun 22] Hols - No B/O periods (was
310.K.EX.A812 25 - Submit - T&C Plan for Airport Authority ancillary buildings [4 Dec 22] C1)
C01_7 d/w - 10h/d - No HK 0 02-Nov-22* 02-Nov-22 0
Hols - No B/O periods (was
310.K.EX.A816 26 - Submit - T&C Plan for WVT (East to West Section) [4 Dec 22] C1)
C01_7 d/w - 10h/d - No HK 0 28-Nov-22* 28-Nov-22 0
Hols - No B/O periods (was
310.K.EX.A820 27 - Submit - T&C Plan for EVT [4 Dec 22] C1)
C01_7 d/w - 10h/d - No HK 0 03-Dec-22* 03-Dec-22 0
Hols - No B/O periods (was
310.K.EX.A824 28 - Submit - T&C Plan for Stage 1 and Stage 2 aviation fuel system [5 Mar 23] C1)
C01_7 d/w - 10h/d - No HK 0 05-Mar-23* 05-Mar-23 0
Hols - No B/O periods (was
310.K.EX.A828 29 - Submit - T&C Plan for readiness of the existing N-Runway for test flights [5 Mar 23] C1)
C01_7 d/w - 10h/d - No HK 0 05-Mar-23* 05-Mar-23 0
Hols - No B/O periods (was
310.K.EX.A832 30 - Submit - T&C Plan for readiness of the operational readiness of initial 3RS [4 Jun 23] C1)
C01_7 d/w - 10h/d - No HK 0 04-Jun-23* 04-Jun-23 0
Hols - No B/O periods (was
C1)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:43
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 7 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
Anticipated BD Exemption Dates [PS Appendix C5] C01_7 d/w - 10h/d - No HK Hols617
- No B/O periods
0 (was
20-Jun-21
C1) A 13-Feb-23 06-Mar-22 20-May-23 96
310.K.EX.A708 2. Stormwater drainage & box culvert system box culverts no. 18 - Structural Plan [15wks C01_7 d/w - 10h/d - No HK 0 20-Jun-21 A 25-May-22
after GI reports] Hols - No B/O periods (was
310.K.EX.A936 14. EVT Structural Plan [12 Sep 21] C1)
C01_7 d/w - 10h/d - No HK 0 12-Sep-21 A 10-Dec-22
Hols - No B/O periods (was
310.K.EX.A704 1. Stormwater drainage & box culvert system box culverts no. 18 - Drainage Plan [17 Oct C1)
C01_7 d/w - 10h/d - No HK 0 17-Oct-21 A 08-Jun-22
21] Hols - No B/O periods (was
310.K.EX.A712 3. Stormwater drainage & box culvert system box culverts no. 19 - Drainage Plan [17 Oct C1)
C01_7 d/w - 10h/d - No HK 0 17-Oct-21 A 08-May-23
21] Hols - No B/O periods (was
310.K.EX.A716 4. Stormwater drainage & box culvert system box culverts no. 19 - Structural Plan [17 Oct C1)
C01_7 d/w - 10h/d - No HK 0 17-Oct-21 A 16-May-22
21] Hols - No B/O periods (was
310.K.EX.A940 15. WVT Structural Plan [6 Mar 22] C1)
C01_7 d/w - 10h/d - No HK 0 27-Mar-22* 06-Mar-22 -20
Hols - No B/O periods (was
310.K.EX.A852 8. GSE Battery Charging B - Building Plan [17 Jul 22] C1)
C01_7 d/w - 10h/d - No HK 0 17-Jul-22* 17-Jul-22 0
Hols - No B/O periods (was
310.K.EX.A856 9. GSE Battery Charging B - Drainage Plan [17 Jul 22] C1)
C01_7 d/w - 10h/d - No HK 0 17-Jul-22* 17-Jul-22 0
Hols - No B/O periods (was
310.K.EX.A860 10. Maintenance Facilities Forecourt & coach staging A & Bus Stop - Drainage Plan [17 C1)
C01_7 d/w - 10h/d - No HK 0 17-Jul-22* 17-Jul-22 0
Jul 22] Hols - No B/O periods (was
310.K.EX.A864 11. Communications Equipment Building D - Drainage Plan [17 Jul 22] C1)
C01_7 d/w - 10h/d - No HK 0 17-Jul-22* 17-Jul-22 0
Hols - No B/O periods (was
310.K.EX.A868 12. GSE Storage Area - Drainage Plan [17 Jul 22] C1)
C01_7 d/w - 10h/d - No HK 0 17-Jul-22* 17-Jul-22 0
Hols - No B/O periods (was
310.K.EX.A872 13. GSE Vehicle Wash Facility - Drainage Plan [18 Sep 22] C1)
C01_7 d/w - 10h/d - No HK 0 18-Sep-22* 18-Sep-22 0
Hols - No B/O periods (was
310.K.EX.A840 5. Road Tunnel Plant Building A - Foundation Plan [25 Sep 22] C1)
C01_7 d/w - 10h/d - No HK 0 25-Sep-22* 25-Sep-22 0
Hols - No B/O periods (was
310.K.EX.A844 6. Road Tunnel Plant Building A - Superstructure Plan [25 Sep 22] C1)
C01_7 d/w - 10h/d - No HK 0 25-Sep-22* 25-Sep-22 0
Hols - No B/O periods (was
310.K.EX.A848 7. Road Tunnel Plant Building A - Drainage Plan [25 Sep 22] C1)
C01_7 d/w - 10h/d - No HK 0 25-Sep-22* 25-Sep-22 0
Hols - No B/O periods (was
Option Work C1)
C01_7 d/w - 10h/d - No HK Hols211
- No B/O periods
0 (was17-Jul-22
C1) 13-Feb-23 17-Jul-22 20-May-23 96
310.K.EX.A900 Option 7. C&ED Vehicle Search Bay - Foundation Plan [17 Jul 22] C01_7 d/w - 10h/d - No HK 0 17-Jul-22* 17-Jul-22 0
Hols - No B/O periods (was
310.K.EX.A904 Option 8. C&ED Vehicle Search Bay - Superstructure Plan [17 Jul 22] C1)
C01_7 d/w - 10h/d - No HK 0 17-Jul-22* 17-Jul-22 0
Hols - No B/O periods (was
310.K.EX.A908 Option 9. C&ED Vehicle Traffic Control Kiosk - Foundation Plan [17 Jul 22] C1)
C01_7 d/w - 10h/d - No HK 0 17-Jul-22* 17-Jul-22 0
Hols - No B/O periods (was
310.K.EX.A912 Option 10. C&ED Vehicle Traffic Control Kiosk - Superstructure Plan [17 Jul 22] C1)
C01_7 d/w - 10h/d - No HK 0 17-Jul-22* 17-Jul-22 0
Hols - No B/O periods (was
310.K.EX.A916 Option 11. C&ED Operational Office and Kennel Area - Drainage Plan [18 Sep 22] C1)
C01_7 d/w - 10h/d - No HK 0 18-Sep-22* 18-Sep-22 0
Hols - No B/O periods (was
310.K.EX.A876 Option 1. CAD Localizer Equipment Building - Foundation Plan [15 wks after receipt of C1)
C01_7 d/w - 10h/d - No HK 0 17-Dec-22 21-Dec-22 4
Gnd Invest. Report] Hols - No B/O periods (was
310.K.EX.A880 Option 2. CAD Localizer Equipment Building - Superstructure Plan [15 wks after receipt of C1)
C01_7 d/w - 10h/d - No HK 0 17-Dec-22 10-Jan-23 24
Gnd Invest. Report] Hols - No B/O periods (was
310.K.EX.A884 Option 3. CAD Localizer Equipment Building - Drainage Plan [15 wks after receipt of Gnd C1)
C01_7 d/w - 10h/d - No HK 0 17-Dec-22 20-May-23 154
Invest. Report] Hols - No B/O periods (was
310.K.EX.A888 Option 4. Police Equipment Room - Foundation Plan [15 wks after receipt of Gnd Invest. C1)
C01_7 d/w - 10h/d - No HK 0 13-Feb-23 13-Feb-23 0
Report] Hols - No B/O periods (was
310.K.EX.A892 Option 5. Police Equipment Room - Superstructure Plan [15 wks after receipt of Gnd C1)
C01_7 d/w - 10h/d - No HK 0 13-Feb-23 13-Feb-23 0
Invest. Report] Hols - No B/O periods (was
C1)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:43
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 8 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.K.EX.A896 Option 6. Police Equipment Room - Drainage Plan [15 wks after receipt of Gnd Invest. C01_7 d/w - 10h/d - No HK 0 13-Feb-23 13-Feb-23 0
Report] Hols - No B/O periods (was
Cost Centre #01 - Preliminaries and General Requirements C1)
C01_7 d/w - 10h/d - No HK Hols1167
- No B/O periods
0 (was
20-Jun-21
C1) A 30-Aug-24 30-Mar-22 01-Sep-24 2
CC#1 ----- Design and Submission ----- C01_7 d/w - 10h/d - No HK Hols741
- No B/O periods
0 (was
21-Jun-21
C1) A 02-Jul-23 31-Mar-22 30-Jun-24 364
Management Plan Submission C01_7 d/w - 10h/d - No HK Hols283
- No B/O periods
0 (was
21-Jun-21
C1) A 31-Mar-22 31-Mar-22 30-Jun-24 822
01 - Site Layout Plan and Logistics Arrangement [PS App C1; 5wks] C01_7 d/w - 10h/d - No HK Hols 0- No B/O periods
0 (was
11-Jul-21
C1) A 11-Jul-21 A 19-Apr-22 19-Apr-22
310.D.EX.A921 Site Layout Plan and Logistics Management - submit document to PM [PS App C1, 5wks] C01_7 d/w - 10h/d - No HK 0 11-Jul-21 A 19-Apr-22
Hols - No B/O periods (was
02 - Interface Management Plan [PS App C1; 5wks] C1)
C01_7 d/w - 10h/d - No HK Hols 0- No B/O periods
0 (was
11-Jul-21
C1) A 11-Jul-21 A 19-Apr-22 19-Apr-22
310.D.EX.A925 Interface Management Plan - Submit document to PM [PS App C1, 5wks] C01_7 d/w - 10h/d - No HK 0 11-Jul-21 A 19-Apr-22
Hols - No B/O periods (was
Site Management Plan [PS13.2.1; within 21d of starting date] C1)
C01_7 d/w - 10h/d - No HK Hols 0- No B/O periods
0 (was
27-Jun-21
C1) A 27-Jun-21 A 19-Apr-22 19-Apr-22
310.D.EX.A929 Site Management Plan - Submit document to PM [PS13.2.1; within 21d of starting date] C01_7 d/w - 10h/d - No HK 0 27-Jun-21 A 19-Apr-22
Hols - No B/O periods (was
Management Quality Plan [PS11.2; within 28d of starting date] C1)
C01_7 d/w - 10h/d - No HK Hols 0- No B/O periods
0 (was
05-Jul-21
C1) A 05-Jul-21 A 30-Jun-24 30-Jun-24
310.D.EX.A945 Management Quality Plan - Submit document to PM [PS11.2; within 28d of starting date] C01_7 d/w - 10h/d - No HK 0 05-Jul-21 A 30-Jun-24
Hols - No B/O periods (was
Design Quality Plan [PS11.3; within 28d of starting date] C1)
C01_7 d/w - 10h/d - No HK Hols 0- No B/O periods
0 (was
05-Jul-21
C1) A 05-Jul-21 A 30-Jun-24 30-Jun-24
310.D.EX.A949 Design Quality Plan - Submit document to PM [PS11.2; within 28d of starting date] C01_7 d/w - 10h/d - No HK 0 05-Jul-21 A 30-Jun-24
Hols - No B/O periods (was
Project Health and Safety Management Plan [PS12.1; within 14d of starting date] C1)
C01_7 d/w - 10h/d - No HK Hols 0- No B/O periods
0 (was
21-Jun-21
C1) A 21-Jun-21 A 30-Jun-24 30-Jun-24
310.D.EX.A953 Project Health and Safety Management Plan - Submit document to PM [PS12.1; within C01_7 d/w - 10h/d - No HK 0 21-Jun-21 A 30-Jun-24
14d of starting date] Hols - No B/O periods (was
Project Health and Safety Management Manual [PS12.1; within 14d of starting date] C1)
C01_7 d/w - 10h/d - No HK Hols 0- No B/O periods
0 (was
21-Jun-21
C1) A 21-Jun-21 A 30-Jun-24 30-Jun-24
310.D.EX.A956 Project Health and Safety Management Manual - Submit document to PM [PS12.1; within C01_7 d/w - 10h/d - No HK 0 21-Jun-21 A 30-Jun-24
14d of starting date] Hols - No B/O periods (was
Detail Environmental Management Plan [PS14.1.4; within 28d of starting date] C1)
C01_7 d/w - 10h/d - No HK Hols 0- No B/O periods
0 (was
05-Jul-21
C1) A 05-Jul-21 A 30-Jun-24 30-Jun-24
310.D.EX.A960 Detail Environmental Management Plan - Submit document to PM [PS14.1.4; within 28d C01_7 d/w - 10h/d - No HK 0 05-Jul-21 A 30-Jun-24
of starting date] Hols - No B/O periods (was
Sustainable Construction Management Plan [PS14.3.2; within 2M of starting date] C1)
C01_7 d/w - 10h/d - No HK Hols 0- No B/O periods
0 (was
18-Aug-21
C1) A 18-Aug-21 A 30-Jun-24 30-Jun-24
310.D.EX.A964 Sustainable Construction Management Plan - Submit document to PM [PS14.3.2; within C01_7 d/w - 10h/d - No HK 0 18-Aug-21 A 30-Jun-24
2M of starting date] Hols - No B/O periods (was
Contract-specific Waste Management Plan (WMP) C1)
C01_7 d/w - 10h/d - No HK Hols 0- No B/O periods
0 (was
05-Jul-21
C1) A 05-Jul-21 A 30-Jun-24 30-Jun-24
310.D.EX.A1004 Contract Specific Waste Management Plan - Submit document to PM [PS14.1.6; within C01_7 d/w - 10h/d - No HK 0 05-Jul-21 A 30-Jun-24
28d of starting date] Hols - No B/O periods (was
Construction and Demolition Material Management Plan C1)
C01_7 d/w - 10h/d - No HK Hols 0- No B/O periods
0 (was31-Mar-22
C1) 31-Mar-22 31-Mar-22 31-Mar-22 0
310.D.EX.A1008 Construction and Demolition Material Management Plan - Submit document to PM C01_7 d/w - 10h/d - No HK 0 31-Mar-22* 31-Mar-22 0
Hols - No B/O periods (was
Site Management Plan for Trip Ticket Implementation C1)
C01_7 d/w - 10h/d - No HK Hols 0- No B/O periods
0 (was
28-Oct-21
C1) A 28-Oct-21 A 30-Jun-24 30-Jun-24
310.D.EX.A1012 Site Management Plan for Trip Ticket Implementation - Submit document to PM C01_7 d/w - 10h/d - No HK 0 28-Oct-21 A 30-Jun-24
Hols - No B/O periods (was
Contract-specific Spill Response Plan (SRP) C1)
C01_7 d/w - 10h/d - No HK Hols 0- No B/O periods
0 (was
05-Jul-21
C1) A 05-Jul-21 A 30-Jun-24 30-Jun-24
310.D.EX.A1016 Contract-specific Spill Response Plan (SRP) - Submit document to PM C01_7 d/w - 10h/d - No HK 0 05-Jul-21 A 30-Jun-24
Hols - No B/O periods (was
Design Management Plan [PS15.2.5; within 1M of starting date] C1)
C01_7 d/w - 10h/d - No HK Hols 0- No B/O periods
0 (was
08-Jul-21
C1) A 08-Jul-21 A 30-Jun-24 30-Jun-24
310.D.EX.A968 Design Management Plan - Submit document to PM [PS15.2.5; within 1M of starting date] C01_7 d/w - 10h/d - No HK 0 08-Jul-21 A 30-Jun-24
Hols - No B/O periods (was
Subcontractor Management Plan [PS22.1.1; within 28d of starting date] C1)
C01_7 d/w - 10h/d - No HK Hols 0- No B/O periods
0 (was
02-Jul-21
C1) A 02-Jul-21 A 30-Jun-24 30-Jun-24
310.D.EX.A972 Subcontractor Management Plan - Submit document to PM [PS22.1.1; within 28d of C01_7 d/w - 10h/d - No HK 0 02-Jul-21 A 30-Jun-24
starting date] Hols - No B/O periods (was
C1)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:43
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 9 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
BIM Project Execution Plan (PXP) [PS26.1; within 1M of starting date] C01_7 d/w - 10h/d - No HK Hols 0- No B/O periods
0 (was
08-Jul-21
C1) A 08-Jul-21 A 30-Jun-24 30-Jun-24
310.D.EX.A976 BIM Project Execution Plan (PXP) - Submit document to PM [PS26.1; within 1M of C01_7 d/w - 10h/d - No HK 0 08-Jul-21 A 30-Jun-24
starting date] Hols - No B/O periods (was
Risk Management Plan [PS27.1; within 1M after starting date] C1)
C01_7 d/w - 10h/d - No HK Hols 0- No B/O periods
0 (was
08-Jul-21
C1) A 08-Jul-21 A 30-Jun-24 30-Jun-24
310.D.EX.A980 Risk Management Plan - Submit document to PM [PS27.1; within 1M after starting date] C01_7 d/w - 10h/d - No HK 0 08-Jul-21 A 30-Jun-24
Hols - No B/O periods (was
Initial Risk Register [PS27.3; within 1M after starting date] C1)
C01_7 d/w - 10h/d - No HK Hols 0- No B/O periods
0 (was
07-Jul-21
C1) A 07-Jul-21 A 19-Apr-22 19-Apr-22
310.D.EX.A984 Initial Risk Register - Submit document to PM [PS27.3; within 1M after starting date] C01_7 d/w - 10h/d - No HK 0 07-Jul-21 A 19-Apr-22
Hols - No B/O periods (was
Initial Subcontracting Strategy for Providing the Works [PS32.3; within 28d of starting date] C1)
C01_7 d/w - 10h/d - No HK Hols 0- No B/O periods
0 (was
04-Jul-21
C1) A 04-Jul-21 A 19-Apr-22 19-Apr-22
310.D.EX.A988 Initial Subcontracting Strategy for Providing the Works - Submit document to PM [PS32.3; C01_7 d/w - 10h/d - No HK 0 04-Jul-21 A 19-Apr-22
within 28d of starting date] Hols - No B/O periods (was
Programme Submission C1)
C01_7 d/w - 10h/d - No HK Hols 0- No B/O periods
0 (was
27-Jun-21
C1) A 27-Jun-21 A 19-Apr-22 19-Apr-22
Programme [PS10.1.1; within 21d of starting date] C01_7 d/w - 10h/d - No HK Hols 0- No B/O periods
0 (was
27-Jun-21
C1) A 27-Jun-21 A 19-Apr-22 19-Apr-22
310.D.EX.A933 Programme - Submit document to PM [PS10.1.1; within 21d of starting date] C01_7 d/w - 10h/d - No HK 0 27-Jun-21 A 19-Apr-22
Hols - No B/O periods (was
Testing and Commissioning Plan for the readiness of the existing North Runway for test flights C1)
C01_7 d/w - 10h/d - No HK Hols28
- No B/O periods
0 (was05-Mar-23
C1) 02-Apr-23 05-Mar-23 29-Mar-24 362
310.D.EX.A130 T&C Plan for readiness of Ex. North Runway for test flights - Preparation of T&C plan C01_7 d/w - 10h/d - No HK 0 05-Mar-23 05-Mar-23 0
Hols - No B/O periods (was
310.D.EX.A992 T&C Plan for readiness of Ex. North Runway for test flights - PM review and acceptance C1)
C01_7 d/w - 10h/d - No HK 0 02-Apr-23 29-Mar-24 362
Hols - No B/O periods (was
Testing and commissioning plan for the operational readiness of initial 3RS C1)
C01_7 d/w - 10h/d - No HK Hols28
- No B/O periods
0 (was04-Jun-23
C1) 02-Jul-23 04-Jun-23 29-Mar-24 271
310.D.EX.A1000 T&C Plan for Operational Readiness of Initial 3RS - Preparation of T&C Plan C01_7 d/w - 10h/d - No HK 0 04-Jun-23 04-Jun-23 0
Hols - No B/O periods (was
310.D.EX.A996 T&C Plan for Operational Readiness of Initial 3RS - PM review and acceptance C1)
C01_7 d/w - 10h/d - No HK 0 02-Jul-23 29-Mar-24 271
Hols - No B/O periods (was
CC#1 ----- Procurement ----- C1)
C01_7 d/w - 10h/d - No HK Hols17
- No B/O periods
0 (was
20-Jun-21
C1) A 07-Jul-21 A 19-Apr-22 30-Jun-24
Appointment of Coordination Manager [PS9.1 within 14d of starting date] C01_7 d/w - 10h/d - No HK Hols 0- No B/O periods
0 (was
20-Jun-21
C1) A 20-Jun-21 A 19-Apr-22 19-Apr-22
310.P.EX.A010 Appointment of Coordination Manager [PS9.1; within 14d of starting date] C01_7 d/w - 10h/d - No HK 0 20-Jun-21 A 19-Apr-22
Hols - No B/O periods (was
Appointment of BIM Manager [PS26.2 within 1M of starting date] C1)
C01_7 d/w - 10h/d - No HK Hols 0- No B/O periods
0 (was
07-Jul-21
C1) A 07-Jul-21 A 30-Jun-24 30-Jun-24
310.P.EX.A014 Appointment of BIM Manager [PS26.2; within 1M of starting date] C01_7 d/w - 10h/d - No HK 0 07-Jul-21 A 30-Jun-24
Hols - No B/O periods (was
Appointment of Risk Manager [PS27.2 within 1M of starting date] C1)
C01_7 d/w - 10h/d - No HK Hols 0- No B/O periods
0 (was
07-Jul-21
C1) A 07-Jul-21 A 19-Apr-22 19-Apr-22
310.P.EX.A018 Appointment of Risk Manager [PS27.2; within 1M of starting date] C01_7 d/w - 10h/d - No HK 0 07-Jul-21 A 19-Apr-22
Hols - No B/O periods (was
CC#1 ----- Construction ----- C1)
C01_7 d/w - 10h/d - No HK Hols404
- No B/O periods
0 (was
30-Jun-21
C1) A 08-Aug-22 30-Mar-22 01-Sep-22 24
Provide Hygene and Welfare Facility for Workers [PS13.9.1 within 28d of starting date] C01_7 d/w - 10h/d - No HK Hols 0- No B/O periods
0 (was
30-Jun-21
C1) A 30-Jun-21 A 30-Mar-22 30-Mar-22
310.C.EX.A100 Provide Hygiene and Welfare Facility for Workers [PS13.9.1; within 28d of starting date] C01_7 d/w - 10h/d - No HK 0 30-Jun-21 A 30-Mar-22
Hols - No B/O periods (was
Provide Land Transportation for Client, PM ... [PS24.1.1 within 2M of starting date] C1)
C01_7 d/w - 10h/d - No HK Hols 0- No B/O periods
0 (was
30-Sep-21
C1) A 30-Sep-21 A 30-Mar-22 30-Mar-22
310.C.EX.A104 Provide Land Transportation for Client, PM... [PS24.1.1; within 2M of starting date] C01_7 d/w - 10h/d - No HK 0 30-Sep-21 A 30-Mar-22
Hols - No B/O periods (was
Application of AHR exemption from CAD for infringement of the gazetted AHRP after Ex. N-Runway close C1)
C01_7 d/w - 10h/d - No HK Hols135
- No B/O periods
0 (was27-Mar-22
C1) 08-Aug-22 20-Apr-22 01-Sep-22 24
310.C.EX.A108 Exemption of AHRP after Ex. N-Runway closure - Prepare application document C01_7 d/w - 10h/d - No HK 30 27-Mar-22 25-Apr-22 20-Apr-22 19-May-22 24
Hols - No B/O periods (was
310.C.EX.A112 Exemption of AHRP after Ex. N-Runway closure - PM review and comment C1)
C01_7 d/w - 10h/d - No HK 28 26-Apr-22 23-May-22 20-May-22 16-Jun-22 24
Hols - No B/O periods (was
310.C.EX.A116 Exemption of AHRP after Ex. N-Runway closure - Address PM comments C1)
C01_7 d/w - 10h/d - No HK 21 24-May-22 13-Jun-22 17-Jun-22 07-Jul-22 24
Hols - No B/O periods (was
C1)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:43
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 10 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.EX.A120 Exemption of AHRP after Ex. N-Runway closure - PM accept C01_7 d/w - 10h/d - No HK 28 14-Jun-22 11-Jul-22 08-Jul-22 04-Aug-22 24
Hols - No B/O periods (was
310.C.EX.A124 Exemption of AHRP after Ex. N-Runway closure - CAD review and approval C1)
C01_7 d/w - 10h/d - No HK 28 12-Jul-22 08-Aug-22 05-Aug-22 01-Sep-22 24
Hols - No B/O periods (was
CC#1 ----- Testing and Commissioning ----- C1)
C01_7 d/w - 10h/d - No HK Hols156
- No B/O periods
0 (was28-Mar-24
C1) 30-Aug-24 30-Mar-24 01-Sep-24 2
Testing and Commissioning for readiness of the existing North Runway to test flights C01_7 d/w - 10h/d - No HK Hols146
- No B/O periods
0 (was28-Mar-24
C1) 20-Aug-24 30-Mar-24 25-Aug-24 5
310.C.EX.A324 Testing and Commissioning for readiness of the existing North Runway to test flights C01_7 d/w - 10h/d - No HK 90 28-Mar-24 25-Jun-24 30-Mar-24 27-Jun-24 2
Hols - No B/O periods (was
310.C.EX.A944 Tentative Commencement Date of Flight Test for Middle Runway [PS 10.2.82] C1)
C01_7 d/w - 10h/d - No HK 0 26-Jun-24 28-Jun-24 2
Hols - No B/O periods (was
310.C.EX.A948 Tentative Flight test period [8 weeks, PS 10.2.82] (remove security fence along the cross C1)
C01_7 d/w - 10h/d - No HK 56 26-Jun-24 20-Aug-24 28-Jun-24 22-Aug-24 2
over taxiway, PS 10.2.83) Hols - No B/O periods (was
310.C.EX.A320 Miscellaneous Works & Final T&C for the Operational Readiness of Initial 3RS to achieve C1)
C01_7 d/w - 10h/d - No HK 27 24-Jul-24 19-Aug-24 27-Jul-24 22-Aug-24 3
KD-12 Hols - No B/O periods (was
310.C.EX.A952 Achieve KD-12 after flight test completed C1)
C01_7 d/w - 10h/d - No HK 0 20-Aug-24 25-Aug-24 5
Hols - No B/O periods (was
Testing and commissioning for the operational readiness of initial 3RS C1)
C01_7 d/w - 10h/d - No HK Hols10
- No B/O periods
0 (was21-Aug-24
C1) 30-Aug-24 23-Aug-24 01-Sep-24 2
310.C.EX.A950 Remove Remaining Equipment off site, Miscellaneous works to achieve KD-13 C01_7 d/w - 10h/d - No HK 10 21-Aug-24 30-Aug-24 23-Aug-24 01-Sep-24 2
Hols - No B/O periods (was
310.C.EX.A951 Achieve KD-13 C1)
C01_7 d/w - 10h/d - No HK 0 30-Aug-24 01-Sep-24 2
Hols - No B/O periods (was
Cost Centre #02 - Land Formation and Ground Treatment Works C1) 932 91 12-Jun-21 A 30-Jul-24 28-Mar-22 25-Aug-24 22
CC#02 ----- Design and Others----- C01_7 d/w - 10h/d - No HK Hols388
- No B/O periods
0 (was
06-Aug-21
C1) A 28-Aug-22 28-Mar-22 01-Sep-22 4
Reclamation - Design of Temporary Marine Platform Erection C01_7 d/w - 10h/d - No HK Hols30
- No B/O periods
0 (was
06-Aug-21
C1) A 15-Oct-21 A 28-Mar-22 28-Mar-22
310.D.G3.F010 Marine Platform Design - prepare and submit with ICE C01_7 d/w - 10h/d - No HK 30 06-Aug-21 A 15-Oct-21 A 28-Mar-22 28-Mar-22
Hols - No B/O periods (was
Reclamation - Demolition Plan for Demolish Approach Light Columns and Bridge C1)
C01_7 d/w - 10h/d - No HK Hols246
- No B/O periods
0 (was
26-Dec-21
C1) A 28-Aug-22 31-Mar-22 01-Sep-22 4
310.D.G3.F122 Demolition Plan for Demolish Approach Light Bridge - prepare design and submit with ICE C01_7 d/w - 10h/d - No HK 60 26-Dec-21 A 27-Apr-22 31-Mar-22 01-May-22 4
Hols - No B/O periods (was
310.D.G3.F126 Demolition Plan for Demolish Approach Light Bridge - PM, AP, RSE reviewing C1)
C01_7 d/w - 10h/d - No HK 28 28-Apr-22 25-May-22 02-May-22 29-May-22 4
Hols - No B/O periods (was
310.D.G3.F130 Demolition Plan for Demolish Approach Light Bridge - ICC, M&VC review design and C1)
C01_7 d/w - 10h/d - No HK 21 26-May-22 15-Jun-22 30-May-22 19-Jun-22 4
issue check certificates Hols - No B/O periods (was
310.D.G3.F146 Demolition Plan for Demolish Approach Light Bridge - BD approve C1)
C01_7 d/w - 10h/d - No HK 60 16-Jun-22 14-Aug-22 20-Jun-22 18-Aug-22 4
Hols - No B/O periods (was
310.D.G3.F150 Demolition Plan for Demolish Approach Light Bridge - prepare and submit Form BA8 and C1)
C01_7 d/w - 10h/d - No HK 7 15-Aug-22 21-Aug-22 19-Aug-22 25-Aug-22 4
grant consent Hols - No B/O periods (was
310.D.G3.F154 Demolition Plan for Demolish Approach Light Bridge - prepare and submit Form BA10 to C1)
C01_7 d/w - 10h/d - No HK 7 22-Aug-22 28-Aug-22 26-Aug-22 01-Sep-22 4
notify work commencement Hols - No B/O periods (was
Reclamation - Notification of works C1)
C01_7 d/w - 10h/d - No HK Hols 7- No B/O periods
0 (was
26-Aug-21
C1) A 01-Sep-21 A 19-Apr-22 19-Apr-22
310.D.R0.L356 Reclamation - Submit Form BA10 for notification of DJM commencement C01_7 d/w - 10h/d - No HK 7 26-Aug-21 A 01-Sep-21 A 19-Apr-22 19-Apr-22
Hols - No B/O periods (was
CC#02 ----- Method Statement----- C1)
C01_7 d/w - 10h/d - No HK Hols383
- No B/O periods
0 (was
12-Jun-21
C1) A 29-Jun-22 28-Mar-22 03-Dec-23 522
MS no. 9 - Method Statement for Seawall Construction incl. temp Platform Erection C01_7 d/w - 10h/d - No HK Hols205
- No B/O periods
0 (was
06-Aug-21
C1) A 26-Nov-21 A 28-Mar-22 28-Mar-22
310.D.G3.F082 MS no.9 - for Seawall construction incl temp Platform erection - prepare document C01_7 d/w - 10h/d - No HK 30 06-Aug-21 A 11-Sep-21 A 28-Mar-22 28-Mar-22
Hols - No B/O periods (was
310.D.G3.F086 MS no.9 - for Seawall construction incl temp platform erection - PM review and accept C1)
C01_7 d/w - 10h/d - No HK 28 13-Sep-21 A 26-Nov-21 A 28-Mar-22 28-Mar-22
Hols - No B/O periods (was
MS no. 9 - Method Statement for Temp Wks & ELS for Rock Wedge Ground Improvement, etc C1)
C01_7 d/w - 10h/d - No HK Hols58
- No B/O periods
0 (was
06-Aug-21
C1) A 18-Nov-21 A 28-Mar-22 28-Mar-22
310.D.G3.F158 MS no.9 - for Temp Works & ELS for Rock Wedge Ground Improvement, Seawall & land C01_7 d/w - 10h/d - No HK 30 06-Aug-21 A 11-Sep-21 A 28-Mar-22 28-Mar-22
formation - prepare document Hols - No B/O periods (was
C1)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:43
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 11 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.G3.F162 MS no.9 - for Temp Works & ELS for Rock Wedge Ground Improvement, Seawall & land C01_7 d/w - 10h/d - No HK 28 12-Sep-21 A 18-Nov-21 A 28-Mar-22 28-Mar-22
formation - PM review and accept Hols - No B/O periods (was
MS no. 4 - Remaining Ground Improvement Works Under the New Taxiway C1)
C01_7 d/w - 10h/d - No HK Hols58
- No B/O periods
0 (was
12-Jun-21
C1) A 17-Sep-21 A 28-Mar-22 28-Mar-22
310.D.G3.F098 MS no.4 - Remaining Ground Improvement Works Under the New Taxiway - prepare C01_7 d/w - 10h/d - No HK 30 12-Jun-21 A 11-Jul-21 A 28-Mar-22 28-Mar-22
document Hols - No B/O periods (was
310.D.G3.F102 MS no.4 - Remaining Ground Improvement Works Under the New Taxiway - PM review C1)
C01_7 d/w - 10h/d - No HK 28 12-Jul-21 A 17-Sep-21 A 28-Mar-22 28-Mar-22
and accept Hols - No B/O periods (was
MS no. 11 - Method Statement for Land Formation at the Western end of Existing North Runway C1)
C01_7 d/w - 10h/d - No HK Hols58
- No B/O periods
0 (was
06-Aug-21
C1) A 03-Nov-21 A 19-Apr-22 19-Apr-22
310.D.G3.F090 MS no.11 - for Land Formation at the Western end of Existing North Runway - prepare
C01_7 d/w - 10h/d - No HK 30 06-Aug-21 A 11-Sep-21 A 19-Apr-22 19-Apr-22
document Hols - No B/O periods (was
310.D.G3.F094 MS no.11 - for Land Formation at the Western end of Existing North Runway - PM review C1)
C01_7 d/w - 10h/d - No HK 28 12-Sep-21 A 03-Nov-21 A 19-Apr-22 19-Apr-22
and accept Hols - No B/O periods (was
MS no. 23 - Method Statement for Demolition of NE Loading Quay and Seawall Reinstatement C1)
C01_7 d/w - 10h/d - No HK Hols58
- No B/O periods
0 (was03-May-22
C1) 29-Jun-22 03-May-22 03-Dec-23 522
310.D.TX.F140 MS no.23 - Method Statement for Demolition of NE Loading Quay and Seawall C01_7 d/w - 10h/d - No HK 30 03-May-22 01-Jun-22 03-May-22 01-Jun-22 0
Reinstatement - prepare document Hols - No B/O periods (was
310.D.TX.F144 MS no.23 - Method Statement for Demolition of NE Loading Quay and Seawall C1)
C01_7 d/w - 10h/d - No HK 28 02-Jun-22 29-Jun-22 06-Nov-23 03-Dec-23 522
Reinstatement - PM review and accept Hols - No B/O periods (was
CC#02 ----- Procurement ----- C1)
C01_7 d/w - 10h/d - No HK Hols281
- No B/O periods
0 (was
09-Aug-21
C1) A 06-Jan-22 A 28-Mar-22 02-Sep-22
Subletting - Reclamation Works in Works Area 3310/11 & 3310/08 C01_7 d/w - 10h/d - No HK Hols281
- No B/O periods
0 (was
09-Aug-21
C1) A 06-Jan-22 A 28-Mar-22 02-Sep-22
310.P.G3.F118 3310/11 Subletting - Temporary Working Platform for Marine Works - Award sub-contract C01_7 d/w - 10h/d - No HK 90 09-Aug-21 A 15-Nov-21 A 28-Mar-22 28-Mar-22
Hols - No B/O periods (was
310.P.EX.H190 Area E2b & E5: Subletting - Cement Supply for DJM - Award supplier C1)
C01_7 d/w - 10h/d - No HK 17 17-Sep-21 A 12-Nov-21 A 26-Apr-22 26-Apr-22
Hols - No B/O periods (was
310.P.G3.F166 3310/11Subletting - Ground Improvement Works DJM - Award sub-contract C1)
C01_7 d/w - 10h/d - No HK 17 17-Sep-21 A 18-Nov-21 A 28-Mar-22 28-Mar-22
Hols - No B/O periods (was
310.P.EX.H189 Area E2b & E5: Subletting - Ground Improvement Works DJM - Award sub-contract C1)
C01_7 d/w - 10h/d - No HK 17 17-Sep-21 A 18-Nov-21 A 30-Mar-22 30-Mar-22
Hols - No B/O periods (was
310.P.G3.F214 3310/11 Subletting - Removal of Existing Structures - Stage 1&2 C1)
C01_7 d/w - 10h/d - No HK 90 17-Sep-21 A 06-Jan-22 A 02-Sep-22 02-Sep-22
Preparation,Submission& Apvl,Tender&Award Hols - No B/O periods (was
310.P.G3.F218 3310/11 Subletting - Cement Supply for DJM - Award supplier C1)
C01_7 d/w - 10h/d - No HK 17 26-Sep-21 A 18-Nov-21 A 28-Mar-22 28-Mar-22
Hols - No B/O periods (was
310.P.G3.F190 Subletting - Land Formation in Works Area 3310/11 - Stage 1&2 Preparation,Submission& C1)
C01_7 d/w - 10h/d - No HK 90 03-Jan-22 A 06-Jan-22 A 16-May-22 16-May-22
Approval,Tender&Award sub-contract Hols - No B/O periods (was
CC#02 ----- Construction ----- C1) 886 91 31-Jul-21 A 23-Jul-24 28-Mar-22 17-Aug-24 22
CC#02 - 3310/11 - Area G1 & G2 - Reclamation Works 259 13 02-Nov-21 A 20-Oct-22 12-Apr-22 20-Oct-22 0
CC#02 - 3310/11 - Area G1 & G2 - Site Preparation C11_6 d/w - 10h/d - With HK Hols4 - No B/O 0periods (was
02-Nov-21
C3) A 10-Nov-21 A 19-Apr-22 19-Apr-22
310.C.G1.J100 3310/11 - Area G1&G2 - Site setup C11_6 d/w - 10h/d - With 4 02-Nov-21 A 10-Nov-21 A 19-Apr-22 19-Apr-22
HK Hols - No B/O periods
CC#02 - 3310/11 - Area G1 & G2 - DJM for Rock Wedge with Testing (was C3) 160 8 11-Nov-21 A 23-Jul-22 12-Apr-22 14-Aug-22 18
310.C.G1.J107 3310/11 - Area G1&G2 - CPT for DJM C11_6 d/w - 10h/d - With 32 2 11-Nov-21 A 28-Nov-21 A 19-Apr-22 19-Apr-22
HK Hols - No B/O periods
310.C.G1.J115.B02 3310/11 - Area G1 - Plant mobilization (was
C11_6C3)
d/w - 10h/d - With 3 12-Apr-22 14-Apr-22 12-Apr-22 14-Apr-22 0
HK Hols - No B/O periods
310.C.G1.J112 3310/11 - Area G1 - construct DJM for rock wedge [436nos. @1.5 no./shift/rig; use 4 rigs (was
C11_6C3)
d/w - 10h/d - With 40 3 19-Apr-22 06-Jun-22 19-Apr-22 06-Jun-22 0
@2-shifts] HK Hols - No B/O periods
310.C.G1.J112.B02 3310/11 - Area G2 - construct DJM for rock wedge [88nos. @1.5 no./2-shifts/rig; use 2 (was
C11_6C3)
d/w - 10h/d - With 32 3 12-May-22 18-Jun-22 12-May-22 18-Jun-22 0
rigs] HK Hols - No B/O periods
310.C.G1.J140 3310/11 - Area G1&G2 - DJM coring, testing & reporting (was
C01_7C3)
d/w - 10h/d - No HK 35 19-Jun-22 23-Jul-22 11-Jul-22 14-Aug-22 22
Hols - No B/O periods (was
CC#02 - 3310/11 - Area G1 & G2 - Backfilling C1)
C11_6 d/w - 10h/d - With HK Hols
116- No B/O 5periods (was
02-Jun-22
C3) 20-Oct-22 02-Jun-22 20-Oct-22 0

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:43
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 12 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.G1.J143 3310/11 - Area G1&G2 - remove armour rock along old seawall w/ transition layer [208m2 C11_6 d/w - 10h/d - With 61 02-Jun-22 13-Aug-22 02-Jun-22 13-Aug-22 0
x 293m=60944m3; @250m3/d/wf; 4wf] HK Hols - No B/O periods
310.C.G1.J152 3310/11 - Area G1&G2 - construct new seawall at final alignment (was
C11_6C3)
d/w - 10h/d - With 24 01-Aug-22 27-Aug-22 01-Aug-22 27-Aug-22 0
HK Hols - No B/O periods
310.C.G1.J136 3310/11 - Area G1&G2 - backfill from +3.0 to +6.5mPD [174,926m3 @350m3/d/wf; 10wf] (was
C11_6C3)
d/w - 10h/d - With 55 5 15-Aug-22 20-Oct-22 15-Aug-22 20-Oct-22 0
HK Hols - No B/O periods
CC#02 - 3310/11 - Area G3 - Reclamation Works (was C3) 324 35 03-Nov-21 A 04-Mar-23 28-Mar-22 10-Apr-23 27
CC#02 - 3310/11 - Area G3 - Site Preparation 4 0 03-Nov-21 A 05-Sep-22 28-Mar-22 06-Sep-22 1
310.C.G3.J200 3310/11 - Area G3 - site preparation & plant mobilization C03_7 d/w - 10h/d - With 4 03-Nov-21 A 06-Nov-21 A 28-Mar-22 28-Mar-22
HK Hols - No B/O periods
310.C.G3.J010 3310/11 - Area G3 - assume closure date of Ex. N-Runway C11_6 d/w - 10h/d - With 0 01-Sep-22 02-Sep-22 1
HK Hols - No B/O periods
310.C.G3.J232 3310/11 - Area G3 - decommissioning of approach light (was
C11_6C3)
d/w - 10h/d - With 4 01-Sep-22 05-Sep-22 02-Sep-22 06-Sep-22 1
HK Hols - No B/O periods
CC#02 - 3310/11 - Area G3 - Construct Temporary Marine Platform (was C3) 205 4 07-Nov-21 A 21-Jan-22 A 28-Mar-22 28-Mar-22
310.C.G3.J308 3310/11 - Area G3 - install pipe pile for temp steel platform [70nos. @4nos./d/wf; 2wf] C03_7 d/w - 10h/d - With 13 3 07-Nov-21 A 24-Nov-21 A 28-Mar-22 28-Mar-22
HK Hols - No B/O periods
310.C.G3.J312 3310/11 - Area G3 - construct steel platform deck C03_7 d/w - 10h/d - With 27 1 25-Nov-21 A 04-Jan-22 A 28-Mar-22 28-Mar-22
HK Hols - No B/O periods
310.C.G3.J399.B01 3310/11 - Area G3 - Silt Curtain Installation C11_6 d/w - 10h/d - With 10 05-Jan-22 A 15-Jan-22 A 28-Mar-22 28-Mar-22
HK Hols - No B/O periods
310.C.G3.J393.B01 3310/11 - Area G3 - Environmental inspection/Dolphin Observation (was
C01_7C3)
d/w - 10h/d - No HK 7 15-Jan-22 A 21-Jan-22 A 28-Mar-22 28-Mar-22
Hols - No B/O periods (was
CC#02 - 3310/11 - Area G3 - DJM along Approach Light Structure with Testing C1)
C03_7 d/w - 10h/d - With HK Hols
338- No B/O 5periods 21-Jan-22 A 03-Feb-23 28-Mar-22 17-Feb-23 14
310.C.G3.J204 3310/11 - Area G3 (within Temp. Platform) - construct DJM [60nos. @1.5 no./shift/rig; use C03_7 d/w - 10h/d - With 32 2 21-Jan-22 A 14-Mar-22 A 28-Mar-22 28-Mar-22
2 rigs] HK Hols - No B/O periods
310.C.G3.J206.B01 3310/11 - Area G3 (within Temp. Platform) - construct Remaining DJM [16 no. @1.5 C03_7 d/w - 10h/d - With 12 1 25-Mar-22 A 30-Mar-22 08-May-22 11-May-22 36
no./2-shift/rig; use 2 rigs] HK Hols - No B/O periods
310.C.G3.J208.B01 3310/11 - Area G3 (outside Temp. Platform) - construct DJM [60 nos. @1.5 no./shift/rig; C03_7 d/w - 10h/d - With 22 2 02-Dec-22 23-Dec-22 02-Dec-22 23-Dec-22 0
use 2 rigs] HK Hols - No B/O periods
310.C.G3.J208 3310/11 - Area G3 - DJM test (along Approach Light Structure) and reporting C03_7 d/w - 10h/d - With 28 24-Dec-22 27-Jan-23 24-Dec-22 27-Jan-23 0
HK Hols - No B/O periods
310.C.G3.J324 3310/11 - Area G3 - remove temp platform (fill area) (24hrs/d; 7d) C03_7 d/w - 10h/d - With 7 28-Jan-23 03-Feb-23 11-Feb-23 17-Feb-23 14
HK Hols - No B/O periods
CC#02 - 3310/11 - Area G3 - Seawall Structure at West End of Old North Runway 252 7 28-Jan-22 A 05-Dec-22 28-Mar-22 10-Apr-23 99
CC#02 - 3310/11 - Area G3 - West End Seawall - Cutting of Existing Approach Light Post 75 2 06-Sep-22 05-Dec-22 07-Sep-22 10-Apr-23 99
310.C.G3.J148 3310/11 - Area G3 - West End Seawall - decommissioning of approach light and cut C03_7 d/w - 10h/d - With 11 2 06-Sep-22 17-Sep-22 07-Sep-22 18-Sep-22 1
approach light post [2 no, 1wf] HK Hols - No B/O periods
310.C.G3.J316 3310/11 - Area G3 - cut approach light post [8 no. @2d/no./wf, 1wf] C11_6 d/w - 10h/d - With 16 14-Nov-22 01-Dec-22 14-Nov-22 01-Dec-22 0
HK Hols - No B/O periods
310.C.G3.J304 3310/11 - Area G3 - demolish approach light - submit Form BA14 for completion of work (was
C01_7C3)
d/w - 10h/d - No HK 4 02-Dec-22 05-Dec-22 07-Apr-23 10-Apr-23 126
Hols - No B/O periods (was
CC#02 - 3310/11 - Area G3 - West End Seawall - DJM Wall Construction with Testing C1) 68 3 28-Jan-22 A 27-Apr-22 28-Mar-22 10-Feb-23 237
310.C.G3.J104 3310/11 - Area G3 - West End Seawall - Plant Mobilization, condition survey and site C11_6 d/w - 10h/d - With 9 28-Jan-22 A 05-Feb-22 A 28-Mar-22 28-Mar-22
setup HK Hols - No B/O periods
310.C.G3.J124 3310/11 - Area G3 - West End Seawall - Construct DJM Wall [98 nos. @1.5 no./shift/rig; (was C3)
C03_7 d/w - 10h/d - With 27 3 06-Feb-22 A 16-Mar-22 A 28-Mar-22 28-Mar-22
use 3 rigs] HK Hols - No B/O periods
310.C.G3.J156 3310/11 - Area G3 - West End Seawall - testing and reporting C01_7 d/w - 10h/d - No HK 28 31-Mar-22 27-Apr-22 07-Jul-22 03-Aug-22 98
Hols - No B/O periods (was
310.C.G3.J320 3310/11 - Area G3 - remove temp platform (seawall) (24hrs/d; 7d) C1)
C03_7 d/w - 10h/d - With 7 14-Apr-22 24-Apr-22 04-Feb-23 10-Feb-23 279
HK Hols - No B/O periods

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:43
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 13 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
CC#02 - 3310/11 - Area G3 - West End Seawall - Seawall Armour Placing C11_6 d/w - 10h/d - With HK Hols
17- No B/O 2periods (was
27-Oct-22
C3) 15-Nov-22 13-Jan-23 04-Feb-23 65
310.C.G3.J152 3310/11 - Area G3 - West End Seawall - place "final" seawall armour C11_6 d/w - 10h/d - With 17 2 27-Oct-22 15-Nov-22 13-Jan-23 04-Feb-23 65
HK Hols - No B/O periods
CC#02 - 3310/11 - Area G3 - DJM for Rock Wedge with Testing (was
C03_7C3)
d/w - 10h/d - With HK Hols
59- No B/O 3periods 02-Dec-22 05-Feb-23 02-Dec-22 05-Feb-23 0
310.C.G3.J224 3310/11 - Area G3 - construct DJM (Area G3) for Rock Wedge [214nos. @1.5 C03_7 d/w - 10h/d - With 31 3 02-Dec-22 04-Jan-23 02-Dec-22 04-Jan-23 0
no./shift/rig; use 3 rigs @2-shifts] HK Hols - No B/O periods
310.C.G3.J228 3310/11 - Area G3 - test and reporting for rock wedge DJM (Area G3) C03_7 d/w - 10h/d - With 28 05-Jan-23 05-Feb-23 05-Jan-23 05-Feb-23 0
HK Hols - No B/O periods
CC#02 - 3310/11 - Area G3 - Removal of Rock Wedge along Old Seawall C11_6 d/w - 10h/d - With HK Hols
48- No B/O 3periods (was
05-Jan-23
C3) 04-Mar-23 18-Jan-23 17-Mar-23 11
310.C.G3.J244 3310/11 - Area G3 - remove armour rock along old seawall w/ transition layer [208mL x C11_6 d/w - 10h/d - With 24 2 05-Jan-23 04-Feb-23 18-Jan-23 17-Feb-23 11
40m2= 8320m3; @250m3/d/wf; 2wf] HK Hols - No B/O periods
310.C.G3.J248 3310/11 - Area G3 - backfill to +6.5mPD after remove armour rock [37,440m3; 5wf] (was
C11_6C3)
d/w - 10h/d - With 24 1 06-Feb-23 04-Mar-23 18-Feb-23 17-Mar-23 11
HK Hols - No B/O periods
CC#02 - 3310/11 - Area G3 - Backfilling (was C3) 113 13 19-Sep-22 05-Feb-23 19-Sep-22 17-Feb-23 11
CC#02 - 3310/11 - Area G3 - West End Seawall - Seawall Core Material Filling C11_6 d/w - 10h/d - With HK Hols
31- No B/O 3periods (was
19-Sep-22
C3) 26-Oct-22 19-Sep-22 18-Nov-22 20
310.C.G3.J136 3310/11 - Area G3 - West End Seawall - fill seawall core seabed to +3.0mPD (14,700m3 C11_6 d/w - 10h/d - With 13 1 19-Sep-22 05-Oct-22 19-Sep-22 05-Oct-22 0
@1200m3/d/wf) HK Hols - No B/O periods
310.C.G3.J140 3310/11 - Area G3 - West End Seawall - fill seawall core +3.0 to + 6.5mPD (33,590m3; (was
C11_6C3)
d/w - 10h/d - With 18 2 06-Oct-22 26-Oct-22 29-Oct-22 18-Nov-22 20
@350m3/d/wf; 6wf) HK Hols - No B/O periods
CC#02 - 3310/11 - Area G3 - along Approach Light Structure - Backfilling to +3.0mPD (was
C01_7C3)
d/w - 10h/d - No HK Hols59
- No B/O periods
4 (was06-Oct-22
C1) 03-Dec-22 06-Oct-22 03-Dec-22 0
310.C.G3.J212 3310/11 - Area G3 - backfill from seabed to +3.0mPD (80m behind seawall) [48,276m3; C01_7 d/w - 10h/d - No HK 18 2 06-Oct-22 23-Oct-22 06-Oct-22 23-Oct-22 0
@500/d/wf; 6wf] Hols - No B/O periods (was
310.C.G3.J220 3310/11 - Area G3 - backfill from seabed to +3.0mPD (remaining 184mL) [119,312m3; C1)
C01_7 d/w - 10h/d - No HK 41 2 24-Oct-22 03-Dec-22 24-Oct-22 03-Dec-22 0
@500/d/wf; 6wf] Hols - No B/O periods (was
CC#02 - 3310/11 - Area G3 - along Approach Light Structure - Backfilling +3.0mPD to 6.5mPD C1)
C01_7 d/w - 10h/d - No HK Hols102
- No B/O periods
6 (was27-Oct-22
C1) 05-Feb-23 19-Nov-22 17-Feb-23 12
310.C.G3.J216 3310/11 - Area G3 - backfill from +3.0 to +6.5mPD (80m behind seawall) [110,100m3; C01_7 d/w - 10h/d - No HK 27 3 27-Oct-22 22-Nov-22 19-Nov-22 15-Dec-22 23
@500/d/wf; 9wf] Hols - No B/O periods (was
310.C.G3.J240 3310/11 - Area G3 - backfill from 3.0m to +6.5mPD (remaining 184mL) [215,686m3; C1)
C01_7 d/w - 10h/d - No HK 64 3 04-Dec-22 05-Feb-23 16-Dec-22 17-Feb-23 12
@350/d/wf; 10wf] Hols - No B/O periods (was
CC#02 - 3310/11 - Area G4 - Reclamation Works C1)
C11_6 d/w - 10h/d - With HK Hols
285- No B/O 9periods (was
18-Nov-21
C3) A 19-Nov-22 28-Mar-22 26-Nov-22 6
CC#02 - 3310/11 - Area G4 - Site Preparation C11_6 d/w - 10h/d - With HK Hols4 - No B/O 0periods (was
06-Dec-21
C3) A 09-Dec-21 A 28-Mar-22 28-Mar-22
310.C.G4.J100 3310/11 - Area G4 - site preparation C11_6 d/w - 10h/d - With 4 06-Dec-21 A 09-Dec-21 A 28-Mar-22 28-Mar-22
HK Hols - No B/O periods
CC#02 - 3310/11 - Area G4 - DJM for Rock Wedge with Testing (was
C11_6C3)
d/w - 10h/d - With HK Hols
123- No B/O 4periods (was
18-Nov-21
C3) A 11-Jun-22 28-Mar-22 14-Jul-22 27
310.C.G4.J112 3310/11 - Area G4 - CPT for DJM [4 nos. @4d/no/rig] C11_6 d/w - 10h/d - With 20 1 18-Nov-21 A 24-Nov-21 A 28-Mar-22 28-Mar-22
HK Hols - No B/O periods
310.C.G4.J113.B02 3310/11 - Area G4 - Plant Mobilization and site setup (was
C11_6C3)
d/w - 10h/d - With 4 24-Mar-22 A 27-Mar-22 A 28-Mar-22 28-Mar-22
HK Hols - No B/O periods
310.C.G4.J116 3310/11 - Area G4 - construct DJM for rock wedge [169 nos. @1.5 no./shift/rig; use 2 rigs (was
C11_6C3)
d/w - 10h/d - With 37 3 28-Mar-22 A 11-May-22 28-Mar-22 11-May-22 0
@2-shifts] HK Hols - No B/O periods
310.C.G4.J140 3310/11 - Area G4 - DJM testing and reporting (was
C11_6C3)
d/w - 10h/d - With 26 12-May-22 11-Jun-22 14-Jun-22 14-Jul-22 27
HK Hols - No B/O periods
CC#02 - 3310/11 - Area G4 - Removal of Rock Wedge along Old Seawall (was
C11_6C3)
d/w - 10h/d - With HK Hols
24- No B/O 2periods (was
12-May-22
C3) 09-Jun-22 16-May-22 13-Jun-22 3
310.C.G4.J124 3310/11 - Area G4 - remove armour rock along old seawall w/ transition layer [32m2 x C11_6 d/w - 10h/d - With 24 2 12-May-22 09-Jun-22 16-May-22 13-Jun-22 3
330=10,560m3; @250m3/d/wf; 2wf] HK Hols - No B/O periods
CC#02 - 3310/11 - Area G4 - Backfill (was
C11_6C3)
d/w - 10h/d - With HK Hols
136- No B/O 3periods (was
10-Jun-22
C3) 19-Nov-22 14-Jun-22 26-Nov-22 6
310.C.G4.J104 3310/11 - Area G4 - backfill (South) from +3.0m to +6.5mPD (south side) [17,978m3; C11_6 d/w - 10h/d - With 64 2 10-Jun-22 24-Aug-22 14-Jun-22 27-Aug-22 3
@350/d/wf] HK Hols - No B/O periods
310.C.G4.J108 3310/11 - Area G4 - backfill (North) from +3.0 to +6.5mPD [25,100m3; @350/d/wf; 4wf] (was
C11_6C3)
d/w - 10h/d - With 24 1 24-Oct-22 19-Nov-22 31-Oct-22 26-Nov-22 6
HK Hols - No B/O periods
(was C3)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:43
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 14 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
CC#02 - 3310/5,6,6A,7 - Area E1 - DJM/CSM at EBC no. 5,6,19 219 2 18-Aug-21 A 15-May-22 30-Mar-22 17-May-22 2
CC#02 - 3310/6A - Box Culvert 5,6,19 - DJM/CSM at Area E1 219 2 18-Aug-21 A 15-May-22 30-Mar-22 17-May-22 2
310.C.R0.X302 BA8 Submission for DJM C11_6 d/w - 10h/d - With 7 18-Aug-21 A 25-Aug-21 A 30-Mar-22 30-Mar-22
HK Hols - No B/O periods
310.C.R0.X306 BA10 Submission for DJM (was
C11_6C3)
d/w - 10h/d - With 7 26-Aug-21 A 02-Sep-21 A 30-Mar-22 30-Mar-22
HK Hols - No B/O periods
310.C.R0.X286 3310/6A - Area E1 - CPT [40 nos. @4d/no; 8wf] (was
C11_6C3)
d/w - 10h/d - With 22 2 10-Sep-21 A 25-Oct-21 A 30-Mar-22 30-Mar-22
HK Hols - No B/O periods
310.C.R0.X279.B01 3310/6A - Area E1 - Plant Mobilization and plant setup (was
C11_6C3)
d/w - 10h/d - With 4 08-Nov-21 A 11-Nov-21 A 22-Apr-22 22-Apr-22
HK Hols - No B/O periods
310.C.R0.X291.B01 3310/6A - Area E1 - construct CSM [1,037nos.; @3 no./shift/rig; use 2rigs @2-shifts] (was
C11_6C3)
d/w - 10h/d - With 52 11-Nov-21 A 06-Mar-22 A 22-Apr-22 22-Apr-22
HK Hols - No B/O periods
310.C.R0.X278 3310/6A - Area E1 - Plant Mobilization and plant setup (was
C11_6C3)
d/w - 10h/d - With 4 25-Nov-21 A 06-Dec-21 A 30-Mar-22 30-Mar-22
HK Hols - No B/O periods
310.C.R0.X290 3310/6A - Area E1 - construct DJM [939nos.; @1.5 no./shift/rig; use 4 rigs @2-shifts] (was
C11_6C3)
d/w - 10h/d - With 71 07-Dec-21 A 21-Apr-22 30-Mar-22 23-Apr-22 2
HK Hols - No B/O periods
310.C.R0.X295.B01 3310/6A - Area E1 - CSM Coring test and reporting (was
C01_7C3)
d/w - 10h/d - No HK 21 07-Mar-22 A 10-Apr-22 22-Apr-22 06-May-22 26
Hols - No B/O periods (was
310.C.R0.X294 3310/6A - Area E1 - DJM test and reporting C1)
C01_7 d/w - 10h/d - No HK 24 22-Apr-22 15-May-22 24-Apr-22 17-May-22 2
Hols - No B/O periods (was
CC#02 - 3310/8 - Area E2b - Reclamation Works C1) 426 17 31-Jul-21 A 31-Dec-22 19-Apr-22 16-Nov-23 259
CC#02 - 3310/8 Site Preparation and Establishment C11_6 d/w - 10h/d - With HK Hols
24- No B/O 0periods (was
31-Jul-21
C3) A 27-Aug-21 A 08-Nov-22 08-Nov-22
310.C.EX.H940 3310/8 - Area E2b - access to Works Area C11_6 d/w - 10h/d - With 0 31-Jul-21 A 08-Nov-22
HK Hols - No B/O periods
310.C.EX.H944 3310/8 - Area E2b - underground utilities survey and reporting (was
C11_6C3)
d/w - 10h/d - With 6 31-Jul-21 A 06-Aug-21 A 08-Nov-22 08-Nov-22
HK Hols - No B/O periods
310.C.EX.H952 3310/8 - Area E2b - carry out condition survey and reporting (was
C11_6C3)
d/w - 10h/d - With 6 31-Jul-21 A 06-Aug-21 A 08-Nov-22 08-Nov-22
HK Hols - No B/O periods
310.C.EX.H948 3310/8 - Area E2b - instrumentation works (was
C11_6C3)
d/w - 10h/d - With 24 31-Jul-21 A 27-Aug-21 A 08-Nov-22 08-Nov-22
HK Hols - No B/O periods
CC#02 - 3310/8 - Area E2b - DJM/CSM (was C3) 238 15 14-Sep-21 A 29-Jul-22 19-Apr-22 14-Feb-23 163
310.C.EX.H960 3310/8 - Area E2b - CPT for DJM [23 nos. @4d/no./wf; 4wf] C11_6 d/w - 10h/d - With 26 3 14-Sep-21 A 01-Nov-21 A 19-Apr-22 19-Apr-22
HK Hols - No B/O periods
310.C.EX.H062.B01 3310/8 - Area E2b - CSM Plant mobilization (was
C11_6C3)
d/w - 10h/d - With 7 13-Mar-22 A 19-Mar-22 A 28-Oct-22 28-Oct-22
HK Hols - No B/O periods
310.C.EX.H965.B01 3310/8 - Area E2b - construct CSM [1,018nos. @3 no./shift/rig; use 2rigs @2-shifts] (was
C11_6C3)
d/w - 10h/d - With 94 9 19-Mar-22 A 25-Jun-22 28-Oct-22 21-Jan-23 174
HK Hols - No B/O periods
310.C.EX.H061 3310/8 - Area E2b - DJM Plant mobilization (was
C11_6C3)
d/w - 10h/d - With 7 22-Apr-22 29-Apr-22 08-Nov-22 15-Nov-22 165
HK Hols - No B/O periods
310.C.EX.H964 3310/8 - Area E2b - construct DJM [509nos. @1.5 no./shift/rig; use 4 rigs @2-shifts] (was
C11_6C3)
d/w - 10h/d - With 47 3 30-Apr-22 25-Jun-22 16-Nov-22 11-Jan-23 165
HK Hols - No B/O periods
310.C.EX.H967.B01 3310/8 - Area E2b - CSM Coring test and reporting (was
C01_7C3)
d/w - 10h/d - No HK 21 26-Jun-22 16-Jul-22 25-Jan-23 14-Feb-23 213
Hols - No B/O periods (was
310.C.EX.H968 3310/8 - Area E2b - DJM test and report C1)
C01_7 d/w - 10h/d - No HK 34 26-Jun-22 29-Jul-22 12-Jan-23 14-Feb-23 200
Hols - No B/O periods (was
CC#02 - 3310/8 - Backfill C1)
C11_6 d/w - 10h/d - With HK Hols
117- No B/O 2periods (was
13-Aug-22
C3) 31-Dec-22 29-Jun-23 16-Nov-23 259
310.C.EX.W302 EVT - 3310/8 - Backfill from +3.0 to +6.5 [169,510m3 @350m3/d/wf, 4wf] C11_6 d/w - 10h/d - With 117 2 13-Aug-22 31-Dec-22 29-Jun-23 16-Nov-23 259
HK Hols - No B/O periods
CC#02 - 3310/10,10A,9 - Area E5 - DJM at WBC no. 3,4,18 (was C3) 488 9 13-Aug-21 A 06-Apr-23 28-Mar-22 06-Apr-23 0
310.C.R0.L138.B01 3310/10,10a - Partial access to Works Area 3310/10 C01_7 d/w - 10h/d - No HK 0 13-Aug-21 A 28-Mar-22
Hols - No B/O periods (was
C1)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 15 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.R0.X1002 BA8 Submission for all DJM Works C11_6 d/w - 10h/d - With 7 18-Aug-21 A 25-Aug-21 A 28-Mar-22 28-Mar-22
HK Hols - No B/O periods
310.C.R0.X1006 BA10 Submission for DJM (was
C11_6C3)
d/w - 10h/d - With 7 26-Aug-21 A 01-Sep-21 A 28-Mar-22 28-Mar-22
HK Hols - No B/O periods
310.C.R0.L138 3310/10,10a - DJM (Area E5) - CPT (was
C11_6C3)
d/w - 10h/d - With 30 01-Nov-21 A 11-Nov-21 A 28-Mar-22 28-Mar-22
HK Hols - No B/O periods
310.C.R0.L132 3310/10,10a - DJM (Area E5) - Plant mobilization (was
C11_6C3)
d/w - 10h/d - With 7 25-Nov-21 A 30-Nov-21 A 26-Apr-22 26-Apr-22
HK Hols - No B/O periods
CC#02 - 3310/10 - BC 3,4,18 - DJM at Area E5 (was C3) 52 2 30-Nov-21 A 06-Apr-22 28-Mar-22 06-May-22 22
310.C.R0.L144 3310/10 - Area E5 - construct DJM (Under Box Culvert) [431 nos. @1.5 no./shift/rig; use 4 C11_6 d/w - 10h/d - With 32 2 30-Nov-21 A 12-Mar-22 A 28-Mar-22 28-Mar-22
rigs @2-shifts] HK Hols - No B/O periods
310.C.R0.L152 3310/10 - Area E5 - testing and reporting for DJM (Under Box Culvert) (was
C01_7C3)
d/w - 10h/d - No HK 24 13-Mar-22 A 06-Apr-22 26-Apr-22 06-May-22 30
Hols - No B/O periods (was
CC#02 - 3310/10a - BC 3,4,18 - DJM at Area E5 C1) 306 7 14-Mar-22 A 06-Apr-23 28-Mar-22 06-Apr-23 0
310.C.R0.L154 3310/10a - Area E5 - construct DJM (Outside swale area) [318nos. @1.5 no./shift/rig; use C11_6 d/w - 10h/d - With 30 3 14-Mar-22 A 11-Apr-22 28-Mar-22 11-Apr-22 0
4 rigs @2-shifts] HK Hols - No B/O periods
310.C.R0.L156 3310/10a - Area E5 - testing and reporting for DJM (Outside swale area) (was
C01_7C3)
d/w - 10h/d - No HK 34 2 12-Apr-22 15-May-22 01-Jul-22 03-Aug-22 80
Hols - No B/O periods (was
310.C.R0.L196 3310/10a - Area E5 - construct DJM (Swale Area) after filling [67nos. @1.5 no./shift/rig; C1)
C11_6 d/w - 10h/d - With 12 2 28-Feb-23 13-Mar-23 28-Feb-23 13-Mar-23 0
use 2rig @2-shifts] HK Hols - No B/O periods
310.C.R0.L197 3310/10a - Area E5 - testing and reporting for DJM (Swale area) after filling (was
C01_7C3)
d/w - 10h/d - No HK 24 14-Mar-23 06-Apr-23 14-Mar-23 06-Apr-23 0
Hols - No B/O periods (was
CC#02 - Removal of North East Quay (Eastern Construction Berth) C1) 71 2 03-Dec-23 29-Feb-24 03-Dec-23 29-Feb-24 0
CC#02 - Demolition of Steel Platform 55 0 03-Dec-23 08-Feb-24 03-Dec-23 08-Feb-24 0
310.C.XX.J090 Removal of NE Quay - latest closure date of NE Loading Quay [Dec 2023, TQ no.232] C01_7 d/w - 10h/d - No HK 0 03-Dec-23 03-Dec-23 0
Hols - No B/O periods (was
310.C.XX.J100 Removal of NE Quay - Plant mobilization C1)
C11_6 d/w - 10h/d - With 10 04-Dec-23 14-Dec-23 04-Dec-23 14-Dec-23 0
HK Hols - No B/O periods
310.C.XX.J104 Removal of NE Quay - Site Setup with Silt Curtain (was
C11_6C3)
d/w - 10h/d - With 10 04-Dec-23 14-Dec-23 04-Dec-23 14-Dec-23 0
HK Hols - No B/O periods
310.C.XX.J184 Removal of NE Quay - demolish steel platform including marine pile (was
C11_6C3)
d/w - 10h/d - With 14 15-Dec-23 03-Jan-24 15-Dec-23 03-Jan-24 0
HK Hols - No B/O periods
310.C.XX.J102 Removal of NE Quay - Fill behind seawall to formation level (was
C11_6C3)
d/w - 10h/d - With 30 15-Dec-23 22-Jan-24 05-Jan-24 08-Feb-24 15
HK Hols - No B/O periods
310.C.XX.J185 Removal of NE Quay - remove marine piles (was
C11_6C3)
d/w - 10h/d - With 31 04-Jan-24 08-Feb-24 04-Jan-24 08-Feb-24 0
HK Hols - No B/O periods
310.C.XX.J103 Removal of NE Quay - complete fill behind seawall [6 wks after closure loading quay, TQ (was
C11_6C3)
d/w - 10h/d - With 0 22-Jan-24 08-Feb-24 15
no.232] HK Hols - No B/O periods
CC#02 - Reinstate North East Quay Seawall Structure (was
C11_6C3)
d/w - 10h/d - With HK Hols
16- No B/O 2periods (was
09-Feb-24
C3) 29-Feb-24 09-Feb-24 29-Feb-24 0
310.C.XX.J188 NE Quay Seawall Structure - fill armour rock [8,282m3 @400m3/d/wf; 2wf] C11_6 d/w - 10h/d - With 16 1 09-Feb-24 29-Feb-24 09-Feb-24 29-Feb-24 0
HK Hols - No B/O periods
310.C.XX.J348 NE Quay Seawall Structure - complete seawall reinstatement [by Feb 2024, TQ no. 232] (was
C11_6C3)
d/w - 10h/d - With 0 1 29-Feb-24* 29-Feb-24 0
HK Hols - No B/O periods
CC#02 - Removal of North Boat Point (was C3) 88 2 13-Aug-22 27-Nov-22 01-Mar-23 12-Jun-23 157
310.C.EX.H965 3310/8 - Ex. N Boat Point - Remove concrete coping C11_6 d/w - 10h/d - With 10 13-Aug-22 24-Aug-22 01-Mar-23 11-Mar-23 163
HK Hols - No B/O periods
310.C.EX.H969 3310/8 - Ex. N Boat Point - Remove seawall blocks [approx 70nos.; 5nos./d] [NOTAM] (was C3) - NOTAM
C23_4d/w 15 1 25-Aug-22 19-Sep-22 12-Mar-23 26-Apr-23 65
(M,W,Th,Su-01:30-07:30) -
310.C.EX.H973 3310/8 - Ex. N Boat Point - Backfill to +6.5mPD [NOTAM] No HK Hols- -NOTAM
C23_4d/w With B/O 15 1 21-Sep-22 27-Nov-22 27-Apr-23 12-Jun-23 65
(M,W,Th,Su-01:30-07:30) -
CC#02 - Seawall Structure at D6 Area (Outfall no. 3 & 4) No HK d/w
C11_6 Hols- -10h/d
With B/O
- With HK Hols
135- No B/O 2periods (was
08-Oct-22
C3) 20-Mar-23 13-Feb-23 01-Apr-23 11

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 16 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.R0.L746 Seawall Structure at Outfall no. 3,4 - fill seawall core and armour rock C11_6 d/w - 10h/d - With 21 1 08-Oct-22 01-Nov-22 13-Feb-23 08-Mar-23 104
HK Hols - No B/O periods
310.C.R0.L754 Seawall Structure at swale outlet - fill seawall core and armour rock (was
C11_6C3)
d/w - 10h/d - With 21 1 24-Feb-23 20-Mar-23 09-Mar-23 01-Apr-23 11
HK Hols - No B/O periods
CC#02 - Seawall Structure at West Construction Berth (was
C11_6C3)
d/w - 10h/d - With HK Hols
120- No B/O 0periods (was
26-Feb-24
C3) 23-Jul-24 22-Mar-24 17-Aug-24 22
310.C.XX.J191 Seawall Structure at West Construction Berth - tentative date of closure C11_6 d/w - 10h/d - With 0 26-Feb-24 22-Mar-24 22
HK Hols - No B/O periods
310.C.XX.J304 Seawall Structure at West Construction Berth - construct the seawall structure (was
C11_6C3)
d/w - 10h/d - With
108 26-Feb-24 09-Jul-24 22-Mar-24 03-Aug-24 22
HK Hols - No B/O periods
310.C.XX.J308 Seawall Structure at West Construction Berth - fill behind seawall [2278m3 @350m3/d/wf] (was
C11_6C3)
d/w - 10h/d - With 12 10-Jul-24 23-Jul-24 05-Aug-24 17-Aug-24 22
HK Hols - No B/O periods
CC#02 - Edge Structures around East Approach Light (was
C11_6C3)
d/w - 10h/d - With HK Hols
96- No B/O 0periods (was
01-Sep-22
C3) 24-Dec-22 09-Dec-22 06-Apr-23 82
310.C.XX.J315 Edge Structure around East Approach Light - site preparation with Silt Curtain & C11_6 d/w - 10h/d - With 50 01-Sep-22 01-Nov-22 09-Dec-22 10-Feb-23 82
demolition works HK Hols - No B/O periods
310.C.XX.J340 Edge Structure around East Approach Light - construct Edge structure (was
C11_6C3)
d/w - 10h/d - With 46 02-Nov-22 24-Dec-22 11-Feb-23 06-Apr-23 82
HK Hols - No B/O periods
CC#02 ----- Testing and Commissioning ----- (was
C01_7C3)
d/w - 10h/d - No HK Hols846
- No B/O periods
0 (was07-Apr-22
C1) 30-Jul-24 07-May-22 25-Aug-24 26
CC#02 - DJM/CSM in Area G1 to G4, E1, E2b & E5 C01_7 d/w - 10h/d - No HK Hols379
- No B/O periods
0 (was07-Apr-22
C1) 20-Apr-23 07-May-22 20-Apr-23 0
310.C.R0.L176 3310/10 - DJM in Area E5 (under Box Culvert) - submit Form BA14 for completion of C01_7 d/w - 10h/d - No HK 7 07-Apr-22 13-Apr-22 07-May-22 13-May-22 30
works Hols - No B/O periods (was
310.C.G3.J160 3310/11 - DJM Wall in Area G3 (West End Seawall) - submit form BA14 for partial C1)
C01_7 d/w - 10h/d - No HK 14 05-May-22 18-May-22 04-Aug-22 17-Aug-22 91
completion of works Hols - No B/O periods (was
310.C.R0.X298 3310/6A - DJM/CSM in Area E1 - DJM submit form BA14 C1)
C01_7 d/w - 10h/d - No HK 14 05-May-22 18-May-22 07-May-22 20-May-22 2
Hols - No B/O periods (was
310.C.R0.L177 3310/10 - DJM in Area E5 (outside Box Culvert) - submit Form BA14 for completion of C1)
C01_7 d/w - 10h/d - No HK 14 16-May-22 29-May-22 04-Aug-22 17-Aug-22 80
works Hols - No B/O periods (was
310.C.G3.J365 3310/11 - DJM in Area G4 - submit Form BA14 for completion of works C1)
C01_7 d/w - 10h/d - No HK 14 12-Jun-22 25-Jun-22 15-Feb-23 28-Feb-23 248
Hols - No B/O periods (was
310.C.G1.J148 3310/11 - DJM in Area G1&G2 - submit form BA14 for completion of works C1)
C01_7 d/w - 10h/d - No HK 14 24-Jul-22 06-Aug-22 15-Feb-23 28-Feb-23 206
Hols - No B/O periods (was
310.C.EX.H133 3310/8 - DJM/CSM in Area E2b - Submit BA14 for completion of work C1)
C01_7 d/w - 10h/d - No HK 14 30-Jul-22 12-Aug-22 15-Feb-23 28-Feb-23 200
Hols - No B/O periods (was
310.C.G3.J361 3310/11 - DJM in Area G3 (along Approach Light Structure) - submit Form BA14 for C1)
C01_7 d/w - 10h/d - No HK 14 28-Jan-23 10-Feb-23 07-Apr-23 20-Apr-23 69
completion of works Hols - No B/O periods (was
310.C.G3.J300 3310/11 - DJM in Area G3 (Rock Wedge) - submit Form BA14 for completion of works C1)
C01_7 d/w - 10h/d - No HK 14 06-Feb-23 19-Feb-23 07-Apr-23 20-Apr-23 60
Hols - No B/O periods (was
310.C.R0.L178 3310/10 - DJM in Area E5 (at Swale area) - submit Form BA14 for completion of works C1)
C01_7 d/w - 10h/d - No HK 14 07-Apr-23 20-Apr-23 07-Apr-23 20-Apr-23 0
Hols - No B/O periods (was
CC#02 - Reclamation Works C1)
C01_7 d/w - 10h/d - No HK Hols238
- No B/O periods
0 (was24-Jul-22
C1) 18-Mar-23 28-Jul-22 20-Apr-23 33
310.C.G3.J398.B01 3310/11 - Reclamation Work in Zone G4 (Localizer Bldg C) - submit Form BA14 for C01_7 d/w - 10h/d - No HK 14 24-Jul-22 06-Aug-22 28-Jul-22 10-Aug-22 4
completion of works Hols - No B/O periods (was
310.C.G3.J397.B01 3310/11 - Reclamation Work in Zone G1 & G2 (HKPF Bldg) - submit Form BA14 for C1)
C01_7 d/w - 10h/d - No HK 14 23-Aug-22 05-Sep-22 23-Aug-22 05-Sep-22 0
completion of works Hols - No B/O periods (was
310.C.G3.J385 3310/11 - Reclamation Work in Zone G4 (South) - submit Form BA14 for completion of C1)
C01_7 d/w - 10h/d - No HK 14 25-Aug-22 07-Sep-22 07-Apr-23 20-Apr-23 225
works Hols - No B/O periods (was
310.C.G3.J377 3310/11 - Reclamation Work in Zone G1 & G2 - submit Form BA14 for completion of C1)
C01_7 d/w - 10h/d - No HK 14 21-Oct-22 03-Nov-22 07-Apr-23 20-Apr-23 168
works Hols - No B/O periods (was
310.C.G3.J389 3310/11 - Reclamation Work in Zone G4 (North) - submit Form BA14 for completion of C1)
C01_7 d/w - 10h/d - No HK 14 20-Nov-22 03-Dec-22 07-Apr-23 20-Apr-23 138
works Hols - No B/O periods (was
310.C.G3.J381 3310/11 - Reclamation Work in Zone G3 - submit Form BA14 for completion of works C1)
C01_7 d/w - 10h/d - No HK 14 05-Mar-23 18-Mar-23 07-Apr-23 20-Apr-23 33
Hols - No B/O periods (was
C1)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 17 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
CC#02 - Road Drainage Works C01_7 d/w - 10h/d - No HK Hols30
- No B/O periods
0 (was20-May-23
C1) 18-Jun-23 01-Jun-24 30-Jun-24 378
310.C.G3.J373 3310/11 - Road Drainage Work - Prepare as-built drawings and submit Form BA14 for C01_7 d/w - 10h/d - No HK 30 20-May-23 18-Jun-23 01-Jun-24 30-Jun-24 378
completion of work Hols - No B/O periods (was
CC#02 - Stormwater Drainage Works C1)
C01_7 d/w - 10h/d - No HK Hols30
- No B/O periods
0 (was08-Feb-23
C1) 09-Mar-23 01-Jun-24 30-Jun-24 479
310.C.G3.J369 3310/11 - Stormwater Drainage Work - Prepare as-built drawings and submit Form BA14 C01_7 d/w - 10h/d - No HK 30 08-Feb-23 09-Mar-23 01-Jun-24 30-Jun-24 479
for completion of work Hols - No B/O periods (was
CC#02 - West End Seawall C1)
C01_7 d/w - 10h/d - No HK Hols 4- No B/O periods
0 (was16-Nov-22
C1) 19-Nov-22 07-Apr-23 10-Apr-23 142
310.C.G3.J164 3310/11 - West End Seawall - submit Form BA14 for completion of West End Seawall C01_7 d/w - 10h/d - No HK 4 16-Nov-22 19-Nov-22 07-Apr-23 10-Apr-23 142
Hols - No B/O periods (was
CC#02 - Roadwork, Security Fencing and Central Reserve C1)
C01_7 d/w - 10h/d - No HK Hols84
- No B/O periods
0 (was21-Mar-24
C1) 12-Jun-24 03-Jun-24 25-Aug-24 74
310.C.G4.J169 3310/11 - Roadwork, Security Fence, Central Reserve - Testing and commissioning C01_7 d/w - 10h/d - No HK 10 21-Mar-24 30-Mar-24 03-Jun-24 12-Jun-24 74
Hols - No B/O periods (was
310.C.G4.J172 3310/11 - Roadwork, Security Fence, Central Reserve - Submit Form BA14 C1)
C01_7 d/w - 10h/d - No HK 14 31-Mar-24 13-Apr-24 13-Jun-24 26-Jun-24 74
Hols - No B/O periods (was
310.C.G4.J176 3310/11 - Roadwork, Security Fence, Central Reserve - Statutory Inspection C1)
C01_7 d/w - 10h/d - No HK 30 14-Apr-24 13-May-24 27-Jun-24 26-Jul-24 74
Hols - No B/O periods (was
310.C.G4.J180 3310/11 - Roadwork, Security Fence, Central Reserve - Achieve KD-12 C1)
C01_7 d/w - 10h/d - No HK 30 14-May-24 12-Jun-24 27-Jul-24 25-Aug-24 74
Hols - No B/O periods (was
CC#02 - NE Quay Seawall Structure C1)
C01_7 d/w - 10h/d - No HK Hols 7- No B/O periods
0 (was01-Mar-24
C1) 07-Mar-24 16-Aug-24 22-Aug-24 168
310.C.G4.J182 NE Quay Seawall Structure - submit Form BA14 for completion of work C01_7 d/w - 10h/d - No HK 7 01-Mar-24 07-Mar-24 16-Aug-24 22-Aug-24 168
Hols - No B/O periods (was
310.C.G4.J190 NE Quay Seawall Structure - Achieve KD-12 C1)
C01_7 d/w - 10h/d - No HK 0 07-Mar-24 22-Aug-24 168
Hols - No B/O periods (was
CC#02 - Seawall Structure at West Construction Berth C1)
C01_7 d/w - 10h/d - No HK Hols 7- No B/O periods
0 (was24-Jul-24
C1) 30-Jul-24 19-Aug-24 25-Aug-24 26
310.C.XX.J311 Seawall Structure at West Construction Berth - submit Form BA14 for completion of work C01_7 d/w - 10h/d - No HK 7 24-Jul-24 30-Jul-24 19-Aug-24 25-Aug-24 26
Hols - No B/O periods (was
310.C.XX.J312 Seawall Structure at West Construction Berth - Achieve KD-12 C1)
C01_7 d/w - 10h/d - No HK 0 30-Jul-24 25-Aug-24 26
Hols - No B/O periods (was
CC#02 - Edge Structure around East Approach Light C1)
C01_7 d/w - 10h/d - No HK Hols 7- No B/O periods
0 (was25-Dec-22
C1) 31-Dec-22 07-Apr-23 25-Aug-24 603
310.C.XX.J342 Edge Structure around East Approach Light - submit Form BA14 for completion of work C01_7 d/w - 10h/d - No HK 7 25-Dec-22 31-Dec-22 07-Apr-23 13-Apr-23 103
Hols - No B/O periods (was
310.C.XX.J344 Edge Structure around East Approach Light - Achieve KD-12 C1)
C01_7 d/w - 10h/d - No HK 0 31-Dec-22 25-Aug-24 603
Hols - No B/O periods (was
Cost Centre #03 - Airfield AGL & Pavement Works C1) 881 325 10-Jul-21 A 25-Jun-24 03-Jan-22 25-Aug-24 51
CC#3 ----- Design and Others----- C01_7 d/w - 10h/d - No HK Hols166
- No B/O periods
0 (was
24-Dec-21
C1) A 31-Aug-22 13-Apr-22 01-Dec-22 92
Mobile Aggregate Mixing Plant C01_7 d/w - 10h/d - No HK Hols42
- No B/O periods
0 (was27-Mar-22
C1) 07-May-22 21-Oct-22 01-Dec-22 208
310.D.G3.F166 Mobile Aggregate Mixing Plant - prepare and submit footing to ICE C01_7 d/w - 10h/d - No HK 14 27-Mar-22 09-Apr-22 21-Oct-22 03-Nov-22 208
Hols - No B/O periods (was
310.D.G3.F170 Mobile Aggregate Mixing Plant - ICE Review/Comments/Approved of footing C1)
C01_7 d/w - 10h/d - No HK 7 10-Apr-22 16-Apr-22 04-Nov-22 10-Nov-22 208
Hols - No B/O periods (was
310.D.G3.F174 Mobile Aggregate Mixing Plant - PM - Review and Approved footing C1)
C01_7 d/w - 10h/d - No HK 21 17-Apr-22 07-May-22 11-Nov-22 01-Dec-22 208
Hols - No B/O periods (was
AGL C1)
C01_7 d/w - 10h/d - No HK Hols166
- No B/O periods
0 (was
24-Dec-21
C1) A 31-Aug-22 13-Apr-22 01-Dec-22 92
AGL - Drawing Submission C01_7 d/w - 10h/d - No HK Hols98
- No B/O periods
0 (was26-May-22
C1) 31-Aug-22 09-Aug-22 14-Nov-22 75
310.D.WS.L1520 Prepare and Submit AGL Drawings C01_7 d/w - 10h/d - No HK 21 26-May-22 15-Jun-22 09-Aug-22 29-Aug-22 75
Hols - No B/O periods (was
310.D.WS.L1660 PM Review and Comments - 1st round C1)
C01_7 d/w - 10h/d - No HK 28 16-Jun-22 13-Jul-22 30-Aug-22 26-Sep-22 75
Hols - No B/O periods (was
310.D.WS.L1656 Prepare and Resubmit AGL Drawings - 2nd round C1)
C01_7 d/w - 10h/d - No HK 21 14-Jul-22 03-Aug-22 27-Sep-22 17-Oct-22 75
Hols - No B/O periods (was
C1)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 18 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L1524 PM Review and Accept AGL Drawing C01_7 d/w - 10h/d - No HK 28 04-Aug-22 31-Aug-22 18-Oct-22 14-Nov-22 75
Hols - No B/O periods (was
AGL - Material Submission Long Lead Item (AGL Cans and Accessories) C1)
C01_7 d/w - 10h/d - No HK Hols79
- No B/O periods
0 (was
24-Dec-21
C1) A 05-Jun-22 13-Apr-22 22-Jun-22 17
310.C.AF.F100 Major Long Lead Items - Preparation & Submission of AGL Cans and Accessories C01_7 d/w - 10h/d - No HK 28 24-Dec-21 A 10-Apr-22 13-Apr-22 27-Apr-22 17
Hols - No B/O periods (was
310.C.AF.F104 Major Long Lead Items - Comments & Acceptance for AGL Cans and Accessories 1st C1)
C01_7 d/w - 10h/d - No HK 28 11-Apr-22 08-May-22 28-Apr-22 25-May-22 17
Round Hols - No B/O periods (was
310.D.WS.L1536 Major Long Lead Items - Preparation & Resubmission of AGL Cans and Accessories 2nd C1)
C01_7 d/w - 10h/d - No HK 7 09-May-22 15-May-22 26-May-22 01-Jun-22 17
Round Hols - No B/O periods (was
310.D.WS.L1540 Major Long Lead Items - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 21 16-May-22 05-Jun-22 02-Jun-22 22-Jun-22 17
Hols - No B/O periods (was
Quarry Submission C1)
C01_7 d/w - 10h/d - No HK Hols77
- No B/O periods
0 (was16-May-22
C1) 31-Jul-22 16-Sep-22 01-Dec-22 123
310.C.AF.F121.B02 Prepare and Submit Proposed Quarry (Primary and Secondary) - 1st Round C01_7 d/w - 10h/d - No HK 14 16-May-22 29-May-22 16-Sep-22 29-Sep-22 123
Hols - No B/O periods (was
310.C.AF.F131.B02 PM Review and Comments Proposed Quarry (Primary and Secondary) - 1st Round C1)
C01_7 d/w - 10h/d - No HK 28 30-May-22 26-Jun-22 30-Sep-22 27-Oct-22 123
Hols - No B/O periods (was
310.C.AF.F141.B02 Prepare and Submit Proposed Quarry (Primary and Secondary) - 2nd Round C1)
C01_7 d/w - 10h/d - No HK 7 27-Jun-22 03-Jul-22 28-Oct-22 03-Nov-22 123
Hols - No B/O periods (was
310.C.AF.F151.B02 PM Review and Accept Proposed Quarry (Primary and Secondary) C1)
C01_7 d/w - 10h/d - No HK 28 04-Jul-22 31-Jul-22 04-Nov-22 01-Dec-22 123
Hols - No B/O periods (was
AGL - Material Submission (CASB/CABC) C1)
C01_7 d/w - 10h/d - No HK Hols100
- No B/O periods
0 (was16-May-22
C1) 23-Aug-22 12-Jun-22 19-Sep-22 27
310.C.AF.F116 Preparation & Submission for CASB/CABC Materials C01_7 d/w - 10h/d - No HK 30 16-May-22 14-Jun-22 12-Jun-22 11-Jul-22 27
Hols - No B/O periods (was
310.C.AF.F532 Comments & Acceptance for CASB/CABC Materials 1st Round C1)
C01_7 d/w - 10h/d - No HK 28 15-Jun-22 12-Jul-22 12-Jul-22 08-Aug-22 27
Hols - No B/O periods (was
310.C.AF.F528 Preparation & Resubmission for CASB/CABC Materials 2nd Round C1)
C01_7 d/w - 10h/d - No HK 14 13-Jul-22 26-Jul-22 09-Aug-22 22-Aug-22 27
Hols - No B/O periods (was
310.C.AF.F120 Comments & Acceptance for CASB/CABC Materials 2nd Round C1)
C01_7 d/w - 10h/d - No HK 28 27-Jul-22 23-Aug-22 23-Aug-22 19-Sep-22 27
Hols - No B/O periods (was
CC#3 ----- Method Statement ------ C1)
C01_7 d/w - 10h/d - No HK Hols318
- No B/O periods
0 (was
10-Jul-21
C1) A 23-May-22 27-Mar-22 25-Jun-23 397
MS no.06 - Method Statement for Construction of Taxiway Pavement C01_7 d/w - 10h/d - No HK Hols197
- No B/O periods
0 (was
10-Jul-21
C1) A 24-Aug-21 A 27-Mar-22 27-Mar-22
310.D.TX.A132 MS no.6 - Method Statement for Construction of Taxiway Pavement - prepare document C01_7 d/w - 10h/d - No HK 30 10-Jul-21 A 07-Aug-21 A 27-Mar-22 27-Mar-22
Hols - No B/O periods (was
310.D.TX.A136 MS no.6 - Method Statement for Construction of Taxiway Pavement - PM review and C1)
C01_7 d/w - 10h/d - No HK 28 08-Aug-21 A 24-Aug-21 A 27-Mar-22 27-Mar-22
accept Hols - No B/O periods (was
MS no.07 - Method Statement for Construction of Runway Pavement C1)
C01_7 d/w - 10h/d - No HK Hols197
- No B/O periods
0 (was
10-Jul-21
C1) A 24-Aug-21 A 27-Mar-22 27-Mar-22
310.D.TX.A108 MS no.7 - Method Statement for Construction of Runway Pavement - prepare document C01_7 d/w - 10h/d - No HK 30 10-Jul-21 A 07-Aug-21 A 27-Mar-22 27-Mar-22
Hols - No B/O periods (was
310.D.TX.A112 MS no.7 - Method Statement for Construction of Runway Pavement - PM review and C1)
C01_7 d/w - 10h/d - No HK 28 08-Aug-21 A 24-Aug-21 A 27-Mar-22 27-Mar-22
accept Hols - No B/O periods (was
MS no.10 - Method Statement for EVWL, AGL and its associated diversion C1)
C01_7 d/w - 10h/d - No HK Hols58
- No B/O periods
0 (was
07-Aug-21
C1) A 26-Feb-22 A 04-Feb-23 25-Jun-23
310.D.TX.A116 MS no.10 - MS for Construction Civil Works for EVWL, AGL and its associated diversion - C01_7 d/w - 10h/d - No HK 30 07-Aug-21 A 30-Aug-21 A 04-Feb-23 04-Feb-23
prepare document Hols - No B/O periods (was
310.D.TX.A120 MS no.10 - MS for Construction Civil Works for EVWL, AGL and its associated diversion - C1)
C01_7 d/w - 10h/d - No HK 28 31-Aug-21 A 26-Feb-22 A 25-Jun-23 25-Jun-23
PM review and accept Hols - No B/O periods (was
MS no.18 - Method Statement for Construction of Pavement Tie-in to Ex. Taxiway E&F incl. AGL C1) d/w - 10h/d - No HK Hols58
C01_7 - No B/O periods
0 (was27-Mar-22
C1) 23-May-22 04-Feb-23 24-Jun-23 397
310.D.TX.A124 MS no.18 - MS for Construction of Pavement Tie-in to Ex. Taxiway E&F - prepare C01_7 d/w - 10h/d - No HK 30 27-Mar-22 25-Apr-22 04-Feb-23 05-Mar-23 314
document Hols - No B/O periods (was
310.D.TX.A128 MS no.18 - MS for Construction of Pavement Tie-in to Ex. Taxiway E&F - PM review and C1)
C01_7 d/w - 10h/d - No HK 28 26-Apr-22 23-May-22 28-May-23 24-Jun-23 397
accept Hols - No B/O periods (was
CC#3 ----- Procurement ------ C1)
C01_7 d/w - 10h/d - No HK Hols399
- No B/O periods
0 (was
30-Oct-21
C1) A 02-Dec-22 13-Apr-22 28-Feb-24 453

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 19 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
Subletting C01_7 d/w - 10h/d - No HK Hols330
- No B/O periods
0 (was
14-Nov-21
C1) A 09-Oct-22 13-Apr-22 01-Dec-23 418
310.C.AF.F182 Subletting - Airfield Pavement AGL Cans - Stage 1&2 Preparation,Submission& C01_7 d/w - 10h/d - No HK 90 14-Nov-21 A 10-Apr-22 13-Apr-22 27-Apr-22 17
Approval,Tender&Award sub-contract Hols - No B/O periods (was
310.C.AF.196 Subletting - Airfield Earthwork - Stage 1&2 Preparation,Submission& C1)
C01_7 d/w - 10h/d - No HK 90 03-Jan-22 A 14-Jun-22 22-Jun-22 09-Sep-22 87
Approval,Tender&Award sub-contract Hols - No B/O periods (was
310.C.AF.F164 Subletting - Airfield Pavement CASB/CABC-Stage 1&2 Preparation,Submission& C1)
C01_7 d/w - 10h/d - No HK 90 30-Jan-22 A 15-May-22 23-Apr-22 11-Jun-22 27
Approval,Tender&Award sub-contract(w.testing) Hols - No B/O periods (was
310.C.AF.F548 Subletting - Civil Works & Others - Stage 1&2 Preparation,Submission& C1)
C01_7 d/w - 10h/d - No HK 76 14-Mar-22 A 10-Jun-22 27-Aug-22 10-Nov-22 153
Approval,Tender&Award sub-contract Hols - No B/O periods (was
310.C.AF.F180 Subletting - Airfield Pavement Asphalt - Stage 1&2 Preparation,Submission& C1)
C01_7 d/w - 10h/d - No HK 90 23-May-22 20-Aug-22 10-Oct-22 07-Jan-23 140
Approval,Tender&Award sub-contract Hols - No B/O periods (was
310.C.AF.F540 Subletting - Pavement Marking - Stage 1&2 Preparation,Submission& C1)
C01_7 d/w - 10h/d - No HK 90 22-Jun-22 19-Sep-22 29-May-23 26-Aug-23 341
Approval,Tender&Award sub-contract Hols - No B/O periods (was
310.C.AF.F544 Subletting - Landscape Softwork - Stage 1&2 Preparation,Submission& C1)
C01_7 d/w - 10h/d - No HK 90 12-Jul-22 09-Oct-22 03-Sep-23 01-Dec-23 418
Approval,Tender&Award sub-contract Hols - No B/O periods (was
Airfield Underground Utilities, Aviation Fuel Pipeline & Hydrant (AFPH) C1)
C01_7 d/w - 10h/d - No HK Hols395
- No B/O periods
0 (was
30-Oct-21
C1) A 28-Nov-22 23-May-22 28-Feb-24 457
310.P.EX.F132 Subletting - Airfield MEP - Award sub-contract C01_7 d/w - 10h/d - No HK 90 30-Oct-21 A 18-Jan-22 A 04-Jun-22 04-Jun-22
Hols - No B/O periods (was
310.P.EX.U154 Subletting - Potable Water&Fire Hydrant (PWFH) - Stage 1&2 Preparation,Submission& C1)
C01_7 d/w - 10h/d - No HK 90 04-Nov-21 A 20-May-22 03-Aug-22 26-Sep-22 129
Approval,Tender&Award sub-contract Hols - No B/O periods (was
310.P.EX.U130 Subletting - AFHS (With testing ) - Section 1&2 Preparation,Submission& C1)
C01_7 d/w - 10h/d - No HK 90 03-Jan-22 A 11-Mar-22 A 23-May-22 23-May-22
Approval,Tender&Award sub-contract Hols - No B/O periods (was
310.P.EX.U142 Subletting - Drainage & Ducting/ Pipeworks - Stage 1&2 Preparation,Submission& C1)
C01_7 d/w - 10h/d - No HK 90 03-Jan-22 A 20-May-22 06-Jun-22 30-Jul-22 71
Approval,Tender&Award sub-contract Hols - No B/O periods (was
310.P.EX.U135 Subletting - Gas Supply System & UUs - Stage 1&2 Preparation,Submission& C1)
C01_7 d/w - 10h/d - No HK90 03-Jan-22 A 31-May-22 04-Jun-22 08-Aug-22 69
Approval,Tender&Award sub-contract Hols - No B/O periods (was
310.C.AF.F536 Subletting - Road Marking - Stage 1&2 Preparation,Submission& Approval,Tender&Award C1)
C01_7 d/w - 10h/d - No HK 90 31-Aug-22 28-Nov-22 01-Dec-23 28-Feb-24 457
sub-contract Hols - No B/O periods (was
Procurement C1)
C01_7 d/w - 10h/d - No HK Hols194
- No B/O periods
0 (was23-May-22
C1) 02-Dec-22 09-Jun-22 19-Dec-22 17
Major Long Lead Items - AGL Cans & Accessories C01_7 d/w - 10h/d - No HK Hols194
- No B/O periods
0 (was23-May-22
C1) 02-Dec-22 09-Jun-22 19-Dec-22 17
310.C.AF.F108 Procurement Major Long Lead Items - Place Order & Manufacture for AGL Cans and C01_7 d/w - 10h/d - No HK 180 23-May-22 18-Nov-22 09-Jun-22 05-Dec-22 17
Accessories Hols - No B/O periods (was
310.C.AF.F112 Procurement Major Long Lead Items - Delivery on Site for AGL Cans and Accessories C1)
C01_7 d/w - 10h/d - No HK 14 19-Nov-22 02-Dec-22 06-Dec-22 19-Dec-22 17
Hols - No B/O periods (was
Major Long Lead Items - CASB/CABC Materials C1)
C01_7 d/w - 10h/d - No HK Hols56
- No B/O periods
0 (was24-Aug-22
C1) 18-Oct-22 20-Sep-22 14-Nov-22 27
310.C.AF.F128 Procurement CASB/CABC - Apply permit from AA and Marine Department for delivery C01_7 d/w - 10h/d - No HK 28 24-Aug-22 20-Sep-22 20-Sep-22 17-Oct-22 27
Hols - No B/O periods (was
310.C.AF.F132 Procurement CASB/CABC - Prepare and deliver CASB/CABC to the Site (source via C1)
C01_7 d/w - 10h/d - No HK 28 21-Sep-22 18-Oct-22 18-Oct-22 14-Nov-22 27
marine) Hols - No B/O periods (was
CC#3 ----- Construction ------ C1) 622 325 28-Mar-22 02-May-24 03-Jan-22 25-Aug-24 95
3310/6B Site Preparation and Establishment C11_6 d/w - 10h/d - With HK Hols
24- No B/O 0periods (was
28-Mar-22
C3) 28-Apr-22 03-Jan-22 17-Jul-23 362
310.C.EX.H065 3310/6B - access to Works Area C11_6 d/w - 10h/d - With 0 28-Mar-22* 03-Jan-22 -69
HK Hols - No B/O periods
310.C.EX.H066 3310/6B - underground utilities survey and reporting + carry out topographic survey and (was
C11_6C3)
d/w - 10h/d - With 6 28-Mar-22 02-Apr-22 17-Jun-23 24-Jun-23 362
reporting HK Hols - No B/O periods
310.C.EX.H074 3310/6B - carry out condition survey and reporting (was C3)
C11_6 d/w - 10h/d - With 6 28-Mar-22 02-Apr-22 17-Jun-23 24-Jun-23 362
HK Hols - No B/O periods
310.C.EX.H070 3310/6B - instrumentation works (was
C11_6C3)
d/w - 10h/d - With 24 28-Mar-22 28-Apr-22 17-Jun-23 17-Jul-23 362
HK Hols - No B/O periods
Preparation Works (was
C11_6C3)
d/w - 10h/d - With HK Hols
118- No B/O 0periods (was
15-Jun-22
C3) 03-Nov-22 27-Aug-22 17-Jan-23 62

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 20 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.T.AF.F022 Aggregate Plant - Footing & Plant Erection C11_6 d/w - 10h/d - With 60 15-Jun-22 24-Aug-22 27-Aug-22 08-Nov-22 62
HK Hols - No B/O periods
310.T.AF.F025 Trial for the pavement and submit report (was
C11_6C3)
d/w - 10h/d - With 30 25-Aug-22 29-Sep-22 09-Nov-22 13-Dec-22 62
HK Hols - No B/O periods
310.T.AF.F025.B02 PM Review and Accept Trial Report (was
C11_6C3)
d/w - 10h/d - With 28 30-Sep-22 03-Nov-22 14-Dec-22 17-Jan-23 62
HK Hols - No B/O periods
Airfield AGL + Pavement Works After Commissioning Interim 2RS (was C3) 538 325 12-Jul-22 02-May-24 26-Aug-22 25-Aug-24 95
AGL Mock Up C11_6 d/w - 10h/d - With HK Hols
96- No B/O 0periods (was
12-Jul-22
C3) 03-Nov-22 26-Aug-22 19-Dec-22 39
310.C.RC.1000.B02 AGL Mock Up - inlc submission/appvl (48d) + installation (24d) C11_6 d/w - 10h/d - With 72 12-Jul-22 06-Oct-22 26-Aug-22 21-Nov-22 39
HK Hols - No B/O periods
310.C.RC.1010.B02 AGL Mock Up - PM review and appvl (was
C11_6C3)
d/w - 10h/d - With 24 07-Oct-22 03-Nov-22 22-Nov-22 19-Dec-22 39
HK Hols - No B/O periods
Works Area 3310/1a (was C3) - NOTAM (M,W,Th,Su-01:30-07:30)
C23_4d/w 77 0 - No HK
04-Dec-22
Hols - With B/O09-Jul-23
Periods & Flight25-Jun-23
Checks 17-Dec-23 68
310.T.AF.F010 Phase 3310/1a - Resurfacing Works of Taxiways and Apron [NOTAM] C23_4d/w - NOTAM 20 04-Dec-22 16-Feb-23 25-Jun-23 27-Jul-23 68
(M,W,Th,Su-01:30-07:30) -
310.T.AF.F015.B02 Carry Out As-Built Survey and Submit Report (NOTAM) No HK Hols- -NOTAM
C23_4d/w With B/O 5 19-Feb-23 26-Feb-23 30-Jul-23 06-Aug-23 68
(M,W,Th,Su-01:30-07:30) -
310.T.AF.F013 Phase 3310/1a - AGL Base Can/Ductbank/Mid Can (10 nr)) [NOTAM] No HK Hols- -NOTAM
C23_4d/w With B/O 20 27-Feb-23 02-Apr-23 07-Aug-23 10-Sep-23 68
(M,W,Th,Su-01:30-07:30) -
310.T.AF.F016 Phase 3310/1a - AGL Top Can (10 nr) [NOTAM] No HK Hols- -NOTAM
C23_4d/w With B/O 14 24-Apr-23 07-Jun-23 11-Sep-23 25-Oct-23 68
(M,W,Th,Su-01:30-07:30) -
310.T.AF.F019 3310/1a - Line markings and defects remedial works [NOTAM] No HK Hols- -NOTAM
C23_4d/w With B/O 18 08-Jun-23 09-Jul-23 26-Oct-23 17-Dec-23 68
(M,W,Th,Su-01:30-07:30) -
Interface Work Area 3310/IA/1 (Pavement and AGL) No HK Hols - With B/O 393 42 01-Sep-22 27-Dec-23 09-Nov-22 29-Mar-24 76
3310/IA/1-2 C11_6 d/w - 10h/d - With HK Hols
181- No B/O20
periods (was
01-Sep-22
C3) 13-Apr-23 09-Nov-22 09-May-23 21
310.T.AF.F010.B02 Carry Out Initial Survey to Check Level C11_6 d/w - 10h/d - With 3 01-Sep-22 03-Sep-22 06-May-23 09-May-23 199
HK Hols - No B/O periods
3310/IA/1-2 Pavement (was
C11_6C3)
d/w - 10h/d - With HK Hols
171- No B/O13
periods (was
01-Sep-22
C3) 28-Mar-23 09-Nov-22 18-Apr-23 14
310.C.FA.P127 3310/IA/1-2 - Site Formation for Taxiway (14048 m3) C11_6 d/w - 10h/d - With 20 2 01-Sep-22 24-Sep-22 09-Nov-22 01-Dec-22 56
HK Hols - No B/O periods
310.C.FA.P133 3310/IA/1-2 Subgrade Works for Taxiway (cut:15169m3; fill:64079m3) (was
C11_6C3)
d/w - 10h/d - With 40 2 27-Oct-22 12-Dec-22 15-Nov-22 31-Dec-22 16
HK Hols - No B/O periods
310.C.FA.P136 3310/IA/1-2 CASB (16600m3) (39840 tonne) (was
C11_6C3)
d/w - 10h/d - With 42 2 14-Nov-22 03-Jan-23 02-Dec-22 21-Jan-23 16
HK Hols - No B/O periods
310.C.FA.P139 3310/IA/1-2 CABC (25152m3) (60364.80 tonne) (was
C11_6C3)
d/w - 10h/d - With 52 2 10-Dec-22 14-Feb-23 18-Jan-23 22-Mar-23 31
HK Hols - No B/O periods
310.C.FA.P142 3310/IA/1-2 Asphalt (MABC/MAWC/PMABC) (7434m3) (17841.6 tonne) (was
C11_6C3)
d/w - 10h/d - With 21 2 21-Feb-23 16-Mar-23 09-Mar-23 01-Apr-23 14
HK Hols - No B/O periods
310.C.FA.P145 3310/IA/1-2 Asphalt (PMAWC) (3896m3) (9350.4 tonne) (was
C11_6C3)
d/w - 10h/d - With 10 1 10-Mar-23 21-Mar-23 27-Mar-23 11-Apr-23 14
HK Hols - No B/O periods
310.C.FA.P792 3310/IA/1-2 - Milling of the Existing Runway (was
C11_6C3)
d/w - 10h/d - With 6 2 22-Mar-23 28-Mar-23 12-Apr-23 18-Apr-23 14
HK Hols - No B/O periods
3310/IA/1-2 AGL (was
C11_6C3)
d/w - 10h/d - With HK Hols
104- No B/O 7periods (was
03-Dec-22
C3) 13-Apr-23 20-Dec-22 29-Apr-23 14
310.C.FA.P151 3310/IA/1-2 AGL Ductbank (8256 m) C11_6 d/w - 10h/d - With 42 2 03-Dec-22 26-Jan-23 28-Dec-22 18-Feb-23 20
HK Hols - No B/O periods
310.C.FA.P148 3310/IA/1-2 AGL Drawpit/Earthpit/Base Can (369 nr) - 8 no/d, 1 WF (was C3)
C11_6 d/w - 10h/d - With 48 2 03-Dec-22 02-Feb-23 20-Dec-22 18-Feb-23 14
HK Hols - No B/O periods
310.C.FA.P154 3310/IA/1-2 AGL Mid Can (369 nr) - 20 no/d, 1 WF (was
C11_6C3)
d/w - 10h/d - With 20 2 03-Feb-23 25-Feb-23 20-Feb-23 14-Mar-23 14
HK Hols - No B/O periods
310.C.FA.P157 3310/IA/1-2 AGL Top Can (369 nr) (was
C11_6C3)
d/w - 10h/d - With 10 1 29-Mar-23 13-Apr-23 19-Apr-23 29-Apr-23 14
HK Hols - No B/O periods
(was C3)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 21 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
3310/IA/1-1 C11_6 d/w - 10h/d - With HK Hols
164- No B/O20
periods (was
26-Sep-22
C3) 17-Apr-23 15-Dec-22 29-Apr-23 11
3310/IA/1-1 Pavement C11_6 d/w - 10h/d - With HK Hols
164- No B/O13
periods (was
26-Sep-22
C3) 17-Apr-23 15-Dec-22 29-Apr-23 11
310.C.FA.P100 3310/IA/1-1 - Site Formation for Taxiway (2565 m3) C11_6 d/w - 10h/d - With 20 2 26-Sep-22 20-Oct-22 15-Dec-22 09-Jan-23 67
HK Hols - No B/O periods
310.C.FA.P103 3310/IA/1-1 - Subgrade (cut:79857m3; fill: 40518m3) (was
C11_6C3)
d/w - 10h/d - With 30 2 27-Dec-22 04-Feb-23 10-Jan-23 16-Feb-23 11
HK Hols - No B/O periods
310.C.FA.P106 3310/IA/1-1 - CASB (24865m3) (59676 tonne) (was
C11_6C3)
d/w - 10h/d - With 34 2 09-Jan-23 20-Feb-23 21-Jan-23 04-Mar-23 11
HK Hols - No B/O periods
310.C.FA.P109 3310/IA/1-1 - CABC (16958m3) (40699.20 tonne) (was
C11_6C3)
d/w - 10h/d - With 22 2 17-Feb-23 14-Mar-23 02-Mar-23 27-Mar-23 11
HK Hols - No B/O periods
310.C.FA.P112 3310/IA/1-1 - Asphalt (MABC/MAWC/PMABC) (14087m3) (33,808.8 tonne) (was
C11_6C3)
d/w - 10h/d - With 24 2 03-Mar-23 30-Mar-23 16-Mar-23 17-Apr-23 11
HK Hols - No B/O periods
310.C.FA.P115 3310/IA/1-1 - Asphalt (PMAWC) (6888m3) (16531.2 tonne) (was
C11_6C3)
d/w - 10h/d - With 16 1 18-Mar-23 06-Apr-23 31-Mar-23 22-Apr-23 11
HK Hols - No B/O periods
310.C.FA.P788 3310/IA/1-1 - Milling of the Existing Runway (was
C11_6C3)
d/w - 10h/d - With 6 2 11-Apr-23 17-Apr-23 24-Apr-23 29-Apr-23 11
HK Hols - No B/O periods
3310/IA/1-1 AGL (was
C11_6C3)
d/w - 10h/d - With HK Hols
59- No B/O 7periods (was
03-Feb-23
C3) 17-Apr-23 16-Feb-23 29-Apr-23 11
310.C.FA.P118 3310/IA/1-1 - AGL Drawpit/Earthpit/Base Can (371 nr) - 8 no/d, 2 WF C11_6 d/w - 10h/d - With 25 2 03-Feb-23 03-Mar-23 16-Feb-23 16-Mar-23 11
HK Hols - No B/O periods
310.C.FA.P121 3310/IA/1-1 - AGL Ductbank (6381m) (was
C11_6C3)
d/w - 10h/d - With 34 2 03-Feb-23 14-Mar-23 16-Feb-23 27-Mar-23 11
HK Hols - No B/O periods
310.C.FA.P124 3310/IA/1-1 - AGL Mid Can (371 nr) - 20 no/d, 2 WF (was
C11_6C3)
d/w - 10h/d - With 11 2 01-Mar-23 13-Mar-23 14-Mar-23 25-Mar-23 11
HK Hols - No B/O periods
310.C.FA.P130 3310/IA/1-1 - AGL Top Can (371 nr) (was
C11_6C3)
d/w - 10h/d - With 16 1 25-Mar-23 17-Apr-23 12-Apr-23 29-Apr-23 11
HK Hols - No B/O periods
3310/IA/1 Interface Work Area Completion and Remaining Works (was C3) 262 2 10-Feb-23 27-Dec-23 06-Mar-23 29-Mar-24 76
310.C.FA.P828 3310/IA/1 - AGL Foundations/Earthing Rode C11_6 d/w - 10h/d - With 28 2 10-Feb-23 14-Mar-23 06-Mar-23 11-Apr-23 20
HK Hols - No B/O periods
310.C.FA.P180 Achieved KD-5A Complete all civil works for AGL Sys at IWA 3310/IA/1 & provide access (was
C01_7C3)
d/w - 10h/d - No HK 0 17-Apr-23 30-Apr-23 13
for Contract <3305> Hols - No B/O periods (was
310.C.FA.P184 Allow Access to Contract <3305> for AGL System Works for Interface Work Area C1)
C01_7 d/w - 10h/d - No HK 0 17-Apr-23 30-Apr-23 13
3310/IA/1 Hols - No B/O periods (was
310.C.FA.P164 3310/IA/1 - AGL System Works (by Contract <3305>) (assumed 6 months) C1)
C01_7 d/w - 10h/d - No HK 180 18-Apr-23 14-Oct-23 21-Jul-23 16-Jan-24 94
Hols - No B/O periods (was
310.C.FA.P160 3310/IA/1 - Runway Grooving C1)
C11_6 d/w - 10h/d - With 12 16-Oct-23 30-Oct-23 17-Jan-24 30-Jan-24 76
HK Hols - No B/O periods
310.C.FA.P163 3310/IA/1 - Line Marking or defect remedial works @ 3310/IA/1 (was
C11_6C3)
d/w - 10h/d - With 48 31-Oct-23 27-Dec-23 31-Jan-24 28-Mar-24 76
HK Hols - No B/O periods
310.C.FA.P166 3310/IA/1 - Stabilized subgrade and Soil mixed with Hydroseeding (was
C11_6C3)
d/w - 10h/d - With 48 31-Oct-23 27-Dec-23 31-Jan-24 28-Mar-24 76
HK Hols - No B/O periods
310.C.FA.P170 WA 3310/3 - Vacate Work Area (was
C01_7C3)
d/w - 10h/d - No HK 0 27-Dec-23 29-Mar-24 93
Hols - No B/O periods (was
Interface Work Area 3310/IA/2 (Pavement and AGL) C1) 466 36 05-Sep-22 28-Mar-24 10-May-23 25-Aug-24 120
3310/IA/2-2 C11_6 d/w - 10h/d - With HK Hols
357- No B/O18
periods (was
05-Sep-22
C3) 16-Nov-23 10-May-23 25-Nov-23 8
3310/IA/2-2 Pavement C11_6 d/w - 10h/d - With HK Hols
329- No B/O11
periods (was
05-Sep-22
C3) 13-Oct-23 10-May-23 04-Nov-23 18
310.C.FA.P860.B02 3310/IA/2 - Carry Out Survey to Check Level C11_6 d/w - 10h/d - With 6 1 05-Sep-22 12-Sep-22 10-May-23 16-May-23 199
HK Hols - No B/O periods
310.C.FA.P117 3310/IA/2-2 (Pavement) - Site Formation (4111 m3) (was
C11_6C3)
d/w - 10h/d - With 6 1 28-Jun-23 05-Jul-23 12-Jul-23 18-Jul-23 11
HK Hols - No B/O periods
310.C.FA.P120 3310/IA/2-2 (Pavement) - Subgrade Works (fill:9138m3, subgrade:41909m3) (was
C11_6C3)
d/w - 10h/d - With 47 2 18-Jul-23 09-Sep-23 19-Jul-23 11-Sep-23 1
HK Hols - No B/O periods
(was C3)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 22 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.FA.P126 3310/IA/2-2 (Pavement) - CASB (22007m3) (52816.80 tonne) C11_6 d/w - 10h/d - With 52 2 18-Jul-23 15-Sep-23 19-Jul-23 16-Sep-23 1
HK Hols - No B/O periods
310.C.FA.P144 3310/IA/2-2 (Pavement) - CABC (15260m3) (36624 tonne) (was
C11_6C3)
d/w - 10h/d - With 47 2 16-Aug-23 11-Oct-23 22-Aug-23 17-Oct-23 5
HK Hols - No B/O periods
310.C.FA.P156 3310/IA/2-2 (Pavement) - Asphalt (MABC/MAWC/PMABC) (9658m3) (23179.2 tonne) (was
C11_6C3)
d/w - 10h/d - With 32 2 02-Sep-23 11-Oct-23 26-Sep-23 04-Nov-23 20
HK Hols - No B/O periods
310.C.FA.P162 3310/IA/2-2 (Pavement) - Asphalt (PMAWC) (2230m3) (5352 tonne) (was
C11_6C3)
d/w - 10h/d - With 10 1 03-Oct-23 13-Oct-23 04-Oct-23 14-Oct-23 1
HK Hols - No B/O periods
3310/IA/2-2 AGL (was
C11_6C3)
d/w - 10h/d - With HK Hols
95- No B/O 7periods (was
26-Jul-23
C3) 16-Nov-23 27-Jul-23 25-Nov-23 8
310.C.FA.P135 3310/IA/2-2 (AGL) - AGL Drawpit/Earthpit/Base Can (427 nr) - 8 no/d, 1 WF C11_6 d/w - 10h/d - With 55 2 26-Jul-23 27-Sep-23 27-Jul-23 28-Sep-23 1
HK Hols - No B/O periods
310.C.FA.P138 3310/IA/2-2 (AGL) - AGL Ductbank (5932 m) (was
C11_6C3)
d/w - 10h/d - With 52 2 29-Jul-23 27-Sep-23 04-Aug-23 05-Oct-23 5
HK Hols - No B/O periods
310.C.FA.P150 3310/IA/2-2 (AGL) - AGL Mid Can (427 nr) - 20 no/d, 1 WF (was
C11_6C3)
d/w - 10h/d - With 23 2 01-Sep-23 27-Sep-23 02-Sep-23 28-Sep-23 1
HK Hols - No B/O periods
310.C.FA.P168 3310/IA/2-2 (AGL) - AGL Top Can (427 nr) (was
C11_6C3)
d/w - 10h/d - With 10 1 06-Nov-23 16-Nov-23 15-Nov-23 25-Nov-23 8
HK Hols - No B/O periods
3310/IA/2-1 (was
C11_6C3)
d/w - 10h/d - With HK Hols
109- No B/O16
periods (was
14-Jul-23
C3) 21-Nov-23 17-Jul-23 22-Nov-23 1
3310/IA/2-1 Pavement C11_6 d/w - 10h/d - With HK Hols
85- No B/O 9periods (was
14-Jul-23
C3) 24-Oct-23 17-Jul-23 25-Oct-23 1
310.C.FA.P105 3310/IA/2-1 (Pavement) - Subgrade Works (cut/fill: subrade:46593 m3) C11_6 d/w - 10h/d - With 52 2 14-Jul-23 12-Sep-23 17-Jul-23 14-Sep-23 2
HK Hols - No B/O periods
310.C.FA.P123 3310/IA/2-1 (Pavement) - CASB (25039m3) (60093.60 tonne) (was
C11_6C3)
d/w - 10h/d - With 62 2 26-Jul-23 07-Oct-23 28-Jul-23 10-Oct-23 2
HK Hols - No B/O periods
310.C.FA.P141 3310/IA/2-1 (Pavement) - CABC (17291m3) (41.498.40 tonne) (was
C11_6C3)
d/w - 10h/d - With 47 2 24-Aug-23 19-Oct-23 26-Aug-23 21-Oct-23 2
HK Hols - No B/O periods
310.C.FA.P153 3310/IA/2-1 (Pavement) - Asphalt (MABC/MAWC/PMABC) (11365m3) (27276 tonne) (was
C11_6C3)
d/w - 10h/d - With 42 2 26-Aug-23 16-Oct-23 29-Aug-23 18-Oct-23 2
HK Hols - No B/O periods
310.C.FA.P159 3310/IA/2-1 (Pavement) - Asphalt (PMAWC) (2464m3) (5913.6 tonne) (was
C11_6C3)
d/w - 10h/d - With 11 1 11-Oct-23 24-Oct-23 12-Oct-23 25-Oct-23 1
HK Hols - No B/O periods
3310/IA/2-1 AGL (was
C11_6C3)
d/w - 10h/d - With HK Hols
101- No B/O 7periods (was
24-Jul-23
C3) 21-Nov-23 26-Jul-23 22-Nov-23 1
310.C.FA.P129 3310/IA/2-1 (AGL) - AGL Drawpit/Earthpit/Base Can (535 nr) - 8 no/d, 1 WF C11_6 d/w - 10h/d - With 69 2 24-Jul-23 13-Oct-23 26-Jul-23 16-Oct-23 2
HK Hols - No B/O periods
310.C.FA.P132 3310/IA/2-1 (AGL) - AGL Ductbank (10475 m) (was
C11_6C3)
d/w - 10h/d - With 62 2 01-Aug-23 13-Oct-23 03-Aug-23 16-Oct-23 2
HK Hols - No B/O periods
310.C.FA.P147 3310/IA/2-1 (AGL) - AGL Mid Can (535 nr) - 20 no/d, 1 WF (was
C11_6C3)
d/w - 10h/d - With 29 2 05-Sep-23 10-Oct-23 07-Sep-23 12-Oct-23 2
HK Hols - No B/O periods
310.C.FA.P165 3310/IA/2-1 (AGL) - AGL Top Can (535 nr) (was
C11_6C3)
d/w - 10h/d - With 11 1 09-Nov-23 21-Nov-23 10-Nov-23 22-Nov-23 1
HK Hols - No B/O periods
3310/IA/2 Interface Work Area Completion and Remaining Works (was C3) 137 2 14-Oct-23 28-Mar-24 20-Oct-23 25-Aug-24 120
310.C.FA.P832 3310/IA/2 - AGL Foundations/Earthing Rode C11_6 d/w - 10h/d - With 28 2 14-Oct-23 16-Nov-23 20-Oct-23 22-Nov-23 5
HK Hols - No B/O periods
310.C.FA.P108 Achieved KD-5F Complete all civil works for AGL Sys at IWA 3310/IA/2 & provide access (was
C01_7C3)
d/w - 10h/d - No HK 0 21-Nov-23 25-Nov-23 4
for Contract <3305> Hols - No B/O periods (was
310.C.FA.P111 Allow Access to Contract <3305> for AGL System Works for Interface Work Area C1)
C01_7 d/w - 10h/d - No HK 0 21-Nov-23 25-Nov-23 4
3310/IA/2 Hols - No B/O periods (was
310.C.FA.P102 Achieved PMS 08 - Complete all civil enabling works in 3310/IA/2 & allow access for C1)
C11_6 d/w - 10h/d - With 3 22-Nov-23 24-Nov-23 23-Nov-23 25-Nov-23 1
Others to install HK Hols - No B/O periods
310.C.FA.P114 3310/IA/2 - AGL System Works (by Contract <3305>) (assumed 3 months) (was
C01_7C3)
d/w - 10h/d - No HK 90 25-Nov-23 22-Feb-24 26-Nov-23 23-Feb-24 1
Hols - No B/O periods (was
310.C.FA.P174 3310/IA/2 - Soil mixed with Hydroseeding C1)
C11_6 d/w - 10h/d - With 30 14-Feb-24 19-Mar-24 23-Feb-24 28-Mar-24 8
HK Hols - No B/O periods
(was C3)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 23 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.FA.P171 3310/IA/2 - Line Marking or defect remedial works C11_6 d/w - 10h/d - With 30 23-Feb-24 28-Mar-24 24-Feb-24 02-Apr-24 1
HK Hols - No B/O periods
310.C.FA.P177 WA 3310/5, 6, 6A, & 7, 7A - Vacate Work Area (Portion) (was
C01_7C3)
d/w - 10h/d - No HK 0 28-Mar-24 25-Aug-24 150
Hols - No B/O periods (was
Interface Work Area 3310/IA/3 (Pavement and AGL) C1) 485 58 13-Sep-22 02-May-24 17-May-23 25-Aug-24 95
3310/IA/3-3 C11_6 d/w - 10h/d - With HK Hols
374- No B/O18
periods (was
13-Sep-22
C3) 13-Dec-23 17-May-23 16-Dec-23 3
3310/IA/3-3 Pavement C11_6 d/w - 10h/d - With HK Hols
314- No B/O11
periods (was
13-Sep-22
C3) 03-Oct-23 17-May-23 30-Nov-23 49
310.C.FA.P865.B02 3310/IA/3 - Carry Out Survey to Check Level C11_6 d/w - 10h/d - With 6 1 13-Sep-22 19-Sep-22 17-May-23 23-May-23 199
HK Hols - No B/O periods
310.C.FA.P400 3310/IA/3-3 (Pavement) - Subgrade Works (cut:2077m3; subgrade:13223m3) (was
C11_6C3)
d/w - 10h/d - With 35 2 02-Mar-23 15-Apr-23 29-Jul-23 07-Sep-23 120
HK Hols - No B/O periods
310.C.FA.P796 3310/IA/3-3 - Milling of the Existing Runway (was
C11_6C3)
d/w - 10h/d - With 6 2 17-Apr-23 22-Apr-23 25-Oct-23 31-Oct-23 157
HK Hols - No B/O periods
310.C.FA.P403 3310/IA/3-3 (Pavement) - CASB (9853m3) (23647.20 tonne) (was
C11_6C3)
d/w - 10h/d - With 23 2 17-Apr-23 13-May-23 08-Sep-23 06-Oct-23 120
HK Hols - No B/O periods
310.C.FA.P412 3310/IA/3-3 (Pavement) - CABC (7201m3) (17282.40 tonne) (was
C11_6C3)
d/w - 10h/d - With 23 2 11-May-23 07-Jun-23 04-Oct-23 31-Oct-23 120
HK Hols - No B/O periods
310.C.FA.P418 3310/IA/3-3 (Pavement) - Asphalt (MABC/MAWC/PMABC) (3414m3) (8193.6 tonne) (was
C11_6C3)
d/w - 10h/d - With 14 1 08-Jun-23 24-Jun-23 01-Nov-23 16-Nov-23 120
HK Hols - No B/O periods
310.C.FA.P421 3310/IA/3-3 (Pavement) - Asphalt (PMAWC) (2668m3) (6403.2 tonne) (was
C11_6C3)
d/w - 10h/d - With 12 1 18-Sep-23 03-Oct-23 17-Nov-23 30-Nov-23 49
HK Hols - No B/O periods
3310/IA/3-3 AGL (was
C11_6C3)
d/w - 10h/d - With HK Hols
197- No B/O 7periods (was
20-Apr-23
C3) 13-Dec-23 10-Oct-23 16-Dec-23 3
310.C.FA.P406 3310/IA/3-3 (AGL) - AGL Drawpit/Earthpit/Base Can (184 nr) - 8 no/d, 1 WF C11_6 d/w - 10h/d - With 25 2 20-Apr-23 19-May-23 10-Oct-23 08-Nov-23 142
HK Hols - No B/O periods
310.C.FA.P409 3310/IA/3-3 (AGL) - AGL Ductbank (3523 m) (was
C11_6C3)
d/w - 10h/d - With 30 2 20-Apr-23 25-May-23 10-Oct-23 14-Nov-23 142
HK Hols - No B/O periods
310.C.FA.P415 3310/IA/3-3 (AGL) - AGL Mid Can (184 nr) - 20 no/d, 1 WF (was
C11_6C3)
d/w - 10h/d - With 11 2 27-May-23 08-Jun-23 21-Nov-23 02-Dec-23 147
HK Hols - No B/O periods
310.C.FA.P424 3310/IA/3-3 (AGL) - AGL Top Can (184 nr) (was
C11_6C3)
d/w - 10h/d - With 12 1 30-Nov-23 13-Dec-23 04-Dec-23 16-Dec-23 3
HK Hols - No B/O periods
3310/IA/3-1 (was
C11_6C3)
d/w - 10h/d - With HK Hols
174- No B/O17
periods (was
18-May-23
C3) 13-Dec-23 18-Jul-23 16-Dec-23 3
3310/IA/3-1 Pavement C11_6 d/w - 10h/d - With HK Hols
106- No B/O10
periods (was
18-May-23
C3) 21-Sep-23 18-Jul-23 21-Nov-23 49
310.C.FA.P427 3310/IA/3-1 (Pavement) - Subgrade Works (fill:4637m3; subgrade: 25259m3) C11_6 d/w - 10h/d - With 34 2 18-May-23 28-Jun-23 18-Jul-23 25-Aug-23 49
HK Hols - No B/O periods
310.C.FA.P430 3310/IA/3-1 (Pavement) - CASB (15469m3) (37125.60 tonne) (was
C11_6C3)
d/w - 10h/d - With 48 2 31-May-23 27-Jul-23 29-Jul-23 22-Sep-23 49
HK Hols - No B/O periods
310.C.FA.P800 3310/IA/3-1 - Milling of the Existing Runway (was
C11_6C3)
d/w - 10h/d - With 6 2 29-Jun-23 06-Jul-23 14-Oct-23 20-Oct-23 89
HK Hols - No B/O periods
310.C.FA.P433 3310/IA/3-1 (Pavement) - CABC (12965m3) (31116.0 tonne) (was
C11_6C3)
d/w - 10h/d - With 41 2 28-Jul-23 13-Sep-23 23-Sep-23 13-Nov-23 49
HK Hols - No B/O periods
310.C.FA.P436 3310/IA/3-1 (Pavement) - Asphalt (MABC/MAWC/PMABC) (3567m3) (8560.8 tonne) (was
C11_6C3)
d/w - 10h/d - With 15 1 23-Aug-23 08-Sep-23 21-Oct-23 08-Nov-23 49
HK Hols - No B/O periods
310.C.FA.P439 3310/IA/3-1 (Pavement) - Asphalt (PMAWC) (2273m3) (5455.2 tonne) (was
C11_6C3)
d/w - 10h/d - With 11 1 09-Sep-23 21-Sep-23 09-Nov-23 21-Nov-23 49
HK Hols - No B/O periods
3310/IA/3-1 AGL (was
C11_6C3)
d/w - 10h/d - With HK Hols
154- No B/O 7periods (was
12-Jun-23
C3) 13-Dec-23 04-Sep-23 16-Dec-23 3
310.C.FA.P442 3310/IA/3-1 (AGL) - AGL Drawpit/Earthpit/Base Can (298 nr) - 8 no/d, 1 WF C11_6 d/w - 10h/d - With 39 2 12-Jun-23 28-Jul-23 09-Sep-23 27-Oct-23 75
HK Hols - No B/O periods
310.C.FA.P445 3310/IA/3-1 (AGL) - AGL Ductbank (5195 m) (was
C11_6C3)
d/w - 10h/d - With 48 2 12-Jun-23 08-Aug-23 04-Sep-23 01-Nov-23 70
HK Hols - No B/O periods
310.C.FA.P448 3310/IA/3-1 (AGL) - AGL Mid Can (298 nr) - 20 no/d, 1 WF (was
C11_6C3)
d/w - 10h/d - With 17 2 09-Aug-23 28-Aug-23 07-Oct-23 27-Oct-23 49
HK Hols - No B/O periods
(was C3)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 24 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.FA.P451 3310/IA/3-1 (AGL) - AGL Top Can (298 nr) C11_6 d/w - 10h/d - With 11 1 01-Dec-23 13-Dec-23 05-Dec-23 16-Dec-23 3
HK Hols - No B/O periods
3310/IA/3-2b (EVT) (was
C11_6C3)
d/w - 10h/d - With HK Hols
155- No B/O 7periods (was
09-Jun-23
C3) 13-Dec-23 17-Oct-23 16-Dec-23 3
3310/IA/3-2b (EVT) Pavement C11_6 d/w - 10h/d - With HK Hols
51- No B/O 2periods (was
09-Jun-23
C3) 10-Aug-23 17-Oct-23 16-Dec-23 107
310.C.FA.P401 *** Complete Backfilling of EVT(Southern Section) *** C11_6 d/w - 10h/d - With 0 09-Jun-23 17-Oct-23 107
HK Hols - No B/O periods
310.C.FA.P407 3310/IA/3-2b (Pavement) - Subgrade Works for Taxiway (cut:6770m3; subgrade:5747m3) (was
C11_6C3)
d/w - 10h/d - With 14 10-Jun-23 27-Jun-23 18-Oct-23 03-Nov-23 107
HK Hols - No B/O periods
310.C.FA.P804 3310/IA/3-2b - Milling of the Existing Runway (was
C11_6C3)
d/w - 10h/d - With 6 2 28-Jun-23 05-Jul-23 30-Nov-23 06-Dec-23 129
HK Hols - No B/O periods
310.C.FA.P410 3310/IA/3-2b (Pavement) - CASB (3248m3) (7795.20 tonne) (was
C11_6C3)
d/w - 10h/d - With 12 28-Jun-23 12-Jul-23 04-Nov-23 17-Nov-23 107
HK Hols - No B/O periods
310.C.FA.P404 3310/IA/3-2b (Pavement) - CABC (3247m3) (7792.80 tonne) (was
C11_6C3)
d/w - 10h/d - With 10 18-Jul-23 28-Jul-23 23-Nov-23 04-Dec-23 107
HK Hols - No B/O periods
310.C.FA.P419 3310/IA/3-2b - realign interim security fence (was
C11_6C3)
d/w - 10h/d - With 10 31-Jul-23 10-Aug-23 06-Dec-23 16-Dec-23 107
HK Hols - No B/O periods
310.C.FA.P413 3310/IA/3-2b (Pavement) - Asphalt (MABC/MAWC/PMABC) (1010m3) (2424 tonne) (was
C11_6C3)
d/w - 10h/d - With 4 01-Aug-23 04-Aug-23 07-Dec-23 11-Dec-23 107
HK Hols - No B/O periods
310.C.FA.P416 3310/IA/3-2b (Pavement) - Asphalt (PMAWC) (1259m3) (3021.6 tonne) (was
C11_6C3)
d/w - 10h/d - With 5 05-Aug-23 10-Aug-23 12-Dec-23 16-Dec-23 107
HK Hols - No B/O periods
3310/IA/3-2b (EVT) AGL (was
C11_6C3)
d/w - 10h/d - With HK Hols
136- No B/O 5periods (was
05-Jul-23
C3) 13-Dec-23 10-Nov-23 16-Dec-23 3
310.C.FA.P422 3310/IA/3-2b (AGL) - AGL Drawpit/Earthpit/Base Can (46 nr) - 8 no/d, 1 WF C11_6 d/w - 10h/d - With 7 1 05-Jul-23 12-Jul-23 10-Nov-23 17-Nov-23 107
HK Hols - No B/O periods
310.C.FA.P425 3310/IA/3-2b (AGL) - AGL Ductbank (800 m) (was
C11_6C3)
d/w - 10h/d - With 12 2 11-Jul-23 24-Jul-23 16-Nov-23 29-Nov-23 107
HK Hols - No B/O periods
310.C.FA.P428 3310/IA/3-2b (AGL) - AGL Mid Can (46 nr) - 20 no/d, 1 WF (was
C11_6C3)
d/w - 10h/d - With 3 1 29-Jul-23 01-Aug-23 05-Dec-23 07-Dec-23 107
HK Hols - No B/O periods
310.C.FA.P431 3310/IA/3-2b (AGL) - AGL Top Can (46 nr) (was
C11_6C3)
d/w - 10h/d - With 5 1 08-Dec-23 13-Dec-23 12-Dec-23 16-Dec-23 3
HK Hols - No B/O periods
3310/IA/3-2a (EVT) (was
C11_6C3)
d/w - 10h/d - With HK Hols
53- No B/O14
periods (was
12-Oct-23
C3) 13-Dec-23 16-Oct-23 16-Dec-23 3
3310/IA/3-2a (EVT) Pavement C11_6 d/w - 10h/d - With HK Hols
44- No B/O 8periods (was
12-Oct-23
C3) 02-Dec-23 16-Oct-23 11-Dec-23 7
310.C.FA.P432 3310/IA/3 -2a (Pavement) - Subgrade Works (cut/fill:0; subgrade:17344m3) C11_6 d/w - 10h/d - With 21 2 12-Oct-23 06-Nov-23 16-Oct-23 09-Nov-23 3
HK Hols - No B/O periods
310.C.FA.P435 3310/IA/3 -2a (Pavement) - CASB (9081m3) (21794.40 tonne) (was
C11_6C3)
d/w - 10h/d - With 21 2 18-Oct-23 11-Nov-23 21-Oct-23 15-Nov-23 3
HK Hols - No B/O periods
310.C.FA.P438 3310/IA/3 -2a (Pavement) - CABC (6995m3) (16788.00 tonne) (was
C11_6C3)
d/w - 10h/d - With 21 2 31-Oct-23 23-Nov-23 08-Nov-23 01-Dec-23 7
HK Hols - No B/O periods
310.C.FA.P441 3310/IA/3 -2a (Pavement) - Asphalt (MABC/MAWC/PMABC) (3659m3) (8781.6 tonne) (was
C11_6C3)
d/w - 10h/d - With 14 1 11-Nov-23 27-Nov-23 20-Nov-23 05-Dec-23 7
HK Hols - No B/O periods
310.C.FA.P444 3310/IA/3 -2a (Pavement) - Asphalt (PMAWC) (935m3) (2244 tonne) (was
C11_6C3)
d/w - 10h/d - With 5 1 28-Nov-23 02-Dec-23 06-Dec-23 11-Dec-23 7
HK Hols - No B/O periods
3310/IA/3-2a (EVT) AGL (was
C11_6C3)
d/w - 10h/d - With HK Hols
51- No B/O 6periods (was
14-Oct-23
C3) 13-Dec-23 18-Oct-23 16-Dec-23 3
310.C.FA.P450 3310/IA/3 -2a (AGL) - AGL Ductbank (3130 m) C11_6 d/w - 10h/d - With 29 2 14-Oct-23 17-Nov-23 18-Oct-23 21-Nov-23 3
HK Hols - No B/O periods
310.C.FA.P447 3310/IA/3 -2a (AGL) - AGL Drawpit/Earthpit/Base Can (151 nr) - 8 no/d, 1 WF (was
C11_6C3)
d/w - 10h/d - With 21 2 25-Oct-23 17-Nov-23 02-Nov-23 25-Nov-23 7
HK Hols - No B/O periods
310.C.FA.P453 3310/IA/3 -2a (AGL) - AGL Mid Can (151 nr) - 20 no/d, 1 WF (was
C11_6C3)
d/w - 10h/d - With 9 1 11-Nov-23 21-Nov-23 20-Nov-23 29-Nov-23 7
HK Hols - No B/O periods
310.C.FA.P456 3310/IA/3 -2a (AGL) - AGL Top Can (151 nr) (was
C11_6C3)
d/w - 10h/d - With 5 1 08-Dec-23 13-Dec-23 12-Dec-23 16-Dec-23 3
HK Hols - No B/O periods
3310/IA/3 Interface Work Area Completion and Remaining Works (was C3) 139 2 11-Nov-23 02-May-24 15-Nov-23 25-Aug-24 95

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 25 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.FA.P836 3310/IA/3 - AGL Foundations/Earthing Rode C11_6 d/w - 10h/d - With 28 2 11-Nov-23 13-Dec-23 15-Nov-23 16-Dec-23 3
HK Hols - No B/O periods
310.C.FA.P455 Achieved KD-5G Complete all civil works for AGL Sys at IWA 3310/IA/3 & provide access (was
C01_7C3)
d/w - 10h/d - No HK 0 13-Dec-23 17-Dec-23 4
for Contract <3305> Hols - No B/O periods (was
310.C.FA.P458 Allow Access to Contract <3305> for AGL System Works for Interface Work Area C1)
C01_7 d/w - 10h/d - No HK 0 13-Dec-23 19-Dec-23 6
3310/IA/3 Hols - No B/O periods (was
310.C.FA.P452 Achieved PMS #16 - Complete all civil wks in 3310/IA/3 &provide access for Others to C1)
C11_6 d/w - 10h/d - With 0 13-Dec-23 28-Mar-24 86
complete installation of AGL system HK Hols - No B/O periods
310.C.FA.P784 3310/IA/3 - AGL System Works (by Contract <3305>) (assumed 3 months) (was
C01_7C3)
d/w - 10h/d - No HK 90 14-Dec-23 12-Mar-24 20-Dec-23 18-Mar-24 6
Hols - No B/O periods (was
310.C.FA.P470 3310/IA/3 - Soil mixed with Hydroseeding (3412 m3) @3310/IA/3-1 C1)
C11_6 d/w - 10h/d - With 30 17-Feb-24 22-Mar-24 23-Feb-24 28-Mar-24 5
HK Hols - No B/O periods
310.C.FA.P464 3310/IA/3 - Runway Grooving @3310/IA/3 (was
C11_6C3)
d/w - 10h/d - With 9 13-Mar-24 22-Mar-24 19-Mar-24 28-Mar-24 5
HK Hols - No B/O periods
310.C.FA.P467 3310/IA/3 - Line Marking or defect remedial works @3310/IA/3-2a (was
C11_6C3)
d/w - 10h/d - With 30 23-Mar-24 02-May-24 02-Apr-24 08-May-24 5
HK Hols - No B/O periods
310.C.FA.P473 WA 3310/3, 6, 6B, 6C, 7, 8 & B - Vacate Work Area (Portion) (was
C01_7C3)
d/w - 10h/d - No HK 0 02-May-24 25-Aug-24 115
Hols - No B/O periods (was
Interface Work Area 3310/IA/4 (Pavement and AGL) C1) 381 38 20-Sep-22 30-Dec-23 24-May-23 24-Aug-24 193
3310/IA/4-1 C11_6 d/w - 10h/d - With HK Hols
279- No B/O13
periods (was
20-Sep-22
C3) 28-Aug-23 24-May-23 23-Sep-23 23
3310/IA/4-1 Pavement C11_6 d/w - 10h/d - With HK Hols
218- No B/O 9periods (was
20-Sep-22
C3) 15-Jun-23 24-May-23 11-Sep-23 73
310.C.FA.P870.B02 3310/IA/4 - Carry Out Survey to Check Level C11_6 d/w - 10h/d - With 6 1 20-Sep-22 26-Sep-22 24-May-23 31-May-23 199
HK Hols - No B/O periods
310.C.FA.P742 3310/IA/4-1 (Pavement) - Site Formation (was
C11_6C3)
d/w - 10h/d - With 2 1 09-Jan-23 10-Jan-23 07-Jul-23 08-Jul-23 143
HK Hols - No B/O periods
310.C.FA.P744 3310/IA/4-1 (Pavement) - Subgrade Works (fill:3473m3; subgrade:5276m3) (was
C11_6C3)
d/w - 10h/d - With 14 1 11-Apr-23 26-Apr-23 10-Jul-23 25-Jul-23 73
HK Hols - No B/O periods
310.C.FA.P748 3310/IA/4-1 (Pavement) - CASB (4399m3) (10557.60 tonne) (was
C11_6C3)
d/w - 10h/d - With 14 1 17-Apr-23 03-May-23 15-Jul-23 31-Jul-23 73
HK Hols - No B/O periods
310.C.FA.P808 3310/IA/4-1 Milling of the Existing Runway (was
C11_6C3)
d/w - 10h/d - With 6 2 27-Apr-23 04-May-23 18-Aug-23 24-Aug-23 93
HK Hols - No B/O periods
310.C.FA.P752 3310/IA/4-1 (Pavement) - CABC (3399m3) (8157.60 tonne) (was
C11_6C3)
d/w - 10h/d - With 11 1 03-May-23 15-May-23 31-Jul-23 11-Aug-23 73
HK Hols - No B/O periods
310.C.FA.P756 3310/IA/4-1 (Pavement) - Asphalt (MABC/MAWC/PMABC) (2082m3) (4996.8 tonne) (was
C11_6C3)
d/w - 10h/d - With 9 1 18-May-23 29-May-23 15-Aug-23 24-Aug-23 73
HK Hols - No B/O periods
310.C.FA.P760 3310/IA/4-1 (Pavement) - Asphalt (PMAWC) (3504m3) (8409.6 tonne) (was
C11_6C3)
d/w - 10h/d - With 15 1 30-May-23 15-Jun-23 25-Aug-23 11-Sep-23 73
HK Hols - No B/O periods
3310/IA/4-1 AGL (was
C11_6C3)
d/w - 10h/d - With HK Hols
107- No B/O 4periods (was
21-Apr-23
C3) 28-Aug-23 20-Jul-23 23-Sep-23 23
310.C.FA.P768 3310/IA/4-1 (AGL) - AGL Drawpit/Earthpit/Base Can (112 nr) - 8 no/d, 1 WF C11_6 d/w - 10h/d - With 15 1 21-Apr-23 09-May-23 20-Jul-23 05-Aug-23 73
HK Hols - No B/O periods
310.C.FA.P772 3310/IA/4-1 (AGL) - AGL Ductbank (2625 m) (was
C11_6C3)
d/w - 10h/d - With 14 1 22-Apr-23 09-May-23 21-Jul-23 05-Aug-23 73
HK Hols - No B/O periods
310.C.FA.P776 3310/IA/4-1( AGL) - AGL Mid Can (112 nr) - 20 no/d, 1 WF (was
C11_6C3)
d/w - 10h/d - With 7 1 15-May-23 22-May-23 11-Aug-23 18-Aug-23 73
HK Hols - No B/O periods
310.C.FA.P780 3310/IA/4-1 (AGL) - AGL Top Can 112nr) (was
C11_6C3)
d/w - 10h/d - With 11 1 16-Aug-23 28-Aug-23 12-Sep-23 23-Sep-23 23
HK Hols - No B/O periods
3310/IA/4-3 (was
C11_6C3)
d/w - 10h/d - With HK Hols
130- No B/O15
periods (was
17-Mar-23
C3) 24-Aug-23 13-Jun-23 23-Sep-23 26
3310/IA/4-3 Pavement C11_6 d/w - 10h/d - With HK Hols
69- No B/O 9periods (was
17-Mar-23
C3) 12-Jun-23 13-Jun-23 22-Sep-23 86
310.C.FA.P061 3310/IA/4-3 (Pavement) - Site Formation C11_6 d/w - 10h/d - With 1 1 17-Mar-23 17-Mar-23 13-Jun-23 13-Jun-23 69
HK Hols - No B/O periods
(was C3)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 26 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.FA.P064 3310/IA/4-3 (Pavement) - Subgrade Works (cut:10366m3; subgrade:27681 m3) C11_6 d/w - 10h/d - With 35 2 18-Mar-23 03-May-23 14-Jun-23 26-Jul-23 69
HK Hols - No B/O periods
310.C.FA.P067 3310/IA/4-3 (Pavement) - CASB (15297m3) (36712.80 tonne) (was
C11_6C3)
d/w - 10h/d - With 45 2 24-Mar-23 20-May-23 20-Jun-23 12-Aug-23 69
HK Hols - No B/O periods
310.C.FA.P076 3310/IA/4-3 (Pavement) - CABC (14475m3) (34740.00 tonne) (was
C11_6C3)
d/w - 10h/d - With 44 2 11-Apr-23 02-Jun-23 03-Aug-23 22-Sep-23 94
HK Hols - No B/O periods
310.C.FA.P082 3310/IA/4-3 (Pavement) - Asphalt (MABC/MAWC/PMABC) (4256m3) (10214.4 tonne) (was
C11_6C3)
d/w - 10h/d - With 16 1 15-May-23 02-Jun-23 31-Aug-23 18-Sep-23 90
HK Hols - No B/O periods
310.C.FA.P085 3310/IA/4-3 (Pavement) - Asphalt (PMAWC) (3432m3) (8236.8 tonne) (was
C11_6C3)
d/w - 10h/d - With 13 1 29-May-23 12-Jun-23 30-Aug-23 13-Sep-23 78
HK Hols - No B/O periods
3310/IA/4-3 AGL (was
C11_6C3)
d/w - 10h/d - With HK Hols
121- No B/O 6periods (was
28-Mar-23
C3) 24-Aug-23 24-Jun-23 23-Sep-23 26
310.C.FA.P073 3310/IA/4-3 (AGL) - AGL Ductbank (5161 m) C11_6 d/w - 10h/d - With 47 2 28-Mar-23 27-May-23 24-Jun-23 18-Aug-23 69
HK Hols - No B/O periods
310.C.FA.P070 3310/IA/4-3 (AGL) - AGL Drawpit/Earthpit/Base Can (251 nr) - 8 no/d, 1 WF (was
C11_6C3)
d/w - 10h/d - With 33 2 18-Apr-23 27-May-23 22-Jul-23 29-Aug-23 78
HK Hols - No B/O periods
310.C.FA.P079 3310/IA/4-3( AGL) - AGL Mid Can (251 nr) - 20 no/d, 1 WF (was
C11_6C3)
d/w - 10h/d - With 13 1 12-May-23 27-May-23 15-Aug-23 29-Aug-23 78
HK Hols - No B/O periods
310.C.FA.P088 3310/IA/4-3 (AGL) - AGL Top Can (251 nr) (was
C11_6C3)
d/w - 10h/d - With 9 1 15-Aug-23 24-Aug-23 14-Sep-23 23-Sep-23 26
HK Hols - No B/O periods
3310/IA/4-2 (was C3) - NOTAM (M,W,Th,Su-01:30-07:30)
C23_4d/w 64 8 - No HK
26-Mar-23
Hols - With B/O
27-Aug-23
Periods & Flight01-Jun-23
Checks 24-Sep-23 17
3310/IA/4-2 Pavement C23_4d/w - NOTAM (M,W,Th,Su-01:30-07:30)
36 4 - No HK
26-Mar-23
Hols - With B/O06-Jul-23
Periods & Flight01-Jun-23
Checks 10-Sep-23 37
310.C.FA.P089 3310/IA/4-2 (Pavement) - Reinstatement of Taxiways T, B6 and A (after modification of C23_4d/w - NOTAM 11 1 26-Mar-23 24-May-23 01-Jun-23 19-Jun-23 15
existing drainage) [NOTAM] (M,W,Th,Su-01:30-07:30) -
310.C.FA.P092 3310/IA/4-2 (Pavement) - Milling or Excavation [NOTAM] No HK Hols- -NOTAM
C23_4d/w With B/O 5 1 25-May-23 01-Jun-23 21-Jun-23 28-Jun-23 15
(M,W,Th,Su-01:30-07:30) -
310.C.FA.P095 3310/IA/4-2 (Pavement) - Asphalt (MABC/MAWC/PMABC) (377m3) (904.80 No HK Hols- -NOTAM
C23_4d/w With B/O 11 1 11-Jun-23 28-Jun-23 14-Aug-23 31-Aug-23 37
tonne)[NOTAM] (M,W,Th,Su-01:30-07:30) -
310.C.FA.P098 3310/IA/4-2 (Pavement) - Asphalt (PMAWC) (1056m3) (2534.40 tonne) [NOTAM] No HK Hols- -NOTAM
C23_4d/w With B/O 5 1 29-Jun-23 06-Jul-23 03-Sep-23 10-Sep-23 37
(M,W,Th,Su-01:30-07:30) -
3310/IA/4-2 AGL No HK Hols- -NOTAM
C23_4d/w With B/O(M,W,Th,Su-01:30-07:30)
54 4 - No HK
24-May-23
Hols - With B/O
27-Aug-23
Periods & Flight19-Jun-23
Checks 24-Sep-23 17
310.C.FA.P113 3310/IA/4-2 (AGL) - AGL Ductbank (561 m) [NOTAM] C23_4d/w - NOTAM 11 1 24-May-23 11-Jun-23 19-Jun-23 06-Jul-23 15
(M,W,Th,Su-01:30-07:30) -
310.C.FA.P116 3310/IA/4-2 (AGL) - AGL Drawpit/Earthpit/Base Can (18 nr) [NOTAM] - 2 no/d, 1 WF No HK Hols- -NOTAM
C23_4d/w With B/O 10 1 25-May-23 11-Jun-23 30-Jul-23 14-Aug-23 37
(NOTAM) (M,W,Th,Su-01:30-07:30) -
310.C.FA.P119 3310/IA/4-2 (AGL) - AGL Mid Can (18 nr) [NOTAM] - 5 no/d, 1 WF (NOTAM) No HK Hols- -NOTAM
C23_4d/w With B/O 5 1 12-Jun-23 19-Jun-23 16-Aug-23 23-Aug-23 37
(M,W,Th,Su-01:30-07:30) -
310.C.FA.P122 3310/IA/4-2 (AGL) - AGL Top Can (18 nr) [NOTAM] No HK Hols- -NOTAM
C23_4d/w With B/O 8 1 13-Aug-23 27-Aug-23 11-Sep-23 24-Sep-23 17
(M,W,Th,Su-01:30-07:30) -
3310/IA/4 Interface Work Area Completion and Remaining Works No HK Hols - With B/O 133 2 24-Jul-23 30-Dec-23 19-Aug-23 24-Aug-24 193
310.C.FA.P840 3310/IA/4 - AGL Foundations/Earthing Rode C11_6 d/w - 10h/d - With 28 2 24-Jul-23 24-Aug-23 19-Aug-23 20-Sep-23 23
HK Hols - No B/O periods
310.C.FA.P101 Achieved KD-5E Complete all civil works for AGL Sys at IWA 3310/IA/4 & provide access (was
C01_7C3)
d/w - 10h/d - No HK 0 28-Aug-23 24-Sep-23 27
for Contract <3305> Hols - No B/O periods (was
310.C.FA.P104 Allow Access to Contract <3305> for AGL System Works for Interface Work Area C1)
C01_7 d/w - 10h/d - No HK 0 28-Aug-23 27-Nov-23 91
3310/IA/4 Hols - No B/O periods (was
310.C.FA.P107 3310/IA/4 - AGL System Works (by Contract <3305>) (assumed 3 months) C1)
C01_7 d/w - 10h/d - No HK 90 29-Aug-23 26-Nov-23 28-Nov-23 25-Feb-24 91
Hols - No B/O periods (was
310.C.FA.P110 3310/IA/4 - Runway Grooving C1)
C11_6 d/w - 10h/d - With 9 27-Nov-23 06-Dec-23 26-Feb-24 06-Mar-24 73
HK Hols - No B/O periods
310.C.FA.P128 3310/IA/4- Line Marking or defect remedial works [NOTAM] (was C3) - NOTAM
C23_4d/w 6 07-Dec-23 17-Dec-23 14-Mar-24 24-Mar-24 32
(M,W,Th,Su-01:30-07:30) -
No HK Hols - With B/O
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 27 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.FA.P125 3310/IA/4 -Soil mixed with Hydroseeding C11_6 d/w - 10h/d - With 19 07-Dec-23 30-Dec-23 07-Mar-24 28-Mar-24 73
HK Hols - No B/O periods
310.C.FA.P131 3310/IA/4 - Vacate Work Areas 3310/2, 3, 8, 8A, 8B (was
C11_6C3)
d/w - 10h/d - With 0 30-Dec-23 24-Aug-24 193
HK Hols - No B/O periods
Interface Work Area 3310/IA/5 (Pavement and AGL) (was C3) 447 60 27-Sep-22 27-Mar-24 07-Sep-23 25-Aug-24 121
3310/IA/5-1 C11_6 d/w - 10h/d - With HK Hols
386- No B/O17
periods (was
27-Sep-22
C3) 13-Jan-24 07-Sep-23 13-Jan-24 0
3310/IA/5-1 Pavement C11_6 d/w - 10h/d - With HK Hols
361- No B/O11
periods (was
27-Sep-22
C3) 12-Dec-23 07-Sep-23 05-Jan-24 18
310.C.FA.P875.B02 3310/IA/5 - Carry Out Survey to Check Level C11_6 d/w - 10h/d - With 6 1 27-Sep-22 05-Oct-22 07-Sep-23 13-Sep-23 281
HK Hols - No B/O periods
310.C.FA.P475 3310/IA/5-1 (Pavement) - Subgrade Works (cut:7193m3; subgrade:14505 m3) (was
C11_6C3)
d/w - 10h/d - With 38 2 14-Sep-23 31-Oct-23 07-Oct-23 21-Nov-23 18
HK Hols - No B/O periods
310.C.FA.P478 3310/IA/5-1 (Pavement) - CASB (9928m3)(23827.20 tonne) (was
C11_6C3)
d/w - 10h/d - With 32 2 29-Sep-23 08-Nov-23 24-Oct-23 29-Nov-23 18
HK Hols - No B/O periods
310.C.FA.P484 3310/IA/5-1 (Pavement) - CABC (8432m3) (20236.80 tonne) (was
C11_6C3)
d/w - 10h/d - With 27 2 24-Oct-23 23-Nov-23 14-Nov-23 14-Dec-23 18
HK Hols - No B/O periods
310.C.FA.P812 3310/IA/5-1 - Milling of the Existing Runway (was
C11_6C3)
d/w - 10h/d - With 6 2 01-Nov-23 07-Nov-23 04-Dec-23 09-Dec-23 28
HK Hols - No B/O periods
310.C.FA.P505 3310/IA/5-1 (Pavement) - Asphalt (MABC/MAWC/PMABC) (2585m3) (6204 tonne) (was
C11_6C3)
d/w - 10h/d - With 11 1 20-Nov-23 01-Dec-23 11-Dec-23 22-Dec-23 18
HK Hols - No B/O periods
310.C.FA.P511 3310/IA/5-1 (Pavement) - Asphalt (PMAWC) (2124m3) (5097.6 tonne) (was
C11_6C3)
d/w - 10h/d - With 9 1 02-Dec-23 12-Dec-23 23-Dec-23 05-Jan-24 18
HK Hols - No B/O periods
3310/IA/5-1 AGL (was
C11_6C3)
d/w - 10h/d - With HK Hols
89- No B/O 6periods (was
26-Sep-23
C3) 13-Jan-24 19-Oct-23 13-Jan-24 0
310.C.FA.P485 3310/IA/5-1 (AGL) - AGL Drawpit/Earthpit/Base Can (313 nr) - 8 no/d, 1 WF C11_6 d/w - 10h/d - With 41 2 26-Sep-23 15-Nov-23 19-Oct-23 06-Dec-23 18
HK Hols - No B/O periods
310.C.FA.P488 3310/IA/5-1 (AGL) - AGL Ductbank (4719m) (was
C11_6C3)
d/w - 10h/d - With 32 2 09-Oct-23 15-Nov-23 31-Oct-23 06-Dec-23 18
HK Hols - No B/O periods
310.C.FA.P494 3310/IA/5-1 (AGL) - AGL Mid Can (313 nr) - 20 no/d, 1 WF (was
C11_6C3)
d/w - 10h/d - With 17 1 04-Nov-23 23-Nov-23 25-Nov-23 14-Dec-23 18
HK Hols - No B/O periods
310.C.FA.P503 3310/IA/5-1 (AGL) - AGL Top Can (313 nr) (was
C11_6C3)
d/w - 10h/d - With 9 1 04-Jan-24 13-Jan-24 04-Jan-24 13-Jan-24 0
HK Hols - No B/O periods
3310/IA/5-2b (was
C11_6C3)
d/w - 10h/d - With HK Hols
93- No B/O13
periods (was
21-Sep-23
C3) 13-Jan-24 28-Oct-23 13-Jan-24 0
3310/IA/5-2b Pavement C11_6 d/w - 10h/d - With HK Hols
53- No B/O 8periods (was
21-Sep-23
C3) 24-Nov-23 28-Oct-23 09-Jan-24 36
310.C.FA.P481 3310/IA/5-2b (Pavement) - Subgrade Works (cut:1676m3: subgrade:2523m3) C11_6 d/w - 10h/d - With 33 2 21-Sep-23 01-Nov-23 28-Oct-23 05-Dec-23 29
HK Hols - No B/O periods
310.C.FA.P487 3310/IA/5-2b (Pavement) - CASB (1971m3) (4730.40 tonne) (was
C11_6C3)
d/w - 10h/d - With 23 2 11-Oct-23 07-Nov-23 15-Nov-23 11-Dec-23 29
HK Hols - No B/O periods
310.C.FA.P496 3310/IA/5-2b (Pavement) - CABC (2004m3) (4809.60 tonne) (was
C11_6C3)
d/w - 10h/d - With 22 2 25-Oct-23 18-Nov-23 06-Dec-23 03-Jan-24 36
HK Hols - No B/O periods
310.C.FA.P502 3310/IA/5-2b (Pavement) - Asphalt (MABC/MAWC/PMABC) (781m3) (1874.4 tonne) (was
C11_6C3)
d/w - 10h/d - With 9 1 08-Nov-23 17-Nov-23 20-Dec-23 02-Jan-24 36
HK Hols - No B/O periods
310.C.FA.P508 3310/IA/5-2b (Pavement) - Asphalt (PMAWC) (950m3) (2280 tonne) (was
C11_6C3)
d/w - 10h/d - With 6 1 18-Nov-23 24-Nov-23 03-Jan-24 09-Jan-24 36
HK Hols - No B/O periods
3310/IA/5-2b AGL (was
C11_6C3)
d/w - 10h/d - With HK Hols
73- No B/O 5periods (was
17-Oct-23
C3) 13-Jan-24 21-Nov-23 13-Jan-24 0
310.C.FA.P493 3310/IA/5-2b (AGL) - AGL Ductbank (2704 m) C11_6 d/w - 10h/d - With 23 2 17-Oct-23 13-Nov-23 21-Nov-23 16-Dec-23 29
HK Hols - No B/O periods
310.C.FA.P490 3310/IA/5-2b (AGL) - AGL Drawpit/Earthpit/Base Can (100 nr) - 8 no/d, 1 WF (was C3)
C11_6 d/w - 10h/d - With 14 1 28-Oct-23 13-Nov-23 01-Dec-23 16-Dec-23 29
HK Hols - No B/O periods
310.C.FA.P499 3310/IA/5-2b (AGL) - AGL Mid Can (100 nr) - 20 no/d, 1 WF (was
C11_6C3)
d/w - 10h/d - With 6 1 06-Nov-23 11-Nov-23 18-Dec-23 23-Dec-23 36
HK Hols - No B/O periods
310.C.FA.P514 3310/IA/5-2b (AGL) - AGL Top Can (120 nr) (was
C11_6C3)
d/w - 10h/d - With 6 1 08-Jan-24 13-Jan-24 08-Jan-24 13-Jan-24 0
HK Hols - No B/O periods
(was C3)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 28 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
3310/IA/5-2a (WVT) C11_6 d/w - 10h/d - With HK Hols
75- No B/O15
periods (was
14-Oct-23
C3) 13-Jan-24 14-Oct-23 13-Jan-24 0
3310/IA/5-2a (WVT) Pavement C11_6 d/w - 10h/d - With HK Hols
68- No B/O10
periods (was
14-Oct-23
C3) 05-Jan-24 14-Oct-23 13-Jan-24 7
310.C.FA.P482 3310/IA/5-2a (Pavement) - Subgrade Works (cut/fill: 0 ; subgrade:29527 m3) C11_6 d/w - 10h/d - With 30 2 14-Oct-23 20-Nov-23 14-Oct-23 18-Nov-23 0
HK Hols - No B/O periods
310.C.FA.P491 3310/IA/5-2a (Pavement) - CASB (14748m3) (35395.20 tonne) (was
C11_6C3)
d/w - 10h/d - With 31 2 03-Nov-23 08-Dec-23 03-Nov-23 08-Dec-23 0
HK Hols - No B/O periods
310.C.EX.U429 3310/IA/5-2a (Pavement) - WVT Completion of Zone 3 backfill to +6.5 (was
C11_6C3)
d/w - 10h/d - With 0 20-Nov-23 18-Nov-23 0
HK Hols - No B/O periods
310.C.FA.P816 3310/IA/5-2a - Milling of the Existing Runway (was
C11_6C3)
d/w - 10h/d - With 6 2 20-Nov-23 25-Nov-23 16-Dec-23 22-Dec-23 23
HK Hols - No B/O periods
310.C.FA.P497 3310/IA/5-2a (Pavement) - CABC (13500m3) (32400 tonne) (was
C11_6C3)
d/w - 10h/d - With 21 2 30-Nov-23 23-Dec-23 08-Dec-23 04-Jan-24 7
HK Hols - No B/O periods
310.C.FA.P500 3310/IA/5-2a (Pavement) - Asphalt (MABC/MAWC/PMABC) (3650m3) (8760 tonne) (was
C11_6C3)
d/w - 10h/d - With 11 1 15-Dec-23 29-Dec-23 23-Dec-23 08-Jan-24 7
HK Hols - No B/O periods
310.C.FA.P506 3310/IA/5-2a (Pavement) - Asphalt (PMAWC) (1499 m3) (3597.6 tonne) (was
C11_6C3)
d/w - 10h/d - With 5 1 30-Dec-23 05-Jan-24 09-Jan-24 13-Jan-24 7
HK Hols - No B/O periods
3310/IA/5-2a (WVT) AGL (was
C11_6C3)
d/w - 10h/d - With HK Hols
59- No B/O 5periods (was
03-Nov-23
C3) 13-Jan-24 03-Nov-23 13-Jan-24 0
310.C.FA.P548 3310/IA/5-2a (AGL) - AGL Ductbank (2703m) C11_6 d/w - 10h/d - With 31 2 03-Nov-23 08-Dec-23 03-Nov-23 08-Dec-23 0
HK Hols - No B/O periods
310.C.FA.P545 3310/IA/5-2a (AGL) - AGL Drawpit/Earthpit/Base Can (100 nr) - 8 no/d, 1 WF (was
C11_6C3)
d/w - 10h/d - With 14 1 23-Nov-23 08-Dec-23 23-Nov-23 08-Dec-23 0
HK Hols - No B/O periods
310.C.FA.P563 3310/IA/5-2a (AGL) - AGL Mid Can (100nr) - 20 no/d, 1 WF (was
C11_6C3)
d/w - 10h/d - With 5 1 12-Dec-23 16-Dec-23 03-Jan-24 08-Jan-24 16
HK Hols - No B/O periods
310.C.FA.P569 3310/IA/5-2a (AGL) - AGL Top Can (100 nr) (was
C11_6C3)
d/w - 10h/d - With 5 1 09-Jan-24 13-Jan-24 09-Jan-24 13-Jan-24 0
HK Hols - No B/O periods
3310/IA/5-3 (was
C11_6C3)
d/w - 10h/d - With HK Hols
215- No B/O13
periods (was
26-Apr-23
C3) 13-Jan-24 14-Sep-23 13-Jan-24 0
3310/IA/5-3 Pavement C11_6 d/w - 10h/d - With HK Hols
91- No B/O 9periods (was
26-Apr-23
C3) 15-Aug-23 14-Sep-23 04-Jan-24 116
310.C.FA.P530 3310.IA/5-3 (Pavement) - Site Formation C11_6 d/w - 10h/d - With 30 2 26-Apr-23 02-Jun-23 14-Sep-23 20-Oct-23 116
HK Hols - No B/O periods
310.C.FA.P533 3310.IA/5-3 (Pavement) - Subgrade Works (cut: 7543m3; subgrade:7023 m3) (was
C11_6C3)
d/w - 10h/d - With 16 1 27-May-23 15-Jun-23 16-Oct-23 03-Nov-23 116
HK Hols - No B/O periods
310.C.FA.P820 3310/IA/5-3 - Milling of the Existing Runway (was
C11_6C3)
d/w - 10h/d - With 6 2 15-Jun-23 23-Jun-23 08-Dec-23 14-Dec-23 145
HK Hols - No B/O periods
310.C.FA.P536 3310.IA/5-3 (Pavement) - CASB (3862m3) (9268.80 tonne) (was
C11_6C3)
d/w - 10h/d - With 11 1 15-Jun-23 29-Jun-23 04-Nov-23 16-Nov-23 116
HK Hols - No B/O periods
310.C.FA.P551 3310.IA/5-3 (Pavement) - CABC (4311m3) (10346.40 tonne) (was
C11_6C3)
d/w - 10h/d - With 11 1 13-Jul-23 26-Jul-23 30-Nov-23 12-Dec-23 116
HK Hols - No B/O periods
310.C.FA.P557 3310.IA/5-3 (Pavement) - Asphalt (MABC/MAWC/PMABC) (1808m3) (4339.2 tonne) (was
C11_6C3)
d/w - 10h/d - With 7 1 28-Jul-23 05-Aug-23 15-Dec-23 22-Dec-23 116
HK Hols - No B/O periods
310.C.FA.P560 3310.IA/5-3 (Pavement) - Asphalt (PMAWC) (1877m3) (4504.8 tonne) (was
C11_6C3)
d/w - 10h/d - With 8 1 05-Aug-23 15-Aug-23 23-Dec-23 04-Jan-24 116
HK Hols - No B/O periods
3310/IA/5-3 AGL (was
C11_6C3)
d/w - 10h/d - With HK Hols
163- No B/O 4periods (was
29-Jun-23
C3) 13-Jan-24 17-Nov-23 13-Jan-24 0
310.C.FA.P539 3310.IA/5-3 (AGL) - AGL Drawpit/Earthpit/Base Can (49 nr) - 8 no/d, 1 WF C11_6 d/w - 10h/d - With 7 1 29-Jun-23 08-Jul-23 22-Nov-23 29-Nov-23 120
HK Hols - No B/O periods
310.C.FA.P542 3310.IA/5-3 (AGL) - AGL Ductbank (937 m) (was
C11_6C3)
d/w - 10h/d - With 11 1 29-Jun-23 13-Jul-23 17-Nov-23 29-Nov-23 116
HK Hols - No B/O periods
310.C.FA.P554 3310.IA/5-3 (AGL) - AGL Mid Can (49 nr) - 20 no/d, 1 WF (was
C11_6C3)
d/w - 10h/d - With 3 1 25-Jul-23 28-Jul-23 12-Dec-23 14-Dec-23 116
HK Hols - No B/O periods
310.C.FA.P566 3310.IA/5-3 (AGL) - AGL Top Can (49 nr) (was
C11_6C3)
d/w - 10h/d - With 8 1 05-Jan-24 13-Jan-24 05-Jan-24 13-Jan-24 0
HK Hols - No B/O periods
3310/IA/5 Interface Work Area Completion and Remaining Works (was C3) 89 2 09-Dec-23 27-Mar-24 09-Dec-23 25-Aug-24 121

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 29 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.FA.P844 3310/IA/5 - AGL Foundations/Earthing Rode C11_6 d/w - 10h/d - With 28 2 09-Dec-23 13-Jan-24 09-Dec-23 13-Jan-24 0
HK Hols - No B/O periods
310.C.FA.P509 Achieved KD-5H Complete all civil works for AGL Sys at IWA 3310/IA/5 & provide access (was
C01_7C3)
d/w - 10h/d - No HK 0 13-Jan-24 14-Jan-24 1
for Contract <3305> Hols - No B/O periods (was
310.C.FA.P512 Allow Access to Contract <3305> for AGL System Works for Interface Work Area C1)
C01_7 d/w - 10h/d - No HK 0 13-Jan-24 14-Jan-24 1
3310/IA/5 Hols - No B/O periods (was
310.C.FA.P515 3310/IA/5 - AGL System Works (by Contract <3305>) (assumed 2 months) C1)
C01_7 d/w - 10h/d - No HK 60 14-Jan-24 13-Mar-24 15-Jan-24 14-Mar-24 1
Hols - No B/O periods (was
310.C.FA.P518 3310/IA/5- Runway Grooving C1)
C11_6 d/w - 10h/d - With 7 06-Mar-24 13-Mar-24 07-Mar-24 14-Mar-24 1
HK Hols - No B/O periods
310.C.FA.P524 3310/IA/5- Soil mixed with Hydroseeding (was
C11_6C3)
d/w - 10h/d - With 12 14-Mar-24 27-Mar-24 15-Mar-24 28-Mar-24 1
HK Hols - No B/O periods
310.C.FA.P521 3310/IA/5- Line Marking or defect remedial works (was
C11_6C3)
d/w - 10h/d - With 12 14-Mar-24 27-Mar-24 15-Mar-24 28-Mar-24 1
HK Hols - No B/O periods
310.C.FA.P527 WA 3310/4, 2, 9, 9A - Vacate Work Area (Portion) (was
C01_7C3)
d/w - 10h/d - No HK 0 27-Mar-24 25-Aug-24 151
Hols - No B/O periods (was
Interface Work Area 3310/IA/6 (Pavement and AGL) C1) 438 42 01-Sep-22 21-Feb-24 03-Feb-23 25-Aug-24 151
3310/IA/6-2 C11_6 d/w - 10h/d - With HK Hols
226- No B/O24
periods (was
01-Sep-22
C3) 07-Jun-23 03-Feb-23 24-Jun-23 14
3310/IA/6-2 Pavement C11_6 d/w - 10h/d - With HK Hols
226- No B/O16
periods (was
01-Sep-22
C3) 07-Jun-23 03-Feb-23 24-Jun-23 14
310.C.FA.P010.B02 3310/IA/6 (Pavement) - Carry Out Survey to Check Level C11_6 d/w - 10h/d - With 6 2 01-Sep-22 07-Sep-22 03-Feb-23 09-Feb-23 125
HK Hols - No B/O periods
310.C.FA.P010 3310/IA/6-2 (Pavement) - Site Formation (was
C11_6C3)
d/w - 10h/d - With 20 2 26-Sep-22 20-Oct-22 10-Feb-23 04-Mar-23 111
HK Hols - No B/O periods
310.C.FA.P013 3310/IA/6-2 (Pavement) - Subgrade Works (cut: 91297m3; subgrade:28810 m3) (was
C11_6C3)
d/w - 10h/d - With 38 2 11-Feb-23 27-Mar-23 28-Feb-23 17-Apr-23 14
HK Hols - No B/O periods
310.C.FA.P016 3310/IA/6-2 (Pavement) - CASB (15450m3) (37080 tonne) (was
C11_6C3)
d/w - 10h/d - With 48 2 17-Feb-23 18-Apr-23 15-Mar-23 15-May-23 22
HK Hols - No B/O periods
310.C.FA.P019 3310/IA/6-2 (Pavement) - CABC (15396m3) (36950.40 tonne) (was
C11_6C3)
d/w - 10h/d - With 48 2 07-Mar-23 06-May-23 13-Apr-23 09-Jun-23 28
HK Hols - No B/O periods
310.C.FA.P824 3310/IA/6-2 - Milling of the Existing Runway (was
C11_6C3)
d/w - 10h/d - With 6 2 28-Mar-23 03-Apr-23 18-Apr-23 24-Apr-23 14
HK Hols - No B/O periods
310.C.FA.P022 3310/IA/6-2 (Pavement) - Asphalt (MABC/MAWC/PMABC) (10714m3) (25713.6 tonne) (was
C11_6C3)
d/w - 10h/d - With 45 2 04-Apr-23 01-Jun-23 25-Apr-23 17-Jun-23 14
HK Hols - No B/O periods
310.C.FA.P025 3310/IA/6-2 (Pavement) - Asphalt (PMAWC) (7002m3) (16804.8 tonne) (was
C11_6C3)
d/w - 10h/d - With 30 2 03-May-23 07-Jun-23 19-May-23 24-Jun-23 14
HK Hols - No B/O periods
3310/IA/6-2 AGL (was
C11_6C3)
d/w - 10h/d - With HK Hols
84- No B/O 8periods (was
23-Feb-23
C3) 07-Jun-23 21-Mar-23 24-Jun-23 14
310.C.FA.P031 3310/IA/6-2 (AGL) - AGL Ductbank (13794 m) C11_6 d/w - 10h/d - With 48 2 23-Feb-23 24-Apr-23 21-Mar-23 20-May-23 22
HK Hols - No B/O periods
310.C.FA.P028 3310/IA/6-2 (AGL) - AGL Drawpit/Earthpit/Base Can (819 nr) - 8 no/d, 2 WF (was
C11_6C3)
d/w - 10h/d - With 53 2 23-Feb-23 29-Apr-23 28-Mar-23 03-Jun-23 28
HK Hols - No B/O periods
310.C.FA.P034 3310/IA/6-2 (AGL) - AGL Mid Can (819 nr) - 20 no/d, 1 WF (was
C11_6C3)
d/w - 10h/d - With 43 2 13-Mar-23 06-May-23 19-Apr-23 09-Jun-23 28
HK Hols - No B/O periods
310.C.FA.P037 3310/IA/6-2 (AGL) - AGL Top Can (819 nr) (was
C11_6C3)
d/w - 10h/d - With 30 2 03-May-23 07-Jun-23 19-May-23 24-Jun-23 14
HK Hols - No B/O periods
3310/IA/6-1 (was
C11_6C3)
d/w - 10h/d - With HK Hols
89- No B/O16
periods (was
06-Mar-23
C3) 24-Jun-23 06-Mar-23 12-Jul-23 14
3310/IA/6-1 Pavement C11_6 d/w - 10h/d - With HK Hols
86- No B/O 9periods (was
06-Mar-23
C3) 20-Jun-23 06-Mar-23 12-Jul-23 17
310.C.FA.P011 3310/IA/6-1 (Pavement) - Subgrade Works (cut/fill:0; subgrade:56087 m3) C11_6 d/w - 10h/d - With 46 2 06-Mar-23 03-May-23 06-Mar-23 03-May-23 0
HK Hols - No B/O periods
310.C.FA.P014 3310/IA/6-1 (Pavement) - CASB (29078m3) (69787 tonne) (was
C11_6C3)
d/w - 10h/d - With 62 2 10-Mar-23 27-May-23 10-Mar-23 27-May-23 0
HK Hols - No B/O periods
(was C3)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 30 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.FA.P017 3310/IA/6-1 (Pavement) - CABC (19007m3) (45616.80 tonne) C11_6 d/w - 10h/d - With 57 2 21-Mar-23 01-Jun-23 04-May-23 12-Jul-23 33
HK Hols - No B/O periods
310.C.FA.P020 3310/IA/6-1 (Pavement) - Asphalt (MABC/MAWC/PMABC) (14,885m3) (35724 tonne) (was
C11_6C3)
d/w - 10h/d - With 25 2 17-May-23 15-Jun-23 20-May-23 19-Jun-23 3
HK Hols - No B/O periods
310.C.FA.P023 3310/IA/6-1 (Pavement) - Asphalt (PMAWC) (2,955m3) (7092 tonne) (was
C11_6C3)
d/w - 10h/d - With 11 1 08-Jun-23 20-Jun-23 12-Jun-23 24-Jun-23 3
HK Hols - No B/O periods
3310/IA/6-1 AGL (was
C11_6C3)
d/w - 10h/d - With HK Hols
81- No B/O 7periods (was
15-Mar-23
C3) 24-Jun-23 15-Mar-23 24-Jun-23 0
310.C.FA.P045 3310/IA/6-1 (AGL) - AGL Ductbank (9153 m) C11_6 d/w - 10h/d - With 62 2 15-Mar-23 01-Jun-23 20-Mar-23 06-Jun-23 4
HK Hols - No B/O periods
310.C.FA.P042 3310/IA/6-1 (AGL) - AGL Drawpit/Earthpit/Base Can (510 nr) - 8 no/d, 1 WF (was
C11_6C3)
d/w - 10h/d - With 66 2 15-Mar-23 06-Jun-23 15-Mar-23 06-Jun-23 0
HK Hols - No B/O periods
310.C.FA.P048 3310/IA/6-1 (AGL) - AGL Mid Can (510 nr) - 20 no/d, 1 WF (was
C11_6C3)
d/w - 10h/d - With 28 2 09-May-23 10-Jun-23 09-May-23 10-Jun-23 0
HK Hols - No B/O periods
310.C.FA.P051 3310/IA/6-1 (AGL) - AGL Top Can (510 nr) (was
C11_6C3)
d/w - 10h/d - With 11 1 12-Jun-23 24-Jun-23 12-Jun-23 24-Jun-23 0
HK Hols - No B/O periods
3310/IA/6 Interface Work Area Completion and Remaining Works (was C3) 248 2 25-Apr-23 21-Feb-24 22-May-23 25-Aug-24 151
310.C.FA.P848 3310/IA/6 - AGL Foundations/Earthing Rode C11_6 d/w - 10h/d - With 28 2 25-Apr-23 29-May-23 22-May-23 24-Jun-23 22
HK Hols - No B/O periods
310.C.FA.P030 Achieved KD-5B Complete all civil works for AGL Sys at IWA 3310/IA/6 & provide access (was
C01_7C3)
d/w - 10h/d - No HK 0 24-Jun-23 25-Jun-23 1
for Contract <3305> Hols - No B/O periods (was
310.C.FA.P033 Allow Access to Contract <3305> for AGL System Works for Interface Work Area C1)
C01_7 d/w - 10h/d - No HK 0 24-Jun-23 03-Aug-23 40
3310/IA/6 Hols - No B/O periods (was
310.C.FA.P027 Achieve PMS 05 - Complete all civil enabling works in area 3310/IA/6 and provide access C1)
C11_6 d/w - 10h/d - With 0 24-Jun-23 24-Jun-23 0
to Others to complete AGL System HK Hols - No B/O periods
310.C.FA.P036 3310/IA/6 - AGL System Works (by Contract <3305>) (assumed 6 months) (was
C01_7C3)
d/w - 10h/d - No HK 180 25-Jun-23 21-Dec-23 04-Aug-23 30-Jan-24 40
Hols - No B/O periods (was
310.C.FA.P039 3310/IA/6 - Runway Grooving C1)
C11_6 d/w - 10h/d - With 12 22-Dec-23 08-Jan-24 31-Jan-24 15-Feb-24 31
HK Hols - No B/O periods
310.C.FA.P054 3310/IA/6 - Line Marking or defect remedial works @3310/IA/6-1 (was
C11_6C3)
d/w - 10h/d - With 48 22-Dec-23 21-Feb-24 31-Jan-24 28-Mar-24 31
HK Hols - No B/O periods
310.C.FA.P057 3310/IA/6 - Soil mixed with Hydroseeding (was
C11_6C3)
d/w - 10h/d - With 48 22-Dec-23 21-Feb-24 31-Jan-24 28-Mar-24 31
HK Hols - No B/O periods
310.C.FA.P060 WA 3310/4, 10, 10A - Vacate Work Area (Portion) (was
C01_7C3)
d/w - 10h/d - No HK 0 21-Feb-24 25-Aug-24 186
Hols - No B/O periods (was
Interface Work Area 3310/IA/7 (Pavement and AGL) C1) 455 20 08-Sep-22 19-Mar-24 04-Mar-23 24-Aug-24 128
3310/IA/7 455 20 08-Sep-22 19-Mar-24 04-Mar-23 24-Aug-24 128
3310/IA/7 Pavement C11_6 d/w - 10h/d - With HK Hols
234- No B/O11
periods (was
08-Sep-22
C3) 24-Jun-23 04-Mar-23 31-Jul-23 30
310.C.FA.P015.B02 3310/IA/7 (Pavement) - Carry Out Survey to Check Level C11_6 d/w - 10h/d - With 6 2 08-Sep-22 15-Sep-22 04-Mar-23 10-Mar-23 144
HK Hols - No B/O periods
310.C.FA.P600 3310/IA/7 (Pavement) - Site Formation (7947 m3) (was
C11_6C3)
d/w - 10h/d - With 9 1 22-Dec-22 03-Jan-23 30-Mar-23 13-Apr-23 79
HK Hols - No B/O periods
310.C.FA.P603 3310/IA/7 (Pavement) - Subgrade Works (47661 m3) (114386.40 tonne) (was
C11_6C3)
d/w - 10h/d - With 50 2 03-Apr-23 06-Jun-23 14-Apr-23 13-Jun-23 6
HK Hols - No B/O periods
310.C.FA.P606 3310/IA/7 (Pavement) - CASB (18846m3) (45230.40 tonne) (was
C11_6C3)
d/w - 10h/d - With 45 2 19-Apr-23 12-Jun-23 26-Apr-23 19-Jun-23 6
HK Hols - No B/O periods
310.C.FA.P615 3310/IA/7 (Pavement) - CABC (18232m3) (43756.80 tonne) (was
C11_6C3)
d/w - 10h/d - With 45 2 02-May-23 24-Jun-23 07-Jun-23 31-Jul-23 30
HK Hols - No B/O periods
310.C.FA.P624 3310/IA/7 (Pavement) - Asphalt (MABC/MAWC/PMABC) (4039m3) (9693.6 tonne) (was
C11_6C3)
d/w - 10h/d - With 15 1 17-May-23 03-Jun-23 23-Jun-23 11-Jul-23 30
HK Hols - No B/O periods
310.C.FA.P636 3310/IA/7 (Pavement) - Asphalt (PMAWC) (2127m3) (5104.8 tonne) (was
C11_6C3)
d/w - 10h/d - With 8 1 05-Jun-23 13-Jun-23 12-Jul-23 20-Jul-23 30
HK Hols - No B/O periods
(was C3)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 31 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
3310/IA/7 AGL C11_6 d/w - 10h/d - With HK Hols
78- No B/O 7periods (was
19-Apr-23
C3) 22-Jul-23 26-Apr-23 29-Jul-23 6
310.C.FA.P612 3310/IA/7 (AGL) - AGL Ductbank (7003 m) C11_6 d/w - 10h/d - With 50 2 19-Apr-23 17-Jun-23 26-Apr-23 26-Jun-23 6
HK Hols - No B/O periods
310.C.FA.P609 3310/IA/7 (AGL) - AGL Drawpit/Earthpit/Base Can (328 nr) - 8 no/d, 1 WF (was
C11_6C3)
d/w - 10h/d - With 43 2 27-Apr-23 17-Jun-23 03-Jun-23 25-Jul-23 30
HK Hols - No B/O periods
310.C.FA.P618 3310/IA/7 (AGL) - AGL Mid Can (328 nr) - 20 no/d, 1 WF (was
C11_6C3)
d/w - 10h/d - With 18 2 08-May-23 29-May-23 13-Jun-23 05-Jul-23 30
HK Hols - No B/O periods
310.C.FA.P639 3310/IA/7 (AGL) - AGL Top Can (328 nr) (was
C11_6C3)
d/w - 10h/d - With 8 1 14-Jul-23 22-Jul-23 21-Jul-23 29-Jul-23 6
HK Hols - No B/O periods
3310/IA/7 Interface Work Area Completion and Remaining Works (was C3) 226 2 19-Jun-23 19-Mar-24 27-Jun-23 24-Aug-24 128
310.C.FA.P852 3310/IA/7 - AGL Foundations/Earthing Rode C11_6 d/w - 10h/d - With 28 2 19-Jun-23 22-Jul-23 27-Jun-23 29-Jul-23 6
HK Hols - No B/O periods
310.C.FA.P540 Achieved KD-5C Complete all civil works for AGL Sys at IWA 3310/IA/7 & provide access (was
C01_7C3)
d/w - 10h/d - No HK 0 22-Jul-23 30-Jul-23 8
for Contract <3305> Hols - No B/O periods (was
310.C.FA.P555 Allow Access to Contract <3305> for AGL System Works for Interface Work Area C1)
C01_7 d/w - 10h/d - No HK 0 22-Jul-23 01-Aug-23 10
3310/IA/7 Hols - No B/O periods (was
310.C.FA.P570 3310/IA/7 - AGL System Works (by Contract <3305>) (assumed 6 months) C1)
C01_7 d/w - 10h/d - No HK 180 23-Jul-23 18-Jan-24 02-Aug-23 28-Jan-24 10
Hols - No B/O periods (was
310.C.FA.P648 3310/IA/7 - Runway Grooving C1)
C11_6 d/w - 10h/d - With 2 19-Jan-24 20-Jan-24 29-Jan-24 30-Jan-24 8
HK Hols - No B/O periods
310.C.FA.P651 3310/IA/7 - Line Marking or defect remedial works (was
C11_6C3)
d/w - 10h/d - With 48 22-Jan-24 19-Mar-24 31-Jan-24 28-Mar-24 8
HK Hols - No B/O periods
310.C.FA.P654 3310/IA/7 - Stabilized subgrade and Soil mixed with Hydroseeding (was
C11_6C3)
d/w - 10h/d - With 47 23-Jan-24 19-Mar-24 01-Feb-24 28-Mar-24 8
HK Hols - No B/O periods
310.C.FA.P657 3310/IA/7 - Vacate Work Areas Portion of WA 3310/4 (was
C11_6C3)
d/w - 10h/d - With 0 19-Mar-24 24-Aug-24 128
HK Hols - No B/O periods
Interface Work Area 3310/IA/8 (Pavement and AGL) (was C3) 369 29 16-Sep-22 11-Dec-23 11-Mar-23 24-Aug-24 208
3310/IA/8a (North) C11_6 d/w - 10h/d - With HK Hols
242- No B/O15
periods (was
16-Sep-22
C3) 12-Jul-23 11-Mar-23 11-Sep-23 52
3310/IA/8a (North) Pavement C11_6 d/w - 10h/d - With HK Hols
202- No B/O10
periods (was
16-Sep-22
C3) 23-May-23 11-Mar-23 11-Sep-23 92
310.C.FA.P020.B02 3310/IA/8 (Pavement) - Carry Out Survey to Check Level C11_6 d/w - 10h/d - With 6 2 16-Sep-22 22-Sep-22 11-Mar-23 17-Mar-23 144
HK Hols - No B/O periods
310.C.FA.P534 3310/IA/8a (Pavement North) - Subgrade Works (cut/fill:0; subrade:51243 m3) (was
C11_6C3)
d/w - 10h/d - With 43 2 09-Mar-23 03-May-23 31-May-23 21-Jul-23 65
HK Hols - No B/O periods
310.C.FA.P549 3310/IA/8a (Pavement North) - CASB (16054m3) (38529.60 tonne) (was
C11_6C3)
d/w - 10h/d - With 24 2 11-Apr-23 09-May-23 29-Jun-23 27-Jul-23 65
HK Hols - No B/O periods
310.C.FA.P564 3310/IA/8a (Pavement North) - CABC (20798m3) (49915.20 tonne) (was
C11_6C3)
d/w - 10h/d - With 31 2 14-Apr-23 20-May-23 07-Aug-23 11-Sep-23 94
HK Hols - No B/O periods
310.C.FA.P576 3310/IA/8a (Pavement North) - Asphalt (MABC/MAWC/PMABC) (5018m3) (12043.2 (was
C11_6C3)
d/w - 10h/d - With 10 1 04-May-23 15-May-23 11-Aug-23 22-Aug-23 82
tonne) HK Hols - No B/O periods
310.C.FA.P588 3310/IA/8a (Pavement North) - Asphalt (PMAWC) (1454m3) (3489.6 tonne) (was
C11_6C3)
d/w - 10h/d - With 2 1 22-May-23 23-May-23 21-Aug-23 22-Aug-23 75
HK Hols - No B/O periods
3310/IA/8a (North) AGL (was
C11_6C3)
d/w - 10h/d - With HK Hols
71- No B/O 5periods (was
17-Apr-23
C3) 12-Jul-23 06-Jul-23 26-Aug-23 39
310.C.FA.P552 3310/IA/8a (AGL North) - AGL Ductbank (230 m) C11_6 d/w - 10h/d - With 24 2 17-Apr-23 15-May-23 06-Jul-23 02-Aug-23 65
HK Hols - No B/O periods
310.C.FA.P537 3310/IA/8a (AGL North) - AGL Drawpit/Earthpit/Base Can (11 nr) - 8 no/d, 1 WF (was
C11_6C3)
d/w - 10h/d - With 3 1 12-May-23 15-May-23 11-Aug-23 14-Aug-23 75
HK Hols - No B/O periods
310.C.FA.P567 3310/IA/8a (AGL North) - AGL Mid Can (11 nr) - 20 no/d, 1 WF (was
C11_6C3)
d/w - 10h/d - With 2 1 13-May-23 15-May-23 12-Aug-23 14-Aug-23 75
HK Hols - No B/O periods
310.C.FA.P582 3310/IA/8a (AGL North) - AGL Top Can (11 nr) (was
C11_6C3)
d/w - 10h/d - With 4 1 08-Jul-23 12-Jul-23 23-Aug-23 26-Aug-23 39
HK Hols - No B/O periods
3310/IA/8b (South) (was C3) 131 12 06-Mar-23 14-Aug-23 18-Mar-23 27-Aug-23 11

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 32 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.FA.P621 *** Completion of Reclamation Works of 3310/11 (South) *** C11_6 d/w - 10h/d - With 0 06-Mar-23 18-Mar-23 11
HK Hols - No B/O periods
3310/IA/8b (South) Pavement (was
C11_6C3)
d/w - 10h/d - With HK Hols
125- No B/O 8periods (was
06-Mar-23
C3) 07-Aug-23 18-Mar-23 19-Aug-23 11
310.C.FA.P531 Subgrade Works (fill: 16583m3; subgrade: 4195 m3) C11_6 d/w - 10h/d - With 36 2 06-Mar-23 20-Apr-23 18-Mar-23 04-May-23 11
HK Hols - No B/O periods
310.C.FA.P546 3310/IA/8b (South) - CASB (1053m3) (2527.20 tonne) (was
C11_6C3)
d/w - 10h/d - With 27 2 21-Apr-23 23-May-23 05-May-23 06-Jun-23 11
HK Hols - No B/O periods
310.C.FA.P561 3310/IA/8b (South) - CABC (10973m3) (26335.20 tonne) (was
C11_6C3)
d/w - 10h/d - With 30 2 08-Jun-23 14-Jul-23 21-Jun-23 27-Jul-23 11
HK Hols - No B/O periods
310.C.FA.P579 3310/IA/8b (South) - Asphalt (MABC/MAWC/PMABC) (4380m3) (10512 tonne) (was
C11_6C3)
d/w - 10h/d - With 18 1 15-Jul-23 04-Aug-23 28-Jul-23 17-Aug-23 11
HK Hols - No B/O periods
310.C.FA.P591 3310/IA/8b (South) - Asphalt (PMAWC) (4m3) (9.6 tonne) (was
C11_6C3)
d/w - 10h/d - With 2 1 05-Aug-23 07-Aug-23 18-Aug-23 19-Aug-23 11
HK Hols - No B/O periods
3310/IA/8b (South) AGL (was C3) 68 4 24-May-23 14-Aug-23 07-Jun-23 27-Aug-23 11
310.C.FA.P627 3310/IA/8b (South) - AGL Drawpit/Earthpit/Base Can (11 nr) - 8 no/d, 1 WF C11_6 d/w - 10h/d - With 6 1 24-May-23 31-May-23 14-Jun-23 20-Jun-23 17
HK Hols - No B/O periods
310.C.FA.P630 3310/IA/8b (South) - AGL Ductbank (230 m) (was
C11_6C3)
d/w - 10h/d - With 12 1 24-May-23 07-Jun-23 07-Jun-23 20-Jun-23 11
HK Hols - No B/O periods
310.C.FA.P633 3310/IA/8b (South) - AGL Mid Can (11 nr) (was
C11_6C3)
d/w - 10h/d - With 6 1 14-Jun-23 20-Jun-23 28-Jul-23 03-Aug-23 36
HK Hols - No B/O periods
310.C.FA.P642 3310/IA/8b (South) - AGL Top Can (11 nr) - 20 no/d, 1 WF (was
C11_6C3)
d/w - 10h/d - With 6 1 08-Aug-23 14-Aug-23 21-Aug-23 26-Aug-23 11
HK Hols - No B/O periods
310.C.FA.P645 3310/IA/8 - Achieve KD-5D (was
C01_7C3)
d/w - 10h/d - No HK 0 14-Aug-23 27-Aug-23 13
Hols - No B/O periods (was
3310/IA/8 Interface Work Area Completion and Remaining Works C1) 155 2 08-Jun-23 11-Dec-23 26-Jul-23 24-Aug-24 208
310.C.FA.P856 3310/IA/8 - AGL Foundations/Earthing Rode C11_6 d/w - 10h/d - With 28 2 08-Jun-23 12-Jul-23 26-Jul-23 26-Aug-23 39
HK Hols - No B/O periods
310.C.FA.P543 Achieved KD-5D Complete all civil works for AGL Sys at IWA 3310/IA/8 & provide access (was
C01_7C3)
d/w - 10h/d - No HK 0 14-Aug-23 27-Aug-23 13
for Contract <3305> Hols - No B/O periods (was
310.C.FA.P558 Allow Access to Contract <3305> for AGL System Works for Interface Work Area C1)
C01_7 d/w - 10h/d - No HK 0 14-Aug-23 30-Nov-23 108
3310/IA/8 Hols - No B/O periods (was
310.C.FA.P573 3310/IA/8 - AGL System Works (by Contract <3305>) (assumed 6 months) C1)
C01_7 d/w - 10h/d - No HK 90 15-Aug-23 12-Nov-23 01-Dec-23 28-Feb-24 108
Hols - No B/O periods (was
310.C.FA.P585 3310/IA/8 - Line Marking or defect remedial works C1)
C11_6 d/w - 10h/d - With 25 13-Nov-23 11-Dec-23 29-Feb-24 28-Mar-24 88
HK Hols - No B/O periods
310.C.FA.P594 3310/IA/8 - Soil mixed with Hydroseeding (was
C11_6C3)
d/w - 10h/d - With 25 13-Nov-23 11-Dec-23 29-Feb-24 28-Mar-24 88
HK Hols - No B/O periods
310.C.FA.P597 3310/IA/8 - Vacate Work Areas Portion of WA 3310/11 (was
C11_6C3)
d/w - 10h/d - With 0 11-Dec-23 24-Aug-24 208
HK Hols - No B/O periods
CC#3 ----- Testing and Commissioning (Pavement & AGL)----- (was
C01_7C3)
d/w - 10h/d - No HK Hols306
- No B/O periods
0 (was24-Aug-23
C1) 25-Jun-24 29-Mar-24 27-Jun-24 2
310.C.FA.X589 Allow Other Contractors Access for follow-on Works in AGL Vault C Annex and AGL Vault C01_7 d/w - 10h/d - No HK 0 24-Aug-23 29-Mar-24 218
D Annex Hols - No B/O periods (was
310.C.FA.X600 Airfield Pavement - Completion of Airfield Pavement Works C1)
C01_7 d/w - 10h/d - No HK 0 05-Jan-24 29-Mar-24 84
Hols - No B/O periods (was
310.C.FA.X604 Airfield AGL - Completion of Airfield AGL (Base Can, Mid Can, Top Can) C1)
C01_7 d/w - 10h/d - No HK 0 13-Jan-24 29-Mar-24 76
Hols - No B/O periods (was
310.C.FA.X620 Airfield AGL - Assumed Completion of AGL System by Contract <3305> C1)
C01_7 d/w - 10h/d - No HK 0 13-Mar-24 29-Mar-24 16
Hols - No B/O periods (was
310.C.FA.X608 Airfield (Line Marking) - Completion of Runway Grooving C1)
C01_7 d/w - 10h/d - No HK 0 22-Mar-24 29-Mar-24 7
Hols - No B/O periods (was
C1)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 33 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.FA.X624 Airfield - Completion of Landscaping/Hydroseeding C01_7 d/w - 10h/d - No HK 0 27-Mar-24 29-Mar-24 2
Hols - No B/O periods (was
310.C.FA.X628 Airfield (Line Marking) - Completion of Taxiways and Rapid Exist Line Marking C1)
C01_7 d/w - 10h/d - No HK 0 28-Mar-24 29-Mar-24 2
Hols - No B/O periods (was
310.C.FA.X616 Airfield (T&C) - Testing and Commissioning C1)
C01_7 d/w - 10h/d - No HK 90 28-Mar-24 25-Jun-24 30-Mar-24 27-Jun-24 2
Hols - No B/O periods (was
310.C.FA.P284 Achieved KD-7 Complete modification of the existing North Runway incl. line marking, C1)
C01_7 d/w - 10h/d - No HK 0 25-Jun-24 27-Jun-24 2
T&C ready for CAD/AA flight check Hols - No B/O periods (was
Cost Centre #04 - Airfield Infrastructure Works C1) 952 368 07-Jun-21 A 16-Aug-24 31-Jan-22 01-Sep-24 13
CC#4 ----- Design and Others ----- 539 0 14-Jun-21 A 02-Apr-23 27-Mar-22 01-Sep-24 420
CC#04 - Permanent Security Fence (PSF) and Interim Security Fence (IPSF) & Associated Works C01_7 d/w - 10h/d - No HK Hols600
- No B/O periods
0 (was
14-Jun-21
C1) A 03-Feb-23 20-Apr-22 20-Aug-23 198
CC#4 - Package 1 - Design of Interim Security Fence and Associated Works (ISF) C01_7 d/w - 10h/d - No HK Hols314
- No B/O periods
0 (was
14-Jun-21
C1) A 23-Apr-22 31-May-22 14-Jun-22 52
310.D.RC.C000 ISF - Prepare Design of Interim Security Fence and Associated Works C01_7 d/w - 10h/d - No HK 28 14-Jun-21 A 12-Jul-21 A 31-May-22 31-May-22
Hols - No B/O periods (was
310.D.RC.C008 ISF - Review by PM, AP, RSE, RGE Package 1 - Int. Sec. Fence and Associated Works C1)
C01_7 d/w - 10h/d - No HK 28 13-Jul-21 A 14-Sep-21 A 31-May-22 31-May-22
Hols - No B/O periods (was
310.D.RC.C012 ISF - Review design by ICC, M&VC and issue check certificate of Package 1 - Int. Sec. C1)
C01_7 d/w - 10h/d - No HK 21 15-Sep-21 A 24-Sep-21 A 31-May-22 31-May-22
Fence and Associated Works Hols - No B/O periods (was
310.D.RC.C023 ISF - Review design by ICC, M&VC and issue check certificate of Package 1 - Int. Sec. C1)
C01_7 d/w - 10h/d - No HK 21 21-Oct-21 A 22-Nov-21 A 31-May-22 31-May-22
Fence&Associated Works 2nd Round Hols - No B/O periods (was
310.D.RC.C024 ISF - BD review and approved design of Package 1 - Int. Sec. Fence and Associated C1) d/w - 10h/d - No HK
C01_7 60 22-Nov-21 A 27-Mar-22 31-May-22 31-May-22 65
Works Hols - No B/O periods (was
310.D.RC.C028 BA8 consent from ICC of Package 1 - Int. Sec. Fence and Associated Works C1)
C01_7 d/w - 10h/d - No HK 7 28-Mar-22 03-Apr-22 01-Jun-22 07-Jun-22 65
Hols - No B/O periods (was
310.D.RC.C032 Submit Form BA10 for notification of work commencement of Int. Sec. Fence C1)
C01_7 d/w - 10h/d - No HK 7 17-Apr-22 23-Apr-22 08-Jun-22 14-Jun-22 52
Hols - No B/O periods (was
CC#4 - Package 2 - Design of Permanent Security Fence and Associated Works) (PSF) C1)
C01_7 d/w - 10h/d - No HK Hols207
- No B/O periods
0 (was12-Jul-22
C1) 03-Feb-23 26-Jan-23 20-Aug-23 198
310.D.RC.C32 PSF - Prepare Design of Permanent Security Fence and Associated Works with ICE C01_7 d/w - 10h/d - No HK 21 12-Jul-22 01-Aug-22 26-Jan-23 15-Feb-23 198
Hols - No B/O periods (was
310.D.RC.C36 PSF - Review by PM, AP, RSE, RGE Package 2 - Permanent Sec. Fence and Associated C1)
C01_7 d/w - 10h/d - No HK 28 02-Aug-22 29-Aug-22 16-Feb-23 15-Mar-23 198
Works Hols - No B/O periods (was
310.D.RC.C40 PSF - Review design by ICC, M&VC and issue check certificate of Package 2 - C1)
C01_7 d/w - 10h/d - No HK 21 30-Aug-22 19-Sep-22 16-Mar-23 05-Apr-23 198
Permanent Sec. Fence and Associated Works Hols - No B/O periods (was
310.D.RC.C44 PSF - address comments of Package 2 - Int. Sec. Fence and Associated Works 2nd C1)
C01_7 d/w - 10h/d - No HK 14 20-Sep-22 03-Oct-22 06-Apr-23 19-Apr-23 198
Round Hols - No B/O periods (was
310.D.RC.C48 PSF - Review by PM, AP, RSE, RGE Package 2 - Permanent Sec. Fence and Associated C1) C01_7 d/w - 10h/d - No HK 28 04-Oct-22 31-Oct-22 20-Apr-23 17-May-23 198
Works 2nd Round Hols - No B/O periods (was
310.D.RC.C52 PSF - Review design by ICC, M&VC and issue check certificate of Package 1 - Int. Sec. C1)
C01_7 d/w - 10h/d - No HK 21 01-Nov-22 21-Nov-22 18-May-23 07-Jun-23 198
Fence&Associated Works 2nd Round Hols - No B/O periods (was
310.D.RC.C56 PSF - BD review and approved design of Package 2 - Permanent Sec. Fence and C1)
C01_7 d/w - 10h/d - No HK 60 22-Nov-22 20-Jan-23 08-Jun-23 06-Aug-23 198
Associated Works Hols - No B/O periods (was
310.D.RC.C60 BA8 consent from BD of Package 2 - Permanent Sec. Fence and Associated Works C1)
C01_7 d/w - 10h/d - No HK 7 21-Jan-23 27-Jan-23 07-Aug-23 13-Aug-23 198
Hols - No B/O periods (was
310.D.RC.C64 Submit Form BA10 for notification of work commencement of Permanent Sec. Fence C1)
C01_7 d/w - 10h/d - No HK 7 28-Jan-23 03-Feb-23 14-Aug-23 20-Aug-23 198
Hols - No B/O periods (was
CC#4 - MS no.13 - Shop Drawings for Interim/ Permanent Security Fence C1)
C01_7 d/w - 10h/d - No HK Hols221
- No B/O periods
0 (was
13-Oct-21
C1) A 21-May-22 20-Apr-22 14-Jun-22 24
310.D.RC.C70 MS no.13 - Shop Drawings for Interim/ Permanent Security Fence - prepare design C01_7 d/w - 10h/d - No HK 21 13-Oct-21 A 16-Apr-22 20-Apr-22 10-May-22 24
Hols - No B/O periods (was
310.D.RC.C74 MS no.13 - Shop Drawings for Interim/ Permanent Security Fence - ICE check and issue C1)
C01_7 d/w - 10h/d - No HK 7 17-Apr-22 23-Apr-22 11-May-22 17-May-22 24
check cert. Hols - No B/O periods (was
C1)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 34 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.RC.C78 MS no.13 - Shop Drawings for Interim/ Permanent Security Fence - PM review and accept C01_7 d/w - 10h/d - No HK 28 24-Apr-22 21-May-22 18-May-22 14-Jun-22 24
Hols - No B/O periods (was
CC#04 - ELS Design - Western Box Culvert (WBC) no. 3, 4, 18 C1)
C01_7 d/w - 10h/d - No HK Hols445
- No B/O periods
0 (was
13-Aug-21
C1) A 08-Nov-22 27-Mar-22 18-Dec-22 40
CC#4 - ELS Design - WBC No. 3,4,18 (Zone 12A for Stage 1) Amendment Submission C01_7 d/w - 10h/d - No HK Hols203
- No B/O periods
0 (was
13-Aug-21
C1) A 04-Jan-22 A 27-Mar-22 10-May-22
310.D.R0.L010 ELS Design for WBC Zone 12A - Prepare Design & submit with ICE for reviewing C01_7 d/w - 10h/d - No HK 28 13-Aug-21 A 23-Aug-21 A 27-Mar-22 27-Mar-22
Hols - No B/O periods (was
310.D.R0.L014 ELS Design for WBC Zone 12A - PM, AP, RSE reviewing C1)
C01_7 d/w - 10h/d - No HK 28 24-Aug-21 A 19-Sep-21 A 10-May-22 10-May-22
Hols - No B/O periods (was
310.D.R0.L022 ELS Design for WBC Zone 12A - address comments and resubmit 2nd Round C1)
C01_7 d/w - 10h/d - No HK 14 07-Sep-21 A 05-Nov-21 A 10-May-22 10-May-22
Hols - No B/O periods (was
310.D.R0.L018 ELS Design for WBC Zone 12A - ICC, M&VC review design and issue check certificate C1)
C01_7 d/w - 10h/d - No HK 21 05-Oct-21 A 21-Nov-21 A 10-May-22 10-May-22
Hols - No B/O periods (was
310.D.R0.L038 ELS Design for WBC Zone 12A - BD review and approve C1)
C01_7 d/w - 10h/d - No HK 30 22-Nov-21 A 21-Dec-21 A 10-May-22 10-May-22
Hols - No B/O periods (was
310.D.R0.L040 ELS Design for WBC Zone 12A - prepare and submit Form BA8 and grant consent C1)
C01_7 d/w - 10h/d - No HK 7 22-Dec-21 A 28-Dec-21 A 10-May-22 10-May-22
Hols - No B/O periods (was
310.D.R0.L041 ELS Design for WBC Zone 12A - prepare and submit Form BA10 (with instrumentation C1)
C01_7 d/w - 10h/d - No HK 7 29-Dec-21 A 04-Jan-22 A 10-May-22 10-May-22
readings) Hols - No B/O periods (was
CC#4 - ELS Design - WBC No. 3,4,18 (Zone 12B, 12C for Stage 2,3) Amendment Submission C1)
C01_7 d/w - 10h/d - No HK Hols121
- No B/O periods
0 (was
13-Aug-21
C1) A 03-May-22 27-Mar-22 17-Jul-22 75
310.D.R0.L700.B01 ELS Design for WBC Zone 12B,12C - Prepare Design & submit with ICE for reviewing C01_7 d/w - 10h/d - No HK 28 13-Aug-21 A 23-Aug-21 A 27-Mar-22 27-Mar-22
Hols - No B/O periods (was
310.D.R0.L705.B01 ELS Design for WBC Zone 12B,12C - PM, AP, RSE reviewing C1)
C01_7 d/w - 10h/d - No HK 28 24-Aug-21 A 19-Sep-21 A 27-Mar-22 27-Mar-22
Hols - No B/O periods (was
310.D.R0.L715.B01 ELS Design for WBC Zone 12B,12C - address comments and resubmit 2nd Round C1)
C01_7 d/w - 10h/d - No HK 14 07-Sep-21 A 05-Nov-21 A 27-Mar-22 27-Mar-22
Hols - No B/O periods (was
310.D.R0.L710.B01 ELS Design for WBC Zone 12B,12C - ICC, M&VC review design and issue check C1)
C01_7 d/w - 10h/d - No HK 21 05-Oct-21 A 21-Nov-21 A 27-Mar-22 27-Mar-22
certificate Hols - No B/O periods (was
310.D.R0.L730.B01 ELS Design for WBC Zone 12B,12C - BD review and approve C1)
C01_7 d/w - 10h/d - No HK 30 22-Nov-21 A 21-Dec-21 A 27-Mar-22 27-Mar-22
Hols - No B/O periods (was
310.D.R0.L735.B01 ELS Design for WBC Zone 12B - prepare and submit Form BA8 and grant consent C1)
C01_7 d/w - 10h/d - No HK 7 16-Mar-22 A 06-Apr-22 30-Apr-22 10-May-22 34
Hols - No B/O periods (was
310.D.R0.L740.B01 ELS Design for WBC Zone 12B - prepare and submit Form BA10 (with instrumentation C1)
C01_7 d/w - 10h/d - No HK 7 06-Apr-22 12-Apr-22 10-May-22 16-May-22 34
readings) Hols - No B/O periods (was
310.D.R0.L747.B02 ELS Design for WBC Zone 12C - prepare and submit Form BA8 and grant consent C1)
C01_7 d/w - 10h/d - No HK 7 21-Apr-22 27-Apr-22 05-Jul-22 11-Jul-22 75
Hols - No B/O periods (was
310.D.R0.L749.B02 ELS Design for WBC Zone 12C - prepare and submit Form BA10 (with instrumentation C1)
C01_7 d/w - 10h/d - No HK 7 27-Apr-22 03-May-22 11-Jul-22 17-Jul-22 75
readings) Hols - No B/O periods (was
CC#4 - ELS Design - WBC No. 3,4,18 (Zones 12D, 12E, 12F for Stage 4,5,6) C1)
C01_7 d/w - 10h/d - No HK Hols255
- No B/O periods
0 (was
16-Feb-22
C1) A 08-Nov-22 27-Mar-22 18-Dec-22 40
310.D.R0.L432 ELS Design for WBC Zone 12D, 12E, 12F - Prepare Design & submit with ICE for C01_7 d/w - 10h/d - No HK 28 16-Feb-22 A 30-Mar-22 27-Mar-22 30-Mar-22 0
reviewing Hols - No B/O periods (was
310.D.R0.L436 ELS Design for WBC Zone 12D, 12E, 12F - PM, AP, RSE reviewing C1)
C01_7 d/w - 10h/d - No HK 28 31-Mar-22 27-Apr-22 31-Mar-22 27-Apr-22 0
Hols - No B/O periods (was
310.D.R0.L440 ELS Design for WBC Zone 12D, 12E, 12F - ICC, M&VC review design and issue check C1)
C01_7 d/w - 10h/d - No HK 21 28-Apr-22 18-May-22 28-Apr-22 18-May-22 0
certificate Hols - No B/O periods (was
310.D.R0.L444 ELS Design for WBC Zone 12D, 12E, 12F - address comments and resubmit 2nd Round C1)
C01_7 d/w - 10h/d - No HK 14 19-May-22 01-Jun-22 19-May-22 01-Jun-22 0
Hols - No B/O periods (was
310.D.R0.L448 ELS Design for WBC Zone 12D, 12E, 12F - PM, AP, RSE reviewing 2nd Round C1)
C01_7 d/w - 10h/d - No HK 28 02-Jun-22 29-Jun-22 02-Jun-22 29-Jun-22 0
Hols - No B/O periods (was
310.D.R0.L452 ELS Design for WBC Zone 12D, 12E, 12F - ICC, M&VC review design and issue check C1)
C01_7 d/w - 10h/d - No HK 21 30-Jun-22 20-Jul-22 30-Jun-22 20-Jul-22 0
certificate 2nd Round Hols - No B/O periods (was
C1)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 35 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.R0.L456 ELS Design for WBC Zone 12D, 12E, 12F - BD review and approve C01_7 d/w - 10h/d - No HK 60 21-Jul-22 18-Sep-22 21-Jul-22 18-Sep-22 0
Hols - No B/O periods (was
310.D.R0.L460 ELS Design for WBC Zone 12D, 12E - prepare and submit Form BA8 and grant consent C1)
C01_7 d/w - 10h/d - No HK 7 19-Sep-22 25-Sep-22 19-Sep-22 25-Sep-22 0
Hols - No B/O periods (was
310.D.R0.L464 ELS Design for WBC Zone 12D, 12E - prepare and submit Form BA10 (with C1)
C01_7 d/w - 10h/d - No HK 7 26-Sep-22 02-Oct-22 26-Sep-22 02-Oct-22 0
instrumentation readings) Hols - No B/O periods (was
310.D.R0.L592.B02 ELS Design for WBC Zone 12F - prepare and submit Form BA8 and grant consent C1)
C01_7 d/w - 10h/d - No HK 7 26-Oct-22 01-Nov-22 05-Dec-22 11-Dec-22 40
Hols - No B/O periods (was
310.D.R0.L596.B02 ELS Design for WBC Zone 12F - prepare and submit Form BA10 (with instrumentation C1)
C01_7 d/w - 10h/d - No HK 7 02-Nov-22 08-Nov-22 12-Dec-22 18-Dec-22 40
readings) Hols - No B/O periods (was
CC#04 - Structural Plan Anticipated BD Approval and Consent Application - WBC no. 18 C1)
C01_7 d/w - 10h/d - No HK Hols 0- No B/O periods
0 (was
20-Jun-21
C1) A 20-Jun-21 A 25-May-22 25-May-22
310.D.R0.L204 Box Culvert (18) - Consent application and grant Consent for Box Culvert Structure C01_7 d/w - 10h/d - No HK 0 20-Jun-21 A 25-May-22
construction Hols - No B/O periods (was
CC#04 - Drainage Plan Anticipated BD Approval and Consent Application - WBC no. 18 C1)
C01_7 d/w - 10h/d - No HK Hols174
- No B/O periods
0 (was
17-Oct-21
C1) A 10-Apr-22 08-Jun-22 22-Jun-22 73
310.D.R0.L216 Box Culvert (18) - grant Anticipated BD approval of Drainage Plan for Stormwater C01_7 d/w - 10h/d - No HK 0 17-Oct-21 A 08-Jun-22
Drainage & Box Culvert 18 Hols - No B/O periods (was
310.D.R0.L220 Box Culvert (18) - Consent application and grant Consent of Drainage Plan for Stormwater C1)
C01_7 d/w - 10h/d - No HK 7 27-Mar-22 02-Apr-22 08-Jun-22 14-Jun-22 73
Drainage & Box Culvert 18 Hols - No B/O periods (was
310.D.R0.L224 Box Culvert (18) - Submit Form BA10 for notification of Stormwater Drainage Works & C1)
C01_7 d/w - 10h/d - No HK 7 03-Apr-22 09-Apr-22 15-Jun-22 21-Jun-22 73
Box Culvert 18 Hols - No B/O periods (was
310.D.R0.L304 Remark - Commencement of stormwater drainage work @ 3310/IA/6-1 relating to Box C1)
C01_7 d/w - 10h/d - No HK 0 10-Apr-22 22-Jun-22 73
Culvert 18 Hols - No B/O periods (was
CC#04 - ELS Design - Eastern Box Culvert (EBC) no. 5, 6, 19 C1)
C01_7 d/w - 10h/d - No HK Hols491
- No B/O periods
0 (was
05-Jul-21
C1) A 07-Nov-22 17-Apr-22 28-Nov-22 21
CC#4 - ELS Design - EBC No. 5,6, 19 (Ground Treatment Done) CH. 0+050 to 0+593 C01_7 d/w - 10h/d - No HK Hols250
- No B/O periods
0 (was
14-Jul-21
C1) A 26-Feb-22 A 17-Apr-22 23-Apr-22
310.D.R0.L046 ELS Design for EBC no. 5,6,19 (CH. 0+50 to CH. 0+593) - Prepare Design & submit with C01_7 d/w - 10h/d - No HK 28 14-Jul-21 A 10-Aug-21 A 17-Apr-22 17-Apr-22
ICE Hols - No B/O periods (was
310.D.R0.L048 ELS Design for EBC no. 5,6,19 (CH. 0+50 to CH. 0+593) - PM, AP, RSE reviewing C1)
C01_7 d/w - 10h/d - No HK 28 11-Aug-21 A 20-Aug-21 A 23-Apr-22 23-Apr-22
Hols - No B/O periods (was
310.D.R0.L050 ELS Design for EBC no. 5,6,19 (CH. 0+50 to CH. 0+593) - ICC, M&VC review design and C1)
C01_7 d/w - 10h/d - No HK 21 22-Aug-21 A 20-Sep-21 A 23-Apr-22 23-Apr-22
issue check certificate Hols - No B/O periods (was
310.D.R0.L052 ELS Design for EBC no. 5,6,19 (CH. 0+50 to CH. 0+593) - address comments & resubmit C1)
C01_7 d/w - 10h/d - No HK 4 21-Sep-21 A 29-Sep-21 A 23-Apr-22 23-Apr-22
2nd Round Hols - No B/O periods (was
310.D.R0.L054 ELS Design for EBC no. 5,6,19 (CH. 0+50 to CH. 0+593) - ICC, M&VC review design and C1)
C01_7 d/w - 10h/d - No HK 21 30-Sep-21 A 02-Nov-21 A 23-Apr-22 23-Apr-22
issue check certificate 2nd Round Hols - No B/O periods (was
310.D.R0.L055 ELS Design for EBC no. 5,6,19 (CH. 0+50 to CH. 0+593) - BD review and approve C1)
C01_7 d/w - 10h/d - No HK 60 03-Nov-21 A 18-Jan-22 A 23-Apr-22 23-Apr-22
Hols - No B/O periods (was
310.D.R0.L060 ELS Design for EBC no. 5,6,19 (CH. 0+50 to CH. 0+593) - prepare and submit Form BA8 C1)
C01_7 d/w - 10h/d - No HK 7 31-Jan-22 A 18-Feb-22 A 23-Apr-22 23-Apr-22
and grant consent Hols - No B/O periods (was
310.D.R0.L062 ELS Design for EBC no. 5,6,19 (CH. 0+50 to CH. 0+593)9 - prepare and submit Form C1)
C01_7 d/w - 10h/d - No HK 7 19-Feb-22 A 26-Feb-22 A 23-Apr-22 23-Apr-22
BA10 (with instrumentation readings) Hols - No B/O periods (was
CC#4 - ELS Design - EBC No. 5,6, 19 (Need Ground Treatment) CH. 0+593 to 1262 C1)
C01_7 d/w - 10h/d - No HK Hols230
- No B/O periods
0 (was
05-Jul-21
C1) A 27-Apr-22 17-Apr-22 03-Jun-22 37
310.D.R0.L360 ELS Design for EBC no. 5,6,19 (CH. 0+539 to 1262) - Prepare Design & submit with ICE C01_7 d/w - 10h/d - No HK 50 05-Jul-21 A 04-Aug-21 A 17-Apr-22 17-Apr-22
Hols - No B/O periods (was
310.D.R0.L364 ELS Design for EBC no. 5,6,19 (CH. 0+539 to 1262) - PM, AP, RSE reviewing C1)
C01_7 d/w - 10h/d - No HK 28 04-Aug-21 A 30-Aug-21 A 03-May-22 03-May-22
Hols - No B/O periods (was
310.D.R0.L368 ELS Design for EBC no. 5,6,19 (CH. 0+539 to 1262) - ICC, M&VC review design and C1)
C01_7 d/w - 10h/d - No HK 21 30-Aug-21 A 12-Jan-22 A 03-May-22 03-May-22
issue check certificate Hols - No B/O periods (was
310.D.R0.L384 ELS Design for EBC no. 5,6,19 (CH. 0+539 to 1262) - BD review and approve C1)
C01_7 d/w - 10h/d - No HK 60 13-Jan-22 A 13-Apr-22 03-May-22 20-May-22 37
Hols - No B/O periods (was
310.D.R0.L388 ELS Design for EBC no. 5,6,19 (CH. 0+539 to 1262) - prepare and submit Form BA8 and C1)
C01_7 d/w - 10h/d - No HK 7 14-Apr-22 20-Apr-22 21-May-22 27-May-22 37
grant consent Hols - No B/O periods (was
C1)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 36 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.R0.L392 ELS Design for EBC no. 5,6,19 (CH. 0+539 to 1262) - prepare and submit Form BA10 C01_7 d/w - 10h/d - No HK 7 21-Apr-22 27-Apr-22 28-May-22 03-Jun-22 37
(with instrumentation readings) Hols - No B/O periods (was
CC#4 - ELS Design - EBC No. 5 & 6 (Outfall Connection) C1)
C01_7 d/w - 10h/d - No HK Hols226
- No B/O periods
0 (was27-Mar-22
C1) 07-Nov-22 17-Apr-22 28-Nov-22 21
310.D.R0.L396 ELS Design for EBC no. 5,6 - Prepare Design & submit with ICE C01_7 d/w - 10h/d - No HK 50 27-Mar-22 15-May-22 17-Apr-22 05-Jun-22 21
Hols - No B/O periods (was
310.D.R0.L400 ELS Design for EBC no. 5,6 - PM, AP, RSE reviewing C1)
C01_7 d/w - 10h/d - No HK 28 16-May-22 12-Jun-22 06-Jun-22 03-Jul-22 21
Hols - No B/O periods (was
310.D.R0.L404 ELS Design for EBC no. 5,6 - ICC, M&VC review design and issue check certificate C1)
C01_7 d/w - 10h/d - No HK 21 13-Jun-22 03-Jul-22 04-Jul-22 24-Jul-22 21
Hols - No B/O periods (was
310.D.R0.L408 ELS Design for EBC no. 5,6 - address comments & resubmit 2nd Round C1)
C01_7 d/w - 10h/d - No HK 4 04-Jul-22 07-Jul-22 25-Jul-22 28-Jul-22 21
Hols - No B/O periods (was
310.D.R0.L412 ELS Design for EBC no. 5,6 - PM, AP, RSE reviewing 2nd Round C1)
C01_7 d/w - 10h/d - No HK 28 08-Jul-22 04-Aug-22 29-Jul-22 25-Aug-22 21
Hols - No B/O periods (was
310.D.R0.L416 ELS Design for EBC no. 5,6 - ICC, M&VC review design and issue check certificate 2nd C1)
C01_7 d/w - 10h/d - No HK 21 05-Aug-22 25-Aug-22 26-Aug-22 15-Sep-22 21
Round Hols - No B/O periods (was
310.D.R0.L420 ELS Design for EBC no. 5,6 - BD review and approve C1)
C01_7 d/w - 10h/d - No HK 60 26-Aug-22 24-Oct-22 16-Sep-22 14-Nov-22 21
Hols - No B/O periods (was
310.D.R0.L424 ELS Design for EBC no. 5,6 - prepare and submit Form BA8 and grant consent C1)
C01_7 d/w - 10h/d - No HK 7 25-Oct-22 31-Oct-22 15-Nov-22 21-Nov-22 21
Hols - No B/O periods (was
310.D.R0.L428 ELS Design for EBC no. 5,6 - prepare and submit Form BA10 (with instrumentation C1)
C01_7 d/w - 10h/d - No HK 7 01-Nov-22 07-Nov-22 22-Nov-22 28-Nov-22 21
readings) Hols - No B/O periods (was
CC#04 - Structural Plan Anticipated BD Approval and Consent Application - WBC no. 19 C1)
C01_7 d/w - 10h/d - No HK Hols 0- No B/O periods
0 (was
17-Oct-21
C1) A 17-Oct-21 A 16-May-22 16-May-22
310.D.R0.L256 Box Culvert (19) - grant BD approval for box culvert structural works C01_7 d/w - 10h/d - No HK 0 17-Oct-21 A 16-May-22
Hols - No B/O periods (was
CC#04 - Drainage Plan Anticipated BD Approval and Consent Application - WBC no. 19 C1) 144 0 17-Oct-21 A 11-Apr-22 08-May-23 22-May-23 329
310.D.R0.L240 Box Culvert (19) - grant BD approval of Drainage Plan for Stormwater Drainage & Box C01_7 d/w - 10h/d - No HK 0 17-Oct-21 A 08-May-23
Culvert 19 Hols - No B/O periods (was
310.D.R0.L244 Box Culvert (19) - Consent application and grant Consent of Drainage Plan for Stormwater C1)
C01_7 d/w - 10h/d - No HK 7 27-Mar-22 02-Apr-22 08-May-23 14-May-23 407
Drainage & Box Culvert 19 Hols - No B/O periods (was
310.D.R0.L248 Box Culvert (19) - Submit Form BA10 for notification of Stormwater Drainage Works & C1)
C01_7 d/w - 10h/d - No HK 7 03-Apr-22 09-Apr-22 15-May-23 21-May-23 407
Box Culvert 19 Hols - No B/O periods (was
310.D.R0.L252 Remark - Commencement of stormwater drainage work at 3310/IA/2-1 (Airfield Infra and C1)
C11_6 d/w - 10h/d - With 0 11-Apr-22 22-May-23 329
UU) xxxxxx HK Hols - No B/O periods
CC#04 - AFHS Design (VE+ELS) (was
C01_7C3)
d/w - 10h/d - No HK Hols281
- No B/O periods
0 (was
29-Nov-21
C1) A 06-Nov-22 03-May-22 17-Dec-22 41
CC#04 - AFHS Design (ELS) - ISO Chamber C01_7 d/w - 10h/d - No HK Hols237
- No B/O periods
0 (was
28-Jan-22
C1) A 23-Sep-22 03-May-22 30-Oct-22 37
310.D.R0.L800.B01 ELS Design for ISO Chamber - Prepare Design & submit with ICE C01_7 d/w - 10h/d - No HK 28 28-Jan-22 A 31-Mar-22 03-May-22 07-May-22 37
Hols - No B/O periods (was
310.D.R0.L805.B01 ELS Design for ISO Chamber - PM, AP, RSE reviewing C1)
C01_7 d/w - 10h/d - No HK 28 01-Apr-22 28-Apr-22 08-May-22 04-Jun-22 37
Hols - No B/O periods (was
310.D.R0.L810.B01 ELS Design for ISO Chamber - ICC, M&VC review design and issue check certificate C1)
C01_7 d/w - 10h/d - No HK 21 29-Apr-22 19-May-22 05-Jun-22 25-Jun-22 37
Hols - No B/O periods (was
310.D.R0.L815.B01 ELS Design for ISO Chamber - address comments & resubmit 2nd Round C1)
C01_7 d/w - 10h/d - No HK 4 20-May-22 23-May-22 26-Jun-22 29-Jun-22 37
Hols - No B/O periods (was
310.D.R0.L820.B01 ELS Design for ISO Chamber - PM, AP, RSE reviewing 2nd Round C1)
C01_7 d/w - 10h/d - No HK 28 24-May-22 20-Jun-22 30-Jun-22 27-Jul-22 37
Hols - No B/O periods (was
310.D.R0.L825.B01 ELS Design for ISO Chamber - ICC, M&VC review design and issue check certificate 2nd C1)
C01_7 d/w - 10h/d - No HK 21 21-Jun-22 11-Jul-22 28-Jul-22 17-Aug-22 37
Round Hols - No B/O periods (was
310.D.R0.L830.B01 ELS Design for ISO Chamber - BD review and approve C1)
C01_7 d/w - 10h/d - No HK 60 12-Jul-22 09-Sep-22 18-Aug-22 16-Oct-22 37
Hols - No B/O periods (was
310.D.R0.L835.B01 ELS Design for ISO Chamber - prepare and submit Form BA8 and grant consent C1)
C01_7 d/w - 10h/d - No HK 7 10-Sep-22 16-Sep-22 17-Oct-22 23-Oct-22 37
Hols - No B/O periods (was
C1)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 37 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.R0.L840.B01 ELS Design for ISO Chamber - prepare and submit Form BA10 (with instrumentation C01_7 d/w - 10h/d - No HK 7 17-Sep-22 23-Sep-22 24-Oct-22 30-Oct-22 37
readings) Hols - No B/O periods (was
CC#04 - AFHS Design (VE+ELS) - Section 1 C1)
C01_7 d/w - 10h/d - No HK Hols195
- No B/O periods
0 (was
29-Nov-21
C1) A 12-Aug-22 09-Jun-22 25-Oct-22 74
310.D.R0.L504 ELS Design Section 1 - Prepare Design & submit with ICE C01_7 d/w - 10h/d - No HK 28 29-Nov-21 A 18-Apr-22 09-Jun-22 01-Jul-22 74
Hols - No B/O periods (was
310.D.R0.L508 ELS Design Section 1 - PM, AP, RSE reviewing C1)
C01_7 d/w - 10h/d - No HK 28 19-Apr-22 16-May-22 02-Jul-22 29-Jul-22 74
Hols - No B/O periods (was
310.D.R0.L512 ELS Design Section 1 - ICC, M&VC review design and issue check certificate C1)
C01_7 d/w - 10h/d - No HK 21 17-May-22 06-Jun-22 30-Jul-22 19-Aug-22 74
Hols - No B/O periods (was
310.D.R0.L516 ELS Design Section 1 - address comments & resubmit 2nd Round C1)
C01_7 d/w - 10h/d - No HK 4 07-Jun-22 10-Jun-22 20-Aug-22 23-Aug-22 74
Hols - No B/O periods (was
310.D.R0.L532 ELS Design Section 1 - PM, AP, RSE reviewing 2nd Round C1)
C01_7 d/w - 10h/d - No HK 28 11-Jun-22 08-Jul-22 24-Aug-22 20-Sep-22 74
Hols - No B/O periods (was
310.D.R0.L536 ELS Design Section 1 - ICC, M&VC review design and issue check certificate 2nd Round C1)
C01_7 d/w - 10h/d - No HK 21 09-Jul-22 29-Jul-22 21-Sep-22 11-Oct-22 74
Hols - No B/O periods (was
310.D.R0.L524 ELS Design Section 1 - prepare and submit Form BA8 and grant consent C1)
C01_7 d/w - 10h/d - No HK 7 30-Jul-22 05-Aug-22 12-Oct-22 18-Oct-22 74
Hols - No B/O periods (was
310.D.R0.L528 ELS Design Section 1 - prepare and submit Form BA10 (with instrumentation readings) C1)
C01_7 d/w - 10h/d - No HK 7 06-Aug-22 12-Aug-22 19-Oct-22 25-Oct-22 74
Hols - No B/O periods (was
CC#04 - AFHS Design (VE+ELS) - Section 2 C1)
C01_7 d/w - 10h/d - No HK Hols204
- No B/O periods
0 (was17-Apr-22
C1) 06-Nov-22 28-May-22 17-Dec-22 41
310.D.R0.L468 ELS Design Section 2 - Prepare Design & submit with ICE C01_7 d/w - 10h/d - No HK 28 17-Apr-22 14-May-22 28-May-22 24-Jun-22 41
Hols - No B/O periods (was
310.D.R0.L472 ELS Design Section 2 - PM, AP, RSE reviewing C1)
C01_7 d/w - 10h/d - No HK 28 15-May-22 11-Jun-22 25-Jun-22 22-Jul-22 41
Hols - No B/O periods (was
310.D.R0.L476 ELS Design Section 2 - ICC, M&VC review design and issue check certificate C1)
C01_7 d/w - 10h/d - No HK 21 12-Jun-22 02-Jul-22 23-Jul-22 12-Aug-22 41
Hols - No B/O periods (was
310.D.R0.L480 ELS Design Section 2 - address comments & resubmit 2nd Round C1)
C01_7 d/w - 10h/d - No HK 4 03-Jul-22 06-Jul-22 13-Aug-22 16-Aug-22 41
Hols - No B/O periods (was
310.D.R0.L484 ELS Design Section 2 - PM, AP, RSE reviewing 2nd Round C1)
C01_7 d/w - 10h/d - No HK 28 07-Jul-22 03-Aug-22 17-Aug-22 13-Sep-22 41
Hols - No B/O periods (was
310.D.R0.L488 ELS Design Aviation Fuel Pipe - ICC, M&VC review design and issue check certificate C1)
C01_7 d/w - 10h/d - No HK 21 04-Aug-22 24-Aug-22 14-Sep-22 04-Oct-22 41
2nd Round Hols - No B/O periods (was
310.D.R0.L492 ELS Design Aviation Fuel Pipe - BD review and approve C1)
C01_7 d/w - 10h/d - No HK 60 25-Aug-22 23-Oct-22 05-Oct-22 03-Dec-22 41
Hols - No B/O periods (was
310.D.R0.L496 ELS Design Aviation Fuel Pipe - prepare and submit Form BA8 and grant consent C1)
C01_7 d/w - 10h/d - No HK 7 24-Oct-22 30-Oct-22 04-Dec-22 10-Dec-22 41
Hols - No B/O periods (was
310.D.R0.L500 ELS Design Aviation Fuel Pipe - prepare and submit Form BA10 (with instrumentation C1)
C01_7 d/w - 10h/d - No HK 7 31-Oct-22 06-Nov-22 11-Dec-22 17-Dec-22 41
readings) Hols - No B/O periods (was
CC#04 - AFHS Testing and Commissioning Plan for Stage 1 & Stage 2 Aviation Fuel System C1)
C01_7 d/w - 10h/d - No HK Hols58
- No B/O periods
0 (was04-Feb-23
C1) 02-Apr-23 04-Feb-23 23-Apr-23 21
310.D.EX.G122 MS.28 - AFP - T&C Plan - Prepare and submit to PM C01_7 d/w - 10h/d - No HK 30 04-Feb-23 05-Mar-23 04-Feb-23 05-Mar-23 0
Hols - No B/O periods (was
310.D.EX.G126 MS.28 - AFP - T&C Plan - PM review and accept C1)
C01_7 d/w - 10h/d - No HK 28 06-Mar-23 02-Apr-23 27-Mar-23 23-Apr-23 21
Hols - No B/O periods (was
CC#4 - UU ELS Design (Airfield Statutory Submission) C1)
C01_7 d/w - 10h/d - No HK Hols145
- No B/O periods
0 (was
22-Dec-21
C1) A 17-Aug-22 06-May-22 01-Sep-24 746
West Wrap Around Area -Design for ELS to underground utilities C01_7 d/w - 10h/d - No HK Hols128
- No B/O periods
0 (was
22-Dec-21
C1) A 19-Apr-22 08-Jul-22 01-Sep-24 824
310.D.EX.U101 UU ELS Design - Prepare design with ICE checked and submit to AA C01_7 d/w - 10h/d - No HK 30 22-Dec-21 A 20-Jan-22 A 01-Sep-24 01-Sep-24
Hols - No B/O periods (was
310.D.EX.U104 UU ELS Design - PM, Project AP/RSE endorse design and submit to ICC and M&VC C1)
C01_7 d/w - 10h/d - No HK 28 21-Jan-22 A 13-Feb-22 A 01-Sep-24 01-Sep-24
Hols - No B/O periods (was
310.D.EX.U107 UU ELS Design - ICC & M&VC review and approved C1)
C01_7 d/w - 10h/d - No HK 21 14-Feb-22 A 25-Mar-22 A 01-Sep-24 01-Sep-24
Hols - No B/O periods (was
C1)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 38 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.EX.U119 UU ELS Design - BA8 consent C01_7 d/w - 10h/d - No HK 7 24-Mar-22 A 12-Apr-22 08-Jul-22 24-Jul-22 103
Hols - No B/O periods (was
310.D.EX.U122 UU ELS Design - submit Form BA10 (west wrap around UU) C1)
C01_7 d/w - 10h/d - No HK 7 13-Apr-22 19-Apr-22 25-Jul-22 31-Jul-22 103
Hols - No B/O periods (was
Design for ELS to other UUs C1)
C01_7 d/w - 10h/d - No HK Hols144
- No B/O periods
0 (was
01-Jan-22
C1) A 17-Aug-22 06-May-22 26-Sep-22 40
310.D.EX.U132.B02 Other UU ELS Design - Prepare design with ICE checked and submit to AA C01_7 d/w - 10h/d - No HK 30 01-Jan-22 A 30-Jan-22 A 06-May-22 06-May-22
Hols - No B/O periods (was
310.D.EX.U142.B02 Other UU ELS Design - PM, Project AP/RSE endorse design and submit to ICC and C1)
C01_7 d/w - 10h/d - No HK 28 31-Jan-22 A 10-Feb-22 A 06-May-22 06-May-22
M&VC Hols - No B/O periods (was
310.D.EX.U152.B02 Other UU ELS Design - ICC & M&VC review and issue comments C1)
C01_7 d/w - 10h/d - No HK 21 11-Feb-22 A 16-Apr-22 06-May-22 26-May-22 40
Hols - No B/O periods (was
310.D.EX.U162.B02 Other UU ELS Design - address ICC & M&VC comments and resubmit C1)
C01_7 d/w - 10h/d - No HK 14 17-Apr-22 30-Apr-22 27-May-22 09-Jun-22 40
Hols - No B/O periods (was
310.D.EX.U172.B02 Other UU ELS Design - PM, Project AP/RSE endorse design and submit to ICC and C1)
C01_7 d/w - 10h/d - No HK 28 01-May-22 28-May-22 10-Jun-22 07-Jul-22 40
M&VC 2nd round Hols - No B/O periods (was
310.D.EX.U182.B02 Other UU ELS Design - ICC & M&VC review and endorse design and submit to BD C1)
C01_7 d/w - 10h/d - No HK 7 29-May-22 04-Jun-22 08-Jul-22 14-Jul-22 40
Hols - No B/O periods (was
310.D.EX.U192.B02 Other UU ELS Design - BD review & approve ELS design - review and approve C1)
C01_7 d/w - 10h/d - No HK 60 05-Jun-22 03-Aug-22 15-Jul-22 12-Sep-22 40
Hols - No B/O periods (was
310.D.EX.U202.B02 Other UU ELS Design - BA8 consent C1)
C01_7 d/w - 10h/d - No HK 7 04-Aug-22 10-Aug-22 13-Sep-22 19-Sep-22 40
Hols - No B/O periods (was
310.D.EX.U212.B02 Other UU ELS Design - submit Form BA10 (new UU inside existing north runway) C1)
C01_7 d/w - 10h/d - No HK 7 11-Aug-22 17-Aug-22 20-Sep-22 26-Sep-22 40
Hols - No B/O periods (was
CC#4 ----- Method Statement Submission C1)
C01_7 d/w - 10h/d - No HK Hols348
- No B/O periods
0 (was
10-Jul-21
C1) A 22-Jun-22 27-Mar-22 01-May-23 313
CC#04 - MS no. 8 - Method Statement for Box Culvert temporary works & ELS Construction C01_7 d/w - 10h/d - No HK Hols42
- No B/O periods
0 (was
23-Aug-21
C1) A 03-Dec-21 A 23-Apr-22 23-Apr-22
310.D.TX.A212 MS no.8 - Method Statement for Box Culvert temporary works & ELS Construction - C01_7 d/w - 10h/d - No HK 14 23-Aug-21 A 09-Sep-21 A 23-Apr-22 23-Apr-22
prepare document Hols - No B/O periods (was
310.D.TX.A216 MS no.8 - Method Statement for Box Culvert temporary works & ELS - PM review and C1)
C01_7 d/w - 10h/d - No HK 28 10-Sep-21 A 03-Dec-21 A 23-Apr-22 23-Apr-22
accept Hols - No B/O periods (was
CC#04 - MS no.12 - AFP - Method Statement for Stage 1 Aviation Fuel Direct Buried Pipe Installation C1)
C01_7 d/w - 10h/d - No HK Hols42
- No B/O periods
0 (was
25-Oct-21
C1) A 06-Apr-22 27-Mar-22 13-Jun-22 68
310.D.EX.G106 MS no.12 - AFP - MS for Stage 1 AFP Installation - prepare and submit to PM for C01_7 d/w - 10h/d - No HK 14 25-Oct-21 A 12-Nov-21 A 27-Mar-22 27-Mar-22
reviewing Hols - No B/O periods (was
310.D.EX.G110 MS.12 - AFP - MS for Stage 1 AFP Installation - PM review and accept C1)
C01_7 d/w - 10h/d - No HK 28 13-Nov-21 A 06-Apr-22 03-Jun-22 13-Jun-22 68
Hols - No B/O periods (was
CC#04 - AFP - Method Statement for Stage 2 Aviation Fuel Pipe Installation through WVT C1)
C01_7 d/w - 10h/d - No HK Hols42
- No B/O periods
0 (was12-May-22
C1) 22-Jun-22 12-May-22 17-Dec-22 178
310.D.EX.G114 MS no.24 - AFP - MS for Stage 2 AFP Installation - prepare and submit to PM for C01_7 d/w - 10h/d - No HK 14 12-May-22 25-May-22 12-May-22 25-May-22 0
reviewing Hols - No B/O periods (was
310.D.EX.G118 MS.24 - AFP - MS for Stage 2 AFP Installation - PM review and accept C1)
C01_7 d/w - 10h/d - No HK 28 26-May-22 22-Jun-22 20-Nov-22 17-Dec-22 178
Hols - No B/O periods (was
CC#04 - MS No. 16 - Method Statement for Installation and Tie-in of various Utilities to Ex. Network C1)
C01_7 d/w - 10h/d - No HK Hols135
- No B/O periods
0 (was
27-Aug-21
C1) A 01-Apr-22 27-Mar-22 01-Apr-22 0
310.D.R0.L315 MS no. 16 - MS for Installation and Tie-in of Various Utilities to Ex. Network - liaison with C01_7 d/w - 10h/d - No HK 30 27-Aug-21 A 25-Sep-21 A 27-Mar-22 27-Mar-22
AA Hols - No B/O periods (was
310.D.R0.L316 MS no. 16 - MS for Installation and Tie-in of Various Utilities to Ex. Network - prepare C1)
C01_7 d/w - 10h/d - No HK 30 05-Nov-21 A 22-Dec-21 A 27-Mar-22 27-Mar-22
document Hols - No B/O periods (was
310.D.R0.L320 MS no. 16 - MS for Installation and Tie-in of Various Utilities to Ex. Network - ICE issue C1)
C01_7 d/w - 10h/d - No HK 7 17-Dec-21 A 23-Dec-21 A 27-Mar-22 27-Mar-22
check certificate Hols - No B/O periods (was
310.D.R0.L324 MS no. 16 - MS for Installation and Tie-in of Various Utilities to Ex. Network - PM review C1)
C01_7 d/w - 10h/d - No HK 28 23-Dec-21 A 01-Apr-22 27-Mar-22 01-Apr-22 0
and accept Hols - No B/O periods (was
CC#04 - MS no. 17 - Method Statement for Construction and Tie-in of Box Culvert no. 3, 4, 5, 6 C1)
C01_7 d/w - 10h/d - No HK Hols240
- No B/O periods
0 (was
27-Aug-21
C1) A 25-Mar-22 A 03-Oct-22 11-Jan-23
310.D.R0.L85 MS no. 17 - MS for Construct Box Culvert Tie-in (no. 3,4,5,6) - liaison with AA C01_7 d/w - 10h/d - No HK 30 27-Aug-21 A 25-Sep-21 A 03-Oct-22 03-Oct-22
Hols - No B/O periods (was
C1)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 39 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.R0.L86 MS no. 17 - MS for Construct Box Culvert Tie-in (no. 3,4,5,6) - prepare document C01_7 d/w - 10h/d - No HK 30 05-Nov-21 A 02-Jan-22 A 11-Jan-23 11-Jan-23
Hols - No B/O periods (was
310.D.R0.L94 MS no. 17 - MS for Construct Box Culvert Tie-in (no. 3,4,5,6) - PM review and accept C1)
C01_7 d/w - 10h/d - No HK
28 03-Jan-22 A 18-Mar-22 A 11-Jan-23 11-Jan-23
Hols - No B/O periods (was
310.D.R0.L90 MS no. 17 - MS for Construct Box Culvert Tie-in (no. 3,4,5,6) - ICE issue check certificate C1)
C01_7 d/w - 10h/d - No HK 7 19-Mar-22 A 25-Mar-22 A 11-Jan-23 11-Jan-23
Hols - No B/O periods (was
CC#04 - MS no. 21 - Method Statement for Construction and Tie-in of Stormwater Box Culvert no.18, 19 C1)
C01_7 d/w - 10h/d - No HK Hols183
- No B/O periods
0 (was
30-Oct-21
C1) A 25-Mar-22 A 03-Oct-22 03-Oct-22
310.D.R0.L099 MS no. 21 - MS for Construct Box Culvert Tie-in (no. 18,19) - liaison with AA C01_7 d/w - 10h/d - No HK 60 30-Oct-21 A 20-Nov-21 A 03-Oct-22 03-Oct-22
Hols - No B/O periods (was
310.D.R0.L101 MS no. 21 - MS for Construct Box Culvert Tie-in (no. 18,19) - prepare document C1)
C01_7 d/w - 10h/d - No HK 30 21-Nov-21 A 20-Dec-21 A 03-Oct-22 03-Oct-22
Hols - No B/O periods (was
310.D.R0.L106 MS no. 21 - MS for Construct Box Culvert Tie-in (no. 18,19) - PM review and accept C1)
C01_7 d/w - 10h/d - No HK 28 21-Dec-21 A 18-Mar-22 A 03-Oct-22 03-Oct-22
Hols - No B/O periods (was
310.D.R0.L102 MS no. 21 - MS for Construct Box Culvert Tie-in (no. 18,19) - ICE issue check certificate C1)
C01_7 d/w - 10h/d - No HK 7 19-Mar-22 A 25-Mar-22 A 03-Oct-22 03-Oct-22
Hols - No B/O periods (was
CC#4 - MS no.5 - UU - MS for Ducting C1)
C01_7 d/w - 10h/d - No HK Hols93
- No B/O periods
0 (was
10-Jul-21
C1) A 02-Dec-21 A 08-Jun-22 03-Nov-22
310.C.EX.U242 MS no.05 - MS for ducting & drawpit construction - prepare & submit method statement to C01_7 d/w - 10h/d - No HK 30 10-Jul-21 A 08-Aug-21 A 08-Jun-22 08-Jun-22
PM Hols - No B/O periods (was
310.C.EX.U245 MS no.05 - MS for ducting & drawpit construction - PM review and comment C1)
C01_7 d/w - 10h/d - No HK 28 09-Aug-21 A 05-Sep-21 A 03-Nov-22 03-Nov-22
Hols - No B/O periods (was
310.C.EX.U248 MS no.05 - MS for ducting & drawpit - address PM's comments C1)
C01_7 d/w - 10h/d - No HK 7 07-Oct-21 A 28-Nov-21 A 03-Nov-22 03-Nov-22
Hols - No B/O periods (was
310.C.EX.U251 MS no.05 - MS for ducting & drawpit - PM accept C1)
C01_7 d/w - 10h/d - No HK 28 29-Nov-21 A 02-Dec-21 A 03-Nov-22 03-Nov-22
Hols - No B/O periods (was
CC#4 - Method Statement for Plate Load Test C1)
C01_7 d/w - 10h/d - No HK Hols58
- No B/O periods
0 (was27-Mar-22
C1) 23-May-22 05-Mar-23 01-May-23 343
310.D.TX.A340 Method Statement for Plate Load Test - prepare document C01_7 d/w - 10h/d - No HK 30 27-Mar-22 25-Apr-22 05-Mar-23 03-Apr-23 343
Hols - No B/O periods (was
310.D.TX.A344 Method Statement for Plate Load Test - BD Acknowledge C1)
C01_7 d/w - 10h/d - No HK 28 26-Apr-22 23-May-22 04-Apr-23 01-May-23 343
Hols - No B/O periods (was
CC#4 ----- Procurement ----- C1)
C01_7 d/w - 10h/d - No HK Hols203
- No B/O periods
0 (was
25-Oct-21
C1) A 20-Aug-22 11-Apr-22 16-Oct-22 57
Subletting C01_7 d/w - 10h/d - No HK Hols123
- No B/O periods
0 (was
25-Oct-21
C1) A 01-Jun-22 11-Apr-22 21-Jun-22 20
CC#4 - Interim Security Fence (ISF) C01_7 d/w - 10h/d - No HK Hols90
- No B/O periods
0 (was
30-Jan-22
C1) A 20-May-22 11-Apr-22 04-Jun-22 15
310.P.RC.C034 Subletting - Interim Security Fence (ISF) - Stage 1&2 Preparation,Submission& C01_7 d/w - 10h/d - No HK 90 30-Jan-22 A 20-May-22 11-Apr-22 04-Jun-22 15
Approval,Tender&Award sub-contract Hols - No B/O periods (was
CC#4 - Box Culvert C1)
C01_7 d/w - 10h/d - No HK Hols90
- No B/O periods
0 (was
25-Oct-21
C1) A 06-Jan-22 A 13-Jun-22 13-Jun-22
310.P.R0.L244 Subletting - Box Culvert - Formwork Supply - Award sub-contract C01_7 d/w - 10h/d - No HK 90 25-Oct-21 A 29-Dec-21 A 13-Jun-22 13-Jun-22
Hols - No B/O periods (was
310.P.R0.L268 Subletting - Box Culvert - Structural Works - Award sub-contract C1)
C01_7 d/w - 10h/d - No HK 90 01-Nov-21 A 06-Jan-22 A 13-Jun-22 13-Jun-22
Hols - No B/O periods (was
CC#4 - Jet Blast Screen C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was
04-Mar-22
C1) A 01-Jun-22 16-Apr-22 21-Jun-22 20
310.P.RC.D096 Subletting - Jet Blast Screen - Stage 1&2 Preparation,Submission& C01_7 d/w - 10h/d - No HK 67 04-Mar-22 A 01-Jun-22 16-Apr-22 21-Jun-22 20
Approval,Tender&Award sub-contract Hols - No B/O periods (was
CC#4 - AGL Diversion C1)
C01_7 d/w - 10h/d - No HK Hols90
- No B/O periods
0 (was
01-Nov-21
C1) A 15-Apr-22 11-Apr-22 30-Apr-22 15
310.P.RC.D551.B01 Subletting - AGL Diversion - Stage 1&2 Preparation,Submission& C01_7 d/w - 10h/d - No HK 90 01-Nov-21 A 15-Apr-22 11-Apr-22 30-Apr-22 15
Approval,Tender&Award sub-contract Hols - No B/O periods (was
Procurement C1)
C01_7 d/w - 10h/d - No HK Hols203
- No B/O periods
0 (was
30-Jan-22
C1) A 20-Aug-22 11-Apr-22 16-Oct-22 57
Major Long Lead Items - Aviation Fuel and Hydrant System (AFHS) C01_7 d/w - 10h/d - No HK Hols147
- No B/O periods
0 (was27-Mar-22
C1) 20-Aug-22 23-May-22 16-Oct-22 57
Major Long Lead Items - Pipe and Fittings C01_7 d/w - 10h/d - No HK Hols147
- No B/O periods
0 (was27-Mar-22
C1) 20-Aug-22 23-May-22 16-Oct-22 57
310.P.EX.U205 Procurement Major Long Lead Items - Preparation & Submission of Pipe and Fittings 1st C01_7 d/w - 10h/d - No HK 7 27-Mar-22 02-Apr-22 23-May-22 29-May-22 57
Round Hols - No B/O periods (was
C1)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 40 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.P.EX.U208 Procurement Major Long Lead Items - Comments & Acceptance for Pipe and Fittings 1st C01_7 d/w - 10h/d - No HK 28 03-Apr-22 30-Apr-22 30-May-22 26-Jun-22 57
Round Hols - No B/O periods (was
310.P.EX.U218 Procurement Major Long Lead Items - Preparation & Submission of Pipe and Fittings 2nd C1)
C01_7 d/w - 10h/d - No HK 7 01-May-22 07-May-22 27-Jun-22 03-Jul-22 57
Round Hols - No B/O periods (was
310.P.EX.U222 Procurement Major Long Lead Items - Comments & Acceptance for Pipe and Fittings C1)
C01_7 d/w - 10h/d - No HK 28 08-May-22 04-Jun-22 04-Jul-22 31-Jul-22 57
2nd Round Hols - No B/O periods (was
310.P.EX.U211 Procurement Major Long Lead Items - Place Order & Manufacture for Pipe and Fittings C1)
C01_7 d/w - 10h/d - No HK 72 05-Jun-22 15-Aug-22 01-Aug-22 11-Oct-22 57
(1st batch) Hols - No B/O periods (was
310.P.EX.U214 Procurement Major Long Lead Items - Delivery on Site for Pipe and Fittings (1st batch) C1)
C01_7 d/w - 10h/d - No HK 5 16-Aug-22 20-Aug-22 12-Oct-22 16-Oct-22 57
Hols - No B/O periods (was
Major Long Lead Items -Interim Security Fence C1)
C01_7 d/w - 10h/d - No HK Hols137
- No B/O periods
0 (was
30-Jan-22
C1) A 31-May-22 11-Apr-22 15-Jun-22 15
310.P.EX.U226.B01 Procurement of Wire Mesh Fence and Barbed Tape- Preparation & Submission C01_7 d/w - 10h/d - No HK 14 30-Jan-22 A 12-Feb-22 A 02-May-22 02-May-22
Hols - No B/O periods (was
310.P.EX.U250.B01 Procurement Footing (Precast) - Preparation & Submission C1)
C01_7 d/w - 10h/d - No HK 14 30-Jan-22 A 12-Feb-22 A 11-Apr-22 11-Apr-22
Hols - No B/O periods (was
310.P.EX.U240.B01 Procurement Marker Board - Preparation & Submission C1)
C01_7 d/w - 10h/d - No HK 14 30-Jan-22 A 12-Feb-22 A 02-May-22 02-May-22
Hols - No B/O periods (was
310.P.EX.U230.B01 Procurement of Wire Mesh Fence and Barbed Tape - AAHK Comments & Acceptance C1)
C01_7 d/w - 10h/d - No HK 21 13-Feb-22 A 05-Mar-22 A 02-May-22 02-May-22
Hols - No B/O periods (was
310.P.EX.U245.B01 Procurement Marker Board - AAHK Comments & Acceptance C1)
C01_7 d/w - 10h/d - No HK 21 13-Feb-22 A 05-Mar-22 A 02-May-22 02-May-22
Hols - No B/O periods (was
310.P.EX.U255.B01 Procurement Footing (Precast) - AAHK Comments & Acceptance C1)
C01_7 d/w - 10h/d - No HK 21 13-Feb-22 A 16-Apr-22 11-Apr-22 01-May-22 15
Hols - No B/O periods (was
310.P.EX.U260.B01 Procurement - Place order & manufacture/fabricate Wire Mesh, Barbed Tape, Marker C1)
C01_7 d/w - 10h/d - No HK 60 06-Mar-22 A 22-May-22 02-May-22 06-Jun-22 15
Board and Precast Footing Hols - No B/O periods (was
310.P.EX.U265.B01 Procurement - Delivery on Site of Interim Fence Components and Marker Boards C1)
C01_7 d/w - 10h/d - No HK 9 23-May-22 31-May-22 07-Jun-22 15-Jun-22 15
Hols - No B/O periods (was
CC#4 ----- Construction ----- C1) 908 368 07-Jun-21 A 25-Jun-24 31-Jan-22 01-Sep-24 57
CC#4.1, 4.2, 4.4, 4.7 - 3310/11 - Area G1 & G2 - CC#4 Airside Road and Landside Road 590 0 24-Sep-21 A 20-Mar-24 08-Jun-22 01-Jun-24 57
CC#4.1, 4.2, 4.4, 4.7 - 3310/11 - Area G1 & G2 - Underground Utilities under ASR & LSR 319 0 24-Sep-21 A 25-Apr-23 08-Jun-22 05-Jul-23 57
310.C.G1.J115 3310/11 - Area G1&G2 (under ASR & LSR) - Plant Mobilization for u/g utilities works C11_6 d/w - 10h/d - With 14 24-Sep-21 A 24-Sep-21 A 08-Jun-22 08-Jun-22
HK Hols - No B/O periods
310.C.G1.J117 3310/11 - Area G1&G2 (under ASR & LSR) - GI for stormwater drain (was
C11_6C3)
d/w - 10h/d - With 10 24-Sep-21 A 21-Oct-21 A 04-Jul-22 04-Jul-22
HK Hols - No B/O periods
310.C.G1.J118 3310/11 - Area G1&G2 (under ASR & LSR) - carry out site survey & ascertain installation (was
C11_6C3)
d/w - 10h/d - With 21 28-Mar-22 25-Apr-22 08-Jun-22 02-Jul-22 56
level for UU HK Hols - No B/O periods
310.C.G1.J119 3310/11 - Area G1&G2 (under ASR & LSR) - confirm installation level with PM (was
C01_7C3)
d/w - 10h/d - No HK 28 26-Apr-22 23-May-22 04-Jul-22 31-Jul-22 69
Hols - No B/O periods (was
310.C.G1.J120 3310/11 - Area G1&G2 (under ASR & LSR) - stormwater drain and manholes [960m C1)
C11_6 d/w - 10h/d - With 58 24-May-22 01-Aug-22 01-Aug-22 10-Oct-22 57
@10m/d/wf, 3WF; 19no.MH @4d/no/wf, 3WF] HK Hols - No B/O periods
310.C.G1.J132 3310/11 - Area G1&G2 (under ASR & LSR) - 132 kv CLP cable ducts and drawpits (L:721 (was
C11_6C3)
d/w - 10h/d - With 60 29-Jun-22 07-Sep-22 05-Sep-22 16-Nov-22 57
m) HK Hols - No B/O periods
310.C.G1.J122 3310/11 - Area G1&G2 (under ASR & LSR) - Gas main (702m) (was
C11_6C3)
d/w - 10h/d - With 58 04-Aug-22 13-Oct-22 13-Oct-22 19-Dec-22 57
HK Hols - No B/O periods
310.C.G1.J128 3310/11 - Area G1&G2 (under ASR & LSR) - Potable Water main for FS (was
C11_6C3)
d/w - 10h/d - With 60 15-Sep-22 25-Nov-22 23-Nov-22 06-Feb-23 57
HK Hols - No B/O periods
310.C.G1.J124 3310/11 - Area G1&G2 (under ASR & LSR) - Airport Systems ductings (was
C11_6C3)
d/w - 10h/d - With 60 26-Nov-22 09-Feb-23 07-Feb-23 21-Apr-23 57
HK Hols - No B/O periods
310.C.G1.J144 3310/11 - Area G1&G2 (under ASR & LSR) - Road Drainage (was
C11_6C3)
d/w - 10h/d - With 60 10-Feb-23 25-Apr-23 22-Apr-23 05-Jul-23 57
HK Hols - No B/O periods
CC#4.10 - 3310/11 - Area G1 & G2 - Landside Road Roadwork (was
C11_6C3)
d/w - 10h/d - With HK Hols
149- No B/O 0periods (was
26-Apr-23
C3) 24-Oct-23 06-Jul-23 11-Apr-24 137

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 41 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.RD.J100 3310/11 - Area G1&G2 - LSR - construct kerb and sub-base [650m @20m/d/wf; 2wf] C11_6 d/w - 10h/d - With 17 26-Apr-23 16-May-23 06-Jul-23 25-Jul-23 57
HK Hols - No B/O periods
310.C.RD.J101 3310/11 - Area G1&G2 - LSR - construct flexible pavement [650m @15m/d/wf; 2wf] (was
C11_6C3)
d/w - 10h/d - With 22 17-May-23 12-Jun-23 26-Jul-23 19-Aug-23 57
HK Hols - No B/O periods
310.C.RD.J102 3310/11 - Area G1&G2 - LSR - install street lighting, road furniture (was
C11_6C3)
d/w - 10h/d - With 30 13-Jun-23 19-Jul-23 16-Feb-24 21-Mar-24 203
HK Hols - No B/O periods
310.C.RD.J103 3310/11 - Area G1&G2 - LSR - wearing course & road marking (was
C11_6C3)
d/w - 10h/d - With 14 07-Oct-23 24-Oct-23 22-Mar-24 11-Apr-24 137
HK Hols - No B/O periods
CC#4.10 - 3310/11 - Area G1 & G2 - Airside Road Roadwork (was
C11_6C3)
d/w - 10h/d - With HK Hols
146- No B/O 0periods (was
17-May-23
C3) 09-Nov-23 01-Dec-23 27-Apr-24 137
310.C.RD.J116 3310/11 - Area G1&G2 - ASR - construct kerb and sub-base [650m @20m/d/wf; 2wf] C11_6 d/w - 10h/d - With 17 17-May-23 06-Jun-23 01-Dec-23 20-Dec-23 164
HK Hols - No B/O periods
310.C.RD.J120 3310/11 - Area G1&G2 - ASR - construct flexible pavement [650m @15m/d/wf; 2wf] (was
C11_6C3)
d/w - 10h/d - With 22 13-Jun-23 10-Jul-23 21-Dec-23 18-Jan-24 159
HK Hols - No B/O periods
310.C.RD.J124 3310/11 - Area G1&G2 - ASR- install street lighting, road furniture (was
C11_6C3)
d/w - 10h/d - With 30 11-Jul-23 14-Aug-23 19-Jan-24 24-Feb-24 159
HK Hols - No B/O periods
310.C.RD.J128 3310/11 - Area G1&G2 - ASR - wearing course & road marking (was
C11_6C3)
d/w - 10h/d - With 14 25-Oct-23 09-Nov-23 12-Apr-24 27-Apr-24 137
HK Hols - No B/O periods
CC#4.11 - 3310/11 - Area G1 & G2 - Security Fencing (was
C11_6C3)
d/w - 10h/d - With HK Hols
232- No B/O 0periods (was
13-Jun-23
C3) 20-Mar-24 21-Aug-23 01-Jun-24 57
3310/11 - Area G1 Security Fencing C11_6 d/w - 10h/d - With HK Hols
162- No B/O 0periods (was
13-Jun-23
C3) 23-Dec-23 21-Aug-23 01-Jun-24 127
310.C.RD.J112 3310/11 - Area G1 - Security Fence & Gate - construct footing [385mL x 2 rows; C11_6 d/w - 10h/d - With 70 13-Jun-23 04-Sep-23 21-Aug-23 13-Nov-23 57
@20m/7d/wf; 4WF] HK Hols - No B/O periods
310.C.RD.J140 3310/11 - Area G1 - Security Fence & Gate - metal works (was
C11_6C3)
d/w - 10h/d - With 40 05-Sep-23 24-Oct-23 07-Feb-24 26-Mar-24 127
HK Hols - No B/O periods
310.C.RD.J144 3310/11 - Area G1 - Security Fence & Gate - install security system (was
C11_6C3)
d/w - 10h/d - With 52 25-Oct-23 23-Dec-23 27-Mar-24 01-Jun-24 127
HK Hols - No B/O periods
3310/11 - Area G2 Security Fencing (was
C11_6C3)
d/w - 10h/d - With HK Hols
162- No B/O 0periods (was
05-Sep-23
C3) 20-Mar-24 14-Nov-23 01-Jun-24 57
310.C.RD.J145 3310/11 - Area G2 - Security Fence & Gate - construct footing [385mL x 2 rows; C11_6 d/w - 10h/d - With 70 05-Sep-23 28-Nov-23 14-Nov-23 06-Feb-24 57
@20m/7d/wf; 4WF] HK Hols - No B/O periods
310.C.RD.J146 3310/11 - Area G2 - Security Fence & Gate - metal works (was
C11_6C3)
d/w - 10h/d - With 40 29-Nov-23 17-Jan-24 07-Feb-24 26-Mar-24 57
HK Hols - No B/O periods
310.C.RD.J147 3310/11 - Area G2 - Security Fence & Gate - install security system (was
C11_6C3)
d/w - 10h/d - With 52 18-Jan-24 20-Mar-24 27-Mar-24 01-Jun-24 57
HK Hols - No B/O periods
CC#4.10 - 3310/11 - Area G1 & G2 - Central Reserve Pavement (was
C11_6C3)
d/w - 10h/d - With HK Hols
34- No B/O 0periods (was
05-Sep-23
C3) 16-Oct-23 22-Apr-24 01-Jun-24 185
310.C.RD.J132 3310/11 - Area G1&G2 - Central Reserve - sub-base [650m; 100mm thk @50m/d/wf] C11_6 d/w - 10h/d - With 20 05-Sep-23 27-Sep-23 22-Apr-24 16-May-24 185
HK Hols - No B/O periods
310.C.RD.J136 3310/11 - Area G1&G2 - Central Reserve - verge [650m, 75mmthk] (was
C11_6C3)
d/w - 10h/d - With 14 28-Sep-23 16-Oct-23 17-May-24 01-Jun-24 185
HK Hols - No B/O periods
CC#4 - 3310/11 - Area G4 - Airside Road and Landside Road (was C3) 513 49 28-Mar-22 15-Dec-23 07-May-22 01-Jun-24 134
CC#4.1, 4.2, 4.4, 4.7 - 3310/11 - Area G4 - Underground Utilities under ASR & LSR 256 14 28-Mar-22 06-Feb-23 07-May-22 19-Mar-23 35
310.C.G4.J123 3310/11 - Area G4 - (under LSR & ASR) - GI for utilities C11_6 d/w - 10h/d - With 14 28-Mar-22 13-Apr-22 07-May-22 23-May-22 30
HK Hols - No B/O periods
310.C.G4.J127 3310/11 - Area G4 - (under LSR & ASR) - PM agree utilities installation level (was
C01_7C3)
d/w - 10h/d - No HK 28 28-Mar-22 24-Apr-22 07-May-22 03-Jun-22 40
Hols - No B/O periods (was
310.C.G4.J127.B01 3310/11 - Area G4 - (under ASR & LSR) - Backfill up to form I.L. of SWD, CLP ducts, C1)
C11_6 d/w - 10h/d - With 28 25-Apr-22 27-May-22 04-Jun-22 07-Jul-22 33
Gasmain and PWFH HK Hols - No B/O periods
310.C.G4.J128 3310/11 - Area G4 - LSR - stormwater drain pipe [394mL @10m/d/wf; 2wf; 10MH (was C3)
C11_6 d/w - 10h/d - With 44 4 13-May-22 05-Jul-22 22-Jun-22 12-Aug-22 33
@4d/no/wf; 3wf] HK Hols - No B/O periods
310.C.G4.J132 3310/11 - Area G4 - LSR - Construct 132kv CLP duct (L=608m) and drawpits (was
C11_6C3)
d/w - 10h/d - With 62 2 07-Jun-22 18-Aug-22 16-Jul-22 27-Sep-22 33
HK Hols - No B/O periods
310.C.G4.J129 3310/11 - Area G4 - LSR - Pipe laying of Gasmain (L=556m) (was
C11_6C3)
d/w - 10h/d - With 42 2 30-Jun-22 18-Aug-22 09-Aug-22 27-Sep-22 33
HK Hols - No B/O periods
(was C3)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 42 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.G4.J131 3310/11 - Area G4 - LSR - Pipe laying of PWFH (Total L=731m) and chamber/pit C11_6 d/w - 10h/d - With 62 2 04-Aug-22 18-Oct-22 01-Sep-22 15-Nov-22 24
HK Hols - No B/O periods
310.C.G4.J130 3310/11 - Area G4 - LSR - Airport System ductings (was
C11_6C3)
d/w - 10h/d - With 62 2 16-Aug-22 29-Oct-22 14-Sep-22 26-Nov-22 24
HK Hols - No B/O periods
310.C.G4.J157 3310/11 - Area G4 - LSR - complete CLP cable duct to achieve KD-04 (was
C01_7C3)
d/w - 10h/d - No HK 0 18-Aug-22 19-Mar-23 213
Hols - No B/O periods (was
310.C.G4.J136 3310/11 - Area G4 - LSR - Road Drainage C1)
C11_6 d/w - 10h/d - With 62 2 21-Nov-22 06-Feb-23 28-Nov-22 13-Feb-23 6
HK Hols - No B/O periods
CC#4.10 - 3310/11 - Area G4 - Landside Road Roadwork (was
C11_6C3)
d/w - 10h/d - With HK Hols
143- No B/O11
periods (was
10-Jan-23
C3) 07-Jul-23 17-Jan-23 13-May-24 253
310.C.RD.J336 3310/11 - Area G4 - LSR - Lay kerb, sub-base + base course [540mL @15m/d/wf; 2wf] C11_6 d/w - 10h/d - With 36 3 10-Jan-23 23-Feb-23 17-Jan-23 02-Mar-23 6
HK Hols - No B/O periods
310.C.RD.J340 3310/11 - Area G4 - LSR - Lay flexible pavement [540mL @80m/6d/wf; 1wf] (was
C11_6C3)
d/w - 10h/d - With 45 4 17-Feb-23 14-Apr-23 22-Dec-23 17-Feb-24 253
HK Hols - No B/O periods
310.C.RD.J352 3310/11 - Area G4 - LSR - install street lighting, road furniture (was
C11_6C3)
d/w - 10h/d - With 52 2 15-Apr-23 16-Jun-23 19-Feb-24 23-Apr-24 253
HK Hols - No B/O periods
310.C.RD.J356 3310/11 - Area G4 - LSR - wearing course & road marking (was
C11_6C3)
d/w - 10h/d - With 16 2 17-Jun-23 07-Jul-23 24-Apr-24 13-May-24 253
HK Hols - No B/O periods
CC#4.10 - 3310/11 - Area G4 - Airside Road Roadwork (was
C11_6C3)
d/w - 10h/d - With HK Hols
143- No B/O11
periods (was
13-Feb-23
C3) 07-Aug-23 20-Feb-23 01-Jun-24 243
310.C.RD.J308 3310/11 - Area G4 - ASR - Lay kerb, sub-base + base course [540mL @15m/d/wf; 2wf] C11_6 d/w - 10h/d - With 36 3 13-Feb-23 25-Mar-23 20-Feb-23 01-Apr-23 6
HK Hols - No B/O periods
310.C.RD.J348 3310/11 - Area G4 - ASR - Lay flexible pavement [540mL @80m/6d/wf; 1wf] (was
C11_6C3)
d/w - 10h/d - With 45 4 27-Mar-23 23-May-23 03-Apr-23 31-May-23 6
HK Hols - No B/O periods
310.C.RD.J360 3310/11 - Area G4 - ASR - install street lighting, road furniture (was
C11_6C3)
d/w - 10h/d - With 41 2 31-May-23 19-Jul-23 07-Jun-23 26-Jul-23 6
HK Hols - No B/O periods
310.C.RD.J364 3310/11 - Area G4 - ASR - wearing course & road marking (was
C11_6C3)
d/w - 10h/d - With 16 2 20-Jul-23 07-Aug-23 14-May-24 01-Jun-24 243
HK Hols - No B/O periods
CC#4.11 - 3310/11 - Area G4 - Security Fencing (was
C11_6C3)
d/w - 10h/d - With HK Hols
105- No B/O 9periods (was
20-Jul-23
C3) 22-Nov-23 29-Dec-23 08-May-24 134
310.C.RD.J316 3310/11 - Area G4 - Security Fence - construct footing [650m @10m/7d/wf; 6wf] C11_6 d/w - 10h/d - With 78 3 20-Jul-23 20-Oct-23 29-Dec-23 05-Apr-24 134
HK Hols - No B/O periods
310.C.RD.J320 3310/11 - Area G4 - Security Fence - metal works (was
C11_6C3)
d/w - 10h/d - With 66 3 18-Aug-23 06-Nov-23 29-Jan-24 20-Apr-24 134
HK Hols - No B/O periods
310.C.RD.J324 3310/11 - Area G4 - Security Fence - install Security System (was
C11_6C3)
d/w - 10h/d - With 66 3 04-Sep-23 22-Nov-23 16-Feb-24 08-May-24 134
HK Hols - No B/O periods
CC#4.10 - 3310/11 - Area G4 - Central Reserve Pavement (was
C11_6C3)
d/w - 10h/d - With HK Hols
47- No B/O 4periods (was
21-Oct-23
C3) 15-Dec-23 15-Apr-24 01-Jun-24 134
310.C.RD.J328 3310/11 - Area G4 - Central Resv - lay sub-base [540mL @15m/d/wf; 2wf] C11_6 d/w - 10h/d - With 20 2 21-Oct-23 14-Nov-23 15-Apr-24 08-May-24 141
HK Hols - No B/O periods
310.C.RD.J332 3310/11 - Area G4 - Central Resv - lay verge [540mL @30m/d/wf] (was
C11_6C3)
d/w - 10h/d - With 20 2 23-Nov-23 15-Dec-23 09-May-24 01-Jun-24 134
HK Hols - No B/O periods
CC#4 - 3310/11 - Area G3 - Airside Road and Landside Road (was C3) 340 31 18-Nov-21 A 12-Dec-23 09-Dec-22 01-Jun-24 137
CC#4.1, 4.2, 4.4, 4.7 - 3310/11 - Area G3 - Underground Utilities under ASR & LSR 169 25 18-Nov-21 A 19-May-23 09-Dec-22 02-Nov-23 137
310.C.G3.J151 3310/11 - Area G3 - (under ASR & LSR) - GI for stormwater drain C01_7 d/w - 10h/d - No HK 7 18-Nov-21 A 20-Nov-21 A 09-Dec-22 09-Dec-22
Hols - No B/O periods (was
310.C.G3.J159 3310/11 - Area G3 - (under ASR & LSR) - confirm installation level with PM C1)
C01_7 d/w - 10h/d - No HK 14 24-Oct-22 06-Nov-22 09-Dec-22 22-Dec-22 46
Hols - No B/O periods (was
310.C.G3.J255 3310/11 - Area G3 - (under ASR & LSR) - Backfill up to form I.L. of SWD and CLP ducts C1)
C03_7 d/w - 10h/d - With 15 5 07-Nov-22 21-Nov-22 30-Dec-22 14-Jan-23 51
HK Hols - No B/O periods
310.C.G3.J252 3310/11 - Area G3 - (under ASR & LSR) - stormwater drain pipe [291mL @10m/d/wf; 2wf; C03_7 d/w - 10h/d - With 70 5 23-Nov-22 07-Feb-23 23-Dec-22 09-Mar-23 30
10MH @4d/no/wf; 3wf] Remaining HK Hols - No B/O periods
310.C.G3.J256 3310/11 - Area G3 - (under ASR & LSR) - 132kv CLP duct (L=284m) use 2 wf C03_7 d/w - 10h/d - With 60 1 13-Dec-22 17-Feb-23 15-Jan-23 19-Mar-23 30
HK Hols - No B/O periods

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 43 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.G3.J253 3310/11 - Area G3 - (under ASR & LSR) - Gas Main C03_7 d/w - 10h/d - With 70 5 17-Dec-22 03-Mar-23 08-Jun-23 18-Aug-23 159
HK Hols - No B/O periods
310.C.G3.J296 3310/11 - Area G3 - (under ASR & LSR) - Airport System ducting C11_6 d/w - 10h/d - With 70 3 17-Jan-23 15-Apr-23 08-Jul-23 27-Sep-23 137
HK Hols - No B/O periods
310.C.G3.J352 3310/11 - Area G3 - (under ASR & LSR) - Portable Water main for FS (was
C11_6C3)
d/w - 10h/d - With 70 3 06-Feb-23 03-May-23 25-Jul-23 16-Oct-23 137
HK Hols - No B/O periods
310.C.G3.J257 3310/11 - Area G3 - completion of CLP ducting to achieve KD-04 (was
C01_7C3)
d/w - 10h/d - No HK 0 17-Feb-23 19-Mar-23 30
Hols - No B/O periods (was
310.C.G3.J353 3310/11 - Area G3 - (under ASR & LSR) - Road Drainage C1)
C11_6 d/w - 10h/d - With 70 3 22-Feb-23 19-May-23 10-Aug-23 02-Nov-23 137
HK Hols - No B/O periods
CC#4.10 - 3310/11 - Area G3 - Landside Road Roadwork (was
C11_6C3)
d/w - 10h/d - With HK Hols
157- No B/O 4periods (was
20-May-23
C3) 25-Nov-23 03-Nov-23 16-May-24 137
310.C.G3.J260 3310/11 - Area G3 - LSR - Lay kerb & sub-base [270mL @15m/d/wf; 1wf] C11_6 d/w - 10h/d - With 20 2 20-May-23 13-Jun-23 03-Nov-23 25-Nov-23 137
HK Hols - No B/O periods
310.C.G3.J264 3310/11 - Area G3 - LSR - Lay flexible pavement [270m @80m/6d/wf; 1wf] (was
C11_6C3)
d/w - 10h/d - With 23 2 14-Jun-23 12-Jul-23 18-Jan-24 15-Feb-24 179
HK Hols - No B/O periods
310.C.RD.J148 3310/11 - Area G3 - LSR - install street lighting, road furniture (was
C11_6C3)
d/w - 10h/d - With 50 15-Aug-23 13-Oct-23 26-Feb-24 27-Apr-24 159
HK Hols - No B/O periods
310.C.RD.J152 3310/11 - Area G3 - LSR - wearing course & road marking (was
C11_6C3)
d/w - 10h/d - With 14 10-Nov-23 25-Nov-23 29-Apr-24 16-May-24 137
HK Hols - No B/O periods
CC#4.10 - 3310/11 - Area G3 - Airside Road Roadwork (was
C11_6C3)
d/w - 10h/d - With HK Hols
151- No B/O 2periods (was
14-Jun-23
C3) 12-Dec-23 27-Nov-23 01-Jun-24 137
310.C.G3.J268 3310/11 - Area G3 - ASR - Lay kerb, sub-base + base course [270mL @15m/d/wf; 1wf] C11_6 d/w - 10h/d - With 19 1 14-Jun-23 07-Jul-23 27-Nov-23 18-Dec-23 137
HK Hols - No B/O periods
310.C.G3.J272 3310/11 - Area G3 - ASR - Lay flexible pavement [270m @80m/6d/wf; 1wf (was
C11_6C3)
d/w - 10h/d - With 22 1 13-Jul-23 07-Aug-23 16-Feb-24 12-Mar-24 179
HK Hols - No B/O periods
310.C.RD.J156 3310/11 - Area G3 - ASR - install street lighting, road furniture (was
C11_6C3)
d/w - 10h/d - With 50 08-Aug-23 06-Oct-23 13-Mar-24 16-May-24 179
HK Hols - No B/O periods
310.C.RD.J160 3310/11 - Area G3 - ASR - wearing course & road marking (was
C11_6C3)
d/w - 10h/d - With 14 27-Nov-23 12-Dec-23 17-May-24 01-Jun-24 137
HK Hols - No B/O periods
CC#4.11 - 3310/11 - Area G3 - Security Fencing (was
C11_6C3)
d/w - 10h/d - With HK Hols
76- No B/O 0periods (was
08-Jul-23
C3) 06-Oct-23 19-Dec-23 21-Mar-24 137
310.C.G3.J276 3310/11 - Area G3 - Security Fence & Gate - construct footing [270m @10m/7d/wf; 4wf] C11_6 d/w - 10h/d - With 48 08-Jul-23 01-Sep-23 19-Dec-23 17-Feb-24 137
HK Hols - No B/O periods
310.C.G3.J280 3310/11 - Area G3 - Security Fence & Gate - metal works (was
C11_6C3)
d/w - 10h/d - With 48 25-Jul-23 18-Sep-23 08-Jan-24 05-Mar-24 137
HK Hols - No B/O periods
310.C.G3.J284 3310/11 - Area G3 - Security Fence & Gate - install Security System and provide power (was
C11_6C3)
d/w - 10h/d - With 48 10-Aug-23 06-Oct-23 24-Jan-24 21-Mar-24 137
HK Hols - No B/O periods
CC#4.10 - 3310/11 - Area G3 - Central Reserve Pavement (was
C11_6C3)
d/w - 10h/d - With HK Hols
48- No B/O 0periods (was
02-Sep-23
C3) 31-Oct-23 15-Apr-24 01-Jun-24 173
310.C.G3.J288 3310/11 - Area G3 - Central Reserve - lay sub-base [270mL @15m/d/wf; 2wf] C11_6 d/w - 10h/d - With 20 02-Sep-23 25-Sep-23 15-Apr-24 08-May-24 181
HK Hols - No B/O periods
310.C.G3.J292 3310/11 - Area G3 - Central Reserve - lay verge [270mL @30m/d/wf] (was
C11_6C3)
d/w - 10h/d - With 20 07-Oct-23 31-Oct-23 09-May-24 01-Jun-24 173
HK Hols - No B/O periods
CC#4 - Airfield UU, Drainage Works, Watermain (was C3) 718 8 07-Jun-21 A 02-Nov-23 27-Mar-22 31-Aug-24 247
Advance UU Works in relation to Interim Security Fence C11_6 d/w - 10h/d - With HK Hols
173- No B/O 0periods (was
31-Jan-22
C3) A 31-Aug-22 28-Mar-22 31-Aug-22 0
310.C.EX.U005.B01 Advance UU works for ISF 2RS (submissions/approvals/construction under NOTAM) C11_6 d/w - 10h/d - With 173 31-Jan-22 A 31-Aug-22 28-Mar-22 31-Aug-22 0
HK Hols - No B/O periods
Interface Work Area 3310/IA/1 (Airfield Drainage and UU Works) (was C3) 539 8 07-Jun-21 A 26-Mar-23 27-Mar-22 08-Aug-23 108
310.C.EX.U005 WA 3310/3 - Site Access (starting date) C01_7 d/w - 10h/d - No HK 0 07-Jun-21 A 15-Sep-22
Hols - No B/O periods (was
310.C.EX.U025 Apply Work Permit (All Interface Areas) C1)
C01_7 d/w - 10h/d - No HK 21 01-Sep-21 A 21-Sep-21 A 27-Mar-22 27-Mar-22
Hols - No B/O periods (was
310.C.EX.U009 --- Closure of Existing North Runway (Commission Date of Interim 2RS) --- C1)
C01_7 d/w - 10h/d - No HK 0 01-Sep-22 14-Sep-22 14
Hols - No B/O periods (was
C1)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 44 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.EX.U013 3310/3 - Carry Out Survey Check and UU Detection at Area 3310/3 + submit report to PM C11_6 d/w - 10h/d - With 12 01-Sep-22 15-Sep-22 15-Sep-22 28-Sep-22 11
HK Hols - No B/O periods
310.C.EX.U017 3310/3 - Carry Out Trial Pits (was
C11_6C3)
d/w - 10h/d - With 20 01-Sep-22 24-Sep-22 15-Sep-22 10-Oct-22 11
HK Hols - No B/O periods
310.C.EX.U021 WA 3310/5A - Site Access (wk 92) (was
C01_7C3)
d/w - 10h/d - No HK 0 06-Mar-23* 06-Mar-23 0
Hols - No B/O periods (was
3310/IA/1-1 C1) 133 0 26-Sep-22 08-Mar-23 11-Oct-22 30-Apr-23 42
Area 7 (Interim Security Fence) - Potable Watermain and FH C23_4d/w - NOTAM (M,W,Th,Su-01:30-07:30)
36 0 - No HK
24-Nov-22
Hols - With B/O
08-Mar-23
Periods & Flight06-Feb-23
Checks 30-Apr-23 18
310.C.EX.U378.B01 3310/IA/1-1 (Interim Fence) PWFH - Trench Excavation and PW pipe laying DN250 C23_4d/w - NOTAM 30 24-Nov-22 26-Feb-23 06-Feb-23 29-Mar-23 18
(L=182m - 82m, 50m, 50m) [NOTAM] (M,W,Th,Su-01:30-07:30) -
310.C.EX.U381.B01 3310/IA/1-1 (Interim Fence) PWFH - Connect to existing Potable Watermain + No HK Hols- -NOTAM
C23_4d/w With B/O 10 20-Feb-23 08-Mar-23 23-Mar-23 30-Apr-23 18
reinstatment work (NOTAM) (M,W,Th,Su-01:30-07:30) -
Drainage - Stormwater and /Oil Separation (SWD/OS) No HK d/w
C11_6 Hols- -10h/d
With B/O
- With HK Hols
40- No B/O 0periods (was
26-Sep-22
C3) 12-Nov-22 11-Oct-22 25-Nov-22 11
310.C.EX.U101 3310/IA/1-1 (SWD/OS) - Open-cut excavation + SW pipe laying (L=570m) @ 19m/d/wf; C11_6 d/w - 10h/d - With 15 26-Sep-22 14-Oct-22 11-Oct-22 27-Oct-22 11
use 2 wf HK Hols - No B/O periods
310.C.EX.U101.B02 3310/IA/1-1 (SWD/OS) -Concrete Surround of Existing Pipe; L:158m (was
C11_6C3)
d/w - 10h/d - With 15 26-Sep-22 14-Oct-22 09-Nov-22 25-Nov-22 36
HK Hols - No B/O periods
310.C.EX.U101.B2 3310/IA/1-1 (SWD/OS) - Abandon Existing SW and Modified to Suit Finish Ground Level (was
C11_6C3)
d/w - 10h/d - With 15 26-Sep-22 14-Oct-22 09-Nov-22 25-Nov-22 36
(FGL) HK Hols - No B/O periods
310.C.EX.U105 3310/IA/1-1 (SWD/OS) - Construction of MH (8 nos.) 15d/MH/wf; use 3 wf (was
C11_6C3)
d/w - 10h/d - With 40 26-Sep-22 12-Nov-22 11-Oct-22 25-Nov-22 11
HK Hols - No B/O periods
Watermains (Seawater/Potable Water and Fire Hydrant (SPWFH) (was
C11_6C3)
d/w - 10h/d - With HK Hols
70- No B/O 0periods (was
14-Nov-22
C3) 08-Feb-23 26-Nov-22 21-Feb-23 11
310.C.EX.U115 3310/IA/1-1 (PWFH) - Trench excavation + PWP Pipe Laying 779m) C11_6 d/w - 10h/d - With 30 14-Nov-22 17-Dec-22 26-Nov-22 31-Dec-22 11
HK Hols - No B/O periods
310.C.EX.U115.B02 3310/IA/1-1 (PWFH) -Sleeve PW Pipe (336m) (was
C11_6C3)
d/w - 10h/d - With 30 14-Nov-22 17-Dec-22 03-Dec-22 09-Jan-23 17
HK Hols - No B/O periods
310.C.EX.U119 3310/IA/1-1 (PWFH) - Chamber (20 nr) (was
C11_6C3)
d/w - 10h/d - With 60 25-Nov-22 08-Feb-23 08-Dec-22 21-Feb-23 11
HK Hols - No B/O periods
3310/IA/1-2 (was C3) 169 8 01-Sep-22 26-Mar-23 27-Sep-22 08-Aug-23 108
Area 8 (Interim Security Fence) - Stormwater C03_7 d/w - 10h/d - With HK Hols
68- No B/O 0periods 26-Sep-22 04-Dec-22 12-Nov-22 22-Dec-22 18
310.C.EX.U310.B01 Area 8 (Outside of Interim Sec. Fence) - Install marker board C03_7 d/w - 10h/d - With 1 26-Sep-22 26-Sep-22 12-Nov-22 12-Nov-22 45
HK Hols - No B/O periods
310.C.EX.U315 Area 8 (Outside of Interim Sec. Fence) - ELS & excavation + SW pipe laying (L=174m C03_7 d/w - 10h/d - With 30 26-Oct-22 24-Nov-22 13-Nov-22 12-Dec-22 18
@ 10m/d/team; 2 wf HK Hols - No B/O periods
310.C.EX.U322.B01 3310/IA/1-2 -(more than 51.5m away from AOA) Abandoned existing SWD and modified C03_7 d/w - 10h/d - With 26 05-Nov-22 30-Nov-22 27-Nov-22 22-Dec-22 22
MH HK Hols - No B/O periods
310.C.EX.U319 Area 8 (Outside of Interim Sec. Fence) - Construction of SW MH (5nos.) 15d/MH/wf ; use C03_7 d/w - 10h/d - With 30 05-Nov-22 04-Dec-22 23-Nov-22 22-Dec-22 18
3 wf HK Hols - No B/O periods
Area 8 (Interim Security Fence) - Potable Watermain and FH C23_4d/w - NOTAM (M,W,Th,Su-01:30-07:30)
51 0 - No HK
26-Oct-22
Hols - With B/O
26-Mar-23
Periods & Flight30-Nov-22
Checks 30-Apr-23 8
310.C.EX.U358.B01 Area 8 (Interim Sec. Fence) PWFH - Cary out existing UU survey, marker board C23_4d/w - NOTAM 2 26-Oct-22 27-Oct-22 30-Nov-22 01-Dec-22 8
(NOTAM) (M,W,Th,Su-01:30-07:30) -
310.C.EX.U309 Area 8 (Interim Sec. Fence) PWFH - Excavation and PW pipe laying DN250 x L=59m No HK Hols- -NOTAM
C23_4d/w With B/O 45 27-Nov-22 26-Mar-23 11-Dec-22 30-Apr-23 8
[NOTAM] (M,W,Th,Su-01:30-07:30) -
310.C.EX.U318 Area 8 (Interim Sec. Fence) PWFH - Watermains Chamber (6 nr) + connect & No HK Hols- -NOTAM
C23_4d/w With B/O 30 12-Jan-23 26-Mar-23 16-Feb-23 30-Apr-23 8
reinstatement works (NOTAM) (M,W,Th,Su-01:30-07:30) -
Drainage - Stormwater and /Oil Separation (SWD/OS) No HK d/w
C11_6 Hols- -10h/d
With B/O
- With HK Hols
75- No B/O 0periods (was
01-Sep-22
C3) 30-Nov-22 27-Sep-22 19-Dec-22 16
310.C.EX.U300.B01 3310/IA/1-2 -(Land Side) Open cut excavation for stormwater pipe laying and PWFH pipe C11_6 d/w - 10h/d - With 30 01-Sep-22 08-Oct-22 27-Sep-22 02-Nov-22 21
laying HK Hols - No B/O periods
310.C.EX.U300 3310/IA/1-2 -(Land Side) Pipe laying SW DN1500~1800 (L=501 m) (assume 10m/d for (was
C11_6C3)
d/w - 10h/d - With 45 26-Sep-22 18-Nov-22 17-Oct-22 07-Dec-22 16
pipe laying) HK Hols - No B/O periods
(was C3)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 45 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.EX.U312 3310/IA/1-2 - Stormwater Manhole (6 nr ) (assume 14d/MH, use 2 wf) + connect + test & C11_6 d/w - 10h/d - With 45 10-Oct-22 30-Nov-22 28-Oct-22 19-Dec-22 16
backfill HK Hols - No B/O periods
Watermains (Seawater/Potable Water and Fire Hydrant (SPWFH) (was
C11_6C3)
d/w - 10h/d - With HK Hols
75- No B/O 8periods (was
01-Sep-22
C3) 30-Nov-22 27-Sep-22 24-Dec-22 21
310.C.EX.U303 310/IA/1-2 (Land Side)- Trench Excavation + PWFH pipe laying DN250 x L= 370 m) C11_6 d/w - 10h/d - With 65 4 01-Sep-22 18-Nov-22 27-Sep-22 13-Dec-22 21
HK Hols - No B/O periods
310.C.EX.U306 3310/IA/1-2 (Land Side) - Construction of Watermains Chamber (10 nr) + Connect to (was
C11_6C3)
d/w - 10h/d - With 45 4 10-Oct-22 30-Nov-22 03-Nov-22 24-Dec-22 21
existing PWFH HK Hols - No B/O periods
Power System (was
C11_6C3)
d/w - 10h/d - With HK Hols
45- No B/O 0periods (was
10-Oct-22
C3) 01-Dec-22 03-Nov-22 08-Aug-23 202
310.C.EX.U322 3310/IA/1-2 - Above Ground Cable Duct + Pillar Box (3 nr) C11_6 d/w - 10h/d - With 45 10-Oct-22 30-Nov-22 03-Nov-22 24-Dec-22 21
HK Hols - No B/O periods
310.C.EX.U326 3310/IA/1-2 - Allow Contract <3802> Access at WA 3310/3 to remove existing seawall (was
C11_6C3)
d/w - 10h/d - With 0 01-Dec-22 08-Aug-23 202
HK Hols - No B/O periods
Interface Work Area 3310/IA/6 (Airfield Drainage and UU Works) (was C3) 567 0 07-Jun-21 A 03-May-23 18-Sep-22 03-May-23 0
310.C.EX.U634 WA 3310/4 - Site Access (starting date) C01_7 d/w - 10h/d - No HK 0 07-Jun-21 A 19-Sep-22
Hols - No B/O periods (was
310.C.EX.U638 --- Closure of Existing North Runway (Commission Date of Interim 2RS) for Works at WA C1)
C01_7 d/w - 10h/d - No HK 0 01-Sep-22 18-Sep-22 18
3310/4 Hols - No B/O periods (was
310.C.EX.U642 3310/4 - Carry Out Survey Check and UU Detection at Area 3310/3 + submit report to PM C1)
C11_6 d/w - 10h/d - With 12 01-Sep-22 15-Sep-22 19-Sep-22 03-Oct-22 14
HK Hols - No B/O periods
310.C.EX.U646 3310/4 - Carry Out Trial Pits (was
C11_6C3)
d/w - 10h/d - With 20 01-Sep-22 24-Sep-22 19-Sep-22 13-Oct-22 14
HK Hols - No B/O periods
3310/IA/6-2 (Airfield UU) (was C3) 170 0 01-Sep-22 27-Mar-23 14-Oct-22 17-Apr-23 14
Drainage - Stormwater and /Oil Separation (SWD/OS) C11_6 d/w - 10h/d - With HK Hols
75- No B/O 0periods (was
26-Sep-22
C3) 23-Dec-22 31-Oct-22 27-Feb-23 51
310.C.EX.U560.B02 3310/6-2 (South of Runway) -Concrete Surround of Existing Pipe; L:106m C11_6 d/w - 10h/d - With 15 26-Sep-22 14-Oct-22 30-Dec-22 17-Jan-23 79
HK Hols - No B/O periods
310.C.EX.U542 3310/6-2 (North of Runway) - Open-cut excavation for SWD pipe laying DN 1050~1950 (was
C11_6C3)
d/w - 10h/d - With 56 26-Sep-22 01-Dec-22 31-Oct-22 05-Jan-23 28
(635 m) @ 10m/d/wf; 2 wf HK Hols - No B/O periods
310.C.EX.U560 3310/6-2 (South of Runway) - Excavation & SWD Pipe laying (1293 m) + Abandon/Modify (was
C11_6C3)
d/w - 10h/d - With 65 26-Sep-22 12-Dec-22 26-Nov-22 15-Feb-23 51
Ex. SWD @ 10m/d/team; 2 team HK Hols - No B/O periods
310.C.EX.U546 3310/6-2 (North of Runway) - SWD DN1050~1950 (L=635M @ 10m/d/wf) + construction (wasC11_6C3)
d/w - 10h/d - With 56 10-Oct-22 13-Dec-22 11-Nov-22 17-Jan-23 28
of SW MH (8 nr ) @ 14d/MH/wf; 2 wf HK Hols - No B/O periods
310.C.EX.U564 3310/6-2 ( South of Runway) - Stormwater/OS Manhole + Abandon/Modify Existing MH (was
C11_6C3)
d/w - 10h/d - With 65 10-Oct-22 23-Dec-22 08-Dec-22 27-Feb-23 51
(14 nr ) @ 14d/MH/team; 3 wf HK Hols - No B/O periods
Area 2a (Outside Interim Security Fence) - Potable Water and Fire Hydrant (PWFH) (was C3) 82 0 01-Sep-22 08-Dec-22 08-Nov-22 15-Jan-23 30
310.C.EX.U582.B01 3310/IA/6-2 (Area 2a & 2b) - Apply Work Permit C01_7 d/w - 10h/d - No HK 21 01-Sep-22 21-Sep-22 08-Nov-22 28-Nov-22 68
Hols - No B/O periods (was
310.C.EX.U584.B01 3310/IA/6-2 (Area 2a) - Install hoarding/marker board C1)
C03_7 d/w - 10h/d - With 1 22-Sep-22 22-Sep-22 29-Nov-22 29-Nov-22 66
HK Hols - No B/O periods
310.C.EX.U580.B01 3310/IA/6-2 (Area 2a) - Trial Pit / UU Survey C03_7 d/w - 10h/d - With 4 26-Oct-22 29-Oct-22 30-Nov-22 03-Dec-22 35
HK Hols - No B/O periods
310.C.EX.U606 3310/IA/6-2 (Area 2a) - Construct PWPH pit/chamber (4 nos); 4 wf C03_7 d/w - 10h/d - With 28 30-Oct-22 26-Nov-22 04-Dec-22 03-Jan-23 35
HK Hols - No B/O periods
310.C.EX.U604 3310/IA/6-2 (Area 2a) - Open-cut excavation and PW pipe laying L=400m [assume 4wks C03_7 d/w - 10h/d - With 28 30-Oct-22 26-Nov-22 04-Dec-22 03-Jan-23 35
full closure] HK Hols - No B/O periods
310.C.EX.U738.B01 3310/IA/6-2 (Area 2a) - Connect to existing potable water line C03_7 d/w - 10h/d - With 2 27-Nov-22 28-Nov-22 04-Jan-23 05-Jan-23 35
HK Hols - No B/O periods
310.C.EX.U742.B01 3310/IA/6-2 (Area 2a) - Backfill and reinstatement works C03_7 d/w - 10h/d - With 10 29-Nov-22 08-Dec-22 06-Jan-23 15-Jan-23 35
HK Hols - No B/O periods
Area 2b (Outside Interim Security Fence) - Potable Water and Fire Hydrant (PWFH) C03_7 d/w - 10h/d - With HK Hols
45- No B/O 0periods 09-Dec-22 29-Jan-23 16-Jan-23 05-Mar-23 35
310.C.EX.U590.B01 3310/IA/6-2 (Area 2b) - Install hoarding/marker board C03_7 d/w - 10h/d - With 1 09-Dec-22 09-Dec-22 16-Jan-23 16-Jan-23 35
HK Hols - No B/O periods

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 46 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.EX.U595.B01 3310/IA/6-2 (Area 2b) - Trial Pit / UU Survey C03_7 d/w - 10h/d - With 4 10-Dec-22 13-Dec-22 17-Jan-23 20-Jan-23 35
HK Hols - No B/O periods
310.C.EX.U600.B01 3310/IA/6-2 (Area 2b) - Construct PWPH pit/chamber (5 nos); 4 wf C03_7 d/w - 10h/d - With 28 14-Dec-22 13-Jan-23 21-Jan-23 21-Feb-23 35
HK Hols - No B/O periods
310.C.EX.U605.B01 3310/IA/6-2 (Area 2b) - Open-cut excavation and PW pipe laying L=300m [assume 4wks C03_7 d/w - 10h/d - With 28 14-Dec-22 13-Jan-23 21-Jan-23 21-Feb-23 35
full closure] HK Hols - No B/O periods
310.C.EX.U610.B01 3310/IA/6-2 (Area 2b) - Connect to existing potable water line C03_7 d/w - 10h/d - With 2 14-Jan-23 15-Jan-23 22-Feb-23 23-Feb-23 35
HK Hols - No B/O periods
310.C.EX.U615.B01 3310/IA/6-2 (Area 2b) - Backfill and reinstatement works C03_7 d/w - 10h/d - With 10 16-Jan-23 29-Jan-23 24-Feb-23 05-Mar-23 35
HK Hols - No B/O periods
Area 2a (Inside Interim Security Fence) - Potable Water and Fire Hydrant (PWFH) C11_6 d/w - 10h/d - With HK Hols
80- No B/O 0periods (was
26-Sep-22
C3) 30-Dec-22 14-Oct-22 27-Feb-23 46
310.C.EX.U601 3310/IA/6-2 (North of Runway) - Construction of PWFH Chamber (8 nr) C11_6 d/w - 10h/d - With 80 26-Sep-22 30-Dec-22 21-Nov-22 27-Feb-23 46
10d/chamber/team; use 1 team HK Hols - No B/O periods
310.C.EX.U599 3310/IA/6-2 (North of Runway) - Trench excavation + PWFH Pipe Laying (700 m) (was
C11_6C3)
d/w - 10h/d - With 80 26-Sep-22 30-Dec-22 14-Oct-22 17-Jan-23 14
HK Hols - No B/O periods
Comms/Power Ducting (was C3) 101 0 24-Nov-22 27-Mar-23 18-Jan-23 17-Apr-23 14
310.C.EX.U633 3310/6-2 (Ducting/Sleeving-Outside Interim Fence) - Modify Comms/Power Cable C23_4d/w - NOTAM 0 24-Nov-22 24-Nov-22 02-Apr-23 02-Apr-23 50
Manhole & Drawpit Modify: 7 nos) [NOTAM] (M,W,Th,Su-01:30-07:30) -
310.C.EX.U625 3310/6-2 (Ducting/Sleeving) - Comms/Power Ducting Laying (288 m) @3310/IA/6-2 No HK d/w
C11_6 Hols- -10h/d
With B/O
- With 60 31-Dec-22 15-Mar-23 18-Jan-23 31-Mar-23 14
HK Hols - No B/O periods
310.C.EX.U629 3310/6-2 (Ducting/Sleeving) - Comms/Power Cable Manhole & Drawpit (new: 6 nr), (was
C11_6C3)
d/w - 10h/d - With 60 13-Jan-23 27-Mar-23 02-Feb-23 17-Apr-23 14
Modify: 46 nos) HK Hols - No B/O periods
3310/IA/6-1 (was C3) 54 0 24-Feb-23 03-May-23 24-Feb-23 03-May-23 0
310.C.EX.U539 Commence Underground Works at Area 3310/IA/6-1 (Upon Completion of Backfilling to C01_7 d/w - 10h/d - No HK 0 24-Feb-23 24-Feb-23 0
pipe formation) Hols - No B/O periods (was
Drainage - Stormwater and /Oil Separation (SWD/OS) C1)
C11_6 d/w - 10h/d - With HK Hols
30- No B/O 0periods (was
24-Feb-23
C3) 30-Mar-23 24-Feb-23 30-Mar-23 0
310.C.EX.U537 3310/IA/6-1 - Open-cut excavation + Manhole (20 nr ) C11_6 d/w - 10h/d - With 30 24-Feb-23 30-Mar-23 24-Feb-23 30-Mar-23 0
HK Hols - No B/O periods
310.C.EX.U535 3310/IA/6-1 - Stormwater/OS Pipe; L:761m (was
C11_6C3)
d/w - 10h/d - With 30 24-Feb-23 30-Mar-23 24-Feb-23 30-Mar-23 0
HK Hols - No B/O periods
Watermains (Seawater/Potable Water and Fire Hydrant (SPWFH) (was
C11_6C3)
d/w - 10h/d - With HK Hols
54- No B/O 0periods (was
24-Feb-23
C3) 03-May-23 24-Feb-23 03-May-23 0
310.C.EX.U591 3310/IA/6-1 - PWFH Chamber (27 nr) @ 10d/chamber/team; use 4 teams C11_6 d/w - 10h/d - With 54 24-Feb-23 03-May-23 24-Feb-23 03-May-23 0
HK Hols - No B/O periods
310.C.EX.U587 3310/IA/6-1 - Open cut excavation + PWFH Pipe Laying (920 m) (was
C11_6C3)
d/w - 10h/d - With 54 24-Feb-23 03-May-23 24-Feb-23 03-May-23 0
HK Hols - No B/O periods
Interface Work Area 3310/IA/4 (Airfield Drainage and UU Works) (was C3) 548 0 07-Jun-21 A 06-Apr-23 04-Jul-22 08-Jul-23 73
310.C.EX.U694 WA 3310/3 - Site Access (starting date) at Interface WA 3310/IA/4 C11_6 d/w - 10h/d - With 0 07-Jun-21 A 18-Jan-23
HK Hols - No B/O periods
310.C.EX.U706 WA 3310/8 - Site Access (starting date) at Interface WA 3310/IA/4 (was
C11_6C3)
d/w - 10h/d - With 0 07-Jun-21 A 15-Dec-22
HK Hols - No B/O periods
310.C.EX.U718 WA 3310/8B - Site Access (wk 40) at Interface WA 3310/IA/4 (was
C11_6C3)
d/w - 10h/d - With 0 28-Mar-22* 15-Dec-22 215
HK Hols - No B/O periods
310.C.EX.U714 WA 3310/8A - Site Access (wk 57) at Interface WA 3310/IA/4 (was
C11_6C3)
d/w - 10h/d - With 0 04-Jul-22* 04-Jul-22 0
HK Hols - No B/O periods
310.C.EX.U700 *** Start Works (After Completion of Interim Security Fence) **** (was
C11_6C3)
d/w - 10h/d - With 0 26-Oct-22 15-Dec-22 43
HK Hols - No B/O periods
310.C.EX.U698 3310/8, 8A, 8B - Carry Out Survey Check and UU Detection + submit report to PM (was
C11_6C3)
d/w - 10h/d - With 21 26-Oct-22 18-Nov-22 15-Dec-22 10-Jan-23 43
HK Hols - No B/O periods
310.C.EX.U702 3310/8, 8A, 8B - Carry Out Trial Pits (was
C11_6C3)
d/w - 10h/d - With 20 27-Oct-22 18-Nov-22 16-Dec-22 10-Jan-23 43
HK Hols - No B/O periods
3310/IA/4-1 (was
C11_6C3)
d/w - 10h/d - With HK Hols
134- No B/O 0periods (was
26-Oct-22
C3) 06-Apr-23 21-Jan-23 08-Jul-23 73

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 47 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
Area 4 - 3310/IA/4-1 Potable Water at Interim Security Fence C11_6 d/w - 10h/d - With HK Hols
62- No B/O 0periods (was
26-Oct-22
C3) 07-Jan-23 17-Feb-23 06-Jul-23 143
310.C.EX.U500 Area 4 (PWFH) - Open-cut Excavation and Watermains Pipe Laying L=146m C11_6 d/w - 10h/d - With 38 26-Oct-22 08-Dec-22 17-Feb-23 01-Apr-23 93
HK Hols - No B/O periods
310.C.EX.U504 Area 4 (PWFH) - ELS + Construction of Watermains Chamber + connect to existing (was
C11_6C3)
d/w - 10h/d - With 38 11-Nov-22 24-Dec-22 09-May-23 23-Jun-23 143
watermain HK Hols - No B/O periods
310.C.EX.U504.B01 Area 4 (PWFH) - Backfill and reinstatement work (was
C11_6C3)
d/w - 10h/d - With 10 27-Dec-22 07-Jan-23 24-Jun-23 06-Jul-23 143
HK Hols - No B/O periods
Drainage (Stormwater and Oil Separation) (SW/OS) (was
C11_6C3)
d/w - 10h/d - With HK Hols
114- No B/O 0periods (was
26-Oct-22
C3) 13-Mar-23 21-Jan-23 08-Jul-23 93
310.C.EX.U452 Area 4 (Stormwater) - Open-cut excavation + Stormwater Pipe laying (L=472m) C11_6 d/w - 10h/d - With 38 26-Oct-22 08-Dec-22 21-Jan-23 09-Mar-23 73
HK Hols - No B/O periods
310.C.EX.U452.B01 Area 5 (Stormwater) - Open-cut excavation + Stormwater Pipe laying (L=120m) (was
C11_6C3)
d/w - 10h/d - With 20 09-Dec-22 03-Jan-23 10-Mar-23 01-Apr-23 73
HK Hols - No B/O periods
310.C.EX.U464 Area 4 (Stormwater) - Construct Stormwater Manhole (3 nr) + connect to existing (was
C11_6C3)
d/w - 10h/d - With 38 09-Dec-22 27-Jan-23 03-Apr-23 22-May-23 93
HK Hols - No B/O periods
310.C.EX.U464.B01 Area 5 (Stormwater) - Construct Stormwater Manhole (2 nr) + connect to existing (was
C11_6C3)
d/w - 10h/d - With 38 28-Jan-23 13-Mar-23 23-May-23 08-Jul-23 93
HK Hols - No B/O periods
Area 5 - Watermains (Seawater/Potable Water and Fire Hydrant (SPWFH) (was
C11_6C3)
d/w - 10h/d - With HK Hols
76- No B/O 0periods (was
04-Jan-23
C3) 06-Apr-23 03-Apr-23 08-Jul-23 73
310.C.EX.U508 3310/IA/4-1 (PWFH) - ELS + Watermains Pipe Laying (364m) C11_6 d/w - 10h/d - With 38 04-Jan-23 20-Feb-23 03-Apr-23 22-May-23 73
HK Hols - No B/O periods
310.C.EX.U512 3310/IA/4-1 (PWFH) - Construction Watermains Chamber 6 nr) (was
C11_6C3)
d/w - 10h/d - With 38 21-Feb-23 06-Apr-23 23-May-23 08-Jul-23 73
HK Hols - No B/O periods
3310/IA/4-3 (was
C11_6C3)
d/w - 10h/d - With HK Hols
131- No B/O 0periods (was
10-Oct-22
C3) 16-Mar-23 18-Jan-23 12-Jun-23 69
Drainage - Stormwater and /Oil Separation (SWD/OS) C11_6 d/w - 10h/d - With HK Hols
94- No B/O 0periods (was
10-Oct-22
C3) 01-Feb-23 18-Jan-23 31-May-23 96
310.C.EX.U460 3310/IA/4-3 (SW/OS) - Stormwater/OS Manhole (5 nr ) @ 14d/MH/team; use 1 team C11_6 d/w - 10h/d - With 94 10-Oct-22 01-Feb-23 04-Feb-23 31-May-23 96
HK Hols - No B/O periods
310.C.EX.U456 3310/IA/4-3 (SW/OS) - Open-cut excavation + Stormwater/OS Pipe (489 m @ 10m/d; 1 (was
C11_6C3)
d/w - 10h/d - With 49 19-Nov-22 17-Jan-23 18-Jan-23 18-Mar-23 49
team) HK Hols - No B/O periods
Area 6 - Watermains (Seawater/Potable Water and Fire Hydrant (SPWFH) (was
C11_6C3)
d/w - 10h/d - With HK Hols
96- No B/O 0periods (was
19-Nov-22
C3) 16-Mar-23 14-Feb-23 12-Jun-23 69
310.C.EX.U491 3310/IA/4-3 (PWFH) - Open cut excavation + Watermains Pipe Laying (701 m) C11_6 d/w - 10h/d - With 70 19-Nov-22 14-Feb-23 14-Feb-23 11-May-23 69
HK Hols - No B/O periods
310.C.EX.U496 3310/IA/4-3 (PWFH) - Watermains Chamber (12 nr) (was
C11_6C3)
d/w - 10h/d - With 96 19-Nov-22 16-Mar-23 14-Feb-23 12-Jun-23 69
HK Hols - No B/O periods
3310/IA/4-2 (was C3) 122 0 26-Oct-22 23-Mar-23 10-Jan-23 31-May-23 53
310.C.EX.U722 *** After Completion of Interim Security Fence **** C11_6 d/w - 10h/d - With 0 26-Oct-22 10-Jan-23 64
HK Hols - No B/O periods
Drainage - Stormwater and /Oil Separation (SWD/OS) (was C3) - NOTAM (M,W,Th,Su-01:30-07:30)
C23_4d/w 45 0 - No HK
24-Nov-22
Hols - With B/O
23-Mar-23
Periods & Flight11-Jan-23
Checks 31-May-23 15
310.C.EX.U454 3310/IA/4-1 SW/OS) - Existing Stormwater/OS Modification (84) @ Taxiway T [NOTAM] C23_4d/w - NOTAM 15 24-Nov-22 09-Jan-23 11-Jan-23 26-Feb-23 15
(M,W,Th,Su-01:30-07:30) -
310.C.EX.U457 3310/IA/4-1 SW/OS) - Existing Stormwater/OS Modification (84) @ Taxiway B6 [NOTAM] No HK Hols- -NOTAM
C23_4d/w With B/O 15 11-Jan-23 26-Feb-23 27-Feb-23 23-Mar-23 15
(M,W,Th,Su-01:30-07:30) -
310.C.EX.U726 3310/IA/4-1 SW/OS) - Existing Stormwater/OS Modification (89m) @ Taxiway A [NOTAM] No HK Hols- -NOTAM
C23_4d/w With B/O 15 27-Feb-23 23-Mar-23 26-Mar-23 31-May-23 15
(M,W,Th,Su-01:30-07:30) -
Interface Work Area 3310/IA/2 (Airfield Drainage and UU Works) No HK Hols - With B/O 648 0 07-Jun-21 A 09-Aug-23 05-Sep-22 05-Oct-23 47
310.C.EX.U650 WA 3310/6 - Site Access (starting date) C01_7 d/w - 10h/d - No HK 0 07-Jun-21 A 13-Jan-23
Hols - No B/O periods (was
310.C.EX.U666 WA 3310/6A - Site Access (wk 18) C1)
C11_6 d/w - 10h/d - With 0 04-Oct-21 A 03-Jun-23
HK Hols - No B/O periods
310.C.EX.U654 --- Closure of Existing North Runway (Commission Date of Interim 2RS) for Works at WA (was
C01_7C3)
d/w - 10h/d - No HK 0 01-Sep-22 13-Jan-23 135
3310/6 and 6A Hols - No B/O periods (was
310.C.EX.U670 WA 3310/7 - Site Access (wk 66) C1)
C11_6 d/w - 10h/d - With 0 05-Sep-22* 05-Sep-22 0
HK Hols - No B/O periods
(was C3)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 48 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.EX.U674 WA 3310/5 - Site Access (wk 83) C11_6 d/w - 10h/d - With 0 03-Jan-23* 03-Jan-23 0
HK Hols - No B/O periods
310.C.EX.U658 3310/5 - Carry Out Survey Check and UU Detection at Area 3310/3 + submit report to PM (was
C11_6C3)
d/w - 10h/d - With 21 03-Jan-23 30-Jan-23 03-Jun-23 28-Jun-23 121
HK Hols - No B/O periods
310.C.EX.U662 3310/5 - Carry Out Trial Pits (was
C11_6C3)
d/w - 10h/d - With 20 04-Jan-23 30-Jan-23 05-Jun-23 28-Jun-23 121
HK Hols - No B/O periods
3310/IA/2-2 (was
C11_6C3)
d/w - 10h/d - With HK Hols
65- No B/O 0periods (was
23-May-23
C3) 09-Aug-23 28-Jun-23 05-Oct-23 47
310.C.EX.U690 BC 5, 6, 19 Stage 1,2,3,4(3310/6 Area) Backfill drainge swale completed C11_6 d/w - 10h/d - With 0 27-Jun-23 28-Jun-23 1
HK Hols - No B/O periods
310.C.EX.U682 BC 5, 6, 19 Stage 5(3310/5 Area) Backfill drainge swale completed (was
C11_6C3)
d/w - 10h/d - With 0 07-Aug-23 08-Aug-23 2
HK Hols - No B/O periods
Drainage - Stormwater and /Oil Separation (SWD/OS) (was
C11_6C3)
d/w - 10h/d - With HK Hols
26- No B/O 0periods (was
28-Jun-23
C3) 28-Jul-23 29-Jun-23 10-Aug-23 11
310.C.EX.U366 3310/IA/2-2 (SW/OS) - Open-cut excavation + pipe laying of SWD/OS (31 m), MH (1 nr) + C11_6 d/w - 10h/d - With 16 28-Jun-23 17-Jul-23 29-Jun-23 18-Jul-23 1
connect to existing stormwater HK Hols - No B/O periods
310.C.EX.U366.B02 3310/IA/2-2 (SWD/OS) -Concrete Surround of Existing Pipe; L:164m (was
C11_6C3)
d/w - 10h/d - With 16 28-Jun-23 17-Jul-23 29-Jun-23 18-Jul-23 1
HK Hols - No B/O periods
310.C.EX.U366.B01 3310/IA/2-2 (SWD/OS) - Abandon Existing SW and Modified to Suit Finish Ground Level (was
C11_6C3)
d/w - 10h/d - With 26 28-Jun-23 28-Jul-23 12-Jul-23 10-Aug-23 11
(FGL) HK Hols - No B/O periods
Watermains (Seawater/Potable Water and Fire Hydrant (SPWFH) (was
C11_6C3)
d/w - 10h/d - With HK Hols
54- No B/O 0periods (was
23-May-23
C3) 27-Jul-23 29-Jun-23 31-Aug-23 30
310.C.EX.U378 3310/IA/2-2 (PWFH) - Watermains Chamber (9 nr) @ 12d/chamber/team; use 2 team C11_6 d/w - 10h/d - With 54 23-May-23 27-Jul-23 29-Jun-23 31-Aug-23 30
HK Hols - No B/O periods
310.C.EX.U373 3310/IA/2-2 (PWFH) - Open cut excavation + Watermains Pipe Laying (513 m) (was
C11_6C3)
d/w - 10h/d - With 54 23-May-23 27-Jul-23 29-Jun-23 31-Aug-23 30
HK Hols - No B/O periods
Comms/Power Ducting (was
C11_6C3)
d/w - 10h/d - With HK Hols
36- No B/O 0periods (was
28-Jun-23
C3) 09-Aug-23 23-Aug-23 05-Oct-23 47
310.C.EX.U372 Comms/Power Cable Drawpit (8 nr) C11_6 d/w - 10h/d - With 32 28-Jun-23 04-Aug-23 23-Aug-23 28-Sep-23 47
HK Hols - No B/O periods
310.C.EX.U375 Comms/Power Ducting Laying (392 m) (was
C11_6C3)
d/w - 10h/d - With 36 28-Jun-23 09-Aug-23 23-Aug-23 05-Oct-23 47
HK Hols - No B/O periods
3310/IA/2-1 (was
C11_6C3)
d/w - 10h/d - With HK Hols
84- No B/O 0periods (was
03-Jan-23
C3) 19-Apr-23 20-May-23 30-Aug-23 110
310.C.EX.U678 *** Completion of Box Culvert and Backfill to +6.5mPD at 3310/7 *** C11_6 d/w - 10h/d - With 0 03-Jan-23 20-May-23 110
HK Hols - No B/O periods
Drainage - Stormwater and /Oil Separation (SWD/OS) (was
C11_6C3)
d/w - 10h/d - With HK Hols
50- No B/O 0periods (was
04-Jan-23
C3) 06-Mar-23 22-May-23 21-Jul-23 110
310.C.EX.U342 3310/IA/2-1 -Open cut excavation + Stormwater/OS Pipe (765m @ 10m/d/team ; 2 teams C11_6 d/w - 10h/d - With 50 04-Jan-23 06-Mar-23 22-May-23 21-Jul-23 110
) + connect to existing HK Hols - No B/O periods
310.C.EX.U345 3310/IA/2-1 - Stormwater/OS Manholes (7nos) @ 14d/MH/team; use 2 teams (was
C11_6C3)
d/w - 10h/d - With 50 04-Jan-23 06-Mar-23 22-May-23 21-Jul-23 110
HK Hols - No B/O periods
Watermains (Seawater/Potable Water and Fire Hydrant (SPWFH) (was
C11_6C3)
d/w - 10h/d - With HK Hols
69- No B/O 0periods (was
21-Jan-23
C3) 19-Apr-23 09-Jun-23 30-Aug-23 110
310.C.EX.U321 3310/IA/2-1 - Watermains Chamber (23 nr) @ 12d/chamber/team; use 4 teams C11_6 d/w - 10h/d - With 69 21-Jan-23 19-Apr-23 09-Jun-23 30-Aug-23 110
HK Hols - No B/O periods
310.C.EX.U317 3310/IA/2-1 - Open cut excavation + Watermains Pipe Laying (1135 m) (was
C11_6C3)
d/w - 10h/d - With 69 21-Jan-23 19-Apr-23 09-Jun-23 30-Aug-23 110
HK Hols - No B/O periods
Interface Work Area 3310/IA/3 (Airfield Drainage and UU Works) (was C3) 476 0 28-Mar-22 02-Nov-23 18-Jan-23 31-Aug-24 247
3310/IA/3-2 C11_6 d/w - 10h/d - With HK Hols
46- No B/O 0periods (was
07-Sep-23
C3) 02-Nov-23 11-Sep-23 06-Nov-23 3
Drainage - Stormwater and /Oil Separation (SWD/OS) C11_6 d/w - 10h/d - With HK Hols
41- No B/O 0periods (was
07-Sep-23
C3) 27-Oct-23 11-Sep-23 31-Oct-23 3
310.C.EX.U357 3310/IA/3-2a (SW/OS) - Open-cut excavation + Stormwater/OS Pipe (357 m @10m/d; use C11_6 d/w - 10h/d - With 36 07-Sep-23 20-Oct-23 11-Sep-23 25-Oct-23 3
1 team) HK Hols - No B/O periods
310.C.EX.U354 3310/IA/3-2a (SW/OS) - Stormwater/OS Manhole (7 nr ) (was
C11_6C3)
d/w - 10h/d - With 36 13-Sep-23 27-Oct-23 16-Sep-23 31-Oct-23 3
HK Hols - No B/O periods
Watermains (Seawater/Potable Water and Fire Hydrant (SPWFH) (was
C11_6C3)
d/w - 10h/d - With HK Hols
29- No B/O 0periods (was
27-Sep-23
C3) 02-Nov-23 03-Oct-23 06-Nov-23 3
310.C.EX.U388 3310/IA/3-2a (PWFH) - Open-cut excavation + Watermains Pipe Laying (360 m) C11_6 d/w - 10h/d - With 24 27-Sep-23 27-Oct-23 03-Oct-23 31-Oct-23 3
@3310/IA/3-2a HK Hols - No B/O periods
(was C3)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 49 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.EX.U390 3310/IA/3-2a (PWFH) - Watermains Chamber (6 nr) @3310/IA/3-2a C11_6 d/w - 10h/d - With 24 05-Oct-23 02-Nov-23 09-Oct-23 06-Nov-23 3
HK Hols - No B/O periods
3310/IA/3-1 (was C3) 144 0 18-Nov-22 17-May-23 18-Jan-23 17-Jul-23 49
Drainage - Stormwater and /Oil Separation (SWD/OS) 64 0 18-Nov-22 07-Feb-23 18-Jan-23 06-Apr-23 49
310.C.FA.U370 Allow Access to Contract <3408> for Interface Work Area 3310/IA/2 C01_7 d/w - 10h/d - No HK 0 18-Nov-22 18-Jan-23 61
Hols - No B/O periods (was
310.C.FA.U371 3310/IA/3 - UU Works (by Contract <3408>) (assumed 2 months) C1)
C01_7 d/w - 10h/d - No HK 60 19-Nov-22 17-Jan-23 19-Jan-23 19-Mar-23 61
Hols - No B/O periods (was
310.C.EX.U369 3310/IA/3-1 (SW/OS) - Open-cut excavation + Stormwater/OS Pipe (64 m) C1)
C11_6 d/w - 10h/d - With 15 18-Jan-23 07-Feb-23 20-Mar-23 06-Apr-23 49
HK Hols - No B/O periods
Watermains (Seawater/Potable Water and Fire Hydrant (SPWFH) (was
C11_6C3)
d/w - 10h/d - With HK Hols
80- No B/O 0periods (was
08-Feb-23
C3) 17-May-23 11-Apr-23 17-Jul-23 49
310.C.EX.U387 3310/IA/3-1 (PWFH) - Open-cut excavation + Watermains Pipe Laying (689 m) C11_6 d/w - 10h/d - With 70 08-Feb-23 05-May-23 11-Apr-23 05-Jul-23 49
HK Hols - No B/O periods
310.C.EX.U384 3310/IA/3-1 (PWFH) - Watermains Chamber (20 nr) (was
C11_6C3)
d/w - 10h/d - With 70 20-Feb-23 17-May-23 22-Apr-23 17-Jul-23 49
HK Hols - No B/O periods
3310/IA/3-3 (was
C11_6C3)
d/w - 10h/d - With HK Hols
276- No B/O 0periods (was
28-Mar-22
C3) 01-Mar-23 21-Mar-23 31-Aug-24 447
Drainage - Stormwater and /Oil Separation (SWD/OS) C11_6 d/w - 10h/d - With HK Hols
26- No B/O 0periods (was
26-Oct-22
C3) 24-Nov-22 21-Mar-23 28-Jul-23 198
310.C.EX.U351 3310/IA/3-3 (SW/OS) - Open-cut excavation + Stormwater/OS Pipe (160 m @ 10m/d; use C11_6 d/w - 10h/d - With 16 26-Oct-22 12-Nov-22 21-Mar-23 12-Apr-23 120
1 team) HK Hols - No B/O periods
310.C.EX.U351.B02 3310/IA/3-3 (SWD/OS) -Concrete Surround of Existing Pipe; L=82m (was
C11_6C3)
d/w - 10h/d - With 16 26-Oct-22 12-Nov-22 11-Jul-23 28-Jul-23 208
HK Hols - No B/O periods
310.C.EX.U360 3310/IA/3-3 (SW/OS) - Stormwater/OS Manhole (1 nr ) (was
C11_6C3)
d/w - 10h/d - With 10 14-Nov-22 24-Nov-22 13-Apr-23 24-Apr-23 120
HK Hols - No B/O periods
Watermains (Seawater/Potable Water and Fire Hydrant (SPWFH) (was
C11_6C3)
d/w - 10h/d - With HK Hols
276- No B/O 0periods (was
28-Mar-22
C3) 01-Mar-23 25-Apr-23 31-Aug-24 447
310.C.EX.U745.B02 3310/IA/3-3 (Area 6) - ELS + Watermains Sleeve Pipe Laying (82 m) C11_6 d/w - 10h/d - With 30 28-Mar-22 06-May-22 29-Jul-24 31-Aug-24 693
HK Hols - No B/O periods
310.C.EX.U399 3310/IA/3-3 (PWFH) - Open-cut excavation + Watermains Pipe Laying (303 m) (was
C11_6C3)
d/w - 10h/d - With 30 25-Nov-22 30-Dec-22 25-Apr-23 31-May-23 120
HK Hols - No B/O periods
310.C.EX.U402 3310/IA/3-3 (PWFH) - Watermains Chamber (6 nr) (was
C11_6C3)
d/w - 10h/d - With 48 31-Dec-22 01-Mar-23 01-Jun-23 28-Jul-23 120
HK Hols - No B/O periods
Interface Work Area 3310/IA/5 (Airfield Drainage and UU Works) (was C3) 303 0 26-Oct-22 01-Nov-23 18-May-23 05-Dec-23 29
3310/IA/5-2 C11_6 d/w - 10h/d - With HK Hols
50- No B/O 0periods (was
01-Sep-23
C3) 01-Nov-23 19-Sep-23 05-Dec-23 29
Drainage - Stormwater and /Oil Separation (SWD/OS) C11_6 d/w - 10h/d - With HK Hols
50- No B/O 0periods (was
01-Sep-23
C3) 01-Nov-23 19-Sep-23 18-Nov-23 15
310.C.EX.U472 3310/IA/5-2b (SW/OS) - Open-cut excavation + Stormwater/OS Pipe (180 m) @ WVT C11_6 d/w - 10h/d - With 30 01-Sep-23 07-Oct-23 19-Sep-23 26-Oct-23 15
Zone 5 Area HK Hols - No B/O periods
310.C.EX.U476 3310/IA/5-2b (SW/OS) - Stormwater/OS Manhole (2 nr ) @ WVT Zone 5 Area (was
C11_6C3)
d/w - 10h/d - With 30 13-Sep-23 19-Oct-23 03-Oct-23 07-Nov-23 15
HK Hols - No B/O periods
310.C.EX.U487 3310/IA/5-2b (SW/OS) - Open-cut excavation + Stormwater/OS Pipe (244 m) @ WVT (was
C11_6C3)
d/w - 10h/d - With 30 13-Sep-23 19-Oct-23 03-Oct-23 07-Nov-23 15
Zone 3 Area HK Hols - No B/O periods
310.C.EX.U484 3310/IA/5-2b (SW/OS) - Stormwater/OS Manhole (2 nr ) @ WVT Zone 3 Area (was
C11_6C3)
d/w - 10h/d - With 30 25-Sep-23 01-Nov-23 14-Oct-23 18-Nov-23 15
HK Hols - No B/O periods
310.C.EX.U435 3310/IA/5-2b (SW/OS) - WVT Completion of Zone 5 backfill to +3.0 (was
C11_6C3)
d/w - 10h/d - With 0 28-Sep-23 18-Oct-23 15
HK Hols - No B/O periods
Watermains (Seawater/Potable Water and Fire Hydrant (SPWFH) (was
C11_6C3)
d/w - 10h/d - With HK Hols
48- No B/O 0periods (was
04-Sep-23
C3) 01-Nov-23 10-Oct-23 05-Dec-23 29
310.C.EX.U509 3310/IA/5-2b (PWPH) - Open-cut excavation + Watermains Pipe Laying (1195 m) C11_6 d/w - 10h/d - With 48 04-Sep-23 01-Nov-23 10-Oct-23 05-Dec-23 29
HK Hols - No B/O periods
310.C.EX.U514 3310/IA/5-2b (PWPH) - Watermains Chamber (12 nr) 8d/chamber/team; use 3 teams (was
C11_6C3)
d/w - 10h/d - With 32 22-Sep-23 01-Nov-23 30-Oct-23 05-Dec-23 29
HK Hols - No B/O periods
3310/IA/5-3 (was C3) 196 0 26-Oct-22 25-Jun-23 18-May-23 24-Sep-23 77
Area 3 (To Cross Interim Security Fence) - Potable Water and Fire Hydrant (PWFH) 196 0 26-Oct-22 25-Jun-23 18-May-23 24-Sep-23 77

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 50 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.EX.U670.B01 3310/IA/5-3 (Area 3) - Construct PWPH pit/chamber (1 nos); 1 wf C03_7 d/w - 10h/d - With 14 26-Oct-22 08-Nov-22 18-May-23 01-Jun-23 191
HK Hols - No B/O periods
310.C.EX.U665.B01 3310/IA/5-3 (Area 3) - ELS + PW pipe laying L=20m [assume 2wks full closure] C03_7 d/w - 10h/d - With 14 26-Oct-22 08-Nov-22 18-May-23 01-Jun-23 191
HK Hols - No B/O periods
310.C.EX.U675.B01 3310/IA/5-3 (Area 3) - Backfill and reinstatement works C03_7 d/w - 10h/d - With 10 09-Nov-22 18-Nov-22 02-Jun-23 11-Jun-23 191
HK Hols - No B/O periods
310.C.EX.U507 3310/IA/5-1 (Area 3) - Open cut excavation + Watermains Pipe Laying (371 m) (airside C23_4d/w - NOTAM 30 09-Jan-23 22-Mar-23 12-Jun-23 02-Aug-23 52
operational area) [NOTAM] (M,W,Th,Su-01:30-07:30) -
310.C.EX.U511 3310/IA/5-1 (Area 3) - Watermains Chamber 7nr) (airside operational area) [NOTAM] No HK Hols- -NOTAM
C23_4d/w With B/O 30 23-Mar-23 25-Jun-23 03-Aug-23 24-Sep-23 52
(M,W,Th,Su-01:30-07:30) -
Drainage - Stormwater and /Oil Separation (SWD/OS) No HK d/w
C11_6 Hols- -10h/d
With B/O
- With HK Hols
28- No B/O 0periods (was
02-Feb-23
C3) 06-Mar-23 26-Jun-23 28-Jul-23 116
310.C.EX.U528 3310/IA/5-3 (SW/OS) - Open-cut excavation + Stormwater/OS Pipe laying (434 m) C11_6 d/w - 10h/d - With 22 02-Feb-23 27-Feb-23 26-Jun-23 21-Jul-23 116
@3310/IA/5-3 HK Hols - No B/O periods
310.C.EX.U531 3310/IA/5-3 (SW/OS) - Construction of Stormwater/OS Manhole (6 nr ) (was
C11_6C3)
d/w - 10h/d - With 22 09-Feb-23 06-Mar-23 04-Jul-23 28-Jul-23 116
HK Hols - No B/O periods
Watermains (Seawater/Potable Water and Fire Hydrant (SPWFH) (was
C11_6C3)
d/w - 10h/d - With HK Hols
40- No B/O 0periods (was
06-Mar-23
C3) 26-Apr-23 29-Jul-23 13-Sep-23 116
310.C.EX.U567 3310/IA/5-3 (PWFH) - Open-cut excavation + Watermains Pipe Laying (274 m) C11_6 d/w - 10h/d - With 30 06-Mar-23 14-Apr-23 29-Jul-23 01-Sep-23 116
HK Hols - No B/O periods
310.C.EX.U738,B02 3310/IA/5-3 (PWFH) - Concrete Sleeve Watermains Pipe (was
C11_6C3)
d/w - 10h/d - With 30 06-Mar-23 14-Apr-23 10-Aug-23 13-Sep-23 126
HK Hols - No B/O periods
310.C.EX.U579 3310/IA/5-3 (PWFH) - Construction of Watermains Chamber (5 nr) (was
C11_6C3)
d/w - 10h/d - With 30 17-Mar-23 26-Apr-23 10-Aug-23 13-Sep-23 116
HK Hols - No B/O periods
Interface Work Area 3310/IA/7 (Airfield Drainage and UU Works) (was
C11_6C3)
d/w - 10h/d - With HK Hols
93- No B/O 0periods (was
01-Sep-22
C3) 21-Dec-22 19-Dec-22 29-Mar-23 79
3310/IA/7 C11_6 d/w - 10h/d - With HK Hols
93- No B/O 0periods (was
01-Sep-22
C3) 21-Dec-22 19-Dec-22 29-Mar-23 79
310.C.EX.U543.B02 3310/IA/7 - Carry Out Survey Check and UU Detection at Area 3310/3 + submit report to C11_6 d/w - 10h/d - With 21 01-Sep-22 26-Sep-22 19-Dec-22 13-Jan-23 90
PM HK Hols - No B/O periods
Drainage - Stormwater and /Oil Separation (SWD/OS) (was
C11_6C3)
d/w - 10h/d - With HK Hols
41- No B/O 0periods (was
12-Oct-22
C3) 28-Nov-22 14-Jan-23 06-Mar-23 79
310.C.EX.U543 3310/IA/7 SW/OS) - Open-cut excavation + Stormwater/OS Pipe (365 m) C11_6 d/w - 10h/d - With 36 12-Oct-22 22-Nov-22 14-Jan-23 28-Feb-23 79
HK Hols - No B/O periods
310.C.EX.U549 3310/IA/7 (SW/OS) - Stormwater/OS Manhole (3 nr ) (was
C11_6C3)
d/w - 10h/d - With 36 18-Oct-22 28-Nov-22 20-Jan-23 06-Mar-23 79
HK Hols - No B/O periods
Watermains (Seawater/Potable Water and Fire Hydrant (SPWFH) (was
C11_6C3)
d/w - 10h/d - With HK Hols
53- No B/O 0periods (was
21-Oct-22
C3) 21-Dec-22 27-Jan-23 29-Mar-23 79
310.C.EX.U603 3310/IA/7 (PWFH) - Open-cut excavation + Watermains Pipe Laying (407 m) C11_6 d/w - 10h/d - With 48 21-Oct-22 15-Dec-22 27-Jan-23 23-Mar-23 79
HK Hols - No B/O periods
310.C.EX.U609 3310/IA/7 (PWFH) - Watermains Chamber (8 nr) (was
C11_6C3)
d/w - 10h/d - With 48 27-Oct-22 21-Dec-22 02-Feb-23 29-Mar-23 79
HK Hols - No B/O periods
Interface Work Area 3310/IA/8 (Airfield Drainage and UU Works) (was
C11_6C3)
d/w - 10h/d - With HK Hols
194- No B/O 0periods (was
16-Jul-22
C3) 08-Mar-23 12-Jan-23 30-May-23 65
3310/IA/8 C11_6 d/w - 10h/d - With HK Hols
194- No B/O 0periods (was
16-Jul-22
C3) 08-Mar-23 12-Jan-23 30-May-23 65
310.C.EX.U562 *** Completion of Reclamation Works of 3310/11 (North) *** C11_6 d/w - 10h/d - With 0 05-Jan-23 29-Apr-23 91
HK Hols - No B/O periods
Drainage - Stormwater and /Oil Separation (SWD/OS) (was
C11_6C3)
d/w - 10h/d - With HK Hols
25- No B/O 0periods (was
08-Feb-23
C3) 08-Mar-23 29-Apr-23 30-May-23 65
310.C.EX.U541 3310/IA/8 (G4 - SW/OS) - Pipe laying Stormwater/OS Pipe (78 m) C11_6 d/w - 10h/d - With 20 08-Feb-23 02-Mar-23 29-Apr-23 23-May-23 65
HK Hols - No B/O periods
310.C.EX.U555 3310/IA/8 (G4 -SW/OS) - Stormwater/OS Manhole (3 nr ) @ 14d/MH/team; (was
C11_6C3)
d/w - 10h/d - With 20 14-Feb-23 08-Mar-23 06-May-23 30-May-23 65
HK Hols - No B/O periods
Area 1 - Watermain (PWFH) (was
C11_6C3)
d/w - 10h/d - With HK Hols
53- No B/O 0periods (was
16-Jul-22
C3) 16-Sep-22 12-Jan-23 17-Mar-23 149
310.C.EX.U755.B02 3310/IA/8 (Area 1) - Open-cut excavation + Watermains Pipe Laying (407 m) C11_6 d/w - 10h/d - With 48 16-Jul-22 09-Sep-22 12-Jan-23 11-Mar-23 149
HK Hols - No B/O periods
310.C.EX.U765.B02 3310/IA/8 (Area) - Watermains Chamber (6 nr) (was
C11_6C3)
d/w - 10h/d - With 48 22-Jul-22 16-Sep-22 18-Jan-23 17-Mar-23 149
HK Hols - No B/O periods
CC#04 - 3310/10,10A,9 - Western Box Culvert (WBC) no. 3, 4, 18 (was C3) 677 128 09-Aug-21 A 15-Nov-23 31-Jan-22 01-Sep-24 236
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 51 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
CC#4.7 - 3310/10,10A,9 - WBC no. 3,4,18 - Steel Formwork Fabrication C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was27-Mar-22
C1) 01-Jun-22 04-Apr-23 09-Jun-23 373
310.C.R0.L100 WBC no. 3,4,18 - Steel Formwork Fabrication C01_7 d/w - 10h/d - No HK 60 27-Mar-22 25-May-22 04-Apr-23 02-Jun-23 373
Hols - No B/O periods (was
310.C.R0.L104 WBC no. 3,4,18 - Steel Formwork delivery C1)
C01_7 d/w - 10h/d - No HK 7 26-May-22 01-Jun-22 03-Jun-23 09-Jun-23 373
Hols - No B/O periods (was
CC#4.7 - 3310/10,10A,9 - WBC no. 3,4,18 - Site Preparation Works C1) 321 0 09-Aug-21 A 05-Sep-22 31-Jan-22 01-Sep-24 592
310.C.R0.L112 WBC - access to Works Area 3310/10A C01_7 d/w - 10h/d - No HK 0 09-Aug-21 A 01-Sep-24
Hols - No B/O periods (was
310.C.R0.L108 WBC - access to Works Area 3310/10 C1)
C01_7 d/w - 10h/d - No HK 0 27-Mar-22* 31-Jan-22 -55
Hols - No B/O periods (was
310.C.R0.L1266 WBC - Access Date of 3310/9A C1)
C11_6 d/w - 10h/d - With 0 04-Jul-22 03-Oct-22 76
HK Hols - No B/O periods
310.C.R0.L781 WBC - Access Date of 3310/9 (was
C11_6C3)
d/w - 10h/d - With 0 05-Sep-22 24-Oct-22 39
HK Hols - No B/O periods
CC#4.7 - 3310/10,10A,9 - WBC no. 3,4,18 - Ground Investigation & Instrumentation Monitoring (was
C11_6C3)
d/w - 10h/d - With HK Hols
122- No B/O 0periods (was
13-Jan-23
C3) 14-Jun-23 27-May-23 24-Jun-23 8
310.C.R0.L218 3310/10,10A - WBC no. 18 - install surface movement marker on top of box culvert [5 nos. C11_6 d/w - 10h/d - With 12 13-Jan-23 30-Jan-23 10-Jun-23 24-Jun-23 118
@7d/nos.; 2wf] HK Hols - No B/O periods
310.C.R0.L128 3310/10,10A - WBC no. 3 & 4 - install surface movement marker on top of box culvert [6 (was
C11_6C3)
d/w - 10h/d - With 12 17-May-23 31-May-23 27-May-23 09-Jun-23 8
nos. @7d/nos.; 2wf] HK Hols - No B/O periods
310.C.R0.L217 3310/10,10A - WBC no. 18 - install settlement marker on ground [2nos. @7d/nos.; 1wf] (was
C11_6C3)
d/w - 10h/d - With 12 17-May-23 31-May-23 10-Jun-23 24-Jun-23 20
HK Hols - No B/O periods
310.C.R0.L124 3310/10,10A - WBC no. 3 & 4 - install surface movement marker on ground [4nos. (was
C11_6C3)
d/w - 10h/d - With 12 01-Jun-23 14-Jun-23 10-Jun-23 24-Jun-23 8
@7d/nos.; 2wf] HK Hols - No B/O periods
CC#4.7 - 3310/10,10A,9 - WBC no. 3,4,18 - R.C. Structure + Backfill (was C3) 325 82 08-Dec-21 A 06-Mar-23 10-May-22 12-May-23 53
CC#4.7 - WBC no. 3,4,18a/18b (12A) - Stage 1 [Ch.0+21 to 0+100] (and connect to new outfall by 3206) 220 16 08-Dec-21 A 28-Oct-22 10-May-22 09-Jan-23 60
310.C.R0.X998 WBC no. 3,4,18a/18b - Mobilization & Instrumentation C01_7 d/w - 10h/d - No HK 48 08-Dec-21 A 03-Jan-22 A 10-May-22 10-May-22
Hols - No B/O periods (was
310.C.R0.L1052.B01 WBC no. 3,4,18a/18b - Stage 1 Pre-grouting works [116no. @4 no./d, 1wf] C1)
C11_6 d/w - 10h/d - With 29 04-Jan-22 A 16-Mar-22 A 10-May-22 10-May-22
HK Hols - No B/O periods
310.C.R0.L1056.B01 WBC no. 3,4,18a/18b - Stage 1 Pre-boring works [470no. @7 no./d, 2wf] (was
C11_6C3)
d/w - 10h/d - With 37 3 14-Mar-22 A 29-Apr-22 10-May-22 08-Jun-22 32
HK Hols - No B/O periods
310.C.R0.L1046 WBC no. 3,4,18a/18b - Stage1 Sheet Piling installation [235no. @6no./d/rig, use 2 rig] (was
C11_6C3)
d/w - 10h/d - With 24 2 04-Apr-22 06-May-22 17-May-22 14-Jun-22 32
HK Hols - No B/O periods
310.C.R0.L1050 WBC no. 3,4,18a/18b - Stage 1 Curtain grout [107no. @3 no./d, 2wf] (was
C11_6C3)
d/w - 10h/d - With 18 0 07-May-22 27-May-22 15-Jun-22 06-Jul-22 32
HK Hols - No B/O periods
310.C.R0.L234 WBC no. 3,4,18a/18b - Stage 1 Submit Form BA14 for vertical element (was
C01_7C3)
d/w - 10h/d - No HK 7 28-May-22 03-Jun-22 07-Jul-22 13-Jul-22 40
Hols - No B/O periods (was
310.C.R0.L1054 WBC no. 3,4,18a/18b - Stage 1 Submit Form BA8 for excavation works C1)
C01_7 d/w - 10h/d - No HK 7 04-Jun-22 10-Jun-22 14-Jul-22 20-Jul-22 40
Hols - No B/O periods (was
310.C.R0.L607.B02 WBC no. 3,4,18a/18b - Submit Form BA8 and grant consent for RC works C1)
C01_7 d/w - 10h/d - No HK 7 04-Jun-22 10-Jun-22 22-Sep-22 28-Sep-22 110
Hols - No B/O periods (was
310.C.R0.L1058 WBC no. 3,4,18a/18b - Stage 1 Submit Form BA10 for excav. works - connection works C1)
C01_7 d/w - 10h/d - No HK 7 11-Jun-22 17-Jun-22 21-Jul-22 27-Jul-22 40
at outfall 1(constructed by <3206>) Hols - No B/O periods (was
310.C.R0.L609.B02 WBC no. 3,4,18a/18b - Submit Form BA10 and grant consent for RC works C1)
C01_7 d/w - 10h/d - No HK 7 11-Jun-22 17-Jun-22 29-Sep-22 05-Oct-22 110
Hols - No B/O periods (was
310.C.R0.L779 Contract <3206> complete Outfall and ready for Contract 3310 box culvert connection C1)
C11_6 d/w - 10h/d - With 0 17-Jun-22 27-Jul-22 33
HK Hols - No B/O periods
310.C.R0.L164 WBC no. 3,4,18a/18b - Stage 1 open excavation [Vol.=18,827m3, @450m3/d] @3WF+ (was
C11_6C3)
d/w - 10h/d - With 30 3 18-Jun-22 23-Jul-22 28-Jul-22 31-Aug-22 33
plate load test (if required) HK Hols - No B/O periods
310.C.R0.L606 WBC no. 3,4,18a/18b - Stage 1 (2~6 cells | 8 bays) - construct slab, Wall & Roof Slab, (was
C11_6C3)
d/w - 10h/d - With 62 6 25-Jul-22 07-Oct-22 06-Oct-22 16-Dec-22 60
@21d/bay, @ 3 WF HK Hols - No B/O periods
(was C3)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 52 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.R1.L930 WBC no. 3,4,18a/18b - Backfill Stage 1 area after RC Structure completed C11_6 d/w - 10h/d - With 18 2 08-Oct-22 28-Oct-22 17-Dec-22 09-Jan-23 60
HK Hols - No B/O periods
CC#4.7 - WBC no. 18a (12B) - Stage 1a [Ch.0+100 - 0+296] (was C3) 157 9 31-Mar-22 11-Oct-22 29-May-22 23-Feb-23 111
310.C.R0.L357.B02 WBC no. 18a - Submit Form BA8 and grant consent for RC works C01_7 d/w - 10h/d - No HK 7 31-Mar-22 06-Apr-22 08-Jun-22 14-Jun-22 69
Hols - No B/O periods (was
310.C.R0.L359.B02 WBC no. 18a - Submit Form BA10 and grant consent for RC works C1)
C01_7 d/w - 10h/d - No HK 7 06-Apr-22 12-Apr-22 14-Jun-22 20-Jun-22 69
Hols - No B/O periods (was
310.C.R0.L1074 WBC no. 18a - Stage 1a open excavation [Vol.=6,028m3, @450/m3/d] C1)
C01_7 d/w - 10h/d - No HK 15 1 25-Apr-22 09-May-22 29-May-22 12-Jun-22 34
Hols - No B/O periods (was
310.C.R0.L350 WBC no. 18a - Stage 1a (2 cells | 13 bays) - construct slab, Wall & Roof Slab @12d/bay; C1)
C11_6 d/w - 10h/d - With 86 8 17-May-22 26-Aug-22 21-Jun-22 30-Sep-22 29
@ 2WF HK Hols - No B/O periods
310.C.R0.L168 WBC no. 18a - Backfill Stage 2 area after RC Structure completed (was
C11_6C3)
d/w - 10h/d - With 36 27-Aug-22 11-Oct-22 10-Jan-23 23-Feb-23 111
HK Hols - No B/O periods
CC#4.7 - WBC no. 3,4,18b (12B) - Stage 2 [Ch.0+78 to 0+158] (was C3) 157 10 31-Mar-22 11-Oct-22 17-May-22 23-Feb-23 111
310.C.R0.L367.B02 WBC no. 3,4,18b - Submit Form BA8 and grant consent for RC works C01_7 d/w - 10h/d - No HK 7 31-Mar-22 06-Apr-22 25-May-22 31-May-22 55
Hols - No B/O periods (was
310.C.R0.L369.B02 WBC no. 3,4,18b - Submit Form BA10 and grant consent for RC works C1)
C01_7 d/w - 10h/d - No HK 7 06-Apr-22 12-Apr-22 31-May-22 06-Jun-22 55
Hols - No B/O periods (was
310.C.R0.L1076.B02 WBC no. 3,4,18b - Stage 2 open excavation [Vol.=7,077m3, @450/m3/d] C1)
C01_7 d/w - 10h/d - No HK 18 2 13-Apr-22 30-Apr-22 17-May-22 03-Jun-22 34
Hols - No B/O periods (was
310.C.R0.L352.B02 WBC no. 3,4,18b - Stage 2 (2~6 cells | 12 bays) - construct slab, Wall & Roof Slab C1)
C11_6 d/w - 10h/d - With 98 8 03-May-22 26-Aug-22 07-Jun-22 30-Sep-22 29
@21d/bay; @ 3 WF HK Hols - No B/O periods
310.C.R0.L169.B02 WBC no. 3,4,18b - Backfill Stage 2 area after RC Structure completed (was
C11_6C3)
d/w - 10h/d - With 36 27-Aug-22 11-Oct-22 10-Jan-23 23-Feb-23 111
HK Hols - No B/O periods
CC#4.7 - WBC no. 3,4,18b (12C) - Stage 3 [Ch.0+158 to 0+450] (was C3) 218 32 14-Apr-22 05-Jan-23 30-May-22 23-Feb-23 39
310.B01.100 3310/10 - DJM (Area E5) - Submit Form BA8 (after BA14) C01_7 d/w - 10h/d - No HK 7 14-Apr-22 20-Apr-22 30-May-22 05-Jun-22 46
Hols - No B/O periods (was
310.C.R0.L1098 3310/10 - DJM (Area E5) - Submit Form BA10 (after BA14) C1)
C01_7 d/w - 10h/d - No HK 7 21-Apr-22 27-Apr-22 06-Jun-22 12-Jun-22 46
Hols - No B/O periods (was
310.C.R0.L1267.B02 WBC no. 3,4,18b - Submit Form BA8 and grant consent for RC works C1)
C01_7 d/w - 10h/d - No HK 7 21-Apr-22 27-Apr-22 05-Jul-22 11-Jul-22 75
Hols - No B/O periods (was
310.C.R0.L1269.B02 WBC no. 3,4,18b - Submit Form BA10 and grant consent for RC works C1)
C01_7 d/w - 10h/d - No HK 7 27-Apr-22 03-May-22 11-Jul-22 17-Jul-22 75
Hols - No B/O periods (was
310.C.R0.L1078 WBC no. 3,4,18b - Stage 3 open excavation [Vol.=51798m3, @450m3/d, 3 WF] + plate C1)
C11_6 d/w - 10h/d - With 43 4 10-May-22 29-Jun-22 13-Jun-22 02-Aug-22 28
load test (if required) HK Hols - No B/O periods
310.C.R0.L1262 WBC no. 3,4,18b - Stage 3 (2~6 cells | 21 bays) - construct slab, Wall & Roof Slab (was
C11_6C3)
d/w - 10h/d - With 81 14 14-Jun-22 17-Sep-22 18-Jul-22 22-Oct-22 28
@21d/bay; @ 6 WF HK Hols - No B/O periods
310.C.R0.L394 WBC no. 4,18b - Stage 3 (6 cells | 20 bays) - construct slab, Wall & Roof Slab @21d/bay; (was
C11_6C3)
d/w - 10h/d - With 77 14 22-Aug-22 22-Nov-22 10-Oct-22 09-Jan-23 39
@ 6 WF HK Hols - No B/O periods
310.C.R0.L758 WBC no. 3,4,18b - Backfill Stage 3 after RC Structure completed (was
C11_6C3)
d/w - 10h/d - With 36 23-Nov-22 05-Jan-23 10-Jan-23 23-Feb-23 39
HK Hols - No B/O periods
CC#4.7 - WBC no. 18a (12D) - Stage 4 [Ch.0+296 to 0+316] & connect to BC18A by 3303 (was C3) 57 3 26-Aug-22 04-Nov-22 30-Sep-22 04-Nov-22 0
310.C.R0.L1086 BC18A Contract <3303> complete box culvert and ready for 3310 box culvert connection C11_6 d/w - 10h/d - With 0 26-Aug-22 30-Sep-22 29
HK Hols - No B/O periods
310.C.R0.L667.B02 WBC no. 18a - Submit Form BA8 and grant consent for RC works (was
C01_7C3)
d/w - 10h/d - No HK 7 19-Sep-22 25-Sep-22 02-Oct-22 08-Oct-22 13
Hols - No B/O periods (was
310.C.R0.L669.B02 WBC no. 18a - Submit Form BA10 and grant consent for RC works C1)
C01_7 d/w - 10h/d - No HK 7 25-Sep-22 01-Oct-22 08-Oct-22 14-Oct-22 13
Hols - No B/O periods (was
310.C.R0.L1082 WBC no. 18a - Stage 4 open excavation [Vol.=1,472m3, @450m3/d] C1)
C11_6 d/w - 10h/d - With 10 1 03-Oct-22 14-Oct-22 03-Oct-22 14-Oct-22 0
HK Hols - No B/O periods
(was C3)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 53 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.R0.L663 WBC no.18a - Stage 4 (2 cells | 2 bays)-construct slab,Wall & Roof Slab @12d/bay; @1 C11_6 d/w - 10h/d - With 18 2 15-Oct-22 04-Nov-22 15-Oct-22 04-Nov-22 0
WF(Comp. Permanent Diversion BC18A) HK Hols - No B/O periods
CC#4.7 - WBC no. 4,18b (12E) - Stage 5 [Ch.0+438 to 0+460] & connect to BC4 & 18B by 3303 (was C3) 96 5 17-Sep-22 12-Jan-23 18-Oct-22 12-May-23 95
310.C.R0.L1090 BC 4, 18B Contract <3303> complete box culvert and ready for 3310 box culvert C11_6 d/w - 10h/d - With 0 17-Sep-22 22-Oct-22 28
connection HK Hols - No B/O periods
310.C.R0.L867.B02 WBC no. 4,18b - Submit Form BA8 and grant consent for RC works (was
C01_7C3)
d/w - 10h/d - No HK 7 19-Sep-22 25-Sep-22 18-Oct-22 24-Oct-22 29
Hols - No B/O periods (was
310.C.R0.L869.B02 WBC no. 4,18b - Submit Form BA10 and grant consent for RC works C1)
C01_7 d/w - 10h/d - No HK 7 25-Sep-22 01-Oct-22 24-Oct-22 30-Oct-22 29
Hols - No B/O periods (was
310.C.R0.L1242 WBC no. 4,18b - Stage 5 open excavation [Vol.=1,791m3, @450m3/d] C1)
C11_6 d/w - 10h/d - With 6 1 24-Oct-22 29-Oct-22 24-Oct-22 29-Oct-22 0
HK Hols - No B/O periods
310.C.R0.L865 WBC no. 4,18b - Stage 5 (6 cells | 2 bays) - construct slab Wall & Roof Slab @21d/bay; @ (was
C11_6C3)
d/w - 10h/d - With 42 4 31-Oct-22 17-Dec-22 31-Oct-22 17-Dec-22 0
1 WF HK Hols - No B/O periods
310.C.R0.L1254 BC4 & 18B Complete connection with 3303 (Complete Permanent Diversion BC4&18B) (was C11_6C3)
d/w - 10h/d - With 0 17-Dec-22 17-Dec-22 0
HK Hols - No B/O periods
310.C.R0.L889 WBC no. 4,18b - Backfilling and removal of Armour Rock (Swale Area) (was
C11_6C3)
d/w - 10h/d - With 20 19-Dec-22 12-Jan-23 19-Apr-23 12-May-23 95
HK Hols - No B/O periods
310.C.R0.L887.B02 WBC no. 4,18b - Backfilling at RC structure (was
C11_6C3)
d/w - 10h/d - With 20 19-Dec-22 12-Jan-23 19-Apr-23 12-May-23 95
HK Hols - No B/O periods
CC#4.7 - WBC no. 3 (12F) - Stage 6 [Ch.0+210 to Extg. Outfall] & connect to extg. Outfall No.3 (was C3) 108 7 26-Oct-22 06-Mar-23 19-Dec-22 06-Mar-23 0
310.C.R0.L787.B02 WBC no. 3 - Submit Form BA8 and grant consent for RC works C01_7 d/w - 10h/d - No HK 7 26-Oct-22 01-Nov-22 29-Dec-22 04-Jan-23 64
Hols - No B/O periods (was
310.C.R0.L789.B02 WBC no. 3 - Submit Form BA10 and grant consent for RC works C1)
C01_7 d/w - 10h/d - No HK 7 01-Nov-22 07-Nov-22 04-Jan-23 10-Jan-23 64
Hols - No B/O periods (was
310.C.R0.L1094 WBC no. 3 - Stage 6 temp drainage diversion works (starts after dry season 1 Nov) C1)
C11_6 d/w - 10h/d - With 12 19-Dec-22 03-Jan-23 19-Dec-22 03-Jan-23 0
HK Hols - No B/O periods
310.C.R0.L1246 WBC no. 3 - Stage 6 open excavation [Vol.=352m3, @93m3/d] (was
C11_6C3)
d/w - 10h/d - With 6 1 04-Jan-23 10-Jan-23 04-Jan-23 10-Jan-23 0
HK Hols - No B/O periods
310.C.R0.L786 WBC no. 3 - Stage 6 (2 cells | 2 bays) - construct slab, Wall & Roof Slab @12d/bay; @ 1 (was
C11_6C3)
d/w - 10h/d - With 24 4 11-Jan-23 10-Feb-23 11-Jan-23 10-Feb-23 0
WF HK Hols - No B/O periods
310.C.R0.L1258 BC3 Complete connection with Outfall 3 (Complete Permanent Diversion BC3) (was
C11_6C3)
d/w - 10h/d - With 0 10-Feb-23 10-Feb-23 0
HK Hols - No B/O periods
310.C.R0.L885 WBC no. 3 - Backfilling and removal of Armour Rock (Swale Area) (was
C11_6C3)
d/w - 10h/d - With 20 1 11-Feb-23 06-Mar-23 11-Feb-23 06-Mar-23 0
HK Hols - No B/O periods
310.C.R0.L883.B02 WBC no. 3 - Backfilling at RC structure (was
C11_6C3)
d/w - 10h/d - With 20 1 11-Feb-23 06-Mar-23 11-Feb-23 06-Mar-23 0
HK Hols - No B/O periods
CC#4.7 - 3310/10,10A,9 - WBC no. 3,4,18 - Metal Works for Desilting Chamber & Spill Trap (was
C11_6C3)
d/w - 10h/d - With HK Hols
103- No B/O 0periods (was
08-Oct-22
C3) 11-Feb-23 13-Jan-23 12-May-23 73
310.C.R0.L909 WBC no. 3,4,18A,18B - metal work for desilting chamber, spill trap, stop log opening in C11_6 d/w - 10h/d - With 75 08-Oct-22 05-Jan-23 13-Jan-23 18-Apr-23 81
3310/10 HK Hols - No B/O periods
310.C.R0.L900 WBC no. 3,4, 18A - metal work for desilting chamber in 3310/9 & 9A (was
C11_6C3)
d/w - 10h/d - With 20 16-Jan-23 11-Feb-23 19-Apr-23 12-May-23 73
HK Hols - No B/O periods
CC#4 - 3310/10,10A - Landside Road and Airside Road (was C3) 438 46 30-May-22 15-Nov-23 18-Aug-22 01-Jun-24 160
CC#4.1, 4.2, 4.4, 4.7 - 3310/10,10A - Underground Utilities along Land Side Road 266 33 30-May-22 20-Apr-23 18-Aug-22 22-Sep-23 129
3310/10,10A - Underground Utilities along Land Side Road (West) C11_6 d/w - 10h/d - With HK Hols
192- No B/O12
periods (was
30-May-22
C3) 16-Jan-23 18-Aug-22 24-Jun-23 127
310.C.R0.L910 3310/10,10A (west) - (UU under LSR & ASR) - GI for utilities C11_6 d/w - 10h/d - With 7 30-May-22 07-Jun-22 18-Aug-22 25-Aug-22 67
HK Hols - No B/O periods
310.C.R0.L913 3310/10,10A (west) - (UU under LSR & ASR) - PM agree utilities installation level (was
C11_6C3)
d/w - 10h/d - With 28 08-Jun-22 11-Jul-22 26-Aug-22 28-Sep-22 67
HK Hols - No B/O periods
310.C.R0.L919 3310/10,10A (west) - LSR - Gas main (was
C11_6C3)
d/w - 10h/d - With 60 2 12-Jul-22 20-Sep-22 29-Sep-22 09-Dec-22 67
HK Hols - No B/O periods
(was C3)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 54 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.R0.L916 3310/10,10A (west) - LSR - stormwater drain pipe [232mL @5m/d/wf; 2wf; 10MH C11_6 d/w - 10h/d - With 60 2 20-Jul-22 28-Sep-22 29-Sep-22 09-Dec-22 60
@4d/no/wf; 1wf] HK Hols - No B/O periods
310.C.R0.L922 3310/10,10A (west) - LSR - Airport System ductings (was
C11_6C3)
d/w - 10h/d - With 60 2 29-Sep-22 09-Dec-22 10-Dec-22 23-Feb-23 60
HK Hols - No B/O periods
310.C.R0.L925 3310/10,10A (west) - LSR - Potable Water main for FS (was
C11_6C3)
d/w - 10h/d - With HK Hols
60- No B/O 2periods (was
13-Oct-22
C3) 21-Dec-22 22-Dec-22 07-Mar-23 60
310.C.R0.L928 3310/10,10A (west) - LSR - 132kv CLP duct and drawpits (L=696 m) C11_6 d/w - 10h/d - With 60 2 25-Oct-22 04-Jan-23 05-Jan-23 18-Mar-23 60
HK Hols - No B/O periods
310.C.R0.L932 3310/10,10A (west) - LSR - Road Drainage works (was
C11_6C3)
d/w - 10h/d - With 60 2 05-Nov-22 16-Jan-23 13-Apr-23 24-Jun-23 127
HK Hols - No B/O periods
3310/10,10A - Underground Utilities along Land Side Road (East) (was
C11_6C3)
d/w - 10h/d - With HK Hols
173- No B/O12
periods (was
25-Jul-22
C3) 20-Feb-23 01-Sep-22 22-Sep-23 176
310.C.R0.L938 3310/10,10A (east) - (UU under LSR & ASR) - GI for utilities C11_6 d/w - 10h/d - With 7 25-Jul-22 01-Aug-22 01-Sep-22 08-Sep-22 33
HK Hols - No B/O periods
310.C.R0.L942 3310/10,10A (east) - (UU under LSR & ASR) - PM agree utilities installation level (was
C11_6C3)
d/w - 10h/d - With 28 02-Aug-22 02-Sep-22 09-Sep-22 14-Oct-22 33
HK Hols - No B/O periods
310.C.R0.L946 3310/10,10A (east) - LSR - stormwater drain pipe [40mL @5m/d/wf; 1wf; 2MH (was
C11_6C3)
d/w - 10h/d - With 48 2 03-Sep-22 01-Nov-22 15-Oct-22 09-Dec-22 33
@4d/no/wf; 1wf] HK Hols - No B/O periods
310.C.R0.L950 3310/10,10A (east) - LSR - Gas main (was
C11_6C3)
d/w - 10h/d - With 48 2 03-Sep-22 01-Nov-22 15-Oct-22 09-Dec-22 33
HK Hols - No B/O periods
310.C.R0.L954 3310/10,10A (east) - LSR - Airport System ductings (was
C11_6C3)
d/w - 10h/d - With 60 2 02-Nov-22 12-Jan-23 10-Dec-22 23-Feb-23 33
HK Hols - No B/O periods
310.C.R0.L958 3310/10,10A (east) - LSR - Potable Water main for FS (was
C11_6C3)
d/w - 10h/d - With 60 2 14-Nov-22 27-Jan-23 22-Dec-22 07-Mar-23 33
HK Hols - No B/O periods
310.C.R0.L962 3310/10,10A (east) - LSR - 132kv & 11kv CLP duct and drawpits (was
C11_6C3)
d/w - 10h/d - With 60 2 25-Nov-22 08-Feb-23 05-Jan-23 18-Mar-23 33
HK Hols - No B/O periods
310.C.R0.L963 3310/10,10A (east) - LSR - Road Drainage works (was
C11_6C3)
d/w - 10h/d - With 60 2 07-Dec-22 20-Feb-23 15-Jul-23 22-Sep-23 176
HK Hols - No B/O periods
3310/10,10A - Underground Utilities along Land Side Road (Swale & Outfall) (was C3) 36 9 06-Mar-23 20-Apr-23 06-Mar-23 02-May-23 9
310.C.R0.L966 3310/10,10A (swale & outfall) - LSR - stormwater drain pipe [225mL @10m/d/wf; 2wf; C11_6 d/w - 10h/d - With 18 06-Mar-23 25-Mar-23 06-Mar-23 25-Mar-23 0
5MH @4d/no/wf; 2wf] HK Hols - No B/O periods
310.C.R0.L970 3310/10,10A (swale & outfall) - LSR - Gas main (was
C11_6C3)
d/w - 10h/d - With 18 2 06-Mar-23 25-Mar-23 06-Mar-23 25-Mar-23 0
HK Hols - No B/O periods
310.C.R0.L982 3310/10,10A (swale & outfall) - LSR - 132 kv CLP duct and drawpits (was
C11_6C3)
d/w - 10h/d - With 6 2 13-Mar-23 18-Mar-23 13-Mar-23 18-Mar-23 0
HK Hols - No B/O periods
310.C.R0.L974 3310/10,10A (swale & outfall) - LSR - Airport System ductings (was
C11_6C3)
d/w - 10h/d - With 18 2 13-Mar-23 01-Apr-23 16-Mar-23 06-Apr-23 3
HK Hols - No B/O periods
310.C.R0.L978 3310/10,10A (swale & outfall) - LSR - Potable Water main for FS (was
C11_6C3)
d/w - 10h/d - With 18 2 13-Mar-23 01-Apr-23 16-Mar-23 06-Apr-23 3
HK Hols - No B/O periods
310.C.R0.L983 3310/10,10A (swale & outfall) - LSR - complete CLP duct and drawpits - Achieve KD-04 (was
C01_7C3)
d/w - 10h/d - No HK 0 18-Mar-23 19-Mar-23 1
Hols - No B/O periods (was
310.C.R0.L984 3310/10,10A (swale & outfall) - LSR - Road Drainage Works C1)
C11_6 d/w - 10h/d - With 12 1 03-Apr-23 20-Apr-23 18-Apr-23 02-May-23 9
HK Hols - No B/O periods
CC#4.10 - 3310/10,10A - Road Work for Landside Road (was
C11_6C3)
d/w - 10h/d - With HK Hols
140- No B/O 6periods (was
17-Jan-23
C3) 11-Jul-23 11-Apr-23 01-Jun-24 266
310.C.R0.X108 3310/10,10A - Allow Access Contract <3206> for final placing of seawall protection C11_6 d/w - 10h/d - With 0 17-Jan-23 24-Jun-23 127
armour (PS 10.2.69) HK Hols - No B/O periods
310.C.R0.L931 3310/10,10A (west) - LSR - lay kerb & sub-base [250mL @15m/d/wf; 2wf] (was
C11_6C3)
d/w - 10h/d - With 19 1 17-Jan-23 10-Feb-23 19-Sep-23 12-Oct-23 199
HK Hols - No B/O periods
310.C.R0.L934 3310/10,10A (west) - LSR - Lay flexible pavement [250m @80m/6d/wf; 1wf] (was
C11_6C3)
d/w - 10h/d - With 20 1 11-Feb-23 06-Mar-23 13-Oct-23 06-Nov-23 199
HK Hols - No B/O periods
310.C.R0.L986 3310/10,10A (east) - LSR - lay kerb & sub-base [240mL @15m/d/wf; 2wf] (was
C11_6C3)
d/w - 10h/d - With 17 1 21-Feb-23 11-Mar-23 23-Sep-23 14-Oct-23 176
HK Hols - No B/O periods
310.C.R0.L990 3310/10,10A (east) - LSR - Lay flexible pavement [240m @80m/6d/wf; 1wf] (was
C11_6C3)
d/w - 10h/d - With 19 1 13-Mar-23 03-Apr-23 16-Oct-23 07-Nov-23 176
HK Hols - No B/O periods
(was C3)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 55 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.R0.L994 3310/10,10A (swale & outfall) - LSR - lay kerb & sub-base [120mL @15m/d/wf; 2wf] C11_6 d/w - 10h/d - With 12 1 03-Apr-23 20-Apr-23 11-Apr-23 24-Apr-23 3
HK Hols - No B/O periods
310.C.R0.L998 3310/10,10A (swale & outfall) - LSR - Lay flexible pavement [120m @80m/6d/wf; 1wf] (was
C11_6C3)
d/w - 10h/d - With 12 1 21-Apr-23 05-May-23 25-Apr-23 09-May-23 3
HK Hols - No B/O periods
310.C.R0.X100 3310/10,10A - LSR - install street lighting and provide power, road furniture (was
C11_6C3)
d/w - 10h/d - With 40 06-May-23 23-Jun-23 25-Mar-24 16-May-24 266
HK Hols - No B/O periods
310.C.R0.X104 3310/10,10A - LSR - wearing course & road marking (was
C11_6C3)
d/w - 10h/d - With 14 24-Jun-23 11-Jul-23 17-May-24 01-Jun-24 266
HK Hols - No B/O periods
CC#4.10 - 3310/10,10A - Road Work for Airside Road (was C3) 133 7 11-Feb-23 25-Jul-23 25-Apr-23 01-Jun-24 254
310.C.R0.X120 3310/10,10A (west) - ASR - lay kerb & sub-base [250mL @15m/d/wf; 2wf] C11_6 d/w - 10h/d - With 18 1 11-Feb-23 03-Mar-23 16-Oct-23 06-Nov-23 201
HK Hols - No B/O periods
310.C.R0.X124 3310/10,10A (west) - ASR - Lay flexible pavement [250m @80m/6d/wf; 1wf] (was
C11_6C3)
d/w - 10h/d - With 20 1 07-Mar-23 29-Mar-23 07-Nov-23 29-Nov-23 199
HK Hols - No B/O periods
310.C.R0.X128 3310/10,10A (east) - ASR - lay kerb & sub-base [240mL @15m/d/wf; 2wf] (was
C11_6C3)
d/w - 10h/d - With 17 1 13-Mar-23 31-Mar-23 18-Oct-23 07-Nov-23 178
HK Hols - No B/O periods
310.C.R0.X132 3310/10,10A (east) - ASR - Lay flexible pavement [240m @80m/6d/wf; 1wf] (was
C11_6C3)
d/w - 10h/d - With 19 1 04-Apr-23 29-Apr-23 08-Nov-23 29-Nov-23 176
HK Hols - No B/O periods
310.C.R0.X136 3310/10,10A (swale & outfall) - ASR - lay kerb & sub-base [120mL @15m/d/wf; 2wf] (was
C11_6C3)
d/w - 10h/d - With 12 1 21-Apr-23 05-May-23 25-Apr-23 09-May-23 3
HK Hols - No B/O periods
310.C.R0.X140 3310/10,10A (swale & outfall) - ASR - Lay flexible pavement [120m @80m/6d/wf; 1wf] (was
C11_6C3)
d/w - 10h/d - With 12 1 06-May-23 19-May-23 10-May-23 23-May-23 3
HK Hols - No B/O periods
310.C.R0.X141 3310/10, 10A - divert temp landside road from south side to new paved road along north (was
C11_6C3)
d/w - 10h/d - With 0 19-May-23 23-May-23 3
seawall HK Hols - No B/O periods
310.C.R0.X142 3310/10,10A - remaining AGL, Pavement along old temp landside road (was
C11_6C3)
d/w - 10h/d - With 26 1 20-May-23 20-Jun-23 24-May-23 24-Jun-23 3
HK Hols - No B/O periods
310.C.R0.X144 3310/10,10A - ASR - install street lighting, road furniture (was
C11_6C3)
d/w - 10h/d - With 40 20-May-23 08-Jul-23 25-Mar-24 16-May-24 254
HK Hols - No B/O periods
310.C.R0.X143 3310/10,10A - Complete Airfield pavement to achieve KD-5B (was
C01_7C3)
d/w - 10h/d - No HK 0 20-Jun-23 25-Jun-23 5
Hols - No B/O periods (was
310.C.R0.X148 3310/10,10A - ASR - wearing course & road marking [610mL] C1)
C11_6 d/w - 10h/d - With 14 10-Jul-23 25-Jul-23 17-May-24 01-Jun-24 254
HK Hols - No B/O periods
CC#4.11 - 3310/10,10A - Security Fence (was
C11_6C3)
d/w - 10h/d - With HK Hols
77- No B/O 0periods (was
20-May-23
C3) 21-Aug-23 30-Nov-23 04-Mar-24 160
310.C.R0.X152 3310/10,10A - Security Fence - construct footing [610m @10m/7d/wf; 6wf] C11_6 d/w - 10h/d - With 63 20-May-23 04-Aug-23 30-Nov-23 16-Feb-24 160
HK Hols - No B/O periods
310.C.R0.X156 3310/10,10A - Security Fence - metal works (was
C11_6C3)
d/w - 10h/d - With 63 07-Jun-23 21-Aug-23 16-Dec-23 04-Mar-24 160
HK Hols - No B/O periods
CC#4.10 - 3310/10,10A - Central Reserve Pavement (was
C11_6C3)
d/w - 10h/d - With HK Hols
85- No B/O 0periods (was
05-Aug-23
C3) 15-Nov-23 16-Mar-24 01-Jun-24 160
310.C.R0.X164 3310/10,10A - Area G4 - Central Resv - lay sub-base [612mL @15m/d/wf] C11_6 d/w - 10h/d - With 40 05-Aug-23 20-Sep-23 16-Mar-24 07-May-24 184
HK Hols - No B/O periods
310.C.R0.X168 3310/10,10A - Area G4 - Central Resv - lay verge [612mL @30m/d/wf] (was
C11_6C3)
d/w - 10h/d - With 21 21-Oct-23 15-Nov-23 08-May-24 01-Jun-24 160
HK Hols - No B/O periods
CC#04 - 3310/5,6,6A,7 - Eastern Box Culvert (EBC) no. 5, 6, 19 (was C3) 734 59 07-Jun-21 A 21-Nov-23 30-Mar-22 25-Nov-23 4
CC#4.7 - 3310/5,6,6A,7 - EBC no. 5,6,19 - Steel Formwork Fabrication C11_6 d/w - 10h/d - With HK Hols
67- No B/O 0periods (was
28-Mar-22
C3) 20-Jun-22 08-Sep-22 28-Nov-22 134
310.C.R0.X170 3310/5,6,6A - EBC no. 5,6,19 - Steel Formwork Fabrication C11_6 d/w - 10h/d - With 60 28-Mar-22 11-Jun-22 08-Sep-22 19-Nov-22 134
HK Hols - No B/O periods
310.C.R0.X174 3310/5,6,6A - EBC no. 5,6,19 - Steel Formwork Delivery (was
C11_6C3)
d/w - 10h/d - With 7 13-Jun-22 20-Jun-22 21-Nov-22 28-Nov-22 134
HK Hols - No B/O periods
CC#4.7 - 3310/5,6,6A,7 - EBC no. 5,6,19 - Site Preparation Works (was
C11_6C3)
d/w - 10h/d - With HK Hols
478- No B/O 0periods (was
07-Jun-21
C3) A 10-Jan-23 30-Mar-22 25-Oct-23 233
CC#4.7 - 3310/5 - EBC no. 5,6,19 - Site Preparation Works C11_6 d/w - 10h/d - With HK Hols7 - No B/O 0periods (was
03-Jan-23
C3) 10-Jan-23 03-Jan-23 02-Feb-23 17
310.C.R0.X178 3310/5,6,6A - EBC no. 5,6,19 - Access to Works Area 3310/5 C11_6 d/w - 10h/d - With 0 03-Jan-23* 03-Jan-23 0
HK Hols - No B/O periods
(was C3)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 56 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.R0.X194 3310/5,6,6A - EBC no. 5,6,19 - Condition survey to Works Area 3310/5 C11_6 d/w - 10h/d - With 7 03-Jan-23 10-Jan-23 26-Jan-23 02-Feb-23 17
HK Hols - No B/O periods
CC#4.7 - 3310/6 - EBC no. 5,6,19 - Site Preparation Works (was
C11_6C3)
d/w - 10h/d - With HK Hols
105- No B/O 0periods (was
07-Jun-21
C3) A 11-Oct-21 A 30-Mar-22 25-Oct-23
310.C.R0.X182 3310/5,6,6A - EBC no. 5,6,19 - Access to Works Area 3310/6 C11_6 d/w - 10h/d - With 0 07-Jun-21 A 30-Mar-22
HK Hols - No B/O periods
310.C.R0.X198 3310/5,6,6A - EBC no. 5,6,19 - Condition survey to Works Area 3310/6 (was
C11_6C3)
d/w - 10h/d - With 7 04-Oct-21 A 11-Oct-21 A 25-Oct-23 25-Oct-23
HK Hols - No B/O periods
CC#4.7 - 3310/6A - EBC no. 5,6,19 - Site Preparation Works (was
C11_6C3)
d/w - 10h/d - With HK Hols7 - No B/O 0periods (was
04-Oct-21
C3) A 11-Oct-21 A 30-Mar-22 30-Mar-22
310.C.R0.X186 3310/5,6,6A - EBC no. 5,6,19 - Access to Works Area 3310/6A C11_6 d/w - 10h/d - With 0 04-Oct-21 A 30-Mar-22
HK Hols - No B/O periods
310.C.R0.X202 3310/5,6,6A - EBC no. 5,6,19 - Condition survey to Works Area 3310/6A (was
C11_6C3)
d/w - 10h/d - With 7 04-Oct-21 A 11-Oct-21 A 30-Mar-22 30-Mar-22
HK Hols - No B/O periods
CC#4.7 - 3310/7 - EBC no. 5,6,19 - Site Preparation Works (was
C11_6C3)
d/w - 10h/d - With HK Hols7 - No B/O 0periods (was
05-Sep-22
C3) 13-Sep-22 05-Sep-22 25-Oct-23 331
310.C.R0.X190 3310/5,6,6A - EBC no. 5,6,19 - Access to Works Area 3310/7 C11_6 d/w - 10h/d - With 0 05-Sep-22* 05-Sep-22 0
HK Hols - No B/O periods
310.C.R0.X206 3310/5,6,6A - EBC no. 5,6,19 - Condition survey to Works Area 3310/7 (was
C11_6C3)
d/w - 10h/d - With 7 05-Sep-22 13-Sep-22 17-Oct-23 25-Oct-23 331
HK Hols - No B/O periods
CC#4.7 - 3310/5,6,6A,7 - EBC no. 5,6,19 - Ground Investigation & Instrumentation Monitoring (was C3) 66 0 02-Sep-23 21-Nov-23 16-Oct-23 25-Nov-23 4
310.C.R0.X210 3310/5,6,6A - EBC no. 5,6,19 - Plant mobilization C11_6 d/w - 10h/d - With 4 02-Sep-23 06-Sep-23 25-Oct-23 28-Oct-23 42
HK Hols - No B/O periods
310.C.R0.X226 3310/5,6,6A - EBC no. 5,6,19 - install surface movement marker on ground [6nos. (was C3)
C11_6 d/w - 10h/d - With 21 07-Sep-23 03-Oct-23 30-Oct-23 22-Nov-23 42
@7d/no.; 2wf] HK Hols - No B/O periods
310.C.R0.X246 3310/5,6,6A - EBC no. 5 & 6 - install surface movement marker on ground [10nos. (was
C11_6C3)
d/w - 10h/d - With 35 14-Sep-23 27-Oct-23 16-Oct-23 25-Nov-23 25
@7d/no.; 2wf] HK Hols - No B/O periods
310.C.R0.X230 3310/5,6,6A - EBC no. 19 - install surface movement marker on top of box culvert [5nos. (was
C11_6C3)
d/w - 10h/d - With 21 20-Sep-23 16-Oct-23 16-Oct-23 09-Nov-23 20
@7d/no.; 2wf] HK Hols - No B/O periods
310.C.R0.X250 3310/5,6,6A - EBC no. 5 & 6 - install surface movement marker on top of box culvert (was
C11_6C3)
d/w - 10h/d - With 14 25-Oct-23 09-Nov-23 07-Nov-23 22-Nov-23 11
[4nos. @7d/no.; 2wf] HK Hols - No B/O periods
310.C.R0.X222 3310/5,6,6A - EBC no. 19 - review and agree installation level with PM (was
C01_7C3)
d/w - 10h/d - No HK 28 25-Oct-23 21-Nov-23 26-Oct-23 22-Nov-23 1
Hols - No B/O periods (was
CC#4.7 - 3310/5,6,6A,7 - EBC no. 5,6 - R.C. Structure + Backfill C1) 451 59 30-Jan-22 A 02-Sep-23 23-Apr-22 03-Oct-23 24
CC#4.7 - EBC no. 5,19 - Stage 1 [Ch.0+050 to 1+553] 254 20 30-Jan-22 A 03-Jan-23 23-Apr-22 20-May-23 110
310.C.R0.X994 Mobilization + Instrumentation (install dewatering wells + pump test) C01_7 d/w - 10h/d - No HK 48 4 30-Jan-22 A 27-Feb-22 A 23-Apr-22 23-Apr-22
Hols - No B/O periods (was
310.C.R0.X434 EBC no. 5,19 - Stage 1 - open excavation [50,375m3 @ 450/m3/d, use 3 WF) C1)
C11_6 d/w - 10h/d - With 39 2 28-Feb-22 A 28-Apr-22 23-Apr-22 21-May-22 19
HK Hols - No B/O periods
310.D.R0.L591.B01 EBC no. 5,19 - Form BA8 and grant consent for RC works (Outside DJM) (was
C01_7C3)
d/w - 10h/d - No HK 7 20-Apr-22 27-Apr-22 16-May-22 22-May-22 26
Hols - No B/O periods (was
310.D.R0.L596.B01 EBC no. 5,19 - Form BA10 and grant consent for RC works (Outside DJM) C1)
C01_7 d/w - 10h/d - No HK 7 27-Apr-22 03-May-22 23-May-22 29-May-22 26
Hols - No B/O periods (was
310.C.R0.X658 EBC no. 5,19 - Stage 1 - prepare Plate Load Test report to PM C1)
C11_6 d/w - 10h/d - With 6 29-Apr-22 06-May-22 23-May-22 28-May-22 19
HK Hols - No B/O periods
310.C.R1.L898 EBC no. 5,19 - Stage 1 (5~6 cells | 36 bays) - construct base slab, @ 6d/bay, use 6 WF (was
C11_6C3)
d/w - 10h/d - With 40 4 07-May-22 23-Jun-22 30-May-22 16-Jul-22 19
HK Hols - No B/O periods
310.C.R1.L902 EBC no. 5,19 - Stage 1 (5~6 cells | 36 bays) - construct wall & roof slab, @ 21d/bay, use 6 (was
C11_6C3)
d/w - 10h/d - With 134 8 28-May-22 05-Nov-22 21-Jun-22 28-Nov-22 19
WF HK Hols - No B/O periods
310.C.R1.L854 EBC no. 5,19 - Backfill Zone 1 (was
C11_6C3)
d/w - 10h/d - With 48 2 07-Nov-22 03-Jan-23 21-Mar-23 20-May-23 110
HK Hols - No B/O periods
CC#4.7 - EBC no. 5,6,19 - Stage 2 [Ch.0+553 to 1+230] (was C3) 260 19 19-May-22 29-Mar-23 21-May-22 03-Oct-23 151
310.D.R0.L328 EBC no. 5,6,19 - Form BA8 and grant consent for RC works (after Area E1 DJM BA14) C01_7 d/w - 10h/d - No HK 7 19-May-22 25-May-22 21-May-22 27-May-22 2
Hols - No B/O periods (was
C1)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 57 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.R0.L332 EBC no. 5,6,19 - Form BA10 and grant consent for RC works (after Area E1 DJM BA14) C01_7 d/w - 10h/d - No HK 7 26-May-22 01-Jun-22 28-May-22 03-Jun-22 2
Hols - No B/O periods (was
310.C.R0.X970 EBC no. 5,6,19 - Stage 2 - open excavation [52,299m3 @ 450/m3/d, use 3 WF) C1)
C11_6 d/w - 10h/d - With 43 2 02-Jun-22 23-Jul-22 04-Jun-22 25-Jul-22 1
HK Hols - No B/O periods
310.C.R0.X986 EBC no. 5,6,19 - Stage 2 - prepare Plate Load Test report to PM (was
C11_6C3)
d/w - 10h/d - With 6 25-Jul-22 30-Jul-22 26-Jul-22 01-Aug-22 1
HK Hols - No B/O periods
310.C.R1.L906 EBC no. 5,6,19 - Stage 2 (6~9 cells | 39 bays) - construct base slab, @ 6d/bay, use 6 WF (was
C11_6C3)
d/w - 10h/d - With 40 4 01-Aug-22 16-Sep-22 02-Aug-22 17-Sep-22 1
HK Hols - No B/O periods
310.C.R1.L910 EBC no. 5,6,19 - Stage 2 (6~9 cells | 39 bays) - construct wall & roof slab, @ 21d/bay, use (was
C11_6C3)
d/w - 10h/d - With 137 11 17-Aug-22 01-Feb-23 18-Aug-22 02-Feb-23 1
6 WF HK Hols - No B/O periods
310.C.R1.L850 EBC no. 5,6,19 - Backfill Zone 2 (was
C11_6C3)
d/w - 10h/d - With 48 2 02-Feb-23 29-Mar-23 07-Aug-23 03-Oct-23 151
HK Hols - No B/O periods
CC#4.7 - EBC no. 5 - Stage 3 [Ch.0+030 to extg. outfall] BC Connection to Existing Outfall 5 (was C3) 141 9 25-Oct-22 17-Apr-23 29-Nov-22 08-Aug-23 93
310.C.R0.L1207.B02 EBC no. 5 - Form BA8 and grant consent for RC works C01_7 d/w - 10h/d - No HK 7 25-Oct-22 31-Oct-22 20-Dec-22 26-Dec-22 56
Hols - No B/O periods (was
310.C.R0.L1209.B02 EBC no. 5 - Form BA10 and grant consent for RC works C1)
C01_7 d/w - 10h/d - No HK 7 01-Nov-22 07-Nov-22 27-Dec-22 02-Jan-23 56
Hols - No B/O periods (was
310.C.R0.L1190 EBC no. 5 - Stage 3 - temporary drainage diversion works (starts after dry season 1 Nov) C1)
C11_6 d/w - 10h/d - With 16 08-Nov-22 25-Nov-22 29-Nov-22 16-Dec-22 18
HK Hols - No B/O periods
310.C.R0.X974 EBC no. 5 - Stage 3 - excavation [2323m3 @ 150/m3/d, use 1 WF) + Plate load test (was
C11_6C3)
d/w - 10h/d - With 12 2 26-Nov-22 09-Dec-22 17-Dec-22 31-Dec-22 18
HK Hols - No B/O periods
310.C.R0.L1202 Stage 3 (3 cells|4 bays) - construct base slab,Wall & Roof Slab @21d/bay;@2 WF (Comp. (was
C11_6C3)
d/w - 10h/d - With 24 3 10-Dec-22 09-Jan-23 03-Jan-23 02-Feb-23 18
connection with extg. Outfall 5) HK Hols - No B/O periods
310.C.R0.L1226 Complete Connection to Outfall No. 5 (after RC Culvert at Stage 1 and Stage 2 (was
C11_6C3)
d/w - 10h/d - With 12 02-Feb-23 15-Feb-23 03-Feb-23 16-Feb-23 1
completed) HK Hols - No B/O periods
310.C.R1.L842 EBC no. 5 - Backfill Zone 3 (was
C11_6C3)
d/w - 10h/d - With 12 2 16-Feb-23 01-Mar-23 12-Jun-23 26-Jun-23 93
HK Hols - No B/O periods
310.C.R1.L830 Remove armour rock & Backfill drainage swale in 3310/6 (after outfall 5 diversion) (was
C11_6C3)
d/w - 10h/d - With 48 2 16-Feb-23 17-Apr-23 12-Jun-23 08-Aug-23 93
HK Hols - No B/O periods
CC#4.7 - EBC no. 6 - Stage 4 [S13 to extg. outfall] BC Connection to Existing Outfall 6 (was C3) 199 6 25-Oct-22 27-Jun-23 17-Feb-23 28-Jun-23 1
310.C.R0.L1217.B02 EBC no. 6 - Form BA8 and grant consent for RC works C01_7 d/w - 10h/d - No HK 7 25-Oct-22 31-Oct-22 07-Mar-23 13-Mar-23 133
Hols - No B/O periods (was
310.C.R0.L1219.B02 EBC no. 6 - Form BA10 and grant consent for RC works C1)
C01_7 d/w - 10h/d - No HK 7 01-Nov-22 07-Nov-22 14-Mar-23 20-Mar-23 133
Hols - No B/O periods (was
310.C.R0.L1210 EBC no. 6 - Stage 4 - temporary drainage diversion work C1)
C11_6 d/w - 10h/d - With 16 16-Feb-23 06-Mar-23 17-Feb-23 07-Mar-23 1
HK Hols - No B/O periods
310.C.R0.X978 EBC no. 6 - Stage 4 - excavation [2,073m3 @ 150/m3/d, use 1 WF) (was
C11_6C3)
d/w - 10h/d - With 12 2 07-Mar-23 20-Mar-23 08-Mar-23 21-Mar-23 1
HK Hols - No B/O periods
310.C.R0.L1218 Stage 4 (2~3 cells | 4 bays)-construct base slab,Wall & Roof Slab @21d/bay; @2 (was
C11_6C3)
d/w - 10h/d - With 25 1 20-Mar-23 21-Apr-23 21-Mar-23 22-Apr-23 1
WF(Comp. connection with extg. Outfall 6) HK Hols - No B/O periods
310.C.R0.L1230 Complete Connection to Outfall No. 6 (was
C11_6C3)
d/w - 10h/d - With 12 15-Apr-23 28-Apr-23 17-Apr-23 29-Apr-23 1
HK Hols - No B/O periods
310.C.R1.L846 EBC no. 6 - Backfill Zone 4 (was
C11_6C3)
d/w - 10h/d - With 12 2 29-Apr-23 13-May-23 02-May-23 15-May-23 1
HK Hols - No B/O periods
310.C.R1.L858 Remove armour rock & Backfill drainage swale in 3310/6A (after outfall 6 diversion) (was
C11_6C3)
d/w - 10h/d - With 48 1 29-Apr-23 27-Jun-23 02-May-23 28-Jun-23 1
HK Hols - No B/O periods
CC#4.7 - EBC no. 5,6,19 - Stage 5 [Ch.0+428 to 1+215] BC Connection to Extg. done by 3802 at 3310/5 (was C3) 413 5 14-Apr-22 02-Sep-23 03-Feb-23 05-Sep-23 2
310.C.R1.L917.B02 EBC no. 5,6,19 - Form BA8 and grant consent for RC works C01_7 d/w - 10h/d - No HK 7 14-Apr-22 20-Apr-22 04-Apr-23 10-Apr-23 355
Hols - No B/O periods (was
310.C.R1.L919.B02 EBC no. 5,6,19 - Form BA10 and grant consent for RC works C1)
C01_7 d/w - 10h/d - No HK 7 21-Apr-22 27-Apr-22 11-Apr-23 17-Apr-23 355
Hols - No B/O periods (was
C1)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 58 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.R0.L1234 Area 3310/5 Start works C01_7 d/w - 10h/d - No HK 1 11-Jan-23 11-Jan-23 03-Feb-23 03-Feb-23 23
Hols - No B/O periods (was
310.D.R0.L340 Box culvert by Contract <3802> completed in 3310/5 C1)
C01_7 d/w - 10h/d - No HK 0 11-Jan-23 03-Feb-23 23
Hols - No B/O periods (was
310.C.R0.L1222 EBC no. 5,6,19 - Stage 5 - temporary diversion works C1)
C11_6 d/w - 10h/d - With 33 02-Feb-23 11-Mar-23 04-Feb-23 14-Mar-23 2
HK Hols - No B/O periods
310.C.R0.X990 EBC no. 5,6,19 - Stage 5 - excavation [6,816m3 @ 300/m3/d, use 1 WF) (was
C11_6C3)
d/w - 10h/d - With 25 2 13-Mar-23 14-Apr-23 15-Mar-23 17-Apr-23 2
HK Hols - No B/O periods
310.C.R1.L918 EBC no. 5,6,19 - Stage 5 (9 cells | 7 bays) - construct base slab, wall & roof @ 21d/bay, (was
C11_6C3)
d/w - 10h/d - With 81 15-Apr-23 22-Jul-23 18-Apr-23 25-Jul-23 2
use 2 WF HK Hols - No B/O periods
310.C.R0.L1238 Complete Connection to 3802 (Comp Permanent Diversion of BC5,6,19 to BC by Contract (was
C11_6C3)
d/w - 10h/d - With 12 24-Jul-23 05-Aug-23 26-Jul-23 08-Aug-23 2
<3802>) HK Hols - No B/O periods
310.C.R1.L926 Remove armour rock & Backfill drainage swale in 3310/5 (after diversion to BC by (was
C11_6C3)
d/w - 10h/d - With 24 2 07-Aug-23 02-Sep-23 08-Aug-23 05-Sep-23 2
Contract <3802>) HK Hols - No B/O periods
310.C.R1.L838 EBC no. 5,6,19 - Backfill Zone 5 (was
C11_6C3)
d/w - 10h/d - With 24 1 07-Aug-23 02-Sep-23 08-Aug-23 05-Sep-23 2
HK Hols - No B/O periods
CC#4.7 - 3310/5,6,6A,7 - EBC no. 5,6,19 - Metal Work and Gate Installation (was
C11_6C3)
d/w - 10h/d - With HK Hols
60- No B/O 0periods (was
09-Jun-23
C3) 19-Aug-23 27-Jul-23 06-Oct-23 39
310.C.R1.L894 EBC no. 5,6,19 - metal work/ gate installation for desilting chamber C11_6 d/w - 10h/d - With 60 09-Jun-23 19-Aug-23 27-Jul-23 06-Oct-23 39
HK Hols - No B/O periods
CC#04 - 3310/4,9,9A - Aviation Fuel and Hydrant System (AFHS) | Interface Work Area 3310/IA/5-2 (was C3) 547 88 07-Apr-22 06-Feb-24 14-Jun-22 15-Feb-24 6
CC#4 - AFHS - Site Preparation C11_6 d/w - 10h/d - With HK Hols
58- No B/O 0periods (was
07-Apr-22
C3) 18-Jun-22 14-Jun-22 20-Aug-22 53
310.C.EX.U519 3310/IA/5-1 (AFHS Section 1) - Site preparation and liaison with AA for Permit to Work C11_6 d/w - 10h/d - With 58 07-Apr-22 18-Jun-22 14-Jun-22 20-Aug-22 53
HK Hols - No B/O periods
CC#4 - AFHS Section 1 - AFHS [Before Commissioning of the Interim 2RS] (was C3) 165 6 19-Jun-22 04-Jan-23 22-Aug-22 21-Feb-23 37
CC#4 - AFHS Section 1 -South - ISO Chamber C23_4d/w - NOTAM (M,W,Th,Su-01:30-07:30)
20 0 - No HK
25-Sep-22
Hols - With B/O
08-Dec-22
Periods & Flight31-Oct-22
Checks 15-Jan-23 9
310.C.EX.U520 3310/IA/5-1 (AFHS Section 1) - ISO Chamber (ISO-AFL-1) (airside operational area) C23_4d/w - NOTAM 20 25-Sep-22 08-Dec-22 31-Oct-22 15-Jan-23 9
[NOTAM] (M,W,Th,Su-01:30-07:30) -
310.C.EX.U523 3310/IA/5-1 (AFHS Section 1) - ISO Chamber (ISO-AFM-1) (airside operational area) No HK Hols- -NOTAM
C23_4d/w With B/O 20 25-Sep-22 08-Dec-22 31-Oct-22 15-Jan-23 9
[NOTAM] (M,W,Th,Su-01:30-07:30) -
CC#4 - AFHS Section 1 -South - AFHS Pipe (AF-L969 to AF-L820 and AF-M920 to AF-M830) No HK Hols - With B/O 165 6 19-Jun-22 04-Jan-23 22-Aug-22 21-Feb-23 37
CC#4 - AFHS Section 1 -South - AFHS Pipe - VE+ELS Installation 109 6 19-Jun-22 28-Oct-22 22-Aug-22 16-Feb-23 90
310.C.EX.H100.B01 3310/IA/5-1 (AFHS Section 1) - Mobilization + instrumentation + UU Detection (NOTAM) C23_4d/w - NOTAM 12 19-Jun-22 07-Jul-22 22-Aug-22 11-Sep-22 37
(M,W,Th,Su-01:30-07:30) -
310.C.EX.H110.B01 3310/IA/5-1 (AFHS Section 1) - ELS - Install Sheet Pile (746 nos. @15no./day/rig; use No HK Hols- -NOTAM
C23_4d/w With B/O 28 3 10-Jul-22 25-Aug-22 12-Sep-22 11-Dec-22 37
2rigs)(NOTAM) (M,W,Th,Su-01:30-07:30) -
310.C.EX.H125.B01 3310/IA/5-1 (AFHS Section 1) - ELS - Submit Form BA14 No HK d/w
C01_7 Hols- -10h/d
With B/O
- No HK 12 25-Aug-22 05-Sep-22 11-Dec-22 23-Dec-22 109
Hols - No B/O periods (was
310.C.EX.H130.B01 3310/IA/5-1 (AFHS Section 1) - ELS - Submit Form BA8 for excavation C1)
C01_7 d/w - 10h/d - No HK 7 06-Sep-22 12-Sep-22 23-Dec-22 30-Dec-22 109
Hols - No B/O periods (was
310.C.EX.H135.B01 3310/IA/5-1 (AFHS Section 1) - ELS - Submit Form BA10 for excavation C1)
C01_7 d/w - 10h/d - No HK 7 13-Sep-22 19-Sep-22 30-Dec-22 06-Jan-23 109
Hols - No B/O periods (was
310.C.EX.H140.B01 3310/IA/5-1 (AFHS Section 1) - ELS - Excavation and struts installation [6,043m3 C1)
C11_6 d/w - 10h/d - With 32 3 20-Sep-22 28-Oct-22 06-Jan-23 16-Feb-23 90
@200m3/d/2wf, 3 layers @ 6d/layer] HK Hols - No B/O periods
CC#4 - AFHS Section 1 -South - AFHS Pipe - Pipe laying (was
C11_6C3)
d/w - 10h/d - With HK Hols
22- No B/O 0periods (was
08-Dec-22
C3) 04-Jan-23 26-Jan-23 21-Feb-23 37
310.C.EX.U526 3310/IA/5-1 (AFHS Section 1) - AFHS Pipe laying DN600 (AF-L969 to AF-L820) (airside
C11_6 d/w - 10h/d - With 22 08-Dec-22 04-Jan-23 26-Jan-23 21-Feb-23 37
operational area) HK Hols - No B/O periods
310.C.EX.U526.B01 3310/IA/5-1 (AFHS Section 1) - AFHS Pipe laying DN600 (AF-M920 to AF-M830) (airside (was
C11_6C3)
d/w - 10h/d - With 22 08-Dec-22 04-Jan-23 26-Jan-23 21-Feb-23 37
operational area) HK Hols - No B/O periods
CC#4 - AFHS Section 1 - North Section - Temporary Filling Point (Outside Works Area) (was C3) 91 0 26-Oct-22 15-Feb-23 26-Oct-22 22-Mar-23 30
310.C.EX.U488 Commencement of Works (after the Interim Security Fence Completion) C11_6 d/w - 10h/d - With 0 26-Oct-22 26-Oct-22 0
HK Hols - No B/O periods
(was C3)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 59 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.EX.U480 AFHS Section 1 - Construction of Temporary Filling Point at Contract 3310 Area (airside C23_4d/w - NOTAM 28 27-Oct-22 15-Feb-23 12-Jan-23 22-Mar-23 20
operational area) [NOTAM] (M,W,Th,Su-01:30-07:30) -
CC#4 - AFHS Section 1 - Middle Section - AFHS Pipe (AF-L820 to AF-L150 and AF-M830 to AF-M150) No HK Hols - With B/O 107 21 26-Oct-22 04-Mar-23 26-Oct-22 04-Mar-23 0
CC#4 - AFHS Section 1 -Middle - AFHS Pipe - VE+ELS Installation 93 9 26-Oct-22 16-Feb-23 26-Oct-22 16-Feb-23 0
310.C.EX.H200.B01 3310/IA/5-1 (AFHS Section 1) - Mobilization + instrumentation + UU Detection C11_6 d/w - 10h/d - With 12 26-Oct-22 08-Nov-22 26-Oct-22 08-Nov-22 0
HK Hols - No B/O periods
310.C.EX.H207.B01 3310/IA/5-1 (AFHS Section 1) - ELS - Excavation [8,434m3 @600m3/d/wf] (was
C11_6C3)
d/w - 10h/d - With 16 2 09-Nov-22 26-Nov-22 13-Dec-22 31-Dec-22 29
HK Hols - No B/O periods
310.C.EX.H203.B01 3310/IA/5-1 (AFHS Section 1) - ELS - Install Sheet Pile Ch.579-830 (1,255 no. (was
C11_6C3)
d/w - 10h/d - With 25 2 09-Nov-22 07-Dec-22 09-Nov-22 07-Dec-22 0
@15no./d/rig; 4rigs) HK Hols - No B/O periods
310.C.EX.H209.B01 3310/IA/5-1 (AFHS Section 1) - ELS - Install wells (was
C11_6C3)
d/w - 10h/d - With 8 28-Nov-22 07-Dec-22 16-Dec-22 27-Dec-22 16
HK Hols - No B/O periods
310.C.EX.H211.B01 3310/IA/5-1 (AFHS Section 1) - ELS - Pumping test and submit report (was
C01_7C3)
d/w - 10h/d - No HK 6 2 08-Dec-22 13-Dec-22 28-Dec-22 02-Jan-23 20
Hols - No B/O periods (was
310.C.EX.H212.B01 3310/IA/5-1 (AFHS Section 1) - ELS - Submit Form BA14 C1)
C01_7 d/w - 10h/d - No HK 12 08-Dec-22 19-Dec-22 08-Dec-22 19-Dec-22 0
Hols - No B/O periods (was
310.C.EX.H213.B01 3310/IA/5-1 (AFHS Section 1) - ELS - Submit Form BA8 for excavation C1)
C01_7 d/w - 10h/d - No HK 7 20-Dec-22 26-Dec-22 20-Dec-22 26-Dec-22 0
Hols - No B/O periods (was
310.C.EX.H214.B01 3310/IA/5-1 (AFHS Section 1) - ELS - Submit Form BA10 for excavation C1)
C01_7 d/w - 10h/d - No HK 7 27-Dec-22 02-Jan-23 27-Dec-22 02-Jan-23 0
Hols - No B/O periods (was
310.C.EX.H216.B01 3310/IA/5-1 (AFHS Section 1) - ELS - Excavation [43,656m3 @600m3/d/4wf, 3 layers @ C1)
C11_6 d/w - 10h/d - With 36 3 03-Jan-23 16-Feb-23 03-Jan-23 16-Feb-23 0
6d/layer] HK Hols - No B/O periods
CC#4 - AFHS Section 1 -Middle - AFHS Pipe - Pipe laying (was
C11_6C3)
d/w - 10h/d - With HK Hols
34- No B/O12
periods (was
21-Jan-23
C3) 04-Mar-23 21-Jan-23 04-Mar-23 0
310.C.EX.H215.B01 3310/IA/5-1 (AFHS Section 1) - AFHS Pipe laying DN600 (AF-L820 to AF-L150) C11_6 d/w - 10h/d - With 34 6 21-Jan-23 04-Mar-23 21-Jan-23 04-Mar-23 0
HK Hols - No B/O periods
310.C.EX.H220.B01 3310/IA/5-1 (AFHS Section 1) - AFHS Pipe laying DN600 (AF-M830 to AF-M150) (was
C11_6C3)
d/w - 10h/d - With 34 6 21-Jan-23 04-Mar-23 21-Jan-23 04-Mar-23 0
HK Hols - No B/O periods
CC#4 - AFHS Section 1 - North Section - (AF-L150 to AF-L0 & AF-M150 to AF-M0) (was C3) 145 9 26-Oct-22 24-Apr-23 26-Oct-22 24-Apr-23 0
CC#4 - AFHS Section 1 -North - AFHS Pipe - VE+ELS Installation 79 7 26-Oct-22 31-Jan-23 26-Oct-22 31-Jan-23 0
310.C.EX.H225.B01 3310/IA/5-2a (AFHS Section 1) - Mobilization + instrumentation + UU Detection C11_6 d/w - 10h/d - With 8 26-Oct-22 03-Nov-22 26-Oct-22 03-Nov-22 0
HK Hols - No B/O periods
310.C.EX.H232.B01 3310/IA/5-2a (AFHS Section 1) - ELS - Install Sheet Pile (750 no. @15no./d/rig; 3rigs) (was
C11_6C3)
d/w - 10h/d - With 19 2 04-Nov-22 25-Nov-22 04-Nov-22 25-Nov-22 0
HK Hols - No B/O periods
310.C.EX.H233.B01 3310/IA/5-2a (AFHS Section 1) - ELS - Install wells (was
C11_6C3)
d/w - 10h/d - With 8 16-Nov-22 25-Nov-22 06-Dec-22 15-Dec-22 17
HK Hols - No B/O periods
310.C.EX.H234.B01 3310/IA/5-2a (AFHS Section 1) - ELS - Pumping test and submit report (was
C01_7C3)
d/w - 10h/d - No HK 6 2 26-Nov-22 01-Dec-22 16-Dec-22 21-Dec-22 20
Hols - No B/O periods (was
310.C.EX.H236.B01 3310/IA/5-2a (AFHS Section 1) - ELS - Submit Form BA14 C1)
C01_7 d/w - 10h/d - No HK 12 26-Nov-22 07-Dec-22 26-Nov-22 07-Dec-22 0
Hols - No B/O periods (was
310.C.EX.H237.B01 3310/IA/5-2a (AFHS Section 1) - ELS - Submit Form BA8 for excavation C1)
C01_7 d/w - 10h/d - No HK 7 08-Dec-22 14-Dec-22 08-Dec-22 14-Dec-22 0
Hols - No B/O periods (was
310.C.EX.H238.B01 3310/IA/5-2a (AFHS Section 1) - ELS - Submit Form BA10 for excavation C1)
C01_7 d/w - 10h/d - No HK 7 15-Dec-22 21-Dec-22 15-Dec-22 21-Dec-22 0
Hols - No B/O periods (was
310.C.EX.H230.B01 3310/IA/5-2a (AFHS Section 1) - ELS - Excavation [7,331m3 @800m3/d/wf, 3 layers @ C1)
C11_6 d/w - 10h/d - With 30 3 22-Dec-22 31-Jan-23 22-Dec-22 31-Jan-23 0
6d/layer] HK Hols - No B/O periods
CC#4 - AFHS Section 1 -North - AFHS Pipe - Pipe laying (was C3) 72 2 21-Jan-23 24-Apr-23 21-Jan-23 24-Apr-23 0
310.C.EX.U421 3310/IA/5-2a ( AFHS Section 1) - AFHS Pipe DN600 (AF-L150 to AF-L0) + Connect to C11_6 d/w - 10h/d - With 49 21-Jan-23 22-Mar-23 21-Jan-23 22-Mar-23 0
ISO-AFH-2 HK Hols - No B/O periods
310.C.EX.U451 3310/IA/5-2a (AFHS Section 1) - AFHS Pipe DN600 (AF-M150 to AF-M0) + Connect to (was
C11_6C3)
d/w - 10h/d - With 49 21-Jan-23 22-Mar-23 21-Jan-23 22-Mar-23 0
ISO AFA-2 HK Hols - No B/O periods
(was C3)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 60 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.EX.U530 3310/IA/5-2a (AFHS Section 1) - AFHS cabling works, install control panels, and Connect C23_4d/w - NOTAM 28 2 15-Feb-23 24-Apr-23 15-Feb-23 24-Apr-23 0
to ex. sys at ISO-AFL-1 (NOTAM) (M,W,Th,Su-01:30-07:30) -
310.C.EX.U534 3310/IA/5-2a (AFHS Section 1) - Complete of the whole Section 1 Connection (NOTAM) No HK Hols- -NOTAM
C23_4d/w With B/O 0 24-Apr-23 24-Apr-23 0
(M,W,Th,Su-01:30-07:30) -
CC#4 - AFHS Section 2 - AFHS [Before Commissioning of the Interim 2RS] No HK Hols- -NOTAM
C23_4d/w With B/O(M,W,Th,Su-01:30-07:30)
110 12 - No HK
24-Nov-22
Hols - With B/O
27-Aug-23
Periods & Flight18-Dec-22
Checks 18-Sep-23 13
CC#4 - AFHS Section 2 - South - AFHS Pipe (AF-H0 to AF-H60 and AF-A0 to AF-A50) C23_4d/w - NOTAM (M,W,Th,Su-01:30-07:30)
110 12 - No HK
24-Nov-22
Hols - With B/O
27-Aug-23
Periods & Flight18-Dec-22
Checks 18-Sep-23 13
CC#4 - AFHS Section 2 - South - AFHS Pipe - VE+ELS Installation (AF-H0 to AF-H60) C23_4d/w - NOTAM (M,W,Th,Su-01:30-07:30)
52 4 - No HK
24-Nov-22
Hols - With B/O26-Apr-23
Periods & Flight18-Dec-22
Checks 20-Jul-23 37
310.C.EX.H300.B01 3310/IA/5-1 (AFHS Section 2) - Mobilization + instrumentation + UU Detection (NOTAM) C23_4d/w - NOTAM 12 24-Nov-22 14-Dec-22 18-Dec-22 16-Feb-23 13
(M,W,Th,Su-01:30-07:30) -
310.C.EX.H325.B01 3310/IA/5-1 (AFHS Section 2) - ELS - Install Sheet Piles (300 nos. @15no./day/rig; 1 rig) No HK Hols- -NOTAM
C23_4d/w With B/O 22 2 15-Dec-22 05-Mar-23 19-Feb-23 27-Mar-23 13
(NOTAM) (M,W,Th,Su-01:30-07:30) -
310.C.EX.H330.B01 3310/IA/5-1 (AFHS Section 2) - ELS - Excavation and struts installation [525m3 No HK Hols- -NOTAM
C23_4d/w With B/O 18 2 06-Mar-23 26-Apr-23 21-Jun-23 20-Jul-23 37
@200m3/d/wf, 2 layers @ 6d/layer] (NOTAM) (M,W,Th,Su-01:30-07:30) -
CC#4 - AFHS Section 2 - South - AFHS Pipe - VE+ELS Installation (AF-A0 to AF-A50) No HK Hols- -NOTAM
C23_4d/w With B/O(M,W,Th,Su-01:30-07:30)
60 4 - No HK
06-Mar-23
Hols - With B/O30-Jul-23
Periods & Flight29-Mar-23
Checks 21-Aug-23 13
310.C.EX.H310.B01 3310/IA/5-2a (AFHS Section 2) - ELS - Install Sheet Piles (250 nos. @15no./day/rig; 1 C23_4d/w - NOTAM 35 2 06-Mar-23 15-Jun-23 29-Mar-23 09-Jul-23 13
rigs) (NOTAM) (M,W,Th,Su-01:30-07:30) -
310.C.EX.H315.B01 3310/IA/5-2a (AFHS Section 2) - ELS - Excavation and struts installation [875m3 No HK Hols- -NOTAM
C23_4d/w With B/O 25 2 18-Jun-23 30-Jul-23 10-Jul-23 21-Aug-23 13
@200m3/d/wf, 2 layers @ 6d/layer] (NOTAM (M,W,Th,Su-01:30-07:30) -
CC#4 - AFHS Section 2 - South - AFHS Pipe - Pipe laying No HK Hols- -NOTAM
C23_4d/w With B/O(M,W,Th,Su-01:30-07:30)
58 4 - No HK
27-Apr-23
Hols - With B/O
27-Aug-23
Periods & Flight23-Jul-23
Checks 18-Sep-23 13
310.C.EX.U449 3310/IA/5-1 (AFHS Section 2) - o/s WVT -AFHS Pipe laying DN600 (AF-H0 to AF-H60) C23_4d/w - NOTAM 18 2 27-Apr-23 18-Jun-23 23-Jul-23 21-Aug-23 37
(NOTAM (M,W,Th,Su-01:30-07:30) -
310.C.EX.U529 3310/IA/5-2a (AFHS Section 2) - o/s WVT - AFHS Pipe laying DN600 (AF-A0 to AF-A50) No HK Hols- -NOTAM
C23_4d/w With B/O 16 2 31-Jul-23 27-Aug-23 23-Aug-23 18-Sep-23 13
(NOTAM (M,W,Th,Su-01:30-07:30) -
CC#4 - AFHS Section 2 - South Section - AFHS Pipe (AF-H60 to AF-H230 and AF-A50 to AF-A180) No HK Hols - With B/O 316 16 28-Nov-22 19-Dec-23 21-Feb-23 14-Jan-24 19
AFHS Section 2 - South - AFHS Pipe - VE+ELS Installation (AF-H100 to AF-H230 and AF-A50 to AF-A180) 177 14 28-Nov-22 06-Jul-23 21-Feb-23 28-Aug-23 45
310.C.EX.H610.B1 3310/IA/5-2a (AFHS Section 2) - ELS - Pipe Piles (182 nos. @2days/no./rig; 4rigs) C11_6 d/w - 10h/d - With 100 9 28-Nov-22 29-Mar-23 21-Feb-23 24-Jun-23 68
HK Hols - No B/O periods
310.C.EX.H209.B1 3310/IA/5-2a (AFHS Section 2) - ELS - Install wells (was
C11_6C3)
d/w - 10h/d - With 8 20-Mar-23 29-Mar-23 06-Jul-23 15-Jul-23 85
HK Hols - No B/O periods
310.C.EX.H211.B1 3310/IA/5-2a (AFHS Section 2) - ELS - Pumping test and submit report (was
C01_7C3)
d/w - 10h/d - No HK 6 2 30-Mar-23 04-Apr-23 16-Jul-23 21-Jul-23 108
Hols - No B/O periods (was
310.C.EX.H625.B1 3310/IA/5-2a (AFHS Section 2) - ELS - Submit Form BA14 C1)
C01_7 d/w - 10h/d - No HK 12 30-Mar-23 10-Apr-23 26-Jun-23 07-Jul-23 88
Hols - No B/O periods (was
310.C.EX.H630.B1 3310/IA/5-2a (AFHS Section 2) - ELS - Submit Form BA8 for excavation C1)
C01_7 d/w - 10h/d - No HK 7 14-May-23 20-May-23 08-Jul-23 14-Jul-23 55
Hols - No B/O periods (was
310.C.EX.H635.B1 3310/IA/5-2a (AFHS Section 2) - ELS - Submit Form BA10 for excavation C1)
C01_7 d/w - 10h/d - No HK 7 21-May-23 27-May-23 15-Jul-23 21-Jul-23 55
Hols - No B/O periods (was
310.C.EX.H640.B1 3310/IA/5-2a (AFHS Section 2) - ELS - Excavation and struts installation [3,613m3 C1)
C11_6 d/w - 10h/d - With 32 3 29-May-23 06-Jul-23 22-Jul-23 28-Aug-23 45
@800m3/d/wf, 4 layers @ 6d/layer] HK Hols - No B/O periods
CC#4 - AFHS Section 2 - South - AFHS Pipe - Pipe laying (was C3) 139 2 07-Jul-23 19-Dec-23 29-Aug-23 14-Jan-24 19
310.C.EX.U533.B01 3310/IA/5-2a (AFHS Section 2) - o/s WVT - AFHS Pipe laying (AF-H100 to AF-H195) C11_6 d/w - 10h/d - With 40 07-Jul-23 22-Aug-23 29-Aug-23 16-Oct-23 45
HK Hols - No B/O periods
310.C.EX.U535.B01 3310/IA/5-2a (AFHS Section 2) - o/s WVT - AFHS Pipe laying (AF-A50 to AF-A145) (was
C11_6C3)
d/w - 10h/d - With 40 28-Aug-23 14-Oct-23 19-Sep-23 07-Nov-23 19
HK Hols - No B/O periods
310.C.EX.U533 3310/IA/5-2a (AFHS Section 2) - o/s WVT - AFHS Pipe laying (AF-H60 to AF-H100) (was
C11_6C3)
d/w - 10h/d - With 8 2 19-Sep-23 27-Sep-23 23-Nov-23 01-Dec-23 53
HK Hols - No B/O periods
310.C.EX.U453 3310/IA/5-2a - South ELS backfill to +6.5 (was
C11_6C3)
d/w - 10h/d - With 30 16-Oct-23 20-Nov-23 08-Nov-23 12-Dec-23 19
HK Hols - No B/O periods
310.C.EX.U730 3310/IA/5-2a - South ELS Area - complete remaining AGL and Pavement (was
C11_6C3)
d/w - 10h/d - With 25 21-Nov-23 19-Dec-23 13-Dec-23 13-Jan-24 19
HK Hols - No B/O periods
(was C3)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 61 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.EX.U734 3310/IA/5-2a - South ELS Area - achieve KD-5H C01_7 d/w - 10h/d - No HK 0 19-Dec-23 14-Jan-24 26
Hols - No B/O periods (was
CC#4 - AFHS Section 2 - Inside WVT - AFHS Pipe (AF-A180 to AF-A595 and AF-H230 to AF-H645) C1)
C11_6 d/w - 10h/d - With HK Hols
90- No B/O 0periods (was
03-Oct-23
C3) 19-Jan-24 28-Oct-23 15-Feb-24 21
CC#4 - AFHS Section 2 - Inside WVT - AFHS Pipe - Pipe laying C11_6 d/w - 10h/d - With HK Hols
90- No B/O 0periods (was
03-Oct-23
C3) 19-Jan-24 28-Oct-23 15-Feb-24 21
310.C.EX.U430 3310/IA/5-2a (AFHS Section 2) - Plinth for 2 x DN600 AFHS Pipe (inside WVT) C11_6 d/w - 10h/d - With 30 03-Oct-23 07-Nov-23 28-Oct-23 01-Dec-23 21
HK Hols - No B/O periods
310.C.EX.U433 3310/IA/5-2a (AFHS Section 2) - Pipe Laying DN600 AFHS Pipe (AF-A180 ~ A595 ) (was
C11_6C3)
d/w - 10h/d - With 60 08-Nov-23 19-Jan-24 02-Dec-23 15-Feb-24 21
(inside WVT) HK Hols - No B/O periods
310.C.EX.U433.B01 3310/IA/5-2a (AFHS Section 2) - Pipe Laying DN600 AFHS Pipe (AF-H230 ~ H645 ) (was
C11_6C3)
d/w - 10h/d - With 60 08-Nov-23 19-Jan-24 02-Dec-23 15-Feb-24 21
(inside WVT) HK Hols - No B/O periods
CC#4 - AFHS Section 2 - North Section - (AF-H645 to AF-H700 & AF-A595 to AF-A650) (was C3) 267 18 17-Jan-23 09-Dec-23 10-Mar-23 16-Dec-23 6
CC#4 - AFHS Section 2 - North - AFHS Pipe - VE+ELS Installation 153 12 17-Jan-23 26-Jul-23 10-Mar-23 18-Aug-23 20
310.C.EX.H810.B01 3310/IA/5-2a (AFHS Section 2) - ELS - Install Pipe Pile (154 no. @2day/no./rig; 3rigs) C11_6 d/w - 10h/d - With 85 8 17-Jan-23 04-May-23 10-Mar-23 24-Jun-23 42
HK Hols - No B/O periods
310.C.EX.H815.B01 3310/IA/5-2a (AFHS Section 2) - ELS - Install wells (was
C11_6C3)
d/w - 10h/d - With 12 20-Apr-23 04-May-23 03-Jul-23 15-Jul-23 59
HK Hols - No B/O periods
310.C.EX.H820.B01 3310/IA/5-2a (AFHS Section 2) - ELS - Pumping test and submit report (was
C01_7C3)
d/w - 10h/d - No HK 6 2 05-May-23 10-May-23 16-Jul-23 21-Jul-23 72
Hols - No B/O periods (was
310.C.EX.H825.B01 3310/IA/5-2a (AFHS Section 2) - ELS - Submit Form BA14 C1)
C01_7 d/w - 10h/d - No HK 12 05-May-23 16-May-23 26-Jun-23 07-Jul-23 52
Hols - No B/O periods (was
310.C.EX.H830.B01 3310/IA/5-2a (AFHS Section 2) - ELS - Submit Form BA8 for excavation C1) d/w - 10h/d - No HK
C01_7 7 14-Jun-23 20-Jun-23 08-Jul-23 14-Jul-23 24
Hols - No B/O periods (was
310.C.EX.H836.B01 3310/IA/5-2a (AFHS Section 2) - ELS - Submit Form BA10 for excavation C1)
C01_7 d/w - 10h/d - No HK 7 21-Jun-23 27-Jun-23 15-Jul-23 21-Jul-23 24
Hols - No B/O periods (was
310.C.EX.H840.B01 3310/IA/5-2a (AFHS Section 2) - ELS - Excavation and struts installation [3,168m3 C1)
C11_6 d/w - 10h/d - With 24 2 28-Jun-23 26-Jul-23 22-Jul-23 18-Aug-23 20
@200m3/d/wf, 3 layers @ 6d/layer] HK Hols - No B/O periods
CC#4 - AFHS Section 2 - North - AFHS Pipe - Pipe laying (was
C11_6C3)
d/w - 10h/d - With HK Hols
33- No B/O 6periods (was
01-Nov-23
C3) 09-Dec-23 08-Nov-23 16-Dec-23 6
310.C.EX.U427 AFHS - WVT Completion of Zone 6 backfill to +6.0 C11_6 d/w - 10h/d - With 0 01-Nov-23 08-Nov-23 6
HK Hols - No B/O periods
310.C.EX.U443 3310/IA/5-2a (AFHS Section 2) - (o/s WVT) Pipe Laying (AF-H645 ~ H700) + WT-AFH-1 (was
C11_6C3)
d/w - 10h/d - With 33 3 02-Nov-23 09-Dec-23 09-Nov-23 16-Dec-23 6
HK Hols - No B/O periods
310.C.EX.U443.B01 3310/IA/5-2a (AFHS Section 2) - (o/s WVT) Pipe Laying (AF-A595 ~ A650) + WT-AFH-2 (was C11_6C3)
d/w - 10h/d - With 33 3 02-Nov-23 09-Dec-23 09-Nov-23 16-Dec-23 6
HK Hols - No B/O periods
CC#4 - AFHS Section 2 - North Section - (AF-H700 to AF-H910 & AF-A650 to AF-A854) (was
C11_6C3)
d/w - 10h/d - With HK Hols
161- No B/O 6periods (was
27-Jul-23
C3) 06-Feb-24 19-Aug-23 15-Feb-24 6
CC#4 - AFHS Section 2 - North - AFHS Pipe - ELS Installation C11_6 d/w - 10h/d - With HK Hols
32- No B/O 2periods (was
27-Jul-23
C3) 01-Sep-23 19-Aug-23 25-Sep-23 20
310.C.EX.H850.B02 3310/IA/5-2a (AFHS Section 2) - Preparation and Mobilization C11_6 d/w - 10h/d - With 8 27-Jul-23 04-Aug-23 19-Aug-23 28-Aug-23 20
HK Hols - No B/O periods
310.C.EX.H860.B02 3310/IA/5-2a (AFHS Section 2) - ELS - Excavation [2,457m3 @600m3/d/wf, Assumed 3 (was
C11_6C3)
d/w - 10h/d - With 24 2 05-Aug-23 01-Sep-23 29-Aug-23 25-Sep-23 20
layers @ 6d/layer] HK Hols - No B/O periods
CC#4 - AFHS Section 2 - North - AFHS Pipe - Pipe laying (was
C11_6C3)
d/w - 10h/d - With HK Hols
129- No B/O 4periods (was
02-Sep-23
C3) 06-Feb-24 26-Sep-23 15-Feb-24 6
310.C.EX.H900.B02 3310/IA/5-2a (AFHS Section 2) - Construction of WT-AF & VT-AF Pit box C11_6 d/w - 10h/d - With 28 02-Sep-23 06-Oct-23 26-Sep-23 31-Oct-23 20
HK Hols - No B/O periods
310.C.EX.H870.B02 3310/IA/5-2a (AFHS Section 2) - (o/s WVT) Pipe Laying (AF-H700 ~ H910) + ISO-AFH-2 (was
C11_6C3)
d/w - 10h/d - With 23 2 16-Sep-23 14-Oct-23 12-Oct-23 08-Nov-23 20
HK Hols - No B/O periods
310.C.EX.H880.B02 3310/IA/5-2a (AFHS Section 2) - (o/s WVT) Pipe Laying (AF-A650 ~ A854) + ISO-AFA-1 (was
C11_6C3)
d/w - 10h/d - With 22 2 18-Sep-23 14-Oct-23 13-Oct-23 08-Nov-23 20
HK Hols - No B/O periods
310.C.EX.U447 3310/IA/5-2a (AFHS Section 2) - connection to ISO-AFA-1 and ISO-AFH-2 (was
C11_6C3)
d/w - 10h/d - With 30 11-Dec-23 17-Jan-24 18-Dec-23 24-Jan-24 6
HK Hols - No B/O periods
310.C.EX.U444 3310/IA/5-2a (AFHS Section 2) - North ELS backfill to +6.5 (was
C11_6C3)
d/w - 10h/d - With 25 09-Jan-24 06-Feb-24 16-Jan-24 15-Feb-24 6
HK Hols - No B/O periods
(was C3)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 62 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.EX.U461 3310/IA/5-2a (AFHS Section 2) - connection to existing AFHS at ISO-269-17 C11_6 d/w - 10h/d - With 10 18-Jan-24 29-Jan-24 25-Jan-24 05-Feb-24 6
HK Hols - No B/O periods
310.C.EX.U455 3310/IA/5-2a (AFHS Section 2) - Complete connection of AFHS at WVT North (was
C11_6C3)
d/w - 10h/d - With 0 06-Feb-24 15-Feb-24 6
HK Hols - No B/O periods
310.C.EX.U465 3310/IA/5-2a (AFHS Section 2) - complete connection of the whole Section 2 AFHS (was
C11_6C3)
d/w - 10h/d - With 0 06-Feb-24 15-Feb-24 6
HK Hols - No B/O periods
AGL Diversion Works (PS 10.2.41) (was C3) 413 5 07-Jun-21 A 24-Oct-22 01-Jun-22 28-Mar-24 426
Step A - AGL Diversion (Before the Closure of Existing North Runway) 363 5 07-Jun-21 A 24-Aug-22 01-Jun-22 01-Sep-22 7
310.C.EX.L100 Coordinate with AAHK and CAD for Site Access of the Area C11_6 d/w - 10h/d - With 20 07-Jun-21 A 30-Jun-21 A 01-Jun-22 01-Jun-22
HK Hols - No B/O periods
310.C.EX.L110 Step A - 1st Round - Submit Method Statement of Detection of Existing UU Detection and (was
C11_6C3)
d/w - 10h/d - With 25 02-Jul-21 A 10-Aug-21 A 01-Jun-22 01-Jun-22
Existing AGL Diversion Works HK Hols - No B/O periods
310.C.EX.L114 Step A - 1st Round - PM Review Method Statement of Detection of Existing UU Detection (was
C11_6C3)
d/w - 10h/d - With 28 11-Aug-21 A 24-Aug-21 A 01-Jun-22 01-Jun-22
and Existing AGL Diversion Works HK Hols - No B/O periods
310.C.EX.L294 Step A - 2nd Round - Submit Method Statement of Detection of Existing UU Detection (was
C11_6C3)
d/w - 10h/d - With 7 25-Aug-21 A 16-Sep-21 A 01-Jun-22 01-Jun-22
and Existing AGL Diversion Works HK Hols - No B/O periods
310.C.EX.L298 Step A - 2nd Round - PM Review/Approved MS of Detection of Existing UU Detection (was
C11_6C3)
d/w - 10h/d - With 28 17-Sep-21 A 14-Oct-21 A 01-Jun-22 01-Jun-22
and Existing AGL Diversion Works HK Hols - No B/O periods
310.C.EX.L302 Step A - Apply Work Permit (was
C01_7C3)
d/w - 10h/d - No HK 21 02-Oct-21 A 22-Oct-21 A 01-Jun-22 01-Jun-22
Hols - No B/O periods (was
310.C.EX.L306 Step A - Trial Pits & Initial Survey (NOTAM) C1)
C23_4d/w - NOTAM 16 27-Feb-22 A 29-May-22 01-Jun-22 06-Jun-22 5
(M,W,Th,Su-01:30-07:30) -
310.C.EX.L310 Step A - Install New Cable Duct and Cabling (NOTAM) No HK Hols- -NOTAM
C23_4d/w With B/O 50 5 30-May-22 24-Aug-22 08-Jun-22 01-Sep-22 5
(M,W,Th,Su-01:30-07:30) -
310.C.EX.L314 Step A - Ready for Cable Diversion after the Closure of the Existing North Runway No HK Hols- -NOTAM
C23_4d/w With B/O 0 24-Aug-22 01-Sep-22 5
(NOTAM) (M,W,Th,Su-01:30-07:30) -
Step B - AGL Diversion (Before the Closure of Existing North Runway) No HK Hols - With B/O 18 0 01-Sep-22 22-Sep-22 08-Oct-22 28-Oct-22 29
310.C.EX.L124 Step B - Closure of Existing North Runway C01_7 d/w - 10h/d - No HK 0 01-Sep-22 08-Oct-22 37
Hols - No B/O periods (was
310.C.EX.L120 Step B - Divert AGL Cable(Change-Over) + T&C C1)
C11_6 d/w - 10h/d - With 18 01-Sep-22 22-Sep-22 08-Oct-22 28-Oct-22 29
HK Hols - No B/O periods
Step C - AGL Diversion Back to Original Alignment (Before the Opening for 3RS) (was
C11_6C3)
d/w - 10h/d - With HK Hols
25- No B/O 0periods (was
23-Sep-22
C3) 24-Oct-22 29-Feb-24 28-Mar-24 426
310.C.EX.L130 Step C - Divert Back AGL to Original Alignment (after modification of centre runway is C11_6 d/w - 10h/d - With 25 23-Sep-22 24-Oct-22 29-Feb-24 28-Mar-24 426
completed) HK Hols - No B/O periods
ES (Interconnect Cable for AGL System) - Power Cable bet, Vault C and D (was C3) 257 0 23-Apr-22 01-Mar-23 07-Jul-23 28-Mar-24 321
310.C.WS.U000.B02 Coordinate with AAHK and TSD for the Detailed Information of the Scope of Works (i.e. C01_7 d/w - 10h/d - No HK 120 23-Apr-22 20-Aug-22 07-Jul-23 03-Nov-23 440
Meetings, SQs) Hols - No B/O periods (was
310.C.WS.U001.B02 Cross Passage Taxiway B6 & T - Carry Out Survey Check for Cable Ducts and Pits C1)
C23_4d/w - NOTAM 12 23-May-22 12-Jun-22 14-Aug-23 03-Sep-23 184
(NOTAM) (M,W,Th,Su-01:30-07:30) -
310.C.WS.U005.B02 Cross Passage Taxiway B6 & T - Carry Out Cable Detection and Trial Pits (NOTAM) No HK Hols- -NOTAM
C23_4d/w With B/O 12 13-Jun-22 03-Jul-22 04-Sep-23 24-Sep-23 184
(M,W,Th,Su-01:30-07:30) -
West Side Area No HK d/w
C11_6 Hols- -10h/d
With B/O
- With HK Hols
148- No B/O 0periods (was
01-Sep-22
C3) 01-Mar-23 29-Sep-23 28-Mar-24 321
310.C.WS.U010.B02 West Side Area - Carry Out Survey Check for Cable Ducts and Pits C11_6 d/w - 10h/d - With 14 01-Sep-22 17-Sep-22 29-Sep-23 17-Oct-23 321
HK Hols - No B/O periods
310.C.WS.U015.B02 West Side Area - Carry Out Cable Detection and Trial Pits (was
C11_6C3)
d/w - 10h/d - With 14 19-Sep-22 06-Oct-22 18-Oct-23 03-Nov-23 321
HK Hols - No B/O periods
310.C.WS.U020.B02 West Side Area - ES - New Power Cable to Vault D (was
C11_6C3)
d/w - 10h/d - With 120 07-Oct-22 01-Mar-23 04-Nov-23 28-Mar-24 321
HK Hols - No B/O periods
East Side Area (was
C11_6C3)
d/w - 10h/d - With HK Hols
148- No B/O 0periods (was
01-Sep-22
C3) 01-Mar-23 29-Sep-23 28-Mar-24 321
310.C.WS.U025.B02 East Side Area - Carry Out Survey Check for Cable Ducts and Pits C11_6 d/w - 10h/d - With 14 01-Sep-22 17-Sep-22 29-Sep-23 17-Oct-23 321
HK Hols - No B/O periods
(was C3)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 63 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.WS.U030.B02 East Side Area - Carry Out Cable Detection and Trial Pits C11_6 d/w - 10h/d - With 14 19-Sep-22 06-Oct-22 18-Oct-23 03-Nov-23 321
HK Hols - No B/O periods
310.C.WS.U035.B02 East Side Area - ES - New Power Cable to Vault C (was
C11_6C3)
d/w - 10h/d - With 120 07-Oct-22 01-Mar-23 04-Nov-23 28-Mar-24 321
HK Hols - No B/O periods
CC#4 - 3310/12 - West Support Area Civil Works (was C3) 415 0 04-Jul-22 21-Nov-23 04-Jul-22 24-Aug-24 225
310.C.WS.U002 3310/12 - Site Access C11_6 d/w - 10h/d - With 0 04-Jul-22* 04-Jul-22 0
HK Hols - No B/O periods
310.C.WS.U005 WSA DN - GI works & submit report (was
C11_6C3)
d/w - 10h/d - With 21 04-Jul-22 27-Jul-22 25-Jul-22 17-Aug-22 18
HK Hols - No B/O periods
310.C.WS.U006 WSA DN - GI works - PM review (was
C11_6C3)
d/w - 10h/d - With 28 28-Jul-22 29-Aug-22 18-Aug-22 20-Sep-22 18
HK Hols - No B/O periods
310.C.WS.U010 WSA DN - Submit BA8 consent application (was
C01_7C3)
d/w - 10h/d - No HK 7 30-Aug-22 05-Sep-22 21-Sep-22 27-Sep-22 22
Hols - No B/O periods (was
310.C.WS.U014 WSA DN - Submit BA10 notice of commencement of work C1)
C01_7 d/w - 10h/d - No HK 7 06-Sep-22 12-Sep-22 28-Sep-22 04-Oct-22 22
Hols - No B/O periods (was
CC#4 - 3310/12 - Zone 16DD C1)
C11_6 d/w - 10h/d - With HK Hols
95- No B/O 0periods (was
13-Sep-22
C3) 05-Jan-23 05-Oct-22 18-Mar-23 59
Zone 16DD - Drainage C11_6 d/w - 10h/d - With HK Hols
80- No B/O 0periods (was
13-Sep-22
C3) 16-Dec-22 05-Oct-22 07-Jan-23 17
310.C.WS.U018 WSA DN - drainage DN2100 (L: 175m) + manholes (5 Nos) at GSE Area C11_6 d/w - 10h/d - With 60 13-Sep-22 23-Nov-22 05-Oct-22 13-Dec-22 17
HK Hols - No B/O periods
310.C.WS.U022 WSA DN - drainage DN1200/1050 (L:215m; DN750 (L: 48m) + manholes (3 nos) at (was
C11_6C3)
d/w - 10h/d - With 70 13-Sep-22 05-Dec-22 05-Oct-22 24-Dec-22 17
Forecourt Area HK Hols - No B/O periods
310.C.WS.U026 WSA DN - drainage DN2100/1800/1650/1350/900 (L:233m) + manholes (9 nos) @ (was
C11_6C3)
d/w - 10h/d - With 70 24-Sep-22 16-Dec-22 17-Oct-22 07-Jan-23 17
Landside Road HK Hols - No B/O periods
Zone 16DD - Hydraulic Services (was
C11_6C3)
d/w - 10h/d - With HK Hols
30- No B/O 0periods (was
12-Nov-22
C3) 16-Dec-22 08-Dec-22 13-Jan-23 22
310.C.WS.U124 WSA PSFH - DN150 pipe laying + PWGV + PWSH & connect to Contract <3303> water C11_6 d/w - 10h/d - With 30 12-Nov-22 16-Dec-22 08-Dec-22 13-Jan-23 22
pipe HK Hols - No B/O periods
Zone 16DD - CLP (was
C11_6C3)
d/w - 10h/d - With HK Hols
85- No B/O 0periods (was
13-Sep-22
C3) 22-Dec-22 19-Oct-22 18-Mar-23 69
310.C.WS.U082 WSA CLP - 132KV CLP Cable Duct ( 2x 234m) w/ Joint Bay C11_6 d/w - 10h/d - With 70 13-Sep-22 05-Dec-22 25-Oct-22 16-Jan-23 34
HK Hols - No B/O periods
310.C.WS.U062 WSA CLP - 11KV CLP Cable Duct (2 x 385m) (was
C11_6C3)
d/w - 10h/d - With 50 24-Sep-22 23-Nov-22 19-Oct-22 15-Dec-22 19
HK Hols - No B/O periods
310.C.WS.U066 WSA CLP - 11KV CLP Cable Duct (2 x 285m) (was
C11_6C3)
d/w - 10h/d - With 50 08-Oct-22 05-Dec-22 31-Oct-22 28-Dec-22 19
HK Hols - No B/O periods
310.C.WS.U070 WSA CLP - 11KV CLP Cable Duct (2 x 328m) (was
C11_6C3)
d/w - 10h/d - With 50 08-Oct-22 05-Dec-22 31-Oct-22 28-Dec-22 19
HK Hols - No B/O periods
310.C.WS.U074 WSA CLP - 11KV CLP Cable Duct (1 x 443m) (was
C11_6C3)
d/w - 10h/d - With 45 26-Oct-22 16-Dec-22 17-Nov-22 10-Jan-23 19
HK Hols - No B/O periods
310.C.WS.U078 WSA CLP - 11KV CLP Cable Duct (1 x 130m) (was
C11_6C3)
d/w - 10h/d - With 30 18-Nov-22 22-Dec-22 10-Dec-22 16-Jan-23 19
HK Hols - No B/O periods
310.C.WS.U332.B01 Achieved KD-04 - WSA 132kv CLP ducts and drawpits (was
C11_6C3)
d/w - 10h/d - With 0 05-Dec-22 18-Mar-23 84
HK Hols - No B/O periods
Zone 16DD - Power/Comms/Tel (was
C11_6C3)
d/w - 10h/d - With HK Hols
60- No B/O 0periods (was
26-Oct-22
C3) 05-Jan-23 17-Nov-22 31-Jan-23 19
310.C.WS.U104 WSA Comm/Tel - duct with concrete surround and drawpits C11_6 d/w - 10h/d - With 50 26-Oct-22 22-Dec-22 17-Nov-22 16-Jan-23 19
HK Hols - No B/O periods
310.C.WS.U102 WSA Power - 2x2 200mm Power Cable Duct and drawpits (was
C11_6C3)
d/w - 10h/d - With 50 26-Oct-22 22-Dec-22 17-Nov-22 16-Jan-23 19
HK Hols - No B/O periods
310.C.WS.U136 WSA Comm/Tel - System Cable installation and connection (was
C11_6C3)
d/w - 10h/d - With 30 30-Nov-22 05-Jan-23 22-Dec-22 31-Jan-23 19
HK Hols - No B/O periods
CC#4 - 3310/12 - Zone 16DB (was
C11_6C3)
d/w - 10h/d - With HK Hols
110- No B/O 0periods (was
24-Sep-22
C3) 07-Feb-23 17-Oct-22 07-Mar-23 24
Zone 16DB - Drainage C11_6 d/w - 10h/d - With HK Hols
90- No B/O 0periods (was
24-Sep-22
C3) 11-Jan-23 17-Oct-22 17-Feb-23 29

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 64 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.WS.U038 WSA DN - drainage DN1950/1350 (L:315m) + manholes (3nos) C11_6 d/w - 10h/d - With 75 24-Sep-22 22-Dec-22 17-Oct-22 13-Jan-23 17
HK Hols - No B/O periods
310.C.WS.U042 WSA DN - drainage DN450/1350 (L:29m) + manholes (2nos) (was
C11_6C3)
d/w - 10h/d - With 30 18-Nov-22 22-Dec-22 08-Dec-22 13-Jan-23 17
HK Hols - No B/O periods
310.C.WS.U046 WSA DN - drainage DN900/750 (L:55m) + manholes (3nos) (was
C11_6C3)
d/w - 10h/d - With 45 18-Nov-22 11-Jan-23 22-Dec-22 17-Feb-23 29
HK Hols - No B/O periods
Zone 16DD - Hydraulic Services (was
C11_6C3)
d/w - 10h/d - With HK Hols
20- No B/O 0periods (was
23-Dec-22
C3) 17-Jan-23 14-Jan-23 09-Feb-23 17
310.C.WS.U128 WSA PSFH - DN150 pipe laying + PWGV + PWSH & connect to Contract <3303> water C11_6 d/w - 10h/d - With 20 23-Dec-22 17-Jan-23 14-Jan-23 09-Feb-23 17
pipe HK Hols - No B/O periods
Zone 16DB - CLP (was
C11_6C3)
d/w - 10h/d - With HK Hols
60- No B/O 0periods (was
24-Nov-22
C3) 07-Feb-23 22-Dec-22 07-Mar-23 24
310.C.WS.U058 WSA CLP - 11KV CLP Cable Duct (L:695m) C11_6 d/w - 10h/d - With 60 24-Nov-22 07-Feb-23 22-Dec-22 07-Mar-23 24
HK Hols - No B/O periods
Zone 16DB - Power/Comms/Tel (was
C11_6C3)
d/w - 10h/d - With HK Hols
65- No B/O 0periods (was
01-Nov-22
C3) 17-Jan-23 25-Nov-22 09-Feb-23 17
310.C.WS.U108 WSA Power - 2x2 200mm Power Cable Duct and drawpits C11_6 d/w - 10h/d - With 45 01-Nov-22 22-Dec-22 25-Nov-22 18-Jan-23 21
HK Hols - No B/O periods
310.C.WS.U112 WSA Comm/Tel - duct with concrete surround and drawpits (was
C11_6C3)
d/w - 10h/d - With 45 10-Nov-22 03-Jan-23 05-Dec-22 31-Jan-23 21
HK Hols - No B/O periods
310.C.WS.U132 WSA Comm/Tel - System Cable installation and connection (was
C11_6C3)
d/w - 10h/d - With 20 23-Dec-22 17-Jan-23 14-Jan-23 09-Feb-23 17
HK Hols - No B/O periods
CC#4 - 3310/12 - Zone 17CC (was
C11_6C3)
d/w - 10h/d - With HK Hols
137- No B/O 0periods (was
13-Sep-22
C3) 27-Feb-23 13-Oct-22 18-Mar-23 17
Zone 17CC - Drainage C11_6 d/w - 10h/d - With HK Hols
80- No B/O 0periods (was
13-Sep-22
C3) 16-Dec-22 13-Oct-22 16-Jan-23 24
310.C.WS.U030 WSA DN - drainage DN1800/1350/1050 (L:571m) + manhole (6 nos) at Maintenance C11_6 d/w - 10h/d - With 80 13-Sep-22 16-Dec-22 13-Oct-22 16-Jan-23 24
Hanger HK Hols - No B/O periods
Zone 17CC - CLP (was
C11_6C3)
d/w - 10h/d - With HK Hols
80- No B/O 0periods (was
24-Sep-22
C3) 29-Dec-22 17-Nov-22 31-Jan-23 24
310.C.WS.U090 WSA CLP - 11KV CLP Cable Duct ( 2 x 150m) C11_6 d/w - 10h/d - With 60 24-Sep-22 05-Dec-22 17-Nov-22 31-Jan-23 44
HK Hols - No B/O periods
310.C.WS.U034 WSA DN - Oil Separator DN450 (L:169m) + manhole (4 nos) at Maintenance Apron (was
C11_6C3)
d/w - 10h/d - With 60 20-Oct-22 29-Dec-22 17-Nov-22 31-Jan-23 24
HK Hols - No B/O periods
310.C.WS.U094 WSA CLP - 11KV CLP Cable Duct ( 1 x 171m) (was
C11_6C3)
d/w - 10h/d - With 45 07-Nov-22 29-Dec-22 05-Dec-22 31-Jan-23 24
HK Hols - No B/O periods
Zone 17CC- Power/Comms/Tel (was
C11_6C3)
d/w - 10h/d - With HK Hols
65- No B/O 0periods (was
08-Dec-22
C3) 27-Feb-23 07-Jan-23 18-Mar-23 17
310.C.WS.U116 WSA Power - 1x1 200mm Power Cable Duct and drawpits C11_6 d/w - 10h/d - With 18 08-Dec-22 29-Dec-22 07-Jan-23 31-Jan-23 24
HK Hols - No B/O periods
310.C.WS.U120 WSA Comm/Tel - duct with concrete surround and drawpits (was
C11_6C3)
d/w - 10h/d - With 30 04-Jan-23 10-Feb-23 01-Feb-23 07-Mar-23 21
HK Hols - No B/O periods
310.C.WS.U118 WSA Power - 2x2- 150mm Power Cable Duct and drawpits (was
C11_6C3)
d/w - 10h/d - With 14 18-Jan-23 06-Feb-23 10-Feb-23 25-Feb-23 17
HK Hols - No B/O periods
310.C.WS.U140 WSA Comm/Tel - System Cable installation and connection (was
C11_6C3)
d/w - 10h/d - With 18 07-Feb-23 27-Feb-23 27-Feb-23 18-Mar-23 17
HK Hols - No B/O periods
CC#4 - 3310/12 - Zone 17CA (was
C11_6C3)
d/w - 10h/d - With HK Hols
30- No B/O 0periods (was
23-Dec-22
C3) 01-Feb-23 19-Jan-23 25-Feb-23 21
310.C.WS.U050 WSA DN - drainage DN1200/1050 (L:170m) + manholes (1 nos) C11_6 d/w - 10h/d - With 30 23-Dec-22 01-Feb-23 19-Jan-23 25-Feb-23 21
HK Hols - No B/O periods
310.C.WS.U054 WSA DN - drainage DN450 (L:203m) + manholes (4 nos) (was
C11_6C3)
d/w - 10h/d - With 30 23-Dec-22 01-Feb-23 19-Jan-23 25-Feb-23 21
HK Hols - No B/O periods
3310/12 Airside and Landside Road Works (was
C11_6C3)
d/w - 10h/d - With HK Hols
165- No B/O 0periods (was
06-May-23
C3) 21-Nov-23 03-Feb-24 24-Aug-24 225
310.C.WS.U300 3310/12 (Zone 16D) - Landside WSA 003 Road - kerb, SB, BC, WC (L: 450m; 1710m3) C11_6 d/w - 10h/d - With 30 06-May-23 10-Jun-23 03-Feb-24 11-Mar-24 225
HK Hols - No B/O periods
310.C.WS.U308 3310/12 (Zone 16D) - Landside WSA 006 Road - kerb,SB, BC, WC (L: 55m; 284m3) (was
C11_6C3)
d/w - 10h/d - With 20 12-Jun-23 06-Jul-23 12-Mar-24 08-Apr-24 225
HK Hols - No B/O periods
310.C.WS.U304 3310/12 (Zone 16D) - Landside WSA 003 Road - road lighting, road markings (was
C11_6C3)
d/w - 10h/d - With 45 12-Jun-23 04-Aug-23 18-Mar-24 14-May-24 230
HK Hols - No B/O periods
(was C3)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 65 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.WS.U312 3310/12 (Zone 16D) - Landside WSA 006 Road - road lighting, road markings C11_6 d/w - 10h/d - With 30 07-Jul-23 10-Aug-23 09-Apr-24 14-May-24 225
HK Hols - No B/O periods
310.C.WS.U316 3310/12 (Zone 16D) - Airside WSA 002 Road - kerb,SB, BC, WC (L: 417m; 1963m3) (was
C11_6C3)
d/w - 10h/d - With 30 11-Aug-23 14-Sep-23 16-May-24 20-Jun-24 225
HK Hols - No B/O periods
310.C.WS.U324 3310/12 (Zone 16D) - Airside WSA 005 Road - kerb, SB, BC, WC (L: 112m; 717m3) (was
C11_6C3)
d/w - 10h/d - With 20 15-Sep-23 10-Oct-23 21-Jun-24 15-Jul-24 225
HK Hols - No B/O periods
310.C.WS.U320 3310/12 (Zone 16D) - Airside WSA 002 Road - road lighting, road markings (was
C11_6C3)
d/w - 10h/d - With 45 15-Sep-23 09-Nov-23 04-Jul-24 24-Aug-24 235
HK Hols - No B/O periods
310.C.WS.U328 3310/12 (Zone 16D) - Airside WSA 005 Road - road lighting, road markings (was
C11_6C3)
d/w - 10h/d - With 35 11-Oct-23 21-Nov-23 16-Jul-24 24-Aug-24 225
HK Hols - No B/O periods
CC#4 - Interim Security Fence (Interim 2RS) (was C3) 902 0 14-Jun-21 A 25-Jun-24 06-Apr-22 25-Aug-24 51
CC#4 - Submission and Permit 319 0 14-Jun-21 A 16-Jun-22 16-May-22 10-Jul-22 19
310.U.RC.C002 Prepare and submit Method Statement of Installation of Int. Sec. Fence and associated C01_7 d/w - 10h/d - No HK 28 14-Jun-21 A 20-Sep-21 A 08-Jun-22 08-Jun-22
works Hols - No B/O periods (was
310.U.RC.C004 PM. AP. RSE. RGE review and approve Method Statement of Installation of Int. Sec. C1)
C01_7 d/w - 10h/d - No HK 28 18-Aug-21 A 29-Sep-21 A 15-Jun-22 15-Jun-22
Fence and associated works Hols - No B/O periods (was
310.U.RC.C008 Prepare and submit proposed alignment of Int. Sec. Fence and location of Guard Post to C1)
C01_7 d/w - 10h/d - No HK 28 24-Mar-22 A 27-Apr-22 16-May-22 12-Jun-22 46
PM,AP,RSE, RGE Hols - No B/O periods (was
310.U.RC.C016 Prepare and submit proposed monitoring points location to PM. AP. RSE. RGE C1)
C01_7 d/w - 10h/d - No HK 28 31-Mar-22 27-Apr-22 16-May-22 12-Jun-22 46
Hols - No B/O periods (was
310.U.RC.C012 PM, AP, RSE, RGE, review and approve proposed alignment of Int. Sec. Fence and C1)
C01_7 d/w - 10h/d - No HK 28 28-Apr-22 25-May-22 13-Jun-22 10-Jul-22 46
location of Guard Post Hols - No B/O periods (was
310.U.RC.C020 PM. AP. RSE. RGE. review and approve propose location of monitoring points C1)
C01_7 d/w - 10h/d - No HK 28 28-Apr-22 25-May-22 13-Jun-22 10-Jul-22 46
Hols - No B/O periods (was
310.U.RC.C026 Apply Work Permit (Int. Security Fence) C1)
C11_6 d/w - 10h/d - With 21 23-May-22 16-Jun-22 15-Jun-22 09-Jul-22 19
HK Hols - No B/O periods
CC#4 - Preparation Works Before Interim 2RS (was C3) 131 0 17-Feb-22 A 04-Sep-22 06-Apr-22 30-Oct-22 45
310.C.RC.C000 Carry out survey check of existing AGL,/MAGS and above ground structure [NOTAM] C23_4d/w - NOTAM 21 17-Feb-22 A 31-Mar-22 06-Apr-22 10-Apr-22 5
(M,W,Th,Su-01:30-07:30) -
310.C.RC.C014 Interim Sec. Fence - Delivery of Materials to site storage area No HK d/w
C01_7 Hols- -10h/d
With B/O
- No HK 28 23-May-22 19-Jun-22 07-Jun-22 04-Jul-22 15
Hols - No B/O periods (was
310.C.RC.C008 Interim Sec. Fence - Setting out alignment of marker board and Interim Sec. Fence C1)
C23_4d/w - NOTAM 30 19-Jun-22 08-Aug-22 11-Jul-22 31-Aug-22 13
[NOTAM] (M,W,Th,Su-01:30-07:30) -
310.C.RC.C004 Interim Sec. Fence - Install monitoring points [NOTAM] No HK Hols- -NOTAM
C23_4d/w With B/O 30 23-Jun-22 14-Aug-22 11-Jul-22 31-Aug-22 10
(M,W,Th,Su-01:30-07:30) -
Area 2a No HK d/w
C01_7 Hols- -10h/d
With B/O
- No HK Hols15
- No B/O periods
0 (was21-Aug-22
C1) 04-Sep-22 16-Oct-22 30-Oct-22 56
310.C.RC.C100.B01 Area 2a - Implement Closure to Taxiway B (bet. Taxiway A1 - Taxilane M & bet. Taxilane C01_7 d/w - 10h/d - No HK 0 21-Aug-22 16-Oct-22 56
M - Taxilane N) Hols - No B/O periods (was
310.C.RC.C105.B01 Area 2a - Install Marker Board C1)
C01_7 d/w - 10h/d - No HK 1 21-Aug-22 21-Aug-22 16-Oct-22 16-Oct-22 56
Hols - No B/O periods (was
310.C.RC.C110.B01 Area 2a - Install Concrete Block ELS for Pit Hydrant C1)
C01_7 d/w - 10h/d - No HK 5 22-Aug-22 26-Aug-22 17-Oct-22 21-Oct-22 56
Hols - No B/O periods (was
310.C.RC.C115.B01 Area 2a - Levelling Work + Footing Installation C1)
C01_7 d/w - 10h/d - No HK 13 22-Aug-22 03-Sep-22 17-Oct-22 29-Oct-22 56
Hols - No B/O periods (was
310.C.RC.C145.B01 Area 2a - Remove Marker Board and Open Taxiway B (bet. Taxiway A1 - Taxilane M & C1)
C01_7 d/w - 10h/d - No HK 1 04-Sep-22 04-Sep-22 30-Oct-22 30-Oct-22 56
bet. Taxilane M - Taxilane N) Hols - No B/O periods (was
Area 2b C1) 70 0 29-May-22 20-Aug-22 12-Sep-22 15-Oct-22 45
310.C.RC.C120.B01 Trial Pit (Area 2a ~ 5) [NOTAM] C23_4d/w - NOTAM 8 29-May-22 09-Jun-22 12-Sep-22 25-Sep-22 61
(M,W,Th,Su-01:30-07:30) -
310.C.RC.C125.B01 Area 2b - Implement Closure to Taxiway B (bet. Taxiway A5 - Taxilane P) No HK d/w
C01_7 Hols- -10h/d
With B/O
- No HK 0 17-Aug-22* 12-Oct-22 56
Hols - No B/O periods (was
C1)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 66 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.RC.C130.B01 Area 2b - Install Marker Board C01_7 d/w - 10h/d - No HK 1 17-Aug-22 17-Aug-22 12-Oct-22 12-Oct-22 56
Hols - No B/O periods (was
310.C.RC.C135.B01 Area 2a - Levelling Work C1)
C01_7 d/w - 10h/d - No HK 2 18-Aug-22 19-Aug-22 13-Oct-22 14-Oct-22 56
Hols - No B/O periods (was
310.C.RC.C140.B01 Area 2a - Remove Marker Board and Open Taxiway B (bet. Taxiway A5 - Taxilane P) C1)
C01_7 d/w - 10h/d - No HK 1 20-Aug-22 20-Aug-22 15-Oct-22 15-Oct-22 56
Hols - No B/O periods (was
Area 6, 7 and 8 C1)
C23_4d/w - NOTAM (M,W,Th,Su-01:30-07:30)
56 0 - No HK
03-Apr-22
Hols - With B/O
18-Aug-22
Periods & Flight17-Jul-22
Checks 11-Sep-22 13
310.C.RC.C150.B01 Trial Pit (Area 6 ~ 8) [NOTAM] C23_4d/w - NOTAM 8 03-Apr-22 26-May-22 29-Aug-22 11-Sep-22 61
(M,W,Th,Su-01:30-07:30) -
310.C.RC.C155.B01 Area 6 ~ 8 - Levelling works [NOTAM] No HK Hols- -NOTAM
C23_4d/w With B/O 28 03-Jul-22 18-Aug-22 17-Jul-22 01-Sep-22 8
(M,W,Th,Su-01:30-07:30) -
CC#4 - Stage 1 - Installation Works No HK Hols - With B/O 44 0 01-Sep-22 25-Oct-22 01-Sep-22 26-Oct-22 1
310.C.RC.C012 Commissioning of New North Runway Change Over (Assumed 1 Sep 22 1:30am) C23_4d/w - NOTAM 0 01-Sep-22* 01-Sep-22 0
(NOTAM (M,W,Th,Su-01:30-07:30) -
310.C.RC.C016 ESA - Interim Sec. Fence - install Marker Boards (ESA: 5 WFs) [NOTAM] No HK Hols- -NOTAM
C23_4d/w With B/O 1 01-Sep-22 01-Sep-22 01-Sep-22 01-Sep-22 0
(M,W,Th,Su-01:30-07:30) -
310.C.RC.C016.B01 WSA - Interim Sec. Fence - install Marker Boards (WSA: 5 WFs) [NOTAM] No HK Hols- -NOTAM
C23_4d/w With B/O 1 01-Sep-22 01-Sep-22 01-Sep-22 01-Sep-22 0
(M,W,Th,Su-01:30-07:30) -
310.C.RC.C032 WSA - Interim Sec. Fence (normal days) - install Int. Sec. Fence (approx. L= 2628M, 3 No HK d/w
C01_7 Hols- -10h/d
With B/O
- No HK 20 01-Sep-22 20-Sep-22 01-Sep-22 20-Sep-22 0
WFs)(& form temporary airside rd) Hols - No B/O periods (was
310.C.RC.C068 ESA - Interim Sec. Fence (normal day) - install Int. Sec. Fence (approx. L=1798m, 2 C1)
C01_7 d/w - 10h/d - No HK 20 01-Sep-22 20-Sep-22 01-Sep-22 20-Sep-22 0
WFs)(& form temporary airside rd) Hols - No B/O periods (was
310.C.RC.C020 WSA - Interim Sec. Fence (NOTAM) - install Int. Sec. Fence (approx. L=364m, 2 WF) C1)
C23_4d/w - NOTAM 13 04-Sep-22 25-Sep-22 04-Sep-22 25-Sep-22 0
[NOTAM](& form temporary airside rd) (M,W,Th,Su-01:30-07:30) -
310.C.RC.C064 ESA - Interim Sec. Fence (NOTAM) - install Int. Sec. Fence (approx. L=825m, 4 WFs) No HK Hols- -NOTAM
C23_4d/w With B/O 13 04-Sep-22 25-Sep-22 04-Sep-22 25-Sep-22 0
[NOTAM](& form temporary airside rd) (M,W,Th,Su-01:30-07:30) -
310.C.RC.C073 WSA - Commencement of Interim Sec. Fence - IDSS No HK d/w
C01_7 Hols- -10h/d
With B/O
- No HK 0 21-Sep-22 21-Sep-22 0
Hols - No B/O periods (was
310.C.RC.C074 ESA - Commencement of Interim Sec. Fence - IDSS C1)
C01_7 d/w - 10h/d - No HK 0 21-Sep-22 21-Sep-22 0
Hols - No B/O periods (was
310.C.RC.C075 WSA - Completion of Interim Sec. Fence - IDSS C1)
C01_7 d/w - 10h/d - No HK 0 11-Oct-22 11-Oct-22 0
Hols - No B/O periods (was
310.C.RC.C096 ESA - Completion of Interim Sec. Fence - IDSS C1)
C01_7 d/w - 10h/d - No HK 0 11-Oct-22 11-Oct-22 0
Hols - No B/O periods (was
310.C.RC.C056 Interim Sec. Fence - Testing and Commissioning C1)
C01_7 d/w - 10h/d - No HK 14 12-Oct-22 25-Oct-22 12-Oct-22 25-Oct-22 0
Hols - No B/O periods (was
310.C.RC.C060 Achieved Interim Security Fence (PS 10.2.47 within 8wks after commissioning of new C1)
C01_7 d/w - 10h/d - No HK 0 25-Oct-22 26-Oct-22 1
North Runway) Hols - No B/O periods (was
CC#4 - Stage 2 - Installation Works C1) 47 0 14-Oct-23 10-Dec-23 06-Nov-23 25-Aug-24 209
310.C.RC.C080 3310/3 EVT - Completion of Backfill of Zone 2 Eastern Vehicular Tunnel for Stage 2 C11_6 d/w - 10h/d - With 0 14-Oct-23 06-Nov-23 18
Interim Security Fence HK Hols - No B/O periods
310.C.RC.C088 Interim Sec. Fence (Stage 2) - remove Stage 1 Interim Sec, Fence and make good of the (was C3) - NOTAM
C23_4d/w 2 23-Nov-23 26-Nov-23 10-Dec-23 11-Dec-23 9
area [NOTAM] (M,W,Th,Su-01:30-07:30) -
310.C.RC.C092 c. Fence (Stage 2) - Complete Stage 2 Interim Security Fence & continue pavement /AGL No HK d/w
C11_6 Hols- -10h/d
With B/O
- With 0 27-Nov-23 11-Dec-23 13
works 2 EVT South HK Hols - No B/O periods
310.C.EX.W512 Remove temporary deck along Taxiway B (3302 interface) PS 10.2.58) (NOTAM) (was C3) - NOTAM
C23_4d/w 7 29-Nov-23 10-Dec-23 14-Aug-24 25-Aug-24 100
(M,W,Th,Su-01:30-07:30) -
CC#4 - Demolish Interim Security Fence No HK d/w
C01_7 Hols- -10h/d
With B/O
- No HK Hols56
- No B/O periods
0 (was01-May-24
C1) 25-Jun-24 03-May-24 25-Aug-24 61
310.C.RC.C067 Remove Interim Security Fence and Marker Boards and reinstate the area (8 wks before C01_7 d/w - 10h/d - No HK 56 01-May-24 25-Jun-24 03-May-24 27-Jun-24 2
commissioning of Centre Runway) Hols - No B/O periods (was
C1)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 67 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.RC.C071 Vacate Work Area 3310/2 C01_7 d/w - 10h/d - No HK 0 25-Jun-24 25-Aug-24 61
Hols - No B/O periods (was
CC#4 - Permanent Security Fence (Area 9 and 12) C1)
C11_6 d/w - 10h/d - With HK Hols
24- No B/O 0periods (was
20-May-23
C3) 17-Jun-23 29-Jul-24 24-Aug-24 354
310.C.B01.104.B01 Construct Permanent security fence at Area 9 & 12. + Metal Works C11_6 d/w - 10h/d - With 24 20-May-23 17-Jun-23 29-Jul-24 24-Aug-24 354
HK Hols - No B/O periods
CC#4 - Jet Blast Screens (was C3) 721 0 07-Jun-21 A 06-Nov-23 22-Jun-22 17-Dec-23 35
Design (Jet Blast Screens) C01_7 d/w - 10h/d - No HK Hols214
- No B/O periods
0 (was07-Jul-22
C1) 05-Feb-23 27-Jul-22 25-Feb-23 20
310.D.R0.L268 Jet Blast Screen & Foundation - Prepare Design & submit with ICE C01_7 d/w - 10h/d - No HK 28 07-Jul-22 03-Aug-22 27-Jul-22 23-Aug-22 20
Hols - No B/O periods (was
310.D.R0.L272 Jet Blast Screen & Foundation - PM, AP, RSE reviewing C1)
C01_7 d/w - 10h/d - No HK 28 04-Aug-22 31-Aug-22 24-Aug-22 20-Sep-22 20
Hols - No B/O periods (was
310.D.R0.L276 Jet Blast Screen & Foundation - ICC, M&VC review design and issue check certificates C1)
C01_7 d/w - 10h/d - No HK 21 01-Sep-22 21-Sep-22 21-Sep-22 11-Oct-22 20
Hols - No B/O periods (was
310.D.R0.L280 Jet Blast Screen & Foundation- address comments & resubmit 2nd Round C1)
C01_7 d/w - 10h/d - No HK 14 22-Sep-22 05-Oct-22 12-Oct-22 25-Oct-22 20
Hols - No B/O periods (was
310.D.R0.L284 Jet Blast Screen & Foundation- PM, AP, RSE reviewing 2nd Round C1)
C01_7 d/w - 10h/d - No HK 28 06-Oct-22 02-Nov-22 26-Oct-22 22-Nov-22 20
Hols - No B/O periods (was
310.D.R0.L288 Jet Blast Screen & Foundation - ICC, M&VC review design and issue check certificates C1)
C01_7 d/w - 10h/d - No HK 21 03-Nov-22 23-Nov-22 23-Nov-22 13-Dec-22 20
2nd Round Hols - No B/O periods (was
310.D.R0.L292 Jet Blast Screen & Foundation - BD review and approve C1)
C01_7 d/w - 10h/d - No HK 60 24-Nov-22 22-Jan-23 14-Dec-22 11-Feb-23 20
Hols - No B/O periods (was
310.D.R0.L296 Jet Blast Screen & Foundation - prepare and submit Form BA8 and grant consent C1)
C01_7 d/w - 10h/d - No HK 7 23-Jan-23 29-Jan-23 12-Feb-23 18-Feb-23 20
Hols - No B/O periods (was
310.D.R0.L300 Jet Blast Screen & Foundation - prepare and submit Form BA10 to notify work C1)
C01_7 d/w - 10h/d - No HK 7 30-Jan-23 05-Feb-23 19-Feb-23 25-Feb-23 20
commencement Hols - No B/O periods (was
Procurement (Jet Blast Screens) C1) 148 0 13-Oct-21 A 26-Nov-22 22-Jun-22 15-Jun-23 161
Procurement - Major Long Lead Materials 148 0 13-Oct-21 A 26-Nov-22 22-Jun-22 15-Jun-23 161
310.P.RC.D58 Procurement Major Long Lead Items - Jet Blast Screen - submit metal works materials, C01_7 d/w - 10h/d - No HK 30 13-Oct-21 A 11-Nov-21 A 22-Jun-22 22-Jun-22
concrete for foundation Hols - No B/O periods (was
310.P.RC.D74 Procurement Major Long Lead Items - Jet Blast Screen - PM reviews of metal works C1)
C01_7 d/w - 10h/d - No HK 28 12-Nov-21 A 06-Dec-21 A 22-Jun-22 22-Jun-22
materials and concrete for foundation Hols - No B/O periods (was
310.P.RC.D58.B02 Procurement Major Long Lead Items - Jet Blast Screen - resubmit metal works materials, C1)
C01_7 d/w - 10h/d - No HK 14 07-Dec-21 A 13-Dec-21 A 22-Jun-22 22-Jun-22
concrete for foundation(2nd rnd.) Hols - No B/O periods (was
310.P.RC.D78 Procurement Major Long Lead Items - Jet Blast Screen - PM review and approved C1)
C01_7 d/w - 10h/d - No HK 28 14-Dec-21 A 06-Jul-22 22-Jun-22 26-Jul-22 20
Hols - No B/O periods (was
310.P.RC.D82 Procurement Major Long Lead Items - Jet Blast Screen - procurement, fabricate and C1)
C11_6 d/w - 10h/d - With 120 07-Jul-22 26-Nov-22 17-Jan-23 15-Jun-23 161
delivery to site HK Hols - No B/O periods
Construction (Jet Blast Screens) (was C3) 714 0 07-Jun-21 A 29-Oct-23 27-Jul-22 07-Dec-23 33
Initial Work (Jet Blast Screens) C11_6 d/w - 10h/d - With HK Hols0 - No B/O 0periods (was
07-Jun-21
C3) A 07-Jun-21 A 27-Jul-22 27-Jul-22
310.C.RC.L116 Jet Blast Screen - access to work area 3310/1 C11_6 d/w - 10h/d - With 0 07-Jun-21 A 27-Jul-22
HK Hols - No B/O periods
JBS-05 (West Side) and JBS-06 (East Side) (was
C11_6C3)
d/w - 10h/d - With HK Hols
149- No B/O 0periods (was
29-Oct-22
C3) 02-May-23 02-May-23 01-Nov-23 151
310.C.RC.L148 Jet Blast Screen (JBS-05 Foundation) - excavate, plate load test, foundation works C11_6 d/w - 10h/d - With 24 29-Oct-22 25-Nov-22 02-May-23 30-May-23 148
HK Hols - No B/O periods
310.C.RC.L152 Jet Blast Screen (JBS-06 Foundation) - excavate, plate load test, foundation works (was
C11_6C3)
d/w - 10h/d - With 24 30-Mar-23 02-May-23 04-Oct-23 01-Nov-23 151
HK Hols - No B/O periods
JBS-07 and JBS-08 (Air Side - NOTAM at WA3310/1) (was C3) - NOTAM (M,W,Th,Su-01:30-07:30)
C23_4d/w 125 0 - No HK
25-Sep-22
Hols - With B/O
03-Sep-23
Periods & Flight24-Nov-22
Checks 21-Sep-23 11
310.C.RC.L104 Jet Blast Screen JBS-07 & 08 - carry out UU detection and trial pits [NOTAM] C23_4d/w - NOTAM 14 25-Sep-22 28-Nov-22 24-Nov-22 18-Dec-22 11
(M,W,Th,Su-01:30-07:30) -
310.C.RC.L108 Jet Blast Screen JBS-07 & 08 - UU diversions works [NOTAM] No HK Hols- -NOTAM
C23_4d/w With B/O 15 30-Nov-22 15-Jan-23 09-Jan-23 23-Feb-23 11
(M,W,Th,Su-01:30-07:30) -
No HK Hols - With B/O
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 68 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.RC.L112 Jet Blast Screen JBS-08 (Footing) - excavate, foundation works (total length=65m; 5 C23_4d/w - NOTAM 30 06-Feb-23 29-Mar-23 26-Feb-23 29-May-23 11
segment: 13m, @ 10d/segment [NOTAM] (M,W,Th,Su-01:30-07:30) -
310.C.RC.L172 Jet Blast Screen JBS-07(Footing) - excavate, foundation wks(total length=230m;18 No HK Hols- -NOTAM
C23_4d/w With B/O 60 22-May-23 03-Sep-23 11-Jun-23 21-Sep-23 11
segment:13m, @ 10d/segment [NOTAM] (M,W,Th,Su-01:30-07:30) -
Metal Works (Jet Blast Screen) No HK Hols - With B/O 273 0 26-Nov-22 29-Oct-23 31-May-23 07-Dec-23 33
310.C.RC.L100 Jet Blast Screen (JBS-05 Metal Structure) - erect jet blast screen steel structure C11_6 d/w - 10h/d - With 14 26-Nov-22 12-Dec-22 31-May-23 15-Jun-23 148
HK Hols - No B/O periods
310.C.RC.L136 Jet Blast Screen (JBS-06 Metal Structure) - erect jet blast screen steel structure (was
C11_6C3)
d/w - 10h/d - With 14 03-May-23 18-May-23 02-Nov-23 17-Nov-23 151
HK Hols - No B/O periods
310.C.RC.L120 Jet Blast Screen (JBS-07 & JBS-08 Metal Structure) - erect jet blast screen steel structure (was C3) - NOTAM
C23_4d/w 20 04-Sep-23 29-Oct-23 24-Sep-23 07-Dec-23 11
[NOTAM] (M,W,Th,Su-01:30-07:30) -
Testing and Commissioning (Jet Blast Screens) No HK Hols - With B/O 266 0 13-Dec-22 06-Nov-23 16-Jun-23 17-Dec-23 35
310.C.RC.L156 Jet Blast Screen JBS-05 (T&C) - Inspection and acceptance C11_6 d/w - 10h/d - With 7 13-Dec-22 20-Dec-22 16-Jun-23 24-Jun-23 148
HK Hols - No B/O periods
310.C.RC.L160 Jet Blast Screen - Achieved KD-5B (was
C01_7C3)
d/w - 10h/d - No HK 0 20-Dec-22 25-Jun-23 187
Hols - No B/O periods (was
310.C.RC.L176 Jet Blast Screen JBS-06 (T&C) - Inspection and acceptance C1)
C11_6 d/w - 10h/d - With 7 19-May-23 27-May-23 18-Nov-23 25-Nov-23 151
HK Hols - No B/O periods
310.C.RC.L168 Jet Blast Screen - Achieved KD-5F (was
C01_7C3)
d/w - 10h/d - No HK 0 27-May-23 26-Nov-23 183
Hols - No B/O periods (was
310.C.RC.L180 Jet Blast Screen JBS-07 and JBS-08 (T&C) - Inspection and acceptance C1)
C11_6 d/w - 10h/d - With 7 30-Oct-23 06-Nov-23 09-Dec-23 16-Dec-23 35
HK Hols - No B/O periods
310.C.RC.L164 Jet Blast Screen - Achieved KD-5G (was
C01_7C3)
d/w - 10h/d - No HK 0 06-Nov-23 17-Dec-23 41
Hols - No B/O periods (was
CC#4 ----- Testing and Commissioning ----- C1) 675 0 13-May-22 16-Aug-24 11-Jun-22 25-Aug-24 7
CC#4 - T&C - (Airfield UU, Drainage Works, Watermain, AFPH) 675 0 13-May-22 16-Aug-24 11-Jun-22 25-Aug-24 7
T&C - Aviation Fuel and Hydrant System (AFHS) 341 0 24-Apr-23 15-Jun-24 24-Apr-23 30-Jun-24 12
T&C - AFHS Section 1 110 0 24-Apr-23 03-Sep-23 24-Apr-23 03-Sep-23 0
310.C.AF.F404 T&C (AFHS Section 1) - Fuel Pipe completed C23_4d/w - NOTAM 0 24-Apr-23 24-Apr-23 0
(M,W,Th,Su-01:30-07:30) -
310.C.AF.F492 T&C (AFHS Section 1) - Fuel Filling (526m3) No HK d/w
C01_7 Hols- -10h/d
With B/O
- No HK 21 24-Apr-23 14-May-23 24-Apr-23 14-May-23 0
Hols - No B/O periods (was
310.C.AF.F496 T&C (AFHS Section 1) - Soak & Pressure Test C1)
C01_7 d/w - 10h/d - No HK 10 15-May-23 24-May-23 15-May-23 24-May-23 0
Hols - No B/O periods (was
310.C.AF.F512 T&C (AFHS Section 1) - AFHS DG Application (Part I and Part II) C1)
C01_7 d/w - 10h/d - No HK 90 23-May-23 20-Aug-23 23-May-23 20-Aug-23 0
Hols - No B/O periods (was
310.C.AF.F500 T&C (AFHS Section 1) - Defueling & Fuel Top-up C1)
C01_7 d/w - 10h/d - No HK 10 25-May-23 03-Jun-23 28-Jul-23 06-Aug-23 64
Hols - No B/O periods (was
310.C.AF.F504 T&C (AFHS Section 1) - SAT for Power & SCADA C1)
C01_7 d/w - 10h/d - No HK 12 04-Jun-23 15-Jun-23 07-Aug-23 18-Aug-23 64
Hols - No B/O periods (was
310.C.AF.F508 T&C (AFHS Section 1) - Loop Flushing & Riser Flushing C1)
C01_7 d/w - 10h/d - No HK 2 16-Jun-23 17-Jun-23 19-Aug-23 20-Aug-23 64
Hols - No B/O periods (was
310.C.AF.F516 T&C (AFHS Section 1) - Submission & Inspection (ALD/CAD) C1)
C01_7 d/w - 10h/d - No HK 14 21-Aug-23 03-Sep-23 21-Aug-23 03-Sep-23 0
Hols - No B/O periods (was
310.C.AF.F520 T&C (AFHS Section 1) - Achieved KD-8 C1)
C01_7 d/w - 10h/d - No HK 0 03-Sep-23 03-Sep-23 0
Hols - No B/O periods (was
T&C - AFHS Section 2 C1)
C01_7 d/w - 10h/d - No HK Hols130
- No B/O periods
0 (was06-Feb-24
C1) 15-Jun-24 15-Feb-24 30-Jun-24 15
310.C.AF.F400 T&C (AFHS Section 2) - Fuel Pipe completed C01_7 d/w - 10h/d - No HK 0 06-Feb-24 15-Feb-24 9
Hols - No B/O periods (was
310.C.AF.F464 T&C (AFHS Section 2) - Fuel Filling (377m3) C1)
C01_7 d/w - 10h/d - No HK 16 07-Feb-24 22-Feb-24 16-Feb-24 02-Mar-24 9
Hols - No B/O periods (was
C1)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 69 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.AF.F468 T&C (AFHS Section 2) - Soak & Pressure Test C01_7 d/w - 10h/d - No HK 10 23-Feb-24 03-Mar-24 03-Mar-24 12-Mar-24 9
Hols - No B/O periods (was
310.C.AF.F472 T&C (AFHS Section 2) - Defueling & Fuel Top-up C1)
C01_7 d/w - 10h/d - No HK 10 04-Mar-24 13-Mar-24 18-May-24 27-May-24 75
Hols - No B/O periods (was
310.C.AF.F484 T&C (AFHS Section 2) - AFHS DG Application (Part I and Part II) C1)
C01_7 d/w - 10h/d - No HK 90 04-Mar-24 01-Jun-24 13-Mar-24 10-Jun-24 9
Hols - No B/O periods (was
310.C.AF.F476 T&C (AFHS Section 2) - SAT for Power & SCADA C1)
C01_7 d/w - 10h/d - No HK 12 14-Mar-24 25-Mar-24 28-May-24 08-Jun-24 75
Hols - No B/O periods (was
310.C.AF.F480 T&C (AFHS Section 2) - Loop Flushing & Riser Flushing C1)
C01_7 d/w - 10h/d - No HK 2 26-Mar-24 27-Mar-24 09-Jun-24 10-Jun-24 75
Hols - No B/O periods (was
310.C.AF.F488 T&C (AFHS Section 2) - Submission & Inspection (ALD/CAD) C1)
C01_7 d/w - 10h/d - No HK 14 02-Jun-24 15-Jun-24 11-Jun-24 24-Jun-24 9
Hols - No B/O periods (was
310.C.AF.F524 T&C (AFHS Section 2) - Achieved KD-9 C1)
C01_7 d/w - 10h/d - No HK 0 15-Jun-24 30-Jun-24 15
Hols - No B/O periods (was
Potable Water and Fire Hydrant (PWFH) C1)
C11_6 d/w - 10h/d - With HK Hols
499- No B/O 0periods (was
13-May-22
C3) 12-Jan-24 11-Jun-22 24-Aug-24 183
310.T.ES.P740.B02 Prepare for Watermain Materials (Potable and Seawater) for Submission C11_6 d/w - 10h/d - With 17 13-May-22 01-Jun-22 11-Jun-22 30-Jun-22 24
HK Hols - No B/O periods
310.T.ES.P744.B02 Submit Watermain Materials (Potable and Seawater) for PM Acceptance (was
C11_6C3)
d/w - 10h/d - With 0 02-Jun-22 02-Jul-22 24
HK Hols - No B/O periods
310.T.ES.P748.B02 PM Acceptance (was
C11_6C3)
d/w - 10h/d - With 48 02-Jun-22 29-Jul-22 02-Jul-22 26-Aug-22 24
HK Hols - No B/O periods
WSD Inspection Potable Water and Fire Hydrant (PWFH) (West Area) (was
C11_6C3)
d/w - 10h/d - With HK Hols
415- No B/O 0periods (was
30-Jul-22
C3) 18-Dec-23 27-Aug-22 24-Jun-24 150
310.S.EX.U101 Form WWO 46 (Part I & Part II) & Annex Submission for WSD Approval (Plumbing / FS / C11_6 d/w - 10h/d - With 0 30-Jul-22 27-Aug-22 24
WP) HK Hols - No B/O periods
310.S.EX.U104 Obtain Form WWO 46 (Part III) - WSD Approval, Endorsed & Return to Licensed Plumber (was
C11_6C3)
d/w - 10h/d - With 4 30-Jul-22 03-Aug-22 27-Aug-22 31-Aug-22 24
HK Hols - No B/O periods
310.C.AF.F408 WWO46 Part IV with pressure test (last portion) (PWFH) (was
C11_6C3)
d/w - 10h/d - With 12 02-Nov-23 15-Nov-23 07-May-24 21-May-24 150
HK Hols - No B/O periods
310.C.AF.F412 WSD Inspection and WWO46 Part V(a) (PWFH) (was
C11_6C3)
d/w - 10h/d - With 6 16-Nov-23 22-Nov-23 22-May-24 28-May-24 150
HK Hols - No B/O periods
310.C.AF.F416 T&C (Pipe flushing and Sterilization) (PWFH) (was
C11_6C3)
d/w - 10h/d - With 6 23-Nov-23 29-Nov-23 29-May-24 04-Jun-24 150
HK Hols - No B/O periods
310.C.AF.F420 Water Sampling (PWFH) (was
C11_6C3)
d/w - 10h/d - With 3 30-Nov-23 02-Dec-23 05-Jun-24 07-Jun-24 150
HK Hols - No B/O periods
310.C.AF.F424 Results of lab test to WSD (PWFH) (was
C11_6C3)
d/w - 10h/d - With 6 04-Dec-23 09-Dec-23 08-Jun-24 15-Jun-24 150
HK Hols - No B/O periods
310.C.AF.F428 WSD to issue WWO part V (b) (PWFH) (was
C11_6C3)
d/w - 10h/d - With 6 11-Dec-23 16-Dec-23 17-Jun-24 22-Jun-24 150
HK Hols - No B/O periods
310.C.AF.F432 Connect to Existing Pipe (PWFH-West) (was
C11_6C3)
d/w - 10h/d - With 1 18-Dec-23 18-Dec-23 24-Jun-24 24-Jun-24 150
HK Hols - No B/O periods
FSD Inspection Fire Hydrant (PWFH) (West Area) (was
C11_6C3)
d/w - 10h/d - With HK Hols
18- No B/O 0periods (was
19-Dec-23
C3) 11-Jan-24 05-Aug-24 24-Aug-24 184
310.T.ES.P745.B02 F.S. Inspection Plan (Form FSI / 314 Submission) C11_6 d/w - 10h/d - With 0 19-Dec-23 05-Aug-24 184
HK Hols - No B/O periods
310.T.ES.P751.B02 F.S. Inspection Application (Form FSI / 501 & 251 Submission) (was
C11_6C3)
d/w - 10h/d - With 0 19-Dec-23 05-Aug-24 184
HK Hols - No B/O periods
310.T.ES.P760.B02 F.S. 1st Inspection (was
C11_6C3)
d/w - 10h/d - With 6 19-Dec-23 27-Dec-23 05-Aug-24 10-Aug-24 184
HK Hols - No B/O periods
310.T.ES.P765.B02 FSD Comment (was
C11_6C3)
d/w - 10h/d - With 0 27-Dec-23 10-Aug-24 184
HK Hols - No B/O periods
310.T.ES.P770.B02 Rectification & Adjustment (was
C11_6C3)
d/w - 10h/d - With 6 28-Dec-23 04-Jan-24 12-Aug-24 17-Aug-24 184
HK Hols - No B/O periods
(was C3)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 70 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.T.ES.P775.B02 F.S. Re-inspection C11_6 d/w - 10h/d - With 6 05-Jan-24 11-Jan-24 19-Aug-24 24-Aug-24 184
HK Hols - No B/O periods
310.T.ES.P781.B02 Issue F.S. Certificate (Form FS172) (West Area) (was
C11_6C3)
d/w - 10h/d - With 0 11-Jan-24 24-Aug-24 184
HK Hols - No B/O periods
WSD Inspection Potable Water and Fire Hydrant (PWFH) (East Area) (was
C11_6C3)
d/w - 10h/d - With HK Hols
416- No B/O 0periods (was
30-Jul-22
C3) 19-Dec-23 22-Sep-22 24-Jun-24 149
310.T.ES.P753.B02 Form WWO 46 (Part I & Part II) & Annex Submission for WSD Approval (Plumbing / FS / C11_6 d/w - 10h/d - With 0 30-Jul-22 22-Sep-22 45
WP) HK Hols - No B/O periods
310.T.ES.P757.B02 Obtain Form WWO 46 (Part III) - WSD Approval, Endorsed & Return to Licensed Plumber (was
C11_6C3)
d/w - 10h/d - With 4 30-Jul-22 03-Aug-22 22-Sep-22 26-Sep-22 45
HK Hols - No B/O periods
310.C.AF.F436.B02 WWO46 Part IV with pressure test (last portion) (PWFH) (was
C11_6C3)
d/w - 10h/d - With 12 03-Nov-23 16-Nov-23 07-May-24 21-May-24 149
HK Hols - No B/O periods
310.C.AF.F440 WSD Inspection and WWO46 Part V(a) (PWFH) (was
C11_6C3)
d/w - 10h/d - With 6 17-Nov-23 23-Nov-23 22-May-24 28-May-24 149
HK Hols - No B/O periods
310.C.AF.F444 T&C (Pipe flushing and Sterilization) (PWFH) (was
C11_6C3)
d/w - 10h/d - With 6 24-Nov-23 30-Nov-23 29-May-24 04-Jun-24 149
HK Hols - No B/O periods
310.C.AF.F448 Water Sampling (PWFH) (was
C11_6C3)
d/w - 10h/d - With 3 01-Dec-23 04-Dec-23 05-Jun-24 07-Jun-24 149
HK Hols - No B/O periods
310.C.AF.F452 Results of lab test to WSD (PWFH) (was
C11_6C3)
d/w - 10h/d - With 6 05-Dec-23 11-Dec-23 08-Jun-24 15-Jun-24 149
HK Hols - No B/O periods
310.C.AF.F456 WSD to issue WWO part V (b) (PWFH) (was
C11_6C3)
d/w - 10h/d - With 6 12-Dec-23 18-Dec-23 17-Jun-24 22-Jun-24 149
HK Hols - No B/O periods
310.C.AF.F460 Connect to Existing Pipe (PWFH - East) (was
C11_6C3)
d/w - 10h/d - With 1 19-Dec-23 19-Dec-23 24-Jun-24 24-Jun-24 149
HK Hols - No B/O periods
FSD Inspection Fire Hydrant (PWFH) (East Area) (was
C11_6C3)
d/w - 10h/d - With HK Hols
18- No B/O 0periods (was
20-Dec-23
C3) 12-Jan-24 05-Aug-24 24-Aug-24 183
310.T.ES.P768.B02 F.S. Inspection Plan (Form FSI / 314 Submission) C11_6 d/w - 10h/d - With 0 20-Dec-23 05-Aug-24 183
HK Hols - No B/O periods
310.T.ES.P772.B02 F.S. Inspection Application (Form FSI / 501 & 251 Submission) (was
C11_6C3)
d/w - 10h/d - With 0 20-Dec-23 05-Aug-24 183
HK Hols - No B/O periods
310.T.ES.P776.B02 F.S. 1st Inspection (was
C11_6C3)
d/w - 10h/d - With 6 20-Dec-23 28-Dec-23 05-Aug-24 10-Aug-24 183
HK Hols - No B/O periods
310.T.ES.P780.B02 FSD Comment (was
C11_6C3)
d/w - 10h/d - With 0 28-Dec-23 10-Aug-24 183
HK Hols - No B/O periods
310.T.ES.P784.B02 Rectification & Adjustment (was
C11_6C3)
d/w - 10h/d - With 6 29-Dec-23 05-Jan-24 12-Aug-24 17-Aug-24 183
HK Hols - No B/O periods
310.T.ES.P788.B02 F.S. Re-inspection (was
C11_6C3)
d/w - 10h/d - With 6 06-Jan-24 12-Jan-24 19-Aug-24 24-Aug-24 183
HK Hols - No B/O periods
310.T.ES.P792.B02 Issue F.S. Certificate (Form FS172) (East Area) (was
C11_6C3)
d/w - 10h/d - With 0 12-Jan-24 24-Aug-24 183
HK Hols - No B/O periods
Stormwater Drainage System and Box Culvert (was C3) 249 0 12-Jan-23 15-Nov-23 12-May-23 25-Aug-24 230
Stormwater Drainage System C01_7 d/w - 10h/d - No HK Hols14
- No B/O periods
0 (was01-Nov-23
C1) 15-Nov-23 11-Aug-24 25-Aug-24 284
310.C.R0.Y408 Stormwater Drainage System - completion of stormwater drain pipes and manholes C01_7 d/w - 10h/d - No HK 0 01-Nov-23 11-Aug-24 284
construction Hols - No B/O periods (was
310.C.R0.Y412 Stormwater Drainage System - submit form BA14 for completion of stormwater drainage C1)
C01_7 d/w - 10h/d - No HK 14 02-Nov-23 15-Nov-23 12-Aug-24 25-Aug-24 284
works Hols - No B/O periods (was
Box Culvert 3, 4 & 18 C1)
C01_7 d/w - 10h/d - No HK Hols146
- No B/O periods
0 (was12-Jan-23
C1) 07-Jun-23 12-May-23 25-Jun-23 18
310.C.R0.Y102 Stormwater Drainage System and Box Culvert - complete box culvert 3,4,18 backfill C01_7 d/w - 10h/d - No HK 0 12-Jan-23 12-May-23 120
Hols - No B/O periods (was
310.C.R0.Y100 Stormwater Drainage System and Box Culvert - complete box culvert 3,4,18 metal work C1)
C01_7 d/w - 10h/d - No HK 0 11-Feb-23 12-May-23 91
Hols - No B/O periods (was
310.C.R0.Y103 Stormwater Drainage System and Box Culvert - Box Culvert 3,4 - Prepare as-built C1)
C01_7 d/w - 10h/d - No HK 30 25-Apr-23 24-May-23 13-May-23 11-Jun-23 18
drawings Hols - No B/O periods (was
C1)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 71 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.R0.Y105 Stormwater Drainage System and Box Culvert - Box Culvert 18 - Prepare as-built C01_7 d/w - 10h/d - No HK 30 25-Apr-23 24-May-23 13-May-23 11-Jun-23 18
drawings Hols - No B/O periods (was
310.C.R0.Y110 Stormwater Drainage System and Box Culvert - submit Form BA14 for completion of Box C1)
C01_7 d/w - 10h/d - No HK 14 25-May-23 07-Jun-23 12-Jun-23 25-Jun-23 18
Culverts 3,4,18 Hols - No B/O periods (was
Box Culvert 5, 6, & 19 C1) 134 0 13-May-23 24-Oct-23 06-Oct-23 26-Nov-23 28
310.C.R0.Y400 Stormwater Drainage System and Box Culvert - complete box culvert 5,6,19 backfill C01_7 d/w - 10h/d - No HK 0 13-May-23 06-Oct-23 146
Hols - No B/O periods (was
310.C.R0.Y396 Stormwater Drainage System and Box Culvert - complete box culvert 5,6,19 fit out C1)
C01_7 d/w - 10h/d - No HK 0 19-Aug-23 06-Oct-23 48
Hols - No B/O periods (was
310.C.R0.Y401 Stormwater Drainage System and Box Culvert - Box Culvert 5,6 - prepare as-built C1)
C11_6 d/w - 10h/d - With 30 04-Sep-23 10-Oct-23 07-Oct-23 11-Nov-23 27
drawings HK Hols - No B/O periods
310.C.R0.Y402 Stormwater Drainage System and Box Culvert - Box Culvert 19 - prepare as-built (was
C11_6C3)
d/w - 10h/d - With 30 04-Sep-23 10-Oct-23 07-Oct-23 11-Nov-23 27
drawings HK Hols - No B/O periods
310.C.R0.Y405 Stormwater Drainage System and Box Culvert - submit Form BA14 for completion of Box (was
C01_7C3)
d/w - 10h/d - No HK 14 11-Oct-23 24-Oct-23 13-Nov-23 26-Nov-23 33
Culverts 5,6,19 Hols - No B/O periods (was
Statutory Submission C1) 52 0 17-Jun-24 16-Aug-24 25-Jun-24 25-Aug-24 7
310.C.AF.F463 Prepare and submit for Full Set of Material & Mill Certificates, as built records,etc, for all C11_6 d/w - 10h/d - With 28 17-Jun-24 19-Jul-24 25-Jun-24 27-Jul-24 7
apron works HK Hols - No B/O periods
310.C.AF.F467 Submit BA14 to BD for Apron Works (was
C01_7C3)
d/w - 10h/d - No HK 28 20-Jul-24 16-Aug-24 29-Jul-24 25-Aug-24 9
Hols - No B/O periods (was
CC#4.7 - 3310/10,10A,9 - BC3,4,18 - Notification of Works Completion to BD C1) 459 0 24-Jul-22 05-Feb-24 30-Mar-23 25-Aug-24 163
CC#4 - ELS and Open Cut Excavation C01_7 d/w - 10h/d - No HK Hols14
- No B/O periods
0 (was24-Jul-22
C1) 06-Aug-22 30-Mar-23 12-Apr-23 249
310.C.R0.L165 3310/10,10A - Box Culvert 3,4,18 - Submit Form BA14 for completion of excavation work C01_7 d/w - 10h/d - No HK 14 24-Jul-22 06-Aug-22 30-Mar-23 12-Apr-23 249
Hols - No B/O periods (was
CC#4 - Stormwater Drainage Works C1)
C01_7 d/w - 10h/d - No HK Hols30
- No B/O periods
0 (was26-Mar-23
C1) 24-Apr-23 13-Apr-23 12-May-23 18
310.C.WS.F460 3310/10,10A - Prepare as-built drawings and submit Form BA14 for partial completion of C01_7 d/w - 10h/d - No HK 30 26-Mar-23 24-Apr-23 13-Apr-23 12-May-23 18
Stormwater Drainage Works Hols - No B/O periods (was
CC#4 - Road Drainage Works C1)
C01_7 d/w - 10h/d - No HK Hols30
- No B/O periods
0 (was21-Apr-23
C1) 20-May-23 13-Jul-24 11-Aug-24 449
310.C.WS.F464 3310/10,10A - Prepare as-built drawings and submit Form BA14 for partial completion of C01_7 d/w - 10h/d - No HK 30 21-Apr-23 20-May-23 13-Jul-24 11-Aug-24 449
Road Drainage Works Hols - No B/O periods (was
CC#4 - Roadwork for Landside Road and Airside Road in 3310/10,10A C1) 67 0 15-Nov-23 05-Feb-24 01-Jun-24 25-Aug-24 163
310.C.R0.X172 3310/10,10A - LSR & ASR - complete wearing course, road marking, central reserve C11_6 d/w - 10h/d - With 0 15-Nov-23 01-Jun-24 160
HK Hols - No B/O periods
310.C.R0.X750 3310/10,10A - LSR & ASR - testing and commissioning (was
C11_6C3)
d/w - 10h/d - With 30 16-Nov-23 20-Dec-23 03-Jun-24 09-Jul-24 160
HK Hols - No B/O periods
310.C.R0.X754 3310/10,10A - LSR & ASR - submit Form BA14 for completion of work (was
C01_7C3)
d/w - 10h/d - No HK 14 21-Dec-23 03-Jan-24 10-Jul-24 23-Jul-24 202
Hols - No B/O periods (was
310.C.R0.X758 3310/10,10A - LSR & ASR - Statutory Inspection C1)
C11_6 d/w - 10h/d - With 28 04-Jan-24 05-Feb-24 24-Jul-24 24-Aug-24 163
HK Hols - No B/O periods
310.C.R0.X762 3310/10,10A - LSR & ASR - Achieve KD-12 (was
C01_7C3)
d/w - 10h/d - No HK 0 05-Feb-24 25-Aug-24 202
Hols - No B/O periods (was
Cost Centre #05 - Airport System C1) 662 85 01-Nov-21 A 19-Mar-24 27-Mar-22 08-Jun-24 64
CC#5 ----- Design & Other Submission ----- C01_7 d/w - 10h/d - No HK Hols315
- No B/O periods
0 (was
05-Feb-22
C1) A 13-Jan-23 27-Mar-22 08-Jan-24 360
CC#5 - MS no.20 - Method Statement for Installation Works of Airport/Airfield Systems and equipment C01_7 d/w - 10h/d - No HK Hols100
- No B/O periods
0 (was
05-Feb-22
C1) A 12-Jun-22 27-Mar-22 12-Jun-22 0
310.D.WS.L328 MS no. 20 - MS for Installation Works of Airport/ Airfield System and Equipment - prepare C01_7 d/w - 10h/d - No HK 28 05-Feb-22 A 01-Apr-22 27-Mar-22 01-Apr-22 0
document Hols - No B/O periods (was
310.D.WS.L332 MS no. 20 - MS for Installation Works of Airport/ Airfield System and Equipment - ICE C1)
C01_7 d/w - 10h/d - No HK 3 08-Apr-22 10-Apr-22 08-Apr-22 10-Apr-22 0
issue check certificate Hols - No B/O periods (was
310.D.WS.L333 MS no. 20 - MS for Installation Works of Airport/ Airfield System and Equipment - PM C1)
C01_7 d/w - 10h/d - No HK 28 11-Apr-22 08-May-22 11-Apr-22 08-May-22 0
review and accept 1st Round Hols - No B/O periods (was
C1)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 72 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L334 MS no. 20 - MS for Installation Works of Airport/ Airfield System and Equipment - address C01_7 d/w - 10h/d - No HK 7 09-May-22 15-May-22 09-May-22 15-May-22 0
comments 2nd Submission Hols - No B/O periods (was
310.D.WS.L336 MS no. 20 - MS for Installation Works of Airport/ Airfield System and Equipment - PM C1)
C01_7 d/w - 10h/d - No HK 28 16-May-22 12-Jun-22 16-May-22 12-Jun-22 0
review and accept 2nd Round Hols - No B/O periods (was
CC#5 - MS no.25 - Testing and Commissioning Plan for Airport Authority Ancillary Buildings C1)
C01_7 d/w - 10h/d - No HK Hols100
- No B/O periods
0 (was06-Oct-22
C1) 13-Jan-23 06-Oct-22 08-Jan-24 360
310.D.WS.L340 MS no. 25 - T&C Plan for Airport Authority Ancillary Buildings - prepare document C01_7 d/w - 10h/d - No HK 28 06-Oct-22 02-Nov-22 06-Oct-22 02-Nov-22 0
Hols - No B/O periods (was
310.D.WS.L344 MS no. 25 - T&C Plan for Airport Authority Ancillary Buildings - ICE issue check certificate C1)
C01_7 d/w - 10h/d - No HK 3 09-Nov-22 11-Nov-22 04-Nov-23 06-Nov-23 360
Hols - No B/O periods (was
310.D.WS.L345 MS no. 25 - T&C Plan for Airport Authority Ancillary Buildings - PM review and accept 1st C1)C01_7 d/w - 10h/d - No HK 28 12-Nov-22 09-Dec-22 07-Nov-23 04-Dec-23 360
Round Hols - No B/O periods (was
310.D.WS.L346 MS no. 25 - T&C Plan for Airport Authority Ancillary Buildings - address comments 2nd C1)
C01_7 d/w - 10h/d - No HK
7 10-Dec-22 16-Dec-22 05-Dec-23 11-Dec-23 360
Submission Hols - No B/O periods (was
310.D.WS.L348 MS no. 25 - T&C Plan for Airport Authority Ancillary Buildings - PM review and accept 2nd C1)
C01_7 d/w - 10h/d - No HK 28 17-Dec-22 13-Jan-23 12-Dec-23 08-Jan-24 360
Round Hols - No B/O periods (was
CC#5 - Airport System - Access Control System (ACS) C1)
C01_7 d/w - 10h/d - No HK Hols56
- No B/O periods
0 (was11-May-22
C1) 05-Jul-22 11-May-22 19-Sep-22 76
Airport System - ACS Drawing Submission C01_7 d/w - 10h/d - No HK Hols56
- No B/O periods
0 (was11-May-22
C1) 05-Jul-22 26-Jul-22 19-Sep-22 76
310.D.WS.L352 Airport System - ACS Drawing Submission - prepare document C01_7 d/w - 10h/d - No HK 14 11-May-22 24-May-22 26-Jul-22 08-Aug-22 76
Hols - No B/O periods (was
310.D.WS.L353 Airport System - ACS Drawing Submission - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 21 25-May-22 14-Jun-22 09-Aug-22 29-Aug-22 76
Hols - No B/O periods (was
310.D.WS.L354 Airport System - ACS Drawing Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 7 15-Jun-22 21-Jun-22 30-Aug-22 05-Sep-22 76
Hols - No B/O periods (was
310.D.WS.L356 Airport System - ACS Drawing Submission - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 14 22-Jun-22 05-Jul-22 06-Sep-22 19-Sep-22 76
Hols - No B/O periods (was
Airport System - ACS Method Statement Submission C1)
C01_7 d/w - 10h/d - No HK Hols56
- No B/O periods
0 (was11-May-22
C1) 05-Jul-22 26-Jul-22 19-Sep-22 76
310.D.WS.L360 Airport System - ACS Method Statement Submission - prepare document C01_7 d/w - 10h/d - No HK 14 11-May-22 24-May-22 26-Jul-22 08-Aug-22 76
Hols - No B/O periods (was
310.D.WS.L361 Airport System - ACS Method Statement Submission - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 21 25-May-22 14-Jun-22 09-Aug-22 29-Aug-22 76
Hols - No B/O periods (was
310.D.WS.L362 Airport System - ACS Method Statement Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 7 15-Jun-22 21-Jun-22 30-Aug-22 05-Sep-22 76
Hols - No B/O periods (was
310.D.WS.L364 Airport System - ACS Method Statement Submission - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 14 22-Jun-22 05-Jul-22 06-Sep-22 19-Sep-22 76
Hols - No B/O periods (was
Airport System - ACS Material Submission C1)
C01_7 d/w - 10h/d - No HK Hols49
- No B/O periods
0 (was11-May-22
C1) 28-Jun-22 11-May-22 28-Jun-22 0
310.D.WS.L368 Airport System - ACS Material Submission - prepare document C01_7 d/w - 10h/d - No HK 14 11-May-22 24-May-22 11-May-22 24-May-22 0
Hols - No B/O periods (was
310.D.WS.L369 Airport System - ACS Material Submission - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 21 25-May-22 14-Jun-22 25-May-22 14-Jun-22 0
Hols - No B/O periods (was
310.D.WS.L370 Airport System - ACS Material Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 7 15-Jun-22 21-Jun-22 15-Jun-22 21-Jun-22 0
Hols - No B/O periods (was
310.D.WS.L372 Airport System - ACS Material Submission - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 7 22-Jun-22 28-Jun-22 22-Jun-22 28-Jun-22 0
Hols - No B/O periods (was
CC#5 - Airport System - Airport Lightning Warnings System (ALWS) C1)
C01_7 d/w - 10h/d - No HK Hols72
- No B/O periods
0 (was11-May-22
C1) 21-Jul-22 11-May-22 14-Nov-22 116
Airport System - ALWS Drawing Submission C01_7 d/w - 10h/d - No HK Hols56
- No B/O periods
0 (was27-May-22
C1) 21-Jul-22 20-Sep-22 14-Nov-22 116
310.D.WS.L376 Airport System - ALWS Drawing Submission - prepare document C01_7 d/w - 10h/d - No HK 14 27-May-22 09-Jun-22 20-Sep-22 03-Oct-22 116
Hols - No B/O periods (was
310.D.WS.L377 Airport System - ALWS Drawing Submission - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 21 10-Jun-22 30-Jun-22 04-Oct-22 24-Oct-22 116
Hols - No B/O periods (was
310.D.WS.L378 Airport System - ALWS Drawing Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 7 01-Jul-22 07-Jul-22 25-Oct-22 31-Oct-22 116
Hols - No B/O periods (was
C1)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 73 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L380 Airport System - ALWS Drawing Submission - PM review and accept 2nd Round C01_7 d/w - 10h/d - No HK 14 08-Jul-22 21-Jul-22 01-Nov-22 14-Nov-22 116
Hols - No B/O periods (was
Airport System - ALWS Method Statement Submission C1)
C01_7 d/w - 10h/d - No HK Hols56
- No B/O periods
0 (was27-May-22
C1) 21-Jul-22 20-Sep-22 14-Nov-22 116
310.D.WS.L384 Airport System - ALWS Method Statement Submission - prepare document C01_7 d/w - 10h/d - No HK 14 27-May-22 09-Jun-22 20-Sep-22 03-Oct-22 116
Hols - No B/O periods (was
310.D.WS.L385 Airport System - ALWS Method Statement Submission - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 21 10-Jun-22 30-Jun-22 04-Oct-22 24-Oct-22 116
Hols - No B/O periods (was
310.D.WS.L386 Airport System - ALWS Method Statement Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 7 01-Jul-22 07-Jul-22 25-Oct-22 31-Oct-22 116
Hols - No B/O periods (was
310.D.WS.L388 Airport System - ALWS Method Statement Submission - PM review and accept 2nd C1)
C01_7 d/w - 10h/d - No HK 14 08-Jul-22 21-Jul-22 01-Nov-22 14-Nov-22 116
Round Hols - No B/O periods (was
Airport System - ALWS Material Submission C1)
C01_7 d/w - 10h/d - No HK Hols49
- No B/O periods
0 (was11-May-22
C1) 28-Jun-22 11-May-22 28-Jun-22 0
310.D.WS.L392 Airport System - ALWS Material Submission - prepare document C01_7 d/w - 10h/d - No HK 14 11-May-22 24-May-22 11-May-22 24-May-22 0
Hols - No B/O periods (was
310.D.WS.L393 Airport System - ALWS Material Submission - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 21 25-May-22 14-Jun-22 25-May-22 14-Jun-22 0
Hols - No B/O periods (was
310.D.WS.L394 Airport System - ALWS Material Submission - prepare resubmission 2nd Round C1)
C01_7 d/w - 10h/d - No HK 7 15-Jun-22 21-Jun-22 15-Jun-22 21-Jun-22 0
Hols - No B/O periods (was
310.D.WS.L396 Airport System - ALWS Material Submission - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 7 22-Jun-22 28-Jun-22 22-Jun-22 28-Jun-22 0
Hols - No B/O periods (was
CC#5 - Airport System - Bird Control System (BCS) C1)
C01_7 d/w - 10h/d - No HK Hols84
- No B/O periods
0 (was10-Jul-22
C1) 01-Oct-22 18-Dec-22 14-May-23 225
Airport System - BCS Drawing Submission C01_7 d/w - 10h/d - No HK Hols84
- No B/O periods
0 (was10-Jul-22
C1) 01-Oct-22 20-Feb-23 14-May-23 225
310.D.WS.L400 Airport System - BCS Drawing Submission - prepare document C01_7 d/w - 10h/d - No HK 14 10-Jul-22 23-Jul-22 20-Feb-23 05-Mar-23 225
Hols - No B/O periods (was
310.D.WS.L401 Airport System - BCS Drawing Submission - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 28 24-Jul-22 20-Aug-22 06-Mar-23 02-Apr-23 225
Hols - No B/O periods (was
310.D.WS.L402 Airport System - BCS Drawing Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 14 21-Aug-22 03-Sep-22 03-Apr-23 16-Apr-23 225
Hols - No B/O periods (was
310.D.WS.L404 Airport System - BCS Drawing Submission - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 28 04-Sep-22 01-Oct-22 17-Apr-23 14-May-23 225
Hols - No B/O periods (was
Airport System - BSC Method Statement Submission C1)
C01_7 d/w - 10h/d - No HK Hols84
- No B/O periods
0 (was10-Jul-22
C1) 01-Oct-22 20-Feb-23 14-May-23 225
310.D.WS.L408 Airport System - BCS Method Statement Submission - prepare document C01_7 d/w - 10h/d - No HK 14 10-Jul-22 23-Jul-22 20-Feb-23 05-Mar-23 225
Hols - No B/O periods (was
310.D.WS.L409 Airport System - BCS Method Statement Submission - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 28 24-Jul-22 20-Aug-22 06-Mar-23 02-Apr-23 225
Hols - No B/O periods (was
310.D.WS.L410 Airport System - BCS Method Statement Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 14 21-Aug-22 03-Sep-22 03-Apr-23 16-Apr-23 225
Hols - No B/O periods (was
310.D.WS.L412 Airport System - BCS Method Statement Submission - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 28 04-Sep-22 01-Oct-22 17-Apr-23 14-May-23 225
Hols - No B/O periods (was
Airport System - BSC Material Submission C1)
C01_7 d/w - 10h/d - No HK Hols84
- No B/O periods
0 (was10-Jul-22
C1) 01-Oct-22 18-Dec-22 11-Mar-23 161
310.D.WS.L416 Airport System - BCS Material Submission - prepare document C01_7 d/w - 10h/d - No HK 14 10-Jul-22 23-Jul-22 18-Dec-22 31-Dec-22 161
Hols - No B/O periods (was
310.D.WS.L417 Airport System - BCS Material Submission - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 28 24-Jul-22 20-Aug-22 01-Jan-23 28-Jan-23 161
Hols - No B/O periods (was
310.D.WS.L418 Airport System - BCS Material Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 14 21-Aug-22 03-Sep-22 29-Jan-23 11-Feb-23 161
Hols - No B/O periods (was
310.D.WS.L420 Airport System - BCS Material Submission - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 28 04-Sep-22 01-Oct-22 12-Feb-23 11-Mar-23 161
Hols - No B/O periods (was
CC#5 - Airport System - Closed Circuit Television System (CCTV) C1)
C01_7 d/w - 10h/d - No HK Hols72
- No B/O periods
0 (was11-May-22
C1) 21-Jul-22 11-May-22 19-Sep-22 60
Airport System - CCTV Drawing Submission C01_7 d/w - 10h/d - No HK Hols56
- No B/O periods
0 (was27-May-22
C1) 21-Jul-22 26-Jul-22 19-Sep-22 60

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 74 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L424 Airport System - CCTV Drawing Submission - prepare document C01_7 d/w - 10h/d - No HK 14 27-May-22 09-Jun-22 26-Jul-22 08-Aug-22 60
Hols - No B/O periods (was
310.D.WS.L425 Airport System - CCTV Drawing Submission - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 21 10-Jun-22 30-Jun-22 09-Aug-22 29-Aug-22 60
Hols - No B/O periods (was
310.D.WS.L426 Airport System - CCTV Drawing Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 7 01-Jul-22 07-Jul-22 30-Aug-22 05-Sep-22 60
Hols - No B/O periods (was
310.D.WS.L428 Airport System - CCTV Drawing Submission - PM review and accept 2nd Round' C1)
C01_7 d/w - 10h/d - No HK 14 08-Jul-22 21-Jul-22 06-Sep-22 19-Sep-22 60
Hols - No B/O periods (was
Airport System - CCTV Method Statement Submission C1)
C01_7 d/w - 10h/d - No HK Hols56
- No B/O periods
0 (was27-May-22
C1) 21-Jul-22 26-Jul-22 19-Sep-22 60
310.D.WS.L432 Airport System - CCTV Method Statement Submission - prepare document C01_7 d/w - 10h/d - No HK 14 27-May-22 09-Jun-22 26-Jul-22 08-Aug-22 60
Hols - No B/O periods (was
310.D.WS.L433 Airport System - CCTV Method Statement Submission - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 21 10-Jun-22 30-Jun-22 09-Aug-22 29-Aug-22 60
Hols - No B/O periods (was
310.D.WS.L434 Airport System - CCTV Method Statement Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 7 01-Jul-22 07-Jul-22 30-Aug-22 05-Sep-22 60
Hols - No B/O periods (was
310.D.WS.L436 Airport System - CCTV Method Statement Submission - PM review and accept 2nd C1)
C01_7 d/w - 10h/d - No HK 14 08-Jul-22 21-Jul-22 06-Sep-22 19-Sep-22 60
Round Hols - No B/O periods (was
Airport System - CCTV Material Submission C1)
C01_7 d/w - 10h/d - No HK Hols49
- No B/O periods
0 (was11-May-22
C1) 28-Jun-22 11-May-22 28-Jun-22 0
310.D.WS.L440 Airport System - CCTV Material Submission - prepare document C01_7 d/w - 10h/d - No HK 14 11-May-22 24-May-22 11-May-22 24-May-22 0
Hols - No B/O periods (was
310.D.WS.L441 Airport System - CCTV Material Submission - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 21 25-May-22 14-Jun-22 25-May-22 14-Jun-22 0
Hols - No B/O periods (was
310.D.WS.L442 Airport System - CCTV Material Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 7 15-Jun-22 21-Jun-22 15-Jun-22 21-Jun-22 0
Hols - No B/O periods (was
310.D.WS.L444 Airport System - CCTV Material Submission - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 7 22-Jun-22 28-Jun-22 22-Jun-22 28-Jun-22 0
Hols - No B/O periods (was
CC#5 - Airport System - Intrusion Detection & Surveillance System (IDSS) C1)
C01_7 d/w - 10h/d - No HK Hols56
- No B/O periods
0 (was06-May-22
C1) 30-Jun-22 12-May-22 20-Sep-22 82
Airport System - IDSS Drawing Submission C01_7 d/w - 10h/d - No HK Hols56
- No B/O periods
0 (was06-May-22
C1) 30-Jun-22 27-Jul-22 20-Sep-22 82
310.D.WS.L448 Airport System - IDSS Drawing Submission - prepare document C01_7 d/w - 10h/d - No HK 14 06-May-22 19-May-22 27-Jul-22 09-Aug-22 82
Hols - No B/O periods (was
310.D.WS.L449 Airport System - IDSS Drawing Submission - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 21 20-May-22 09-Jun-22 10-Aug-22 30-Aug-22 82
Hols - No B/O periods (was
310.D.WS.L450 Airport System - IDSS Drawing Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 7 10-Jun-22 16-Jun-22 31-Aug-22 06-Sep-22 82
Hols - No B/O periods (was
310.D.WS.L452 Airport System - IDSS Drawing Submission - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 14 17-Jun-22 30-Jun-22 07-Sep-22 20-Sep-22 82
Hols - No B/O periods (was
Airport System - IDSS Method Statement Submission C1)
C01_7 d/w - 10h/d - No HK Hols56
- No B/O periods
0 (was06-May-22
C1) 30-Jun-22 27-Jul-22 20-Sep-22 82
310.D.WS.L456 Airport System - IDSS Method Statement Submission - prepare document C01_7 d/w - 10h/d - No HK 14 06-May-22 19-May-22 27-Jul-22 09-Aug-22 82
Hols - No B/O periods (was
310.D.WS.L457 Airport System - IDSS Method Statement Submission - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 21 20-May-22 09-Jun-22 10-Aug-22 30-Aug-22 82
Hols - No B/O periods (was
310.D.WS.L458 Airport System - IDSS Method Statement Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK
7 10-Jun-22 16-Jun-22 31-Aug-22 06-Sep-22 82
Hols - No B/O periods (was
310.D.WS.L460 Airport System - IDSS Method Statement Submission - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 14 17-Jun-22 30-Jun-22 07-Sep-22 20-Sep-22 82
Hols - No B/O periods (was
Airport System - IDSS Material Submission C1)
C01_7 d/w - 10h/d - No HK Hols56
- No B/O periods
0 (was06-May-22
C1) 30-Jun-22 12-May-22 06-Jul-22 6
310.D.WS.L464 Airport System - IDSS Material Submission - prepare document C01_7 d/w - 10h/d - No HK 14 06-May-22 19-May-22 12-May-22 25-May-22 6
Hols - No B/O periods (was
310.D.WS.L465 Airport System - IDSS Material Submission - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 21 20-May-22 09-Jun-22 26-May-22 15-Jun-22 6
Hols - No B/O periods (was
C1)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 75 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L466 Airport System - IDSS Material Submission - prepare resubmission C01_7 d/w - 10h/d - No HK 7 10-Jun-22 16-Jun-22 16-Jun-22 22-Jun-22 6
Hols - No B/O periods (was
310.D.WS.L468 Airport System - IDSS Material Submission - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 14 17-Jun-22 30-Jun-22 23-Jun-22 06-Jul-22 6
Hols - No B/O periods (was
CC#5 - Airport System - Airfield Supervisory Control & Data Acquisition (SCADA) C1)
C01_7 d/w - 10h/d - No HK Hols56
- No B/O periods
0 (was11-May-22
C1) 05-Jul-22 11-May-22 19-Sep-22 76
Airport System - SCADA Drawing Submission C01_7 d/w - 10h/d - No HK Hols56
- No B/O periods
0 (was11-May-22
C1) 05-Jul-22 26-Jul-22 19-Sep-22 76
310.D.WS.L472 Airport System - SCADA Drawing Submission - prepare document C01_7 d/w - 10h/d - No HK 14 11-May-22 24-May-22 26-Jul-22 08-Aug-22 76
Hols - No B/O periods (was
310.D.WS.L473 Airport System - SCADA Drawing Submission - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 21 25-May-22 14-Jun-22 09-Aug-22 29-Aug-22 76
Hols - No B/O periods (was
310.D.WS.L474 Airport System - SCADA Drawing Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 7 15-Jun-22 21-Jun-22 30-Aug-22 05-Sep-22 76
Hols - No B/O periods (was
310.D.WS.L476 Airport System - SCADA Drawing Submission - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 14 22-Jun-22 05-Jul-22 06-Sep-22 19-Sep-22 76
Hols - No B/O periods (was
Airport System - SCADA Method Statement Submission C1)
C01_7 d/w - 10h/d - No HK Hols56
- No B/O periods
0 (was11-May-22
C1) 05-Jul-22 26-Jul-22 19-Sep-22 76
310.D.WS.L480 Airport System - SCADA Method Statement Submission - prepare document C01_7 d/w - 10h/d - No HK 14 11-May-22 24-May-22 26-Jul-22 08-Aug-22 76
Hols - No B/O periods (was
310.D.WS.L481 Airport System - SCADA Method Statement Submission - PM review and accept 1st C1)
C01_7 d/w - 10h/d - No HK 21 25-May-22 14-Jun-22 09-Aug-22 29-Aug-22 76
Round Hols - No B/O periods (was
310.D.WS.L482 Airport System - SCADA Method Statement Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 7 15-Jun-22 21-Jun-22 30-Aug-22 05-Sep-22 76
Hols - No B/O periods (was
310.D.WS.L484 Airport System - SCADA Method Statement Submission - PM review and accept 2nd C1)
C01_7 d/w - 10h/d - No HK 14 22-Jun-22 05-Jul-22 06-Sep-22 19-Sep-22 76
Round Hols - No B/O periods (was
Airport System - SCADA Material Submission C1)
C01_7 d/w - 10h/d - No HK Hols49
- No B/O periods
0 (was11-May-22
C1) 28-Jun-22 11-May-22 28-Jun-22 0
310.D.WS.L488 Airport System - SCADA Material Submission - prepare document C01_7 d/w - 10h/d - No HK 14 11-May-22 24-May-22 11-May-22 24-May-22 0
Hols - No B/O periods (was
310.D.WS.L489 Airport System - SCADA Material Submission - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 21 25-May-22 14-Jun-22 25-May-22 14-Jun-22 0
Hols - No B/O periods (was
310.D.WS.L490 Airport System - SCADA Material Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 7 15-Jun-22 21-Jun-22 15-Jun-22 21-Jun-22 0
Hols - No B/O periods (was
310.D.WS.L492 Airport System - SCADA Material Submission - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 7 22-Jun-22 28-Jun-22 22-Jun-22 28-Jun-22 0
Hols - No B/O periods (was
CC#5 - Airport System - Sub-Pavement Monitoring System (SPMS) C1)
C01_7 d/w - 10h/d - No HK Hols72
- No B/O periods
0 (was11-May-22
C1) 21-Jul-22 11-May-22 04-Oct-22 75
Airport System - SPMS Drawing Submission C01_7 d/w - 10h/d - No HK Hols56
- No B/O periods
0 (was27-May-22
C1) 21-Jul-22 10-Aug-22 04-Oct-22 75
310.D.WS.L496 Airport System - SPMS Drawing Submission - prepare document C01_7 d/w - 10h/d - No HK 14 27-May-22 09-Jun-22 10-Aug-22 23-Aug-22 75
Hols - No B/O periods (was
310.D.WS.L497 Airport System - SPMS Drawing Submission - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 21 10-Jun-22 30-Jun-22 24-Aug-22 13-Sep-22 75
Hols - No B/O periods (was
310.D.WS.L498 Airport System - SPMS Drawing Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 7 01-Jul-22 07-Jul-22 14-Sep-22 20-Sep-22 75
Hols - No B/O periods (was
310.D.WS.L500 Airport System - SPMS Drawing Submission - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 14 08-Jul-22 21-Jul-22 21-Sep-22 04-Oct-22 75
Hols - No B/O periods (was
Airport System - SPMS Method Statement Submission C1)
C01_7 d/w - 10h/d - No HK Hols56
- No B/O periods
0 (was27-May-22
C1) 21-Jul-22 10-Aug-22 04-Oct-22 75
310.D.WS.L504 Airport System - SPMS Method Statement Submission - prepare document C01_7 d/w - 10h/d - No HK 14 27-May-22 09-Jun-22 10-Aug-22 23-Aug-22 75
Hols - No B/O periods (was
310.D.WS.L505 Airport System - SPMS Method Statement Submission - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 21 10-Jun-22 30-Jun-22 24-Aug-22 13-Sep-22 75
Hols - No B/O periods (was
310.D.WS.L506 Airport System - SPMS Method Statement Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 7 01-Jul-22 07-Jul-22 14-Sep-22 20-Sep-22 75
Hols - No B/O periods (was
310.D.WS.L508 Airport System - SPMS Method Statement Submission - PM review and accept 2nd C1)
C01_7 d/w - 10h/d - No HK 14 08-Jul-22 21-Jul-22 21-Sep-22 04-Oct-22 75
Round Hols - No B/O periods (was
C1)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 76 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
Airport System - SPMS Material Submission C01_7 d/w - 10h/d - No HK Hols49
- No B/O periods
0 (was11-May-22
C1) 28-Jun-22 11-May-22 28-Jun-22 0
310.D.WS.L512 Airport System - SPMS Material Submission - prepare document C01_7 d/w - 10h/d - No HK 14 11-May-22 24-May-22 11-May-22 24-May-22 0
Hols - No B/O periods (was
310.D.WS.L513 Airport System - SPMS Material Submission - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 21 25-May-22 14-Jun-22 25-May-22 14-Jun-22 0
Hols - No B/O periods (was
310.D.WS.L514 Airport System - SPMS Material Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 7 15-Jun-22 21-Jun-22 15-Jun-22 21-Jun-22 0
Hols - No B/O periods (was
310.D.WS.L516 Airport System - SPMS Material Submission - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 7 22-Jun-22 28-Jun-22 22-Jun-22 28-Jun-22 0
Hols - No B/O periods (was
CC#5 - Airport System - Airport Network System (AANET) & Time of Day Clock System (TODC) C1)
C01_7 d/w - 10h/d - No HK Hols65
- No B/O periods
0 (was11-May-22
C1) 14-Jul-22 25-May-22 31-Oct-22 109
Airport System - AANET Drawing Submission C01_7 d/w - 10h/d - No HK Hols49
- No B/O periods
0 (was27-May-22
C1) 14-Jul-22 13-Sep-22 31-Oct-22 109
310.D.WS.L520 Airport System - AANET Drawing Submission - prepare document C01_7 d/w - 10h/d - No HK 14 27-May-22 09-Jun-22 13-Sep-22 26-Sep-22 109
Hols - No B/O periods (was
310.D.WS.L521 Airport System - AANET Drawing Submission - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 21 10-Jun-22 30-Jun-22 27-Sep-22 17-Oct-22 109
Hols - No B/O periods (was
310.D.WS.L522 Airport System - AANET Drawing Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 7 01-Jul-22 07-Jul-22 18-Oct-22 24-Oct-22 109
Hols - No B/O periods (was
310.D.WS.L524 Airport System - AANET Drawing Submission - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 7 08-Jul-22 14-Jul-22 25-Oct-22 31-Oct-22 109
Hols - No B/O periods (was
Airport System - AANET Method Statement Submission C1)
C01_7 d/w - 10h/d - No HK Hols49
- No B/O periods
0 (was27-May-22
C1) 14-Jul-22 13-Sep-22 31-Oct-22 109
310.D.WS.L528 Airport System - AANET Method Statement Submission - prepare document C01_7 d/w - 10h/d - No HK 14 27-May-22 09-Jun-22 13-Sep-22 26-Sep-22 109
Hols - No B/O periods (was
310.D.WS.L529 Airport System - AANET Method Statement Submission - PM review and accept 1st C1)
C01_7 d/w - 10h/d - No HK 21 10-Jun-22 30-Jun-22 27-Sep-22 17-Oct-22 109
Round Hols - No B/O periods (was
310.D.WS.L530 Airport System - AANET Method Statement Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 7 01-Jul-22 07-Jul-22 18-Oct-22 24-Oct-22 109
Hols - No B/O periods (was
310.D.WS.L532 Airport System - AANET Method Statement Submission - PM review and accept 2nd C1)
C01_7 d/w - 10h/d - No HK 7 08-Jul-22 14-Jul-22 25-Oct-22 31-Oct-22 109
Round Hols - No B/O periods (was
Airport System - AANET Material Submission C1)
C01_7 d/w - 10h/d - No HK Hols49
- No B/O periods
0 (was11-May-22
C1) 28-Jun-22 25-May-22 12-Jul-22 14
310.D.WS.L536 Airport System - AANET Material Submission - prepare document C01_7 d/w - 10h/d - No HK 14 11-May-22 24-May-22 25-May-22 07-Jun-22 14
Hols - No B/O periods (was
310.D.WS.L537 Airport System - AANET Material Submission - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 21 25-May-22 14-Jun-22 08-Jun-22 28-Jun-22 14
Hols - No B/O periods (was
310.D.WS.L538 Airport System - AANET Material Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 7 15-Jun-22 21-Jun-22 29-Jun-22 05-Jul-22 14
Hols - No B/O periods (was
310.D.WS.L540 Airport System - AANET Material Submission - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 7 22-Jun-22 28-Jun-22 06-Jul-22 12-Jul-22 14
Hols - No B/O periods (was
CC#5 - Airport System - Airport Private Automatic Branch Exchange System (APABX) C1)
C01_7 d/w - 10h/d - No HK Hols72
- No B/O periods
0 (was11-May-22
C1) 21-Jul-22 11-May-22 19-Sep-22 60
Airport System - APABX Drawing Submission C01_7 d/w - 10h/d - No HK Hols56
- No B/O periods
0 (was27-May-22
C1) 21-Jul-22 26-Jul-22 19-Sep-22 60
310.D.WS.L544 Airport System - APABX Drawing Submission - prepare document C01_7 d/w - 10h/d - No HK 14 27-May-22 09-Jun-22 26-Jul-22 08-Aug-22 60
Hols - No B/O periods (was
310.D.WS.L545 Airport System - APABX Drawing Submission - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 21 10-Jun-22 30-Jun-22 09-Aug-22 29-Aug-22 60
Hols - No B/O periods (was
310.D.WS.L546 Airport System - APABX Drawing Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 7 01-Jul-22 07-Jul-22 30-Aug-22 05-Sep-22 60
Hols - No B/O periods (was
310.D.WS.L548 Airport System - APABX Drawing Submission - PM review and accept 2nd Round C1) d/w - 10h/d - No HK
C01_7 14 08-Jul-22 21-Jul-22 06-Sep-22 19-Sep-22 60
Hols - No B/O periods (was
Airport System - APABX Method Statement Submission C1)
C01_7 d/w - 10h/d - No HK Hols56
- No B/O periods
0 (was27-May-22
C1) 21-Jul-22 26-Jul-22 19-Sep-22 60
310.D.WS.L552 Airport System - APABX Method Statement Submission - prepare document C01_7 d/w - 10h/d - No HK 14 27-May-22 09-Jun-22 26-Jul-22 08-Aug-22 60
Hols - No B/O periods (was
C1)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 77 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L553 Airport System - APABX Method Statement Submission - PM review and accept 1st C01_7 d/w - 10h/d - No HK 21 10-Jun-22 30-Jun-22 09-Aug-22 29-Aug-22 60
Round Hols - No B/O periods (was
310.D.WS.L554 Airport System - APABX Method Statement Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 7 01-Jul-22 07-Jul-22 30-Aug-22 05-Sep-22 60
Hols - No B/O periods (was
310.D.WS.L556 Airport System - APABX Method Statement Submission - PM review and accept 2nd C1)
C01_7 d/w - 10h/d - No HK 14 08-Jul-22 21-Jul-22 06-Sep-22 19-Sep-22 60
Round Hols - No B/O periods (was
Airport System - APABX Material Submission C1)
C01_7 d/w - 10h/d - No HK Hols49
- No B/O periods
0 (was11-May-22
C1) 28-Jun-22 11-May-22 28-Jun-22 0
310.D.WS.L560 Airport System - APABX Material Submission - prepare document C01_7 d/w - 10h/d - No HK 14 11-May-22 24-May-22 11-May-22 24-May-22 0
Hols - No B/O periods (was
310.D.WS.L561 Airport System - APABX Material Submission - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 21 25-May-22 14-Jun-22 25-May-22 14-Jun-22 0
Hols - No B/O periods (was
310.D.WS.L562 Airport System - APABX Material Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 7 15-Jun-22 21-Jun-22 15-Jun-22 21-Jun-22 0
Hols - No B/O periods (was
310.D.WS.L564 Airport System - APABX Material Submission - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 7 22-Jun-22 28-Jun-22 22-Jun-22 28-Jun-22 0
Hols - No B/O periods (was
CC#5 - Airport System - Trunked Mobile Radio System (TMR) C1)
C01_7 d/w - 10h/d - No HK Hols72
- No B/O periods
0 (was11-May-22
C1) 21-Jul-22 11-May-22 19-Sep-22 60
Airport System - TMR Drawing Submission C01_7 d/w - 10h/d - No HK Hols56
- No B/O periods
0 (was27-May-22
C1) 21-Jul-22 26-Jul-22 19-Sep-22 60
310.D.WS.L568 Airport System - TMR Drawing Submission - prepare document C01_7 d/w - 10h/d - No HK 14 27-May-22 09-Jun-22 26-Jul-22 08-Aug-22 60
Hols - No B/O periods (was
310.D.WS.L569 Airport System - TMR Drawing Submission - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 21 10-Jun-22 30-Jun-22 09-Aug-22 29-Aug-22 60
Hols - No B/O periods (was
310.D.WS.L570 Airport System - TMR Drawing Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 7 01-Jul-22 07-Jul-22 30-Aug-22 05-Sep-22 60
Hols - No B/O periods (was
310.D.WS.L572 Airport System - TMR Drawing Submission - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 14 08-Jul-22 21-Jul-22 06-Sep-22 19-Sep-22 60
Hols - No B/O periods (was
Airport System - TMR Method Statement Submission C1)
C01_7 d/w - 10h/d - No HK Hols56
- No B/O periods
0 (was27-May-22
C1) 21-Jul-22 26-Jul-22 19-Sep-22 60
310.D.WS.L576 Airport System - TMR Method Statement Submission - prepare document C01_7 d/w - 10h/d - No HK 14 27-May-22 09-Jun-22 26-Jul-22 08-Aug-22 60
Hols - No B/O periods (was
310.D.WS.L577 Airport System - TMR Method Statement Submission - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 21 10-Jun-22 30-Jun-22 09-Aug-22 29-Aug-22 60
Hols - No B/O periods (was
310.D.WS.L578 Airport System - TMR Method Statement Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK
7 01-Jul-22 07-Jul-22 30-Aug-22 05-Sep-22 60
Hols - No B/O periods (was
310.D.WS.L580 Airport System - TMR Method Statement Submission - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 14 08-Jul-22 21-Jul-22 06-Sep-22 19-Sep-22 60
Hols - No B/O periods (was
Airport System - TMR Material Submission C1)
C01_7 d/w - 10h/d - No HK Hols49
- No B/O periods
0 (was11-May-22
C1) 28-Jun-22 11-May-22 28-Jun-22 0
310.D.WS.L584 Airport System - TMR Material Submission - prepare document C01_7 d/w - 10h/d - No HK 14 11-May-22 24-May-22 11-May-22 24-May-22 0
Hols - No B/O periods (was
310.D.WS.L585 Airport System - TMR Material Submission - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 21 25-May-22 14-Jun-22 25-May-22 14-Jun-22 0
Hols - No B/O periods (was
310.D.WS.L586 Airport System - TMR Material Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 7 15-Jun-22 21-Jun-22 15-Jun-22 21-Jun-22 0
Hols - No B/O periods (was
310.D.WS.L588 Airport System - TMR Material Submission - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 7 22-Jun-22 28-Jun-22 22-Jun-22 28-Jun-22 0
Hols - No B/O periods (was
CC#5 - Airport System - Voice & Data Cabling System (VDC) C1)
C01_7 d/w - 10h/d - No HK Hols72
- No B/O periods
0 (was26-Apr-22
C1) 06-Jul-22 26-Apr-22 19-Sep-22 75
Airport System - VDC Drawing Submission C01_7 d/w - 10h/d - No HK Hols56
- No B/O periods
0 (was12-May-22
C1) 06-Jul-22 26-Jul-22 19-Sep-22 75
310.D.WS.L592 Airport System - VDC Drawing Submission - prepare document C01_7 d/w - 10h/d - No HK 14 12-May-22 25-May-22 26-Jul-22 08-Aug-22 75
Hols - No B/O periods (was
310.D.WS.L593 Airport System - VDC Drawing Submission - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 21 26-May-22 15-Jun-22 09-Aug-22 29-Aug-22 75
Hols - No B/O periods (was
310.D.WS.L594 Airport System - VDC Drawing Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 7 16-Jun-22 22-Jun-22 30-Aug-22 05-Sep-22 75
Hols - No B/O periods (was
C1)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 78 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L596 Airport System - VDC Drawing Submission - PM review and accept 2nd Round C01_7 d/w - 10h/d - No HK 14 23-Jun-22 06-Jul-22 06-Sep-22 19-Sep-22 75
Hols - No B/O periods (was
Airport System - VDC Method Statement Submission C1)
C01_7 d/w - 10h/d - No HK Hols56
- No B/O periods
0 (was12-May-22
C1) 06-Jul-22 26-Jul-22 19-Sep-22 75
310.D.WS.L600 Airport System - VDC Method Statement Submission - prepare document C01_7 d/w - 10h/d - No HK 14 12-May-22 25-May-22 26-Jul-22 08-Aug-22 75
Hols - No B/O periods (was
310.D.WS.L601 Airport System - VDC Method Statement Submission - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 21 26-May-22 15-Jun-22 09-Aug-22 29-Aug-22 75
Hols - No B/O periods (was
310.D.WS.L602 Airport System - VDC Method Statement Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 7 16-Jun-22 22-Jun-22 30-Aug-22 05-Sep-22 75
Hols - No B/O periods (was
310.D.WS.L604 Airport System - VDC Method Statement Submission - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 14 23-Jun-22 06-Jul-22 06-Sep-22 19-Sep-22 75
Hols - No B/O periods (was
Airport System - VDC Material Submission C1)
C01_7 d/w - 10h/d - No HK Hols49
- No B/O periods
0 (was26-Apr-22
C1) 13-Jun-22 26-Apr-22 13-Jun-22 0
310.D.WS.L608 Airport System - VDC Material Submission - prepare document C01_7 d/w - 10h/d - No HK 14 26-Apr-22 09-May-22 26-Apr-22 09-May-22 0
Hols - No B/O periods (was
310.D.WS.L609 Airport System - VDC Material Submission - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 21 10-May-22 30-May-22 10-May-22 30-May-22 0
Hols - No B/O periods (was
310.D.WS.L610 Airport System - VDC Material Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 7 31-May-22 06-Jun-22 31-May-22 06-Jun-22 0
Hols - No B/O periods (was
310.D.WS.L612 Airport System - VDC Material Submission - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 7 07-Jun-22 13-Jun-22 07-Jun-22 13-Jun-22 0
Hols - No B/O periods (was
CC#5 - Airport System - Apron Wireless LAN System (WNET) C1)
C01_7 d/w - 10h/d - No HK Hols56
- No B/O periods
0 (was11-May-22
C1) 05-Jul-22 13-May-22 19-Sep-22 76
Airport System - WNET Drawing Submission C01_7 d/w - 10h/d - No HK Hols56
- No B/O periods
0 (was11-May-22
C1) 05-Jul-22 26-Jul-22 19-Sep-22 76
310.D.WS.L616 Airport System - WNET Drawing Submission - prepare document C01_7 d/w - 10h/d - No HK 14 11-May-22 24-May-22 26-Jul-22 08-Aug-22 76
Hols - No B/O periods (was
310.D.WS.L617 Airport System - WNET Drawing Submission - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 21 25-May-22 14-Jun-22 09-Aug-22 29-Aug-22 76
Hols - No B/O periods (was
310.D.WS.L618 Airport System - WNET Drawing Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 7 15-Jun-22 21-Jun-22 30-Aug-22 05-Sep-22 76
Hols - No B/O periods (was
310.D.WS.L620 Airport System - WNET Drawing Submission - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 14 22-Jun-22 05-Jul-22 06-Sep-22 19-Sep-22 76
Hols - No B/O periods (was
Airport System - WNET Method Statement Submission C1)
C01_7 d/w - 10h/d - No HK Hols49
- No B/O periods
0 (was11-May-22
C1) 28-Jun-22 02-Aug-22 19-Sep-22 83
310.D.WS.L624 Airport System - WNET Method Statement Submission - prepare document C01_7 d/w - 10h/d - No HK 14 11-May-22 24-May-22 02-Aug-22 15-Aug-22 83
Hols - No B/O periods (was
310.D.WS.L625 Airport System - WNET Method Statement Submission - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 21 25-May-22 14-Jun-22 16-Aug-22 05-Sep-22 83
Hols - No B/O periods (was
310.D.WS.L626 Airport System - WNET Method Statement Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 7 15-Jun-22 21-Jun-22 06-Sep-22 12-Sep-22 83
Hols - No B/O periods (was
310.D.WS.L628 Airport System - WNET Method Statement Submission - PM review and accept 2nd C1)
C01_7 d/w - 10h/d - No HK 7 22-Jun-22 28-Jun-22 13-Sep-22 19-Sep-22 83
Round Hols - No B/O periods (was
Airport System - WNET Material Submission C1)
C01_7 d/w - 10h/d - No HK Hols49
- No B/O periods
0 (was11-May-22
C1) 28-Jun-22 13-May-22 30-Jun-22 2
310.D.WS.L632 Airport System - WNET Material Submission - prepare document C01_7 d/w - 10h/d - No HK 14 11-May-22 24-May-22 13-May-22 26-May-22 2
Hols - No B/O periods (was
310.D.WS.L633 Airport System - WNET Material Submission - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 21 25-May-22 14-Jun-22 27-May-22 16-Jun-22 2
Hols - No B/O periods (was
310.D.WS.L634 Airport System - WNET Material Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 7 15-Jun-22 21-Jun-22 17-Jun-22 23-Jun-22 2
Hols - No B/O periods (was
310.D.WS.L636 Airport System - WNET Material Submission - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 7 22-Jun-22 28-Jun-22 24-Jun-22 30-Jun-22 2
Hols - No B/O periods (was
CC#5 - Airport System - Tunnel Traffic Lane Control System (TTLCS) C1)
C01_7 d/w - 10h/d - No HK Hols56
- No B/O periods
0 (was11-May-22
C1) 05-Jul-22 13-May-22 04-Oct-22 91
Airport System - TTLCS Drawing Submission C01_7 d/w - 10h/d - No HK Hols56
- No B/O periods
0 (was11-May-22
C1) 05-Jul-22 10-Aug-22 04-Oct-22 91

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 79 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L2032.B01 Airport System - TTLCS Drawing Submission - prepare document C01_7 d/w - 10h/d - No HK 14 11-May-22 24-May-22 10-Aug-22 23-Aug-22 91
Hols - No B/O periods (was
310.D.WS.L2044.B01 Airport System - TTLCS Drawing Submission - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 21 25-May-22 14-Jun-22 24-Aug-22 13-Sep-22 91
Hols - No B/O periods (was
310.D.WS.L2040.B01 Airport System - TTLCS Drawing Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 7 15-Jun-22 21-Jun-22 14-Sep-22 20-Sep-22 91
Hols - No B/O periods (was
310.D.WS.L2036.B01 Airport System - TTLCS Drawing Submission - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 14 22-Jun-22 05-Jul-22 21-Sep-22 04-Oct-22 91
Hols - No B/O periods (was
Airport System - TTLCS Method Statement Submission C1)
C01_7 d/w - 10h/d - No HK Hols49
- No B/O periods
0 (was11-May-22
C1) 28-Jun-22 17-Aug-22 04-Oct-22 98
310.D.WS.L2048.B01 Airport System - TTLCS Method Statement Submission - prepare document C01_7 d/w - 10h/d - No HK 14 11-May-22 24-May-22 17-Aug-22 30-Aug-22 98
Hols - No B/O periods (was
310.D.WS.L2060.B01 Airport System - TTLCS Method Statement Submission - PM review and accept 1st C1)
C01_7 d/w - 10h/d - No HK 21 25-May-22 14-Jun-22 31-Aug-22 20-Sep-22 98
Round Hols - No B/O periods (was
310.D.WS.L2056.B01 Airport System - TTLCS Method Statement Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 7 15-Jun-22 21-Jun-22 21-Sep-22 27-Sep-22 98
Hols - No B/O periods (was
310.D.WS.L2052.B01 Airport System - TTLCS Method Statement Submission - PM review and accept 2nd C1)
C01_7 d/w - 10h/d - No HK 7 22-Jun-22 28-Jun-22 28-Sep-22 04-Oct-22 98
Round Hols - No B/O periods (was
Airport System - TTLCS Material Submission C1)
C01_7 d/w - 10h/d - No HK Hols49
- No B/O periods
0 (was11-May-22
C1) 28-Jun-22 13-May-22 30-Jun-22 2
310.D.WS.L2064.B01 Airport System - TTLCS Material Submission - prepare document C01_7 d/w - 10h/d - No HK 14 11-May-22 24-May-22 13-May-22 26-May-22 2
Hols - No B/O periods (was
310.D.WS.L2076.B01 Airport System - TTLCS Material Submission - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 21 25-May-22 14-Jun-22 27-May-22 16-Jun-22 2
Hols - No B/O periods (was
310.D.WS.L2072.B01 Airport System - TTLCS Material Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 7 15-Jun-22 21-Jun-22 17-Jun-22 23-Jun-22 2
Hols - No B/O periods (was
310.D.WS.L2068.B01 Airport System - TTLCS Material Submission - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 7 22-Jun-22 28-Jun-22 24-Jun-22 30-Jun-22 2
Hols - No B/O periods (was
CC#5 ----- Procurement ----- C1)
C01_7 d/w - 10h/d - No HK Hols428
- No B/O periods
0 (was
01-Nov-21
C1) A 26-Feb-23 27-Mar-22 06-Aug-23 161
Subletting C01_7 d/w - 10h/d - No HK Hols125
- No B/O periods
0 (was
01-Nov-21
C1) A 10-May-22 27-Mar-22 18-Oct-22 161
310.P.AF.F564.B01 Subletting - Airport System IDSS - Stage 1&2 Preparation, Submission & Approval, C01_7 d/w - 10h/d - No HK 90 01-Nov-21 A 19-Apr-22 02-Apr-22 25-Apr-22 6
Tender & Award sub-contract Hols - No B/O periods (was
310.P.AF.F532.B01 Subletting - Airport System VDC & LAN- Stage 1&2 Preparation, Submission & Approval, C1)
C01_7 d/w - 10h/d - No HK 90 01-Nov-21 A 25-Apr-22 27-Mar-22 25-Apr-22 0
Tender & Award sub-contract Hols - No B/O periods (was
310.P.AF.F528 Subletting - Airport System AANET & WNET - Stage 1&2 Preparation, Submission & C1)
C01_7 d/w - 10h/d - No HK 90 01-Nov-21 A 10-May-22 29-Mar-22 12-May-22 2
Approval, Tender & Award sub-contract Hols - No B/O periods (was
310.P.AF.F536.B01 Subletting - Airport System SPMS - Stage 1&2 Preparation, Submission & Approval, C1)
C01_7 d/w - 10h/d - No HK 90 01-Nov-21 A 10-May-22 27-Mar-22 10-May-22 0
Tender & Award sub-contract Hols - No B/O periods (was
310.P.AF.F540.B01 Subletting - Airport System BCS - Stage 1&2 Preparation, Submission & Approval, Tender C1)
C01_7 d/w - 10h/d - No HK 90 01-Nov-21 A 10-May-22 04-Sep-22 18-Oct-22 161
& Award sub-contract Hols - No B/O periods (was
310.P.AF.F544.B01 Subletting - Airport System APABX - Stage 1&2 Preparation, Submission & Approval, C1)
C01_7 d/w - 10h/d - No HK 90 01-Nov-21 A 10-May-22 27-Mar-22 10-May-22 0
Tender & Award sub-contract Hols - No B/O periods (was
310.P.AF.F548.B01 Subletting - Airport System ACS - Stage 1&2 Preparation, Submission & Approval, Tender C1)
C01_7 d/w - 10h/d - No HK 90 01-Nov-21 A 10-May-22 27-Mar-22 10-May-22 0
& Award sub-contract Hols - No B/O periods (was
310.P.AF.F552.B01 Subletting - Airport System SCADA - Stage 1&2 Preparation, Submission & Approval, C1)
C01_7 d/w - 10h/d - No HK 90 01-Nov-21 A 10-May-22 27-Mar-22 10-May-22 0
Tender & Award sub-contract Hols - No B/O periods (was
310.P.AF.F556.B01 Subletting - Airport System TMR - Stage 1&2 Preparation, Submission & Approval, C1)
C01_7 d/w - 10h/d - No HK 90 01-Nov-21 A 10-May-22 27-Mar-22 10-May-22 0
Tender & Award sub-contract Hols - No B/O periods (was
310.P.AF.F560.B01 Subletting - Airport System ALWS - Stage 1&2 Preparation, Submission & Approval, C1)
C01_7 d/w - 10h/d - No HK 90 01-Nov-21 A 10-May-22 27-Mar-22 10-May-22 0
Tender & Award sub-contract Hols - No B/O periods (was
310.P.AF.F568.B01 Subletting - Airport System CCTV - Stage 1&2 Preparation, Submission & Approval, C1)
C01_7 d/w - 10h/d - No HK 90 01-Nov-21 A 10-May-22 27-Mar-22 10-May-22 0
Tender & Award sub-contract Hols - No B/O periods (was
C1)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 80 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.P.AF.F569.B01 Subletting - Airport System TTLCS - Stage 1&2 Preparation, Submission & Approval, C01_7 d/w - 10h/d - No HK 90 01-Nov-21 A 10-May-22 29-Mar-22 12-May-22 2
Tender & Award sub-contract Hols - No B/O periods (was
Procurement C1)
C01_7 d/w - 10h/d - No HK Hols258
- No B/O periods
0 (was14-Jun-22
C1) 26-Feb-23 14-Jun-22 06-Aug-23 161
Airport System - Access Control System (ACS) C01_7 d/w - 10h/d - No HK Hols124
- No B/O periods
0 (was29-Jun-22
C1) 30-Oct-22 29-Jun-22 14-Nov-22 15
310.P.ES.P60 Airport System (Procurement ACS) - Access Control System ACS - Place Order for C01_7 d/w - 10h/d - No HK 4 29-Jun-22 02-Jul-22 29-Jun-22 02-Jul-22 0
Material Hols - No B/O periods (was
310.P.ES.P78 Airport System (Procurement ACS) - Access Control System ACS - FAT/ Mockup C1)
C01_7 d/w - 10h/d - No HK 120 03-Jul-22 30-Oct-22 03-Jul-22 30-Oct-22 0
/Manufacturing of Material Hols - No B/O periods (was
310.P.ES.P98.B01 Airport System (Procurement ACS) - Access Control System ACS - Delivery of Material C1)
C01_7 d/w - 10h/d - No HK 14 06-Sep-22 19-Sep-22 06-Sep-22 19-Sep-22 0
for AGL Vault D Hols - No B/O periods (was
310.P.ES.P99.B01 Airport System (Procurement ACS) - Access Control System ACS - Delivery of Material C1)
C01_7 d/w - 10h/d - No HK 14 21-Sep-22 04-Oct-22 21-Sep-22 04-Oct-22 0
for PBB Comms Room Hols - No B/O periods (was
310.P.ES.P86 Airport System (Procurement ACS) - Access Control System ACS - Delivery of Material C1)
C01_7 d/w - 10h/d - No HK 7 24-Oct-22 30-Oct-22 08-Nov-22 14-Nov-22 15
Hols - No B/O periods (was
Airport System - Airport Lightning Warnings System (ALWS) C1)
C01_7 d/w - 10h/d - No HK Hols124
- No B/O periods
0 (was29-Jun-22
C1) 30-Oct-22 29-Jun-22 23-Nov-22 24
310.P.WS.M564 Airport System (Procurement ALWS) - Airport Lightning Warnings System ALWS - Place C01_7 d/w - 10h/d - No HK 4 29-Jun-22 02-Jul-22 29-Jun-22 02-Jul-22 0
Order for Material Hols - No B/O periods (was
310.P.WS.M568 Airport System (Procurement ALWS) - Airport Lightning Warnings System ALWS - FAT/ C1)
C01_7 d/w - 10h/d - No HK 120 03-Jul-22 30-Oct-22 03-Jul-22 30-Oct-22 0
Mockup /Manufacturing of Material Hols - No B/O periods (was
310.P.WS.M572.B01 Airport System (Procurement ALWS) - Airport Lightning Warnings System ALWS - C1)
C01_7 d/w - 10h/d - No HK 7 13-Sep-22 19-Sep-22 13-Sep-22 19-Sep-22 0
Delivery of Material for AGL Vault D Hols - No B/O periods (was
310.P.WS.M576 Airport System (Procurement ALWS) - Airport Lightning Warnings System ALWS - C1)
C01_7 d/w - 10h/d - No HK 7 24-Oct-22 30-Oct-22 17-Nov-22 23-Nov-22 24
Delivery of Material Hols - No B/O periods (was
Airport System - Bird Control System (BCS) C1)
C01_7 d/w - 10h/d - No HK Hols148
- No B/O periods
0 (was02-Oct-22
C1) 26-Feb-23 12-Mar-23 06-Aug-23 161
310.P.WS.M580 Airport System - Bird Control System BCS - Place Order for Material C01_7 d/w - 10h/d - No HK 14 02-Oct-22 15-Oct-22 12-Mar-23 25-Mar-23 161
Hols - No B/O periods (was
310.P.WS.M596 Airport System - Bird Control System BCS - FAT/ Mockup /Manufacturing of Material C1)
C01_7 d/w - 10h/d - No HK 120 16-Oct-22 12-Feb-23 26-Mar-23 23-Jul-23 161
Hols - No B/O periods (was
310.P.WS.M604 Airport System - Bird Control System BCS - Delivery of Material C1)
C01_7 d/w - 10h/d - No HK 14 13-Feb-23 26-Feb-23 24-Jul-23 06-Aug-23 161
Hols - No B/O periods (was
Airport System - Closed Circuit Television System (CCTV) C1)
C01_7 d/w - 10h/d - No HK Hols131
- No B/O periods
0 (was29-Jun-22
C1) 06-Nov-22 29-Jun-22 15-Nov-22 9
310.P.WS.M620 Airport System (Procurement CCTV) - Closed Circuit System CCTV - Place Order for C01_7 d/w - 10h/d - No HK 4 29-Jun-22 02-Jul-22 29-Jun-22 02-Jul-22 0
Material Hols - No B/O periods (was
310.P.WS.M624 Airport System (Procurement CCTV) - Closed Circuit System CCTV - FAT/ Mockup C1)
C01_7 d/w - 10h/d - No HK 120 03-Jul-22 30-Oct-22 03-Jul-22 30-Oct-22 0
/Manufacturing of Material Hols - No B/O periods (was
310.P.WS.M628.B01 Airport System (Procurement CCTV) - Closed Circuit System CCTV - Delivery of Material C1)
C01_7 d/w - 10h/d - No HK 7 13-Sep-22 19-Sep-22 13-Sep-22 19-Sep-22 0
for AGL Vault D Hols - No B/O periods (was
310.P.WS.M684.B01 Airport System (Procurement CCTV) - Closed Circuit System CCTV - Delivery of Material C1)
C01_7 d/w - 10h/d - No HK 9 26-Sep-22 04-Oct-22 26-Sep-22 04-Oct-22 0
for PBB Comms Rm Hols - No B/O periods (was
310.P.WS.M632 Airport System (Procurement CCTV) - Closed Circuit System CCTV - Delivery of Material C1)
C01_7 d/w - 10h/d - No HK 7 31-Oct-22 06-Nov-22 09-Nov-22 15-Nov-22 9
Hols - No B/O periods (was
Airport System - Intrusion Detection & Surveillance System (IDSS) C1)
C01_7 d/w - 10h/d - No HK Hols131
- No B/O periods
0 (was01-Jul-22
C1) 08-Nov-22 07-Jul-22 14-Nov-22 6
310.P.ES.M637 Airport System - Intrusion Detection & Surveillance System - Place Order for Material C01_7 d/w - 10h/d - No HK 4 01-Jul-22 04-Jul-22 07-Jul-22 10-Jul-22 6
Hols - No B/O periods (was
310.P.ES.M641 Airport System - Intrusion Detection & Surveillance System - FAT/ Mockup Manufacturing C1)
C01_7 d/w - 10h/d - No HK 120 05-Jul-22 01-Nov-22 11-Jul-22 07-Nov-22 6
of Material Hols - No B/O periods (was
310.P.ES.M649 Airport System - Intrusion Detection & Surveillance System - Delivery of Material C1)
C01_7 d/w - 10h/d - No HK 7 02-Nov-22 08-Nov-22 08-Nov-22 14-Nov-22 6
Hols - No B/O periods (was
Airport System - Airfield Supervisory Control & Data Acquisition (SCADA) C1)
C01_7 d/w - 10h/d - No HK Hols124
- No B/O periods
0 (was29-Jun-22
C1) 30-Oct-22 29-Jun-22 14-Nov-22 15
310.P.RC.D395 Airport System (Procurement SCADA) - Intrusion Detection & Surveillance System C01_7 d/w - 10h/d - No HK 4 29-Jun-22 02-Jul-22 29-Jun-22 02-Jul-22 0
SCADA - Place Order for Material Hols - No B/O periods (was
C1)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 81 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.P.RC.D399 Airport System (Procurement SCADA)- Intrusion Detection & Surveillance Sys SCADA - C01_7 d/w - 10h/d - No HK 120 03-Jul-22 30-Oct-22 03-Jul-22 30-Oct-22 0
FAT/ Mockup Manufacturing of Material Hols - No B/O periods (was
310.P.RC.D403.B01 Airport System (Procurement SCADA) - Intrusion Detection & Surveillance Sys SCADA - C1)
C01_7 d/w - 10h/d - No HK 7 13-Sep-22 19-Sep-22 13-Sep-22 19-Sep-22 0
Delivery of Material for AGL Vault D Hols - No B/O periods (was
310.P.RC.D419.B01 Airport System (Procurement SCADA) - Intrusion Detection & Surveillance Sys SCADA - C1)
C01_7 d/w - 10h/d - No HK 9 26-Sep-22 04-Oct-22 26-Sep-22 04-Oct-22 0
Delivery of Material for PBB CommsRm Hols - No B/O periods (was
310.P.RC.D407 Airport System (Procurement SCADA) - Intrusion Detection & Surveillance Sys SCADA - C1)
C01_7 d/w - 10h/d - No HK 7 24-Oct-22 30-Oct-22 08-Nov-22 14-Nov-22 15
Delivery of Material Hols - No B/O periods (was
Airport System - Sub-Pavement Monitoring System (SPMS) C1)
C01_7 d/w - 10h/d - No HK Hols131
- No B/O periods
0 (was29-Jun-22
C1) 06-Nov-22 29-Jun-22 20-Jan-23 75
310.P.RC.D367 Airport System - Sub-Pavement Monitoring System SPMS - Place Order for Material C01_7 d/w - 10h/d - No HK 4 29-Jun-22 02-Jul-22 29-Jun-22 02-Jul-22 0
Hols - No B/O periods (was
310.P.RC.D371 Airport System - Sub-Pavement Monitoring System SPMS - FAT/ Mockup Manufacturing C1)
C01_7 d/w - 10h/d - No HK 120 03-Jul-22 30-Oct-22 03-Jul-22 30-Oct-22 0
of Material Hols - No B/O periods (was
310.P.RC.D383.B01 Airport System - Sub-Pavement Monitoring System SPMS - Delivery of Material for PBB C1)
C01_7 d/w - 10h/d - No HK 9 26-Sep-22 04-Oct-22 26-Sep-22 04-Oct-22 0
Comms Rm Hols - No B/O periods (was
310.P.RC.D379 Airport System - Sub-Pavement Monitoring System SPMS - Delivery of Material C1)
C01_7 d/w - 10h/d - No HK 7 31-Oct-22 06-Nov-22 14-Jan-23 20-Jan-23 75
Hols - No B/O periods (was
Airport System - Airport Network System (AANET) & Time of Day Clock System (TODC) C1)
C01_7 d/w - 10h/d - No HK Hols111
- No B/O periods
0 (was29-Jun-22
C1) 17-Oct-22 13-Jul-22 31-Oct-22 14
310.P.RC.D411 Airport System - Airport Network System TODC/ AANET - Place Order for Material C01_7 d/w - 10h/d - No HK 4 29-Jun-22 02-Jul-22 13-Jul-22 16-Jul-22 14
Hols - No B/O periods (was
310.P.RC.D415 Airport System - Airport Network System TODC/ AANET - FAT/ Mockup Manufacturing of C1)
C01_7 d/w - 10h/d - No HK 100 03-Jul-22 10-Oct-22 17-Jul-22 24-Oct-22 14
Material Hols - No B/O periods (was
310.P.RC.D423 Airport System - Airport Network System TODC/ AANET - Delivery of Material C1)
C01_7 d/w - 10h/d - No HK 7 11-Oct-22 17-Oct-22 25-Oct-22 31-Oct-22 14
Hols - No B/O periods (was
Airport System - Airport Private Automatic Branch Exchange System (APABX) C1)
C01_7 d/w - 10h/d - No HK Hols124
- No B/O periods
0 (was29-Jun-22
C1) 30-Oct-22 29-Jun-22 14-Nov-22 15
310.P.RC.P650 Airport System (Procurement APABX) - Airport Private Automatic Branch Exchange C01_7 d/w - 10h/d - No HK 4 29-Jun-22 02-Jul-22 29-Jun-22 02-Jul-22 0
System APABX - Place Order for Material Hols - No B/O periods (was
310.P.RC.P654 Airport System (Procurement APABX) - Airport Private Automatic Branch Exchange Sys C1)
C01_7 d/w - 10h/d - No HK 120 03-Jul-22 30-Oct-22 03-Jul-22 30-Oct-22 0
APABX - FAT/ Mockup Manufacturing Hols - No B/O periods (was
310.P.RC.P710.B01 Airport System (Procurement APABX) - Airport Private Automatic Branch Exchange C1)
C01_7 d/w - 10h/d - No HK 7 13-Sep-22 19-Sep-22 13-Sep-22 19-Sep-22 0
System APABX - Delivery for AGL Vault D Hols - No B/O periods (was
310.P.RC.P706.B01 Airport System (Procurement APABX) - Airport Private Automatic Branch Exchange C1)
C01_7 d/w - 10h/d - No HK 9 26-Sep-22 04-Oct-22 26-Sep-22 04-Oct-22 0
System APABX - Delivery for PBB Comms Rm Hols - No B/O periods (was
310.P.RC.P658 Airport System (Procurement APABX) - Airport Private Automatic Branch Exchange C1)
C01_7 d/w - 10h/d - No HK 7 24-Oct-22 30-Oct-22 08-Nov-22 14-Nov-22 15
System APABX - Delivery of Material Hols - No B/O periods (was
Airport System - Trunked Mobile Radio System (TMR) C1)
C01_7 d/w - 10h/d - No HK Hols131
- No B/O periods
0 (was29-Jun-22
C1) 06-Nov-22 29-Jun-22 15-Nov-22 9
310.P.RC.P590 Airport System (Procurement TMR) - Trucked Mobile Radio System TMR - Place Order C01_7 d/w - 10h/d - No HK 4 29-Jun-22 02-Jul-22 29-Jun-22 02-Jul-22 0
for Material Hols - No B/O periods (was
310.P.RC.P598 Airport System (Procurement TMR) - Trucked Mobile Radio System TMR - FAT/ Mockup C1)
C01_7 d/w - 10h/d - No HK 120 03-Jul-22 30-Oct-22 03-Jul-22 30-Oct-22 0
Manufacturing of Material Hols - No B/O periods (was
310.P.RC.P602.B01 Airport System (Procurement TMR) - Trucked Mobile Radio System TMR - Delivery of C1)
C01_7 d/w - 10h/d - No HK 7 13-Sep-22 19-Sep-22 13-Sep-22 19-Sep-22 0
Material for AGL Vault D Hols - No B/O periods (was
310.P.RC.P610.B01 Airport System (Procurement TMR) - Trucked Mobile Radio System TMR - Delivery of C1)
C01_7 d/w - 10h/d - No HK 9 26-Sep-22 04-Oct-22 26-Sep-22 04-Oct-22 0
Material for PBB Comms Rm Hols - No B/O periods (was
310.P.RC.P606 Airport System (Procurement TMR) - Trucked Mobile Radio System TMR - Delivery of C1)
C01_7 d/w - 10h/d - No HK 7 31-Oct-22 06-Nov-22 09-Nov-22 15-Nov-22 9
Material Hols - No B/O periods (was
Airport System - Voice & Data Cabling System (VDC) C1)
C01_7 d/w - 10h/d - No HK Hols131
- No B/O periods
0 (was14-Jun-22
C1) 22-Oct-22 14-Jun-22 31-Oct-22 9
310.P.RC.P618 Airport System (Procurement VDC) - Voice & Data Cabling System VDC - Place Order for C01_7 d/w - 10h/d - No HK 4 14-Jun-22 17-Jun-22 14-Jun-22 17-Jun-22 0
Material Hols - No B/O periods (was
310.P.RC.P626 Airport System (Procurement VDC) - Voice & Data Cabling System VDC - FAT/ Mockup C1) C01_7 d/w - 10h/d - No HK 120 18-Jun-22 15-Oct-22 18-Jun-22 15-Oct-22 0
Manufacturing of Material Hols - No B/O periods (was
C1)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 82 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.P.RC.P630.B01 Airport System (Procurement VDC) - Voice & Data Cabling System VDC - Delivery of C01_7 d/w - 10h/d - No HK 9 11-Sep-22 19-Sep-22 11-Sep-22 19-Sep-22 0
Material for AGL Vault D Hols - No B/O periods (was
310.P.RC.P698.B01 Airport System (Procurement VDC) - Voice & Data Cabling System VDC - Delivery of C1)
C01_7 d/w - 10h/d - No HK 14 16-Sep-22 29-Sep-22 21-Sep-22 04-Oct-22 5
Material for PBB Comms Rm Hols - No B/O periods (was
310.P.RC.P702.B01 Airport System (Procurement VDC) - Voice & Data Cabling System VDC - Delivery of C1)
C01_7 d/w - 10h/d - No HK 9 21-Sep-22 29-Sep-22 29-Sep-22 07-Oct-22 8
Material for GSE Vehicle Wash Facility Hols - No B/O periods (was
310.P.RC.P634 Airport System (Procurement VDC) - Voice & Data Cabling System VDC - Delivery of C1)
C01_7 d/w - 10h/d - No HK 7 16-Oct-22 22-Oct-22 25-Oct-22 31-Oct-22 9
Material Hols - No B/O periods (was
Airport System - Apron Wireless LAN System (WNET) C1)
C01_7 d/w - 10h/d - No HK Hols111
- No B/O periods
0 (was29-Jun-22
C1) 17-Oct-22 01-Jul-22 31-Oct-22 14
310.P.RC.P638 Airport System (Procurement WNET) - Apron Wireless LAN System WNET - Place Order C01_7 d/w - 10h/d - No HK 4 29-Jun-22 02-Jul-22 01-Jul-22 04-Jul-22 2
for Material Hols - No B/O periods (was
310.P.RC.P642 Airport System (Procurement WNET) - Apron Wireless LAN System WNET - FAT/ C1)
C01_7 d/w - 10h/d - No HK 100 03-Jul-22 10-Oct-22 05-Jul-22 12-Oct-22 2
Mockup Manufacturing of Material Hols - No B/O periods (was
310.P.RC.P698 Airport System (Procurement WNET) - Apron Wireless LAN System WNET - Delivery of C1)
C01_7 d/w - 10h/d - No HK 7 26-Sep-22 02-Oct-22 28-Sep-22 04-Oct-22 2
Material for PBB Comms Rm Hols - No B/O periods (was
310.P.RC.P646 Airport System (Procurement WNET) - Apron Wireless LAN System WNET - Delivery of C1)
C01_7 d/w - 10h/d - No HK 7 11-Oct-22 17-Oct-22 25-Oct-22 31-Oct-22 14
Material Hols - No B/O periods (was
Airport System - Tunnel Traffic Lane Control System (TTLCS) C1)
C01_7 d/w - 10h/d - No HK Hols111
- No B/O periods
0 (was29-Jun-22
C1) 17-Oct-22 01-Jul-22 31-Oct-22 14
310.P.ES.P166.B01 Airport System (Procurement TTLCS) - Tunnel Traffic Lane Control System - Place Order C01_7 d/w - 10h/d - No HK 4 29-Jun-22 02-Jul-22 01-Jul-22 04-Jul-22 2
for Material Hols - No B/O periods (was
310.P.ES.P170.B01 Airport System (Procurement TTLCS) - Tunnel Traffic Lane Control System - FAT/ C1)
C01_7 d/w - 10h/d - No HK 100 03-Jul-22 10-Oct-22 05-Jul-22 12-Oct-22 2
Mockup /Manufacturing of Material Hols - No B/O periods (was
310.P.ES.P174.B05 Airport System (Procurement TTLCS) - Tunnel Traffic Lane Control System - Delivery of C1)
C01_7 d/w - 10h/d - No HK 7 26-Sep-22 02-Oct-22 28-Sep-22 04-Oct-22 2
Material for PBB Comms Rm Hols - No B/O periods (was
310.P.ES.P174.B01 Airport System (Procurement TTLCS) - Tunnel Traffic Lane Control System - Delivery of C1)
C01_7 d/w - 10h/d - No HK 7 11-Oct-22 17-Oct-22 25-Oct-22 31-Oct-22 14
Material Hols - No B/O periods (was
CC#5 ----- Construction ----- C1) 446 85 20-Sep-22 19-Mar-24 20-Sep-22 08-Jun-24 64
Airfield (West & East Area) 359 32 04-Jan-23 19-Mar-24 21-Jan-23 08-Jun-24 64
Airport System - EVT C11_6 d/w - 10h/d - With HK Hols
264- No B/O 8periods (was
09-Mar-23
C3) 26-Jan-24 17-Mar-23 08-Feb-24 11
310.C.EX.W2440 EVT (EU) Eastern Approach Ramp - Airport System cabling & equipment Inst'n C11_6 d/w - 10h/d - With 75 2 09-Mar-23 10-Jun-23 17-Mar-23 19-Jun-23 7
(VDC,CCTV,SCADA,TMR,TTLCS,APABX) HK Hols - No B/O periods
310.C.EX.W2444 EVT (EA) Eastern Roundabout - Airport System cabling & equipment Inst'n (was
C11_6C3)
d/w - 10h/d - With 75 2 12-Jun-23 08-Sep-23 20-Jun-23 16-Sep-23 7
(VDC,CCTV,SCADA,TMR,TTLCS,APABX) HK Hols - No B/O periods
310.C.EX.W2448 EVT (ES) Eastern Switch Ramp - Airport System cabling & equipment Inst'n (was
C11_6C3)
d/w - 10h/d - With 75 2 09-Sep-23 08-Dec-23 18-Sep-23 16-Dec-23 7
(VDC,CCTV,SCADA,TMR,TTLCS,APABX) HK Hols - No B/O periods
310.C.EX.W2452 EVT (ET) Eastern Tunnel - Airport System cabling & equipment Inst'n (was
C11_6C3)
d/w - 10h/d - With 40 2 08-Dec-23 26-Jan-24 21-Dec-23 08-Feb-24 11
(VDC,CCTV,SCADA,TMR,TTLCS,APABX) HK Hols - No B/O periods
Airport System - WVT (was
C11_6C3)
d/w - 10h/d - With HK Hols
339- No B/O22
periods (was
04-Jan-23
C3) 24-Feb-24 21-Jan-23 26-Mar-24 26
310.C.EX.W2460 WVT (WA02) Western Roundabout - North-Bound - Airport System cabling & equipment C11_6 d/w - 10h/d - With 30 2 04-Jan-23 10-Feb-23 11-Feb-23 17-Mar-23 30
Inst'n (VDC,CCTV,SCADA,TMR,TTLCS,APABX) HK Hols - No B/O periods
310.C.EX.W2456 WVT (WR) Western Ramp - North-Bound - Airport System cabling & equipment Inst'n (was
C11_6C3)
d/w - 10h/d - With 45 2 04-Jan-23 28-Feb-23 21-Jan-23 17-Mar-23 15
(VDC,CCTV,SCADA,TMR,TTLCS,APABX) HK Hols - No B/O periods
310.C.EX.W2464 WVT (WU) Western Underpass - North-Bound - Airport System cabling & equipment Inst'n (was
C11_6C3)
d/w - 10h/d - With 45 2 24-Feb-23 21-Apr-23 03-Mar-23 28-Apr-23 6
(VDC,CCTV,SCADA,TMR,TTLCS,APABX) HK Hols - No B/O periods
310.C.EX.W2468 WVT (WA01) Western Roundabout - North-Bound - Airport System cabling & equipment (wasC11_6C3)
d/w - 10h/d - With 30 2 03-Apr-23 12-May-23 15-May-23 19-Jun-23 31
Inst'n (VDC,CCTV,SCADA,TMR,TTLCS,APABX) HK Hols - No B/O periods
310.C.EX.W2472 WVT (WUR) Western Underpass Ramp - North-Bound - Airport System cabling & eqpt (was
C11_6C3)
d/w - 10h/d - With 45 2 16-May-23 10-Jul-23 05-Jun-23 28-Jul-23 16
Inst'n (VDC,CCTV,SCADA,TMR,TTLCS,APABX) HK Hols - No B/O periods
310.C.EX.X708 WVT (WR) Western Ramp - South-Bound - Airport System cabling & equipment Inst'n (was
C11_6C3)
d/w - 10h/d - With 45 2 07-Jul-23 28-Aug-23 14-Jul-23 04-Sep-23 6
(VDC,CCTV,SCADA,TMR,TTLCS,APABX) HK Hols - No B/O periods
(was C3)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 83 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.EX.X712 WVT (WA02) Western Roundabout - South-Bound - Airport System cabling & equipment C11_6 d/w - 10h/d - With 30 2 02-Aug-23 05-Sep-23 19-Sep-23 26-Oct-23 41
Inst'n (VDC,CCTV,SCADA,TMR,TTLCS,APABX) HK Hols - No B/O periods
310.C.EX.X716 WVT (WU) Western Underpass - South-Bound - Airport System cabling & equipment (was
C11_6C3)
d/w - 10h/d - With 45 2 04-Oct-23 25-Nov-23 11-Oct-23 02-Dec-23 6
Inst'n (VDC,CCTV,SCADA,TMR,TTLCS,APABX) HK Hols - No B/O periods
310.C.EX.X720 WVT (WA01) Western Roundabout - South-Bound - Airport System cabling & equipment (was
C11_6C3)
d/w - 10h/d - With 30 2 11-Nov-23 15-Dec-23 15-Dec-23 22-Jan-24 29
Inst'n (VDC,CCTV,SCADA,TMR,TTLCS,APABX) HK Hols - No B/O periods
310.C.EX.W2476 WVT (WT) Western Vehicular Tunnel - Airport System cabling & equipment Inst'n (was
C11_6C3)
d/w - 10h/d - With 60 2 12-Dec-23 24-Feb-24 15-Jan-24 26-Mar-24 26
(VDC,CCTV,SCADA,TMR,TTLCS,APABX) HK Hols - No B/O periods
310.C.EX.X724 WVT (WUR) Western Underpass Ramp - South-Bound - Airport System cabling & eqpt (was
C11_6C3)
d/w - 10h/d - With 45 2 19-Dec-23 14-Feb-24 05-Jan-24 28-Feb-24 12
Inst'n (VDC,CCTV,SCADA,TMR,TTLCS,APABX) HK Hols - No B/O periods
Airport System - Airfield (West & East Area) - Testing & Commissioning (was C3) 43 2 27-Jan-24 19-Mar-24 04-May-24 08-Jun-24 64
310.T.EX.L500 EVT (T&C) - Airport System T&C C11_6 d/w - 10h/d - With 21 2 27-Jan-24 22-Feb-24 04-May-24 29-May-24 77
HK Hols - No B/O periods
310.T.EX.L504 WVT (T&C) - Airport System Test (was
C01_7C3)
d/w - 10h/d - No HK 24 25-Feb-24 19-Mar-24 16-May-24 08-Jun-24 81
Hols - No B/O periods (was
Airport System - Security Fence C1) 346 12 21-Sep-22 18-Nov-23 21-Sep-22 07-May-24 136
Stage 1 Installation Works C01_7 d/w - 10h/d - No HK Hols21
- No B/O periods
2 (was21-Sep-22
C1) 11-Oct-22 21-Sep-22 11-Oct-22 0
310.C.RC.C072 WSA - Interim Sec. Fence (normal days) - install IDSS C01_7 d/w - 10h/d - No HK 21 1 21-Sep-22 11-Oct-22 21-Sep-22 11-Oct-22 0
Hols - No B/O periods (was
310.C.RC.C076 ESA - Interim Sec. Fence (normal days) - install IDSS C1)
C01_7 d/w - 10h/d - No HK 21 1 21-Sep-22 11-Oct-22 21-Sep-22 11-Oct-22 0
Hols - No B/O periods (was
Stage 2 Installation Works C1)
C11_6 d/w - 10h/d - With HK Hols
29- No B/O 1periods (was
16-Oct-23
C3) 18-Nov-23 07-Nov-23 09-Dec-23 18
310.C.RC.C084 Interim Sec. Fence (Stage 2) - install Interim Sec. Fence, IDSS, CCTV C11_6 d/w - 10h/d - With 29 1 16-Oct-23 18-Nov-23 07-Nov-23 09-Dec-23 18
HK Hols - No B/O periods
Permanent Security Fence (was
C11_6C3)
d/w - 10h/d - With HK Hols
99- No B/O 9periods (was
24-Jun-23
C3) 20-Oct-23 05-Jan-24 07-May-24 160
310.C.R0.X160 3310/10,10A - Security Fence - install Security System C11_6 d/w - 10h/d - With 99 9 24-Jun-23 20-Oct-23 05-Jan-24 07-May-24 160
HK Hols - No B/O periods
Airport System - Ancillary Buildings (was C3) 330 41 20-Sep-22 30-Oct-23 20-Sep-22 30-May-24 172
Airport System - Security Gate House C11_6 d/w - 10h/d - With HK Hols
79- No B/O 4periods (was
15-May-23
C3) 17-Aug-23 26-Jul-23 28-Oct-23 59
310.C.WS.S233 Gatehouse B/Vehicle Search Bay, C&ED - (1st-Final Fix)-Airport C11_6 d/w - 10h/d - With 79 4 15-May-23 17-Aug-23 26-Jul-23 28-Oct-23 59
System-VDC,CCTV,ALWS,SCADA,TMR,ACS,WNET,APABX HK Hols - No B/O periods
Airport System - Maintenance Facilities Forecourt & Coach Staging A, & Bus Stop (was
C11_6C3)
d/w - 10h/d - With HK Hols
25- No B/O 1periods (was
26-Jul-23
C3) 23-Aug-23 15-Feb-24 14-Mar-24 167
310.C.D.WS.M130 WSA - MFF and Bus Stop (Airport System) - cabling & equipment Inst'n for CCTV C11_6 d/w - 10h/d - With 25 1 26-Jul-23 23-Aug-23 15-Feb-24 14-Mar-24 167
HK Hols - No B/O periods
Airport System - Communication Equipment Building D (was
C11_6C3)
d/w - 10h/d - With HK Hols
32- No B/O 2periods (was
09-Nov-22
C3) 15-Dec-22 15-Nov-22 21-Dec-22 5
310.C.TC.M332 WSA - Comm Eqpt Bldg D (Airport System) - cabling & equipment Inst'n for C11_6 d/w - 10h/d - With 32 2 09-Nov-22 15-Dec-22 15-Nov-22 21-Dec-22 5
VDC,CCTV,ALWS,SCADA,TMR,ACS,WNET,IDSS,APABX HK Hols - No B/O periods
Airport System - C&ED Operational Office & Kennel Area (was
C11_6C3)
d/w - 10h/d - With HK Hols
79- No B/O 4periods (was
07-Jul-23
C3) 09-Oct-23 08-Sep-23 12-Dec-23 54
310.C.ES.P636 C&ED Op. Office & Kennel Area - (1st Fix - Final Fix) - Airport System - cabling & C11_6 d/w - 10h/d - With 79 4 07-Jul-23 09-Oct-23 08-Sep-23 12-Dec-23 54
equipment Inst'n for VDC,APABX HK Hols - No B/O periods
Airport System - GSE Battery Charging B (was
C11_6C3)
d/w - 10h/d - With HK Hols
40- No B/O 4periods (was
31-Oct-22
C3) 15-Dec-22 24-Nov-22 11-Jan-23 21
310.C.TC.N410 GSE Battery Charging B (Airport System) - cabling & equipment Inst'n for C11_6 d/w - 10h/d - With 40 2 31-Oct-22 15-Dec-22 24-Nov-22 11-Jan-23 21
VDC,ALWS,SCADA,ACS,APABX HK Hols - No B/O periods
310.C.ES.P608 GSE Battery Charging B - 1st Fix - Final Fix) - Airport System - cabling & eqpt Inst'n (was
C11_6C3)
d/w - 10h/d - With 40 2 31-Oct-22 15-Dec-22 24-Nov-22 11-Jan-23 21
VDC,ALWS,SCADA,ACS,APABX HK Hols - No B/O periods
Airport System - Screening Facility (was
C11_6C3)
d/w - 10h/d - With HK Hols
60- No B/O 3periods (was
26-Nov-22
C3) 09-Feb-23 16-Dec-22 01-Mar-23 17
310.C.WS.R094 WSA - Screening Facility (Airport System) - cabling & equipment Inst'n for C11_6 d/w - 10h/d - With 60 3 26-Nov-22 09-Feb-23 16-Dec-22 01-Mar-23 17
VDC,CCTV,SCADA,TMR,ACS,WNET,APABX HK Hols - No B/O periods
Airport System - GSE Vehicle Wash Facility (was
C11_6C3)
d/w - 10h/d - With HK Hols
32- No B/O 2periods (was
30-Sep-22
C3) 08-Nov-22 08-Oct-22 14-Nov-22 5

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 84 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.TC.M408 GSE Wash Facility (Airport System) - cabling & equipment Inst'n for C11_6 d/w - 10h/d - With 32 2 30-Sep-22 08-Nov-22 08-Oct-22 14-Nov-22 5
VDC,SCADA,ACS,APABX HK Hols - No B/O periods
Airport System - AGL Vault C & D Annexes (was
C11_6C3)
d/w - 10h/d - With HK Hols
142- No B/O10
periods (was
20-Sep-22
C3) 11-Mar-23 20-Sep-22 18-Feb-23 -18
310.D.RC.D503 AGL Vault D Annex (Airport System) - cabling & equipment Inst'n for VDC, CCTV,C11_6 d/w - 10h/d - With 75 5 20-Sep-22 17-Dec-22 20-Sep-22 17-Dec-22 0
SCADA, TMRS, ACS, AWLS, APABX HK Hols - No B/O periods
310.C.RC.D128 AGL Vault C Annex (Airport System) - cabling & equipment Inst'n for VDC, SCADA, TMR, (was
C11_6C3)
d/w - 10h/d - With 75 5 09-Dec-22 11-Mar-23 18-Nov-22 18-Feb-23 -18
ACS, APABX HK Hols - No B/O periods
Airport System - Tunnel Plant Building A (was C3) 229 6 30-Dec-22 09-Oct-23 31-Dec-22 02-Mar-24 119
310.C.ES.P420 PBA (Comms Room 1st Fix - Final Fix) - Airport System C11_6 d/w - 10h/d - With 45 2 30-Dec-22 24-Feb-23 31-Dec-22 25-Feb-23 1
VDC,CCTV,SCADA,WNET,TMR,ACS,AANET,TTLCS,APABX HK Hols - No B/O periods
310.C.ES.P424 Achieved KD-3 (Stage 3) - Complete all works for CR305 w/in Plant Bldg A incl. all ABWF, (was
C01_7C3)
d/w - 10h/d - No HK 0 24-Feb-23 26-Feb-23 2
BS, and AS to final fix Hols - No B/O periods (was
310.C.ES.P392 PBA (1st Fix - Final Fix) - Airport System - cabling & eqpt Inst'n C1)
C11_6 d/w - 10h/d - With 79 4 07-Jul-23 09-Oct-23 27-Nov-23 02-Mar-24 119
VDC,CCTV,SCADA,WNET,TMR,ACS,AANET,TTLCS,APABX HK Hols - No B/O periods
Airport System - Tunnel Plant Building B (was
C11_6C3)
d/w - 10h/d - With HK Hols
21- No B/O 2periods (was
05-Oct-22
C3) 28-Oct-22 05-Oct-22 28-Oct-22 0
310.C.ES.P528 PBB (Comms Room 1st Fix - Final Fix) - Airport System cabling & eqpt Inst'n C11_6 d/w - 10h/d - With 21 1 05-Oct-22 28-Oct-22 05-Oct-22 28-Oct-22 0
VDC,CCTV,SCADA,TMR,ACS,WNET,TTLCS,APABX,SPMS HK Hols - No B/O periods
310.C.ES.P552 PBB (1st Fix - Final Fix) - Airport System - cabling & eqpt Inst'n (was
C11_6C3)
d/w - 10h/d - With 21 1 05-Oct-22 28-Oct-22 05-Oct-22 28-Oct-22 0
VDC,CCTV,SCADA,TMR,ACS,WNET,TTLCS,APABX,SPMS HK Hols - No B/O periods
Airport System - Tunnel Plant Building C (was
C11_6C3)
d/w - 10h/d - With HK Hols
35- No B/O 3periods (was
24-Oct-22
C3) 02-Dec-22 01-Nov-22 10-Dec-22 7
310.C.EX.P150 PBC (Ground Floor, AS) - VDC,CCTV,SCADA,TMR,ACS,WNET,AANET,TTLCS,APABX C11_6 d/w - 10h/d - With 21 1 24-Oct-22 16-Nov-22 01-Nov-22 24-Nov-22 7
HK Hols - No B/O periods
310.C.ES.P472 PBC (Comms Room 1st Fix - Final Fix) -Airport System cabling & eqpt Inst'n (was
C11_6C3)
d/w - 10h/d - With 21 1 07-Nov-22 30-Nov-22 16-Nov-22 09-Dec-22 8
VDC,CCTV,SCADA,TMR,ACS,WNET,AANET,TTLCS,APABX HK Hols - No B/O periods
310.C.EX.P158 PBC (1st Floor, AS) - VDC,CCTV,SCADA,TMR,ACS,WNET,AANET,TTLCS,APABX (was
C11_6C3)
d/w - 10h/d - With 21 1 09-Nov-22 02-Dec-22 17-Nov-22 10-Dec-22 7
HK Hols - No B/O periods
Airport System - Ancillary Building - Testing & Commissioning (was
C01_7C3)
d/w - 10h/d - No HK Hols367
- No B/O periods
0 (was29-Oct-22
C1) 30-Oct-23 29-Oct-22 30-May-24 213
310.C.ES.P776 PBB - Airport System T&C - VDC,CCTV,SCADA,TMR,ACS,WNET,TTLCS,APABX,SPMS C01_7 d/w - 10h/d - No HK 21 29-Oct-22 18-Nov-22 29-Oct-22 18-Nov-22 0
Hols - No B/O periods (was
310.C.ES.P760 GSE Wash Facility - Airport System T&C - VDC,SCADA,ACS,APABX C1)
C01_7 d/w - 10h/d - No HK 21 09-Nov-22 29-Nov-22 26-Dec-22 15-Jan-23 47
Hols - No B/O periods (was
310.C.ES.P804 PBC - Airport System T&C - C1)
C01_7 d/w - 10h/d - No HK 21 03-Dec-22 23-Dec-22 12-Dec-22 01-Jan-23 9
VDC,CCTV,SCADA,TMR,ACS,WNET,AANET,TTLCS,APABX Hols - No B/O periods (was
310.C.ES.P748 WSA - Comm Eqpt Bldg D - Airport System T&C - C1)
C01_7 d/w - 10h/d - No HK 21 16-Dec-22 05-Jan-23 16-Jan-23 05-Feb-23 31
VDC,CCTV,ALWS,SCADA,TMR,ACS,WNET,IDSS,APABX Hols - No B/O periods (was
310.C.ES.P752 GSE Battery Charging B - Airport System T&C - VDC,ALWS,SCADA,ACS,APABX C1)
C01_7 d/w - 10h/d - No HK 21 16-Dec-22 05-Jan-23 15-Jul-23 04-Aug-23 211
Hols - No B/O periods (was
310.C.ES.P764 AGL Vault D Annex - Airport System T&C - VDC, CCTV, SCADA, TMRS, ACS, AWLS, C1)
C01_7 d/w - 10h/d - No HK 21 18-Dec-22 07-Jan-23 19-Oct-23 08-Nov-23 305
APABX Hols - No B/O periods (was
310.C.ES.P756 WSA - Screening Facility - Airport System T&C - C1)
C01_7 d/w - 10h/d - No HK 21 10-Feb-23 02-Mar-23 27-Apr-23 17-May-23 76
VDC,CCTV,SCADA,TMR,ACS,WNET,APABX Hols - No B/O periods (was
310.C.ES.P768 AGL Vault C Annex - Airport System T&C - VDC, SCADA, TMR, ACS, APABX C1)
C01_7 d/w - 10h/d - No HK 21 12-Mar-23 01-Apr-23 23-Nov-23 13-Dec-23 256
Hols - No B/O periods (was
310.C.ES.P740 WSA - Gatehouse B/Vehicle Search Bay, C&ED - Airport System C1)
C01_7 d/w - 10h/d - No HK 21 18-Aug-23 07-Sep-23 28-Nov-23 18-Dec-23 102
T&C-VDC,CCTV,ALWS,SCADA,TMR,ACS,WNET,APABX Hols - No B/O periods (was
310.C.ES.P744 WSA - MFF and Bus Stop - Airport System T&C - CCTV C1)
C01_7 d/w - 10h/d - No HK 21 24-Aug-23 13-Sep-23 10-May-24 30-May-24 260
Hols - No B/O periods (was
310.C.ES.P772 PBA - Airport System T&C - C1)
C01_7 d/w - 10h/d - No HK 21 10-Oct-23 30-Oct-23 04-Mar-24 24-Mar-24 146
VDC,CCTV,SCADA,WNET,TMR,ACS,AANET,TTLCS,APABX Hols - No B/O periods (was
310.C.ES.P796 C&ED Op. Office & Kennel Area Annex - Airport System T&C - VDC,APABX C1)
C01_7 d/w - 10h/d - No HK 21 10-Oct-23 30-Oct-23 05-Jan-24 25-Jan-24 87
Hols - No B/O periods (was
C1)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 85 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
Cost Centre #06 - East Vehicular Tunnels & Plant Building A & C 930 307 07-Jun-21 A 22-Jul-24 07-Mar-22 28-Jul-24 5
CC#06 ----- Design & Other Submission ----- C01_7 d/w - 10h/d - No HK Hols553
- No B/O periods
0 (was
27-Jun-21
C1) A 31-Dec-22 28-Mar-22 25-Apr-23 115
CC#06 - EVT - Statutory Submission and Consent Application C01_7 d/w - 10h/d - No HK Hols553
- No B/O periods
0 (was
27-Jun-21
C1) A 31-Dec-22 29-Mar-22 25-Apr-23 115
CC#06 - EVT - Ground Investigation Plan for ELS Design C01_7 d/w - 10h/d - No HK Hols391
- No B/O periods
0 (was
09-Jul-21
C1) A 01-Sep-22 19-Apr-22 01-Sep-22 1
310.D.EX.H010 EVT - SI Plan for ELS Design - prepare and submit to PM C01_7 d/w - 10h/d - No HK 21 09-Jul-21 A 29-Jul-21 A 19-Apr-22 19-Apr-22
Hols - No B/O periods (was
310.D.EX.H034 EVT - SI Plan for ELS Design - prepare and submit Form BA10 to notify work C1)
C01_7 d/w - 10h/d - No HK 7 14-Aug-21 A 20-Aug-21 A 19-Apr-22 19-Apr-22
commencement (Zone 6 & 7) Hols - No B/O periods (was
310.D.EX.H517 EVT - SI Plan for ELS Design - prepare and submit Form BA10 to notify work C1)
C01_7 d/w - 10h/d - No HK 7 25-Aug-22 01-Sep-22 26-Aug-22 01-Sep-22 1
commencement (Other Zones) Hols - No B/O periods (was
CC#06 - EVT - Consent Application for DJM Works C1)
C01_7 d/w - 10h/d - No HK Hols21
- No B/O periods
0 (was
26-Aug-21
C1) A 15-Sep-21 A 08-Nov-22 08-Nov-22
310.D.EX.H325 EVT - DJM Works - prepare and submit Form BA8 C01_7 d/w - 10h/d - No HK 7 26-Aug-21 A 01-Sep-21 A 08-Nov-22 08-Nov-22
Hols - No B/O periods (was
310.D.EX.H329 EVT - DJM Works - BD review and grant Consent C1)
C01_7 d/w - 10h/d - No HK 7 02-Sep-21 A 08-Sep-21 A 08-Nov-22 08-Nov-22
Hols - No B/O periods (was
310.D.EX.H333 EVT - DJM Works - prepare and submit form BA10 for Notification of Work C1)
C01_7 d/w - 10h/d - No HK 7 09-Sep-21 A 15-Sep-21 A 08-Nov-22 08-Nov-22
Commencement Hols - No B/O periods (was
CC#06 - EVT - ELS Design - Vertical Element C1)
C01_7 d/w - 10h/d - No HK Hols474
- No B/O periods
0 (was
27-Jun-21
C1) A 13-Oct-22 29-Mar-22 07-Jan-23 86
ELS Design (Vertical Elements) - EVT Ch1027 to 1275 (Zones 6 &7) Pkg.1 C01_7 d/w - 10h/d - No HK Hols277
- No B/O periods
0 (was
27-Jun-21
C1) A 16-Apr-22 29-Mar-22 18-Apr-22 2
310.D.EX.H357 EVT - ELS design (Vertical Elements) - prepare and submit to ICE for reviewing C01_7 d/w - 10h/d - No HK 74 27-Jun-21 A 08-Sep-21 A 29-Mar-22 29-Mar-22
Hols - No B/O periods (was
310.D.EX.H361 EVT - ELS design (Vertical Elements) - ICE issue check certificate C1)
C01_7 d/w - 10h/d - No HK 1 09-Sep-21 A 09-Sep-21 A 29-Mar-22 29-Mar-22
Hols - No B/O periods (was
310.D.EX.H365 EVT - ELS design (Vertical Elements) - PM, AP, RSE reviewing 1st Round C1)
C01_7 d/w - 10h/d - No HK 28 10-Sep-21 A 08-Nov-21 A 29-Mar-22 29-Mar-22
Hols - No B/O periods (was
310.D.EX.H393 EVT - ELS design (Vertical Elements) - ICC, M&VC review design and issue check C1)
C01_7 d/w - 10h/d - No HK 21 09-Nov-21 A 07-Jan-22 A 29-Mar-22 29-Mar-22
certificates Hols - No B/O periods (was
310.D.EX.H373 EVT - ELS design (Vertical Elements) - BD review and comment C1)
C01_7 d/w - 10h/d - No HK 60 07-Jan-22 A 16-Apr-22 29-Mar-22 18-Apr-22 2
Hols - No B/O periods (was
ELS Design (Vertical Elements) - EVT Ch532 to 562 (Zone 1) Pkg.3 C1)
C01_7 d/w - 10h/d - No HK Hols214
- No B/O periods
0 (was
04-Dec-21
C1) A 31-Aug-22 03-Aug-22 07-Jan-23 129
310.D.EX.H437 EVT - ELS design (Vertical Elements) - prepare and submit to ICE for reviewing C01_7 d/w - 10h/d - No HK 74 04-Dec-21 A 18-Mar-22 A 03-Aug-22 03-Aug-22
Hols - No B/O periods (was
310.D.EX.H441 EVT - ELS design (Vertical Elements) - ICE issue check certificate C1)
C01_7 d/w - 10h/d - No HK 1 19-Mar-22 A 19-Mar-22 A 03-Aug-22 03-Aug-22
Hols - No B/O periods (was
310.D.EX.H445 EVT - ELS design (Vertical Elements) - PM, AP, RSE reviewing 1st Round C1)
C01_7 d/w - 10h/d - No HK 28 20-Mar-22 A 16-Apr-22 03-Aug-22 23-Aug-22 129
Hols - No B/O periods (was
310.D.EX.H473 EVT - ELS design (Vertical Elements) - ICC, M&VC review design and issue check C1)
C01_7 d/w - 10h/d - No HK 21 17-Apr-22 07-May-22 24-Aug-22 13-Sep-22 129
certificates Hols - No B/O periods (was
310.D.EX.H465 EVT - ELS design (Vertical Elements) - prepare and resubmit C1)
C01_7 d/w - 10h/d - No HK 7 08-May-22 14-May-22 14-Sep-22 20-Sep-22 129
Hols - No B/O periods (was
310.D.EX.H469 EVT - ELS design (Vertical Elements) - PM, AP, RSE reviewing 2nd Round C1)
C01_7 d/w - 10h/d - No HK 28 15-May-22 11-Jun-22 21-Sep-22 18-Oct-22 129
Hols - No B/O periods (was
310.D.EX.H449 EVT - ELS design (Vertical Elements) - ICC, M&VC review design and issue check C1)
C01_7 d/w - 10h/d - No HK 21 12-Jun-22 02-Jul-22 19-Oct-22 08-Nov-22 129
certificates 2nd Round Hols - No B/O periods (was
310.D.EX.H453 EVT - ELS design (Vertical Elements) - BD review and comment C1)
C01_7 d/w - 10h/d - No HK 60 03-Jul-22 31-Aug-22 09-Nov-22 07-Jan-23 129
Hols - No B/O periods (was
ELS Design (Vertical Elements) - EVT Ch562 to 920 (Zones 2 &3) Pkg.4 C1)
C01_7 d/w - 10h/d - No HK Hols257
- No B/O periods
0 (was
04-Dec-21
C1) A 13-Oct-22 28-Apr-22 16-Oct-22 3
310.D.EX.H477 EVT - ELS design (Vertical Elements) - prepare and submit to ICE for reviewing C01_7 d/w - 10h/d - No HK 74 04-Dec-21 A 18-Mar-22 A 28-Apr-22 28-Apr-22
Hols - No B/O periods (was
310.D.EX.H481 EVT - ELS design (Vertical Elements) - ICE issue check certificate C1)
C01_7 d/w - 10h/d - No HK 1 19-Mar-22 A 19-Mar-22 A 28-Apr-22 28-Apr-22
Hols - No B/O periods (was
C1)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 86 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.EX.H485 EVT - ELS design (Vertical Elements) - PM, AP, RSE reviewing 1st Round C01_7 d/w - 10h/d - No HK 28 20-Mar-22 A 16-Apr-22 28-Apr-22 18-May-22 32
Hols - No B/O periods (was
310.D.EX.H513 EVT - ELS design (Vertical Elements) - ICC, M&VC review design and issue check C1)
C01_7 d/w - 10h/d - No HK 21 17-Apr-22 07-May-22 19-May-22 08-Jun-22 32
certificates Hols - No B/O periods (was
310.D.EX.H505 EVT - ELS design (Vertical Elements) - prepare and resubmit C1)
C01_7 d/w - 10h/d - No HK 7 08-May-22 14-May-22 09-Jun-22 15-Jun-22 32
Hols - No B/O periods (was
310.D.EX.H509 EVT - ELS design (Vertical Elements) - PM, AP, RSE reviewing 2nd Round C1)
C01_7 d/w - 10h/d - No HK 28 15-May-22 11-Jun-22 16-Jun-22 13-Jul-22 32
Hols - No B/O periods (was
310.D.EX.H489 EVT - ELS design (Vertical Elements) - ICC, M&VC review design and issue check C1)
C01_7 d/w - 10h/d - No HK 21 12-Jun-22 02-Jul-22 14-Jul-22 03-Aug-22 32
certificates 2nd Round Hols - No B/O periods (was
310.D.EX.H493 EVT - ELS design (Vertical Elements) - BD review and comment C1)
C01_7 d/w - 10h/d - No HK 60 03-Jul-22 31-Aug-22 04-Aug-22 02-Oct-22 32
Hols - No B/O periods (was
310.D.EX.H497 EVT - ELS design (Vertical Elements) - prepare and submit Form BA8 and grant consent C1)
C01_7 d/w - 10h/d - No HK 7 30-Sep-22 06-Oct-22 03-Oct-22 09-Oct-22 3
Hols - No B/O periods (was
310.D.EX.H501 EVT - ELS design (Vertical Elements) - prepare and submit Form BA10 to notify work C1)
C01_7 d/w - 10h/d - No HK 7 07-Oct-22 13-Oct-22 10-Oct-22 16-Oct-22 3
commencement Hols - No B/O periods (was
ELS Design (Vertical Elements) - EVT Ch920 to 1027 (Zones 4 &5) Pkg.2 C1)
C01_7 d/w - 10h/d - No HK Hols214
- No B/O periods
0 (was
04-Dec-21
C1) A 31-Aug-22 28-Apr-22 28-Oct-22 58
310.D.EX.H397 EVT - ELS design (Vertical Elements) - prepare and submit to ICE for reviewing C01_7 d/w - 10h/d - No HK 74 04-Dec-21 A 18-Mar-22 A 28-Apr-22 28-Apr-22
Hols - No B/O periods (was
310.D.EX.H401 EVT - ELS design (Vertical Elements) - ICE issue check certificate C1)
C01_7 d/w - 10h/d - No HK 1 19-Mar-22 A 19-Mar-22 A 24-May-22 24-May-22
Hols - No B/O periods (was
310.D.EX.H405 EVT - ELS design (Vertical Elements) - PM, AP, RSE reviewing 1st Round C1)
C01_7 d/w - 10h/d - No HK 28 20-Mar-22 A 16-Apr-22 24-May-22 13-Jun-22 58
Hols - No B/O periods (was
310.D.EX.H433 EVT - ELS design (Vertical Elements) - ICC, M&VC review design and issue check C1)
C01_7 d/w - 10h/d - No HK 21 17-Apr-22 07-May-22 14-Jun-22 04-Jul-22 58
certificates Hols - No B/O periods (was
310.D.EX.H425 EVT - ELS design (Vertical Elements) - prepare and resubmit C1)
C01_7 d/w - 10h/d - No HK 7 08-May-22 14-May-22 05-Jul-22 11-Jul-22 58
Hols - No B/O periods (was
310.D.EX.H429 EVT - ELS design (Vertical Elements) - PM, AP, RSE reviewing 2nd Round C1)
C01_7 d/w - 10h/d - No HK 28 15-May-22 11-Jun-22 12-Jul-22 08-Aug-22 58
Hols - No B/O periods (was
310.D.EX.H409 EVT - ELS design (Vertical Elements) - ICC, M&VC review design and issue check C1)
C01_7 d/w - 10h/d - No HK 21 12-Jun-22 02-Jul-22 09-Aug-22 29-Aug-22 58
certificates 2nd Round Hols - No B/O periods (was
310.D.EX.H413 EVT - ELS design (Vertical Elements) - BD review and comment C1)
C01_7 d/w - 10h/d - No HK 60 03-Jul-22 31-Aug-22 30-Aug-22 28-Oct-22 58
Hols - No B/O periods (was
CC#06 - EVT - ELS Design - Excavation C1)
C01_7 d/w - 10h/d - No HK Hols478
- No B/O periods
0 (was
01-Aug-21
C1) A 21-Nov-22 25-May-22 25-Apr-23 155
ELS Design (Excavation) - EVT Ch1027 to 1275 (Zones 6 &7) Pkg.1 C01_7 d/w - 10h/d - No HK Hols372
- No B/O periods
0 (was
01-Aug-21
C1) A 21-May-22 05-Jul-22 29-Aug-22 100
310.D.EX.H646 EVT - ELS design (Excavation) - prepare and submit to ICE for reviewing C01_7 d/w - 10h/d - No HK 74 01-Aug-21 A 06-Dec-21 A 05-Jul-22 05-Jul-22
Hols - No B/O periods (was
310.D.EX.H651 EVT - ELS design (Excavation) - ICE issue check certificate C1)
C01_7 d/w - 10h/d - No HK 1 07-Dec-21 A 07-Dec-21 A 05-Jul-22 05-Jul-22
Hols - No B/O periods (was
310.D.EX.H656 EVT - ELS design (Excavation) - PM, AP, RSE reviewing 1st Round C1)
C01_7 d/w - 10h/d - No HK 28 08-Dec-21 A 26-Jan-22 A 05-Jul-22 05-Jul-22
Hols - No B/O periods (was
310.D.EX.H691 EVT - ELS design (Excavation) - ICC, M&VC review design and issue check certificates C1)
C01_7 d/w - 10h/d - No HK 21 27-Jan-22 A 10-Mar-22 A 05-Jul-22 05-Jul-22
Hols - No B/O periods (was
310.D.EX.H666 EVT - ELS design (Excavation) - BD review and comment C1)
C01_7 d/w - 10h/d - No HK 60 23-Mar-22 A 21-May-22 05-Jul-22 29-Aug-22 100
Hols - No B/O periods (was
ELS Design (Excavation) - EVT Ch532 to 562 (Zone 1) Pkg.3 C1)
C01_7 d/w - 10h/d - No HK Hols240
- No B/O periods
0 (was27-Mar-22
C1) 21-Nov-22 29-Aug-22 25-Apr-23 155
310.D.EX.H746 EVT - ELS design (Excavation) - prepare and submit to ICE for reviewing C01_7 d/w - 10h/d - No HK 74 27-Mar-22 08-Jun-22 29-Aug-22 10-Nov-22 155
Hols - No B/O periods (was
310.D.EX.H751 EVT - ELS design (Excavation) - ICE issue check certificate C1)
C01_7 d/w - 10h/d - No HK 1 09-Jun-22 09-Jun-22 11-Nov-22 11-Nov-22 155
Hols - No B/O periods (was
C1)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 87 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.EX.H756 EVT - ELS design (Excavation) - PM, AP, RSE reviewing 1st Round C01_7 d/w - 10h/d - No HK 28 10-Jun-22 07-Jul-22 12-Nov-22 09-Dec-22 155
Hols - No B/O periods (was
310.D.EX.H791 EVT - ELS design (Excavation) - ICC, M&VC review design and issue check certificates C1)
C01_7 d/w - 10h/d - No HK 21 08-Jul-22 28-Jul-22 10-Dec-22 30-Dec-22 155
Hols - No B/O periods (was
310.D.EX.H781 EVT - ELS design (Excavation) - prepare and resubmit C1)
C01_7 d/w - 10h/d - No HK 7 29-Jul-22 04-Aug-22 31-Dec-22 06-Jan-23 155
Hols - No B/O periods (was
310.D.EX.H786 EVT - ELS design (Excavation) - PM, AP, RSE reviewing 2nd Round C1)
C01_7 d/w - 10h/d - No HK 28 05-Aug-22 01-Sep-22 07-Jan-23 03-Feb-23 155
Hols - No B/O periods (was
310.D.EX.H761 EVT - ELS design (Excavation) - ICC, M&VC review design and issue check certificates C1)
C01_7 d/w - 10h/d - No HK 21 02-Sep-22 22-Sep-22 04-Feb-23 24-Feb-23 155
2nd Round Hols - No B/O periods (was
310.D.EX.H766 EVT - ELS design (Excavation) - BD review and comment C1)
C01_7 d/w - 10h/d - No HK 60 23-Sep-22 21-Nov-22 25-Feb-23 25-Apr-23 155
Hols - No B/O periods (was
ELS Design (Excavation) - EVT Ch562 to 920 (Zones 2 &3) Pkg.4 C1)
C01_7 d/w - 10h/d - No HK Hols240
- No B/O periods
0 (was27-Mar-22
C1) 21-Nov-22 09-Jun-22 03-Feb-23 74
310.D.EX.H795.B01 EVT - ELS design (Excavation) - prepare and submit to ICE for reviewing C01_7 d/w - 10h/d - No HK 74 27-Mar-22 08-Jun-22 09-Jun-22 21-Aug-22 74
Hols - No B/O periods (was
310.D.EX.H799.B01 EVT - ELS design (Excavation) - ICE issue check certificate C1)
C01_7 d/w - 10h/d - No HK 1 09-Jun-22 09-Jun-22 22-Aug-22 22-Aug-22 74
Hols - No B/O periods (was
310.D.EX.H803.B01 EVT - ELS design (Excavation) - PM, AP, RSE reviewing 1st Round C1)
C01_7 d/w - 10h/d - No HK 28 10-Jun-22 07-Jul-22 23-Aug-22 19-Sep-22 74
Hols - No B/O periods (was
310.D.EX.H807.B01 EVT - ELS design (Excavation) - ICC, M&VC review design and issue check certificates C1)
C01_7 d/w - 10h/d - No HK 21 08-Jul-22 28-Jul-22 20-Sep-22 10-Oct-22 74
Hols - No B/O periods (was
310.D.EX.H811.B01 EVT - ELS design (Excavation) - prepare and resubmit C1)
C01_7 d/w - 10h/d - No HK 7 29-Jul-22 04-Aug-22 11-Oct-22 17-Oct-22 74
Hols - No B/O periods (was
310.D.EX.H815.B01 EVT - ELS design (Excavation) - PM, AP, RSE reviewing 2nd Round C1)
C01_7 d/w - 10h/d - No HK 28 05-Aug-22 01-Sep-22 18-Oct-22 14-Nov-22 74
Hols - No B/O periods (was
310.D.EX.H819.B01 EVT - ELS design (Excavation) - ICC, M&VC review design and issue check certificates C1)
C01_7 d/w - 10h/d - No HK 21 02-Sep-22 22-Sep-22 15-Nov-22 05-Dec-22 74
2nd Round Hols - No B/O periods (was
310.D.EX.H823.B01 EVT - ELS design (Excavation) - BD review and comment C1)
C01_7 d/w - 10h/d - No HK 60 23-Sep-22 21-Nov-22 06-Dec-22 03-Feb-23 74
Hols - No B/O periods (was
ELS Design (Excavation) - EVT Ch920 to 1027 (Zones 4 &5) Pkg.2 C1)
C01_7 d/w - 10h/d - No HK Hols240
- No B/O periods
0 (was27-Mar-22
C1) 21-Nov-22 25-May-22 19-Jan-23 59
310.D.EX.H696 EVT - ELS design (Excavation) - prepare and submit to ICE for reviewing C01_7 d/w - 10h/d - No HK 74 27-Mar-22 08-Jun-22 25-May-22 06-Aug-22 59
Hols - No B/O periods (was
310.D.EX.H701 EVT - ELS design (Excavation) - ICE issue check certificate C1)
C01_7 d/w - 10h/d - No HK 1 09-Jun-22 09-Jun-22 07-Aug-22 07-Aug-22 59
Hols - No B/O periods (was
310.D.EX.H706 EVT - ELS design (Excavation) - PM, AP, RSE reviewing 1st Round C1)
C01_7 d/w - 10h/d - No HK 28 10-Jun-22 07-Jul-22 08-Aug-22 04-Sep-22 59
Hols - No B/O periods (was
310.D.EX.H741 EVT - ELS design (Excavation) - ICC, M&VC review design and issue check certificates C1)
C01_7 d/w - 10h/d - No HK 21 08-Jul-22 28-Jul-22 05-Sep-22 25-Sep-22 59
Hols - No B/O periods (was
310.D.EX.H731 EVT - ELS design (Excavation) - prepare and resubmit C1)
C01_7 d/w - 10h/d - No HK 7 29-Jul-22 04-Aug-22 26-Sep-22 02-Oct-22 59
Hols - No B/O periods (was
310.D.EX.H736 EVT - ELS design (Excavation) - PM, AP, RSE reviewing 2nd Round C1)
C01_7 d/w - 10h/d - No HK 28 05-Aug-22 01-Sep-22 03-Oct-22 30-Oct-22 59
Hols - No B/O periods (was
310.D.EX.H711 EVT - ELS design (Excavation) - ICC, M&VC review design and issue check certificates C1)
C01_7 d/w - 10h/d - No HK 21 02-Sep-22 22-Sep-22 31-Oct-22 20-Nov-22 59
2nd Round Hols - No B/O periods (was
310.D.EX.H716 EVT - ELS design (Excavation) - BD review and comment C1)
C01_7 d/w - 10h/d - No HK 60 23-Sep-22 21-Nov-22 21-Nov-22 19-Jan-23 59
Hols - No B/O periods (was
CC#06 - EVT/WVT - Temporary Utilities Support C1)
C01_7 d/w - 10h/d - No HK Hols212
- No B/O periods
0 (was27-Mar-22
C1) 24-Oct-22 14-Apr-22 11-Nov-22 18
310.D.EX.H180 Temporary UU Support design - prepare and submit to ICE for reviewing C01_7 d/w - 10h/d - No HK 30 27-Mar-22 25-Apr-22 14-Apr-22 13-May-22 18
Hols - No B/O periods (was
310.D.EX.H184 Temporary UU Support design - ICE issue check certificate C1)
C01_7 d/w - 10h/d - No HK 3 26-Apr-22 28-Apr-22 14-May-22 16-May-22 18
Hols - No B/O periods (was
C1)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 88 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.EX.H188 Temporary UU Support design - PM, AP, RSE reviewing C01_7 d/w - 10h/d - No HK 28 29-Apr-22 26-May-22 17-May-22 13-Jun-22 18
Hols - No B/O periods (was
310.D.EX.H192 Temporary UU Support design - ICC, M&VC review design and issue check certificates C1)
C01_7 d/w - 10h/d - No HK 21 27-May-22 16-Jun-22 14-Jun-22 04-Jul-22 18
Hols - No B/O periods (was
310.D.EX.H196 Temporary UU Support design - address comments & resubmit 2nd Round C1)
C01_7 d/w - 10h/d - No HK 7 17-Jun-22 23-Jun-22 05-Jul-22 11-Jul-22 18
Hols - No B/O periods (was
310.D.EX.H200 Temporary UU Support design - PM, AP, RSE reviewing 2nd Round C1)
C01_7 d/w - 10h/d - No HK 28 24-Jun-22 21-Jul-22 12-Jul-22 08-Aug-22 18
Hols - No B/O periods (was
310.D.EX.H202 Temporary UU Support design - ICC, M&VC review design and issue check certificates C1)
C01_7 d/w - 10h/d - No HK 21 22-Jul-22 11-Aug-22 09-Aug-22 29-Aug-22 18
2nd Round Hols - No B/O periods (was
310.D.EX.H204 Temporary UU Support design - BD review and approve C1)
C01_7 d/w - 10h/d - No HK 60 12-Aug-22 10-Oct-22 30-Aug-22 28-Oct-22 18
Hols - No B/O periods (was
310.D.EX.H208 Temporary UU Support design - prepare and submit Form BA8 and grant consent C1)
C01_7 d/w - 10h/d - No HK 7 11-Oct-22 17-Oct-22 29-Oct-22 04-Nov-22 18
Hols - No B/O periods (was
310.D.EX.H212 Temporary UU Support design - prepare and submit Form BA10 to notify work C1)
C01_7 d/w - 10h/d - No HK 7 18-Oct-22 24-Oct-22 05-Nov-22 11-Nov-22 18
commencement Hols - No B/O periods (was
CC#06 - EVT - Testing and Commissioning Plan for EVT C1)
C01_7 d/w - 10h/d - No HK Hols58
- No B/O periods
0 (was04-Nov-22
C1) 31-Dec-22 04-Nov-22 05-Mar-23 64
310.D.EX.H124 EVT no.27 - Testing and Commissioning Plan for EVT - Prepare and submit to PM C01_7 d/w - 10h/d - No HK 30 04-Nov-22 03-Dec-22 04-Nov-22 03-Dec-22 0
Hols - No B/O periods (was
310.D.EX.H128 EVT no.27 - Testing and Commissioning Plan for EVT - PM review and accept C1)
C01_7 d/w - 10h/d - No HK 28 04-Dec-22 31-Dec-22 06-Feb-23 05-Mar-23 64
Hols - No B/O periods (was
CC#06 - EVT - MEP Submission C1)
C01_7 d/w - 10h/d - No HK Hols113
- No B/O periods
0 (was28-Apr-22
C1) 18-Aug-22 20-Oct-22 09-Feb-23 175
EVT - MEP - Drawing Submission C01_7 d/w - 10h/d - No HK Hols113
- No B/O periods
0 (was28-Apr-22
C1) 18-Aug-22 20-Oct-22 09-Feb-23 175
310.D.WS.L664 EVT - MEP - Drawing Submission - prepare document C01_7 d/w - 10h/d - No HK 50 28-Apr-22 16-Jun-22 20-Oct-22 08-Dec-22 175
Hols - No B/O periods (was
310.D.WS.L665 EVT - MEP - Drawing Submission - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 50 19-May-22 07-Jul-22 10-Nov-22 29-Dec-22 175
Hols - No B/O periods (was
310.D.WS.L666 EVT - MEP - Drawing Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 50 09-Jun-22 28-Jul-22 01-Dec-22 19-Jan-23 175
Hols - No B/O periods (was
310.D.WS.L668 EVT - MEP - Drawing Submission - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 50 30-Jun-22 18-Aug-22 22-Dec-22 09-Feb-23 175
Hols - No B/O periods (was
CC#06 - EVT - ABWF Submission C1)
C01_7 d/w - 10h/d - No HK Hols84
- No B/O periods
0 (was26-Apr-22
C1) 18-Jul-22 04-May-22 26-Jul-22 8
EVT - ABWF - Drawing Submission C01_7 d/w - 10h/d - No HK Hols84
- No B/O periods
0 (was26-Apr-22
C1) 18-Jul-22 04-May-22 26-Jul-22 8
310.D.WS.L1400 EVT - ABWF - prepare document C01_7 d/w - 10h/d - No HK 14 26-Apr-22 09-May-22 04-May-22 17-May-22 8
Hols - No B/O periods (was
310.D.WS.L1668 EVT - ABWF - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 28 10-May-22 06-Jun-22 18-May-22 14-Jun-22 8
Hols - No B/O periods (was
310.D.WS.L1664 EVT - ABWF - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 14 07-Jun-22 20-Jun-22 15-Jun-22 28-Jun-22 8
Hols - No B/O periods (was
310.D.WS.L1404 EVT - ABWF - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 28 21-Jun-22 18-Jul-22 29-Jun-22 26-Jul-22 8
Hols - No B/O periods (was
EVT - ABWF - Material Submission C1)
C01_7 d/w - 10h/d - No HK Hols84
- No B/O periods
0 (was26-Apr-22
C1) 18-Jul-22 04-May-22 26-Jul-22 8
310.D.WS.L1416 EVT - ABWF - Material Submission - prepare document C01_7 d/w - 10h/d - No HK 14 26-Apr-22 09-May-22 04-May-22 17-May-22 8
Hols - No B/O periods (was
310.D.WS.L1676 EVT - ABWF - Material Submission - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 28 10-May-22 06-Jun-22 18-May-22 14-Jun-22 8
Hols - No B/O periods (was
310.D.WS.L1672 EVT - ABWF - Material Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 14 07-Jun-22 20-Jun-22 15-Jun-22 28-Jun-22 8
Hols - No B/O periods (was
310.D.WS.L1420 EVT - ABWF - Material Submission - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 28 21-Jun-22 18-Jul-22 29-Jun-22 26-Jul-22 8
Hols - No B/O periods (was
CC#06 - PBA - MEP Submission C1)
C01_7 d/w - 10h/d - No HK Hols174
- No B/O periods
0 (was02-Jun-22
C1) 22-Nov-22 10-Jul-22 30-Dec-22 38

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 89 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
PBA - MEP - Drawing Submission C01_7 d/w - 10h/d - No HK Hols174
- No B/O periods
0 (was02-Jun-22
C1) 22-Nov-22 10-Jul-22 30-Dec-22 38
310.D.WS.L688 PBA - MEP - Drawing Submission - prepare document C01_7 d/w - 10h/d - No HK 90 02-Jun-22 30-Aug-22 10-Jul-22 07-Oct-22 38
Hols - No B/O periods (was
310.D.WS.L689 PBA - MEP - Drawing Submission - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 90 30-Jun-22 27-Sep-22 07-Aug-22 04-Nov-22 38
Hols - No B/O periods (was
310.D.WS.L691 PBA - MEP - Drawing Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 90 28-Jul-22 25-Oct-22 04-Sep-22 02-Dec-22 38
Hols - No B/O periods (was
310.D.WS.L692 PBA - MEP - Drawing Submission - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 90 25-Aug-22 22-Nov-22 02-Oct-22 30-Dec-22 38
Hols - No B/O periods (was
CC#06 - PBA - ABWF Submission C1)
C01_7 d/w - 10h/d - No HK Hols119
- No B/O periods
0 (was26-Apr-22
C1) 22-Aug-22 28-Apr-22 24-Aug-22 2
PBA - ABWF - Drawing Submission C01_7 d/w - 10h/d - No HK Hols91
- No B/O periods
0 (was26-Apr-22
C1) 25-Jul-22 28-Apr-22 03-Aug-22 9
310.D.WS.L1424 PBA - ABWF - prepare document C01_7 d/w - 10h/d - No HK 28 26-Apr-22 23-May-22 28-Apr-22 25-May-22 2
Hols - No B/O periods (was
310.D.WS.L1684 PBA - ABWF - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 28 24-May-22 20-Jun-22 02-Jun-22 29-Jun-22 9
Hols - No B/O periods (was
310.D.WS.L1680 PBA - ABWF - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 14 21-Jun-22 04-Jul-22 30-Jun-22 13-Jul-22 9
Hols - No B/O periods (was
310.D.WS.L1428 PBA - ABWF - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 21 05-Jul-22 25-Jul-22 14-Jul-22 03-Aug-22 9
Hols - No B/O periods (was
PBA - ABWF - Material Submission C1)
C01_7 d/w - 10h/d - No HK Hols91
- No B/O periods
0 (was24-May-22
C1) 22-Aug-22 26-May-22 24-Aug-22 2
310.D.WS.L1440 PBA - ABWF - Material Submission - prepare document C01_7 d/w - 10h/d - No HK 28 24-May-22 20-Jun-22 26-May-22 22-Jun-22 2
Hols - No B/O periods (was
310.D.WS.L1692 PBA - ABWF - Material Submission - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 28 21-Jun-22 18-Jul-22 23-Jun-22 20-Jul-22 2
Hols - No B/O periods (was
310.D.WS.L1688 PBA - ABWF - Material Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 14 19-Jul-22 01-Aug-22 21-Jul-22 03-Aug-22 2
Hols - No B/O periods (was
310.D.WS.L1444 PBA - ABWF - Material Submission - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 21 02-Aug-22 22-Aug-22 04-Aug-22 24-Aug-22 2
Hols - No B/O periods (was
CC#06 - PBC - MEP Submission C1)
C01_7 d/w - 10h/d - No HK Hols82
- No B/O periods
0 (was
23-Mar-22
C1) A 18-Jun-22 19-Jun-22 08-Sep-22 82
PBC - MEP - Drawing Submission C01_7 d/w - 10h/d - No HK Hols82
- No B/O periods
0 (was
23-Mar-22
C1) A 18-Jun-22 19-Jun-22 08-Sep-22 82
310.D.WS.L712 PBC - MEP - Drawing Submission - prepare document C01_7 d/w - 10h/d - No HK 40 23-Mar-22 A 07-May-22 19-Jun-22 28-Jul-22 82
Hols - No B/O periods (was
310.D.WS.L713 PBC - MEP - Drawing Submission - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 40 12-Apr-22 21-May-22 03-Jul-22 11-Aug-22 82
Hols - No B/O periods (was
310.D.WS.L714 PBC - MEP - Drawing Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 40 26-Apr-22 04-Jun-22 17-Jul-22 25-Aug-22 82
Hols - No B/O periods (was
310.D.WS.L716 PBC - MEP - Drawing Submission - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 40 10-May-22 18-Jun-22 31-Jul-22 08-Sep-22 82
Hols - No B/O periods (was
CC#06 - PBC - ABWF Submission C1)
C01_7 d/w - 10h/d - No HK Hols42
- No B/O periods
0 (was26-Apr-22
C1) 06-Jun-22 27-Apr-22 07-Jun-22 1
PBC - ABWF - Drawing Submission C01_7 d/w - 10h/d - No HK Hols42
- No B/O periods
0 (was26-Apr-22
C1) 06-Jun-22 27-Apr-22 07-Jun-22 1
310.D.WS.L1448 PBC - ABWF - prepare document C01_7 d/w - 10h/d - No HK 7 26-Apr-22 02-May-22 27-Apr-22 03-May-22 1
Hols - No B/O periods (was
310.D.WS.L1700 PBC - ABWF - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 14 03-May-22 16-May-22 04-May-22 17-May-22 1
Hols - No B/O periods (was
310.D.WS.L1696 PBC - ABWF - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 7 17-May-22 23-May-22 18-May-22 24-May-22 1
Hols - No B/O periods (was
310.D.WS.L1452 PBC - ABWF - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 14 24-May-22 06-Jun-22 25-May-22 07-Jun-22 1
Hols - No B/O periods (was
PBC - ABWF - Material Submission C1)
C01_7 d/w - 10h/d - No HK Hols42
- No B/O periods
0 (was26-Apr-22
C1) 06-Jun-22 27-Apr-22 07-Jun-22 1
310.D.WS.L1464 PBC - ABWF - Material Submission - prepare document C01_7 d/w - 10h/d - No HK 7 26-Apr-22 02-May-22 27-Apr-22 03-May-22 1
Hols - No B/O periods (was
C1)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 90 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L1708 PBC - ABWF - Material Submission - PM review and accept 1st Round C01_7 d/w - 10h/d - No HK 14 03-May-22 16-May-22 04-May-22 17-May-22 1
Hols - No B/O periods (was
310.D.WS.L1704 PBC - ABWF - Material Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 7 17-May-22 23-May-22 18-May-22 24-May-22 1
Hols - No B/O periods (was
310.D.WS.L1468 PBC - ABWF - Material Submission - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 14 24-May-22 06-Jun-22 25-May-22 07-Jun-22 1
Hols - No B/O periods (was
CC#06 - EVT - Submission of Method Statement and Shop Drawings C1)
C01_7 d/w - 10h/d - No HK Hols234
- No B/O periods
0 (was
13-Oct-21
C1) A 23-Apr-22 24-Apr-22 23-Dec-22 244
CC#06 - EVT - Method Statement of EVT Construction C01_7 d/w - 10h/d - No HK Hols58
- No B/O periods
0 (was
13-Oct-21
C1) A 18-Apr-22 24-Apr-22 16-May-22 28
310.D.TX.A204 MS no.15 - Method Statement for EVT Construction - prepare document C01_7 d/w - 10h/d - No HK 30 13-Oct-21 A 12-Nov-21 A 24-Apr-22 24-Apr-22
Hols - No B/O periods (was
310.D.TX.A208 MS no.15 - Method Statement for EVT Construction - PM review and accept C1)
C01_7 d/w - 10h/d - No HK 28 13-Nov-21 A 18-Apr-22 24-Apr-22 16-May-22 28
Hols - No B/O periods (was
CC#06 - EVT - Method Statement for Plate Load Test C1)
C01_7 d/w - 10h/d - No HK Hols58
- No B/O periods
0 (was
01-Nov-21
C1) A 23-Apr-22 26-Nov-22 23-Dec-22 244
310.D.TX.A324 Method Statement for Plate Load Test - prepare document C01_7 d/w - 10h/d - No HK 30 01-Nov-21 A 30-Nov-21 A 26-Nov-22 26-Nov-22
Hols - No B/O periods (was
310.D.TX.A328 Method Statement for Plate Load Test - BD Acknowledge C1)
C01_7 d/w - 10h/d - No HK 28 01-Dec-21 A 23-Apr-22 26-Nov-22 23-Dec-22 244
Hols - No B/O periods (was
CC#06 - General - MEP - Material Submission C1)
C01_7 d/w - 10h/d - No HK Hols292
- No B/O periods
0 (was
27-Jan-22
C1) A 14-Nov-22 28-Mar-22 02-Feb-23 80
Preliminaries C01_7 d/w - 10h/d - No HK Hols 7- No B/O periods
0 (was
27-Jan-22
C1) A 08-Feb-22 A 28-Mar-22 13-Apr-22
310.C.EX.S000.01aB02 Contract award (Tentative) C01_7 d/w - 10h/d - No HK 0 27-Jan-22 A 28-Mar-22
Hols - No B/O periods (was
310.C.EX.S000.02aB02 Mobilization C1)
C01_7 d/w - 10h/d - No HK 0 27-Jan-22 A 02-Feb-22 A 28-Mar-22 28-Mar-22
Hols - No B/O periods (was
310.C.EX.S000.03aB02 Prepare and submit O Chart C1)
C01_7 d/w - 10h/d - No HK 0 03-Feb-22 A 07-Feb-22 A 28-Mar-22 28-Mar-22
Hols - No B/O periods (was
310.C.EX.S000.04aB02 Prepare and submit Equipment/Material Submission Schedule C1)
C01_7 d/w - 10h/d - No HK 0 03-Feb-22 A 08-Feb-22 A 28-Mar-22 28-Mar-22
Hols - No B/O periods (was
310.C.EX.S000.05aB02 Prepare and submit Drawing Submission Shcedule C1)
C01_7 d/w - 10h/d - No HK 0 03-Feb-22 A 08-Feb-22 A 13-Apr-22 13-Apr-22
Hols - No B/O periods (was
Electrical C1)
C01_7 d/w - 10h/d - No HK Hols103
- No B/O periods
0 (was
06-Mar-22
C1) A 16-Jun-22 11-Apr-22 01-Jul-22 15
Armoured Cable C01_7 d/w - 10h/d - No HK Hols53
- No B/O periods
0 (was
14-Mar-22
C1) A 18-May-22 10-May-22 01-Jul-22 44
310.D.WS.L992.01aB02Prepare and submit info. of Armoured Cable C01_7 d/w - 10h/d - No HK 0 14-Mar-22 A 07-Apr-22 10-May-22 21-May-22 44
Hols - No B/O periods (was
310.D.WS.L993.01aB02Review and comment info. of Armoured Cable C1)
C01_7 d/w - 10h/d - No HK 23 08-Apr-22 30-Apr-22 22-May-22 13-Jun-22 44
Hols - No B/O periods (was
310.D.WS.L994.01aB02Prepare and re-submit info. of Armoured Cable C1)
C01_7 d/w - 10h/d - No HK 9 01-May-22 09-May-22 14-Jun-22 22-Jun-22 44
Hols - No B/O periods (was
310.D.WS.L996.01aB02Obtain "No objection" of Armoured Cable C1)
C01_7 d/w - 10h/d - No HK 9 10-May-22 18-May-22 23-Jun-22 01-Jul-22 44
Hols - No B/O periods (was
FR Cable C1)
C01_7 d/w - 10h/d - No HK Hols82
- No B/O periods
0 (was
14-Mar-22
C1) A 16-Jun-22 11-Apr-22 01-Jul-22 15
310.D.WS.L992.02aB02Prepare and submit info. of FR Cable C01_7 d/w - 10h/d - No HK 0 14-Mar-22 A 07-Apr-22 11-Apr-22 22-Apr-22 15
Hols - No B/O periods (was
310.D.WS.L993.02aB02Review and comment info. of FR Cable C1)
C01_7 d/w - 10h/d - No HK 24 08-Apr-22 01-May-22 23-Apr-22 16-May-22 15
Hols - No B/O periods (was
310.D.WS.L994.02aB02Prepare and re-submit info. of FR Cable C1)
C01_7 d/w - 10h/d - No HK 22 02-May-22 23-May-22 17-May-22 07-Jun-22 15
Hols - No B/O periods (was
310.D.WS.L996.02aB02Obtain "No objection" of FR Cable C1)
C01_7 d/w - 10h/d - No HK 24 24-May-22 16-Jun-22 08-Jun-22 01-Jul-22 15
Hols - No B/O periods (was
Single Core Cable C1)
C01_7 d/w - 10h/d - No HK Hols46
- No B/O periods
0 (was
14-Mar-22
C1) A 19-May-22 09-May-22 01-Jul-22 43
310.D.WS.L992.03aB02Prepare and submit info. of Single Core Cable C01_7 d/w - 10h/d - No HK 0 14-Mar-22 A 07-Apr-22 09-May-22 20-May-22 43
Hols - No B/O periods (was
C1)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 91 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L993.03aB02Review and comment info. of Single Core Cable C01_7 d/w - 10h/d - No HK 24 08-Apr-22 01-May-22 21-May-22 13-Jun-22 43
Hols - No B/O periods (was
310.D.WS.L994.03aB02Prepare and re-submit info. of Single Core Cable C1)
C01_7 d/w - 10h/d - No HK 9 02-May-22 10-May-22 14-Jun-22 22-Jun-22 43
Hols - No B/O periods (was
310.D.WS.L996.03aB02Obtain "No objection" of Single Core Cable C1)
C01_7 d/w - 10h/d - No HK 9 11-May-22 19-May-22 23-Jun-22 01-Jul-22 43
Hols - No B/O periods (was
General Lighting (included E-Lighting) C1)
C01_7 d/w - 10h/d - No HK Hols60
- No B/O periods
0 (was
20-Mar-22
C1) A 19-May-22 09-May-22 01-Jul-22 43
310.D.WS.L992.04aB02Prepare and submit info. of General Lighting (included E-Lighting) C01_7 d/w - 10h/d - No HK 12 20-Mar-22 A 07-Apr-22 09-May-22 20-May-22 43
Hols - No B/O periods (was
310.D.WS.L993.04aB02Review and comment info. of General Lighting (included E-Lighting) C1)
C01_7 d/w - 10h/d - No HK 24 08-Apr-22 01-May-22 21-May-22 13-Jun-22 43
Hols - No B/O periods (was
310.D.WS.L994.04aB02Prepare and re-submit info. of General Lighting (included E-Lighting) C1)
C01_7 d/w - 10h/d - No HK 9 02-May-22 10-May-22 14-Jun-22 22-Jun-22 43
Hols - No B/O periods (was
310.D.WS.L996.04aB02Obtain "No objection" of General Lighting (included E-Lighting) C1)
C01_7 d/w - 10h/d - No HK 9 11-May-22 19-May-22 23-Jun-22 01-Jul-22 43
Hols - No B/O periods (was
Distribution Board for MCB, MCCB & Accessories C1)
C01_7 d/w - 10h/d - No HK Hols68
- No B/O periods
0 (was
11-Mar-22
C1) A 17-May-22 11-May-22 01-Jul-22 45
310.D.WS.L992.05aB02Prepare and submit info. of Distribution Board for MCB, MCCB & Accessories C01_7 d/w - 10h/d - No HK 10 11-Mar-22 A 05-Apr-22 11-May-22 20-May-22 45
Hols - No B/O periods (was
310.D.WS.L993.05aB02Review and comment info. of Distribution Board for MCB, MCCB & Accessories C1)
C01_7 d/w - 10h/d - No HK 24 06-Apr-22 29-Apr-22 21-May-22 13-Jun-22 45
Hols - No B/O periods (was
310.D.WS.L994.05aB02Prepare and re-submit info. of Distribution Board for MCB, MCCB & Accessories C1)
C01_7 d/w - 10h/d - No HK 9 30-Apr-22 08-May-22 14-Jun-22 22-Jun-22 45
Hols - No B/O periods (was
310.D.WS.L996.05aB02Obtain "No objection" of Distribution Board for MCB, MCCB & Accessories C1)
C01_7 d/w - 10h/d - No HK 9 09-May-22 17-May-22 23-Jun-22 01-Jul-22 45
Hols - No B/O periods (was
MCB, MCCB & Accessories C1)
C01_7 d/w - 10h/d - No HK Hols64
- No B/O periods
0 (was
11-Mar-22
C1) A 13-May-22 15-May-22 01-Jul-22 49
310.D.WS.L992.06aB02Prepare and submit info. of MCB, MCCB & Accessories C01_7 d/w - 10h/d - No HK 6 11-Mar-22 A 01-Apr-22 15-May-22 20-May-22 49
Hols - No B/O periods (was
310.D.WS.L993.06aB02Review and comment info. of MCB, MCCB & Accessories C1)
C01_7 d/w - 10h/d - No HK 24 02-Apr-22 25-Apr-22 21-May-22 13-Jun-22 49
Hols - No B/O periods (was
310.D.WS.L994.06aB02Prepare and re-submit info. of MCB, MCCB & Accessories C1)
C01_7 d/w - 10h/d - No HK 9 26-Apr-22 04-May-22 14-Jun-22 22-Jun-22 49
Hols - No B/O periods (was
310.D.WS.L996.06aB02Obtain "No objection" of MCB, MCCB & Accessories C1)
C01_7 d/w - 10h/d - No HK 9 05-May-22 13-May-22 23-Jun-22 01-Jul-22 49
Hols - No B/O periods (was
Busduct C1)
C01_7 d/w - 10h/d - No HK Hols62
- No B/O periods
0 (was04-Apr-22
C1) 04-Jun-22 01-May-22 01-Jul-22 27
310.D.WS.L992.07aB02Prepare and submit info. of Busduct C01_7 d/w - 10h/d - No HK 20 04-Apr-22 23-Apr-22 01-May-22 20-May-22 27
Hols - No B/O periods (was
310.D.WS.L993.07aB02Review and comment info. of Busduct C1)
C01_7 d/w - 10h/d - No HK 24 24-Apr-22 17-May-22 21-May-22 13-Jun-22 27
Hols - No B/O periods (was
310.D.WS.L994.07aB02Prepare and re-submit info. of Busduct C1)
C01_7 d/w - 10h/d - No HK 9 18-May-22 26-May-22 14-Jun-22 22-Jun-22 27
Hols - No B/O periods (was
310.D.WS.L996.07aB02Obtain "No objection" of Busduct C1)
C01_7 d/w - 10h/d - No HK 9 27-May-22 04-Jun-22 23-Jun-22 01-Jul-22 27
Hols - No B/O periods (was
Water Leakage Detection System C1)
C01_7 d/w - 10h/d - No HK Hols62
- No B/O periods
0 (was04-Apr-22
C1) 04-Jun-22 01-May-22 01-Jul-22 27
310.D.WS.L992.08aB02Prepare and submit info. of Water Leakage Detection System C01_7 d/w - 10h/d - No HK 20 04-Apr-22 23-Apr-22 01-May-22 20-May-22 27
Hols - No B/O periods (was
310.D.WS.L993.08aB02Review and comment info. of Water Leakage Detection System C1)
C01_7 d/w - 10h/d - No HK 24 24-Apr-22 17-May-22 21-May-22 13-Jun-22 27
Hols - No B/O periods (was
310.D.WS.L994.08aB02Prepare and re-submit info. of Water Leakage Detection System C1)
C01_7 d/w - 10h/d - No HK 9 18-May-22 26-May-22 14-Jun-22 22-Jun-22 27
Hols - No B/O periods (was
310.D.WS.L996.08aB02Obtain "No objection" of Water Leakage Detection System C1)
C01_7 d/w - 10h/d - No HK 9 27-May-22 04-Jun-22 23-Jun-22 01-Jul-22 27
Hols - No B/O periods (was
C1)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 92 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
MICC Cable C01_7 d/w - 10h/d - No HK Hols76
- No B/O periods
0 (was
07-Mar-22
C1) A 21-May-22 07-May-22 01-Jul-22 41
310.D.WS.L992.09aB02Prepare and submit info. of MICC Cable C01_7 d/w - 10h/d - No HK 14 07-Mar-22 A 09-Apr-22 07-May-22 20-May-22 41
Hols - No B/O periods (was
310.D.WS.L993.09aB02Review and comment info. of MICC Cable C1)
C01_7 d/w - 10h/d - No HK 24 10-Apr-22 03-May-22 21-May-22 13-Jun-22 41
Hols - No B/O periods (was
310.D.WS.L994.09aB02Prepare and re-submit info. of MICC Cable C1)
C01_7 d/w - 10h/d - No HK 9 04-May-22 12-May-22 14-Jun-22 22-Jun-22 41
Hols - No B/O periods (was
310.D.WS.L996.09aB02Obtain "No objection" of MICC Cable C1)
C01_7 d/w - 10h/d - No HK 9 13-May-22 21-May-22 23-Jun-22 01-Jul-22 41
Hols - No B/O periods (was
LV Switchboards & Accessories C1)
C01_7 d/w - 10h/d - No HK Hols61
- No B/O periods
0 (was
22-Mar-22
C1) A 21-May-22 07-May-22 01-Jul-22 41
310.D.WS.L992.10aB02Prepare and submit info. of LV Switchboards & Accessories C01_7 d/w - 10h/d - No HK 14 22-Mar-22 A 09-Apr-22 07-May-22 20-May-22 41
Hols - No B/O periods (was
310.D.WS.L993.10aB02Review and comment info. of LV Switchboards & Accessories C1)
C01_7 d/w - 10h/d - No HK 24 10-Apr-22 03-May-22 21-May-22 13-Jun-22 41
Hols - No B/O periods (was
310.D.WS.L994.10aB02Prepare and re-submit info. of LV Switchboards & Accessories C1)
C01_7 d/w - 10h/d - No HK 9 04-May-22 12-May-22 14-Jun-22 22-Jun-22 41
Hols - No B/O periods (was
310.D.WS.L996.10aB02Obtain "No objection" of LV Switchboards & Accessories C1)
C01_7 d/w - 10h/d - No HK 9 13-May-22 21-May-22 23-Jun-22 01-Jul-22 41
Hols - No B/O periods (was
ACB & Accessories C1)
C01_7 d/w - 10h/d - No HK Hols61
- No B/O periods
0 (was
22-Mar-22
C1) A 21-May-22 07-May-22 01-Jul-22 41
310.D.WS.L992.11aB02Prepare and submit info. of ACB & Accessories C01_7 d/w - 10h/d - No HK 14 22-Mar-22 A 09-Apr-22 07-May-22 20-May-22 41
Hols - No B/O periods (was
310.D.WS.L993.11aB02Review and comment info. of ACB & Accessories C1)
C01_7 d/w - 10h/d - No HK 24 10-Apr-22 03-May-22 21-May-22 13-Jun-22 41
Hols - No B/O periods (was
310.D.WS.L994.11aB02Prepare and re-submit info. of ACB & Accessories C1)
C01_7 d/w - 10h/d - No HK 9 04-May-22 12-May-22 14-Jun-22 22-Jun-22 41
Hols - No B/O periods (was
310.D.WS.L996.11aB02Obtain "No objection" of ACB & Accessories C1)
C01_7 d/w - 10h/d - No HK 9 13-May-22 21-May-22 23-Jun-22 01-Jul-22 41
Hols - No B/O periods (was
Automatic Transfer Switch C1)
C01_7 d/w - 10h/d - No HK Hols61
- No B/O periods
0 (was
22-Mar-22
C1) A 21-May-22 07-May-22 01-Jul-22 41
310.D.WS.L992.12aB02Prepare and submit info. of Automatic Transfer Switch C01_7 d/w - 10h/d - No HK 14 22-Mar-22 A 09-Apr-22 07-May-22 20-May-22 41
Hols - No B/O periods (was
310.D.WS.L993.12aB02Review and comment info. of Automatic Transfer Switch C1)
C01_7 d/w - 10h/d - No HK 24 10-Apr-22 03-May-22 21-May-22 13-Jun-22 41
Hols - No B/O periods (was
310.D.WS.L994.12aB02Prepare and re-submit info. of Automatic Transfer Switch C1)
C01_7 d/w - 10h/d - No HK 9 04-May-22 12-May-22 14-Jun-22 22-Jun-22 41
Hols - No B/O periods (was
310.D.WS.L996.12aB02Obtain "No objection" of Automatic Transfer Switch C1)
C01_7 d/w - 10h/d - No HK 9 13-May-22 21-May-22 23-Jun-22 01-Jul-22 41
Hols - No B/O periods (was
Battery Set C1)
C01_7 d/w - 10h/d - No HK Hols61
- No B/O periods
0 (was
22-Mar-22
C1) A 21-May-22 07-May-22 01-Jul-22 41
310.D.WS.L992.13aB02Prepare and submit info. of Battery Set C01_7 d/w - 10h/d - No HK 14 22-Mar-22 A 09-Apr-22 07-May-22 20-May-22 41
Hols - No B/O periods (was
310.D.WS.L993.13aB02Review and comment info. of Battery Set C1)
C01_7 d/w - 10h/d - No HK 24 10-Apr-22 03-May-22 21-May-22 13-Jun-22 41
Hols - No B/O periods (was
310.D.WS.L994.13aB02Prepare and re-submit info. of Battery Set C1)
C01_7 d/w - 10h/d - No HK 9 04-May-22 12-May-22 14-Jun-22 22-Jun-22 41
Hols - No B/O periods (was
310.D.WS.L996.13aB02Obtain "No objection" of Battery Set C1)
C01_7 d/w - 10h/d - No HK 9 13-May-22 21-May-22 23-Jun-22 01-Jul-22 41
Hols - No B/O periods (was
HRC Fuse for Fuse-switch C1)
C01_7 d/w - 10h/d - No HK Hols62
- No B/O periods
0 (was27-Mar-22
C1) 27-May-22 01-May-22 01-Jul-22 35
310.D.WS.L992.14aB02Prepare and submit info. of HRC Fuse for Fuse-switch C01_7 d/w - 10h/d - No HK 20 27-Mar-22 15-Apr-22 01-May-22 20-May-22 35
Hols - No B/O periods (was
310.D.WS.L993.14aB02Review and comment info. of HRC Fuse for Fuse-switch C1)
C01_7 d/w - 10h/d - No HK 24 16-Apr-22 09-May-22 21-May-22 13-Jun-22 35
Hols - No B/O periods (was
C1)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 93 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L994.14aB02Prepare and re-submit info. of HRC Fuse for Fuse-switch C01_7 d/w - 10h/d - No HK 9 10-May-22 18-May-22 14-Jun-22 22-Jun-22 35
Hols - No B/O periods (was
310.D.WS.L996.14aB02Obtain "No objection" of HRC Fuse for Fuse-switch C1)
C01_7 d/w - 10h/d - No HK 9 19-May-22 27-May-22 23-Jun-22 01-Jul-22 35
Hols - No B/O periods (was
MCCB C1)
C01_7 d/w - 10h/d - No HK Hols61
- No B/O periods
0 (was
22-Mar-22
C1) A 21-May-22 07-May-22 01-Jul-22 41
310.D.WS.L992.15aB02Prepare and submit info. of MCCB C01_7 d/w - 10h/d - No HK 14 22-Mar-22 A 09-Apr-22 07-May-22 20-May-22 41
Hols - No B/O periods (was
310.D.WS.L993.15aB02Review and comment info. of MCCB C1)
C01_7 d/w - 10h/d - No HK 24 10-Apr-22 03-May-22 21-May-22 13-Jun-22 41
Hols - No B/O periods (was
310.D.WS.L994.15aB02Prepare and re-submit info. of MCCB C1)
C01_7 d/w - 10h/d - No HK 9 04-May-22 12-May-22 14-Jun-22 22-Jun-22 41
Hols - No B/O periods (was
310.D.WS.L996.15aB02Obtain "No objection" of MCCB C1)
C01_7 d/w - 10h/d - No HK 9 13-May-22 21-May-22 23-Jun-22 01-Jul-22 41
Hols - No B/O periods (was
Digital Protection Device C1)
C01_7 d/w - 10h/d - No HK Hols77
- No B/O periods
0 (was
06-Mar-22
C1) A 21-May-22 07-May-22 01-Jul-22 41
310.D.WS.L992.16aB02Prepare and submit info. of Digital Protection Device C01_7 d/w - 10h/d - No HK 14 06-Mar-22 A 09-Apr-22 07-May-22 20-May-22 41
Hols - No B/O periods (was
310.D.WS.L993.16aB02Review and comment info. of Digital Protection Device C1)
C01_7 d/w - 10h/d - No HK 24 10-Apr-22 03-May-22 21-May-22 13-Jun-22 41
Hols - No B/O periods (was
310.D.WS.L994.16aB02Prepare and re-submit info. of Digital Protection Device C1)
C01_7 d/w - 10h/d - No HK 9 04-May-22 12-May-22 14-Jun-22 22-Jun-22 41
Hols - No B/O periods (was
310.D.WS.L996.16aB02Obtain "No objection" of Digital Protection Device C1)
C01_7 d/w - 10h/d - No HK 9 13-May-22 21-May-22 23-Jun-22 01-Jul-22 41
Hols - No B/O periods (was
Capacitor Bank C1)
C01_7 d/w - 10h/d - No HK Hols77
- No B/O periods
0 (was
06-Mar-22
C1) A 21-May-22 07-May-22 01-Jul-22 41
310.D.WS.L992.17aB02Prepare and submit info. of Capacitor Bank C01_7 d/w - 10h/d - No HK 14 06-Mar-22 A 09-Apr-22 07-May-22 20-May-22 41
Hols - No B/O periods (was
310.D.WS.L993.17aB02Review and comment info. of Capacitor Bank C1)
C01_7 d/w - 10h/d - No HK 24 10-Apr-22 03-May-22 21-May-22 13-Jun-22 41
Hols - No B/O periods (was
310.D.WS.L994.17aB02Prepare and re-submit info. of Capacitor Bank C1)
C01_7 d/w - 10h/d - No HK 9 04-May-22 12-May-22 14-Jun-22 22-Jun-22 41
Hols - No B/O periods (was
310.D.WS.L996.17aB02Obtain "No objection" of Capacitor Bank C1)
C01_7 d/w - 10h/d - No HK 9 13-May-22 21-May-22 23-Jun-22 01-Jul-22 41
Hols - No B/O periods (was
UPS C1)
C01_7 d/w - 10h/d - No HK Hols56
- No B/O periods
0 (was29-Mar-22
C1) 23-May-22 07-May-22 01-Jul-22 39
310.D.WS.L992.18aB02Prepare and submit info. of UPS C01_7 d/w - 10h/d - No HK 14 29-Mar-22 11-Apr-22 07-May-22 20-May-22 39
Hols - No B/O periods (was
310.D.WS.L993.18aB02Review and comment info. of UPS C1)
C01_7 d/w - 10h/d - No HK 24 12-Apr-22 05-May-22 21-May-22 13-Jun-22 39
Hols - No B/O periods (was
310.D.WS.L994.18aB02Prepare and re-submit info. of UPS C1)
C01_7 d/w - 10h/d - No HK 9 06-May-22 14-May-22 14-Jun-22 22-Jun-22 39
Hols - No B/O periods (was
310.D.WS.L996.18aB02Obtain "No objection" of UPS C1)
C01_7 d/w - 10h/d - No HK 9 15-May-22 23-May-22 23-Jun-22 01-Jul-22 39
Hols - No B/O periods (was
Active Harmoice Filter C1)
C01_7 d/w - 10h/d - No HK Hols56
- No B/O periods
0 (was29-Mar-22
C1) 23-May-22 07-May-22 01-Jul-22 39
310.D.WS.L992.19aB02Prepare and submit info. of Active Harmoice Filter C01_7 d/w - 10h/d - No HK 14 29-Mar-22 11-Apr-22 07-May-22 20-May-22 39
Hols - No B/O periods (was
310.D.WS.L993.19aB02Review and comment info. of Active Harmoice Filter C1)
C01_7 d/w - 10h/d - No HK 24 12-Apr-22 05-May-22 21-May-22 13-Jun-22 39
Hols - No B/O periods (was
310.D.WS.L994.19aB02Prepare and re-submit info. of Active Harmoice Filter C1)
C01_7 d/w - 10h/d - No HK 9 06-May-22 14-May-22 14-Jun-22 22-Jun-22 39
Hols - No B/O periods (was
310.D.WS.L996.19aB02Obtain "No objection" of Active Harmoice Filter C1)
C01_7 d/w - 10h/d - No HK 9 15-May-22 23-May-22 23-Jun-22 01-Jul-22 39
Hols - No B/O periods (was
Isolation Transformer C1)
C01_7 d/w - 10h/d - No HK Hols56
- No B/O periods
0 (was29-Mar-22
C1) 23-May-22 07-May-22 01-Jul-22 39

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 94 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L992.20aB02Prepare and submit info. of Isolation Transformer C01_7 d/w - 10h/d - No HK 14 29-Mar-22 11-Apr-22 07-May-22 20-May-22 39
Hols - No B/O periods (was
310.D.WS.L993.20aB02Review and comment info. of Isolation Transformer C1)
C01_7 d/w - 10h/d - No HK 24 12-Apr-22 05-May-22 21-May-22 13-Jun-22 39
Hols - No B/O periods (was
310.D.WS.L994.20aB02Prepare and re-submit info. of Isolation Transformer C1)
C01_7 d/w - 10h/d - No HK 9 06-May-22 14-May-22 14-Jun-22 22-Jun-22 39
Hols - No B/O periods (was
310.D.WS.L996.20aB02Obtain "No objection" of Isolation Transformer C1)
C01_7 d/w - 10h/d - No HK 9 15-May-22 23-May-22 23-Jun-22 01-Jul-22 39
Hols - No B/O periods (was
By-pass switch C1)
C01_7 d/w - 10h/d - No HK Hols62
- No B/O periods
0 (was27-Mar-22
C1) 27-May-22 01-May-22 01-Jul-22 35
310.D.WS.L992.21aB02Prepare and submit info. of By-pass switch C01_7 d/w - 10h/d - No HK 20 27-Mar-22 15-Apr-22 01-May-22 20-May-22 35
Hols - No B/O periods (was
310.D.WS.L993.21aB02Review and comment info. of By-pass switch C1)
C01_7 d/w - 10h/d - No HK 24 16-Apr-22 09-May-22 21-May-22 13-Jun-22 35
Hols - No B/O periods (was
310.D.WS.L994.21aB02Prepare and re-submit info. of By-pass switch C1)
C01_7 d/w - 10h/d - No HK 9 10-May-22 18-May-22 14-Jun-22 22-Jun-22 35
Hols - No B/O periods (was
310.D.WS.L996.21aB02Obtain "No objection" of By-pass switch C1)
C01_7 d/w - 10h/d - No HK 9 19-May-22 27-May-22 23-Jun-22 01-Jul-22 35
Hols - No B/O periods (was
LV Generator Set (included Alternator & Diesel Engine) C1)
C01_7 d/w - 10h/d - No HK Hols54
- No B/O periods
0 (was
22-Mar-22
C1) A 14-May-22 14-May-22 01-Jul-22 48
310.D.WS.L992.22aB02Prepare and submit info. of LV Generator Set (included Alternator & Diesel Engine) C01_7 d/w - 10h/d - No HK 7 22-Mar-22 A 02-Apr-22 14-May-22 20-May-22 48
Hols - No B/O periods (was
310.D.WS.L993.22aB02Review and comment info. of LV Generator Set (included Alternator & Diesel Engine) C1)
C01_7 d/w - 10h/d - No HK 24 03-Apr-22 26-Apr-22 21-May-22 13-Jun-22 48
Hols - No B/O periods (was
310.D.WS.L994.22aB02Prepare and re-submit info. of LV Generator Set (included Alternator & Diesel Engine) C1)
C01_7 d/w - 10h/d - No HK 9 27-Apr-22 05-May-22 14-Jun-22 22-Jun-22 48
Hols - No B/O periods (was
310.D.WS.L996.22aB02Obtain "No objection" of LV Generator Set (included Alternator & Diesel Engine) C1)
C01_7 d/w - 10h/d - No HK 9 06-May-22 14-May-22 23-Jun-22 01-Jul-22 48
Hols - No B/O periods (was
Generator Controller C1)
C01_7 d/w - 10h/d - No HK Hols54
- No B/O periods
0 (was
22-Mar-22
C1) A 14-May-22 14-May-22 01-Jul-22 48
310.D.WS.L992.23aB02Prepare and submit info. of Generator Controller C01_7 d/w - 10h/d - No HK 7 22-Mar-22 A 02-Apr-22 14-May-22 20-May-22 48
Hols - No B/O periods (was
310.D.WS.L993.23aB02Review and comment info. of Generator Controller C1)
C01_7 d/w - 10h/d - No HK 24 03-Apr-22 26-Apr-22 21-May-22 13-Jun-22 48
Hols - No B/O periods (was
310.D.WS.L994.23aB02Prepare and re-submit info. of Generator Controller C1)
C01_7 d/w - 10h/d - No HK 9 27-Apr-22 05-May-22 14-Jun-22 22-Jun-22 48
Hols - No B/O periods (was
310.D.WS.L996.23aB02Obtain "No objection" of Generator Controller C1)
C01_7 d/w - 10h/d - No HK 9 06-May-22 14-May-22 23-Jun-22 01-Jul-22 48
Hols - No B/O periods (was
Starting Battery System C1)
C01_7 d/w - 10h/d - No HK Hols54
- No B/O periods
0 (was
22-Mar-22
C1) A 14-May-22 14-May-22 01-Jul-22 48
310.D.WS.L992.24aB02Prepare and submit info. of Starting Battery System C01_7 d/w - 10h/d - No HK 7 22-Mar-22 A 02-Apr-22 14-May-22 20-May-22 48
Hols - No B/O periods (was
310.D.WS.L993.24aB02Review and comment info. of Starting Battery System C1)
C01_7 d/w - 10h/d - No HK 24 03-Apr-22 26-Apr-22 21-May-22 13-Jun-22 48
Hols - No B/O periods (was
310.D.WS.L994.24aB02Prepare and re-submit info. of Starting Battery System C1)
C01_7 d/w - 10h/d - No HK 9 27-Apr-22 05-May-22 14-Jun-22 22-Jun-22 48
Hols - No B/O periods (was
310.D.WS.L996.24aB02Obtain "No objection" of Starting Battery System C1)
C01_7 d/w - 10h/d - No HK 9 06-May-22 14-May-22 23-Jun-22 01-Jul-22 48
Hols - No B/O periods (was
Battery Charger C1)
C01_7 d/w - 10h/d - No HK Hols54
- No B/O periods
0 (was
22-Mar-22
C1) A 14-May-22 14-May-22 01-Jul-22 48
310.D.WS.L992.25aB02Prepare and submit info. of Battery Charger C01_7 d/w - 10h/d - No HK 7 22-Mar-22 A 02-Apr-22 14-May-22 20-May-22 48
Hols - No B/O periods (was
310.D.WS.L993.25aB02Review and comment info. of Battery Charger C1)
C01_7 d/w - 10h/d - No HK 24 03-Apr-22 26-Apr-22 21-May-22 13-Jun-22 48
Hols - No B/O periods (was
310.D.WS.L994.25aB02Prepare and re-submit info. of Battery Charger C1)
C01_7 d/w - 10h/d - No HK 9 27-Apr-22 05-May-22 14-Jun-22 22-Jun-22 48
Hols - No B/O periods (was
C1)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 95 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L996.25aB02Obtain "No objection" of Battery Charger C01_7 d/w - 10h/d - No HK 9 06-May-22 14-May-22 23-Jun-22 01-Jul-22 48
Hols - No B/O periods (was
MVAC C1)
C01_7 d/w - 10h/d - No HK Hols115
- No B/O periods
0 (was
08-Feb-22
C1) A 26-Jun-22 28-Mar-22 11-Oct-22 107
CRAC Unit C01_7 d/w - 10h/d - No HK Hols72
- No B/O periods
0 (was
04-Mar-22
C1) A 14-May-22 14-May-22 01-Jul-22 48
310.D.WS.L992.26aB02Prepare and submit info. of CRAC Unit C01_7 d/w - 10h/d - No HK 7 04-Mar-22 A 02-Apr-22 14-May-22 20-May-22 48
Hols - No B/O periods (was
310.D.WS.L993.26aB02Review and comment info. of CRAC Unit C1)
C01_7 d/w - 10h/d - No HK 24 03-Apr-22 26-Apr-22 21-May-22 13-Jun-22 48
Hols - No B/O periods (was
310.D.WS.L994.26aB02Prepare and re-submit info. of CRAC Unit C1)
C01_7 d/w - 10h/d - No HK 9 27-Apr-22 05-May-22 14-Jun-22 22-Jun-22 48
Hols - No B/O periods (was
310.D.WS.L996.26aB02Obtain "No objection" of CRAC Unit C1)
C01_7 d/w - 10h/d - No HK 9 06-May-22 14-May-22 23-Jun-22 01-Jul-22 48
Hols - No B/O periods (was
Axial Fan C1)
C01_7 d/w - 10h/d - No HK Hols69
- No B/O periods
0 (was
04-Mar-22
C1) A 11-May-22 28-Mar-22 12-May-22 1
310.D.WS.L992.27aB02Prepare and submit info. of Axial Fan C01_7 d/w - 10h/d - No HK 4 04-Mar-22 A 30-Mar-22 28-Mar-22 31-Mar-22 1
Hols - No B/O periods (was
310.D.WS.L993.27aB02Review and comment info. of Axial Fan C1)
C01_7 d/w - 10h/d - No HK 24 31-Mar-22 23-Apr-22 01-Apr-22 24-Apr-22 1
Hols - No B/O periods (was
310.D.WS.L994.27aB02Prepare and re-submit info. of Axial Fan C1)
C01_7 d/w - 10h/d - No HK 9 24-Apr-22 02-May-22 25-Apr-22 03-May-22 1
Hols - No B/O periods (was
310.D.WS.L996.27aB02Obtain "No objection" of Axial Fan C1)
C01_7 d/w - 10h/d - No HK 9 03-May-22 11-May-22 04-May-22 12-May-22 1
Hols - No B/O periods (was
Split Type & VRV AC Unit C1)
C01_7 d/w - 10h/d - No HK Hols72
- No B/O periods
0 (was
04-Mar-22
C1) A 14-May-22 14-May-22 01-Jul-22 48
310.D.WS.L992.30aB02Prepare and submit info. of Split Type & VRV AC Unit C01_7 d/w - 10h/d - No HK 7 04-Mar-22 A 02-Apr-22 14-May-22 20-May-22 48
Hols - No B/O periods (was
310.D.WS.L993.30aB02Review and comment info. of Split Type & VRV AC Unit C1)
C01_7 d/w - 10h/d - No HK 24 03-Apr-22 26-Apr-22 21-May-22 13-Jun-22 48
Hols - No B/O periods (was
310.D.WS.L994.30aB02Prepare and re-submit info. of Split Type & VRV AC Unit C1)
C01_7 d/w - 10h/d - No HK 9 27-Apr-22 05-May-22 14-Jun-22 22-Jun-22 48
Hols - No B/O periods (was
310.D.WS.L996.30aB02Obtain "No objection" of Split Type & VRV AC Unit C1)
C01_7 d/w - 10h/d - No HK 9 06-May-22 14-May-22 23-Jun-22 01-Jul-22 48
Hols - No B/O periods (was
Tunnel Jet Fan C1)
C01_7 d/w - 10h/d - No HK Hols54
- No B/O periods
0 (was
04-Apr-22
C1) A 27-May-22 11-Aug-22 11-Oct-22 137
310.D.WS.L992.31aB02Prepare and submit info. of Tunnel Jet Fan C01_7 d/w - 10h/d - No HK 20 04-Apr-22 A 15-Apr-22 11-Aug-22 30-Aug-22 137
Hols - No B/O periods (was
310.D.WS.L993.31aB02Review and comment info. of Tunnel Jet Fan C1)
C01_7 d/w - 10h/d - No HK 24 16-Apr-22 09-May-22 31-Aug-22 23-Sep-22 137
Hols - No B/O periods (was
310.D.WS.L994.31aB02Prepare and re-submit info. of Tunnel Jet Fan C1)
C01_7 d/w - 10h/d - No HK 9 10-May-22 18-May-22 24-Sep-22 02-Oct-22 137
Hols - No B/O periods (was
310.D.WS.L996.31aB02Obtain "No objection" of Tunnel Jet Fan C1)
C01_7 d/w - 10h/d - No HK 9 19-May-22 27-May-22 03-Oct-22 11-Oct-22 137
Hols - No B/O periods (was
Motor Control Centre C1)
C01_7 d/w - 10h/d - No HK Hols55
- No B/O periods
0 (was27-Mar-22
C1) 20-May-22 08-May-22 01-Jul-22 42
310.D.WS.L992.33aB02Prepare and submit info. of Motor Control Centre C01_7 d/w - 10h/d - No HK 13 27-Mar-22 08-Apr-22 08-May-22 20-May-22 42
Hols - No B/O periods (was
310.D.WS.L993.33aB02Review and comment info. of Motor Control Centre C1)
C01_7 d/w - 10h/d - No HK 24 09-Apr-22 02-May-22 21-May-22 13-Jun-22 42
Hols - No B/O periods (was
310.D.WS.L994.33aB02Prepare and re-submit info. of Motor Control Centre C1)
C01_7 d/w - 10h/d - No HK 9 03-May-22 11-May-22 14-Jun-22 22-Jun-22 42
Hols - No B/O periods (was
310.D.WS.L996.33aB02Obtain "No objection" of Motor Control Centre C1)
C01_7 d/w - 10h/d - No HK 9 12-May-22 20-May-22 23-Jun-22 01-Jul-22 42
Hols - No B/O periods (was
Local Motor Control Panel C1)
C01_7 d/w - 10h/d - No HK Hols59
- No B/O periods
0 (was27-Mar-22
C1) 24-May-22 04-May-22 01-Jul-22 38
310.D.WS.L992.34aB02Prepare and submit info. of Local Motor Control Panel C01_7 d/w - 10h/d - No HK 17 27-Mar-22 12-Apr-22 04-May-22 20-May-22 38
Hols - No B/O periods (was
C1)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 96 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L993.34aB02Review and comment info. of Local Motor Control Panel C01_7 d/w - 10h/d - No HK 24 13-Apr-22 06-May-22 21-May-22 13-Jun-22 38
Hols - No B/O periods (was
310.D.WS.L994.34aB02Prepare and re-submit info. of Local Motor Control Panel C1)
C01_7 d/w - 10h/d - No HK 9 07-May-22 15-May-22 14-Jun-22 22-Jun-22 38
Hols - No B/O periods (was
310.D.WS.L996.34aB02Obtain "No objection" of Local Motor Control Panel C1)
C01_7 d/w - 10h/d - No HK 9 16-May-22 24-May-22 23-Jun-22 01-Jul-22 38
Hols - No B/O periods (was
MFSD C1)
C01_7 d/w - 10h/d - No HK Hols72
- No B/O periods
0 (was
04-Mar-22
C1) A 14-May-22 14-May-22 01-Jul-22 48
310.D.WS.L992.35aB02Prepare and submit info. of MFSD C01_7 d/w - 10h/d - No HK 7 04-Mar-22 A 02-Apr-22 14-May-22 20-May-22 48
Hols - No B/O periods (was
310.D.WS.L993.35aB02Review and comment info. of MSD C1)
C01_7 d/w - 10h/d - No HK 24 03-Apr-22 26-Apr-22 21-May-22 13-Jun-22 48
Hols - No B/O periods (was
310.D.WS.L994.35aB02Prepare and re-submit info. of MSD C1)
C01_7 d/w - 10h/d - No HK 9 27-Apr-22 05-May-22 14-Jun-22 22-Jun-22 48
Hols - No B/O periods (was
310.D.WS.L996.35aB02Obtain "No objection" of MSD C1)
C01_7 d/w - 10h/d - No HK 9 06-May-22 14-May-22 23-Jun-22 01-Jul-22 48
Hols - No B/O periods (was
Fire Damper C1)
C01_7 d/w - 10h/d - No HK Hols72
- No B/O periods
0 (was
04-Mar-22
C1) A 14-May-22 14-May-22 01-Jul-22 48
310.D.WS.L992.36aB02Prepare and submit info. of Fire Damper C01_7 d/w - 10h/d - No HK 7 04-Mar-22 A 02-Apr-22 14-May-22 20-May-22 48
Hols - No B/O periods (was
310.D.WS.L993.36aB02Review and comment info. of Fire Damper C1)
C01_7 d/w - 10h/d - No HK 24 03-Apr-22 26-Apr-22 21-May-22 13-Jun-22 48
Hols - No B/O periods (was
310.D.WS.L994.36aB02Prepare and re-submit info. of Fire Damper C1)
C01_7 d/w - 10h/d - No HK 9 27-Apr-22 05-May-22 14-Jun-22 22-Jun-22 48
Hols - No B/O periods (was
310.D.WS.L996.36aB02Obtain "No objection" of Fire Damper C1)
C01_7 d/w - 10h/d - No HK 9 06-May-22 14-May-22 23-Jun-22 01-Jul-22 48
Hols - No B/O periods (was
Air Grille & Accessories C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was21-Apr-22
C1) 26-Jun-22 26-Apr-22 01-Jul-22 5
310.D.WS.L992.37aB02Prepare and submit info. of Air Grille & Accessories C01_7 d/w - 10h/d - No HK 25 21-Apr-22 15-May-22 26-Apr-22 20-May-22 5
Hols - No B/O periods (was
310.D.WS.L993.37aB02Review and comment info. of Air Grille & Accessories C1)
C01_7 d/w - 10h/d - No HK 24 16-May-22 08-Jun-22 21-May-22 13-Jun-22 5
Hols - No B/O periods (was
310.D.WS.L994.37aB02Prepare and re-submit info. of Air Grille & Accessories C1)
C01_7 d/w - 10h/d - No HK 9 09-Jun-22 17-Jun-22 14-Jun-22 22-Jun-22 5
Hols - No B/O periods (was
310.D.WS.L996.37aB02Obtain "No objection" of Air Grille & Accessories C1)
C01_7 d/w - 10h/d - No HK 9 18-Jun-22 26-Jun-22 23-Jun-22 01-Jul-22 5
Hols - No B/O periods (was
G.I. Sheet Ductwork & Accessories C1)
C01_7 d/w - 10h/d - No HK Hols58
- No B/O periods
0 (was
08-Feb-22
C1) A 23-Mar-22 A 13-May-22 13-May-22
310.D.WS.L992.38aB02Prepare and submit info. of G.I. Sheet Ductwork & Accessories C01_7 d/w - 10h/d - No HK 0 08-Feb-22 A 04-Mar-22 A 13-May-22 13-May-22
Hols - No B/O periods (was
310.D.WS.L993.38aB02Review and comment info. of G.I. Sheet Ductwork & Accessories C1)
C01_7 d/w - 10h/d - No HK 0 05-Mar-22 A 23-Mar-22 A 13-May-22 13-May-22
Hols - No B/O periods (was
310.D.WS.L994.38aB02Prepare and re-submit info. of G.I. Sheet Ductwork & Accessories C1)
C01_7 d/w - 10h/d - No HK 0 23-Mar-22 A 23-Mar-22 A 13-May-22 13-May-22
Hols - No B/O periods (was
310.D.WS.L996.38aB02Obtain "No objection" of G.I. Sheet Ductwork & Accessories C1)
C01_7 d/w - 10h/d - No HK 0 23-Mar-22 A 23-Mar-22 A 13-May-22 13-May-22
Hols - No B/O periods (was
Refrigerant Pipework & Fittings C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was07-Apr-22
C1) 12-Jun-22 26-Apr-22 01-Jul-22 19
310.D.WS.L992.39aB02Prepare and submit info. of Refrigerant Pipework & Fittings C01_7 d/w - 10h/d - No HK 25 07-Apr-22 01-May-22 26-Apr-22 20-May-22 19
Hols - No B/O periods (was
310.D.WS.L993.39aB02Review and comment info. of Refrigerant Pipework & Fittings C1)
C01_7 d/w - 10h/d - No HK 24 02-May-22 25-May-22 21-May-22 13-Jun-22 19
Hols - No B/O periods (was
310.D.WS.L994.39aB02Prepare and re-submit info. of Refrigerant Pipework & Fittings C1)
C01_7 d/w - 10h/d - No HK 9 26-May-22 03-Jun-22 14-Jun-22 22-Jun-22 19
Hols - No B/O periods (was
310.D.WS.L996.39aB02Obtain "No objection" of Refrigerant Pipework & Fittings C1)
C01_7 d/w - 10h/d - No HK 9 04-Jun-22 12-Jun-22 23-Jun-22 01-Jul-22 19
Hols - No B/O periods (was
C1)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 97 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
Fire Services C01_7 d/w - 10h/d - No HK Hols219
- No B/O periods
0 (was10-Apr-22
C1) 14-Nov-22 22-May-22 02-Feb-23 80
Hose Reel Set C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was30-Apr-22
C1) 05-Jul-22 01-Jul-22 05-Sep-22 62
310.D.WS.L992.40aB02Prepare and submit info. of Hose Reel Set C01_7 d/w - 10h/d - No HK 25 30-Apr-22 24-May-22 01-Jul-22 25-Jul-22 62
Hols - No B/O periods (was
310.D.WS.L993.40aB02Review and comment info. of Hose Reel Set C1)
C01_7 d/w - 10h/d - No HK 24 25-May-22 17-Jun-22 26-Jul-22 18-Aug-22 62
Hols - No B/O periods (was
310.D.WS.L994.40aB02Prepare and re-submit info. of Hose Reel Set C1)
C01_7 d/w - 10h/d - No HK 9 18-Jun-22 26-Jun-22 19-Aug-22 27-Aug-22 62
Hols - No B/O periods (was
310.D.WS.L996.40aB02Obtain "No objection" of Hose Reel Set C1)
C01_7 d/w - 10h/d - No HK 9 27-Jun-22 05-Jul-22 28-Aug-22 05-Sep-22 62
Hols - No B/O periods (was
Fire Hydrant C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was30-Apr-22
C1) 05-Jul-22 01-Jul-22 05-Sep-22 62
310.D.WS.L992.41aB02Prepare and submit info. of Fire Hydrant C01_7 d/w - 10h/d - No HK 25 30-Apr-22 24-May-22 01-Jul-22 25-Jul-22 62
Hols - No B/O periods (was
310.D.WS.L993.41aB02Review and comment info. of Fire Hydrant C1)
C01_7 d/w - 10h/d - No HK 24 25-May-22 17-Jun-22 26-Jul-22 18-Aug-22 62
Hols - No B/O periods (was
310.D.WS.L994.41aB02Prepare and re-submit info. of Fire Hydrant C1)
C01_7 d/w - 10h/d - No HK 9 18-Jun-22 26-Jun-22 19-Aug-22 27-Aug-22 62
Hols - No B/O periods (was
310.D.WS.L996.41aB02Obtain "No objection" of Fire Hydrant C1)
C01_7 d/w - 10h/d - No HK 9 27-Jun-22 05-Jul-22 28-Aug-22 05-Sep-22 62
Hols - No B/O periods (was
MCC/ LMCP C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was14-May-22
C1) 19-Jul-22 01-Jul-22 05-Sep-22 48
310.D.WS.L992.43aB02Prepare and submit info. of MCC/ LMCP C01_7 d/w - 10h/d - No HK 25 14-May-22 07-Jun-22 01-Jul-22 25-Jul-22 48
Hols - No B/O periods (was
310.D.WS.L993.43aB02Review and comment info. of MCC/ LMCP C1)
C01_7 d/w - 10h/d - No HK 24 08-Jun-22 01-Jul-22 26-Jul-22 18-Aug-22 48
Hols - No B/O periods (was
310.D.WS.L994.43aB02Prepare and re-submit info. of MCC/ LMCP C1)
C01_7 d/w - 10h/d - No HK 9 02-Jul-22 10-Jul-22 19-Aug-22 27-Aug-22 48
Hols - No B/O periods (was
310.D.WS.L996.43aB02Obtain "No objection" of MCC/ LMCP C1)
C01_7 d/w - 10h/d - No HK 9 11-Jul-22 19-Jul-22 28-Aug-22 05-Sep-22 48
Hols - No B/O periods (was
FS Jockey Pump C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was29-May-22
C1) 03-Aug-22 01-Jul-22 05-Sep-22 33
310.D.WS.L992.45aB02Prepare and submit info. of FS Jockey Pump C01_7 d/w - 10h/d - No HK 25 29-May-22 22-Jun-22 01-Jul-22 25-Jul-22 33
Hols - No B/O periods (was
310.D.WS.L993.45aB02Review and comment info. of FS Jockey Pump C1)
C01_7 d/w - 10h/d - No HK 24 23-Jun-22 16-Jul-22 26-Jul-22 18-Aug-22 33
Hols - No B/O periods (was
310.D.WS.L994.45aB02Prepare and re-submit info. of FS Jockey Pump C1)
C01_7 d/w - 10h/d - No HK 9 17-Jul-22 25-Jul-22 19-Aug-22 27-Aug-22 33
Hols - No B/O periods (was
310.D.WS.L996.45aB02Obtain "No objection" of FS Jockey Pump C1)
C01_7 d/w - 10h/d - No HK 9 26-Jul-22 03-Aug-22 28-Aug-22 05-Sep-22 33
Hols - No B/O periods (was
Fixed Foam System Water Pump C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was29-May-22
C1) 03-Aug-22 28-Nov-22 02-Feb-23 183
310.D.WS.L992.46aB02Prepare and submit info. of Fixed Foam System Water Pump C01_7 d/w - 10h/d - No HK 25 29-May-22 22-Jun-22 28-Nov-22 22-Dec-22 183
Hols - No B/O periods (was
310.D.WS.L993.46aB02Review and comment info. of Fixed Foam System Water Pump C1)
C01_7 d/w - 10h/d - No HK 24 23-Jun-22 16-Jul-22 23-Dec-22 15-Jan-23 183
Hols - No B/O periods (was
310.D.WS.L994.46aB02Prepare and re-submit info. of Fixed Foam System Water Pump C1)
C01_7 d/w - 10h/d - No HK 9 17-Jul-22 25-Jul-22 16-Jan-23 24-Jan-23 183
Hols - No B/O periods (was
310.D.WS.L996.46aB02Obtain "No objection" of Fixed Foam System Water Pump C1)
C01_7 d/w - 10h/d - No HK 9 26-Jul-22 03-Aug-22 25-Jan-23 02-Feb-23 183
Hols - No B/O periods (was
G.I. Pipe & Fittings C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was22-May-22
C1) 27-Jul-22 01-Jul-22 05-Sep-22 40
310.D.WS.L992.48aB02Prepare and submit info. of G.I. Pipe & Fittings C01_7 d/w - 10h/d - No HK 25 22-May-22 15-Jun-22 01-Jul-22 25-Jul-22 40
Hols - No B/O periods (was
310.D.WS.L993.48aB02Review and comment info. of G.I. Pipe & Fittings C1)
C01_7 d/w - 10h/d - No HK 24 16-Jun-22 09-Jul-22 26-Jul-22 18-Aug-22 40
Hols - No B/O periods (was
C1)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 98 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L994.48aB02Prepare and re-submit info. of G.I. Pipe & Fittings C01_7 d/w - 10h/d - No HK 9 10-Jul-22 18-Jul-22 19-Aug-22 27-Aug-22 40
Hols - No B/O periods (was
310.D.WS.L996.48aB02Obtain "No objection" of G.I. Pipe & Fittings C1)
C01_7 d/w - 10h/d - No HK 9 19-Jul-22 27-Jul-22 28-Aug-22 05-Sep-22 40
Hols - No B/O periods (was
Automatic Fire Alarm Control Panel C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was10-Apr-22
C1) 15-Jun-22 22-May-22 27-Jul-22 42
310.D.WS.L992.49aB02Prepare and submit info. of Automatic Fire Alarm Control Panel C01_7 d/w - 10h/d - No HK 25 10-Apr-22 04-May-22 22-May-22 15-Jun-22 42
Hols - No B/O periods (was
310.D.WS.L993.49aB02Review and comment info. of Automatic Fire Alarm Control Panel C1)
C01_7 d/w - 10h/d - No HK 24 05-May-22 28-May-22 16-Jun-22 09-Jul-22 42
Hols - No B/O periods (was
310.D.WS.L994.49aB02Prepare and re-submit info. of Automatic Fire Alarm Control Panel C1)
C01_7 d/w - 10h/d - No HK 9 29-May-22 06-Jun-22 10-Jul-22 18-Jul-22 42
Hols - No B/O periods (was
310.D.WS.L996.49aB02Obtain "No objection" of Automatic Fire Alarm Control Panel C1)
C01_7 d/w - 10h/d - No HK 9 07-Jun-22 15-Jun-22 19-Jul-22 27-Jul-22 42
Hols - No B/O periods (was
Gas Flooding System C1)
C01_7 d/w - 10h/d - No HK Hols46
- No B/O periods
0 (was13-Apr-22
C1) 28-May-22 22-Jul-22 05-Sep-22 100
310.D.WS.L992.50aB02Prepare and submit info. of Gas Flooding System C01_7 d/w - 10h/d - No HK 14 13-Apr-22 26-Apr-22 22-Jul-22 04-Aug-22 100
Hols - No B/O periods (was
310.D.WS.L993.50aB02Review and comment info. of Gas Flooding System C1)
C01_7 d/w - 10h/d - No HK 14 27-Apr-22 10-May-22 05-Aug-22 18-Aug-22 100
Hols - No B/O periods (was
310.D.WS.L994.50aB02Prepare and re-submit info. of Gas Flooding System C1)
C01_7 d/w - 10h/d - No HK 9 11-May-22 19-May-22 19-Aug-22 27-Aug-22 100
Hols - No B/O periods (was
310.D.WS.L996.50aB02Obtain "No objection" of Gas Flooding System C1)
C01_7 d/w - 10h/d - No HK 9 20-May-22 28-May-22 28-Aug-22 05-Sep-22 100
Hols - No B/O periods (was
Smoke Detector C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was10-May-22
C1) 15-Jul-22 29-Jun-22 03-Sep-22 50
310.D.WS.L992.53aB02Prepare and submit info. of Smoke Detector C01_7 d/w - 10h/d - No HK 25 10-May-22 03-Jun-22 29-Jun-22 23-Jul-22 50
Hols - No B/O periods (was
310.D.WS.L993.53aB02Review and comment info. of Smoke Detector C1)
C01_7 d/w - 10h/d - No HK 24 04-Jun-22 27-Jun-22 24-Jul-22 16-Aug-22 50
Hols - No B/O periods (was
310.D.WS.L994.53aB02Prepare and re-submit info. of Smoke Detector C1)
C01_7 d/w - 10h/d - No HK 9 28-Jun-22 06-Jul-22 17-Aug-22 25-Aug-22 50
Hols - No B/O periods (was
310.D.WS.L996.53aB02Obtain "No objection" of Smoke Detector C1)
C01_7 d/w - 10h/d - No HK 9 07-Jul-22 15-Jul-22 26-Aug-22 03-Sep-22 50
Hols - No B/O periods (was
Heat Detector C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was24-Jun-22
C1) 29-Aug-22 01-Jul-22 05-Sep-22 7
310.D.WS.L992.54aB02Prepare and submit info. of Heat Detector C01_7 d/w - 10h/d - No HK 25 24-Jun-22 18-Jul-22 01-Jul-22 25-Jul-22 7
Hols - No B/O periods (was
310.D.WS.L993.54aB02Review and comment info. of Heat Detector C1)
C01_7 d/w - 10h/d - No HK 24 19-Jul-22 11-Aug-22 26-Jul-22 18-Aug-22 7
Hols - No B/O periods (was
310.D.WS.L994.54aB02Prepare and re-submit info. of Heat Detector C1)
C01_7 d/w - 10h/d - No HK 9 12-Aug-22 20-Aug-22 19-Aug-22 27-Aug-22 7
Hols - No B/O periods (was
310.D.WS.L996.54aB02Obtain "No objection" of Heat Detector C1)
C01_7 d/w - 10h/d - No HK 9 21-Aug-22 29-Aug-22 28-Aug-22 05-Sep-22 7
Hols - No B/O periods (was
Cable Tray & Accessories C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was24-Jun-22
C1) 29-Aug-22 01-Jul-22 05-Sep-22 7
310.D.WS.L992.55aB02Prepare and submit info. of Cable Tray & Accessories C01_7 d/w - 10h/d - No HK 25 24-Jun-22 18-Jul-22 01-Jul-22 25-Jul-22 7
Hols - No B/O periods (was
310.D.WS.L993.55aB02Review and comment info. of Cable Tray & Accessories C1)
C01_7 d/w - 10h/d - No HK 24 19-Jul-22 11-Aug-22 26-Jul-22 18-Aug-22 7
Hols - No B/O periods (was
310.D.WS.L994.55aB02Prepare and re-submit info. of Cable Tray & Accessories C1)
C01_7 d/w - 10h/d - No HK 9 12-Aug-22 20-Aug-22 19-Aug-22 27-Aug-22 7
Hols - No B/O periods (was
310.D.WS.L996.55aB02Obtain "No objection" of Cable Tray & Accessories C1)
C01_7 d/w - 10h/d - No HK 9 21-Aug-22 29-Aug-22 28-Aug-22 05-Sep-22 7
Hols - No B/O periods (was
Linear Heat Detector C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was09-Sep-22
C1) 14-Nov-22 28-Nov-22 02-Feb-23 80

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 99 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L992.57aB02Prepare and submit info. of Linear Heat Detector C01_7 d/w - 10h/d - No HK 25 09-Sep-22 03-Oct-22 28-Nov-22 22-Dec-22 80
Hols - No B/O periods (was
310.D.WS.L993.57aB02Review and comment info. of Linear Heat Detector C1)
C01_7 d/w - 10h/d - No HK 24 04-Oct-22 27-Oct-22 23-Dec-22 15-Jan-23 80
Hols - No B/O periods (was
310.D.WS.L994.57aB02Prepare and re-submit info. of Linear Heat Detector C1)
C01_7 d/w - 10h/d - No HK 9 28-Oct-22 05-Nov-22 16-Jan-23 24-Jan-23 80
Hols - No B/O periods (was
310.D.WS.L996.57aB02Obtain "No objection" of Linear Heat Detector C1)
C01_7 d/w - 10h/d - No HK 9 06-Nov-22 14-Nov-22 25-Jan-23 02-Feb-23 80
Hols - No B/O periods (was
PLC C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was11-May-22
C1) 16-Jul-22 29-Jun-22 03-Sep-22 49
310.D.WS.L992.58aB02Prepare and submit info. of PLC C01_7 d/w - 10h/d - No HK 25 11-May-22 04-Jun-22 29-Jun-22 23-Jul-22 49
Hols - No B/O periods (was
310.D.WS.L993.58aB02Review and comment info. of PLC C1)
C01_7 d/w - 10h/d - No HK 24 05-Jun-22 28-Jun-22 24-Jul-22 16-Aug-22 49
Hols - No B/O periods (was
310.D.WS.L994.58aB02Prepare and re-submit info. of PLC C1)
C01_7 d/w - 10h/d - No HK 9 29-Jun-22 07-Jul-22 17-Aug-22 25-Aug-22 49
Hols - No B/O periods (was
310.D.WS.L996.58aB02Obtain "No objection" of PLC C1)
C01_7 d/w - 10h/d - No HK 9 08-Jul-22 16-Jul-22 26-Aug-22 03-Sep-22 49
Hols - No B/O periods (was
Plumbing and Drainage C1)
C01_7 d/w - 10h/d - No HK Hols215
- No B/O periods
0 (was27-Mar-22
C1) 27-Oct-22 28-Mar-22 02-Feb-23 98
Fibreglass Tank C01_7 d/w - 10h/d - No HK Hols57
- No B/O periods
0 (was27-Mar-22
C1) 22-May-22 28-Mar-22 23-May-22 1
310.D.WS.L992.59aB02Prepare and submit info. of Fribreglass Tank C01_7 d/w - 10h/d - No HK 18 27-Mar-22 13-Apr-22 28-Mar-22 14-Apr-22 1
Hols - No B/O periods (was
310.D.WS.L993.59aB02Review and comment info. of Fribreglass Tank C1)
C01_7 d/w - 10h/d - No HK 21 14-Apr-22 04-May-22 15-Apr-22 05-May-22 1
Hols - No B/O periods (was
310.D.WS.L994.59aB02Prepare and re-submit info. of Fribreglass Tank C1)
C01_7 d/w - 10h/d - No HK 9 05-May-22 13-May-22 06-May-22 14-May-22 1
Hols - No B/O periods (was
310.D.WS.L996.59aB02Obtain "No objection" of Fribreglass Tank C1)
C01_7 d/w - 10h/d - No HK 9 14-May-22 22-May-22 15-May-22 23-May-22 1
Hols - No B/O periods (was
Ductile Iron Pipe & Accessories C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was30-Apr-22
C1) 05-Jul-22 28-Nov-22 02-Feb-23 212
310.D.WS.L992.64aB02Prepare and submit info. of Ductile Iron Pipe & Accessories C01_7 d/w - 10h/d - No HK 25 30-Apr-22 24-May-22 28-Nov-22 22-Dec-22 212
Hols - No B/O periods (was
310.D.WS.L993.64aB02Review and comment info. of Ductile Iron Pipe & Accessories C1)
C01_7 d/w - 10h/d - No HK 24 25-May-22 17-Jun-22 23-Dec-22 15-Jan-23 212
Hols - No B/O periods (was
310.D.WS.L994.64aB02Prepare and re-submit info. of Ductile Iron Pipe & Accessories C1)
C01_7 d/w - 10h/d - No HK 9 18-Jun-22 26-Jun-22 16-Jan-23 24-Jan-23 212
Hols - No B/O periods (was
310.D.WS.L996.64aB02Obtain "No objection" of Ductile Iron Pipe & Accessories C1)
C01_7 d/w - 10h/d - No HK 9 27-Jun-22 05-Jul-22 25-Jan-23 02-Feb-23 212
Hols - No B/O periods (was
Epoxy Cast Iron Pipe & Accessories C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was30-Apr-22
C1) 05-Jul-22 01-Jul-22 05-Sep-22 62
310.D.WS.L992.65aB02Prepare and submit info. of Epoxy Cast Iron Pipe & Accessories C01_7 d/w - 10h/d - No HK 25 30-Apr-22 24-May-22 01-Jul-22 25-Jul-22 62
Hols - No B/O periods (was
310.D.WS.L993.65aB02Review and comment info. of Epoxy Cast Iron Pipe & Accessories C1)
C01_7 d/w - 10h/d - No HK 24 25-May-22 17-Jun-22 26-Jul-22 18-Aug-22 62
Hols - No B/O periods (was
310.D.WS.L994.65aB02Prepare and re-submit info. of Epoxy Cast Iron Pipe & Accessories C1)
C01_7 d/w - 10h/d - No HK 9 18-Jun-22 26-Jun-22 19-Aug-22 27-Aug-22 62
Hols - No B/O periods (was
310.D.WS.L996.65aB02Obtain "No objection" of Epoxy Cast Iron Pipe & Accessories C1)
C01_7 d/w - 10h/d - No HK 9 27-Jun-22 05-Jul-22 28-Aug-22 05-Sep-22 62
Hols - No B/O periods (was
Local Motor Control Panel C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was13-Jun-22
C1) 18-Aug-22 28-Nov-22 02-Feb-23 168
310.D.WS.L992.66aB02Prepare and submit info. of Local Motor Control Panel C01_7 d/w - 10h/d - No HK 25 13-Jun-22 07-Jul-22 28-Nov-22 22-Dec-22 168
Hols - No B/O periods (was
310.D.WS.L993.66aB02Review and comment info. of Local Motor Control Panel C1)
C01_7 d/w - 10h/d - No HK 24 08-Jul-22 31-Jul-22 23-Dec-22 15-Jan-23 168
Hols - No B/O periods (was
C1)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 100 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L994.66aB02Prepare and re-submit info. of Local Motor Control Panel C01_7 d/w - 10h/d - No HK 9 01-Aug-22 09-Aug-22 16-Jan-23 24-Jan-23 168
Hols - No B/O periods (was
310.D.WS.L996.66aB02Obtain "No objection" of Local Motor Control Panel C1)
C01_7 d/w - 10h/d - No HK 9 10-Aug-22 18-Aug-22 25-Jan-23 02-Feb-23 168
Hols - No B/O periods (was
Sump Pump C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was22-Aug-22
C1) 27-Oct-22 28-Nov-22 02-Feb-23 98
310.D.WS.L992.67aB02Prepare and submit info. of Sump Pump C01_7 d/w - 10h/d - No HK 25 22-Aug-22 15-Sep-22 28-Nov-22 22-Dec-22 98
Hols - No B/O periods (was
310.D.WS.L993.67aB02Review and comment info. of Sump Pump C1)
C01_7 d/w - 10h/d - No HK 24 16-Sep-22 09-Oct-22 23-Dec-22 15-Jan-23 98
Hols - No B/O periods (was
310.D.WS.L994.67aB02Prepare and re-submit info. of Sump Pump C1)
C01_7 d/w - 10h/d - No HK 9 10-Oct-22 18-Oct-22 16-Jan-23 24-Jan-23 98
Hols - No B/O periods (was
310.D.WS.L996.67aB02Obtain "No objection" of Sump Pump C1)
C01_7 d/w - 10h/d - No HK 9 19-Oct-22 27-Oct-22 25-Jan-23 02-Feb-23 98
Hols - No B/O periods (was
CC#06 - General - MEP - Method Statement C1)
C01_7 d/w - 10h/d - No HK Hols260
- No B/O periods
0 (was27-Mar-22
C1) 11-Dec-22 18-May-22 21-Feb-23 72
ELECT C01_7 d/w - 10h/d - No HK Hols210
- No B/O periods
0 (was27-Mar-22
C1) 22-Oct-22 26-Jun-22 21-Jan-23 91
310.D.WS.L984.05aB02 Prepare and submit Elect. Method Statement (15 nos.) C01_7 d/w - 10h/d - No HK 165 27-Mar-22 07-Sep-22 26-Jun-22 07-Dec-22 91
Hols - No B/O periods (was
310.D.WS.L985.05aB02 Review and comment Elect. Method Statement (15 nos.) C1)
C01_7 d/w - 10h/d - No HK 165 11-Apr-22 22-Sep-22 11-Jul-22 22-Dec-22 91
Hols - No B/O periods (was
310.D.WS.L986.05aB02 Prepare and re-submit Elect. Method Statement (15 nos.) C1)
C01_7 d/w - 10h/d - No HK 165 26-Apr-22 07-Oct-22 26-Jul-22 06-Jan-23 91
Hols - No B/O periods (was
310.D.WS.L988.05aB02 Obtain approval of Elect. Method Statement (15 nos.) C1)
C01_7 d/w - 10h/d - No HK 165 11-May-22 22-Oct-22 10-Aug-22 21-Jan-23 91
Hols - No B/O periods (was
MVAC C1)
C01_7 d/w - 10h/d - No HK Hols260
- No B/O periods
0 (was27-Mar-22
C1) 11-Dec-22 07-Jun-22 21-Feb-23 72
310.D.WS.L984.06aB02 Prepare and submit MVAC Method Statement (13 nos.) C01_7 d/w - 10h/d - No HK 215 27-Mar-22 27-Oct-22 07-Jun-22 07-Jan-23 72
Hols - No B/O periods (was
310.D.WS.L985.06aB02 Review and comment MVAC Method Statement (13 nos.) C1)
C01_7 d/w - 10h/d - No HK 215 11-Apr-22 11-Nov-22 22-Jun-22 22-Jan-23 72
Hols - No B/O periods (was
310.D.WS.L986.06aB02 Prepare and re-submit MVAC Method Statement (13 nos.) C1)
C01_7 d/w - 10h/d - No HK 215 26-Apr-22 26-Nov-22 07-Jul-22 06-Feb-23 72
Hols - No B/O periods (was
310.D.WS.L988.06aB02 Obtain approval of MVAC Method Statement (13 nos.) C1)
C01_7 d/w - 10h/d - No HK 215 11-May-22 11-Dec-22 22-Jul-22 21-Feb-23 72
Hols - No B/O periods (was
FS C1)
C01_7 d/w - 10h/d - No HK Hols138
- No B/O periods
0 (was01-May-22
C1) 15-Sep-22 18-May-22 02-Oct-22 17
310.D.WS.L984.07aB02 Prepare and submit FS Method Statement (12 nos.) C01_7 d/w - 10h/d - No HK 93 01-May-22 01-Aug-22 18-May-22 18-Aug-22 17
Hols - No B/O periods (was
310.D.WS.L985.07aB02 Review and comment FS Method Statement (12 nos.) C1)
C01_7 d/w - 10h/d - No HK 93 16-May-22 16-Aug-22 02-Jun-22 02-Sep-22 17
Hols - No B/O periods (was
310.D.WS.L986.07aB02 Prepare and re-submit FS Method Statement (12 nos.) C1)
C01_7 d/w - 10h/d - No HK 93 31-May-22 31-Aug-22 17-Jun-22 17-Sep-22 17
Hols - No B/O periods (was
310.D.WS.L988.07aB02 Obtain approval of FS Method Statement (12 nos.) C1)
C01_7 d/w - 10h/d - No HK 93 15-Jun-22 15-Sep-22 02-Jul-22 02-Oct-22 17
Hols - No B/O periods (was
P&D C1)
C01_7 d/w - 10h/d - No HK Hols199
- No B/O periods
0 (was27-Mar-22
C1) 11-Oct-22 29-Jun-22 13-Jan-23 94
310.D.WS.L984.08aB02 Prepare and submit P&D Method Statement (5 nos.) C01_7 d/w - 10h/d - No HK 154 27-Mar-22 27-Aug-22 29-Jun-22 29-Nov-22 94
Hols - No B/O periods (was
310.D.WS.L985.08aB02 Review and comment P&D Method Statement (5 nos.) C1)
C01_7 d/w - 10h/d - No HK 154 11-Apr-22 11-Sep-22 14-Jul-22 14-Dec-22 94
Hols - No B/O periods (was
310.D.WS.L986.08aB02 Prepare and re-submit P&D Method Statement (5 nos.) C1)
C01_7 d/w - 10h/d - No HK 154 26-Apr-22 26-Sep-22 29-Jul-22 29-Dec-22 94
Hols - No B/O periods (was
310.D.WS.L988.08aB02 Obtain approval of P&D Method Statement (5 nos.) C1)
C01_7 d/w - 10h/d - No HK 154 11-May-22 11-Oct-22 13-Aug-22 13-Jan-23 94
Hols - No B/O periods (was
CC#06 ----- Procurement ----- C1)
C01_7 d/w - 10h/d - No HK Hols484
- No B/O periods
0 (was
30-Oct-21
C1) A 31-Jan-23 28-Mar-22 09-Feb-23 9

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 101 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
CC#06 - Subletting - East Vehicular Tunnel (EVT) C01_7 d/w - 10h/d - No HK Hols300
- No B/O periods
0 (was
30-Oct-21
C1) A 31-Jul-22 28-Mar-22 23-Dec-22 145
310.P.EX.H198 Subletting - EVT, Plant A & Plant C MEP - Award sub-contract C01_7 d/w - 10h/d - No HK 90 30-Oct-21 A 18-Jan-22 A 17-Jun-22 17-Jun-22
Hols - No B/O periods (was
310.P.EX.H140 Subletting - EVT - Earthwork - Stage 1&2 Preparation,Submission& C1)
C01_7 d/w - 10h/d - No HK 90 04-Dec-21 A 14-Apr-22 28-Apr-22 16-May-22 32
Approval,Tender&Award sub-contract Hols - No B/O periods (was
310.P.EX.H206 Subletting - ABWF (Plastering) - Stage 1&2 Preparation,Submission& C1)
C01_7 d/w - 10h/d - No HK 90 03-Jan-22 A 20-Apr-22 02-Apr-22 26-Apr-22 6
Approval,Tender&Award sub-contract Hols - No B/O periods (was
310.P.EX.H227.B01 Subletting - ABWF (Painting) - Stage 1&2 Preparation,Submission& C1)
C01_7 d/w - 10h/d - No HK 90 03-Jan-22 A 25-Apr-22 28-Mar-22 26-Apr-22 1
Approval,Tender&Award sub-contract Hols - No B/O periods (was
310.P.EX.H231.B01 Subletting - ABWF (Door) - Stage 1&2 Preparation,Submission& Approval,Tender&Award C1)
C01_7 d/w - 10h/d - No HK 90 03-Jan-22 A 25-Apr-22 28-Mar-22 26-Apr-22 1
sub-contract Hols - No B/O periods (was
310.P.EX.H235.B01 Subletting - ABWF (Louver,Window,etc) - Stage 1&2 Preparation,Submission& C1)
C01_7 d/w - 10h/d - No HK 90 03-Jan-22 A 25-Apr-22 28-Mar-22 26-Apr-22 1
Approval,Tender&Award sub-contract Hols - No B/O periods (was
310.P.EX.H239.B01 Subletting - ABWF (Steel&Metal) - Stage 1&2 Preparation,Submission& C1)
C01_7 d/w - 10h/d - No HK 90 03-Jan-22 A 25-Apr-22 28-Mar-22 26-Apr-22 1
Approval,Tender&Award sub-contract Hols - No B/O periods (was
310.P.EX.H188 Subletting - EVT - RC Structural Works - Stage 1&2 Preparation,Submission& C1)
C01_7 d/w - 10h/d - No HK 90 03-May-22 31-Jul-22 25-Sep-22 23-Dec-22 145
Approval,Tender&Award sub-contract Hols - No B/O periods (was
310.P.EX.H222 Subletting - EVT - Waterproofing - Stage 1&2 Preparation,Submission& C1)
C01_7 d/w - 10h/d - No HK 90 03-May-22 31-Jul-22 25-Sep-22 23-Dec-22 145
Approval,Tender&Award sub-contract Hols - No B/O periods (was
310.P.EX.H164 Subletting - EVT - Plant Building RC Works - Stage 1&2 Preparation,Submission& C1)
C01_7 d/w - 10h/d - No HK 90 03-May-22 31-Jul-22 30-May-22 27-Aug-22 27
Approval,Tender&Award sub-contract Hols - No B/O periods (was
CC#06 - Procurement - East Vehicular Tunnel (EVT) C1)
C01_7 d/w - 10h/d - No HK Hols265
- No B/O periods
0 (was12-May-22
C1) 31-Jan-23 27-Jul-22 09-Feb-23 9
EVT - Procurement - MEP C01_7 d/w - 10h/d - No HK Hols265
- No B/O periods
0 (was12-May-22
C1) 31-Jan-23 28-Jul-22 09-Feb-23 9
310.P.RC.D435 EVT - (Procurement Electrical & MVAC and Other Materials) - Place Order for Material C01_7 d/w - 10h/d - No HK 50 12-May-22 30-Jun-22 23-Aug-22 11-Oct-22 103
Hols - No B/O periods (was
310.P.RC.D443 EVT - (Procurement Electrical & MVAC and Other Materials) - Manufacturing of Material C1)
C01_7 d/w - 10h/d - No HK 150 19-May-22 15-Oct-22 30-Aug-22 26-Jan-23 103
Hols - No B/O periods (was
310.P.RC.D431 EVT - (Procurement FS and P&D Materials) - Place Order for Material C1)
C01_7 d/w - 10h/d - No HK 190 16-Jun-22 22-Dec-22 28-Jul-22 02-Feb-23 42
Hols - No B/O periods (was
310.P.RC.D439 EVT - (Procurement FS and P&D Materials) - Manufacturing of Material C1)
C01_7 d/w - 10h/d - No HK 190 26-Jul-22 31-Jan-23 04-Aug-22 09-Feb-23 9
Hols - No B/O periods (was
310.P.RC.D447 EVT - (Procurement) - Delivery of Material C1)
C01_7 d/w - 10h/d - No HK 14 18-Jan-23 31-Jan-23 27-Jan-23 09-Feb-23 9
Hols - No B/O periods (was
EVT - Procurement - ABWF C1)
C01_7 d/w - 10h/d - No HK Hols134
- No B/O periods
0 (was19-Jul-22
C1) 29-Nov-22 27-Jul-22 07-Dec-22 8
310.P.RC.D427 EVT - (Procurement ABWF) - Place Order for Materials C01_7 d/w - 10h/d - No HK 7 19-Jul-22 25-Jul-22 27-Jul-22 02-Aug-22 8
Hols - No B/O periods (was
310.P.RC.D451 EVT - (Procurement ABWF) - Manufacturing of Materials C1)
C01_7 d/w - 10h/d - No HK 120 26-Jul-22 22-Nov-22 03-Aug-22 30-Nov-22 8
Hols - No B/O periods (was
310.P.RC.D459 EVT - (Procurement ABWF) - Delivery of Materials C1)
C01_7 d/w - 10h/d - No HK 7 23-Nov-22 29-Nov-22 01-Dec-22 07-Dec-22 8
Hols - No B/O periods (was
CC#06 ----- Construction ----- C1) 856 287 07-Jun-21 A 22-Apr-24 07-Mar-22 27-Jul-24 79
CC#06 - East Vehicular Tunnel - EVT (HYBRID METHOD) 856 272 07-Jun-21 A 22-Apr-24 07-Mar-22 27-Jul-24 79
CC#06 - EVT - Site Preparation and Establishment C11_6 d/w - 10h/d - With HK Hols
394- No B/O 0periods (was
07-Jun-21
C3) A 29-Sep-22 07-Mar-22 11-Jan-23 84
310.C.EX.H093 EVT - tentative date of closure of existing N-Runway C11_6 d/w - 10h/d - With 0 01-Sep-22 01-Sep-22 1
HK Hols - No B/O periods
CC#06 - EVT - 3310/3 Site Preparation and Establishment (was C3)
C11_6 d/w - 10h/d - With HK Hols
394- No B/O 0periods (was
07-Jun-21
C3) A 29-Sep-22 16-Sep-22 05-Nov-22 30
310.C.EX.H021 EVT - 3310/3 - access to Works Area C11_6 d/w - 10h/d - With 0 07-Jun-21 A 16-Sep-22
HK Hols - No B/O periods
310.C.EX.H034 EVT - 3310/3 - carry out condition survey and reporting (was
C11_6C3)
d/w - 10h/d - With 6 01-Sep-22 07-Sep-22 10-Oct-22 15-Oct-22 30
HK Hols - No B/O periods
(was C3)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 102 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.EX.H030 EVT - 3310/3 - instrumentation works C11_6 d/w - 10h/d - With 24 01-Sep-22 29-Sep-22 16-Sep-22 15-Oct-22 12
HK Hols - No B/O periods
310.C.EX.H026 EVT - 3310/3 - underground utilities survey and reporting + carry out topographic survey (was
C11_6C3)
d/w - 10h/d - With 6 03-Sep-22 12-Sep-22 31-Oct-22 05-Nov-22 46
and reporting HK Hols - No B/O periods
CC#06 - EVT - 3310/6 Site Preparation and Establishment (was
C11_6C3)
d/w - 10h/d - With HK Hols
266- No B/O 0periods (was
07-Jun-21
C3) A 28-Apr-22 14-Apr-22 11-Jan-23 212
310.C.EX.H049 EVT - 3310/6 - access to Works Area C11_6 d/w - 10h/d - With 0 07-Jun-21 A 14-Apr-22
HK Hols - No B/O periods
310.C.EX.H054 EVT - 3310/6 - underground utilities survey and reporting + carry out topographic survey (was
C11_6C3)
d/w - 10h/d - With 6 29-Jun-21 A 06-Jul-21 A 22-May-22 22-May-22
and reporting HK Hols - No B/O periods
310.C.EX.H062 EVT - 3310/6 - carry out condition survey and reporting (was
C11_6C3)
d/w - 10h/d - With 6 07-Jul-21 A 13-Jul-21 A 11-Jan-23 11-Jan-23
HK Hols - No B/O periods
310.C.EX.H058 EVT - 3310/6 - instrumentation works (was
C11_6C3)
d/w - 10h/d - With 24 28-Mar-22 28-Apr-22 14-Apr-22 16-May-22 14
HK Hols - No B/O periods
CC#06 - EVT - 3310/6C Site Preparation and Establishment (was
C11_6C3)
d/w - 10h/d - With HK Hols
24- No B/O 0periods (was
28-Mar-22
C3) 28-Apr-22 07-Mar-22 16-May-22 14
310.C.EX.H078 EVT - 3310/6C - access to Works Area C11_6 d/w - 10h/d - With 0 28-Mar-22* 07-Mar-22 -18
HK Hols - No B/O periods
310.C.EX.H082 EVT - 3310/6C - underground utilities survey and reporting (was
C11_6C3)
d/w - 10h/d - With 6 28-Mar-22 02-Apr-22 10-May-22 16-May-22 32
HK Hols - No B/O periods
310.C.EX.H090 EVT - 3310/6C - carry out condition survey and reporting (was
C11_6C3)
d/w - 10h/d - With 6 28-Mar-22 02-Apr-22 10-May-22 16-May-22 32
HK Hols - No B/O periods
310.C.EX.H086 EVT - 3310/6C - instrumentation works (was
C11_6C3)
d/w - 10h/d - With 24 28-Mar-22 28-Apr-22 14-Apr-22 16-May-22 14
HK Hols - No B/O periods
CC#06 - EVT - 3310/7 Site Preparation and Establishment (was
C11_6C3)
d/w - 10h/d - With HK Hols6 - No B/O 0periods (was
05-Sep-22
C3) 12-Sep-22 05-Sep-22 12-Sep-22 0
310.C.EX.H094 EVT - 3310/7 - access to Works Area C11_6 d/w - 10h/d - With 0 05-Sep-22 05-Sep-22 0
HK Hols - No B/O periods
310.C.EX.H102 EVT - 3310/7 - instrumentation works (was
C11_6C3)
d/w - 10h/d - With 6 05-Sep-22 12-Sep-22 05-Sep-22 12-Sep-22 0
HK Hols - No B/O periods
CC#06 - EVT - Existing UU - temporary support (and/or diversion as necessary) (was
C01_7C3)
d/w - 10h/d - No HK Hols168
- No B/O periods
0 (was27-Mar-22
C1) 10-Sep-22 22-May-22 05-Nov-22 56
Submissions and Application C01_7 d/w - 10h/d - No HK Hols155
- No B/O periods
0 (was27-Mar-22
C1) 28-Aug-22 22-May-22 24-Oct-22 56
310.C.EX.H913 UU Support Works - Prepare Presentation of Propose Temporary Diversion of Existing UU C01_7 d/w - 10h/d - No HK 45 27-Mar-22 10-May-22 22-May-22 06-Jul-22 56
to CAD Hols - No B/O periods (was
310.C.EX.H917 UU Support Works - PM 1st review Presentation of Propose Temporary Diversion of C1)
C01_7 d/w - 10h/d - No HK 28 11-May-22 07-Jun-22 06-Jul-22 03-Aug-22 56
Existing UU to CAD Hols - No B/O periods (was
310.C.EX.H921 UU Support Works - Revise Presentation of Propose Temporary Diversion of Existing UU C1)
C01_7 d/w - 10h/d - No HK 8 08-Jun-22 15-Jun-22 21-Aug-22 29-Aug-22 74
to CAD Hols - No B/O periods (was
310.C.EX.H933 UU Support Works - Method Statement C1)
C01_7 d/w - 10h/d - No HK 21 08-Jun-22 28-Jun-22 03-Aug-22 24-Aug-22 56
Hols - No B/O periods (was
310.C.EX.H1013 UU Support Works - PM 2nd review Presentation of Propose Temporary Diversion of C1)
C01_7 d/w - 10h/d - No HK 28 16-Jun-22 13-Jul-22 29-Aug-22 26-Sep-22 74
Existing UU to CAD Hols - No B/O periods (was
310.C.EX.H937 UU Support Works - PM 1st review and approved Method Statement C1)
C01_7 d/w - 10h/d - No HK 28 29-Jun-22 26-Jul-22 24-Aug-22 21-Sep-22 56
Hols - No B/O periods (was
310.C.EX.H1009 UU Support Works - Revise Method Statement C1)
C01_7 d/w - 10h/d - No HK 5 27-Jul-22 31-Jul-22 21-Sep-22 26-Sep-22 56
Hols - No B/O periods (was
310.C.EX.H1017 UU Support Works - PM 2nd review and approved Method Statement C1)
C01_7 d/w - 10h/d - No HK 28 01-Aug-22 28-Aug-22 26-Sep-22 24-Oct-22 56
Hols - No B/O periods (was
Existing UU - temporary support (and/or diversion as necessary) C1)
C01_7 d/w - 10h/d - No HK Hols13
- No B/O periods
0 (was29-Aug-22
C1) 10-Sep-22 24-Oct-22 05-Nov-22 56
310.C.EX.H947 UU temporary support and/ or Diversion Works - Work Permit C01_7 d/w - 10h/d - No HK 13 29-Aug-22 10-Sep-22 24-Oct-22 05-Nov-22 56
Hols - No B/O periods (was
CC#06 - EVT - Ground Investigation C1)
C11_6 d/w - 10h/d - With HK Hols
655- No B/O 4periods (was
27-Aug-21
C3) A 15-Nov-23 19-Apr-22 16-Dec-23 27
EVT - Instrumentation (before tunnel construction commence) C11_6 d/w - 10h/d - With HK Hols
10- No B/O 0periods (was
30-Sep-22
C3) 13-Oct-22 11-Jan-23 21-Jan-23 84

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 103 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.EX.H038 EVT - Install background ground surface markers [8 nos. @5d/no./wf; 4wf] C11_6 d/w - 10h/d - With 10 30-Sep-22 13-Oct-22 11-Jan-23 21-Jan-23 84
HK Hols - No B/O periods
EVT - Instrumentation (after tunnel construction complete) (was
C11_6C3)
d/w - 10h/d - With HK Hols
26- No B/O 0periods (was
16-Oct-23
C3) 15-Nov-23 17-Nov-23 16-Dec-23 27
310.C.EX.H042 EVT - install instruments outside tunnel [17 nos. @10d/nos; 3WF] C11_6 d/w - 10h/d - With 26 16-Oct-23 15-Nov-23 17-Nov-23 16-Dec-23 27
HK Hols - No B/O periods
EVT - GI for ELS Design (was
C11_6C3)
d/w - 10h/d - With HK Hols
320- No B/O 4periods (was
27-Aug-21
C3) A 29-Sep-22 19-Apr-22 30-Sep-22 1
310.C.EX.H046 EVT - GI for ELS design - Carry out GI (Zones 6 & 7) C11_6 d/w - 10h/d - With 21 2 27-Aug-21 A 11-Nov-21 A 19-Apr-22 19-Apr-22
HK Hols - No B/O periods
310.C.EX.H050 EVT - GI for ELS design - prepare report and submit (Zones 6 & 7) (was
C11_6C3)
d/w - 10h/d - With 3 11-Nov-21 A 14-Nov-21 A 19-Apr-22 19-Apr-22
HK Hols - No B/O periods
310.C.EX.H1233 EVT - GI for ELS design - Carry out GI (Other Zones) (was
C11_6C3)
d/w - 10h/d - With 21 2 01-Sep-22 26-Sep-22 02-Sep-22 27-Sep-22 1
HK Hols - No B/O periods
310.C.EX.H1237 EVT - GI for ELS design - prepare report and submit (Other Zones) (was
C11_6C3)
d/w - 10h/d - With 3 27-Sep-22 29-Sep-22 28-Sep-22 30-Sep-22 1
HK Hols - No B/O periods
CC#06 - EVT - VE+ELS Installation (was C3) 341 102 17-Apr-22 09-Jun-23 19-Apr-22 11-Jul-23 25
CC#06 - EVT - Zone 6 (3310/6, 6C) - ELS Stage 1 202 19 17-Apr-22 16-Dec-22 19-Apr-22 16-Dec-22 0
310.D.EX.H417 EVT - ELS design (Vertical Elements) - Prepare and submit Form BA8 and grant consent C01_7 d/w - 10h/d - No HK 7 17-Apr-22 23-Apr-22 19-Apr-22 25-Apr-22 2
Hols - No B/O periods (was
310.D.EX.H421 EVT - ELS design (Vertical Elements) - Prepare and submit Form BA10 to notify work C1)
C01_7 d/w - 10h/d - No HK 7 24-Apr-22 30-Apr-22 26-Apr-22 02-May-22 2
commencement Hols - No B/O periods (was
310.D.EX.H795.B02 ne 6 (3310/6,6c) - mobilization and preparation C1) d/w - 10h/d - With
C11_6 12 03-May-22 16-May-22 03-May-22 16-May-22 0
HK Hols - No B/O periods
310.C.EX.H126 EVT - Zone 6 (3310/6,6c) - ELS - Trial pile & install Pipe Pile (395nos. @2days/no./rig; (was
C11_6C3)
d/w - 10h/d - With 78 4 17-May-22 17-Aug-22 17-May-22 17-Aug-22 0
use 11 rigs) HK Hols - No B/O periods
310.C.EX.H126.B01 EVT - Zone 6 (3310/6,6c) - ELS - Install Sheet Pile (3,878m. @56m/d/rig; use 2 rigs) (was
C11_6C3)
d/w - 10h/d - With 38 3 05-Jul-22 17-Aug-22 05-Jul-22 17-Aug-22 0
HK Hols - No B/O periods
310.C.EX.H1037 EVT - Zone 6 (3310/6,6c) - ELS - Install wells (was
C11_6C3)
d/w - 10h/d - With 24 2 21-Jul-22 17-Aug-22 29-Aug-22 26-Sep-22 33
HK Hols - No B/O periods
310.C.EX.H1033 EVT - Zone 6 (3310/6,6c) - ELS - Submit Form BA14 (was
C01_7C3)
d/w - 10h/d - No HK 12 18-Aug-22 29-Aug-22 18-Aug-22 29-Aug-22 0
Hols - No B/O periods (was
310.C.EX.H1297 EVT - Zone 6 (3310/6,6c) - ELS - Pumping test and submit report C1)
C11_6 d/w - 10h/d - With 12 2 18-Aug-22 31-Aug-22 27-Sep-22 12-Oct-22 33
HK Hols - No B/O periods
310.C.EX.H1041 EVT - Zone 6 (3310/6,6c) - ELS - Submit Form BA8 for excavation (was
C01_7C3)
d/w - 10h/d - No HK 7 30-Aug-22 05-Sep-22 30-Aug-22 05-Sep-22 0
Hols - No B/O periods (was
310.C.EX.H1045 EVT - Zone 6 (3310/6,6c) - ELS - Submit Form BA10 for excavation C1)
C01_7 d/w - 10h/d - No HK 7 06-Sep-22 12-Sep-22 06-Sep-22 12-Sep-22 0
Hols - No B/O periods (was
310.C.EX.H985 EVT - Zone 6 (3310/6,6c) - ELS 1st layer, GL to +3mPD [22,950 @1000m3/d/wf, 4wf C1)
C11_6 d/w - 10h/d - With 24 2 13-Sep-22 12-Oct-22 13-Sep-22 12-Oct-22 0
+18d/layer of strut; 1 Layer] HK Hols - No B/O periods
310.C.EX.H985.B01 EVT - Zone 6 (3310/6,6c) - ELS - Remaining layer, +3mPD to FEL+ [68,850 (was
C11_6C3)
d/w - 10h/d - With 56 6 13-Oct-22 16-Dec-22 13-Oct-22 16-Dec-22 0
@1000m3/d/wf, 4wf +18d/layer of strut; 3 layers] HK Hols - No B/O periods
CC#06 - EVT - Zone 7 (3310/7) - ELS Stage 2 (was C3) 282 23 17-Apr-22 25-Mar-23 22-Aug-22 25-Mar-23 0
310.D.EX.H377 EVT - ELS design (Vertical Elements) - Prepare and submit Form BA8 and grant consent C01_7 d/w - 10h/d - No HK 7 17-Apr-22 23-Apr-22 22-Aug-22 28-Aug-22 127
Hols - No B/O periods (was
310.D.EX.H381 EVT - ELS design (Vertical Elements) - Prepare and submit Form BA10 to notify work C1)
C01_7 d/w - 10h/d - No HK 7 24-Apr-22 30-Apr-22 29-Aug-22 04-Sep-22 127
commencement Hols - No B/O periods (was
310.C.EX.H144 Site Access 3310/07 and Assumed Contract <3408> complete EVT (Northern Portion) C1)
C11_6 d/w - 10h/d - With 0 05-Sep-22 05-Sep-22 0
structure HK Hols - No B/O periods
310.C.EX.H146 EVT - Zone 7 (3310/7) - ELS - Install Sheet pile (8,201m. @56m/d/rig; use 2 rigs) (was
C11_6C3)
d/w - 10h/d - With 80 7 13-Sep-22 16-Dec-22 13-Sep-22 16-Dec-22 0
HK Hols - No B/O periods
310.C.EX.H1301 EVT - Zone 7 (3310/7) - ELS - Install wells (was
C11_6C3)
d/w - 10h/d - With 24 2 19-Nov-22 16-Dec-22 22-Dec-22 20-Jan-23 28
HK Hols - No B/O periods
(was C3)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 104 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.EX.H1049 EVT - Zone 7 (3310/7) - ELS - Submit Form BA14 C01_7 d/w - 10h/d - No HK 12 17-Dec-22 28-Dec-22 17-Dec-22 28-Dec-22 0
Hols - No B/O periods (was
310.C.EX.H1053 EVT - Zone 7 (3310/7) - ELS - Pumping test and submit report C1)
C11_6 d/w - 10h/d - With 12 2 17-Dec-22 31-Dec-22 21-Jan-23 07-Feb-23 28
HK Hols - No B/O periods
310.C.EX.H1057 EVT - Zone 7 (3310/7) - ELS - Submit Form BA8 for excavation (was
C01_7C3)
d/w - 10h/d - No HK 7 29-Dec-22 04-Jan-23 29-Dec-22 04-Jan-23 0
Hols - No B/O periods (was
310.C.EX.H1061 EVT - Zone 7 (3310/7) - ELS - Submit Form BA10 for excavation C1)
C01_7 d/w - 10h/d - No HK 7 05-Jan-23 11-Jan-23 05-Jan-23 11-Jan-23 0
Hols - No B/O periods (was
310.C.EX.H989 EVT - Zone 7 (3310/7) - ELS - 1st layer, GL to +3mPD [16,167m3 @600m3/d/wf; 2wf + C1)
C11_6 d/w - 10h/d - With 20 6 12-Jan-23 07-Feb-23 12-Jan-23 07-Feb-23 0
18d/layer of strut; 1 Layer] HK Hols - No B/O periods
310.C.EX.H989.B01 EVT - Zone 7 (3310/7) - ELS - Remaining 2 layer,+3mPD to FEL+ (was
C11_6C3)
d/w - 10h/d - With 40 6 08-Feb-23 25-Mar-23 08-Feb-23 25-Mar-23 0
PLT[32,333m3@600m3/d/wf; 2wf+18d/layer of strut; 2 Layers] HK Hols - No B/O periods
CC#06 - EVT - Zones 1-5 (3310/3) - ELS Stage 3 (Start after North Runway closure) (was C3) 228 60 01-Sep-22 09-Jun-23 16-Sep-22 11-Jul-23 25
CC#06 - EVT - Zone 1 (3310/3) - ELS 170 11 01-Sep-22 27-Mar-23 09-Dec-22 11-Jul-23 83
310.C.EX.H109 EVT - Zone 1 (3310/3) - Mobilization + instrumentation C11_6 d/w - 10h/d - With 24 01-Sep-22 29-Sep-22 09-Dec-22 07-Jan-23 82
HK Hols - No B/O periods
310.D.EX.H138.B01 EVT - ELS design (Vertical Elements) - Prepare and submit Form BA8 and grant consent (was
C01_7C3)
d/w - 10h/d - No HK 7 30-Sep-22 06-Oct-22 08-Jan-23 14-Jan-23 100
Hols - No B/O periods (was
310.C.EX.H137 EVT - Zone 1 (3310/3) - UU detection C1)
C11_6 d/w - 10h/d - With 12 30-Sep-22 15-Oct-22 09-Jan-23 21-Jan-23 82
HK Hols - No B/O periods
310.D.EX.H831.B01 EVT - ELS design (Vertical Elements) - Prepare and submit Form BA10 to notify work (was
C01_7C3)
d/w - 10h/d - No HK 7 07-Oct-22 13-Oct-22 15-Jan-23 21-Jan-23 100
commencement Hols - No B/O periods (was
310.C.EX.H105 Contract <3302> complete EVT Southern Portion tunnel structure for cofferdam C1)
C11_6 d/w - 10h/d - With 0 13-Oct-22 21-Jan-23 84
connection HK Hols - No B/O periods
310.C.EX.H106 EVT - Zone 1 (3310/3) - ELS - Install vertical element (87 nos. @2day/no./rig; use 3 rigs) (was
C11_6C3)
d/w - 10h/d - With 63 5 17-Oct-22 29-Dec-22 26-Jan-23 13-Apr-23 82
HK Hols - No B/O periods
310.C.EX.H162 EVT - Zone 1 (3310/3) - ELS - Install wells (was
C11_6C3)
d/w - 10h/d - With 24 01-Dec-22 29-Dec-22 31-Mar-23 03-May-23 98
HK Hols - No B/O periods
310.C.EX.H110 EVT - Zone 1 (3310/3) - ELS - Pumping test and submit report (was
C01_7C3)
d/w - 10h/d - No HK 6 2 30-Dec-22 04-Jan-23 04-May-23 09-May-23 125
Hols - No B/O periods (was
310.C.EX.H121 EVT - Zone 1 (3310/3) - ELS - Submit Form BA14 C1)
C01_7 d/w - 10h/d - No HK 12 30-Dec-22 10-Jan-23 14-Apr-23 25-Apr-23 105
Hols - No B/O periods (was
310.C.EX.H129 EVT - Zone 1 (3310/3) - ELS - Submit Form BA8 for excavation C1)
C01_7 d/w - 10h/d - No HK 7 11-Jan-23 17-Jan-23 26-Apr-23 02-May-23 105
Hols - No B/O periods (was
310.C.EX.H139 EVT - Zone 1 (3310/3) - ELS - Submit Form BA10 for excavation C1)
C01_7 d/w - 10h/d - No HK 7 18-Jan-23 24-Jan-23 03-May-23 09-May-23 105
Hols - No B/O periods (was
310.C.EX.H158 EVT - Zone 1 (3310/3) - ELS - Excavation and struts installation [15,900m3 @600m3/d/wf, C1)
C11_6 d/w - 10h/d - With 42 2 26-Jan-23 15-Mar-23 10-May-23 29-Jun-23 84
1wf + 6d/layer; 2 layers] HK Hols - No B/O periods
310.C.EX.H1145 EVT - Zone 1 (3310/3) - ELS - Make good FEL + PLT (Install remaining struts if any) (was
C01_7C3)
d/w - 10h/d - No HK 12 2 16-Mar-23 27-Mar-23 30-Jun-23 11-Jul-23 106
Hols - No B/O periods (was
CC#06 - EVT - Zone 2 (3310/3) - ELS C1) 211 9 01-Sep-22 19-May-23 30-Sep-22 09-Jun-23 17
310.C.EX.H1078 EVT - Zone 2 (3310/3) - Mobilization + instrumentation + UU detection C11_6 d/w - 10h/d - With 24 01-Sep-22 29-Sep-22 30-Sep-22 29-Oct-22 24
HK Hols - No B/O periods
310.C.EX.H114 EVT - Zone 2 (3310/3) - ELS - Install Pipe Piles (269nos. @2day/no./rig; use 8 rigs) (was
C11_6C3)
d/w - 10h/d - With 72 3 14-Oct-22 07-Jan-23 31-Oct-22 27-Jan-23 14
HK Hols - No B/O periods
310.C.EX.H1357.B01 EVT - Zone 2 (3310/3) - ELS - Install wells (was
C11_6C3)
d/w - 10h/d - With 18 2 16-Dec-22 07-Jan-23 18-Jan-23 10-Feb-23 26
HK Hols - No B/O periods
310.C.EX.H1065 EVT - Zone 2 (3310/3) - ELS - Submit Form BA14 (was
C01_7C3)
d/w - 10h/d - No HK 12 08-Jan-23 19-Jan-23 28-Jan-23 08-Feb-23 20
Hols - No B/O periods (was
310.C.EX.H1361.B01 EVT - Zone 2 (3310/3) - ELS - Pumping test and submit report C1)
C01_7 d/w - 10h/d - No HK 12 2 08-Jan-23 19-Jan-23 11-Feb-23 22-Feb-23 34
Hols - No B/O periods (was
C1)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 105 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.EX.H1073 EVT - Zone 2 (3310/3) - ELS - Submit Form BA8 for excavation C01_7 d/w - 10h/d - No HK 7 20-Jan-23 26-Jan-23 09-Feb-23 15-Feb-23 20
Hols - No B/O periods (was
310.C.EX.H1077 EVT - Zone 2 (3310/3) - ELS - Submit Form BA10 for excavation C1)
C01_7 d/w - 10h/d - No HK 7 27-Jan-23 02-Feb-23 16-Feb-23 22-Feb-23 20
Hols - No B/O periods (was
310.C.EX.H170 EVT - Zone 2 (3310/3) - Excavation and struts installation [64,131m3, @600m3/d/wf, 3wf C1)
C11_6 d/w - 10h/d - With 74 0 03-Feb-23 05-May-23 23-Feb-23 25-May-23 17
+ 18d/ layer of strut; 2 layers] HK Hols - No B/O periods
310.C.EX.H172.B01 EVT - Zone 2 (3310/3) - ELS - Make good FEL + PLT (assumed) (was
C11_6C3)
d/w - 10h/d - With 12 2 06-May-23 19-May-23 27-May-23 09-Jun-23 17
HK Hols - No B/O periods
CC#06 - EVT - Zone 3 (3310/3) - ELS (was C3) 228 14 01-Sep-22 09-Jun-23 16-Sep-22 13-Jun-23 3
310.C.EX.H167 EVT - Zone 3 (3310/3) - Mobilization + instrumentation + UU detection C11_6 d/w - 10h/d - With 24 01-Sep-22 29-Sep-22 16-Sep-22 15-Oct-22 12
HK Hols - No B/O periods
310.C.EX.H168.B01 EVT - Zone 3 (3310/3) - ELS - Install pipe pile (777 nos. @2day/no./rig; use 20 rigs) (was
C11_6C3)
d/w - 10h/d - With 82 3 14-Oct-22 19-Jan-23 17-Oct-22 21-Jan-23 2
HK Hols - No B/O periods
310.C.EX.H174.B01 EVT - Zone 3 (3310/3) - ELS - Install wells (was
C11_6C3)
d/w - 10h/d - With 18 2 29-Dec-22 19-Jan-23 12-Jan-23 04-Feb-23 11
HK Hols - No B/O periods
310.C.EX.H175.B01 EVT - Zone 3 (3310/3) - ELS - Submit Form BA14 (was
C01_7C3)
d/w - 10h/d - No HK 12 20-Jan-23 31-Jan-23 23-Jan-23 03-Feb-23 3
Hols - No B/O periods (was
310.C.EX.H1365.B01 EVT - Zone 3 (3310/3) - ELS - Pumping test and submit report C1)
C01_7 d/w - 10h/d - No HK 12 2 20-Jan-23 31-Jan-23 06-Feb-23 17-Feb-23 17
Hols - No B/O periods (was
310.C.EX.H176.B01 EVT - Zone 3 (3310/3) - ELS - Submit Form BA8 for excavation C1)
C01_7 d/w - 10h/d - No HK 7 01-Feb-23 07-Feb-23 04-Feb-23 10-Feb-23 3
Hols - No B/O periods (was
310.C.EX.H177.B01 EVT - Zone 3 (3310/3) - ELS - Submit Form BA10 for excavation C1)
C01_7 d/w - 10h/d - No HK 7 08-Feb-23 14-Feb-23 11-Feb-23 17-Feb-23 3
Hols - No B/O periods (was
310.C.EX.H173 EVT - Zone 3 (3310/3) - Initial excavation + UU hanger support + divert existing UU to C1)
C11_6 d/w - 10h/d - With 24 15-Feb-23 14-Mar-23 18-Feb-23 17-Mar-23 3
hanger support HK Hols - No B/O periods
310.C.EX.H178 EVT - Zone 3 (3310/3) - ELS [132,081m3, @800m3/d/wf; 12wf+ 12d/ layer of strut; (was
C11_6C3)
d/w - 10h/d - With 55 5 15-Mar-23 23-May-23 18-Mar-23 27-May-23 3
assume 3 layers] HK Hols - No B/O periods
310.C.EX.H179.B01 EVT - Zone 3 (3310/3) - ELS - Make good FEL + PLT (assumed) (was
C11_6C3)
d/w - 10h/d - With 14 2 24-May-23 09-Jun-23 29-May-23 13-Jun-23 3
HK Hols - No B/O periods
CC#06 - EVT - Zone 4 (3310/3) - ELS (was C3) 215 11 01-Sep-22 24-May-23 15-Oct-22 16-Jun-23 19
310.C.EX.H189 EVT - Zone 4 (3310/3) - Mobilization + instrumentation + UU detection C11_6 d/w - 10h/d - With 24 01-Sep-22 29-Sep-22 15-Oct-22 11-Nov-22 35
HK Hols - No B/O periods
310.D.EX.H835.B01 EVT - ELS design (Vertical Elements) - Prepare and submit Form BA8 and grant consent (was
C01_7C3)
d/w - 10h/d - No HK 7 30-Sep-22 06-Oct-22 29-Oct-22 04-Nov-22 29
Hols - No B/O periods (was
310.D.EX.H839.B01 EVT - ELS design (Vertical Elements) - Prepare and submit Form BA10 to notify work C1)
C01_7 d/w - 10h/d - No HK 7 07-Oct-22 13-Oct-22 05-Nov-22 11-Nov-22 29
commencement Hols - No B/O periods (was
310.C.EX.H122 EVT - Zone 4 (3310/3) - ELS - Install pipe pile (107 nos. @2day/no./rig; use 3 rigs) C1)
C11_6 d/w - 10h/d - With 74 3 25-Oct-22 20-Jan-23 12-Nov-22 11-Feb-23 16
HK Hols - No B/O periods
310.C.EX.H1137 EVT - Zone 4 (3310/3) - ELS - Install wells (was
C11_6C3)
d/w - 10h/d - With 18 2 30-Dec-22 20-Jan-23 06-Feb-23 25-Feb-23 28
HK Hols - No B/O periods
310.C.EX.H1085 EVT - Zone 4 (3310/3) - ELS - Pumping test and submit report (was
C01_7C3)
d/w - 10h/d - No HK 12 2 21-Jan-23 01-Feb-23 26-Feb-23 09-Mar-23 36
Hols - No B/O periods (was
310.C.EX.H1081 EVT - Zone 4 (3310/3) - ELS - Submit Form BA14 C1)
C01_7 d/w - 10h/d - No HK 12 21-Jan-23 01-Feb-23 12-Feb-23 23-Feb-23 22
Hols - No B/O periods (was
310.C.EX.H1089 EVT - Zone 4 (3310/3) - ELS - Submit Form BA8 for excavation C1)
C01_7 d/w - 10h/d - No HK 7 02-Feb-23 08-Feb-23 24-Feb-23 02-Mar-23 22
Hols - No B/O periods (was
310.C.EX.H1093 EVT - Zone 4 (3310/3) - ELS - Submit Form BA10 for excavation C1)
C01_7 d/w - 10h/d - No HK 7 09-Feb-23 15-Feb-23 03-Mar-23 09-Mar-23 22
Hols - No B/O periods (was
310.C.EX.H186 EVT - Zone 4 (3310/3) - Initial excavation + UU hanger support+ divert existing UU to C1)
C11_6 d/w - 10h/d - With 24 16-Feb-23 15-Mar-23 10-Mar-23 11-Apr-23 19
hanger support HK Hols - No B/O periods
310.C.EX.H182 EVT - Zone 4 (3310/3) - Excavation and struts installation [21,200m3 @600m3/d/wf; 2wf + (was
C11_6C3)
d/w - 10h/d - With 45 2 16-Mar-23 12-May-23 12-Apr-23 05-Jun-23 19
12d/layer of strut; 2 layers] HK Hols - No B/O periods
(was C3)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 106 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.EX.H1149 EVT - Zone 4 (3310/3) - ELS - Make good FEL + PLT (Install remaining struts if any) C11_6 d/w - 10h/d - With 10 2 13-May-23 24-May-23 06-Jun-23 16-Jun-23 19
HK Hols - No B/O periods
CC#06 - EVT - Zone 5 (3310/3) - ELS (was C3) 219 15 01-Sep-22 30-May-23 15-Oct-22 16-Jun-23 15
310.D.EX.H444 EVT - Zone 5 (3310/3) - Mobilization + instrumentation + UU detection C11_6 d/w - 10h/d - With 24 01-Sep-22 29-Sep-22 15-Oct-22 11-Nov-22 35
HK Hols - No B/O periods
310.D.EX.H457 EVT - ELS design (Vertical Elements) - Prepare and submit Form BA8 and grant consent (was
C01_7C3)
d/w - 10h/d - No HK 7 30-Sep-22 06-Oct-22 29-Oct-22 04-Nov-22 29
Hols - No B/O periods (was
310.D.EX.H461 EVT - ELS design (Vertical Elements) - Prepare and submit Form BA10 to notify work C1)
C01_7 d/w - 10h/d - No HK 7 07-Oct-22 13-Oct-22 05-Nov-22 11-Nov-22 29
commencement Hols - No B/O periods (was
310.C.EX.H134 EVT - Zone 5 (3310/3) - ELS - Install pipe pile (107nos. @2days/no./rig; use 5 rigs) C1)
C11_6 d/w - 10h/d - With 47 4 25-Oct-22 17-Dec-22 12-Nov-22 07-Jan-23 16
HK Hols - No B/O periods
310.C.EX.H141 EVT - Zone 5 (3310/3) - ELS - Install wells (was
C11_6C3)
d/w - 10h/d - With 18 2 28-Nov-22 17-Dec-22 31-Dec-22 21-Jan-23 28
HK Hols - No B/O periods
310.C.EX.H161 EVT - Zone 5 (3310/3) - ELS - Pumping test and submit report (was
C01_7C3)
d/w - 10h/d - No HK 12 2 18-Dec-22 29-Dec-22 22-Jan-23 02-Feb-23 35
Hols - No B/O periods (was
310.C.EX.H151 EVT - Zone 5 (3310/3) - ELS - Submit Form BA14 C1)
C01_7 d/w - 10h/d - No HK 12 18-Dec-22 29-Dec-22 08-Jan-23 19-Jan-23 21
Hols - No B/O periods (was
310.C.EX.H171 EVT - Zone 5 (3310/3) - ELS - Submit Form BA8 for excavation C1)
C01_7 d/w - 10h/d - No HK 7 30-Dec-22 05-Jan-23 20-Jan-23 26-Jan-23 21
Hols - No B/O periods (was
310.C.EX.H181 EVT - Zone 5 (3310/3) - ELS - Submit Form BA10 for excavation C1)
C01_7 d/w - 10h/d - No HK 7 06-Jan-23 12-Jan-23 27-Jan-23 02-Feb-23 21
Hols - No B/O periods (was
310.C.EX.H191 EVT - Zone 5 (3310/3) - Initial excavation + UU hanger support + divert existing UU to C1)
C11_6 d/w - 10h/d - With 24 13-Jan-23 13-Feb-23 03-Feb-23 02-Mar-23 15
hanger support HK Hols - No B/O periods
310.C.EX.H981 EVT - Zone 5 (3310/3) - Excavation and struts installation [21,200m3 @600m3/d/wf, 2wf + (was
C11_6C3)
d/w - 10h/d - With 75 5 14-Feb-23 17-May-23 03-Mar-23 05-Jun-23 15
12d/layer of strut; 4 layers] HK Hols - No B/O periods
310.C.EX.H983.B01 EVT - Zone 5 (3310/3) - ELS - Make good FEL + PLT (assumed) (was
C11_6C3)
d/w - 10h/d - With 10 2 18-May-23 30-May-23 06-Jun-23 16-Jun-23 15
HK Hols - No B/O periods
CC#06 - EVT - Tunnel Structure Construction (was C3) 365 33 06-Sep-22 27-Nov-23 10-Dec-22 14-Dec-23 15
CC#06 - EVT - Zone 6 (3310/6, 6C) - Tunnel Structure 145 6 06-Sep-22 02-Mar-23 10-Dec-22 02-Mar-23 0
310.C.EX.H280.B01 EVT - Zone 6 (3310/6,c) - Submit Form BA8 for RC works C01_7 d/w - 10h/d - No HK 7 06-Sep-22 12-Sep-22 10-Dec-22 16-Dec-22 95
Hols - No B/O periods (was
310.C.EX.H282.B01 EVT - Zone 6 (3310/6,c) - Submit Form BA10 for RC works C1)
C01_7 d/w - 10h/d - No HK 7 17-Dec-22 23-Dec-22 17-Dec-22 23-Dec-22 0
Hols - No B/O periods (was
310.C.EX.H284 EVT - Zone 6 (3310/6,c) - Bay 1 to 9 - Construct base slab [@6d/bay 2wf] C1)
C11_6 d/w - 10h/d - With 36 2 24-Dec-22 09-Feb-23 24-Dec-22 09-Feb-23 0
HK Hols - No B/O periods
310.C.EX.H436 EVT - Zone 6 (3310/6,c) - Bay 1 to 9 - Construct wall & roof slab [@12d/bay; 3wf] (was
C11_6C3)
d/w - 10h/d - With 40 4 12-Jan-23 02-Mar-23 12-Jan-23 02-Mar-23 0
HK Hols - No B/O periods
CC#06 - EVT - Zone 7 (3310/7) - Tunnel Structure (was C3) 120 6 05-Jan-23 03-Jun-23 20-Mar-23 03-Jun-23 0
310.C.EX.H603.B1 EVT - Zone 7 (3310/7) - Submit Form BA8 for RC works C01_7 d/w - 10h/d - No HK 7 05-Jan-23 11-Jan-23 20-Mar-23 26-Mar-23 74
Hols - No B/O periods (was
310.C.EX.H605.B1 EVT - Zone 7 (3310/7) - Submit Form BA10 for RC works C1)
C01_7 d/w - 10h/d - No HK 7 26-Mar-23 01-Apr-23 27-Mar-23 02-Apr-23 1
Hols - No B/O periods (was
310.C.EX.H607 EVT - Zone 7 (3310/7) - Bay 1 to 6 - Construct base slab [6d/bay; 2wf] C1)
C11_6 d/w - 10h/d - With 36 3 03-Apr-23 19-May-23 03-Apr-23 19-May-23 0
HK Hols - No B/O periods
310.C.EX.H630 EVT - Zone 7 (3310/7) - Bay 1 to 6 - Construct wall & roof slab 12d/bay; 2wf] (PMS 14) (was
C11_6C3)
d/w - 10h/d - With 40 3 17-Apr-23 03-Jun-23 17-Apr-23 03-Jun-23 0
HK Hols - No B/O periods
CC#06 - EVT - Zone 1 (3310/3) - Tunnel Structure (was C3) 102 6 18-Jan-23 25-May-23 05-Jul-23 02-Sep-23 83
310.C.EX.H204.B01 EVT - Zone 1 (3310/3) - Submit Form BA8 for RC works C01_7 d/w - 10h/d - No HK 7 18-Jan-23 24-Jan-23 05-Jul-23 11-Jul-23 168
Hols - No B/O periods (was
310.C.EX.H206.B01 EVT - Zone 1 (3310/3) - Submit Form BA10 for RC works C1)
C01_7 d/w - 10h/d - No HK 7 28-Mar-23 03-Apr-23 12-Jul-23 18-Jul-23 106
Hols - No B/O periods (was
C1)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 107 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.EX.H208 EVT - Zone 1 (3310/3) - Bay 1 to 2 - Construct base slab [@6d/bay; 1wf] C11_6 d/w - 10h/d - With 14 1 04-Apr-23 24-Apr-23 19-Jul-23 03-Aug-23 83
HK Hols - No B/O periods
310.C.EX.H344 EVT - Zone 1 (3310/3) - Bay 1 to 2 - Construct wall & roof slab [@12d/bay; 1wf] (was
C11_6C3)
d/w - 10h/d - With 26 5 25-Apr-23 25-May-23 04-Aug-23 02-Sep-23 83
HK Hols - No B/O periods
CC#06 - EVT - Zone 2 (3310/3) - Tunnel Structure (was C3) 162 2 27-Jan-23 12-Aug-23 03-Jun-23 02-Sep-23 18
310.C.EX.H127.B01 EVT - Zone 2 (3310/3) - Submit Form BA8 for RC works C01_7 d/w - 10h/d - No HK 7 27-Jan-23 02-Feb-23 03-Jun-23 09-Jun-23 127
Hols - No B/O periods (was
310.C.EX.H129.B01 EVT - Zone 2 (3310/3) - Submit Form BA10 for RC works C1)
C01_7 d/w - 10h/d - No HK 7 20-May-23 26-May-23 10-Jun-23 16-Jun-23 21
Hols - No B/O periods (was
310.C.EX.H131.B01 EVT - Zone 2 (3310/3) - Bay 1 to 7 - construct base slab [@6d/bay; 2wf] C1)
C11_6 d/w - 10h/d - With 22 1 27-May-23 21-Jun-23 17-Jun-23 14-Jul-23 18
HK Hols - No B/O periods
310.C.EX.H133.B01 EVT - Zone 2 (3310/3) - Bay 1 to 7 - construct wall & roof slab [@12d/bay; 2wf] (was
C11_6C3)
d/w - 10h/d - With 43 1 23-Jun-23 12-Aug-23 15-Jul-23 02-Sep-23 18
HK Hols - No B/O periods
CC#06 - EVT - Zone 3 (3310/3) - Tunnel Structure (was C3) 161 5 08-Feb-23 23-Aug-23 07-Jun-23 02-Sep-23 9
310.C.EX.H829.B01 EVT - Zone 3 (3310/3) - Submit Form BA8 for RC works C01_7 d/w - 10h/d - No HK 7 08-Feb-23 14-Feb-23 07-Jun-23 13-Jun-23 119
Hols - No B/O periods (was
310.C.EX.H831.B01 EVT - Zone 3 (3310/3) - Submit Form BA10 for RC works C1)
C01_7 d/w - 10h/d - No HK 7 10-Jun-23 16-Jun-23 14-Jun-23 20-Jun-23 4
Hols - No B/O periods (was
310.C.EX.H833.B01 EVT - Zone 3 (3310/3) - Bay 1 to 14 - Construct base slab [@6d/bay; 5wf] C1)
C11_6 d/w - 10h/d - With 18 1 17-Jun-23 10-Jul-23 21-Jun-23 13-Jul-23 3
HK Hols - No B/O periods
310.C.EX.H835.B01 EVT - Zone 3 (3310/3) - Bay 1 to 14 - Construct wall & roof slab [@12d/bay; 5wf] (was
C11_6C3)
d/w - 10h/d - With 38 4 11-Jul-23 23-Aug-23 14-Jul-23 26-Aug-23 3
HK Hols - No B/O periods
310.C.EX.W315 EVT - Tunnel R.C. Structure completed (PMS 15) (was
C11_6C3)
d/w - 10h/d - With 0 23-Aug-23 02-Sep-23 9
HK Hols - No B/O periods
CC#06 - EVT - Zone 4 (3310/3) - Tunnel Structure (was C3) 150 4 09-Feb-23 11-Aug-23 10-Jun-23 02-Sep-23 19
310.C.EX.H244.B01 EVT - Zone 4 (3310/3) - Submit Form BA8 for RC works C01_7 d/w - 10h/d - No HK 7 09-Feb-23 15-Feb-23 10-Jun-23 16-Jun-23 121
Hols - No B/O periods (was
310.C.EX.H246.B01 EVT - Zone 4 (3310/3) - Submit Form BA10 for RC works C1)
C01_7 d/w - 10h/d - No HK 7 25-May-23 31-May-23 17-Jun-23 23-Jun-23 23
Hols - No B/O periods (was
310.C.EX.H248 EVT - Zone 4 (3310/3) - Bay 1 to 3 - Construct base slab [@6d/bay; 1wf] C1)
C11_6 d/w - 10h/d - With 20 2 01-Jun-23 24-Jun-23 24-Jun-23 18-Jul-23 19
HK Hols - No B/O periods
310.C.EX.H364 EVT - Zone 4 (3310/3) - Bay 1 to 3 - Construct wall & roof slab [@12d/bay; 1wf] (was
C11_6C3)
d/w - 10h/d - With 40 2 26-Jun-23 11-Aug-23 19-Jul-23 02-Sep-23 19
HK Hols - No B/O periods
CC#06 - EVT - Zone 5 (3310/3) - Tunnel Structure (was C3) 181 4 06-Jan-23 17-Aug-23 10-Jun-23 02-Sep-23 14
310.C.EX.H224.B01 EVT - Zone 5 (3310/3) - Submit Form BA8 for RC works C01_7 d/w - 10h/d - No HK 7 06-Jan-23 12-Jan-23 10-Jun-23 16-Jun-23 155
Hols - No B/O periods (was
310.C.EX.H226.B01 EVT - Zone 5 (3310/3) - Submit Form BA10 for RC works C1)
C01_7 d/w - 10h/d - No HK 7 31-May-23 06-Jun-23 17-Jun-23 23-Jun-23 17
Hols - No B/O periods (was
310.C.EX.H228 EVT - Zone 5 (3310/3) - bay 1 to 3 - Construct base slab [@6d/bay; 1wf] C1)
C11_6 d/w - 10h/d - With 20 2 07-Jun-23 30-Jun-23 24-Jun-23 18-Jul-23 14
HK Hols - No B/O periods
310.C.EX.H384 EVT - Zone 5 (3310/3) - bay 1 to 3 - Construct wall & roof slab [@12d/bay; 1wf] (was
C11_6C3)
d/w - 10h/d - With 40 2 03-Jul-23 17-Aug-23 19-Jul-23 02-Sep-23 14
HK Hols - No B/O periods
CC#06 - EVT - Mass Concrete Fill inside Tunnel (Ballast Concrete) (was
C11_6C3)
d/w - 10h/d - With HK Hols
79- No B/O 0periods (was
24-Aug-23
C3) 27-Nov-23 11-Sep-23 14-Dec-23 15
CC#06 - EVT - North Section N1 C11_6 d/w - 10h/d - With HK Hols
30- No B/O 0periods (was
24-Aug-23
C3) 27-Sep-23 11-Sep-23 17-Oct-23 15
310.C.EX.Y556 EVT - North - Zone 6,7 - bay 1 to 29 & Zone 5 bay 1 - permanent mass concrete fill C11_6 d/w - 10h/d - With 30 24-Aug-23 27-Sep-23 11-Sep-23 17-Oct-23 15
[515m3/bay] HK Hols - No B/O periods
CC#06 - EVT - North Section N2 (was
C11_6C3)
d/w - 10h/d - With HK Hols6 - No B/O 0periods (was
28-Sep-23
C3) 06-Oct-23 18-Oct-23 25-Oct-23 15
310.C.EX.Y624 EVT - North - Zone 4 & 5 - bay 2 to 7 - permanent mass concrete fill [515m3/bay] C11_6 d/w - 10h/d - With 6 28-Sep-23 06-Oct-23 18-Oct-23 25-Oct-23 15
HK Hols - No B/O periods
CC#06 - EVT - Middle Section (was
C11_6C3)
d/w - 10h/d - With HK Hols
39- No B/O 0periods (was
07-Oct-23
C3) 22-Nov-23 26-Oct-23 09-Dec-23 15

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 108 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.EX.Y692 EVT - Middle - Zone 3 - bay 1 to 13 - permanent mass concrete fill [1130 x 13m3] C11_6 d/w - 10h/d - With 39 07-Oct-23 22-Nov-23 26-Oct-23 09-Dec-23 15
HK Hols - No B/O periods
CC#06 - EVT - South Section (was
C11_6C3)
d/w - 10h/d - With HK Hols4 - No B/O 0periods (was
23-Nov-23
C3) 27-Nov-23 11-Dec-23 14-Dec-23 15
310.C.EX.Y696 EVT - North - South bay 1 & 2 - permanent mass concrete fill [515m3] C11_6 d/w - 10h/d - With 2 23-Nov-23 24-Nov-23 11-Dec-23 12-Dec-23 15
HK Hols - No B/O periods
310.C.EX.Y700 EVT - North - South bay 3 - permanent mass concrete fill [515m3] (was
C11_6C3)
d/w - 10h/d - With 4 23-Nov-23 27-Nov-23 11-Dec-23 14-Dec-23 15
HK Hols - No B/O periods
CC#06 - EVT - Earthwork - Backfilling (was
C11_6C3)
d/w - 10h/d - With HK Hols
184- No B/O13
periods (was
03-Mar-23
C3) 14-Oct-23 02-Aug-23 16-Dec-23 53
CC#06 - EVT - Zone 6 (3310/6, 6C) - Backfill C11_6 d/w - 10h/d - With HK Hols
40- No B/O 2periods (was
03-Mar-23
C3) 22-Apr-23 07-Aug-23 16-Nov-23 171
310.C.EX.W1000 EVT - Zone 6 - Backfill from FL to +3.0mPD [48,383m3 @350m3/d/wf; 4wf] C11_6 d/w - 10h/d - With 30 03-Mar-23 11-Apr-23 07-Aug-23 09-Sep-23 126
HK Hols - No B/O periods
310.C.EX.W1004 EVT - Zone 6 - Backfill from +3.0 to +6.5mPD [10,029m3 @350m3/d/wf; 4wf] (was
C11_6C3)
d/w - 10h/d - With 10 2 12-Apr-23 22-Apr-23 06-Nov-23 16-Nov-23 171
HK Hols - No B/O periods
CC#06 - EVT - Zone 7 (3310/7) - Backfill (was
C11_6C3)
d/w - 10h/d - With HK Hols
54- No B/O 2periods (was
05-Jun-23
C3) 08-Aug-23 12-Sep-23 16-Nov-23 83
310.C.EX.W1008 EVT - Zone 7 - Backfill from FL to +3.0mPD [25,535m3 @350m3/d/wf; 2wf] C11_6 d/w - 10h/d - With 37 05-Jun-23 19-Jul-23 12-Sep-23 27-Oct-23 83
HK Hols - No B/O periods
310.C.EX.W1012 EVT - Zone 7 - Backfill from +3.0 to +6.5mPD [10,029m3 @350m3/d/wf; 2wf] (was
C11_6C3)
d/w - 10h/d - With 17 2 20-Jul-23 08-Aug-23 28-Oct-23 16-Nov-23 83
HK Hols - No B/O periods
CC#06 - EVT - Zone 1 (3310/3) - Backfill (was
C11_6C3)
d/w - 10h/d - With HK Hols
12- No B/O 1periods (was
27-May-23
C3) 09-Jun-23 04-Oct-23 17-Oct-23 107
310.C.EX.W288 EVT - Zone 1 - Backfill from FL to +3.0mPD [8,540m3 @350m3/d/wf; 3wf] C11_6 d/w - 10h/d - With 6 27-May-23 02-Jun-23 04-Oct-23 10-Oct-23 107
HK Hols - No B/O periods
310.C.EX.W292 EVT - Zone 1 - Backfill from +3.0 to +6.5mPD [1,770m3 @350m3/d/wf; 1wf] (was
C11_6C3)
d/w - 10h/d - With 6 1 03-Jun-23 09-Jun-23 11-Oct-23 17-Oct-23 107
HK Hols - No B/O periods
CC#06 - EVT - Zone 2 (3310/3) - Backfill (was
C11_6C3)
d/w - 10h/d - With HK Hols
52- No B/O 2periods (was
14-Aug-23
C3) 14-Oct-23 04-Sep-23 06-Nov-23 18
310.C.EX.W312 EVT - Zone 2 - Backfill from FL to +3.0mPD [39,670m3 @350m3/d/wf; 4wf] C11_6 d/w - 10h/d - With 29 14-Aug-23 15-Sep-23 04-Sep-23 09-Oct-23 18
HK Hols - No B/O periods
310.C.EX.W316 EVT - Zone 2 - Backfill from +3.0 to +6.5mPD [29,247m3 @350m3/d/wf; 4wf] (was
C11_6C3)
d/w - 10h/d - With 23 2 16-Sep-23 14-Oct-23 10-Oct-23 06-Nov-23 18
HK Hols - No B/O periods
CC#06 - EVT - Zone 3 (3310/3) - Backfill (was
C11_6C3)
d/w - 10h/d - With HK Hols
64- No B/O 2periods (was
29-Jul-23
C3) 13-Oct-23 02-Aug-23 16-Nov-23 28
310.C.EX.W304 EVT - Zone 3 - Backfill from FL to +3.0mPD [72,410m3 @350m3/d/wf; 6wf] C11_6 d/w - 10h/d - With 34 29-Jul-23 06-Sep-23 02-Aug-23 09-Sep-23 3
HK Hols - No B/O periods
310.C.EX.W308 EVT - Zone 3 - Backfill from +3.0 to +6.5mPD [57,285m3 @350m3/d/wf; 6wf] (was
C11_6C3)
d/w - 10h/d - With 30 2 07-Sep-23 13-Oct-23 12-Oct-23 16-Nov-23 28
HK Hols - No B/O periods
CC#06 - EVT - Zone 4 (3310/3) - Backfill (was
C11_6C3)
d/w - 10h/d - With HK Hols
34- No B/O 2periods (was
12-Aug-23
C3) 20-Sep-23 08-Nov-23 16-Dec-23 72
310.C.EX.W296 EVT - Zone 4 - Backfill from FL to +3.0mPD [12,220m3 @350m3/d/wf; 2wf] C11_6 d/w - 10h/d - With 18 12-Aug-23 01-Sep-23 08-Nov-23 28-Nov-23 72
HK Hols - No B/O periods
310.C.EX.W300 EVT - Zone 4 - Backfill from +3.0 to +6.5mPD [9,668m3 @350m3/d/wf; 2wf] (was
C11_6C3)
d/w - 10h/d - With 16 2 02-Sep-23 20-Sep-23 29-Nov-23 16-Dec-23 72
HK Hols - No B/O periods
CC#06 - EVT - Zone 5 (3310/3) - Backfill (was
C11_6C3)
d/w - 10h/d - With HK Hols
47- No B/O 2periods (was
18-Aug-23
C3) 13-Oct-23 20-Sep-23 16-Nov-23 28
310.C.EX.W600 EVT - Zone 5 - Backfill from FL to +3.0mPD [10,750m3 @350m3/d/wf; 1wf] C11_6 d/w - 10h/d - With 31 18-Aug-23 22-Sep-23 20-Sep-23 28-Oct-23 28
HK Hols - No B/O periods
310.C.EX.W604 EVT - Zone 5 - Backfill from +3.0 to +6.5mPD [2,230m3 @350m3/d/wf; 1wf] (was
C11_6C3)
d/w - 10h/d - With 16 2 23-Sep-23 13-Oct-23 30-Oct-23 16-Nov-23 28
HK Hols - No B/O periods
CC#06 - EVT - Internal ABWF Works (was
C11_6C3)
d/w - 10h/d - With HK Hols
462- No B/O48
periods (was
05-Sep-22
C3) 23-Mar-24 05-Sep-22 03-Jul-24 79
310.C.EX.W311 EVT - Access to Works Area 3310/7 C11_6 d/w - 10h/d - With 0 05-Sep-22* 05-Sep-22 0
HK Hols - No B/O periods
310.C.EX.W313 Contract <3408> complete EVT (EA, EU, ES); provide access to 3310 and ready for (was
C11_6C3)
d/w - 10h/d - With 0 05-Sep-22 07-Dec-22 78
internal ABWF & MEP works HK Hols - No B/O periods
310.C.EX.W327 Contract <3408> complete EVT (Northern Portion); provide access to 3310 and ready for (was
C11_6C3)
d/w - 10h/d - With 0 23-Aug-23 14-Sep-23 19
bulkhead removal HK Hols - No B/O periods
CC#06 - EVT - ABWF - Eastern Approach Ramp (EU) (was
C11_6C3)
d/w - 10h/d - With HK Hols
201- No B/O12
periods (was
30-Nov-22
C3) 05-Aug-23 08-Dec-22 14-Feb-24 157
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 109 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.EX.W368 EVT (EU) - brickwork and blockwork C11_6 d/w - 10h/d - With 50 2 30-Nov-22 01-Feb-23 08-Dec-22 09-Feb-23 7
HK Hols - No B/O periods
310.C.EX.W384 EVT (EU) - Builder works in connection with BS (was
C11_6C3)
d/w - 10h/d - With 50 2 30-Nov-22 01-Feb-23 08-Dec-22 09-Feb-23 7
HK Hols - No B/O periods
310.C.EX.W372 EVT (EU) - steel and metalwork (was
C11_6C3)
d/w - 10h/d - With 50 2 12-Dec-22 13-Feb-23 03-Oct-23 30-Nov-23 238
HK Hols - No B/O periods
310.C.EX.W376 EVT (EU) - plastering and screeding works (was
C11_6C3)
d/w - 10h/d - With 50 2 23-Dec-22 24-Feb-23 14-Oct-23 12-Dec-23 238
HK Hols - No B/O periods
310.C.EX.W380 EVT (EU) - Painting Works (was
C11_6C3)
d/w - 10h/d - With 50 2 06-Jan-23 08-Mar-23 27-Oct-23 23-Dec-23 238
HK Hols - No B/O periods
310.C.EX.W388 EVT (EU) - Road Paving works (was
C11_6C3)
d/w - 10h/d - With 36 2 24-Jun-23 05-Aug-23 02-Jan-24 14-Feb-24 157
HK Hols - No B/O periods
CC#06 - EVT - ABWF - Eastern Roundabout (EA) (was
C11_6C3)
d/w - 10h/d - With HK Hols
230- No B/O12
periods (was
02-Feb-23
C3) 09-Nov-23 23-Mar-23 05-Apr-24 118
310.C.EX.W344 EVT (EA) - brickwork and blockwork C11_6 d/w - 10h/d - With 40 2 02-Feb-23 20-Mar-23 23-Mar-23 13-May-23 42
HK Hols - No B/O periods
310.C.EX.W360 EVT (EA) - Builder works in connection with BS (was
C11_6C3)
d/w - 10h/d - With 40 2 02-Feb-23 20-Mar-23 23-Mar-23 13-May-23 42
HK Hols - No B/O periods
310.C.EX.W348 EVT (EA) - steel and metalwork (was
C11_6C3)
d/w - 10h/d - With 40 2 14-Feb-23 31-Mar-23 01-Dec-23 19-Jan-24 238
HK Hols - No B/O periods
310.C.EX.W352 EVT (EA) - plastering and screeding works (was
C11_6C3)
d/w - 10h/d - With 40 2 25-Feb-23 17-Apr-23 13-Dec-23 31-Jan-24 238
HK Hols - No B/O periods
310.C.EX.W356 EVT (EA) - Painting Works (was
C11_6C3)
d/w - 10h/d - With 40 2 09-Mar-23 28-Apr-23 27-Dec-23 14-Feb-24 238
HK Hols - No B/O periods
310.C.EX.W364 EVT (EA) - Road Paving works (was
C11_6C3)
d/w - 10h/d - With 40 2 21-Sep-23 09-Nov-23 15-Feb-24 05-Apr-24 118
HK Hols - No B/O periods
CC#06 - EVT - ABWF - Eastern Switch Ramp (ES) (was
C11_6C3)
d/w - 10h/d - With HK Hols
261- No B/O12
periods (was
21-Mar-23
C3) 03-Feb-24 27-Jun-23 20-May-24 83
310.C.EX.W392 EVT (ES) - brickwork and blockwork C11_6 d/w - 10h/d - With 40 2 21-Mar-23 11-May-23 27-Jun-23 12-Aug-23 77
HK Hols - No B/O periods
310.C.EX.W408 EVT (ES) - Builder works in connection with BS (was
C11_6C3)
d/w - 10h/d - With 40 2 21-Mar-23 11-May-23 27-Jun-23 12-Aug-23 77
HK Hols - No B/O periods
310.C.EX.W396 EVT (ES) - steel and metalwork (was
C11_6C3)
d/w - 10h/d - With 40 2 01-Apr-23 23-May-23 20-Jan-24 08-Mar-24 238
HK Hols - No B/O periods
310.C.EX.W400 EVT (ES) - plastering and screeding works (was
C11_6C3)
d/w - 10h/d - With 40 2 18-Apr-23 05-Jun-23 01-Feb-24 20-Mar-24 238
HK Hols - No B/O periods
310.C.EX.W404 EVT (ES) - Painting Works (was
C11_6C3)
d/w - 10h/d - With 40 2 29-Apr-23 16-Jun-23 15-Feb-24 05-Apr-24 238
HK Hols - No B/O periods
310.C.EX.W412 EVT (ES) - Road Paving works (was
C11_6C3)
d/w - 10h/d - With 36 2 21-Dec-23 03-Feb-24 06-Apr-24 20-May-24 83
HK Hols - No B/O periods
CC#06 - EVT - ABWF - Eastern Tunnel (ET) (was
C11_6C3)
d/w - 10h/d - With HK Hols
175- No B/O12
periods (was
24-Aug-23
C3) 23-Mar-24 15-Sep-23 03-Jul-24 79
310.C.EX.W319 EVT (ET) - remove temporary bulkheads C11_6 d/w - 10h/d - With 14 2 24-Aug-23 08-Sep-23 15-Sep-23 03-Oct-23 19
HK Hols - No B/O periods
310.C.EX.W320 EVT (ET) - brickwork and blockwork (was
C11_6C3)
d/w - 10h/d - With 38 01-Sep-23 17-Oct-23 23-Sep-23 09-Nov-23 19
HK Hols - No B/O periods
310.C.EX.W336 EVT (ET) - Builder works in connection with BS (was
C11_6C3)
d/w - 10h/d - With 40 2 01-Sep-23 19-Oct-23 06-Nov-23 21-Dec-23 53
HK Hols - No B/O periods
310.C.EX.W324 EVT (ET) - steel and metalwork (was
C11_6C3)
d/w - 10h/d - With 50 2 13-Sep-23 13-Nov-23 07-Oct-23 05-Dec-23 19
HK Hols - No B/O periods
310.C.EX.W328 EVT (ET) - plastering and screeding works (was
C11_6C3)
d/w - 10h/d - With 50 2 25-Sep-23 24-Nov-23 19-Oct-23 16-Dec-23 19
HK Hols - No B/O periods
310.C.EX.W332 EVT (ET) - Painting Works (was
C11_6C3)
d/w - 10h/d - With 50 2 09-Oct-23 06-Dec-23 01-Nov-23 30-Dec-23 19
HK Hols - No B/O periods
(was C3)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 110 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.EX.W340 EVT (ET) - Road Paving works C11_6 d/w - 10h/d - With 36 2 09-Feb-24 23-Mar-24 21-May-24 03-Jul-24 79
HK Hols - No B/O periods
CC#06 - EVT - Building Service Installation (was
C11_6C3)
d/w - 10h/d - With HK Hols
305- No B/O54
periods (was
02-Feb-23
C3) 08-Feb-24 10-Feb-23 29-May-24 87
CC#06 - EVT - MEP - Eastern Approach Ramp (EU) C11_6 d/w - 10h/d - With HK Hols
115- No B/O14
periods (was
02-Feb-23
C3) 23-Jun-23 10-Feb-23 06-Oct-23 87
310.C.EX.W464 EVT (EU) - Electrical Installation works C11_6 d/w - 10h/d - With 75 2 02-Feb-23 05-May-23 10-Feb-23 13-May-23 7
HK Hols - No B/O periods
310.C.EX.W484 EVT (EU) - Drainage Installation (was
C11_6C3)
d/w - 10h/d - With 75 2 02-Feb-23 05-May-23 10-Jul-23 06-Oct-23 127
HK Hols - No B/O periods
310.C.EX.W468 EVT (EU) - Tunnel Ventilation System Installation (was
C11_6C3)
d/w - 10h/d - With 75 2 14-Feb-23 17-May-23 22-Feb-23 25-May-23 7
HK Hols - No B/O periods
310.C.EX.W472 EVT (EU) - Air Quality Monitoring System (was
C11_6C3)
d/w - 10h/d - With 75 2 25-Feb-23 30-May-23 06-Mar-23 07-Jun-23 7
HK Hols - No B/O periods
310.C.EX.W476 EVT (EU) - Electrical and Control System (was
C11_6C3)
d/w - 10h/d - With 75 2 09-Mar-23 10-Jun-23 17-Mar-23 19-Jun-23 7
HK Hols - No B/O periods
310.C.EX.W480 EVT (EU) - FS Installation (was
C11_6C3)
d/w - 10h/d - With 75 2 21-Mar-23 23-Jun-23 29-Apr-23 29-Jul-23 30
HK Hols - No B/O periods
310.C.EX.W482 EVT (EU) - Plumbing System for FS (was
C11_6C3)
d/w - 10h/d - With 75 2 21-Mar-23 23-Jun-23 29-Mar-23 03-Jul-23 7
HK Hols - No B/O periods
CC#06 - EVT - MEP - Eastern Roundabout (EA) (was
C11_6C3)
d/w - 10h/d - With HK Hols
115- No B/O14
periods (was
06-May-23
C3) 20-Sep-23 15-May-23 06-Jan-24 87
310.C.EX.W440 EVT (EA) - Electrical Installation works C11_6 d/w - 10h/d - With 75 2 06-May-23 04-Aug-23 15-May-23 12-Aug-23 7
HK Hols - No B/O periods
310.C.EX.W460 EVT (EA) - Drainage Installation (was
C11_6C3)
d/w - 10h/d - With 75 2 06-May-23 04-Aug-23 07-Oct-23 06-Jan-24 127
HK Hols - No B/O periods
310.C.EX.W444 EVT (EA) - Tunnel Ventilation System Installation (was
C11_6C3)
d/w - 10h/d - With 75 2 18-May-23 16-Aug-23 27-May-23 24-Aug-23 7
HK Hols - No B/O periods
310.C.EX.W448 EVT (EA) - Air Quality Monitoring System (was
C11_6C3)
d/w - 10h/d - With 75 2 31-May-23 28-Aug-23 08-Jun-23 05-Sep-23 7
HK Hols - No B/O periods
310.C.EX.W452 EVT (EA) - Electrical and Control System (was
C11_6C3)
d/w - 10h/d - With 75 2 12-Jun-23 08-Sep-23 20-Jun-23 16-Sep-23 7
HK Hols - No B/O periods
310.C.EX.W456 EVT (EA) - FS Installation (was
C11_6C3)
d/w - 10h/d - With 75 2 24-Jun-23 20-Sep-23 31-Jul-23 28-Oct-23 30
HK Hols - No B/O periods
310.C.EX.W458 EVT (EA) - Plumbing System for FS (was
C11_6C3)
d/w - 10h/d - With 75 2 24-Jun-23 20-Sep-23 04-Jul-23 28-Sep-23 7
HK Hols - No B/O periods
CC#06 - EVT - MEP - Eastern Switch Ramp (ES) (was
C11_6C3)
d/w - 10h/d - With HK Hols
115- No B/O14
periods (was
05-Aug-23
C3) 20-Dec-23 14-Aug-23 10-Apr-24 87
310.C.EX.W488 EVT (ES) - Electrical Installation works C11_6 d/w - 10h/d - With 75 2 05-Aug-23 03-Nov-23 14-Aug-23 11-Nov-23 7
HK Hols - No B/O periods
310.C.EX.W508 EVT (ES) - Drainage Installation (was
C11_6C3)
d/w - 10h/d - With 75 2 05-Aug-23 03-Nov-23 08-Jan-24 10-Apr-24 127
HK Hols - No B/O periods
310.C.EX.W492 EVT (ES) - Tunnel Ventilation System Installation (was
C11_6C3)
d/w - 10h/d - With 75 2 17-Aug-23 15-Nov-23 25-Aug-23 23-Nov-23 7
HK Hols - No B/O periods
310.C.EX.W496 EVT (ES) - Air Quality Monitoring System (was
C11_6C3)
d/w - 10h/d - With 75 2 29-Aug-23 27-Nov-23 06-Sep-23 05-Dec-23 7
HK Hols - No B/O periods
310.C.EX.W500 EVT (ES) - Electrical and Control System (was
C11_6C3)
d/w - 10h/d - With 75 2 09-Sep-23 08-Dec-23 18-Sep-23 16-Dec-23 7
HK Hols - No B/O periods
310.C.EX.W504 EVT (ES) - FS Installation (was
C11_6C3)
d/w - 10h/d - With 75 2 21-Sep-23 20-Dec-23 30-Oct-23 27-Jan-24 30
HK Hols - No B/O periods
310.C.EX.W506 EVT (ES) - Plumbing System for FS (was
C11_6C3)
d/w - 10h/d - With 75 2 21-Sep-23 20-Dec-23 29-Sep-23 30-Dec-23 7
HK Hols - No B/O periods
CC#06 - EVT - MEP - Eastern Tunnel (ET) (was
C11_6C3)
d/w - 10h/d - With HK Hols
80- No B/O12
periods (was
04-Nov-23
C3) 08-Feb-24 17-Nov-23 29-May-24 87
310.C.EX.W416 EVT (ET) - Electrical Installation works C11_6 d/w - 10h/d - With 38 04-Nov-23 18-Dec-23 17-Nov-23 03-Jan-24 11
HK Hols - No B/O periods
(was C3)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 111 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.EX.W420 EVT (ET) - Tunnel Ventilation System Installation C11_6 d/w - 10h/d - With 40 2 16-Nov-23 04-Jan-24 29-Nov-23 17-Jan-24 11
HK Hols - No B/O periods
310.C.EX.W424 EVT (ET) - Air Quality Monitoring System (was
C11_6C3)
d/w - 10h/d - With 40 2 28-Nov-23 16-Jan-24 11-Dec-23 29-Jan-24 11
HK Hols - No B/O periods
310.C.EX.W436 EVT (ET) - Drainage Installation (was
C11_6C3)
d/w - 10h/d - With 40 2 28-Nov-23 16-Jan-24 11-Apr-24 29-May-24 107
HK Hols - No B/O periods
310.C.EX.W428 EVT (ET) - Electrical and Control System (was
C11_6C3)
d/w - 10h/d - With 40 2 09-Dec-23 27-Jan-24 21-Dec-23 08-Feb-24 10
HK Hols - No B/O periods
310.C.EX.W432 EVT (ET) - FS Installation (was
C11_6C3)
d/w - 10h/d - With 40 2 21-Dec-23 08-Feb-24 29-Jan-24 16-Mar-24 30
HK Hols - No B/O periods
310.C.EX.W434 EVT (ET) - Plumbing System for FS (was
C11_6C3)
d/w - 10h/d - With 40 2 21-Dec-23 08-Feb-24 02-Jan-24 19-Feb-24 7
HK Hols - No B/O periods
CC#06 - EVT - External Works (was
C11_6C3)
d/w - 10h/d - With HK Hols
172- No B/O18
periods (was
21-Sep-23
C3) 22-Apr-24 24-Feb-24 27-Jul-24 79
CC#06 - EVT - High Mast Lighting C11_6 d/w - 10h/d - With HK Hols
172- No B/O 8periods (was
21-Sep-23
C3) 22-Apr-24 24-Feb-24 27-Jul-24 79
310.C.EX.W442 EVT - External Works - High Mast Lighting - construct footing [2 nos.] C11_6 d/w - 10h/d - With 14 2 21-Sep-23 09-Oct-23 24-Feb-24 11-Mar-24 126
HK Hols - No B/O periods
310.C.EX.W446 EVT - External Works - High Mast Lighting - cable ducting (was
C11_6C3)
d/w - 10h/d - With 10 2 10-Oct-23 20-Oct-23 12-Mar-24 22-Mar-24 126
HK Hols - No B/O periods
310.C.EX.W454 EVT - External Works - High Mast Lighting - install lighting post [2 nos.] (was
C11_6C3)
d/w - 10h/d - With 5 2 25-Mar-24 02-Apr-24 04-Jul-24 09-Jul-24 79
HK Hols - No B/O periods
310.C.EX.W462 EVT - External Works - High Mast Lighting - Cabling and Fixing (was
C11_6C3)
d/w - 10h/d - With 16 2 03-Apr-24 22-Apr-24 10-Jul-24 27-Jul-24 79
HK Hols - No B/O periods
CC#06 - EVT - Concrete Pavement (was
C11_6C3)
d/w - 10h/d - With HK Hols
80- No B/O10
periods (was
21-Oct-23
C3) 26-Jan-24 23-Mar-24 03-Jul-24 126
310.C.EX.W438 EVT - External Works - Pavement (west side) - prepare sub-grade C11_6 d/w - 10h/d - With 16 2 21-Oct-23 09-Nov-23 23-Mar-24 15-Apr-24 126
HK Hols - No B/O periods
310.C.EX.W992 EVT - External Works - Pavement (east side) - prepare sub-grade (was
C11_6C3)
d/w - 10h/d - With 16 2 10-Nov-23 28-Nov-23 19-Apr-24 08-May-24 129
HK Hols - No B/O periods
310.C.EX.W450 EVT - External Works - Pavement (west side) - lay and compact 225thk sub-base (was
C11_6C3)
d/w - 10h/d - With 24 1 10-Nov-23 07-Dec-23 16-Apr-24 14-May-24 126
[4,580m2 @100m2/d/wf; 2wf] HK Hols - No B/O periods
310.C.EX.W990 EVT - External Works - Pavement (west side) - construct 6mx6m concrete pavement [130 (was
C11_6C3)
d/w - 10h/d - With 54 2 22-Nov-23 26-Jan-24 27-Apr-24 03-Jul-24 126
bays @2d/bay/wf; 5wf] HK Hols - No B/O periods
310.C.EX.W994 EVT - External Works - Pavement (east side) - lay and compact 225thk sub-base (was
C11_6C3)
d/w - 10h/d - With 19 1 29-Nov-23 20-Dec-23 09-May-24 31-May-24 129
[1,800m2 @100m2/d/wf; 1wf] HK Hols - No B/O periods
310.C.EX.W996 EVT - External Works - Pavement (east side) - construct 6mx6m concrete pavement [50 (was
C11_6C3)
d/w - 10h/d - With 35 2 11-Dec-23 23-Jan-24 22-May-24 03-Jul-24 129
bays @2d/bay/wf; 3wf] HK Hols - No B/O periods
CC#06 - Tunnel Plant Building A - PBA (was C3) 549 8 08-Dec-21 A 30-Jan-24 19-Apr-22 01-Jun-24 98
CC#06 - PBA - ELS Design - Excavation C01_7 d/w - 10h/d - No HK Hols213
- No B/O periods
0 (was01-Aug-22
C1) 01-Mar-23 21-Apr-23 19-Nov-23 263
ELS Design (Excavation) - PBA U/G Fuel Chamber C01_7 d/w - 10h/d - No HK Hols213
- No B/O periods
0 (was01-Aug-22
C1) 01-Mar-23 21-Apr-23 19-Nov-23 263
310.D.EX.H796.B01 PBA U/G Fuel Chamber - ELS design (Excavation) - prepare and submit to ICE for C01_7 d/w - 10h/d - No HK 45 01-Aug-22 14-Sep-22 21-Apr-23 04-Jun-23 263
reviewing Hols - No B/O periods (was
310.D.EX.H800.B01 PBA U/G Fuel Chamber - ELS design (Excavation) - ICE issue check certificate C1)
C01_7 d/w - 10h/d - No HK 3 15-Sep-22 17-Sep-22 05-Jun-23 07-Jun-23 263
Hols - No B/O periods (was
310.D.EX.H804.B01 PBA U/G Fuel Chamber - ELS design (Excavation) - PM, AP, RSE reviewing 1st Round C1)
C01_7 d/w - 10h/d - No HK 28 18-Sep-22 15-Oct-22 08-Jun-23 05-Jul-23 263
Hols - No B/O periods (was
310.D.EX.H824.B01 PBA U/G Fuel Chamber - ELS design (Excavation) - ICC, M&VC review design and issue C1)
C01_7 d/w - 10h/d - No HK 21 16-Oct-22 05-Nov-22 06-Jul-23 26-Jul-23 263
check certificates Hols - No B/O periods (was
310.D.EX.H816.B01 PBA U/G Fuel Chamber - ELS design (Excavation) - prepare and resubmit C1)
C01_7 d/w - 10h/d - No HK 7 06-Nov-22 12-Nov-22 27-Jul-23 02-Aug-23 263
Hols - No B/O periods (was
310.D.EX.H820.B01 PBA U/G Fuel Chamber - ELS design (Excavation) - PM, AP, RSE reviewing 2nd Round C1)
C01_7 d/w - 10h/d - No HK 28 13-Nov-22 10-Dec-22 03-Aug-23 30-Aug-23 263
Hols - No B/O periods (was
C1)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 112 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.EX.H808.B01 PBA U/G Fuel Chamber - ELS design (Excavation) - ICC, M&VC review design and issue C01_7 d/w - 10h/d - No HK 21 11-Dec-22 31-Dec-22 31-Aug-23 20-Sep-23 263
check certificates 2nd Round Hols - No B/O periods (was
310.D.EX.H812.B01 PBA U/G Fuel Chamber - ELS design (Excavation) - BD review and comment C1)
C01_7 d/w - 10h/d - No HK 60 01-Jan-23 01-Mar-23 21-Sep-23 19-Nov-23 263
Hols - No B/O periods (was
CC#06 - PBA - Submission of Method Statement C1)
C01_7 d/w - 10h/d - No HK Hols30
- No B/O periods
0 (was
08-Dec-21
C1) A 23-Apr-22 19-Apr-22 10-Oct-22 170
Method Statement for Construction of Airport Authority C01_7 d/w - 10h/d - No HK Hols30
- No B/O periods
0 (was
08-Dec-21
C1) A 23-Apr-22 19-Apr-22 10-Oct-22 170
310.D.TX.A156 MS no.22 - Method Statement for Construction of Air Authority Ancillary Buildings - C01_7 d/w - 10h/d - No HK 30 08-Dec-21 A 25-Feb-22 A 19-Apr-22 19-Apr-22
prepare document Hols - No B/O periods (was
310.D.TX.A160 MS no.22 - Method Statement for Construction of Air Authority Ancillary Buildings - PM C1)
C01_7 d/w - 10h/d - No HK 28 27-Mar-22 23-Apr-22 13-Sep-22 10-Oct-22 170
review and accept Hols - No B/O periods (was
CC#06 - PBA - Procurement C1)
C01_7 d/w - 10h/d - No HK Hols298
- No B/O periods
0 (was17-Jun-22
C1) 10-Apr-23 25-Aug-22 29-May-23 49
Procurement - MEP C01_7 d/w - 10h/d - No HK Hols298
- No B/O periods
0 (was17-Jun-22
C1) 10-Apr-23 04-Sep-22 29-May-23 49
310.P.RC.S66 PBA (Procurement Electrical & MVAC Major Equipment and Others) - Place Order for C01_7 d/w - 10h/d - No HK 30 17-Jun-22 16-Jul-22 09-Jan-23 07-Feb-23 206
Materials Hols - No B/O periods (was
310.P.RC.S78 PBA (Procurement Electrical & MVAC Major Equipment and Others) - Manufacturing of C1)
C01_7 d/w - 10h/d - No HK 120 24-Jun-22 21-Oct-22 16-Jan-23 15-May-23 206
Materials Hols - No B/O periods (was
310.P.RC.S62 PBA (Procurement FS and P&D Major Equipment) - Place Order for Materials C1)
C01_7 d/w - 10h/d - No HK 180 17-Jul-22 12-Jan-23 04-Sep-22 02-Mar-23 49
Hols - No B/O periods (was
310.P.RC.S74 PBA (Procurement FS and P&D Major Equipment) - Manufacturing of Materials C1)
C01_7 d/w - 10h/d - No HK 240 31-Jul-22 27-Mar-23 18-Sep-22 15-May-23 49
Hols - No B/O periods (was
310.P.RC.S82 PBA (Procurement MEP) - Delivery of Materials C1) d/w - 10h/d - No HK
C01_7 14 28-Mar-23 10-Apr-23 16-May-23 29-May-23 49
Hols - No B/O periods (was
Procurement - ABWF C1)
C01_7 d/w - 10h/d - No HK Hols116
- No B/O periods
0 (was23-Aug-22
C1) 16-Dec-22 25-Aug-22 18-Dec-22 2
310.P.RC.S150 PBA (Procurement ABWF) - Place Order for Materials C01_7 d/w - 10h/d - No HK 14 23-Aug-22 05-Sep-22 25-Aug-22 07-Sep-22 2
Hols - No B/O periods (was
310.P.RC.S154 PBA (Procurement ABWF) - Manufacturing of Materials C1)
C01_7 d/w - 10h/d - No HK 90 06-Sep-22 04-Dec-22 08-Sep-22 06-Dec-22 2
Hols - No B/O periods (was
310.P.RC.S162 PBA (Procurement ABWF) - Delivery of Materials C1)
C01_7 d/w - 10h/d - No HK 12 05-Dec-22 16-Dec-22 07-Dec-22 18-Dec-22 2
Hols - No B/O periods (was
CC#06 - PBA - Site Preparation and Establishment C1) 72 0 12-Jul-22 06-Oct-22 06-Aug-22 26-Oct-22 17
310.C.ES.P052 PBA (Coordination) - Interface meeting and coordination with other Contract for the Site C01_7 d/w - 10h/d - No HK 30 12-Jul-22 10-Aug-22 06-Aug-22 04-Sep-22 25
Access Hols - No B/O periods (was
310.C.ES.P060 PBA (Initial Works) - Site Access of WA3310/7 C1)
C01_7 d/w - 10h/d - No HK 0 05-Sep-22* 05-Sep-22 0
Hols - No B/O periods (was
310.C.ES.P064 PBA (Initial Works) - Site handover by other Contract at +3.0mPD C1)
C01_7 d/w - 10h/d - No HK 0 05-Sep-22 09-Sep-22 4
Hols - No B/O periods (was
310.C.ES.P072 PBA (Initial Works)- condition survey and carry out ground investigation (e.g. SI work and C1)
C11_6 d/w - 10h/d - With 6 05-Sep-22 12-Sep-22 09-Sep-22 16-Sep-22 4
SRT test) HK Hols - No B/O periods
310.C.ES.P068 PBA (Initial Works)- erect hoarding (was
C11_6C3)
d/w - 10h/d - With 6 05-Sep-22 12-Sep-22 20-Oct-22 26-Oct-22 36
HK Hols - No B/O periods
310.C.ES.P076 PBA (Initial Works)- carry out existing UU detection (i.e. existing drainage, UUs) (was
C11_6C3)
d/w - 10h/d - With 1 12-Sep-22 12-Sep-22 10-Oct-22 10-Oct-22 22
HK Hols - No B/O periods
310.C.ES.P108.B01 PBA (Initial Works)- diversion of underground utilities (if any) (was
C01_7C3)
d/w - 10h/d - No HK 24 13-Sep-22 06-Oct-22 17-Sep-22 10-Oct-22 4
Hols - No B/O periods (was
CC#06 - PBA - Earthwork C1) 18 0 25-Sep-22 18-Oct-22 26-Sep-22 19-Oct-22 1
310.C.ES.P078 PBA - Anticipated BD approval of Foundation, superstructure and drainage plan C01_7 d/w - 10h/d - No HK 0 25-Sep-22 26-Sep-22 1
Hols - No B/O periods (was
310.C.ES.P080 PBA (Foundation, superstructure, fuel chamber and drainage - BD Submission)- submit C1)
C01_7 d/w - 10h/d - No HK 7 26-Sep-22 02-Oct-22 27-Sep-22 03-Oct-22 1
BA8 consent application Hols - No B/O periods (was
310.C.ES.P084 PBA (Foundation, superstructure, fuel chamber and drainage - BD Submission)- BD C1)
C01_7 d/w - 10h/d - No HK 0 02-Oct-22 03-Oct-22 1
issued consent (BA8) Hols - No B/O periods (was
C1)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 113 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.ES.P088 PBA (Foundation - BD Submission) - submit BA10 commencement of work and C01_7 d/w - 10h/d - No HK 7 03-Oct-22 09-Oct-22 04-Oct-22 10-Oct-22 1
acknowledgement Hols - No B/O periods (was
310.C.ES.P092 PBA (Earthworks)- Excavation down to formation level C1)
C11_6 d/w - 10h/d - With 5 10-Oct-22 14-Oct-22 11-Oct-22 15-Oct-22 1
HK Hols - No B/O periods
310.C.ES.P096 PBA (Instrumentation) - install Instrumentation (settlement monitoring) (was
C11_6C3)
d/w - 10h/d - With 3 15-Oct-22 18-Oct-22 17-Oct-22 19-Oct-22 1
HK Hols - No B/O periods
CC#06 - PBA - Structural Works (was
C11_6C3)
d/w - 10h/d - With HK Hols
183- No B/O 2periods (was
19-Oct-22
C3) 01-Jun-23 20-Oct-22 24-Jan-24 195
PBA - Initial Works C11_6 d/w - 10h/d - With HK Hols6 - No B/O 0periods (was
19-Oct-22
C3) 25-Oct-22 20-Oct-22 26-Oct-22 1
310.C.ES.P100 PBA (Foundation)- plate load test C11_6 d/w - 10h/d - With 6 19-Oct-22 25-Oct-22 20-Oct-22 26-Oct-22 1
HK Hols - No B/O periods
PBA - Grid 3-5/A-D (was
C11_6C3)
d/w - 10h/d - With HK Hols
76- No B/O 2periods (was
26-Oct-22
C3) 27-Jan-23 27-Oct-22 07-Feb-23 9
310.C.ES.P112 PBA Grid 3-5/A-D(Foundation) - construction of foundation/base slab C11_6 d/w - 10h/d - With 16 26-Oct-22 12-Nov-22 27-Oct-22 14-Nov-22 1
HK Hols - No B/O periods
310.C.ES.P128 PBA Grid 3-5/A-D (1F Comms Room & associated rooms) - construct 1F columns, (was
C11_6C3)
d/w - 10h/d - With 14 1 14-Nov-22 29-Nov-22 15-Nov-22 30-Nov-22 1
beams, slabs, walls HK Hols - No B/O periods
310.C.ES.P132 PBA Grid 3-5/A-D (RF Comms Room & associated rooms) - construct RF columns, (was
C11_6C3)
d/w - 10h/d - With 15 1 30-Nov-22 16-Dec-22 01-Dec-22 17-Dec-22 1
beams, slab, walls HK Hols - No B/O periods
310.C.ES.P136 PBA Grid 3-5/A-D (GF) - remove falsework for 1F and construct upstand wall, mass fill (was
C11_6C3)
d/w - 10h/d - With 10 06-Dec-22 16-Dec-22 08-Dec-22 19-Dec-22 2
HK Hols - No B/O periods
310.C.ES.P140 PBA Grid 3-5/A-D (GF) - construct GF slab, beams (was
C11_6C3)
d/w - 10h/d - With 10 17-Dec-22 29-Dec-22 20-Dec-22 31-Dec-22 2
HK Hols - No B/O periods
310.C.ES.P144 PBA Grid 3-5/A-D (GF) - construct staircases (was
C11_6C3)
d/w - 10h/d - With 14 30-Dec-22 16-Jan-23 03-Jan-23 18-Jan-23 2
HK Hols - No B/O periods
310.C.ES.P148 PBA (Water Tanks) - construction of FS water tank, Foam Sys Water Tank, (was
C11_6C3)
d/w - 10h/d - With 21 30-Dec-22 27-Jan-23 11-Jan-23 07-Feb-23 9
HK Hols - No B/O periods
PBA - Grid 1-3/A-D (was
C11_6C3)
d/w - 10h/d - With HK Hols
86- No B/O 0periods (was
30-Dec-22
C3) 18-Apr-23 11-Jan-23 28-Apr-23 9
310.C.ES.P164 PBA Grid 1-3/A-D(Foundation ) - construction of foundation/base slab C11_6 d/w - 10h/d - With 16 30-Dec-22 18-Jan-23 11-Jan-23 01-Feb-23 9
HK Hols - No B/O periods
310.C.ES.P168 PBA Grid 1-3/A-D (GF) - construct upstand wall, column and mass fill (was
C11_6C3)
d/w - 10h/d - With 16 19-Jan-23 09-Feb-23 02-Feb-23 20-Feb-23 9
HK Hols - No B/O periods
310.C.ES.P172 PBA (1F - Grid 1-3, A-D) - construction of double slab below FF, hanging walls, beams, (was
C11_6C3)
d/w - 10h/d - With 18 10-Feb-23 02-Mar-23 21-Feb-23 13-Mar-23 9
FF slab, FF walls HK Hols - No B/O periods
310.C.ES.P176 PBA Grid 1-3/A-D (1F) - construct columns, beams, slab, and external walls (was
C11_6C3)
d/w - 10h/d - With 18 03-Mar-23 23-Mar-23 14-Mar-23 03-Apr-23 9
HK Hols - No B/O periods
310.C.ES.P180 PBA Grid 1-3/A-D (RF) - construct columns, beams, roof slab (was
C11_6C3)
d/w - 10h/d - With 18 24-Mar-23 18-Apr-23 04-Apr-23 28-Apr-23 9
HK Hols - No B/O periods
PBA - UG Fuel Chamber (was
C11_6C3)
d/w - 10h/d - With HK Hols
54- No B/O 0periods (was
24-Mar-23
C3) 01-Jun-23 20-Nov-23 24-Jan-24 195
310.C.ES.P832.B01 PBA (UG Fuel Chamber) - ELS down to formation level C11_6 d/w - 10h/d - With 24 24-Mar-23 25-Apr-23 20-Nov-23 16-Dec-23 195
HK Hols - No B/O periods
310.C.ES.P448 PBA (UG Fuel Chamber) - construction of Underground Fuel Chamber (was
C11_6C3)
d/w - 10h/d - With 30 26-Apr-23 01-Jun-23 18-Dec-23 24-Jan-24 195
HK Hols - No B/O periods
PBA - Others (was
C11_6C3)
d/w - 10h/d - With HK Hols
12- No B/O 0periods (was
19-Apr-23
C3) 03-May-23 02-May-23 15-May-23 10
310.C.ES.P184 PBA (Roof Top) - dog house structure C11_6 d/w - 10h/d - With 12 19-Apr-23 03-May-23 02-May-23 15-May-23 10
HK Hols - No B/O periods
CC#06 - PBA - ABWF (was
C11_6C3)
d/w - 10h/d - With HK Hols
198- No B/O 0periods (was
08-May-23
C3) 04-Jan-24 17-Jun-23 18-Apr-24 84
310.C.EX.W160 PBA Structure completed, curing and complete removal of falseworks C11_6 d/w - 10h/d - With 0 08-May-23 17-Jun-23 34
HK Hols - No B/O periods
310.C.EX.W112 PBA Partition Wall & Door Subframe (was
C11_6C3)
d/w - 10h/d - With 128 09-May-23 10-Oct-23 12-Aug-23 15-Jan-24 79
HK Hols - No B/O periods
310.C.EX.W144 PBA Plastering & Screeding (was
C11_6C3)
d/w - 10h/d - With 128 20-May-23 21-Oct-23 24-Aug-23 26-Jan-24 79
HK Hols - No B/O periods
(was C3)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 114 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.EX.W148 PBA Tiling & Stonework C11_6 d/w - 10h/d - With 128 02-Jun-23 03-Nov-23 05-Sep-23 07-Feb-24 79
HK Hols - No B/O periods
310.C.EX.W152 PBA Suspended Ceiling Framework (was
C11_6C3)
d/w - 10h/d - With 124 14-Jun-23 10-Nov-23 16-Sep-23 16-Feb-24 79
HK Hols - No B/O periods
310.C.EX.W156 PBA Sanitary Ware & Fixtures (was
C11_6C3)
d/w - 10h/d - With 124 27-Jun-23 22-Nov-23 28-Sep-23 28-Feb-24 79
HK Hols - No B/O periods
310.C.EX.W172 PBA Door Sets & Ironmongery (was
C11_6C3)
d/w - 10h/d - With 124 10-Jul-23 04-Dec-23 18-Oct-23 16-Mar-24 84
HK Hols - No B/O periods
310.C.EX.W176 PBA Glazing (was
C11_6C3)
d/w - 10h/d - With 124 21-Jul-23 15-Dec-23 31-Oct-23 28-Mar-24 84
HK Hols - No B/O periods
310.C.EX.W180 PBA Ceiling Panels & Finishes (was
C11_6C3)
d/w - 10h/d - With 124 02-Aug-23 29-Dec-23 11-Nov-23 13-Apr-24 84
HK Hols - No B/O periods
310.C.EX.W184 PBA Painting, Graphics & Signage (was
C11_6C3)
d/w - 10h/d - With 124 07-Aug-23 04-Jan-24 16-Nov-23 18-Apr-24 84
HK Hols - No B/O periods
CC#06 - PBA - MEP Installation Works (was
C11_6C3)
d/w - 10h/d - With HK Hols
332- No B/O 6periods (was
17-Dec-22
C3) 30-Jan-24 19-Dec-22 18-Apr-24 62
CC#06 - PBA - Transformers (CLP) C11_6 d/w - 10h/d - With HK Hols
149- No B/O 2periods (was
19-Apr-23
C3) 16-Oct-23 29-Apr-23 27-Oct-23 9
310.C.EX.W100 PBA Complete Transformer Room Structure C11_6 d/w - 10h/d - With 0 19-Apr-23 29-Apr-23 9
HK Hols - No B/O periods
310.C.EX.W108 PBA Builder Works in Transformer Room (was
C11_6C3)
d/w - 10h/d - With 42 19-Apr-23 08-Jun-23 29-Apr-23 19-Jun-23 9
HK Hols - No B/O periods
310.C.EX.W2232 PBA MEP Works in Transformer Room (was
C11_6C3)
d/w - 10h/d - With 42 18-May-23 08-Jul-23 30-May-23 19-Jul-23 9
HK Hols - No B/O periods
310.C.EX.W164 PBA Inspection & Handover Transformer Room to CLP (was
C11_6C3)
d/w - 10h/d - With 18 10-Jul-23 29-Jul-23 20-Jul-23 09-Aug-23 9
HK Hols - No B/O periods
310.C.EX.W189 PBA Transformer Installation by CLP (was
C11_6C3)
d/w - 10h/d - With 65 31-Jul-23 16-Oct-23 10-Aug-23 27-Oct-23 9
HK Hols - No B/O periods
310.C.EX.W225 PBA Cable Laying by CLP (was
C11_6C3)
d/w - 10h/d - With 24 2 13-Sep-23 12-Oct-23 25-Sep-23 25-Oct-23 10
HK Hols - No B/O periods
310.C.EX.W236 PBA Energization of Transformers (was
C11_6C3)
d/w - 10h/d - With 0 16-Oct-23 27-Oct-23 9
HK Hols - No B/O periods
CC#06 - PBA - Plumbing & Drainage Installation (was
C11_6C3)
d/w - 10h/d - With HK Hols
160- No B/O 0periods (was
07-Jul-23
C3) 16-Jan-24 24-Jul-23 01-Feb-24 14
310.C.EX.W124 PBA Plumbing & Drainage 1st Fix & Installation C11_6 d/w - 10h/d - With 96 07-Jul-23 30-Oct-23 24-Jul-23 15-Nov-23 14
HK Hols - No B/O periods
310.C.EX.W140 PBA Water Pump Installation (was
C11_6C3)
d/w - 10h/d - With 48 17-Jul-23 09-Sep-23 25-Sep-23 22-Nov-23 60
HK Hols - No B/O periods
310.C.EX.W201 PBA Plumbing & Drainage 2nd Fix & Installation (was
C11_6C3)
d/w - 10h/d - With 72 01-Sep-23 27-Nov-23 18-Sep-23 13-Dec-23 14
HK Hols - No B/O periods
310.C.EX.W252 PBA Plumbing & Drainage Final Fix & Adjustment (was
C11_6C3)
d/w - 10h/d - With 18 23-Dec-23 16-Jan-24 12-Jan-24 01-Feb-24 14
HK Hols - No B/O periods
CC#06 - PBA - Electrical Installation (was
C11_6C3)
d/w - 10h/d - With HK Hols
159- No B/O 0periods (was
19-Jun-23
C3) 28-Dec-23 03-Jul-23 18-Apr-24 89
310.C.EX.W116 PBA Electrical 1st Fix & Installation C11_6 d/w - 10h/d - With 75 19-Jun-23 15-Sep-23 03-Jul-23 27-Sep-23 10
HK Hols - No B/O periods
310.C.EX.W104 PBA Switchgear Installation (was
C11_6C3)
d/w - 10h/d - With 48 19-Jul-23 12-Sep-23 31-Jul-23 23-Sep-23 10
HK Hols - No B/O periods
310.C.EX.W132 PBA Emergency Genset Installation (was
C11_6C3)
d/w - 10h/d - With 48 19-Jul-23 12-Sep-23 27-Nov-23 24-Jan-24 109
HK Hols - No B/O periods
310.C.EX.W193 PBA Electrical 2nd Fix & Installation (was
C11_6C3)
d/w - 10h/d - With 72 22-Jul-23 16-Oct-23 12-Dec-23 09-Mar-24 119
HK Hols - No B/O periods
310.C.EX.W232 PBA Power On to All Floors (was
C11_6C3)
d/w - 10h/d - With 0 16-Oct-23 01-Feb-24 89
HK Hols - No B/O periods
(was C3)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 115 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.EX.W268 PBA Electrical Final Fix & Adjustment C11_6 d/w - 10h/d - With 18 06-Dec-23 28-Dec-23 25-Mar-24 18-Apr-24 89
HK Hols - No B/O periods
CC#06 - PBA - Fire Services Installation (was
C11_6C3)
d/w - 10h/d - With HK Hols
172- No B/O 0periods (was
07-Jul-23
C3) 30-Jan-24 10-Aug-23 06-Mar-24 29
310.C.EX.W128 PBA Fire Services 1st Fix & Installation C11_6 d/w - 10h/d - With 96 07-Jul-23 30-Oct-23 10-Aug-23 02-Dec-23 29
HK Hols - No B/O periods
310.C.EX.W136 PBA FS Pump Installation (was
C11_6C3)
d/w - 10h/d - With 48 17-Jul-23 09-Sep-23 30-Oct-23 23-Dec-23 87
HK Hols - No B/O periods
310.C.EX.W209 PBA Fire Services 2nd Fix & Installation (was
C11_6C3)
d/w - 10h/d - With 72 01-Sep-23 27-Nov-23 07-Oct-23 03-Jan-24 29
HK Hols - No B/O periods
310.C.EX.W264 PBA Fire Service Final Fix & Adjustment (was
C11_6C3)
d/w - 10h/d - With 18 10-Jan-24 30-Jan-24 15-Feb-24 06-Mar-24 29
HK Hols - No B/O periods
CC#06 - PBA - MVAC Installation (was
C11_6C3)
d/w - 10h/d - With HK Hols
156- No B/O 0periods (was
07-Jul-23
C3) 11-Jan-24 12-Sep-23 20-Mar-24 57
310.C.EX.W120 PBA MVAC 1st Fix & Installation C11_6 d/w - 10h/d - With 96 07-Jul-23 30-Oct-23 12-Sep-23 08-Jan-24 57
HK Hols - No B/O periods
310.C.EX.W197 PBA MVAC 2nd Fix & Installation (was
C11_6C3)
d/w - 10h/d - With 72 01-Sep-23 27-Nov-23 17-Nov-23 14-Feb-24 63
HK Hols - No B/O periods
310.C.EX.W260 PBA MVAC Final Fix & Adjustment (was
C11_6C3)
d/w - 10h/d - With 18 19-Dec-23 11-Jan-24 29-Feb-24 20-Mar-24 57
HK Hols - No B/O periods
CC#06 - PBA - Comms Room and Associated Rooms (was
C11_6C3)
d/w - 10h/d - With HK Hols
55- No B/O 4periods (was
17-Dec-22
C3) 24-Feb-23 19-Dec-22 25-Feb-23 1
310.C.ES.P104 PBA ABWF (Comms Room) - Commence ABWF works C11_6 d/w - 10h/d - With 0 17-Dec-22 19-Dec-22 1
HK Hols - No B/O periods
310.C.ES.P296 PBA (Comms Room 1st Degree - 3rd Degree) - ABWF Works (floor screed, partition (was
C11_6C3)
d/w - 10h/d - With 20 1 17-Dec-22 11-Jan-23 19-Dec-22 12-Jan-23 1
walls, installed conduits) HK Hols - No B/O periods
310.C.ES.P400 PBA (Novec 1234 Comms Room 1st Degree - 3rd Degree) - ABWF works Comms Rooms (was
C11_6C3)
d/w - 10h/d - With 20 1 23-Dec-22 17-Jan-23 24-Dec-22 18-Jan-23 1
(wall, floors, ceiling, doors) HK Hols - No B/O periods
310.C.ES.P404 PBA (Comms Room) - Commence Building Services works (was
C11_6C3)
d/w - 10h/d - With 0 30-Dec-22 31-Dec-22 1
HK Hols - No B/O periods
310.C.ES.P408 PBA (Comms Room 1st Fix - Final Fix) -Building Services Installations (was
C11_6C3)
d/w - 10h/d - With 45 2 30-Dec-22 24-Feb-23 31-Dec-22 25-Feb-23 1
HK Hols - No B/O periods
CC#06 - PBA - External Works (was
C11_6C3)
d/w - 10h/d - With HK Hols
166- No B/O 0periods (was
04-May-23
C3) 20-Nov-23 16-May-23 01-Jun-24 156
CC#06 - PBA - External Building Finishes C11_6 d/w - 10h/d - With HK Hols
139- No B/O 0periods (was
04-May-23
C3) 18-Oct-23 16-May-23 01-Jun-24 183
310.C.ES.P188 PBA Roof Top waterproofing C11_6 d/w - 10h/d - With 28 04-May-23 06-Jun-23 16-May-23 17-Jun-23 10
HK Hols - No B/O periods
310.C.ES.P388 PBA External building finishes (was
C11_6C3)
d/w - 10h/d - With 72 07-Jun-23 31-Aug-23 28-Jun-23 20-Sep-23 17
HK Hols - No B/O periods
310.C.ES.P324 PBA Hard and soft landscape woks (was
C11_6C3)
d/w - 10h/d - With 21 22-Sep-23 18-Oct-23 08-May-24 01-Jun-24 183
HK Hols - No B/O periods
CC#06 - PBA - Drainage and UU (was
C11_6C3)
d/w - 10h/d - With HK Hols
90- No B/O 0periods (was
07-Jun-23
C3) 21-Sep-23 28-Jun-23 27-Oct-23 28
310.C.ES.P312 PBA Building drainage and watermain works C11_6 d/w - 10h/d - With 45 07-Jun-23 31-Jul-23 28-Jun-23 19-Aug-23 17
HK Hols - No B/O periods
310.C.ES.P315 PBA CLP Cable ducts + drawpits (was
C11_6C3)
d/w - 10h/d - With 30 01-Aug-23 04-Sep-23 21-Aug-23 23-Sep-23 17
HK Hols - No B/O periods
310.C.ES.P316 PBA AS Cable ducts + drawpits (was
C11_6C3)
d/w - 10h/d - With 45 01-Aug-23 21-Sep-23 02-Sep-23 27-Oct-23 28
HK Hols - No B/O periods
310.C.ES.P320 PBA cable ducting + drawpits (was
C11_6C3)
d/w - 10h/d - With 45 01-Aug-23 21-Sep-23 02-Sep-23 27-Oct-23 28
HK Hols - No B/O periods
CC#06 - PBA - EVA Construction (was
C11_6C3)
d/w - 10h/d - With HK Hols
48- No B/O 0periods (was
22-Sep-23
C3) 20-Nov-23 19-Feb-24 18-Apr-24 120
310.C.ES.P330 PBA Site Formation Works and Road Works for EVA C11_6 d/w - 10h/d - With 48 22-Sep-23 20-Nov-23 19-Feb-24 18-Apr-24 120
HK Hols - No B/O periods
CC#06 - Tunnel Plant Building C - PBC (was C3) 168 7 12-May-22 29-Nov-22 13-May-22 27-Dec-22 23
CC#06 - PBC - Procurement C01_7 d/w - 10h/d - No HK Hols130
- No B/O periods
0 (was12-May-22
C1) 18-Sep-22 13-May-22 19-Sep-22 1

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 116 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
Procurement - MEP C01_7 d/w - 10h/d - No HK Hols119
- No B/O periods
0 (was12-May-22
C1) 07-Sep-22 13-May-22 08-Sep-22 1
310.P.RC.S90 PBC (Procurement Electrical & MVAC Major Equipment and Others) - Place Order for C01_7 d/w - 10h/d - No HK 50 12-May-22 30-Jun-22 13-May-22 01-Jul-22 1
Material Hols - No B/O periods (was
310.P.RC.S86 PBC (Procurement FS and P&D Major Equipment) - Place Order for Material C1)
C01_7 d/w - 10h/d - No HK 105 23-May-22 04-Sep-22 24-May-22 05-Sep-22 1
Hols - No B/O periods (was
310.P.RC.S102 PBC (Procurement FS and P&D Major Equipment) - Manufacturing of Material C1)
C01_7 d/w - 10h/d - No HK 105 26-May-22 07-Sep-22 27-May-22 08-Sep-22 1
Hols - No B/O periods (was
310.P.RC.S106 PBC (Procurement Electrical & MVAC Major Equipment and Others) - Manufacturing of C1)
C01_7 d/w - 10h/d - No HK 90 03-Jun-22 31-Aug-22 04-Jun-22 01-Sep-22 1
Material Hols - No B/O periods (was
310.P.RC.S110 PBC (Procurement MEP) - Delivery of Material C1)
C01_7 d/w - 10h/d - No HK 7 01-Sep-22 07-Sep-22 02-Sep-22 08-Sep-22 1
Hols - No B/O periods (was
Procurement - ABWF C1)
C01_7 d/w - 10h/d - No HK Hols104
- No B/O periods
0 (was07-Jun-22
C1) 18-Sep-22 08-Jun-22 19-Sep-22 1
310.P.RC.S174 PBC (Procurement ABWF) - Place Order for Materials C01_7 d/w - 10h/d - No HK 4 07-Jun-22 10-Jun-22 08-Jun-22 11-Jun-22 1
Hols - No B/O periods (was
310.P.RC.S178 PBC (Procurement ABWF) - Manufacturing of Materials C1)
C01_7 d/w - 10h/d - No HK 100 11-Jun-22 18-Sep-22 12-Jun-22 19-Sep-22 1
Hols - No B/O periods (was
310.P.RC.S186 PBC (Procurement ABWF) - Delivery of Materials C1)
C01_7 d/w - 10h/d - No HK 7 12-Sep-22 18-Sep-22 13-Sep-22 19-Sep-22 1
Hols - No B/O periods (was
CC#06 - PBC - Preparation and Initial Works C1)
C11_6 d/w - 10h/d - With HK Hols0 - No B/O 0periods (was
05-Sep-22
C3) 05-Sep-22 03-Sep-22 05-Sep-22 0
310.C.EX.P002 PBC - Handover inspection and acceptance from Contract <3302> C11_6 d/w - 10h/d - With 0 05-Sep-22 03-Sep-22 0
HK Hols - No B/O periods
310.C.EX.P006 PBC - Access to Tunnel Plant Building C from Contract <3302> (was
C11_6C3)
d/w - 10h/d - With 0 05-Sep-22* 05-Sep-22 0
HK Hols - No B/O periods
310.C.EX.P010 PBC - Commence ABWF, MEP Works (was
C11_6C3)
d/w - 10h/d - With 0 05-Sep-22 05-Sep-22 0
HK Hols - No B/O periods
CC#06 - PBC - ABWF (was
C11_6C3)
d/w - 10h/d - With HK Hols
61- No B/O 0periods (was
05-Sep-22
C3) 17-Nov-22 07-Sep-22 18-Nov-22 1
310.C.EX.W1136 PBC Plastering & Screeding C11_6 d/w - 10h/d - With 50 05-Sep-22 04-Nov-22 20-Sep-22 18-Nov-22 12
HK Hols - No B/O periods
310.C.EX.W1140 PBC Tiling & Stonework (was
C11_6C3)
d/w - 10h/d - With 50 05-Sep-22 04-Nov-22 20-Sep-22 18-Nov-22 12
HK Hols - No B/O periods
310.C.EX.W1144 PBC Suspended Ceiling Framework (was
C11_6C3)
d/w - 10h/d - With 50 05-Sep-22 04-Nov-22 20-Sep-22 18-Nov-22 12
HK Hols - No B/O periods
310.C.EX.W1148 PBC Sanitary Ware & Fixtures (was
C11_6C3)
d/w - 10h/d - With 50 05-Sep-22 04-Nov-22 08-Sep-22 08-Nov-22 3
HK Hols - No B/O periods
310.C.EX.W1152 PBC Door Sets & Ironmongery (was
C11_6C3)
d/w - 10h/d - With 50 05-Sep-22 04-Nov-22 20-Sep-22 18-Nov-22 12
HK Hols - No B/O periods
310.C.EX.W1156 PBC Glazing (was
C11_6C3)
d/w - 10h/d - With 50 05-Sep-22 04-Nov-22 20-Sep-22 18-Nov-22 12
HK Hols - No B/O periods
310.C.EX.W1160 PBC Ceiling Panels & Finishes (was
C11_6C3)
d/w - 10h/d - With 50 05-Sep-22 04-Nov-22 07-Sep-22 07-Nov-22 2
HK Hols - No B/O periods
310.C.EX.W1132 PBC Partition Wall & Door Subframe (was
C11_6C3)
d/w - 10h/d - With 50 19-Sep-22 17-Nov-22 20-Sep-22 18-Nov-22 1
HK Hols - No B/O periods
310.C.EX.W1164 PBC Painting, Graphics & Signage (was
C11_6C3)
d/w - 10h/d - With 50 19-Sep-22 17-Nov-22 20-Sep-22 18-Nov-22 1
HK Hols - No B/O periods
310.C.EX.W2240 PBC Material Hoist & Roller Shutter (was
C11_6C3)
d/w - 10h/d - With 30 14-Oct-22 17-Nov-22 15-Oct-22 18-Nov-22 1
HK Hols - No B/O periods
CC#06 - PBC MEP Installation Works (was
C11_6C3)
d/w - 10h/d - With HK Hols
61- No B/O 7periods (was
05-Sep-22
C3) 17-Nov-22 06-Sep-22 27-Dec-22 33
Transformers (CLP) C11_6 d/w - 10h/d - With HK Hols
61- No B/O 3periods (was
05-Sep-22
C3) 17-Nov-22 06-Sep-22 18-Nov-22 1
310.C.EX.W1168 PBC Complete Transformer Room Structure C11_6 d/w - 10h/d - With 0 05-Sep-22 06-Sep-22 1
HK Hols - No B/O periods
(was C3)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 117 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.EX.W1092 PBC Builder Works in Transformer Room C11_6 d/w - 10h/d - With 12 05-Sep-22 19-Sep-22 06-Sep-22 20-Sep-22 1
HK Hols - No B/O periods
310.C.EX.W2236 PBC MEP Works in Transformer Room (was
C11_6C3)
d/w - 10h/d - With 12 08-Sep-22 22-Sep-22 09-Sep-22 23-Sep-22 1
HK Hols - No B/O periods
310.C.EX.W1096 PBC Inspection & Handover Transformer Room to CLP (was
C11_6C3)
d/w - 10h/d - With 6 23-Sep-22 29-Sep-22 24-Sep-22 30-Sep-22 1
HK Hols - No B/O periods
310.C.EX.W1100 PBC Transformer Installation by CLP (was
C11_6C3)
d/w - 10h/d - With 40 30-Sep-22 17-Nov-22 03-Oct-22 18-Nov-22 1
HK Hols - No B/O periods
310.C.EX.W1172 PBC Cable Laying by CLP (was
C11_6C3)
d/w - 10h/d - With 30 3 13-Oct-22 16-Nov-22 15-Oct-22 18-Nov-22 2
HK Hols - No B/O periods
310.C.EX.W1104 PBC Energization of Transformers (was
C11_6C3)
d/w - 10h/d - With 0 17-Nov-22 18-Nov-22 1
HK Hols - No B/O periods
Plumbing & Drainage Installation (was
C11_6C3)
d/w - 10h/d - With HK Hols
41- No B/O 0periods (was
12-Sep-22
C3) 31-Oct-22 12-Sep-22 31-Oct-22 0
310.C.EX.W1116 PBC Water Pump Installation C11_6 d/w - 10h/d - With 10 12-Sep-22 22-Sep-22 12-Sep-22 22-Sep-22 0
HK Hols - No B/O periods
310.C.EX.W1108 PBC Plumbing & Drainage 1st Fix & Installation (was
C11_6C3)
d/w - 10h/d - With 15 12-Sep-22 28-Sep-22 12-Sep-22 28-Sep-22 0
HK Hols - No B/O periods
310.C.EX.W1112 PBC Plumbing & Drainage 2nd Fix & Installation (was
C11_6C3)
d/w - 10h/d - With 15 15-Sep-22 03-Oct-22 17-Sep-22 06-Oct-22 2
HK Hols - No B/O periods
310.C.EX.W1128 PBC Plumbing & Drainage Final Fix & Adjustment (was
C11_6C3)
d/w - 10h/d - With 7 24-Oct-22 31-Oct-22 24-Oct-22 31-Oct-22 0
HK Hols - No B/O periods
Electrical Installation (was
C11_6C3)
d/w - 10h/d - With HK Hols
54- No B/O 0periods (was
14-Sep-22
C3) 17-Nov-22 15-Sep-22 18-Nov-22 1
310.C.EX.W1016 PBC Electrical 1st Fix & Installation C11_6 d/w - 10h/d - With 20 14-Sep-22 08-Oct-22 15-Sep-22 10-Oct-22 1
HK Hols - No B/O periods
310.C.EX.W1024 PBC Switchgear Installation (was
C11_6C3)
d/w - 10h/d - With 20 20-Sep-22 14-Oct-22 28-Sep-22 22-Oct-22 7
HK Hols - No B/O periods
310.C.EX.W1020 PBC Electrical 2nd Fix & Installation (was
C11_6C3)
d/w - 10h/d - With 20 26-Sep-22 20-Oct-22 30-Sep-22 25-Oct-22 4
HK Hols - No B/O periods
310.C.EX.W1028 PBC Emergency Genset Installation (was
C11_6C3)
d/w - 10h/d - With 14 06-Oct-22 21-Oct-22 07-Oct-22 22-Oct-22 1
HK Hols - No B/O periods
310.C.EX.W1032 PBC Provide Temporary Power for Power On to All Floors (was
C11_6C3)
d/w - 10h/d - With 0 21-Oct-22 22-Oct-22 1
HK Hols - No B/O periods
310.C.EX.W1044 PBC Electrical Final Fix & Adjustment (was
C11_6C3)
d/w - 10h/d - With 7 10-Nov-22 17-Nov-22 11-Nov-22 18-Nov-22 1
HK Hols - No B/O periods
Fire Services Installation (was
C11_6C3)
d/w - 10h/d - With HK Hols
48- No B/O 0periods (was
14-Sep-22
C3) 10-Nov-22 14-Sep-22 10-Nov-22 0
310.C.EX.W1048 PBC Fire Services 1st Fix & Installation C11_6 d/w - 10h/d - With 18 14-Sep-22 06-Oct-22 14-Sep-22 06-Oct-22 0
HK Hols - No B/O periods
310.C.EX.W1052 PBC Fire Services 2nd Fix & Installation (was
C11_6C3)
d/w - 10h/d - With 18 22-Sep-22 14-Oct-22 22-Sep-22 14-Oct-22 0
HK Hols - No B/O periods
310.C.EX.W1056 PBC FS Pump Installation (was
C11_6C3)
d/w - 10h/d - With 10 23-Sep-22 06-Oct-22 03-Oct-22 14-Oct-22 7
HK Hols - No B/O periods
310.C.EX.W1068 PBC Fire Services Final Fix & Adjustment (was
C11_6C3)
d/w - 10h/d - With 7 03-Nov-22 10-Nov-22 03-Nov-22 10-Nov-22 0
HK Hols - No B/O periods
MVAC Installation (was
C11_6C3)
d/w - 10h/d - With HK Hols
46- No B/O 0periods (was
14-Sep-22
C3) 08-Nov-22 16-Sep-22 10-Nov-22 2
310.C.EX.W1072 PBC MVAC 1st Fix & Installation C11_6 d/w - 10h/d - With 15 14-Sep-22 30-Sep-22 16-Sep-22 05-Oct-22 2
HK Hols - No B/O periods
310.C.EX.W1076 PBC MVAC 2nd Fix & Installation (was
C11_6C3)
d/w - 10h/d - With 15 23-Sep-22 12-Oct-22 26-Sep-22 14-Oct-22 2
HK Hols - No B/O periods
310.C.EX.W1088 PBC MVAC Final Fix & Adjustment (was
C11_6C3)
d/w - 10h/d - With 7 01-Nov-22 08-Nov-22 03-Nov-22 10-Nov-22 2
HK Hols - No B/O periods
Comms Room and Associated Rooms (was
C11_6C3)
d/w - 10h/d - With HK Hols
40- No B/O 4periods (was
05-Sep-22
C3) 24-Oct-22 10-Nov-22 27-Dec-22 54

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 118 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.ES.P460 ABWF (Comms Room) - Commence ABWF works C11_6 d/w - 10h/d - With 0 05-Sep-22 10-Nov-22 54
HK Hols - No B/O periods
310.C.ES.P452 PBC (Comms Room 1st Degree - 3rd Degree) - ABWF Works (floor screed, partition (was
C11_6C3)
d/w - 10h/d - With 40 1 05-Sep-22 24-Oct-22 10-Nov-22 27-Dec-22 54
walls, installed conduits) HK Hols - No B/O periods
310.C.ES.P456 PBC (Novec 1234 Comms Room 1st Degree - 3rd Degree) - ABWF works Comms (was
C11_6C3)
d/w - 10h/d - With 40 1 05-Sep-22 24-Oct-22 10-Nov-22 27-Dec-22 54
Rooms (wall, floors, ceiling, doors) HK Hols - No B/O periods
310.C.ES.P464 PBC (Comms Room) - Commence Building Services works (was
C11_6C3)
d/w - 10h/d - With 0 12-Sep-22 16-Nov-22 54
HK Hols - No B/O periods
310.C.ES.P468 PBC (Comms Room 1st Fix - Final Fix) -Building Services Installations (was
C11_6C3)
d/w - 10h/d - With 20 2 16-Sep-22 11-Oct-22 16-Nov-22 08-Dec-22 50
HK Hols - No B/O periods
CC#06 - PBC External Works (was
C11_6C3)
d/w - 10h/d - With HK Hols
71- No B/O 0periods (was
05-Sep-22
C3) 29-Nov-22 07-Sep-22 09-Dec-22 9
External Building Finishes C11_6 d/w - 10h/d - With HK Hols
71- No B/O 0periods (was
05-Sep-22
C3) 29-Nov-22 07-Sep-22 09-Dec-22 9
310.C.ES.P500 PBC External building finishes C11_6 d/w - 10h/d - With 40 05-Sep-22 24-Oct-22 07-Sep-22 26-Oct-22 2
HK Hols - No B/O periods
310.C.ES.P496.B01 PBC Waterproofing and roof finishes (was
C11_6C3)
d/w - 10h/d - With 40 05-Sep-22 24-Oct-22 25-Oct-22 09-Dec-22 40
HK Hols - No B/O periods
310.C.ES.P492 PBC Hard and soft landscape works (was
C11_6C3)
d/w - 10h/d - With 21 05-Nov-22 29-Nov-22 16-Nov-22 09-Dec-22 9
HK Hols - No B/O periods
Drainage and UU (was
C11_6C3)
d/w - 10h/d - With HK Hols
50- No B/O 0periods (was
05-Sep-22
C3) 04-Nov-22 07-Sep-22 15-Nov-22 9
310.C.ES.P480 PBC Building drainage and watermain works C11_6 d/w - 10h/d - With 30 05-Sep-22 12-Oct-22 07-Sep-22 14-Oct-22 2
HK Hols - No B/O periods
310.C.ES.P488 PBC cable ducting + drawpits (was
C11_6C3)
d/w - 10h/d - With 30 05-Sep-22 12-Oct-22 03-Oct-22 07-Nov-22 22
HK Hols - No B/O periods
310.C.ES.P504 PBC CLP Cable ducts + drawpits (was
C11_6C3)
d/w - 10h/d - With 30 05-Sep-22 12-Oct-22 07-Sep-22 14-Oct-22 2
HK Hols - No B/O periods
310.C.ES.P484 PBC AS Cable ducts + drawpits (was
C11_6C3)
d/w - 10h/d - With 30 29-Sep-22 04-Nov-22 12-Oct-22 15-Nov-22 9
HK Hols - No B/O periods
EVA Construction (was
C11_6C3)
d/w - 10h/d - With HK Hols
15- No B/O 0periods (was
25-Oct-22
C3) 10-Nov-22 02-Nov-22 18-Nov-22 7
310.C.ES.P498 PBC Site Formation Works and Road Works for EVA C11_6 d/w - 10h/d - With 15 25-Oct-22 10-Nov-22 02-Nov-22 18-Nov-22 7
HK Hols - No B/O periods
CC#06 ----- Testing and Commissioning ----- (was C3) 682 20 04-Apr-22 22-Jul-24 21-Jun-22 28-Jul-24 5
CC#06 - EVT - Testing and Commissioning 512 8 31-Oct-22 22-Jul-24 04-Jan-23 28-Jul-24 5
CC#06 - EVT - Testing and Commissioning C11_6 d/w - 10h/d - With HK Hols
86- No B/O 8periods (was
29-Jan-24
C3) 16-May-24 20-Feb-24 26-Jul-24 59
310.T.EX.L104 EVT (T&C) - Ventilation System T&C C11_6 d/w - 10h/d - With 35 2 29-Jan-24 11-Mar-24 17-Apr-24 29-May-24 62
HK Hols - No B/O periods
310.T.EX.L100 EVT (T&C) - FS System T&C (was
C11_6C3)
d/w - 10h/d - With 28 2 09-Feb-24 14-Mar-24 18-Mar-24 23-Apr-24 30
HK Hols - No B/O periods
310.T.EX.L090 EVT (T&C) - Plumbing System T&C (was
C11_6C3)
d/w - 10h/d - With 28 2 09-Feb-24 14-Mar-24 20-Feb-24 22-Mar-24 7
HK Hols - No B/O periods
310.T.EX.L112 EVT (T&C) - Systems Integration T&C (was
C11_6C3)
d/w - 10h/d - With 48 2 15-Mar-24 16-May-24 30-May-24 26-Jul-24 59
HK Hols - No B/O periods
CC#06 - EVT - Statutory Inspection (was C3) 512 0 31-Oct-22 22-Jul-24 04-Jan-23 28-Jul-24 5
Water Supply Department (WSD) C11_6 d/w - 10h/d - With HK Hols
432- No B/O 0periods (was
31-Oct-22
C3) 15-Apr-24 04-Jan-23 23-Apr-24 7
310.T.EX.T300 EVT Prepare for Plumbing Material for Submission C11_6 d/w - 10h/d - With 17 31-Oct-22 18-Nov-22 04-Jan-23 26-Jan-23 54
HK Hols - No B/O periods
310.T.EX.T310 EVT Submit all Plumbing Material for PM Acceptance (was
C11_6C3)
d/w - 10h/d - With 0 19-Nov-22 27-Jan-23 54
HK Hols - No B/O periods
310.T.EX.T315 EVT PM Acceptance (was
C11_6C3)
d/w - 10h/d - With 48 19-Nov-22 16-Jan-23 27-Jan-23 23-Mar-23 54
HK Hols - No B/O periods
310.T.EX.T320 EVT Form WWO 46 (Part I & Part II) & Annex Submission for WSD Approval (Plumbing / (was
C11_6C3)
d/w - 10h/d - With 0 17-Jan-23 24-Mar-23 54
FS / WP) HK Hols - No B/O periods
(was C3)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 119 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.T.EX.T325 EVT Obtain Form WWO 46 (Part III) - WSD Approval, Endorsed & Return to Licensed C11_6 d/w - 10h/d - With 4 17-Jan-23 20-Jan-23 24-Mar-23 28-Mar-23 54
Plumber HK Hols - No B/O periods
310.T.EX.T330 EVT Form WWO 46 (Part IV) Submission for WSD Inspection (Plumbing / FS / WP) (was
C11_6C3)
d/w - 10h/d - With 0 15-Mar-24 23-Mar-24 7
HK Hols - No B/O periods
310.T.EX.T335 EVT WSD Inspection for Water Supply System (was
C11_6C3)
d/w - 10h/d - With 10 23-Mar-24 08-Apr-24 05-Apr-24 16-Apr-24 7
HK Hols - No B/O periods
310.T.EX.T340 EVT Obtain Form WWO 46 (Part V) (was
C11_6C3)
d/w - 10h/d - With 0 08-Apr-24 16-Apr-24 7
HK Hols - No B/O periods
310.T.EX.T345 EVT Form WWO 132 (Part II) Submission for Water Supply Connection (was
C11_6C3)
d/w - 10h/d - With 0 08-Apr-24 16-Apr-24 7
HK Hols - No B/O periods
310.T.EX.T350 EVT Final Water Supply Connection (was
C11_6C3)
d/w - 10h/d - With 6 09-Apr-24 15-Apr-24 17-Apr-24 23-Apr-24 7
HK Hols - No B/O periods
310.T.EX.T355 EVT Obtain Water Certificate (Form WWO 1005) (was
C11_6C3)
d/w - 10h/d - With 0 15-Apr-24 23-Apr-24 7
HK Hols - No B/O periods
Fire Services Department (FSD) (was C3) 200 0 16-Oct-23 19-Jun-24 20-Oct-23 24-Jun-24 4
310.T.EX.T365 EVT F.S. Inspection Plan (Form FSI / 314 Submission) (Tunnel VAC System) C11_6 d/w - 10h/d - With 0 16-Oct-23 20-Oct-23 4
HK Hols - No B/O periods
310.T.EX.T439 Completion of 1st FS Inspection of PBA (was
C11_6C3)
d/w - 10h/d - With 0 16-Apr-24 23-May-24 30
HK Hols - No B/O periods
310.T.EX.T370 EVT F.S. Inspection Application (Form FSI / 501 & 251 Submission) (was
C11_6C3)
d/w - 10h/d - With 0 19-Apr-24 24-Apr-24 4
HK Hols - No B/O periods
310.T.EX.T375 EVT F.S. 1st Inspection (was
C11_6C3)
d/w - 10h/d - With 14 02-May-24 18-May-24 07-May-24 23-May-24 4
HK Hols - No B/O periods
310.T.EX.T389.B02 Completion of FS Re-inspection of PBA (was
C01_7C3)
d/w - 10h/d - No HK 0 16-May-24 24-Jun-24 39
Hols - No B/O periods (was
310.T.EX.T380 EVT FSD Comment C1)
C11_6 d/w - 10h/d - With 0 18-May-24 23-May-24 4
HK Hols - No B/O periods
310.T.EX.T385 EVT Rectification & Adjustment (was
C11_6C3)
d/w - 10h/d - With 12 20-May-24 01-Jun-24 24-May-24 06-Jun-24 4
HK Hols - No B/O periods
310.T.EX.T390 EVT F.S. Re-inspection (was
C11_6C3)
d/w - 10h/d - With 14 03-Jun-24 19-Jun-24 07-Jun-24 24-Jun-24 4
HK Hols - No B/O periods
310.T.EX.T395 EVT Issue F.S. Certificate (Form FS172) (was
C11_6C3)
d/w - 10h/d - With 0 19-Jun-24 24-Jun-24 4
HK Hols - No B/O periods
Building Department (BD) (was C3) 27 0 20-Jun-24 22-Jul-24 25-Jun-24 28-Jul-24 5
310.T.EX.T405 EVT BD Inspection Application for Occupation Permit (Form BA13 Submission) C11_6 d/w - 10h/d - With 0 20-Jun-24 25-Jun-24 4
HK Hols - No B/O periods
310.T.EX.T410 EVT BD 1st Inspection (was
C11_6C3)
d/w - 10h/d - With 10 20-Jun-24 02-Jul-24 25-Jun-24 06-Jul-24 4
HK Hols - No B/O periods
310.T.EX.T415 EVT BD Comment (was
C11_6C3)
d/w - 10h/d - With 0 02-Jul-24 06-Jul-24 4
HK Hols - No B/O periods
310.T.EX.T420 EVT Rectification & Adjustment (was
C11_6C3)
d/w - 10h/d - With 10 03-Jul-24 13-Jul-24 08-Jul-24 18-Jul-24 4
HK Hols - No B/O periods
310.T.EX.T425 EVT BD Re-inspection (was
C11_6C3)
d/w - 10h/d - With 7 15-Jul-24 22-Jul-24 19-Jul-24 26-Jul-24 4
HK Hols - No B/O periods
310.T.EX.L136 EVT - Achieve KD-11 (was
C01_7C3)
d/w - 10h/d - No HK 0 22-Jul-24 28-Jul-24 6
Hols - No B/O periods (was
310.T.EX.T435 EVT Issue Occupation Permit (Form BD104) C1)
C11_6 d/w - 10h/d - With 0 22-Jul-24 26-Jul-24 4
HK Hols - No B/O periods
CC#06 - PBA - Testing and Commissioning (was
C11_6C3)
d/w - 10h/d - With HK Hols
376- No B/O 8periods (was
20-Mar-23
C3) 26-Jun-24 29-Apr-23 13-Jul-24 14
Preliminary Testing and Commissioning C11_6 d/w - 10h/d - With HK Hols
87- No B/O 0periods (was
23-Sep-23
C3) 09-Jan-24 23-Nov-23 01-Jun-24 116
Preliminary T&C - Plumbing and Drainage C11_6 d/w - 10h/d - With HK Hols
40- No B/O 0periods (was
07-Nov-23
C3) 22-Dec-23 23-Nov-23 11-Jan-24 14

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 120 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.EX.W213 PBA Plumbing & Drainage Preliminary Inspection & Adjustment C11_6 d/w - 10h/d - With 30 07-Nov-23 11-Dec-23 23-Nov-23 29-Dec-23 14
HK Hols - No B/O periods
310.C.EX.W229 PBA Plumbing & Drainage Preliminary Testing & Commissioning (was
C11_6C3)
d/w - 10h/d - With 30 18-Nov-23 22-Dec-23 05-Dec-23 11-Jan-24 14
HK Hols - No B/O periods
Preliminary T&C - Electrical (was
C11_6C3)
d/w - 10h/d - With HK Hols
60- No B/O 0periods (was
23-Sep-23
C3) 05-Dec-23 02-Feb-24 01-Jun-24 143
310.C.EX.W2480.B02 PBA Electrical Preliminary Inspection & Adjustment (Non-FSI) C11_6 d/w - 10h/d - With 30 23-Sep-23 31-Oct-23 18-Mar-24 25-Apr-24 143
HK Hols - No B/O periods
310.C.EX.W240 PBA Electrical Preliminary Inspection & Adjustment (was
C11_6C3)
d/w - 10h/d - With 30 17-Oct-23 21-Nov-23 02-Feb-24 09-Mar-24 89
HK Hols - No B/O periods
310.C.EX.W256 PBA Electrical Preliminary Testing & Commissioning (was
C11_6C3)
d/w - 10h/d - With 30 01-Nov-23 05-Dec-23 19-Feb-24 23-Mar-24 89
HK Hols - No B/O periods
310.C.EX.W2484.B02 PBA Electrical Preliminary Testing & Commissioning (Non-FSI) (was
C11_6C3)
d/w - 10h/d - With 30 01-Nov-23 05-Dec-23 26-Apr-24 01-Jun-24 143
HK Hols - No B/O periods
Preliminary T&C - Fire Services (was
C11_6C3)
d/w - 10h/d - With HK Hols
40- No B/O 0periods (was
21-Nov-23
C3) 09-Jan-24 27-Dec-23 07-May-24 95
310.C.EX.W221 PBA Fire Service Preliminary Inspection & Adjustment (FSI) C11_6 d/w - 10h/d - With 30 21-Nov-23 27-Dec-23 27-Dec-23 31-Jan-24 29
HK Hols - No B/O periods
310.C.EX.W22.B01 PBA Fire Service Preliminary Inspection & Adjustment (Non-FSI) (was
C11_6C3)
d/w - 10h/d - With 30 21-Nov-23 27-Dec-23 16-Mar-24 24-Apr-24 95
HK Hols - No B/O periods
310.C.EX.W248 PBA Fire Service Preliminary Testing & Commissioning (FSI) (was
C11_6C3)
d/w - 10h/d - With 30 02-Dec-23 09-Jan-24 09-Jan-24 14-Feb-24 29
HK Hols - No B/O periods
310.C.EX.W249.B01 PBA Fire Service Preliminary Testing & Commissioning (Non-FSI) (was
C11_6C3)
d/w - 10h/d - With 30 02-Dec-23 09-Jan-24 28-Mar-24 07-May-24 95
HK Hols - No B/O periods
Preliminary T&C - MVAC (was
C11_6C3)
d/w - 10h/d - With HK Hols
42- No B/O 0periods (was
31-Oct-23
C3) 18-Dec-23 09-Jan-24 28-Feb-24 57
310.C.EX.W217 PBA MVAC Preliminary Inspection & Adjustment C11_6 d/w - 10h/d - With 30 31-Oct-23 04-Dec-23 09-Jan-24 14-Feb-24 57
HK Hols - No B/O periods
310.C.EX.W244 PBA MVAC Preliminary Testing & Commissioning (was
C11_6C3)
d/w - 10h/d - With 30 14-Nov-23 18-Dec-23 23-Jan-24 28-Feb-24 57
HK Hols - No B/O periods
Testing and Commissioning (was
C11_6C3)
d/w - 10h/d - With HK Hols
87- No B/O 8periods (was
10-Jan-24
C3) 26-Apr-24 02-Feb-24 13-Jul-24 63
310.T.EX.L216.B01 PBA Fire Service T&C (Non-FSI) C11_6 d/w - 10h/d - With 21 10-Jan-24 02-Feb-24 08-May-24 01-Jun-24 95
HK Hols - No B/O periods
310.T.EX.L192 PBA MVAC T&C (was
C11_6C3)
d/w - 10h/d - With 21 2 12-Jan-24 05-Feb-24 21-Mar-24 18-Apr-24 57
HK Hols - No B/O periods
310.T.EX.L204 PBA Plumbing & Drainage T&C (was
C11_6C3)
d/w - 10h/d - With 21 2 17-Jan-24 09-Feb-24 02-Feb-24 28-Feb-24 14
HK Hols - No B/O periods
310.T.EX.L200 PBA Fire Service T&C (FSI) (was
C11_6C3)
d/w - 10h/d - With 21 2 31-Jan-24 26-Feb-24 07-Mar-24 03-Apr-24 29
HK Hols - No B/O periods
310.T.EX.L208 PBA System Integration T&C (was
C11_6C3)
d/w - 10h/d - With 48 2 27-Feb-24 26-Apr-24 17-May-24 13-Jul-24 63
HK Hols - No B/O periods
Water Supply Department (WSD) (was
C11_6C3)
d/w - 10h/d - With HK Hols
294- No B/O 0periods (was
20-Mar-23
C3) 14-Mar-24 29-Apr-23 03-Apr-24 14
310.T.ES.P112 PBA Prepare for Plumbing Material for Submission C11_6 d/w - 10h/d - With 17 20-Mar-23 12-Apr-23 29-Apr-23 19-May-23 31
HK Hols - No B/O periods
310.T.ES.P144 PBA Submit all Plumbing Material for PM Acceptance (was
C11_6C3)
d/w - 10h/d - With 0 13-Apr-23 20-May-23 31
HK Hols - No B/O periods
310.T.ES.P148 PBA PM Acceptance (was
C11_6C3)
d/w - 10h/d - With 48 13-Apr-23 09-Jun-23 20-May-23 18-Jul-23 31
HK Hols - No B/O periods
310.T.ES.P192 PBA Form WWO 46 (Part I & Part II) & Annex Submission for WSD Approval (Plumbing / (was
C11_6C3)
d/w - 10h/d - With 0 10-Jun-23 19-Jul-23 31
FS / WP) HK Hols - No B/O periods
310.T.ES.P196 PBA Obtain Form WWO 46 (Part III) - WSD Approval, Endorsed & Return to Licensed (was
C11_6C3)
d/w - 10h/d - With 4 10-Jun-23 14-Jun-23 19-Jul-23 22-Jul-23 31
Plumber HK Hols - No B/O periods
310.T.ES.P104 PBA Form WWO 46 (Part IV) Submission for WSD Inspection (Plumbing / FS / WP) (was
C11_6C3)
d/w - 10h/d - With 0 10-Feb-24 29-Feb-24 14
HK Hols - No B/O periods
(was C3)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 121 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.T.ES.P108 PBA WSD Inspection for Water Supply System C11_6 d/w - 10h/d - With 14 21-Feb-24 07-Mar-24 08-Mar-24 23-Mar-24 14
HK Hols - No B/O periods
310.T.ES.P116 PBA Obtain Form WWO 46 (Part V) (was
C11_6C3)
d/w - 10h/d - With 0 07-Mar-24 23-Mar-24 14
HK Hols - No B/O periods
310.T.ES.P120 PBA Form WWO 132 (Part II) Submission for Water Supply Connection (was
C11_6C3)
d/w - 10h/d - With 0 07-Mar-24 23-Mar-24 14
HK Hols - No B/O periods
310.T.ES.P124 PBA Final Water Supply Connection (was
C11_6C3)
d/w - 10h/d - With 6 08-Mar-24 14-Mar-24 25-Mar-24 03-Apr-24 14
HK Hols - No B/O periods
310.T.ES.P128 PBA Obtain Water Certificate (Form WWO 1005) (was
C11_6C3)
d/w - 10h/d - With 0 14-Mar-24 03-Apr-24 14
HK Hols - No B/O periods
Fire Services Department (FSD) (was
C11_6C3)
d/w - 10h/d - With HK Hols
198- No B/O 0periods (was
13-Sep-23
C3) 16-May-24 25-Jan-24 01-Jun-24 14
DG Application & Inspection C11_6 d/w - 10h/d - With HK Hols
55- No B/O 0periods (was
13-Sep-23
C3) 18-Nov-23 25-Jan-24 03-Apr-24 109
310.T.ES.P452 PBA DG Inspection Application (Form Submission) C11_6 d/w - 10h/d - With 0 13-Sep-23 25-Jan-24 109
HK Hols - No B/O periods
310.T.ES.P456 PBA DG 1st Inspection (was
C11_6C3)
d/w - 10h/d - With 12 13-Oct-23 27-Oct-23 24-Feb-24 08-Mar-24 109
HK Hols - No B/O periods
310.T.ES.P460 PBA DG FSD Comment (was
C11_6C3)
d/w - 10h/d - With 0 27-Oct-23 08-Mar-24 109
HK Hols - No B/O periods
310.T.ES.P464 PBA DG Rectification & Adjustment (was
C11_6C3)
d/w - 10h/d - With 12 28-Oct-23 10-Nov-23 09-Mar-24 22-Mar-24 109
HK Hols - No B/O periods
310.T.ES.P468 PBA DG Re-inspection (was
C11_6C3)
d/w - 10h/d - With 7 11-Nov-23 18-Nov-23 23-Mar-24 03-Apr-24 109
HK Hols - No B/O periods
310.T.ES.P472 PBA Issue DG Certificate (was
C11_6C3)
d/w - 10h/d - With 0 18-Nov-23 03-Apr-24 109
HK Hols - No B/O periods
FS Application & Inspection (was
C11_6C3)
d/w - 10h/d - With HK Hols
63- No B/O 0periods (was
27-Feb-24
C3) 16-May-24 05-Apr-24 01-Jun-24 14
310.T.ES.P132 PBA F.S. Inspection Plan (Form FSI / 314 Submission) C11_6 d/w - 10h/d - With 0 27-Feb-24 05-Apr-24 29
HK Hols - No B/O periods
310.T.ES.P136 PBA F.S. Inspection Application (Form FSI / 501 & 251 Submission) (was
C11_6C3)
d/w - 10h/d - With 0 15-Mar-24 05-Apr-24 14
HK Hols - No B/O periods
310.T.ES.P140 PBA F.S. 1st Inspection (was
C11_6C3)
d/w - 10h/d - With 12 02-Apr-24 16-Apr-24 19-Apr-24 03-May-24 14
HK Hols - No B/O periods
310.T.ES.P152 PBA FSD Comment (was
C11_6C3)
d/w - 10h/d - With 0 16-Apr-24 03-May-24 14
HK Hols - No B/O periods
310.T.ES.P156 PBA Rectification & Adjustment (was
C11_6C3)
d/w - 10h/d - With 12 17-Apr-24 30-Apr-24 04-May-24 18-May-24 14
HK Hols - No B/O periods
310.T.ES.P160 PBA F.S. Re-inspection (was
C11_6C3)
d/w - 10h/d - With 12 02-May-24 16-May-24 20-May-24 01-Jun-24 14
HK Hols - No B/O periods
310.T.ES.P164 PBA Issue F.S. Certificate (Form FS172) (was
C11_6C3)
d/w - 10h/d - With 0 16-May-24 01-Jun-24 14
HK Hols - No B/O periods
Environmental Protection Department (EDP) (was
C11_6C3)
d/w - 10h/d - With HK Hols
55- No B/O 0periods (was
13-Sep-23
C3) 18-Nov-23 25-Jan-24 03-Apr-24 109
EPD Application & Inspection C11_6 d/w - 10h/d - With HK Hols
55- No B/O 0periods (was
13-Sep-23
C3) 18-Nov-23 25-Jan-24 03-Apr-24 109
310.T.ES.P668 PBA - EPD Inspection Application C11_6 d/w - 10h/d - With 0 13-Sep-23 25-Jan-24 109
HK Hols - No B/O periods
310.T.ES.P672 PBA - EPD 1st Inspection (was
C11_6C3)
d/w - 10h/d - With 12 13-Oct-23 27-Oct-23 24-Feb-24 08-Mar-24 109
HK Hols - No B/O periods
310.T.ES.P676 PBA - EPD Comment (was
C11_6C3)
d/w - 10h/d - With 0 27-Oct-23 08-Mar-24 109
HK Hols - No B/O periods
310.T.ES.P680 PBA - EPD Rectification & Adjustment (was
C11_6C3)
d/w - 10h/d - With 12 28-Oct-23 10-Nov-23 09-Mar-24 22-Mar-24 109
HK Hols - No B/O periods
310.T.ES.P684 PBA - EPD Re-inspection (was
C11_6C3)
d/w - 10h/d - With 7 11-Nov-23 18-Nov-23 23-Mar-24 03-Apr-24 109
HK Hols - No B/O periods
(was C3)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 122 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.T.ES.P688 PBA - Issue License C11_6 d/w - 10h/d - With 0 18-Nov-23 03-Apr-24 109
HK Hols - No B/O periods
Building Department (BD) (was
C11_6C3)
d/w - 10h/d - With HK Hols
34- No B/O 0periods (was
17-May-24
C3) 26-Jun-24 03-Jun-24 13-Jul-24 14
310.T.ES.P168 PBA BD Inspection Application for Occupation Permit (Form BA13 Submission) C11_6 d/w - 10h/d - With 0 17-May-24 03-Jun-24 14
HK Hols - No B/O periods
310.T.ES.P172 PBA BD 1st Inspection (was
C11_6C3)
d/w - 10h/d - With 14 17-May-24 01-Jun-24 03-Jun-24 19-Jun-24 14
HK Hols - No B/O periods
310.T.ES.P176 PBA BD Comment (was
C11_6C3)
d/w - 10h/d - With 0 01-Jun-24 19-Jun-24 14
HK Hols - No B/O periods
310.T.ES.P180 PBA Rectification & Adjustment (was
C11_6C3)
d/w - 10h/d - With 6 03-Jun-24 08-Jun-24 20-Jun-24 26-Jun-24 14
HK Hols - No B/O periods
310.T.ES.P184 PBA BD Re-inspection (was
C11_6C3)
d/w - 10h/d - With 14 11-Jun-24 26-Jun-24 27-Jun-24 13-Jul-24 14
HK Hols - No B/O periods
310.T.ES.P037 PBA Achieved Completion and T&C of Tunnel Plant Building A (was
C11_6C3)
d/w - 10h/d - With 0 26-Jun-24 13-Jul-24 14
HK Hols - No B/O periods
310.T.ES.P188 PBA Issue Occupation Permit (Form BD104) (was
C11_6C3)
d/w - 10h/d - With 0 26-Jun-24 13-Jul-24 14
HK Hols - No B/O periods
CC#06 - PBC - Testing and Commissioning (was C3) 223 4 04-Apr-22 31-Dec-22 21-Jun-22 01-Jan-23 0
Preliminary Testing and Commissioning C11_6 d/w - 10h/d - With HK Hols
44- No B/O 0periods (was
23-Sep-22
C3) 15-Nov-22 23-Sep-22 09-Dec-22 21
Preliminary T&C - Plumbing and Drainage C11_6 d/w - 10h/d - With HK Hols
24- No B/O 0periods (was
23-Sep-22
C3) 22-Oct-22 23-Sep-22 22-Oct-22 0
310.C.EX.W1120 PBC Plumbing & Drainage Preliminary Inspection & Adjustment C11_6 d/w - 10h/d - With 10 23-Sep-22 06-Oct-22 23-Sep-22 06-Oct-22 0
HK Hols - No B/O periods
310.C.EX.W1124 PBC Plumbing & Drainage Preliminary Testing & Commissioning (was
C11_6C3)
d/w - 10h/d - With 14 07-Oct-22 22-Oct-22 07-Oct-22 22-Oct-22 0
HK Hols - No B/O periods
Preliminary T&C - Electrical (was
C11_6C3)
d/w - 10h/d - With HK Hols
21- No B/O 0periods (was
22-Oct-22
C3) 15-Nov-22 24-Oct-22 09-Dec-22 21
310.C.EX.W1036 PBC Electrical Preliminary Inspection & Adjustment C11_6 d/w - 10h/d - With 10 22-Oct-22 02-Nov-22 24-Oct-22 03-Nov-22 1
HK Hols - No B/O periods
310.C.EX.W1037.B02 PBC Electrical Preliminary Inspection & Adjustment (Non-FSI) (was
C11_6C3)
d/w - 10h/d - With 10 24-Oct-22 03-Nov-22 17-Nov-22 28-Nov-22 21
HK Hols - No B/O periods
310.C.EX.W1040 PBC Electrical Preliminary Testing & Commissioning (was
C11_6C3)
d/w - 10h/d - With 14 25-Oct-22 09-Nov-22 26-Oct-22 10-Nov-22 1
HK Hols - No B/O periods
310.C.EX.W1045.B02 PBC Electrical Preliminary Testing & Commissioning (Non-FSI) (was
C11_6C3)
d/w - 10h/d - With 10 04-Nov-22 15-Nov-22 29-Nov-22 09-Dec-22 21
HK Hols - No B/O periods
Preliminary T&C - Fire Services (was
C11_6C3)
d/w - 10h/d - With HK Hols
16- No B/O 0periods (was
15-Oct-22
C3) 02-Nov-22 15-Oct-22 01-Dec-22 25
310.C.EX.W1060 PBC Fire Services Preliminary Inspection & Adjustment (FSI) C11_6 d/w - 10h/d - With 10 15-Oct-22 26-Oct-22 15-Oct-22 26-Oct-22 0
HK Hols - No B/O periods
310.C.EX.W1061.B01 PBC Fire Services Preliminary Inspection & Adjustment (Non-FSI) (was
C11_6C3)
d/w - 10h/d - With 10 15-Oct-22 26-Oct-22 14-Nov-22 24-Nov-22 25
HK Hols - No B/O periods
310.C.EX.W1064 PBC Fire Services Preliminary Testing & Commissioning (FSI) (was
C11_6C3)
d/w - 10h/d - With 14 18-Oct-22 02-Nov-22 18-Oct-22 02-Nov-22 0
HK Hols - No B/O periods
310.C.EX.W1065.B01 PBC Fire Services Preliminary Testing & Commissioning (Non-FSI) (was
C11_6C3)
d/w - 10h/d - With 14 18-Oct-22 02-Nov-22 16-Nov-22 01-Dec-22 25
HK Hols - No B/O periods
Preliminary T&C - MVAC (was
C11_6C3)
d/w - 10h/d - With HK Hols
16- No B/O 0periods (was
13-Oct-22
C3) 31-Oct-22 15-Oct-22 02-Nov-22 2
310.C.EX.W1080 PBC MVAC Preliminary Inspection & Adjustment C11_6 d/w - 10h/d - With 10 13-Oct-22 24-Oct-22 15-Oct-22 26-Oct-22 2
HK Hols - No B/O periods
310.C.EX.W1084 PBC MVAC Preliminary Testing & Commissioning (was C3)
C11_6 d/w - 10h/d - With 14 15-Oct-22 31-Oct-22 18-Oct-22 02-Nov-22 2
HK Hols - No B/O periods
Testing and Commissioning (was
C11_6C3)
d/w - 10h/d - With HK Hols
16- No B/O 4periods (was
01-Nov-22
C3) 18-Nov-22 01-Nov-22 09-Dec-22 18
310.T.EX.L224 PBC Plumbing and Drainage T&C C11_6 d/w - 10h/d - With 7 1 01-Nov-22 08-Nov-22 01-Nov-22 08-Nov-22 0
HK Hols - No B/O periods
(was C3)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 123 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.T.EX.L212 PBC MVAC T&C C11_6 d/w - 10h/d - With 7 1 09-Nov-22 16-Nov-22 11-Nov-22 18-Nov-22 2
HK Hols - No B/O periods
310.T.EX.L220 PBC Fire Services T&C (FSI) (was
C11_6C3)
d/w - 10h/d - With 7 1 11-Nov-22 18-Nov-22 11-Nov-22 18-Nov-22 0
HK Hols - No B/O periods
310.T.EX.L228.B01 PBC Fire Services T&C (Non-FSI) (was
C11_6C3)
d/w - 10h/d - With 7 1 11-Nov-22 18-Nov-22 02-Dec-22 09-Dec-22 18
HK Hols - No B/O periods
Water Supply Department (WSD) (was
C11_6C3)
d/w - 10h/d - With HK Hols
187- No B/O 0periods (was
04-Apr-22
C3) 18-Nov-22 21-Jun-22 18-Nov-22 0
310.T.ES.P228 PBC Prepare for Plumbing Material for Submission C11_6 d/w - 10h/d - With 17 04-Apr-22 27-Apr-22 21-Jun-22 11-Jul-22 61
HK Hols - No B/O periods
310.T.ES.P232 PBC Submit all Plumbing Material for PM Acceptance (was
C11_6C3)
d/w - 10h/d - With 0 28-Apr-22 12-Jul-22 61
HK Hols - No B/O periods
310.T.ES.P236 PBC PM Acceptance (was
C11_6C3)
d/w - 10h/d - With 48 28-Apr-22 24-Jun-22 12-Jul-22 05-Sep-22 61
HK Hols - No B/O periods
310.T.ES.P240 PBC Form WWO 46 (Part I & Part II) & Annex Submission for WSD Approval (Plumbing / (was
C11_6C3)
d/w - 10h/d - With 0 25-Jun-22 06-Sep-22 61
FS / WP) HK Hols - No B/O periods
310.T.ES.P244 PBC Obtain Form WWO 46 (Part III) - WSD Approval, Endorsed & Return to Licensed (was
C11_6C3)
d/w - 10h/d - With 4 25-Jun-22 29-Jun-22 06-Sep-22 09-Sep-22 61
Plumber HK Hols - No B/O periods
310.T.ES.P204 PBC Form WWO 46 (Part IV) Submission for WSD Inspection (Plumbing / FS / WP) (was
C11_6C3)
d/w - 10h/d - With 0 09-Nov-22 09-Nov-22 0
HK Hols - No B/O periods
310.T.ES.P208 PBC WSD Inspection for Water Supply System (was
C11_6C3)
d/w - 10h/d - With 6 09-Nov-22 15-Nov-22 09-Nov-22 15-Nov-22 0
HK Hols - No B/O periods
310.T.ES.P212 PBC Obtain Form WWO 46 (Part V) (was
C11_6C3)
d/w - 10h/d - With 0 15-Nov-22 15-Nov-22 0
HK Hols - No B/O periods
310.T.ES.P216 PBC Form WWO 132 (Part II) Submission for Water Supply Connection (was
C11_6C3)
d/w - 10h/d - With 0 15-Nov-22 15-Nov-22 0
HK Hols - No B/O periods
310.T.ES.P220 PBC Final Water Supply Connection (was
C11_6C3)
d/w - 10h/d - With 3 16-Nov-22 18-Nov-22 16-Nov-22 18-Nov-22 0
HK Hols - No B/O periods
310.T.ES.P224 PBC Obtain Water Certificate (Form WWO 1005) (was
C11_6C3)
d/w - 10h/d - With 0 18-Nov-22 18-Nov-22 0
HK Hols - No B/O periods
Fire Services Department (FSD) (was
C11_6C3)
d/w - 10h/d - With HK Hols
42- No B/O 0periods (was
22-Oct-22
C3) 09-Dec-22 26-Oct-22 09-Dec-22 0
DG Application & Inspection C11_6 d/w - 10h/d - With HK Hols
21- No B/O 0periods (was
22-Oct-22
C3) 15-Nov-22 26-Oct-22 18-Nov-22 3
310.T.ES.P428 PBC DG Inspection Application (Form Submission) C11_6 d/w - 10h/d - With 0 22-Oct-22 26-Oct-22 3
HK Hols - No B/O periods
310.T.ES.P432 PBC DG 1st Inspection (was
C11_6C3)
d/w - 10h/d - With 6 31-Oct-22 05-Nov-22 03-Nov-22 09-Nov-22 3
HK Hols - No B/O periods
310.T.ES.P436 PBC DG FSD Comment (was
C11_6C3)
d/w - 10h/d - With 0 05-Nov-22 09-Nov-22 3
HK Hols - No B/O periods
310.T.ES.P440 PBC DG Rectification & Adjustment (was
C11_6C3)
d/w - 10h/d - With 2 07-Nov-22 08-Nov-22 10-Nov-22 11-Nov-22 3
HK Hols - No B/O periods
310.T.ES.P444 PBC DG Re-inspection (was
C11_6C3)
d/w - 10h/d - With 6 09-Nov-22 15-Nov-22 12-Nov-22 18-Nov-22 3
HK Hols - No B/O periods
310.T.ES.P448 PBC Issue DG Certificate (was
C11_6C3)
d/w - 10h/d - With 0 15-Nov-22 18-Nov-22 3
HK Hols - No B/O periods
FS Application & Inspection (was
C11_6C3)
d/w - 10h/d - With HK Hols
18- No B/O 0periods (was
19-Nov-22
C3) 09-Dec-22 19-Nov-22 09-Dec-22 0
310.T.ES.P248 PBC F.S. Inspection Plan (Form FSI / 314 Submission) C11_6 d/w - 10h/d - With 0 19-Nov-22 19-Nov-22 0
HK Hols - No B/O periods
310.T.ES.P252 PBC F.S. Inspection Application (Form FSI / 501 & 251 Submission) (was
C11_6C3)
d/w - 10h/d - With 0 19-Nov-22 19-Nov-22 0
HK Hols - No B/O periods
310.T.ES.P256 PBC F.S. 1st Inspection (was
C11_6C3)
d/w - 10h/d - With 6 19-Nov-22 25-Nov-22 19-Nov-22 25-Nov-22 0
HK Hols - No B/O periods
(was C3)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 124 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.T.ES.P260 PBC FSD Comment C11_6 d/w - 10h/d - With 0 25-Nov-22 25-Nov-22 0
HK Hols - No B/O periods
310.T.ES.P264 PBC Rectification & Adjustment (was
C11_6C3)
d/w - 10h/d - With 6 26-Nov-22 02-Dec-22 26-Nov-22 02-Dec-22 0
HK Hols - No B/O periods
310.T.ES.P268 PBC F.S. Re-inspection (was
C11_6C3)
d/w - 10h/d - With 6 03-Dec-22 09-Dec-22 03-Dec-22 09-Dec-22 0
HK Hols - No B/O periods
310.T.ES.P272 PBC Issue F.S. Certificate (Form FS172) (was
C11_6C3)
d/w - 10h/d - With 0 09-Dec-22 09-Dec-22 0
HK Hols - No B/O periods
Environmental Protection Department (EDP) (was
C11_6C3)
d/w - 10h/d - With HK Hols
18- No B/O 0periods (was
22-Oct-22
C3) 11-Nov-22 29-Oct-22 18-Nov-22 6
EPD Application & Inspection C11_6 d/w - 10h/d - With HK Hols
18- No B/O 0periods (was
22-Oct-22
C3) 11-Nov-22 29-Oct-22 18-Nov-22 6
310.T.ES.P692 PBC - EPD Inspection Application C11_6 d/w - 10h/d - With 0 22-Oct-22 29-Oct-22 6
HK Hols - No B/O periods
310.T.ES.P696 PBC - EPD 1st Inspection (was
C11_6C3)
d/w - 10h/d - With 6 22-Oct-22 28-Oct-22 29-Oct-22 04-Nov-22 6
HK Hols - No B/O periods
310.T.ES.P700 PBC - EPD Comment (was
C11_6C3)
d/w - 10h/d - With 0 28-Oct-22 04-Nov-22 6
HK Hols - No B/O periods
310.T.ES.P704 PBC - EPD Rectification & Adjustment (was
C11_6C3)
d/w - 10h/d - With 6 29-Oct-22 04-Nov-22 05-Nov-22 11-Nov-22 6
HK Hols - No B/O periods
310.T.ES.P708 PBC - EPD Re-inspection (was
C11_6C3)
d/w - 10h/d - With 6 05-Nov-22 11-Nov-22 12-Nov-22 18-Nov-22 6
HK Hols - No B/O periods
310.T.ES.P712 PBC - Issue License (was
C11_6C3)
d/w - 10h/d - With 0 11-Nov-22 18-Nov-22 6
HK Hols - No B/O periods
Building Department (BD) (was C3) 18 0 10-Dec-22 31-Dec-22 10-Dec-22 01-Jan-23 0
310.T.ES.P276 PBC BD Inspection Application for Occupation Permit (Form BA13 Submission) C11_6 d/w - 10h/d - With 0 10-Dec-22 10-Dec-22 0
HK Hols - No B/O periods
310.T.ES.P280 PBC BD 1st Inspection (was
C11_6C3)
d/w - 10h/d - With 6 10-Dec-22 16-Dec-22 10-Dec-22 16-Dec-22 0
HK Hols - No B/O periods
310.T.ES.P284 PBC BD Comment (was
C11_6C3)
d/w - 10h/d - With 0 16-Dec-22 16-Dec-22 0
HK Hols - No B/O periods
310.T.ES.P288 PBC Rectification & Adjustment (was
C11_6C3)
d/w - 10h/d - With 6 17-Dec-22 23-Dec-22 17-Dec-22 23-Dec-22 0
HK Hols - No B/O periods
310.T.ES.P292 PBC BD Re-inspection (was
C11_6C3)
d/w - 10h/d - With 6 24-Dec-22 31-Dec-22 24-Dec-22 31-Dec-22 0
HK Hols - No B/O periods
310.T.ES.P200 PBC Achieved Completion and T&C of Tunnel Plant Building C (was
C11_6C3)
d/w - 10h/d - With 0 31-Dec-22 31-Dec-22 0
HK Hols - No B/O periods
310.T.ES.P296 PBC Issue Occupation Permit (Form BD104) (was
C11_6C3)
d/w - 10h/d - With 0 31-Dec-22 31-Dec-22 0
HK Hols - No B/O periods
310.T.ES.P297 PMS24 - Comp all works for Road Tunnel PBC and stat. apprv, consents, ready for use [1 (was
C01_7C3)
d/w - 10h/d - No HK 0 31-Dec-22 01-Jan-23 1
Jan 23] Hols - No B/O periods (was
Cost Centre #07 - West Vehicular Tunnels & Plant Building B C1) 931 457 07-Jun-21 A 23-Jul-24 27-Mar-22 24-Aug-24 28
CC#07 ----- Design & Other Submission ----- C01_7 d/w - 10h/d - No HK Hols518
- No B/O periods
0 (was
23-Jul-21
C1) A 26-Dec-22 27-Mar-22 21-Mar-24 451
CC#07 - WVT - Statutory Submission and Consent Application C01_7 d/w - 10h/d - No HK Hols518
- No B/O periods
0 (was
23-Jul-21
C1) A 26-Dec-22 27-Mar-22 21-Mar-24 451
CC#07 - WVT - Ground Investigation Plan for ELS Design C01_7 d/w - 10h/d - No HK Hols401
- No B/O periods
0 (was
23-Jul-21
C1) A 01-Sep-22 27-Mar-22 05-Sep-22 5
310.D.EX.H252 WVT - SI Plan for ELS Design - prepare and submit to PM C01_7 d/w - 10h/d - No HK 7 23-Jul-21 A 29-Jul-21 A 27-Mar-22 27-Mar-22
Hols - No B/O periods (was
310.D.EX.H276 WVT - SI Plan for ELS Design - prepare and submit Form BA10 to notify work C1)
C01_7 d/w - 10h/d - No HK 7 25-Aug-22 01-Sep-22 30-Aug-22 05-Sep-22 5
commencement Hols - No B/O periods (was
CC#07 - WVT - ELS Design - Vertical Element C1)
C01_7 d/w - 10h/d - No HK Hols315
- No B/O periods
0 (was
01-Nov-21
C1) A 11-Sep-22 27-Mar-22 11-Sep-22 0
WVT - ELS Works Design - WVT Ch447 to 575 (Zone 5 & 6) Pkg.1 C01_7 d/w - 10h/d - No HK Hols291
- No B/O periods
0 (was
01-Nov-21
C1) A 18-Aug-22 27-Mar-22 07-Sep-22 20
310.D.EX.F174 WVT - ELS design (Vertical Elements) - prepare and submit to ICE for reviewing C01_7 d/w - 10h/d - No HK 6 01-Nov-21 A 07-Jan-22 A 27-Mar-22 27-Mar-22
Hols - No B/O periods (was
C1)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 125 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.EX.F178 WVT - ELS design (Vertical Elements) - ICE issue check certificate C01_7 d/w - 10h/d - No HK 1 08-Jan-22 A 08-Jan-22 A 16-Apr-22 16-Apr-22
Hols - No B/O periods (was
310.D.EX.F182 WVT - ELS design (Vertical Elements) - PM, AP, RSE reviewing C1)
C01_7 d/w - 10h/d - No HK 28 08-Jan-22 A 06-Apr-22 16-Apr-22 26-Apr-22 20
Hols - No B/O periods (was
310.D.EX.F202 WVT - ELS design (Vertical Elements) - ICC, M&VC review design and issue check C1)
C01_7 d/w - 10h/d - No HK 21 07-Apr-22 27-Apr-22 27-Apr-22 17-May-22 20
certificates Hols - No B/O periods (was
310.D.EX.H349 WVT - ELS design (Vertical Elements) - prepare and resubmit C1)
C01_7 d/w - 10h/d - No HK 4 28-Apr-22 01-May-22 18-May-22 21-May-22 20
Hols - No B/O periods (was
310.D.EX.H353 WVT - ELS design (Vertical Elements) - PM, AP, RSE reviewing 2nd Round C1)
C01_7 d/w - 10h/d - No HK 28 02-May-22 29-May-22 22-May-22 18-Jun-22 20
Hols - No B/O periods (was
310.D.EX.F186 WVT - ELS design (Vertical Elements) - ICC, M&VC review design and issue check C1)
C01_7 d/w - 10h/d - No HK 21 30-May-22 19-Jun-22 19-Jun-22 09-Jul-22 20
certificates 2nd Round Hols - No B/O periods (was
310.D.EX.F190 WVT - ELS design (Vertical Elements) - BD review and comment C1)
C01_7 d/w - 10h/d - No HK 60 20-Jun-22 18-Aug-22 10-Jul-22 07-Sep-22 20
Hols - No B/O periods (was
WVT - ELS Works Design - WVT Ch0 to 447 (Zone 1, 2, 3 & 4) Pkg.2 C1)
C01_7 d/w - 10h/d - No HK Hols169
- No B/O periods
0 (was27-Mar-22
C1) 11-Sep-22 27-Mar-22 11-Sep-22 0
310.D.EX.F142 WVT - ELS design (Vertical Elements) - prepare and submit to ICE for reviewing C01_7 d/w - 10h/d - No HK 6 27-Mar-22 01-Apr-22 27-Mar-22 01-Apr-22 0
Hols - No B/O periods (was
310.D.EX.F146 WVT - ELS design (Vertical Elements) - ICE issue check certificate C1)
C01_7 d/w - 10h/d - No HK 1 02-Apr-22 02-Apr-22 02-Apr-22 02-Apr-22 0
Hols - No B/O periods (was
310.D.EX.F150 WVT - ELS design (Vertical Elements) - PM, AP, RSE reviewing C1)
C01_7 d/w - 10h/d - No HK 28 03-Apr-22 30-Apr-22 03-Apr-22 30-Apr-22 0
Hols - No B/O periods (was
310.D.EX.F170 WVT - ELS design (Vertical Elements) - ICC, M&VC review design and issue check C1)
C01_7 d/w - 10h/d - No HK 21 01-May-22 21-May-22 01-May-22 21-May-22 0
certificates Hols - No B/O periods (was
310.D.EX.H341 WVT - ELS design (Vertical Elements) - prepare and resubmit C1)
C01_7 d/w - 10h/d - No HK 4 22-May-22 25-May-22 22-May-22 25-May-22 0
Hols - No B/O periods (was
310.D.EX.H345 WVT - ELS design (Vertical Elements) - PM, AP, RSE reviewing 2nd Round C1)
C01_7 d/w - 10h/d - No HK 28 26-May-22 22-Jun-22 26-May-22 22-Jun-22 0
Hols - No B/O periods (was
310.D.EX.F154 WVT - ELS design (Vertical Elements) - ICC, M&VC review design and issue check C1)
C01_7 d/w - 10h/d - No HK 21 23-Jun-22 13-Jul-22 23-Jun-22 13-Jul-22 0
certificates 2nd Round Hols - No B/O periods (was
310.D.EX.F158 WVT - ELS design (Vertical Elements) - BD review and comment C1)
C01_7 d/w - 10h/d - No HK 60 14-Jul-22 11-Sep-22 14-Jul-22 11-Sep-22 0
Hols - No B/O periods (was
CC#07 - WVT - ELS Design - Excavation C1)
C01_7 d/w - 10h/d - No HK Hols204
- No B/O periods
0 (was21-Apr-22
C1) 10-Nov-22 25-Jun-22 20-Jan-23 71
WVT - ELS Works Design - WVT Ch450 to 575 (Zone 4, 5 & 6) Pkg.1 C01_7 d/w - 10h/d - No HK Hols169
- No B/O periods
0 (was21-Apr-22
C1) 06-Oct-22 05-Aug-22 20-Jan-23 106
310.D.EX.F262.B01 WVT - ELS design (Excavation) - prepare and submit to ICE for reviewing C01_7 d/w - 10h/d - No HK 6 21-Apr-22 26-Apr-22 05-Aug-22 10-Aug-22 106
Hols - No B/O periods (was
310.D.EX.F266.B01 WVT - ELS design (Excavation) - ICE issue check certificate C1)
C01_7 d/w - 10h/d - No HK 1 27-Apr-22 27-Apr-22 11-Aug-22 11-Aug-22 106
Hols - No B/O periods (was
310.D.EX.F270.B01 WVT - ELS design (Excavation) - PM, AP, RSE reviewing C1)
C01_7 d/w - 10h/d - No HK 28 28-Apr-22 25-May-22 12-Aug-22 08-Sep-22 106
Hols - No B/O periods (was
310.D.EX.F282.B01 WVT - ELS design (Excavation) - ICC, M&VC review design and issue check certificates C1)
C01_7 d/w - 10h/d - No HK 21 26-May-22 15-Jun-22 09-Sep-22 29-Sep-22 106
Hols - No B/O periods (was
310.D.EX.H851.B01 WVT - ELS design (Excavation) - prepare and resubmit C1)
C01_7 d/w - 10h/d - No HK 4 16-Jun-22 19-Jun-22 30-Sep-22 03-Oct-22 106
Hols - No B/O periods (was
310.D.EX.H855.B01 WVT - ELS design (Excavation) - PM, AP, RSE reviewing 2nd Round C1)
C01_7 d/w - 10h/d - No HK 28 20-Jun-22 17-Jul-22 04-Oct-22 31-Oct-22 106
Hols - No B/O periods (was
310.D.EX.F274.B01 WVT - ELS design (Excavation) - ICC, M&VC review design and issue check certificates C1)
C01_7 d/w - 10h/d - No HK 21 18-Jul-22 07-Aug-22 01-Nov-22 21-Nov-22 106
2nd Round Hols - No B/O periods (was
310.D.EX.F278.B01 WVT - ELS design (Excavation) - BD review and comment C1)
C01_7 d/w - 10h/d - No HK 60 08-Aug-22 06-Oct-22 22-Nov-22 20-Jan-23 106
Hols - No B/O periods (was
WVT - ELS Works Design - WVT Ch0 to 450 (Zone 1, 2, & 3) Pkg.2 C1)
C01_7 d/w - 10h/d - No HK Hols169
- No B/O periods
0 (was26-May-22
C1) 10-Nov-22 25-Jun-22 10-Dec-22 30

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 126 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.EX.F238.B01 WVT - ELS design (Excavation) - prepare and submit to ICE for reviewing C01_7 d/w - 10h/d - No HK 6 26-May-22 31-May-22 25-Jun-22 30-Jun-22 30
Hols - No B/O periods (was
310.D.EX.F242.B01 WVT - ELS design (Excavation) - ICE issue check certificate C1)
C01_7 d/w - 10h/d - No HK 1 01-Jun-22 01-Jun-22 01-Jul-22 01-Jul-22 30
Hols - No B/O periods (was
310.D.EX.F246.B01 WVT - ELS design (Excavation) - PM, AP, RSE reviewing C1)
C01_7 d/w - 10h/d - No HK 28 02-Jun-22 29-Jun-22 02-Jul-22 29-Jul-22 30
Hols - No B/O periods (was
310.D.EX.F258.B01 WVT - ELS design (Excavation) - ICC, M&VC review design and issue check certificates C1)
C01_7 d/w - 10h/d - No HK 21 30-Jun-22 20-Jul-22 30-Jul-22 19-Aug-22 30
Hols - No B/O periods (was
310.D.EX.H843.B01 WVT - ELS design (Excavation) - prepare and resubmit C1)
C01_7 d/w - 10h/d - No HK 4 21-Jul-22 24-Jul-22 20-Aug-22 23-Aug-22 30
Hols - No B/O periods (was
310.D.EX.H847.B01 WVT - ELS design (Excavation) - PM, AP, RSE reviewing 2nd Round C1)
C01_7 d/w - 10h/d - No HK 28 25-Jul-22 21-Aug-22 24-Aug-22 20-Sep-22 30
Hols - No B/O periods (was
310.D.EX.F250.B01 WVT - ELS design (Excavation) - ICC, M&VC review design and issue check certificates C1)
C01_7 d/w - 10h/d - No HK 21 22-Aug-22 11-Sep-22 21-Sep-22 11-Oct-22 30
2nd Round Hols - No B/O periods (was
310.D.EX.F254.B01 WVT - ELS design (Excavation) - BD review and comment C1)
C01_7 d/w - 10h/d - No HK 60 12-Sep-22 10-Nov-22 12-Oct-22 10-Dec-22 30
Hols - No B/O periods (was
CC#07 - WVT - Testing and Commissioning Plan for WVT C1)
C01_7 d/w - 10h/d - No HK Hols58
- No B/O periods
0 (was30-Oct-22
C1) 26-Dec-22 30-Oct-22 21-Mar-24 451
310.D.TX.A148 WVT no.26 - Testing and Commissioning Plan for WVT - Prepare and submit to PM C01_7 d/w - 10h/d - No HK 30 30-Oct-22 28-Nov-22 30-Oct-22 28-Nov-22 0
Hols - No B/O periods (was
310.D.TX.A152 WVT no.26 - Testing and Commissioning Plan for WVT - PM review and accept C1)
C01_7 d/w - 10h/d - No HK 28 29-Nov-22 26-Dec-22 23-Feb-24 21-Mar-24 451
Hols - No B/O periods (was
CC#07 - WVT - MEP Submission C1)
C01_7 d/w - 10h/d - No HK Hols144
- No B/O periods
0 (was
23-Mar-22
C1) A 20-Aug-22 10-Jul-22 30-Nov-22 102
WVT - MEP - Drawing Submission C01_7 d/w - 10h/d - No HK Hols144
- No B/O periods
0 (was
23-Mar-22
C1) A 20-Aug-22 10-Jul-22 30-Nov-22 102
310.D.WS.L736 WVT - MEP - Drawing Submission - prepare document C01_7 d/w - 10h/d - No HK 14 23-Mar-22 A 28-May-22 10-Jul-22 07-Sep-22 102
Hols - No B/O periods (was
310.D.WS.L737 WVT - MEP - Drawing Submission - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 60 27-Apr-22 25-Jun-22 07-Aug-22 05-Oct-22 102
Hols - No B/O periods (was
310.D.WS.L738 WVT - MEP - Drawing Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 60 25-May-22 23-Jul-22 04-Sep-22 02-Nov-22 102
Hols - No B/O periods (was
310.D.WS.L740 WVT - MEP - Drawing Submission - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 60 22-Jun-22 20-Aug-22 02-Oct-22 30-Nov-22 102
Hols - No B/O periods (was
CC#07 - WVT - ABWF Submission C1)
C01_7 d/w - 10h/d - No HK Hols49
- No B/O periods
0 (was26-Apr-22
C1) 13-Jun-22 03-May-22 20-Jun-22 7
WVT - ABWF - Drawing Submission C01_7 d/w - 10h/d - No HK Hols49
- No B/O periods
0 (was26-Apr-22
C1) 13-Jun-22 03-May-22 20-Jun-22 7
310.D.WS.L1472 WVT - ABWF - prepare document C01_7 d/w - 10h/d - No HK 14 26-Apr-22 09-May-22 03-May-22 16-May-22 7
Hols - No B/O periods (was
310.D.WS.L1716 WVT - ABWF - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 21 10-May-22 30-May-22 17-May-22 06-Jun-22 7
Hols - No B/O periods (was
310.D.WS.L1712 WVT - ABWF - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 7 31-May-22 06-Jun-22 07-Jun-22 13-Jun-22 7
Hols - No B/O periods (was
310.D.WS.L1476 WVT - ABWF - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 7 07-Jun-22 13-Jun-22 14-Jun-22 20-Jun-22 7
Hols - No B/O periods (was
WVT - ABWF - Material Submission C1)
C01_7 d/w - 10h/d - No HK Hols49
- No B/O periods
0 (was26-Apr-22
C1) 13-Jun-22 03-May-22 20-Jun-22 7
310.D.WS.L1488 WVT - ABWF - Material Submission - prepare document C01_7 d/w - 10h/d - No HK 14 26-Apr-22 09-May-22 03-May-22 16-May-22 7
Hols - No B/O periods (was
310.D.WS.L1724 WVT - ABWF - Material Submission - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 21 10-May-22 30-May-22 17-May-22 06-Jun-22 7
Hols - No B/O periods (was
310.D.WS.L1720 WVT - ABWF - Material Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 7 31-May-22 06-Jun-22 07-Jun-22 13-Jun-22 7
Hols - No B/O periods (was
310.D.WS.L1492 WVT - ABWF - Material Submission - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 7 07-Jun-22 13-Jun-22 14-Jun-22 20-Jun-22 7
Hols - No B/O periods (was
CC#07 - PBB - MEP Submission C1)
C01_7 d/w - 10h/d - No HK Hols82
- No B/O periods
0 (was
23-Mar-22
C1) A 19-Jun-22 19-Jun-22 08-Sep-22 81

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 127 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
PBB - MEP - Drawing Submission C01_7 d/w - 10h/d - No HK Hols82
- No B/O periods
0 (was
23-Mar-22
C1) A 19-Jun-22 19-Jun-22 08-Sep-22 81
310.D.WS.L760 PBB - MEP - Drawing Submission - prepare document C01_7 d/w - 10h/d - No HK 7 23-Mar-22 A 08-May-22 19-Jun-22 28-Jul-22 81
Hols - No B/O periods (was
310.D.WS.L761 PBB - MEP - Drawing Submission - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 40 13-Apr-22 22-May-22 03-Jul-22 11-Aug-22 81
Hols - No B/O periods (was
310.D.WS.L762 PBB - MEP - Drawing Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 40 27-Apr-22 05-Jun-22 17-Jul-22 25-Aug-22 81
Hols - No B/O periods (was
310.D.WS.L764 PBB - MEP - Drawing Submission - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 40 11-May-22 19-Jun-22 31-Jul-22 08-Sep-22 81
Hols - No B/O periods (was
CC#07 - PBB - ABWF Submission C1)
C01_7 d/w - 10h/d - No HK Hols35
- No B/O periods
0 (was26-Apr-22
C1) 30-May-22 28-Apr-22 01-Jun-22 2
PBB - ABWF - Drawing Submission C01_7 d/w - 10h/d - No HK Hols35
- No B/O periods
0 (was26-Apr-22
C1) 30-May-22 28-Apr-22 01-Jun-22 2
310.D.WS.L1496 PBB - ABWF - prepare document C01_7 d/w - 10h/d - No HK 7 26-Apr-22 02-May-22 28-Apr-22 04-May-22 2
Hols - No B/O periods (was
310.D.WS.L1732 PBB - ABWF - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 14 03-May-22 16-May-22 05-May-22 18-May-22 2
Hols - No B/O periods (was
310.D.WS.L1728 PBB - ABWF - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 7 17-May-22 23-May-22 19-May-22 25-May-22 2
Hols - No B/O periods (was
310.D.WS.L1500 PBB - ABWF - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 7 24-May-22 30-May-22 26-May-22 01-Jun-22 2
Hols - No B/O periods (was
PBB - ABWF - Material Submission C1)
C01_7 d/w - 10h/d - No HK Hols35
- No B/O periods
0 (was26-Apr-22
C1) 30-May-22 28-Apr-22 01-Jun-22 2
310.D.WS.L1512 PBB - ABWF - Material Submission - prepare document C01_7 d/w - 10h/d - No HK 7 26-Apr-22 02-May-22 28-Apr-22 04-May-22 2
Hols - No B/O periods (was
310.D.WS.L1740 PBB - ABWF - Material Submission - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 14 03-May-22 16-May-22 05-May-22 18-May-22 2
Hols - No B/O periods (was
310.D.WS.L1736 PBB - ABWF - Material Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 7 17-May-22 23-May-22 19-May-22 25-May-22 2
Hols - No B/O periods (was
310.D.WS.L1516 PBB - ABWF - Material Submission - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 7 24-May-22 30-May-22 26-May-22 01-Jun-22 2
Hols - No B/O periods (was
CC#07 - WVT - Submission of Method Statement and Shop Drawings C1)
C01_7 d/w - 10h/d - No HK Hols384
- No B/O periods
0 (was
09-Oct-21
C1) A 27-Oct-22 26-Jul-22 11-Jul-23 257
CC#07 - WVT - Method Statement of WVT Construction C01_7 d/w - 10h/d - No HK Hols58
- No B/O periods
0 (was
09-Oct-21
C1) A 23-Apr-22 26-Jul-22 21-Sep-22 151
310.D.TX.A196 MS no.14 - Method Statement for WVT Construction - prepare document C01_7 d/w - 10h/d - No HK 30 09-Oct-21 A 12-Nov-21 A 26-Jul-22 26-Jul-22
Hols - No B/O periods (was
310.D.TX.A200 MS no.14 - Method Statement for WVT Construction - PM review and accept C1)
C01_7 d/w - 10h/d - No HK 28 13-Nov-21 A 23-Apr-22 25-Aug-22 21-Sep-22 151
Hols - No B/O periods (was
CC#07 - WVT - Method Statement for Plate Load Test C1)
C01_7 d/w - 10h/d - No HK Hols58
- No B/O periods
0 (was31-Aug-22
C1) 27-Oct-22 15-May-23 11-Jul-23 257
310.D.TX.A332 Method Statement for Plate Load Test - prepare document C01_7 d/w - 10h/d - No HK 30 31-Aug-22 29-Sep-22 15-May-23 13-Jun-23 257
Hols - No B/O periods (was
310.D.TX.A336 Method Statement for Plate Load Test - BD Acknowledge C1)
C01_7 d/w - 10h/d - No HK 28 30-Sep-22 27-Oct-22 14-Jun-23 11-Jul-23 257
Hols - No B/O periods (was
CC#07 - General - MEP - Material Submission C1)
C01_7 d/w - 10h/d - No HK Hols294
- No B/O periods
0 (was
27-Jan-22
C1) A 16-Nov-22 28-Mar-22 19-Nov-22 3
Preliminaries C01_7 d/w - 10h/d - No HK Hols 7- No B/O periods
0 (was
27-Jan-22
C1) A 08-Feb-22 A 28-Mar-22 25-Apr-22
310.C.EX.S000.01bB02 Contract award (Tentative) C01_7 d/w - 10h/d - No HK 0 27-Jan-22 A 28-Mar-22
Hols - No B/O periods (was
310.C.EX.S000.02bB02 Mobilization C1)
C01_7 d/w - 10h/d - No HK 0 27-Jan-22 A 02-Feb-22 A 28-Mar-22 28-Mar-22
Hols - No B/O periods (was
310.C.EX.S000.03bB02 Prepare and submit O Chart C1)
C01_7 d/w - 10h/d - No HK 0 03-Feb-22 A 07-Feb-22 A 28-Mar-22 28-Mar-22
Hols - No B/O periods (was
310.C.EX.S000.04bB02 Prepare and submit Equipment/Material Submission Schedule C1)
C01_7 d/w - 10h/d - No HK 0 03-Feb-22 A 08-Feb-22 A 28-Mar-22 28-Mar-22
Hols - No B/O periods (was
310.C.EX.S000.05bB02 Prepare and submit Drawing Submission Shcedule C1)
C01_7 d/w - 10h/d - No HK 0 03-Feb-22 A 08-Feb-22 A 25-Apr-22 25-Apr-22
Hols - No B/O periods (was
C1)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 128 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
Electrical C01_7 d/w - 10h/d - No HK Hols103
- No B/O periods
0 (was
06-Mar-22
C1) A 16-Jun-22 23-Apr-22 01-Aug-22 46
Armoured Cable C01_7 d/w - 10h/d - No HK Hols53
- No B/O periods
0 (was
14-Mar-22
C1) A 18-May-22 22-May-22 13-Jul-22 56
310.D.WS.L992.01bB02Prepare and submit info. of Armoured Cable C01_7 d/w - 10h/d - No HK 0 14-Mar-22 A 07-Apr-22 22-May-22 02-Jun-22 56
Hols - No B/O periods (was
310.D.WS.L993.01bB02Review and comment info. of Armoured Cable C1)
C01_7 d/w - 10h/d - No HK 23 08-Apr-22 30-Apr-22 03-Jun-22 25-Jun-22 56
Hols - No B/O periods (was
310.D.WS.L994.01bB02Prepare and re-submit info. of Armoured Cable C1)
C01_7 d/w - 10h/d - No HK 9 01-May-22 09-May-22 26-Jun-22 04-Jul-22 56
Hols - No B/O periods (was
310.D.WS.L996.01bB02Obtain "No objection" of Armoured Cable C1)
C01_7 d/w - 10h/d - No HK 9 10-May-22 18-May-22 05-Jul-22 13-Jul-22 56
Hols - No B/O periods (was
FR Cable C1)
C01_7 d/w - 10h/d - No HK Hols82
- No B/O periods
0 (was
14-Mar-22
C1) A 16-Jun-22 23-Apr-22 13-Jul-22 27
310.D.WS.L992.02bB02Prepare and submit info. of FR Cable C01_7 d/w - 10h/d - No HK 0 14-Mar-22 A 07-Apr-22 23-Apr-22 04-May-22 27
Hols - No B/O periods (was
310.D.WS.L993.02bB02Review and comment info. of FR Cable C1)
C01_7 d/w - 10h/d - No HK 24 08-Apr-22 01-May-22 05-May-22 28-May-22 27
Hols - No B/O periods (was
310.D.WS.L994.02bB02Prepare and re-submit info. of FR Cable C1)
C01_7 d/w - 10h/d - No HK 22 02-May-22 23-May-22 29-May-22 19-Jun-22 27
Hols - No B/O periods (was
310.D.WS.L996.02bB02Obtain "No objection" of FR Cable C1)
C01_7 d/w - 10h/d - No HK 24 24-May-22 16-Jun-22 20-Jun-22 13-Jul-22 27
Hols - No B/O periods (was
Single Core Cable C1)
C01_7 d/w - 10h/d - No HK Hols46
- No B/O periods
0 (was
14-Mar-22
C1) A 19-May-22 21-May-22 13-Jul-22 55
310.D.WS.L992.03bB02Prepare and submit info. of Single Core Cable C01_7 d/w - 10h/d - No HK 0 14-Mar-22 A 07-Apr-22 21-May-22 01-Jun-22 55
Hols - No B/O periods (was
310.D.WS.L993.03bB02Review and comment info. of Single Core Cable C1)
C01_7 d/w - 10h/d - No HK 24 08-Apr-22 01-May-22 02-Jun-22 25-Jun-22 55
Hols - No B/O periods (was
310.D.WS.L994.03bB02Prepare and re-submit info. of Single Core Cable C1)
C01_7 d/w - 10h/d - No HK 9 02-May-22 10-May-22 26-Jun-22 04-Jul-22 55
Hols - No B/O periods (was
310.D.WS.L996.03bB02Obtain "No objection" of Single Core Cable C1)
C01_7 d/w - 10h/d - No HK 9 11-May-22 19-May-22 05-Jul-22 13-Jul-22 55
Hols - No B/O periods (was
General Lighting (included E-Lighting) C1)
C01_7 d/w - 10h/d - No HK Hols60
- No B/O periods
0 (was
20-Mar-22
C1) A 19-May-22 21-May-22 13-Jul-22 55
310.D.WS.L992.04bB02Prepare and submit info. of General Lighting (included E-Lighting) C01_7 d/w - 10h/d - No HK 12 20-Mar-22 A 07-Apr-22 21-May-22 01-Jun-22 55
Hols - No B/O periods (was
310.D.WS.L993.04bB02Review and comment info. of General Lighting (included E-Lighting) C1)
C01_7 d/w - 10h/d - No HK 24 08-Apr-22 01-May-22 02-Jun-22 25-Jun-22 55
Hols - No B/O periods (was
310.D.WS.L994.04bB02Prepare and re-submit info. of General Lighting (included E-Lighting) C1)
C01_7 d/w - 10h/d - No HK 9 02-May-22 10-May-22 26-Jun-22 04-Jul-22 55
Hols - No B/O periods (was
310.D.WS.L996.04bB02Obtain "No objection" of General Lighting (included E-Lighting) C1)
C01_7 d/w - 10h/d - No HK 9 11-May-22 19-May-22 05-Jul-22 13-Jul-22 55
Hols - No B/O periods (was
Distribution Board for MCB, MCCB & Accessories C1)
C01_7 d/w - 10h/d - No HK Hols68
- No B/O periods
0 (was
11-Mar-22
C1) A 17-May-22 23-May-22 13-Jul-22 57
310.D.WS.L992.05bB02Prepare and submit info. of Distribution Board for MCB, MCCB & Accessories C01_7 d/w - 10h/d - No HK 10 11-Mar-22 A 05-Apr-22 23-May-22 01-Jun-22 57
Hols - No B/O periods (was
310.D.WS.L993.05bB02Review and comment info. of Distribution Board for MCB, MCCB & Accessories C1)
C01_7 d/w - 10h/d - No HK 24 06-Apr-22 29-Apr-22 02-Jun-22 25-Jun-22 57
Hols - No B/O periods (was
310.D.WS.L994.05bB02Prepare and re-submit info. of Distribution Board for MCB, MCCB & Accessories C1)
C01_7 d/w - 10h/d - No HK 9 30-Apr-22 08-May-22 26-Jun-22 04-Jul-22 57
Hols - No B/O periods (was
310.D.WS.L996.05bB02Obtain "No objection" of Distribution Board for MCB, MCCB & Accessories C1)
C01_7 d/w - 10h/d - No HK 9 09-May-22 17-May-22 05-Jul-22 13-Jul-22 57
Hols - No B/O periods (was
MCB, MCCB & Accessories C1)
C01_7 d/w - 10h/d - No HK Hols64
- No B/O periods
0 (was
11-Mar-22
C1) A 13-May-22 27-May-22 13-Jul-22 61
310.D.WS.L992.06bB02Prepare and submit info. of MCB, MCCB & Accessories C01_7 d/w - 10h/d - No HK 6 11-Mar-22 A 01-Apr-22 27-May-22 01-Jun-22 61
Hols - No B/O periods (was
310.D.WS.L993.06bB02Review and comment info. of MCB, MCCB & Accessories C1)
C01_7 d/w - 10h/d - No HK 24 02-Apr-22 25-Apr-22 02-Jun-22 25-Jun-22 61
Hols - No B/O periods (was
C1)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 129 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L994.06bB02Prepare and re-submit info. of MCB, MCCB & Accessories C01_7 d/w - 10h/d - No HK 9 26-Apr-22 04-May-22 26-Jun-22 04-Jul-22 61
Hols - No B/O periods (was
310.D.WS.L996.06bB02Obtain "No objection" of MCB, MCCB & Accessories C1)
C01_7 d/w - 10h/d - No HK 9 05-May-22 13-May-22 05-Jul-22 13-Jul-22 61
Hols - No B/O periods (was
Busduct C1)
C01_7 d/w - 10h/d - No HK Hols62
- No B/O periods
0 (was04-Apr-22
C1) 04-Jun-22 01-Jun-22 01-Aug-22 58
310.D.WS.L992.07bB02Prepare and submit info. of Busduct C01_7 d/w - 10h/d - No HK 20 04-Apr-22 23-Apr-22 01-Jun-22 20-Jun-22 58
Hols - No B/O periods (was
310.D.WS.L993.07bB02Review and comment info. of Busduct C1)
C01_7 d/w - 10h/d - No HK 24 24-Apr-22 17-May-22 21-Jun-22 14-Jul-22 58
Hols - No B/O periods (was
310.D.WS.L994.07bB02Prepare and re-submit info. of Busduct C1)
C01_7 d/w - 10h/d - No HK 9 18-May-22 26-May-22 15-Jul-22 23-Jul-22 58
Hols - No B/O periods (was
310.D.WS.L996.07bB02Obtain "No objection" of Busduct C1)
C01_7 d/w - 10h/d - No HK 9 27-May-22 04-Jun-22 24-Jul-22 01-Aug-22 58
Hols - No B/O periods (was
Water Leakage Detection System C1)
C01_7 d/w - 10h/d - No HK Hols62
- No B/O periods
0 (was04-Apr-22
C1) 04-Jun-22 01-Jun-22 01-Aug-22 58
310.D.WS.L992.08bB02Prepare and submit info. of Water Leakage Detection System C01_7 d/w - 10h/d - No HK 20 04-Apr-22 23-Apr-22 01-Jun-22 20-Jun-22 58
Hols - No B/O periods (was
310.D.WS.L993.08bB02Review and comment info. of Water Leakage Detection System C1)
C01_7 d/w - 10h/d - No HK 24 24-Apr-22 17-May-22 21-Jun-22 14-Jul-22 58
Hols - No B/O periods (was
310.D.WS.L994.08bB02Prepare and re-submit info. of Water Leakage Detection System C1)
C01_7 d/w - 10h/d - No HK 9 18-May-22 26-May-22 15-Jul-22 23-Jul-22 58
Hols - No B/O periods (was
310.D.WS.L996.08bB02Obtain "No objection" of Water Leakage Detection System C1)
C01_7 d/w - 10h/d - No HK 9 27-May-22 04-Jun-22 24-Jul-22 01-Aug-22 58
Hols - No B/O periods (was
MICC Cable C1)
C01_7 d/w - 10h/d - No HK Hols76
- No B/O periods
0 (was
07-Mar-22
C1) A 21-May-22 07-Jun-22 01-Aug-22 72
310.D.WS.L992.09bB02Prepare and submit info. of MICC Cable C01_7 d/w - 10h/d - No HK 14 07-Mar-22 A 09-Apr-22 07-Jun-22 20-Jun-22 72
Hols - No B/O periods (was
310.D.WS.L993.09bB02Review and comment info. of MICC Cable C1)
C01_7 d/w - 10h/d - No HK 24 10-Apr-22 03-May-22 21-Jun-22 14-Jul-22 72
Hols - No B/O periods (was
310.D.WS.L994.09bB02Prepare and re-submit info. of MICC Cable C1)
C01_7 d/w - 10h/d - No HK 9 04-May-22 12-May-22 15-Jul-22 23-Jul-22 72
Hols - No B/O periods (was
310.D.WS.L996.09bB02Obtain "No objection" of MICC Cable C1)
C01_7 d/w - 10h/d - No HK 9 13-May-22 21-May-22 24-Jul-22 01-Aug-22 72
Hols - No B/O periods (was
LV Switchboards & Accessories C1)
C01_7 d/w - 10h/d - No HK Hols61
- No B/O periods
0 (was
22-Mar-22
C1) A 21-May-22 07-Jun-22 01-Aug-22 72
310.D.WS.L992.10bB02Prepare and submit info. of LV Switchboards & Accessories C01_7 d/w - 10h/d - No HK 14 22-Mar-22 A 09-Apr-22 07-Jun-22 20-Jun-22 72
Hols - No B/O periods (was
310.D.WS.L993.10bB02Review and comment info. of LV Switchboards & Accessories C1)
C01_7 d/w - 10h/d - No HK 24 10-Apr-22 03-May-22 21-Jun-22 14-Jul-22 72
Hols - No B/O periods (was
310.D.WS.L994.10bB02Prepare and re-submit info. of LV Switchboards & Accessories C1)
C01_7 d/w - 10h/d - No HK 9 04-May-22 12-May-22 15-Jul-22 23-Jul-22 72
Hols - No B/O periods (was
310.D.WS.L996.10bB02Obtain "No objection" of LV Switchboards & Accessories C1)
C01_7 d/w - 10h/d - No HK 9 13-May-22 21-May-22 24-Jul-22 01-Aug-22 72
Hols - No B/O periods (was
ACB & Accessories C1)
C01_7 d/w - 10h/d - No HK Hols61
- No B/O periods
0 (was
22-Mar-22
C1) A 21-May-22 07-Jun-22 01-Aug-22 72
310.D.WS.L992.11bB02Prepare and submit info. of ACB & Accessories C01_7 d/w - 10h/d - No HK 14 22-Mar-22 A 09-Apr-22 07-Jun-22 20-Jun-22 72
Hols - No B/O periods (was
310.D.WS.L993.11bB02Review and comment info. of ACB & Accessories C1)
C01_7 d/w - 10h/d - No HK 24 10-Apr-22 03-May-22 21-Jun-22 14-Jul-22 72
Hols - No B/O periods (was
310.D.WS.L994.11bB02Prepare and re-submit info. of ACB & Accessories C1)
C01_7 d/w - 10h/d - No HK 9 04-May-22 12-May-22 15-Jul-22 23-Jul-22 72
Hols - No B/O periods (was
310.D.WS.L996.11bB02Obtain "No objection" of ACB & Accessories C1)
C01_7 d/w - 10h/d - No HK 9 13-May-22 21-May-22 24-Jul-22 01-Aug-22 72
Hols - No B/O periods (was
Automatic Transfer Switch C1)
C01_7 d/w - 10h/d - No HK Hols61
- No B/O periods
0 (was
22-Mar-22
C1) A 21-May-22 07-Jun-22 01-Aug-22 72

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 130 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L992.12bB02Prepare and submit info. of Automatic Transfer Switch C01_7 d/w - 10h/d - No HK 14 22-Mar-22 A 09-Apr-22 07-Jun-22 20-Jun-22 72
Hols - No B/O periods (was
310.D.WS.L993.12bB02Review and comment info. of Automatic Transfer Switch C1)
C01_7 d/w - 10h/d - No HK 24 10-Apr-22 03-May-22 21-Jun-22 14-Jul-22 72
Hols - No B/O periods (was
310.D.WS.L994.12bB02Prepare and re-submit info. of Automatic Transfer Switch C1)
C01_7 d/w - 10h/d - No HK 9 04-May-22 12-May-22 15-Jul-22 23-Jul-22 72
Hols - No B/O periods (was
310.D.WS.L996.12bB02Obtain "No objection" of Automatic Transfer Switch C1)
C01_7 d/w - 10h/d - No HK 9 13-May-22 21-May-22 24-Jul-22 01-Aug-22 72
Hols - No B/O periods (was
Battery Set C1)
C01_7 d/w - 10h/d - No HK Hols61
- No B/O periods
0 (was
22-Mar-22
C1) A 21-May-22 07-Jun-22 01-Aug-22 72
310.D.WS.L992.13bB02Prepare and submit info. of Battery Set C01_7 d/w - 10h/d - No HK 14 22-Mar-22 A 09-Apr-22 07-Jun-22 20-Jun-22 72
Hols - No B/O periods (was
310.D.WS.L993.13bB02Review and comment info. of Battery Set C1)
C01_7 d/w - 10h/d - No HK 24 10-Apr-22 03-May-22 21-Jun-22 14-Jul-22 72
Hols - No B/O periods (was
310.D.WS.L994.13bB02Prepare and re-submit info. of Battery Set C1)
C01_7 d/w - 10h/d - No HK 9 04-May-22 12-May-22 15-Jul-22 23-Jul-22 72
Hols - No B/O periods (was
310.D.WS.L996.13bB02Obtain "No objection" of Battery Set C1)
C01_7 d/w - 10h/d - No HK 9 13-May-22 21-May-22 24-Jul-22 01-Aug-22 72
Hols - No B/O periods (was
HRC Fuse for Fuse-switch C1)
C01_7 d/w - 10h/d - No HK Hols62
- No B/O periods
0 (was27-Mar-22
C1) 27-May-22 01-Jun-22 01-Aug-22 66
310.D.WS.L992.14bB02Prepare and submit info. of HRC Fuse for Fuse-switch C01_7 d/w - 10h/d - No HK 20 27-Mar-22 15-Apr-22 01-Jun-22 20-Jun-22 66
Hols - No B/O periods (was
310.D.WS.L993.14bB02Review and comment info. of HRC Fuse for Fuse-switch C1)
C01_7 d/w - 10h/d - No HK 24 16-Apr-22 09-May-22 21-Jun-22 14-Jul-22 66
Hols - No B/O periods (was
310.D.WS.L994.14bB02Prepare and re-submit info. of HRC Fuse for Fuse-switch C1)
C01_7 d/w - 10h/d - No HK 9 10-May-22 18-May-22 15-Jul-22 23-Jul-22 66
Hols - No B/O periods (was
310.D.WS.L996.14bB02Obtain "No objection" of HRC Fuse for Fuse-switch C1)
C01_7 d/w - 10h/d - No HK 9 19-May-22 27-May-22 24-Jul-22 01-Aug-22 66
Hols - No B/O periods (was
MCCB C1)
C01_7 d/w - 10h/d - No HK Hols61
- No B/O periods
0 (was
22-Mar-22
C1) A 21-May-22 07-Jun-22 01-Aug-22 72
310.D.WS.L992.15bB02Prepare and submit info. of MCCB C01_7 d/w - 10h/d - No HK 14 22-Mar-22 A 09-Apr-22 07-Jun-22 20-Jun-22 72
Hols - No B/O periods (was
310.D.WS.L993.15bB02Review and comment info. of MCCB C1)
C01_7 d/w - 10h/d - No HK 24 10-Apr-22 03-May-22 21-Jun-22 14-Jul-22 72
Hols - No B/O periods (was
310.D.WS.L994.15bB02Prepare and re-submit info. of MCCB C1)
C01_7 d/w - 10h/d - No HK 9 04-May-22 12-May-22 15-Jul-22 23-Jul-22 72
Hols - No B/O periods (was
310.D.WS.L996.15bB02Obtain "No objection" of MCCB C1)
C01_7 d/w - 10h/d - No HK 9 13-May-22 21-May-22 24-Jul-22 01-Aug-22 72
Hols - No B/O periods (was
Digital Protection Device C1)
C01_7 d/w - 10h/d - No HK Hols77
- No B/O periods
0 (was
06-Mar-22
C1) A 21-May-22 07-Jun-22 01-Aug-22 72
310.D.WS.L992.16bB02Prepare and submit info. of Digital Protection Device C01_7 d/w - 10h/d - No HK 14 06-Mar-22 A 09-Apr-22 07-Jun-22 20-Jun-22 72
Hols - No B/O periods (was
310.D.WS.L993.16bB02Review and comment info. of Digital Protection Device C1)
C01_7 d/w - 10h/d - No HK 24 10-Apr-22 03-May-22 21-Jun-22 14-Jul-22 72
Hols - No B/O periods (was
310.D.WS.L994.16bB02Prepare and re-submit info. of Digital Protection Device C1)
C01_7 d/w - 10h/d - No HK 9 04-May-22 12-May-22 15-Jul-22 23-Jul-22 72
Hols - No B/O periods (was
310.D.WS.L996.16bB02Obtain "No objection" of Digital Protection Device C1)
C01_7 d/w - 10h/d - No HK 9 13-May-22 21-May-22 24-Jul-22 01-Aug-22 72
Hols - No B/O periods (was
Capacitor Bank C1)
C01_7 d/w - 10h/d - No HK Hols77
- No B/O periods
0 (was
06-Mar-22
C1) A 21-May-22 07-Jun-22 01-Aug-22 72
310.D.WS.L992.17bB02Prepare and submit info. of Capacitor Bank C01_7 d/w - 10h/d - No HK 14 06-Mar-22 A 09-Apr-22 07-Jun-22 20-Jun-22 72
Hols - No B/O periods (was
310.D.WS.L993.17bB02Review and comment info. of Capacitor Bank C1)
C01_7 d/w - 10h/d - No HK 24 10-Apr-22 03-May-22 21-Jun-22 14-Jul-22 72
Hols - No B/O periods (was
310.D.WS.L994.17bB02Prepare and re-submit info. of Capacitor Bank C1)
C01_7 d/w - 10h/d - No HK 9 04-May-22 12-May-22 15-Jul-22 23-Jul-22 72
Hols - No B/O periods (was
C1)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 131 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L996.17bB02Obtain "No objection" of Capacitor Bank C01_7 d/w - 10h/d - No HK 9 13-May-22 21-May-22 24-Jul-22 01-Aug-22 72
Hols - No B/O periods (was
UPS C1)
C01_7 d/w - 10h/d - No HK Hols56
- No B/O periods
0 (was29-Mar-22
C1) 23-May-22 07-Jun-22 01-Aug-22 70
310.D.WS.L992.18bB02Prepare and submit info. of UPS C01_7 d/w - 10h/d - No HK 14 29-Mar-22 11-Apr-22 07-Jun-22 20-Jun-22 70
Hols - No B/O periods (was
310.D.WS.L993.18bB02Review and comment info. of UPS C1)
C01_7 d/w - 10h/d - No HK 24 12-Apr-22 05-May-22 21-Jun-22 14-Jul-22 70
Hols - No B/O periods (was
310.D.WS.L994.18bB02Prepare and re-submit info. of UPS C1)
C01_7 d/w - 10h/d - No HK 9 06-May-22 14-May-22 15-Jul-22 23-Jul-22 70
Hols - No B/O periods (was
310.D.WS.L996.18bB02Obtain "No objection" of UPS C1)
C01_7 d/w - 10h/d - No HK 9 15-May-22 23-May-22 24-Jul-22 01-Aug-22 70
Hols - No B/O periods (was
Active Harmoice Filter C1)
C01_7 d/w - 10h/d - No HK Hols56
- No B/O periods
0 (was29-Mar-22
C1) 23-May-22 07-Jun-22 01-Aug-22 70
310.D.WS.L992.19bB02Prepare and submit info. of Active Harmoice Filter C01_7 d/w - 10h/d - No HK 14 29-Mar-22 11-Apr-22 07-Jun-22 20-Jun-22 70
Hols - No B/O periods (was
310.D.WS.L993.19bB02Review and comment info. of Active Harmoice Filter C1)
C01_7 d/w - 10h/d - No HK 24 12-Apr-22 05-May-22 21-Jun-22 14-Jul-22 70
Hols - No B/O periods (was
310.D.WS.L994.19bB02Prepare and re-submit info. of Active Harmoice Filter C1)
C01_7 d/w - 10h/d - No HK 9 06-May-22 14-May-22 15-Jul-22 23-Jul-22 70
Hols - No B/O periods (was
310.D.WS.L996.19bB02Obtain "No objection" of Active Harmoice Filter C1)
C01_7 d/w - 10h/d - No HK 9 15-May-22 23-May-22 24-Jul-22 01-Aug-22 70
Hols - No B/O periods (was
Isolation Transformer C1)
C01_7 d/w - 10h/d - No HK Hols56
- No B/O periods
0 (was29-Mar-22
C1) 23-May-22 07-Jun-22 01-Aug-22 70
310.D.WS.L992.20bB02Prepare and submit info. of Isolation Transformer C01_7 d/w - 10h/d - No HK 14 29-Mar-22 11-Apr-22 07-Jun-22 20-Jun-22 70
Hols - No B/O periods (was
310.D.WS.L993.20bB02Review and comment info. of Isolation Transformer C1)
C01_7 d/w - 10h/d - No HK 24 12-Apr-22 05-May-22 21-Jun-22 14-Jul-22 70
Hols - No B/O periods (was
310.D.WS.L994.20bB02Prepare and re-submit info. of Isolation Transformer C1)
C01_7 d/w - 10h/d - No HK 9 06-May-22 14-May-22 15-Jul-22 23-Jul-22 70
Hols - No B/O periods (was
310.D.WS.L996.20bB02Obtain "No objection" of Isolation Transformer C1)
C01_7 d/w - 10h/d - No HK 9 15-May-22 23-May-22 24-Jul-22 01-Aug-22 70
Hols - No B/O periods (was
By-pass switch C1)
C01_7 d/w - 10h/d - No HK Hols62
- No B/O periods
0 (was27-Mar-22
C1) 27-May-22 01-Jun-22 01-Aug-22 66
310.D.WS.L992.21bB02Prepare and submit info. of By-pass switch C01_7 d/w - 10h/d - No HK 20 27-Mar-22 15-Apr-22 01-Jun-22 20-Jun-22 66
Hols - No B/O periods (was
310.D.WS.L993.21bB02Review and comment info. of By-pass switch C1)
C01_7 d/w - 10h/d - No HK 24 16-Apr-22 09-May-22 21-Jun-22 14-Jul-22 66
Hols - No B/O periods (was
310.D.WS.L994.21bB02Prepare and re-submit info. of By-pass switch C1)
C01_7 d/w - 10h/d - No HK 9 10-May-22 18-May-22 15-Jul-22 23-Jul-22 66
Hols - No B/O periods (was
310.D.WS.L996.21bB02Obtain "No objection" of By-pass switch C1)
C01_7 d/w - 10h/d - No HK 9 19-May-22 27-May-22 24-Jul-22 01-Aug-22 66
Hols - No B/O periods (was
LV Generator Set (included Alternator & Diesel Engine) C1)
C01_7 d/w - 10h/d - No HK Hols54
- No B/O periods
0 (was
22-Mar-22
C1) A 14-May-22 14-Jun-22 01-Aug-22 79
310.D.WS.L992.22bB02Prepare and submit info. of LV Generator Set (included Alternator & Diesel Engine) C01_7 d/w - 10h/d - No HK 7 22-Mar-22 A 02-Apr-22 14-Jun-22 20-Jun-22 79
Hols - No B/O periods (was
310.D.WS.L993.22bB02Review and comment info. of LV Generator Set (included Alternator & Diesel Engine) C1)
C01_7 d/w - 10h/d - No HK 24 03-Apr-22 26-Apr-22 21-Jun-22 14-Jul-22 79
Hols - No B/O periods (was
310.D.WS.L994.22bB02Prepare and re-submit info. of LV Generator Set (included Alternator & Diesel Engine) C1)
C01_7 d/w - 10h/d - No HK 9 27-Apr-22 05-May-22 15-Jul-22 23-Jul-22 79
Hols - No B/O periods (was
310.D.WS.L996.22bB02Obtain "No objection" of LV Generator Set (included Alternator & Diesel Engine) C1)
C01_7 d/w - 10h/d - No HK 9 06-May-22 14-May-22 24-Jul-22 01-Aug-22 79
Hols - No B/O periods (was
Generator Controller C1)
C01_7 d/w - 10h/d - No HK Hols54
- No B/O periods
0 (was
22-Mar-22
C1) A 14-May-22 14-Jun-22 01-Aug-22 79
310.D.WS.L992.23bB02Prepare and submit info. of Generator Controller C01_7 d/w - 10h/d - No HK 7 22-Mar-22 A 02-Apr-22 14-Jun-22 20-Jun-22 79
Hols - No B/O periods (was
C1)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 132 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L993.23bB02Review and comment info. of Generator Controller C01_7 d/w - 10h/d - No HK 24 03-Apr-22 26-Apr-22 21-Jun-22 14-Jul-22 79
Hols - No B/O periods (was
310.D.WS.L994.23bB02Prepare and re-submit info. of Generator Controller C1)
C01_7 d/w - 10h/d - No HK 9 27-Apr-22 05-May-22 15-Jul-22 23-Jul-22 79
Hols - No B/O periods (was
310.D.WS.L996.23bB02Obtain "No objection" of Generator Controller C1)
C01_7 d/w - 10h/d - No HK 9 06-May-22 14-May-22 24-Jul-22 01-Aug-22 79
Hols - No B/O periods (was
Starting Battery System C1)
C01_7 d/w - 10h/d - No HK Hols54
- No B/O periods
0 (was
22-Mar-22
C1) A 14-May-22 14-Jun-22 01-Aug-22 79
310.D.WS.L992.24bB02Prepare and submit info. of Starting Battery System C01_7 d/w - 10h/d - No HK 7 22-Mar-22 A 02-Apr-22 14-Jun-22 20-Jun-22 79
Hols - No B/O periods (was
310.D.WS.L993.24bB02Review and comment info. of Starting Battery System C1)
C01_7 d/w - 10h/d - No HK 24 03-Apr-22 26-Apr-22 21-Jun-22 14-Jul-22 79
Hols - No B/O periods (was
310.D.WS.L994.24bB02Prepare and re-submit info. of Starting Battery System C1)
C01_7 d/w - 10h/d - No HK 9 27-Apr-22 05-May-22 15-Jul-22 23-Jul-22 79
Hols - No B/O periods (was
310.D.WS.L996.24bB02Obtain "No objection" of Starting Battery System C1)
C01_7 d/w - 10h/d - No HK 9 06-May-22 14-May-22 24-Jul-22 01-Aug-22 79
Hols - No B/O periods (was
Battery Charger C1)
C01_7 d/w - 10h/d - No HK Hols54
- No B/O periods
0 (was
22-Mar-22
C1) A 14-May-22 14-Jun-22 01-Aug-22 79
310.D.WS.L992.25bB02Prepare and submit info. of Battery Charger C01_7 d/w - 10h/d - No HK 7 22-Mar-22 A 02-Apr-22 14-Jun-22 20-Jun-22 79
Hols - No B/O periods (was
310.D.WS.L993.25bB02Review and comment info. of Battery Charger C1)
C01_7 d/w - 10h/d - No HK 24 03-Apr-22 26-Apr-22 21-Jun-22 14-Jul-22 79
Hols - No B/O periods (was
310.D.WS.L994.25bB02Prepare and re-submit info. of Battery Charger C1)
C01_7 d/w - 10h/d - No HK 9 27-Apr-22 05-May-22 15-Jul-22 23-Jul-22 79
Hols - No B/O periods (was
310.D.WS.L996.25bB02Obtain "No objection" of Battery Charger C1)
C01_7 d/w - 10h/d - No HK 9 06-May-22 14-May-22 24-Jul-22 01-Aug-22 79
Hols - No B/O periods (was
MVAC C1)
C01_7 d/w - 10h/d - No HK Hols115
- No B/O periods
0 (was
08-Feb-22
C1) A 26-Jun-22 04-Apr-22 01-Aug-22 36
CRAC Unit C01_7 d/w - 10h/d - No HK Hols72
- No B/O periods
0 (was
04-Mar-22
C1) A 14-May-22 14-Jun-22 01-Aug-22 79
310.D.WS.L992.26bB02Prepare and submit info. of CRAC Unit C01_7 d/w - 10h/d - No HK 7 04-Mar-22 A 02-Apr-22 14-Jun-22 20-Jun-22 79
Hols - No B/O periods (was
310.D.WS.L993.26bB02Review and comment info. of CRAC Unit C1)
C01_7 d/w - 10h/d - No HK 24 03-Apr-22 26-Apr-22 21-Jun-22 14-Jul-22 79
Hols - No B/O periods (was
310.D.WS.L994.26bB02Prepare and re-submit info. of CRAC Unit C1)
C01_7 d/w - 10h/d - No HK 9 27-Apr-22 05-May-22 15-Jul-22 23-Jul-22 79
Hols - No B/O periods (was
310.D.WS.L996.26bB02Obtain "No objection" of CRAC Unit C1)
C01_7 d/w - 10h/d - No HK 9 06-May-22 14-May-22 24-Jul-22 01-Aug-22 79
Hols - No B/O periods (was
Axial Fan C1)
C01_7 d/w - 10h/d - No HK Hols69
- No B/O periods
0 (was
04-Mar-22
C1) A 11-May-22 04-Apr-22 19-May-22 8
310.D.WS.L992.27bB02Prepare and submit info. of Axial Fan C01_7 d/w - 10h/d - No HK 4 04-Mar-22 A 30-Mar-22 04-Apr-22 07-Apr-22 8
Hols - No B/O periods (was
310.D.WS.L993.27bB02Review and comment info. of Axial Fan C1)
C01_7 d/w - 10h/d - No HK 24 31-Mar-22 23-Apr-22 08-Apr-22 01-May-22 8
Hols - No B/O periods (was
310.D.WS.L994.27bB02Prepare and re-submit info. of Axial Fan C1)
C01_7 d/w - 10h/d - No HK 9 24-Apr-22 02-May-22 02-May-22 10-May-22 8
Hols - No B/O periods (was
310.D.WS.L996.27bB02Obtain "No objection" of Axial Fan C1)
C01_7 d/w - 10h/d - No HK 9 03-May-22 11-May-22 11-May-22 19-May-22 8
Hols - No B/O periods (was
Split Type & VRV AC Unit C1)
C01_7 d/w - 10h/d - No HK Hols72
- No B/O periods
0 (was
04-Mar-22
C1) A 14-May-22 14-Jun-22 01-Aug-22 79
310.D.WS.L992.30bB02Prepare and submit info. of Split Type & VRV AC Unit C01_7 d/w - 10h/d - No HK 7 04-Mar-22 A 02-Apr-22 14-Jun-22 20-Jun-22 79
Hols - No B/O periods (was
310.D.WS.L993.30bB02Review and comment info. of Split Type & VRV AC Unit C1)
C01_7 d/w - 10h/d - No HK 24 03-Apr-22 26-Apr-22 21-Jun-22 14-Jul-22 79
Hols - No B/O periods (was
310.D.WS.L994.30bB02Prepare and re-submit info. of Split Type & VRV AC Unit C1)
C01_7 d/w - 10h/d - No HK 9 27-Apr-22 05-May-22 15-Jul-22 23-Jul-22 79
Hols - No B/O periods (was
C1)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 133 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L996.30bB02Obtain "No objection" of Split Type & VRV AC Unit C01_7 d/w - 10h/d - No HK 9 06-May-22 14-May-22 24-Jul-22 01-Aug-22 79
Hols - No B/O periods (was
Tunnel Jet Fan C1)
C01_7 d/w - 10h/d - No HK Hols54
- No B/O periods
0 (was
04-Apr-22
C1) A 27-May-22 13-May-22 13-Jul-22 47
310.D.WS.L992.31bB02Prepare and submit info. of Tunnel Jet Fan C01_7 d/w - 10h/d - No HK 20 04-Apr-22 A 15-Apr-22 13-May-22 01-Jun-22 47
Hols - No B/O periods (was
310.D.WS.L993.31bB02Review and comment info. of Tunnel Jet Fan C1)
C01_7 d/w - 10h/d - No HK 24 16-Apr-22 09-May-22 02-Jun-22 25-Jun-22 47
Hols - No B/O periods (was
310.D.WS.L994.31bB02Prepare and re-submit info. of Tunnel Jet Fan C1)
C01_7 d/w - 10h/d - No HK 9 10-May-22 18-May-22 26-Jun-22 04-Jul-22 47
Hols - No B/O periods (was
310.D.WS.L996.31bB02Obtain "No objection" of Tunnel Jet Fan C1)
C01_7 d/w - 10h/d - No HK 9 19-May-22 27-May-22 05-Jul-22 13-Jul-22 47
Hols - No B/O periods (was
Motor Control Centre C1)
C01_7 d/w - 10h/d - No HK Hols55
- No B/O periods
0 (was27-Mar-22
C1) 20-May-22 08-Jun-22 01-Aug-22 73
310.D.WS.L992.33bB02Prepare and submit info. of Motor Control Centre C01_7 d/w - 10h/d - No HK 13 27-Mar-22 08-Apr-22 08-Jun-22 20-Jun-22 73
Hols - No B/O periods (was
310.D.WS.L993.33bB02Review and comment info. of Motor Control Centre C1)
C01_7 d/w - 10h/d - No HK 24 09-Apr-22 02-May-22 21-Jun-22 14-Jul-22 73
Hols - No B/O periods (was
310.D.WS.L994.33bB02Prepare and re-submit info. of Motor Control Centre C1)
C01_7 d/w - 10h/d - No HK 9 03-May-22 11-May-22 15-Jul-22 23-Jul-22 73
Hols - No B/O periods (was
310.D.WS.L996.33bB02Obtain "No objection" of Motor Control Centre C1)
C01_7 d/w - 10h/d - No HK 9 12-May-22 20-May-22 24-Jul-22 01-Aug-22 73
Hols - No B/O periods (was
Local Motor Control Panel C1)
C01_7 d/w - 10h/d - No HK Hols59
- No B/O periods
0 (was27-Mar-22
C1) 24-May-22 16-May-22 13-Jul-22 50
310.D.WS.L992.34bB02Prepare and submit info. of Local Motor Control Panel C01_7 d/w - 10h/d - No HK 17 27-Mar-22 12-Apr-22 16-May-22 01-Jun-22 50
Hols - No B/O periods (was
310.D.WS.L993.34bB02Review and comment info. of Local Motor Control Panel C1)
C01_7 d/w - 10h/d - No HK 24 13-Apr-22 06-May-22 02-Jun-22 25-Jun-22 50
Hols - No B/O periods (was
310.D.WS.L994.34bB02Prepare and re-submit info. of Local Motor Control Panel C1)
C01_7 d/w - 10h/d - No HK 9 07-May-22 15-May-22 26-Jun-22 04-Jul-22 50
Hols - No B/O periods (was
310.D.WS.L996.34bB02Obtain "No objection" of Local Motor Control Panel C1)
C01_7 d/w - 10h/d - No HK 9 16-May-22 24-May-22 05-Jul-22 13-Jul-22 50
Hols - No B/O periods (was
MFSD C1)
C01_7 d/w - 10h/d - No HK Hols72
- No B/O periods
0 (was
04-Mar-22
C1) A 14-May-22 26-May-22 13-Jul-22 60
310.D.WS.L992.35bB02Prepare and submit info. of MFSD C01_7 d/w - 10h/d - No HK 7 04-Mar-22 A 02-Apr-22 26-May-22 01-Jun-22 60
Hols - No B/O periods (was
310.D.WS.L993.35bB02Review and comment info. of MSD C1)
C01_7 d/w - 10h/d - No HK 24 03-Apr-22 26-Apr-22 02-Jun-22 25-Jun-22 60
Hols - No B/O periods (was
310.D.WS.L994.35bB02Prepare and re-submit info. of MSD C1)
C01_7 d/w - 10h/d - No HK 9 27-Apr-22 05-May-22 26-Jun-22 04-Jul-22 60
Hols - No B/O periods (was
310.D.WS.L996.35bB02Obtain "No objection" of MSD C1)
C01_7 d/w - 10h/d - No HK 9 06-May-22 14-May-22 05-Jul-22 13-Jul-22 60
Hols - No B/O periods (was
Fire Damper C1)
C01_7 d/w - 10h/d - No HK Hols72
- No B/O periods
0 (was
04-Mar-22
C1) A 14-May-22 14-Jun-22 01-Aug-22 79
310.D.WS.L992.36bB02Prepare and submit info. of Fire Damper C01_7 d/w - 10h/d - No HK 7 04-Mar-22 A 02-Apr-22 14-Jun-22 20-Jun-22 79
Hols - No B/O periods (was
310.D.WS.L993.36bB02Review and comment info. of Fire Damper C1)
C01_7 d/w - 10h/d - No HK 24 03-Apr-22 26-Apr-22 21-Jun-22 14-Jul-22 79
Hols - No B/O periods (was
310.D.WS.L994.36bB02Prepare and re-submit info. of Fire Damper C1)
C01_7 d/w - 10h/d - No HK 9 27-Apr-22 05-May-22 15-Jul-22 23-Jul-22 79
Hols - No B/O periods (was
310.D.WS.L996.36bB02Obtain "No objection" of Fire Damper C1)
C01_7 d/w - 10h/d - No HK 9 06-May-22 14-May-22 24-Jul-22 01-Aug-22 79
Hols - No B/O periods (was
Air Grille & Accessories C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was21-Apr-22
C1) 26-Jun-22 08-May-22 13-Jul-22 17
310.D.WS.L992.37bB02Prepare and submit info. of Air Grille & Accessories C01_7 d/w - 10h/d - No HK 25 21-Apr-22 15-May-22 08-May-22 01-Jun-22 17
Hols - No B/O periods (was
C1)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 134 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L993.37bB02Review and comment info. of Air Grille & Accessories C01_7 d/w - 10h/d - No HK 24 16-May-22 08-Jun-22 02-Jun-22 25-Jun-22 17
Hols - No B/O periods (was
310.D.WS.L994.37bB02Prepare and re-submit info. of Air Grille & Accessories C1)
C01_7 d/w - 10h/d - No HK 9 09-Jun-22 17-Jun-22 26-Jun-22 04-Jul-22 17
Hols - No B/O periods (was
310.D.WS.L996.37bB02Obtain "No objection" of Air Grille & Accessories C1)
C01_7 d/w - 10h/d - No HK 9 18-Jun-22 26-Jun-22 05-Jul-22 13-Jul-22 17
Hols - No B/O periods (was
G.I. Sheet Ductwork & Accessories C1)
C01_7 d/w - 10h/d - No HK Hols58
- No B/O periods
0 (was
08-Feb-22
C1) A 23-Mar-22 A 20-May-22 20-May-22
310.D.WS.L992.38bB02Prepare and submit info. of G.I. Sheet Ductwork & Accessories C01_7 d/w - 10h/d - No HK 0 08-Feb-22 A 04-Mar-22 A 20-May-22 20-May-22
Hols - No B/O periods (was
310.D.WS.L993.38bB02Review and comment info. of G.I. Sheet Ductwork & Accessories C1)
C01_7 d/w - 10h/d - No HK 0 05-Mar-22 A 23-Mar-22 A 20-May-22 20-May-22
Hols - No B/O periods (was
310.D.WS.L994.38bB02Prepare and re-submit info. of G.I. Sheet Ductwork & Accessories C1)
C01_7 d/w - 10h/d - No HK 0 23-Mar-22 A 23-Mar-22 A 20-May-22 20-May-22
Hols - No B/O periods (was
310.D.WS.L996.38bB02Obtain "No objection" of G.I. Sheet Ductwork & Accessories C1)
C01_7 d/w - 10h/d - No HK 0 23-Mar-22 A 23-Mar-22 A 20-May-22 20-May-22
Hols - No B/O periods (was
Refrigerant Pipework & Fittings C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was07-Apr-22
C1) 12-Jun-22 08-May-22 13-Jul-22 31
310.D.WS.L992.39bB02Prepare and submit info. of Refrigerant Pipework & Fittings C01_7 d/w - 10h/d - No HK 25 07-Apr-22 01-May-22 08-May-22 01-Jun-22 31
Hols - No B/O periods (was
310.D.WS.L993.39bB02Review and comment info. of Refrigerant Pipework & Fittings C1)
C01_7 d/w - 10h/d - No HK 24 02-May-22 25-May-22 02-Jun-22 25-Jun-22 31
Hols - No B/O periods (was
310.D.WS.L994.39bB02Prepare and re-submit info. of Refrigerant Pipework & Fittings C1)
C01_7 d/w - 10h/d - No HK 9 26-May-22 03-Jun-22 26-Jun-22 04-Jul-22 31
Hols - No B/O periods (was
310.D.WS.L996.39bB02Obtain "No objection" of Refrigerant Pipework & Fittings C1)
C01_7 d/w - 10h/d - No HK 9 04-Jun-22 12-Jun-22 05-Jul-22 13-Jul-22 31
Hols - No B/O periods (was
Fire Services C1)
C01_7 d/w - 10h/d - No HK Hols221
- No B/O periods
0 (was10-Apr-22
C1) 16-Nov-22 08-May-22 19-Nov-22 3
Hose Reel Set C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was30-Apr-22
C1) 05-Jul-22 26-Jun-22 31-Aug-22 57
310.D.WS.L992.40bB02Prepare and submit info. of Hose Reel Set C01_7 d/w - 10h/d - No HK 25 30-Apr-22 24-May-22 26-Jun-22 20-Jul-22 57
Hols - No B/O periods (was
310.D.WS.L993.40bB02Review and comment info. of Hose Reel Set C1)
C01_7 d/w - 10h/d - No HK 24 25-May-22 17-Jun-22 21-Jul-22 13-Aug-22 57
Hols - No B/O periods (was
310.D.WS.L994.40bB02Prepare and re-submit info. of Hose Reel Set C1)
C01_7 d/w - 10h/d - No HK 9 18-Jun-22 26-Jun-22 14-Aug-22 22-Aug-22 57
Hols - No B/O periods (was
310.D.WS.L996.40bB02Obtain "No objection" of Hose Reel Set C1)
C01_7 d/w - 10h/d - No HK 9 27-Jun-22 05-Jul-22 23-Aug-22 31-Aug-22 57
Hols - No B/O periods (was
Fire Hydrant C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was30-Apr-22
C1) 05-Jul-22 26-Jun-22 31-Aug-22 57
310.D.WS.L992.41bB02Prepare and submit info. of Fire Hydrant C01_7 d/w - 10h/d - No HK 25 30-Apr-22 24-May-22 26-Jun-22 20-Jul-22 57
Hols - No B/O periods (was
310.D.WS.L993.41bB02Review and comment info. of Fire Hydrant C1)
C01_7 d/w - 10h/d - No HK 24 25-May-22 17-Jun-22 21-Jul-22 13-Aug-22 57
Hols - No B/O periods (was
310.D.WS.L994.41bB02Prepare and re-submit info. of Fire Hydrant C1)
C01_7 d/w - 10h/d - No HK 9 18-Jun-22 26-Jun-22 14-Aug-22 22-Aug-22 57
Hols - No B/O periods (was
310.D.WS.L996.41bB02Obtain "No objection" of Fire Hydrant C1)
C01_7 d/w - 10h/d - No HK 9 27-Jun-22 05-Jul-22 23-Aug-22 31-Aug-22 57
Hols - No B/O periods (was
Sprinkler Head (All type) C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was05-May-22
C1) 10-Jul-22 14-Sep-22 19-Nov-22 132
310.D.WS.L992.42bB02Prepare and submit info. of Sprinkler Head (All type) C01_7 d/w - 10h/d - No HK 25 05-May-22 29-May-22 14-Sep-22 08-Oct-22 132
Hols - No B/O periods (was
310.D.WS.L993.42bB02Review and comment info. of Sprinkler Head (All type) C1)
C01_7 d/w - 10h/d - No HK 24 30-May-22 22-Jun-22 09-Oct-22 01-Nov-22 132
Hols - No B/O periods (was
310.D.WS.L994.42bB02Prepare and re-submit info. of Sprinkler Head (All type) C1)
C01_7 d/w - 10h/d - No HK 9 23-Jun-22 01-Jul-22 02-Nov-22 10-Nov-22 132
Hols - No B/O periods (was
C1)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 135 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L996.42bB02Obtain "No objection" of Sprinkler Head (All type) C01_7 d/w - 10h/d - No HK 9 02-Jul-22 10-Jul-22 11-Nov-22 19-Nov-22 132
Hols - No B/O periods (was
MCC/ LMCP C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was14-May-22
C1) 19-Jul-22 26-Jun-22 31-Aug-22 43
310.D.WS.L992.43bB02Prepare and submit info. of MCC/ LMCP C01_7 d/w - 10h/d - No HK 25 14-May-22 07-Jun-22 26-Jun-22 20-Jul-22 43
Hols - No B/O periods (was
310.D.WS.L993.43bB02Review and comment info. of MCC/ LMCP C1)
C01_7 d/w - 10h/d - No HK 24 08-Jun-22 01-Jul-22 21-Jul-22 13-Aug-22 43
Hols - No B/O periods (was
310.D.WS.L994.43bB02Prepare and re-submit info. of MCC/ LMCP C1)
C01_7 d/w - 10h/d - No HK 9 02-Jul-22 10-Jul-22 14-Aug-22 22-Aug-22 43
Hols - No B/O periods (was
310.D.WS.L996.43bB02Obtain "No objection" of MCC/ LMCP C1)
C01_7 d/w - 10h/d - No HK 9 11-Jul-22 19-Jul-22 23-Aug-22 31-Aug-22 43
Hols - No B/O periods (was
FS Jockey Pump C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was29-May-22
C1) 03-Aug-22 26-Jun-22 31-Aug-22 28
310.D.WS.L992.45bB02Prepare and submit info. of FS Jockey Pump C01_7 d/w - 10h/d - No HK 25 29-May-22 22-Jun-22 26-Jun-22 20-Jul-22 28
Hols - No B/O periods (was
310.D.WS.L993.45bB02Review and comment info. of FS Jockey Pump C1)
C01_7 d/w - 10h/d - No HK 24 23-Jun-22 16-Jul-22 21-Jul-22 13-Aug-22 28
Hols - No B/O periods (was
310.D.WS.L994.45bB02Prepare and re-submit info. of FS Jockey Pump C1)
C01_7 d/w - 10h/d - No HK 9 17-Jul-22 25-Jul-22 14-Aug-22 22-Aug-22 28
Hols - No B/O periods (was
310.D.WS.L996.45bB02Obtain "No objection" of FS Jockey Pump C1)
C01_7 d/w - 10h/d - No HK 9 26-Jul-22 03-Aug-22 23-Aug-22 31-Aug-22 28
Hols - No B/O periods (was
G.I. Pipe & Fittings C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was22-May-22
C1) 27-Jul-22 26-Jun-22 31-Aug-22 35
310.D.WS.L992.48bB02Prepare and submit info. of G.I. Pipe & Fittings C01_7 d/w - 10h/d - No HK 25 22-May-22 15-Jun-22 26-Jun-22 20-Jul-22 35
Hols - No B/O periods (was
310.D.WS.L993.48bB02Review and comment info. of G.I. Pipe & Fittings C1)
C01_7 d/w - 10h/d - No HK 24 16-Jun-22 09-Jul-22 21-Jul-22 13-Aug-22 35
Hols - No B/O periods (was
310.D.WS.L994.48bB02Prepare and re-submit info. of G.I. Pipe & Fittings C1)
C01_7 d/w - 10h/d - No HK 9 10-Jul-22 18-Jul-22 14-Aug-22 22-Aug-22 35
Hols - No B/O periods (was
310.D.WS.L996.48bB02Obtain "No objection" of G.I. Pipe & Fittings C1)
C01_7 d/w - 10h/d - No HK 9 19-Jul-22 27-Jul-22 23-Aug-22 31-Aug-22 35
Hols - No B/O periods (was
Automatic Fire Alarm Control Panel C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was10-Apr-22
C1) 15-Jun-22 26-Jun-22 31-Aug-22 77
310.D.WS.L992.49bB02Prepare and submit info. of Automatic Fire Alarm Control Panel C01_7 d/w - 10h/d - No HK 25 10-Apr-22 04-May-22 26-Jun-22 20-Jul-22 77
Hols - No B/O periods (was
310.D.WS.L993.49bB02Review and comment info. of Automatic Fire Alarm Control Panel C1)
C01_7 d/w - 10h/d - No HK 24 05-May-22 28-May-22 21-Jul-22 13-Aug-22 77
Hols - No B/O periods (was
310.D.WS.L994.49bB02Prepare and re-submit info. of Automatic Fire Alarm Control Panel C1)
C01_7 d/w - 10h/d - No HK 9 29-May-22 06-Jun-22 14-Aug-22 22-Aug-22 77
Hols - No B/O periods (was
310.D.WS.L996.49bB02Obtain "No objection" of Automatic Fire Alarm Control Panel C1)
C01_7 d/w - 10h/d - No HK 9 07-Jun-22 15-Jun-22 23-Aug-22 31-Aug-22 77
Hols - No B/O periods (was
Gas Flooding System C1)
C01_7 d/w - 10h/d - No HK Hols46
- No B/O periods
0 (was13-Apr-22
C1) 28-May-22 08-May-22 22-Jun-22 25
310.D.WS.L992.50bB02Prepare and submit info. of Gas Flooding System C01_7 d/w - 10h/d - No HK 14 13-Apr-22 26-Apr-22 08-May-22 21-May-22 25
Hols - No B/O periods (was
310.D.WS.L993.50bB02Review and comment info. of Gas Flooding System C1)
C01_7 d/w - 10h/d - No HK 14 27-Apr-22 10-May-22 22-May-22 04-Jun-22 25
Hols - No B/O periods (was
310.D.WS.L994.50bB02Prepare and re-submit info. of Gas Flooding System C1)
C01_7 d/w - 10h/d - No HK 9 11-May-22 19-May-22 05-Jun-22 13-Jun-22 25
Hols - No B/O periods (was
310.D.WS.L996.50bB02Obtain "No objection" of Gas Flooding System C1)
C01_7 d/w - 10h/d - No HK 9 20-May-22 28-May-22 14-Jun-22 22-Jun-22 25
Hols - No B/O periods (was
Automatic Sprinkler Jockey Pump C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was11-Sep-22
C1) 16-Nov-22 14-Sep-22 19-Nov-22 3
310.D.WS.L992.52bB02Prepare and submit info. of Automatic Sprinkler Jockey Pump C01_7 d/w - 10h/d - No HK 25 11-Sep-22 05-Oct-22 14-Sep-22 08-Oct-22 3
Hols - No B/O periods (was
C1)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 136 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L993.52bB02Review and comment info. of Automatic Sprinkler Jockey Pump C01_7 d/w - 10h/d - No HK 24 06-Oct-22 29-Oct-22 09-Oct-22 01-Nov-22 3
Hols - No B/O periods (was
310.D.WS.L994.52bB02Prepare and re-submit info. of Automatic Sprinkler Jockey Pump C1)
C01_7 d/w - 10h/d - No HK 9 30-Oct-22 07-Nov-22 02-Nov-22 10-Nov-22 3
Hols - No B/O periods (was
310.D.WS.L996.52bB02Obtain "No objection" of Automatic Sprinkler Jockey Pump C1)
C01_7 d/w - 10h/d - No HK 9 08-Nov-22 16-Nov-22 11-Nov-22 19-Nov-22 3
Hols - No B/O periods (was
Smoke Detector C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was10-May-22
C1) 15-Jul-22 26-Jun-22 31-Aug-22 47
310.D.WS.L992.53bB02Prepare and submit info. of Smoke Detector C01_7 d/w - 10h/d - No HK 25 10-May-22 03-Jun-22 26-Jun-22 20-Jul-22 47
Hols - No B/O periods (was
310.D.WS.L993.53bB02Review and comment info. of Smoke Detector C1)
C01_7 d/w - 10h/d - No HK 24 04-Jun-22 27-Jun-22 21-Jul-22 13-Aug-22 47
Hols - No B/O periods (was
310.D.WS.L994.53bB02Prepare and re-submit info. of Smoke Detector C1)
C01_7 d/w - 10h/d - No HK 9 28-Jun-22 06-Jul-22 14-Aug-22 22-Aug-22 47
Hols - No B/O periods (was
310.D.WS.L996.53bB02Obtain "No objection" of Smoke Detector C1)
C01_7 d/w - 10h/d - No HK 9 07-Jul-22 15-Jul-22 23-Aug-22 31-Aug-22 47
Hols - No B/O periods (was
Heat Detector C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was24-Jun-22
C1) 29-Aug-22 26-Jun-22 31-Aug-22 2
310.D.WS.L992.54bB02Prepare and submit info. of Heat Detector C01_7 d/w - 10h/d - No HK 25 24-Jun-22 18-Jul-22 26-Jun-22 20-Jul-22 2
Hols - No B/O periods (was
310.D.WS.L993.54bB02Review and comment info. of Heat Detector C1)
C01_7 d/w - 10h/d - No HK 24 19-Jul-22 11-Aug-22 21-Jul-22 13-Aug-22 2
Hols - No B/O periods (was
310.D.WS.L994.54bB02Prepare and re-submit info. of Heat Detector C1)
C01_7 d/w - 10h/d - No HK 9 12-Aug-22 20-Aug-22 14-Aug-22 22-Aug-22 2
Hols - No B/O periods (was
310.D.WS.L996.54bB02Obtain "No objection" of Heat Detector C1)
C01_7 d/w - 10h/d - No HK 9 21-Aug-22 29-Aug-22 23-Aug-22 31-Aug-22 2
Hols - No B/O periods (was
Cable Tray & Accessories C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was24-Jun-22
C1) 29-Aug-22 26-Jun-22 31-Aug-22 2
310.D.WS.L992.55bB02Prepare and submit info. of Cable Tray & Accessories C01_7 d/w - 10h/d - No HK 25 24-Jun-22 18-Jul-22 26-Jun-22 20-Jul-22 2
Hols - No B/O periods (was
310.D.WS.L993.55bB02Review and comment info. of Cable Tray & Accessories C1)
C01_7 d/w - 10h/d - No HK 24 19-Jul-22 11-Aug-22 21-Jul-22 13-Aug-22 2
Hols - No B/O periods (was
310.D.WS.L994.55bB02Prepare and re-submit info. of Cable Tray & Accessories C1)
C01_7 d/w - 10h/d - No HK 9 12-Aug-22 20-Aug-22 14-Aug-22 22-Aug-22 2
Hols - No B/O periods (was
310.D.WS.L996.55bB02Obtain "No objection" of Cable Tray & Accessories C1)
C01_7 d/w - 10h/d - No HK 9 21-Aug-22 29-Aug-22 23-Aug-22 31-Aug-22 2
Hols - No B/O periods (was
PLC C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was11-May-22
C1) 16-Jul-22 26-Jun-22 31-Aug-22 46
310.D.WS.L992.58bB02Prepare and submit info. of PLC C01_7 d/w - 10h/d - No HK 25 11-May-22 04-Jun-22 26-Jun-22 20-Jul-22 46
Hols - No B/O periods (was
310.D.WS.L993.58bB02Review and comment info. of PLC C1)
C01_7 d/w - 10h/d - No HK 24 05-Jun-22 28-Jun-22 21-Jul-22 13-Aug-22 46
Hols - No B/O periods (was
310.D.WS.L994.58bB02Prepare and re-submit info. of PLC C1)
C01_7 d/w - 10h/d - No HK 9 29-Jun-22 07-Jul-22 14-Aug-22 22-Aug-22 46
Hols - No B/O periods (was
310.D.WS.L996.58bB02Obtain "No objection" of PLC C1)
C01_7 d/w - 10h/d - No HK 9 08-Jul-22 16-Jul-22 23-Aug-22 31-Aug-22 46
Hols - No B/O periods (was
Plumbing and Drainage C1)
C01_7 d/w - 10h/d - No HK Hols215
- No B/O periods
0 (was27-Mar-22
C1) 27-Oct-22 28-Mar-22 19-Nov-22 23
Fibreglass Tank C01_7 d/w - 10h/d - No HK Hols57
- No B/O periods
0 (was27-Mar-22
C1) 22-May-22 28-Mar-22 23-May-22 1
310.D.WS.L992.59bB02Prepare and submit info. of Fribreglass Tank C01_7 d/w - 10h/d - No HK 18 27-Mar-22 13-Apr-22 28-Mar-22 14-Apr-22 1
Hols - No B/O periods (was
310.D.WS.L993.59bB02Review and comment info. of Fribreglass Tank C1)
C01_7 d/w - 10h/d - No HK 21 14-Apr-22 04-May-22 15-Apr-22 05-May-22 1
Hols - No B/O periods (was
310.D.WS.L994.59bB02Prepare and re-submit info. of Fribreglass Tank C1)
C01_7 d/w - 10h/d - No HK 9 05-May-22 13-May-22 06-May-22 14-May-22 1
Hols - No B/O periods (was
C1)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 137 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L996.59bB02Obtain "No objection" of Fribreglass Tank C01_7 d/w - 10h/d - No HK 9 14-May-22 22-May-22 15-May-22 23-May-22 1
Hols - No B/O periods (was
Ductile Iron Pipe & Accessories C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was30-Apr-22
C1) 05-Jul-22 14-Sep-22 19-Nov-22 137
310.D.WS.L992.64bB02Prepare and submit info. of Ductile Iron Pipe & Accessories C01_7 d/w - 10h/d - No HK 25 30-Apr-22 24-May-22 14-Sep-22 08-Oct-22 137
Hols - No B/O periods (was
310.D.WS.L993.64bB02Review and comment info. of Ductile Iron Pipe & Accessories C1)
C01_7 d/w - 10h/d - No HK 24 25-May-22 17-Jun-22 09-Oct-22 01-Nov-22 137
Hols - No B/O periods (was
310.D.WS.L994.64bB02Prepare and re-submit info. of Ductile Iron Pipe & Accessories C1)
C01_7 d/w - 10h/d - No HK 9 18-Jun-22 26-Jun-22 02-Nov-22 10-Nov-22 137
Hols - No B/O periods (was
310.D.WS.L996.64bB02Obtain "No objection" of Ductile Iron Pipe & Accessories C1)
C01_7 d/w - 10h/d - No HK 9 27-Jun-22 05-Jul-22 11-Nov-22 19-Nov-22 137
Hols - No B/O periods (was
Epoxy Cast Iron Pipe & Accessories C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was30-Apr-22
C1) 05-Jul-22 26-Jun-22 31-Aug-22 57
310.D.WS.L992.65bB02Prepare and submit info. of Epoxy Cast Iron Pipe & Accessories C01_7 d/w - 10h/d - No HK 25 30-Apr-22 24-May-22 26-Jun-22 20-Jul-22 57
Hols - No B/O periods (was
310.D.WS.L993.65bB02Review and comment info. of Epoxy Cast Iron Pipe & Accessories C1)
C01_7 d/w - 10h/d - No HK 24 25-May-22 17-Jun-22 21-Jul-22 13-Aug-22 57
Hols - No B/O periods (was
310.D.WS.L994.65bB02Prepare and re-submit info. of Epoxy Cast Iron Pipe & Accessories C1)
C01_7 d/w - 10h/d - No HK 9 18-Jun-22 26-Jun-22 14-Aug-22 22-Aug-22 57
Hols - No B/O periods (was
310.D.WS.L996.65bB02Obtain "No objection" of Epoxy Cast Iron Pipe & Accessories C1)
C01_7 d/w - 10h/d - No HK 9 27-Jun-22 05-Jul-22 23-Aug-22 31-Aug-22 57
Hols - No B/O periods (was
Local Motor Control Panel C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was13-Jun-22
C1) 18-Aug-22 14-Sep-22 19-Nov-22 93
310.D.WS.L992.66bB02Prepare and submit info. of Local Motor Control Panel C01_7 d/w - 10h/d - No HK 25 13-Jun-22 07-Jul-22 14-Sep-22 08-Oct-22 93
Hols - No B/O periods (was
310.D.WS.L993.66bB02Review and comment info. of Local Motor Control Panel C1)
C01_7 d/w - 10h/d - No HK 24 08-Jul-22 31-Jul-22 09-Oct-22 01-Nov-22 93
Hols - No B/O periods (was
310.D.WS.L994.66bB02Prepare and re-submit info. of Local Motor Control Panel C1)
C01_7 d/w - 10h/d - No HK 9 01-Aug-22 09-Aug-22 02-Nov-22 10-Nov-22 93
Hols - No B/O periods (was
310.D.WS.L996.66bB02Obtain "No objection" of Local Motor Control Panel C1)
C01_7 d/w - 10h/d - No HK 9 10-Aug-22 18-Aug-22 11-Nov-22 19-Nov-22 93
Hols - No B/O periods (was
Sump Pump C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was22-Aug-22
C1) 27-Oct-22 14-Sep-22 19-Nov-22 23
310.D.WS.L992.67bB02Prepare and submit info. of Sump Pump C01_7 d/w - 10h/d - No HK 25 22-Aug-22 15-Sep-22 14-Sep-22 08-Oct-22 23
Hols - No B/O periods (was
310.D.WS.L993.67bB02Review and comment info. of Sump Pump C1)
C01_7 d/w - 10h/d - No HK 24 16-Sep-22 09-Oct-22 09-Oct-22 01-Nov-22 23
Hols - No B/O periods (was
310.D.WS.L994.67bB02Prepare and re-submit info. of Sump Pump C1)
C01_7 d/w - 10h/d - No HK 9 10-Oct-22 18-Oct-22 02-Nov-22 10-Nov-22 23
Hols - No B/O periods (was
310.D.WS.L996.67bB02Obtain "No objection" of Sump Pump C1)
C01_7 d/w - 10h/d - No HK 9 19-Oct-22 27-Oct-22 11-Nov-22 19-Nov-22 23
Hols - No B/O periods (was
CC#07 - General - MEP - Method Statement C1)
C01_7 d/w - 10h/d - No HK Hols260
- No B/O periods
0 (was27-Mar-22
C1) 11-Dec-22 25-Apr-22 09-Jan-23 29
ELECT C01_7 d/w - 10h/d - No HK Hols210
- No B/O periods
0 (was27-Mar-22
C1) 22-Oct-22 05-May-22 30-Nov-22 39
310.D.WS.L984.05bB02 Prepare and submit Elect. Method Statement (15 nos.) C01_7 d/w - 10h/d - No HK 165 27-Mar-22 07-Sep-22 05-May-22 16-Oct-22 39
Hols - No B/O periods (was
310.D.WS.L985.05bB02 Review and comment Elect. Method Statement (15 nos.) C1)
C01_7 d/w - 10h/d - No HK 165 11-Apr-22 22-Sep-22 20-May-22 31-Oct-22 39
Hols - No B/O periods (was
310.D.WS.L986.05bB02 Prepare and re-submit Elect. Method Statement (15 nos.) C1)
C01_7 d/w - 10h/d - No HK 165 26-Apr-22 07-Oct-22 04-Jun-22 15-Nov-22 39
Hols - No B/O periods (was
310.D.WS.L988.05bB02 Obtain approval of Elect. Method Statement (15 nos.) C1)
C01_7 d/w - 10h/d - No HK 165 11-May-22 22-Oct-22 19-Jun-22 30-Nov-22 39
Hols - No B/O periods (was
MVAC C1)
C01_7 d/w - 10h/d - No HK Hols260
- No B/O periods
0 (was27-Mar-22
C1) 11-Dec-22 25-Apr-22 09-Jan-23 29
310.D.WS.L984.06bB02 Prepare and submit MVAC Method Statement (13 nos.) C01_7 d/w - 10h/d - No HK 215 27-Mar-22 27-Oct-22 25-Apr-22 25-Nov-22 29
Hols - No B/O periods (was
C1)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 138 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L985.06bB02 Review and comment MVAC Method Statement (13 nos.) C01_7 d/w - 10h/d - No HK 215 11-Apr-22 11-Nov-22 10-May-22 10-Dec-22 29
Hols - No B/O periods (was
310.D.WS.L986.06bB02 Prepare and re-submit MVAC Method Statement (13 nos.) C1)
C01_7 d/w - 10h/d - No HK 215 26-Apr-22 26-Nov-22 25-May-22 25-Dec-22 29
Hols - No B/O periods (was
310.D.WS.L988.06bB02 Obtain approval of MVAC Method Statement (13 nos.) C1)
C01_7 d/w - 10h/d - No HK 215 11-May-22 11-Dec-22 09-Jun-22 09-Jan-23 29
Hols - No B/O periods (was
FS C1)
C01_7 d/w - 10h/d - No HK Hols138
- No B/O periods
0 (was01-May-22
C1) 15-Sep-22 26-Jun-22 10-Nov-22 56
310.D.WS.L984.07bB02 Prepare and submit FS Method Statement (12 nos.) C01_7 d/w - 10h/d - No HK 93 01-May-22 01-Aug-22 26-Jun-22 26-Sep-22 56
Hols - No B/O periods (was
310.D.WS.L985.07bB02 Review and comment FS Method Statement (12 nos.) C1)
C01_7 d/w - 10h/d - No HK 93 16-May-22 16-Aug-22 11-Jul-22 11-Oct-22 56
Hols - No B/O periods (was
310.D.WS.L986.07bB02 Prepare and re-submit FS Method Statement (12 nos.) C1)
C01_7 d/w - 10h/d - No HK 93 31-May-22 31-Aug-22 26-Jul-22 26-Oct-22 56
Hols - No B/O periods (was
310.D.WS.L988.07bB02 Obtain approval of FS Method Statement (12 nos.) C1)
C01_7 d/w - 10h/d - No HK 93 15-Jun-22 15-Sep-22 10-Aug-22 10-Nov-22 56
Hols - No B/O periods (was
P&D C1)
C01_7 d/w - 10h/d - No HK Hols199
- No B/O periods
0 (was27-Mar-22
C1) 11-Oct-22 28-May-22 12-Dec-22 62
310.D.WS.L984.08bB02 Prepare and submit P&D Method Statement (5 nos.) C01_7 d/w - 10h/d - No HK 154 27-Mar-22 27-Aug-22 28-May-22 28-Oct-22 62
Hols - No B/O periods (was
310.D.WS.L985.08bB02 Review and comment P&D Method Statement (5 nos.) C1)
C01_7 d/w - 10h/d - No HK 154 11-Apr-22 11-Sep-22 12-Jun-22 12-Nov-22 62
Hols - No B/O periods (was
310.D.WS.L986.08bB02 Prepare and re-submit P&D Method Statement (5 nos.) C1)
C01_7 d/w - 10h/d - No HK 154 26-Apr-22 26-Sep-22 27-Jun-22 27-Nov-22 62
Hols - No B/O periods (was
310.D.WS.L988.08bB02 Obtain approval of P&D Method Statement (5 nos.) C1)
C01_7 d/w - 10h/d - No HK 154 11-May-22 11-Oct-22 12-Jul-22 12-Dec-22 62
Hols - No B/O periods (was
CC#07 ----- Procurement ----- C1)
C01_7 d/w - 10h/d - No HK Hols384
- No B/O periods
0 (was
30-Oct-21
C1) A 27-Nov-22 29-Mar-22 01-May-23 155
CC#07 - Subletting - West Vehicular Tunnel (WVT) C01_7 d/w - 10h/d - No HK Hols324
- No B/O periods
0 (was
30-Oct-21
C1) A 28-Sep-22 29-Mar-22 01-May-23 215
310.P.EX.H202 Subletting - WVT & Plant B MEP - Award sub-contract C01_7 d/w - 10h/d - No HK 90 30-Oct-21 A 18-Jan-22 A 16-Jun-22 16-Jun-22
Hols - No B/O periods (was
310.P.EX.H210 Subletting - ABWF (Plastering) - Stage 1&2 Preparation,Submission& C1)
C01_7 d/w - 10h/d - No HK 90 03-Jan-22 A 20-Apr-22 03-Apr-22 27-Apr-22 7
Approval,Tender&Award sub-contract Hols - No B/O periods (was
310.P.EX.H226.B01 Subletting - ABWF (Painting) - Stage 1&2 Preparation,Submission& C1)
C01_7 d/w - 10h/d - No HK 90 03-Jan-22 A 25-Apr-22 29-Mar-22 27-Apr-22 2
Approval,Tender&Award sub-contract Hols - No B/O periods (was
310.P.EX.H230.B01 Subletting - ABWF (Door) - Stage 1&2 Preparation,Submission& Approval,Tender&Award C1)
C01_7 d/w - 10h/d - No HK 90 03-Jan-22 A 25-Apr-22 29-Mar-22 27-Apr-22 2
sub-contract Hols - No B/O periods (was
310.P.EX.H234.B01 Subletting - ABWF (Louver,Window,etc) - Stage 1&2 Preparation,Submission& C1)
C01_7 d/w - 10h/d - No HK 90 03-Jan-22 A 25-Apr-22 29-Mar-22 27-Apr-22 2
Approval,Tender&Award sub-contract Hols - No B/O periods (was
310.P.EX.H238.B01 Subletting - ABWF (Steel&Metal) - Stage 1&2 Preparation,Submission& C1)
C01_7 d/w - 10h/d - No HK 90 03-Jan-22 A 25-Apr-22 29-Mar-22 27-Apr-22 2
Approval,Tender&Award sub-contract Hols - No B/O periods (was
310.P.EX.F054 Subletting - WVT - Earthwork - Stage 1&2 Preparation,Submission& C1)
C01_7 d/w - 10h/d - No HK 90 01-May-22 29-Jul-22 01-Jul-22 28-Sep-22 61
Approval,Tender&Award sub-contract Hols - No B/O periods (was
310.P.EX.F096 Subletting - WVT - RC Structural Works - Stage 1&2 Preparation,Submission& C1)
C01_7 d/w - 10h/d - No HK 90 01-Jul-22 28-Sep-22 01-Feb-23 01-May-23 215
Approval,Tender&Award sub-contract Hols - No B/O periods (was
310.P.EX.F160 Subletting - WVT - Waterproofing - Stage 1&2 Preparation,Submission& C1)
C01_7 d/w - 10h/d - No HK 90 01-Jul-22 28-Sep-22 01-Feb-23 01-May-23 215
Approval,Tender&Award sub-contract Hols - No B/O periods (was
CC#07 - Procurement - West Vehicular Tunnel (WVT) C1)
C01_7 d/w - 10h/d - No HK Hols200
- No B/O periods
0 (was12-May-22
C1) 27-Nov-22 20-May-22 30-Nov-22 3
WVT - Procurement - MEP C01_7 d/w - 10h/d - No HK Hols200
- No B/O periods
0 (was12-May-22
C1) 27-Nov-22 20-May-22 30-Nov-22 3
310.P.RC.D467 WVT - (Procurement Electrical & MVAC and Others) - Place Order for Material C01_7 d/w - 10h/d - No HK 55 12-May-22 05-Jul-22 20-May-22 13-Jul-22 8
Hols - No B/O periods (was
310.P.RC.D475 WVT - (Procurement Electrical & MVAC and Others) - Manufacturing of Material C1)
C01_7 d/w - 10h/d - No HK 160 02-Jun-22 08-Nov-22 10-Jun-22 16-Nov-22 8
Hols - No B/O periods (was
C1)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 139 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.P.RC.D463 WVT - (Procurement FS and P&D Materials) - Place Order for Material C01_7 d/w - 10h/d - No HK 150 20-Jun-22 16-Nov-22 23-Jun-22 19-Nov-22 3
Hols - No B/O periods (was
310.P.RC.D471 WVT - (Procurement FS and P&D Materials) - Manufacturing of Material C1)
C01_7 d/w - 10h/d - No HK 150 01-Jul-22 27-Nov-22 04-Jul-22 30-Nov-22 3
Hols - No B/O periods (was
310.P.RC.D479 WVT - (Procurement) - Delivery of Material C1)
C01_7 d/w - 10h/d - No HK 14 14-Nov-22 27-Nov-22 17-Nov-22 30-Nov-22 3
Hols - No B/O periods (was
WVT - Procurement - ABWF C1)
C01_7 d/w - 10h/d - No HK Hols127
- No B/O periods
0 (was14-Jun-22
C1) 18-Oct-22 21-Jun-22 25-Oct-22 7
310.P.RC.D483 WVT - (Procurement ABWF) - Place Order for Materials C01_7 d/w - 10h/d - No HK 7 14-Jun-22 20-Jun-22 21-Jun-22 27-Jun-22 7
Hols - No B/O periods (was
310.P.RC.D487 WVT - (Procurement ABWF) - Manufacturing of Materials & Delivery of Materials C1)
C01_7 d/w - 10h/d - No HK 120 21-Jun-22 18-Oct-22 28-Jun-22 25-Oct-22 7
Hols - No B/O periods (was
CC#07 ----- Construction ----- C1) 881 453 07-Jun-21 A 23-May-24 24-May-22 24-Aug-24 78
CC#07 - West Vehicular Tunnel - WVT (HYBRID METHOD) 881 443 07-Jun-21 A 23-May-24 04-Jul-22 24-Aug-24 78
CC#07 - WVT - Site Preparation and Establishment 397 0 07-Jun-21 A 05-Oct-22 04-Jul-22 21-Oct-22 14
310.C.EX.F010 WVT - Work Permit - Prepare and apply for Work Permit C01_7 d/w - 10h/d - No HK 30 27-Mar-22 25-Apr-22 26-Jul-22 24-Aug-22 121
Hols - No B/O periods (was
310.C.EX.F014 WVT - Work Permit - Review application by PM and Authorities C1)
C01_7 d/w - 10h/d - No HK 28 26-Apr-22 23-May-22 25-Aug-22 21-Sep-22 121
Hols - No B/O periods (was
310.C.EX.F018 WVT - Work Permit - Work permit grant C1)
C01_7 d/w - 10h/d - No HK 0 23-May-22 21-Sep-22 121
Hols - No B/O periods (was
310.C.EX.F020 WVT - tentative date of closure of existing N-Runway C1) d/w - 10h/d - With
C11_6 0 01-Sep-22 05-Sep-22 4
HK Hols - No B/O periods
CC#07 - WVT - 3310/4 Site Preparation and Establishment (was
C11_6C3)
d/w - 10h/d - With HK Hols
394- No B/O 0periods (was
07-Jun-21
C3) A 29-Sep-22 22-Sep-22 21-Oct-22 17
310.C.EX.F019 WVT - 3310/4 - access to Works Area C11_6 d/w - 10h/d - With 0 07-Jun-21 A 22-Sep-22
HK Hols - No B/O periods
310.C.EX.F026 WVT - 3310/4 - underground utilities survey and reporting (was
C11_6C3)
d/w - 10h/d - With 6 01-Sep-22 07-Sep-22 22-Sep-22 28-Sep-22 17
HK Hols - No B/O periods
310.C.EX.F030 WVT - 3310/4 - carry out topographic survey and reporting (was
C11_6C3)
d/w - 10h/d - With 6 01-Sep-22 07-Sep-22 22-Sep-22 28-Sep-22 17
HK Hols - No B/O periods
310.C.EX.F034 WVT - 3310/4 - instrumentation (was
C11_6C3)
d/w - 10h/d - With 24 01-Sep-22 29-Sep-22 22-Sep-22 21-Oct-22 17
HK Hols - No B/O periods
CC#07 - WVT - 3310/9 Site Preparation and Establishment (was
C11_6C3)
d/w - 10h/d - With HK Hols
24- No B/O 0periods (was
05-Sep-22
C3) 05-Oct-22 05-Sep-22 21-Oct-22 14
310.C.EX.F482 WVT - 3310/9 - access to Works Area C11_6 d/w - 10h/d - With 0 05-Sep-22* 05-Sep-22 0
HK Hols - No B/O periods
310.C.EX.F494 WVT - 3310/9 - underground utilities survey and reporting (was
C11_6C3)
d/w - 10h/d - With 7 05-Sep-22 13-Sep-22 22-Sep-22 29-Sep-22 14
HK Hols - No B/O periods
310.C.EX.F502 WVT - 3310/9 - carry out condition survey and reporting (was
C11_6C3)
d/w - 10h/d - With 7 05-Sep-22 13-Sep-22 22-Sep-22 29-Sep-22 14
HK Hols - No B/O periods
310.C.EX.F498 WVT - 3310/9 - instrumentation (was
C11_6C3)
d/w - 10h/d - With 24 05-Sep-22 05-Oct-22 22-Sep-22 21-Oct-22 14
HK Hols - No B/O periods
CC#07 - WVT - 3310/9A Site Preparation and Establishment (was
C11_6C3)
d/w - 10h/d - With HK Hols
24- No B/O 0periods (was
04-Jul-22
C3) 30-Jul-22 04-Jul-22 08-Oct-22 57
310.C.EX.F1044 WVT - 3310/9A - access to Works Area C11_6 d/w - 10h/d - With 0 04-Jul-22* 04-Jul-22 0
HK Hols - No B/O periods
310.C.EX.F1048 WVT - 3310/9A - underground utilities survey and reporting (was
C11_6C3)
d/w - 10h/d - With 14 04-Jul-22 19-Jul-22 21-Sep-22 08-Oct-22 67
HK Hols - No B/O periods
310.C.EX.F1056 WVT - 3310/9A - carry out condition survey and reporting (was C3)
C11_6 d/w - 10h/d - With 14 04-Jul-22 19-Jul-22 21-Sep-22 08-Oct-22 67
HK Hols - No B/O periods
310.C.EX.F1052 WVT - 3310/9A - instrumentation (was
C11_6C3)
d/w - 10h/d - With 24 04-Jul-22 30-Jul-22 08-Sep-22 08-Oct-22 57
HK Hols - No B/O periods
CC#07 - WVT - Ground Investigation (was
C11_6C3)
d/w - 10h/d - With HK Hols
431- No B/O 0periods (was
01-Aug-22
C3) 10-Jan-24 06-Sep-22 24-Aug-24 185
WVT - GI for ELS Design C11_6 d/w - 10h/d - With HK Hols
21- No B/O 0periods (was
01-Sep-22
C3) 26-Sep-22 06-Sep-22 30-Sep-22 4

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 140 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.EX.H1001 WVT - GI for ELS design - Carry out GI C11_6 d/w - 10h/d - With 18 01-Sep-22 22-Sep-22 06-Sep-22 27-Sep-22 4
HK Hols - No B/O periods
310.C.EX.H1005 WVT - GI for ELS design - prepare report and submit (was
C11_6C3)
d/w - 10h/d - With 3 23-Sep-22 26-Sep-22 28-Sep-22 30-Sep-22 4
HK Hols - No B/O periods
WVT - Instrumentation (before tunnel construction commence) (was
C11_6C3)
d/w - 10h/d - With HK Hols
36- No B/O 0periods (was
01-Aug-22
C3) 12-Sep-22 22-Sep-22 15-Oct-22 27
310.C.EX.F1060 WVT - 3310/9A - Install background ground surface markers [2 nos. @5d/no./wf; 1wf] C11_6 d/w - 10h/d - With 6 01-Aug-22 06-Aug-22 10-Oct-22 15-Oct-22 57
HK Hols - No B/O periods
310.C.EX.F038 WVT - 3310/4 - Install background ground surface markers [6 nos. @5d/no./wf; 3wf] (was
C11_6C3)
d/w - 10h/d - With 6 05-Sep-22 12-Sep-22 22-Sep-22 28-Sep-22 14
HK Hols - No B/O periods
WVT - Instrumentation (after tunnel construction complete) (was
C11_6C3)
d/w - 10h/d - With HK Hols
57- No B/O 0periods (was
02-Nov-23
C3) 10-Jan-24 19-Jun-24 24-Aug-24 185
310.C.EX.F042 WVT - install instruments outside tunnel [17 nos. @10d/nos; 3WF] C11_6 d/w - 10h/d - With 57 02-Nov-23 10-Jan-24 19-Jun-24 24-Aug-24 185
HK Hols - No B/O periods
CC#07 - WVT - Existing UU - temporary support (and/or diversion as necessary) (was
C01_7C3)
d/w - 10h/d - No HK Hols155
- No B/O periods
0 (was27-Mar-22
C1) 28-Aug-22 23-Jul-22 24-Dec-22 118
Submissions and Application C01_7 d/w - 10h/d - No HK Hols155
- No B/O periods
0 (was27-Mar-22
C1) 28-Aug-22 23-Jul-22 24-Dec-22 118
310.C.EX.H1241 UU Diversion Works - Prepare Presentation of Propose Temporary Diversion of Existing C01_7 d/w - 10h/d - No HK 45 27-Mar-22 10-May-22 23-Jul-22 05-Sep-22 118
UU to CAD Hols - No B/O periods (was
310.C.EX.H1245 UU Diversion Works - PM 1st review Presentation of Propose Temporary Diversion of C1)
C01_7 d/w - 10h/d - No HK 28 11-May-22 07-Jun-22 06-Sep-22 03-Oct-22 118
Existing UU to CAD Hols - No B/O periods (was
310.C.EX.H1249 UU Diversion Works - Revise Presentation of Propose Temporary Diversion of Existing C1)
C01_7 d/w - 10h/d - No HK 8 08-Jun-22 15-Jun-22 19-Nov-22 26-Nov-22 164
UU to CAD Hols - No B/O periods (was
310.C.EX.H1261 UU Diversion Works - Method Statement C1) d/w - 10h/d - No HK
C01_7 21 08-Jun-22 28-Jun-22 04-Oct-22 24-Oct-22 118
Hols - No B/O periods (was
310.C.EX.H1289 UU Diversion Works - PM 2nd review Presentation of Propose Temporary Diversion of C1)
C01_7 d/w - 10h/d - No HK 28 16-Jun-22 13-Jul-22 27-Nov-22 24-Dec-22 164
Existing UU to CAD Hols - No B/O periods (was
310.C.EX.H1265 UU Diversion Works - PM 1st review and approved Method Statement C1)
C01_7 d/w - 10h/d - No HK 28 29-Jun-22 26-Jul-22 25-Oct-22 21-Nov-22 118
Hols - No B/O periods (was
310.C.EX.H1285 UU Diversion Works - Revise Method Statement C1)
C01_7 d/w - 10h/d - No HK 5 27-Jul-22 31-Jul-22 22-Nov-22 26-Nov-22 118
Hols - No B/O periods (was
310.C.EX.H1293 UU Diversion Works - PM 2nd review and approved Method Statement C1)
C01_7 d/w - 10h/d - No HK 28 01-Aug-22 28-Aug-22 27-Nov-22 24-Dec-22 118
Hols - No B/O periods (was
CC#07 - WVT - VE+ELS Installation C1) 262 70 19-Aug-22 08-Jul-23 08-Sep-22 31-Jul-23 19
CC#07 - WVT - Zone 1 (3310/4) - VE + ELS Installation 230 21 27-Sep-22 08-Jul-23 15-Oct-22 25-Jul-23 14
310.D.EX.F162 WVT - ELS design (Vertical Elements) - prepare and submit Form BA8 and grant consent C01_7 d/w - 10h/d - No HK 7 27-Sep-22 03-Oct-22 15-Oct-22 21-Oct-22 18
Hols - No B/O periods (was
310.D.EX.F166 WVT - ELS design (Vertical Elements) - prepare and submit Form BA10 to notify work C1)
C01_7 d/w - 10h/d - No HK 7 04-Oct-22 10-Oct-22 22-Oct-22 28-Oct-22 18
commencement Hols - No B/O periods (was
310.C.EX.F474 WVT - Zone 1 (3310/4) - ELS - Install pipe pile (87nos. @2d/no./rig; use 2 rigs) C1)
C11_6 d/w - 10h/d - With 96 9 11-Oct-22 04-Feb-23 29-Oct-22 23-Feb-23 16
HK Hols - No B/O periods
310.C.EX.H1153 WVT - Zone 1 (3310/4) - ELS - Install wells (was
C11_6C3)
d/w - 10h/d - With 26 2 03-Jan-23 04-Feb-23 02-Feb-23 03-Mar-23 23
HK Hols - No B/O periods
310.C.EX.H1157 WVT - Zone 1 (3310/4) - ELS - Submit Form BA14 (was
C01_7C3)
d/w - 10h/d - No HK 12 2 05-Feb-23 16-Feb-23 24-Feb-23 07-Mar-23 19
Hols - No B/O periods (was
310.C.EX.F478 WVT - Zone 1 (3310/4) - ELS - Pumping test and submit report C1)
C01_7 d/w - 10h/d - No HK 18 05-Feb-23 22-Feb-23 04-Mar-23 21-Mar-23 27
Hols - No B/O periods (was
310.C.EX.H1161 WVT - Zone 1 (3310/4) - ELS - Submit Form BA8 for excavation C1)
C01_7 d/w - 10h/d - No HK 7 2 17-Feb-23 23-Feb-23 08-Mar-23 14-Mar-23 19
Hols - No B/O periods (was
310.C.EX.H1165 WVT - Zone 1 (3310/4) - ELS - Submit Form BA10 for excavation C1)
C01_7 d/w - 10h/d - No HK 7 2 24-Feb-23 02-Mar-23 15-Mar-23 21-Mar-23 19
Hols - No B/O periods (was
310.C.EX.H1305 WVT - Zone 1 (3310/4) - ELS - Initial excavation + uu hanger support + hang UU C1)
C01_7 d/w - 10h/d - No HK 24 2 03-Mar-23 26-Mar-23 22-Mar-23 14-Apr-23 19
Hols - No B/O periods (was
C1)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 141 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.EX.F514 WVT - Zone 1 (3310/4) - ELS - Excavation, install struts [17,073m3, @600m3/d/wf, 2wf; 2 C11_6 d/w - 10h/d - With 60 2 27-Mar-23 10-Jun-23 15-Apr-23 27-Jun-23 13
layers struts @20d/layer] HK Hols - No B/O periods
310.C.EX.F738 WVT - Zone 1 (3310/4) - ELS - Make good FEL (and/or install remaining struts if any) (was
C01_7C3)
d/w - 10h/d - No HK 16 11-Jun-23 26-Jun-23 28-Jun-23 13-Jul-23 17
Hols - No B/O periods (was
310.C.EX.F522 WVT - Zone 1 (3310/4) - ELS (N) - Plate Load Test (1 nos.) C1)
C01_7 d/w - 10h/d - No HK 12 27-Jun-23 08-Jul-23 14-Jul-23 25-Jul-23 17
Hols - No B/O periods (was
CC#07 - WVT - Zone 2 (3310/4) - VE + ELS Installation C1) 164 13 12-Sep-22 29-Mar-23 03-Oct-22 24-Apr-23 18
310.D.EX.F222 WVT - ELS design (Vertical Elements) - prepare and submit Form BA8 and grant consent C01_7 d/w - 10h/d - No HK 7 12-Sep-22 18-Sep-22 03-Oct-22 09-Oct-22 21
Hols - No B/O periods (was
310.D.EX.F226 WVT - ELS design (Vertical Elements) - prepare and submit Form BA10 to notify work C1)
C01_7 d/w - 10h/d - No HK 7 19-Sep-22 25-Sep-22 10-Oct-22 16-Oct-22 21
commencement Hols - No B/O periods (was
310.C.EX.F298 WVT - Zone 2 (3310/4) - ELS - Install vertical element (29nos. @2d/no./rig; use 1 rig) C1)
C11_6 d/w - 10h/d - With 66 7 26-Sep-22 13-Dec-22 17-Oct-22 03-Jan-23 16
HK Hols - No B/O periods
310.C.EX.F1128.B01 WVT - Zone 2 (3310/4) - ELS - Install wells (was
C01_7C3)
d/w - 10h/d - No HK 24 20-Nov-22 13-Dec-22 19-Dec-22 11-Jan-23 29
Hols - No B/O periods (was
310.C.EX.H1173 WVT - Zone 2 (3310/4) - ELS - Submit Form BA14 C1)
C01_7 d/w - 10h/d - No HK 12 14-Dec-22 25-Dec-22 04-Jan-23 15-Jan-23 21
Hols - No B/O periods (was
310.C.EX.F1132.B01 WVT - Zone 2 (3310/4) - ELS - Pumping test and submit report C1)
C01_7 d/w - 10h/d - No HK 18 14-Dec-22 31-Dec-22 12-Jan-23 29-Jan-23 29
Hols - No B/O periods (was
310.C.EX.H1177 WVT - Zone 2 (3310/4) - ELS - Submit Form BA8 for excavation C1)
C01_7 d/w - 10h/d - No HK 7 26-Dec-22 01-Jan-23 16-Jan-23 22-Jan-23 21
Hols - No B/O periods (was
310.C.EX.H1181 WVT - Zone 2 (3310/4) - ELS - Submit Form BA10 for excavation C1)
C01_7 d/w - 10h/d - No HK 7 02-Jan-23 08-Jan-23 23-Jan-23 29-Jan-23 21
Hols - No B/O periods (was
310.C.EX.H1309 WVT - Zone 2 (3310/4) - ELS - Initial excavation + uu hanger support + hang UU C1)
C01_7 d/w - 10h/d - No HK 24 2 09-Jan-23 01-Feb-23 30-Jan-23 22-Feb-23 21
Hols - No B/O periods (was
310.C.EX.F532 WVT - Zone 2 (3310/4) - ELS - Excavation, install struts [11,951m3 @600m3/d/wf; 2 layer C1)
C11_6 d/w - 10h/d - With 36 2 02-Feb-23 15-Mar-23 23-Feb-23 06-Apr-23 18
struts @ 6d/strut, 1wf] HK Hols - No B/O periods
310.C.EX.F534.B01 WVT - Zone 2 (3310/4) - ELS - Make good FEL + PLT (assumed) (was
C11_6C3)
d/w - 10h/d - With 12 2 16-Mar-23 29-Mar-23 11-Apr-23 24-Apr-23 18
HK Hols - No B/O periods
CC#07 - WVT - Zone 3 (3310/4) - VE + ELS Installation (was C3) 210 8 12-Sep-22 29-May-23 12-Sep-22 29-May-23 0
310.D.EX.F230 WVT - ELS design (Vertical Elements) - prepare and submit Form BA8 and grant consent C01_7 d/w - 10h/d - No HK 7 12-Sep-22 18-Sep-22 12-Sep-22 18-Sep-22 0
Hols - No B/O periods (was
310.D.EX.F234 WVT - ELS design (Vertical Elements) - prepare and submit Form BA10 to notify work C1)
C01_7 d/w - 10h/d - No HK 7 19-Sep-22 25-Sep-22 19-Sep-22 25-Sep-22 0
commencement Hols - No B/O periods (was
310.C.EX.F1088.B01 WVT - Zone 3 (3310/4) - ELS - trial pile & install vertical element (1,018nos. @2d/no./rig; C1)
C11_6 d/w - 10h/d - With 52 1 26-Sep-22 26-Nov-22 26-Sep-22 26-Nov-22 0
use 10 rigs) HK Hols - No B/O periods
310.C.EX.F1092.B01 WVT - Zone 3 (3310/4) - ELS - install wells (was
C01_7C3)
d/w - 10h/d - No HK 24 03-Nov-22 26-Nov-22 13-Nov-22 06-Dec-22 10
Hols - No B/O periods (was
310.C.EX.H1345.B01 WVT - Zone 3 (3310/4) - ELS - submit Form BA14 C1)
C01_7 d/w - 10h/d - No HK 14 27-Nov-22 10-Dec-22 27-Nov-22 10-Dec-22 0
Hols - No B/O periods (was
310.C.EX.F1096.B01 WVT - Zone 3 (3310/4) - ELS - pumping test and submit report C1)
C01_7 d/w - 10h/d - No HK 18 27-Nov-22 14-Dec-22 07-Dec-22 24-Dec-22 10
Hols - No B/O periods (was
310.C.EX.H1349.B01 WVT - Zone 3 (3310/4) - ELS - submit Form BA8 for excavation C1)
C01_7 d/w - 10h/d - No HK 7 11-Dec-22 17-Dec-22 11-Dec-22 17-Dec-22 0
Hols - No B/O periods (was
310.C.EX.H1353.B01 WVT - Zone 3 (3310/4) - ELS - submit Form BA10 for excavation C1)
C01_7 d/w - 10h/d - No HK 7 18-Dec-22 24-Dec-22 18-Dec-22 24-Dec-22 0
Hols - No B/O periods (was
310.C.EX.H1313 WVT - Zone 3 (3310/4) - ELS - Initial excavation + uu hanger support + hang UU C1)
C01_7 d/w - 10h/d - No HK 60 2 25-Dec-22 22-Feb-23 25-Dec-22 22-Feb-23 0
Hols - No B/O periods (was
310.C.EX.F530 WVT - Zone 3 (3310/4) - ELS - excavation + strut installation [176,082m3 @1000m3/d/wf; C1)
C11_6 d/w - 10h/d - With 64 5 23-Feb-23 13-May-23 23-Feb-23 13-May-23 0
3wf], assume 3 layers HK Hols - No B/O periods
310.C.EX.F532.B01 WVT - Zone 3 (3310/4) - ELS - Make good FEL + PLT (assumed) (was
C11_6C3)
d/w - 10h/d - With 12 0 15-May-23 29-May-23 15-May-23 29-May-23 0
HK Hols - No B/O periods
(was C3)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 142 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
CC#07 - WVT - Zone 4 (3310/4) - VE + ELS Installation 194 6 19-Aug-22 16-Apr-23 06-Dec-22 31-Jul-23 87
310.D.EX.F214 WVT - ELS design (Vertical Elements) - prepare and submit Form BA8 and grant consent C01_7 d/w - 10h/d - No HK 7 19-Aug-22 25-Aug-22 06-Dec-22 12-Dec-22 109
Hols - No B/O periods (was
310.D.EX.F218 WVT - ELS design (Vertical Elements) - prepare and submit Form BA10 to notify work C1)
C01_7 d/w - 10h/d - No HK 7 26-Aug-22 01-Sep-22 13-Dec-22 19-Dec-22 109
commencement Hols - No B/O periods (was
310.C.EX.F480 WVT - Zone 4 (3310/4) - ELS - install vertical element (91nos. @2d/no./rig; use 3 rigs) C1)
C11_6 d/w - 10h/d - With 62 2 08-Sep-22 22-Nov-22 20-Dec-22 07-Mar-23 85
HK Hols - No B/O periods
310.C.EX.F1124.B01 WVT - Zone 4 (3310/4) - ELS - install wells (was
C01_7C3)
d/w - 10h/d - No HK 24 30-Oct-22 22-Nov-22 20-Feb-23 15-Mar-23 113
Hols - No B/O periods (was
310.C.EX.H1189 WVT - Zone 4 (3310/4) - ELS - submit Form BA14 C1)
C01_7 d/w - 10h/d - No HK 12 23-Nov-22 04-Dec-22 08-Mar-23 19-Mar-23 105
Hols - No B/O periods (was
310.C.EX.F497 WVT - Zone 4 (3310/4) - ELS - pumping test and submit report C1)
C01_7 d/w - 10h/d - No HK 18 23-Nov-22 10-Dec-22 16-Mar-23 02-Apr-23 113
Hols - No B/O periods (was
310.C.EX.H1193 WVT - Zone 4 (3310/4) - ELS - submit Form BA8 for excavation C1)
C01_7 d/w - 10h/d - No HK 7 05-Dec-22 11-Dec-22 20-Mar-23 26-Mar-23 105
Hols - No B/O periods (was
310.C.EX.H1197 WVT - Zone 4 (3310/4) - ELS - submit Form BA10 for excavation C1)
C01_7 d/w - 10h/d - No HK 7 12-Dec-22 18-Dec-22 27-Mar-23 02-Apr-23 105
Hols - No B/O periods (was
310.C.EX.H1317 WVT - Zone 4 (3310/4) - ELS - Initial excavation + uu hanger support + hang UU C1)
C01_7 d/w - 10h/d - No HK 24 2 19-Dec-22 11-Jan-23 03-Apr-23 26-Apr-23 105
Hols - No B/O periods (was
310.C.EX.X700 WVT - Zone 4 (3310/4) - Excavation, install struts [18,211m3 @500m3/d/wf; 1wf; 2 layers C1)
C11_6 d/w - 10h/d - With 58 2 12-Jan-23 23-Mar-23 27-Apr-23 07-Jul-23 83
struts @12d/layer] HK Hols - No B/O periods
310.C.EX.F1072 WVT - Zone 4 (3310/4) - ELS - make good FEL (and/or install remaining struts if any) (was
C01_7C3)
d/w - 10h/d - No HK 12 24-Mar-23 04-Apr-23 08-Jul-23 19-Jul-23 106
Hols - No B/O periods (was
310.C.EX.F1076 WVT - Zone 4 (3310/4) - ELS - Plate Load Test (1 nos.) (if required) C1)
C01_7 d/w - 10h/d - No HK 12 05-Apr-23 16-Apr-23 20-Jul-23 31-Jul-23 106
Hols - No B/O periods (was
CC#07 - WVT - Zone 5 (3310/4) - VE + ELS Installation C1) 238 14 19-Aug-22 08-Jun-23 08-Sep-22 28-Jun-23 16
310.D.EX.F206 WVT - ELS design (Vertical Elements) - prepare and submit Form BA8 and grant consent C01_7 d/w - 10h/d - No HK 7 19-Aug-22 25-Aug-22 08-Sep-22 14-Sep-22 20
Hols - No B/O periods (was
310.D.EX.F210 WVT - ELS design (Vertical Elements) - prepare and submit Form BA10 to notify work C1)
C01_7 d/w - 10h/d - No HK 7 26-Aug-22 01-Sep-22 15-Sep-22 21-Sep-22 20
commencement Hols - No B/O periods (was
310.C.EX.F1000 WVT - Zone 5 (3310/4) - ELS - install vertical element (163 nos. @2d/no./rig; use 4 rigs) C1)
C11_6 d/w - 10h/d - With 89 8 05-Sep-22 20-Dec-22 22-Sep-22 07-Jan-23 14
HK Hols - No B/O periods
310.C.EX.F1084 WVT - Zone 5 (3310/4) - ELS - install wells (was
C01_7C3)
d/w - 10h/d - No HK 24 27-Nov-22 20-Dec-22 24-Dec-22 16-Jan-23 27
Hols - No B/O periods (was
310.C.EX.H1205 WVT - Zone 5 (3310/4) - ELS - submit Form BA14 C1)
C01_7 d/w - 10h/d - No HK 12 21-Dec-22 01-Jan-23 09-Jan-23 20-Jan-23 19
Hols - No B/O periods (was
310.C.EX.F1004 WVT - Zone 5 (3310/4) - ELS - pumping test and submit report C1)
C01_7 d/w - 10h/d - No HK 18 21-Dec-22 07-Jan-23 17-Jan-23 03-Feb-23 27
Hols - No B/O periods (was
310.C.EX.H1209 WVT - Zone 5 (3310/4) - ELS - submit Form BA8 for excavation C1)
C01_7 d/w - 10h/d - No HK 7 02-Jan-23 08-Jan-23 21-Jan-23 27-Jan-23 19
Hols - No B/O periods (was
310.C.EX.H1213 WVT - Zone 5 (3310/4) - ELS - submit Form BA10 for excavation C1)
C01_7 d/w - 10h/d - No HK 7 09-Jan-23 15-Jan-23 28-Jan-23 03-Feb-23 19
Hols - No B/O periods (was
310.C.EX.H1321 WVT - Zone 5 (3310/4) - ELS - Initial excavation + uu hanger support + hang UU C1)
C01_7 d/w - 10h/d - No HK 24 2 16-Jan-23 08-Feb-23 04-Feb-23 27-Feb-23 19
Hols - No B/O periods (was
310.C.EX.X704 WVT - Zone 5 (3310/4) - ELS - Excavation, install struts [38,699m3 @600m3/d/wf; 2wf; 4 C1)
C11_6 d/w - 10h/d - With 87 2 09-Feb-23 27-May-23 28-Feb-23 15-Jun-23 16
layers struts @12d/layer] HK Hols - No B/O periods
310.C.EX.X706.B01 WVT - Zone 5 (3310/4) - ELS - Make good FEL + PLT (assumed) (was
C11_6C3)
d/w - 10h/d - With 10 2 29-May-23 08-Jun-23 16-Jun-23 28-Jun-23 16
HK Hols - No B/O periods
CC#07 - WVT - Zone 6 (3310/9A) - VE + ELS Installation (was C3) 222 8 27-Sep-22 28-Jun-23 02-Oct-22 04-Jul-23 4
310.D.EX.F194 WVT - ELS design (Vertical Elements) - prepare and submit Form BA8 and grant consent C01_7 d/w - 10h/d - No HK 7 27-Sep-22 03-Oct-22 02-Oct-22 08-Oct-22 5
Hols - No B/O periods (was
C1)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 143 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.EX.F198 WVT - ELS design (Vertical Elements) - prepare and submit Form BA10 to notify work C01_7 d/w - 10h/d - No HK 7 04-Oct-22 10-Oct-22 09-Oct-22 15-Oct-22 5
commencement Hols - No B/O periods (was
310.C.EX.F1007 Site Access 3310/9A and Contract <3303> complete WVT (Northern Portion) and ready C1)
C11_6 d/w - 10h/d - With 0 10-Oct-22 15-Oct-22 5
for 3310 ELS construction HK Hols - No B/O periods
310.C.EX.F1008 WVT - Zone 6 (3310/9A) - ELS - trial pile & install vertical element (147nos. @2d/no./rig; (was
C11_6C3)
d/w - 10h/d - With 82 2 11-Oct-22 16-Jan-23 17-Oct-22 21-Jan-23 5
use 4 rigs) HK Hols - No B/O periods
310.C.EX.F1080 WVT - Zone 6 (3310/9A) - ELS - install wells (was
C01_7C3)
d/w - 10h/d - No HK 24 24-Dec-22 16-Jan-23 06-Jan-23 29-Jan-23 13
Hols - No B/O periods (was
310.C.EX.H1221 WVT - Zone 6 (3310/9A) - ELS - submit Form BA14 C1)
C01_7 d/w - 10h/d - No HK 12 17-Jan-23 28-Jan-23 22-Jan-23 02-Feb-23 5
Hols - No B/O periods (was
310.C.EX.F1012 WVT - Zone 6 (3310/9A) - ELS - pumping test and submit report C1)
C01_7 d/w - 10h/d - No HK 18 17-Jan-23 03-Feb-23 30-Jan-23 16-Feb-23 13
Hols - No B/O periods (was
310.C.EX.H1225 WVT - Zone 6 (3310/9A) - ELS - submit Form BA8 for excavation C1)
C01_7 d/w - 10h/d - No HK 7 29-Jan-23 04-Feb-23 03-Feb-23 09-Feb-23 5
Hols - No B/O periods (was
310.C.EX.H1229 WVT - Zone 6 (3310/9A) - ELS - submit Form BA10 for excavation C1)
C01_7 d/w - 10h/d - No HK 7 05-Feb-23 11-Feb-23 10-Feb-23 16-Feb-23 5
Hols - No B/O periods (was
310.C.EX.H1325 WVT - Zone 6 (3310/9A) - ELS - Initial excavation + uu hanger support + hang UU C1)
C01_7 d/w - 10h/d - No HK 24 2 12-Feb-23 07-Mar-23 17-Feb-23 12-Mar-23 5
Hols - No B/O periods (was
310.C.EX.F518 WVT - Zone 6 (3310/9A) - ELS [34,146m3, @600m3/d/wf, 2wf; 4 layers struts C1)
C11_6 d/w - 10h/d - With 78 2 08-Mar-23 13-Jun-23 13-Mar-23 17-Jun-23 4
@12d/layer] HK Hols - No B/O periods
310.C.EX.F520.B01 WVT - Zone 6 (3310/9A) - ELS - Make good FEL + PLT (assumed) (was
C11_6C3)
d/w - 10h/d - With 12 2 14-Jun-23 28-Jun-23 19-Jun-23 04-Jul-23 4
HK Hols - No B/O periods
CC#07 - WVT - Tunnel Structure Construction (was C3) 305 49 12-Dec-22 20-Dec-23 18-Apr-23 22-Feb-24 50
CC#07 - WVT - Zone 1 (3310/4) - Tunnel Structure 165 6 24-Feb-23 13-Sep-23 19-Jul-23 29-Sep-23 14
310.C.EX.F542.B01 WVT - Zone 1 (3310/4) - Submit Form BA8 for RC works C01_7 d/w - 10h/d - No HK 7 24-Feb-23 02-Mar-23 19-Jul-23 25-Jul-23 145
Hols - No B/O periods (was
310.C.EX.F544.B01 WVT - Zone 1 (3310/4) - Submit Form BA10 for RC works C1)
C01_7 d/w - 10h/d - No HK 7 09-Jul-23 15-Jul-23 26-Jul-23 01-Aug-23 17
Hols - No B/O periods (was
310.C.EX.F546 WVT - Zone 1 (3310/4) - Bay 1 to 2 - construct base slab [@6d/bay; 1wf] C1)
C11_6 d/w - 10h/d - With 24 3 17-Jul-23 12-Aug-23 02-Aug-23 29-Aug-23 14
HK Hols - No B/O periods
310.C.EX.F614 WVT - Zone 1 (3310/4) - Bay 1 to 2 - construct walls & roof slab [9d/bay; 1wf] (was
C11_6C3)
d/w - 10h/d - With 27 3 14-Aug-23 13-Sep-23 30-Aug-23 29-Sep-23 14
HK Hols - No B/O periods
CC#07 - WVT - Zone 2 (3310/4) - Tunnel Structure (was C3) 127 6 02-Jan-23 09-Jun-23 18-Apr-23 03-Jul-23 18
310.C.EX.F750.B01 WVT - Zone 2 (3310/4) - Submit Form BA8 for RC works C01_7 d/w - 10h/d - No HK 7 02-Jan-23 08-Jan-23 18-Apr-23 24-Apr-23 106
Hols - No B/O periods (was
310.C.EX.F752.B01 WVT - Zone 2 (3310/4) - Submit Form BA10 for RC works C1)
C01_7 d/w - 10h/d - No HK 7 30-Mar-23 05-Apr-23 25-Apr-23 01-May-23 26
Hols - No B/O periods (was
310.C.EX.F754.B01 WVT - Zone 2 (3310/4) - Bay 1 to 2 - construct base slab [@6d/bay; 1wf] C1)
C11_6 d/w - 10h/d - With 24 3 06-Apr-23 08-May-23 02-May-23 30-May-23 18
HK Hols - No B/O periods
310.C.EX.F756.B01 WVT - Zone 2 (3310/4) - Bay 1 to 2 - construct walls & roof slab [9d/bay; 1wf] (was
C11_6C3)
d/w - 10h/d - With 27 3 09-May-23 09-Jun-23 31-May-23 03-Jul-23 18
HK Hols - No B/O periods
CC#07 - WVT - Zone 3 (3310/4) - Tunnel Structure (was C3) 232 14 18-Dec-22 29-Sep-23 23-May-23 29-Sep-23 0
310.C.EX.F102.B01 WVT - Zone 3 (3310/4) - Submit Form BA8 for RC works C01_7 d/w - 10h/d - No HK 7 18-Dec-22 24-Dec-22 23-May-23 29-May-23 156
Hols - No B/O periods (was
310.C.EX.F104.B01 WVT - Zone 3 (3310/4) - Submit Form BA10 for RC works C1)
C01_7 d/w - 10h/d - No HK 7 30-May-23 05-Jun-23 30-May-23 05-Jun-23 0
Hols - No B/O periods (was
310.C.EX.F106.B01 WVT - Zone 3 (3310/4) - Bay 1 to 10 - Construct base slab [@6d/bay; 2wf] C1)
C11_6 d/w - 10h/d - With 33 3 06-Jun-23 15-Jul-23 06-Jun-23 15-Jul-23 0
HK Hols - No B/O periods
310.C.EX.F110.B01 WVT - Zone 3 (3310/4) - Bay 1 to 10 - Construct walls & roof slab [12d/bay; 3wf] (was
C11_6C3)
d/w - 10h/d - With 45 4 30-Jun-23 22-Aug-23 30-Jun-23 22-Aug-23 0
HK Hols - No B/O periods
(was C3)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 144 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.EX.F108.B01 WVT - Zone 3 (3310/4) - Bay 10 to 20 - Construct base slab [@6d/bay; 2wf] C11_6 d/w - 10h/d - With 33 3 17-Jul-23 23-Aug-23 17-Jul-23 23-Aug-23 0
HK Hols - No B/O periods
310.C.EX.F112.B01 WVT - Zone 3 (3310/4) - Bay 10 to 20 - Construct walls & roof slab [12d/bay; 3wf] (was
C11_6C3)
d/w - 10h/d - With 45 4 09-Aug-23 29-Sep-23 09-Aug-23 29-Sep-23 0
HK Hols - No B/O periods
310.C.EX.W088 WVT - Zone 3 - construct access tower (was
C11_6C3)
d/w - 10h/d - With 35 21-Aug-23 29-Sep-23 21-Aug-23 29-Sep-23 0
HK Hols - No B/O periods
CC#07 - WVT - Zone 4 (3310/4) - Tunnel Structure (was C3) 147 7 12-Dec-22 13-Jun-23 25-Jul-23 25-Sep-23 87
310.C.EX.F722.B01 WVT - Zone 4 (3310/4) - Submit Form BA8 for RC works C01_7 d/w - 10h/d - No HK 7 12-Dec-22 18-Dec-22 25-Jul-23 31-Jul-23 225
Hols - No B/O periods (was
310.C.EX.F724.B01 WVT - Zone 4 (3310/4) - Submit Form BA10 for RC works C1)
C01_7 d/w - 10h/d - No HK 7 17-Apr-23 23-Apr-23 01-Aug-23 07-Aug-23 106
Hols - No B/O periods (was
310.C.EX.F726 WVT - Zone 4 (3310/4) - Bay 1 to 2 - Construct base slab [@6d/bay; 1wf] C1)
C11_6 d/w - 10h/d - With 15 2 24-Apr-23 11-May-23 08-Aug-23 24-Aug-23 87
HK Hols - No B/O periods
310.C.EX.F758 WVT - Zone 4 (3310/4) - Bay 1 to 2 - Construct walls & roof [@12d/bay; 1wf] (was
C11_6C3)
d/w - 10h/d - With 27 5 12-May-23 13-Jun-23 25-Aug-23 25-Sep-23 87
HK Hols - No B/O periods
CC#07 - WVT - Zone 5 (3310/4) - Tunnel Structure (was C3) 197 7 09-Jan-23 07-Sep-23 22-Jun-23 25-Sep-23 15
310.C.EX.F574.B01 WVT - Zone 5 (3310/4) -Submit Form BA8 for RC works C01_7 d/w - 10h/d - No HK 7 09-Jan-23 15-Jan-23 22-Jun-23 28-Jun-23 164
Hols - No B/O periods (was
310.C.EX.F576.B01 WVT - Zone 5 (3310/4) - Submit Form BA10 for RC works C1)
C01_7 d/w - 10h/d - No HK 7 09-Jun-23 15-Jun-23 29-Jun-23 05-Jul-23 20
Hols - No B/O periods (was
310.C.EX.F578 WVT - Zone 5 (3310/4) - Bay 1 to 4 - Construct base slab [@6d/bay; 2wf] C1)
C11_6 d/w - 10h/d - With 30 2 16-Jun-23 22-Jul-23 06-Jul-23 09-Aug-23 15
HK Hols - No B/O periods
310.C.EX.F626 WVT - Zone 5 (3310/4) - Bay 1 to 4 - Construct wall & roof slab [@12d/bay; 2wf] (was
C11_6C3)
d/w - 10h/d - With 54 5 07-Jul-23 07-Sep-23 25-Jul-23 25-Sep-23 15
HK Hols - No B/O periods
CC#07 - WVT - Zone 6 (3310/9A) - Tunnel Structure (was C3) 190 9 05-Feb-23 23-Sep-23 28-Jun-23 29-Sep-23 5
310.C.EX.F650.B01 WVT - Zone 6 (3310/9A) - Submit Form BA8 for RC works C01_7 d/w - 10h/d - No HK 7 05-Feb-23 11-Feb-23 28-Jun-23 04-Jul-23 143
Hols - No B/O periods (was
310.C.EX.F652.B01 WVT - Zone 6 (3310/9A) - Submit Form BA10 for RC works C1)
C01_7 d/w - 10h/d - No HK 7 29-Jun-23 05-Jul-23 05-Jul-23 11-Jul-23 6
Hols - No B/O periods (was
310.C.EX.F654 WVT - Zone 6 (3310/9A) - Bay 1 to 4 - Construct base slab [@6d/bay; 2wf] C1)
C11_6 d/w - 10h/d - With 30 4 06-Jul-23 09-Aug-23 12-Jul-23 15-Aug-23 5
HK Hols - No B/O periods
310.C.EX.F682 WVT - Zone 6 (3310/9A) - Bay 1 to 4 - Construct walls & roof slab [@12d/bay; 2wf] (was
C11_6C3)
d/w - 10h/d - With 54 5 24-Jul-23 23-Sep-23 29-Jul-23 29-Sep-23 5
HK Hols - No B/O periods
CC#07 - WVT - Mass Concrete Fill inside Tunnel (was
C11_6C3)
d/w - 10h/d - With HK Hols
64- No B/O 0periods (was
06-Oct-23
C3) 20-Dec-23 31-Oct-23 22-Feb-24 50
CC#07 - WVT - North Zone 5,6 C11_6 d/w - 10h/d - With HK Hols
16- No B/O 0periods (was
06-Oct-23
C3) 25-Oct-23 31-Oct-23 17-Nov-23 20
310.C.EX.Y728 WVT - North Zone 5 & 6 - bay 1 to 15 - Permanent Mass concrete fill (780m3] C11_6 d/w - 10h/d - With 16 06-Oct-23 25-Oct-23 31-Oct-23 17-Nov-23 20
HK Hols - No B/O periods
CC#07 - WVT - Middle Zone 3,4 (was
C11_6C3)
d/w - 10h/d - With HK Hols
42- No B/O 0periods (was
26-Oct-23
C3) 13-Dec-23 23-Dec-23 15-Feb-24 50
310.C.EX.Y796 WVT - Middle - Zone 3 & 4 - bay 1 to 14 - Permanent Mass concrete fill [1110m3/bay] C11_6 d/w - 10h/d - With 42 26-Oct-23 13-Dec-23 23-Dec-23 15-Feb-24 50
HK Hols - No B/O periods
CC#07 - WVT - South Zone 1,2 (was
C11_6C3)
d/w - 10h/d - With HK Hols6 - No B/O 0periods (was
14-Dec-23
C3) 20-Dec-23 16-Feb-24 22-Feb-24 50
310.C.EX.Y768 WVT - South - Zone 5 & 6 - bay 1 to 5 - Permanent Mass concrete fill [780m3x2] C11_6 d/w - 10h/d - With 6 14-Dec-23 20-Dec-23 16-Feb-24 22-Feb-24 50
HK Hols - No B/O periods
CC#07 - WVT - Earthwork - Backfilling (was
C11_6C3)
d/w - 10h/d - With HK Hols
142- No B/O18
periods (was
10-Jun-23
C3) 28-Nov-23 04-Jul-23 28-Nov-23 0
WVT - Zone 1 (3310/4) - Backfill C11_6 d/w - 10h/d - With HK Hols
26- No B/O 3periods (was
05-Sep-23
C3) 06-Oct-23 26-Sep-23 28-Oct-23 18
310.C.EX.F822 WVT - Zone 1 - Backfill from FL to +3.0mPD [3,650m3 @350m3/d/wf; 1wf] C11_6 d/w - 10h/d - With 12 1 05-Sep-23 18-Sep-23 26-Sep-23 11-Oct-23 18
HK Hols - No B/O periods
310.C.EX.F826 WVT - Zone 1 - Backfill from +3.0 to +6.5mPD [11,530m3 @350m3/d/wf; 2wf] (was
C11_6C3)
d/w - 10h/d - With 18 2 14-Sep-23 06-Oct-23 07-Oct-23 28-Oct-23 18
HK Hols - No B/O periods
WVT - Zone 2 (3310/4) - Backfill (was
C11_6C3)
d/w - 10h/d - With HK Hols
35- No B/O 4periods (was
10-Jun-23
C3) 22-Jul-23 04-Jul-23 12-Aug-23 18

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 145 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.EX.W084 WVT - Zone 2 - Backfill from FL to +3.0mPD [2,550m3 @350m3/d/wf; 1wf] C11_6 d/w - 10h/d - With 10 2 10-Jun-23 21-Jun-23 04-Jul-23 14-Jul-23 18
HK Hols - No B/O periods
310.C.EX.W84 WVT - Zone 2 - Backfill from +3.0 to +6.5mPD [8,070m3 @350m3/d/wf; 1wf] (was
C11_6C3)
d/w - 10h/d - With 25 2 23-Jun-23 22-Jul-23 15-Jul-23 12-Aug-23 18
HK Hols - No B/O periods
WVT - Zone 3 (3310/4) - Backfill (was
C11_6C3)
d/w - 10h/d - With HK Hols
89- No B/O 2periods (was
14-Aug-23
C3) 28-Nov-23 14-Aug-23 28-Nov-23 0
310.C.EX.F830 WVT - Zone 3 - bay 1 to 10 - Backfill from FL to +3.0mPD [25,910m3 @350m3/d/wf; 3wf] C11_6 d/w - 10h/d - With 27 2 14-Aug-23 13-Sep-23 14-Aug-23 13-Sep-23 0
HK Hols - No B/O periods
310.C.EX.F834 WVT - Zone 3 - bay 1 to 10 - Backfill from +3.0 to +6.5mPD [217,180m3 @350m3/d/wf; (was
C11_6C3)
d/w - 10h/d - With 32 14-Sep-23 24-Oct-23 14-Sep-23 24-Oct-23 0
10wf] HK Hols - No B/O periods
310.C.EX.F836 WVT - Zone 3 - bay 10 to 20 - Backfill from FL to +3.0mPD [51,820m3 @350m3/d/wf; 5wf] (was
C11_6C3)
d/w - 10h/d - With 30 16-Sep-23 24-Oct-23 16-Sep-23 24-Oct-23 0
HK Hols - No B/O periods
310.C.EX.F839 WVT - Zone 3 - bay 10 to 20 - Backfill from +3.0 to +6.5mPD [217,180m3 @350m3/d/wf; (was
C11_6C3)
d/w - 10h/d - With 30 25-Oct-23 28-Nov-23 25-Oct-23 28-Nov-23 0
10wf] HK Hols - No B/O periods
WVT - Zone 4 (3310/4) - Backfill (was
C11_6C3)
d/w - 10h/d - With HK Hols
47- No B/O 3periods (was
10-Jun-23
C3) 05-Aug-23 22-Sep-23 18-Nov-23 87
310.C.EX.F1020 WVT - Zone 4 - Backfill from FL to +3.0mPD [5,920m3 @350m3/d/wf; 1wf] C11_6 d/w - 10h/d - With 18 1 10-Jun-23 03-Jul-23 22-Sep-23 14-Oct-23 87
HK Hols - No B/O periods
310.C.EX.F1024 WVT - Zone 4 - Backfill from +3.0 to +6.5mPD [19,095m3 @350m3/d/wf; 2wf] (was
C11_6C3)
d/w - 10h/d - With 29 2 04-Jul-23 05-Aug-23 16-Oct-23 18-Nov-23 87
HK Hols - No B/O periods
WVT - Zone 5 (3310/4) - Backfill (was
C11_6C3)
d/w - 10h/d - With HK Hols
37- No B/O 2periods (was
08-Sep-23
C3) 24-Oct-23 26-Sep-23 14-Nov-23 18
310.C.EX.F1028 WVT - Zone 5 - Backfill from FL to +3.0mPD [6,220m3 @350m3/d/wf; 1wf] C11_6 d/w - 10h/d - With 18 1 08-Sep-23 28-Sep-23 26-Sep-23 18-Oct-23 15
HK Hols - No B/O periods
310.C.EX.F1032 WVT - Zone 5 - Backfill from +3.0 to +6.5mPD [17,370m3 @350m3/d/wf; 2wf] (was
C11_6C3)
d/w - 10h/d - With 26 1 21-Sep-23 24-Oct-23 14-Oct-23 14-Nov-23 18
HK Hols - No B/O periods
WVT - Zone 6 (3310/9A) - Backfill (was
C11_6C3)
d/w - 10h/d - With HK Hols
42- No B/O 4periods (was
11-Sep-23
C3) 01-Nov-23 18-Sep-23 08-Nov-23 6
310.C.EX.F1036 WVT - Zone 6 - Backfill from FL to +3.0mPD [5,490m3 @350m3/d/wf; 1wf] C11_6 d/w - 10h/d - With 18 2 11-Sep-23 03-Oct-23 18-Sep-23 10-Oct-23 6
HK Hols - No B/O periods
310.C.EX.F1040 WVT - Zone 6 - Backfill from +3.0 to +6.5mPD [15,330m3 @350m3/d/wf; 2wf] (was
C11_6C3)
d/w - 10h/d - With 24 2 04-Oct-23 01-Nov-23 11-Oct-23 08-Nov-23 6
HK Hols - No B/O periods
CC#07 - WVT - Internal ABWF Works (was
C11_6C3)
d/w - 10h/d - With HK Hols
562- No B/O132
periods (was
04-Jul-22
C3) 23-May-24 04-Jul-22 27-May-24 3
310.C.EX.F837 WVT - access to Works Area 3310/9A C11_6 d/w - 10h/d - With 0 04-Jul-22* 04-Jul-22 0
HK Hols - No B/O periods
310.C.EX.F841 WVT - access to Works Area 3310/12 (was
C11_6C3)
d/w - 10h/d - With 0 04-Jul-22* 04-Jul-22 0
HK Hols - No B/O periods
310.C.EX.F842 WVT - Contract <3303> complete whole WVT and allow access into WUR, WA01, WU, (was
C11_6C3)
d/w - 10h/d - With 0 04-Jul-22 03-Sep-22 54
WA02, WR & WVT north portion HK Hols - No B/O periods
310.C.EX.F845 WVT - R.C. Structure completed (PMS 18) (was
C11_6C3)
d/w - 10h/d - With 0 29-Sep-23 29-Sep-23 0
HK Hols - No B/O periods
WVT - ABWF - Western Ramp (WR) (was
C11_6C3)
d/w - 10h/d - With HK Hols
352- No B/O24
periods (was
29-Aug-22
C3) 03-Nov-23 05-Sep-22 07-Nov-23 3
WVT - TTM Stage 1 (WR) - Northbound C11_6 d/w - 10h/d - With HK Hols
172- No B/O12
periods (was
29-Aug-22
C3) 25-Mar-23 05-Sep-22 29-Mar-23 3
310.C.EX.W834 WVT - TTM Stage 1 (WR) - North-Bound - brickwork and blockwork C11_6 d/w - 10h/d - With 42 2 29-Aug-22 19-Oct-22 05-Sep-22 26-Oct-22 6
HK Hols - No B/O periods
310.C.EX.W850 WVT - TTM Stage 1 (WR) - North-Bound - Builder works in connection with BS (was
C11_6C3)
d/w - 10h/d - With 42 2 29-Aug-22 19-Oct-22 05-Sep-22 26-Oct-22 6
HK Hols - No B/O periods
310.C.EX.W838 WVT - TTM Stage 1 (WR) - North-Bound - steel and metalwork (was
C11_6C3)
d/w - 10h/d - With 42 2 09-Sep-22 31-Oct-22 20-Sep-22 09-Nov-22 8
HK Hols - No B/O periods
310.C.EX.W842 WVT - TTM Stage 1 (WR) - North-Bound - plastering and screeding works (was C3)
C11_6 d/w - 10h/d - With 42 2 22-Sep-22 11-Nov-22 03-Oct-22 21-Nov-22 8
HK Hols - No B/O periods
310.C.EX.W846 WVT - TTM Stage 1 (WR) - North-Bound - Painting Works (was
C11_6C3)
d/w - 10h/d - With 42 2 06-Oct-22 23-Nov-22 15-Oct-22 02-Dec-22 8
HK Hols - No B/O periods
310.C.EX.W854 WVT - TTM Stage 1 (WR) - North-Bound - Road Paving works (was
C11_6C3)
d/w - 10h/d - With 42 2 06-Feb-23 25-Mar-23 09-Feb-23 29-Mar-23 3
HK Hols - No B/O periods
(was C3)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 146 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
WVT - TTM Stage 2 (WR) - Southbound C11_6 d/w - 10h/d - With HK Hols
172- No B/O12
periods (was
06-Apr-23
C3) 03-Nov-23 17-Apr-23 07-Nov-23 3
310.C.EX.W914 WVT - TTM Stage 2 (WR) - South-Bound - brickwork and blockwork C11_6 d/w - 10h/d - With 42 2 06-Apr-23 30-May-23 17-Apr-23 06-Jun-23 6
HK Hols - No B/O periods
310.C.EX.W930 WVT - TTM Stage 2 (WR) - South-Bound - Builder works in connection with BS (was
C11_6C3)
d/w - 10h/d - With 42 2 06-Apr-23 30-May-23 17-Apr-23 06-Jun-23 6
HK Hols - No B/O periods
310.C.EX.W918 WVT - TTM Stage 2 (WR) - South-Bound - steel and metalwork (was
C11_6C3)
d/w - 10h/d - With 42 2 21-Apr-23 10-Jun-23 02-May-23 20-Jun-23 8
HK Hols - No B/O periods
310.C.EX.W922 WVT - TTM Stage 2 (WR) - South-Bound - plastering and screeding works (was
C11_6C3)
d/w - 10h/d - With 42 2 04-May-23 23-Jun-23 13-May-23 04-Jul-23 8
HK Hols - No B/O periods
310.C.EX.W926 WVT - TTM Stage 2 (WR) - South-Bound - Painting Works (was
C11_6C3)
d/w - 10h/d - With 42 2 16-May-23 06-Jul-23 25-May-23 15-Jul-23 8
HK Hols - No B/O periods
310.C.EX.W934 WVT - TTM Stage 2 (WR) - South-Bound - Road Paving works (was
C11_6C3)
d/w - 10h/d - With 42 2 13-Sep-23 03-Nov-23 16-Sep-23 07-Nov-23 3
HK Hols - No B/O periods
WVT - ABWF - Western Roundabout (WA02) (was
C11_6C3)
d/w - 10h/d - With HK Hols
342- No B/O24
periods (was
20-Oct-22
C3) 11-Dec-23 27-Oct-22 14-Dec-23 3
WVT - TTM Stage 1 (WA02) - Northbound C11_6 d/w - 10h/d - With HK Hols
162- No B/O12
periods (was
20-Oct-22
C3) 08-May-23 27-Oct-22 11-May-23 3
310.C.EX.W626 WVT - TTM Stage 1 (WA02) - North-Bound - brickwork and blockwork C11_6 d/w - 10h/d - With 32 2 20-Oct-22 25-Nov-22 27-Oct-22 02-Dec-22 6
HK Hols - No B/O periods
310.C.EX.W642 WVT - TTM Stage 1 (WA02) - North-Bound - Builder works in connection with BS (was
C11_6C3)
d/w - 10h/d - With 32 2 20-Oct-22 25-Nov-22 27-Oct-22 02-Dec-22 6
HK Hols - No B/O periods
310.C.EX.W630 WVT - TTM Stage 1 (WA02) - North-Bound - steel and metalwork (was
C11_6C3)
d/w - 10h/d - With 32 2 01-Nov-22 07-Dec-22 10-Nov-22 16-Dec-22 8
HK Hols - No B/O periods
310.C.EX.W634 WVT - TTM Stage 1 (WA02) - North-Bound - plastering and screeding works (was
C11_6C3)
d/w - 10h/d - With 32 2 12-Nov-22 19-Dec-22 22-Nov-22 29-Dec-22 8
HK Hols - No B/O periods
310.C.EX.W638 WVT - TTM Stage 1 (WA02) - North-Bound - Painting Works (was
C11_6C3)
d/w - 10h/d - With 32 2 24-Nov-22 31-Dec-22 03-Dec-22 11-Jan-23 8
HK Hols - No B/O periods
310.C.EX.W646 WVT - TTM Stage 1 (WA02) - North-Bound - Road Paving works (was
C11_6C3)
d/w - 10h/d - With 32 2 27-Mar-23 08-May-23 30-Mar-23 11-May-23 3
HK Hols - No B/O periods
WVT - TTM Stage 2 (WA02) - Southbound (was
C11_6C3)
d/w - 10h/d - With HK Hols
162- No B/O12
periods (was
31-May-23
C3) 11-Dec-23 07-Jun-23 14-Dec-23 3
310.C.EX.W938 WVT - TTM Stage 2 (WA02) - South-Bound - brickwork and blockwork C11_6 d/w - 10h/d - With 32 2 31-May-23 08-Jul-23 07-Jun-23 15-Jul-23 6
HK Hols - No B/O periods
310.C.EX.W954 WVT - TTM Stage 2 (WA02) - South-Bound - Builder works in connection with BS (was
C11_6C3)
d/w - 10h/d - With 32 2 31-May-23 08-Jul-23 07-Jun-23 15-Jul-23 6
HK Hols - No B/O periods
310.C.EX.W942 WVT - TTM Stage 2 (WA02) - South-Bound - steel and metalwork (was
C11_6C3)
d/w - 10h/d - With 32 2 12-Jun-23 20-Jul-23 21-Jun-23 29-Jul-23 8
HK Hols - No B/O periods
310.C.EX.W946 WVT - TTM Stage 2 (WA02) - South-Bound - plastering and screeding works (was
C11_6C3)
d/w - 10h/d - With 32 2 24-Jun-23 01-Aug-23 05-Jul-23 10-Aug-23 8
HK Hols - No B/O periods
310.C.EX.W950 WVT - TTM Stage 2 (WA02) - South-Bound - Painting Works (was
C11_6C3)
d/w - 10h/d - With 32 2 07-Jul-23 12-Aug-23 17-Jul-23 22-Aug-23 8
HK Hols - No B/O periods
310.C.EX.W958 WVT - TTM Stage 2 (WA02) - South-Bound - Road Paving works (was
C11_6C3)
d/w - 10h/d - With 32 2 04-Nov-23 11-Dec-23 08-Nov-23 14-Dec-23 3
HK Hols - No B/O periods
WVT - ABWF - Western Underpass (WU) (was
C11_6C3)
d/w - 10h/d - With HK Hols
350- No B/O24
periods (was
26-Nov-22
C3) 30-Jan-24 03-Dec-22 02-Feb-24 3
WVT - TTM Stage 1 (WU) - Northbound C11_6 d/w - 10h/d - With HK Hols
172- No B/O12
periods (was
26-Nov-22
C3) 28-Jun-23 03-Dec-22 03-Jul-23 3
310.C.EX.W650 WVT - TTM Stage 1 (WU) - North-Bound - brickwork and blockwork C11_6 d/w - 10h/d - With 42 2 26-Nov-22 16-Jan-23 03-Dec-22 26-Jan-23 6
HK Hols - No B/O periods
310.C.EX.W666 WVT - TTM Stage 1 (WU) - North-Bound - Builder works in connection with BS (was
C11_6C3)
d/w - 10h/d - With 42 2 26-Nov-22 16-Jan-23 03-Dec-22 26-Jan-23 6
HK Hols - No B/O periods
310.C.EX.W654 WVT - TTM Stage 1 (WU) - North-Bound - steel and metalwork (was
C11_6C3)
d/w - 10h/d - With 42 2 08-Dec-22 31-Jan-23 17-Dec-22 09-Feb-23 8
HK Hols - No B/O periods
310.C.EX.W658 WVT - TTM Stage 1 (WU) - North-Bound - plastering and screeding works (was
C11_6C3)
d/w - 10h/d - With 42 2 20-Dec-22 11-Feb-23 30-Dec-22 21-Feb-23 8
HK Hols - No B/O periods
(was C3)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 147 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.EX.W662 WVT - TTM Stage 1 (WU) - North-Bound - Painting Works C11_6 d/w - 10h/d - With 42 2 03-Jan-23 23-Feb-23 12-Jan-23 04-Mar-23 8
HK Hols - No B/O periods
310.C.EX.W670 WVT - TTM Stage 1 (WU) - North-Bound - Road Paving works (was
C11_6C3)
d/w - 10h/d - With 42 2 09-May-23 28-Jun-23 12-May-23 03-Jul-23 3
HK Hols - No B/O periods
WVT - TTM Stage 2 (WU) - Southbound (was
C11_6C3)
d/w - 10h/d - With HK Hols
170- No B/O12
periods (was
10-Jul-23
C3) 30-Jan-24 17-Jul-23 02-Feb-24 3
310.C.EX.W962 WVT - TTM Stage 2 (WU) - South-Bound - brickwork and blockwork C11_6 d/w - 10h/d - With 42 2 10-Jul-23 26-Aug-23 17-Jul-23 02-Sep-23 6
HK Hols - No B/O periods
310.C.EX.W978 WVT - TTM Stage 2 (WU) - South-Bound - Builder works in connection with BS (was
C11_6C3)
d/w - 10h/d - With 42 2 10-Jul-23 26-Aug-23 17-Jul-23 02-Sep-23 6
HK Hols - No B/O periods
310.C.EX.W966 WVT - TTM Stage 2 (WU) - South-Bound - steel and metalwork (was
C11_6C3)
d/w - 10h/d - With 42 2 21-Jul-23 07-Sep-23 31-Jul-23 16-Sep-23 8
HK Hols - No B/O periods
310.C.EX.W970 WVT - TTM Stage 2 (WU) - South-Bound - plastering and screeding works (was
C11_6C3)
d/w - 10h/d - With 42 2 02-Aug-23 19-Sep-23 11-Aug-23 28-Sep-23 8
HK Hols - No B/O periods
310.C.EX.W974 WVT - TTM Stage 2 (WU) - South-Bound - Painting Works (was
C11_6C3)
d/w - 10h/d - With 42 2 14-Aug-23 03-Oct-23 23-Aug-23 12-Oct-23 8
HK Hols - No B/O periods
310.C.EX.W982 WVT - TTM Stage 2 (WU) - South-Bound - Road Paving works (was
C11_6C3)
d/w - 10h/d - With 40 2 12-Dec-23 30-Jan-24 15-Dec-23 02-Feb-24 3
HK Hols - No B/O periods
WVT - ABWF - Western Roundabout (WA01) (was
C11_6C3)
d/w - 10h/d - With HK Hols
338- No B/O24
periods (was
17-Jan-23
C3) 07-Mar-24 27-Jan-23 11-Mar-24 3
WVT - TTM Stage 1 (WA01) - Northbound C11_6 d/w - 10h/d - With HK Hols
162- No B/O12
periods (was
17-Jan-23
C3) 05-Aug-23 27-Jan-23 09-Aug-23 3
310.C.EX.W810 WVT - TTM Stage 1 (WA01) - North-Bound - brickwork and blockwork C11_6 d/w - 10h/d - With 32 2 17-Jan-23 25-Feb-23 27-Jan-23 04-Mar-23 6
HK Hols - No B/O periods
310.C.EX.W826 WVT - TTM Stage 1 (WA01) - North-Bound - Builder works in connection with BS (was
C11_6C3)
d/w - 10h/d - With 32 2 17-Jan-23 25-Feb-23 27-Jan-23 04-Mar-23 6
HK Hols - No B/O periods
310.C.EX.W814 WVT - TTM Stage 1 (WA01) - North-Bound - steel and metalwork (was
C11_6C3)
d/w - 10h/d - With 32 2 01-Feb-23 09-Mar-23 10-Feb-23 18-Mar-23 8
HK Hols - No B/O periods
310.C.EX.W818 WVT - TTM Stage 1 (WA01) - North-Bound - plastering and screeding works (was
C11_6C3)
d/w - 10h/d - With 32 2 13-Feb-23 21-Mar-23 22-Feb-23 30-Mar-23 8
HK Hols - No B/O periods
310.C.EX.W822 WVT - TTM Stage 1 (WA01) - North-Bound - Painting Works (was
C11_6C3)
d/w - 10h/d - With 32 2 24-Feb-23 01-Apr-23 06-Mar-23 15-Apr-23 8
HK Hols - No B/O periods
310.C.EX.W830 WVT - TTM Stage 1 (WA01) - North-Bound - Road Paving works (was
C11_6C3)
d/w - 10h/d - With 32 2 29-Jun-23 05-Aug-23 04-Jul-23 09-Aug-23 3
HK Hols - No B/O periods
WVT - TTM Stage 2 (WA01) - Southbound (was
C11_6C3)
d/w - 10h/d - With HK Hols
158- No B/O12
periods (was
28-Aug-23
C3) 07-Mar-24 06-Sep-23 11-Mar-24 3
310.C.EX.W839 WVT - TTM Stage 2 (WA01) - South-Bound - brickwork and blockwork C11_6 d/w - 10h/d - With 32 2 28-Aug-23 05-Oct-23 06-Sep-23 14-Oct-23 8
HK Hols - No B/O periods
310.C.EX.W852 WVT - TTM Stage 2 (WA01) - South-Bound - Builder works in connection with BS (was
C11_6C3)
d/w - 10h/d - With 32 2 28-Aug-23 05-Oct-23 11-Sep-23 19-Oct-23 12
HK Hols - No B/O periods
310.C.EX.W843 WVT - TTM Stage 2 (WA01) - South-Bound - steel and metalwork (was
C11_6C3)
d/w - 10h/d - With 32 2 08-Sep-23 17-Oct-23 18-Sep-23 27-Oct-23 8
HK Hols - No B/O periods
310.C.EX.W847 WVT - TTM Stage 2 (WA01) - South-Bound - plastering and screeding works (was
C11_6C3)
d/w - 10h/d - With 32 2 20-Sep-23 30-Oct-23 29-Sep-23 08-Nov-23 8
HK Hols - No B/O periods
310.C.EX.W851 WVT - TTM Stage 2 (WA01) - South-Bound - Painting Works (was
C11_6C3)
d/w - 10h/d - With 32 2 04-Oct-23 10-Nov-23 13-Oct-23 20-Nov-23 8
HK Hols - No B/O periods
310.C.EX.W856 WVT - TTM Stage 2 (WA01) - South-Bound - Road Paving works (was
C11_6C3)
d/w - 10h/d - With 30 2 31-Jan-24 07-Mar-24 03-Feb-24 11-Mar-24 3
HK Hols - No B/O periods
WVT - ABWF - Western Underpass Ramp (WUR) (was
C11_6C3)
d/w - 10h/d - With HK Hols
336- No B/O24
periods (was
27-Feb-23
C3) 16-Apr-24 06-Mar-23 19-Apr-24 3
WVT - TTM Stage 1 (WUR) - Northbound C11_6 d/w - 10h/d - With HK Hols
162- No B/O12
periods (was
27-Feb-23
C3) 12-Sep-23 06-Mar-23 15-Sep-23 3
310.C.EX.W602 WVT - TTM Stage 1 (WUR) - North-Bound - brickwork and blockwork C11_6 d/w - 10h/d - With 32 2 27-Feb-23 04-Apr-23 06-Mar-23 15-Apr-23 6
HK Hols - No B/O periods
310.C.EX.W618 WVT - TTM Stage 1 (WUR) - North-Bound - Builder works in connection with BS (was
C11_6C3)
d/w - 10h/d - With 32 2 27-Feb-23 04-Apr-23 06-Mar-23 15-Apr-23 6
HK Hols - No B/O periods
(was C3)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 148 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.EX.W606 WVT - TTM Stage 1 (WUR) - North-Bound - steel and metalwork C11_6 d/w - 10h/d - With 32 2 10-Mar-23 20-Apr-23 20-Mar-23 29-Apr-23 8
HK Hols - No B/O periods
310.C.EX.W610 WVT - TTM Stage 1 (WUR) - North-Bound - plastering and screeding works (was
C11_6C3)
d/w - 10h/d - With 32 2 22-Mar-23 03-May-23 31-Mar-23 12-May-23 8
HK Hols - No B/O periods
310.C.EX.W614 WVT - TTM Stage 1 (WUR) - North-Bound - Painting Works (was
C11_6C3)
d/w - 10h/d - With 32 2 03-Apr-23 15-May-23 17-Apr-23 24-May-23 8
HK Hols - No B/O periods
310.C.EX.W622 WVT - TTM Stage 1 (WUR) - North-Bound - Road Paving works (was
C11_6C3)
d/w - 10h/d - With 32 2 07-Aug-23 12-Sep-23 10-Aug-23 15-Sep-23 3
HK Hols - No B/O periods
WVT - TTM Stage 2 (WUR) - Southbound (was
C11_6C3)
d/w - 10h/d - With HK Hols
156- No B/O12
periods (was
06-Oct-23
C3) 16-Apr-24 16-Oct-23 19-Apr-24 3
310.C.EX.W623 WVT - TTM Stage 2 (WUR) - South-Bound - brickwork and blockwork C11_6 d/w - 10h/d - With 32 2 06-Oct-23 13-Nov-23 16-Oct-23 22-Nov-23 8
HK Hols - No B/O periods
310.C.EX.W639 WVT - TTM Stage 2 (WUR) - South-Bound - Builder works in connection with BS (was
C11_6C3)
d/w - 10h/d - With 32 2 06-Oct-23 13-Nov-23 20-Oct-23 27-Nov-23 12
HK Hols - No B/O periods
310.C.EX.W627 WVT - TTM Stage 2 (WUR) - South-Bound - steel and metalwork (was
C11_6C3)
d/w - 10h/d - With 32 2 18-Oct-23 24-Nov-23 28-Oct-23 04-Dec-23 8
HK Hols - No B/O periods
310.C.EX.W631 WVT - TTM Stage 2 (WUR) - South-Bound - plastering and screeding works (was
C11_6C3)
d/w - 10h/d - With 32 2 31-Oct-23 06-Dec-23 09-Nov-23 15-Dec-23 8
HK Hols - No B/O periods
310.C.EX.W635 WVT - TTM Stage 2 (WUR) - South-Bound - Painting Works (was
C11_6C3)
d/w - 10h/d - With 32 2 11-Nov-23 18-Dec-23 21-Nov-23 29-Dec-23 8
HK Hols - No B/O periods
310.C.EX.W643 WVT - TTM Stage 2 (WUR) - South-Bound - Road Paving works (was
C11_6C3)
d/w - 10h/d - With 30 2 08-Mar-24 16-Apr-24 12-Mar-24 19-Apr-24 3
HK Hols - No B/O periods
WVT - ABWF - Western Vehicular Tunnel (WT) (was
C11_6C3)
d/w - 10h/d - With HK Hols
189- No B/O12
periods (was
03-Oct-23
C3) 23-May-24 27-Oct-23 27-May-24 3
310.C.EX.W673 WVT (WT) - Remove Bulkhead Walls C11_6 d/w - 10h/d - With 3 2 03-Oct-23 05-Oct-23 27-Oct-23 30-Oct-23 20
HK Hols - No B/O periods
310.C.EX.W674 WVT (WT) - brickwork and blockwork (was
C11_6C3)
d/w - 10h/d - With 60 18-Oct-23 29-Dec-23 11-Nov-23 23-Jan-24 20
HK Hols - No B/O periods
310.C.EX.W690 WVT (WT) - Builder works in connection with BS (was
C11_6C3)
d/w - 10h/d - With 62 2 18-Oct-23 02-Jan-24 23-Nov-23 06-Feb-24 30
HK Hols - No B/O periods
310.C.EX.W678 WVT (WT) - steel and metalwork (was
C11_6C3)
d/w - 10h/d - With 62 2 11-Nov-23 25-Jan-24 05-Dec-23 20-Feb-24 20
HK Hols - No B/O periods
310.C.EX.W682 WVT (WT) - plastering and screeding works (was
C11_6C3)
d/w - 10h/d - With 62 2 19-Dec-23 05-Mar-24 30-Dec-23 14-Mar-24 8
HK Hols - No B/O periods
310.C.EX.W686 WVT (WT) - Painting Works (was
C11_6C3)
d/w - 10h/d - With 62 2 15-Jan-24 28-Mar-24 24-Jan-24 11-Apr-24 8
HK Hols - No B/O periods
310.C.EX.W694 WVT (WT) - Road Paving works (was
C11_6C3)
d/w - 10h/d - With 30 2 17-Apr-24 23-May-24 20-Apr-24 27-May-24 3
HK Hols - No B/O periods
CC#07 - WVT - MEP Installation (was
C11_6C3)
d/w - 10h/d - With HK Hols
397- No B/O174
periods (was
28-Nov-22
C3) 28-Mar-24 01-Dec-22 29-Apr-24 23
WVT - MEP - Western Ramp (WR) C11_6 d/w - 10h/d - With HK Hols
232- No B/O32
periods (was
28-Nov-22
C3) 08-Sep-23 01-Dec-22 15-Sep-23 6
WVT - TTM Stage 1 (WR) - Northbound C11_6 d/w - 10h/d - With HK Hols
85- No B/O16
periods (was
28-Nov-22
C3) 11-Mar-23 01-Dec-22 29-Mar-23 15
310.C.EX.W886 WVT - TTM Stage 1 (WR) - North-Bound - Electrical Installation works C11_6 d/w - 10h/d - With 45 2 28-Nov-22 20-Jan-23 01-Dec-22 27-Jan-23 3
HK Hols - No B/O periods
310.C.EX.W910 WVT - TTM Stage 1 (WR) - North-Bound - Drainage Installation (was
C11_6C3)
d/w - 10h/d - With 45 2 28-Nov-22 20-Jan-23 13-Dec-22 08-Feb-23 13
HK Hols - No B/O periods
310.C.EX.W890 WVT - TTM Stage 1 (WR) - North-Bound - Tunnel Ventilation System Installation (was
C11_6C3)
d/w - 10h/d - With 45 2 09-Dec-22 04-Feb-23 13-Dec-22 08-Feb-23 3
HK Hols - No B/O periods
310.C.EX.W894 WVT - TTM Stage 1 (WR) - North-Bound - Air Quality Monitoring System (was
C11_6C3)
d/w - 10h/d - With 45 2 21-Dec-22 16-Feb-23 10-Jan-23 06-Mar-23 15
HK Hols - No B/O periods
310.C.EX.W898 WVT - TTM Stage 1 (WR) - North-Bound - Electrical and Control System (was
C11_6C3)
d/w - 10h/d - With 45 2 04-Jan-23 28-Feb-23 21-Jan-23 17-Mar-23 15
HK Hols - No B/O periods
310.C.EX.W899 WVT - TTM Stage 1 (WR) - North-Bound - Cabling Works (was
C11_6C3)
d/w - 10h/d - With 45 2 04-Jan-23 28-Feb-23 21-Jan-23 17-Mar-23 15
HK Hols - No B/O periods
(was C3)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 149 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.EX.W902 WVT - TTM Stage 1 (WR) - North-Bound - FS Installation C11_6 d/w - 10h/d - With 45 2 16-Jan-23 11-Mar-23 06-Feb-23 29-Mar-23 15
HK Hols - No B/O periods
310.C.EX.W906 WVT - TTM Stage 1 (WR) - North-Bound - Plumbing System for FS (was
C11_6C3)
d/w - 10h/d - With 45 2 16-Jan-23 11-Mar-23 06-Feb-23 29-Mar-23 15
HK Hols - No B/O periods
WVT - TTM Stage 2 (WR) - Southbound (was
C11_6C3)
d/w - 10h/d - With HK Hols
85- No B/O16
periods (was
31-May-23
C3) 08-Sep-23 07-Jun-23 15-Sep-23 6
310.C.EX.X100 WVT - TTM Stage 2 (WR) - South-Bound - Electrical Installation works C11_6 d/w - 10h/d - With 45 2 31-May-23 24-Jul-23 07-Jun-23 31-Jul-23 6
HK Hols - No B/O periods
310.C.EX.X124 WVT - TTM Stage 2 (WR) - South-Bound - Drainage Installation (was
C11_6C3)
d/w - 10h/d - With 45 2 31-May-23 24-Jul-23 26-Jul-23 15-Sep-23 46
HK Hols - No B/O periods
310.C.EX.X104 WVT - TTM Stage 2 (WR) - South-Bound - Tunnel Ventilation System Installation (was
C11_6C3)
d/w - 10h/d - With 45 2 12-Jun-23 04-Aug-23 19-Jun-23 11-Aug-23 6
HK Hols - No B/O periods
310.C.EX.X108 WVT - TTM Stage 2 (WR) - South-Bound - Air Quality Monitoring System (was
C11_6C3)
d/w - 10h/d - With 45 2 24-Jun-23 16-Aug-23 03-Jul-23 23-Aug-23 6
HK Hols - No B/O periods
310.C.EX.X112 WVT - TTM Stage 2 (WR) - South-Bound - Electrical and Control System (was
C11_6C3)
d/w - 10h/d - With 45 2 07-Jul-23 28-Aug-23 14-Jul-23 04-Sep-23 6
HK Hols - No B/O periods
310.C.EX.X113 WVT - TTM Stage 2 (WR) - South-Bound - Cabling Works (was
C11_6C3)
d/w - 10h/d - With 45 2 07-Jul-23 28-Aug-23 14-Jul-23 04-Sep-23 6
HK Hols - No B/O periods
310.C.EX.X116 WVT - TTM Stage 2 (WR) - South-Bound - FS Installation (was
C11_6C3)
d/w - 10h/d - With 45 2 19-Jul-23 08-Sep-23 26-Jul-23 15-Sep-23 6
HK Hols - No B/O periods
310.C.EX.X120 WVT - TTM Stage 2 (WR) - South-Bound - Plumbing System for FS (was
C11_6C3)
d/w - 10h/d - With 45 2 19-Jul-23 08-Sep-23 26-Jul-23 15-Sep-23 6
HK Hols - No B/O periods
WVT - MEP - Western Roundabout (WA02) (was
C11_6C3)
d/w - 10h/d - With HK Hols
249- No B/O32
periods (was
28-Nov-22
C3) 28-Sep-23 04-Jan-23 07-Nov-23 31
WVT - TTM Stage 1 (WA02) - Northbound C11_6 d/w - 10h/d - With HK Hols
70- No B/O16
periods (was
28-Nov-22
C3) 22-Feb-23 04-Jan-23 29-Mar-23 30
310.C.EX.W726 WVT - TTM Stage 1 (WA02) - North-Bound - Electrical Installation works C11_6 d/w - 10h/d - With 30 2 28-Nov-22 03-Jan-23 04-Jan-23 10-Feb-23 30
HK Hols - No B/O periods
310.C.EX.W750 WVT - TTM Stage 1 (WA02) - North-Bound - Drainage Installation (was
C11_6C3)
d/w - 10h/d - With 30 2 28-Nov-22 03-Jan-23 22-Feb-23 28-Mar-23 69
HK Hols - No B/O periods
310.C.EX.W730 WVT - TTM Stage 1 (WA02) - North-Bound - Tunnel Ventilation System Installation (was
C11_6C3)
d/w - 10h/d - With 30 2 09-Dec-22 14-Jan-23 16-Jan-23 22-Feb-23 30
HK Hols - No B/O periods
310.C.EX.W734 WVT - TTM Stage 1 (WA02) - North-Bound - Air Quality Monitoring System (was
C11_6C3)
d/w - 10h/d - With 30 2 21-Dec-22 30-Jan-23 31-Jan-23 06-Mar-23 30
HK Hols - No B/O periods
310.C.EX.W738 WVT - TTM Stage 1 (WA02) - North-Bound - Electrical and Control System (was
C11_6C3)
d/w - 10h/d - With 30 2 04-Jan-23 10-Feb-23 11-Feb-23 17-Mar-23 30
HK Hols - No B/O periods
310.C.EX.W739 WVT - TTM Stage 1 (WA02) - North-Bound - Cabling Works (was
C11_6C3)
d/w - 10h/d - With 30 2 04-Jan-23 10-Feb-23 11-Feb-23 17-Mar-23 30
HK Hols - No B/O periods
310.C.EX.W742 WVT - TTM Stage 1 (WA02) - North-Bound - FS Installation (was
C11_6C3)
d/w - 10h/d - With 30 2 16-Jan-23 22-Feb-23 23-Feb-23 29-Mar-23 30
HK Hols - No B/O periods
310.C.EX.W746 WVT - TTM Stage 1 (WA02) - North-Bound - Plumbing System for FS (was
C11_6C3)
d/w - 10h/d - With 30 2 16-Jan-23 22-Feb-23 23-Feb-23 29-Mar-23 30
HK Hols - No B/O periods
WVT - TTM Stage 2 (WA02) - Southbound (was
C11_6C3)
d/w - 10h/d - With HK Hols
70- No B/O16
periods (was
10-Jul-23
C3) 28-Sep-23 15-Aug-23 07-Nov-23 31
310.C.EX.X130 WVT - TTM Stage 2 (WA02) - South-Bound - Electrical Installation works C11_6 d/w - 10h/d - With 30 2 10-Jul-23 12-Aug-23 15-Aug-23 18-Sep-23 31
HK Hols - No B/O periods
310.C.EX.X154 WVT - TTM Stage 2 (WA02) - South-Bound - Drainage Installation (was
C11_6C3)
d/w - 10h/d - With 30 2 10-Jul-23 12-Aug-23 03-Oct-23 07-Nov-23 71
HK Hols - No B/O periods
310.C.EX.X134 WVT - TTM Stage 2 (WA02) - South-Bound - Tunnel Ventilation System Installation (was
C11_6C3)
d/w - 10h/d - With 30 2 21-Jul-23 24-Aug-23 26-Aug-23 29-Sep-23 31
HK Hols - No B/O periods
310.C.EX.X138 WVT - TTM Stage 2 (WA02) - South-Bound - Air Quality Monitoring System (was
C11_6C3)
d/w - 10h/d - With 30 2 02-Aug-23 05-Sep-23 07-Sep-23 13-Oct-23 31
HK Hols - No B/O periods
310.C.EX.X142 WVT - TTM Stage 2 (WA02) - South-Bound - Electrical and Control System (was
C11_6C3)
d/w - 10h/d - With 30 2 14-Aug-23 16-Sep-23 19-Sep-23 26-Oct-23 31
HK Hols - No B/O periods
(was C3)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 150 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.EX.X143 WVT - TTM Stage 2 (WA02) - South-Bound - Cabling Works C11_6 d/w - 10h/d - With 30 2 14-Aug-23 16-Sep-23 19-Sep-23 26-Oct-23 31
HK Hols - No B/O periods
310.C.EX.X146 WVT - TTM Stage 2 (WA02) - South-Bound - FS Installation (was
C11_6C3)
d/w - 10h/d - With 30 2 25-Aug-23 28-Sep-23 03-Oct-23 07-Nov-23 31
HK Hols - No B/O periods
310.C.EX.X150 WVT - TTM Stage 2 (WA02) - South-Bound - Plumbing System for FS (was
C11_6C3)
d/w - 10h/d - With 30 2 25-Aug-23 28-Sep-23 03-Oct-23 07-Nov-23 31
HK Hols - No B/O periods
WVT - MEP - Western Underpass (WU) (was
C11_6C3)
d/w - 10h/d - With HK Hols
265- No B/O32
periods (was
17-Jan-23
C3) 07-Dec-23 27-Jan-23 14-Dec-23 6
WVT - TTM Stage 1 (WU) - Northbound C11_6 d/w - 10h/d - With HK Hols
85- No B/O16
periods (was
17-Jan-23
C3) 04-May-23 27-Jan-23 25-May-23 18
310.C.EX.W754 WVT - TTM Stage 1 (WU) - North-Bound - Electrical Installation works C11_6 d/w - 10h/d - With 45 2 17-Jan-23 13-Mar-23 27-Jan-23 20-Mar-23 6
HK Hols - No B/O periods
310.C.EX.W778 WVT - TTM Stage 1 (WU) - North-Bound - Drainage Installation (was
C11_6C3)
d/w - 10h/d - With 45 2 17-Jan-23 13-Mar-23 29-Mar-23 25-May-23 58
HK Hols - No B/O periods
310.C.EX.W758 WVT - TTM Stage 1 (WU) - North-Bound - Tunnel Ventilation System Installation (was
C11_6C3)
d/w - 10h/d - With 45 2 01-Feb-23 24-Mar-23 08-Feb-23 31-Mar-23 6
HK Hols - No B/O periods
310.C.EX.W762 WVT - TTM Stage 1 (WU) - North-Bound - Air Quality Monitoring System (was
C11_6C3)
d/w - 10h/d - With 45 2 13-Feb-23 06-Apr-23 20-Feb-23 17-Apr-23 6
HK Hols - No B/O periods
310.C.EX.W766 WVT - TTM Stage 1 (WU) - North-Bound - Electrical and Control System (was
C11_6C3)
d/w - 10h/d - With 45 2 24-Feb-23 21-Apr-23 03-Mar-23 28-Apr-23 6
HK Hols - No B/O periods
310.C.EX.W768 WVT - TTM Stage 1 (WU) - North-Bound - Cabling Works (was
C11_6C3)
d/w - 10h/d - With 45 2 24-Feb-23 21-Apr-23 03-Mar-23 28-Apr-23 6
HK Hols - No B/O periods
310.C.EX.W770 WVT - TTM Stage 1 (WU) - North-Bound - FS Installation (was
C11_6C3)
d/w - 10h/d - With 45 2 08-Mar-23 04-May-23 15-Mar-23 11-May-23 6
HK Hols - No B/O periods
310.C.EX.W774 WVT - TTM Stage 1 (WU) - North-Bound - Plumbing System for FS (was
C11_6C3)
d/w - 10h/d - With 45 2 08-Mar-23 04-May-23 15-Mar-23 11-May-23 6
HK Hols - No B/O periods
WVT - TTM Stage 2 (WU) - Southbound (was
C11_6C3)
d/w - 10h/d - With HK Hols
85- No B/O16
periods (was
28-Aug-23
C3) 07-Dec-23 04-Sep-23 14-Dec-23 6
310.C.EX.X160 WVT - TTM Stage 2 (WU) - South-Bound - Electrical Installation works C11_6 d/w - 10h/d - With 45 2 28-Aug-23 20-Oct-23 04-Sep-23 28-Oct-23 6
HK Hols - No B/O periods
310.C.EX.X184 WVT - TTM Stage 2 (WU) - South-Bound - Drainage Installation (was
C11_6C3)
d/w - 10h/d - With 45 2 28-Aug-23 20-Oct-23 24-Oct-23 14-Dec-23 46
HK Hols - No B/O periods
310.C.EX.X164 WVT - TTM Stage 2 (WU) - South-Bound - Tunnel Ventilation System Installation (was
C11_6C3)
d/w - 10h/d - With 45 2 08-Sep-23 02-Nov-23 15-Sep-23 09-Nov-23 6
HK Hols - No B/O periods
310.C.EX.X168 WVT - TTM Stage 2 (WU) - South-Bound - Air Quality Monitoring System (was
C11_6C3)
d/w - 10h/d - With 45 2 20-Sep-23 14-Nov-23 27-Sep-23 21-Nov-23 6
HK Hols - No B/O periods
310.C.EX.X172 WVT - TTM Stage 2 (WU) - South-Bound - Electrical and Control System (was
C11_6C3)
d/w - 10h/d - With 45 2 04-Oct-23 25-Nov-23 11-Oct-23 02-Dec-23 6
HK Hols - No B/O periods
310.C.EX.X174 WVT - TTM Stage 2 (WU) - South-Bound - Cabling Works (was
C11_6C3)
d/w - 10h/d - With 45 2 04-Oct-23 25-Nov-23 11-Oct-23 02-Dec-23 6
HK Hols - No B/O periods
310.C.EX.X176 WVT - TTM Stage 2 (WU) - South-Bound - FS Installation (was
C11_6C3)
d/w - 10h/d - With 45 2 16-Oct-23 07-Dec-23 24-Oct-23 14-Dec-23 6
HK Hols - No B/O periods
310.C.EX.X180 WVT - TTM Stage 2 (WU) - South-Bound - Plumbing System for FS (was
C11_6C3)
d/w - 10h/d - With 45 2 16-Oct-23 07-Dec-23 24-Oct-23 14-Dec-23 6
HK Hols - No B/O periods
WVT - MEP - Western Roundabout (WA01) (was
C11_6C3)
d/w - 10h/d - With HK Hols
250- No B/O32
periods (was
27-Feb-23
C3) 29-Dec-23 04-Apr-23 02-Feb-24 29
WVT - TTM Stage 1 (WA01) - Northbound C11_6 d/w - 10h/d - With HK Hols
70- No B/O16
periods (was
27-Feb-23
C3) 24-May-23 04-Apr-23 03-Jul-23 31
310.C.EX.W858 WVT - TTM Stage 1 (WA01) - North-Bound - Electrical Installation works C11_6 d/w - 10h/d - With 30 2 27-Feb-23 01-Apr-23 04-Apr-23 13-May-23 31
HK Hols - No B/O periods
310.C.EX.W862 WVT - TTM Stage 1 (WA01) - North-Bound - Tunnel Ventilation System Installation (was
C11_6C3)
d/w - 10h/d - With 30 2 10-Mar-23 18-Apr-23 20-Apr-23 25-May-23 31
HK Hols - No B/O periods
310.C.EX.W882 WVT - TTM Stage 1 (WA01) - North-Bound - Drainage Installation (was
C11_6C3)
d/w - 10h/d - With 30 2 14-Mar-23 21-Apr-23 27-May-23 03-Jul-23 58
HK Hols - No B/O periods
310.C.EX.W866 WVT - TTM Stage 1 (WA01) - North-Bound - Air Quality Monitoring System (was
C11_6C3)
d/w - 10h/d - With 30 2 22-Mar-23 29-Apr-23 03-May-23 07-Jun-23 31
HK Hols - No B/O periods
(was C3)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 151 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.EX.W870 WVT - TTM Stage 1 (WA01) - North-Bound - Electrical and Control System C11_6 d/w - 10h/d - With 30 2 03-Apr-23 12-May-23 15-May-23 19-Jun-23 31
HK Hols - No B/O periods
310.C.EX.W872 WVT - TTM Stage 1 (WA01) - North-Bound - Cabling Works (was
C11_6C3)
d/w - 10h/d - With 30 2 03-Apr-23 12-May-23 15-May-23 19-Jun-23 31
HK Hols - No B/O periods
310.C.EX.W874 WVT - TTM Stage 1 (WA01) - North-Bound - FS Installation (was
C11_6C3)
d/w - 10h/d - With 30 2 19-Apr-23 24-May-23 27-May-23 03-Jul-23 31
HK Hols - No B/O periods
310.C.EX.W878 WVT - TTM Stage 1 (WA01) - North-Bound - Plumbing System for FS (was
C11_6C3)
d/w - 10h/d - With 30 2 19-Apr-23 24-May-23 27-May-23 03-Jul-23 31
HK Hols - No B/O periods
WVT - TTM Stage 2 (WA01) - Southbound (was
C11_6C3)
d/w - 10h/d - With HK Hols
70- No B/O16
periods (was
06-Oct-23
C3) 29-Dec-23 10-Nov-23 02-Feb-24 29
310.C.EX.X200 WVT - TTM Stage 2 (WA01) - South-Bound - Electrical Installation works C11_6 d/w - 10h/d - With 30 2 06-Oct-23 10-Nov-23 10-Nov-23 14-Dec-23 29
HK Hols - No B/O periods
310.C.EX.X224 WVT - TTM Stage 2 (WA01) - South-Bound - Drainage Installation (was
C11_6C3)
d/w - 10h/d - With 30 2 06-Oct-23 10-Nov-23 29-Dec-23 02-Feb-24 69
HK Hols - No B/O periods
310.C.EX.X204 WVT - TTM Stage 2 (WA01) - South-Bound - Tunnel Ventilation System Installation (was
C11_6C3)
d/w - 10h/d - With 30 2 18-Oct-23 22-Nov-23 22-Nov-23 28-Dec-23 29
HK Hols - No B/O periods
310.C.EX.X208 WVT - TTM Stage 2 (WA01) - South-Bound - Air Quality Monitoring System (was
C11_6C3)
d/w - 10h/d - With 30 2 31-Oct-23 04-Dec-23 04-Dec-23 10-Jan-24 29
HK Hols - No B/O periods
310.C.EX.X212 WVT - TTM Stage 2 (WA01) - South-Bound - Electrical and Control System (was
C11_6C3)
d/w - 10h/d - With 30 2 11-Nov-23 15-Dec-23 15-Dec-23 22-Jan-24 29
HK Hols - No B/O periods
310.C.EX.X214 WVT - TTM Stage 2 (WA01) - South-Bound - Cabling Works (was
C11_6C3)
d/w - 10h/d - With 30 2 11-Nov-23 15-Dec-23 15-Dec-23 22-Jan-24 29
HK Hols - No B/O periods
310.C.EX.X216 WVT - TTM Stage 2 (WA01) - South-Bound - FS Installation (was
C11_6C3)
d/w - 10h/d - With 30 2 23-Nov-23 29-Dec-23 29-Dec-23 02-Feb-24 29
HK Hols - No B/O periods
310.C.EX.X220 WVT - TTM Stage 2 (WA01) - South-Bound - Plumbing System for FS (was
C11_6C3)
d/w - 10h/d - With 30 2 23-Nov-23 29-Dec-23 29-Dec-23 02-Feb-24 29
HK Hols - No B/O periods
WVT - MEP - Western Underpass Ramp (WUR) (was
C11_6C3)
d/w - 10h/d - With HK Hols
265- No B/O32
periods (was
06-Apr-23
C3) 26-Feb-24 28-Apr-23 11-Mar-24 12
WVT - TTM Stage 1 (WUR) - Northbound C11_6 d/w - 10h/d - With HK Hols
85- No B/O16
periods (was
06-Apr-23
C3) 21-Jul-23 28-Apr-23 09-Aug-23 16
310.C.EX.W698 WVT - TTM Stage 1 (WUR) - North-Bound - Electrical Installation works C11_6 d/w - 10h/d - With 45 2 06-Apr-23 02-Jun-23 28-Apr-23 21-Jun-23 16
HK Hols - No B/O periods
310.C.EX.W722 WVT - TTM Stage 1 (WUR) - North-Bound - Drainage Installation (was
C11_6C3)
d/w - 10h/d - With 45 2 06-Apr-23 02-Jun-23 16-Jun-23 09-Aug-23 56
HK Hols - No B/O periods
310.C.EX.W702 WVT - TTM Stage 1 (WUR) - North-Bound - Tunnel Ventilation System Installation (was
C11_6C3)
d/w - 10h/d - With 45 2 21-Apr-23 14-Jun-23 11-May-23 05-Jul-23 16
HK Hols - No B/O periods
310.C.EX.W706 WVT - TTM Stage 1 (WUR) - North-Bound - Air Quality Monitoring System (was
C11_6C3)
d/w - 10h/d - With 45 2 04-May-23 27-Jun-23 23-May-23 17-Jul-23 16
HK Hols - No B/O periods
310.C.EX.W710 WVT - TTM Stage 1 (WUR) - North-Bound - Electrical and Control System (was
C11_6C3)
d/w - 10h/d - With 45 2 16-May-23 10-Jul-23 05-Jun-23 28-Jul-23 16
HK Hols - No B/O periods
310.C.EX.W712 WVT - TTM Stage 1 (WUR) - North-Bound - Cabling Works (was
C11_6C3)
d/w - 10h/d - With 45 2 16-May-23 10-Jul-23 05-Jun-23 28-Jul-23 16
HK Hols - No B/O periods
310.C.EX.W714 WVT - TTM Stage 1 (WUR) - North-Bound - FS Installation (was
C11_6C3)
d/w - 10h/d - With 45 2 29-May-23 21-Jul-23 16-Jun-23 09-Aug-23 16
HK Hols - No B/O periods
310.C.EX.W718 WVT - TTM Stage 1 (WUR) - North-Bound - Plumbing System for FS (was
C11_6C3)
d/w - 10h/d - With 45 2 29-May-23 21-Jul-23 16-Jun-23 09-Aug-23 16
HK Hols - No B/O periods
WVT - TTM Stage 2 (WUR) - Southbound (was
C11_6C3)
d/w - 10h/d - With HK Hols
85- No B/O16
periods (was
14-Nov-23
C3) 26-Feb-24 28-Nov-23 11-Mar-24 12
310.C.EX.X230 WVT - TTM Stage 2 (WUR) - South-Bound - Electrical Installation works C11_6 d/w - 10h/d - With 45 2 14-Nov-23 08-Jan-24 28-Nov-23 22-Jan-24 12
HK Hols - No B/O periods
310.C.EX.X254 WVT - TTM Stage 2 (WUR) - South-Bound - Drainage Installation (was
C11_6C3)
d/w - 10h/d - With 45 2 14-Nov-23 08-Jan-24 17-Jan-24 11-Mar-24 52
HK Hols - No B/O periods
310.C.EX.X234 WVT - TTM Stage 2 (WUR) - South-Bound - Tunnel Ventilation System Installation (was
C11_6C3)
d/w - 10h/d - With 45 2 25-Nov-23 19-Jan-24 09-Dec-23 02-Feb-24 12
HK Hols - No B/O periods
(was C3)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 152 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.EX.X238 WVT - TTM Stage 2 (WUR) - South-Bound - Air Quality Monitoring System C11_6 d/w - 10h/d - With 45 2 07-Dec-23 31-Jan-24 21-Dec-23 16-Feb-24 12
HK Hols - No B/O periods
310.C.EX.X242 WVT - TTM Stage 2 (WUR) - South-Bound - Electrical and Control System (was
C11_6C3)
d/w - 10h/d - With 45 2 19-Dec-23 14-Feb-24 05-Jan-24 28-Feb-24 12
HK Hols - No B/O periods
310.C.EX.X244 WVT - TTM Stage 2 (WUR) - South-Bound - Cabling Works (was
C11_6C3)
d/w - 10h/d - With 45 2 19-Dec-23 14-Feb-24 05-Jan-24 28-Feb-24 12
HK Hols - No B/O periods
310.C.EX.X246 WVT - TTM Stage 2 (WUR) - South-Bound - FS Installation (was
C11_6C3)
d/w - 10h/d - With 45 2 03-Jan-24 26-Feb-24 17-Jan-24 11-Mar-24 12
HK Hols - No B/O periods
310.C.EX.X250 WVT - TTM Stage 2 (WUR) - South-Bound - Plumbing System for FS (was
C11_6C3)
d/w - 10h/d - With 45 2 03-Jan-24 26-Feb-24 17-Jan-24 11-Mar-24 12
HK Hols - No B/O periods
WVT - MEP - Western Vehicular Tunnel (WT) (was
C11_6C3)
d/w - 10h/d - With HK Hols
112- No B/O14
periods (was
14-Nov-23
C3) 28-Mar-24 09-Dec-23 29-Apr-24 23
310.C.EX.W782 WVT (WT) - Electrical Installation works C11_6 d/w - 10h/d - With 58 14-Nov-23 23-Jan-24 09-Dec-23 20-Feb-24 22
HK Hols - No B/O periods
310.C.EX.W786 WVT (WT) - Tunnel Ventilation System Installation (was
C11_6C3)
d/w - 10h/d - With 60 2 22-Nov-23 02-Feb-24 18-Dec-23 01-Mar-24 22
HK Hols - No B/O periods
310.C.EX.W790 WVT (WT) - Air Quality Monitoring System (was
C11_6C3)
d/w - 10h/d - With 60 2 30-Nov-23 10-Feb-24 28-Dec-23 09-Mar-24 22
HK Hols - No B/O periods
310.C.EX.W806 WVT (WT) - Drainage Installation (was
C11_6C3)
d/w - 10h/d - With 60 2 04-Dec-23 16-Feb-24 03-Feb-24 19-Apr-24 50
HK Hols - No B/O periods
310.C.EX.W794 WVT (WT) - Electrical and Control System (was
C11_6C3)
d/w - 10h/d - With 60 2 12-Dec-23 24-Feb-24 10-Jan-24 21-Mar-24 22
HK Hols - No B/O periods
310.C.EX.W796 WVT (WT) - Cabling Works (was
C11_6C3)
d/w - 10h/d - With 60 2 12-Dec-23 24-Feb-24 03-Feb-24 19-Apr-24 43
HK Hols - No B/O periods
310.C.EX.W798 WVT (WT) - FS Installation (was
C11_6C3)
d/w - 10h/d - With 60 2 21-Dec-23 05-Mar-24 15-Feb-24 29-Apr-24 43
HK Hols - No B/O periods
310.C.EX.W802 WVT (WT) - Plumbing System for FS (was
C11_6C3)
d/w - 10h/d - With 60 2 17-Jan-24 28-Mar-24 26-Jan-24 11-Apr-24 8
HK Hols - No B/O periods
CC#07 - Tunnel Plant Building B - PBB (was C3) 210 10 12-May-22 19-Jan-23 24-May-22 06-Feb-23 12
CC#07 - PBB - Procurement C01_7 d/w - 10h/d - No HK Hols118
- No B/O periods
0 (was12-May-22
C1) 06-Sep-22 24-May-22 07-Sep-22 1
Major Materials MEP C01_7 d/w - 10h/d - No HK Hols118
- No B/O periods
0 (was12-May-22
C1) 06-Sep-22 24-May-22 07-Sep-22 1
310.P.RC.S118 PBB (Procurement Electrical & MVAC Major Equipment and Others)-Place Order for C01_7 d/w - 10h/d - No HK 60 12-May-22 10-Jul-22 03-Jun-22 01-Aug-22 22
Materials Hols - No B/O periods (was
310.P.RC.S134 PBB (Procurement Electrical & MVAC Major Equipment and Others)-Manufacturing of C1)
C01_7 d/w - 10h/d - No HK 90 19-May-22 16-Aug-22 10-Jun-22 07-Sep-22 22
Materials Hols - No B/O periods (was
310.P.RC.S114 PBB (Procurement FS and P&D Major Equipment) - Place Order for Materials C1)
C01_7 d/w - 10h/d - No HK 100 23-May-22 30-Aug-22 24-May-22 31-Aug-22 1
Hols - No B/O periods (was
310.P.RC.S130 PBB (Procurement FS and P&D Major Equipment) - Manufacturing of Materials C1)
C01_7 d/w - 10h/d - No HK 100 30-May-22 06-Sep-22 31-May-22 07-Sep-22 1
Hols - No B/O periods (was
310.P.RC.S138 PBB (Procurement) - Delivery of Materials C1)
C01_7 d/w - 10h/d - No HK 7 31-Aug-22 06-Sep-22 01-Sep-22 07-Sep-22 1
Hols - No B/O periods (was
Major Materials ABWF C1)
C01_7 d/w - 10h/d - No HK Hols96
- No B/O periods
0 (was31-May-22
C1) 03-Sep-22 02-Jun-22 05-Sep-22 2
310.P.RC.S122 PBB (Procurement ABWF) - Place Order for Materials C01_7 d/w - 10h/d - No HK 4 31-May-22 03-Jun-22 02-Jun-22 05-Jun-22 2
Hols - No B/O periods (was
310.P.RC.S190 PBB (Procurement ABWF) - Manufacturing of Materials C1)
C01_7 d/w - 10h/d - No HK 90 04-Jun-22 01-Sep-22 06-Jun-22 03-Sep-22 2
Hols - No B/O periods (was
310.P.RC.S198 PBB (Procurement ABWF) - Delivery of Materials C1)
C01_7 d/w - 10h/d - No HK 7 28-Aug-22 03-Sep-22 30-Aug-22 05-Sep-22 2
Hols - No B/O periods (was
CC#07 - PBB - Preparation and Initial Works C1) 51 1 08-Jul-22 06-Sep-22 08-Jul-22 06-Sep-22 0
310.C.WS.P014 PBB - Handover inspection and acceptance FROM Contract <3303> C01_7 d/w - 10h/d - No HK 60 1 08-Jul-22 05-Sep-22 08-Jul-22 05-Sep-22 0
Hols - No B/O periods (was
C1)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 153 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.WS.P016 PBB - Access to Tunnel Plant Building B FROM Contract <3303> C01_7 d/w - 10h/d - No HK 0 05-Sep-22* 05-Sep-22 0
Hols - No B/O periods (was
310.C.WS.P018 PBB - Commence ABWF, MEP Works C1)
C11_6 d/w - 10h/d - With 0 06-Sep-22 06-Sep-22 0
HK Hols - No B/O periods
CC#07 - PBB - ABWF (was
C11_6C3)
d/w - 10h/d - With HK Hols
49- No B/O 0periods (was
06-Sep-22
C3) 04-Nov-22 09-Sep-22 10-Nov-22 5
310.C.EX.W1308 PBB Sanitary Ware & Fixtures C11_6 d/w - 10h/d - With 33 06-Sep-22 17-Oct-22 09-Sep-22 20-Oct-22 3
HK Hols - No B/O periods
310.C.EX.W1292 PBB Partition Wall & Door Subframe (was
C11_6C3)
d/w - 10h/d - With 45 06-Sep-22 31-Oct-22 09-Sep-22 03-Nov-22 3
HK Hols - No B/O periods
310.C.EX.W1296 PBB Plastering & Screeding (was
C11_6C3)
d/w - 10h/d - With 45 06-Sep-22 31-Oct-22 09-Sep-22 03-Nov-22 3
HK Hols - No B/O periods
310.C.EX.W1300 PBB Tiling & Stonework (was
C11_6C3)
d/w - 10h/d - With 45 06-Sep-22 31-Oct-22 09-Sep-22 03-Nov-22 3
HK Hols - No B/O periods
310.C.EX.W1304 PBB Suspended Ceiling Framework (was
C11_6C3)
d/w - 10h/d - With 45 06-Sep-22 31-Oct-22 09-Sep-22 03-Nov-22 3
HK Hols - No B/O periods
310.C.EX.W1312 PBB Door Sets & Ironmongery (was
C11_6C3)
d/w - 10h/d - With 45 06-Sep-22 31-Oct-22 13-Sep-22 05-Nov-22 5
HK Hols - No B/O periods
310.C.EX.W1316 PBB Glazing (was
C11_6C3)
d/w - 10h/d - With 45 06-Sep-22 31-Oct-22 13-Sep-22 05-Nov-22 5
HK Hols - No B/O periods
310.C.EX.W1320 PBB Ceiling Panels & Finishes (was
C11_6C3)
d/w - 10h/d - With 45 06-Sep-22 31-Oct-22 13-Sep-22 05-Nov-22 5
HK Hols - No B/O periods
310.C.EX.W1324 PBB Painting, Graphics & Signage (was
C11_6C3)
d/w - 10h/d - With 42 15-Sep-22 04-Nov-22 21-Sep-22 10-Nov-22 5
HK Hols - No B/O periods
CC#07 - PBB - MEP Installation Works (was
C11_6C3)
d/w - 10h/d - With HK Hols
112- No B/O 7periods (was
06-Sep-22
C3) 19-Jan-23 06-Sep-22 06-Feb-23 12
CC#07 - PBB - Transformers (CLP) C11_6 d/w - 10h/d - With HK Hols
48- No B/O 3periods (was
06-Sep-22
C3) 03-Nov-22 06-Sep-22 03-Nov-22 0
310.C.EX.W1328 PBB Complete Transformer Room Structure C11_6 d/w - 10h/d - With 0 06-Sep-22 06-Sep-22 0
HK Hols - No B/O periods
310.C.EX.W1252 PBB Builder Works in Transformer Room (was
C11_6C3)
d/w - 10h/d - With 12 06-Sep-22 20-Sep-22 06-Sep-22 20-Sep-22 0
HK Hols - No B/O periods
310.C.EX.W1253 PBB MEP Works in Transformer Room (was
C11_6C3)
d/w - 10h/d - With 12 09-Sep-22 23-Sep-22 09-Sep-22 23-Sep-22 0
HK Hols - No B/O periods
310.C.EX.W1256 PBB Inspection & Handover Transformer Room to CLP (was
C11_6C3)
d/w - 10h/d - With 3 24-Sep-22 27-Sep-22 24-Sep-22 27-Sep-22 0
HK Hols - No B/O periods
310.C.EX.W1260 PBB Transformer Installation by CLP (was
C11_6C3)
d/w - 10h/d - With 30 28-Sep-22 03-Nov-22 28-Sep-22 03-Nov-22 0
HK Hols - No B/O periods
310.C.EX.W1332 PBB Cable Laying by CLP (was
C11_6C3)
d/w - 10h/d - With 30 3 28-Sep-22 03-Nov-22 28-Sep-22 03-Nov-22 0
HK Hols - No B/O periods
310.C.EX.W1264 PBB Energization of Transformers (was
C11_6C3)
d/w - 10h/d - With 0 03-Nov-22 03-Nov-22 0
HK Hols - No B/O periods
CC#07 - PBB - Plumbing & Drainage Installation (was
C11_6C3)
d/w - 10h/d - With HK Hols
23- No B/O 0periods (was
09-Sep-22
C3) 08-Oct-22 15-Sep-22 13-Oct-22 4
310.C.EX.W1268 PBB Plumbing & Drainage 1st Fix & Installation C11_6 d/w - 10h/d - With 10 09-Sep-22 21-Sep-22 15-Sep-22 26-Sep-22 4
HK Hols - No B/O periods
310.C.EX.W1276 PBB Water Pump Installation (was
C11_6C3)
d/w - 10h/d - With 15 09-Sep-22 27-Sep-22 16-Sep-22 05-Oct-22 5
HK Hols - No B/O periods
310.C.EX.W1272 PBB Plumbing & Drainage 2nd Fix & Installation (was
C11_6C3)
d/w - 10h/d - With 15 14-Sep-22 30-Sep-22 19-Sep-22 07-Oct-22 4
HK Hols - No B/O periods
310.C.EX.W1288 PBB Plumbing & Drainage Final Fix & Adjustment (was
C11_6C3)
d/w - 10h/d - With 7 29-Sep-22 08-Oct-22 06-Oct-22 13-Oct-22 4
HK Hols - No B/O periods
CC#07 - PBB - Electrical Installation (was
C11_6C3)
d/w - 10h/d - With HK Hols
43- No B/O 0periods (was
09-Sep-22
C3) 01-Nov-22 13-Sep-22 03-Nov-22 2
310.C.EX.W1176 PBB Electrical 1st Fix & Installation C11_6 d/w - 10h/d - With 20 09-Sep-22 05-Oct-22 13-Sep-22 07-Oct-22 2
HK Hols - No B/O periods
(was C3)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 154 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.EX.W1184 PBB Switchgear Installation C11_6 d/w - 10h/d - With 20 15-Sep-22 10-Oct-22 17-Sep-22 12-Oct-22 2
HK Hols - No B/O periods
310.C.EX.W1188 PBB Emergency Genset Installation (was
C11_6C3)
d/w - 10h/d - With 14 20-Sep-22 07-Oct-22 22-Sep-22 10-Oct-22 2
HK Hols - No B/O periods
310.C.EX.W1180 PBB Electrical 2nd Fix & Installation (was
C11_6C3)
d/w - 10h/d - With 14 06-Oct-22 21-Oct-22 08-Oct-22 24-Oct-22 2
HK Hols - No B/O periods
310.C.EX.W1192 PBB Provide Temporary Power for Power On to All Floors (was
C11_6C3)
d/w - 10h/d - With 0 10-Oct-22 12-Oct-22 2
HK Hols - No B/O periods
310.C.EX.W1204 PBB Electrical Final Fix & Adjustment (was
C11_6C3)
d/w - 10h/d - With 7 25-Oct-22 01-Nov-22 27-Oct-22 03-Nov-22 2
HK Hols - No B/O periods
CC#07 - PBB - Fire Services Installation (was
C11_6C3)
d/w - 10h/d - With HK Hols
39- No B/O 0periods (was
08-Sep-22
C3) 26-Oct-22 09-Sep-22 27-Oct-22 1
310.C.EX.W1208 PBB Fire Services 1st Fix & Installation C11_6 d/w - 10h/d - With 18 08-Sep-22 29-Sep-22 09-Sep-22 30-Sep-22 1
HK Hols - No B/O periods
310.C.EX.W1212 PBB Fire Services 2nd Fix & Installation (was
C11_6C3)
d/w - 10h/d - With 18 13-Sep-22 05-Oct-22 16-Sep-22 08-Oct-22 3
HK Hols - No B/O periods
310.C.EX.W1216 PBB FS Pump Installation (was
C11_6C3)
d/w - 10h/d - With 10 17-Sep-22 28-Sep-22 20-Sep-22 30-Sep-22 2
HK Hols - No B/O periods
310.C.EX.W1228 PBB Fire Services Final Fix & Adjustment (was
C11_6C3)
d/w - 10h/d - With 7 19-Oct-22 26-Oct-22 20-Oct-22 27-Oct-22 1
HK Hols - No B/O periods
CC#07 - PBB - MVAC Installation (was
C11_6C3)
d/w - 10h/d - With HK Hols
38- No B/O 0periods (was
09-Sep-22
C3) 26-Oct-22 12-Sep-22 27-Oct-22 1
310.C.EX.W1232 PBB MVAC 1st Fix & Installation C11_6 d/w - 10h/d - With 15 09-Sep-22 27-Sep-22 12-Sep-22 28-Sep-22 1
HK Hols - No B/O periods
310.C.EX.W1236 PBB MVAC 2nd Fix & Installation (was
C11_6C3)
d/w - 10h/d - With 15 20-Sep-22 08-Oct-22 23-Sep-22 12-Oct-22 3
HK Hols - No B/O periods
310.C.EX.W1248 PBB MVAC Final Fix & Adjustment (was
C11_6C3)
d/w - 10h/d - With 7 19-Oct-22 26-Oct-22 20-Oct-22 27-Oct-22 1
HK Hols - No B/O periods
CC#07 - PBB - Comms Room and Associated Rooms (was
C11_6C3)
d/w - 10h/d - With HK Hols
112- No B/O 4periods (was
06-Sep-22
C3) 19-Jan-23 21-Sep-22 06-Feb-23 12
310.C.ES.P516 ABWF (Comms Room) - Commence ABWF works C11_6 d/w - 10h/d - With 0 06-Sep-22 21-Sep-22 12
HK Hols - No B/O periods
310.C.ES.P508 PBB (Comms Room 1st Degree - 3rd Degree) - ABWF Works (floor screed, partition (was
C11_6C3)
d/w - 10h/d - With 40 1 06-Sep-22 25-Oct-22 21-Sep-22 08-Nov-22 12
walls, installed conduits) HK Hols - No B/O periods
310.C.ES.P512 PBB (Novec 1234 Comms Room 1st Degree - 3rd Degree) - ABWF works Comms Rooms (was
C11_6C3)
d/w - 10h/d - With 107 1 13-Sep-22 19-Jan-23 27-Sep-22 06-Feb-23 12
(wall, floors, ceiling, doors) HK Hols - No B/O periods
310.C.ES.P520 PBB (Comms Room) - Commence Building Services works (was
C11_6C3)
d/w - 10h/d - With 0 19-Sep-22 05-Oct-22 12
HK Hols - No B/O periods
310.C.ES.P524 PBB (Comms Room 1st Fix - Final Fix) -Building Services Installations (was
C11_6C3)
d/w - 10h/d - With 20 2 19-Sep-22 13-Oct-22 05-Oct-22 27-Oct-22 12
HK Hols - No B/O periods
CC#07 - PBB - External Works (was
C11_6C3)
d/w - 10h/d - With HK Hols
48- No B/O 2periods (was
06-Sep-22
C3) 03-Nov-22 08-Sep-22 18-Nov-22 13
CC#07 - PBB - External Building Finishes C11_6 d/w - 10h/d - With HK Hols
48- No B/O 0periods (was
06-Sep-22
C3) 03-Nov-22 08-Sep-22 18-Nov-22 13
310.C.ES.P556 PBB External building finishes C11_6 d/w - 10h/d - With 35 06-Sep-22 19-Oct-22 08-Sep-22 21-Oct-22 2
HK Hols - No B/O periods
310.C.ES.P564.B01 PBB Roof Waterproofing and roof finishes (was
C11_6C3)
d/w - 10h/d - With 35 06-Sep-22 19-Oct-22 10-Oct-22 18-Nov-22 26
HK Hols - No B/O periods
310.C.ES.P548 PBB Hard and soft landscape works (was
C11_6C3)
d/w - 10h/d - With 21 11-Oct-22 03-Nov-22 26-Oct-22 18-Nov-22 13
HK Hols - No B/O periods
CC#07 - PBB - Drainage and UU (was
C11_6C3)
d/w - 10h/d - With HK Hols
46- No B/O 2periods (was
07-Sep-22
C3) 02-Nov-22 08-Sep-22 03-Nov-22 1
310.C.ES.P536 PBB Building drainage and watermain works C11_6 d/w - 10h/d - With 18 07-Sep-22 28-Sep-22 08-Sep-22 29-Sep-22 1
HK Hols - No B/O periods
310.C.ES.P540 PBB AS Cable ducts + drawpits (was
C11_6C3)
d/w - 10h/d - With 18 17-Sep-22 10-Oct-22 19-Sep-22 11-Oct-22 1
HK Hols - No B/O periods
(was C3)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 155 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.ES.P544 PBB EL cable ducts + drawpits C11_6 d/w - 10h/d - With 18 17-Sep-22 10-Oct-22 19-Sep-22 11-Oct-22 1
HK Hols - No B/O periods
310.C.ES.P560 PBB CLP Cable ducts + drawpits (was
C11_6C3)
d/w - 10h/d - With 18 17-Sep-22 10-Oct-22 19-Sep-22 11-Oct-22 1
HK Hols - No B/O periods
310.C.ES.P831.B01 PBB Cabling Works (was
C11_6C3)
d/w - 10h/d - With 20 2 11-Oct-22 02-Nov-22 12-Oct-22 03-Nov-22 1
HK Hols - No B/O periods
CC#07 - PBB -- EVA Construction (was
C11_6C3)
d/w - 10h/d - With HK Hols8 - No B/O 0periods (was
25-Oct-22
C3) 02-Nov-22 26-Oct-22 03-Nov-22 1
310.C.EX.L290 PBB Site Formation Works and Road Works for EVA C11_6 d/w - 10h/d - With 8 25-Oct-22 02-Nov-22 26-Oct-22 03-Nov-22 1
HK Hols - No B/O periods
CC#07 ----- Testing and Commissioning ----- (was C3) 646 4 23-May-22 23-Jul-24 24-Jun-22 28-Jul-24 4
CC#07 - WVT - Testing and Commissioning 621 0 22-Jun-22 23-Jul-24 21-Sep-22 28-Jul-24 4
CC#07 - WVT - Testing and Commissioning C01_7 d/w - 10h/d - No HK Hols109
- No B/O periods
0 (was25-Feb-24
C1) 12-Jun-24 22-Mar-24 26-Jul-24 44
310.T.EX.L148 WVT (T&C) - Ventilation System Test C01_7 d/w - 10h/d - No HK 35 25-Feb-24 30-Mar-24 22-Mar-24 25-Apr-24 26
Hols - No B/O periods (was
310.T.EX.L140 WVT (T&C) - Plumbing System Test C1)
C01_7 d/w - 10h/d - No HK 24 29-Mar-24 21-Apr-24 12-Apr-24 05-May-24 14
Hols - No B/O periods (was
310.T.EX.L144 WVT (T&C) - FS System Test C1)
C01_7 d/w - 10h/d - No HK 28 29-Mar-24 25-Apr-24 30-Apr-24 27-May-24 32
Hols - No B/O periods (was
310.T.EX.L156 WVT (T&C) - Systems Integration Test C1)
C01_7 d/w - 10h/d - No HK 48 26-Apr-24 12-Jun-24 09-Jun-24 26-Jul-24 44
Hols - No B/O periods (was
CC#07 - WVT - Statutory Inspection C1) 621 0 22-Jun-22 23-Jul-24 21-Sep-22 28-Jul-24 4
Water Supply Department (WSD) C11_6 d/w - 10h/d - With HK Hols
563- No B/O 0periods (was
22-Jun-22
C3) 13-May-24 21-Sep-22 27-May-24 11
310.T.WS.T100 WVT Prepare for Plumbing Material for Submission C11_6 d/w - 10h/d - With 17 22-Jun-22 12-Jul-22 21-Sep-22 12-Oct-22 76
HK Hols - No B/O periods
310.T.WS.T105 WVT Submit all Plumbing Material for PM Acceptance (was
C11_6C3)
d/w - 10h/d - With 0 13-Jul-22 13-Oct-22 76
HK Hols - No B/O periods
310.T.WS.T110 WVT PM Acceptance (was
C11_6C3)
d/w - 10h/d - With 48 13-Jul-22 06-Sep-22 13-Oct-22 07-Dec-22 76
HK Hols - No B/O periods
310.T.WS.T115 WVT Form WWO 46 (Part I & Part II) & Annex Submission for WSD Approval (Plumbing / (was
C11_6C3)
d/w - 10h/d - With 0 07-Sep-22 08-Dec-22 76
FS / WP) HK Hols - No B/O periods
310.T.WS.T120 WVT Obtain Form WWO 46 (Part III) - WSD Approval, Endorsed & Return to Licensed (was
C11_6C3)
d/w - 10h/d - With 4 07-Sep-22 12-Sep-22 08-Dec-22 12-Dec-22 76
Plumber HK Hols - No B/O periods
310.T.WS.T125 WVT Form WWO 46 (Part IV) Submission for WSD Inspection (Plumbing / FS / WP) (was
C11_6C3)
d/w - 10h/d - With 0 22-Apr-24 06-May-24 11
HK Hols - No B/O periods
310.T.WS.T130 WVT WSD Inspection for Water Supply System (was
C11_6C3)
d/w - 10h/d - With 12 22-Apr-24 06-May-24 06-May-24 20-May-24 11
HK Hols - No B/O periods
310.T.WS.T135 WVT Obtain Form WWO 46 (Part V) (was
C11_6C3)
d/w - 10h/d - With 0 06-May-24 20-May-24 11
HK Hols - No B/O periods
310.T.WS.T140 WVT Form WWO 132 (Part II) Submission for Water Supply Connection (was
C11_6C3)
d/w - 10h/d - With 0 06-May-24 20-May-24 11
HK Hols - No B/O periods
310.T.WS.T145 WVT Final Water Supply Connection (was
C11_6C3)
d/w - 10h/d - With 6 07-May-24 13-May-24 21-May-24 27-May-24 11
HK Hols - No B/O periods
310.T.WS.T150 WVT Obtain Water Certificate (Form WWO 1005) (was
C11_6C3)
d/w - 10h/d - With 0 13-May-24 27-May-24 11
HK Hols - No B/O periods
Fire Services Department (FSD) (was
C11_6C3)
d/w - 10h/d - With HK Hols
194- No B/O 0periods (was
04-Nov-23
C3) 02-Jul-24 10-Nov-23 05-Jul-24 3
310.T.WS.T155 WVT F.S. Inspection Plan (Form FSI / 314 Submission) (VAC System) C11_6 d/w - 10h/d - With 0 04-Nov-23 10-Nov-23 5
HK Hols - No B/O periods
310.T.WS.T160 WVT F.S. Inspection Application (Form FSI / 501 & 251 Submission) (was
C11_6C3)
d/w - 10h/d - With 0 24-May-24 28-May-24 3
HK Hols - No B/O periods
310.T.WS.T165 WVT F.S. 1st Inspection (was
C11_6C3)
d/w - 10h/d - With 8 05-Jun-24 14-Jun-24 08-Jun-24 18-Jun-24 3
HK Hols - No B/O periods
(was C3)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 156 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.T.WS.T170 WVT FSD Comment C11_6 d/w - 10h/d - With 0 14-Jun-24 18-Jun-24 3
HK Hols - No B/O periods
310.T.WS.T175 WVT Rectification & Adjustment (was
C11_6C3)
d/w - 10h/d - With 6 15-Jun-24 21-Jun-24 19-Jun-24 25-Jun-24 3
HK Hols - No B/O periods
310.T.WS.T180 WVT F.S. Re-inspection (was
C11_6C3)
d/w - 10h/d - With 8 22-Jun-24 02-Jul-24 26-Jun-24 05-Jul-24 3
HK Hols - No B/O periods
310.T.WS.T185 WVT Issue F.S. Certificate (Form FS172) (was
C11_6C3)
d/w - 10h/d - With 0 02-Jul-24 05-Jul-24 3
HK Hols - No B/O periods
Building Department (BD) (was C3) 18 0 03-Jul-24 23-Jul-24 06-Jul-24 28-Jul-24 4
310.T.WS.T190 WVT BD Inspection Application for Occupation Permit (Form BA13 Submission) C11_6 d/w - 10h/d - With 0 03-Jul-24 06-Jul-24 3
HK Hols - No B/O periods
310.T.WS.T195 WVT BD 1st Inspection (was
C11_6C3)
d/w - 10h/d - With 6 03-Jul-24 09-Jul-24 06-Jul-24 12-Jul-24 3
HK Hols - No B/O periods
310.T.WS.T200 WVT BD Comment (was
C11_6C3)
d/w - 10h/d - With 0 09-Jul-24 12-Jul-24 3
HK Hols - No B/O periods
310.T.WS.T205 WVT Rectification & Adjustment (was
C11_6C3)
d/w - 10h/d - With 6 10-Jul-24 16-Jul-24 13-Jul-24 19-Jul-24 3
HK Hols - No B/O periods
310.T.WS.T210 WVT BD Re-inspection (was
C11_6C3)
d/w - 10h/d - With 6 17-Jul-24 23-Jul-24 20-Jul-24 26-Jul-24 3
HK Hols - No B/O periods
310.T.EX.L184 WVT - Achieve KD-11 (was
C01_7C3)
d/w - 10h/d - No HK 0 23-Jul-24 28-Jul-24 5
Hols - No B/O periods (was
310.T.WS.T215 WVT Issue Occupation Permit (Form BD104) C1)
C11_6 d/w - 10h/d - With 0 23-Jul-24 26-Jul-24 3
HK Hols - No B/O periods
CC#07 - PBB -Testing and Commissioning (was C3) 163 4 23-May-22 04-Dec-22 24-Jun-22 04-Dec-22 0
Preliminary Testing & Commissioning C11_6 d/w - 10h/d - With HK Hols
36- No B/O 0periods (was
17-Sep-22
C3) 31-Oct-22 22-Sep-22 18-Nov-22 16
Preliminary T&C - Plumbing and Drainage C11_6 d/w - 10h/d - With HK Hols
24- No B/O 0periods (was
17-Sep-22
C3) 17-Oct-22 22-Sep-22 21-Oct-22 4
310.C.EX.W1284 PBB Plumbing & Drainage Preliminary Testing & Commissioning C11_6 d/w - 10h/d - With 10 17-Sep-22 28-Sep-22 22-Sep-22 05-Oct-22 4
HK Hols - No B/O periods
310.C.EX.W1280 PBB Plumbing & Drainage Preliminary Inspection & Adjustment (was
C11_6C3)
d/w - 10h/d - With 14 29-Sep-22 17-Oct-22 06-Oct-22 21-Oct-22 4
HK Hols - No B/O periods
Preliminary T&C - Electrical (was
C11_6C3)
d/w - 10h/d - With HK Hols
20- No B/O 0periods (was
08-Oct-22
C3) 31-Oct-22 11-Oct-22 18-Nov-22 16
310.C.EX.W1200 PBB Electrical Preliminary Testing & Commissioning C11_6 d/w - 10h/d - With 14 08-Oct-22 24-Oct-22 11-Oct-22 26-Oct-22 2
HK Hols - No B/O periods
310.C.EX.W1196 PBB Electrical Preliminary Inspection & Adjustment (was
C11_6C3)
d/w - 10h/d - With 10 11-Oct-22 21-Oct-22 13-Oct-22 24-Oct-22 2
HK Hols - No B/O periods
310.C.EX.W1198.B02 PBB Electrical Preliminary Inspection & Adjustment (Non-FSI) (was
C11_6C3)
d/w - 10h/d - With 10 13-Oct-22 24-Oct-22 01-Nov-22 11-Nov-22 16
HK Hols - No B/O periods
310.C.EX.W1205.B02 PBB Electrical Preliminary Testing & Commissioning (Non-FSI) (was
C11_6C3)
d/w - 10h/d - With 14 15-Oct-22 31-Oct-22 03-Nov-22 18-Nov-22 16
HK Hols - No B/O periods
Preliminary T&C - Fire Service (was
C11_6C3)
d/w - 10h/d - With HK Hols
17- No B/O 0periods (was
30-Sep-22
C3) 21-Oct-22 03-Oct-22 11-Nov-22 18
310.C.EX.W1220 PBB Fire Services Preliminary Inspection & Adjustment (FSI) C11_6 d/w - 10h/d - With 10 30-Sep-22 13-Oct-22 03-Oct-22 14-Oct-22 1
HK Hols - No B/O periods
310.C.EX.W1224 PBB Fire Services Preliminary Testing & Commissioning (FSI) (was
C11_6C3)
d/w - 10h/d - With 14 30-Sep-22 18-Oct-22 03-Oct-22 19-Oct-22 1
HK Hols - No B/O periods
310.C.EX.W1576.B01 PBB Fire Services Preliminary Inspection & Adjustment (Non -FSI) (was
C11_6C3)
d/w - 10h/d - With 10 06-Oct-22 17-Oct-22 27-Oct-22 07-Nov-22 18
HK Hols - No B/O periods
310.C.EX.W1577.B01 PBB Fire Services Preliminary Testing & Commissioning (Non -FSI) (was
C11_6C3)
d/w - 10h/d - With 14 06-Oct-22 21-Oct-22 27-Oct-22 11-Nov-22 18
HK Hols - No B/O periods
Preliminary T&C - MVAC (was
C11_6C3)
d/w - 10h/d - With HK Hols
16- No B/O 0periods (was
28-Sep-22
C3) 18-Oct-22 29-Sep-22 19-Oct-22 1
310.C.EX.W1240 PBB MVAC Preliminary Inspection & Adjustment C11_6 d/w - 10h/d - With 10 28-Sep-22 11-Oct-22 29-Sep-22 12-Oct-22 1
HK Hols - No B/O periods
(was C3)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 157 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.EX.W1244 PBB MVAC Preliminary Testing & Commissioning C11_6 d/w - 10h/d - With 14 30-Sep-22 18-Oct-22 03-Oct-22 19-Oct-22 1
HK Hols - No B/O periods
Testing and Commissioning (was
C11_6C3)
d/w - 10h/d - With HK Hols
21- No B/O 4periods (was
10-Oct-22
C3) 02-Nov-22 14-Oct-22 18-Nov-22 14
310.T.EX.L248 PBB Plumbing and Drainage T&C C11_6 d/w - 10h/d - With 6 1 10-Oct-22 15-Oct-22 14-Oct-22 20-Oct-22 4
HK Hols - No B/O periods
310.T.EX.L232 PBB Fire Service T&C (FSI) (was
C11_6C3)
d/w - 10h/d - With 6 1 27-Oct-22 02-Nov-22 28-Oct-22 03-Nov-22 1
HK Hols - No B/O periods
310.T.EX.L236 PBB MVAC T&C (was
C11_6C3)
d/w - 10h/d - With 6 1 27-Oct-22 02-Nov-22 28-Oct-22 03-Nov-22 1
HK Hols - No B/O periods
310.T.EX.L240.B01 PBB Fire Service T&C (Non-FSI) (was
C11_6C3)
d/w - 10h/d - With 6 1 27-Oct-22 02-Nov-22 12-Nov-22 18-Nov-22 14
HK Hols - No B/O periods
Water Supply Department (WSD) (was
C11_6C3)
d/w - 10h/d - With HK Hols
134- No B/O 0periods (was
23-May-22
C3) 31-Oct-22 24-Jun-22 03-Nov-22 3
310.T.ES.P328 PBB Prepare for Plumbing Material for Submission C11_6 d/w - 10h/d - With 17 23-May-22 11-Jun-22 24-Jun-22 14-Jul-22 27
HK Hols - No B/O periods
310.T.ES.P332 PBB Submit all Plumbing Material for PM Acceptance (was
C11_6C3)
d/w - 10h/d - With 0 11-Jun-22 15-Jul-22 27
HK Hols - No B/O periods
310.T.ES.P336 PBB PM Acceptance (was
C11_6C3)
d/w - 10h/d - With 48 11-Jun-22 08-Aug-22 15-Jul-22 08-Sep-22 27
HK Hols - No B/O periods
310.T.ES.P340 PBB Form WWO 46 (Part I & Part II) & Annex Submission for WSD Approval (Plumbing / (was
C11_6C3)
d/w - 10h/d - With 0 08-Aug-22 09-Sep-22 27
FS / WP) HK Hols - No B/O periods
310.T.ES.P344 PBB Obtain Form WWO 46 (Part III) - WSD Approval, Endorsed & Return to Licensed (was
C11_6C3)
d/w - 10h/d - With 4 08-Aug-22 12-Aug-22 09-Sep-22 14-Sep-22 27
Plumber HK Hols - No B/O periods
310.T.ES.P304 PBB Form WWO 46 (Part IV) Submission for WSD Inspection (Plumbing / FS / WP) (was
C11_6C3)
d/w - 10h/d - With 0 18-Oct-22 21-Oct-22 3
HK Hols - No B/O periods
310.T.ES.P308 PBB WSD Inspection for Water Supply System (was
C11_6C3)
d/w - 10h/d - With 6 18-Oct-22 24-Oct-22 21-Oct-22 27-Oct-22 3
HK Hols - No B/O periods
310.T.ES.P312 PBB Obtain Form WWO 46 (Part V) (was
C11_6C3)
d/w - 10h/d - With 0 24-Oct-22 27-Oct-22 3
HK Hols - No B/O periods
310.T.ES.P316 PBB Form WWO 132 (Part II) Submission for Water Supply Connection (was
C11_6C3)
d/w - 10h/d - With 0 24-Oct-22 27-Oct-22 3
HK Hols - No B/O periods
310.T.ES.P320 PBB Final Water Supply Connection (was
C11_6C3)
d/w - 10h/d - With 6 25-Oct-22 31-Oct-22 28-Oct-22 03-Nov-22 3
HK Hols - No B/O periods
310.T.ES.P324 PBB Obtain Water Certificate (Form WWO 1005) (was
C11_6C3)
d/w - 10h/d - With 0 31-Oct-22 03-Nov-22 3
HK Hols - No B/O periods
Fire Services Department (FSD) (was
C11_6C3)
d/w - 10h/d - With HK Hols
36- No B/O 0periods (was
08-Oct-22
C3) 18-Nov-22 11-Oct-22 18-Nov-22 0
DG Application & Inspection C11_6 d/w - 10h/d - With HK Hols
21- No B/O 0periods (was
08-Oct-22
C3) 01-Nov-22 11-Oct-22 03-Nov-22 2
310.T.ES.P404 PBB DG Inspection Application (Form Submission) C11_6 d/w - 10h/d - With 0 08-Oct-22 11-Oct-22 2
HK Hols - No B/O periods
310.T.ES.P408 PBB DG 1st Inspection (was
C11_6C3)
d/w - 10h/d - With 6 17-Oct-22 22-Oct-22 19-Oct-22 25-Oct-22 2
HK Hols - No B/O periods
310.T.ES.P412 PBB DG FSD Comment (was
C11_6C3)
d/w - 10h/d - With 0 22-Oct-22 25-Oct-22 2
HK Hols - No B/O periods
310.T.ES.P416 PBB DG Rectification & Adjustment (was
C11_6C3)
d/w - 10h/d - With 2 24-Oct-22 25-Oct-22 26-Oct-22 27-Oct-22 2
HK Hols - No B/O periods
310.T.ES.P420 PBB DG Re-inspection (was
C11_6C3)
d/w - 10h/d - With 6 26-Oct-22 01-Nov-22 28-Oct-22 03-Nov-22 2
HK Hols - No B/O periods
310.T.ES.P424 PBB Issue DG Certificate (was
C11_6C3)
d/w - 10h/d - With 0 01-Nov-22 03-Nov-22 2
HK Hols - No B/O periods
FS Application & Inspection (was
C11_6C3)
d/w - 10h/d - With HK Hols
14- No B/O 0periods (was
03-Nov-22
C3) 18-Nov-22 04-Nov-22 18-Nov-22 0
310.T.ES.P348 PBB F.S. Inspection Plan (Form FSI / 314 Submission) C11_6 d/w - 10h/d - With 0 03-Nov-22 04-Nov-22 1
HK Hols - No B/O periods
(was C3)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 158 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.T.ES.P352 PBB F.S. Inspection Application (Form FSI / 501 & 251 Submission) C11_6 d/w - 10h/d - With 0 03-Nov-22 04-Nov-22 1
HK Hols - No B/O periods
310.T.ES.P356 PBB F.S. 1st Inspection (was
C11_6C3)
d/w - 10h/d - With 6 04-Nov-22 10-Nov-22 04-Nov-22 10-Nov-22 0
HK Hols - No B/O periods
310.T.ES.P360 PBB FSD Comment (was
C11_6C3)
d/w - 10h/d - With 0 10-Nov-22 10-Nov-22 0
HK Hols - No B/O periods
310.T.ES.P364 PBB Rectification & Adjustment (was
C11_6C3)
d/w - 10h/d - With 1 11-Nov-22 11-Nov-22 11-Nov-22 11-Nov-22 0
HK Hols - No B/O periods
310.T.ES.P368 PBB F.S. Re-inspection (was
C11_6C3)
d/w - 10h/d - With 6 12-Nov-22 18-Nov-22 12-Nov-22 18-Nov-22 0
HK Hols - No B/O periods
310.T.ES.P372 PBB Issue F.S. Certificate (Form FS172) (was
C11_6C3)
d/w - 10h/d - With 0 18-Nov-22 18-Nov-22 0
HK Hols - No B/O periods
Environmental Protection Department (EDP) (was
C11_6C3)
d/w - 10h/d - With HK Hols
13- No B/O 0periods (was
08-Oct-22
C3) 22-Oct-22 20-Oct-22 03-Nov-22 10
EPD Application & Inspection C11_6 d/w - 10h/d - With HK Hols
13- No B/O 0periods (was
08-Oct-22
C3) 22-Oct-22 20-Oct-22 03-Nov-22 10
310.T.ES.P716 PBB- EPD Inspection Application C11_6 d/w - 10h/d - With 0 08-Oct-22 20-Oct-22 10
HK Hols - No B/O periods
310.T.ES.P720 PBB- EPD 1st Inspection (was
C11_6C3)
d/w - 10h/d - With 6 08-Oct-22 14-Oct-22 20-Oct-22 26-Oct-22 10
HK Hols - No B/O periods
310.T.ES.P724 PBB - EPD Comment (was
C11_6C3)
d/w - 10h/d - With 0 14-Oct-22 26-Oct-22 10
HK Hols - No B/O periods
310.T.ES.P728 PBB - EPD Rectification & Adjustment (was
C11_6C3)
d/w - 10h/d - With 1 15-Oct-22 15-Oct-22 27-Oct-22 27-Oct-22 10
HK Hols - No B/O periods
310.T.ES.P732 PBB - EPD Re-inspection (was
C11_6C3)
d/w - 10h/d - With 6 17-Oct-22 22-Oct-22 28-Oct-22 03-Nov-22 10
HK Hols - No B/O periods
310.T.ES.P736 PBB - Issue License (was
C11_6C3)
d/w - 10h/d - With 0 22-Oct-22 03-Nov-22 10
HK Hols - No B/O periods
Building Department (BD) (was C3) 13 0 19-Nov-22 04-Dec-22 19-Nov-22 04-Dec-22 0
310.T.ES.P376 PBB BD Inspection Application for Occupation Permit (Form BA13 Submission) C11_6 d/w - 10h/d - With 0 19-Nov-22 19-Nov-22 0
HK Hols - No B/O periods
310.T.ES.P380 PBB BD 1st Inspection (was
C11_6C3)
d/w - 10h/d - With 6 19-Nov-22 25-Nov-22 19-Nov-22 25-Nov-22 0
HK Hols - No B/O periods
310.T.ES.P384 PBB BD Comment (was
C11_6C3)
d/w - 10h/d - With 0 25-Nov-22 25-Nov-22 0
HK Hols - No B/O periods
310.T.ES.P388 PBB Rectification & Adjustment (was
C11_6C3)
d/w - 10h/d - With 1 26-Nov-22 26-Nov-22 26-Nov-22 26-Nov-22 0
HK Hols - No B/O periods
310.T.ES.P392 PBB BD Re-inspection (was
C11_6C3)
d/w - 10h/d - With 6 28-Nov-22 03-Dec-22 28-Nov-22 03-Dec-22 0
HK Hols - No B/O periods
310.T.ES.P300 PBB Achieved Completion and T&C of Tunnel Plant Building B (was
C11_6C3)
d/w - 10h/d - With 0 03-Dec-22 03-Dec-22 0
HK Hols - No B/O periods
310.T.ES.P396 PBB Issue Occupation Permit (Form BD104) (was
C11_6C3)
d/w - 10h/d - With 0 03-Dec-22 03-Dec-22 0
HK Hols - No B/O periods
310.T.ES.P397 PMS23 - Comp all works for Road Tunnel PBB and stat. apprv, consents, ready for use [4 (was
C01_7C3)
d/w - 10h/d - No HK 0 04-Dec-22* 04-Dec-22 0
Dec 22] Hols - No B/O periods (was
Cost Centre #08 - Ancillary Buildings C1) 831 37 07-Jun-21 A 19-Mar-24 19-Feb-22 31-Aug-24 134
------Design & Other Submission ------------- C01_7 d/w - 10h/d - No HK Hols598
- No B/O periods
0 (was
26-Aug-21
C1) A 15-Apr-23 26-Feb-22 26-Oct-23 194
CC#08 - General - MEP - Method Statement C01_7 d/w - 10h/d - No HK Hols260
- No B/O periods
0 (was27-Mar-22
C1) 11-Dec-22 05-Apr-22 03-Feb-23 54
ELECT C01_7 d/w - 10h/d - No HK Hols210
- No B/O periods
0 (was27-Mar-22
C1) 22-Oct-22 05-Apr-22 31-Oct-22 9
310.D.WS.L984.05.B02 Prepare and submit Elect. Method Statement (15 nos.) C01_7 d/w - 10h/d - No HK 165 27-Mar-22 07-Sep-22 05-Apr-22 16-Sep-22 9
Hols - No B/O periods (was
310.D.WS.L985.05.B02 Review and comment Elect. Method Statement (15 nos.) C1)
C01_7 d/w - 10h/d - No HK 165 11-Apr-22 22-Sep-22 20-Apr-22 01-Oct-22 9
Hols - No B/O periods (was
C1)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 159 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L986.05.B02 Prepare and re-submit Elect. Method Statement (15 nos.) C01_7 d/w - 10h/d - No HK 165 26-Apr-22 07-Oct-22 05-May-22 16-Oct-22 9
Hols - No B/O periods (was
310.D.WS.L988.05.B02 Obtain approval of Elect. Method Statement (15 nos.) C1)
C01_7 d/w - 10h/d - No HK 165 11-May-22 22-Oct-22 20-May-22 31-Oct-22 9
Hols - No B/O periods (was
MVAC C1)
C01_7 d/w - 10h/d - No HK Hols260
- No B/O periods
0 (was27-Mar-22
C1) 11-Dec-22 20-May-22 03-Feb-23 54
310.D.WS.L984.06.B02 Prepare and submit MVAC Method Statement (13 nos.) C01_7 d/w - 10h/d - No HK 215 27-Mar-22 27-Oct-22 20-May-22 20-Dec-22 54
Hols - No B/O periods (was
310.D.WS.L985.06.B02 Review and comment MVAC Method Statement (13 nos.) C1)
C01_7 d/w - 10h/d - No HK 215 11-Apr-22 11-Nov-22 04-Jun-22 04-Jan-23 54
Hols - No B/O periods (was
310.D.WS.L986.06.B02 Prepare and re-submit MVAC Method Statement (13 nos.) C1)
C01_7 d/w - 10h/d - No HK 215 26-Apr-22 26-Nov-22 19-Jun-22 19-Jan-23 54
Hols - No B/O periods (was
310.D.WS.L988.06.B02 Obtain approval of MVAC Method Statement (13 nos.) C1)
C01_7 d/w - 10h/d - No HK 215 11-May-22 11-Dec-22 04-Jul-22 03-Feb-23 54
Hols - No B/O periods (was
FS C1)
C01_7 d/w - 10h/d - No HK Hols138
- No B/O periods
0 (was01-May-22
C1) 15-Sep-22 20-May-22 04-Oct-22 19
310.D.WS.L984.07.B02 Prepare and submit FS Method Statement (12 nos.) C01_7 d/w - 10h/d - No HK 93 01-May-22 01-Aug-22 20-May-22 20-Aug-22 19
Hols - No B/O periods (was
310.D.WS.L985.07.B02 Review and comment FS Method Statement (12 nos.) C1)
C01_7 d/w - 10h/d - No HK 93 16-May-22 16-Aug-22 04-Jun-22 04-Sep-22 19
Hols - No B/O periods (was
310.D.WS.L986.07.B02 Prepare and re-submit FS Method Statement (12 nos.) C1)
C01_7 d/w - 10h/d - No HK 93 31-May-22 31-Aug-22 19-Jun-22 19-Sep-22 19
Hols - No B/O periods (was
310.D.WS.L988.07.B02 Obtain approval of FS Method Statement (12 nos.) C1)
C01_7 d/w - 10h/d - No HK 93 15-Jun-22 15-Sep-22 04-Jul-22 04-Oct-22 19
Hols - No B/O periods (was
P&D C1)
C01_7 d/w - 10h/d - No HK Hols199
- No B/O periods
0 (was27-Mar-22
C1) 11-Oct-22 16-Apr-22 31-Oct-22 20
310.D.WS.L984.08.B02 Prepare and submit P&D Method Statement (5 nos.) C01_7 d/w - 10h/d - No HK 154 27-Mar-22 27-Aug-22 16-Apr-22 16-Sep-22 20
Hols - No B/O periods (was
310.D.WS.L985.08.B02 Review and comment P&D Method Statement (5 nos.) C1)
C01_7 d/w - 10h/d - No HK 154 11-Apr-22 11-Sep-22 01-May-22 01-Oct-22 20
Hols - No B/O periods (was
310.D.WS.L986.08.B02 Prepare and re-submit P&D Method Statement (5 nos.) C1)
C01_7 d/w - 10h/d - No HK 154 26-Apr-22 26-Sep-22 16-May-22 16-Oct-22 20
Hols - No B/O periods (was
310.D.WS.L988.08.B02 Obtain approval of P&D Method Statement (5 nos.) C1)
C01_7 d/w - 10h/d - No HK 154 11-May-22 11-Oct-22 31-May-22 31-Oct-22 20
Hols - No B/O periods (was
CC#08 - General - MEP - Material Submission C1)
C01_7 d/w - 10h/d - No HK Hols294
- No B/O periods
0 (was
27-Jan-22
C1) A 16-Nov-22 26-Feb-22 11-Mar-23 115
Preliminaries C01_7 d/w - 10h/d - No HK Hols 7- No B/O periods
0 (was
27-Jan-22
C1) A 08-Feb-22 A 26-Feb-22 05-Apr-22
310.C.EX.S000.01.B02 Contract award (Tentative) C01_7 d/w - 10h/d - No HK 0 27-Jan-22 A 26-Feb-22
Hols - No B/O periods (was
310.C.EX.S000.02.B02 Mobilization C1)
C01_7 d/w - 10h/d - No HK 0 27-Jan-22 A 02-Feb-22 A 26-Feb-22 26-Feb-22
Hols - No B/O periods (was
310.C.EX.S000.03.B02 Prepare and submit O Chart C1)
C01_7 d/w - 10h/d - No HK 0 03-Feb-22 A 07-Feb-22 A 26-Feb-22 26-Feb-22
Hols - No B/O periods (was
310.C.EX.S000.04.B02 Prepare and submit Equipment/Material Submission Schedule C1)
C01_7 d/w - 10h/d - No HK 0 03-Feb-22 A 08-Feb-22 A 26-Feb-22 26-Feb-22
Hols - No B/O periods (was
310.C.EX.S000.05.B02 Prepare and submit Drawing Submission Shcedule C1)
C01_7 d/w - 10h/d - No HK 0 03-Feb-22 A 08-Feb-22 A 05-Apr-22 05-Apr-22
Hols - No B/O periods (was
Electrical C1)
C01_7 d/w - 10h/d - No HK Hols103
- No B/O periods
0 (was
06-Mar-22
C1) A 16-Jun-22 31-Mar-22 16-Aug-22 61
Armoured Cable C01_7 d/w - 10h/d - No HK Hols53
- No B/O periods
0 (was
14-Mar-22
C1) A 18-May-22 16-Apr-22 07-Jun-22 20
310.D.WS.L992.01.B02Prepare and submit info. of Armoured Cable C01_7 d/w - 10h/d - No HK 0 14-Mar-22 A 07-Apr-22 16-Apr-22 27-Apr-22 20
Hols - No B/O periods (was
310.D.WS.L993.01.B02Review and comment info. of Armoured Cable C1)
C01_7 d/w - 10h/d - No HK 23 08-Apr-22 30-Apr-22 28-Apr-22 20-May-22 20
Hols - No B/O periods (was
310.D.WS.L994.01.B02Prepare and re-submit info. of Armoured Cable C1)
C01_7 d/w - 10h/d - No HK 9 01-May-22 09-May-22 21-May-22 29-May-22 20
Hols - No B/O periods (was
C1)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 160 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L996.01.B02Obtain "No objection" of Armoured Cable C01_7 d/w - 10h/d - No HK 9 10-May-22 18-May-22 30-May-22 07-Jun-22 20
Hols - No B/O periods (was
FR Cable C1)
C01_7 d/w - 10h/d - No HK Hols82
- No B/O periods
0 (was
14-Mar-22
C1) A 16-Jun-22 27-May-22 16-Aug-22 61
310.D.WS.L992.02.B02Prepare and submit info. of FR Cable C01_7 d/w - 10h/d - No HK 0 14-Mar-22 A 07-Apr-22 27-May-22 07-Jun-22 61
Hols - No B/O periods (was
310.D.WS.L993.02.B02Review and comment info. of FR Cable C1)
C01_7 d/w - 10h/d - No HK 24 08-Apr-22 01-May-22 08-Jun-22 01-Jul-22 61
Hols - No B/O periods (was
310.D.WS.L994.02.B02Prepare and re-submit info. of FR Cable C1)
C01_7 d/w - 10h/d - No HK 22 02-May-22 23-May-22 02-Jul-22 23-Jul-22 61
Hols - No B/O periods (was
310.D.WS.L996.02.B02Obtain "No objection" of FR Cable C1)
C01_7 d/w - 10h/d - No HK 24 24-May-22 16-Jun-22 24-Jul-22 16-Aug-22 61
Hols - No B/O periods (was
Single Core Cable C1)
C01_7 d/w - 10h/d - No HK Hols46
- No B/O periods
0 (was
14-Mar-22
C1) A 19-May-22 24-Jun-22 16-Aug-22 89
310.D.WS.L992.03.B02Prepare and submit info. of Single Core Cable C01_7 d/w - 10h/d - No HK 0 14-Mar-22 A 07-Apr-22 24-Jun-22 05-Jul-22 89
Hols - No B/O periods (was
310.D.WS.L993.03.B02Review and comment info. of Single Core Cable C1)
C01_7 d/w - 10h/d - No HK 24 08-Apr-22 01-May-22 06-Jul-22 29-Jul-22 89
Hols - No B/O periods (was
310.D.WS.L994.03.B02Prepare and re-submit info. of Single Core Cable C1)
C01_7 d/w - 10h/d - No HK 9 02-May-22 10-May-22 30-Jul-22 07-Aug-22 89
Hols - No B/O periods (was
310.D.WS.L996.03.B02Obtain "No objection" of Single Core Cable C1)
C01_7 d/w - 10h/d - No HK 9 11-May-22 19-May-22 08-Aug-22 16-Aug-22 89
Hols - No B/O periods (was
General Lighting (included E-Lighting) C1)
C01_7 d/w - 10h/d - No HK Hols60
- No B/O periods
0 (was
20-Mar-22
C1) A 19-May-22 18-Apr-22 10-Jun-22 22
310.D.WS.L992.04.B02Prepare and submit info. of General Lighting (included E-Lighting) C01_7 d/w - 10h/d - No HK 12 20-Mar-22 A 07-Apr-22 18-Apr-22 29-Apr-22 22
Hols - No B/O periods (was
310.D.WS.L993.04.B02Review and comment info. of General Lighting (included E-Lighting) C1)
C01_7 d/w - 10h/d - No HK 24 08-Apr-22 01-May-22 30-Apr-22 23-May-22 22
Hols - No B/O periods (was
310.D.WS.L994.04.B02Prepare and re-submit info. of General Lighting (included E-Lighting) C1)
C01_7 d/w - 10h/d - No HK 9 02-May-22 10-May-22 24-May-22 01-Jun-22 22
Hols - No B/O periods (was
310.D.WS.L996.04.B02Obtain "No objection" of General Lighting (included E-Lighting) C1)
C01_7 d/w - 10h/d - No HK 9 11-May-22 19-May-22 02-Jun-22 10-Jun-22 22
Hols - No B/O periods (was
Distribution Board for MCB, MCCB & Accessories C1)
C01_7 d/w - 10h/d - No HK Hols68
- No B/O periods
0 (was
11-Mar-22
C1) A 17-May-22 20-Apr-22 10-Jun-22 24
310.D.WS.L992.05.B02Prepare and submit info. of Distribution Board for MCB, MCCB & Accessories C01_7 d/w - 10h/d - No HK 10 11-Mar-22 A 05-Apr-22 20-Apr-22 29-Apr-22 24
Hols - No B/O periods (was
310.D.WS.L993.05.B02Review and comment info. of Distribution Board for MCB, MCCB & Accessories C1)
C01_7 d/w - 10h/d - No HK 24 06-Apr-22 29-Apr-22 30-Apr-22 23-May-22 24
Hols - No B/O periods (was
310.D.WS.L994.05.B02Prepare and re-submit info. of Distribution Board for MCB, MCCB & Accessories C1)
C01_7 d/w - 10h/d - No HK 9 30-Apr-22 08-May-22 24-May-22 01-Jun-22 24
Hols - No B/O periods (was
310.D.WS.L996.05.B02Obtain "No objection" of Distribution Board for MCB, MCCB & Accessories C1)
C01_7 d/w - 10h/d - No HK 9 09-May-22 17-May-22 02-Jun-22 10-Jun-22 24
Hols - No B/O periods (was
MCB, MCCB & Accessories C1)
C01_7 d/w - 10h/d - No HK Hols64
- No B/O periods
0 (was
11-Mar-22
C1) A 13-May-22 31-Mar-22 17-May-22 4
310.D.WS.L992.06.B02Prepare and submit info. of MCB, MCCB & Accessories C01_7 d/w - 10h/d - No HK 6 11-Mar-22 A 01-Apr-22 31-Mar-22 05-Apr-22 4
Hols - No B/O periods (was
310.D.WS.L993.06.B02Review and comment info. of MCB, MCCB & Accessories C1)
C01_7 d/w - 10h/d - No HK 24 02-Apr-22 25-Apr-22 06-Apr-22 29-Apr-22 4
Hols - No B/O periods (was
310.D.WS.L994.06.B02Prepare and re-submit info. of MCB, MCCB & Accessories C1)
C01_7 d/w - 10h/d - No HK 9 26-Apr-22 04-May-22 30-Apr-22 08-May-22 4
Hols - No B/O periods (was
310.D.WS.L996.06.B02Obtain "No objection" of MCB, MCCB & Accessories C1)
C01_7 d/w - 10h/d - No HK 9 05-May-22 13-May-22 09-May-22 17-May-22 4
Hols - No B/O periods (was
Busduct C1)
C01_7 d/w - 10h/d - No HK Hols62
- No B/O periods
0 (was04-Apr-22
C1) 04-Jun-22 11-Apr-22 11-Jun-22 7
310.D.WS.L992.07.B02Prepare and submit info. of Busduct C01_7 d/w - 10h/d - No HK 20 04-Apr-22 23-Apr-22 11-Apr-22 30-Apr-22 7
Hols - No B/O periods (was
C1)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 161 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L993.07.B02Review and comment info. of Busduct C01_7 d/w - 10h/d - No HK 24 24-Apr-22 17-May-22 01-May-22 24-May-22 7
Hols - No B/O periods (was
310.D.WS.L994.07.B02Prepare and re-submit info. of Busduct C1)
C01_7 d/w - 10h/d - No HK 9 18-May-22 26-May-22 25-May-22 02-Jun-22 7
Hols - No B/O periods (was
310.D.WS.L996.07.B02Obtain "No objection" of Busduct C1)
C01_7 d/w - 10h/d - No HK 9 27-May-22 04-Jun-22 03-Jun-22 11-Jun-22 7
Hols - No B/O periods (was
Water Leakage Detection System C1)
C01_7 d/w - 10h/d - No HK Hols62
- No B/O periods
0 (was04-Apr-22
C1) 04-Jun-22 10-Apr-22 10-Jun-22 6
310.D.WS.L992.08.B02Prepare and submit info. of Water Leakage Detection System C01_7 d/w - 10h/d - No HK 20 04-Apr-22 23-Apr-22 10-Apr-22 29-Apr-22 6
Hols - No B/O periods (was
310.D.WS.L993.08.B02Review and comment info. of Water Leakage Detection System C1)
C01_7 d/w - 10h/d - No HK 24 24-Apr-22 17-May-22 30-Apr-22 23-May-22 6
Hols - No B/O periods (was
310.D.WS.L994.08.B02Prepare and re-submit info. of Water Leakage Detection System C1)
C01_7 d/w - 10h/d - No HK 9 18-May-22 26-May-22 24-May-22 01-Jun-22 6
Hols - No B/O periods (was
310.D.WS.L996.08.B02Obtain "No objection" of Water Leakage Detection System C1)
C01_7 d/w - 10h/d - No HK 9 27-May-22 04-Jun-22 02-Jun-22 10-Jun-22 6
Hols - No B/O periods (was
MICC Cable C1)
C01_7 d/w - 10h/d - No HK Hols76
- No B/O periods
0 (was
07-Mar-22
C1) A 21-May-22 17-Apr-22 11-Jun-22 21
310.D.WS.L992.09.B02Prepare and submit info. of MICC Cable C01_7 d/w - 10h/d - No HK 14 07-Mar-22 A 09-Apr-22 17-Apr-22 30-Apr-22 21
Hols - No B/O periods (was
310.D.WS.L993.09.B02Review and comment info. of MICC Cable C1)
C01_7 d/w - 10h/d - No HK 24 10-Apr-22 03-May-22 01-May-22 24-May-22 21
Hols - No B/O periods (was
310.D.WS.L994.09.B02Prepare and re-submit info. of MICC Cable C1)
C01_7 d/w - 10h/d - No HK 9 04-May-22 12-May-22 25-May-22 02-Jun-22 21
Hols - No B/O periods (was
310.D.WS.L996.09.B02Obtain "No objection" of MICC Cable C1)
C01_7 d/w - 10h/d - No HK 9 13-May-22 21-May-22 03-Jun-22 11-Jun-22 21
Hols - No B/O periods (was
LV Switchboards & Accessories C1)
C01_7 d/w - 10h/d - No HK Hols61
- No B/O periods
0 (was
22-Mar-22
C1) A 21-May-22 16-Apr-22 10-Jun-22 20
310.D.WS.L992.10.B02Prepare and submit info. of LV Switchboards & Accessories C01_7 d/w - 10h/d - No HK 14 22-Mar-22 A 09-Apr-22 16-Apr-22 29-Apr-22 20
Hols - No B/O periods (was
310.D.WS.L993.10.B02Review and comment info. of LV Switchboards & Accessories C1)
C01_7 d/w - 10h/d - No HK 24 10-Apr-22 03-May-22 30-Apr-22 23-May-22 20
Hols - No B/O periods (was
310.D.WS.L994.10.B02Prepare and re-submit info. of LV Switchboards & Accessories C1)
C01_7 d/w - 10h/d - No HK 9 04-May-22 12-May-22 24-May-22 01-Jun-22 20
Hols - No B/O periods (was
310.D.WS.L996.10.B02Obtain "No objection" of LV Switchboards & Accessories C1)
C01_7 d/w - 10h/d - No HK 9 13-May-22 21-May-22 02-Jun-22 10-Jun-22 20
Hols - No B/O periods (was
ACB & Accessories C1)
C01_7 d/w - 10h/d - No HK Hols61
- No B/O periods
0 (was
22-Mar-22
C1) A 21-May-22 17-Apr-22 11-Jun-22 21
310.D.WS.L992.11.B02Prepare and submit info. of ACB & Accessories C01_7 d/w - 10h/d - No HK 14 22-Mar-22 A 09-Apr-22 17-Apr-22 30-Apr-22 21
Hols - No B/O periods (was
310.D.WS.L993.11.B02Review and comment info. of ACB & Accessories C1)
C01_7 d/w - 10h/d - No HK 24 10-Apr-22 03-May-22 01-May-22 24-May-22 21
Hols - No B/O periods (was
310.D.WS.L994.11.B02Prepare and re-submit info. of ACB & Accessories C1)
C01_7 d/w - 10h/d - No HK 9 04-May-22 12-May-22 25-May-22 02-Jun-22 21
Hols - No B/O periods (was
310.D.WS.L996.11.B02Obtain "No objection" of ACB & Accessories C1)
C01_7 d/w - 10h/d - No HK 9 13-May-22 21-May-22 03-Jun-22 11-Jun-22 21
Hols - No B/O periods (was
Automatic Transfer Switch C1)
C01_7 d/w - 10h/d - No HK Hols61
- No B/O periods
0 (was
22-Mar-22
C1) A 21-May-22 16-Apr-22 10-Jun-22 20
310.D.WS.L992.12.B02Prepare and submit info. of Automatic Transfer Switch C01_7 d/w - 10h/d - No HK 14 22-Mar-22 A 09-Apr-22 16-Apr-22 29-Apr-22 20
Hols - No B/O periods (was
310.D.WS.L993.12.B02Review and comment info. of Automatic Transfer Switch C1)
C01_7 d/w - 10h/d - No HK 24 10-Apr-22 03-May-22 30-Apr-22 23-May-22 20
Hols - No B/O periods (was
310.D.WS.L994.12.B02Prepare and re-submit info. of Automatic Transfer Switch C1)
C01_7 d/w - 10h/d - No HK 9 04-May-22 12-May-22 24-May-22 01-Jun-22 20
Hols - No B/O periods (was
310.D.WS.L996.12.B02Obtain "No objection" of Automatic Transfer Switch C1)
C01_7 d/w - 10h/d - No HK 9 13-May-22 21-May-22 02-Jun-22 10-Jun-22 20
Hols - No B/O periods (was
C1)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 162 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
Battery Set C01_7 d/w - 10h/d - No HK Hols61
- No B/O periods
0 (was
22-Mar-22
C1) A 21-May-22 17-Apr-22 11-Jun-22 21
310.D.WS.L992.13.B02Prepare and submit info. of Battery Set C01_7 d/w - 10h/d - No HK 14 22-Mar-22 A 09-Apr-22 17-Apr-22 30-Apr-22 21
Hols - No B/O periods (was
310.D.WS.L993.13.B02Review and comment info. of Battery Set C1)
C01_7 d/w - 10h/d - No HK 24 10-Apr-22 03-May-22 01-May-22 24-May-22 21
Hols - No B/O periods (was
310.D.WS.L994.13.B02Prepare and re-submit info. of Battery Set C1)
C01_7 d/w - 10h/d - No HK 9 04-May-22 12-May-22 25-May-22 02-Jun-22 21
Hols - No B/O periods (was
310.D.WS.L996.13.B02Obtain "No objection" of Battery Set C1)
C01_7 d/w - 10h/d - No HK 9 13-May-22 21-May-22 03-Jun-22 11-Jun-22 21
Hols - No B/O periods (was
HRC Fuse for Fuse-switch C1)
C01_7 d/w - 10h/d - No HK Hols62
- No B/O periods
0 (was27-Mar-22
C1) 27-May-22 10-Apr-22 10-Jun-22 14
310.D.WS.L992.14.B02Prepare and submit info. of HRC Fuse for Fuse-switch C01_7 d/w - 10h/d - No HK 20 27-Mar-22 15-Apr-22 10-Apr-22 29-Apr-22 14
Hols - No B/O periods (was
310.D.WS.L993.14.B02Review and comment info. of HRC Fuse for Fuse-switch C1)
C01_7 d/w - 10h/d - No HK 24 16-Apr-22 09-May-22 30-Apr-22 23-May-22 14
Hols - No B/O periods (was
310.D.WS.L994.14.B02Prepare and re-submit info. of HRC Fuse for Fuse-switch C1)
C01_7 d/w - 10h/d - No HK 9 10-May-22 18-May-22 24-May-22 01-Jun-22 14
Hols - No B/O periods (was
310.D.WS.L996.14.B02Obtain "No objection" of HRC Fuse for Fuse-switch C1)
C01_7 d/w - 10h/d - No HK 9 19-May-22 27-May-22 02-Jun-22 10-Jun-22 14
Hols - No B/O periods (was
MCCB C1)
C01_7 d/w - 10h/d - No HK Hols61
- No B/O periods
0 (was
22-Mar-22
C1) A 21-May-22 16-Apr-22 10-Jun-22 20
310.D.WS.L992.15.B02Prepare and submit info. of MCCB C01_7 d/w - 10h/d - No HK 14 22-Mar-22 A 09-Apr-22 16-Apr-22 29-Apr-22 20
Hols - No B/O periods (was
310.D.WS.L993.15.B02Review and comment info. of MCCB C1)
C01_7 d/w - 10h/d - No HK 24 10-Apr-22 03-May-22 30-Apr-22 23-May-22 20
Hols - No B/O periods (was
310.D.WS.L994.15.B02Prepare and re-submit info. of MCCB C1)
C01_7 d/w - 10h/d - No HK 9 04-May-22 12-May-22 24-May-22 01-Jun-22 20
Hols - No B/O periods (was
310.D.WS.L996.15.B02Obtain "No objection" of MCCB C1)
C01_7 d/w - 10h/d - No HK 9 13-May-22 21-May-22 02-Jun-22 10-Jun-22 20
Hols - No B/O periods (was
Digital Protection Device C1)
C01_7 d/w - 10h/d - No HK Hols77
- No B/O periods
0 (was
06-Mar-22
C1) A 21-May-22 16-Apr-22 10-Jun-22 20
310.D.WS.L992.16.B02Prepare and submit info. of Digital Protection Device C01_7 d/w - 10h/d - No HK 14 06-Mar-22 A 09-Apr-22 16-Apr-22 29-Apr-22 20
Hols - No B/O periods (was
310.D.WS.L993.16.B02Review and comment info. of Digital Protection Device C1)
C01_7 d/w - 10h/d - No HK 24 10-Apr-22 03-May-22 30-Apr-22 23-May-22 20
Hols - No B/O periods (was
310.D.WS.L994.16.B02Prepare and re-submit info. of Digital Protection Device C1)
C01_7 d/w - 10h/d - No HK 9 04-May-22 12-May-22 24-May-22 01-Jun-22 20
Hols - No B/O periods (was
310.D.WS.L996.16.B02Obtain "No objection" of Digital Protection Device C1)
C01_7 d/w - 10h/d - No HK 9 13-May-22 21-May-22 02-Jun-22 10-Jun-22 20
Hols - No B/O periods (was
Capacitor Bank C1)
C01_7 d/w - 10h/d - No HK Hols77
- No B/O periods
0 (was
06-Mar-22
C1) A 21-May-22 16-Apr-22 10-Jun-22 20
310.D.WS.L992.17.B02Prepare and submit info. of Capacitor Bank C01_7 d/w - 10h/d - No HK 14 06-Mar-22 A 09-Apr-22 16-Apr-22 29-Apr-22 20
Hols - No B/O periods (was
310.D.WS.L993.17.B02Review and comment info. of Capacitor Bank C1)
C01_7 d/w - 10h/d - No HK 24 10-Apr-22 03-May-22 30-Apr-22 23-May-22 20
Hols - No B/O periods (was
310.D.WS.L994.17.B02Prepare and re-submit info. of Capacitor Bank C1)
C01_7 d/w - 10h/d - No HK 9 04-May-22 12-May-22 24-May-22 01-Jun-22 20
Hols - No B/O periods (was
310.D.WS.L996.17.B02Obtain "No objection" of Capacitor Bank C1)
C01_7 d/w - 10h/d - No HK 9 13-May-22 21-May-22 02-Jun-22 10-Jun-22 20
Hols - No B/O periods (was
UPS C1)
C01_7 d/w - 10h/d - No HK Hols56
- No B/O periods
0 (was29-Mar-22
C1) 23-May-22 16-Apr-22 10-Jun-22 18
310.D.WS.L992.18.B02Prepare and submit info. of UPS C01_7 d/w - 10h/d - No HK 14 29-Mar-22 11-Apr-22 16-Apr-22 29-Apr-22 18
Hols - No B/O periods (was
310.D.WS.L993.18.B02Review and comment info. of UPS C1)
C01_7 d/w - 10h/d - No HK 24 12-Apr-22 05-May-22 30-Apr-22 23-May-22 18
Hols - No B/O periods (was
C1)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 163 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L994.18.B02Prepare and re-submit info. of UPS C01_7 d/w - 10h/d - No HK 9 06-May-22 14-May-22 24-May-22 01-Jun-22 18
Hols - No B/O periods (was
310.D.WS.L996.18.B02Obtain "No objection" of UPS C1)
C01_7 d/w - 10h/d - No HK 9 15-May-22 23-May-22 02-Jun-22 10-Jun-22 18
Hols - No B/O periods (was
Active Harmoice Filter C1)
C01_7 d/w - 10h/d - No HK Hols56
- No B/O periods
0 (was29-Mar-22
C1) 23-May-22 16-Apr-22 10-Jun-22 18
310.D.WS.L992.19.B02Prepare and submit info. of Active Harmoice Filter C01_7 d/w - 10h/d - No HK 14 29-Mar-22 11-Apr-22 16-Apr-22 29-Apr-22 18
Hols - No B/O periods (was
310.D.WS.L993.19.B02Review and comment info. of Active Harmoice Filter C1)
C01_7 d/w - 10h/d - No HK 24 12-Apr-22 05-May-22 30-Apr-22 23-May-22 18
Hols - No B/O periods (was
310.D.WS.L994.19.B02Prepare and re-submit info. of Active Harmoice Filter C1)
C01_7 d/w - 10h/d - No HK 9 06-May-22 14-May-22 24-May-22 01-Jun-22 18
Hols - No B/O periods (was
310.D.WS.L996.19.B02Obtain "No objection" of Active Harmoice Filter C1)
C01_7 d/w - 10h/d - No HK 9 15-May-22 23-May-22 02-Jun-22 10-Jun-22 18
Hols - No B/O periods (was
Isolation Transformer C1)
C01_7 d/w - 10h/d - No HK Hols56
- No B/O periods
0 (was29-Mar-22
C1) 23-May-22 17-Apr-22 11-Jun-22 19
310.D.WS.L992.20.B02Prepare and submit info. of Isolation Transformer C01_7 d/w - 10h/d - No HK 14 29-Mar-22 11-Apr-22 17-Apr-22 30-Apr-22 19
Hols - No B/O periods (was
310.D.WS.L993.20.B02Review and comment info. of Isolation Transformer C1)
C01_7 d/w - 10h/d - No HK 24 12-Apr-22 05-May-22 01-May-22 24-May-22 19
Hols - No B/O periods (was
310.D.WS.L994.20.B02Prepare and re-submit info. of Isolation Transformer C1)
C01_7 d/w - 10h/d - No HK 9 06-May-22 14-May-22 25-May-22 02-Jun-22 19
Hols - No B/O periods (was
310.D.WS.L996.20.B02Obtain "No objection" of Isolation Transformer C1)
C01_7 d/w - 10h/d - No HK 9 15-May-22 23-May-22 03-Jun-22 11-Jun-22 19
Hols - No B/O periods (was
By-pass switch C1)
C01_7 d/w - 10h/d - No HK Hols62
- No B/O periods
0 (was27-Mar-22
C1) 27-May-22 11-Apr-22 11-Jun-22 15
310.D.WS.L992.21.B02Prepare and submit info. of By-pass switch C01_7 d/w - 10h/d - No HK 20 27-Mar-22 15-Apr-22 11-Apr-22 30-Apr-22 15
Hols - No B/O periods (was
310.D.WS.L993.21.B02Review and comment info. of By-pass switch C1)
C01_7 d/w - 10h/d - No HK 24 16-Apr-22 09-May-22 01-May-22 24-May-22 15
Hols - No B/O periods (was
310.D.WS.L994.21.B02Prepare and re-submit info. of By-pass switch C1)
C01_7 d/w - 10h/d - No HK 9 10-May-22 18-May-22 25-May-22 02-Jun-22 15
Hols - No B/O periods (was
310.D.WS.L996.21.B02Obtain "No objection" of By-pass switch C1)
C01_7 d/w - 10h/d - No HK 9 19-May-22 27-May-22 03-Jun-22 11-Jun-22 15
Hols - No B/O periods (was
LV Generator Set (included Alternator & Diesel Engine) C1)
C01_7 d/w - 10h/d - No HK Hols54
- No B/O periods
0 (was
22-Mar-22
C1) A 14-May-22 24-Apr-22 11-Jun-22 28
310.D.WS.L992.22.B02Prepare and submit info. of LV Generator Set (included Alternator & Diesel Engine) C01_7 d/w - 10h/d - No HK 7 22-Mar-22 A 02-Apr-22 24-Apr-22 30-Apr-22 28
Hols - No B/O periods (was
310.D.WS.L993.22.B02Review and comment info. of LV Generator Set (included Alternator & Diesel Engine) C1)
C01_7 d/w - 10h/d - No HK 24 03-Apr-22 26-Apr-22 01-May-22 24-May-22 28
Hols - No B/O periods (was
310.D.WS.L994.22.B02Prepare and re-submit info. of LV Generator Set (included Alternator & Diesel Engine) C1)
C01_7 d/w - 10h/d - No HK 9 27-Apr-22 05-May-22 25-May-22 02-Jun-22 28
Hols - No B/O periods (was
310.D.WS.L996.22.B02Obtain "No objection" of LV Generator Set (included Alternator & Diesel Engine) C1)
C01_7 d/w - 10h/d - No HK 9 06-May-22 14-May-22 03-Jun-22 11-Jun-22 28
Hols - No B/O periods (was
Generator Controller C1)
C01_7 d/w - 10h/d - No HK Hols54
- No B/O periods
0 (was
22-Mar-22
C1) A 14-May-22 24-Apr-22 11-Jun-22 28
310.D.WS.L992.23.B02Prepare and submit info. of Generator Controller C01_7 d/w - 10h/d - No HK 7 22-Mar-22 A 02-Apr-22 24-Apr-22 30-Apr-22 28
Hols - No B/O periods (was
310.D.WS.L993.23.B02Review and comment info. of Generator Controller C1)
C01_7 d/w - 10h/d - No HK 24 03-Apr-22 26-Apr-22 01-May-22 24-May-22 28
Hols - No B/O periods (was
310.D.WS.L994.23.B02Prepare and re-submit info. of Generator Controller C1)
C01_7 d/w - 10h/d - No HK 9 27-Apr-22 05-May-22 25-May-22 02-Jun-22 28
Hols - No B/O periods (was
310.D.WS.L996.23.B02Obtain "No objection" of Generator Controller C1)
C01_7 d/w - 10h/d - No HK 9 06-May-22 14-May-22 03-Jun-22 11-Jun-22 28
Hols - No B/O periods (was
Starting Battery System C1)
C01_7 d/w - 10h/d - No HK Hols54
- No B/O periods
0 (was
22-Mar-22
C1) A 14-May-22 24-Apr-22 11-Jun-22 28

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:44
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 164 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L992.24.B02Prepare and submit info. of Starting Battery System C01_7 d/w - 10h/d - No HK 7 22-Mar-22 A 02-Apr-22 24-Apr-22 30-Apr-22 28
Hols - No B/O periods (was
310.D.WS.L993.24.B02Review and comment info. of Starting Battery System C1)
C01_7 d/w - 10h/d - No HK 24 03-Apr-22 26-Apr-22 01-May-22 24-May-22 28
Hols - No B/O periods (was
310.D.WS.L994.24.B02Prepare and re-submit info. of Starting Battery System C1)
C01_7 d/w - 10h/d - No HK 9 27-Apr-22 05-May-22 25-May-22 02-Jun-22 28
Hols - No B/O periods (was
310.D.WS.L996.24.B02Obtain "No objection" of Starting Battery System C1)
C01_7 d/w - 10h/d - No HK 9 06-May-22 14-May-22 03-Jun-22 11-Jun-22 28
Hols - No B/O periods (was
Battery Charger C1)
C01_7 d/w - 10h/d - No HK Hols54
- No B/O periods
0 (was
22-Mar-22
C1) A 14-May-22 24-Apr-22 11-Jun-22 28
310.D.WS.L992.25.B02Prepare and submit info. of Battery Charger C01_7 d/w - 10h/d - No HK 7 22-Mar-22 A 02-Apr-22 24-Apr-22 30-Apr-22 28
Hols - No B/O periods (was
310.D.WS.L993.25.B02Review and comment info. of Battery Charger C1)
C01_7 d/w - 10h/d - No HK 24 03-Apr-22 26-Apr-22 01-May-22 24-May-22 28
Hols - No B/O periods (was
310.D.WS.L994.25.B02Prepare and re-submit info. of Battery Charger C1)
C01_7 d/w - 10h/d - No HK 9 27-Apr-22 05-May-22 25-May-22 02-Jun-22 28
Hols - No B/O periods (was
310.D.WS.L996.25.B02Obtain "No objection" of Battery Charger C1)
C01_7 d/w - 10h/d - No HK 9 06-May-22 14-May-22 03-Jun-22 11-Jun-22 28
Hols - No B/O periods (was
MVAC C1)
C01_7 d/w - 10h/d - No HK Hols115
- No B/O periods
0 (was
08-Feb-22
C1) A 26-Jun-22 02-Apr-22 23-Aug-22 58
CRAC Unit C01_7 d/w - 10h/d - No HK Hols72
- No B/O periods
0 (was
04-Mar-22
C1) A 14-May-22 03-May-22 20-Jun-22 37
310.D.WS.L992.26.B02Prepare and submit info. of CRAC Unit C01_7 d/w - 10h/d - No HK 7 04-Mar-22 A 02-Apr-22 03-May-22 09-May-22 37
Hols - No B/O periods (was
310.D.WS.L993.26.B02Review and comment info. of CRAC Unit C1)
C01_7 d/w - 10h/d - No HK 24 03-Apr-22 26-Apr-22 10-May-22 02-Jun-22 37
Hols - No B/O periods (was
310.D.WS.L994.26.B02Prepare and re-submit info. of CRAC Unit C1)
C01_7 d/w - 10h/d - No HK 9 27-Apr-22 05-May-22 03-Jun-22 11-Jun-22 37
Hols - No B/O periods (was
310.D.WS.L996.26.B02Obtain "No objection" of CRAC Unit C1)
C01_7 d/w - 10h/d - No HK 9 06-May-22 14-May-22 12-Jun-22 20-Jun-22 37
Hols - No B/O periods (was
Axial Fan C1)
C01_7 d/w - 10h/d - No HK Hols69
- No B/O periods
0 (was
04-Mar-22
C1) A 11-May-22 02-Apr-22 17-May-22 6
310.D.WS.L992.27.B02Prepare and submit info. of Axial Fan C01_7 d/w - 10h/d - No HK 4 04-Mar-22 A 30-Mar-22 02-Apr-22 05-Apr-22 6
Hols - No B/O periods (was
310.D.WS.L993.27.B02Review and comment info. of Axial Fan C1)
C01_7 d/w - 10h/d - No HK 24 31-Mar-22 23-Apr-22 06-Apr-22 29-Apr-22 6
Hols - No B/O periods (was
310.D.WS.L994.27.B02Prepare and re-submit info. of Axial Fan C1)
C01_7 d/w - 10h/d - No HK 9 24-Apr-22 02-May-22 30-Apr-22 08-May-22 6
Hols - No B/O periods (was
310.D.WS.L996.27.B02Obtain "No objection" of Axial Fan C1)
C01_7 d/w - 10h/d - No HK 9 03-May-22 11-May-22 09-May-22 17-May-22 6
Hols - No B/O periods (was
Centrifugal Fan C1)
C01_7 d/w - 10h/d - No HK Hols71
- No B/O periods
0 (was
04-Mar-22
C1) A 13-May-22 07-Jul-22 23-Aug-22 102
310.D.WS.L992.28.B02Prepare and submit info. of Centrifugal Fan C01_7 d/w - 10h/d - No HK 6 04-Mar-22 A 01-Apr-22 07-Jul-22 12-Jul-22 102
Hols - No B/O periods (was
310.D.WS.L993.28.B02Review and comment info. of Centrifugal Fan C1)
C01_7 d/w - 10h/d - No HK 24 02-Apr-22 25-Apr-22 13-Jul-22 05-Aug-22 102
Hols - No B/O periods (was
310.D.WS.L994.28.B02Prepare and re-submit info. of Centrifugal Fan C1)
C01_7 d/w - 10h/d - No HK 9 26-Apr-22 04-May-22 06-Aug-22 14-Aug-22 102
Hols - No B/O periods (was
310.D.WS.L996.28.B02Obtain "No objection" of Centrifugal Fan C1)
C01_7 d/w - 10h/d - No HK 9 05-May-22 13-May-22 15-Aug-22 23-Aug-22 102
Hols - No B/O periods (was
In-line Fan C1)
C01_7 d/w - 10h/d - No HK Hols59
- No B/O periods
0 (was27-Mar-22
C1) 24-May-22 08-May-22 05-Jul-22 42
310.D.WS.L992.29.B02Prepare and submit info. of In-line Fan C01_7 d/w - 10h/d - No HK 17 27-Mar-22 12-Apr-22 08-May-22 24-May-22 42
Hols - No B/O periods (was
310.D.WS.L993.29.B02Review and comment info. of In-line Fan C1)
C01_7 d/w - 10h/d - No HK 24 13-Apr-22 06-May-22 25-May-22 17-Jun-22 42
Hols - No B/O periods (was
C1)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 165 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L994.29.B02Prepare and re-submit info. of In-line Fan C01_7 d/w - 10h/d - No HK 9 07-May-22 15-May-22 18-Jun-22 26-Jun-22 42
Hols - No B/O periods (was
310.D.WS.L996.29.B02Obtain "No objection" of In-line Fan C1)
C01_7 d/w - 10h/d - No HK 9 16-May-22 24-May-22 27-Jun-22 05-Jul-22 42
Hols - No B/O periods (was
Split Type & VRV AC Unit C1)
C01_7 d/w - 10h/d - No HK Hols72
- No B/O periods
0 (was
04-Mar-22
C1) A 14-May-22 19-Apr-22 06-Jun-22 23
310.D.WS.L992.30.B02Prepare and submit info. of Split Type & VRV AC Unit C01_7 d/w - 10h/d - No HK 7 04-Mar-22 A 02-Apr-22 19-Apr-22 25-Apr-22 23
Hols - No B/O periods (was
310.D.WS.L993.30.B02Review and comment info. of Split Type & VRV AC Unit C1)
C01_7 d/w - 10h/d - No HK 24 03-Apr-22 26-Apr-22 26-Apr-22 19-May-22 23
Hols - No B/O periods (was
310.D.WS.L994.30.B02Prepare and re-submit info. of Split Type & VRV AC Unit C1)
C01_7 d/w - 10h/d - No HK 9 27-Apr-22 05-May-22 20-May-22 28-May-22 23
Hols - No B/O periods (was
310.D.WS.L996.30.B02Obtain "No objection" of Split Type & VRV AC Unit C1)
C01_7 d/w - 10h/d - No HK 9 06-May-22 14-May-22 29-May-22 06-Jun-22 23
Hols - No B/O periods (was
Tunnel Jet Fan C1)
C01_7 d/w - 10h/d - No HK Hols54
- No B/O periods
0 (was
04-Apr-22
C1) A 27-May-22 23-Jun-22 23-Aug-22 88
310.D.WS.L992.31.B02Prepare and submit info. of Tunnel Jet Fan C01_7 d/w - 10h/d - No HK 20 04-Apr-22 A 15-Apr-22 23-Jun-22 12-Jul-22 88
Hols - No B/O periods (was
310.D.WS.L993.31.B02Review and comment info. of Tunnel Jet Fan C1)
C01_7 d/w - 10h/d - No HK 24 16-Apr-22 09-May-22 13-Jul-22 05-Aug-22 88
Hols - No B/O periods (was
310.D.WS.L994.31.B02Prepare and re-submit info. of Tunnel Jet Fan C1)
C01_7 d/w - 10h/d - No HK 9 10-May-22 18-May-22 06-Aug-22 14-Aug-22 88
Hols - No B/O periods (was
310.D.WS.L996.31.B02Obtain "No objection" of Tunnel Jet Fan C1)
C01_7 d/w - 10h/d - No HK 9 19-May-22 27-May-22 15-Aug-22 23-Aug-22 88
Hols - No B/O periods (was
Package Fresh Air Processing Unit C1)
C01_7 d/w - 10h/d - No HK Hols72
- No B/O periods
0 (was
04-Mar-22
C1) A 14-May-22 19-Apr-22 06-Jun-22 23
310.D.WS.L992.32.B02Prepare and submit info. of Package Fresh Air Processing Unit C01_7 d/w - 10h/d - No HK 7 04-Mar-22 A 02-Apr-22 19-Apr-22 25-Apr-22 23
Hols - No B/O periods (was
310.D.WS.L993.32.B02Review and comment info. of Package Fresh Air Processing Unit C1)
C01_7 d/w - 10h/d - No HK 24 03-Apr-22 26-Apr-22 26-Apr-22 19-May-22 23
Hols - No B/O periods (was
310.D.WS.L994.32.B02Prepare and re-submit info. of Package Fresh Air Processing Unit C1)
C01_7 d/w - 10h/d - No HK 9 27-Apr-22 05-May-22 20-May-22 28-May-22 23
Hols - No B/O periods (was
310.D.WS.L996.32.B02Obtain "No objection" of Package Fresh Air Processing Unit C1)
C01_7 d/w - 10h/d - No HK 9 06-May-22 14-May-22 29-May-22 06-Jun-22 23
Hols - No B/O periods (was
Motor Control Centre C1)
C01_7 d/w - 10h/d - No HK Hols55
- No B/O periods
0 (was27-Mar-22
C1) 20-May-22 12-May-22 05-Jul-22 46
310.D.WS.L992.33.B02Prepare and submit info. of Motor Control Centre C01_7 d/w - 10h/d - No HK 13 27-Mar-22 08-Apr-22 12-May-22 24-May-22 46
Hols - No B/O periods (was
310.D.WS.L993.33.B02Review and comment info. of Motor Control Centre C1)
C01_7 d/w - 10h/d - No HK 24 09-Apr-22 02-May-22 25-May-22 17-Jun-22 46
Hols - No B/O periods (was
310.D.WS.L994.33.B02Prepare and re-submit info. of Motor Control Centre C1)
C01_7 d/w - 10h/d - No HK 9 03-May-22 11-May-22 18-Jun-22 26-Jun-22 46
Hols - No B/O periods (was
310.D.WS.L996.33.B02Obtain "No objection" of Motor Control Centre C1)
C01_7 d/w - 10h/d - No HK 9 12-May-22 20-May-22 27-Jun-22 05-Jul-22 46
Hols - No B/O periods (was
Local Motor Control Panel C1)
C01_7 d/w - 10h/d - No HK Hols59
- No B/O periods
0 (was27-Mar-22
C1) 24-May-22 30-Apr-22 27-Jun-22 34
310.D.WS.L992.34.B02Prepare and submit info. of Local Motor Control Panel C01_7 d/w - 10h/d - No HK 17 27-Mar-22 12-Apr-22 30-Apr-22 16-May-22 34
Hols - No B/O periods (was
310.D.WS.L993.34.B02Review and comment info. of Local Motor Control Panel C1)
C01_7 d/w - 10h/d - No HK 24 13-Apr-22 06-May-22 17-May-22 09-Jun-22 34
Hols - No B/O periods (was
310.D.WS.L994.34.B02Prepare and re-submit info. of Local Motor Control Panel C1)
C01_7 d/w - 10h/d - No HK 9 07-May-22 15-May-22 10-Jun-22 18-Jun-22 34
Hols - No B/O periods (was
310.D.WS.L996.34.B02Obtain "No objection" of Local Motor Control Panel C1)
C01_7 d/w - 10h/d - No HK 9 16-May-22 24-May-22 19-Jun-22 27-Jun-22 34
Hols - No B/O periods (was
MFSD C1)
C01_7 d/w - 10h/d - No HK Hols72
- No B/O periods
0 (was
04-Mar-22
C1) A 14-May-22 10-May-22 27-Jun-22 44

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 166 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L992.35.B02Prepare and submit info. of MFSD C01_7 d/w - 10h/d - No HK 7 04-Mar-22 A 02-Apr-22 10-May-22 16-May-22 44
Hols - No B/O periods (was
310.D.WS.L993.35.B02Review and comment info. of MSD C1)
C01_7 d/w - 10h/d - No HK 24 03-Apr-22 26-Apr-22 17-May-22 09-Jun-22 44
Hols - No B/O periods (was
310.D.WS.L994.35.B02Prepare and re-submit info. of MSD C1)
C01_7 d/w - 10h/d - No HK 9 27-Apr-22 05-May-22 10-Jun-22 18-Jun-22 44
Hols - No B/O periods (was
310.D.WS.L996.35.B02Obtain "No objection" of MSD C1)
C01_7 d/w - 10h/d - No HK 9 06-May-22 14-May-22 19-Jun-22 27-Jun-22 44
Hols - No B/O periods (was
Fire Damper C1)
C01_7 d/w - 10h/d - No HK Hols72
- No B/O periods
0 (was
04-Mar-22
C1) A 14-May-22 19-Apr-22 06-Jun-22 23
310.D.WS.L992.36.B02Prepare and submit info. of Fire Damper C01_7 d/w - 10h/d - No HK 7 04-Mar-22 A 02-Apr-22 19-Apr-22 25-Apr-22 23
Hols - No B/O periods (was
310.D.WS.L993.36.B02Review and comment info. of Fire Damper C1)
C01_7 d/w - 10h/d - No HK 24 03-Apr-22 26-Apr-22 26-Apr-22 19-May-22 23
Hols - No B/O periods (was
310.D.WS.L994.36.B02Prepare and re-submit info. of Fire Damper C1)
C01_7 d/w - 10h/d - No HK 9 27-Apr-22 05-May-22 20-May-22 28-May-22 23
Hols - No B/O periods (was
310.D.WS.L996.36.B02Obtain "No objection" of Fire Damper C1)
C01_7 d/w - 10h/d - No HK 9 06-May-22 14-May-22 29-May-22 06-Jun-22 23
Hols - No B/O periods (was
Air Grille & Accessories C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was21-Apr-22
C1) 26-Jun-22 22-Apr-22 27-Jun-22 1
310.D.WS.L992.37.B02Prepare and submit info. of Air Grille & Accessories C01_7 d/w - 10h/d - No HK 25 21-Apr-22 15-May-22 22-Apr-22 16-May-22 1
Hols - No B/O periods (was
310.D.WS.L993.37.B02Review and comment info. of Air Grille & Accessories C1)
C01_7 d/w - 10h/d - No HK 24 16-May-22 08-Jun-22 17-May-22 09-Jun-22 1
Hols - No B/O periods (was
310.D.WS.L994.37.B02Prepare and re-submit info. of Air Grille & Accessories C1)
C01_7 d/w - 10h/d - No HK 9 09-Jun-22 17-Jun-22 10-Jun-22 18-Jun-22 1
Hols - No B/O periods (was
310.D.WS.L996.37.B02Obtain "No objection" of Air Grille & Accessories C1)
C01_7 d/w - 10h/d - No HK 9 18-Jun-22 26-Jun-22 19-Jun-22 27-Jun-22 1
Hols - No B/O periods (was
G.I. Sheet Ductwork & Accessories C1)
C01_7 d/w - 10h/d - No HK Hols58
- No B/O periods
0 (was
08-Feb-22
C1) A 23-Mar-22 A 18-May-22 18-May-22
310.D.WS.L992.38.B02Prepare and submit info. of G.I. Sheet Ductwork & Accessories C01_7 d/w - 10h/d - No HK 0 08-Feb-22 A 04-Mar-22 A 18-May-22 18-May-22
Hols - No B/O periods (was
310.D.WS.L993.38.B02Review and comment info. of G.I. Sheet Ductwork & Accessories C1)
C01_7 d/w - 10h/d - No HK 0 05-Mar-22 A 23-Mar-22 A 18-May-22 18-May-22
Hols - No B/O periods (was
310.D.WS.L994.38.B02Prepare and re-submit info. of G.I. Sheet Ductwork & Accessories C1)
C01_7 d/w - 10h/d - No HK 0 23-Mar-22 A 23-Mar-22 A 18-May-22 18-May-22
Hols - No B/O periods (was
310.D.WS.L996.38.B02Obtain "No objection" of G.I. Sheet Ductwork & Accessories C1)
C01_7 d/w - 10h/d - No HK 0 23-Mar-22 A 23-Mar-22 A 18-May-22 18-May-22
Hols - No B/O periods (was
Refrigerant Pipework & Fittings C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was07-Apr-22
C1) 12-Jun-22 22-Apr-22 27-Jun-22 15
310.D.WS.L992.39.B02Prepare and submit info. of Refrigerant Pipework & Fittings C01_7 d/w - 10h/d - No HK 25 07-Apr-22 01-May-22 22-Apr-22 16-May-22 15
Hols - No B/O periods (was
310.D.WS.L993.39.B02Review and comment info. of Refrigerant Pipework & Fittings C1)
C01_7 d/w - 10h/d - No HK 24 02-May-22 25-May-22 17-May-22 09-Jun-22 15
Hols - No B/O periods (was
310.D.WS.L994.39.B02Prepare and re-submit info. of Refrigerant Pipework & Fittings C1)
C01_7 d/w - 10h/d - No HK 9 26-May-22 03-Jun-22 10-Jun-22 18-Jun-22 15
Hols - No B/O periods (was
310.D.WS.L996.39.B02Obtain "No objection" of Refrigerant Pipework & Fittings C1)
C01_7 d/w - 10h/d - No HK 9 04-Jun-22 12-Jun-22 19-Jun-22 27-Jun-22 15
Hols - No B/O periods (was
Fire Services C1)
C01_7 d/w - 10h/d - No HK Hols221
- No B/O periods
0 (was10-Apr-22
C1) 16-Nov-22 13-Apr-22 11-Mar-23 115
Hose Reel Set C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was30-Apr-22
C1) 05-Jul-22 26-May-22 31-Jul-22 26
310.D.WS.L992.40.B02Prepare and submit info. of Hose Reel Set C01_7 d/w - 10h/d - No HK 25 30-Apr-22 24-May-22 26-May-22 19-Jun-22 26
Hols - No B/O periods (was
310.D.WS.L993.40.B02Review and comment info. of Hose Reel Set C1)
C01_7 d/w - 10h/d - No HK 24 25-May-22 17-Jun-22 20-Jun-22 13-Jul-22 26
Hols - No B/O periods (was
C1)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 167 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L994.40.B02Prepare and re-submit info. of Hose Reel Set C01_7 d/w - 10h/d - No HK 9 18-Jun-22 26-Jun-22 14-Jul-22 22-Jul-22 26
Hols - No B/O periods (was
310.D.WS.L996.40.B02Obtain "No objection" of Hose Reel Set C1)
C01_7 d/w - 10h/d - No HK 9 27-Jun-22 05-Jul-22 23-Jul-22 31-Jul-22 26
Hols - No B/O periods (was
Fire Hydrant C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was30-Apr-22
C1) 05-Jul-22 26-May-22 31-Jul-22 26
310.D.WS.L992.41.B02Prepare and submit info. of Fire Hydrant C01_7 d/w - 10h/d - No HK 25 30-Apr-22 24-May-22 26-May-22 19-Jun-22 26
Hols - No B/O periods (was
310.D.WS.L993.41.B02Review and comment info. of Fire Hydrant C1)
C01_7 d/w - 10h/d - No HK 24 25-May-22 17-Jun-22 20-Jun-22 13-Jul-22 26
Hols - No B/O periods (was
310.D.WS.L994.41.B02Prepare and re-submit info. of Fire Hydrant C1)
C01_7 d/w - 10h/d - No HK 9 18-Jun-22 26-Jun-22 14-Jul-22 22-Jul-22 26
Hols - No B/O periods (was
310.D.WS.L996.41.B02Obtain "No objection" of Fire Hydrant C1)
C01_7 d/w - 10h/d - No HK 9 27-Jun-22 05-Jul-22 23-Jul-22 31-Jul-22 26
Hols - No B/O periods (was
Sprinkler Head (All type) C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was05-May-22
C1) 10-Jul-22 26-May-22 31-Jul-22 21
310.D.WS.L992.42.B02Prepare and submit info. of Sprinkler Head (All type) C01_7 d/w - 10h/d - No HK 25 05-May-22 29-May-22 26-May-22 19-Jun-22 21
Hols - No B/O periods (was
310.D.WS.L993.42.B02Review and comment info. of Sprinkler Head (All type) C1)
C01_7 d/w - 10h/d - No HK 24 30-May-22 22-Jun-22 20-Jun-22 13-Jul-22 21
Hols - No B/O periods (was
310.D.WS.L994.42.B02Prepare and re-submit info. of Sprinkler Head (All type) C1)
C01_7 d/w - 10h/d - No HK 9 23-Jun-22 01-Jul-22 14-Jul-22 22-Jul-22 21
Hols - No B/O periods (was
310.D.WS.L996.42.B02Obtain "No objection" of Sprinkler Head (All type) C1)
C01_7 d/w - 10h/d - No HK 9 02-Jul-22 10-Jul-22 23-Jul-22 31-Jul-22 21
Hols - No B/O periods (was
MCC/ LMCP C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was14-May-22
C1) 19-Jul-22 02-Jun-22 07-Aug-22 19
310.D.WS.L992.43.B02Prepare and submit info. of MCC/ LMCP C01_7 d/w - 10h/d - No HK 25 14-May-22 07-Jun-22 02-Jun-22 26-Jun-22 19
Hols - No B/O periods (was
310.D.WS.L993.43.B02Review and comment info. of MCC/ LMCP C1)
C01_7 d/w - 10h/d - No HK 24 08-Jun-22 01-Jul-22 27-Jun-22 20-Jul-22 19
Hols - No B/O periods (was
310.D.WS.L994.43.B02Prepare and re-submit info. of MCC/ LMCP C1)
C01_7 d/w - 10h/d - No HK 9 02-Jul-22 10-Jul-22 21-Jul-22 29-Jul-22 19
Hols - No B/O periods (was
310.D.WS.L996.43.B02Obtain "No objection" of MCC/ LMCP C1)
C01_7 d/w - 10h/d - No HK 9 11-Jul-22 19-Jul-22 30-Jul-22 07-Aug-22 19
Hols - No B/O periods (was
Fire Hydrant and Hosereel Pump C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was29-May-22
C1) 03-Aug-22 12-Aug-22 17-Oct-22 75
310.D.WS.L992.44.B02Prepare and submit info. of Fire Hydrant and Hosereel Pump C01_7 d/w - 10h/d - No HK 25 29-May-22 22-Jun-22 12-Aug-22 05-Sep-22 75
Hols - No B/O periods (was
310.D.WS.L993.44.B02Review and comment info. of Fire Hydrant and Hosereel Pump C1)
C01_7 d/w - 10h/d - No HK 24 23-Jun-22 16-Jul-22 06-Sep-22 29-Sep-22 75
Hols - No B/O periods (was
310.D.WS.L994.44.B02Prepare and re-submit info. of Fire Hydrant and Hosereel Pump C1)
C01_7 d/w - 10h/d - No HK 9 17-Jul-22 25-Jul-22 30-Sep-22 08-Oct-22 75
Hols - No B/O periods (was
310.D.WS.L996.44.B02Obtain "No objection" of Fire Hydrant and Hosereel Pump C1)
C01_7 d/w - 10h/d - No HK 9 26-Jul-22 03-Aug-22 09-Oct-22 17-Oct-22 75
Hols - No B/O periods (was
FS Jockey Pump C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was29-May-22
C1) 03-Aug-22 05-Jul-22 09-Sep-22 37
310.D.WS.L992.45.B02Prepare and submit info. of FS Jockey Pump C01_7 d/w - 10h/d - No HK 25 29-May-22 22-Jun-22 05-Jul-22 29-Jul-22 37
Hols - No B/O periods (was
310.D.WS.L993.45.B02Review and comment info. of FS Jockey Pump C1)
C01_7 d/w - 10h/d - No HK 24 23-Jun-22 16-Jul-22 30-Jul-22 22-Aug-22 37
Hols - No B/O periods (was
310.D.WS.L994.45.B02Prepare and re-submit info. of FS Jockey Pump C1)
C01_7 d/w - 10h/d - No HK 9 17-Jul-22 25-Jul-22 23-Aug-22 31-Aug-22 37
Hols - No B/O periods (was
310.D.WS.L996.45.B02Obtain "No objection" of FS Jockey Pump C1)
C01_7 d/w - 10h/d - No HK 9 26-Jul-22 03-Aug-22 01-Sep-22 09-Sep-22 37
Hols - No B/O periods (was
Fixed Foam System Water Pump C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was29-May-22
C1) 03-Aug-22 28-Jul-22 02-Oct-22 60

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 168 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L992.46.B02Prepare and submit info. of Fixed Foam System Water Pump C01_7 d/w - 10h/d - No HK 25 29-May-22 22-Jun-22 28-Jul-22 21-Aug-22 60
Hols - No B/O periods (was
310.D.WS.L993.46.B02Review and comment info. of Fixed Foam System Water Pump C1)
C01_7 d/w - 10h/d - No HK 24 23-Jun-22 16-Jul-22 22-Aug-22 14-Sep-22 60
Hols - No B/O periods (was
310.D.WS.L994.46.B02Prepare and re-submit info. of Fixed Foam System Water Pump C1)
C01_7 d/w - 10h/d - No HK 9 17-Jul-22 25-Jul-22 15-Sep-22 23-Sep-22 60
Hols - No B/O periods (was
310.D.WS.L996.46.B02Obtain "No objection" of Fixed Foam System Water Pump C1)
C01_7 d/w - 10h/d - No HK 9 26-Jul-22 03-Aug-22 24-Sep-22 02-Oct-22 60
Hols - No B/O periods (was
Fixed Foam System Jockey Pump C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was29-May-22
C1) 03-Aug-22 28-Jul-22 02-Oct-22 60
310.D.WS.L992.47.B02Prepare and submit info. of Fixed Foam System Jockey Pump C01_7 d/w - 10h/d - No HK 25 29-May-22 22-Jun-22 28-Jul-22 21-Aug-22 60
Hols - No B/O periods (was
310.D.WS.L993.47.B02Review and comment info. of Fixed Foam System Jockey Pump C1)
C01_7 d/w - 10h/d - No HK 24 23-Jun-22 16-Jul-22 22-Aug-22 14-Sep-22 60
Hols - No B/O periods (was
310.D.WS.L994.47.B02Prepare and re-submit info. of Fixed Foam System Jockey Pump C1)
C01_7 d/w - 10h/d - No HK 9 17-Jul-22 25-Jul-22 15-Sep-22 23-Sep-22 60
Hols - No B/O periods (was
310.D.WS.L996.47.B02Obtain "No objection" of Fixed Foam System Jockey Pump C1)
C01_7 d/w - 10h/d - No HK 9 26-Jul-22 03-Aug-22 24-Sep-22 02-Oct-22 60
Hols - No B/O periods (was
G.I. Pipe & Fittings C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was22-May-22
C1) 27-Jul-22 02-Jun-22 07-Aug-22 11
310.D.WS.L992.48.B02Prepare and submit info. of G.I. Pipe & Fittings C01_7 d/w - 10h/d - No HK 25 22-May-22 15-Jun-22 02-Jun-22 26-Jun-22 11
Hols - No B/O periods (was
310.D.WS.L993.48.B02Review and comment info. of G.I. Pipe & Fittings C1)
C01_7 d/w - 10h/d - No HK 24 16-Jun-22 09-Jul-22 27-Jun-22 20-Jul-22 11
Hols - No B/O periods (was
310.D.WS.L994.48.B02Prepare and re-submit info. of G.I. Pipe & Fittings C1)
C01_7 d/w - 10h/d - No HK 9 10-Jul-22 18-Jul-22 21-Jul-22 29-Jul-22 11
Hols - No B/O periods (was
310.D.WS.L996.48.B02Obtain "No objection" of G.I. Pipe & Fittings C1)
C01_7 d/w - 10h/d - No HK 9 19-Jul-22 27-Jul-22 30-Jul-22 07-Aug-22 11
Hols - No B/O periods (was
Automatic Fire Alarm Control Panel C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was10-Apr-22
C1) 15-Jun-22 16-Apr-22 21-Jun-22 6
310.D.WS.L992.49.B02Prepare and submit info. of Automatic Fire Alarm Control Panel C01_7 d/w - 10h/d - No HK 25 10-Apr-22 04-May-22 16-Apr-22 10-May-22 6
Hols - No B/O periods (was
310.D.WS.L993.49.B02Review and comment info. of Automatic Fire Alarm Control Panel C1)
C01_7 d/w - 10h/d - No HK 24 05-May-22 28-May-22 11-May-22 03-Jun-22 6
Hols - No B/O periods (was
310.D.WS.L994.49.B02Prepare and re-submit info. of Automatic Fire Alarm Control Panel C1)
C01_7 d/w - 10h/d - No HK 9 29-May-22 06-Jun-22 04-Jun-22 12-Jun-22 6
Hols - No B/O periods (was
310.D.WS.L996.49.B02Obtain "No objection" of Automatic Fire Alarm Control Panel C1)
C01_7 d/w - 10h/d - No HK 9 07-Jun-22 15-Jun-22 13-Jun-22 21-Jun-22 6
Hols - No B/O periods (was
Gas Flooding System C1)
C01_7 d/w - 10h/d - No HK Hols46
- No B/O periods
0 (was13-Apr-22
C1) 28-May-22 13-Apr-22 28-May-22 0
310.D.WS.L992.50.B02Prepare and submit info. of Gas Flooding System C01_7 d/w - 10h/d - No HK 14 13-Apr-22 26-Apr-22 13-Apr-22 26-Apr-22 0
Hols - No B/O periods (was
310.D.WS.L993.50.B02Review and comment info. of Gas Flooding System C1)
C01_7 d/w - 10h/d - No HK 14 27-Apr-22 10-May-22 27-Apr-22 10-May-22 0
Hols - No B/O periods (was
310.D.WS.L994.50.B02Prepare and re-submit info. of Gas Flooding System C1)
C01_7 d/w - 10h/d - No HK 9 11-May-22 19-May-22 11-May-22 19-May-22 0
Hols - No B/O periods (was
310.D.WS.L996.50.B02Obtain "No objection" of Gas Flooding System C1)
C01_7 d/w - 10h/d - No HK 9 20-May-22 28-May-22 20-May-22 28-May-22 0
Hols - No B/O periods (was
Automatic Sprinkler Pump C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was11-Sep-22
C1) 16-Nov-22 04-Jan-23 11-Mar-23 115
310.D.WS.L992.51.B02Prepare and submit info. of Automatic Sprinkler Pump C01_7 d/w - 10h/d - No HK 25 11-Sep-22 05-Oct-22 04-Jan-23 28-Jan-23 115
Hols - No B/O periods (was
310.D.WS.L993.51.B02Review and comment info. of Automatic Sprinkler Pump C1)
C01_7 d/w - 10h/d - No HK 24 06-Oct-22 29-Oct-22 29-Jan-23 21-Feb-23 115
Hols - No B/O periods (was
310.D.WS.L994.51.B02Prepare and re-submit info. of Automatic Sprinkler Pump C1)
C01_7 d/w - 10h/d - No HK 9 30-Oct-22 07-Nov-22 22-Feb-23 02-Mar-23 115
Hols - No B/O periods (was
C1)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 169 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L996.51.B02Obtain "No objection" of Automatic Sprinkler Pump C01_7 d/w - 10h/d - No HK 9 08-Nov-22 16-Nov-22 03-Mar-23 11-Mar-23 115
Hols - No B/O periods (was
Automatic Sprinkler Jockey Pump C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was11-Sep-22
C1) 16-Nov-22 25-Sep-22 30-Nov-22 14
310.D.WS.L992.52.B02Prepare and submit info. of Automatic Sprinkler Jockey Pump C01_7 d/w - 10h/d - No HK 25 11-Sep-22 05-Oct-22 25-Sep-22 19-Oct-22 14
Hols - No B/O periods (was
310.D.WS.L993.52.B02Review and comment info. of Automatic Sprinkler Jockey Pump C1)
C01_7 d/w - 10h/d - No HK 24 06-Oct-22 29-Oct-22 20-Oct-22 12-Nov-22 14
Hols - No B/O periods (was
310.D.WS.L994.52.B02Prepare and re-submit info. of Automatic Sprinkler Jockey Pump C1)
C01_7 d/w - 10h/d - No HK 9 30-Oct-22 07-Nov-22 13-Nov-22 21-Nov-22 14
Hols - No B/O periods (was
310.D.WS.L996.52.B02Obtain "No objection" of Automatic Sprinkler Jockey Pump C1)
C01_7 d/w - 10h/d - No HK 9 08-Nov-22 16-Nov-22 22-Nov-22 30-Nov-22 14
Hols - No B/O periods (was
Smoke Detector C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was10-May-22
C1) 15-Jul-22 15-May-22 20-Jul-22 5
310.D.WS.L992.53.B02Prepare and submit info. of Smoke Detector C01_7 d/w - 10h/d - No HK 25 10-May-22 03-Jun-22 15-May-22 08-Jun-22 5
Hols - No B/O periods (was
310.D.WS.L993.53.B02Review and comment info. of Smoke Detector C1)
C01_7 d/w - 10h/d - No HK 24 04-Jun-22 27-Jun-22 09-Jun-22 02-Jul-22 5
Hols - No B/O periods (was
310.D.WS.L994.53.B02Prepare and re-submit info. of Smoke Detector C1)
C01_7 d/w - 10h/d - No HK 9 28-Jun-22 06-Jul-22 03-Jul-22 11-Jul-22 5
Hols - No B/O periods (was
310.D.WS.L996.53.B02Obtain "No objection" of Smoke Detector C1)
C01_7 d/w - 10h/d - No HK 9 07-Jul-22 15-Jul-22 12-Jul-22 20-Jul-22 5
Hols - No B/O periods (was
Heat Detector C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was24-Jun-22
C1) 29-Aug-22 13-Jul-22 17-Sep-22 19
310.D.WS.L992.54.B02Prepare and submit info. of Heat Detector C01_7 d/w - 10h/d - No HK 25 24-Jun-22 18-Jul-22 13-Jul-22 06-Aug-22 19
Hols - No B/O periods (was
310.D.WS.L993.54.B02Review and comment info. of Heat Detector C1)
C01_7 d/w - 10h/d - No HK 24 19-Jul-22 11-Aug-22 07-Aug-22 30-Aug-22 19
Hols - No B/O periods (was
310.D.WS.L994.54.B02Prepare and re-submit info. of Heat Detector C1)
C01_7 d/w - 10h/d - No HK 9 12-Aug-22 20-Aug-22 31-Aug-22 08-Sep-22 19
Hols - No B/O periods (was
310.D.WS.L996.54.B02Obtain "No objection" of Heat Detector C1)
C01_7 d/w - 10h/d - No HK 9 21-Aug-22 29-Aug-22 09-Sep-22 17-Sep-22 19
Hols - No B/O periods (was
Cable Tray & Accessories C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was24-Jun-22
C1) 29-Aug-22 05-Jul-22 09-Sep-22 11
310.D.WS.L992.55.B02Prepare and submit info. of Cable Tray & Accessories C01_7 d/w - 10h/d - No HK 25 24-Jun-22 18-Jul-22 05-Jul-22 29-Jul-22 11
Hols - No B/O periods (was
310.D.WS.L993.55.B02Review and comment info. of Cable Tray & Accessories C1)
C01_7 d/w - 10h/d - No HK 24 19-Jul-22 11-Aug-22 30-Jul-22 22-Aug-22 11
Hols - No B/O periods (was
310.D.WS.L994.55.B02Prepare and re-submit info. of Cable Tray & Accessories C1)
C01_7 d/w - 10h/d - No HK 9 12-Aug-22 20-Aug-22 23-Aug-22 31-Aug-22 11
Hols - No B/O periods (was
310.D.WS.L996.55.B02Obtain "No objection" of Cable Tray & Accessories C1)
C01_7 d/w - 10h/d - No HK 9 21-Aug-22 29-Aug-22 01-Sep-22 09-Sep-22 11
Hols - No B/O periods (was
Conventional Linear Heat Control Panel C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was09-Sep-22
C1) 14-Nov-22 04-Jan-23 11-Mar-23 117
310.D.WS.L992.56.B02Prepare and submit info. of Conventional Linear Heat Control Panel C01_7 d/w - 10h/d - No HK 25 09-Sep-22 03-Oct-22 04-Jan-23 28-Jan-23 117
Hols - No B/O periods (was
310.D.WS.L993.56.B02Review and comment info. of Conventional Linear Heat Control Panel C1)
C01_7 d/w - 10h/d - No HK 24 04-Oct-22 27-Oct-22 29-Jan-23 21-Feb-23 117
Hols - No B/O periods (was
310.D.WS.L994.56.B02Prepare and re-submit info. of Conventional Linear Heat Control Panel C1)
C01_7 d/w - 10h/d - No HK 9 28-Oct-22 05-Nov-22 22-Feb-23 02-Mar-23 117
Hols - No B/O periods (was
310.D.WS.L996.56.B02Obtain "No objection" of Conventional Linear Heat Control Panel C1)
C01_7 d/w - 10h/d - No HK 9 06-Nov-22 14-Nov-22 03-Mar-23 11-Mar-23 117
Hols - No B/O periods (was
Linear Heat Detector C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was09-Sep-22
C1) 14-Nov-22 04-Jan-23 11-Mar-23 117
310.D.WS.L992.57.B02Prepare and submit info. of Linear Heat Detector C01_7 d/w - 10h/d - No HK 25 09-Sep-22 03-Oct-22 04-Jan-23 28-Jan-23 117
Hols - No B/O periods (was
C1)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 170 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L993.57.B02Review and comment info. of Linear Heat Detector C01_7 d/w - 10h/d - No HK 24 04-Oct-22 27-Oct-22 29-Jan-23 21-Feb-23 117
Hols - No B/O periods (was
310.D.WS.L994.57.B02Prepare and re-submit info. of Linear Heat Detector C1)
C01_7 d/w - 10h/d - No HK 9 28-Oct-22 05-Nov-22 22-Feb-23 02-Mar-23 117
Hols - No B/O periods (was
310.D.WS.L996.57.B02Obtain "No objection" of Linear Heat Detector C1)
C01_7 d/w - 10h/d - No HK 9 06-Nov-22 14-Nov-22 03-Mar-23 11-Mar-23 117
Hols - No B/O periods (was
PLC C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was11-May-22
C1) 16-Jul-22 15-May-22 20-Jul-22 4
310.D.WS.L992.58.B02Prepare and submit info. of PLC C01_7 d/w - 10h/d - No HK 25 11-May-22 04-Jun-22 15-May-22 08-Jun-22 4
Hols - No B/O periods (was
310.D.WS.L993.58.B02Review and comment info. of PLC C1)
C01_7 d/w - 10h/d - No HK 24 05-Jun-22 28-Jun-22 09-Jun-22 02-Jul-22 4
Hols - No B/O periods (was
310.D.WS.L994.58.B02Prepare and re-submit info. of PLC C1)
C01_7 d/w - 10h/d - No HK 9 29-Jun-22 07-Jul-22 03-Jul-22 11-Jul-22 4
Hols - No B/O periods (was
310.D.WS.L996.58.B02Obtain "No objection" of PLC C1)
C01_7 d/w - 10h/d - No HK 9 08-Jul-22 16-Jul-22 12-Jul-22 20-Jul-22 4
Hols - No B/O periods (was
Plumbing and Drainage C1)
C01_7 d/w - 10h/d - No HK Hols215
- No B/O periods
0 (was27-Mar-22
C1) 27-Oct-22 08-Apr-22 24-Jan-23 89
Fibreglass Tank C01_7 d/w - 10h/d - No HK Hols57
- No B/O periods
0 (was27-Mar-22
C1) 22-May-22 08-Apr-22 03-Jun-22 12
310.D.WS.L992.59.B02Prepare and submit info. of Fribreglass Tank C01_7 d/w - 10h/d - No HK 18 27-Mar-22 13-Apr-22 08-Apr-22 25-Apr-22 12
Hols - No B/O periods (was
310.D.WS.L993.59.B02Review and comment info. of Fribreglass Tank C1)
C01_7 d/w - 10h/d - No HK 21 14-Apr-22 04-May-22 26-Apr-22 16-May-22 12
Hols - No B/O periods (was
310.D.WS.L994.59.B02Prepare and re-submit info. of Fribreglass Tank C1)
C01_7 d/w - 10h/d - No HK 9 05-May-22 13-May-22 17-May-22 25-May-22 12
Hols - No B/O periods (was
310.D.WS.L996.59.B02Obtain "No objection" of Fribreglass Tank C1)
C01_7 d/w - 10h/d - No HK 9 14-May-22 22-May-22 26-May-22 03-Jun-22 12
Hols - No B/O periods (was
Pressure Vessel C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was13-Jun-22
C1) 18-Aug-22 05-Jul-22 09-Sep-22 22
310.D.WS.L992.60.B02Prepare and submit info. of Pressure Vessel C01_7 d/w - 10h/d - No HK 25 13-Jun-22 07-Jul-22 05-Jul-22 29-Jul-22 22
Hols - No B/O periods (was
310.D.WS.L993.60.B02Review and comment info. of Pressure Vessel C1)
C01_7 d/w - 10h/d - No HK 24 08-Jul-22 31-Jul-22 30-Jul-22 22-Aug-22 22
Hols - No B/O periods (was
310.D.WS.L994.60.B02Prepare and re-submit info. of Pressure Vessel C1)
C01_7 d/w - 10h/d - No HK 9 01-Aug-22 09-Aug-22 23-Aug-22 31-Aug-22 22
Hols - No B/O periods (was
310.D.WS.L996.60.B02Obtain "No objection" of Pressure Vessel C1)
C01_7 d/w - 10h/d - No HK 9 10-Aug-22 18-Aug-22 01-Sep-22 09-Sep-22 22
Hols - No B/O periods (was
Potable Water Booster Pump C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was29-May-22
C1) 03-Aug-22 19-Nov-22 24-Jan-23 174
310.D.WS.L992.61.B02Prepare and submit info. of Potable Water Booster Pump C01_7 d/w - 10h/d - No HK 25 29-May-22 22-Jun-22 19-Nov-22 13-Dec-22 174
Hols - No B/O periods (was
310.D.WS.L993.61.B02Review and comment info. of Potable Water Booster Pump C1)
C01_7 d/w - 10h/d - No HK 24 23-Jun-22 16-Jul-22 14-Dec-22 06-Jan-23 174
Hols - No B/O periods (was
310.D.WS.L994.61.B02Prepare and re-submit info. of Potable Water Booster Pump C1)
C01_7 d/w - 10h/d - No HK 9 17-Jul-22 25-Jul-22 07-Jan-23 15-Jan-23 174
Hols - No B/O periods (was
310.D.WS.L996.61.B02Obtain "No objection" of Potable Water Booster Pump C1)
C01_7 d/w - 10h/d - No HK 9 26-Jul-22 03-Aug-22 16-Jan-23 24-Jan-23 174
Hols - No B/O periods (was
Cleansing Water Booster Pump C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was29-May-22
C1) 03-Aug-22 05-Jul-22 09-Sep-22 37
310.D.WS.L992.62.B02Prepare and submit info. of Cleansing Water Booster Pump C01_7 d/w - 10h/d - No HK 25 29-May-22 22-Jun-22 05-Jul-22 29-Jul-22 37
Hols - No B/O periods (was
310.D.WS.L993.62.B02Review and comment info. of Cleansing Water Booster Pump C1)
C01_7 d/w - 10h/d - No HK 24 23-Jun-22 16-Jul-22 30-Jul-22 22-Aug-22 37
Hols - No B/O periods (was
310.D.WS.L994.62.B02Prepare and re-submit info. of Cleansing Water Booster Pump C1)
C01_7 d/w - 10h/d - No HK 9 17-Jul-22 25-Jul-22 23-Aug-22 31-Aug-22 37
Hols - No B/O periods (was
C1)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 171 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L996.62.B02Obtain "No objection" of Cleansing Water Booster Pump C01_7 d/w - 10h/d - No HK 9 26-Jul-22 03-Aug-22 01-Sep-22 09-Sep-22 37
Hols - No B/O periods (was
Flushing Water Booster Pump C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was29-May-22
C1) 03-Aug-22 31-Jul-22 05-Oct-22 63
310.D.WS.L992.63.B02Prepare and submit info. of Flushing Water Booster Pump C01_7 d/w - 10h/d - No HK 25 29-May-22 22-Jun-22 31-Jul-22 24-Aug-22 63
Hols - No B/O periods (was
310.D.WS.L993.63.B02Review and comment info. of Flushing Water Booster Pump C1)
C01_7 d/w - 10h/d - No HK 24 23-Jun-22 16-Jul-22 25-Aug-22 17-Sep-22 63
Hols - No B/O periods (was
310.D.WS.L994.63.B02Prepare and re-submit info. of Flushing Water Booster Pump C1)
C01_7 d/w - 10h/d - No HK 9 17-Jul-22 25-Jul-22 18-Sep-22 26-Sep-22 63
Hols - No B/O periods (was
310.D.WS.L996.63.B02Obtain "No objection" of Flushing Water Booster Pump C1)
C01_7 d/w - 10h/d - No HK 9 26-Jul-22 03-Aug-22 27-Sep-22 05-Oct-22 63
Hols - No B/O periods (was
Ductile Iron Pipe & Accessories C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was30-Apr-22
C1) 05-Jul-22 20-Sep-22 25-Nov-22 143
310.D.WS.L992.64.B02Prepare and submit info. of Ductile Iron Pipe & Accessories C01_7 d/w - 10h/d - No HK 25 30-Apr-22 24-May-22 20-Sep-22 14-Oct-22 143
Hols - No B/O periods (was
310.D.WS.L993.64.B02Review and comment info. of Ductile Iron Pipe & Accessories C1)
C01_7 d/w - 10h/d - No HK 24 25-May-22 17-Jun-22 15-Oct-22 07-Nov-22 143
Hols - No B/O periods (was
310.D.WS.L994.64.B02Prepare and re-submit info. of Ductile Iron Pipe & Accessories C1)
C01_7 d/w - 10h/d - No HK 9 18-Jun-22 26-Jun-22 08-Nov-22 16-Nov-22 143
Hols - No B/O periods (was
310.D.WS.L996.64.B02Obtain "No objection" of Ductile Iron Pipe & Accessories C1)
C01_7 d/w - 10h/d - No HK 9 27-Jun-22 05-Jul-22 17-Nov-22 25-Nov-22 143
Hols - No B/O periods (was
Epoxy Cast Iron Pipe & Accessories C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was30-Apr-22
C1) 05-Jul-22 08-May-22 13-Jul-22 8
310.D.WS.L992.65.B02Prepare and submit info. of Epoxy Cast Iron Pipe & Accessories C01_7 d/w - 10h/d - No HK 25 30-Apr-22 24-May-22 08-May-22 01-Jun-22 8
Hols - No B/O periods (was
310.D.WS.L993.65.B02Review and comment info. of Epoxy Cast Iron Pipe & Accessories C1)
C01_7 d/w - 10h/d - No HK 24 25-May-22 17-Jun-22 02-Jun-22 25-Jun-22 8
Hols - No B/O periods (was
310.D.WS.L994.65.B02Prepare and re-submit info. of Epoxy Cast Iron Pipe & Accessories C1)
C01_7 d/w - 10h/d - No HK 9 18-Jun-22 26-Jun-22 26-Jun-22 04-Jul-22 8
Hols - No B/O periods (was
310.D.WS.L996.65.B02Obtain "No objection" of Epoxy Cast Iron Pipe & Accessories C1)
C01_7 d/w - 10h/d - No HK 9 27-Jun-22 05-Jul-22 05-Jul-22 13-Jul-22 8
Hols - No B/O periods (was
Local Motor Control Panel C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was13-Jun-22
C1) 18-Aug-22 05-Jul-22 09-Sep-22 22
310.D.WS.L992.66.B02Prepare and submit info. of Local Motor Control Panel C01_7 d/w - 10h/d - No HK 25 13-Jun-22 07-Jul-22 05-Jul-22 29-Jul-22 22
Hols - No B/O periods (was
310.D.WS.L993.66.B02Review and comment info. of Local Motor Control Panel C1)
C01_7 d/w - 10h/d - No HK 24 08-Jul-22 31-Jul-22 30-Jul-22 22-Aug-22 22
Hols - No B/O periods (was
310.D.WS.L994.66.B02Prepare and re-submit info. of Local Motor Control Panel C1)
C01_7 d/w - 10h/d - No HK 9 01-Aug-22 09-Aug-22 23-Aug-22 31-Aug-22 22
Hols - No B/O periods (was
310.D.WS.L996.66.B02Obtain "No objection" of Local Motor Control Panel C1)
C01_7 d/w - 10h/d - No HK 9 10-Aug-22 18-Aug-22 01-Sep-22 09-Sep-22 22
Hols - No B/O periods (was
Sump Pump C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was22-Aug-22
C1) 27-Oct-22 20-Sep-22 25-Nov-22 29
310.D.WS.L992.67.B02Prepare and submit info. of Sump Pump C01_7 d/w - 10h/d - No HK 25 22-Aug-22 15-Sep-22 20-Sep-22 14-Oct-22 29
Hols - No B/O periods (was
310.D.WS.L993.67.B02Review and comment info. of Sump Pump C1)
C01_7 d/w - 10h/d - No HK 24 16-Sep-22 09-Oct-22 15-Oct-22 07-Nov-22 29
Hols - No B/O periods (was
310.D.WS.L994.67.B02Prepare and re-submit info. of Sump Pump C1)
C01_7 d/w - 10h/d - No HK 9 10-Oct-22 18-Oct-22 08-Nov-22 16-Nov-22 29
Hols - No B/O periods (was
310.D.WS.L996.67.B02Obtain "No objection" of Sump Pump C1)
C01_7 d/w - 10h/d - No HK 9 19-Oct-22 27-Oct-22 17-Nov-22 25-Nov-22 29
Hols - No B/O periods (was
Hammer Arrestor C1)
C01_7 d/w - 10h/d - No HK Hols67
- No B/O periods
0 (was27-Jun-22
C1) 01-Sep-22 31-Jul-22 05-Oct-22 34
310.D.WS.L992.68.B02Prepare and submit info. of Hammer Arrestor C01_7 d/w - 10h/d - No HK 25 27-Jun-22 21-Jul-22 31-Jul-22 24-Aug-22 34
Hols - No B/O periods (was
C1)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 172 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L993.68.B02Review and comment info. of Hammer Arrestor C01_7 d/w - 10h/d - No HK 24 22-Jul-22 14-Aug-22 25-Aug-22 17-Sep-22 34
Hols - No B/O periods (was
310.D.WS.L994.68.B02Prepare and re-submit info. of Hammer Arrestor C1)
C01_7 d/w - 10h/d - No HK 9 15-Aug-22 23-Aug-22 18-Sep-22 26-Sep-22 34
Hols - No B/O periods (was
310.D.WS.L996.68.B02Obtain "No objection" of Hammer Arrestor C1)
C01_7 d/w - 10h/d - No HK 9 24-Aug-22 01-Sep-22 27-Sep-22 05-Oct-22 34
Hols - No B/O periods (was
CC#8 - Plate Load Test Method Statement C1)
C01_7 d/w - 10h/d - No HK Hols453
- No B/O periods
0 (was
31-Aug-21
C1) A 26-Nov-22 28-Mar-22 08-May-23 163
Method Statement for Plate Load Test for C&ED Operational Office and Kennel Area C01_7 d/w - 10h/d - No HK Hols58
- No B/O periods
0 (was23-May-22
C1) 19-Jul-22 30-Jul-22 25-Sep-22 68
310.D.TX.A220 Method Statement for Plate Load Test for C&ED Operational Office and Kennel Area -
C01_7 d/w - 10h/d - No HK 30 23-May-22 21-Jun-22 30-Jul-22 28-Aug-22 68
prepare document Hols - No B/O periods (was
310.D.TX.A224 Method Statement for Plate Load Test for C&ED Operational Office and Kennel Area - BD C1)
C01_7 d/w - 10h/d - No HK 28 22-Jun-22 19-Jul-22 29-Aug-22 25-Sep-22 68
Acknowledgement Hols - No B/O periods (was
Method Statement for Plate Load Test for WSA Comm. Equipment Building D C1)
C01_7 d/w - 10h/d - No HK Hols58
- No B/O periods
0 (was23-May-22
C1) 19-Jul-22 03-Jul-22 29-Aug-22 41
310.D.TX.A228 Method Statement for Plate Load Test for WSA Comm. Equipment Building D - prepare C01_7 d/w - 10h/d - No HK 30 23-May-22 21-Jun-22 03-Jul-22 01-Aug-22 41
document Hols - No B/O periods (was
310.D.TX.A232 Method Statement for Plate Load Test for WSA Comm. Equipment Building D - BD C1)
C01_7 d/w - 10h/d - No HK 28 22-Jun-22 19-Jul-22 02-Aug-22 29-Aug-22 41
Acknowledgement Hols - No B/O periods (was
Method Statement for Plate Load Test for ESA - GSE Vehicle Wash Facility C1)
C01_7 d/w - 10h/d - No HK Hols58
- No B/O periods
0 (was12-Jul-22
C1) 07-Sep-22 20-Jul-22 15-Sep-22 8
310.D.TX.A236 Method Statement for Plate Load Test for ESA - GSE Wash Facility - prepare document C01_7 d/w - 10h/d - No HK 30 12-Jul-22 10-Aug-22 20-Jul-22 18-Aug-22 8
Hols - No B/O periods (was
310.D.TX.A240 Method Statement for Plate Load Test for ESA - GSE Wash Facility - BD C1)
C01_7 d/w - 10h/d - No HK 28 11-Aug-22 07-Sep-22 19-Aug-22 15-Sep-22 8
Acknowledgement Hols - No B/O periods (was
Method Statement for Plate Load Test for WSA - GSE Battery Charging B C1)
C01_7 d/w - 10h/d - No HK Hols58
- No B/O periods
0 (was03-Apr-22
C1) 30-May-22 13-Jun-22 09-Aug-22 71
310.D.TX.A244 Method Statement for Plate Load Test for WSA - GSE Battery Charging - prepare C01_7 d/w - 10h/d - No HK 30 03-Apr-22 02-May-22 13-Jun-22 12-Jul-22 71
document Hols - No B/O periods (was
310.D.TX.A248 Method Statement for Plate Load Test for WSA - GSE Battery Charging - BD C1)
C01_7 d/w - 10h/d - No HK 28 03-May-22 30-May-22 13-Jul-22 09-Aug-22 71
Acknowledgement Hols - No B/O periods (was
MS for Plate Load Test for WSA - Maintenance Facilities Forecourt & Coach Staging A and Bus Stop C1)
C01_7 d/w - 10h/d - No HK Hols58
- No B/O periods
0 (was30-Sep-22
C1) 26-Nov-22 12-Mar-23 08-May-23 163
310.D.TX.A252 Method Statement for Plate Load Test for Maintenance Facilities Forecourt & Coach C01_7 d/w - 10h/d - No HK 30 30-Sep-22 29-Oct-22 12-Mar-23 10-Apr-23 163
Staging A - prepare document Hols - No B/O periods (was
310.D.TX.A256 Method Statement for Plate Load Test for Maintenance Facilities Forecourt & Coach C1)
C01_7 d/w - 10h/d - No HK 28 30-Oct-22 26-Nov-22 11-Apr-23 08-May-23 163
Staging A - BD Acknowledgement Hols - No B/O periods (was
Method Statement for Plate Load Test for WSA - Gate House B C1)
C01_7 d/w - 10h/d - No HK Hols58
- No B/O periods
0 (was03-Apr-22
C1) 30-May-22 22-May-22 18-Jul-22 49
310.D.TX.A260 Method Statement for Plate Load Test for WSA - Gate House B - prepare document C01_7 d/w - 10h/d - No HK 30 03-Apr-22 02-May-22 22-May-22 20-Jun-22 49
Hols - No B/O periods (was
310.D.TX.A264 Method Statement for Plate Load Test for WSA - Gate House B - BD Acknowledgement C1)
C01_7 d/w - 10h/d - No HK 28 03-May-22 30-May-22 21-Jun-22 18-Jul-22 49
Hols - No B/O periods (was
Method Statement for Plate Load Test for WSA - Screen Facilities C1)
C01_7 d/w - 10h/d - No HK Hols58
- No B/O periods
0 (was03-Apr-22
C1) 30-May-22 10-Jun-22 06-Aug-22 68
310.D.TX.A268 Method Statement for Plate Load Test for WSA - Screen Facilities - prepare document
C01_7 d/w - 10h/d - No HK 30 03-Apr-22 02-May-22 10-Jun-22 09-Jul-22 68
Hols - No B/O periods (was
310.D.TX.A272 Method Statement for Plate Load Test for WSA - Screen Facilities - BD Acknowledgement C1)
C01_7 d/w - 10h/d - No HK 28 03-May-22 30-May-22 10-Jul-22 06-Aug-22 68
Hols - No B/O periods (was
Method Statement for Plate Load Test for AGL Vault D Annex C1)
C01_7 d/w - 10h/d - No HK Hols180
- No B/O periods
0 (was
31-Aug-21
C1) A 07-Feb-22 A 28-Mar-22 05-Apr-22
310.D.TX.A276 Method Statement for Plate Load Test for AGL Vault D Annex - prepare document C01_7 d/w - 10h/d - No HK 30 31-Aug-21 A 17-Nov-21 A 28-Mar-22 28-Mar-22
Hols - No B/O periods (was
310.D.TX.A280.B01 Method Statement for Plate Load Test for AGL Vault D Annex - PM Review and C1)
C01_7 d/w - 10h/d - No HK 28 18-Nov-21 A 20-Jan-22 A 28-Mar-22 28-Mar-22
Acceptance Hols - No B/O periods (was
310.D.TX.A280 Method Statement for Plate Load Test for AGL Vault D Annex - BD Acknowledgement C1)
C01_7 d/w - 10h/d - No HK 28 20-Jan-22 A 07-Feb-22 A 05-Apr-22 05-Apr-22
Hols - No B/O periods (was
Method Statement for Plate Load Test for AGL Vault C Annex C1)
C01_7 d/w - 10h/d - No HK Hols87
- No B/O periods
0 (was
01-Nov-21
C1) A 02-Apr-22 15-Apr-22 10-May-22 38

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 173 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.TX.A284 Method Statement for Plate Load Test for AGL Vault C Annex - prepare document C01_7 d/w - 10h/d - No HK 30 01-Nov-21 A 17-Nov-21 A 15-Apr-22 15-Apr-22
Hols - No B/O periods (was
310.D.TX.A288.B01 Method Statement for Plate Load Test for AGL Vault C Annex - PM Review and C1)
C01_7 d/w - 10h/d - No HK 28 18-Nov-21 A 20-Jan-22 A 15-Apr-22 15-Apr-22
Acceptance Hols - No B/O periods (was
310.D.TX.A288 Method Statement for Plate Load Test for AGL Vault C Annex - BD Acknowledgement C1)
C01_7 d/w - 10h/d - No HK 28 20-Jan-22 A 02-Apr-22 04-May-22 10-May-22 38
Hols - No B/O periods (was
CC#08 - C&ED Op.Office & Kennel Area - MEP Submission C1)
C01_7 d/w - 10h/d - No HK Hols190
- No B/O periods
0 (was31-Aug-22
C1) 08-Mar-23 29-Dec-22 06-Jul-23 120
C&ED Op.Office & Kennel Area - MEP - Drawing Submission C01_7 d/w - 10h/d - No HK Hols190
- No B/O periods
0 (was31-Aug-22
C1) 08-Mar-23 29-Dec-22 06-Jul-23 120
310.D.WS.L784 C&ED Op.Office & Kennel Area - MEP - Drawing Submission - prepare document C01_7 d/w - 10h/d - No HK 100 31-Aug-22 08-Dec-22 29-Dec-22 07-Apr-23 120
Hols - No B/O periods (was
310.D.WS.L785 C&ED Op.Office & Kennel Area - MEP - Drawing Submission - PM review and accept 1st C1)
C01_7 d/w - 10h/d - No HK 100 30-Sep-22 07-Jan-23 28-Jan-23 07-May-23 120
Round Hols - No B/O periods (was
310.D.WS.L786 C&ED Op.Office & Kennel Area - MEP - Drawing Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK
100 30-Oct-22 06-Feb-23 27-Feb-23 06-Jun-23 120
Hols - No B/O periods (was
310.D.WS.L788 C&ED Op.Office & Kennel Area - MEP - Drawing Submission - PM review and accept 2nd C1)
C01_7 d/w - 10h/d - No HK 100 29-Nov-22 08-Mar-23 29-Mar-23 06-Jul-23 120
Round Hols - No B/O periods (was
CC#08 - C&ED Op.Office & Kennel Area - ABWF Submission C1)
C01_7 d/w - 10h/d - No HK Hols169
- No B/O periods
0 (was31-Aug-22
C1) 15-Feb-23 13-Oct-22 23-Oct-23 250
C&ED Op.Office & Kennel Area - ABWF - Drawing Submission C01_7 d/w - 10h/d - No HK Hols112
- No B/O periods
0 (was31-Aug-22
C1) 20-Dec-22 13-Oct-22 01-Feb-23 43
310.D.WS.L1072 C&ED Op.Office & Kennel Area - ABWF - prepare document C01_7 d/w - 10h/d - No HK 28 31-Aug-22 27-Sep-22 13-Oct-22 09-Nov-22 43
Hols - No B/O periods (was
310.D.WS.L1748 C&ED Op.Office & Kennel Area - ABWF - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 28 28-Sep-22 25-Oct-22 10-Nov-22 07-Dec-22 43
Hols - No B/O periods (was
310.D.WS.L1744 C&ED Op.Office & Kennel Area - ABWF - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 28 26-Oct-22 22-Nov-22 08-Dec-22 04-Jan-23 43
Hols - No B/O periods (was
310.D.WS.L1076 C&ED Op.Office & Kennel Area - ABWF - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 28 23-Nov-22 20-Dec-22 05-Jan-23 01-Feb-23 43
Hols - No B/O periods (was
C&ED Op.Office & Kennel Area - ABWF - Material Submission C1)
C01_7 d/w - 10h/d - No HK Hols112
- No B/O periods
0 (was28-Sep-22
C1) 17-Jan-23 10-Nov-22 01-Mar-23 43
310.D.WS.L1088 C&ED Op.Office & Kennel Area - ABWF - Material Submission - prepare document C01_7 d/w - 10h/d - No HK 28 28-Sep-22 25-Oct-22 10-Nov-22 07-Dec-22 43
Hols - No B/O periods (was
310.D.WS.L1756 C&ED Op.Office & Kennel Area - ABWF - Material Submission - PM review and accept C1)
C01_7 d/w - 10h/d - No HK 28 26-Oct-22 22-Nov-22 08-Dec-22 04-Jan-23 43
1st Round Hols - No B/O periods (was
310.D.WS.L1752 C&ED Op.Office & Kennel Area - ABWF - Material Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 28 23-Nov-22 20-Dec-22 05-Jan-23 01-Feb-23 43
Hols - No B/O periods (was
310.D.WS.L1092 C&ED Op.Office & Kennel Area - ABWF - Material Submission - PM review and accept C1)
C01_7 d/w - 10h/d - No HK 28 21-Dec-22 17-Jan-23 02-Feb-23 01-Mar-23 43
2nd Round Hols - No B/O periods (was
C&ED Op.Office & Kennel Area - BD Submission C1)
C01_7 d/w - 10h/d - No HK Hols169
- No B/O periods
0 (was31-Aug-22
C1) 15-Feb-23 06-Mar-23 23-Oct-23 250
C&ED Op.Office & Kennel Area - BD Submission - Fire Shutter C01_7 d/w - 10h/d - No HK Hols169
- No B/O periods
0 (was31-Aug-22
C1) 15-Feb-23 06-Apr-23 21-Sep-23 218
310.D.WS.L1193.B02 C&ED Op.Office & Kennel Area - Prepare Design & submit with ICE C01_7 d/w - 10h/d - No HK 30 31-Aug-22 29-Sep-22 06-Apr-23 05-May-23 218
Hols - No B/O periods (was
310.D.WS.L1194.B02 C&ED Op.Office & Kennel Area - PM, AP, RSE reviewing C1)
C01_7 d/w - 10h/d - No HK 28 30-Sep-22 27-Oct-22 06-May-23 02-Jun-23 218
Hols - No B/O periods (was
310.D.WS.L1195.B02 C&ED Op.Office & Kennel Area - ICC, M&VC review design and issue check certificate C1)
C01_7 d/w - 10h/d - No HK
21 28-Oct-22 17-Nov-22 03-Jun-23 23-Jun-23 218
Hols - No B/O periods (was
310.D.WS.L1197.B02 C&ED Op.Office & Kennel Area - BD Review and Acceptance (1st Acceptance requires 2 C1)
C01_7 d/w - 10h/d - No HK 60 18-Nov-22 16-Jan-23 24-Jun-23 22-Aug-23 218
months) Hols - No B/O periods (was
310.D.WS.L1198.B02 C&ED Op.Office & Kennel Area - Consent Application and Acceptance C1) d/w - 10h/d - No HK
C01_7 30 17-Jan-23 15-Feb-23 23-Aug-23 21-Sep-23 218
Hols - No B/O periods (was
C&ED Op.Office & Kennel Area - BD Submission - Cladding C1)
C01_7 d/w - 10h/d - No HK Hols169
- No B/O periods
0 (was31-Aug-22
C1) 15-Feb-23 06-Mar-23 21-Aug-23 187
310.D.WS.L1199.B01 C&ED Op.Office & Kennel Area - Prepare Design & submit with ICE C01_7 d/w - 10h/d - No HK 30 31-Aug-22 29-Sep-22 06-Mar-23 04-Apr-23 187
Hols - No B/O periods (was
C1)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 174 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L1200.B01 C&ED Op.Office & Kennel Area - PM, AP, RSE reviewing C01_7 d/w - 10h/d - No HK 28 30-Sep-22 27-Oct-22 05-Apr-23 02-May-23 187
Hols - No B/O periods (was
310.D.WS.L1201.B01 C&ED Op.Office & Kennel Area - ICC, M&VC review design and issue check certificate C1)
C01_7 d/w - 10h/d - No HK
21 28-Oct-22 17-Nov-22 03-May-23 23-May-23 187
Hols - No B/O periods (was
310.D.WS.L1202.B01 C&ED Op.Office & Kennel Area - BD Review and Acceptance (1st Acceptance requires 2 C1)
C01_7 d/w - 10h/d - No HK 60 18-Nov-22 16-Jan-23 24-May-23 22-Jul-23 187
months) Hols - No B/O periods (was
310.D.WS.L1203.B01 C&ED Op.Office & Kennel Area - Consent Application and Acceptance C1)
C01_7 d/w - 10h/d - No HK 30 17-Jan-23 15-Feb-23 23-Jul-23 21-Aug-23 187
Hols - No B/O periods (was
C&ED Op.Office & Kennel Area - BD Submission - Signage C1)
C01_7 d/w - 10h/d - No HK Hols169
- No B/O periods
0 (was31-Aug-22
C1) 15-Feb-23 08-May-23 23-Oct-23 250
310.D.WS.L1199.B02 C&ED Op.Office & Kennel Area - Prepare Design & submit with ICE C01_7 d/w - 10h/d - No HK 30 31-Aug-22 29-Sep-22 08-May-23 06-Jun-23 250
Hols - No B/O periods (was
310.D.WS.L1200.B02 C&ED Op.Office & Kennel Area - PM, AP, RSE reviewing C1)
C01_7 d/w - 10h/d - No HK 28 30-Sep-22 27-Oct-22 07-Jun-23 04-Jul-23 250
Hols - No B/O periods (was
310.D.WS.L1201.B02 C&ED Op.Office & Kennel Area - ICC, M&VC review design and issue check certificate C1)
C01_7 d/w - 10h/d - No HK
21 28-Oct-22 17-Nov-22 05-Jul-23 25-Jul-23 250
Hols - No B/O periods (was
310.D.WS.L1202.B02 C&ED Op.Office & Kennel Area - BD Review and Acceptance (1st Acceptance requires 2 C1)
C01_7 d/w - 10h/d - No HK 60 18-Nov-22 16-Jan-23 26-Jul-23 23-Sep-23 250
months) Hols - No B/O periods (was
310.D.WS.L1203.B02 C&ED Op.Office & Kennel Area - Consent Application and Acceptance C1)
C01_7 d/w - 10h/d - No HK 30 17-Jan-23 15-Feb-23 24-Sep-23 23-Oct-23 250
Hols - No B/O periods (was
C&ED Op.Office & Kennel Area - BD Submission - Louvre C1)
C01_7 d/w - 10h/d - No HK Hols169
- No B/O periods
0 (was31-Aug-22
C1) 15-Feb-23 06-Mar-23 21-Aug-23 187
310.D.WS.L1193.B01 C&ED Op.Office & Kennel Area - Prepare Design & submit with ICE C01_7 d/w - 10h/d - No HK 30 31-Aug-22 29-Sep-22 06-Mar-23 04-Apr-23 187
Hols - No B/O periods (was
310.D.WS.L1194.B01 C&ED Op.Office & Kennel Area - PM, AP, RSE reviewing C1)
C01_7 d/w - 10h/d - No HK 28 30-Sep-22 27-Oct-22 05-Apr-23 02-May-23 187
Hols - No B/O periods (was
310.D.WS.L1195.B01 C&ED Op.Office & Kennel Area - ICC, M&VC review design and issue check certificate C1)
C01_7 d/w - 10h/d - No HK
21 28-Oct-22 17-Nov-22 03-May-23 23-May-23 187
Hols - No B/O periods (was
310.D.WS.L1197.B01 C&ED Op.Office & Kennel Area - BD Review and Acceptance (1st Acceptance requires 2 C1)
C01_7 d/w - 10h/d - No HK 60 18-Nov-22 16-Jan-23 24-May-23 22-Jul-23 187
months) Hols - No B/O periods (was
310.D.WS.L1198.B01 C&ED Op.Office & Kennel Area - Consent Application and Acceptance C1)
C01_7 d/w - 10h/d - No HK 30 17-Jan-23 15-Feb-23 23-Jul-23 21-Aug-23 187
Hols - No B/O periods (was
CC#08 - Comm. Equipment Building D - MEP Submission C1)
C01_7 d/w - 10h/d - No HK Hols82
- No B/O periods
0 (was
20-Mar-22
C1) A 28-Jun-22 15-Aug-22 04-Nov-22 129
Comm. Equipment Building D - MEP - Drawing Submission C01_7 d/w - 10h/d - No HK Hols82
- No B/O periods
0 (was
20-Mar-22
C1) A 28-Jun-22 15-Aug-22 04-Nov-22 129
310.D.WS.L808 Comm. Equipment Building D - MEP - Drawing Submission - prepare document C01_7 d/w - 10h/d - No HK 14 20-Mar-22 A 17-May-22 15-Aug-22 23-Sep-22 129
Hols - No B/O periods (was
310.D.WS.L809 Comm. Equipment Building D - MEP - Drawing Submission - PM review and accept 1st C1)
C01_7 d/w - 10h/d - No HK 40 22-Apr-22 31-May-22 29-Aug-22 07-Oct-22 129
Round Hols - No B/O periods (was
310.D.WS.L810 Comm. Equipment Building D - MEP - Drawing Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 40 06-May-22 14-Jun-22 12-Sep-22 21-Oct-22 129
Hols - No B/O periods (was
310.D.WS.L812 Comm. Equipment Building D - MEP - Drawing Submission - PM review and accept 2nd C1)
C01_7 d/w - 10h/d - No HK 40 20-May-22 28-Jun-22 26-Sep-22 04-Nov-22 129
Round Hols - No B/O periods (was
CC#08 - Comm. Equipment Building D - ABWF Submission C1)
C01_7 d/w - 10h/d - No HK Hols169
- No B/O periods
0 (was26-Apr-22
C1) 11-Oct-22 04-May-22 23-Nov-22 43
Comm. Equipment Building D - ABWF - Drawing Submission C01_7 d/w - 10h/d - No HK Hols42
- No B/O periods
0 (was26-Apr-22
C1) 06-Jun-22 04-May-22 14-Jun-22 8
310.D.WS.L1096 Comm. Equipment Building D - ABWF - prepare document C01_7 d/w - 10h/d - No HK 7 26-Apr-22 02-May-22 04-May-22 10-May-22 8
Hols - No B/O periods (was
310.D.WS.L1764 Comm. Equipment Building D - ABWF - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 14 03-May-22 16-May-22 11-May-22 24-May-22 8
Hols - No B/O periods (was
310.D.WS.L1760 Comm. Equipment Building D - ABWF - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 7 17-May-22 23-May-22 25-May-22 31-May-22 8
Hols - No B/O periods (was
310.D.WS.L1100 Comm. Equipment Building D - ABWF - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 14 24-May-22 06-Jun-22 01-Jun-22 14-Jun-22 8
Hols - No B/O periods (was
Comm. Equipment Building D - ABWF - Material Submission C1)
C01_7 d/w - 10h/d - No HK Hols42
- No B/O periods
0 (was26-Apr-22
C1) 06-Jun-22 04-May-22 14-Jun-22 8

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 175 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L1112 Comm. Equipment Building D - ABWF - Material Submission - prepare document C01_7 d/w - 10h/d - No HK 7 26-Apr-22 02-May-22 04-May-22 10-May-22 8
Hols - No B/O periods (was
310.D.WS.L1772 Comm. Equipment Building D - ABWF - Material Submission - PM review and accept 1st C1)
C01_7 d/w - 10h/d - No HK 14 03-May-22 16-May-22 11-May-22 24-May-22 8
Round Hols - No B/O periods (was
310.D.WS.L1768 Comm. Equipment Building D - ABWF - Material Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK
7 17-May-22 23-May-22 25-May-22 31-May-22 8
Hols - No B/O periods (was
310.D.WS.L1116 Comm. Equipment Building D - ABWF - Material Submission - PM review and accept 2nd C1)
C01_7 d/w - 10h/d - No HK 14 24-May-22 06-Jun-22 01-Jun-22 14-Jun-22 8
Round Hols - No B/O periods (was
Comm. Equipment Building D - BD Submission C1)
C01_7 d/w - 10h/d - No HK Hols169
- No B/O periods
0 (was26-Apr-22
C1) 11-Oct-22 08-Jun-22 23-Nov-22 43
Comm. Equipment Building D - BD Submission - Signage C01_7 d/w - 10h/d - No HK Hols169
- No B/O periods
0 (was26-Apr-22
C1) 11-Oct-22 08-Jun-22 23-Nov-22 43
310.D.WS.L1122.B02 Comm. Equipment Building D - Prepare Design & submit with ICE C01_7 d/w - 10h/d - No HK 30 26-Apr-22 25-May-22 08-Jun-22 07-Jul-22 43
Hols - No B/O periods (was
310.D.WS.L1125.B02 Comm. Equipment Building D - PM, AP, RSE reviewing C1)
C01_7 d/w - 10h/d - No HK 28 26-May-22 22-Jun-22 08-Jul-22 04-Aug-22 43
Hols - No B/O periods (was
310.D.WS.L1137.B02 Comm. Equipment Building D - ICC, M&VC review design and issue check certificate C1)
C01_7 d/w - 10h/d - No HK 21 23-Jun-22 13-Jul-22 05-Aug-22 25-Aug-22 43
Hols - No B/O periods (was
310.D.WS.L1129.B02 Comm. Equipment Building D - BD Review and Acceptance (1st Acceptance requires 2 C1)
C01_7 d/w - 10h/d - No HK 60 14-Jul-22 11-Sep-22 26-Aug-22 24-Oct-22 43
months) Hols - No B/O periods (was
310.D.WS.L1133.B02 Comm. Equipment Building D - Consent Application and Acceptance C1)
C01_7 d/w - 10h/d - No HK 30 12-Sep-22 11-Oct-22 25-Oct-22 23-Nov-22 43
Hols - No B/O periods (was
Comm. Equipment Building D - BD Submission - Louvre C1)
C01_7 d/w - 10h/d - No HK Hols169
- No B/O periods
0 (was26-Apr-22
C1) 11-Oct-22 08-Jun-22 23-Nov-22 43
310.D.WS.L1111.B01 Comm. Equipment Building D - Prepare Design & submit with ICE C01_7 d/w - 10h/d - No HK 30 26-Apr-22 25-May-22 08-Jun-22 07-Jul-22 43
Hols - No B/O periods (was
310.D.WS.L1115.B01 Comm. Equipment Building D - PM, AP, RSE reviewing C1)
C01_7 d/w - 10h/d - No HK 28 26-May-22 22-Jun-22 08-Jul-22 04-Aug-22 43
Hols - No B/O periods (was
310.D.WS.L1119.B01 Comm. Equipment Building D - ICC, M&VC review design and issue check certificate C1)
C01_7 d/w - 10h/d - No HK 21 23-Jun-22 13-Jul-22 05-Aug-22 25-Aug-22 43
Hols - No B/O periods (was
310.D.WS.L1120.B01 Comm. Equipment Building D - BD Review and Acceptance (1st Acceptance requires 2 C1)
C01_7 d/w - 10h/d - No HK 60 14-Jul-22 11-Sep-22 26-Aug-22 24-Oct-22 43
months) Hols - No B/O periods (was
310.D.WS.L1121.B01 Comm. Equipment Building D - Consent Application and Acceptance C1)
C01_7 d/w - 10h/d - No HK 30 12-Sep-22 11-Oct-22 25-Oct-22 23-Nov-22 43
Hols - No B/O periods (was
Comm. Equipment Building D - BD Submission - Cladding C1)
C01_7 d/w - 10h/d - No HK Hols169
- No B/O periods
0 (was26-Apr-22
C1) 11-Oct-22 08-Jun-22 23-Nov-22 43
310.D.WS.L1122.B01 Comm. Equipment Building D - Prepare Design & submit with ICE C01_7 d/w - 10h/d - No HK 30 26-Apr-22 25-May-22 08-Jun-22 07-Jul-22 43
Hols - No B/O periods (was
310.D.WS.L1125.B01 Comm. Equipment Building D - PM, AP, RSE reviewing C1)
C01_7 d/w - 10h/d - No HK 28 26-May-22 22-Jun-22 08-Jul-22 04-Aug-22 43
Hols - No B/O periods (was
310.D.WS.L1137.B01 Comm. Equipment Building D - ICC, M&VC review design and issue check certificate C1)
C01_7 d/w - 10h/d - No HK 21 23-Jun-22 13-Jul-22 05-Aug-22 25-Aug-22 43
Hols - No B/O periods (was
310.D.WS.L1129.B01 Comm. Equipment Building D - BD Review and Acceptance (1st Acceptance requires 2 C1)
C01_7 d/w - 10h/d - No HK 60 14-Jul-22 11-Sep-22 26-Aug-22 24-Oct-22 43
months) Hols - No B/O periods (was
310.D.WS.L1133.B01 Comm. Equipment Building D - Consent Application and Acceptance C1)
C01_7 d/w - 10h/d - No HK 30 12-Sep-22 11-Oct-22 25-Oct-22 23-Nov-22 43
Hols - No B/O periods (was
CC#08 - GSE Vehicle Wash Facility - MEP Submission C1)
C01_7 d/w - 10h/d - No HK Hols150
- No B/O periods
0 (was
14-Mar-22
C1) A 04-Sep-22 18-Jun-22 14-Nov-22 71
GSE Vehicle Wash Facility - MEP - Drawing Submission C01_7 d/w - 10h/d - No HK Hols150
- No B/O periods
0 (was
14-Mar-22
C1) A 04-Sep-22 18-Jun-22 14-Nov-22 71
310.D.WS.L832 GSE Vehicle Wash Facility - MEP - Drawing Submission - prepare document C01_7 d/w - 10h/d - No HK 14 14-Mar-22 A 06-Jun-22 18-Jun-22 16-Aug-22 71
Hols - No B/O periods (was
310.D.WS.L833 GSE Vehicle Wash Facility - MEP - Drawing Submission - PM review and accept 1st C1)
C01_7 d/w - 10h/d - No HK 60 08-May-22 06-Jul-22 18-Jul-22 15-Sep-22 71
Round Hols - No B/O periods (was
310.D.WS.L834 GSE Vehicle Wash Facility - MEP - Drawing Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 60 07-Jun-22 05-Aug-22 17-Aug-22 15-Oct-22 71
Hols - No B/O periods (was
C1)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 176 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L836 GSE Vehicle Wash Facility - MEP - Drawing Submission - PM review and accept 2nd C01_7 d/w - 10h/d - No HK 60 07-Jul-22 04-Sep-22 16-Sep-22 14-Nov-22 71
Round Hols - No B/O periods (was
CC#08 - GSE Vehicle Wash Facility - ABWF Submission C1)
C01_7 d/w - 10h/d - No HK Hols169
- No B/O periods
0 (was26-Apr-22
C1) 11-Oct-22 02-May-22 09-Dec-22 59
GSE Vehicle Wash Facility - ABWF - Drawing Submission C01_7 d/w - 10h/d - No HK Hols49
- No B/O periods
0 (was26-Apr-22
C1) 13-Jun-22 02-May-22 19-Jun-22 6
310.D.WS.L1120 GSE Vehicle Wash Facility - ABWF - prepare document C01_7 d/w - 10h/d - No HK 7 26-Apr-22 02-May-22 02-May-22 08-May-22 6
Hols - No B/O periods (was
310.D.WS.L1780 GSE Vehicle Wash Facility - ABWF - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 21 03-May-22 23-May-22 09-May-22 29-May-22 6
Hols - No B/O periods (was
310.D.WS.L1776 GSE Vehicle Wash Facility - ABWF - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 7 24-May-22 30-May-22 30-May-22 05-Jun-22 6
Hols - No B/O periods (was
310.D.WS.L1124 GSE Vehicle Wash Facility - ABWF - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 14 31-May-22 13-Jun-22 06-Jun-22 19-Jun-22 6
Hols - No B/O periods (was
GSE Vehicle Wash Facility - ABWF - Material Submission C1)
C01_7 d/w - 10h/d - No HK Hols56
- No B/O periods
0 (was03-May-22
C1) 27-Jun-22 16-May-22 03-Jul-22 6
310.D.WS.L1136 GSE Vehicle Wash Facility - ABWF - Material Submission - prepare document C01_7 d/w - 10h/d - No HK 7 03-May-22 09-May-22 16-May-22 22-May-22 13
Hols - No B/O periods (was
310.D.WS.L1788 GSE Vehicle Wash Facility - ABWF - Material Submission - PM review and accept1st C1)
C01_7 d/w - 10h/d - No HK 21 10-May-22 30-May-22 23-May-22 12-Jun-22 13
Round Hols - No B/O periods (was
310.D.WS.L1784 GSE Vehicle Wash Facility - ABWF - Material Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 7 31-May-22 06-Jun-22 13-Jun-22 19-Jun-22 13
Hols - No B/O periods (was
310.D.WS.L1140 GSE Vehicle Wash Facility - ABWF - Material Submission - PM review and accept 2nd C1)
C01_7 d/w - 10h/d - No HK 14 14-Jun-22 27-Jun-22 20-Jun-22 03-Jul-22 6
Round Hols - No B/O periods (was
GSE Vehicle Wash Facility - BD Submission C1)
C01_7 d/w - 10h/d - No HK Hols169
- No B/O periods
0 (was26-Apr-22
C1) 11-Oct-22 22-Jun-22 09-Dec-22 59
GSE Vehicle Wash Facility - BD Submission - Signage C01_7 d/w - 10h/d - No HK Hols169
- No B/O periods
0 (was26-Apr-22
C1) 11-Oct-22 22-Jun-22 07-Dec-22 57
310.D.WS.L11421.B02 GSE Vehicle Wash Facility - Prepare Design & submit with ICE C01_7 d/w - 10h/d - No HK 30 26-Apr-22 25-May-22 22-Jun-22 21-Jul-22 57
Hols - No B/O periods (was
310.D.WS.L11425.B02 GSE Vehicle Wash Facility - PM, AP, RSE reviewing C1)
C01_7 d/w - 10h/d - No HK 28 26-May-22 22-Jun-22 22-Jul-22 18-Aug-22 57
Hols - No B/O periods (was
310.D.WS.L11437.B02 GSE Vehicle Wash Facility - ICC, M&VC review design and issue check certificate C1)
C01_7 d/w - 10h/d - No HK 21 23-Jun-22 13-Jul-22 19-Aug-22 08-Sep-22 57
Hols - No B/O periods (was
310.D.WS.L11429.B02 GSE Vehicle Wash Facility - BD Review and Acceptance (1st Acceptance requires 2 C1)
C01_7 d/w - 10h/d - No HK 60 14-Jul-22 11-Sep-22 09-Sep-22 07-Nov-22 57
months) Hols - No B/O periods (was
310.D.WS.L11433.B02 GSE Vehicle Wash Facility - Consent Application and Acceptance C1)
C01_7 d/w - 10h/d - No HK 30 12-Sep-22 11-Oct-22 08-Nov-22 07-Dec-22 57
Hols - No B/O periods (was
GSE Vehicle Wash Facility - BD Submission - Louvre C1)
C01_7 d/w - 10h/d - No HK Hols169
- No B/O periods
0 (was26-Apr-22
C1) 11-Oct-22 24-Jun-22 09-Dec-22 59
310.D.WS.L1141.B01 GSE Vehicle Wash Facility - Prepare Design & submit with ICE C01_7 d/w - 10h/d - No HK 30 26-Apr-22 25-May-22 24-Jun-22 23-Jul-22 59
Hols - No B/O periods (was
310.D.WS.L1145.B01 GSE Vehicle Wash Facility - PM, AP, RSE reviewing C1)
C01_7 d/w - 10h/d - No HK 28 26-May-22 22-Jun-22 24-Jul-22 20-Aug-22 59
Hols - No B/O periods (was
310.D.WS.L1149.B01 GSE Vehicle Wash Facility - ICC, M&VC review design and issue check certificate C1)
C01_7 d/w - 10h/d - No HK 21 23-Jun-22 13-Jul-22 21-Aug-22 10-Sep-22 59
Hols - No B/O periods (was
310.D.WS.L11413.B01 GSE Vehicle Wash Facility - BD Review and Acceptance (1st Acceptance requires 2 C1)
C01_7 d/w - 10h/d - No HK 60 14-Jul-22 11-Sep-22 11-Sep-22 09-Nov-22 59
months) Hols - No B/O periods (was
310.D.WS.L11417.B01 GSE Vehicle Wash Facility - Consent Application and Acceptance C1)
C01_7 d/w - 10h/d - No HK 30 12-Sep-22 11-Oct-22 10-Nov-22 09-Dec-22 59
Hols - No B/O periods (was
GSE Vehicle Wash Facility - BD Submission - Cladding C1)
C01_7 d/w - 10h/d - No HK Hols169
- No B/O periods
0 (was26-Apr-22
C1) 11-Oct-22 24-Jun-22 09-Dec-22 59
310.D.WS.L11421.B01 GSE Vehicle Wash Facility - Prepare Design & submit with ICE C01_7 d/w - 10h/d - No HK 30 26-Apr-22 25-May-22 24-Jun-22 23-Jul-22 59
Hols - No B/O periods (was
310.D.WS.L11425.B01 GSE Vehicle Wash Facility - PM, AP, RSE reviewing C1)
C01_7 d/w - 10h/d - No HK 28 26-May-22 22-Jun-22 24-Jul-22 20-Aug-22 59
Hols - No B/O periods (was
310.D.WS.L11437.B01 GSE Vehicle Wash Facility - ICC, M&VC review design and issue check certificate C1)
C01_7 d/w - 10h/d - No HK 21 23-Jun-22 13-Jul-22 21-Aug-22 10-Sep-22 59
Hols - No B/O periods (was
C1)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 177 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L11429.B01 GSE Vehicle Wash Facility - BD Review and Acceptance (1st Acceptance requires 2 C01_7 d/w - 10h/d - No HK 60 14-Jul-22 11-Sep-22 11-Sep-22 09-Nov-22 59
months) Hols - No B/O periods (was
310.D.WS.L11433.B01 GSE Vehicle Wash Facility - Consent Application and Acceptance C1)
C01_7 d/w - 10h/d - No HK 30 12-Sep-22 11-Oct-22 10-Nov-22 09-Dec-22 59
Hols - No B/O periods (was
CC#08 - GSE Battery Charging B - MEP Submission C1)
C01_7 d/w - 10h/d - No HK Hols210
- No B/O periods
0 (was
20-Mar-22
C1) A 22-Oct-22 18-May-22 13-Dec-22 52
GSE Battery Charging B - MEP - Drawing Submission C01_7 d/w - 10h/d - No HK Hols210
- No B/O periods
0 (was
20-Mar-22
C1) A 22-Oct-22 18-May-22 13-Dec-22 52
310.D.WS.L856 GSE Battery Charging B - MEP - Drawing Submission - prepare document C01_7 d/w - 10h/d - No HK 21 20-Mar-22 A 24-Jul-22 18-May-22 14-Sep-22 52
Hols - No B/O periods (was
310.D.WS.L857 GSE Battery Charging B - MEP - Drawing Submission - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 120 26-Apr-22 23-Aug-22 17-Jun-22 14-Oct-22 52
Hols - No B/O periods (was
310.D.WS.L858 GSE Battery Charging B - MEP - Drawing Submission - prepare resubmission 2nd Round C1)
C01_7 d/w - 10h/d - No HK
120 26-May-22 22-Sep-22 17-Jul-22 13-Nov-22 52
Hols - No B/O periods (was
310.D.WS.L860 GSE Battery Charging B - MEP - Drawing Submission - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 120 25-Jun-22 22-Oct-22 16-Aug-22 13-Dec-22 52
Hols - No B/O periods (was
CC#08 - GSE Battery Charging B - ABWF Submission C1)
C01_7 d/w - 10h/d - No HK Hols169
- No B/O periods
0 (was26-Apr-22
C1) 11-Oct-22 23-May-22 22-Dec-22 72
GSE Battery Charging B - ABWF - Drawing Submission C01_7 d/w - 10h/d - No HK Hols56
- No B/O periods
0 (was26-Apr-22
C1) 20-Jun-22 23-May-22 17-Jul-22 27
310.D.WS.L1144 GSE Battery Charging B - ABWF - prepare document C01_7 d/w - 10h/d - No HK 14 26-Apr-22 09-May-22 23-May-22 05-Jun-22 27
Hols - No B/O periods (was
310.D.WS.L1796 GSE Battery Charging B - ABWF - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 28 10-May-22 06-Jun-22 06-Jun-22 03-Jul-22 27
Hols - No B/O periods (was
310.D.WS.L1792 GSE Battery Charging B - ABWF - prepare resubmission C1) d/w - 10h/d - No HK
C01_7 7 07-Jun-22 13-Jun-22 04-Jul-22 10-Jul-22 27
Hols - No B/O periods (was
310.D.WS.L1148 GSE Battery Charging B - ABWF - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 7 14-Jun-22 20-Jun-22 11-Jul-22 17-Jul-22 27
Hols - No B/O periods (was
GSE Battery Charging B - ABWF - Material Submission C1)
C01_7 d/w - 10h/d - No HK Hols56
- No B/O periods
0 (was26-Apr-22
C1) 20-Jun-22 23-May-22 17-Jul-22 27
310.D.WS.L1160 GSE Battery Charging B - ABWF - Material Submission - prepare document C01_7 d/w - 10h/d - No HK 14 26-Apr-22 09-May-22 23-May-22 05-Jun-22 27
Hols - No B/O periods (was
310.D.WS.L1804 GSE Battery Charging B - ABWF - Material Submission - PM review and accept 1st C1)
C01_7 d/w - 10h/d - No HK 28 10-May-22 06-Jun-22 06-Jun-22 03-Jul-22 27
Round Hols - No B/O periods (was
310.D.WS.L1800 GSE Battery Charging B - ABWF - Material Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 7 07-Jun-22 13-Jun-22 04-Jul-22 10-Jul-22 27
Hols - No B/O periods (was
310.D.WS.L1164 GSE Battery Charging B - ABWF - Material Submission - PM review and accept 2nd C1)
C01_7 d/w - 10h/d - No HK 7 14-Jun-22 20-Jun-22 11-Jul-22 17-Jul-22 27
Round Hols - No B/O periods (was
GSE Battery Charging B - BD Submission C1)
C01_7 d/w - 10h/d - No HK Hols169
- No B/O periods
0 (was26-Apr-22
C1) 11-Oct-22 17-Jun-22 22-Dec-22 72
GSE Battery Charging B - BD Submission - Fire Shutter C01_7 d/w - 10h/d - No HK Hols169
- No B/O periods
0 (was26-Apr-22
C1) 11-Oct-22 17-Jun-22 02-Dec-22 52
310.D.WS.L11621.B02 GSE Battery Charging B - Prepare Design & submit with ICE C01_7 d/w - 10h/d - No HK 30 26-Apr-22 25-May-22 17-Jun-22 16-Jul-22 52
Hols - No B/O periods (was
310.D.WS.L11625.B02 GSE Battery Charging B - PM, AP, RSE reviewing C1)
C01_7 d/w - 10h/d - No HK 28 26-May-22 22-Jun-22 17-Jul-22 13-Aug-22 52
Hols - No B/O periods (was
310.D.WS.L11637.B02 GSE Battery Charging B - ICC, M&VC review design and issue check certificate C1)
C01_7 d/w - 10h/d - No HK 21 23-Jun-22 13-Jul-22 14-Aug-22 03-Sep-22 52
Hols - No B/O periods (was
310.D.WS.L11629.B02 GSE Battery Charging B - BD Review and Acceptance (1st Acceptance requires 2 C1)
C01_7 d/w - 10h/d - No HK 60 14-Jul-22 11-Sep-22 04-Sep-22 02-Nov-22 52
months) Hols - No B/O periods (was
310.D.WS.L11633.B02 GSE Battery Charging B - Consent Application and Acceptance C1)
C01_7 d/w - 10h/d - No HK 30 12-Sep-22 11-Oct-22 03-Nov-22 02-Dec-22 52
Hols - No B/O periods (was
GSE Battery Charging B - BD Submission - Signage C1) d/w - 10h/d - No HK Hols169
C01_7 - No B/O periods
0 (was26-Apr-22
C1) 11-Oct-22 28-Jun-22 13-Dec-22 63
310.D.WS.L11622.B02 GSE Battery Charging B - Prepare Design & submit with ICE C01_7 d/w - 10h/d - No HK 30 26-Apr-22 25-May-22 28-Jun-22 27-Jul-22 63
Hols - No B/O periods (was
310.D.WS.L11626.B02 GSE Battery Charging B - PM, AP, RSE reviewing C1)
C01_7 d/w - 10h/d - No HK 28 26-May-22 22-Jun-22 28-Jul-22 24-Aug-22 63
Hols - No B/O periods (was
C1)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 178 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L11638.B02 GSE Battery Charging B - ICC, M&VC review design and issue check certificate C01_7 d/w - 10h/d - No HK 21 23-Jun-22 13-Jul-22 25-Aug-22 14-Sep-22 63
Hols - No B/O periods (was
310.D.WS.L11630.B02 GSE Battery Charging B - BD Review and Acceptance (1st Acceptance requires 2 C1)
C01_7 d/w - 10h/d - No HK 60 14-Jul-22 11-Sep-22 15-Sep-22 13-Nov-22 63
months) Hols - No B/O periods (was
310.D.WS.L11634.B02 GSE Battery Charging B - Consent Application and Acceptance C1)
C01_7 d/w - 10h/d - No HK 30 12-Sep-22 11-Oct-22 14-Nov-22 13-Dec-22 63
Hols - No B/O periods (was
GSE Battery Charging B - BD Submission - Louvre C1)
C01_7 d/w - 10h/d - No HK Hols169
- No B/O periods
0 (was26-Apr-22
C1) 11-Oct-22 07-Jul-22 22-Dec-22 72
310.D.WS.L1161.B01 GSE Battery Charging B - Prepare Design & submit with ICE C01_7 d/w - 10h/d - No HK 30 26-Apr-22 25-May-22 07-Jul-22 05-Aug-22 72
Hols - No B/O periods (was
310.D.WS.L1165.B01 GSE Battery Charging B - PM, AP, RSE reviewing C1)
C01_7 d/w - 10h/d - No HK 28 26-May-22 22-Jun-22 06-Aug-22 02-Sep-22 72
Hols - No B/O periods (was
310.D.WS.L1169.B01 GSE Battery Charging B - ICC, M&VC review design and issue check certificate C1)
C01_7 d/w - 10h/d - No HK 21 23-Jun-22 13-Jul-22 03-Sep-22 23-Sep-22 72
Hols - No B/O periods (was
310.D.WS.L11613.B01 GSE Battery Charging B - BD Review and Acceptance (1st Acceptance requires 2 C1)
C01_7 d/w - 10h/d - No HK 60 14-Jul-22 11-Sep-22 24-Sep-22 22-Nov-22 72
months) Hols - No B/O periods (was
310.D.WS.L11617.B01 GSE Battery Charging B - Consent Application and Acceptance C1)
C01_7 d/w - 10h/d - No HK 30 12-Sep-22 11-Oct-22 23-Nov-22 22-Dec-22 72
Hols - No B/O periods (was
GSE Battery Charging B - BD Submission - Cladding C1)
C01_7 d/w - 10h/d - No HK Hols169
- No B/O periods
0 (was26-Apr-22
C1) 11-Oct-22 07-Jul-22 22-Dec-22 72
310.D.WS.L11621.B01 GSE Battery Charging B - Prepare Design & submit with ICE C01_7 d/w - 10h/d - No HK 30 26-Apr-22 25-May-22 07-Jul-22 05-Aug-22 72
Hols - No B/O periods (was
310.D.WS.L11625.B01 GSE Battery Charging B - PM, AP, RSE reviewing C1)
C01_7 d/w - 10h/d - No HK 28 26-May-22 22-Jun-22 06-Aug-22 02-Sep-22 72
Hols - No B/O periods (was
310.D.WS.L11637.B01 GSE Battery Charging B - ICC, M&VC review design and issue check certificate C1)
C01_7 d/w - 10h/d - No HK 21 23-Jun-22 13-Jul-22 03-Sep-22 23-Sep-22 72
Hols - No B/O periods (was
310.D.WS.L11629.B01 GSE Battery Charging B - BD Review and Acceptance (1st Acceptance requires 2 C1)
C01_7 d/w - 10h/d - No HK 60 14-Jul-22 11-Sep-22 24-Sep-22 22-Nov-22 72
months) Hols - No B/O periods (was
310.D.WS.L11633.B01 GSE Battery Charging B - Consent Application and Acceptance C1)
C01_7 d/w - 10h/d - No HK 30 12-Sep-22 11-Oct-22 23-Nov-22 22-Dec-22 72
Hols - No B/O periods (was
CC#08 - Maintenance Facilities Forecourt & Coach Staging A & Bus Stop - MEP Submission C1)
C01_7 d/w - 10h/d - No HK Hols98
- No B/O periods
0 (was08-Jan-23
C1) 15-Apr-23 21-Jul-23 26-Oct-23 194
Maintenance Facilities Forecourt & Coach Staging A & Bus Stop - MEP - Drawing Submission C01_7 d/w - 10h/d - No HK Hols98
- No B/O periods
0 (was08-Jan-23
C1) 15-Apr-23 21-Jul-23 26-Oct-23 194
310.D.WS.L880 Maintenance Facilities Forecourt & Coach Staging A & Bus Stop - MEP - Drawing C01_7 d/w - 10h/d - No HK 28 08-Jan-23 04-Feb-23 21-Jul-23 17-Aug-23 194
Submission - prepare document Hols - No B/O periods (was
310.D.WS.L881 Maintenance Facilities Forecourt & Coach Staging A & Bus Stop - MEP - Drawing C1)
C01_7 d/w - 10h/d - No HK 28 05-Feb-23 04-Mar-23 18-Aug-23 14-Sep-23 194
Submission - PM review & accept 1st Round Hols - No B/O periods (was
310.D.WS.L882 Maintenance Facilities Forecourt & Coach Staging A & Bus Stop - MEP - Drawing C1)
C01_7 d/w - 10h/d - No HK 14 05-Mar-23 18-Mar-23 15-Sep-23 28-Sep-23 194
Submission - prepare resubmission Hols - No B/O periods (was
310.D.WS.L884 Maintenance Facilities Forecourt & Coach Staging A & Bus Stop - MEP - Drawing C1)
C01_7 d/w - 10h/d - No HK 28 19-Mar-23 15-Apr-23 29-Sep-23 26-Oct-23 194
Submission - PM review & accept 2nd Round Hols - No B/O periods (was
CC#08 - Maintenance Facilities Forecourt & Coach Staging A & Bus Stop - ABWF Submission C1)
C01_7 d/w - 10h/d - No HK Hols119
- No B/O periods
0 (was31-Aug-22
C1) 27-Dec-22 08-Feb-23 06-Jun-23 161
Maintenance Facilities Forecourt & Coach Staging A & Bus Stop - ABWF - Drawing Submission C01_7 d/w - 10h/d - No HK Hols91
- No B/O periods
0 (was31-Aug-22
C1) 29-Nov-22 08-Feb-23 09-May-23 161
310.D.WS.L1168 Maintenance Facilities Forecourt & Coach Staging A & Bus Stop - ABWF - prepare C01_7 d/w - 10h/d - No HK 21 31-Aug-22 20-Sep-22 08-Feb-23 28-Feb-23 161
document Hols - No B/O periods (was
310.D.WS.L1812 Maintenance Facilities Forecourt & Coach Staging A & Bus Stop - ABWF - PM review and C1)
C01_7 d/w - 10h/d - No HK 28 21-Sep-22 18-Oct-22 01-Mar-23 28-Mar-23 161
accept 1st Round Hols - No B/O periods (was
310.D.WS.L1808 Maintenance Facilities Forecourt & Coach Staging A & Bus Stop - ABWF - prepare C1)
C01_7 d/w - 10h/d - No HK
14 19-Oct-22 01-Nov-22 29-Mar-23 11-Apr-23 161
resubmission Hols - No B/O periods (was
310.D.WS.L1172 Maintenance Facilities Forecourt & Coach Staging A & Bus Stop - ABWF - PM review and C1)
C01_7 d/w - 10h/d - No HK 28 02-Nov-22 29-Nov-22 12-Apr-23 09-May-23 161
accept 2nd Round Hols - No B/O periods (was
Maintenance Facilities Forecourt & Coach Staging A & Bus Stop - ABWF - Material Submission C1)
C01_7 d/w - 10h/d - No HK Hols98
- No B/O periods
0 (was21-Sep-22
C1) 27-Dec-22 08-Mar-23 06-Jun-23 161
310.D.WS.L1184 Maintenance Facilities Forecourt & Coach Staging A & Bus Stop - ABWF - Material C01_7 d/w - 10h/d - No HK 21 21-Sep-22 11-Oct-22 08-Mar-23 28-Mar-23 168
Submission - prepare document Hols - No B/O periods (was
C1)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 179 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L1820 Maintenance Facilities Forecourt & Coach Staging A & Bus Stop - ABWF - Material C01_7 d/w - 10h/d - No HK 28 12-Oct-22 08-Nov-22 29-Mar-23 25-Apr-23 168
Submission - PM review and accept Hols - No B/O periods (was
310.D.WS.L1816 Maintenance Facilities Forecourt & Coach Staging A & Bus Stop - ABWF - Material C1)
C01_7 d/w - 10h/d - No HK 14 09-Nov-22 22-Nov-22 26-Apr-23 09-May-23 168
Submission - prepare resubmission Hols - No B/O periods (was
310.D.WS.L1188 Maintenance Facilities Forecourt & Coach Staging A & Bus Stop - ABWF - Material C1)
C01_7 d/w - 10h/d - No HK 28 30-Nov-22 27-Dec-22 10-May-23 06-Jun-23 161
Submission - PM review&accept 2nd Round Hols - No B/O periods (was
CC#08 - WSA - GSE Storage Area - MEP Submission C1)
C01_7 d/w - 10h/d - No HK Hols98
- No B/O periods
0 (was31-Aug-22
C1) 06-Dec-22 11-May-23 16-Aug-23 253
WSA - GSE Storage Area - MEP - Drawing Submission C01_7 d/w - 10h/d - No HK Hols98
- No B/O periods
0 (was31-Aug-22
C1) 06-Dec-22 11-May-23 16-Aug-23 253
310.D.WS.L904 WSA - GSE Storage Area - MEP - Drawing Submission - prepare document C01_7 d/w - 10h/d - No HK 28 31-Aug-22 27-Sep-22 11-May-23 07-Jun-23 253
Hols - No B/O periods (was
310.D.WS.L905 WSA - GSE Storage Area - MEP - Drawing Submission - PM review and accept 1st C1)
C01_7 d/w - 10h/d - No HK 28 28-Sep-22 25-Oct-22 08-Jun-23 05-Jul-23 253
Round Hols - No B/O periods (was
310.D.WS.L906 WSA - GSE Storage Area - MEP - Drawing Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 14 26-Oct-22 08-Nov-22 06-Jul-23 19-Jul-23 253
Hols - No B/O periods (was
310.D.WS.L908 WSA - GSE Storage Area - MEP - Drawing Submission - PM review and accept 2nd C1)
C01_7 d/w - 10h/d - No HK 28 09-Nov-22 06-Dec-22 20-Jul-23 16-Aug-23 253
Round Hols - No B/O periods (was
CC#08 - WSA - GSE Storage Area - ABWF Submission C1)
C01_7 d/w - 10h/d - No HK Hols119
- No B/O periods
0 (was31-Aug-22
C1) 27-Dec-22 28-Feb-23 26-Jun-23 181
WSA - GSE Storage Area - ABWF - Drawing Submission C01_7 d/w - 10h/d - No HK Hols91
- No B/O periods
0 (was31-Aug-22
C1) 29-Nov-22 28-Feb-23 29-May-23 181
310.D.WS.L1192 WSA - GSE Storage Area - ABWF - prepare document C01_7 d/w - 10h/d - No HK 21 31-Aug-22 20-Sep-22 28-Feb-23 20-Mar-23 181
Hols - No B/O periods (was
310.D.WS.L1828 WSA - GSE Storage Area - ABWF - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 28 21-Sep-22 18-Oct-22 21-Mar-23 17-Apr-23 181
Hols - No B/O periods (was
310.D.WS.L1824 WSA - GSE Storage Area - ABWF - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 14 19-Oct-22 01-Nov-22 18-Apr-23 01-May-23 181
Hols - No B/O periods (was
310.D.WS.L1196 WSA - GSE Storage Area - ABWF - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 28 02-Nov-22 29-Nov-22 02-May-23 29-May-23 181
Hols - No B/O periods (was
WSA - GSE Storage Area - ABWF - Material Submission C1)
C01_7 d/w - 10h/d - No HK Hols98
- No B/O periods
0 (was21-Sep-22
C1) 27-Dec-22 28-Mar-23 26-Jun-23 181
310.D.WS.L1208 WSA - GSE Storage Area - ABWF - Material Submission - prepare document C01_7 d/w - 10h/d - No HK 21 21-Sep-22 11-Oct-22 28-Mar-23 17-Apr-23 188
Hols - No B/O periods (was
310.D.WS.L1836 WSA - GSE Storage Area - ABWF - Material Submission - PM review and accept 1st C1)
C01_7 d/w - 10h/d - No HK 28 12-Oct-22 08-Nov-22 18-Apr-23 15-May-23 188
Round Hols - No B/O periods (was
310.D.WS.L1832 WSA - GSE Storage Area - ABWF - Material Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 14 09-Nov-22 22-Nov-22 16-May-23 29-May-23 188
Hols - No B/O periods (was
310.D.WS.L1212 WSA - GSE Storage Area - ABWF - Material Submission - PM review and accept 2nd C1)
C01_7 d/w - 10h/d - No HK 28 30-Nov-22 27-Dec-22 30-May-23 26-Jun-23 181
Round Hols - No B/O periods (was
CC#08 - WSA - Gatehouse B - MEP Submission C1)
C01_7 d/w - 10h/d - No HK Hols204
- No B/O periods
0 (was03-Apr-22
C1) 23-Oct-22 05-Sep-22 27-Mar-23 155
WSA - Gatehouse B - MEP - Drawing Submission C01_7 d/w - 10h/d - No HK Hols204
- No B/O periods
0 (was03-Apr-22
C1) 23-Oct-22 05-Sep-22 27-Mar-23 155
310.D.WS.L928 WSA - Gatehouse B - MEP - Drawing Submission - prepare document C01_7 d/w - 10h/d - No HK 120 03-Apr-22 31-Jul-22 05-Sep-22 02-Jan-23 155
Hols - No B/O periods (was
310.D.WS.L929 WSA - Gatehouse B - MEP - Drawing Submission - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 120 01-May-22 28-Aug-22 03-Oct-22 30-Jan-23 155
Hols - No B/O periods (was
310.D.WS.L930 WSA - Gatehouse B - MEP - Drawing Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 120 29-May-22 25-Sep-22 31-Oct-22 27-Feb-23 155
Hols - No B/O periods (was
310.D.WS.L932 WSA - Gatehouse B - MEP - Drawing Submission - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 120 26-Jun-22 23-Oct-22 28-Nov-22 27-Mar-23 155
Hols - No B/O periods (was
CC#08 - WSA - Gatehouse B - ABWF Submission C1) d/w - 10h/d - No HK Hols169
C01_7 - No B/O periods
0 (was13-May-22
C1) 28-Oct-22 20-Sep-22 16-Jun-23 231
WSA - Gatehouse B - ABWF - Drawing Submission C01_7 d/w - 10h/d - No HK Hols91
- No B/O periods
0 (was13-May-22
C1) 11-Aug-22 20-Sep-22 19-Dec-22 130
310.D.WS.L1216 WSA - Gatehouse B - ABWF - prepare document C01_7 d/w - 10h/d - No HK 21 13-May-22 02-Jun-22 20-Sep-22 10-Oct-22 130
Hols - No B/O periods (was
310.D.WS.L1844 WSA - Gatehouse B - ABWF - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 28 03-Jun-22 30-Jun-22 11-Oct-22 07-Nov-22 130
Hols - No B/O periods (was
C1)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 180 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L1840 WSA - Gatehouse B - ABWF - prepare resubmission C01_7 d/w - 10h/d - No HK 14 01-Jul-22 14-Jul-22 08-Nov-22 21-Nov-22 130
Hols - No B/O periods (was
310.D.WS.L1220 WSA - Gatehouse B - ABWF - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 28 15-Jul-22 11-Aug-22 22-Nov-22 19-Dec-22 130
Hols - No B/O periods (was
WSA - Gatehouse B - ABWF - Material Submission C1)
C01_7 d/w - 10h/d - No HK Hols98
- No B/O periods
0 (was03-Jun-22
C1) 08-Sep-22 18-Oct-22 16-Jan-23 130
310.D.WS.L1232 WSA - Gatehouse B - ABWF - Material Submission - prepare document C01_7 d/w - 10h/d - No HK 21 03-Jun-22 23-Jun-22 18-Oct-22 07-Nov-22 137
Hols - No B/O periods (was
310.D.WS.L1852 WSA - Gatehouse B - ABWF - Material Submission - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 28 24-Jun-22 21-Jul-22 08-Nov-22 05-Dec-22 137
Hols - No B/O periods (was
310.D.WS.L1848 WSA - Gatehouse B - ABWF - Material Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 14 22-Jul-22 04-Aug-22 06-Dec-22 19-Dec-22 137
Hols - No B/O periods (was
310.D.WS.L1236 WSA - Gatehouse B - ABWF - Material Submission - PM review and accept C1)
C01_7 d/w - 10h/d - No HK 28 12-Aug-22 08-Sep-22 20-Dec-22 16-Jan-23 130
Hols - No B/O periods (was
WSA - Gatehouse B - BD Submission C1)
C01_7 d/w - 10h/d - No HK Hols169
- No B/O periods
0 (was13-May-22
C1) 28-Oct-22 16-Nov-22 16-Jun-23 231
WSA - Gatehouse B - BD Submission - Signage C01_7 d/w - 10h/d - No HK Hols169
- No B/O periods
0 (was13-May-22
C1) 28-Oct-22 16-Nov-22 03-May-23 187
310.D.WS.L1261.B02 WSA - Gatehouse B - Prepare Design & submit with ICE C01_7 d/w - 10h/d - No HK 30 13-May-22 11-Jun-22 16-Nov-22 15-Dec-22 187
Hols - No B/O periods (was
310.D.WS.L1265.B02 WSA - Gatehouse B - PM, AP, RSE reviewing C1)
C01_7 d/w - 10h/d - No HK 28 12-Jun-22 09-Jul-22 16-Dec-22 12-Jan-23 187
Hols - No B/O periods (was
310.D.WS.L1277.B02 WSA - Gatehouse B - ICC, M&VC review design and issue check certificate C1)
C01_7 d/w - 10h/d - No HK 21 10-Jul-22 30-Jul-22 13-Jan-23 02-Feb-23 187
Hols - No B/O periods (was
310.D.WS.L1269.B02 WSA - Gatehouse B - BD Review and Acceptance (1st Acceptance requires 2 months) C1)
C01_7 d/w - 10h/d - No HK 60 31-Jul-22 28-Sep-22 03-Feb-23 03-Apr-23 187
Hols - No B/O periods (was
310.D.WS.L1273.B02 WSA - Gatehouse B - Consent Application and Acceptance C1)
C01_7 d/w - 10h/d - No HK 30 29-Sep-22 28-Oct-22 04-Apr-23 03-May-23 187
Hols - No B/O periods (was
WSA - Gatehouse B - BD Submission - Louvre C1)
C01_7 d/w - 10h/d - No HK Hols169
- No B/O periods
0 (was13-May-22
C1) 28-Oct-22 30-Dec-22 16-Jun-23 231
310.D.WS.L121.B01 WSA - Gatehouse B - Prepare Design & submit with ICE C01_7 d/w - 10h/d - No HK 30 13-May-22 11-Jun-22 30-Dec-22 28-Jan-23 231
Hols - No B/O periods (was
310.D.WS.L125.B01 WSA - Gatehouse B - PM, AP, RSE reviewing C1)
C01_7 d/w - 10h/d - No HK 28 12-Jun-22 09-Jul-22 29-Jan-23 25-Feb-23 231
Hols - No B/O periods (was
310.D.WS.L129.B01 WSA - Gatehouse B - ICC, M&VC review design and issue check certificate C1)
C01_7 d/w - 10h/d - No HK 21 10-Jul-22 30-Jul-22 26-Feb-23 18-Mar-23 231
Hols - No B/O periods (was
310.D.WS.L1213.B01 WSA - Gatehouse B - BD Review and Acceptance (1st Acceptance requires 2 months) C1)
C01_7 d/w - 10h/d - No HK 60 31-Jul-22 28-Sep-22 19-Mar-23 17-May-23 231
Hols - No B/O periods (was
310.D.WS.L1217.B01 WSA - Gatehouse B - Consent Application and Acceptance C1)
C01_7 d/w - 10h/d - No HK 30 29-Sep-22 28-Oct-22 18-May-23 16-Jun-23 231
Hols - No B/O periods (was
WSA - Gatehouse B - BD Submission - Canopy C1)
C01_7 d/w - 10h/d - No HK Hols169
- No B/O periods
0 (was13-May-22
C1) 28-Oct-22 30-Dec-22 16-Jun-23 231
310.D.WS.L1241.B01 WSA - Gatehouse B - Prepare Design & submit with ICE C01_7 d/w - 10h/d - No HK 30 13-May-22 11-Jun-22 30-Dec-22 28-Jan-23 231
Hols - No B/O periods (was
310.D.WS.L1245.B01 WSA - Gatehouse B - PM, AP, RSE reviewing C1)
C01_7 d/w - 10h/d - No HK 28 12-Jun-22 09-Jul-22 29-Jan-23 25-Feb-23 231
Hols - No B/O periods (was
310.D.WS.L1249.B01 WSA - Gatehouse B - ICC, M&VC review design and issue check certificate C1)
C01_7 d/w - 10h/d - No HK 21 10-Jul-22 30-Jul-22 26-Feb-23 18-Mar-23 231
Hols - No B/O periods (was
310.D.WS.L1253.B01 WSA - Gatehouse B - BD Review and Acceptance (1st Acceptance requires 2 months) C1)
C01_7 d/w - 10h/d - No HK 60 31-Jul-22 28-Sep-22 19-Mar-23 17-May-23 231
Hols - No B/O periods (was
310.D.WS.L1257.B01 WSA - Gatehouse B - Consent Application and Acceptance C1)
C01_7 d/w - 10h/d - No HK 30 29-Sep-22 28-Oct-22 18-May-23 16-Jun-23 231
Hols - No B/O periods (was
WSA - Gatehouse B - BD Submission - Cladding C1)
C01_7 d/w - 10h/d - No HK Hols169
- No B/O periods
0 (was13-May-22
C1) 28-Oct-22 30-Dec-22 16-Jun-23 231
310.D.WS.L1221.B01 WSA - Gatehouse B - Prepare Design & submit with ICE C01_7 d/w - 10h/d - No HK 30 13-May-22 11-Jun-22 30-Dec-22 28-Jan-23 231
Hols - No B/O periods (was
C1)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 181 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L1225.B01 WSA - Gatehouse B - PM, AP, RSE reviewing C01_7 d/w - 10h/d - No HK 28 12-Jun-22 09-Jul-22 29-Jan-23 25-Feb-23 231
Hols - No B/O periods (was
310.D.WS.L1237.B01 WSA - Gatehouse B - ICC, M&VC review design and issue check certificate C1)
C01_7 d/w - 10h/d - No HK 21 10-Jul-22 30-Jul-22 26-Feb-23 18-Mar-23 231
Hols - No B/O periods (was
310.D.WS.L1229.B01 WSA - Gatehouse B - BD Review and Acceptance (1st Acceptance requires 2 months) C1)
C01_7 d/w - 10h/d - No HK 60 31-Jul-22 28-Sep-22 19-Mar-23 17-May-23 231
Hols - No B/O periods (was
310.D.WS.L1233.B01 WSA - Gatehouse B - Consent Application and Acceptance C1)
C01_7 d/w - 10h/d - No HK 30 29-Sep-22 28-Oct-22 18-May-23 16-Jun-23 231
Hols - No B/O periods (was
WSA - Gatehouse B - BD Submission - Skylight C1)
C01_7 d/w - 10h/d - No HK Hols169
- No B/O periods
0 (was13-May-22
C1) 28-Oct-22 30-Dec-22 16-Jun-23 231
310.D.WS.L1261.B01 WSA - Gatehouse B - Prepare Design & submit with ICE C01_7 d/w - 10h/d - No HK 30 13-May-22 11-Jun-22 30-Dec-22 28-Jan-23 231
Hols - No B/O periods (was
310.D.WS.L1265.B01 WSA - Gatehouse B - PM, AP, RSE reviewing C1)
C01_7 d/w - 10h/d - No HK 28 12-Jun-22 09-Jul-22 29-Jan-23 25-Feb-23 231
Hols - No B/O periods (was
310.D.WS.L1277.B01 WSA - Gatehouse B - ICC, M&VC review design and issue check certificate C1)
C01_7 d/w - 10h/d - No HK 21 10-Jul-22 30-Jul-22 26-Feb-23 18-Mar-23 231
Hols - No B/O periods (was
310.D.WS.L1269.B01 WSA - Gatehouse B - BD Review and Acceptance (1st Acceptance requires 2 months) C1)
C01_7 d/w - 10h/d - No HK 60 31-Jul-22 28-Sep-22 19-Mar-23 17-May-23 231
Hols - No B/O periods (was
310.D.WS.L1273.B01 WSA - Gatehouse B - Consent Application and Acceptance C1)
C01_7 d/w - 10h/d - No HK 30 29-Sep-22 28-Oct-22 18-May-23 16-Jun-23 231
Hols - No B/O periods (was
CC#08 - WSA - Screening Facilities - MEP Submission C1)
C01_7 d/w - 10h/d - No HK Hols210
- No B/O periods
0 (was
20-Mar-22
C1) A 22-Oct-22 20-May-22 15-Dec-22 54
WSA - Screening Facilities - MEP - Drawing Submission C01_7 d/w - 10h/d - No HK Hols210
- No B/O periods
0 (was
20-Mar-22
C1) A 22-Oct-22 20-May-22 15-Dec-22 54
310.D.WS.L952 WSA - Screening Facilities - MEP - Drawing Submission - prepare document C01_7 d/w - 10h/d - No HK 21 20-Mar-22 A 24-Jul-22 20-May-22 16-Sep-22 54
Hols - No B/O periods (was
310.D.WS.L953 WSA - Screening Facilities - MEP - Drawing Submission - PM review and accept 1st C1)
C01_7 d/w - 10h/d - No HK 120 26-Apr-22 23-Aug-22 19-Jun-22 16-Oct-22 54
Round Hols - No B/O periods (was
310.D.WS.L954 WSA - Screening Facilities - MEP - Drawing Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 120 26-May-22 22-Sep-22 19-Jul-22 15-Nov-22 54
Hols - No B/O periods (was
310.D.WS.L956 WSA - Screening Facilities - MEP - Drawing Submission - PM review and accept 2nd C1)
C01_7 d/w - 10h/d - No HK 120 25-Jun-22 22-Oct-22 18-Aug-22 15-Dec-22 54
Round Hols - No B/O periods (was
CC#08 - WSA - Screening Facilities - ABWF Submission C1)
C01_7 d/w - 10h/d - No HK Hols169
- No B/O periods
0 (was26-Apr-22
C1) 11-Oct-22 27-May-22 27-Feb-23 139
WSA - Screening Facilities - ABWF - Drawing Submission C01_7 d/w - 10h/d - No HK Hols70
- No B/O periods
0 (was26-Apr-22
C1) 04-Jul-22 27-May-22 04-Aug-22 31
310.D.WS.L1240 WSA - Screening Facilities - ABWF - prepare document C01_7 d/w - 10h/d - No HK 21 26-Apr-22 16-May-22 27-May-22 16-Jun-22 31
Hols - No B/O periods (was
310.D.WS.L1860 WSA - Screening Facilities - ABWF - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 28 17-May-22 13-Jun-22 17-Jun-22 14-Jul-22 31
Hols - No B/O periods (was
310.D.WS.L1856 WSA - Screening Facilities - ABWF - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 7 14-Jun-22 20-Jun-22 15-Jul-22 21-Jul-22 31
Hols - No B/O periods (was
310.D.WS.L1244 WSA - Screening Facilities - ABWF - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 14 21-Jun-22 04-Jul-22 22-Jul-22 04-Aug-22 31
Hols - No B/O periods (was
WSA - Screening Facilities - ABWF - Material Submission C1)
C01_7 d/w - 10h/d - No HK Hols169
- No B/O periods
0 (was26-Apr-22
C1) 11-Oct-22 27-May-22 27-Feb-23 139
310.D.WS.L1256 WSA - Screening Facilities - ABWF - Material Submission - prepare document C01_7 d/w - 10h/d - No HK 21 26-Apr-22 16-May-22 27-May-22 16-Jun-22 31
Hols - No B/O periods (was
310.D.WS.L1868 WSA - Screening Facilities - ABWF - Material Submission - PM review and accept 1st C1)
C01_7 d/w - 10h/d - No HK 28 17-May-22 13-Jun-22 17-Jun-22 14-Jul-22 31
Round Hols - No B/O periods (was
310.D.WS.L1864 WSA - Screening Facilities - ABWF - Material Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 7 14-Jun-22 20-Jun-22 15-Jul-22 21-Jul-22 31
Hols - No B/O periods (was
310.D.WS.L1260 WSA - Screening Facilities - ABWF - Material Submission - PM review and accept 2nd C1)
C01_7 d/w - 10h/d - No HK 14 21-Jun-22 04-Jul-22 22-Jul-22 04-Aug-22 31
Round Hols - No B/O periods (was
WSA - Screening Facilities - BD Submission C1)
C01_7 d/w - 10h/d - No HK Hols169
- No B/O periods
0 (was26-Apr-22
C1) 11-Oct-22 01-Jun-22 27-Feb-23 139
WSA - Screening Facilities - BD Submission - Signage C01_7 d/w - 10h/d - No HK Hols169
- No B/O periods
0 (was26-Apr-22
C1) 11-Oct-22 01-Jun-22 16-Nov-22 36

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 182 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L1281.B02 WSA - Screening Facilities - Prepare Design & submit with ICE C01_7 d/w - 10h/d - No HK 30 26-Apr-22 25-May-22 01-Jun-22 30-Jun-22 36
Hols - No B/O periods (was
310.D.WS.L1285.B02 WSA - Screening Facilities - PM, AP, RSE reviewing C1)
C01_7 d/w - 10h/d - No HK 28 26-May-22 22-Jun-22 01-Jul-22 28-Jul-22 36
Hols - No B/O periods (was
310.D.WS.L1289.B02 WSA - Screening Facilities - ICC, M&VC review design and issue check certificate C1)
C01_7 d/w - 10h/d - No HK 21 23-Jun-22 13-Jul-22 29-Jul-22 18-Aug-22 36
Hols - No B/O periods (was
310.D.WS.L1293.B02 WSA - Screening Facilities - BD Review and Acceptance (1st Acceptance requires 2 C1)
C01_7 d/w - 10h/d - No HK 60 14-Jul-22 11-Sep-22 19-Aug-22 17-Oct-22 36
months) Hols - No B/O periods (was
310.D.WS.L1297.B02 WSA - Screening Facilities - Consent Application and Acceptance C1)
C01_7 d/w - 10h/d - No HK 30 12-Sep-22 11-Oct-22 18-Oct-22 16-Nov-22 36
Hols - No B/O periods (was
WSA - Screening Facilities - BD Submission - Louvre C1)
C01_7 d/w - 10h/d - No HK Hols169
- No B/O periods
0 (was26-Apr-22
C1) 11-Oct-22 12-Sep-22 27-Feb-23 139
310.D.WS.L1281.B01 WSA - Screening Facilities - Prepare Design & submit with ICE C01_7 d/w - 10h/d - No HK 30 26-Apr-22 25-May-22 12-Sep-22 11-Oct-22 139
Hols - No B/O periods (was
310.D.WS.L1285.B01 WSA - Screening Facilities - PM, AP, RSE reviewing C1)
C01_7 d/w - 10h/d - No HK 28 26-May-22 22-Jun-22 12-Oct-22 08-Nov-22 139
Hols - No B/O periods (was
310.D.WS.L1289.B01 WSA - Screening Facilities - ICC, M&VC review design and issue check certificate C1)
C01_7 d/w - 10h/d - No HK 21 23-Jun-22 13-Jul-22 09-Nov-22 29-Nov-22 139
Hols - No B/O periods (was
310.D.WS.L1293.B01 WSA - Screening Facilities - BD Review and Acceptance (1st Acceptance requires 2 C1)
C01_7 d/w - 10h/d - No HK 60 14-Jul-22 11-Sep-22 30-Nov-22 28-Jan-23 139
months) Hols - No B/O periods (was
310.D.WS.L1297.B01 WSA - Screening Facilities - Consent Application and Acceptance C1)
C01_7 d/w - 10h/d - No HK 30 12-Sep-22 11-Oct-22 29-Jan-23 27-Feb-23 139
Hols - No B/O periods (was
WSA - Screening Facilities - BD Submission - Canopy C1)
C01_7 d/w - 10h/d - No HK Hols169
- No B/O periods
0 (was26-Apr-22
C1) 11-Oct-22 12-Sep-22 27-Feb-23 139
310.D.WS.L12121.B01WSA - Screening Facilities - Prepare Design & submit with ICE C01_7 d/w - 10h/d - No HK 30 26-Apr-22 25-May-22 12-Sep-22 11-Oct-22 139
Hols - No B/O periods (was
310.D.WS.L12125.B01WSA - Screening Facilities - PM, AP, RSE reviewing C1)
C01_7 d/w - 10h/d - No HK 28 26-May-22 22-Jun-22 12-Oct-22 08-Nov-22 139
Hols - No B/O periods (was
310.D.WS.L12129.B01WSA - Screening Facilities - ICC, M&VC review design and issue check certificate C1)
C01_7 d/w - 10h/d - No HK 21 23-Jun-22 13-Jul-22 09-Nov-22 29-Nov-22 139
Hols - No B/O periods (was
310.D.WS.L12133.B01WSA - Screening Facilities - BD Review and Acceptance (1st Acceptance requires 2 C1)
C01_7 d/w - 10h/d - No HK 60 14-Jul-22 11-Sep-22 30-Nov-22 28-Jan-23 139
months) Hols - No B/O periods (was
310.D.WS.L12137.B01WSA - Screening Facilities - Consent Application and Acceptance C1)
C01_7 d/w - 10h/d - No HK 30 12-Sep-22 11-Oct-22 29-Jan-23 27-Feb-23 139
Hols - No B/O periods (was
WSA - Screening Facilities - BD Submission - Cladding C1)
C01_7 d/w - 10h/d - No HK Hols169
- No B/O periods
0 (was26-Apr-22
C1) 11-Oct-22 12-Sep-22 27-Feb-23 139
310.D.WS.L12101.B01WSA - Screening Facilities - Prepare Design & submit with ICE C01_7 d/w - 10h/d - No HK 30 26-Apr-22 25-May-22 12-Sep-22 11-Oct-22 139
Hols - No B/O periods (was
310.D.WS.L12105.B01WSA - Screening Facilities - PM, AP, RSE reviewing C1)
C01_7 d/w - 10h/d - No HK 28 26-May-22 22-Jun-22 12-Oct-22 08-Nov-22 139
Hols - No B/O periods (was
310.D.WS.L12117.B01WSA - Screening Facilities - ICC, M&VC review design and issue check certificate C1)
C01_7 d/w - 10h/d - No HK 21 23-Jun-22 13-Jul-22 09-Nov-22 29-Nov-22 139
Hols - No B/O periods (was
310.D.WS.L12109.B01WSA - Screening Facilities - BD Review and Acceptance (1st Acceptance requires 2 C1)
C01_7 d/w - 10h/d - No HK 60 14-Jul-22 11-Sep-22 30-Nov-22 28-Jan-23 139
months) Hols - No B/O periods (was
310.D.WS.L12113.B01WSA - Screening Facilities - Consent Application and Acceptance C1)
C01_7 d/w - 10h/d - No HK 30 12-Sep-22 11-Oct-22 29-Jan-23 27-Feb-23 139
Hols - No B/O periods (was
WSA - Screening Facilities - BD Submission - Skylight C1)
C01_7 d/w - 10h/d - No HK Hols169
- No B/O periods
0 (was26-Apr-22
C1) 11-Oct-22 12-Sep-22 27-Feb-23 139
310.D.WS.L12141.B01WSA - Screening Facilities - Prepare Design & submit with ICE C01_7 d/w - 10h/d - No HK 30 26-Apr-22 25-May-22 12-Sep-22 11-Oct-22 139
Hols - No B/O periods (was
310.D.WS.L12145.B01WSA - Screening Facilities - PM, AP, RSE reviewing C1)
C01_7 d/w - 10h/d - No HK 28 26-May-22 22-Jun-22 12-Oct-22 08-Nov-22 139
Hols - No B/O periods (was
310.D.WS.L12157.B01WSA - Screening Facilities - ICC, M&VC review design and issue check certificate C1)
C01_7 d/w - 10h/d - No HK 21 23-Jun-22 13-Jul-22 09-Nov-22 29-Nov-22 139
Hols - No B/O periods (was
C1)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 183 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L12149.B01WSA - Screening Facilities - BD Review and Acceptance (1st Acceptance requires 2 C01_7 d/w - 10h/d - No HK 60 14-Jul-22 11-Sep-22 30-Nov-22 28-Jan-23 139
months) Hols - No B/O periods (was
310.D.WS.L12153.B01WSA - Screening Facilities - Consent Application and Acceptance C1)
C01_7 d/w - 10h/d - No HK 30 12-Sep-22 11-Oct-22 29-Jan-23 27-Feb-23 139
Hols - No B/O periods (was
CC#08 - AGL Vault D Annex - MEP Submission C1)
C01_7 d/w - 10h/d - No HK Hols195
- No B/O periods
0 (was
28-Jan-22
C1) A 18-Jun-22 10-Jun-22 01-Sep-22 75
AGL Vault D Annex - MEP - Drawing Submission C01_7 d/w - 10h/d - No HK Hols195
- No B/O periods
0 (was
28-Jan-22
C1) A 18-Jun-22 10-Jun-22 01-Sep-22 75
AGL Vault D Annex - Drawing Submission for CSD & CBWD C01_7 d/w - 10h/d - No HK Hols104
- No B/O periods
0 (was
28-Jan-22
C1) A 16-May-22 10-Jun-22 01-Sep-22 108
310.D.WS.L976.0B01 AGL Vault D Annex - MEP - CSD/CBWD Shop Drawing Submission - prepare & C01_7 d/w - 10h/d - No HK 28 28-Jan-22 A 04-Apr-22 10-Jun-22 18-Jun-22 75
submission of document Hols - No B/O periods (was
310.D.WS.L976.1B01 AGL Vault D Annex - MEP - CSD/CBWD Shop Drawing Submission - PM review and C1)
C01_7 d/w - 10h/d - No HK 14 05-Apr-22 18-Apr-22 24-Jun-22 07-Jul-22 80
accept Hols - No B/O periods (was
310.D.WS.L976.2B01 AGL Vault D Annex - MEP - CSD/CBWD + ISD Drawing Submission - prepare & C1)
C01_7 d/w - 10h/d - No HK 14 19-Apr-22 02-May-22 08-Jul-22 21-Jul-22 80
submission of document Hols - No B/O periods (was
310.D.WS.L976.3B01 AGL Vault D Annex - MEP - CSD/CBWD + ISD Drawing Submission - PM review and C1)
C01_7 d/w - 10h/d - No HK 14 03-May-22 16-May-22 19-Aug-22 01-Sep-22 108
accept Hols - No B/O periods (was
AGL Vault D Annex - Drawing Submission for Electrical Services C1)
C01_7 d/w - 10h/d - No HK Hols75
- No B/O periods
0 (was
20-Mar-22
C1) A 18-Jun-22 10-Jun-22 01-Sep-22 75
310.D.WS.L976 AGL Vault D Annex - MEP - Drawing Submission for Electrical Services - prepare C01_7 d/w - 10h/d - No HK 14 20-Mar-22 A 09-Apr-22 10-Jun-22 23-Jun-22 75
document Hols - No B/O periods (was
310.D.WS.L977 AGL Vault D Annex - MEP - Drawing Submission for Electrical Services - PM review and C1)
C01_7 d/w - 10h/d - No HK 28 10-Apr-22 07-May-22 24-Jun-22 21-Jul-22 75
accept 1st Round Hols - No B/O periods (was
310.D.WS.L978 AGL Vault D Annex - MEP - Drawing Submission for Electrical Services - prepare C1) d/w - 10h/d - No HK
C01_7 14 08-May-22 21-May-22 22-Jul-22 04-Aug-22 75
resubmission Hols - No B/O periods (was
310.D.WS.L980 AGL Vault D Annex - MEP - Drawing Submission for Electrical Services - PM review and C1)
C01_7 d/w - 10h/d - No HK 28 22-May-22 18-Jun-22 05-Aug-22 01-Sep-22 75
accept 2nd Round Hols - No B/O periods (was
AGL Vault D Annex - Drawing Submission for MVAC Services C1)
C01_7 d/w - 10h/d - No HK Hols98
- No B/O periods
0 (was
20-Feb-22
C1) A 13-Jun-22 24-Jun-22 01-Sep-22 80
310.D.WS.L2031.B01 AGL Vault D Annex - MEP - Drawing Submission for MVAC Services - prepare document C01_7 d/w - 10h/d - No HK 14 20-Feb-22 A 17-Mar-22 A 24-Jun-22 24-Jun-22
Hols - No B/O periods (was
310.D.WS.L2043.B01 AGL Vault D Annex - MEP - Drawing Submission for MVAC Services - PM review and C1)
C01_7 d/w - 10h/d - No HK 28 18-Mar-22 A 23-Apr-22 24-Jun-22 21-Jul-22 89
accept 1st Round Hols - No B/O periods (was
310.D.WS.L2039.B01 AGL Vault D Annex - MEP - Drawing Submission for MVAC Services - prepare C1)
C01_7 d/w - 10h/d - No HK 14 03-May-22 16-May-22 22-Jul-22 04-Aug-22 80
resubmission Hols - No B/O periods (was
310.D.WS.L2035.B01 AGL Vault D Annex - MEP - Drawing Submission for MVAC Services - PM review and C1)
C01_7 d/w - 10h/d - No HK 28 17-May-22 13-Jun-22 05-Aug-22 01-Sep-22 80
accept 2nd Round Hols - No B/O periods (was
AGL Vault D Annex - Drawing Submission for Fire Services C1)
C01_7 d/w - 10h/d - No HK Hols70
- No B/O periods
0 (was
04-Mar-22
C1) A 18-Jun-22 10-Jun-22 01-Sep-22 75
310.D.WS.L2047.B01 AGL Vault D Annex - MEP - Drawing Submission for Fire Services - prepare document C01_7 d/w - 10h/d - No HK 14 04-Mar-22 A 09-Apr-22 10-Jun-22 23-Jun-22 75
Hols - No B/O periods (was
310.D.WS.L2059.B01 AGL Vault D Annex - MEP - Drawing Submission for Fire Services - PM review and C1)
C01_7 d/w - 10h/d - No HK 28 10-Apr-22 07-May-22 24-Jun-22 21-Jul-22 75
accept 1st Round Hols - No B/O periods (was
310.D.WS.L2055.B01 AGL Vault D Annex - MEP - Drawing Submission for Fire Services - prepare C1)
C01_7 d/w - 10h/d - No HK 14 08-May-22 21-May-22 22-Jul-22 04-Aug-22 75
resubmission Hols - No B/O periods (was
310.D.WS.L2051.B01 AGL Vault D Annex - MEP - Drawing Submission for Fire Services - PM review and C1)
C01_7 d/w - 10h/d - No HK 28 22-May-22 18-Jun-22 05-Aug-22 01-Sep-22 75
accept 2nd Round Hols - No B/O periods (was
AGL Vault D Annex - Drawing Submission for Plumbing & Drainage C1)
C01_7 d/w - 10h/d - No HK Hols105
- No B/O periods
0 (was
16-Feb-22
C1) A 13-Jun-22 24-Jun-22 01-Sep-22 80
310.D.WS.L2063.B01 AGL Vault D Annex - MEP - Drawing Submission for Plumbing & Drainage Services - C01_7 d/w - 10h/d - No HK 14 16-Feb-22 A 17-Mar-22 A 24-Jun-22 24-Jun-22
prepare document Hols - No B/O periods (was
310.D.WS.L2075.B01 AGL Vault D Annex - MEP - Drawing Submission for Plumbing & Drainage Services - PM C1)
C01_7 d/w - 10h/d - No HK 28 18-Mar-22 A 23-Apr-22 24-Jun-22 21-Jul-22 89
review and accept 1st Round Hols - No B/O periods (was
310.D.WS.L2071.B01 AGL Vault D Annex - MEP - Drawing Submission for Plumbing & Drainage Services - C1)
C01_7 d/w - 10h/d - No HK 14 03-May-22 16-May-22 22-Jul-22 04-Aug-22 80
prepare resubmission Hols - No B/O periods (was
310.D.WS.L2067.B01 AGL Vault D Annex - MEP - Drawing Submission for Plumbing & Drainage Services - PM C1)
C01_7 d/w - 10h/d - No HK 28 17-May-22 13-Jun-22 05-Aug-22 01-Sep-22 80
review and accept 2nd Round Hols - No B/O periods (was
C1)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 184 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
CC#08 - AGL Vault D Annex - ABWF Submission C01_7 d/w - 10h/d - No HK Hols153
- No B/O periods
0 (was26-Apr-22
C1) 25-Sep-22 11-Jun-22 10-Nov-22 46
AGL Vault D Annex - ABWF - Drawing Submission C01_7 d/w - 10h/d - No HK Hols116
- No B/O periods
0 (was11-May-22
C1) 03-Sep-22 20-Jun-22 25-Oct-22 52
AGL Vault D Annex - Shop Drawing submission and Acceptance of Louvre C01_7 d/w - 10h/d - No HK Hols84
- No B/O periods
0 (was16-May-22
C1) 07-Aug-22 05-Jul-22 26-Sep-22 50
310.D.WS.L1264 AGL Vault D Annex - Louvre - Shop Drawing Submission C01_7 d/w - 10h/d - No HK 14 16-May-22 29-May-22 05-Jul-22 18-Jul-22 50
Hols - No B/O periods (was
310.D.WS.L1876 AGL Vault D Annex - Louvre - Shop Drawing PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 28 30-May-22 26-Jun-22 19-Jul-22 15-Aug-22 50
Hols - No B/O periods (was
310.D.WS.L1872 AGL Vault D Annex - Louvre - Shop Drawing prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 14 27-Jun-22 10-Jul-22 16-Aug-22 29-Aug-22 50
Hols - No B/O periods (was
310.D.WS.L1268 AGL Vault D Annex - Louvre - Shop Drawing PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 28 11-Jul-22 07-Aug-22 30-Aug-22 26-Sep-22 50
Hols - No B/O periods (was
AGL Vault D Annex - Shop Drawing submission and Acceptance of Cladding C1)
C01_7 d/w - 10h/d - No HK Hols84
- No B/O periods
0 (was16-May-22
C1) 07-Aug-22 05-Jul-22 26-Sep-22 50
310.D.WS.L1264.1.B01AGL Vault D Annex - Cladding - Shop Drawing Submission C01_7 d/w - 10h/d - No HK 14 16-May-22 29-May-22 05-Jul-22 18-Jul-22 50
Hols - No B/O periods (was
310.D.WS.L1264.2.B01AGL Vault D Annex - Cladding - Shop Drawing PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 28 30-May-22 26-Jun-22 19-Jul-22 15-Aug-22 50
Hols - No B/O periods (was
310.D.WS.L1264.3.B01AGL Vault D Annex - Cladding - Shop Drawing prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 14 27-Jun-22 10-Jul-22 16-Aug-22 29-Aug-22 50
Hols - No B/O periods (was
310.D.WS.L1264.4.B01AGL Vault D Annex - Cladding - Shop Drawing PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 28 11-Jul-22 07-Aug-22 30-Aug-22 26-Sep-22 50
Hols - No B/O periods (was
AGL Vault D Annex - Shop Drawing submission and Acceptance of Door C1) d/w - 10h/d - No HK Hols84
C01_7 - No B/O periods
0 (was12-Jun-22
C1) 03-Sep-22 03-Aug-22 25-Oct-22 52
310.D.WS.L1264.5.B01AGL Vault D Annex - Door - Shop Drawing Submission C01_7 d/w - 10h/d - No HK 14 12-Jun-22 25-Jun-22 03-Aug-22 16-Aug-22 52
Hols - No B/O periods (was
310.D.WS.L1264.6.B01AGL Vault D Annex - Door - Shop Drawing PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 28 26-Jun-22 23-Jul-22 17-Aug-22 13-Sep-22 52
Hols - No B/O periods (was
310.D.WS.L1264.7.B01AGL Vault D Annex - Door - Shop Drawing prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 14 24-Jul-22 06-Aug-22 14-Sep-22 27-Sep-22 52
Hols - No B/O periods (was
310.D.WS.L1264.8.B01AGL Vault D Annex - Door - Shop Drawing PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 28 07-Aug-22 03-Sep-22 28-Sep-22 25-Oct-22 52
Hols - No B/O periods (was
AGL Vault D Annex - Shop Drawing submission and Acceptance of Metal Cover at G/F (1 set) C1)
C01_7 d/w - 10h/d - No HK Hols84
- No B/O periods
0 (was11-May-22
C1) 02-Aug-22 20-Jun-22 11-Sep-22 40
310.D.WS.L1264.9.B01AGL Vault D Annex - Metal Cover - Shop Drawing Submission C01_7 d/w - 10h/d - No HK 14 11-May-22 24-May-22 20-Jun-22 03-Jul-22 40
Hols - No B/O periods (was
310.D.WS.L1264.10B01AGL Vault D Annex - Metal Cover - Shop Drawing PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 28 25-May-22 21-Jun-22 04-Jul-22 31-Jul-22 40
Hols - No B/O periods (was
310.D.WS.L1264.11B01AGL Vault D Annex - Metal Cover - Shop Drawing prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 14 22-Jun-22 05-Jul-22 01-Aug-22 14-Aug-22 40
Hols - No B/O periods (was
310.D.WS.L1264.12B01AGL Vault D Annex - Metal Cover - Shop Drawing PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 28 06-Jul-22 02-Aug-22 15-Aug-22 11-Sep-22 40
Hols - No B/O periods (was
AGL Vault D Annex - Shop Drawing submission and Acceptance of Cat Ladder C1)
C01_7 d/w - 10h/d - No HK Hols84
- No B/O periods
0 (was05-Jun-22
C1) 27-Aug-22 20-Jul-22 11-Oct-22 45
310.D.WS.L1264.13B01AGL Vault D Annex - Cat Ladder - Shop Drawing Submission C01_7 d/w - 10h/d - No HK 14 05-Jun-22 18-Jun-22 20-Jul-22 02-Aug-22 45
Hols - No B/O periods (was
310.D.WS.L1264.14B01AGL Vault D Annex - Cat Ladder - Shop Drawing PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 28 19-Jun-22 16-Jul-22 03-Aug-22 30-Aug-22 45
Hols - No B/O periods (was
310.D.WS.L1264.15B01AGL Vault D Annex - Cat Ladder - Shop Drawing prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 14 17-Jul-22 30-Jul-22 31-Aug-22 13-Sep-22 45
Hols - No B/O periods (was
310.D.WS.L1264.16B01AGL Vault D Annex - Cat Ladder - Shop Drawing PM review and accept 2nd Round C1) d/w - 10h/d - No HK
C01_7 28 31-Jul-22 27-Aug-22 14-Sep-22 11-Oct-22 45
Hols - No B/O periods (was
AGL Vault D Annex - Shop Drawing submission and Acceptance of Fall Restraint System C1)
C01_7 d/w - 10h/d - No HK Hols84
- No B/O periods
0 (was26-May-22
C1) 17-Aug-22 25-Jun-22 16-Sep-22 30
310.D.WS.L1264.17B01AGL Vault D Annex - Fall Restraint System - Shop Drawing Submission C01_7 d/w - 10h/d - No HK 14 26-May-22 08-Jun-22 25-Jun-22 08-Jul-22 30
Hols - No B/O periods (was
C1)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 185 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L1264.18B01AGL Vault D Annex - Fall Restraint System - Shop Drawing PM review and accept 1st C01_7 d/w - 10h/d - No HK 28 09-Jun-22 06-Jul-22 09-Jul-22 05-Aug-22 30
Round Hols - No B/O periods (was
310.D.WS.L1264.19B01AGL Vault D Annex - Fall Restraint System - Shop Drawing prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 14 07-Jul-22 20-Jul-22 06-Aug-22 19-Aug-22 30
Hols - No B/O periods (was
310.D.WS.L1264.20B01AGL Vault D Annex - Fall Restraint System - Shop Drawing PM review and accept 2nd C1)
C01_7 d/w - 10h/d - No HK 28 21-Jul-22 17-Aug-22 20-Aug-22 16-Sep-22 30
Round Hols - No B/O periods (was
AGL Vault D Annex - Shop Drawing submission and Acceptance of Drainage Channel at R/F C1)
C01_7 d/w - 10h/d - No HK Hols84
- No B/O periods
0 (was26-May-22
C1) 17-Aug-22 28-Jun-22 19-Sep-22 33
310.D.WS.L1264.21B01AGL Vault D Annex - Drainage Channel - Shop Drawing Submission C01_7 d/w - 10h/d - No HK 14 26-May-22 08-Jun-22 28-Jun-22 11-Jul-22 33
Hols - No B/O periods (was
310.D.WS.L1264.22B01AGL Vault D Annex - Drainage Channel - Shop Drawing PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 28 09-Jun-22 06-Jul-22 12-Jul-22 08-Aug-22 33
Hols - No B/O periods (was
310.D.WS.L1264.23B01AGL Vault D Annex - Drainage Channel - Shop Drawing prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 14 07-Jul-22 20-Jul-22 09-Aug-22 22-Aug-22 33
Hols - No B/O periods (was
310.D.WS.L1264.24B01AGL Vault D Annex - Drainage Channel - Shop Drawing PM review and accept 2nd C1)
C01_7 d/w - 10h/d - No HK 28 21-Jul-22 17-Aug-22 23-Aug-22 19-Sep-22 33
Round Hols - No B/O periods (was
AGL Vault D Annex - Shop Drawing submission and Acceptance of Raised Floor at Communication Room C1)
C01_7 d/w - 10h/d - No HK Hols84
- No B/O periods
0 (was26-May-22
C1) 17-Aug-22 05-Jul-22 26-Sep-22 40
310.D.WS.L1264.25B01AGL Vault D Annex - Raised Floor - Shop Drawing Submission C01_7 d/w - 10h/d - No HK 14 26-May-22 08-Jun-22 05-Jul-22 18-Jul-22 40
Hols - No B/O periods (was
310.D.WS.L1264.26B01AGL Vault D Annex - Raised Floor - Shop Drawing PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 28 09-Jun-22 06-Jul-22 19-Jul-22 15-Aug-22 40
Hols - No B/O periods (was
310.D.WS.L1264.27B01AGL Vault D Annex - Raised Floor - Shop Drawing prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 14 07-Jul-22 20-Jul-22 16-Aug-22 29-Aug-22 40
Hols - No B/O periods (was
310.D.WS.L1264.28B01AGL Vault D Annex - Raised Floor - Shop Drawing PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 28 21-Jul-22 17-Aug-22 30-Aug-22 26-Sep-22 40
Hols - No B/O periods (was
AGL Vault D Annex - ABWF Material Submission C1)
C01_7 d/w - 10h/d - No HK Hols116
- No B/O periods
0 (was11-May-22
C1) 03-Sep-22 20-Jun-22 25-Oct-22 52
AGL Vault D Annex - Material Submission and Acceptance of Louvre C01_7 d/w - 10h/d - No HK Hols84
- No B/O periods
0 (was16-May-22
C1) 07-Aug-22 05-Jul-22 26-Sep-22 50
310.D.WS.L1280 AGL Vault D Annex - Louvre - Material Submission - prepare & submission of document C01_7 d/w - 10h/d - No HK 14 16-May-22 29-May-22 05-Jul-22 18-Jul-22 50
Hols - No B/O periods (was
310.D.WS.L1884 AGL Vault D Annex - Louvre - Material Submission - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 28 30-May-22 26-Jun-22 19-Jul-22 15-Aug-22 50
Hols - No B/O periods (was
310.D.WS.L1880 AGL Vault D Annex - Louvre - Material Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 14 27-Jun-22 10-Jul-22 16-Aug-22 29-Aug-22 50
Hols - No B/O periods (was
310.D.WS.L1284 AGL Vault D Annex - Louvre - Material Submission - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 28 11-Jul-22 07-Aug-22 30-Aug-22 26-Sep-22 50
Hols - No B/O periods (was
AGL Vault D Annex - Material Submission and Acceptance of Cladding C1)
C01_7 d/w - 10h/d - No HK Hols84
- No B/O periods
0 (was16-May-22
C1) 07-Aug-22 05-Jul-22 26-Sep-22 50
310.D.WS.L1280.1B01 AGL Vault D Annex - Cladding - Material Submission - prepare & submission of document C01_7 d/w - 10h/d - No HK 14 16-May-22 29-May-22 05-Jul-22 18-Jul-22 50
Hols - No B/O periods (was
310.D.WS.L1884.2B01 AGL Vault D Annex - Cladding - Material Submission - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 28 30-May-22 26-Jun-22 19-Jul-22 15-Aug-22 50
Hols - No B/O periods (was
310.D.WS.L1880.3B01 AGL Vault D Annex - Cladding - Material Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 14 27-Jun-22 10-Jul-22 16-Aug-22 29-Aug-22 50
Hols - No B/O periods (was
310.D.WS.L1284.4B01 AGL Vault D Annex - Cladding - Material Submission - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 28 11-Jul-22 07-Aug-22 30-Aug-22 26-Sep-22 50
Hols - No B/O periods (was
AGL Vault D Annex - Material Submission and Acceptance of Door C1)
C01_7 d/w - 10h/d - No HK Hols84
- No B/O periods
0 (was12-Jun-22
C1) 03-Sep-22 03-Aug-22 25-Oct-22 52
310.D.WS.L1280.5B01 AGL Vault D Annex - Door - Material Submission - prepare & submission of document C01_7 d/w - 10h/d - No HK 14 12-Jun-22 25-Jun-22 03-Aug-22 16-Aug-22 52
Hols - No B/O periods (was
310.D.WS.L1884.6B01 AGL Vault D Annex - Door - Material Submission - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 28 26-Jun-22 23-Jul-22 17-Aug-22 13-Sep-22 52
Hols - No B/O periods (was
310.D.WS.L1880.7B01 AGL Vault D Annex - Door - Material Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 14 24-Jul-22 06-Aug-22 14-Sep-22 27-Sep-22 52
Hols - No B/O periods (was
C1)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 186 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L1284.8B01 AGL Vault D Annex - Door - Material Submission - PM review and accept 2nd Round C01_7 d/w - 10h/d - No HK 28 07-Aug-22 03-Sep-22 28-Sep-22 25-Oct-22 52
Hols - No B/O periods (was
AGL Vault D Annex - Material Submission and Acceptance of Cat Ladder C1)
C01_7 d/w - 10h/d - No HK Hols84
- No B/O periods
0 (was05-Jun-22
C1) 27-Aug-22 20-Jul-22 11-Oct-22 45
310.D.WS.L1280.13B01AGL Vault D Annex - Cat Ladder - Material Submission - prepare & submission of C01_7 d/w - 10h/d - No HK 14 05-Jun-22 18-Jun-22 20-Jul-22 02-Aug-22 45
document Hols - No B/O periods (was
310.D.WS.L1884.14B01AGL Vault D Annex - Cat Ladder - Material Submission - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 28 19-Jun-22 16-Jul-22 03-Aug-22 30-Aug-22 45
Hols - No B/O periods (was
310.D.WS.L1880.15B01AGL Vault D Annex - Cat Ladder - Material Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 14 17-Jul-22 30-Jul-22 31-Aug-22 13-Sep-22 45
Hols - No B/O periods (was
310.D.WS.L1284.16B01AGL Vault D Annex - Cat Ladder - Material Submission - PM review and accept 2nd C1)
C01_7 d/w - 10h/d - No HK 28 31-Jul-22 27-Aug-22 14-Sep-22 11-Oct-22 45
Round Hols - No B/O periods (was
AGL Vault D Annex - Material Submission and Acceptance of Fall Restraint System C1)
C01_7 d/w - 10h/d - No HK Hols84
- No B/O periods
0 (was26-May-22
C1) 17-Aug-22 25-Jun-22 16-Sep-22 30
310.D.WS.L1280.17B01AGL Vault D Annex - Fall Restraint System - Material Submission - prepare & submission C01_7 d/w - 10h/d - No HK 14 26-May-22 08-Jun-22 25-Jun-22 08-Jul-22 30
of document Hols - No B/O periods (was
310.D.WS.L1884.18B01AGL Vault D Annex - Fall Restraint System - Material Submission - PM review and accept C1)
C01_7 d/w - 10h/d - No HK 28 09-Jun-22 06-Jul-22 09-Jul-22 05-Aug-22 30
1st Round Hols - No B/O periods (was
310.D.WS.L1880.19B01AGL Vault D Annex - Fall Restraint System - Material Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 14 07-Jul-22 20-Jul-22 06-Aug-22 19-Aug-22 30
Hols - No B/O periods (was
310.D.WS.L1284.20B01AGL Vault D Annex - Fall Restraint System - Material Submission - PM review and accept C1)
C01_7 d/w - 10h/d - No HK 28 21-Jul-22 17-Aug-22 20-Aug-22 16-Sep-22 30
2nd Round Hols - No B/O periods (was
AGL Vault D Annex - Material Submission and Acceptance of Metal Cover at G/F (1 set) C1)
C01_7 d/w - 10h/d - No HK Hols84
- No B/O periods
0 (was11-May-22
C1) 02-Aug-22 20-Jun-22 11-Sep-22 40
310.D.WS.L1280.9B01 AGL Vault D Annex - Metal Cover - Material Submission - prepare & submission of C01_7 d/w - 10h/d - No HK 14 11-May-22 24-May-22 20-Jun-22 03-Jul-22 40
document Hols - No B/O periods (was
310.D.WS.L1884.10B01AGL Vault D Annex - Metal Cover - Material Submission - PM review and accept 1st C1)
C01_7 d/w - 10h/d - No HK 28 25-May-22 21-Jun-22 04-Jul-22 31-Jul-22 40
Round Hols - No B/O periods (was
310.D.WS.L1880.11B01AGL Vault D Annex - Metal Cover - Material Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 14 22-Jun-22 05-Jul-22 01-Aug-22 14-Aug-22 40
Hols - No B/O periods (was
310.D.WS.L1284.12B01AGL Vault D Annex - Metal Cover - Material Submission - PM review and accept 2nd C1)
C01_7 d/w - 10h/d - No HK 28 06-Jul-22 02-Aug-22 15-Aug-22 11-Sep-22 40
Round Hols - No B/O periods (was
AGL Vault D Annex - Material Submission and Acceptance of Drainage Channel at R/F C1)
C01_7 d/w - 10h/d - No HK Hols84
- No B/O periods
0 (was26-May-22
C1) 17-Aug-22 28-Jun-22 19-Sep-22 33
310.D.WS.L1280.21B01AGL Vault D Annex - Drainage Channel - Material Submission - prepare & submission of C01_7 d/w - 10h/d - No HK 14 26-May-22 08-Jun-22 28-Jun-22 11-Jul-22 33
document Hols - No B/O periods (was
310.D.WS.L1884.22B01AGL Vault D Annex - Drainage Channel - Material Submission - PM review and accept 1st C1)
C01_7 d/w - 10h/d - No HK 28 09-Jun-22 06-Jul-22 12-Jul-22 08-Aug-22 33
Round Hols - No B/O periods (was
310.D.WS.L1880.23B01AGL Vault D Annex - Drainage Channel - Material Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 14 07-Jul-22 20-Jul-22 09-Aug-22 22-Aug-22 33
Hols - No B/O periods (was
310.D.WS.L1284.24B01AGL Vault D Annex - Drainage Channel - Material Submission - PM review and accept C1)
C01_7 d/w - 10h/d - No HK 28 21-Jul-22 17-Aug-22 23-Aug-22 19-Sep-22 33
2nd Round Hols - No B/O periods (was
AGL Vault D Annex - Material Submission and Acceptance of Raised Floor at Communication Room C1)
C01_7 d/w - 10h/d - No HK Hols84
- No B/O periods
0 (was26-May-22
C1) 17-Aug-22 05-Jul-22 26-Sep-22 40
310.D.WS.L1280.25B01AGL Vault D Annex - Raised Floor - Material Submission - prepare & submission of C01_7 d/w - 10h/d - No HK 14 26-May-22 08-Jun-22 05-Jul-22 18-Jul-22 40
document Hols - No B/O periods (was
310.D.WS.L1884.26B01AGL Vault D Annex - Raised Floor - Material Submission - PM review and accept 1st C1)
C01_7 d/w - 10h/d - No HK 28 09-Jun-22 06-Jul-22 19-Jul-22 15-Aug-22 40
Round Hols - No B/O periods (was
310.D.WS.L1880.27B01AGL Vault D Annex - Raised Floor - Material Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 14 07-Jul-22 20-Jul-22 16-Aug-22 29-Aug-22 40
Hols - No B/O periods (was
310.D.WS.L1284.28B01AGL Vault D Annex - Raised Floor - Material Submission - PM review and accept 2nd C1)
C01_7 d/w - 10h/d - No HK 28 21-Jul-22 17-Aug-22 30-Aug-22 26-Sep-22 40
Round Hols - No B/O periods (was
AGL Vault D Annex - BD Submission - Signage C1)
C01_7 d/w - 10h/d - No HK Hols153
- No B/O periods
0 (was26-Apr-22
C1) 25-Sep-22 11-Jun-22 10-Nov-22 46
310.D.WS.L1268.1.B02 AGL Vault D Annex - Louvre - Prepare Design & submit with ICE C01_7 d/w - 10h/d - No HK 14 26-Apr-22 09-May-22 11-Jun-22 24-Jun-22 46
Hols - No B/O periods (was
C1)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 187 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L1268.2.B02 AGL Vault D Annex - Louvre - PM, AP, RSE reviewing C01_7 d/w - 10h/d - No HK 28 10-May-22 06-Jun-22 25-Jun-22 22-Jul-22 46
Hols - No B/O periods (was
310.D.WS.L1268.3.B02 AGL Vault D Annex - Louvre - ICC, M&VC review design and issue check certificate C1)
C01_7 d/w - 10h/d - No HK 21 07-Jun-22 27-Jun-22 23-Jul-22 12-Aug-22 46
Hols - No B/O periods (was
310.D.WS.L1268.5.B02 AGL Vault D Annex - Louvre - BD Review and Acceptance (1st Acceptance requires 2 C1)
C01_7 d/w - 10h/d - No HK 60 28-Jun-22 26-Aug-22 13-Aug-22 11-Oct-22 46
months) Hols - No B/O periods (was
310.D.WS.L1268.6.B02 AGL Vault D Annex - Louvre - Consent Application and Acceptance C1)
C01_7 d/w - 10h/d - No HK 30 27-Aug-22 25-Sep-22 12-Oct-22 10-Nov-22 46
Hols - No B/O periods (was
AGL Vault D Annex - BD Submission - Louvre C1)
C01_7 d/w - 10h/d - No HK Hols153
- No B/O periods
0 (was26-Apr-22
C1) 25-Sep-22 11-Jun-22 10-Nov-22 46
310.D.WS.L1268.1.B01 AGL Vault D Annex - Louvre - Prepare Design & submit with ICE C01_7 d/w - 10h/d - No HK 14 26-Apr-22 09-May-22 11-Jun-22 24-Jun-22 46
Hols - No B/O periods (was
310.D.WS.L1268.2.B01 AGL Vault D Annex - Louvre - PM, AP, RSE reviewing C1)
C01_7 d/w - 10h/d - No HK 28 10-May-22 06-Jun-22 25-Jun-22 22-Jul-22 46
Hols - No B/O periods (was
310.D.WS.L1268.3.B01 AGL Vault D Annex - Louvre - ICC, M&VC review design and issue check certificate C1)
C01_7 d/w - 10h/d - No HK 21 07-Jun-22 27-Jun-22 23-Jul-22 12-Aug-22 46
Hols - No B/O periods (was
310.D.WS.L1268.5.B01 AGL Vault D Annex - Louvre - BD Review and Acceptance (1st Acceptance requires 2 C1)
C01_7 d/w - 10h/d - No HK 60 28-Jun-22 26-Aug-22 13-Aug-22 11-Oct-22 46
months) Hols - No B/O periods (was
310.D.WS.L1268.6.B01 AGL Vault D Annex - Louvre - Consent Application and Acceptance C1)
C01_7 d/w - 10h/d - No HK 30 27-Aug-22 25-Sep-22 12-Oct-22 10-Nov-22 46
Hols - No B/O periods (was
AGL Vault D Annex - BD Submission - Cladding C1)
C01_7 d/w - 10h/d - No HK Hols153
- No B/O periods
0 (was26-Apr-22
C1) 25-Sep-22 11-Jun-22 10-Nov-22 46
310.D.WS.L1268.7.B01 AGL Vault D Annex - Cladding - Prepare Design & submit with ICE C01_7 d/w - 10h/d - No HK 14 26-Apr-22 09-May-22 11-Jun-22 24-Jun-22 46
Hols - No B/O periods (was
310.D.WS.L1268.8.B01 AGL Vault D Annex - Cladding - PM, AP, RSE reviewing C1)
C01_7 d/w - 10h/d - No HK 28 10-May-22 06-Jun-22 25-Jun-22 22-Jul-22 46
Hols - No B/O periods (was
310.D.WS.L1268.9.B01 AGL Vault D Annex - Cladding - ICC, M&VC review design and issue check certificate C1)
C01_7 d/w - 10h/d - No HK 21 07-Jun-22 27-Jun-22 23-Jul-22 12-Aug-22 46
Hols - No B/O periods (was
310.D.WS.L1268.11B01 AGL Vault D Annex - Cladding - BD Review and Acceptance (1st Acceptance requires 2 C1)
C01_7 d/w - 10h/d - No HK 60 28-Jun-22 26-Aug-22 13-Aug-22 11-Oct-22 46
months) Hols - No B/O periods (was
310.D.WS.L1268.12B01 AGL Vault D Annex - Cladding - Consent Application and Acceptance C1)
C01_7 d/w - 10h/d - No HK 30 27-Aug-22 25-Sep-22 12-Oct-22 10-Nov-22 46
Hols - No B/O periods (was
CC#08 - AGL Vault C Annex - MEP Submission C1)
C01_7 d/w - 10h/d - No HK Hols220
- No B/O periods
0 (was
19-Feb-22
C1) A 18-Jun-22 09-Aug-22 31-Oct-22 135
AGL Vault C Annex - MEP - Drawing Submission C01_7 d/w - 10h/d - No HK Hols220
- No B/O periods
0 (was
19-Feb-22
C1) A 18-Jun-22 09-Aug-22 31-Oct-22 135
AGL Vault C Annex - Drawing Submission for CSD & CBWD C01_7 d/w - 10h/d - No HK Hols122
- No B/O periods
0 (was
20-Mar-22
C1) A 31-May-22 27-Aug-22 31-Oct-22 153
310.D.WS.L1080.B01 AGL Vault C Annex - MEP - CSD/CBWD Shop Drawing Submission - prepare & C01_7 d/w - 10h/d - No HK 21 20-Mar-22 A 19-Apr-22 27-Aug-22 19-Sep-22 153
submission of document Hols - No B/O periods (was
310.D.WS.L1084.B01 AGL Vault C Annex - MEP - CSD/CBWD Shop Drawing Submission - PM review and C1)
C01_7 d/w - 10h/d - No HK 14 20-Apr-22 03-May-22 20-Sep-22 03-Oct-22 153
accept Hols - No B/O periods (was
310.D.WS.L1104.B01 AGL Vault C Annex - MEP - CSD/CBWD + ISD Drawing Submission - prepare & C1)
C01_7 d/w - 10h/d - No HK 14 04-May-22 17-May-22 04-Oct-22 17-Oct-22 153
submission of document Hols - No B/O periods (was
310.D.WS.L1108.B01 AGL Vault C Annex - MEP - CSD/CBWD + ISD Drawing Submission - PM review and C1)
C01_7 d/w - 10h/d - No HK 14 18-May-22 31-May-22 18-Oct-22 31-Oct-22 153
accept Hols - No B/O periods (was
AGL Vault C Annex - Drawing Submission for Electrical Services C1)
C01_7 d/w - 10h/d - No HK Hols70
- No B/O periods
0 (was
20-Mar-22
C1) A 18-Jun-22 09-Aug-22 31-Oct-22 135
310.D.WS.L1000 AGL Vault C Annex - MEP - Drawing Submission for Electrical Services - prepare & C01_7 d/w - 10h/d - No HK 14 20-Mar-22 A 09-Apr-22 09-Aug-22 22-Aug-22 135
submission of document Hols - No B/O periods (was
310.D.WS.L1564 AGL Vault C Annex - MEP - Drawing Submission for Electrical Services - PM review and C1)
C01_7 d/w - 10h/d - No HK 28 10-Apr-22 07-May-22 23-Aug-22 19-Sep-22 135
accept 1st Round Hols - No B/O periods (was
310.D.WS.L1560 AGL Vault C Annex - MEP - Drawing Submission for Electrical Services - prepare C1)
C01_7 d/w - 10h/d - No HK 14 08-May-22 21-May-22 20-Sep-22 03-Oct-22 135
resubmission Hols - No B/O periods (was
310.D.WS.L1004 AGL Vault C Annex - MEP - Drawing Submission for Electrical Services - PM review and C1)
C01_7 d/w - 10h/d - No HK 28 22-May-22 18-Jun-22 04-Oct-22 31-Oct-22 135
accept 2nd Round Hols - No B/O periods (was
AGL Vault C Annex - Drawing Submission for MVAC Services C1)
C01_7 d/w - 10h/d - No HK Hols150
- No B/O periods
0 (was
19-Feb-22
C1) A 04-Jun-22 23-Aug-22 31-Oct-22 149

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 188 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L2030.B01 AGL Vault C Annex - MEP - Drawing Submission for MVAC Services - prepare & C01_7 d/w - 10h/d - No HK 14 19-Feb-22 A 09-Apr-22 23-Aug-22 05-Sep-22 149
submission of document Hols - No B/O periods (was
310.D.WS.L2034.B01 AGL Vault C Annex - MEP - Drawing Submission for MVAC Services - PM review and C1)
C01_7 d/w - 10h/d - No HK 28 15-Mar-22 A 23-Apr-22 23-Aug-22 19-Sep-22 149
accept 1st Round Hols - No B/O periods (was
310.D.WS.L2038.B01 AGL Vault C Annex - MEP - Drawing Submission for MVAC Services - prepare C1)
C01_7 d/w - 10h/d - No HK 14 24-Apr-22 07-May-22 20-Sep-22 03-Oct-22 149
resubmission Hols - No B/O periods (was
310.D.WS.L2042.B01 AGL Vault C Annex - MEP - Drawing Submission for MVAC Services - PM review and C1)
C01_7 d/w - 10h/d - No HK 28 08-May-22 04-Jun-22 04-Oct-22 31-Oct-22 149
accept 2nd Round Hols - No B/O periods (was
AGL Vault C Annex - Drawing Submission for Fire Services C1)
C01_7 d/w - 10h/d - No HK Hols66
- No B/O periods
0 (was
07-Mar-22
C1) A 04-Jun-22 23-Aug-22 31-Oct-22 149
310.D.WS.L2050.B01 AGL Vault C Annex - MEP - Drawing Submission for Fire Services - prepare & submission C01_7 d/w - 10h/d - No HK 14 07-Mar-22 A 09-Apr-22 23-Aug-22 05-Sep-22 149
of document Hols - No B/O periods (was
310.D.WS.L2054.B01 AGL Vault C Annex - MEP - Drawing Submission for Fire Services - PM review and C1)
C01_7 d/w - 10h/d - No HK 28 17-Mar-22 A 23-Apr-22 23-Aug-22 19-Sep-22 149
accept 1st Round Hols - No B/O periods (was
310.D.WS.L2058.B01 AGL Vault C Annex - MEP - Drawing Submission for Fire Services - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 14 24-Apr-22 07-May-22 20-Sep-22 03-Oct-22 149
Hols - No B/O periods (was
310.D.WS.L2062.B01 AGL Vault C Annex - MEP - Drawing Submission for Fire Services - PM review and C1)
C01_7 d/w - 10h/d - No HK 28 08-May-22 04-Jun-22 04-Oct-22 31-Oct-22 149
accept 2nd Round Hols - No B/O periods (was
AGL Vault C Annex - Drawing Submission for Plumbing & Drainage Services C1)
C01_7 d/w - 10h/d - No HK Hols136
- No B/O periods
0 (was
23-Feb-22
C1) A 04-Jun-22 23-Aug-22 31-Oct-22 149
310.D.WS.L2066.B01 AGL Vault C Annex - MEP - Drawing Submission for Plumbing & Drainage Services - C01_7 d/w - 10h/d - No HK 14 23-Feb-22 A 09-Apr-22 23-Aug-22 05-Sep-22 149
prepare & submission of document Hols - No B/O periods (was
310.D.WS.L2070.B01 AGL Vault C Annex - MEP - Drawing Submission for Plumbing & Drainage Services - PM C1)
C01_7 d/w - 10h/d - No HK 28 11-Mar-22 A 23-Apr-22 23-Aug-22 19-Sep-22 149
review and accept 1st Round Hols - No B/O periods (was
310.D.WS.L2074.B01 AGL Vault C Annex - MEP - Drawing Submission for Plumbing & Drainage Services - C1)
C01_7 d/w - 10h/d - No HK 14 24-Apr-22 07-May-22 20-Sep-22 03-Oct-22 149
prepare resubmission Hols - No B/O periods (was
310.D.WS.L2078.B01 AGL Vault C Annex - MEP - Drawing Submission for Plumbing & Drainage Services - PM C1)
C01_7 d/w - 10h/d - No HK 28 08-May-22 04-Jun-22 04-Oct-22 31-Oct-22 149
review and accept 2nd Round Hols - No B/O periods (was
CC#08 - AGL Vault C Annex - ABWF Submission C1)
C01_7 d/w - 10h/d - No HK Hols199
- No B/O periods
0 (was26-Apr-22
C1) 10-Nov-22 20-Apr-22 22-Aug-23 285
AGL Vault C Annex - ABWF - Drawing Submission C01_7 d/w - 10h/d - No HK Hols199
- No B/O periods
0 (was26-Apr-22
C1) 10-Nov-22 20-Apr-22 22-Aug-23 285
310.D.WS.L1288.B01 AGL Vault C Annex - ABWF - prepare document C01_7 d/w - 10h/d - No HK 30 26-Apr-22 25-May-22 20-Apr-22 19-May-22 -6
Hols - No B/O periods (was
AGL Vault C Annex - Shop Drawing submission and Acceptance of Louvre C1)
C01_7 d/w - 10h/d - No HK Hols84
- No B/O periods
0 (was12-Jul-22
C1) 03-Oct-22 16-Apr-23 08-Jul-23 278
310.D.WS.L1288 AGL Vault C Annex - Louvre - Shop Drawing Submission C01_7 d/w - 10h/d - No HK 14 12-Jul-22 25-Jul-22 16-Apr-23 29-Apr-23 278
Hols - No B/O periods (was
310.D.WS.L1892 AGL Vault C Annex - Louvre - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 28 26-Jul-22 22-Aug-22 30-Apr-23 27-May-23 278
Hols - No B/O periods (was
310.D.WS.L1888 AGL Vault C Annex - Louvre - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 14 23-Aug-22 05-Sep-22 28-May-23 10-Jun-23 278
Hols - No B/O periods (was
310.D.WS.L1292 AGL Vault C Annex - Louvre - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 28 06-Sep-22 03-Oct-22 11-Jun-23 08-Jul-23 278
Hols - No B/O periods (was
AGL Vault C Annex - Shop Drawing submission and Acceptance of Cladding C1)
C01_7 d/w - 10h/d - No HK Hols84
- No B/O periods
0 (was12-Jul-22
C1) 03-Oct-22 16-Apr-23 08-Jul-23 278
310.D.WS.L1288.20B01AGL Vault C Annex - Cladding - Shop Drawing Submission C01_7 d/w - 10h/d - No HK 14 12-Jul-22 25-Jul-22 16-Apr-23 29-Apr-23 278
Hols - No B/O periods (was
310.D.WS.L1892.20B01AGL Vault C Annex - Cladding - Shop Drawing PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 28 26-Jul-22 22-Aug-22 30-Apr-23 27-May-23 278
Hols - No B/O periods (was
310.D.WS.L1888.20B01AGL Vault C Annex - Cladding - Shop Drawing prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 14 23-Aug-22 05-Sep-22 28-May-23 10-Jun-23 278
Hols - No B/O periods (was
310.D.WS.L1292.20B01AGL Vault C Annex - Cladding - Shop Drawing PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 28 06-Sep-22 03-Oct-22 11-Jun-23 08-Jul-23 278
Hols - No B/O periods (was
AGL Vault C Annex - Shop Drawing submission and Acceptance of Door C1)
C01_7 d/w - 10h/d - No HK Hols84
- No B/O periods
0 (was12-Jul-22
C1) 03-Oct-22 16-Apr-23 08-Jul-23 278
310.D.WS.L1288.30B01AGL Vault C Annex - Door - Shop Drawing Submission C01_7 d/w - 10h/d - No HK 14 12-Jul-22 25-Jul-22 16-Apr-23 29-Apr-23 278
Hols - No B/O periods (was
C1)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 189 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L1892.30B01AGL Vault C Annex - Door - Shop Drawing PM review and accept 1st Round C01_7 d/w - 10h/d - No HK 28 26-Jul-22 22-Aug-22 30-Apr-23 27-May-23 278
Hols - No B/O periods (was
310.D.WS.L1888.30B01AGL Vault C Annex - Door - Shop Drawing prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 14 23-Aug-22 05-Sep-22 28-May-23 10-Jun-23 278
Hols - No B/O periods (was
310.D.WS.L1292.30B01AGL Vault C Annex - Door - Shop Drawing PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 28 06-Sep-22 03-Oct-22 11-Jun-23 08-Jul-23 278
Hols - No B/O periods (was
AGL Vault C Annex - Shop Drawing submission and Acceptance of Stainless chequered plate G/F C1)
C01_7 d/w - 10h/d - No HK Hols84
- No B/O periods
0 (was26-May-22
C1) 17-Aug-22 07-Sep-22 29-Nov-22 104
310.D.WS.L1288.40B01AGL Vault C Annex - Stainless Chequered Plate - Shop Drawing Submission C01_7 d/w - 10h/d - No HK 14 26-May-22 08-Jun-22 07-Sep-22 20-Sep-22 104
Hols - No B/O periods (was
310.D.WS.L1892.40B01AGL Vault C Annex - Stainless Chequered Plate - Shop Drawing PM review and accept C1)
C01_7 d/w - 10h/d - No HK 28 09-Jun-22 06-Jul-22 21-Sep-22 18-Oct-22 104
1st Round Hols - No B/O periods (was
310.D.WS.L1888.40B01AGL Vault C Annex - Stainless Chequered Plate - Shop Drawing prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 14 07-Jul-22 20-Jul-22 19-Oct-22 01-Nov-22 104
Hols - No B/O periods (was
310.D.WS.L1292.40B01AGL Vault C Annex - Stainless Chequered Plate - Shop Drawing PM review and accept C1)
C01_7 d/w - 10h/d - No HK 28 21-Jul-22 17-Aug-22 02-Nov-22 29-Nov-22 104
2nd Round Hols - No B/O periods (was
AGL Vault C Annex - Shop Drawing submission and Acceptance of Cat Ladder C1)
C01_7 d/w - 10h/d - No HK Hols84
- No B/O periods
0 (was12-Jul-22
C1) 03-Oct-22 16-Apr-23 08-Jul-23 278
310.D.WS.L1288.50B01AGL Vault C Annex - Cat Ladder - Shop Drawing Submission C01_7 d/w - 10h/d - No HK 14 12-Jul-22 25-Jul-22 16-Apr-23 29-Apr-23 278
Hols - No B/O periods (was
310.D.WS.L1892.50B01AGL Vault C Annex - Cat Ladder - Shop Drawing PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 28 26-Jul-22 22-Aug-22 30-Apr-23 27-May-23 278
Hols - No B/O periods (was
310.D.WS.L1888.50B01AGL Vault C Annex - Cat Ladder - Shop Drawing prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 14 23-Aug-22 05-Sep-22 28-May-23 10-Jun-23 278
Hols - No B/O periods (was
310.D.WS.L1292.50B01AGL Vault C Annex - Cat Ladder - Shop Drawing PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 28 06-Sep-22 03-Oct-22 11-Jun-23 08-Jul-23 278
Hols - No B/O periods (was
AGL Vault C Annex - Shop Drawing submission and Acceptance of Fall Restraint System C1)
C01_7 d/w - 10h/d - No HK Hols84
- No B/O periods
0 (was12-Jul-22
C1) 03-Oct-22 29-Aug-22 20-Nov-22 48
310.D.WS.L1288.60B01AGL Vault C Annex - Fall Restraint System - Shop Drawing Submission C01_7 d/w - 10h/d - No HK 14 12-Jul-22 25-Jul-22 29-Aug-22 11-Sep-22 48
Hols - No B/O periods (was
310.D.WS.L1892.60B01AGL Vault C Annex - Fall Restraint System - Shop Drawing PM review and accept 1st C1)
C01_7 d/w - 10h/d - No HK 28 26-Jul-22 22-Aug-22 12-Sep-22 09-Oct-22 48
Round Hols - No B/O periods (was
310.D.WS.L1888.60B01AGL Vault C Annex - Fall Restraint System - Shop Drawing prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 14 23-Aug-22 05-Sep-22 10-Oct-22 23-Oct-22 48
Hols - No B/O periods (was
310.D.WS.L1292.60B01AGL Vault C Annex - Fall Restraint System - Shop Drawing PM review and accept 2nd C1)
C01_7 d/w - 10h/d - No HK 28 06-Sep-22 03-Oct-22 24-Oct-22 20-Nov-22 48
Round Hols - No B/O periods (was
AGL Vault C Annex - Shop Drawing submission and Acceptance of Drainage Channel at R/F C1)
C01_7 d/w - 10h/d - No HK Hols84
- No B/O periods
0 (was12-Jul-22
C1) 03-Oct-22 29-Aug-22 20-Nov-22 48
310.D.WS.L1288.70B01AGL Vault C Annex - Drainage Channel - Shop Drawing Submission C01_7 d/w - 10h/d - No HK 14 12-Jul-22 25-Jul-22 29-Aug-22 11-Sep-22 48
Hols - No B/O periods (was
310.D.WS.L1892.70B01AGL Vault C Annex - Drainage Channel - Shop Drawing PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 28 26-Jul-22 22-Aug-22 12-Sep-22 09-Oct-22 48
Hols - No B/O periods (was
310.D.WS.L1888.70B01AGL Vault C Annex - Drainage Channel - Shop Drawing prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 14 23-Aug-22 05-Sep-22 10-Oct-22 23-Oct-22 48
Hols - No B/O periods (was
310.D.WS.L1264.70B01AGL Vault C Annex - Drainage Channel - Shop Drawing PM review and accept 2nd C1)
C01_7 d/w - 10h/d - No HK 28 06-Sep-22 03-Oct-22 24-Oct-22 20-Nov-22 48
Round Hols - No B/O periods (was
AGL Vault C Annex - BD Submission - Signage C1)
C01_7 d/w - 10h/d - No HK Hols169
- No B/O periods
0 (was26-May-22
C1) 10-Nov-22 20-May-22 04-Nov-22 -6
310.D.WS.L1268.B02 AGL Vault C Annex - Louvre - Prepare Design & submit with ICE C01_7 d/w - 10h/d - No HK 30 26-May-22 24-Jun-22 20-May-22 18-Jun-22 -6
Hols - No B/O periods (was
310.D.WS.L1272.B02 AGL Vault C Annex - Louvre - PM, AP, RSE reviewing C1)
C01_7 d/w - 10h/d - No HK 28 25-Jun-22 22-Jul-22 19-Jun-22 16-Jul-22 -6
Hols - No B/O periods (was
310.D.WS.L1276.B02 AGL Vault C Annex - Louvre - ICC, M&VC review design and issue check certificate C1)
C01_7 d/w - 10h/d - No HK 21 23-Jul-22 12-Aug-22 17-Jul-22 06-Aug-22 -6
Hols - No B/O periods (was
310.D.WS.L1280.B02 AGL Vault C Annex - Louvre - BD Review and Acceptance (1st Acceptance requires 2 C1)
C01_7 d/w - 10h/d - No HK 60 13-Aug-22 11-Oct-22 07-Aug-22 05-Oct-22 -6
months) Hols - No B/O periods (was
C1)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 190 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L1284.B02 AGL Vault C Annex - Louvre - Consent Application and Acceptance C01_7 d/w - 10h/d - No HK 30 12-Oct-22 10-Nov-22 06-Oct-22 04-Nov-22 -6
Hols - No B/O periods (was
AGL Vault C Annex - BD Submission - Louvre C1)
C01_7 d/w - 10h/d - No HK Hols169
- No B/O periods
0 (was26-May-22
C1) 10-Nov-22 07-Mar-23 22-Aug-23 285
310.D.WS.L1268.1B01 AGL Vault C Annex - Louvre - Prepare Design & submit with ICE C01_7 d/w - 10h/d - No HK 30 26-May-22 24-Jun-22 07-Mar-23 05-Apr-23 285
Hols - No B/O periods (was
310.D.WS.L1268.2B01 AGL Vault C Annex - Louvre - PM, AP, RSE reviewing C1)
C01_7 d/w - 10h/d - No HK 28 25-Jun-22 22-Jul-22 06-Apr-23 03-May-23 285
Hols - No B/O periods (was
310.D.WS.L1268.3B01 AGL Vault C Annex - Louvre - ICC, M&VC review design and issue check certificate C1)
C01_7 d/w - 10h/d - No HK 21 23-Jul-22 12-Aug-22 04-May-23 24-May-23 285
Hols - No B/O periods (was
310.D.WS.L1268.5B01 AGL Vault C Annex - Louvre - BD Review and Acceptance (1st Acceptance requires 2 C1)
C01_7 d/w - 10h/d - No HK 60 13-Aug-22 11-Oct-22 25-May-23 23-Jul-23 285
months) Hols - No B/O periods (was
310.D.WS.L1268.6B01 AGL Vault C Annex - Louvre - Consent Application and Acceptance C1)
C01_7 d/w - 10h/d - No HK 30 12-Oct-22 10-Nov-22 24-Jul-23 22-Aug-23 285
Hols - No B/O periods (was
AGL Vault C Annex - BD Submission - Cladding C1)
C01_7 d/w - 10h/d - No HK Hols169
- No B/O periods
0 (was26-May-22
C1) 10-Nov-22 07-Mar-23 22-Aug-23 285
310.D.WS.L1268.7B01 AGL Vault C Annex - Cladding - Prepare Design & submit with ICE C01_7 d/w - 10h/d - No HK 30 26-May-22 24-Jun-22 07-Mar-23 05-Apr-23 285
Hols - No B/O periods (was
310.D.WS.L1268.8B01 AGL Vault C Annex - Cladding - PM, AP, RSE reviewing C1)
C01_7 d/w - 10h/d - No HK 28 25-Jun-22 22-Jul-22 06-Apr-23 03-May-23 285
Hols - No B/O periods (was
310.D.WS.L1268.24B01AGL Vault C Annex - Cladding - ICC, M&VC review design and issue check certificate C1)
C01_7 d/w - 10h/d - No HK 21 23-Jul-22 12-Aug-22 04-May-23 24-May-23 285
Hols - No B/O periods (was
310.D.WS.L1268.22B01AGL Vault C Annex - Cladding - BD Review and Acceptance (1st Acceptance requires 2 C1)
C01_7 d/w - 10h/d - No HK 60 13-Aug-22 11-Oct-22 25-May-23 23-Jul-23 285
months) Hols - No B/O periods (was
310.D.WS.L1268.23B01AGL Vault C Annex - Cladding - Consent Application and Acceptance C1)
C01_7 d/w - 10h/d - No HK 30 12-Oct-22 10-Nov-22 24-Jul-23 22-Aug-23 285
Hols - No B/O periods (was
AGL Vault C Annex - ABWF - Material Submission C1)
C01_7 d/w - 10h/d - No HK Hols131
- No B/O periods
0 (was26-May-22
C1) 03-Oct-22 04-Jun-22 08-Jul-23 278
AGL Vault C Annex - Material Submission and Acceptance of Louvre C01_7 d/w - 10h/d - No HK Hols84
- No B/O periods
0 (was12-Jul-22
C1) 03-Oct-22 16-Apr-23 08-Jul-23 278
310.D.WS.L2032.3B01 AGL Vault C Annex - Louvre - Material Submission - prepare document C01_7 d/w - 10h/d - No HK 14 12-Jul-22 25-Jul-22 16-Apr-23 29-Apr-23 278
Hols - No B/O periods (was
310.D.WS.L2044.3B01 AGL Vault C Annex - Louvre - Material Submission - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 28 26-Jul-22 22-Aug-22 30-Apr-23 27-May-23 278
Hols - No B/O periods (was
310.D.WS.L2040.3B01 AGL Vault C Annex - Louvre - Material Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 14 23-Aug-22 05-Sep-22 28-May-23 10-Jun-23 278
Hols - No B/O periods (was
310.D.WS.L2036.3B01 AGL Vault C Annex - Louvre - Material Submission - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 28 06-Sep-22 03-Oct-22 11-Jun-23 08-Jul-23 278
Hols - No B/O periods (was
AGL Vault C Annex - Material Submission and Acceptance of Cladding C1)
C01_7 d/w - 10h/d - No HK Hols84
- No B/O periods
0 (was12-Jul-22
C1) 03-Oct-22 16-Apr-23 08-Jul-23 278
310.D.WS.L1304 AGL Vault C Annex - Cladding - Material Submission - prepare document C01_7 d/w - 10h/d - No HK 14 12-Jul-22 25-Jul-22 16-Apr-23 29-Apr-23 278
Hols - No B/O periods (was
310.D.WS.L1900 AGL Vault C Annex - Cladding - Material Submission - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 28 26-Jul-22 22-Aug-22 30-Apr-23 27-May-23 278
Hols - No B/O periods (was
310.D.WS.L1896 AGL Vault C Annex - Cladding - Material Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 14 23-Aug-22 05-Sep-22 28-May-23 10-Jun-23 278
Hols - No B/O periods (was
310.D.WS.L1308 AGL Vault C Annex - Cladding - Material Submission - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 28 06-Sep-22 03-Oct-22 11-Jun-23 08-Jul-23 278
Hols - No B/O periods (was
AGL Vault C Annex - Material Submission and Acceptance of Door C1)
C01_7 d/w - 10h/d - No HK Hols84
- No B/O periods
0 (was12-Jul-22
C1) 03-Oct-22 16-Apr-23 08-Jul-23 278
310.D.WS.L2048.3B01 AGL Vault C Annex - Door - Material Submission - prepare document C01_7 d/w - 10h/d - No HK 14 12-Jul-22 25-Jul-22 16-Apr-23 29-Apr-23 278
Hols - No B/O periods (was
310.D.WS.L2060.3B01 AGL Vault C Annex - Door - Material Submission - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 28 26-Jul-22 22-Aug-22 30-Apr-23 27-May-23 278
Hols - No B/O periods (was
310.D.WS.L2056.3B01 AGL Vault C Annex - Door - Material Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 14 23-Aug-22 05-Sep-22 28-May-23 10-Jun-23 278
Hols - No B/O periods (was
C1)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 191 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L2052.3B01 AGL Vault C Annex - Door - Material Submission - PM review and accept 2nd Round C01_7 d/w - 10h/d - No HK 28 06-Sep-22 03-Oct-22 11-Jun-23 08-Jul-23 278
Hols - No B/O periods (was
AGL Vault C Annex - Material Submission and Acceptance of Stainless chequered plate C1)
C01_7 d/w - 10h/d - No HK Hols70
- No B/O periods
0 (was26-May-22
C1) 03-Aug-22 04-Jun-22 12-Aug-22 9
310.D.WS.L2064.3B01 AGL Vault C Annex - Stainless Chequered Plate - Material Submission - prepare C01_7 d/w - 10h/d - No HK 14 26-May-22 08-Jun-22 04-Jun-22 17-Jun-22 9
document Hols - No B/O periods (was
310.D.WS.L2076.3B01 AGL Vault C Annex - Stainless Chequered Plate - Material Submission - PM review and C1)
C01_7 d/w - 10h/d - No HK 28 09-Jun-22 06-Jul-22 18-Jun-22 15-Jul-22 9
accept 1st Round Hols - No B/O periods (was
310.D.WS.L2072.3B01 AGL Vault C Annex - Stainless Chequered Plate - Material Submission - prepare C1)
C01_7 d/w - 10h/d - No HK 14 07-Jul-22 20-Jul-22 16-Jul-22 29-Jul-22 9
resubmission Hols - No B/O periods (was
310.D.WS.L2068.3B01 AGL Vault C Annex - Stainless Chequered Plate - Material Submission - PM review and C1)
C01_7 d/w - 10h/d - No HK 14 21-Jul-22 03-Aug-22 30-Jul-22 12-Aug-22 9
accept 2nd Round Hols - No B/O periods (was
AGL Vault C Annex - Material Submission and Acceptance of Cat Ladder C1)
C01_7 d/w - 10h/d - No HK Hols84
- No B/O periods
0 (was12-Jul-22
C1) 03-Oct-22 16-Apr-23 08-Jul-23 278
310.D.WS.L2080.3B01 AGL Vault C Annex - Cat Ladder - Material Submission - prepare document C01_7 d/w - 10h/d - No HK 14 12-Jul-22 25-Jul-22 16-Apr-23 29-Apr-23 278
Hols - No B/O periods (was
310.D.WS.L2092.3B01 AGL Vault C Annex - Cat Ladder - Material Submission - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 28 26-Jul-22 22-Aug-22 30-Apr-23 27-May-23 278
Hols - No B/O periods (was
310.D.WS.L2088.3B01 AGL Vault C Annex - Cat Ladder - Material Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 14 23-Aug-22 05-Sep-22 28-May-23 10-Jun-23 278
Hols - No B/O periods (was
310.D.WS.L2084.3B01 AGL Vault C Annex - Cat Ladder - Material Submission - PM review and accept 2nd C1)
C01_7 d/w - 10h/d - No HK 28 06-Sep-22 03-Oct-22 11-Jun-23 08-Jul-23 278
Round Hols - No B/O periods (was
AGL Vault C Annex - Material Submission and Acceptance of Fall Restraint System C1)
C01_7 d/w - 10h/d - No HK Hols84
- No B/O periods
0 (was12-Jul-22
C1) 03-Oct-22 29-Aug-22 20-Nov-22 48
310.D.WS.L2096.3B01 AGL Vault C Annex - Fall Restraint System - Material Submission - prepare document C01_7 d/w - 10h/d - No HK 14 12-Jul-22 25-Jul-22 29-Aug-22 11-Sep-22 48
Hols - No B/O periods (was
310.D.WS.L2108.3B01 AGL Vault C Annex - Fall Restraint System - Material Submission - PM review and accept C1)
C01_7 d/w - 10h/d - No HK 28 26-Jul-22 22-Aug-22 12-Sep-22 09-Oct-22 48
1st Round Hols - No B/O periods (was
310.D.WS.L2104.3B01 AGL Vault C Annex - Fall Restraint System - Material Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 14 23-Aug-22 05-Sep-22 10-Oct-22 23-Oct-22 48
Hols - No B/O periods (was
310.D.WS.L2100.3B01 AGL Vault C Annex - Fall Restraint System - Material Submission - PM review and accept C1)
C01_7 d/w - 10h/d - No HK 28 06-Sep-22 03-Oct-22 24-Oct-22 20-Nov-22 48
2nd Round Hols - No B/O periods (was
AGL Vault C Annex - Material Submission and Acceptance of Drainage Channel C1)
C01_7 d/w - 10h/d - No HK Hols84
- No B/O periods
0 (was12-Jul-22
C1) 03-Oct-22 29-Aug-22 20-Nov-22 48
310.D.WS.L2112.3B01 AGL Vault C Annex - Drainage Channel - Material Submission - prepare document C01_7 d/w - 10h/d - No HK 14 12-Jul-22 25-Jul-22 29-Aug-22 11-Sep-22 48
Hols - No B/O periods (was
310.D.WS.L2124.3B01 AGL Vault C Annex - Drainage Channel - Material Submission - PM review and accept 1st C1)
C01_7 d/w - 10h/d - No HK 28 26-Jul-22 22-Aug-22 12-Sep-22 09-Oct-22 48
Round Hols - No B/O periods (was
310.D.WS.L2120.3B01 AGL Vault C Annex - Drainage Channel - Material Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 14 23-Aug-22 05-Sep-22 10-Oct-22 23-Oct-22 48
Hols - No B/O periods (was
310.D.WS.L2116.3B01 AGL Vault C Annex - Drainage Channel - Material Submission - PM review and accept C1)
C01_7 d/w - 10h/d - No HK 28 06-Sep-22 03-Oct-22 24-Oct-22 20-Nov-22 48
2nd Round Hols - No B/O periods (was
CC#8 - Hoarding Plan - AGL Vault D Annex C1)
C01_7 d/w - 10h/d - No HK Hols139
- No B/O periods
0 (was
26-Aug-21
C1) A 17-Jan-22 A 09-May-22 09-May-22
310.D.R0.L540 Hoarding Plan AGL Vault D Annex - Prepare Design & submit with ICE C01_7 d/w - 10h/d - No HK 30 26-Aug-21 A 21-Sep-21 A 09-May-22 09-May-22
Hols - No B/O periods (was
310.D.R0.L544 Hoarding Plan AGL Vault D Annex - PM, AP, RSE reviewing C1)
C01_7 d/w - 10h/d - No HK 28 22-Sep-21 A 11-Oct-21 A 09-May-22 09-May-22
Hols - No B/O periods (was
310.D.R0.L548 Hoarding Plan AGL Vault D Annex - ICC, M&VC review design and issue check certificate C1)
C01_7 d/w - 10h/d - No HK 21 12-Oct-21 A 19-Nov-21 A 09-May-22 09-May-22
Hols - No B/O periods (was
310.D.R0.L556 Hoarding Plan AGL Vault D Annex - 1st BD review and Acceptance C1)
C01_7 d/w - 10h/d - No HK 60 17-Nov-21 A 17-Jan-22 A 09-May-22 09-May-22
Hols - No B/O periods (was
CC#8 - Hoarding Plan - AGL Vault C Annex C1)
C01_7 d/w - 10h/d - No HK Hols274
- No B/O periods
0 (was
01-Sep-21
C1) A 09-Apr-22 03-May-22 16-May-22 37
310.D.R0.L568 Hoarding Plan AGL Vault C Annex - Prepare Design & submit with ICE C01_7 d/w - 10h/d - No HK 30 01-Sep-21 A 29-Sep-21 A 03-May-22 03-May-22
Hols - No B/O periods (was
C1)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 192 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.R0.L572 Hoarding Plan AGL Vault C Annex - PM, AP, RSE reviewing C01_7 d/w - 10h/d - No HK 28 30-Sep-21 A 24-Oct-21 A 03-May-22 03-May-22
Hols - No B/O periods (was
310.D.R0.L576 Hoarding Plan AGL Vault C Annex - ICC, M&VC review design and issue check certificate C1)
C01_7 d/w - 10h/d - No HK 21 25-Oct-21 A 16-Nov-21 A 03-May-22 03-May-22
Hols - No B/O periods (was
310.D.R0.L580 Hoarding Plan AGL Vault C Annex - 1st BD review and accept C1)
C01_7 d/w - 10h/d - No HK 60 17-Nov-21 A 17-Jan-22 A 03-May-22 03-May-22
Hols - No B/O periods (was
310.D.R0.L584 Hoarding Plan AGL Vault C Annex - prepare and submit Form BA8 and grant consent C1)
C01_7 d/w - 10h/d - No HK
7 20-Jan-22 A 02-Apr-22 03-May-22 09-May-22 37
Hols - No B/O periods (was
310.D.R0.L588 Hoarding Plan AGL Vault C Annex - prepare and submit Form BA10 (with instrumentation C1)
C01_7 d/w - 10h/d - No HK 7 03-Apr-22 09-Apr-22 10-May-22 16-May-22 37
readings) Hols - No B/O periods (was
CC#08 ----- Procurement ----- C1)
C01_7 d/w - 10h/d - No HK Hols301
- No B/O periods
0 (was
05-Oct-21
C1) A 01-Aug-22 21-Mar-22 01-Sep-22 31
CC#08 - Subletting - Ancillary Buildings C01_7 d/w - 10h/d - No HK Hols301
- No B/O periods
0 (was
05-Oct-21
C1) A 01-Aug-22 21-Mar-22 01-Sep-22 31
310.P.EX.F144 Subletting - Vault C & D Earthwork - Award sub-contract C01_7 d/w - 10h/d - No HK 90 05-Oct-21 A 28-Nov-21 A 28-Mar-22 28-Mar-22
Hols - No B/O periods (was
310.P.EX.F144.B01 Subletting - Vault C Earthwork - Award sub-contract C1)
C01_7 d/w - 10h/d - No HK 90 05-Oct-21 A 28-Nov-21 A 23-Apr-22 23-Apr-22
Hols - No B/O periods (was
310.P.EX.F96 Subletting - Vault C MEP - Award sub-contract C1)
C01_7 d/w - 10h/d - No HK 90 30-Oct-21 A 18-Jan-22 A 21-Jun-22 21-Jun-22
Hols - No B/O periods (was
310.P.EX.F100 Subletting - Vault D MEP - Award sub-contract C1)
C01_7 d/w - 10h/d - No HK 90 30-Oct-21 A 18-Jan-22 A 19-Apr-22 19-Apr-22
Hols - No B/O periods (was
310.P.EX.F104 Subletting - Ancillary Buildings MEP - Award sub-contract C1)
C01_7 d/w - 10h/d - No HK 90 30-Oct-21 A 18-Jan-22 A 18-May-22 18-May-22
Hols - No B/O periods (was
310.P.EX.F152 Subletting - Vault C & D RC Structural Works - Award sub-contract C1)
C01_7 d/w - 10h/d - No HK 90 04-Nov-21 A 28-Nov-21 A 19-Apr-22 19-Apr-22
Hols - No B/O periods (was
310.P.EX.F108 Subletting - ABWF (Plastering) - Stage 1&2 Preparation,Submission& C1)
C01_7 d/w - 10h/d - No HK 90 03-Jan-22 A 20-Apr-22 26-Mar-22 19-Apr-22 -1
Approval,Tender&Award sub-contract Hols - No B/O periods (was
310.P.EX.F112 Subletting - ABWF (Painting) - Stage 1&2 Preparation,Submission& C1)
C01_7 d/w - 10h/d - No HK 90 03-Jan-22 A 25-Apr-22 21-Mar-22 19-Apr-22 -6
Approval,Tender&Award sub-contract Hols - No B/O periods (was
310.P.EX.F165.B01 Subletting - ABWF (Door) - Stage 1&2 Preparation,Submission& Approval,Tender&Award C1)
C01_7 d/w - 10h/d - No HK 90 03-Jan-22 A 25-Apr-22 21-Mar-22 19-Apr-22 -6
sub-contract Hols - No B/O periods (was
310.P.EX.F169.B01 Subletting - ABWF (Louver,Window,etc) - Stage 1&2 Preparation,Submission& C1)
C01_7 d/w - 10h/d - No HK 90 03-Jan-22 A 25-Apr-22 21-Mar-22 19-Apr-22 -6
Approval,Tender&Award sub-contract Hols - No B/O periods (was
310.P.EX.F173.B01 Subletting - ABWF (Steel&Metal) - Stage 1&2 Preparation,Submission& C1)
C01_7 d/w - 10h/d - No HK 90 03-Jan-22 A 25-Apr-22 21-Mar-22 19-Apr-22 -6
Approval,Tender&Award sub-contract Hols - No B/O periods (was
310.P.EX.F136 Subletting - Ancillary Buildings Earthwork - Stage 1&2 Preparation,Submission& C1)
C01_7 d/w - 10h/d - No HK 90 01-May-22 29-Jul-22 22-May-22 19-Aug-22 21
Approval,Tender&Award sub-contract Hols - No B/O periods (was
310.P.EX.F148 Subletting-Ancillary Buildings&Government Facilities RC-Stage 1&2 C1)
C01_7 d/w - 10h/d - No HK 62 01-Jun-22 01-Aug-22 02-Jul-22 01-Sep-22 31
Preparation,Submission& Approval,Tender&Award Hols - No B/O periods (was
CC#08 ----- Construction ----- C1) 731 4 07-Jun-21 A 17-Nov-23 19-Feb-22 31-Aug-24 234
ESA - C&ED Operational Office and Kennel Area 363 0 30-Aug-22 17-Nov-23 05-Sep-22 04-Jan-24 38
Procurement C01_7 d/w - 10h/d - No HK Hols282
- No B/O periods
0 (was30-Aug-22
C1) 07-Jun-23 28-Oct-22 20-Jul-23 43
Major Materials ABWF C01_7 d/w - 10h/d - No HK Hols141
- No B/O periods
0 (was18-Jan-23
C1) 07-Jun-23 02-Mar-23 20-Jul-23 43
310.P.ES.M011 C&ED Op.Office & Kennel Area (Procurement ABWF)- C01_7 d/w - 10h/d - No HK 7 18-Jan-23 24-Jan-23 02-Mar-23 08-Mar-23 43
louvres,doors,windows,handrails,cladding&Others-Place Order Hols - No B/O periods (was
310.P.ES.M027 C&ED Op.Office & Kennel Area (Procurement ABWF) - Manufacturing of Materials C1)
C01_7 d/w - 10h/d - No HK 120 25-Jan-23 24-May-23 09-Mar-23 06-Jul-23 43
Hols - No B/O periods (was
310.P.ES.M035 C&ED Op.Office & Kennel Area (Procurement ABWF) - Delivery of Materials C1)
C01_7 d/w - 10h/d - No HK 14 25-May-23 07-Jun-23 07-Jul-23 20-Jul-23 43
Hols - No B/O periods (was
Major Materials MEP C1)
C01_7 d/w - 10h/d - No HK Hols252
- No B/O periods
0 (was30-Aug-22
C1) 08-May-23 28-Oct-22 06-Jul-23 59
310.P.ES.M015 C&ED Op.Office & Kennel Area (Procurement FS and P&D Materials) - NOVEC 1230, C01_7 d/w - 10h/d - No HK 180 30-Aug-22 25-Feb-23 28-Oct-22 25-Apr-23 59
FA system, Sprinkler&Others-Place Order Hols - No B/O periods (was
C1)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 193 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.P.ES.M661 C&ED Op.Office & Kennel Area (Procurement FS and P&D Materials) - Manufacturing of C01_7 d/w - 10h/d - No HK 210 13-Sep-22 10-Apr-23 11-Nov-22 08-Jun-23 59
Material Hols - No B/O periods (was
310.P.ES.M023 C&ED Op.Office & Kennel Area (Procurement Electrical Materials) - cable trays, LV C1)
C01_7 d/w - 10h/d - No HK 30 30-Sep-22 29-Oct-22 09-Mar-23 07-Apr-23 160
panels, generators&Others-Place Order Hols - No B/O periods (was
310.P.ES.M019 C&ED Op.Office & Kennel Area (Procurement MVAC)- ventilation fan, a/c units, air C1)
C01_7 d/w - 10h/d - No HK 30 30-Oct-22 28-Nov-22 09-Mar-23 07-Apr-23 130
ducting & Others - Place Order Hols - No B/O periods (was
310.P.ES.M657 C&ED Op.Office & Kennel Area (Procurement Electrical Materials) - Manufacturing of C1)
C01_7 d/w - 10h/d - No HK 90 30-Oct-22 27-Jan-23 08-Apr-23 06-Jul-23 160
Material Hols - No B/O periods (was
310.P.ES.M653 C&ED Op.Office & Kennel Area (Procurement MVAC)- Manufacturing of Material C1)
C01_7 d/w - 10h/d - No HK 90 29-Nov-22 26-Feb-23 08-Apr-23 06-Jul-23 130
Hols - No B/O periods (was
310.P.ES.M665 C&ED Op.Office & Kennel Area (Procurement MEP) - Delivery of Material C1)
C01_7 d/w - 10h/d - No HK 28 11-Apr-23 08-May-23 09-Jun-23 06-Jul-23 59
Hols - No B/O periods (was
Initial Works C1) 38 0 05-Sep-22 21-Oct-22 05-Sep-22 10-Nov-22 17
310.C.ES.M011 C&ED Op. Office & Kennel Area - Site access WA 3310/7 and WA 3310/7A C01_7 d/w - 10h/d - No HK 0 05-Sep-22* 05-Sep-22 0
Hols - No B/O periods (was
310.C.ES.M015 C&ED Op. Office & Kennel Area - Hoarding C1)
C11_6 d/w - 10h/d - With 5 05-Sep-22 09-Sep-22 25-Oct-22 29-Oct-22 40
HK Hols - No B/O periods
310.C.ES.M019 C&ED Op. Office & Kennel Area - Carry out site survey + Report (was
C11_6C3)
d/w - 10h/d - With 7 05-Sep-22 13-Sep-22 26-Sep-22 05-Oct-22 17
HK Hols - No B/O periods
310.C.ES.M023 C&ED Op. Office & Kennel Area - Install monitoring point (was
C11_6C3)
d/w - 10h/d - With 1 14-Sep-22 14-Sep-22 06-Oct-22 06-Oct-22 17
HK Hols - No B/O periods
310.C.ES.M027 C&ED Op. Office & Kennel Area - UU detection and trial pit (was
C11_6C3)
d/w - 10h/d - With 6 15-Sep-22 21-Sep-22 07-Oct-22 13-Oct-22 17
HK Hols - No B/O periods
310.D.ES.M011 Submit BA8 consent application (foundation works) (was
C01_7C3)
d/w - 10h/d - No HK 28 19-Sep-22 16-Oct-22 26-Sep-22 23-Oct-22 7
Hols - No B/O periods (was
310.C.ES.M047.B01 C&ED Op. Office & Kennel Area - diversion of underground utilities (if any) C1)
C11_6 d/w - 10h/d - With 24 22-Sep-22 21-Oct-22 14-Oct-22 10-Nov-22 17
HK Hols - No B/O periods
Structural Works (was C3) 174 0 17-Oct-22 18-May-23 24-Oct-22 25-May-23 6
310.C.ES.M031 C&ED Op. Office & Kennel Area - BA10 notice of commencement of works C01_7 d/w - 10h/d - No HK 7 17-Oct-22 23-Oct-22 24-Oct-22 30-Oct-22 7
Hols - No B/O periods (was
310.C.ES.M035 C&ED Op. Office & Kennel Area - SI works C1)
C11_6 d/w - 10h/d - With 10 24-Oct-22 03-Nov-22 31-Oct-22 10-Nov-22 6
HK Hols - No B/O periods
310.C.ES.M039 C&ED Op. Office & Kennel Area - Open Cut Excavation to FL (4351 m3) (was
C11_6C3)
d/w - 10h/d - With 21 04-Nov-22 28-Nov-22 11-Nov-22 05-Dec-22 6
HK Hols - No B/O periods
310.C.ES.M041 C&ED Op. Office & Kennel Area - Plate Load Test (was
C11_6C3)
d/w - 10h/d - With 7 29-Nov-22 06-Dec-22 06-Dec-22 13-Dec-22 6
HK Hols - No B/O periods
310.C.ES.M043 C&ED Op. Office & Kennel Area - Foundation/footing, bearing wall, backfill (7002m3) (was
C11_6C3)
d/w - 10h/d - With 30 07-Dec-22 12-Jan-23 14-Dec-22 19-Jan-23 6
HK Hols - No B/O periods
310.C.ES.M051 C&ED Op. Office & Kennel Area (GF) - Construction of base slab, column and walls (was
C11_6C3)
d/w - 10h/d - With 50 13-Jan-23 15-Mar-23 20-Jan-23 22-Mar-23 6
(1827m3) HK Hols - No B/O periods
310.C.ES.M059 C&ED Op. Office & Kennel Area - Construction of Water Pump Room, Generator Room, (was
C11_6C3)
d/w - 10h/d - With 30 16-Mar-23 24-Apr-23 23-Mar-23 02-May-23 6
LV Switch Room, Water Tank (127m3) HK Hols - No B/O periods
310.C.ES.M063 C&ED Op. Office & Kennel Area - Roof Level - Construction of roof slab, RC beam (was
C11_6C3)
d/w - 10h/d - With 30 13-Apr-23 18-May-23 20-Apr-23 25-May-23 6
(547m3) HK Hols - No B/O periods
ABWF (was
C11_6C3)
d/w - 10h/d - With HK Hols
135- No B/O 0periods (was
06-Jun-23
C3) 16-Nov-23 13-Jun-23 04-Jan-24 39
310.C.EX.W1660 C&ED Op. Office & Kennel Area - Structure completed and falsework removal C11_6 d/w - 10h/d - With 0 06-Jun-23 13-Jun-23 6
HK Hols - No B/O periods
310.C.EX.W1616 C&ED Op. Office & Kennel Area - Partition Wall & Door Subframe (was
C11_6C3)
d/w - 10h/d - With 60 08-Jun-23 18-Aug-23 21-Jul-23 28-Sep-23 35
HK Hols - No B/O periods
310.C.EX.W1620 C&ED Op. Office & Kennel Area - Plastering & Screeding (was
C11_6C3)
d/w - 10h/d - With 60 20-Jun-23 30-Aug-23 02-Aug-23 12-Oct-23 35
HK Hols - No B/O periods
(was C3)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 194 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.EX.W1624 C&ED Op. Office & Kennel Area - Tiling & Stonework C11_6 d/w - 10h/d - With 60 04-Jul-23 11-Sep-23 14-Aug-23 25-Oct-23 35
HK Hols - No B/O periods
310.C.EX.W1628 C&ED Op. Office & Kennel Area - Suspended Ceiling Framework (was
C11_6C3)
d/w - 10h/d - With 60 15-Jul-23 22-Sep-23 25-Aug-23 06-Nov-23 35
HK Hols - No B/O periods
310.C.EX.W1632 C&ED Op. Office & Kennel Area - Sanitary Ware & Fixtures (was
C11_6C3)
d/w - 10h/d - With 60 27-Jul-23 06-Oct-23 06-Sep-23 17-Nov-23 35
HK Hols - No B/O periods
310.C.EX.W1636 C&ED Op. Office & Kennel Area - Fire Shutter, Door Sets & Ironmongery (was
C11_6C3)
d/w - 10h/d - With 60 08-Aug-23 18-Oct-23 22-Sep-23 04-Dec-23 39
HK Hols - No B/O periods
310.C.EX.W1640 C&ED Op. Office & Kennel Area - Glazing (was
C11_6C3)
d/w - 10h/d - With 60 19-Aug-23 31-Oct-23 06-Oct-23 15-Dec-23 39
HK Hols - No B/O periods
310.C.EX.W1644 C&ED Op. Office & Kennel Area - Ceiling Panels & Finishes (was
C11_6C3)
d/w - 10h/d - With 60 31-Aug-23 11-Nov-23 18-Oct-23 29-Dec-23 39
HK Hols - No B/O periods
310.C.EX.W1648 C&ED Op. Office & Kennel Area - Painting, Graphics & Signage (was
C11_6C3)
d/w - 10h/d - With 60 05-Sep-23 16-Nov-23 24-Oct-23 04-Jan-24 39
HK Hols - No B/O periods
MEP Installation Works (was
C11_6C3)
d/w - 10h/d - With HK Hols
118- No B/O 0periods (was
29-Jun-23
C3) 17-Nov-23 07-Jul-23 29-Nov-23 10
Plumbing & Drainage Installation C11_6 d/w - 10h/d - With HK Hols
94- No B/O 0periods (was
29-Jun-23
C3) 19-Oct-23 07-Jul-23 27-Oct-23 6
310.C.EX.W1592 C&ED Op. Office & Kennel Area - Plumbing & Drainage 1st Fix & Installation C11_6 d/w - 10h/d - With 48 29-Jun-23 24-Aug-23 07-Jul-23 31-Aug-23 6
HK Hols - No B/O periods
310.C.EX.W1600 C&ED Op. Office & Kennel Area - Water Pump Installation (was
C11_6C3)
d/w - 10h/d - With 48 10-Jul-23 02-Sep-23 21-Jul-23 14-Sep-23 10
HK Hols - No B/O periods
310.C.EX.W1596 C&ED Op. Office & Kennel Area - Plumbing & Drainage 2nd Fix & Installation (was
C11_6C3)
d/w - 10h/d - With 48 21-Jul-23 14-Sep-23 28-Jul-23 21-Sep-23 6
HK Hols - No B/O periods
310.C.EX.W1612 C&ED Op. Office & Kennel Area - Plumbing & Drainage Final Fix & Adjustment (was
C11_6C3)
d/w - 10h/d - With 6 13-Oct-23 19-Oct-23 20-Oct-23 27-Oct-23 6
HK Hols - No B/O periods
Electrical Installation (was
C11_6C3)
d/w - 10h/d - With HK Hols
106- No B/O 0periods (was
07-Jul-23
C3) 10-Nov-23 19-Jul-23 22-Nov-23 10
310.C.EX.W1500 C&ED Op. Office & Kennel Area - Electrical 1st Fix & Installation C11_6 d/w - 10h/d - With 50 07-Jul-23 02-Sep-23 19-Jul-23 14-Sep-23 10
HK Hols - No B/O periods
310.C.EX.W1508 C&ED Op. Office & Kennel Area - Switchgear Installation (was
C11_6C3)
d/w - 10h/d - With 48 04-Aug-23 28-Sep-23 16-Aug-23 12-Oct-23 10
HK Hols - No B/O periods
310.C.EX.W1512 C&ED Op. Office & Kennel Area - Emergency Genset Installation (was
C11_6C3)
d/w - 10h/d - With 48 04-Aug-23 28-Sep-23 16-Aug-23 12-Oct-23 10
HK Hols - No B/O periods
310.C.EX.W1504 C&ED Op. Office & Kennel Area - Electrical 2nd Fix & Installation (was
C11_6C3)
d/w - 10h/d - With 50 04-Aug-23 03-Oct-23 04-Sep-23 03-Nov-23 26
HK Hols - No B/O periods
310.C.EX.W1516 C&ED Op. Office & Kennel Area - Power On to All Floors (was
C11_6C3)
d/w - 10h/d - With 0 28-Sep-23 12-Oct-23 10
HK Hols - No B/O periods
310.C.EX.W1528 C&ED Op. Office & Kennel Area - Electrical Final Fix & Adjustment (was
C11_6C3)
d/w - 10h/d - With 6 04-Nov-23 10-Nov-23 16-Nov-23 22-Nov-23 10
HK Hols - No B/O periods
Fire Services Installation (was
C11_6C3)
d/w - 10h/d - With HK Hols
116- No B/O 0periods (was
03-Jul-23
C3) 17-Nov-23 17-Jul-23 29-Nov-23 10
310.C.EX.W1532 C&ED Op. Office & Kennel Area - Fire Services 1st Fix & Installation C11_6 d/w - 10h/d - With 50 03-Jul-23 29-Aug-23 17-Jul-23 12-Sep-23 12
HK Hols - No B/O periods
310.C.EX.W1540 C&ED Op. Office & Kennel Area - FS Pump Installation (was
C11_6C3)
d/w - 10h/d - With 48 12-Jul-23 05-Sep-23 23-Aug-23 19-Oct-23 36
HK Hols - No B/O periods
310.C.EX.W1536 C&ED Op. Office & Kennel Area - Fire Services 2nd Fix & Installation (was
C11_6C3)
d/w - 10h/d - With 50 31-Jul-23 26-Sep-23 14-Aug-23 12-Oct-23 12
HK Hols - No B/O periods
310.C.EX.W1552 C&ED Op. Office & Kennel Area - Fire Services Final Fix & Adjustment (was
C11_6C3)
d/w - 10h/d - With 6 11-Nov-23 17-Nov-23 23-Nov-23 29-Nov-23 10
HK Hols - No B/O periods
MVAC Installation (was
C11_6C3)
d/w - 10h/d - With HK Hols
90- No B/O 0periods (was
04-Jul-23
C3) 18-Oct-23 05-Aug-23 21-Nov-23 28
310.C.EX.W1556 C&ED Op. Office & Kennel Area - MVAC 1st Fix & Installation C11_6 d/w - 10h/d - With 50 04-Jul-23 30-Aug-23 05-Aug-23 04-Oct-23 28
HK Hols - No B/O periods
310.C.EX.W1560 C&ED Op. Office & Kennel Area - MVAC 2nd Fix & Installation (was
C11_6C3)
d/w - 10h/d - With 50 01-Aug-23 27-Sep-23 02-Sep-23 02-Nov-23 28
HK Hols - No B/O periods
(was C3)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 195 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.EX.W1572 C&ED Op. Office & Kennel Area - MVAC Final Fix & Adjustment C11_6 d/w - 10h/d - With 6 12-Oct-23 18-Oct-23 15-Nov-23 21-Nov-23 28
HK Hols - No B/O periods
External Works (was
C11_6C3)
d/w - 10h/d - With HK Hols
150- No B/O 0periods (was
19-May-23
C3) 16-Nov-23 04-Aug-23 04-Jan-24 39
External Building Finishes C11_6 d/w - 10h/d - With HK Hols
63- No B/O 0periods (was
19-May-23
C3) 03-Aug-23 04-Aug-23 18-Oct-23 63
310.C.ES.M067 C&ED Op. Office & Kennel Area - Roof waterproofing & Roof Finishes (1153 m2) C11_6 d/w - 10h/d - With 15 19-May-23 06-Jun-23 04-Aug-23 21-Aug-23 63
HK Hols - No B/O periods
310.C.ES.P640 C&ED Op. Office & Kennel Area - External building finishes (was
C11_6C3)
d/w - 10h/d - With 48 07-Jun-23 03-Aug-23 22-Aug-23 18-Oct-23 63
HK Hols - No B/O periods
Drainage and UU (was
C11_6C3)
d/w - 10h/d - With HK Hols
78- No B/O 0periods (was
07-Jun-23
C3) 07-Sep-23 22-Aug-23 07-Dec-23 75
310.C.ES.P620 C&ED Op. Office & Kennel Area - Building drainage and watermain works C11_6 d/w - 10h/d - With 48 07-Jun-23 03-Aug-23 22-Aug-23 18-Oct-23 63
HK Hols - No B/O periods
310.C.ES.P624 C&ED Op. Office & Kennel Area - AS Cable ducts + drawpits (was
C11_6C3)
d/w - 10h/d - With 21 04-Aug-23 28-Aug-23 14-Nov-23 07-Dec-23 84
HK Hols - No B/O periods
310.C.ES.P628 C&ED Op. Office & Kennel Area - EL cable ducting + drawpits (was
C11_6C3)
d/w - 10h/d - With 21 04-Aug-23 28-Aug-23 19-Oct-23 13-Nov-23 63
HK Hols - No B/O periods
310.C.ES.P644 C&ED Op. Office & Kennel Area - CLP Cable ducts + drawpits (was
C11_6C3)
d/w - 10h/d - With 30 04-Aug-23 07-Sep-23 03-Nov-23 07-Dec-23 75
HK Hols - No B/O periods
Soft and Hard landscape & EVA Construction (was
C11_6C3)
d/w - 10h/d - With HK Hols
57- No B/O 0periods (was
08-Sep-23
C3) 16-Nov-23 14-Nov-23 04-Jan-24 39
310.C.ES.P632 C&ED Op. Office & Kennel Area - Hard and soft landscape wroks C11_6 d/w - 10h/d - With 21 08-Sep-23 04-Oct-23 08-Dec-23 04-Jan-24 75
HK Hols - No B/O periods
310.C.ES.C100 C&ED Op. Office & Kennel Area - Site Formation Works and Road Works for EVA (was C3)
C11_6 d/w - 10h/d - With 42 26-Sep-23 16-Nov-23 14-Nov-23 04-Jan-24 39
HK Hols - No B/O periods
WSA - Comm. Equipment Building D (was C3) 217 0 29-May-22 17-Feb-23 11-Jun-22 18-Feb-23 1
Procurement C01_7 d/w - 10h/d - No HK Hols163
- No B/O periods
0 (was29-May-22
C1) 07-Nov-22 11-Jun-22 08-Nov-22 1
Major Materials ABWF C01_7 d/w - 10h/d - No HK Hols134
- No B/O periods
0 (was07-Jun-22
C1) 18-Oct-22 15-Jun-22 26-Oct-22 8
310.P.WS.M510 Comm Eqpt Bldg D (Procurement ABWF)- C01_7 d/w - 10h/d - No HK 7 07-Jun-22 13-Jun-22 15-Jun-22 21-Jun-22 8
louvres,doors,windows,handrails,cladding&Others-Place Order of Materials Hols - No B/O periods (was
310.P.WS.M522 Comm Eqpt Bldg D (Procurement ABWF) - Manufacturing of Materials C1)
C01_7 d/w - 10h/d - No HK 120 14-Jun-22 11-Oct-22 22-Jun-22 19-Oct-22 8
Hols - No B/O periods (was
310.P.WS.M528 Comm Eqpt Bldg D (Procurement ABWF) - Delivery of Materials C1)
C01_7 d/w - 10h/d - No HK 7 12-Oct-22 18-Oct-22 20-Oct-22 26-Oct-22 8
Hols - No B/O periods (was
Major Materials MEP C1)
C01_7 d/w - 10h/d - No HK Hols163
- No B/O periods
0 (was29-May-22
C1) 07-Nov-22 11-Jun-22 08-Nov-22 1
310.P.WS.M513 Comm Eqpt Bldg D (Procurement FS Materials) - NOVEC 1230, FA system, Sprinkler C01_7 d/w - 10h/d - No HK 70 29-May-22 06-Aug-22 11-Jun-22 19-Aug-22 13
system & Others -Place Order for Material Hols - No B/O periods (was
310.P.WS.M519 Comm Eqpt Bldg D (Procurement Electrical Materials) - cable trays,LV C1)
C01_7 d/w - 10h/d - No HK 30 05-Jun-22 04-Jul-22 11-Jun-22 10-Jul-22 6
panels&Others-Place Order for Material Hols - No B/O periods (was
310.P.WS.M656 Comm Eqpt Bldg D (Procurement FS Materials) - NOVEC 1230, FA, Sprinkler & C1)
C01_7 d/w - 10h/d - No HK 130 12-Jun-22 19-Oct-22 25-Jun-22 01-Nov-22 13
Others-Manufacturing of Material Hols - No B/O periods (was
310.P.WS.M664 Comm Eqpt Bldg D (Procurement Electrical Materials)-cable trays,LV C1)
C01_7 d/w - 10h/d - No HK 130 19-Jun-22 26-Oct-22 25-Jun-22 01-Nov-22 6
panels,generators&Others-Manufacuting of Material Hols - No B/O periods (was
310.P.WS.M516 Comm Eqpt Bldg D (Procurement MVAC Materials) - ventilation fan, a/c units,air C1)
C01_7 d/w - 10h/d - No HK 65 27-Jun-22 30-Aug-22 28-Jun-22 31-Aug-22 1
ducting&Others - Place Order for Material Hols - No B/O periods (was
310.P.WS.M660 Comm Eqpt Bldg D (Procurement MVAC Materials) - ventilation fan, a/c units, air C1)
C01_7 d/w - 10h/d - No HK 120 04-Jul-22 31-Oct-22 05-Jul-22 01-Nov-22 1
ducting&Others-Manufacturing of Material Hols - No B/O periods (was
310.P.WS.M668 Comm Eqpt Bldg D (Procurement MEP) - Delivery of Material C1)
C01_7 d/w - 10h/d - No HK 7 01-Nov-22 07-Nov-22 02-Nov-22 08-Nov-22 1
Hols - No B/O periods (was
Initial Works C1) 5 0 05-Sep-22 09-Sep-22 05-Sep-22 12-Sep-22 1
310.C.WS.M516 WSA - Comm Eqpt Bldg D - Site access WA 3310/9 C01_7 d/w - 10h/d - No HK 0 05-Sep-22* 05-Sep-22 0
Hols - No B/O periods (was
310.C.WS.M522 WSA - Comm Eqpt Bldg D - Site survey, hoarding, UU detection/trial pits C1)
C11_6 d/w - 10h/d - With 3 05-Sep-22 07-Sep-22 06-Sep-22 08-Sep-22 1
HK Hols - No B/O periods
(was C3)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 196 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.WS.M528 WSA - Comm Eqpt Bldg D - Install Instrumentation (piezometers, settlement markers, C11_6 d/w - 10h/d - With 3 05-Sep-22 07-Sep-22 08-Sep-22 12-Sep-22 3
groundwater checkpoint) HK Hols - No B/O periods
310.C.WS.M529.B01 WSA - Comm Eqpt Bldg D - Diversion of underground utilities (if any) (was
C11_6C3)
d/w - 10h/d - With 3 07-Sep-22 09-Sep-22 08-Sep-22 12-Sep-22 1
HK Hols - No B/O periods
Structural Works (was C3) 79 0 20-Jul-22 22-Oct-22 30-Aug-22 14-Nov-22 19
310.C.WS.M510 WSA - Comm Eqpt Bldg D - Submit BA8 consent application (foundation works) C01_7 d/w - 10h/d - No HK 7 20-Jul-22 26-Jul-22 30-Aug-22 05-Sep-22 41
Hols - No B/O periods (was
310.C.WS.M513 WSA - Comm Eqpt Bldg D - Submit BA10 notice of commencement to work C1)
C01_7 d/w - 10h/d - No HK 7 27-Jul-22 02-Aug-22 06-Sep-22 12-Sep-22 41
Hols - No B/O periods (was
310.C.WS.M531 WSA - Comm Eqpt Bldg D - SI works C1)
C11_6 d/w - 10h/d - With 1 08-Sep-22 08-Sep-22 12-Sep-22 12-Sep-22 2
HK Hols - No B/O periods
310.C.WS.M534 WSA - Comm Eqpt Bldg D - Open cut excavation to foundation level (596m3) (was
C11_6C3)
d/w - 10h/d - With 2 12-Sep-22 13-Sep-22 13-Sep-22 14-Sep-22 1
HK Hols - No B/O periods
310.C.WS.M537 WSA - Comm Eqpt Bldg D - Foundation Works - Plate load test & Report (was
C11_6C3)
d/w - 10h/d - With 12 14-Sep-22 27-Sep-22 15-Sep-22 28-Sep-22 1
HK Hols - No B/O periods
310.C.WS.M541 WSA - Comm Eqpt Bldg D - Foundation Works - Footing & Backfilling (105m3) (was
C11_6C3)
d/w - 10h/d - With 6 28-Sep-22 06-Oct-22 29-Sep-22 07-Oct-22 1
HK Hols - No B/O periods
310.C.WS.M543 WSA - Comm Eqpt Bldg D - Ground Floor - construction of base slab and columns (was
C11_6C3)
d/w - 10h/d - With 6 07-Oct-22 13-Oct-22 08-Oct-22 14-Oct-22 1
(124m3) HK Hols - No B/O periods
310.C.WS.M546 WSA - Comm Eqpt Bldg D - Roof - construction of walls, RC beams and roof slab (was
C11_6C3)
d/w - 10h/d - With 10 12-Oct-22 22-Oct-22 03-Nov-22 14-Nov-22 19
(226m3) HK Hols - No B/O periods
ABWF (was
C11_6C3)
d/w - 10h/d - With HK Hols
54- No B/O 0periods (was
25-Oct-22
C3) 28-Dec-22 26-Oct-22 29-Dec-22 1
310.C.EX.W1824 WSA - Comm Eqpt Bldg D - Structure completed and falsework removal C11_6 d/w - 10h/d - With 0 25-Oct-22 26-Oct-22 1
HK Hols - No B/O periods
310.C.EX.W1780 WSA - Comm Eqpt Bldg D - Partition Wall & Door Subframe (was
C11_6C3)
d/w - 10h/d - With 30 26-Oct-22 29-Nov-22 27-Oct-22 30-Nov-22 1
HK Hols - No B/O periods
310.C.EX.W1784 WSA - Comm Eqpt Bldg D - Plastering & Screeding (was
C11_6C3)
d/w - 10h/d - With 30 29-Oct-22 02-Dec-22 31-Oct-22 03-Dec-22 1
HK Hols - No B/O periods
310.C.EX.W1788 WSA - Comm Eqpt Bldg D - Tiling & Stonework (was
C11_6C3)
d/w - 10h/d - With 30 02-Nov-22 06-Dec-22 03-Nov-22 07-Dec-22 1
HK Hols - No B/O periods
310.C.EX.W1792 WSA - Comm Eqpt Bldg D - Suspended Ceiling Framework (was
C11_6C3)
d/w - 10h/d - With 30 05-Nov-22 09-Dec-22 07-Nov-22 10-Dec-22 1
HK Hols - No B/O periods
310.C.EX.W1796 WSA - Comm Eqpt Bldg D - Sanitary Ware & Fixtures (was
C11_6C3)
d/w - 10h/d - With 30 09-Nov-22 13-Dec-22 10-Nov-22 14-Dec-22 1
HK Hols - No B/O periods
310.C.EX.W1800 WSA - Comm Eqpt Bldg D - Door Sets & Ironmongery (was
C11_6C3)
d/w - 10h/d - With 30 12-Nov-22 16-Dec-22 14-Nov-22 17-Dec-22 1
HK Hols - No B/O periods
310.C.EX.W1804 WSA - Comm Eqpt Bldg D - Glazing (was
C11_6C3)
d/w - 10h/d - With 30 16-Nov-22 20-Dec-22 17-Nov-22 21-Dec-22 1
HK Hols - No B/O periods
310.C.EX.W1808 WSA - Comm Eqpt Bldg D - Ceiling Panels & Finishes (was
C11_6C3)
d/w - 10h/d - With 30 19-Nov-22 23-Dec-22 21-Nov-22 24-Dec-22 1
HK Hols - No B/O periods
310.C.EX.W1812 WSA - Comm Eqpt Bldg D - Painting, Graphics & Signage (was
C11_6C3)
d/w - 10h/d - With 30 23-Nov-22 28-Dec-22 24-Nov-22 29-Dec-22 1
HK Hols - No B/O periods
MEP Installation Works (was
C11_6C3)
d/w - 10h/d - With HK Hols
63- No B/O 0periods (was
03-Nov-22
C3) 17-Jan-23 05-Nov-22 04-Feb-23 13
Drainage Installation C11_6 d/w - 10h/d - With HK Hols
53- No B/O 0periods (was
08-Nov-22
C3) 10-Jan-23 09-Nov-22 11-Jan-23 1
310.C.EX.W1756 WSA - Comm Eqpt Bldg D - Drainage 1st Fix & Installation C11_6 d/w - 10h/d - With 30 08-Nov-22 12-Dec-22 09-Nov-22 13-Dec-22 1
HK Hols - No B/O periods
310.C.EX.W1760 WSA - Comm Eqpt Bldg D - Drainage 2nd Fix & Installation (was
C11_6C3)
d/w - 10h/d - With 30 22-Nov-22 27-Dec-22 25-Nov-22 30-Dec-22 3
HK Hols - No B/O periods
310.C.EX.W1776 WSA - Comm Eqpt Bldg D - Drainage Final Fix & Adjustment (was
C11_6C3)
d/w - 10h/d - With 5 05-Jan-23 10-Jan-23 06-Jan-23 11-Jan-23 1
HK Hols - No B/O periods
Electrical Installation (was
C11_6C3)
d/w - 10h/d - With HK Hols
63- No B/O 0periods (was
03-Nov-22
C3) 17-Jan-23 05-Nov-22 19-Jan-23 2

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 197 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.EX.W1664 WSA - Comm Eqpt Bldg D - Electrical 1st Fix & Installation C11_6 d/w - 10h/d - With 30 03-Nov-22 07-Dec-22 05-Nov-22 09-Dec-22 2
HK Hols - No B/O periods
310.C.EX.W1668 WSA - Comm Eqpt Bldg D - Electrical 2nd Fix & Installation (was
C11_6C3)
d/w - 10h/d - With 30 15-Nov-22 19-Dec-22 17-Nov-22 21-Dec-22 2
HK Hols - No B/O periods
310.C.EX.W1672 WSA - Comm Eqpt Bldg D - Switchgear Installation (was
C11_6C3)
d/w - 10h/d - With 18 24-Nov-22 14-Dec-22 01-Dec-22 21-Dec-22 6
HK Hols - No B/O periods
310.C.EX.W1680 WSA - Comm Eqpt Bldg D - Power On to All Floors (was
C11_6C3)
d/w - 10h/d - With 0 19-Dec-22 21-Dec-22 2
HK Hols - No B/O periods
310.C.EX.W1692 WSA - Comm Eqpt Bldg D - Electrical Final Fix & Adjustment (was
C11_6C3)
d/w - 10h/d - With 5 12-Jan-23 17-Jan-23 14-Jan-23 19-Jan-23 2
HK Hols - No B/O periods
Fire Services Installation (was
C11_6C3)
d/w - 10h/d - With HK Hols
63- No B/O 0periods (was
03-Nov-22
C3) 17-Jan-23 17-Nov-22 19-Jan-23 2
310.C.EX.W1696 WSA - Comm Eqpt Bldg D - Fire Services 1st Fix & Installation C11_6 d/w - 10h/d - With 30 03-Nov-22 07-Dec-22 17-Nov-22 21-Dec-22 12
HK Hols - No B/O periods
310.C.EX.W1700 WSA - Comm Eqpt Bldg D - Fire Services 2nd Fix & Installation (was
C11_6C3)
d/w - 10h/d - With 30 19-Nov-22 23-Dec-22 03-Dec-22 09-Jan-23 12
HK Hols - No B/O periods
310.C.EX.W1716 WSA - Comm Eqpt Bldg D - Fire Service Final Fix & Adjustment (was
C11_6C3)
d/w - 10h/d - With 5 12-Jan-23 17-Jan-23 14-Jan-23 19-Jan-23 2
HK Hols - No B/O periods
MVAC Installation (was
C11_6C3)
d/w - 10h/d - With HK Hols
53- No B/O 0periods (was
03-Nov-22
C3) 05-Jan-23 30-Nov-22 04-Feb-23 23
310.C.EX.W1720 WSA - Comm Eqpt Bldg D - MVAC 1st Fix & Installation C11_6 d/w - 10h/d - With 30 03-Nov-22 07-Dec-22 30-Nov-22 05-Jan-23 23
HK Hols - No B/O periods
310.C.EX.W1724 WSA - Comm Eqpt Bldg D - MVAC 2nd Fix & Installation (was
C11_6C3)
d/w - 10h/d - With 30 15-Nov-22 19-Dec-22 16-Dec-22 21-Jan-23 27
HK Hols - No B/O periods
310.C.EX.W1736 WSA - Comm Eqpt Bldg D - MVAC Final Fix & Adjustment (was
C11_6C3)
d/w - 10h/d - With 5 30-Dec-22 05-Jan-23 31-Jan-23 04-Feb-23 23
HK Hols - No B/O periods
External Works (was
C11_6C3)
d/w - 10h/d - With HK Hols
96- No B/O 0periods (was
24-Oct-22
C3) 17-Feb-23 22-Nov-22 18-Feb-23 1
External Building Finishes C11_6 d/w - 10h/d - With HK Hols
56- No B/O 0periods (was
24-Oct-22
C3) 28-Dec-22 22-Nov-22 29-Dec-22 1
310.C.WS.M549 WSA - Comm Eqpt Bldg D - Roof Slab - waterproofing & Roof Finishes (11 m2) C11_6 d/w - 10h/d - With 2 24-Oct-22 25-Oct-22 22-Nov-22 23-Nov-22 25
HK Hols - No B/O periods
310.C.ES.P668 WSA - Comm Eqpt Bldg D - External building finishes (was
C11_6C3)
d/w - 10h/d - With 30 23-Nov-22 28-Dec-22 24-Nov-22 29-Dec-22 1
HK Hols - No B/O periods
Drainage and UU (was
C11_6C3)
d/w - 10h/d - With HK Hols
42- No B/O 0periods (was
23-Nov-22
C3) 12-Jan-23 24-Nov-22 04-Feb-23 17
310.C.ES.P648 WSA - Comm Eqpt Bldg D - Building drainage and watermain works C11_6 d/w - 10h/d - With 28 23-Nov-22 24-Dec-22 24-Nov-22 27-Dec-22 1
HK Hols - No B/O periods
310.C.ES.P652 WSA - Comm Eqpt Bldg D - AS Cable ducts + drawpits (was
C11_6C3)
d/w - 10h/d - With 14 27-Dec-22 12-Jan-23 17-Jan-23 04-Feb-23 17
HK Hols - No B/O periods
310.C.ES.P656 WSA - Comm Eqpt Bldg D - EL cable ducting + drawpits (was
C11_6C3)
d/w - 10h/d - With 14 27-Dec-22 12-Jan-23 28-Dec-22 13-Jan-23 1
HK Hols - No B/O periods
Soft and Hard landscape & EVA Construction (was
C11_6C3)
d/w - 10h/d - With HK Hols
28- No B/O 0periods (was
13-Jan-23
C3) 17-Feb-23 14-Jan-23 18-Feb-23 1
310.C.ES.P660 WSA - Comm Eqpt Bldg D - Hard and soft landscape works C11_6 d/w - 10h/d - With 12 13-Jan-23 30-Jan-23 06-Feb-23 18-Feb-23 17
HK Hols - No B/O periods
310.C.WS.C100 WSA - Comm Eqpt Bldg D - Site Formation Works and Road Works for EVA (was
C11_6C3)
d/w - 10h/d - With 28 13-Jan-23 17-Feb-23 14-Jan-23 18-Feb-23 1
HK Hols - No B/O periods
ESA - GSE Vehicle Wash Facility (was C3) 199 0 28-May-22 26-Jan-23 22-Jun-22 28-Jan-23 2
Procurement C01_7 d/w - 10h/d - No HK Hols165
- No B/O periods
0 (was28-May-22
C1) 08-Nov-22 22-Jun-22 14-Nov-22 6
Major Materials ABWF C01_7 d/w - 10h/d - No HK Hols134
- No B/O periods
0 (was28-Jun-22
C1) 08-Nov-22 04-Jul-22 14-Nov-22 6
310.P.ES.M610 GSE Vehicle Wash Facility (Procurement ABWF)- louvres, doors, windows, handrails, C01_7 d/w - 10h/d - No HK 7 28-Jun-22 04-Jul-22 04-Jul-22 10-Jul-22 6
cladding&Others-Place Order Hols - No B/O periods (was
310.P.ES.M619 GSE Vehicle Wash Facility (Procurement ABWF) - Manufacturing of Materials C1)
C01_7 d/w - 10h/d - No HK 120 05-Jul-22 01-Nov-22 11-Jul-22 07-Nov-22 6
Hols - No B/O periods (was
310.P.ES.M625 GSE Vehicle Wash Facility (Procurement ABWF) - Delivery of Materials C1)
C01_7 d/w - 10h/d - No HK 7 02-Nov-22 08-Nov-22 08-Nov-22 14-Nov-22 6
Hols - No B/O periods (was
C1)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 198 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
Major Materials MEP C01_7 d/w - 10h/d - No HK Hols165
- No B/O periods
0 (was28-May-22
C1) 08-Nov-22 22-Jun-22 14-Nov-22 6
310.P.ES.M616 GSE Vehicle Wash Facility (Procurement Electrical & MVAC C01_7 d/w - 10h/d - No HK 30 28-May-22 26-Jun-22 27-Jun-22 26-Jul-22 30
Materials)-power&lights&Others-Place Order for Material Hols - No B/O periods (was
310.P.ES.M673 GSE Vehicle Wash Facility (Procurement Electrical & MVAC Materials) - C1)
C01_7 d/w - 10h/d - No HK 120 11-Jun-22 08-Oct-22 11-Jul-22 07-Nov-22 30
power&lights&Others-Manufacturing of Material Hols - No B/O periods (was
310.P.ES.M613 GSE Vehicle Wash Facility (Procurement FS and P&D Materials) - FA system,Hose C1)
C01_7 d/w - 10h/d - No HK 80 16-Jun-22 03-Sep-22 22-Jun-22 09-Sep-22 6
Wheel&Others-Place Order for Material Hols - No B/O periods (was
310.P.ES.M669 GSE Vehicle Wash Facility (Procurement FS and P&D Materials) - FA system, Hose C1)
C01_7 d/w - 10h/d - No HK 125 30-Jun-22 01-Nov-22 06-Jul-22 07-Nov-22 6
Wheel&Others-Manufacturing of Material Hols - No B/O periods (was
310.P.ES.M677 GSE Vehicle Wash Facility (Procurement MEP) - Delivery of Materials C1)
C01_7 d/w - 10h/d - No HK 7 02-Nov-22 08-Nov-22 08-Nov-22 14-Nov-22 6
Hols - No B/O periods (was
Initial Works C1) 28 0 05-Sep-22 10-Oct-22 05-Sep-22 17-Oct-22 6
310.C.ES.M725 ESA - GSE Wash Facility - Site access WA 3310/7, 7A C01_7 d/w - 10h/d - No HK 0 05-Sep-22* 05-Sep-22 0
Hols - No B/O periods (was
310.C.ES.M731 ESA - GSE Wash Facility - Site survey, hoarding, UU detection/trial pit C1)
C11_6 d/w - 10h/d - With 4 05-Sep-22 08-Sep-22 05-Sep-22 08-Sep-22 0
HK Hols - No B/O periods
310.C.ES.M737 ESA - GSE Wash Facility - Install Instrumentation (piezometers, settlement markers, (was
C11_6C3)
d/w - 10h/d - With 5 09-Sep-22 15-Sep-22 09-Sep-22 15-Sep-22 0
groundwater checkpoint) HK Hols - No B/O periods
310.C.ES.M735.B01 ESA - GSE Wash Facility - Diversion of underground utilities (if any) (was
C11_6C3)
d/w - 10h/d - With 24 09-Sep-22 10-Oct-22 17-Sep-22 17-Oct-22 6
HK Hols - No B/O periods
Structural Works (was C3) 45 0 16-Sep-22 09-Nov-22 16-Sep-22 09-Nov-22 0
310.C.TC.M600 ESA - GSE Wash Facility - Submit BA8 consent application C01_7 d/w - 10h/d - No HK 7 16-Sep-22 22-Sep-22 16-Sep-22 22-Sep-22 0
Hols - No B/O periods (was
310.C.TC.M456 ESA - GSE Wash Facility - submit BA10 notice of commencement of work C1)
C01_7 d/w - 10h/d - No HK 7 23-Sep-22 29-Sep-22 23-Sep-22 29-Sep-22 0
Hols - No B/O periods (was
310.C.TC.M420 ESA - GSE Wash Facility - SI works + reports C1)
C11_6 d/w - 10h/d - With 3 30-Sep-22 05-Oct-22 30-Sep-22 05-Oct-22 0
HK Hols - No B/O periods
310.C.TC.M448 ESA - GSE Wash Facility - submit Geotechnical Assessment Report to PM (was
C11_6C3)
d/w - 10h/d - With 2 06-Oct-22 07-Oct-22 06-Oct-22 07-Oct-22 0
HK Hols - No B/O periods
310.C.TC.M424 ESA - GSE Wash Facility - backfill from +3.0mPD (handover level) to +5.65mPD (FL) (was
C03_7C3)
d/w - 10h/d - With 7 06-Oct-22 12-Oct-22 11-Oct-22 17-Oct-22 5
HK Hols - No B/O periods
310.C.TC.M452 ESA - GSE Wash Facility - PM submit Geotechnical Assessment Report to BD C01_7 d/w - 10h/d - No HK 10 08-Oct-22 17-Oct-22 08-Oct-22 17-Oct-22 0
Hols - No B/O periods (was
310.C.TC.M429 ESA - GSE Wash Facility - Foundation Works -plate load test, footing + backfill to GL C1)
C03_7 d/w - 10h/d - With 12 18-Oct-22 29-Oct-22 18-Oct-22 29-Oct-22 0
(Exc=638m3, Conc=163m3) HK Hols - No B/O periods
310.C.TC.M436 ESA - GSE Wash Facility - Ground Floor - construction of base slab and columns (57m3) C03_7 d/w - 10h/d - With 5 30-Oct-22 03-Nov-22 30-Oct-22 03-Nov-22 0
HK Hols - No B/O periods
310.C.TC.M440 ESA - GSE Wash Facility - Roof - construction of walls, RC beams and roof slab (249m3) C03_7 d/w - 10h/d - With 6 04-Nov-22 09-Nov-22 04-Nov-22 09-Nov-22 0
HK Hols - No B/O periods
ABWF C11_6 d/w - 10h/d - With HK Hols
50- No B/O 0periods (was
11-Nov-22
C3) 11-Jan-23 11-Nov-22 13-Jan-23 2
310.C.EX.W1964 ESA - GSE Wash Facility -Structure completed and falsework removal C11_6 d/w - 10h/d - With 0 11-Nov-22 11-Nov-22 0
HK Hols - No B/O periods
310.C.EX.W1928 ESA - GSE Wash Facility - Partition Wall & Door Subframe (was
C11_6C3)
d/w - 10h/d - With 30 12-Nov-22 16-Dec-22 15-Nov-22 19-Dec-22 2
HK Hols - No B/O periods
310.C.EX.W1932 ESA - GSE Wash Facility - Plastering & Screeding (was
C11_6C3)
d/w - 10h/d - With 30 17-Nov-22 21-Dec-22 19-Nov-22 23-Dec-22 2
HK Hols - No B/O periods
310.C.EX.W1936 ESA - GSE Wash Facility - Tiling & Stonework (was
C11_6C3)
d/w - 10h/d - With 30 22-Nov-22 27-Dec-22 24-Nov-22 29-Dec-22 2
HK Hols - No B/O periods
310.C.EX.W1948 ESA - GSE Wash Facility - Door Sets & Ironmongery (was
C11_6C3)
d/w - 10h/d - With 30 26-Nov-22 31-Dec-22 29-Nov-22 04-Jan-23 2
HK Hols - No B/O periods
(was C3)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 199 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.EX.W1956 ESA - GSE Wash Facility - Ceiling Finishes C11_6 d/w - 10h/d - With 30 01-Dec-22 06-Jan-23 03-Dec-22 09-Jan-23 2
HK Hols - No B/O periods
310.C.EX.W1960 ESA - GSE Wash Facility - Painting, Graphics & Signage (was
C11_6C3)
d/w - 10h/d - With 30 06-Dec-22 11-Jan-23 08-Dec-22 13-Jan-23 2
HK Hols - No B/O periods
MEP Installation Works (was
C11_6C3)
d/w - 10h/d - With HK Hols
55- No B/O 0periods (was
15-Nov-22
C3) 19-Jan-23 15-Nov-22 19-Jan-23 0
Plumbing & Drainage Installation C11_6 d/w - 10h/d - With HK Hols
39- No B/O 0periods (was
15-Nov-22
C3) 30-Dec-22 15-Nov-22 30-Dec-22 0
310.C.EX.W1904 ESA - GSE Wash Facility - Plumbing & Drainage 1st Fix & Installation C11_6 d/w - 10h/d - With 22 15-Nov-22 09-Dec-22 15-Nov-22 09-Dec-22 0
HK Hols - No B/O periods
310.C.EX.W1912 ESA - GSE Wash Facility - Water Pump Installation (was
C11_6C3)
d/w - 10h/d - With 18 19-Nov-22 09-Dec-22 19-Nov-22 09-Dec-22 0
HK Hols - No B/O periods
310.C.EX.W1908 ESA - GSE Wash Facility - Plumbing & Drainage 2nd Fix & Installation (was
C11_6C3)
d/w - 10h/d - With 24 21-Nov-22 17-Dec-22 22-Nov-22 19-Dec-22 1
HK Hols - No B/O periods
310.C.EX.W1924 ESA - GSE Wash Facility - Plumbing & Drainage Final Fix & Adjustment (was
C11_6C3)
d/w - 10h/d - With 5 24-Dec-22 30-Dec-22 24-Dec-22 30-Dec-22 0
HK Hols - No B/O periods
Electrical Installation (was
C11_6C3)
d/w - 10h/d - With HK Hols
52- No B/O 0periods (was
18-Nov-22
C3) 19-Jan-23 18-Nov-22 19-Jan-23 0
310.C.EX.W1828 ESA - GSE Wash Facility - Electrical 1st Fix & Installation C11_6 d/w - 10h/d - With 24 18-Nov-22 15-Dec-22 18-Nov-22 15-Dec-22 0
HK Hols - No B/O periods
310.C.EX.W1832 ESA - GSE Wash Facility - Electrical 2nd Fix & Installation (was
C11_6C3)
d/w - 10h/d - With 24 26-Nov-22 23-Dec-22 26-Nov-22 23-Dec-22 0
HK Hols - No B/O periods
310.C.EX.W1844 ESA - GSE Wash Facility - Power On (was
C11_6C3)
d/w - 10h/d - With 0 23-Dec-22 23-Dec-22 0
HK Hols - No B/O periods
310.C.EX.W1856 ESA - GSE Wash Facility - Electrical Final Fix & Adjustment (was
C11_6C3)
d/w - 10h/d - With 5 14-Jan-23 19-Jan-23 14-Jan-23 19-Jan-23 0
HK Hols - No B/O periods
Fire Services Installation (was
C11_6C3)
d/w - 10h/d - With HK Hols
52- No B/O 0periods (was
18-Nov-22
C3) 19-Jan-23 21-Nov-22 19-Jan-23 0
310.C.EX.W1860 ESA - GSE Wash Facility - Fire Services 1st Fix & Installation C11_6 d/w - 10h/d - With 24 18-Nov-22 15-Dec-22 21-Nov-22 17-Dec-22 2
HK Hols - No B/O periods
310.C.EX.W1864 ESA - GSE Wash Facility - Fire Services 2nd Fix & Installation (was
C11_6C3)
d/w - 10h/d - With 24 26-Nov-22 23-Dec-22 29-Nov-22 27-Dec-22 2
HK Hols - No B/O periods
310.C.EX.W1868 ESA - GSE Wash Facility - FS Pump Installation (was
C11_6C3)
d/w - 10h/d - With 24 30-Nov-22 28-Dec-22 08-Dec-22 06-Jan-23 7
HK Hols - No B/O periods
310.C.EX.W1880 ESA - GSE Wash Facility - Fire Services Final Fix & Adjustment (was
C11_6C3)
d/w - 10h/d - With 5 14-Jan-23 19-Jan-23 14-Jan-23 19-Jan-23 0
HK Hols - No B/O periods
External Works (was C3) 105 0 19-Sep-22 26-Jan-23 26-Nov-22 28-Jan-23 2
External Building Finishes 52 0 10-Nov-22 11-Jan-23 09-Dec-22 13-Jan-23 2
310.C.TC.M444 ESA - GSE Wash Facility - Roof Slab - waterproofing & Roof Finishes C03_7 d/w - 10h/d - With 1 10-Nov-22 10-Nov-22 09-Dec-22 09-Dec-22 29
HK Hols - No B/O periods
310.C.ES.P692 ESA - GSE Wash Facility - External building finishes C11_6 d/w - 10h/d - With 28 08-Dec-22 11-Jan-23 10-Dec-22 13-Jan-23 2
HK Hols - No B/O periods
Drainage and UU (was C3) 95 0 19-Sep-22 11-Jan-23 26-Nov-22 13-Jan-23 2
310.C.TC.M604.B01 ESA - GSE Wash Facility - Submit BA8 consent application (Drainage Works) C01_7 d/w - 10h/d - No HK 7 19-Sep-22 25-Sep-22 26-Nov-22 02-Dec-22 68
Hols - No B/O periods (was
310.C.TC.M608.B01 ESA - GSE Wash Facility - submit BA10 notice of commencement of work (Drainage C1)
C01_7 d/w - 10h/d - No HK 7 26-Sep-22 02-Oct-22 03-Dec-22 09-Dec-22 68
Works) Hols - No B/O periods (was
310.C.ES.P672 ESA - GSE Wash Facility - Building drainage and watermain works C1)
C11_6 d/w - 10h/d - With 21 08-Dec-22 03-Jan-23 10-Dec-22 05-Jan-23 2
HK Hols - No B/O periods
310.C.ES.P676 ESA - GSE Wash Facility - AS Cable ducts + drawpits (was C3)
C11_6 d/w - 10h/d - With 14 24-Dec-22 11-Jan-23 28-Dec-22 13-Jan-23 2
HK Hols - No B/O periods
310.C.ES.P680 ESA - GSE Wash Facility - EL cable ducting + drawpits (was
C11_6C3)
d/w - 10h/d - With 14 24-Dec-22 11-Jan-23 28-Dec-22 13-Jan-23 2
HK Hols - No B/O periods
Soft and Hard landscape & EVA Construction (was
C11_6C3)
d/w - 10h/d - With HK Hols
21- No B/O 0periods (was
29-Dec-22
C3) 26-Jan-23 31-Dec-22 28-Jan-23 2

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 200 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.ES.C200 ESA - GSE Wash Facility - Site Formation Works and Road Works for EVA C11_6 d/w - 10h/d - With 21 29-Dec-22 26-Jan-23 31-Dec-22 28-Jan-23 2
HK Hols - No B/O periods
310.C.ES.P684 ESA - GSE Wash Facility - Hard and soft landscape works (was
C11_6C3)
d/w - 10h/d - With 10 12-Jan-23 26-Jan-23 14-Jan-23 28-Jan-23 2
HK Hols - No B/O periods
WSA - GSE Battery Charging B (was C3) 256 2 19-May-22 24-Mar-23 04-Jun-22 18-Aug-23 118
Procurement C01_7 d/w - 10h/d - No HK Hols212
- No B/O periods
0 (was19-May-22
C1) 16-Dec-22 04-Jun-22 28-Dec-22 12
Major Materials ABWF C01_7 d/w - 10h/d - No HK Hols121
- No B/O periods
0 (was21-Jun-22
C1) 19-Oct-22 18-Jul-22 15-Nov-22 27
310.P.WS.M010 GSE Battery Charging B (Procurement ABWF)- louvres,doors,raised floor panels,cat C01_7 d/w - 10h/d - No HK 4 21-Jun-22 24-Jun-22 18-Jul-22 21-Jul-22 27
ladder&Others-Place Order Hols - No B/O periods (was
310.P.WS.M026 GSE Battery Charging B (Procurement ABWF) - Manufacturing of Materials C1)
C01_7 d/w - 10h/d - No HK 110 25-Jun-22 12-Oct-22 22-Jul-22 08-Nov-22 27
Hols - No B/O periods (was
310.P.WS.M034 GSE Battery Charging B (Procurement ABWF) - Delivery of Materials C1)
C01_7 d/w - 10h/d - No HK 7 13-Oct-22 19-Oct-22 09-Nov-22 15-Nov-22 27
Hols - No B/O periods (was
Major Materials MEP C1)
C01_7 d/w - 10h/d - No HK Hols212
- No B/O periods
0 (was19-May-22
C1) 16-Dec-22 04-Jun-22 28-Dec-22 12
310.P.WS.M018 GSE Battery Charging B (Procurement Electrical & MVAC Materials) - AC, LV C01_7 d/w - 10h/d - No HK 50 19-May-22 07-Jul-22 28-Jun-22 16-Aug-22 40
switchboard & Others-Place Order for Material Hols - No B/O periods (was
310.P.WS.M014 GSE Battery Charging B (Procurement FS and P&D Materials) - NOVEC 1230, FA & C1)
C01_7 d/w - 10h/d - No HK 180 23-May-22 18-Nov-22 04-Jun-22 30-Nov-22 12
Others-Place Order for Material Hols - No B/O periods (was
310.P.WS.M672 GSE Battery Charging B (Procurement FS and P&D Materials) - NOVEC 1230, C1)
C01_7 d/w - 10h/d - No HK 180 06-Jun-22 02-Dec-22 18-Jun-22 14-Dec-22 12
FA&Others-Manufacturing of Material Hols - No B/O periods (was
310.P.WS.M676 GSE Battery Charging B (Procurement Electrical & MVAC Materials) - AC, LV C1) d/w - 10h/d - No HK
C01_7 120 08-Jul-22 04-Nov-22 17-Aug-22 14-Dec-22 40
switchboard&Others-Manufacturing of Material Hols - No B/O periods (was
310.P.WS.M680 GSE Battery Charging B (Procurement MEP) - Delivery of Material C1)
C01_7 d/w - 10h/d - No HK 14 03-Dec-22 16-Dec-22 15-Dec-22 28-Dec-22 12
Hols - No B/O periods (was
Initial Works C1) 24 0 04-Jul-22 31-Jul-22 04-Jul-22 25-Aug-22 22
310.C.WS.M010 GSE Battery Charging B - Site access WA 3310/12 C01_7 d/w - 10h/d - No HK 0 04-Jul-22* 04-Jul-22 0
Hols - No B/O periods (was
310.C.WS.M018 GSE Battery Charging B - Site survey, Hoarding C1)
C11_6 d/w - 10h/d - With 4 04-Jul-22 07-Jul-22 28-Jul-22 01-Aug-22 21
HK Hols - No B/O periods
310.C.WS.M022 GSE Battery Charging B - Install monitoring point, UU detection/trial pit (was
C03_7C3)
d/w - 10h/d - With 10 08-Jul-22 17-Jul-22 02-Aug-22 11-Aug-22 25
HK Hols - No B/O periods
310.S.TC.N242 GSE Battery Charging B - Submit BA8 consent application (foundation works) C01_7 d/w - 10h/d - No HK 7 18-Jul-22 24-Jul-22 10-Aug-22 16-Aug-22 23
Hols - No B/O periods (was
310.C.WS.M038.B01 GSE Battery Charging B - Diversion of underground utilities (if any) C1)
C01_7 d/w - 10h/d - No HK 14 18-Jul-22 31-Jul-22 12-Aug-22 25-Aug-22 25
Hols - No B/O periods (was
Foundation Works C1) 41 0 25-Jul-22 10-Sep-22 17-Aug-22 05-Oct-22 19
310.C.WS.M029 GSE Battery Charging B - BA10 notice of commencement of works C01_7 d/w - 10h/d - No HK 7 25-Jul-22 31-Jul-22 17-Aug-22 23-Aug-22 23
Hols - No B/O periods (was
310.C.WS.M033 GSE Battery Charging B - SI works C1)
C11_6 d/w - 10h/d - With 2 01-Aug-22 02-Aug-22 24-Aug-22 25-Aug-22 20
HK Hols - No B/O periods
310.C.WS.M037 GSE Battery Charging B - Open Cut Excavation to FL(1,326m3) (was
C11_6C3)
d/w - 10h/d - With 3 03-Aug-22 05-Aug-22 26-Aug-22 29-Aug-22 20
HK Hols - No B/O periods
310.C.WS.M041.B01 GSE Battery Charging B - Plate load test (was
C11_6C3)
d/w - 10h/d - With 9 06-Aug-22 16-Aug-22 30-Aug-22 08-Sep-22 20
HK Hols - No B/O periods
310.C.WS.M045 GSE Battery Charging B - Construction of footing + backfill to GL (352m3) (was
C11_6C3)
d/w - 10h/d - With 10 17-Aug-22 27-Aug-22 09-Sep-22 21-Sep-22 20
HK Hols - No B/O periods
310.C.WS.M049 GSE Battery Charging B - Submit BA14 - as-built record (footing) (was
C01_7C3)
d/w - 10h/d - No HK 14 28-Aug-22 10-Sep-22 22-Sep-22 05-Oct-22 25
Hols - No B/O periods (was
RC Structural C1) 34 0 11-Sep-22 22-Oct-22 06-Oct-22 14-Nov-22 19
310.C.WS.M117 GSE Battery Charging B - Submit B10 notice of commencement of work (above ground C01_7 d/w - 10h/d - No HK 7 11-Sep-22 17-Sep-22 06-Oct-22 12-Oct-22 25
structure) Hols - No B/O periods (was
C1)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 201 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.WS.M133 GSE Battery Charging B - GF construction of base slab, column and walls (400m3) C11_6 d/w - 10h/d - With 14 19-Sep-22 06-Oct-22 13-Oct-22 28-Oct-22 19
HK Hols - No B/O periods
310.C.WS.M145 GSE Battery Charging B - Construction of roof slab, RC beam (334m3) (was
C11_6C3)
d/w - 10h/d - With 14 07-Oct-22 22-Oct-22 29-Oct-22 14-Nov-22 19
HK Hols - No B/O periods
ABWF (was
C11_6C3)
d/w - 10h/d - With HK Hols
62- No B/O 0periods (was
22-Oct-22
C3) 05-Jan-23 14-Nov-22 01-Feb-23 20
310.C.EX.W1496 GSE Battery Charging B - Structure completed and falsework removal C11_6 d/w - 10h/d - With 0 22-Oct-22 14-Nov-22 19
HK Hols - No B/O periods
310.C.EX.W1452 GSE Battery Charging B - Partition Wall & Door Subframe (was
C11_6C3)
d/w - 10h/d - With 38 24-Oct-22 06-Dec-22 16-Nov-22 30-Dec-22 20
HK Hols - No B/O periods
310.C.EX.W1456 GSE Battery Charging B - Plastering & Screeding (was
C11_6C3)
d/w - 10h/d - With 38 27-Oct-22 09-Dec-22 19-Nov-22 04-Jan-23 20
HK Hols - No B/O periods
310.C.EX.W1460 GSE Battery Charging B - Tiling & Stonework (was
C11_6C3)
d/w - 10h/d - With 38 31-Oct-22 13-Dec-22 23-Nov-22 07-Jan-23 20
HK Hols - No B/O periods
310.C.EX.W1464 GSE Battery Charging B - Suspended Ceiling Framework (was
C11_6C3)
d/w - 10h/d - With 38 03-Nov-22 16-Dec-22 26-Nov-22 11-Jan-23 20
HK Hols - No B/O periods
310.C.EX.W1468 GSE Battery Charging B - Sanitary Ware & Fixtures (was
C11_6C3)
d/w - 10h/d - With 38 07-Nov-22 20-Dec-22 30-Nov-22 14-Jan-23 20
HK Hols - No B/O periods
310.C.EX.W1472 GSE Battery Charging B - Fire Shutter, Door Sets & Ironmongery (was
C11_6C3)
d/w - 10h/d - With 38 10-Nov-22 23-Dec-22 03-Dec-22 18-Jan-23 20
HK Hols - No B/O periods
310.C.EX.W1476 GSE Battery Charging B - Glazing (was
C11_6C3)
d/w - 10h/d - With 38 14-Nov-22 28-Dec-22 07-Dec-22 21-Jan-23 20
HK Hols - No B/O periods
310.C.EX.W1480 GSE Battery Charging B - Ceiling Panels & Finishes (was
C11_6C3)
d/w - 10h/d - With 38 17-Nov-22 31-Dec-22 10-Dec-22 28-Jan-23 20
HK Hols - No B/O periods
310.C.EX.W1484 GSE Battery Charging B - Painting, Graphics & Signage (was
C11_6C3)
d/w - 10h/d - With 38 21-Nov-22 05-Jan-23 14-Dec-22 01-Feb-23 20
HK Hols - No B/O periods
MEP Installation Works (was
C11_6C3)
d/w - 10h/d - With HK Hols
109- No B/O 2periods (was
10-Nov-22
C3) 22-Mar-23 06-Dec-22 21-Jul-23 96
Transformers (CLP) C11_6 d/w - 10h/d - With HK Hols
79- No B/O 2periods (was
14-Nov-22
C3) 18-Feb-23 06-Dec-22 01-Mar-23 9
310.C.EX.W1488 GSE Battery Charging B - Complete Transformer Room Structure C11_6 d/w - 10h/d - With 0 14-Nov-22 06-Dec-22 19
HK Hols - No B/O periods
310.C.EX.W1578.B01 GSE Battery Charging B - Builder Works in Transformer Room (was
C11_6C3)
d/w - 10h/d - With 12 14-Nov-22 26-Nov-22 06-Dec-22 19-Dec-22 19
HK Hols - No B/O periods
310.C.EX.W1412 GSE Battery Charging B - MEP Works in Transformer Room (was
C11_6C3)
d/w - 10h/d - With 12 03-Dec-22 16-Dec-22 14-Dec-22 28-Dec-22 9
HK Hols - No B/O periods
310.C.EX.W1416 GSE Battery Charging B - Inspection & Handover Transformer Room to CLP (was
C11_6C3)
d/w - 10h/d - With 6 17-Dec-22 23-Dec-22 29-Dec-22 05-Jan-23 9
HK Hols - No B/O periods
310.C.EX.W1420 GSE Battery Charging B - Transformer Installation by CLP (was
C11_6C3)
d/w - 10h/d - With 42 24-Dec-22 16-Feb-23 06-Jan-23 27-Feb-23 9
HK Hols - No B/O periods
310.C.EX.W1492 GSE Battery Charging B - Cable Laying by CLP (was
C11_6C3)
d/w - 10h/d - With 24 2 06-Jan-23 06-Feb-23 02-Feb-23 01-Mar-23 20
HK Hols - No B/O periods
310.C.EX.W1424 GSE Battery Charging B - Energization of Transformers (was
C11_6C3)
d/w - 10h/d - With 0 18-Feb-23 01-Mar-23 9
HK Hols - No B/O periods
Plumbing & Drainage Installation (was
C11_6C3)
d/w - 10h/d - With HK Hols
96- No B/O 0periods (was
11-Nov-22
C3) 08-Mar-23 15-Mar-23 13-Jul-23 101
310.C.EX.W1428 GSE Battery Charging B - Plumbing & Drainage 1st Fix & Installation C11_6 d/w - 10h/d - With 45 11-Nov-22 04-Jan-23 15-Mar-23 11-May-23 101
HK Hols - No B/O periods
310.C.EX.W1432 GSE Battery Charging B - Plumbing & Drainage 2nd Fix & Installation (was
C11_6C3)
d/w - 10h/d - With 45 09-Dec-22 04-Feb-23 17-Apr-23 09-Jun-23 101
HK Hols - No B/O periods
310.C.EX.W1436 GSE Battery Charging B - Water Pump Installation (was
C11_6C3)
d/w - 10h/d - With 35 16-Dec-22 31-Jan-23 28-Apr-23 09-Jun-23 105
HK Hols - No B/O periods
310.C.EX.W1448 GSE Battery Charging B - Plumbing & Drainage Final Fix & Adjustment (was
C11_6C3)
d/w - 10h/d - With 7 01-Mar-23 08-Mar-23 06-Jul-23 13-Jul-23 101
HK Hols - No B/O periods
Electrical Installation (was
C11_6C3)
d/w - 10h/d - With HK Hols
100- No B/O 0periods (was
21-Nov-22
C3) 22-Mar-23 14-Dec-22 13-Jul-23 89

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 202 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.EX.W1336 GSE Battery Charging B - Electrical 1st Fix & Installation C11_6 d/w - 10h/d - With 42 21-Nov-22 10-Jan-23 14-Dec-22 06-Feb-23 20
HK Hols - No B/O periods
310.C.EX.W1344 GSE Battery Charging B - Switchgear Installation (was
C11_6C3)
d/w - 10h/d - With 30 19-Dec-22 27-Jan-23 13-Jan-23 20-Feb-23 20
HK Hols - No B/O periods
310.C.EX.W1348 GSE Battery Charging B - Emergency Genset Installation (was
C11_6C3)
d/w - 10h/d - With 30 19-Dec-22 27-Jan-23 05-May-23 09-Jun-23 108
HK Hols - No B/O periods
310.C.EX.W1340 GSE Battery Charging B - Electrical 2nd Fix & Installation (was
C11_6C3)
d/w - 10h/d - With 42 19-Dec-22 10-Feb-23 08-May-23 27-Jun-23 110
HK Hols - No B/O periods
310.C.EX.W1352 GSE Battery Charging B - Power On to All Floors (was
C11_6C3)
d/w - 10h/d - With 0 18-Feb-23 09-Jun-23 89
HK Hols - No B/O periods
310.C.EX.W1364 GSE Battery Charging B - Electrical Final Fix & Adjustment (was
C11_6C3)
d/w - 10h/d - With 7 15-Mar-23 22-Mar-23 06-Jul-23 13-Jul-23 89
HK Hols - No B/O periods
Fire Services Installation (was
C11_6C3)
d/w - 10h/d - With HK Hols
103- No B/O 0periods (was
10-Nov-22
C3) 15-Mar-23 15-Mar-23 21-Jul-23 102
310.C.EX.W1368 GSE Battery Charging B - Fire Services 1st Fix & Installation C11_6 d/w - 10h/d - With 42 10-Nov-22 29-Dec-22 15-Mar-23 08-May-23 102
HK Hols - No B/O periods
310.C.EX.W1376 GSE Battery Charging B - FS Pump Installation (was
C11_6C3)
d/w - 10h/d - With 30 19-Nov-22 23-Dec-22 13-May-23 17-Jun-23 140
HK Hols - No B/O periods
310.C.EX.W1372 GSE Battery Charging B - Fire Services 2nd Fix & Installation (was
C11_6C3)
d/w - 10h/d - With 42 08-Dec-22 31-Jan-23 17-Apr-23 06-Jun-23 102
HK Hols - No B/O periods
310.C.EX.W1388 GSE Battery Charging B - Fire Services Final Fix & Adjustment (was
C11_6C3)
d/w - 10h/d - With 7 08-Mar-23 15-Mar-23 14-Jul-23 21-Jul-23 102
HK Hols - No B/O periods
MVAC Installation (was
C11_6C3)
d/w - 10h/d - With HK Hols
79- No B/O 0periods (was
21-Nov-22
C3) 25-Feb-23 17-Apr-23 21-Jul-23 117
310.C.EX.W1392 GSE Battery Charging B - MVAC 1st Fix & Installation C11_6 d/w - 10h/d - With 42 21-Nov-22 10-Jan-23 17-Apr-23 06-Jun-23 117
HK Hols - No B/O periods
310.C.EX.W1396 GSE Battery Charging B - MVAC 2nd Fix & Installation (was
C11_6C3)
d/w - 10h/d - With 42 19-Dec-22 10-Feb-23 16-May-23 06-Jul-23 117
HK Hols - No B/O periods
310.C.EX.W1408 GSE Battery Charging B - MVAC Final Fix & Adjustment (was
C11_6C3)
d/w - 10h/d - With 7 18-Feb-23 25-Feb-23 14-Jul-23 21-Jul-23 117
HK Hols - No B/O periods
External Works (was C3) 126 0 23-Oct-22 24-Mar-23 23-Nov-22 18-Aug-23 118
External Building Finishes 62 0 23-Oct-22 05-Jan-23 23-Nov-22 01-Feb-23 20
310.C.ES.P613.B01 GSE Battery Charging B - Roof Waterproofing & Roof Finishes C01_7 d/w - 10h/d - No HK 30 23-Oct-22 21-Nov-22 23-Nov-22 22-Dec-22 31
Hols - No B/O periods (was
310.C.ES.P612 GSE Battery Charging B - External building finishes C1)
C11_6 d/w - 10h/d - With 30 30-Nov-22 05-Jan-23 23-Dec-22 01-Feb-23 20
HK Hols - No B/O periods
Drainage and UU (was
C11_6C3)
d/w - 10h/d - With HK Hols
42- No B/O 0periods (was
10-Dec-22
C3) 02-Feb-23 05-Jan-23 25-Jul-23 140
310.C.ES.P592 GSE Battery Charging B - Building drainage and watermain works C11_6 d/w - 10h/d - With 21 10-Dec-22 05-Jan-23 05-Jan-23 01-Feb-23 20
HK Hols - No B/O periods
310.C.ES.P616 GSE Battery Charging B - CLP Cable ducts + drawpits (was
C11_6C3)
d/w - 10h/d - With 16 16-Dec-22 05-Jan-23 11-Jan-23 01-Feb-23 20
HK Hols - No B/O periods
310.C.ES.P600 GSE Battery Charging B - EL cable ducting + drawpits (was
C11_6C3)
d/w - 10h/d - With 16 06-Jan-23 27-Jan-23 11-Feb-23 01-Mar-23 28
HK Hols - No B/O periods
310.C.ES.P596 GSE Battery Charging B - AS Cable ducts + drawpits (was
C11_6C3)
d/w - 10h/d - With 21 06-Jan-23 02-Feb-23 30-Jun-23 25-Jul-23 140
HK Hols - No B/O periods
Soft and Hard landscape & EVA Construction (was
C11_6C3)
d/w - 10h/d - With HK Hols
48- No B/O 0periods (was
28-Jan-23
C3) 24-Mar-23 23-Jun-23 18-Aug-23 118
310.C.WS.C110 GSE Battery Charging B - Site Formation Works and Road Works for EVA C11_6 d/w - 10h/d - With 48 28-Jan-23 24-Mar-23 23-Jun-23 18-Aug-23 118
HK Hols - No B/O periods
310.C.ES.P604 GSE Battery Charging B - Hard and soft landscape works (was
C11_6C3)
d/w - 10h/d - With 21 03-Feb-23 27-Feb-23 26-Jul-23 18-Aug-23 140
HK Hols - No B/O periods
WSA - Maintenance Facilities Forecourt & Coach Staging A and Bus Stop (MFF and Bus Stop) (was C3) 410 0 04-Jul-22 15-Nov-23 09-May-23 16-Apr-24 122
Procurement C01_7 d/w - 10h/d - No HK Hols176
- No B/O periods
0 (was28-Dec-22
C1) 21-Jun-23 07-Jun-23 29-Nov-23 161
Major Materials C01_7 d/w - 10h/d - No HK Hols176
- No B/O periods
0 (was28-Dec-22
C1) 21-Jun-23 07-Jun-23 29-Nov-23 161

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 203 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.P.WS.M540 WSA - MFF and Bus Stop (Procurement) - 4500N Concrete Pipes, grating for U C01_7 d/w - 10h/d - No HK 28 28-Dec-22 24-Jan-23 07-Jun-23 04-Jul-23 161
channel&Catch pits & Others-Place Order Hols - No B/O periods (was
310.P.WS.M544 WSA - MFF and Bus Stop (Procurement) - pillar box, light post & Others-Place Order for C1)
C01_7 d/w - 10h/d - No HK 28 28-Dec-22 24-Jan-23 07-Jun-23 04-Jul-23 161
Material Hols - No B/O periods (was
310.P.WS.M548 WSA - MFF and Bus Stop (Procurement) - 4500N Concrete Pipes, grating for U C1)
C01_7 d/w - 10h/d - No HK 120 25-Jan-23 24-May-23 05-Jul-23 01-Nov-23 161
channel&Catch pits & Others-Manufacturing Hols - No B/O periods (was
310.P.WS.M552 WSA - MFF and Bus Stop (Procurement) - pillar box, light post & Others-Manufacturing of C1)
C01_7 d/w - 10h/d - No HK 120 25-Jan-23 24-May-23 05-Jul-23 01-Nov-23 161
Material Hols - No B/O periods (was
310.P.WS.M556 WSA - MFF and Bus Stop (Procurement) - Delivery of Material C1)
C01_7 d/w - 10h/d - No HK 28 25-May-23 21-Jun-23 02-Nov-23 29-Nov-23 161
Hols - No B/O periods (was
Initial Works C1)
C11_6 d/w - 10h/d - With HK Hols
166- No B/O 0periods (was
04-Jul-22
C3) 18-Jan-23 30-Jun-23 07-Jul-23 135
310.C.WS.M009 WSA - MFF and Bus Stop - Site access WA3310/12 C11_6 d/w - 10h/d - With 0 04-Jul-22 30-Jun-23 295
HK Hols - No B/O periods
310.C.WS.M011 WSA - MFF and Bus Stop - Initial Works (hoarding, GI works, instrumentation, trial pits, (was
C11_6C3)
d/w - 10h/d - With 6 12-Jan-23 18-Jan-23 30-Jun-23 07-Jul-23 135
diversion if any) HK Hols - No B/O periods
Bus Stop Structure (was
C11_6C3)
d/w - 10h/d - With HK Hols
68- No B/O 0periods (was
26-Jan-23
C3) 19-Apr-23 08-Jul-23 25-Sep-23 132
310.C.WS.M034 WSA - MFF and Bus Stop (Excavation) - open cut excavation to FL, plate load test (2 nos) C11_6 d/w - 10h/d - With 12 26-Jan-23 08-Feb-23 08-Jul-23 21-Jul-23 132
HK Hols - No B/O periods
310.C.WS.M042 WSA - MFF and Bus Stop (Structure) - Footings (Pillar Box/ Road lighting/ advertising (was
C11_6C3)
d/w - 10h/d - With 35 09-Feb-23 21-Mar-23 22-Jul-23 31-Aug-23 132
panel) + Submit BA14 HK Hols - No B/O periods
310.C.WS.M046 WSA - MFF and Bus Stop Structure) - Columns (concrete: 49m3),roof slab, drainage (was
C11_6C3)
d/w - 10h/d - With 21 22-Mar-23 19-Apr-23 01-Sep-23 25-Sep-23 132
downpipe and advert panels HK Hols - No B/O periods
Drainage and Petrol Interceptor (was C3) 114 0 12-Jan-23 03-Jun-23 09-May-23 25-Sep-23 95
310.C.WS.M026 WSA - MFF and Bus Stop (Drainage) - Submit BA8 consent application C01_7 d/w - 10h/d - No HK 7 12-Jan-23 18-Jan-23 09-May-23 15-May-23 117
Hols - No B/O periods (was
310.C.WS.M030 WSA - MFF and Bus Stop (Drainage) - Submit BA10 - notice of commencement of work C1)
C01_7 d/w - 10h/d - No HK 7 19-Jan-23 25-Jan-23 16-May-23 22-May-23 117
Hols - No B/O periods (was
310.C.WS.M050 WSA - MFF and Bus Stop (Drainage) - Trench excavation to invert level for drainage and C1)
C11_6 d/w - 10h/d - With
30 26-Jan-23 01-Mar-23 23-May-23 28-Jun-23 95
manholes HK Hols - No B/O periods
310.C.WS.M054 WSA - MFF and Bus Stop (Drainage) - Drainage Works (DN450, DN375, DN300, DN225, (was
C11_6C3)
d/w - 10h/d - With 75 02-Mar-23 03-Jun-23 29-Jun-23 25-Sep-23 95
DN150), MH + mass concrete HK Hols - No B/O periods
ABWF (was
C11_6C3)
d/w - 10h/d - With HK Hols
92- No B/O 0periods (was
03-Jun-23
C3) 21-Sep-23 25-Sep-23 14-Mar-24 142
310.C.EX.W2228 WSA - MFF and Bus Stop - Structure completed and falsework removal C11_6 d/w - 10h/d - With 0 03-Jun-23 25-Sep-23 95
HK Hols - No B/O periods
310.C.EX.W2204 WSA - MFF and Bus Stop - Wall finishes (was
C11_6C3)
d/w - 10h/d - With 48 05-Jun-23 01-Aug-23 23-Nov-23 20-Jan-24 142
HK Hols - No B/O periods
310.C.EX.W2208 WSA - MFF and Bus Stop - Floor finishes (was
C11_6C3)
d/w - 10h/d - With 48 16-Jun-23 12-Aug-23 05-Dec-23 01-Feb-24 142
HK Hols - No B/O periods
310.C.EX.W2212 WSA - MFF and Bus Stop - external finishes (was
C11_6C3)
d/w - 10h/d - With 48 29-Jun-23 24-Aug-23 16-Dec-23 15-Feb-24 142
HK Hols - No B/O periods
310.C.EX.W2224 WSA - MFF and Bus Stop - Painting, Graphics & Signage (was
C11_6C3)
d/w - 10h/d - With 48 28-Jul-23 21-Sep-23 17-Jan-24 14-Mar-24 142
HK Hols - No B/O periods
MEP Installation Works (was
C11_6C3)
d/w - 10h/d - With HK Hols
112- No B/O 0periods (was
05-Jul-23
C3) 15-Nov-23 27-Oct-23 03-Apr-24 112
Drainage Installation C11_6 d/w - 10h/d - With HK Hols
100- No B/O 0periods (was
05-Jul-23
C3) 01-Nov-23 30-Nov-23 03-Apr-24 124
310.C.EX.W2180 WSA - MFF and Bus Stop - Drainage 1st Fix & Installation C11_6 d/w - 10h/d - With 48 05-Jul-23 29-Aug-23 30-Nov-23 27-Jan-24 124
HK Hols - No B/O periods
310.C.EX.W2184 WSA - MFF and Bus Stop - Drainage 2nd Fix & Installation (was
C11_6C3)
d/w - 10h/d - With 48 02-Aug-23 26-Sep-23 30-Dec-23 27-Feb-24 124
HK Hols - No B/O periods
310.C.EX.W2200 WSA - MFF and Bus Stop - Drainage Final Fix & Adjustment (was
C11_6C3)
d/w - 10h/d - With 6 26-Oct-23 01-Nov-23 25-Mar-24 03-Apr-24 124
HK Hols - No B/O periods
Electrical Installation (was
C11_6C3)
d/w - 10h/d - With HK Hols
106- No B/O 0periods (was
05-Jul-23
C3) 08-Nov-23 27-Oct-23 04-Mar-24 95

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 204 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.EX.W2132 WSA - MFF and Bus Stop - Electrical 1st Fix & Installation C11_6 d/w - 10h/d - With 48 05-Jul-23 29-Aug-23 27-Oct-23 21-Dec-23 95
HK Hols - No B/O periods
310.C.EX.W2136 WSA - MFF and Bus Stop - Electrical 2nd Fix & Installation (was
C11_6C3)
d/w - 10h/d - With 48 02-Aug-23 26-Sep-23 24-Nov-23 22-Jan-24 95
HK Hols - No B/O periods
310.C.EX.W2140 WSA - MFF and Bus Stop - Power On (was
C11_6C3)
d/w - 10h/d - With 0 26-Sep-23 22-Jan-24 95
HK Hols - No B/O periods
310.C.EX.W2152 WSA - MFF and Bus Stop - Electrical Final Fix & Adjustment (was
C11_6C3)
d/w - 10h/d - With 6 02-Nov-23 08-Nov-23 27-Feb-24 04-Mar-24 95
HK Hols - No B/O periods
Fire Services Installation (was
C11_6C3)
d/w - 10h/d - With HK Hols
112- No B/O 0periods (was
05-Jul-23
C3) 15-Nov-23 27-Oct-23 11-Mar-24 95
310.C.EX.W2156 WSA - MFF and Bus Stop - Fire Services 1st Fix & Installation C11_6 d/w - 10h/d - With 48 05-Jul-23 29-Aug-23 27-Oct-23 21-Dec-23 95
HK Hols - No B/O periods
310.C.EX.W2160 WSA - MFF and Bus Stop - Fire Services 2nd Fix & Installation (was
C11_6C3)
d/w - 10h/d - With 48 02-Aug-23 26-Sep-23 24-Nov-23 22-Jan-24 95
HK Hols - No B/O periods
310.C.EX.W2176 WSA - MFF and Bus Stop - Fire Services Preliminary Final Fix & Adjustment (was
C11_6C3)
d/w - 10h/d - With 6 09-Nov-23 15-Nov-23 05-Mar-24 11-Mar-24 95
HK Hols - No B/O periods
External Works (was
C11_6C3)
d/w - 10h/d - With HK Hols
116- No B/O 0periods (was
05-Jun-23
C3) 21-Oct-23 22-Dec-23 16-Apr-24 142
Drainage and UU C11_6 d/w - 10h/d - With HK Hols
42- No B/O 0periods (was
05-Jun-23
C3) 25-Jul-23 22-Dec-23 14-Mar-24 192
310.C.ES.P724 WSA - MFF and Bus Stop - Drainage and watermain works C11_6 d/w - 10h/d - With 24 05-Jun-23 04-Jul-23 22-Dec-23 22-Jan-24 167
HK Hols - No B/O periods
310.C.ES.P728 WSA - MFF and Bus Stop - Airport System Cable ducts + drawpits (was
C11_6C3)
d/w - 10h/d - With 18 05-Jul-23 25-Jul-23 23-Jan-24 14-Feb-24 167
HK Hols - No B/O periods
310.C.ES.P732 WSA - MFF and Bus Stop - EL cable ducting + drawpits (was
C11_6C3)
d/w - 10h/d - With 18 05-Jul-23 25-Jul-23 23-Feb-24 14-Mar-24 192
HK Hols - No B/O periods
Soft and Hard landscape & EVA Construction (was
C11_6C3)
d/w - 10h/d - With HK Hols
24- No B/O 0periods (was
22-Sep-23
C3) 21-Oct-23 15-Mar-24 16-Apr-24 142
310.C.ES.P736 WSA - MFF and Bus Stop - Hard and soft landscape works C11_6 d/w - 10h/d - With 21 22-Sep-23 18-Oct-23 19-Mar-24 16-Apr-24 145
HK Hols - No B/O periods
310.C.ES.C204 WSA - MFF and Bus Stop - Road Works for EVA (was
C11_6C3)
d/w - 10h/d - With 24 22-Sep-23 21-Oct-23 15-Mar-24 16-Apr-24 142
HK Hols - No B/O periods
WSA - GSE Storage Area (was C3) 386 0 04-Jul-22 17-Oct-23 04-Jul-22 18-Apr-24 148
Procurement C01_7 d/w - 10h/d - No HK Hols148
- No B/O periods
0 (was28-Dec-22
C1) 24-May-23 27-Jun-23 21-Nov-23 181
Major Materials C01_7 d/w - 10h/d - No HK Hols148
- No B/O periods
0 (was28-Dec-22
C1) 24-May-23 27-Jun-23 21-Nov-23 181
310.P.WS.M636 WSA - GSE Storage Area (Procurement) - Concrete Pipes, grating for U channel&Catch C01_7 d/w - 10h/d - No HK 14 28-Dec-22 10-Jan-23 27-Jun-23 10-Jul-23 181
pits&Others-Place Order for Material Hols - No B/O periods (was
310.P.WS.M640 WSA - GSE Storage Area (Procurement) - pillar box, light post&Others-Place Order for C1)
C01_7 d/w - 10h/d - No HK 14 28-Dec-22 10-Jan-23 27-Jun-23 10-Jul-23 181
Material Hols - No B/O periods (was
310.P.WS.M644 WSA - GSE Storage Area (Procurement) - Concrete Pipes, grating for U channel&Catch C1)
C01_7 d/w - 10h/d - No HK 120 11-Jan-23 10-May-23 11-Jul-23 07-Nov-23 181
pits&Others-Manufacturing of Material Hols - No B/O periods (was
310.P.WS.M648 WSA - GSE Storage Area (Procurement) - pillar box, light post&Others-Manufacturing of C1)
C01_7 d/w - 10h/d - No HK 120 11-Jan-23 10-May-23 11-Jul-23 07-Nov-23 181
Material Hols - No B/O periods (was
310.P.WS.M652 WSA - GSE Storage Area (Procurement) - Delivery of Material C1)
C01_7 d/w - 10h/d - No HK 14 11-May-23 24-May-23 08-Nov-23 21-Nov-23 181
Hols - No B/O periods (was
Initial Works C1) 187 0 04-Jul-22 15-Feb-23 04-Jul-22 16-Aug-23 148
310.C.WS.N101 WSA - GSE Storage Area - Site access WA3310/12 C11_6 d/w - 10h/d - With 0 04-Jul-22* 04-Jul-22 0
HK Hols - No B/O periods
310.C.WS.N117 WSA - GSE Storage Area - Obtained BA8 consent (was
C01_7C3)
d/w - 10h/d - No HK 0 17-Jul-22 09-Aug-23 388
Hols - No B/O periods (was
310.C.WS.N121 WSA - GSE Storage Area - Submit BA10 - notice of commencement of work C1)
C01_7 d/w - 10h/d - No HK 0 17-Jul-22 09-Aug-23 388
Hols - No B/O periods (was
310.C.WS.N109 WSA - GSE Storage Area - Temporary drainage C1)
C11_6 d/w - 10h/d - With 6 02-Feb-23 08-Feb-23 03-Aug-23 09-Aug-23 148
HK Hols - No B/O periods
(was C3)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 205 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.WS.N105 WSA - GSE Storage Area - Hoarding/trial pits for UU C11_6 d/w - 10h/d - With 6 02-Feb-23 08-Feb-23 03-Aug-23 09-Aug-23 148
HK Hols - No B/O periods
310.C.WS.N113 WSA - GSE Storage Area - Carry out GI works/install instrumentation,diversion of (was
C11_6C3)
d/w - 10h/d - With 6 02-Feb-23 08-Feb-23 03-Aug-23 09-Aug-23 148
underground utilities (if any) HK Hols - No B/O periods
310.C.WS.N125 WSA - GSE Storage Area - Site layout and formation works (was
C11_6C3)
d/w - 10h/d - With 6 09-Feb-23 15-Feb-23 10-Aug-23 16-Aug-23 148
HK Hols - No B/O periods
Drainage and UU Works (was
C11_6C3)
d/w - 10h/d - With HK Hols
44- No B/O 0periods (was
16-Feb-23
C3) 12-Apr-23 17-Aug-23 18-Apr-24 303
310.C.WS.N133 WSA - GSE Storage Area (Drainage) - Trench excavation for U-channel, catch pit C11_6 d/w - 10h/d - With 30 16-Feb-23 22-Mar-23 17-Aug-23 20-Sep-23 148
HK Hols - No B/O periods
310.C.WS.N145 WSA - GSE Storage Area (Drainage) - excavate and pipe laying stormwater DN150, (was
C11_6C3)
d/w - 10h/d - With 30 16-Feb-23 22-Mar-23 17-Aug-23 20-Sep-23 148
DN225, DN300 + manholes (4nos) HK Hols - No B/O periods
310.C.WS.N149 WSA - GSE Storage Area (Drainage) - Submit BA14 and BD acknowledgement (was
C11_6C3)
d/w - 10h/d - With 14 23-Mar-23 12-Apr-23 02-Apr-24 18-Apr-24 303
HK Hols - No B/O periods
Electrical Services and Light Post (was
C11_6C3)
d/w - 10h/d - With HK Hols
125- No B/O 0periods (was
23-Mar-23
C3) 24-Aug-23 21-Sep-23 22-Feb-24 148
310.C.WS.N161.B02 WSA - GSE Storage Area (Pillar Box) - Plate load test , construct Pillar Box and Road C11_6 d/w - 10h/d - With 50 23-Mar-23 25-May-23 21-Sep-23 21-Nov-23 148
Light Footings + submit BA14 HK Hols - No B/O periods
310.C.WS.N137 WSA - GSE Storage Area (Pillar Box) - Install Pillar Box and Electrical Services (was
C11_6C3)
d/w - 10h/d - With 30 27-May-23 03-Jul-23 22-Nov-23 28-Dec-23 148
HK Hols - No B/O periods
310.C.WS.N141 WSA - GSE Storage Area (Road Lights) - Cable drawpits &Install Road Light (10 nos) + (was
C11_6C3)
d/w - 10h/d - With 45 04-Jul-23 24-Aug-23 29-Dec-23 22-Feb-24 148
install electrical services HK Hols - No B/O periods
Pavement and Landscaping (was
C11_6C3)
d/w - 10h/d - With HK Hols
44- No B/O 0periods (was
25-Aug-23
C3) 17-Oct-23 23-Feb-24 18-Apr-24 148
310.C.WS.N153 WSA - GSE Storage Area (Pavement) - backfill, paving, landscaping C11_6 d/w - 10h/d - With 30 25-Aug-23 28-Sep-23 23-Feb-24 28-Mar-24 148
HK Hols - No B/O periods
310.C.WS.N157 WSA - GSE Storage Area (Pavement) - Storage Area marking, signages (was
C11_6C3)
d/w - 10h/d - With 14 29-Sep-23 17-Oct-23 02-Apr-24 18-Apr-24 148
HK Hols - No B/O periods
WSA - Gatehouse B (was C3) 418 2 03-Jun-22 27-Oct-23 04-Jul-22 18-Dec-23 44
Procurement C01_7 d/w - 10h/d - No HK Hols281
- No B/O periods
0 (was03-Jun-22
C1) 10-Mar-23 09-Jul-22 30-May-23 81
Major Materials ABWF C01_7 d/w - 10h/d - No HK Hols232
- No B/O periods
0 (was03-Jun-22
C1) 20-Jan-23 19-Oct-22 30-May-23 130
310.P.ES.P70.B02 WSA - Gatehouse B (Procurement ABWF) - Visual Prototypes drawing submission, C01_7 d/w - 10h/d - No HK 90 03-Jun-22 31-Aug-22 19-Oct-22 16-Jan-23 138
erection, testing and approval Hols - No B/O periods (was
310.P.ES.P48 WSA - Gatehouse B (Procurement ABWF)- louvres,doors,raised floor C1)
C01_7 d/w - 10h/d - No HK 14 09-Sep-22 22-Sep-22 17-Jan-23 30-Jan-23 130
panels&Others-Place Order Hols - No B/O periods (was
310.P.ES.P66 WSA - Gatehouse B (Procurement ABWF) - Manufacturing of Materials C1)
C01_7 d/w - 10h/d - No HK 120 23-Sep-22 20-Jan-23 31-Jan-23 30-May-23 130
Hols - No B/O periods (was
310.P.ES.P74 WSA - Gatehouse B (Procurement ABWF) - Delivery of Materials C1)
C01_7 d/w - 10h/d - No HK 14 07-Jan-23 20-Jan-23 17-May-23 30-May-23 130
Hols - No B/O periods (was
Major Materials MEP C1)
C01_7 d/w - 10h/d - No HK Hols262
- No B/O periods
0 (was22-Jun-22
C1) 10-Mar-23 09-Jul-22 27-Mar-23 17
310.P.ES.P52 WSA - Gatehouse B (Procurement FS and P&D Materials) - sprinkler, FA&Others - Place C01_7 d/w - 10h/d - No HK 200 22-Jun-22 07-Jan-23 09-Jul-22 24-Jan-23 17
Order for Material Hols - No B/O periods (was
310.P.ES.P56 WSA - Gatehouse B (Procurement Electrical&MVAC)-AC/ vent fan,LV C1)
C01_7 d/w - 10h/d - No HK 60 27-Jun-22 25-Aug-22 01-Sep-22 30-Oct-22 66
switchboard,genset&Others-Place Order Hols - No B/O periods (was
310.P.ES.P114 WSA - Gatehouse B (Procurement FS and P&D Materials) - sprinkler, C1)
C01_7 d/w - 10h/d - No HK 220 06-Jul-22 10-Feb-23 23-Jul-22 27-Feb-23 17
FA&Others-Manufacturing Hols - No B/O periods (was
310.P.ES.P118 WSA - Gatehouse B (Procurement Electrical&MVAC)-AC/ vent fan,LV C1)
C01_7 d/w - 10h/d - No HK 120 26-Aug-22 23-Dec-22 31-Oct-22 27-Feb-23 66
switchboard,genset&Other-Manufacturing Hols - No B/O periods (was
310.P.ES.P122 WSA - Gatehouse B (Procurement MEP) - Delivery of Materials C1) d/w - 10h/d - No HK
C01_7 28 11-Feb-23 10-Mar-23 28-Feb-23 27-Mar-23 17
Hols - No B/O periods (was
Initial Work and Site Preparation C1) 36 0 04-Jul-22 13-Aug-22 04-Jul-22 02-Sep-22 17
310.C.WS.S400 WSA - Gatehouse B - Site access WA3310/12 C01_7 d/w - 10h/d - No HK 0 04-Jul-22* 04-Jul-22 0
Hols - No B/O periods (was
C1)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 206 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.WS.S104 WSA - Gatehouse B - Hoarding C11_6 d/w - 10h/d - With 5 04-Jul-22 08-Jul-22 23-Jul-22 28-Jul-22 17
HK Hols - No B/O periods
310.C.WS.S108 WSA - Gatehouse B - Carry out site survey (was
C11_6C3)
d/w - 10h/d - With 1 08-Jul-22 08-Jul-22 28-Jul-22 28-Jul-22 17
HK Hols - No B/O periods
310.C.WS.S112 WSA - Gatehouse B - Install monitoring point (was
C11_6C3)
d/w - 10h/d - With 1 09-Jul-22 09-Jul-22 29-Jul-22 29-Jul-22 17
HK Hols - No B/O periods
310.C.WS.S116 WSA - Gatehouse B - UU detection and trial pit (was
C11_6C3)
d/w - 10h/d - With 6 11-Jul-22 16-Jul-22 30-Jul-22 05-Aug-22 17
HK Hols - No B/O periods
310.C.WS.S160.B01 WSA - Gatehouse B - Diversion of underground utilities (if any) (was
C11_6C3)
d/w - 10h/d - With 24 18-Jul-22 13-Aug-22 06-Aug-22 02-Sep-22 17
HK Hols - No B/O periods
Structural Works (was C3) 172 0 18-Jul-22 11-Feb-23 19-Jul-22 13-Feb-23 1
310.C.WS.S118 WSA - Gatehouse B - Obtain BA8 consent C01_7 d/w - 10h/d - No HK 28 18-Jul-22 14-Aug-22 19-Jul-22 15-Aug-22 1
Hols - No B/O periods (was
310.C.WS.S120 WSA - Gatehouse B - BA10 notice of commencement of works C1)
C01_7 d/w - 10h/d - No HK 7 15-Aug-22 21-Aug-22 16-Aug-22 22-Aug-22 1
Hols - No B/O periods (was
310.C.WS.S124 WSA - Gatehouse B - SI works and submit report to PM C1)
C11_6 d/w - 10h/d - With 10 22-Aug-22 01-Sep-22 23-Aug-22 02-Sep-22 1
HK Hols - No B/O periods
Gatehouse B (was
C11_6C3)
d/w - 10h/d - With HK Hols
132- No B/O 0periods (was
02-Sep-22
C3) 11-Feb-23 03-Sep-22 13-Feb-23 1
310.C.WS.S128 WSA - Gatehouse B - Open Cut Excavation to FL (assumed ex. GL + 6.75) (7,474m3) C11_6 d/w - 10h/d - With 5 02-Sep-22 07-Sep-22 03-Sep-22 08-Sep-22 1
HK Hols - No B/O periods
310.C.WS.S132 WSA - Gatehouse B - Plate load test (was
C11_6C3)
d/w - 10h/d - With 10 08-Sep-22 20-Sep-22 09-Sep-22 21-Sep-22 1
HK Hols - No B/O periods
310.C.WS.S136 WSA - Gatehouse B - Construction of footing; Vol. = 2,672 m3 (was
C11_6C3)
d/w - 10h/d - With 20 21-Sep-22 15-Oct-22 22-Sep-22 17-Oct-22 1
HK Hols - No B/O periods
310.C.WS.S140 WSA - Gatehouse B (GF) - Backfill, construct GF slab; Vol = 296 m3 (was
C11_6C3)
d/w - 10h/d - With 14 17-Oct-22 01-Nov-22 18-Oct-22 02-Nov-22 1
HK Hols - No B/O periods
310.C.WS.S144 WSA - Gatehouse B (1F) - columns, walls, beams and slab; Vol = 648 m3 (was
C11_6C3)
d/w - 10h/d - With 21 02-Nov-22 25-Nov-22 03-Nov-22 26-Nov-22 1
HK Hols - No B/O periods
310.C.WS.S148 WSA - Gatehouse B (RF) - columns, walls, beams and slab; Vol = 436 m3 (was
C11_6C3)
d/w - 10h/d - With 21 26-Nov-22 20-Dec-22 28-Nov-22 21-Dec-22 1
HK Hols - No B/O periods
310.C.WS.S156 WSA - Gatehouse B (1F) - Water Tanks (FS and Sprinkler);Vol = 137 m3 (was
C11_6C3)
d/w - 10h/d - With 27 09-Jan-23 11-Feb-23 10-Jan-23 13-Feb-23 1
HK Hols - No B/O periods
ABWF (was
C11_6C3)
d/w - 10h/d - With HK Hols
128- No B/O 0periods (was
11-Feb-23
C3) 20-Jul-23 13-Feb-23 02-Aug-23 11
310.C.EX.W2128 WSA - Gatehouse B - Structure completed and falsework removal C11_6 d/w - 10h/d - With 0 11-Feb-23 13-Feb-23 1
HK Hols - No B/O periods
310.C.EX.W2084 WSA - Gatehouse B - Partition Wall & Door Subframe (was
C11_6C3)
d/w - 10h/d - With 75 13-Feb-23 16-May-23 25-Feb-23 30-May-23 11
HK Hols - No B/O periods
310.C.EX.W2088 WSA - Gatehouse B - Plastering & Screeding (was
C11_6C3)
d/w - 10h/d - With 75 21-Feb-23 24-May-23 06-Mar-23 07-Jun-23 11
HK Hols - No B/O periods
310.C.EX.W2092 WSA - Gatehouse B - Tiling & Stonework (was
C11_6C3)
d/w - 10h/d - With 75 01-Mar-23 02-Jun-23 14-Mar-23 15-Jun-23 11
HK Hols - No B/O periods
310.C.EX.W2096 WSA - Gatehouse B - Suspended Ceiling Framework (was
C11_6C3)
d/w - 10h/d - With 75 09-Mar-23 10-Jun-23 22-Mar-23 24-Jun-23 11
HK Hols - No B/O periods
310.C.EX.W2100 WSA - Gatehouse B - Sanitary Ware & Fixtures (was
C11_6C3)
d/w - 10h/d - With 75 17-Mar-23 19-Jun-23 30-Mar-23 04-Jul-23 11
HK Hols - No B/O periods
310.C.EX.W2104 WSA - Gatehouse B - Door Sets & Ironmongery (was
C11_6C3)
d/w - 10h/d - With 75 25-Mar-23 28-Jun-23 12-Apr-23 12-Jul-23 11
HK Hols - No B/O periods
310.C.EX.W2108 WSA - Gatehouse B - Glazing (was
C11_6C3)
d/w - 10h/d - With 75 03-Apr-23 07-Jul-23 20-Apr-23 20-Jul-23 11
HK Hols - No B/O periods
310.C.EX.W2112 WSA - Gatehouse B - Ceiling Panels & Finishes (was
C11_6C3)
d/w - 10h/d - With 75 15-Apr-23 15-Jul-23 28-Apr-23 28-Jul-23 11
HK Hols - No B/O periods
(was C3)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 207 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.EX.W2116 WSA - Gatehouse B - Painting, Graphics & Signage C11_6 d/w - 10h/d - With 75 20-Apr-23 20-Jul-23 04-May-23 02-Aug-23 11
HK Hols - No B/O periods
MEP Installation Works (was
C11_6C3)
d/w - 10h/d - With HK Hols
210- No B/O 2periods (was
11-Feb-23
C3) 27-Oct-23 14-Mar-23 18-Dec-23 44
Transformers (CLP) C11_6 d/w - 10h/d - With HK Hols
140- No B/O 2periods (was
13-Mar-23
C3) 31-Aug-23 14-Mar-23 01-Sep-23 1
310.C.EX.W2120 WSA - Gatehouse B - Complete Transformer Room Structure C11_6 d/w - 10h/d - With 0 13-Mar-23 14-Mar-23 1
HK Hols - No B/O periods
310.C.EX.W2164.B01 WSA - Gatehouse B - Builder Works in Transformer Room (was
C11_6C3)
d/w - 10h/d - With 12 13-Mar-23 25-Mar-23 14-Mar-23 27-Mar-23 1
HK Hols - No B/O periods
310.C.EX.W2044 WSA - Gatehouse B - MEP Works in Transformer Room (was
C11_6C3)
d/w - 10h/d - With 36 27-Mar-23 12-May-23 28-Mar-23 13-May-23 1
HK Hols - No B/O periods
310.C.EX.W2048 WSA - Gatehouse B - Inspection & Handover Transformer Room to CLP (was
C11_6C3)
d/w - 10h/d - With 18 13-May-23 03-Jun-23 15-May-23 05-Jun-23 1
HK Hols - No B/O periods
310.C.EX.W2052 WSA - Gatehouse B - Transformer Installation by CLP (was
C11_6C3)
d/w - 10h/d - With 72 05-Jun-23 29-Aug-23 06-Jun-23 30-Aug-23 1
HK Hols - No B/O periods
310.C.EX.W2124 WSA - Gatehouse B - Cable Laying by CLP (was
C11_6C3)
d/w - 10h/d - With 24 2 21-Jul-23 17-Aug-23 03-Aug-23 30-Aug-23 11
HK Hols - No B/O periods
310.C.EX.W2056 WSA - Gatehouse B - Energization of Transformers (was
C11_6C3)
d/w - 10h/d - With 0 31-Aug-23 01-Sep-23 1
HK Hols - No B/O periods
Plumbing & Drainage Installation (was
C11_6C3)
d/w - 10h/d - With HK Hols
130- No B/O 0periods (was
13-Mar-23
C3) 19-Aug-23 11-May-23 14-Oct-23 46
310.C.EX.W2060 WSA - Gatehouse B - Plumbing & Drainage 1st Fix & Installation C11_6 d/w - 10h/d - With 60 13-Mar-23 27-May-23 11-May-23 22-Jul-23 46
HK Hols - No B/O periods
310.C.EX.W2068 WSA - Gatehouse B - Water Pump Installation (was
C11_6C3)
d/w - 10h/d - With 48 22-Mar-23 22-May-23 24-Jun-23 19-Aug-23 74
HK Hols - No B/O periods
310.C.EX.W2064 WSA - Gatehouse B - Plumbing & Drainage 2nd Fix & Installation (was
C11_6C3)
d/w - 10h/d - With 60 14-Apr-23 26-Jun-23 09-Jun-23 19-Aug-23 46
HK Hols - No B/O periods
310.C.EX.W2080 WSA - Gatehouse B - Plumbing & Drainage Final Fix & Adjustment (was
C11_6C3)
d/w - 10h/d - With 12 07-Aug-23 19-Aug-23 29-Sep-23 14-Oct-23 46
HK Hols - No B/O periods
Electrical Installation (was
C11_6C3)
d/w - 10h/d - With HK Hols
186- No B/O 0periods (was
13-Mar-23
C3) 27-Oct-23 27-May-23 28-Oct-23 1
310.C.EX.W1968 WSA - Gatehouse B - Electrical 1st Fix & Installation C11_6 d/w - 10h/d - With 60 13-Mar-23 27-May-23 27-May-23 07-Aug-23 59
HK Hols - No B/O periods
310.C.EX.W1976 WSA - Gatehouse B - Switchgear Installation (was
C11_6C3)
d/w - 10h/d - With 48 14-Apr-23 10-Jun-23 26-Jun-23 21-Aug-23 59
HK Hols - No B/O periods
310.C.EX.W1980 WSA - Gatehouse B - Emergency Genset Installation (was
C11_6C3)
d/w - 10h/d - With 48 14-Apr-23 10-Jun-23 08-Jul-23 01-Sep-23 69
HK Hols - No B/O periods
310.C.EX.W1972 WSA - Gatehouse B - Electrical 2nd Fix & Installation (was
C11_6C3)
d/w - 10h/d - With 60 14-Apr-23 26-Jun-23 22-Jul-23 29-Sep-23 81
HK Hols - No B/O periods
310.C.EX.W1984 WSA - Gatehouse B - Power On to All Floors (was
C11_6C3)
d/w - 10h/d - With 0 31-Aug-23 01-Sep-23 1
HK Hols - No B/O periods
310.C.EX.W1996 WSA - Gatehouse B - Electrical Final Fix & Adjustment (was
C11_6C3)
d/w - 10h/d - With 12 13-Oct-23 27-Oct-23 14-Oct-23 28-Oct-23 1
HK Hols - No B/O periods
Fire Services Installation (was
C11_6C3)
d/w - 10h/d - With HK Hols
130- No B/O 0periods (was
13-Mar-23
C3) 19-Aug-23 24-May-23 28-Oct-23 57
310.C.EX.W2000 WSA - Gatehouse B - Fire Services 1st Fix & Installation C11_6 d/w - 10h/d - With 60 13-Mar-23 27-May-23 24-May-23 04-Aug-23 57
HK Hols - No B/O periods
310.C.EX.W2008 WSA - Gatehouse B - FS Pump Installation (was
C11_6C3)
d/w - 10h/d - With 48 14-Apr-23 10-Jun-23 08-Jul-23 01-Sep-23 69
HK Hols - No B/O periods
310.C.EX.W2004 WSA - Gatehouse B - Fire Services 2nd Fix & Installation (was
C11_6C3)
d/w - 10h/d - With 60 14-Apr-23 26-Jun-23 23-Jun-23 01-Sep-23 57
HK Hols - No B/O periods
310.C.EX.W2020 WSA - Gatehouse B - Fire Services Final Fix & Adjustment (was
C11_6C3)
d/w - 10h/d - With 12 07-Aug-23 19-Aug-23 14-Oct-23 28-Oct-23 57
HK Hols - No B/O periods
MVAC Installation (was
C11_6C3)
d/w - 10h/d - With HK Hols
130- No B/O 0periods (was
13-Mar-23
C3) 19-Aug-23 24-May-23 28-Oct-23 57

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 208 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.EX.W2024 WSA - Gatehouse B - MVAC 1st Fix & Installation C11_6 d/w - 10h/d - With 60 13-Mar-23 27-May-23 24-May-23 04-Aug-23 57
HK Hols - No B/O periods
310.C.EX.W2028 WSA - Gatehouse B - MVAC 2nd Fix & Installation (was
C11_6C3)
d/w - 10h/d - With 60 14-Apr-23 26-Jun-23 23-Jun-23 01-Sep-23 57
HK Hols - No B/O periods
310.C.EX.W2040 WSA - Gatehouse B - MVAC Final Fix & Adjustment (was
C11_6C3)
d/w - 10h/d - With 12 07-Aug-23 19-Aug-23 14-Oct-23 28-Oct-23 57
HK Hols - No B/O periods
Lifts Installation Works (was
C11_6C3)
d/w - 10h/d - With HK Hols
138- No B/O 0periods (was
11-Feb-23
C3) 01-Aug-23 07-Jul-23 18-Dec-23 116
310.C.EX.W2436 WSA - Gatehouse B - Submit Form LE 2&3 C11_6 d/w - 10h/d - With 0 11-Feb-23 03-Aug-23 140
HK Hols - No B/O periods
310.C.EX.W2042 WSA - Gatehouse B - Builder Works in Lift Shaft / Lift Pit / Pulley Room (was
C11_6C3)
d/w - 10h/d - With 24 13-Feb-23 11-Mar-23 07-Jul-23 03-Aug-23 116
HK Hols - No B/O periods
310.C.EX.W2050 WSA - Gatehouse B - Lift Installation (incl. T&C) (was
C11_6C3)
d/w - 10h/d - With 90 13-Mar-23 04-Jul-23 04-Aug-23 20-Nov-23 116
HK Hols - No B/O periods
310.C.EX.W2054 WSA - Gatehouse B - Submit Form LE5 (was
C11_6C3)
d/w - 10h/d - With 0 04-Jul-23 20-Nov-23 116
HK Hols - No B/O periods
310.C.EX.W2058 WSA - Gatehouse B - Waiting for EMSD Inspection for Lift (was
C11_6C3)
d/w - 10h/d - With 11 05-Jul-23 17-Jul-23 21-Nov-23 02-Dec-23 116
HK Hols - No B/O periods
310.C.EX.W2062 WSA - Gatehouse B - EMSD Inspection (was
C11_6C3)
d/w - 10h/d - With 11 18-Jul-23 29-Jul-23 04-Dec-23 15-Dec-23 116
HK Hols - No B/O periods
310.C.EX.W2066 WSA - Gatehouse B - Waiting for Issue of Use Permit (was
C11_6C3)
d/w - 10h/d - With 2 31-Jul-23 01-Aug-23 16-Dec-23 18-Dec-23 116
HK Hols - No B/O periods
310.C.EX.W2070 WSA - Gatehouse B - Issue of Use Permit (was
C11_6C3)
d/w - 10h/d - With 0 01-Aug-23 18-Dec-23 116
HK Hols - No B/O periods
External Works (was
C11_6C3)
d/w - 10h/d - With HK Hols
251- No B/O 0periods (was
21-Dec-22
C3) 27-Oct-23 23-May-23 28-Oct-23 1
External Building Finishes C11_6 d/w - 10h/d - With HK Hols
169- No B/O 0periods (was
21-Dec-22
C3) 20-Jul-23 23-May-23 02-Aug-23 11
310.C.WS.S152 WSA - Gatehouse B - Roof Waterproofing & Roof Finishes C11_6 d/w - 10h/d - With 21 21-Dec-22 16-Jan-23 23-May-23 16-Jun-23 121
HK Hols - No B/O periods
310.C.ES.P716 WSA - Gatehouse B - External building finishes (was
C11_6C3)
d/w - 10h/d - With 38 05-Jun-23 20-Jul-23 17-Jun-23 02-Aug-23 11
HK Hols - No B/O periods
Drainage and UU (was
C11_6C3)
d/w - 10h/d - With HK Hols
62- No B/O 0periods (was
05-Jun-23
C3) 17-Aug-23 17-Jun-23 03-Oct-23 38
310.C.ES.P696 WSA - Gatehouse B - Building drainage and watermain works C11_6 d/w - 10h/d - With 38 05-Jun-23 20-Jul-23 17-Jun-23 02-Aug-23 11
HK Hols - No B/O periods
310.C.ES.P720 WSA - Gatehouse B - CLP Cable ducts + drawpits (was
C11_6C3)
d/w - 10h/d - With 30 14-Jun-23 20-Jul-23 28-Jun-23 02-Aug-23 11
HK Hols - No B/O periods
310.C.ES.P700 WSA - Gatehouse B - AS Cable ducts + drawpits (was
C11_6C3)
d/w - 10h/d - With 24 21-Jul-23 17-Aug-23 04-Sep-23 03-Oct-23 38
HK Hols - No B/O periods
310.C.ES.P704 WSA - Gatehouse B - EL cable ducting + drawpits (was
C11_6C3)
d/w - 10h/d - With 24 21-Jul-23 17-Aug-23 05-Aug-23 01-Sep-23 13
HK Hols - No B/O periods
Soft and Hard landscape & EVA Construction (was
C11_6C3)
d/w - 10h/d - With HK Hols
58- No B/O 0periods (was
18-Aug-23
C3) 27-Oct-23 15-Sep-23 28-Oct-23 1
310.C.ES.P708 WSA - Gatehouse B - Hard and soft landscape works C11_6 d/w - 10h/d - With 21 18-Aug-23 11-Sep-23 04-Oct-23 28-Oct-23 38
HK Hols - No B/O periods
310.C.WS.C120 WSA - Gatehouse B - Site Formation Works and Road Works for EVA (was
C11_6C3)
d/w - 10h/d - With 35 14-Sep-23 27-Oct-23 15-Sep-23 28-Oct-23 1
HK Hols - No B/O periods
WSA - Screening Facilities (was C3) 269 0 19-May-22 13-Apr-23 08-Jun-22 31-Aug-24 414
Procurement C01_7 d/w - 10h/d - No HK Hols191
- No B/O periods
0 (was19-May-22
C1) 25-Nov-22 08-Jun-22 15-Dec-22 20
Major Materials ABWF C01_7 d/w - 10h/d - No HK Hols104
- No B/O periods
0 (was05-Jul-22
C1) 16-Oct-22 05-Aug-22 16-Nov-22 31
310.P.ES.P90 WSA Screening Facilities (Procurement ABWF) - Place Order for Materials C01_7 d/w - 10h/d - No HK 7 05-Jul-22 11-Jul-22 05-Aug-22 11-Aug-22 31
Hols - No B/O periods (was
310.P.ES.P102 WSA Screening Facilities (Procurement ABWF) - Manufacturing of Materials C1)
C01_7 d/w - 10h/d - No HK 90 12-Jul-22 09-Oct-22 12-Aug-22 09-Nov-22 31
Hols - No B/O periods (was
C1)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 209 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.P.ES.P110 WSA Screening Facilities (Procurement ABWF) - Delivery of Materials C01_7 d/w - 10h/d - No HK 7 10-Oct-22 16-Oct-22 10-Nov-22 16-Nov-22 31
Hols - No B/O periods (was
Major Materials MEP C1)
C01_7 d/w - 10h/d - No HK Hols191
- No B/O periods
0 (was19-May-22
C1) 25-Nov-22 08-Jun-22 15-Dec-22 20
310.P.ES.P94 WSA Screening Facilities (Procurement MEP) - Place Order for Material C01_7 d/w - 10h/d - No HK 120 19-May-22 15-Sep-22 08-Jun-22 05-Oct-22 20
Hols - No B/O periods (was
310.P.ES.P126 WSA Screening Facilities (Procurement MEP) - Manufacturing of Material C1)
C01_7 d/w - 10h/d - No HK 170 02-Jun-22 18-Nov-22 22-Jun-22 08-Dec-22 20
Hols - No B/O periods (was
310.P.ES.P130 WSA Screening Facilities (Procurement MEP) - Delivery of Materials C1)
C01_7 d/w - 10h/d - No HK 7 19-Nov-22 25-Nov-22 09-Dec-22 15-Dec-22 20
Hols - No B/O periods (was
Initial Work and Site Preparation C1) 25 0 04-Jul-22 01-Aug-22 04-Jul-22 19-Aug-22 16
310.C.WS.R010 WSA - Screening Facilities - Site access WA3310/12 C01_7 d/w - 10h/d - No HK 0 04-Jul-22* 04-Jul-22 0
Hols - No B/O periods (was
310.C.WS.R026 WSA - Screening Facilities - Hoarding C1)
C03_7 d/w - 10h/d - With 3 04-Jul-22 06-Jul-22 22-Jul-22 24-Jul-22 18
HK Hols - No B/O periods
310.C.WS.R014 WSA - Screening Facilities - Carry out site survey C03_7 d/w - 10h/d - With 1 06-Jul-22 06-Jul-22 24-Jul-22 24-Jul-22 18
HK Hols - No B/O periods
310.C.WS.R018 WSA - Screening Facilities - Install monitoring point C03_7 d/w - 10h/d - With 1 07-Jul-22 07-Jul-22 25-Jul-22 25-Jul-22 18
HK Hols - No B/O periods
310.C.WS.R022 WSA - Screening Facilities - UU detection and trial pit C03_7 d/w - 10h/d - With 4 08-Jul-22 11-Jul-22 26-Jul-22 29-Jul-22 18
HK Hols - No B/O periods
310.C.WS.R046.B01 WSA - Screening Facilities - Diversion of underground utilities (if any) C03_7 d/w - 10h/d - With 21 12-Jul-22 01-Aug-22 30-Jul-22 19-Aug-22 18
HK Hols - No B/O periods
Structural Works C11_6 d/w - 10h/d - With HK Hols
82- No B/O 0periods (was
04-Jul-22
C3) 10-Oct-22 06-Aug-22 28-Oct-22 16
310.C.WS.R030 WSA - Screening Facilities - Obtain BA8 consent C11_6 d/w - 10h/d - With 0 04-Jul-22 06-Aug-22 30
HK Hols - No B/O periods
310.C.WS.R034 WSA - Screening Facilities - BA10 notice of commencement of works (was
C11_6C3)
d/w - 10h/d - With 6 04-Jul-22 09-Jul-22 08-Aug-22 13-Aug-22 30
HK Hols - No B/O periods
310.C.WS.R038 WSA - Screening Facilities - SI works + Submit Report (was
C11_6C3)
d/w - 10h/d - With 5 12-Jul-22 16-Jul-22 15-Aug-22 19-Aug-22 29
HK Hols - No B/O periods
310.C.WS.R042 WSA - Screening Facilities - Open Cut Excavation to FL + Plate Load Test (was
C11_6C3)
d/w - 10h/d - With 11 02-Aug-22 13-Aug-22 20-Aug-22 01-Sep-22 16
HK Hols - No B/O periods
310.C.WS.R050 WSA - Screening Facilities - Construction of footing(621 m3), backfill, GF base slab (126 (was
C11_6C3)
d/w - 10h/d - With 28 15-Aug-22 16-Sep-22 02-Sep-22 07-Oct-22 16
M3) HK Hols - No B/O periods
310.C.WS.R058 WSA - Screening Facilities (RF) - columns, walls, beams and slab; Vol = 82 m3 (was
C11_6C3)
d/w - 10h/d - With 18 17-Sep-22 10-Oct-22 08-Oct-22 28-Oct-22 16
HK Hols - No B/O periods
ABWF Works (was
C11_6C3)
d/w - 10h/d - With HK Hols
65- No B/O 0periods (was
11-Oct-22
C3) 24-Dec-22 17-Nov-22 31-Aug-24 499
310.C.WS.R062 WSA - Screening Facilities - Roof Waterproofing & Roof Finishes C11_6 d/w - 10h/d - With 14 11-Oct-22 26-Oct-22 16-Aug-24 31-Aug-24 550
HK Hols - No B/O periods
310.C.WS.R066 WSA - Screening Facilities - ABWF Internal Works (was
C11_6C3)
d/w - 10h/d - With 51 27-Oct-22 24-Dec-22 17-Nov-22 17-Jan-23 18
HK Hols - No B/O periods
310.C.WS.R068 WSA - Screening Facilities - ABWF External Works (was
C11_6C3)
d/w - 10h/d - With 51 27-Oct-22 24-Dec-22 28-Feb-23 03-May-23 101
HK Hols - No B/O periods
MEP Works (was
C11_6C3)
d/w - 10h/d - With HK Hols
68- No B/O 0periods (was
26-Nov-22
C3) 18-Feb-23 16-Dec-22 10-Mar-23 17
310.C.WS.R078 WSA - Screening Facilities - Building Services Installations C11_6 d/w - 10h/d - With 52 26-Nov-22 31-Jan-23 16-Dec-22 20-Feb-23 17
HK Hols - No B/O periods
310.C.WS.R198 WSA - Screening Facilities - Power On Test (was
C11_6C3)
d/w - 10h/d - With 8 10-Feb-23 18-Feb-23 02-Mar-23 10-Mar-23 17
HK Hols - No B/O periods
Fencing, Drainage and UU (was
C11_6C3)
d/w - 10h/d - With HK Hols
150- No B/O 0periods (was
11-Oct-22
C3) 13-Apr-23 29-Oct-22 03-May-23 16
310.C.WS.R102 WSA - Screening Facilities (Drainage) - Drainage (stormwater, rainwater, sewerage) C11_6 d/w - 10h/d - With 30 11-Oct-22 14-Nov-22 29-Oct-22 02-Dec-22 16
HK Hols - No B/O periods
(was C3)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 210 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.WS.R106 WSA - Screening Facilities (UU) - CLP, watermain, telecomm C11_6 d/w - 10h/d - With 90 15-Nov-22 04-Mar-23 03-Dec-22 23-Mar-23 16
HK Hols - No B/O periods
310.C.WS.R110 WSA - Screening Facilities (pavement) - pavement and landscaping (was
C11_6C3)
d/w - 10h/d - With 30 06-Mar-23 13-Apr-23 24-Mar-23 03-May-23 16
HK Hols - No B/O periods
310.C.WS.R190 WSA - Screening Facilities (Security Fence) - construction of security fence (was
C11_6C3)
d/w - 10h/d - With 30 06-Mar-23 13-Apr-23 24-Mar-23 03-May-23 16
HK Hols - No B/O periods
AGL Vault D Annex (was C3) 592 0 07-Jun-21 A 02-Jun-23 28-Mar-22 14-Jul-24 331
Procurement C01_7 d/w - 10h/d - No HK Hols160
- No B/O periods
0 (was12-May-22
C1) 18-Oct-22 18-May-22 09-Dec-22 52
Major Materials ABWF C01_7 d/w - 10h/d - No HK Hols77
- No B/O periods
0 (was03-Aug-22
C1) 18-Oct-22 12-Sep-22 09-Dec-22 52
310.P.RC.D343.6.B01 AGL Vault D Annex (Procurement ABWF) - Place order, Manufacturing & Delivery of C01_7 d/w - 10h/d - No HK 45 03-Aug-22 16-Sep-22 12-Sep-22 26-Oct-22 40
Metal Cover at G/F (1 set) Hols - No B/O periods (was
310.P.RC.D343 AGL Vault D Annex (Procurement ABWF) - Place order, Manufacturing & Delivery of C1)
C01_7 d/w - 10h/d - No HK 45 08-Aug-22 21-Sep-22 27-Sep-22 10-Nov-22 50
Louvre (Approx 6 nos) Hols - No B/O periods (was
310.P.RC.D343.4.B01 AGL Vault D Annex (Procurement ABWF) - Place order, Manufacturing & Delivery of C1)
C01_7 d/w - 10h/d - No HK 45 08-Aug-22 21-Sep-22 27-Sep-22 10-Nov-22 50
Cladding Hols - No B/O periods (was
310.P.RC.D343.2.B01 AGL Vault D Annex (Procurement ABWF) - Place order, Manufacturing & Delivery of C1)
C01_7 d/w - 10h/d - No HK 30 18-Aug-22 16-Sep-22 20-Sep-22 19-Oct-22 33
Drainage Channel at R/F Hols - No B/O periods (was
310.P.RC.D343.3.B01 AGL Vault D Annex (Procurement ABWF) - Place order, Manufacturing & Delivery of C1)
C01_7 d/w - 10h/d - No HK 30 18-Aug-22 16-Sep-22 27-Sep-22 26-Oct-22 40
Raised Floor at Communication Room Hols - No B/O periods (was
310.P.RC.D511 AGL Vault D Annex (Procurement ABWF) - Place order, Manufacturing & Delivery of Fall C1)
C01_7 d/w - 10h/d - No HK 45 18-Aug-22 01-Oct-22 17-Sep-22 31-Oct-22 30
Restraint System (1set) Hols - No B/O periods (was
310.P.RC.D339 AGL Vault D Annex (Procurement ABWF) - Place order, Manufacturing & Delivery of cat C1)
C01_7 d/w - 10h/d - No HK
30 28-Aug-22 26-Sep-22 12-Oct-22 10-Nov-22 45
ladder (1 no) Hols - No B/O periods (was
310.P.RC.D343.5.B01 AGL Vault D Annex (Procurement ABWF) - Place order, Manufacturing & Delivery of Door C1)
C01_7 d/w - 10h/d - No HK 45 04-Sep-22 18-Oct-22 26-Oct-22 09-Dec-22 52
with ironmongery (Approx 5 Nos) Hols - No B/O periods (was
Major Materials MEP C1)
C01_7 d/w - 10h/d - No HK Hols113
- No B/O periods
0 (was12-May-22
C1) 01-Sep-22 18-May-22 01-Sep-22 0
Electrical & MVAC Services C01_7 d/w - 10h/d - No HK Hols104
- No B/O periods
0 (was12-May-22
C1) 23-Aug-22 18-May-22 01-Sep-22 9
310.P.RC.D331 AGL Vault D Annex (Procurement Electrical & MVAC Materials) - AC/ ventilation fan, LV & C01_7 d/w - 10h/d - No HK 50 12-May-22 30-Jun-22 18-May-22 06-Jul-22 6
Others Place Order for Materials Hols - No B/O periods (was
310.P.RC.D519 AGL Vault D Annex (Procurement Electrical & MVAC Materials) - AC/ ventilation fan, LV C1)
C01_7 d/w - 10h/d - No HK 90 19-May-22 16-Aug-22 25-May-22 22-Aug-22 6
&Others-Manufacturing of Materials Hols - No B/O periods (was
310.P.RC.D499 AGL Vault D Annex (Procurement Electrical & MVAC Materials) - Delivery of Materials C1)
C01_7 d/w - 10h/d - No HK 28 27-Jul-22 23-Aug-22 05-Aug-22 01-Sep-22 9
Hols - No B/O periods (was
310.P.RC.D351 AGL Vault D Annex (Procurement Electrical & MVAC Materials) - Delivery of Materials C1)
C01_7 d/w - 10h/d - No HK 14 10-Aug-22 23-Aug-22 16-Aug-22 29-Aug-22 6
(Long Lead Items) Hols - No B/O periods (was
Plumbing & Drainage Services C1)
C01_7 d/w - 10h/d - No HK Hols50
- No B/O periods
0 (was06-Jul-22
C1) 24-Aug-22 14-Jul-22 01-Sep-22 8
310.P.RC.D327 AGL Vault D Annex (Procurement Plumbing & Drainage Materials) - Pipes, valves & C01_7 d/w - 10h/d - No HK 3 06-Jul-22 08-Jul-22 14-Jul-22 16-Jul-22 8
Others - Place Order for Materials Hols - No B/O periods (was
310.P.RC.D515 AGL Vault D Annex (Procurement Plumbing & Drainage Materials) - Pipes, valves & C1)
C01_7 d/w - 10h/d - No HK
40 09-Jul-22 17-Aug-22 17-Jul-22 25-Aug-22 8
Others - Manufacturing of Materials Hols - No B/O periods (was
310.P.RC.D575.B01 AGL Vault D Annex (Procurement Plumbing & Drainage Materials) - Delivery of Materials C1)
C01_7 d/w - 10h/d - No HK 7 18-Aug-22 24-Aug-22 26-Aug-22 01-Sep-22 8
(Long Lead Items) Hols - No B/O periods (was
310.P.RC.D571.B01 AGL Vault D Annex (Procurement Plumbing & Drainage Materials) - Delivery of Materials C1)
C01_7 d/w - 10h/d - No HK 7 18-Aug-22 24-Aug-22 26-Aug-22 01-Sep-22 8
Hols - No B/O periods (was
Fire Services C1)
C01_7 d/w - 10h/d - No HK Hols96
- No B/O periods
0 (was29-May-22
C1) 01-Sep-22 29-May-22 01-Sep-22 0
310.P.RC.D328 AGL Vault D Annex (Procurement FS Materials) - 1230 system, AC & Others - Place C01_7 d/w - 10h/d - No HK 60 29-May-22 27-Jul-22 29-May-22 27-Jul-22 0
Order for Materials Hols - No B/O periods (was
310.P.RC.D523 AGL Vault D Annex (Procurement FS Materials) - 1230 system, AC & Others - C1)
C01_7 d/w - 10h/d - No HK 75 12-Jun-22 25-Aug-22 12-Jun-22 25-Aug-22 0
Manufacturing of Materials Hols - No B/O periods (was
310.P.RC.D563.B01 AGL Vault D Annex (Procurement FS Materials) - Delivery of Materials C1)
C01_7 d/w - 10h/d - No HK 28 05-Aug-22 01-Sep-22 05-Aug-22 01-Sep-22 0
Hols - No B/O periods (was
C1)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 211 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.P.RC.D567.B01 AGL Vault D Annex (Procurement FS Materials) - Delivery of Materials (Long Lead Items) C01_7 d/w - 10h/d - No HK 14 12-Aug-22 25-Aug-22 19-Aug-22 01-Sep-22 7
Hols - No B/O periods (was
Construction C1) 506 0 07-Jun-21 A 15-Feb-23 28-Mar-22 13-Dec-23 247
Initial Works 278 0 07-Jun-21 A 21-Mar-22 A 28-Mar-22 28-Mar-22
310.D.RC.D379 AGL Vault D Annex (Work Permit) - Coordination with AA to grant Site Access + C01_7 d/w - 10h/d - No HK 117 07-Jun-21 A 01-Oct-21 A 28-Mar-22 28-Mar-22
preparation works Hols - No B/O periods (was
310.D.RC.D391 AGL Vault D Annex (Site Prep.) - Assumed site possession of the area C1)
C11_6 d/w - 10h/d - With 0 25-Oct-21 A 28-Mar-22
HK Hols - No B/O periods
310.D.RC.D467.B01 AGL Vault D Annex (Site Prep.) - MS Instrumentation Submission and Acceptance (was
C01_7C3)
d/w - 10h/d - No HK 60 11-Nov-21 A 04-Dec-21 A 28-Mar-22 28-Mar-22
Hols - No B/O periods (was
310.D.RC.D455.B01 AGL Vault D Annex (Site Prep.) - Site query (CFJV-SQ-00120) on existing UU - C1)
C11_6 d/w - 10h/d - With 6 17-Nov-21 A 24-Nov-21 A 28-Mar-22 28-Mar-22
Submission HK Hols - No B/O periods
310.D.RC.D399 AGL Vault D Annex (Site Prep.) - carry out condition survey and report (was
C11_6C3)
d/w - 10h/d - With 10 19-Nov-21 A 19-Nov-21 A 28-Mar-22 28-Mar-22
HK Hols - No B/O periods
310.D.RC.D411 AGL Vault D Annex (Site Prep.) - carry out trial pit (was
C11_6C3)
d/w - 10h/d - With 6 20-Nov-21 A 23-Nov-21 A 28-Mar-22 28-Mar-22
HK Hols - No B/O periods
310.D.RC.D403 AGL Vault D Annex (Site Prep.) - carry out UU detection survey and report (was
C11_6C3)
d/w - 10h/d - With 8 20-Nov-21 A 09-Dec-21 A 28-Mar-22 28-Mar-22
HK Hols - No B/O periods
310.D.RC.D459.B01 AGL Vault D Annex (Site Prep.) - Site query (CFJV-SQ-00120) on existing UU - Review & (was
C11_6C3)
d/w - 10h/d - With 14 25-Nov-21 A 21-Mar-22 A 28-Mar-22 28-Mar-22
Comments HK Hols - No B/O periods
310.D.RC.D407 AGL Vault D Annex (Site Prep.) - install Instrumentation (was
C11_6C3)
d/w - 10h/d - With 6 06-Dec-21 A 09-Dec-21 A 28-Mar-22 28-Mar-22
HK Hols - No B/O periods
310.D.RC.D415 AGL Vault D Annex (Site Prep.) - divert existing UU cables (was
C11_6C3)
d/w - 10h/d - With 14 21-Mar-22 A 21-Mar-22 A 28-Mar-22 28-Mar-22
HK Hols - No B/O periods
Excavation (was C3) 91 0 20-Dec-21 A 18-Apr-22 28-Mar-22 18-Apr-22 0
310.D.RC.D414 AGL Vault D Annex - Submit BA8 consent application C01_7 d/w - 10h/d - No HK 7 20-Dec-21 A 07-Feb-22 A 28-Mar-22 28-Mar-22
Hols - No B/O periods (was
310.D.RC.D416 AGL Vault D Annex - Submit BA10 notice to commencement of work C1)
C01_7 d/w - 10h/d - No HK 7 11-Feb-22 A 16-Feb-22 A 28-Mar-22 28-Mar-22
Hols - No B/O periods (was
310.D.RC.D419 AGL Vault D Annex (Excavation) - open excavation to from +7.40mPD to +5.525mPD C1)
C11_6 d/w - 10h/d - With 13 21-Mar-22 A 04-Apr-22 28-Mar-22 04-Apr-22 0
(Qty. 630m3) HK Hols - No B/O periods
310.D.RC.D423 AGL Vault D Annex (Foundation) - plate load test (Qty: 2 nos.) (was
C01_7C3)
d/w - 10h/d - No HK 14 05-Apr-22 18-Apr-22 05-Apr-22 18-Apr-22 0
Hols - No B/O periods (was
Structure C1)
C11_6 d/w - 10h/d - With HK Hols
90- No B/O 0periods (was
11-Mar-22
C3) A 04-Aug-22 19-Apr-22 04-Aug-22 0
Foundation C11_6 d/w - 10h/d - With HK Hols
16- No B/O 0periods (was
19-Apr-22
C3) 07-May-22 19-Apr-22 07-May-22 0
310.D.RC.D427 AGL Vault D Annex (Foundation) - construction of footing (600mm thk) (104m3) C11_6 d/w - 10h/d - With 16 19-Apr-22 07-May-22 19-Apr-22 07-May-22 0
HK Hols - No B/O periods
Screen wall from footing to Ground Floor Slab (was
C11_6C3)
d/w - 10h/d - With HK Hols
18- No B/O 0periods (was
09-May-22
C3) 28-May-22 09-May-22 28-May-22 0
310.D.RC.D431 AGL Vault D Annex (Ground) - Upstand/screen wall & mass concrete fill for cable trench C11_6 d/w - 10h/d - With 18 09-May-22 28-May-22 09-May-22 28-May-22 0
& construct G/F slab (445m3) HK Hols - No B/O periods
UG column/wall to Roof Slab Including parapet wall (was
C11_6C3)
d/w - 10h/d - With HK Hols
56- No B/O 0periods (was
11-Mar-22
C3) A 04-Aug-22 09-May-22 04-Aug-22 0
310.D.RC.D395 AGL Vault D Annex (Site Prep.) - erect hoarding C11_6 d/w - 10h/d - With 4 11-Mar-22 A 11-Mar-22 A 09-May-22 09-May-22
HK Hols - No B/O periods
310.D.RC.D435 AGL Vault D Annex (Ground ) - columns, walls from UG to roof (57m3) (was
C11_6C3)
d/w - 10h/d - With 28 30-May-22 02-Jul-22 30-May-22 02-Jul-22 0
HK Hols - No B/O periods
310.D.RC.D439 AGL Vault D Annex (Roof) - construction of beams and roof slab (159m3) (was C3)
C11_6 d/w - 10h/d - With 21 04-Jul-22 27-Jul-22 04-Jul-22 27-Jul-22 0
HK Hols - No B/O periods
310.D.RC.D439.1.B01AGL Vault D Annex (Roof) - construction of parapet wall (13m3) (was
C11_6C3)
d/w - 10h/d - With 7 28-Jul-22 04-Aug-22 28-Jul-22 04-Aug-22 0
HK Hols - No B/O periods
ABWF and MEP (was C3) 159 0 05-Aug-22 15-Feb-23 05-Aug-22 13-Dec-23 247
Internal Finishes 72 0 05-Aug-22 31-Oct-22 05-Aug-22 30-Nov-22 26

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 212 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.RC.D463.B01 AGL Vault D Annex (ABWF and MEP) - Curing and Removal of Falsework/Formworks C01_7 d/w - 10h/d - No HK 12 05-Aug-22 16-Aug-22 05-Aug-22 16-Aug-22 0
Hols - No B/O periods (was
310.D.RC.D447 AGL Vault D Annex (ABWF) - commencement C1)
C11_6 d/w - 10h/d - With 0 17-Aug-22 17-Aug-22 0
HK Hols - No B/O periods
310.D.RC.D451 AGL Vault D Annex (ABWF) - Internal Works - Blockwall (was
C11_6C3)
d/w - 10h/d - With 10 17-Aug-22 27-Aug-22 17-Aug-22 27-Aug-22 0
HK Hols - No B/O periods
310.D.RC.D663.B01 AGL Vault D Annex (ABWF) - Internal Works - Wall & Ceiling Finishes (was
C11_6C3)
d/w - 10h/d - With 20 29-Aug-22 21-Sep-22 29-Aug-22 21-Sep-22 0
HK Hols - No B/O periods
310.D.RC.D667.B01 AGL Vault D Annex (ABWF) - Internal Works - Flooring (was
C11_6C3)
d/w - 10h/d - With 20 22-Sep-22 17-Oct-22 27-Oct-22 18-Nov-22 28
HK Hols - No B/O periods
310.D.RC.D668.B01 AGL Vault D Annex (ABWF) - Internal Works - Metal Works (was
C11_6C3)
d/w - 10h/d - With 10 20-Oct-22 31-Oct-22 19-Nov-22 30-Nov-22 26
HK Hols - No B/O periods
MEP Installation Works (was C3) 135 0 02-Sep-22 15-Feb-23 02-Sep-22 13-Dec-23 247
Drainage Installation C11_6 d/w - 10h/d - With HK Hols
89- No B/O 0periods (was
02-Sep-22
C3) 17-Dec-22 02-Sep-22 17-Dec-22 0
310.D.RC.D475.100B02
AGL Vault D Annex - Drainage 1st Fix & Installation C11_6 d/w - 10h/d - With 60 02-Sep-22 14-Nov-22 02-Sep-22 14-Nov-22 0
HK Hols - No B/O periods
310.D.RC.D475.110B02
AGL Vault D Annex - Drainage 2nd Fix & Installation (was
C11_6C3)
d/w - 10h/d - With 60 29-Sep-22 09-Dec-22 29-Sep-22 09-Dec-22 0
HK Hols - No B/O periods
310.D.RC.D475.120B02
AGL Vault D Annex - Drainage Final Fix & Adjustment (was
C11_6C3)
d/w - 10h/d - With 7 10-Dec-22 17-Dec-22 10-Dec-22 17-Dec-22 0
HK Hols - No B/O periods
Electrical Installation (was C3) 135 0 02-Sep-22 15-Feb-23 02-Sep-22 13-Dec-23 247
310.D.RC.D475 AGL Vault D Annex - Electrical 1st Fix & Installation C11_6 d/w - 10h/d - With 60 02-Sep-22 14-Nov-22 02-Sep-22 14-Nov-22 0
HK Hols - No B/O periods
310.D.RC.D475.140B02
AGL Vault D Annex - Electrical 2nd Fix & Installation (was
C11_6C3)
d/w - 10h/d - With 60 12-Sep-22 22-Nov-22 12-Sep-22 22-Nov-22 0
HK Hols - No B/O periods
310.D.RC.D635.1B01AGL Vault D Annex - Access Date for Power Supply Installation by others (was
C11_6C3)
d/w - 10h/d - With 0 14-Nov-22 14-Nov-22 0
HK Hols - No B/O periods
310.D.RC.D475.150B02
AGL Vault D Annex - Electrical Final Fix & Adjustment (was
C11_6C3)
d/w - 10h/d - With 7 23-Nov-22 30-Nov-22 23-Nov-22 30-Nov-22 0
HK Hols - No B/O periods
310.D.RC.D659.B01 AGL Vault D Annex (MEP) - Megger Test (was
C11_6C3)
d/w - 10h/d - With 15 01-Dec-22 17-Dec-22 01-Dec-22 17-Dec-22 0
HK Hols - No B/O periods
310.D.RC.D611 AGL Vault D Annex - Achieved KD-1 (Stage 1)/ Provide Access for Other Contractors to (was
C01_7C3)
d/w - 10h/d - No HK 0 17-Dec-22 17-Dec-22 0
Commence their follow-on works Hols - No B/O periods (was
310.D.RC.D635 AGL Vault D Annex - Latest Date for Power Supply by Others C1)
C11_6 d/w - 10h/d - With 0 17-Dec-22 17-Dec-22 0
HK Hols - No B/O periods
310.D.RC.D627 AGL Vault D Annex - System Integration T&C (was
C11_6C3)
d/w - 10h/d - With 30 09-Jan-23 15-Feb-23 09-Nov-23 13-Dec-23 247
HK Hols - No B/O periods
Fire Services Installation (was
C11_6C3)
d/w - 10h/d - With HK Hols
89- No B/O 0periods (was
02-Sep-22
C3) 17-Dec-22 02-Sep-22 17-Dec-22 0
310.D.RC.D475.160B02
AGL Vault D Annex - Fire Services 1st Fix & Installation C11_6 d/w - 10h/d - With 60 02-Sep-22 14-Nov-22 02-Sep-22 14-Nov-22 0
HK Hols - No B/O periods
310.D.RC.D475.170B02
AGL Vault D Annex - Fire Services 2nd Fix & Installation (was
C11_6C3)
d/w - 10h/d - With 60 29-Sep-22 09-Dec-22 29-Sep-22 09-Dec-22 0
HK Hols - No B/O periods
310.D.RC.D475.180B02
AGL Vault D Annex - Fire Service Final Fix & Adjustment (was
C11_6C3)
d/w - 10h/d - With 7 10-Dec-22 17-Dec-22 10-Dec-22 17-Dec-22 0
HK Hols - No B/O periods
MVAC Installation (was
C11_6C3)
d/w - 10h/d - With HK Hols
89- No B/O 0periods (was
02-Sep-22
C3) 17-Dec-22 02-Sep-22 17-Dec-22 0
310.D.RC.D475.190B02
AGL Vault D Annex - MVAC 1st Fix & Installation C11_6 d/w - 10h/d - With 60 02-Sep-22 14-Nov-22 02-Sep-22 14-Nov-22 0
HK Hols - No B/O periods
310.D.RC.D475.200B02
AGL Vault D Annex - MVAC 2nd Fix & Installation (was
C11_6C3)
d/w - 10h/d - With 60 29-Sep-22 09-Dec-22 29-Sep-22 09-Dec-22 0
HK Hols - No B/O periods
310.D.RC.D475.210B02
AGL Vault D Annex - MVAC Final Fix & Adjustment (was
C11_6C3)
d/w - 10h/d - With 7 10-Dec-22 17-Dec-22 10-Dec-22 17-Dec-22 0
HK Hols - No B/O periods
(was C3)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 213 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
Roof Floor Finishes 72 0 05-Aug-22 31-Oct-22 12-Oct-22 30-Nov-22 26
310.D.RC.D442.B01 AGL Vault D Annex (Roof) - Curing and Removal of formworks C01_7 d/w - 10h/d - No HK 8 05-Aug-22 12-Aug-22 12-Oct-22 19-Oct-22 68
Hols - No B/O periods (was
310.D.RC.D443 AGL Vault D Annex (Roof) - Drainage channel, waterproofing and concrete paving, C1)
C11_6 d/w - 10h/d - With 36 17-Sep-22 31-Oct-22 20-Oct-22 30-Nov-22 26
painting and fall restraint system HK Hols - No B/O periods
External Wall Finishes (was C3) 76 0 05-Aug-22 04-Nov-22 28-Oct-22 17-Dec-22 37
310.D.RC.D603.37.B01AGL Vault D Annex (External Wall) - Curing and Removal of formworks C01_7 d/w - 10h/d - No HK 8 05-Aug-22 12-Aug-22 28-Oct-22 04-Nov-22 84
Hols - No B/O periods (was
310.D.RC.D603.05.B01AGL Vault D Annex (External Wall) - Erect Scaffolding for external Wall C1)
C11_6 d/w - 10h/d - With 5 13-Aug-22 18-Aug-22 05-Nov-22 10-Nov-22 69
HK Hols - No B/O periods
310.D.RC.D603.17.B01AGL Vault D Annex (External Wall) - External rendering, Installation of cladding, cat (was
C11_6C3)
d/w - 10h/d - With 25 27-Sep-22 27-Oct-22 11-Nov-22 09-Dec-22 37
ladder, louvres HK Hols - No B/O periods
310.D.RC.D603.33.B01AGL Vault D Annex (External Wall) - Dismantle Scaffolding & Install door with (was
C11_6C3)
d/w - 10h/d - With 7 28-Oct-22 04-Nov-22 10-Dec-22 17-Dec-22 37
ironmongery HK Hols - No B/O periods
External Works (was
C11_6C3)
d/w - 10h/d - With HK Hols
120- No B/O 0periods (was
19-Aug-22
C3) 11-Jan-23 28-Aug-23 13-Dec-23 274
310.D.RC.D515 AGL Vault D Annex (Drain/UU) - Drainage System + Watermain Works C11_6 d/w - 10h/d - With 30 19-Aug-22 23-Sep-22 28-Aug-23 03-Oct-23 304
HK Hols - No B/O periods
310.D.RC.D515.1.B01 AGL Vault D Annex (Drain/UU) - Cable & System Duct (was
C11_6C3)
d/w - 10h/d - With 30 24-Sep-22 31-Oct-22 04-Oct-23 08-Nov-23 304
HK Hols - No B/O periods
310.D.RC.D603 AGL Vault D Annex - External Works (was
C11_6C3)
d/w - 10h/d - With 60 01-Nov-22 11-Jan-23 04-Oct-23 13-Dec-23 274
HK Hols - No B/O periods
Statutory Inspection (was
C01_7C3)
d/w - 10h/d - No HK Hols107
- No B/O periods
0 (was16-Feb-23
C1) 02-Jun-23 14-Dec-23 14-Jul-24 408
Fire Services Department (FSD) C01_7 d/w - 10h/d - No HK Hols77
- No B/O periods
0 (was16-Feb-23
C1) 03-May-23 14-Dec-23 28-Feb-24 301
310.D.RC.D539 AGL Vault D Annex - Submit FS Statutory Form Submissions for Inspection (FS314, C01_7 d/w - 10h/d - No HK 14 16-Feb-23 01-Mar-23 14-Dec-23 27-Dec-23 301
FS251, FS501) Hols - No B/O periods (was
310.D.RC.D543 AGL Vault D Annex - FS Inspection and defects rectification C1)
C01_7 d/w - 10h/d - No HK 30 14-Mar-23 12-Apr-23 09-Jan-24 07-Feb-24 301
Hols - No B/O periods (was
310.D.RC.D547 AGL Vault D Annex - Obtain FS 172 Certificate C1)
C01_7 d/w - 10h/d - No HK 21 13-Apr-23 03-May-23 08-Feb-24 28-Feb-24 301
Hols - No B/O periods (was
Building Department (BD) C1)
C01_7 d/w - 10h/d - No HK Hols30
- No B/O periods
0 (was04-May-23
C1) 02-Jun-23 29-Feb-24 14-Jul-24 408
310.D.RC.D551 AGL Vault D Annex - BD Inspection + Submit BA13 and Apply for OP to BD C01_7 d/w - 10h/d - No HK 30 04-May-23 02-Jun-23 29-Feb-24 29-Mar-24 301
Hols - No B/O periods (was
310.D.RC.D555 AGL Vault D Annex - BD issued OP certificate C1)
C01_7 d/w - 10h/d - No HK 0 02-Jun-23 29-Mar-24 301
Hols - No B/O periods (was
310.D.RC.D559 AGL Vault D Annex - Achieved KD-10 (Section 3) C1)
C01_7 d/w - 10h/d - No HK 0 02-Jun-23 14-Jul-24 408
Hols - No B/O periods (was
AGL Vault C Annex C1) 661 0 07-Jun-21 A 24-Aug-23 19-Feb-22 14-Jul-24 262
Procurement C01_7 d/w - 10h/d - No HK Hols184
- No B/O periods
0 (was18-May-22
C1) 17-Nov-22 21-Jun-22 22-Aug-23 278
Major Materials ABWF C01_7 d/w - 10h/d - No HK Hols106
- No B/O periods
0 (was04-Aug-22
C1) 17-Nov-22 13-Aug-22 22-Aug-23 278
310.P.RC.D128.3B01 AGL Vault C Annex (Procurement ABWF) - Place order, Manufacturing & Delivery of C01_7 d/w - 10h/d - No HK 45 04-Aug-22 17-Sep-22 13-Aug-22 26-Sep-22 9
Stainless Steel chequered plate at G/F Hols - No B/O periods (was
310.P.RC.D128 AGL Vault C Annex (Procurement ABWF) - Place order, Manufacturing & Delivery of C1)
C01_7 d/w - 10h/d - No HK 45 04-Oct-22 17-Nov-22 09-Jul-23 22-Aug-23 278
louvre (4 nos) Hols - No B/O periods (was
310.P.RC.D128.1B01 AGL Vault C Annex (Procurement ABWF) - Place order, Manufacturing & Delivery of C1)
C01_7 d/w - 10h/d - No HK 45 04-Oct-22 17-Nov-22 09-Jul-23 22-Aug-23 278
Cladding Hols - No B/O periods (was
310.P.RC.D128.2B01 AGL Vault C Annex (Procurement ABWF) - Place order, Manufacturing & Delivery of door C1)
C01_7 d/w - 10h/d - No HK 45 04-Oct-22 17-Nov-22 09-Jul-23 22-Aug-23 278
with ironmongery (Approx 4 Nos) Hols - No B/O periods (was
310.P.RC.D128.4B01 AGL Vault C Annex (Procurement ABWF) - Place order, Manufacturing & Delivery of cat C1)
C01_7 d/w - 10h/d - No HK 45 04-Oct-22 17-Nov-22 09-Jul-23 22-Aug-23 278
ladder (1 no) Hols - No B/O periods (was
310.P.RC.D527 AGL Vault C Annex (Procurement ABWF) -Place order, Manufacturing & Delivery of fall C1)
C01_7 d/w - 10h/d - No HK 45 04-Oct-22 17-Nov-22 21-Nov-22 04-Jan-23 48
restraint system (1 set) Hols - No B/O periods (was
C1)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 214 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
3310.P.RC.D112.B01 AGL Vault C Annex (Procurement ABWF) - Place order, Manufacturing & Delivery of C01_7 d/w - 10h/d - No HK 45 04-Oct-22 17-Nov-22 21-Nov-22 04-Jan-23 48
drainage channel Hols - No B/O periods (was
Major Materials MEP C1)
C01_7 d/w - 10h/d - No HK Hols163
- No B/O periods
0 (was18-May-22
C1) 27-Oct-22 21-Jun-22 31-Oct-22 4
Electrical & MVAC Services C01_7 d/w - 10h/d - No HK Hols103
- No B/O periods
0 (was18-May-22
C1) 28-Aug-22 21-Jul-22 31-Oct-22 64
310.P.RC.D120 AGL Vault C Annex (Procurement Electrical & MVAC Materials) - AC/ ventilation fan, LV & C01_7 d/w - 10h/d - No HK 40 18-May-22 26-Jun-22 21-Jul-22 29-Aug-22 64
Others Place Order Hols - No B/O periods (was
310.P.RC.D535 AGL Vault C Annex (Procurement Electrical & MVAC Materials) - AC/ ventilation fan, LV & C1)
C01_7 d/w - 10h/d - No HK 95 18-May-22 20-Aug-22 21-Jul-22 23-Oct-22 64
Others-Manufacturing of material Hols - No B/O periods (was
310.P.RC.D507 AGL Vault C Annex (Procurement Electrical & MVAC Materials) - Delivery of Materials C1)
C01_7 d/w - 10h/d - No HK 28 31-Jul-22 27-Aug-22 04-Oct-22 31-Oct-22 65
Hols - No B/O periods (was
310.P.RC.D136 AGL Vault C Annex (Procurement Electrical & MVAC Materials) - Delivery of Materials C1)
C01_7 d/w - 10h/d - No HK 14 15-Aug-22 28-Aug-22 18-Oct-22 31-Oct-22 64
(Long Lead Items) Hols - No B/O periods (was
Plumbing & Drainage Services C1)
C01_7 d/w - 10h/d - No HK Hols108
- No B/O periods
0 (was06-Jul-22
C1) 21-Oct-22 16-Jul-22 31-Oct-22 10
310.P.RC.D116 AGL Vault C Annex (Procurement Plumbing & Drainage Materials) - Pipes, valves & C01_7 d/w - 10h/d - No HK 5 06-Jul-22 10-Jul-22 16-Jul-22 20-Jul-22 10
Others - Place Order for Materials Hols - No B/O periods (was
310.P.RC.D531 AGL Vault C Annex (Procurement Plumbing & Drainage Materials) - Pipes, valves & C1)
C01_7 d/w - 10h/d - No HK
95 11-Jul-22 13-Oct-22 21-Jul-22 23-Oct-22 10
Others - Manufacturing of Materials Hols - No B/O periods (was
310.P.RC.D543.B01 AGL Vault C Annex (Procurement Plumbing & Drainage Materials) - Delivery of Materials C1)
C01_7 d/w - 10h/d - No HK 28 23-Sep-22 20-Oct-22 04-Oct-22 31-Oct-22 11
Hols - No B/O periods (was
310.P.RC.D547.B01 AGL Vault C Annex (Procurement Plumbing & Drainage Materials) - Delivery of Materials C1)
C01_7 d/w - 10h/d - No HK 14 08-Oct-22 21-Oct-22 18-Oct-22 31-Oct-22 10
(Long Lead Items) Hols - No B/O periods (was
Fire Services C1)
C01_7 d/w - 10h/d - No HK Hols133
- No B/O periods
0 (was17-Jun-22
C1) 27-Oct-22 21-Jun-22 31-Oct-22 4
310.P.RC.D503 AGL Vault C Annex (Procurement FS Materials) - 1230 system, AC & Others - Place C01_7 d/w - 10h/d - No HK 30 17-Jun-22 16-Jul-22 21-Jun-22 20-Jul-22 4
Order for Materials Hols - No B/O periods (was
310.P.RC.D539 AGL Vault C Annex (Procurement FS Materials) - 1230 system, AC & Others - C1)
C01_7 d/w - 10h/d - No HK 95 17-Jul-22 19-Oct-22 21-Jul-22 23-Oct-22 4
Manufacturing of Materials Hols - No B/O periods (was
310.P.RC.D555.B01 AGL Vault C Annex (Procurement FS Materials) - Delivery of Materials C1)
C01_7 d/w - 10h/d - No HK 28 29-Sep-22 26-Oct-22 04-Oct-22 31-Oct-22 5
Hols - No B/O periods (was
310.P.RC.D559.B01 AGL Vault C Annex (Procurement FS Materials) - Delivery of Materials (Long Lead Items) C1)
C01_7 d/w - 10h/d - No HK 14 14-Oct-22 27-Oct-22 18-Oct-22 31-Oct-22 4
Hols - No B/O periods (was
Construction C1) 572 0 07-Jun-21 A 09-May-23 19-Feb-22 13-Dec-23 181
Initial Works 292 0 07-Jun-21 A 30-May-22 19-Feb-22 24-May-22 -5
310.C.RC.D018 AGL Vault C Annex - Coordination with AA/Other Contractor/AD to grant Site Access + C01_7 d/w - 10h/d - No HK 165 07-Jun-21 A 18-Nov-21 A 19-Feb-22 19-Feb-22
preparation works Hols - No B/O periods (was
310.C.RC.D078.B01 AGL Vault C Annex (Site Prep.) - Method statement for Installation and monitoring @ AGL C1)
C01_7 d/w - 10h/d - No HK 49 16-Nov-21 A 05-Jan-22 A 24-Feb-22 24-Feb-22
Vault C & D Hols - No B/O periods (was
310.C.RC.D030 AGL Vault C Annex (Site Prep.) - carry out condition survey and report C1)
C11_6 d/w - 10h/d - With 10 17-Nov-21 A 08-Dec-21 A 19-Feb-22 19-Feb-22
HK Hols - No B/O periods
310.C.RC.D082.B01 AGL Vault C Annex (Site Prep.) - Review and Acceptance 4th round (was
C01_7C3)
d/w - 10h/d - No HK 29 05-Jan-22 A 14-Feb-22 A 24-Feb-22 24-Feb-22
Hols - No B/O periods (was
310.C.RC.D086.B01 AGL Vault C Annex (Site Prep.) - Application of work permit C1)
C01_7 d/w - 10h/d - No HK 21 05-Jan-22 A 14-Feb-22 A 24-Feb-22 24-Feb-22
Hols - No B/O periods (was
310.C.RC.D022 AGL Vault C Annex (Site Prep.) - site access C1)
C11_6 d/w - 10h/d - With 0 28-Mar-22 19-Feb-22 -31
HK Hols - No B/O periods
310.C.RC.D038 AGL Vault C Annex (Site Prep.) - install Instrumentation (was
C11_6C3)
d/w - 10h/d - With 6 28-Mar-22 02-Apr-22 24-Feb-22 02-Mar-22 -27
HK Hols - No B/O periods
310.C.RC.D034 AGL Vault C Annex (Site Prep.) - carry out UU detection survey and report (was
C11_6C3)
d/w - 10h/d - With 10 28-Mar-22 08-Apr-22 19-Feb-22 02-Mar-22 -31
HK Hols - No B/O periods
310.C.RC.D042 AGL Vault C Annex (Site Prep.) - carry out trial pit (was
C11_6C3)
d/w - 10h/d - With 10 09-Apr-22 23-Apr-22 03-Mar-22 14-Mar-22 -31
HK Hols - No B/O periods
(was C3)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 215 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.RC.D026 AGL Vault C Annex (Site Prep.) - erect hoarding C11_6 d/w - 10h/d - With 7 11-Apr-22 21-Apr-22 17-May-22 24-May-22 27
HK Hols - No B/O periods
310.C.RC.D046 AGL Vault C Annex (Site Prep.) - divert existing UU cables (if any) (was
C11_6C3)
d/w - 10h/d - With 30 25-Apr-22 30-May-22 15-Mar-22 22-Apr-22 -31
HK Hols - No B/O periods
Excavation (was C3) 111 0 20-Jan-22 A 30-Jun-22 09-Apr-22 24-May-22 -31
310.D.RC.D619 AGL Vault C Annex - Submit BA8 consent application C01_7 d/w - 10h/d - No HK 7 20-Jan-22 A 02-Apr-22 09-Apr-22 15-Apr-22 13
Hols - No B/O periods (was
310.D.RC.D623 AGL Vault C Annex - Submit BA10 notice to commencement of work C1)
C01_7 d/w - 10h/d - No HK 7 03-Apr-22 09-Apr-22 16-Apr-22 22-Apr-22 13
Hols - No B/O periods (was
310.C.RC.D050 AGL Vault C Annex (Excavation) - open excavation to from +7.40mPD to +5.525mPD C1)
C11_6 d/w - 10h/d - With 14 31-May-22 16-Jun-22 23-Apr-22 10-May-22 -31
(Qty. 596m3) HK Hols - No B/O periods
310.C.RC.D054 AGL Vault C Annex (Foundation) - plate load test (Qty: 2 nos.) (was
C01_7C3)
d/w - 10h/d - No HK 14 17-Jun-22 30-Jun-22 11-May-22 24-May-22 -37
Hols - No B/O periods (was
Structure C1) 89 0 02-Jul-22 17-Oct-22 25-May-22 07-Sep-22 -31
Foundation C11_6 d/w - 10h/d - With HK Hols
16- No B/O 0periods (was
02-Jul-22
C3) 20-Jul-22 25-May-22 13-Jun-22 -31
310.C.RC.D058 AGL Vault C Annex (Foundation) - Construction of footing (600mm thk) (104m3) C11_6 d/w - 10h/d - With 16 02-Jul-22 20-Jul-22 25-May-22 13-Jun-22 -31
HK Hols - No B/O periods
Screen wall from footing to Ground Floor Slab (was
C11_6C3)
d/w - 10h/d - With HK Hols
46- No B/O 0periods (was
21-Jul-22
C3) 13-Sep-22 14-Jun-22 06-Aug-22 -31
310.C.RC.D062 AGL Vault C Annex (Ground) - construction of upstand/screen wall & column to ground C11_6 d/w - 10h/d - With 18 21-Jul-22 10-Aug-22 14-Jun-22 05-Jul-22 -31
floor with Backfill (62m3) HK Hols - No B/O periods
310.C.RC.D066 AGL Vault C Annex (Roof) - columns, walls to roof (37m3) (was C3)
C11_6 d/w - 10h/d - With 28 11-Aug-22 13-Sep-22 06-Jul-22 06-Aug-22 -31
HK Hols - No B/O periods
UG column/wall to Roof Slab Including parapet wall (was C3) 27 0 14-Sep-22 17-Oct-22 08-Aug-22 07-Sep-22 -31
310.C.RC.D070 AGL Vault C Annex (Roof) - construction of beams and roof slab (98m3) C11_6 d/w - 10h/d - With 21 14-Sep-22 10-Oct-22 08-Aug-22 31-Aug-22 -31
HK Hols - No B/O periods
310.C.RC.D071.B01 AGL Vault C Annex (Roof) - construction parapet roof parapet wall (6m3) (was
C01_7C3)
d/w - 10h/d - No HK 7 11-Oct-22 17-Oct-22 01-Sep-22 07-Sep-22 -40
Hols - No B/O periods (was
ABWF, MEP and T&C C1) 171 0 11-Oct-22 09-May-23 08-Sep-22 13-Dec-23 181
Internal Finishes 77 0 18-Oct-22 17-Jan-23 08-Sep-22 18-Feb-23 25
310.C.RC.D072.B01 AGL Vault C Annex (ABWF/MEP) - curing and removal of falsework C01_7 d/w - 10h/d - No HK 19 18-Oct-22 05-Nov-22 08-Sep-22 26-Sep-22 -40
Hols - No B/O periods (was
310.C.RC.D080 AGL Vault C Annex (ABWF) - commencement C1)
C11_6 d/w - 10h/d - With 0 07-Nov-22 27-Sep-22 -33
HK Hols - No B/O periods
310.C.RC.D084 AGL Vault C Annex (ABWF) - Internal Works - Blockwall (was
C11_6C3)
d/w - 10h/d - With 14 07-Nov-22 22-Nov-22 27-Sep-22 14-Oct-22 -33
HK Hols - No B/O periods
310.D.RC.D669.B01 AGL Vault C Annex (ABWF) - Internal Works - Wall & Ceiling Finishes (was
C11_6C3)
d/w - 10h/d - With 20 23-Nov-22 15-Dec-22 15-Oct-22 07-Nov-22 -33
HK Hols - No B/O periods
310.D.RC.D670.B01 AGL Vault C Annex (ABWF) - Internal Works - Flooring (was
C11_6C3)
d/w - 10h/d - With 20 16-Dec-22 10-Jan-23 30-Nov-22 22-Dec-22 -14
HK Hols - No B/O periods
310.D.RC.D671.B01 AGL Vault C Annex (ABWF) - Internal Works - Metal Works (was
C11_6C3)
d/w - 10h/d - With 6 11-Jan-23 17-Jan-23 13-Feb-23 18-Feb-23 25
HK Hols - No B/O periods
MEP Installation Works (was C3) 120 0 09-Dec-22 09-May-23 01-Nov-22 13-Dec-23 181
Drainage Installation C11_6 d/w - 10h/d - With HK Hols
90- No B/O 0periods (was
09-Dec-22
C3) 29-Mar-23 01-Nov-22 18-Feb-23 -33
310.C.RC.D104.100B02
AGL Vault C Annex - Drainage 1st Fix & Installation C11_6 d/w - 10h/d - With 60 09-Dec-22 22-Feb-23 01-Nov-22 11-Jan-23 -33
HK Hols - No B/O periods
310.C.RC.D104.110B02
AGL Vault C Annex - Drainage 2nd Fix & Installation (was
C11_6C3)
d/w - 10h/d - With 60 10-Jan-23 23-Mar-23 30-Nov-22 13-Feb-23 -33
HK Hols - No B/O periods
310.C.RC.D104.120B02
AGL Vault C Annex - Drainage Final Fix & Adjustment (was
C11_6C3)
d/w - 10h/d - With 5 24-Mar-23 29-Mar-23 14-Feb-23 18-Feb-23 -33
HK Hols - No B/O periods
Electrical Installation (was C3) 120 0 09-Dec-22 09-May-23 01-Nov-22 13-Dec-23 181

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 216 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.RC.D104 AGL Vault C Annex - Electrical 1st Fix & Installation C11_6 d/w - 10h/d - With 60 09-Dec-22 22-Feb-23 01-Nov-22 11-Jan-23 -33
HK Hols - No B/O periods
310.C.RC.D104.140B02
AGL Vault C Annex - Electrical 2nd Fix & Installation (was
C11_6C3)
d/w - 10h/d - With 60 21-Dec-22 06-Mar-23 12-Nov-22 26-Jan-23 -33
HK Hols - No B/O periods
310.C.RC.D104.B01 AGL Vault C Annex - Access Date for Power Supply Installation by Others (was
C11_6C3)
d/w - 10h/d - With 0 23-Feb-23 12-Jan-23 -33
HK Hols - No B/O periods
310.C.RC.D104.150B02
AGL Vault C Annex - Electrical Final Fix & Adjustment (was
C11_6C3)
d/w - 10h/d - With 5 07-Mar-23 11-Mar-23 27-Jan-23 01-Feb-23 -33
HK Hols - No B/O periods
310.C.RC.D192.B01 AGL Vault C Annex (MEP) - Megger Test (was
C11_6C3)
d/w - 10h/d - With 15 13-Mar-23 29-Mar-23 02-Feb-23 18-Feb-23 -33
HK Hols - No B/O periods
310.C.RC.D184 AGL Vault C Annex - Achieved KD-2 (Stage 2) (was
C01_7C3)
d/w - 10h/d - No HK 0 29-Mar-23 18-Feb-23 -39
Hols - No B/O periods (was
310.D.RC.D655 AGL Vault C Annex - Latest Date for Power Supply by Others C1)
C11_6 d/w - 10h/d - With 0 29-Mar-23 18-Feb-23 -33
HK Hols - No B/O periods
310.D.RC.D631 AGL Vault C Annex - System Integration T&C (was
C11_6C3)
d/w - 10h/d - With 30 30-Mar-23 09-May-23 09-Nov-23 13-Dec-23 181
HK Hols - No B/O periods
Fire Services Installation (was
C11_6C3)
d/w - 10h/d - With HK Hols
90- No B/O 0periods (was
09-Dec-22
C3) 29-Mar-23 01-Nov-22 18-Feb-23 -33
310.C.RC.D104.160B02
AGL Vault C Annex - Fire Services 1st Fix & Installation C11_6 d/w - 10h/d - With 60 09-Dec-22 22-Feb-23 01-Nov-22 11-Jan-23 -33
HK Hols - No B/O periods
310.C.RC.D104.170B02
AGL Vault C Annex - Fire Services 2nd Fix & Installation (was
C11_6C3)
d/w - 10h/d - With 60 10-Jan-23 23-Mar-23 30-Nov-22 13-Feb-23 -33
HK Hols - No B/O periods
310.C.RC.D104.180B02
AGL Vault C Annex - Fire Service Final Fix & Adjustment (was
C11_6C3)
d/w - 10h/d - With 5 24-Mar-23 29-Mar-23 14-Feb-23 18-Feb-23 -33
HK Hols - No B/O periods
MVAC Installation (was
C11_6C3)
d/w - 10h/d - With HK Hols
90- No B/O 0periods (was
09-Dec-22
C3) 29-Mar-23 01-Nov-22 18-Feb-23 -33
310.C.RC.D104.190B02
AGL Vault C Annex - MVAC 1st Fix & Installation C11_6 d/w - 10h/d - With 60 09-Dec-22 22-Feb-23 01-Nov-22 11-Jan-23 -33
HK Hols - No B/O periods
310.C.RC.D104.200B02
AGL Vault C Annex - MVAC 2nd Fix & Installation (was
C11_6C3)
d/w - 10h/d - With 60 10-Jan-23 23-Mar-23 30-Nov-22 13-Feb-23 -33
HK Hols - No B/O periods
310.C.RC.D104.210B02
AGL Vault C Annex - MVAC Final Fix & Adjustment (was
C11_6C3)
d/w - 10h/d - With 5 24-Mar-23 29-Mar-23 14-Feb-23 18-Feb-23 -33
HK Hols - No B/O periods
Roof Finishes (was
C11_6C3)
d/w - 10h/d - With HK Hols
63- No B/O 0periods (was
11-Oct-22
C3) 22-Dec-22 17-Dec-22 11-Feb-23 39
310.C.RC.D073.B01 AGL Vault C Annex (Roof) - Curing and removal of formworks C11_6 d/w - 10h/d - With 14 11-Oct-22 26-Oct-22 17-Dec-22 04-Jan-23 58
HK Hols - No B/O periods
310.C.RC.D074 AGL Vault C Annex (Roof) - waterproofing and roof finishes (drainage channel, (was
C11_6C3)
d/w - 10h/d - With 30 18-Nov-22 22-Dec-22 05-Jan-23 11-Feb-23 39
painting,paver, etc) HK Hols - No B/O periods
External Wall Finishes (was C3) 57 0 18-Oct-22 22-Dec-22 08-Aug-23 26-Sep-23 225
310.C.RC.D188.B01 AGL Vault C Annex (External Wall) - Curing and removal of formworks C01_7 d/w - 10h/d - No HK 10 18-Oct-22 27-Oct-22 08-Aug-23 17-Aug-23 294
Hols - No B/O periods (was
310.C.RC.D189.B01 AGL Vault C Annex (External Wall) - Erect scaffolding for external wall C1)
C11_6 d/w - 10h/d - With 4 28-Oct-22 01-Nov-22 18-Aug-23 22-Aug-23 239
HK Hols - No B/O periods
310.C.RC.D190.B01 AGL Vault C Annex (External Wall) - External rendering, Installation of cladding, cat (was
C11_6C3)
d/w - 10h/d - With 24 18-Nov-22 15-Dec-22 23-Aug-23 19-Sep-23 225
ladder, louvres HK Hols - No B/O periods
310.C.RC.D191.B01 AGL Vault C Annex (External Wall) - Dismantle Scaffolding & Install door with (was
C11_6C3)
d/w - 10h/d - With 6 16-Dec-22 22-Dec-22 20-Sep-23 26-Sep-23 225
ironmongery HK Hols - No B/O periods
External Works (was
C11_6C3)
d/w - 10h/d - With HK Hols
108- No B/O 0periods (was
02-Nov-22
C3) 13-Mar-23 26-Aug-23 13-Dec-23 225
310.C.RC.D136 AGL Vault C Annex (Drain/UU) - Drainage System + Watermain Works C11_6 d/w - 10h/d - With 27 02-Nov-22 02-Dec-22 26-Aug-23 26-Sep-23 242
HK Hols - No B/O periods
310.C.RC.D137.B01 AGL Vault C Annex (Drain/UU) - Cable & System duct (was
C11_6C3)
d/w - 10h/d - With 27 23-Dec-22 28-Jan-23 27-Sep-23 31-Oct-23 225
HK Hols - No B/O periods
310.C.RC.D188 AGL Vault C Annex - External Works (was
C11_6C3)
d/w - 10h/d - With 50 11-Jan-23 13-Mar-23 16-Oct-23 13-Dec-23 225
HK Hols - No B/O periods
(was C3)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 217 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
Statutory Inspection C01_7 d/w - 10h/d - No HK Hols107
- No B/O periods
0 (was10-May-23
C1) 24-Aug-23 14-Dec-23 14-Jul-24 325
Fire Services Department (FSD) C01_7 d/w - 10h/d - No HK Hols77
- No B/O periods
0 (was10-May-23
C1) 25-Jul-23 14-Dec-23 28-Feb-24 218
310.C.RC.D164 AGL Vault C Annex - Submit FS Statutory Form Submissions for Inspection (FS314, C01_7 d/w - 10h/d - No HK 14 10-May-23 23-May-23 14-Dec-23 27-Dec-23 218
FS251, FS501) Hols - No B/O periods (was
310.C.RC.D168 AGL Vault C Annex - FS Inspection and defects rectification C1)
C01_7 d/w - 10h/d - No HK 30 05-Jun-23 04-Jul-23 09-Jan-24 07-Feb-24 218
Hols - No B/O periods (was
310.C.RC.D172 AGL Vault C Annex - Obtain FS 172 Certificate C1)
C01_7 d/w - 10h/d - No HK 21 05-Jul-23 25-Jul-23 08-Feb-24 28-Feb-24 218
Hols - No B/O periods (was
Building Department (BD) C1)
C01_7 d/w - 10h/d - No HK Hols30
- No B/O periods
0 (was26-Jul-23
C1) 24-Aug-23 29-Feb-24 14-Jul-24 325
310.C.RC.D176 AGL Vault C Annex - BD Inspection + Submit BA13 and Apply for OP to BD C01_7 d/w - 10h/d - No HK 30 26-Jul-23 24-Aug-23 29-Feb-24 29-Mar-24 218
Hols - No B/O periods (was
310.C.RC.D180 AGL Vault C Annex - BD issued OP certificate C1)
C01_7 d/w - 10h/d - No HK 0 24-Aug-23 29-Mar-24 218
Hols - No B/O periods (was
310.D.RC.D615 AGL Vault C Annex - Achieved KD-10 (Section 3) C1)
C01_7 d/w - 10h/d - No HK 0 24-Aug-23 14-Jul-24 325
Hols - No B/O periods (was
CC#08 ----- Testing and Commissioning ----- C1) 496 33 22-Jul-22 19-Mar-24 09-Sep-22 14-Jul-24 92
ESA - C&ED Operational Office and Kennel Area 283 0 27-Feb-23 07-Feb-24 13-Apr-23 17-Feb-24 7
Testing and Commissioning 283 0 27-Feb-23 07-Feb-24 13-Apr-23 17-Feb-24 7
Preliminary Testing and Commissioning C11_6 d/w - 10h/d - With HK Hols
51- No B/O 0periods (was
07-Sep-23
C3) 08-Nov-23 15-Sep-23 25-Jan-24 64
Preliminary T&C - Plumbing and Drainage C11_6 d/w - 10h/d - With HK Hols
28- No B/O 0periods (was
08-Sep-23
C3) 12-Oct-23 15-Sep-23 19-Oct-23 6
310.C.EX.W1604 C&ED Op. Office & Kennel Area - Plumbing & Drainage Preliminary Inspection & C11_6 d/w - 10h/d - With 18 08-Sep-23 28-Sep-23 15-Sep-23 07-Oct-23 6
Adjustment HK Hols - No B/O periods
310.C.EX.W1608 C&ED Op. Office & Kennel Area - Plumbing & Drainage Preliminary Testing & (was
C11_6C3)
d/w - 10h/d - With 18 20-Sep-23 12-Oct-23 27-Sep-23 19-Oct-23 6
Commissioning HK Hols - No B/O periods
Preliminary T&C - Electrical (was
C11_6C3)
d/w - 10h/d - With HK Hols
28- No B/O 0periods (was
29-Sep-23
C3) 03-Nov-23 13-Oct-23 25-Jan-24 68
310.C.EX.W1520 C&ED Op. Office & Kennel Area - Electrical Preliminary Inspection & Adjustment C11_6 d/w - 10h/d - With 18 29-Sep-23 21-Oct-23 13-Oct-23 03-Nov-23 10
HK Hols - No B/O periods
310.C.EX.W2481.B02 C&ED Op. Office & Kennel Area - Electrical Preliminary Inspection & Adjustment (was
C11_6C3)
d/w - 10h/d - With 18 29-Sep-23 21-Oct-23 21-Dec-23 13-Jan-24 68
(Non-FSI) HK Hols - No B/O periods
310.C.EX.W1524 C&ED Op. Office & Kennel Area - Electrical Preliminary Testing & Commissioning (was
C11_6C3)
d/w - 10h/d - With 18 13-Oct-23 03-Nov-23 26-Oct-23 15-Nov-23 10
HK Hols - No B/O periods
310.C.EX.W2486.B02 C&ED Op. Office & Kennel Area - Electrical Preliminary Testing & Commissioning (was
C11_6C3)
d/w - 10h/d - With 18 13-Oct-23 03-Nov-23 05-Jan-24 25-Jan-24 68
(Non-FSI) HK Hols - No B/O periods
Preliminary T&C - Fire Services (was
C11_6C3)
d/w - 10h/d - With HK Hols
28- No B/O 0periods (was
06-Oct-23
C3) 08-Nov-23 20-Oct-23 22-Nov-23 12
310.C.EX.W1544 C&ED Op. Office & Kennel Area - Fire Services Preliminary Inspection & Adjustment (FSI) C11_6 d/w - 10h/d - With 18 06-Oct-23 27-Oct-23 20-Oct-23 10-Nov-23 12
HK Hols - No B/O periods
310.C.EX.W2480.B01 C&ED Op. Office & Kennel Area - Fire Services Preliminary Inspection & Adjustment (was
C11_6C3)
d/w - 10h/d - With 18 06-Oct-23 27-Oct-23 20-Oct-23 10-Nov-23 12
(Non-FSI) HK Hols - No B/O periods
310.C.EX.W1548 C&ED Op. Office & Kennel Area - Fire Services Preliminary Testing & Commissioning (was
C11_6C3)
d/w - 10h/d - With 18 18-Oct-23 08-Nov-23 02-Nov-23 22-Nov-23 12
(FSI) HK Hols - No B/O periods
310.C.EX.W2484.B01 C&ED Op. Office & Kennel Area - Fire Services Preliminary Testing & Commissioning (was
C11_6C3)
d/w - 10h/d - With 18 18-Oct-23 08-Nov-23 02-Nov-23 22-Nov-23 12
(Non-FSI) HK Hols - No B/O periods
Preliminary T&C - MVAC (was
C11_6C3)
d/w - 10h/d - With HK Hols
28- No B/O 0periods (was
07-Sep-23
C3) 11-Oct-23 12-Oct-23 14-Nov-23 28
310.C.EX.W1564 C&ED Op. Office & Kennel Area - MVAC Preliminary Inspection & Adjustment C11_6 d/w - 10h/d - With 18 07-Sep-23 27-Sep-23 12-Oct-23 02-Nov-23 28
HK Hols - No B/O periods
310.C.EX.W1568 C&ED Op. Office & Kennel Area - MVAC Preliminary Testing & Commissioning (was
C11_6C3)
d/w - 10h/d - With 18 19-Sep-23 11-Oct-23 25-Oct-23 14-Nov-23 28
HK Hols - No B/O periods
Testing and Commissioning (was
C01_7C3)
d/w - 10h/d - No HK Hols62
- No B/O periods
0 (was16-Oct-23
C1) 17-Dec-23 27-Oct-23 25-Jan-24 39
310.T.EX.L496 Completion of CLP Cable Laying & Power Energization of PBA C01_7 d/w - 10h/d - No HK 0 16-Oct-23 27-Oct-23 11
Hols - No B/O periods (was
C1)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 218 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.T.EX.L276 C&ED Operational Office and Kennel Area - Ventilation System Test C01_7 d/w - 10h/d - No HK 21 19-Oct-23 08-Nov-23 22-Nov-23 12-Dec-23 34
Hols - No B/O periods (was
310.T.EX.L288 C&ED Operational Office and Kennel Area - Plumbing System Test C1)
C01_7 d/w - 10h/d - No HK 21 20-Oct-23 09-Nov-23 28-Oct-23 17-Nov-23 8
Hols - No B/O periods (was
310.T.EX.L272 C&ED Operational Office and Kennel Area - FS System Test (FSI) C1)
C01_7 d/w - 10h/d - No HK 21 18-Nov-23 08-Dec-23 30-Nov-23 20-Dec-23 12
Hols - No B/O periods (was
310.T.EX.L280.B01 C&ED Operational Office and Kennel Area - FS System Test (Non-FSI) C1)
C01_7 d/w - 10h/d - No HK 21 18-Nov-23 08-Dec-23 05-Jan-24 25-Jan-24 48
Hols - No B/O periods (was
310.T.EX.L284 C&ED Operational Office and Kennel Area - Systems Integration Test C1)
C01_7 d/w - 10h/d - No HK 30 18-Nov-23 17-Dec-23 13-Dec-23 11-Jan-24 25
Hols - No B/O periods (was
Statutory Inspection C1) 283 0 27-Feb-23 07-Feb-24 13-Apr-23 17-Feb-24 7
Water Supply Department (WSD) C11_6 d/w - 10h/d - With HK Hols
237- No B/O 0periods (was
27-Feb-23
C3) 12-Dec-23 13-Apr-23 20-Dec-23 7
310.T.ES.T100 C&ED Operational Office and Kennel Area - Prepare for Plumbing Material for Submission C11_6 d/w - 10h/d - With 17 27-Feb-23 17-Mar-23 13-Apr-23 03-May-23 35
HK Hols - No B/O periods
310.T.ES.T105 C&ED Operational Office and Kennel Area - Submit all Plumbing Material for PM (was
C11_6C3)
d/w - 10h/d - With 0 18-Mar-23 04-May-23 35
Acceptance HK Hols - No B/O periods
310.T.ES.T110 C&ED Operational Office and Kennel Area - PM Acceptance (was
C11_6C3)
d/w - 10h/d - With 48 18-Mar-23 18-May-23 04-May-23 30-Jun-23 35
HK Hols - No B/O periods
310.T.ES.T115 C&ED Operational Office and Kennel Area - Form WWO 46 (Part1&2)&Annex Submission (was
C11_6C3)
d/w - 10h/d - With 0 19-May-23 03-Jul-23 35
for WSD Approval (Plumbing / FS / WP) HK Hols - No B/O periods
310.T.ES.T120 C&ED Operational Office and Kennel Area -Obtain Form WWO 46 (Part III)-WSD (was
C11_6C3)
d/w - 10h/d - With 4 19-May-23 23-May-23 03-Jul-23 06-Jul-23 35
Approval, Endorsed&Return to Licensed Plumber HK Hols - No B/O periods
310.T.ES.T125 C&ED Operational Office and Kennel Area - Form WWO 46 (Part IV) Submission for WSD (was
C11_6C3)
d/w - 10h/d - With 0 10-Nov-23 18-Nov-23 7
Inspection (Plumbing / FS / WP) HK Hols - No B/O periods
310.T.ES.T130 C&ED Operational Office and Kennel Area - WSD Inspection for Water Supply System (was
C11_6C3)
d/w - 10h/d - With 14 18-Nov-23 04-Dec-23 27-Nov-23 12-Dec-23 7
HK Hols - No B/O periods
310.T.ES.T135 C&ED Operational Office and Kennel Area - Obtain Form WWO 46 (Part V) (was
C11_6C3)
d/w - 10h/d - With 0 04-Dec-23 12-Dec-23 7
HK Hols - No B/O periods
310.T.ES.T140 C&ED Operational Office and Kennel Area - Form WWO 132 (Part II) Submission for (was
C11_6C3)
d/w - 10h/d - With 0 04-Dec-23 12-Dec-23 7
Water Supply Connection HK Hols - No B/O periods
310.T.ES.T145 C&ED Operational Office and Kennel Area - Final Water Supply Connection (was
C11_6C3)
d/w - 10h/d - With 7 05-Dec-23 12-Dec-23 13-Dec-23 20-Dec-23 7
HK Hols - No B/O periods
310.T.ES.T150 C&ED Operational Office and Kennel Area - Obtain Water Certificate (Form WWO 1005) (was
C11_6C3)
d/w - 10h/d - With 0 12-Dec-23 20-Dec-23 7
HK Hols - No B/O periods
Fire Services Department (FSD) (was
C11_6C3)
d/w - 10h/d - With HK Hols
31- No B/O 0periods (was
09-Dec-23
C3) 17-Jan-24 21-Dec-23 25-Jan-24 7
310.T.ES.T155 C&ED Operational Office and Kennel Area - F.S. Inspection Plan (Form FSI / 314 C11_6 d/w - 10h/d - With 0 09-Dec-23 21-Dec-23 10
Submission) HK Hols - No B/O periods
310.T.ES.T160 C&ED Operational Office and Kennel Area - F.S. Inspection Application (Form FSI / 501 & (was
C11_6C3)
d/w - 10h/d - With 0 13-Dec-23 21-Dec-23 7
251 Submission) HK Hols - No B/O periods
310.T.ES.T165 C&ED Operational Office and Kennel Area - F.S. 1st Inspection (was
C11_6C3)
d/w - 10h/d - With 6 27-Dec-23 03-Jan-24 05-Jan-24 11-Jan-24 7
HK Hols - No B/O periods
310.T.ES.T170 C&ED Operational Office and Kennel Area - FSD Comment (was
C11_6C3)
d/w - 10h/d - With 0 03-Jan-24 11-Jan-24 7
HK Hols - No B/O periods
310.T.ES.T175 C&ED Operational Office and Kennel Area - Rectification & Adjustment (was
C11_6C3)
d/w - 10h/d - With 6 04-Jan-24 10-Jan-24 12-Jan-24 18-Jan-24 7
HK Hols - No B/O periods
310.T.ES.T180 C&ED Operational Office and Kennel Area - F.S. Re-inspection (was
C11_6C3)
d/w - 10h/d - With 6 11-Jan-24 17-Jan-24 19-Jan-24 25-Jan-24 7
HK Hols - No B/O periods
310.T.ES.T185 C&ED Operational Office and Kennel Area - Issue F.S. Certificate (Form FS172) (was
C11_6C3)
d/w - 10h/d - With 0 17-Jan-24 25-Jan-24 7
HK Hols - No B/O periods
Building Department (BD) (was C3) 18 0 18-Jan-24 07-Feb-24 26-Jan-24 17-Feb-24 7

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 219 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.T.ES.T190 C&ED Operational Office and Kennel Area - BD Inspection Application for Occupation C11_6 d/w - 10h/d - With 0 18-Jan-24 26-Jan-24 7
Permit (Form BA13 Submission) HK Hols - No B/O periods
310.T.ES.T195 C&ED Operational Office and Kennel Area - BD 1st Inspection (was
C11_6C3)
d/w - 10h/d - With 6 18-Jan-24 24-Jan-24 26-Jan-24 01-Feb-24 7
HK Hols - No B/O periods
310.T.ES.T200 C&ED Operational Office and Kennel Area - BD Comment (was
C11_6C3)
d/w - 10h/d - With 0 24-Jan-24 01-Feb-24 7
HK Hols - No B/O periods
310.T.ES.T205 C&ED Operational Office and Kennel Area - Rectification & Adjustment (was
C11_6C3)
d/w - 10h/d - With 6 25-Jan-24 31-Jan-24 02-Feb-24 08-Feb-24 7
HK Hols - No B/O periods
310.T.ES.T210 C&ED Operational Office and Kennel Area - BD Re-inspection (was
C11_6C3)
d/w - 10h/d - With 6 01-Feb-24 07-Feb-24 09-Feb-24 17-Feb-24 7
HK Hols - No B/O periods
310.T.ES.M040 Achieved KD-G4 and Allow Other Contractor to Commence their works (was
C01_7C3)
d/w - 10h/d - No HK 0 07-Feb-24 17-Feb-24 10
Hols - No B/O periods (was
310.T.ES.T215 C&ED Operational Office and Kennel Area - Issue Occupation Permit (Form BD104) C1)
C11_6 d/w - 10h/d - With 0 07-Feb-24 17-Feb-24 7
HK Hols - No B/O periods
WSA - Comm. Equipment Building D (was C3) 192 0 11-Aug-22 31-Mar-23 09-Sep-22 13-Jul-24 379
Testing and Commissioning 192 0 11-Aug-22 31-Mar-23 09-Sep-22 13-Jul-24 379
Preliminary Testing and Commissioning C11_6 d/w - 10h/d - With HK Hols
28- No B/O 0periods (was
08-Dec-22
C3) 11-Jan-23 14-Dec-22 11-Mar-23 48
Preliminary T&C - Drainage C11_6 d/w - 10h/d - With HK Hols
18- No B/O 0periods (was
13-Dec-22
C3) 04-Jan-23 14-Dec-22 05-Jan-23 1
310.C.EX.W1768 WSA - Comm Eqpt Bldg D - Drainage Preliminary Inspection & Adjustment C11_6 d/w - 10h/d - With 14 13-Dec-22 29-Dec-22 14-Dec-22 30-Dec-22 1
HK Hols - No B/O periods
310.C.EX.W1772 WSA - Comm Eqpt Bldg D - Drainage Preliminary Testing & Commissioning (was C3)
C11_6 d/w - 10h/d - With 14 17-Dec-22 04-Jan-23 19-Dec-22 05-Jan-23 1
HK Hols - No B/O periods
Preliminary T&C - Electrical (was
C11_6C3)
d/w - 10h/d - With HK Hols
22- No B/O 0periods (was
15-Dec-22
C3) 11-Jan-23 22-Dec-22 11-Mar-23 48
310.C.EX.W2482.B02 WSA - Comm Eqpt Bldg D - Electrical Preliminary Inspection & Adjustment (Non-FSI) C11_6 d/w - 10h/d - With 14 15-Dec-22 31-Dec-22 20-Feb-23 07-Mar-23 52
HK Hols - No B/O periods
310.C.EX.W1684 WSA - Comm Eqpt Bldg D - Electrical Preliminary Inspection & Adjustment (was
C11_6C3)
d/w - 10h/d - With 14 20-Dec-22 06-Jan-23 22-Dec-22 09-Jan-23 2
HK Hols - No B/O periods
310.C.EX.W2487.B02 WSA - Comm Eqpt Bldg D - Electrical Preliminary Testing & Commissioning (Non-FSI) (was
C11_6C3)
d/w - 10h/d - With 14 20-Dec-22 06-Jan-23 24-Feb-23 11-Mar-23 52
HK Hols - No B/O periods
310.C.EX.W1688 WSA - Comm Eqpt Bldg D - Electrical Preliminary Testing & Commissioning (was
C11_6C3)
d/w - 10h/d - With 14 24-Dec-22 11-Jan-23 28-Dec-22 13-Jan-23 2
HK Hols - No B/O periods
Preliminary T&C - Fire Services (was
C11_6C3)
d/w - 10h/d - With HK Hols
18- No B/O 0periods (was
08-Dec-22
C3) 29-Dec-22 22-Dec-22 13-Jan-23 12
310.C.EX.W1708 WSA - Comm Eqpt Bldg D - Fire Services Preliminary Inspection & Adjustment (FSI)
C11_6 d/w - 10h/d - With 14 08-Dec-22 23-Dec-22 22-Dec-22 09-Jan-23 12
HK Hols - No B/O periods
310.C.EX.W1709.B01 WSA - Comm Eqpt Bldg D - Fire Services Preliminary Inspection & Adjustment (Non-FSI) (was
C11_6C3)
d/w - 10h/d - With 14 08-Dec-22 23-Dec-22 22-Dec-22 09-Jan-23 12
HK Hols - No B/O periods
310.C.EX.W1712 WSA - Comm Eqpt Bldg D - Fire Services Preliminary Testing & Commissioning (FSI) (was
C11_6C3)
d/w - 10h/d - With 14 13-Dec-22 29-Dec-22 28-Dec-22 13-Jan-23 12
HK Hols - No B/O periods
310.C.EX.W1713.B01 WSA - Comm Eqpt Bldg D - Fire Services Preliminary Testing & Commissioning (was
C11_6C3)
d/w - 10h/d - With 14 13-Dec-22 29-Dec-22 28-Dec-22 13-Jan-23 12
(Non-FSI) HK Hols - No B/O periods
Preliminary T&C - MVAC (was
C11_6C3)
d/w - 10h/d - With HK Hols
18- No B/O 0periods (was
08-Dec-22
C3) 29-Dec-22 06-Jan-23 30-Jan-23 23
310.C.EX.W1728 WSA - Comm Eqpt Bldg D - MVAC Preliminary Inspection & Adjustment C11_6 d/w - 10h/d - With 14 08-Dec-22 23-Dec-22 06-Jan-23 21-Jan-23 23
HK Hols - No B/O periods
310.C.EX.W1732 WSA - Comm Eqpt Bldg D - MVAC Preliminary Testing & Commissioning (was
C11_6C3)
d/w - 10h/d - With 14 13-Dec-22 29-Dec-22 11-Jan-23 30-Jan-23 23
HK Hols - No B/O periods
Testing and Commissioning (was C3)
C01_7 d/w - 10h/d - No HK Hols26
- No B/O periods
0 (was06-Jan-23
C1) 31-Jan-23 20-Jan-23 12-Mar-23 40
310.T.EX.L296 WSA - Comm. Equipment Building D - Ventilation System Test C01_7 d/w - 10h/d - No HK 14 06-Jan-23 19-Jan-23 06-Feb-23 19-Feb-23 31
Hols - No B/O periods (was
310.T.EX.L292 WSA - Comm. Equipment Building D - FS System Test (FSI) C1)
C01_7 d/w - 10h/d - No HK 14 18-Jan-23 31-Jan-23 20-Jan-23 02-Feb-23 2
Hols - No B/O periods (was
C1)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 220 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.T.EX.L304 WSA - Comm. Equipment Building D - Systems Integration Test C01_7 d/w - 10h/d - No HK 14 18-Jan-23 31-Jan-23 06-Feb-23 19-Feb-23 19
Hols - No B/O periods (was
310.T.EX.L300.B01 WSA - Comm. Equipment Building D - FS System Test (Non-FSI) C1)
C01_7 d/w - 10h/d - No HK 14 18-Jan-23 31-Jan-23 27-Feb-23 12-Mar-23 40
Hols - No B/O periods (was
Statutory Inspection C1) 192 0 11-Aug-22 31-Mar-23 09-Sep-22 13-Jul-24 379
Water Supply Department (WSD) C11_6 d/w - 10h/d - With HK Hols
142- No B/O 0periods (was
11-Aug-22
C3) 01-Feb-23 09-Sep-22 02-Feb-23 1
310.T.ES.T443.B01 WSA - Comm. Equipment Building D - Prepare for Plumbing Material for Submission C11_6 d/w - 10h/d - With 17 11-Aug-22 30-Aug-22 09-Sep-22 29-Sep-22 25
HK Hols - No B/O periods
310.T.ES.T447.B01 WSA - Comm. Equipment Building D - Submit all Plumbing Material for PM Acceptance (was
C11_6C3)
d/w - 10h/d - With 0 31-Aug-22 30-Sep-22 25
HK Hols - No B/O periods
310.T.ES.T451.B01 WSA - Comm. Equipment Building D - PM Acceptance (was
C11_6C3)
d/w - 10h/d - With 28 31-Aug-22 05-Oct-22 30-Sep-22 03-Nov-22 25
HK Hols - No B/O periods
310.T.ES.T455.B01 WSA - Comm. Equipment Building D - Form WWO 46 (Part I & Part II) & Annex (was
C11_6C3)
d/w - 10h/d - With 0 06-Oct-22 04-Nov-22 25
Submission for WSD Approval (Plumbing / FS / W HK Hols - No B/O periods
310.T.ES.T459.B01 WSA - Comm. Equipment Building D - Obtain Form WWO 46 (Part III) - WSD Approval, (was
C11_6C3)
d/w - 10h/d - With 4 06-Oct-22 10-Oct-22 04-Nov-22 08-Nov-22 25
Endorsed & Return to Licensed Plumber HK Hols - No B/O periods
310.T.ES.T419.B01 WSA - Comm. Equipment Building D - Form WWO 46 (Part IV) Submission for WSD (was
C11_6C3)
d/w - 10h/d - With 0 11-Jan-23 12-Jan-23 1
Inspection (Plumbing / FS / WP) HK Hols - No B/O periods
310.T.ES.T423.B01 WSA - Comm. Equipment Building D - WSD Inspection for Water Supply System (was
C11_6C3)
d/w - 10h/d - With 6 19-Jan-23 28-Jan-23 20-Jan-23 30-Jan-23 1
HK Hols - No B/O periods
310.T.ES.T427.B01 WSA - Comm. Equipment Building D - Obtain Form WWO 46 (Part V) (was
C11_6C3)
d/w - 10h/d - With 0 28-Jan-23 30-Jan-23 1
HK Hols - No B/O periods
310.T.ES.T431.B01 WSA - Comm. Equipment Building D - Form WWO 132 (Part II) Submission for Water (was
C11_6C3)
d/w - 10h/d - With 0 28-Jan-23 30-Jan-23 1
Supply Connection HK Hols - No B/O periods
310.T.ES.T435.B01 WSA - Comm. Equipment Building D - Final Water Supply Connection (was
C11_6C3)
d/w - 10h/d - With 3 30-Jan-23 01-Feb-23 31-Jan-23 02-Feb-23 1
HK Hols - No B/O periods
310.T.ES.T439.B01 WSA - Comm. Equipment Building D - Obtain Water Certificate (Form WWO 1005) (was
C11_6C3)
d/w - 10h/d - With 0 01-Feb-23 02-Feb-23 1
HK Hols - No B/O periods
Fire Services Department (FSD) (was
C11_6C3)
d/w - 10h/d - With HK Hols
50- No B/O 0periods (was
09-Jan-23
C3) 10-Mar-23 03-Feb-23 11-Mar-23 1
310.T.WS.T455 WSA - Comm. Equipment Building D - F.S. Inspection Plan (Form FSI / 314 Submission) C11_6 d/w - 10h/d - With 0 09-Jan-23 03-Feb-23 19
HK Hols - No B/O periods
310.T.WS.T460 WSA - Comm. Equipment Building D - F.S. Inspection Application (Form FSI / 501 & 251 (was
C11_6C3)
d/w - 10h/d - With 0 02-Feb-23 03-Feb-23 1
Submission) HK Hols - No B/O periods
310.T.WS.T465 WSA - Comm. Equipment Building D - F.S. 1st Inspection (was
C11_6C3)
d/w - 10h/d - With 6 18-Feb-23 24-Feb-23 20-Feb-23 25-Feb-23 1
HK Hols - No B/O periods
310.T.WS.T470 WSA - Comm. Equipment Building D - FSD Comment (was
C11_6C3)
d/w - 10h/d - With 0 24-Feb-23 25-Feb-23 1
HK Hols - No B/O periods
310.T.WS.T475 WSA - Comm. Equipment Building D - Rectification & Adjustment (was
C11_6C3)
d/w - 10h/d - With 6 25-Feb-23 03-Mar-23 27-Feb-23 04-Mar-23 1
HK Hols - No B/O periods
310.T.WS.T480 WSA - Comm. Equipment Building D - F.S. Re-inspection (was
C11_6C3)
d/w - 10h/d - With 6 04-Mar-23 10-Mar-23 06-Mar-23 11-Mar-23 1
HK Hols - No B/O periods
310.T.WS.T485 WSA - Comm. Equipment Building D - Issue F.S. Certificate (Form FS172) (was
C11_6C3)
d/w - 10h/d - With 0 10-Mar-23 11-Mar-23 1
HK Hols - No B/O periods
Building Department (BD) (was C3) 18 0 11-Mar-23 31-Mar-23 13-Mar-23 13-Jul-24 379
310.T.WS.T490 WSA - Comm. Equipment Building D - BD Inspection Application for Occupation Permit C11_6 d/w - 10h/d - With 0 11-Mar-23 13-Mar-23 1
(Form BA13 Submission) HK Hols - No B/O periods
310.T.WS.T495 WSA - Comm. Equipment Building D - BD 1st Inspection (was
C11_6C3)
d/w - 10h/d - With 6 11-Mar-23 17-Mar-23 13-Mar-23 18-Mar-23 1
HK Hols - No B/O periods
310.T.WS.T500 WSA - Comm. Equipment Building D - BD Comment (was
C11_6C3)
d/w - 10h/d - With 0 17-Mar-23 18-Mar-23 1
HK Hols - No B/O periods
(was C3)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 221 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.T.WS.T505 WSA - Comm. Equipment Building D - Rectification & Adjustment C11_6 d/w - 10h/d - With 6 18-Mar-23 24-Mar-23 20-Mar-23 25-Mar-23 1
HK Hols - No B/O periods
310.T.WS.T510 WSA - Comm. Equipment Building D - BD Re-inspection (was
C11_6C3)
d/w - 10h/d - With 6 25-Mar-23 31-Mar-23 27-Mar-23 01-Apr-23 1
HK Hols - No B/O periods
310.T.WS.M540 WSA - Comm Eqpt Bldg D (T&C) - Achieved MS 26 (was
C01_7C3)
d/w - 10h/d - No HK 0 31-Mar-23 02-Apr-23 2
Hols - No B/O periods (was
310.T.WS.M543 Achieved KD-10 Completion of Communication Equipment Bldg D incl T&C C1)
C01_7 d/w - 10h/d - No HK 0 31-Mar-23 13-Jul-24 470
Hols - No B/O periods (was
310.T.WS.T515 WSA - Comm. Equipment Building D - Issue Occupation Permit (Form BD104) C1)
C11_6 d/w - 10h/d - With 0 31-Mar-23 01-Apr-23 1
HK Hols - No B/O periods
ESA - GSE Vehicle Wash Facility (was C3) 160 0 22-Aug-22 04-Mar-23 16-Sep-22 13-Jul-24 402
Testing and Commissioning 160 0 22-Aug-22 04-Mar-23 16-Sep-22 13-Jul-24 402
Preliminary Testing and Commissioning C11_6 d/w - 10h/d - With HK Hols
28- No B/O 0periods (was
10-Dec-22
C3) 13-Jan-23 10-Dec-22 13-Jan-23 0
Preliminary T&C - Plumbing and Drainage C11_6 d/w - 10h/d - With HK Hols
12- No B/O 0periods (was
10-Dec-22
C3) 23-Dec-22 10-Dec-22 23-Dec-22 0
310.C.EX.W1916 ESA - GSE Wash Facility - Plumbing & Drainage Preliminary Inspection & Adjustment C11_6 d/w - 10h/d - With 8 10-Dec-22 19-Dec-22 10-Dec-22 19-Dec-22 0
HK Hols - No B/O periods
310.C.EX.W1920 ESA - GSE Wash Facility - Plumbing & Drainage Preliminary Testing & Commissioning (was
C11_6C3)
d/w - 10h/d - With 8 15-Dec-22 23-Dec-22 15-Dec-22 23-Dec-22 0
HK Hols - No B/O periods
Preliminary T&C - Electrical (was
C11_6C3)
d/w - 10h/d - With HK Hols
16- No B/O 0periods (was
24-Dec-22
C3) 13-Jan-23 24-Dec-22 13-Jan-23 0
310.C.EX.W1848 ESA - GSE Wash Facility - Electrical Preliminary Inspection & Adjustment C11_6 d/w - 10h/d - With 10 24-Dec-22 06-Jan-23 24-Dec-22 06-Jan-23 0
HK Hols - No B/O periods
310.C.EX.W1852 ESA - GSE Wash Facility - Electrical Testing & Commissioning (was
C11_6C3)
d/w - 10h/d - With 10 03-Jan-23 13-Jan-23 03-Jan-23 13-Jan-23 0
HK Hols - No B/O periods
Preliminary T&C - Fire Services (was
C11_6C3)
d/w - 10h/d - With HK Hols
16- No B/O 0periods (was
22-Dec-22
C3) 11-Jan-23 24-Dec-22 13-Jan-23 2
310.C.EX.W1872 ESA - GSE Wash Facility - Fire Services Preliminary Inspection & Adjustment (FSI) C11_6 d/w - 10h/d - With 10 22-Dec-22 04-Jan-23 24-Dec-22 06-Jan-23 2
HK Hols - No B/O periods
310.C.EX.W1873.B01 ESA - GSE Wash Facility - Fire Services Preliminary Inspection & Adjustment (Non-FSI) (was
C11_6C3)
d/w - 10h/d - With 10 22-Dec-22 04-Jan-23 24-Dec-22 06-Jan-23 2
HK Hols - No B/O periods
310.C.EX.W1876 ESA - GSE Wash Facility - Fire Services Preliminary Testing & Commissioning (FSI) (was
C11_6C3)
d/w - 10h/d - With
10 30-Dec-22 11-Jan-23 03-Jan-23 13-Jan-23 2
HK Hols - No B/O periods
310.C.EX.W1877.B01 ESA - GSE Wash Facility - Fire Services Preliminary Testing & Commissioning (Non-FSI) (was
C11_6C3)
d/w - 10h/d - With 10 30-Dec-22 11-Jan-23 03-Jan-23 13-Jan-23 2
HK Hols - No B/O periods
Testing and Commissioning (was
C01_7C3)
d/w - 10h/d - No HK Hols30
- No B/O periods
0 (was31-Dec-22
C1) 29-Jan-23 31-Dec-22 15-Feb-23 17
310.T.EX.L328 ESA - GSE Vehicle Wash Facility - Plumbing System Test C01_7 d/w - 10h/d - No HK 7 31-Dec-22 06-Jan-23 31-Dec-22 06-Jan-23 0
Hols - No B/O periods (was
310.T.EX.L312 ESA - GSE Vehicle Wash Facility - FS System Test (FSI) C1)
C01_7 d/w - 10h/d - No HK 10 20-Jan-23 29-Jan-23 20-Jan-23 29-Jan-23 0
Hols - No B/O periods (was
310.T.EX.L316.B01 ESA - GSE Vehicle Wash Facility - FS System Test (Non-FSI) C1)
C01_7 d/w - 10h/d - No HK 10 20-Jan-23 29-Jan-23 06-Feb-23 15-Feb-23 17
Hols - No B/O periods (was
Statutory Inspection C1) 160 0 22-Aug-22 04-Mar-23 16-Sep-22 13-Jul-24 402
Water Supply Department (WSD) C11_6 d/w - 10h/d - With HK Hols
130- No B/O 0periods (was
22-Aug-22
C3) 28-Jan-23 16-Sep-22 28-Jan-23 0
310.T.ES.T300 ESA - GSE Vehicle Wash Facility - Prepare for Plumbing Material for Submission C11_6 d/w - 10h/d - With 17 22-Aug-22 09-Sep-22 16-Sep-22 07-Oct-22 21
HK Hols - No B/O periods
310.T.ES.T305 ESA - GSE Vehicle Wash Facility - Submit all Plumbing Material for PM Acceptance (was
C11_6C3)
d/w - 10h/d - With 0 12-Sep-22 08-Oct-22 21
HK Hols - No B/O periods
310.T.ES.T310 ESA - GSE Vehicle Wash Facility - PM Acceptance (was
C11_6C3)
d/w - 10h/d - With 28 12-Sep-22 15-Oct-22 08-Oct-22 09-Nov-22 21
HK Hols - No B/O periods
310.T.ES.T315 ESA - GSE Vehicle Wash Facility - Form WWO 46 (Part I & Part II) & Annex Submission (was
C11_6C3)
d/w - 10h/d - With 0 17-Oct-22 10-Nov-22 21
for WSD Approval (Plumbing / FS / WP HK Hols - No B/O periods
310.T.ES.T320 ESA - GSE Vehicle Wash Facility - Obtain Form WWO 46 (Part III) - WSD Approval, (was
C11_6C3)
d/w - 10h/d - With 4 17-Oct-22 20-Oct-22 10-Nov-22 14-Nov-22 21
Endorsed & Return to Licensed Plumber HK Hols - No B/O periods
(was C3)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 222 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.T.ES.T325 ESA - GSE Vehicle Wash Facility - Form WWO 46 (Part IV) Submission for WSD C11_6 d/w - 10h/d - With 0 07-Jan-23 07-Jan-23 0
Inspection (Plumbing / FS / WP) HK Hols - No B/O periods
310.T.ES.T330 ESA - GSE Vehicle Wash Facility - WSD Inspection for Water Supply System (was
C11_6C3)
d/w - 10h/d - With 6 16-Jan-23 21-Jan-23 16-Jan-23 21-Jan-23 0
HK Hols - No B/O periods
310.T.ES.T335 ESA - GSE Vehicle Wash Facility - Water supply available for water connection (by (was
C11_6C3)
d/w - 10h/d - With 0 21-Jan-23 21-Jan-23 0
others) & Obtain Form WWO 46 (Part V) HK Hols - No B/O periods
310.T.ES.T340 ESA - GSE Vehicle Wash Facility - Form WWO 132 (Part II) Submission for Water Supply (was
C11_6C3)
d/w - 10h/d - With 0 21-Jan-23 21-Jan-23 0
Connection HK Hols - No B/O periods
310.T.ES.T345 ESA - GSE Vehicle Wash Facility - Final Water Supply Connection (was
C11_6C3)
d/w - 10h/d - With 3 26-Jan-23 28-Jan-23 26-Jan-23 28-Jan-23 0
HK Hols - No B/O periods
310.T.ES.T350 ESA - GSE Vehicle Wash Facility - Obtain Water Certificate (Form WWO 1005) (was
C11_6C3)
d/w - 10h/d - With 0 28-Jan-23 28-Jan-23 0
HK Hols - No B/O periods
Fire Services Department (FSD) (was
C11_6C3)
d/w - 10h/d - With HK Hols
35- No B/O 0periods (was
03-Jan-23
C3) 15-Feb-23 30-Jan-23 15-Feb-23 0
310.T.ES.T355 ESA - GSE Vehicle Wash Facility - F.S. Inspection Plan (Form FSI / 314 Submission) C11_6 d/w - 10h/d - With 0 03-Jan-23 30-Jan-23 20
HK Hols - No B/O periods
310.T.ES.T360 ESA - GSE Vehicle Wash Facility - F.S. Inspection Application (Form FSI / 501 & 251 (was
C11_6C3)
d/w - 10h/d - With 0 30-Jan-23 30-Jan-23 0
Submission) HK Hols - No B/O periods
310.T.ES.T365 ESA - GSE Vehicle Wash Facility - F.S. 1st Inspection (was
C11_6C3)
d/w - 10h/d - With 6 30-Jan-23 04-Feb-23 30-Jan-23 04-Feb-23 0
HK Hols - No B/O periods
310.T.ES.T370 ESA - GSE Vehicle Wash Facility - FSD Comment (was
C11_6C3)
d/w - 10h/d - With 0 04-Feb-23 04-Feb-23 0
HK Hols - No B/O periods
310.T.ES.T375 ESA - GSE Vehicle Wash Facility - Rectification & Adjustment (was
C11_6C3)
d/w - 10h/d - With 3 06-Feb-23 08-Feb-23 06-Feb-23 08-Feb-23 0
HK Hols - No B/O periods
310.T.ES.T380 ESA - GSE Vehicle Wash Facility - F.S. Re-inspection (was
C11_6C3)
d/w - 10h/d - With 6 09-Feb-23 15-Feb-23 09-Feb-23 15-Feb-23 0
HK Hols - No B/O periods
310.T.ES.T385 ESA - GSE Vehicle Wash Facility - Issue F.S. Certificate (Form FS172) (was
C11_6C3)
d/w - 10h/d - With 0 15-Feb-23 15-Feb-23 0
HK Hols - No B/O periods
Building Department (BD) (was C3) 15 0 16-Feb-23 04-Mar-23 16-Feb-23 13-Jul-24 402
310.T.ES.T390 ESA - GSE Vehicle Wash Facility - BD Inspection Application for Occupation Permit C11_6 d/w - 10h/d - With 0 16-Feb-23 16-Feb-23 0
(Form BA13 Submission) HK Hols - No B/O periods
310.T.ES.T395 ESA - GSE Vehicle Wash Facility - BD 1st Inspection (was
C11_6C3)
d/w - 10h/d - With 6 16-Feb-23 22-Feb-23 16-Feb-23 22-Feb-23 0
HK Hols - No B/O periods
310.T.ES.T400 ESA - GSE Vehicle Wash Facility - BD Comment (was
C11_6C3)
d/w - 10h/d - With 0 22-Feb-23 22-Feb-23 0
HK Hols - No B/O periods
310.T.ES.T405 ESA - GSE Vehicle Wash Facility - Rectification & Adjustment (was
C11_6C3)
d/w - 10h/d - With 3 23-Feb-23 25-Feb-23 23-Feb-23 25-Feb-23 0
HK Hols - No B/O periods
310.T.ES.T410 ESA - GSE Vehicle Wash Facility - BD Re-inspection (was
C11_6C3)
d/w - 10h/d - With 6 27-Feb-23 04-Mar-23 27-Feb-23 04-Mar-23 0
HK Hols - No B/O periods
310.T.ES.M650 ESA- GSE Vehicle Wash Facility (T&C) - Achieved Milestone 25 (was
C01_7C3)
d/w - 10h/d - No HK 0 04-Mar-23 05-Mar-23 1
Hols - No B/O periods (was
310.T.ES.M654 ESA - Achieved KD-10 (Section 3) - Others (Wash Facility) C1)
C01_7 d/w - 10h/d - No HK 0 04-Mar-23 13-Jul-24 497
Hols - No B/O periods (was
310.T.ES.T415 ESA - GSE Vehicle Wash Facility - Issue Occupation Permit (Form BD104) C1)
C11_6 d/w - 10h/d - With 0 04-Mar-23 04-Mar-23 0
HK Hols - No B/O periods
WSA - GSE Battery Charging B (was C3) 267 0 22-Jul-22 14-Jun-23 19-Dec-22 13-Jul-24 321
Testing and Commissioning 267 0 22-Jul-22 14-Jun-23 19-Dec-22 13-Jul-24 321
Preliminary Testing and Commissioning C11_6 d/w - 10h/d - With HK Hols
41- No B/O 0periods (was
26-Jan-23
C3) 14-Mar-23 10-Jun-23 13-Jul-23 96
Preliminary T&C - Plumbing and Drainage C11_6 d/w - 10h/d - With HK Hols
20- No B/O 0periods (was
06-Feb-23
C3) 28-Feb-23 10-Jun-23 05-Jul-23 101
310.C.EX.W1440 GSE Battery Charging B - Plumbing & Drainage Preliminary Inspection & Adjustment C11_6 d/w - 10h/d - With 14 06-Feb-23 21-Feb-23 10-Jun-23 27-Jun-23 101
HK Hols - No B/O periods
(was C3)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 223 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.EX.W1444 GSE Battery Charging B - Plumbing & Drainage Preliminary Testing & Commissioning C11_6 d/w - 10h/d - With 14 13-Feb-23 28-Feb-23 17-Jun-23 05-Jul-23 101
HK Hols - No B/O periods
Preliminary T&C - Electrical (was
C11_6C3)
d/w - 10h/d - With HK Hols
20- No B/O 0periods (was
20-Feb-23
C3) 14-Mar-23 10-Jun-23 05-Jul-23 89
310.C.EX.W1356 GSE Battery Charging B - Electrical Preliminary Inspection & Adjustment C11_6 d/w - 10h/d - With 14 20-Feb-23 07-Mar-23 10-Jun-23 27-Jun-23 89
HK Hols - No B/O periods
310.C.EX.W1360 GSE Battery Charging B - Electrical Preliminary Testing & Commissioning (was
C11_6C3)
d/w - 10h/d - With 14 27-Feb-23 14-Mar-23 17-Jun-23 05-Jul-23 89
HK Hols - No B/O periods
Preliminary T&C - Fire Services (was
C11_6C3)
d/w - 10h/d - With HK Hols
20- No B/O 0periods (was
13-Feb-23
C3) 07-Mar-23 19-Jun-23 13-Jul-23 102
310.C.EX.W1380 GSE Battery Charging B - Fire Services Preliminary Inspection & Adjustment (FSI) C11_6 d/w - 10h/d - With 14 13-Feb-23 28-Feb-23 19-Jun-23 06-Jul-23 102
HK Hols - No B/O periods
310.C.EX.W1381.B01 GSE Battery Charging B - Fire Services Preliminary Inspection & Adjustment (Non-FSI) (was
C11_6C3)
d/w - 10h/d - With 14 13-Feb-23 28-Feb-23 19-Jun-23 06-Jul-23 102
HK Hols - No B/O periods
310.C.EX.W1384 GSE Battery Charging B - Fire Services Preliminary Testing & Commissioning (FSI) (was
C11_6C3)
d/w - 10h/d - With 14 20-Feb-23 07-Mar-23 27-Jun-23 13-Jul-23 102
HK Hols - No B/O periods
310.C.EX.W1385.B01 GSE Battery Charging B - Fire Services Preliminary Testing & Commissioning (Non-FSI) (was
C11_6C3)
d/w - 10h/d - With 14 20-Feb-23 07-Mar-23 27-Jun-23 13-Jul-23 102
HK Hols - No B/O periods
Preliminary T&C - MVAC (was
C11_6C3)
d/w - 10h/d - With HK Hols
20- No B/O 0periods (was
26-Jan-23
C3) 17-Feb-23 19-Jun-23 13-Jul-23 117
310.C.EX.W1400 GSE Battery Charging B - MVAC Preliminary Inspection & Adjustment C11_6 d/w - 10h/d - With 14 26-Jan-23 10-Feb-23 19-Jun-23 06-Jul-23 117
HK Hols - No B/O periods
310.C.EX.W1404 GSE Battery Charging B - MVAC Preliminary Testing & Commissioning (was
C11_6C3)
d/w - 10h/d - With 14 02-Feb-23 17-Feb-23 27-Jun-23 13-Jul-23 117
HK Hols - No B/O periods
Testing and Commissioning (was
C01_7C3)
d/w - 10h/d - No HK Hols35
- No B/O periods
0 (was16-Mar-23
C1) 19-Apr-23 14-Jul-23 08-Sep-23 142
310.T.EX.L252 WSA - GSE Battery Charging B - FS System Test (FSI) C01_7 d/w - 10h/d - No HK 14 16-Mar-23 29-Mar-23 22-Jul-23 04-Aug-23 128
Hols - No B/O periods (was
310.T.EX.L260.B01 WSA - GSE Battery Charging B - FS System Test (Non-FSI) C1)
C01_7 d/w - 10h/d - No HK 14 16-Mar-23 29-Mar-23 26-Aug-23 08-Sep-23 163
Hols - No B/O periods (was
310.T.EX.L256 WSA - GSE Battery Charging B - Ventilation System Test C1)
C01_7 d/w - 10h/d - No HK 14 23-Mar-23 05-Apr-23 22-Jul-23 04-Aug-23 121
Hols - No B/O periods (was
310.T.EX.L268 WSA - GSE Battery Charging B - Plumbing System Test C1)
C01_7 d/w - 10h/d - No HK 14 23-Mar-23 05-Apr-23 14-Jul-23 27-Jul-23 113
Hols - No B/O periods (was
310.T.EX.L264 WSA - GSE Battery Charging B - Systems Integration Test C1)
C01_7 d/w - 10h/d - No HK 14 06-Apr-23 19-Apr-23 05-Aug-23 18-Aug-23 121
Hols - No B/O periods (was
Statutory Inspection C1) 267 0 22-Jul-22 14-Jun-23 19-Dec-22 13-Jul-24 321
Water Supply Department (WSD) C11_6 d/w - 10h/d - With HK Hols
231- No B/O 0periods (was
22-Jul-22
C3) 02-May-23 19-Dec-22 18-Aug-23 90
310.T.WS.T625 WSA - GSE Battery Charging B - Prepare for Plumbing Material for Submission C11_6 d/w - 10h/d - With 17 22-Jul-22 10-Aug-22 19-Dec-22 09-Jan-23 125
HK Hols - No B/O periods
310.T.WS.T630 WSA - GSE Battery Charging B - Submit all Plumbing Material for PM Acceptance (was
C11_6C3)
d/w - 10h/d - With 0 11-Aug-22 10-Jan-23 125
HK Hols - No B/O periods
310.T.WS.T635 WSA - GSE Battery Charging B - PM Acceptance (was
C11_6C3)
d/w - 10h/d - With 48 11-Aug-22 08-Oct-22 10-Jan-23 09-Mar-23 125
HK Hols - No B/O periods
310.T.WS.T655 WSA - GSE Battery Charging B - Form WWO 46 (Part I & Part II) & Annex Submission for (was
C11_6C3)
d/w - 10h/d - With 0 10-Oct-22 10-Mar-23 125
WSD Approval (Plumbing / FS / WP) HK Hols - No B/O periods
310.T.WS.T660 WSA - GSE Battery Charging B - Obtain Form WWO 46 (Part III) - WSD Approval, (was
C11_6C3)
d/w - 10h/d - With 4 10-Oct-22 13-Oct-22 10-Mar-23 14-Mar-23 125
Endorsed & Return to Licensed Plumber HK Hols - No B/O periods
310.T.WS.T715 WSA - GSE Battery Charging B - Form WWO 46 (Part IV) Submission for WSD Inspection (was
C11_6C3)
d/w - 10h/d - With 0 06-Apr-23 28-Jul-23 90
(Plumbing / FS / WP) HK Hols - No B/O periods
310.T.WS.T720 WSA - GSE Battery Charging B - WSD Inspection for Water Supply System (was
C11_6C3)
d/w - 10h/d - With 6 18-Apr-23 24-Apr-23 05-Aug-23 11-Aug-23 90
HK Hols - No B/O periods
310.T.WS.T725 WSA - GSE Battery Charging B - Obtain Form WWO 46 (Part V) (was
C11_6C3)
d/w - 10h/d - With 0 24-Apr-23 11-Aug-23 90
HK Hols - No B/O periods
(was C3)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 224 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.T.WS.T730 WSA - GSE Battery Charging B - Form WWO 132 (Part II) Submission for Water Supply C11_6 d/w - 10h/d - With 0 24-Apr-23 11-Aug-23 90
Connection HK Hols - No B/O periods
310.T.WS.T735 WSA - GSE Battery Charging B - Final Water Supply Connection (was
C11_6C3)
d/w - 10h/d - With 6 25-Apr-23 02-May-23 12-Aug-23 18-Aug-23 90
HK Hols - No B/O periods
310.T.WS.T740 WSA - GSE Battery Charging B - Obtain Water Certificate (Form WWO 1005) (was
C11_6C3)
d/w - 10h/d - With 0 02-May-23 18-Aug-23 90
HK Hols - No B/O periods
Fire Services Department (FSD) (was
C11_6C3)
d/w - 10h/d - With HK Hols
37- No B/O 0periods (was
06-Apr-23
C3) 23-May-23 19-Aug-23 08-Sep-23 90
310.T.WS.T745 WSA - GSE Battery Charging B - F.S. Inspection Plan (Form FSI / 314 Submission) C11_6 d/w - 10h/d - With 0 06-Apr-23 19-Aug-23 109
HK Hols - No B/O periods
310.T.WS.T750 WSA - GSE Battery Charging B - F.S. Inspection Application (Form FSI / 501 & 251 (was
C11_6C3)
d/w - 10h/d - With 0 03-May-23 19-Aug-23 90
Submission) HK Hols - No B/O periods
310.T.WS.T755 WSA - GSE Battery Charging B - F.S. 1st Inspection (was
C11_6C3)
d/w - 10h/d - With 6 03-May-23 09-May-23 19-Aug-23 25-Aug-23 90
HK Hols - No B/O periods
310.T.WS.T760 WSA - GSE Battery Charging B - FSD Comment (was
C11_6C3)
d/w - 10h/d - With 0 09-May-23 25-Aug-23 90
HK Hols - No B/O periods
310.T.WS.T765 WSA - GSE Battery Charging B - Rectification & Adjustment (was
C11_6C3)
d/w - 10h/d - With 6 10-May-23 16-May-23 26-Aug-23 01-Sep-23 90
HK Hols - No B/O periods
310.T.WS.T770 WSA - GSE Battery Charging B - F.S. Re-inspection (was
C11_6C3)
d/w - 10h/d - With 6 17-May-23 23-May-23 02-Sep-23 08-Sep-23 90
HK Hols - No B/O periods
310.T.WS.T785 WSA - GSE Battery Charging B - Issue F.S. Certificate (Form FS172) (was
C11_6C3)
d/w - 10h/d - With 0 23-May-23 08-Sep-23 90
HK Hols - No B/O periods
Building Department (BD) (was C3) 18 0 24-May-23 14-Jun-23 09-Sep-23 13-Jul-24 321
310.T.WS.T790 WSA - GSE Battery Charging B - BD Inspection Application for Occupation Permit (Form C11_6 d/w - 10h/d - With 0 24-May-23 09-Sep-23 90
BA13 Submission) HK Hols - No B/O periods
310.T.WS.T795 WSA - GSE Battery Charging B - BD 1st Inspection (was
C11_6C3)
d/w - 10h/d - With 6 24-May-23 31-May-23 09-Sep-23 15-Sep-23 90
HK Hols - No B/O periods
310.T.WS.T815 WSA - GSE Battery Charging B - BD Comment (was
C11_6C3)
d/w - 10h/d - With 0 31-May-23 15-Sep-23 90
HK Hols - No B/O periods
310.T.WS.T820 WSA - GSE Battery Charging B - Rectification & Adjustment (was
C11_6C3)
d/w - 10h/d - With 6 01-Jun-23 07-Jun-23 16-Sep-23 22-Sep-23 90
HK Hols - No B/O periods
310.T.WS.T830 WSA - GSE Battery Charging B - BD Re-inspection (was
C11_6C3)
d/w - 10h/d - With 6 08-Jun-23 14-Jun-23 23-Sep-23 29-Sep-23 90
HK Hols - No B/O periods
310.T.WS.M038 WSA - GSE Battery Charging B (T&C) - Achieved Milestone 27 (was
C01_7C3)
d/w - 10h/d - No HK 0 14-Jun-23 01-Oct-23 109
Hols - No B/O periods (was
310.T.WS.M042 WSA - GSE Battery Charging B (T&C) - Achieved KD-10 C1)
C01_7 d/w - 10h/d - No HK 0 14-Jun-23 13-Jul-24 395
Hols - No B/O periods (was
310.T.WS.T835 WSA - GSE Battery Charging B - Issue Occupation Permit (Form BD104) C1)
C11_6 d/w - 10h/d - With 0 14-Jun-23 29-Sep-23 90
HK Hols - No B/O periods
WSA - Maintenance Facilities Forecourt & Coach Staging A and Bus Stop (MFF and Bus Stop) (was C3) 148 0 20-Sep-23 19-Mar-24 23-Jan-24 13-Jul-24 92
Testing and Commissioning 148 0 20-Sep-23 19-Mar-24 23-Jan-24 13-Jul-24 92
Preliminary Testing and Commissioning C11_6 d/w - 10h/d - With HK Hols
40- No B/O 0periods (was
20-Sep-23
C3) 08-Nov-23 23-Jan-24 23-Mar-24 112
Preliminary T&C - Drainage C11_6 d/w - 10h/d - With HK Hols
28- No B/O 0periods (was
20-Sep-23
C3) 25-Oct-23 21-Feb-24 23-Mar-24 124
310.C.EX.W2192 WSA - MFF and Bus Stop - Drainage Preliminary Inspection & Adjustment C11_6 d/w - 10h/d - With 18 20-Sep-23 12-Oct-23 21-Feb-24 12-Mar-24 124
HK Hols - No B/O periods
310.C.EX.W2196 WSA - MFF and Bus Stop - Drainage Preliminary Testing & Commissioning (was
C11_6C3)
d/w - 10h/d - With 18 04-Oct-23 25-Oct-23 04-Mar-24 23-Mar-24 124
HK Hols - No B/O periods
Preliminary T&C - Electrical (was
C11_6C3)
d/w - 10h/d - With HK Hols
28- No B/O 0periods (was
27-Sep-23
C3) 01-Nov-23 23-Jan-24 26-Feb-24 95
310.C.EX.W2144 WSA - MFF and Bus Stop - Electrical Preliminary Inspection & Adjustment C11_6 d/w - 10h/d - With 18 27-Sep-23 19-Oct-23 23-Jan-24 14-Feb-24 95
HK Hols - No B/O periods
310.C.EX.W2148 WSA - MFF and Bus Stop - Electrical Preliminary Testing & Commissioning (was
C11_6C3)
d/w - 10h/d - With 18 11-Oct-23 01-Nov-23 03-Feb-24 26-Feb-24 95
HK Hols - No B/O periods
(was C3)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 225 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
Preliminary T&C - Fire Services C11_6 d/w - 10h/d - With HK Hols
28- No B/O 0periods (was
06-Oct-23
C3) 08-Nov-23 30-Jan-24 04-Mar-24 95
310.C.EX.W2168 WSA - MFF and Bus Stop - Fire Services Preliminary Inspection & Adjustment (FSI) C11_6 d/w - 10h/d - With 18 06-Oct-23 27-Oct-23 30-Jan-24 21-Feb-24 95
HK Hols - No B/O periods
310.C.EX.W2172 WSA - MFF and Bus Stop - Fire Services Preliminary Testing & Commissioning (FSI) (was
C11_6C3)
d/w - 10h/d - With 18 18-Oct-23 08-Nov-23 10-Feb-24 04-Mar-24 95
HK Hols - No B/O periods
Testing and Commissioning (was
C01_7C3)
d/w - 10h/d - No HK Hols73
- No B/O periods
0 (was09-Nov-23
C1) 20-Jan-24 12-Mar-24 16-May-24 117
310.T.EX.L468 WSA - MFF and Bus Stop - Electrical System Test C01_7 d/w - 10h/d - No HK 24 09-Nov-23 02-Dec-23 12-Mar-24 04-Apr-24 124
Hols - No B/O periods (was
310.T.EX.L464 WSA - MFF and Bus Stop - FS System Test (FSI) C1)
C01_7 d/w - 10h/d - No HK 24 16-Nov-23 09-Dec-23 12-Mar-24 04-Apr-24 117
Hols - No B/O periods (was
310.T.EX.L476 WSA - MFF and Bus Stop - Systems Integration Test C1)
C01_7 d/w - 10h/d - No HK 42 10-Dec-23 20-Jan-24 05-Apr-24 16-May-24 117
Hols - No B/O periods (was
Statutory Inspection C1) 102 0 16-Nov-23 19-Mar-24 17-Apr-24 13-Jul-24 92
Fire Services Department (FSD) 102 0 16-Nov-23 19-Mar-24 17-Apr-24 13-Jul-24 92
310.T.WS.T948 WSA - MFF and Bus Stop - F.S. Inspection Plan (Form FSI / 314 Submission) C11_6 d/w - 10h/d - With 0 16-Nov-23 17-Apr-24 122
HK Hols - No B/O periods
310.T.WS.T952 WSA - MFF and Bus Stop - F.S. Inspection Application (Form FSI / 501 & 251 (was
C11_6C3)
d/w - 10h/d - With 0 22-Jan-24 17-May-24 92
Submission) HK Hols - No B/O periods
310.T.WS.T956 WSA - MFF and Bus Stop - F.S. 1st Inspection (was
C11_6C3)
d/w - 10h/d - With 12 05-Feb-24 20-Feb-24 31-May-24 14-Jun-24 92
HK Hols - No B/O periods
310.T.WS.T960 WSA - MFF and Bus Stop - FSD Comment (was C3)
C11_6 d/w - 10h/d - With 0 20-Feb-24 14-Jun-24 92
HK Hols - No B/O periods
310.T.WS.T964 WSA - MFF and Bus Stop - Rectification & Adjustment (was
C11_6C3)
d/w - 10h/d - With 12 21-Feb-24 05-Mar-24 15-Jun-24 28-Jun-24 92
HK Hols - No B/O periods
310.T.WS.T968 WSA - MFF and Bus Stop - F.S. Re-inspection (was
C11_6C3)
d/w - 10h/d - With 12 06-Mar-24 19-Mar-24 29-Jun-24 13-Jul-24 92
HK Hols - No B/O periods
310.T.WS.M022 WSA - Achieved KD-10 (Section 3) - Maintenance Facilities (was
C01_7C3)
d/w - 10h/d - No HK 0 19-Mar-24 13-Jul-24 116
Hols - No B/O periods (was
310.T.WS.T972 WSA - MFF and Bus Stop - Issue F.S. Certificate (Form FS172) C1)
C11_6 d/w - 10h/d - With 0 19-Mar-24 13-Jul-24 92
HK Hols - No B/O periods
WSA - GSE Storage Area (was C3) 70 0 18-Oct-23 11-Jan-24 19-Apr-24 14-Jul-24 148
Testing and Commissioning C11_6 d/w - 10h/d - With HK Hols
28- No B/O 0periods (was
18-Oct-23
C3) 20-Nov-23 19-Apr-24 23-May-24 148
310.T.WS.N101 WSA - GSE Storage Area - Testing and Commissioning C11_6 d/w - 10h/d - With 28 18-Oct-23 20-Nov-23 19-Apr-24 23-May-24 148
HK Hols - No B/O periods
Inspection (was C3) 42 0 21-Nov-23 11-Jan-24 24-May-24 14-Jul-24 148
310.T.WS.N117 WSA - GSE Storage Area - Inspection and defects rectification C11_6 d/w - 10h/d - With 28 21-Nov-23 22-Dec-23 24-May-24 26-Jun-24 148
HK Hols - No B/O periods
310.T.WS.N105 WSA - GSE Storage Area - PM Acceptance (was
C11_6C3)
d/w - 10h/d - With 14 23-Dec-23 11-Jan-24 27-Jun-24 13-Jul-24 148
HK Hols - No B/O periods
310.T.WS.N109 WSA - GSE Storage Area - PM Issued Letter of Completion (was
C11_6C3)
d/w - 10h/d - With 0 11-Jan-24 13-Jul-24 148
HK Hols - No B/O periods
310.T.WS.N113 WSA - GSE Storage Area - completion of GSE Storage Area (KD-10) (was
C01_7C3)
d/w - 10h/d - No HK 0 11-Jan-24 14-Jul-24 185
Hols - No B/O periods (was
WSA - Gatehouse B C1) 386 33 31-Oct-22 16-Feb-24 14-Feb-23 18-Feb-24 1
Testing and Commissioning 386 33 31-Oct-22 16-Feb-24 14-Feb-23 18-Feb-24 1
Preliminary Testing and Commissioning C11_6 d/w - 10h/d - With HK Hols
90- No B/O 0periods (was
27-Jun-23
C3) 12-Oct-23 21-Aug-23 25-Jan-24 86
Preliminary T&C - Plumbing and Drainage C11_6 d/w - 10h/d - With HK Hols
34- No B/O 0periods (was
27-Jun-23
C3) 05-Aug-23 21-Aug-23 28-Sep-23 46
310.C.EX.W2072 WSA - Gatehouse B - Plumbing & Drainage Preliminary Inspection & Adjustment C11_6 d/w - 10h/d - With 24 27-Jun-23 25-Jul-23 21-Aug-23 16-Sep-23 46
HK Hols - No B/O periods
310.C.EX.W2076 WSA - Gatehouse B - Plumbing & Drainage Preliminary Testing & Commissioning (was
C11_6C3)
d/w - 10h/d - With 24 10-Jul-23 05-Aug-23 01-Sep-23 28-Sep-23 46
HK Hols - No B/O periods
(was C3)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 226 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
Preliminary T&C - Electrical C11_6 d/w - 10h/d - With HK Hols
90- No B/O 0periods (was
27-Jun-23
C3) 12-Oct-23 02-Sep-23 25-Jan-24 86
310.C.EX.W2483.B02 WSA - Gatehouse B - Electrical Preliminary Inspection & Adjustment (non-FSI) C11_6 d/w - 10h/d - With 24 27-Jun-23 25-Jul-23 28-Nov-23 27-Dec-23 128
HK Hols - No B/O periods
310.C.EX.W2490.B02 WSA - Gatehouse B - Electrical Preliminary Testing & Commissioning (non-FSI) (was
C11_6C3)
d/w - 10h/d - With 24 26-Jul-23 22-Aug-23 28-Dec-23 25-Jan-24 128
HK Hols - No B/O periods
310.C.EX.W1988 WSA - Gatehouse B - Electrical Preliminary Inspection & Adjustment (was
C11_6C3)
d/w - 10h/d - With 24 01-Sep-23 28-Sep-23 02-Sep-23 29-Sep-23 1
HK Hols - No B/O periods
310.C.EX.W1992 WSA - Gatehouse B - Electrical Preliminary Testing & Commissioning (was
C11_6C3)
d/w - 10h/d - With 24 13-Sep-23 12-Oct-23 14-Sep-23 13-Oct-23 1
HK Hols - No B/O periods
Preliminary T&C - Fire Services (was
C11_6C3)
d/w - 10h/d - With HK Hols
34- No B/O 0periods (was
27-Jun-23
C3) 05-Aug-23 02-Sep-23 13-Oct-23 57
310.C.EX.W2012 WSA - Gatehouse B - Fire Services Preliminary Inspection & Adjustment (FSI) C11_6 d/w - 10h/d - With 24 27-Jun-23 25-Jul-23 02-Sep-23 29-Sep-23 57
HK Hols - No B/O periods
310.C.EX.W2013.B01 WSA - Gatehouse B - Fire Services Preliminary Inspection & Adjustment (Non-FSI) (was
C11_6C3)
d/w - 10h/d - With 24 27-Jun-23 25-Jul-23 02-Sep-23 29-Sep-23 57
HK Hols - No B/O periods
310.C.EX.W2016 WSA - Gatehouse B - Fire Services Preliminary Testing & Commissioning (FSI) (was
C11_6C3)
d/w - 10h/d - With 24 10-Jul-23 05-Aug-23 14-Sep-23 13-Oct-23 57
HK Hols - No B/O periods
310.C.EX.W2017.B01 WSA - Gatehouse B - Fire Services Preliminary Testing & Commissioning (Non-FSI) (was
C11_6C3)
d/w - 10h/d - With 24 10-Jul-23 05-Aug-23 14-Sep-23 13-Oct-23 57
HK Hols - No B/O periods
Preliminary T&C - MVAC (was
C11_6C3)
d/w - 10h/d - With HK Hols
34- No B/O 0periods (was
27-Jun-23
C3) 05-Aug-23 02-Sep-23 13-Oct-23 57
310.C.EX.W2032 WSA - Gatehouse B - MVAC Preliminary Inspection & Adjustment C11_6 d/w - 10h/d - With 24 27-Jun-23 25-Jul-23 02-Sep-23 29-Sep-23 57
HK Hols - No B/O periods
310.C.EX.W2036 WSA - Gatehouse B - MVAC Preliminary Testing & Commissioning (was
C11_6C3)
d/w - 10h/d - With 24 10-Jul-23 05-Aug-23 14-Sep-23 13-Oct-23 57
HK Hols - No B/O periods
Testing and Commissioning (was
C01_7C3)
d/w - 10h/d - No HK Hols120
- No B/O periods
11 (was20-Aug-23
C1) 17-Dec-23 16-Oct-23 25-Jan-24 39
310.T.EX.L336 WSA - Gatehouse B - Ventilation System Test C01_7 d/w - 10h/d - No HK 21 2 20-Aug-23 09-Sep-23 29-Oct-23 18-Nov-23 70
Hols - No B/O periods (was
310.T.EX.L348 WSA - Gatehouse B - Plumbing System Test C1)
C01_7 d/w - 10h/d - No HK 21 2 20-Aug-23 09-Sep-23 16-Oct-23 05-Nov-23 57
Hols - No B/O periods (was
310.T.EX.L332 WSA - Gatehouse B - FS System Test (FSI) C1)
C01_7 d/w - 10h/d - No HK 21 2 28-Oct-23 17-Nov-23 29-Oct-23 18-Nov-23 1
Hols - No B/O periods (was
310.T.EX.L340.B01 WSA - Gatehouse B - FS System Test (Non-FSI) C1)
C01_7 d/w - 10h/d - No HK 21 2 28-Oct-23 17-Nov-23 05-Jan-24 25-Jan-24 69
Hols - No B/O periods (was
310.T.EX.L344 WSA - Gatehouse B - Systems Integration Test C1)
C01_7 d/w - 10h/d - No HK 30 3 18-Nov-23 17-Dec-23 19-Nov-23 18-Dec-23 1
Hols - No B/O periods (was
Statutory Inspection C1) 386 22 31-Oct-22 16-Feb-24 14-Feb-23 18-Feb-24 1
Water Supply Department (WSD) C11_6 d/w - 10h/d - With HK Hols
284- No B/O10
periods (was
31-Oct-22
C3) 13-Oct-23 14-Feb-23 04-Dec-23 43
310.T.WS.T600 WSA - Gatehouse B & Vehicle Search Bay and C&ED Control Kiosk - Prepare for C11_6 d/w - 10h/d - With 17 3 31-Oct-22 18-Nov-22 14-Feb-23 04-Mar-23 86
Plumbing Material for Submission HK Hols - No B/O periods
310.T.WS.T605 WSA - Gatehouse B & Vehicle Search Bay and C&ED Control Kiosk - Submit all (was
C11_6C3)
d/w - 10h/d - With 0 19-Nov-22 06-Mar-23 86
Plumbing Material for PM Acceptance HK Hols - No B/O periods
310.T.WS.T610 WSA - Gatehouse B & Vehicle Search Bay and C&ED Control Kiosk - PM Acceptance (was
C11_6C3)
d/w - 10h/d - With 48 4 19-Nov-22 16-Jan-23 06-Mar-23 05-May-23 86
HK Hols - No B/O periods
310.T.WS.T615 WSA-Gatehouse B&Vehicle Search Bay&C&ED Control Kiosk - Form WWO46(Part (was
C11_6C3)
d/w - 10h/d - With 0 17-Jan-23 06-May-23 86
I&II)&Submission for WSD App.(Plumbing/FS/WP) HK Hols - No B/O periods
310.T.WS.T620 WSA - Gatehouse B&Vehicle Search Bay&C&ED - Obtain Form WWO46(Part III)-WSD (was
C11_6C3)
d/w - 10h/d - With 4 1 17-Jan-23 20-Jan-23 06-May-23 10-May-23 86
Approval,Endorsed&Return to Licensed Plumber HK Hols - No B/O periods
310.T.WS.T775 WSA - Gatehouse B&Vehicle Search Bay&C&ED-Form WWO 46(Part IV)Submission for (was
C11_6C3)
d/w - 10h/d - With 0 13-Sep-23 06-Nov-23 43
WSD Inspection(Plumbing/FS/WP) HK Hols - No B/O periods
310.T.WS.T780 WSA - Gatehouse B & Vehicle Search Bay and C&ED Control Kiosk - WSD Inspection for (was
C11_6C3)
d/w - 10h/d - With 12 1 21-Sep-23 06-Oct-23 14-Nov-23 27-Nov-23 43
Water Supply System HK Hols - No B/O periods
(was C3)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 227 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.T.WS.T800 WSA - Gatehouse B & Vehicle Search Bay and C&ED Control Kiosk - Obtain Form WWO C11_6 d/w - 10h/d - With 0 06-Oct-23 27-Nov-23 43
46 (Part V) HK Hols - No B/O periods
310.T.WS.T805 WSA - Gatehouse B&Vehicle Search Bay and C&ED Control Kiosk-Form WWO132(Part (was
C11_6C3)
d/w - 10h/d - With 0 06-Oct-23 27-Nov-23 43
II)Submission for Water Supply Connection HK Hols - No B/O periods
310.T.WS.T810 WSA - Gatehouse B & Vehicle Search Bay and C&ED Control Kiosk - Final Water Supply (was
C11_6C3)
d/w - 10h/d - With 6 1 07-Oct-23 13-Oct-23 28-Nov-23 04-Dec-23 43
Connection HK Hols - No B/O periods
310.T.WS.T825 WSA - Gatehouse B & Vehicle Search Bay and C&ED Control Kiosk - Obtain Water (was
C11_6C3)
d/w - 10h/d - With 0 13-Oct-23 04-Dec-23 43
Certificate (Form WWO 1005) HK Hols - No B/O periods
Fire Services Department (FSD) (was
C11_6C3)
d/w - 10h/d - With HK Hols
187- No B/O 6periods (was
12-Jun-23
C3) 24-Jan-24 04-Oct-23 25-Jan-24 1
DG Application & Inspection C11_6 d/w - 10h/d - With HK Hols
52- No B/O 3periods (was
12-Jun-23
C3) 12-Aug-23 04-Oct-23 04-Dec-23 94
310.T.ES.P500 WSA - Gatehouse B - DG Inspection Application (Form Submission) C11_6 d/w - 10h/d - With 0 12-Jun-23 04-Oct-23 94
HK Hols - No B/O periods
310.T.ES.P504 WSA - Gatehouse B - DG 1st Inspection (was
C11_6C3)
d/w - 10h/d - With 7 1 12-Jul-23 19-Jul-23 02-Nov-23 09-Nov-23 94
HK Hols - No B/O periods
310.T.ES.P508 WSA - Gatehouse B - DG FSD Comment (was
C11_6C3)
d/w - 10h/d - With 0 19-Jul-23 09-Nov-23 94
HK Hols - No B/O periods
310.T.ES.P512 WSA - Gatehouse B - DG Rectification & Adjustment (was
C11_6C3)
d/w - 10h/d - With 14 1 20-Jul-23 04-Aug-23 10-Nov-23 25-Nov-23 94
HK Hols - No B/O periods
310.T.ES.P516 WSA - Gatehouse B - DG Re-inspection (was
C11_6C3)
d/w - 10h/d - With 7 1 05-Aug-23 12-Aug-23 27-Nov-23 04-Dec-23 94
HK Hols - No B/O periods
310.T.ES.P520 WSA - Gatehouse B - Issue DG Certificate (was
C11_6C3)
d/w - 10h/d - With 0 12-Aug-23 04-Dec-23 94
HK Hols - No B/O periods
Fire Services Application & Inspection (was
C11_6C3)
d/w - 10h/d - With HK Hols
55- No B/O 3periods (was
18-Nov-23
C3) 24-Jan-24 05-Dec-23 25-Jan-24 1
310.T.WS.T840 WSA - Gatehouse B - F.S. Inspection Plan (Form FSI / 314 Submission) C11_6 d/w - 10h/d - With 0 18-Nov-23 05-Dec-23 14
HK Hols - No B/O periods
310.T.WS.T845 WSA - Gatehouse B - F.S. Inspection Application (Form FSI / 501 & 251 Submission) (was
C11_6C3)
d/w - 10h/d - With 0 18-Nov-23 05-Dec-23 14
HK Hols - No B/O periods
310.T.WS.T850 WSA - Gatehouse B - F.S. 1st Inspection (was
C11_6C3)
d/w - 10h/d - With 10 1 18-Dec-23 30-Dec-23 19-Dec-23 02-Jan-24 1
HK Hols - No B/O periods
310.T.WS.T855 WSA - Gatehouse B - FSD Comment (was
C11_6C3)
d/w - 10h/d - With 0 30-Dec-23 02-Jan-24 1
HK Hols - No B/O periods
310.T.WS.T860 WSA - Gatehouse B - Rectification & Adjustment (was
C11_6C3)
d/w - 10h/d - With 10 1 02-Jan-24 12-Jan-24 03-Jan-24 13-Jan-24 1
HK Hols - No B/O periods
310.T.WS.T865 WSA - Gatehouse B - F.S. Re-inspection (was
C11_6C3)
d/w - 10h/d - With 10 1 13-Jan-24 24-Jan-24 15-Jan-24 25-Jan-24 1
HK Hols - No B/O periods
310.T.WS.T870 WSA - Gatehouse B - Issue F.S. Certificate (Form FS172) (was
C11_6C3)
d/w - 10h/d - With 0 24-Jan-24 25-Jan-24 1
HK Hols - No B/O periods
Environmental Protection Department (EDP) (was
C11_6C3)
d/w - 10h/d - With HK Hols
48- No B/O 3periods (was
12-Jun-23
C3) 08-Aug-23 09-Oct-23 04-Dec-23 98
EPD Application & Inspection C11_6 d/w - 10h/d - With HK Hols
48- No B/O 3periods (was
12-Jun-23
C3) 08-Aug-23 09-Oct-23 04-Dec-23 98
310.T.ES.P596 WSA - Gatehouse B - EPD Inspection Application C11_6 d/w - 10h/d - With 0 12-Jun-23 09-Oct-23 98
HK Hols - No B/O periods
310.T.ES.P600 WSA - Gatehouse B - EPD 1st Inspection (was
C11_6C3)
d/w - 10h/d - With 6 1 12-Jul-23 18-Jul-23 07-Nov-23 13-Nov-23 98
HK Hols - No B/O periods
310.T.ES.P604 WSA - Gatehouse B - EPD Comment (was
C11_6C3)
d/w - 10h/d - With 0 18-Jul-23 13-Nov-23 98
HK Hols - No B/O periods
310.T.ES.P608 WSA - Gatehouse B - EPD Rectification & Adjustment (was
C11_6C3)
d/w - 10h/d - With 6 1 19-Jul-23 25-Jul-23 14-Nov-23 20-Nov-23 98
HK Hols - No B/O periods
310.T.ES.P612 WSA - Gatehouse B - EPD Re-inspection (was
C11_6C3)
d/w - 10h/d - With 12 1 26-Jul-23 08-Aug-23 21-Nov-23 04-Dec-23 98
HK Hols - No B/O periods
310.T.ES.P616 WSA - Gatehouse B - Issue License (was
C11_6C3)
d/w - 10h/d - With 0 08-Aug-23 04-Dec-23 98
HK Hols - No B/O periods
(was C3)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 228 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
Building Department (BD) 18 3 25-Jan-24 16-Feb-24 26-Jan-24 18-Feb-24 1
310.T.WS.T875 BD Inspection Application for Occupation Permit (Form BA13 Submission) C11_6 d/w - 10h/d - With 0 25-Jan-24 26-Jan-24 1
HK Hols - No B/O periods
310.T.WS.T880 WSA - Gatehouse B - BD 1st Inspection (was
C11_6C3)
d/w - 10h/d - With 6 1 25-Jan-24 31-Jan-24 26-Jan-24 01-Feb-24 1
HK Hols - No B/O periods
310.T.WS.T885 WSA - Gatehouse B - BD Comment (was
C11_6C3)
d/w - 10h/d - With 0 31-Jan-24 01-Feb-24 1
HK Hols - No B/O periods
310.T.WS.T890 WSA - Gatehouse B - Rectification & Adjustment (was
C11_6C3)
d/w - 10h/d - With 6 1 01-Feb-24 07-Feb-24 02-Feb-24 08-Feb-24 1
HK Hols - No B/O periods
310.T.WS.T895 WSA - Gatehouse B - BD Re-inspection (was
C11_6C3)
d/w - 10h/d - With 6 1 08-Feb-24 16-Feb-24 09-Feb-24 17-Feb-24 1
HK Hols - No B/O periods
310.D.RC.D599 WSA - Gatehouse B - Achieved KD-G4(d) (was
C01_7C3)
d/w - 10h/d - No HK 0 16-Feb-24 17-Feb-24 1
Hols - No B/O periods (was
310.T.WS.M551 WSA - Gatehouse B - (T&C) - Achieved KD-10 C1)
C01_7 d/w - 10h/d - No HK 0 16-Feb-24 17-Feb-24 1
Hols - No B/O periods (was
310.T.WS.T900 WSA - Gatehouse B - Issue Occupation Permit (Form BD104) C1)
C11_6 d/w - 10h/d - With 0 16-Feb-24 17-Feb-24 1
HK Hols - No B/O periods
310.K.EX.A1040 PMS29 - Comp all works for Security Gatehouse B, obtain stat. apprv., consents, ready (was
C01_7C3)
d/w - 10h/d - No HK 0 16-Feb-24 18-Feb-24 2
for use [18 Feb 24] Hols - No B/O periods (was
310.D.RC.D651 WSA - Vehicle Traffic Control Kiosk, Vehicle Search Bay - Achieved KD-G4(d) C1)
C01_7 d/w - 10h/d - No HK 0 16-Feb-24 18-Feb-24 2
Hols - No B/O periods (was
310.T.WS.M555 WSA - Vehicle Search Bay and C&ED Control Kiosk - (T&C) - Achieved KD-10 C1)
C01_7 d/w - 10h/d - No HK 0 16-Feb-24 18-Feb-24 2
Hols - No B/O periods (was
WSA - Screening Facilities C1) 237 0 31-Aug-22 19-Jun-23 22-Sep-22 17-Feb-24 199
Testing and Commissioning C01_7 d/w - 10h/d - No HK Hols28
- No B/O periods
0 (was18-Feb-23
C1) 18-Mar-23 01-Mar-23 29-Mar-23 11
310.K.EX.A1044 Completion of CLP Cabling & Energization (from GSE Battery Charing B) C01_7 d/w - 10h/d - No HK 0 18-Feb-23 01-Mar-23 11
Hols - No B/O periods (was
310.T.WS.T1642 WSA - Screening Facilities - Testing & Commissioning C1)
C01_7 d/w - 10h/d - No HK 28 19-Feb-23 18-Mar-23 02-Mar-23 29-Mar-23 11
Hols - No B/O periods (was
Statutory Inspection C1) 237 0 31-Aug-22 19-Jun-23 22-Sep-22 17-Feb-24 199
Water Supply Department (WSD) C11_6 d/w - 10h/d - With HK Hols
189- No B/O 0periods (was
31-Aug-22
C3) 21-Apr-23 22-Sep-22 03-May-23 9
310.T.WS.T1640 WSA - Screening Facilities - Prepare for Plumbing Material for Submission C11_6 d/w - 10h/d - With 17 31-Aug-22 20-Sep-22 22-Sep-22 13-Oct-22 18
HK Hols - No B/O periods
310.T.WS.T1644 WSA - Screening Facilities - Submit all Plumbing Material for PM Acceptance (was
C11_6C3)
d/w - 10h/d - With 0 21-Sep-22 14-Oct-22 18
HK Hols - No B/O periods
310.T.WS.T1648 WSA - Screening Facilities - PM Acceptance (was
C11_6C3)
d/w - 10h/d - With 48 21-Sep-22 17-Nov-22 14-Oct-22 08-Dec-22 18
HK Hols - No B/O periods
310.T.WS.T1652 WSA - Screening Facilities - Form WWO 46 (Part I & Part II) & Annex Submission for (was
C11_6C3)
d/w - 10h/d - With 0 18-Nov-22 09-Dec-22 18
WSD Approval (Plumbing / FS / WP) HK Hols - No B/O periods
310.T.WS.T1656 WSA - Screening Facilities - Obtain Form WWO 46 (Part III) - WSD Approval, Endorsed & (was
C11_6C3)
d/w - 10h/d - With 6 18-Nov-22 24-Nov-22 09-Dec-22 15-Dec-22 18
Return to Licensed Plumber HK Hols - No B/O periods
310.T.WS.T1660 WSA - Screening Facilities - Form WWO 46 (Part IV) Submission for WSD Inspection (was
C11_6C3)
d/w - 10h/d - With 0 20-Mar-23 30-Mar-23 9
(Plumbing / FS / WP) HK Hols - No B/O periods
310.T.WS.T1664 WSA - Screening Facilities - WSD Inspection for Water Supply System (was
C11_6C3)
d/w - 10h/d - With 12 28-Mar-23 14-Apr-23 12-Apr-23 25-Apr-23 9
HK Hols - No B/O periods
310.T.WS.T1668 WSA - Screening Facilities - Obtain Form WWO 46 (Part V) (was
C11_6C3)
d/w - 10h/d - With 0 14-Apr-23 25-Apr-23 9
HK Hols - No B/O periods
310.T.WS.T1672 WSA - Screening Facilities - Form WWO 132 (Part II) Submission for Water Supply (was
C11_6C3)
d/w - 10h/d - With 0 14-Apr-23 25-Apr-23 9
Connection HK Hols - No B/O periods
310.T.WS.T1676 WSA - Screening Facilities - Final Water Supply Connection (was
C11_6C3)
d/w - 10h/d - With 6 15-Apr-23 21-Apr-23 26-Apr-23 03-May-23 9
HK Hols - No B/O periods
(was C3)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 229 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.T.WS.T1680 WSA - Screening Facilities - Obtain Water Certificate (Form WWO 1005) C11_6 d/w - 10h/d - With 0 21-Apr-23 03-May-23 9
HK Hols - No B/O periods
Fire Services Department (FSD) (was
C11_6C3)
d/w - 10h/d - With HK Hols
95- No B/O 0periods (was
01-Feb-23
C3) 29-May-23 15-Mar-23 08-Jun-23 9
DG Application & Inspection C11_6 d/w - 10h/d - With HK Hols
38- No B/O 0periods (was
01-Feb-23
C3) 16-Mar-23 15-Mar-23 03-May-23 36
310.T.ES.P524 WSA - Screening Facilities - DG Inspection Application (Form Submission) C11_6 d/w - 10h/d - With 0 01-Feb-23 15-Mar-23 36
HK Hols - No B/O periods
310.T.ES.P528 WSA - Screening Facilities - DG 1st Inspection (was
C11_6C3)
d/w - 10h/d - With 7 15-Feb-23 22-Feb-23 29-Mar-23 06-Apr-23 36
HK Hols - No B/O periods
310.T.ES.P532 WSA - Screening Facilities - DG FSD Comment (was
C11_6C3)
d/w - 10h/d - With 0 22-Feb-23 06-Apr-23 36
HK Hols - No B/O periods
310.T.ES.P536 WSA - Screening Facilities - DG Rectification & Adjustment (was
C11_6C3)
d/w - 10h/d - With 12 23-Feb-23 08-Mar-23 11-Apr-23 24-Apr-23 36
HK Hols - No B/O periods
310.T.ES.P540 WSA - Screening Facilities - DG Re-inspection (was
C11_6C3)
d/w - 10h/d - With 7 09-Mar-23 16-Mar-23 25-Apr-23 03-May-23 36
HK Hols - No B/O periods
310.T.ES.P544 WSA - Screening Facilities - Issue DG Certificate (was
C11_6C3)
d/w - 10h/d - With 0 16-Mar-23 03-May-23 36
HK Hols - No B/O periods
Fire Services Application & Inspection (was
C11_6C3)
d/w - 10h/d - With HK Hols
37- No B/O 0periods (was
14-Apr-23
C3) 29-May-23 04-May-23 08-Jun-23 9
310.T.WS.T640 WSA - Screening Facilities - F.S. Inspection Plan (Form FSI / 314 Submission) C11_6 d/w - 10h/d - With 0 14-Apr-23 04-May-23 16
HK Hols - No B/O periods
310.T.WS.T645 WSA - Screening Facilities - F.S. Inspection Application (Form FSI / 501 & 251 (was
C11_6C3)
d/w - 10h/d - With 0 22-Apr-23 04-May-23 9
Submission) HK Hols - No B/O periods
310.T.WS.T650 WSA - Screening Facilities - F.S. 1st Inspection (was
C11_6C3)
d/w - 10h/d - With 6 08-May-23 13-May-23 18-May-23 24-May-23 9
HK Hols - No B/O periods
310.T.WS.T665 WSA - Screening Facilities - FSD Comment (was
C11_6C3)
d/w - 10h/d - With 0 13-May-23 24-May-23 9
HK Hols - No B/O periods
310.T.WS.T670 WSA - Screening Facilities - Rectification & Adjustment (was
C11_6C3)
d/w - 10h/d - With 6 15-May-23 20-May-23 25-May-23 01-Jun-23 9
HK Hols - No B/O periods
310.T.WS.T675 WSA - Screening Facilities - F.S. Re-inspection (was
C11_6C3)
d/w - 10h/d - With 6 22-May-23 29-May-23 02-Jun-23 08-Jun-23 9
HK Hols - No B/O periods
310.T.WS.T680 WSA - Screening Facilities - Issue F.S. Certificate (Form FS172) (was
C11_6C3)
d/w - 10h/d - With 0 29-May-23 08-Jun-23 9
HK Hols - No B/O periods
Environmental Protection Department (EDP) (was
C11_6C3)
d/w - 10h/d - With HK Hols
30- No B/O 0periods (was
01-Feb-23
C3) 07-Mar-23 24-Mar-23 03-May-23 44
EPD Application & Inspection C11_6 d/w - 10h/d - With HK Hols
30- No B/O 0periods (was
01-Feb-23
C3) 07-Mar-23 24-Mar-23 03-May-23 44
310.T.ES.P620 WSA - Screening Facilities - EPD Inspection Application C11_6 d/w - 10h/d - With 0 01-Feb-23 24-Mar-23 44
HK Hols - No B/O periods
310.T.ES.P624 WSA - Screening Facilities - EPD 1st Inspection (was
C11_6C3)
d/w - 10h/d - With 6 15-Feb-23 21-Feb-23 12-Apr-23 18-Apr-23 44
HK Hols - No B/O periods
310.T.ES.P628 WSA - Screening Facilities - EPD Comment (was
C11_6C3)
d/w - 10h/d - With 0 21-Feb-23 18-Apr-23 44
HK Hols - No B/O periods
310.T.ES.P632 WSA - Screening Facilities - EPD Rectification & Adjustment (was
C11_6C3)
d/w - 10h/d - With 6 22-Feb-23 28-Feb-23 19-Apr-23 25-Apr-23 44
HK Hols - No B/O periods
310.T.ES.P636 WSA - Screening Facilities - EPD Re-inspection (was
C11_6C3)
d/w - 10h/d - With 6 01-Mar-23 07-Mar-23 26-Apr-23 03-May-23 44
HK Hols - No B/O periods
310.T.ES.P640 WSA - Screening Facilities - Issue License (was
C11_6C3)
d/w - 10h/d - With 0 07-Mar-23 03-May-23 44
HK Hols - No B/O periods
Building Department (BD) (was C3) 18 0 30-May-23 19-Jun-23 09-Jun-23 17-Feb-24 199
310.T.WS.T685 WSA - Screening Facilities - BD Inspection Application for Occupation Permit (Form BA13 C11_6 d/w - 10h/d - With 0 30-May-23 09-Jun-23 9
Submission) HK Hols - No B/O periods
310.T.WS.T690 WSA - Screening Facilities - BD 1st Inspection (was
C11_6C3)
d/w - 10h/d - With 6 30-May-23 05-Jun-23 09-Jun-23 15-Jun-23 9
HK Hols - No B/O periods
(was C3)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 230 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.T.WS.T695 WSA - Screening Facilities - BD Comment C11_6 d/w - 10h/d - With 0 05-Jun-23 15-Jun-23 9
HK Hols - No B/O periods
310.T.WS.T700 WSA - Screening Facilities - Rectification & Adjustment (was
C11_6C3)
d/w - 10h/d - With 6 06-Jun-23 12-Jun-23 16-Jun-23 23-Jun-23 9
HK Hols - No B/O periods
310.T.WS.T705 WSA - Screening Facilities - BD Re-inspection (was
C11_6C3)
d/w - 10h/d - With 6 13-Jun-23 19-Jun-23 24-Jun-23 30-Jun-23 9
HK Hols - No B/O periods
310.T.WS.R046 WSA - Screening Facilities- Achieved Milestone 28 (was
C11_6C3)
d/w - 10h/d - With 0 19-Jun-23 30-Jun-23 9
HK Hols - No B/O periods
310.T.WS.R050 Achieved KD-10 (Section 3) - Screening Facilities (was
C01_7C3)
d/w - 10h/d - No HK 0 19-Jun-23 17-Feb-24 243
Hols - No B/O periods (was
310.T.WS.T710 Issue Occupation Permit (Form BD104) C1)
C11_6 d/w - 10h/d - With 0 19-Jun-23 30-Jun-23 9
HK Hols - No B/O periods
Option 3310/A1 - CAD Facilities (was C3) 756 29 07-Jun-21 A 17-Dec-23 27-Mar-22 18-Dec-23 1
CAD Glide Path Building C 697 3 07-Jun-21 A 07-Oct-23 14-Apr-22 07-Oct-23 0
Design and Submission - ELS C01_7 d/w - 10h/d - No HK Hols129
- No B/O periods
0 (was
01-Dec-21
C1) A 07-Jun-22 06-Jun-22 02-Aug-22 56
310.D.RC.P032 Glide Path Bldg C - Prepares ELS Design for Foundation Works C01_7 d/w - 10h/d - No HK 28 01-Dec-21 A 21-Dec-21 A 06-Jun-22 06-Jun-22
Hols - No B/O periods (was
310.D.RC.P574.B01 Glide Path Bldg C - ICE review and issue check certificate C1)
C01_7 d/w - 10h/d - No HK 7 21-Dec-21 A 22-Dec-21 A 06-Jun-22 06-Jun-22
Hols - No B/O periods (was
310.D.RC.P578.B01 Glide Path Bldg C - Review by PM, AP, RSE, RGE C1)
C01_7 d/w - 10h/d - No HK 28 23-Dec-21 A 20-Jan-22 A 06-Jun-22 06-Jun-22
Hols - No B/O periods (was
310.D.RC.P056 Glide Path Bldg C - BD review and approves design C1)
C01_7 d/w - 10h/d - No HK 60 22-Jan-22 A 25-Apr-22 06-Jun-22 05-Jul-22 71
Hols - No B/O periods (was
310.D.RC.P084 Glide Path Bldg C - submit BA8 consent application (excavation + structure) C1)
C01_7 d/w - 10h/d - No HK 28 11-May-22 07-Jun-22 06-Jul-22 02-Aug-22 56
Hols - No B/O periods (was
ELS Design - UU Trench Below 2.5m C1)
C01_7 d/w - 10h/d - No HK Hols242
- No B/O periods
0 (was02-Jun-22
C1) 29-Jan-23 21-Sep-22 20-May-23 111
310.D.RC.P538 ELS for UU Trench Below 2.5m - Prepares ELS Design for Foundation Works C01_7 d/w - 10h/d - No HK 28 02-Jun-22 29-Jun-22 21-Sep-22 18-Oct-22 111
Hols - No B/O periods (was
310.D.RC.P542 ELS for UU Trench Below 2.5m - ICE review and issue check certificate C1)
C01_7 d/w - 10h/d - No HK 7 30-Jun-22 06-Jul-22 19-Oct-22 25-Oct-22 111
Hols - No B/O periods (was
310.D.RC.P546 ELS for UU Trench Below 2.5m - Review by PM, AP, RSE, RGE C1)
C01_7 d/w - 10h/d - No HK 28 07-Jul-22 03-Aug-22 26-Oct-22 22-Nov-22 111
Hols - No B/O periods (was
310.D.RC.P550 ELS for UU Trench Below 2.5m - Review design by ICC, M&VC and issue check C1)
C01_7 d/w - 10h/d - No HK 21 04-Aug-22 24-Aug-22 23-Nov-22 13-Dec-22 111
certificate Hols - No B/O periods (was
310.D.RC.P554 ELS for UU Trench Below 2.5m - address comment and resubmit 2nd Round C1)
C01_7 d/w - 10h/d - No HK 21 25-Aug-22 14-Sep-22 14-Dec-22 03-Jan-23 111
Hols - No B/O periods (was
310.D.RC.P558 ELS for UU Trench Below 2.5m - Review by PM, AP, RSE, RGE 2nd Round C1)
C01_7 d/w - 10h/d - No HK 28 15-Sep-22 12-Oct-22 04-Jan-23 31-Jan-23 111
Hols - No B/O periods (was
310.D.RC.P570 ELS for UU Trench Below 2.5m - Review design by ICC, M&VC and issue check C1)
C01_7 d/w - 10h/d - No HK 21 13-Oct-22 02-Nov-22 01-Feb-23 21-Feb-23 111
certificate 2nd Round Hols - No B/O periods (was
310.D.RC.P562 ELS for UU Trench Below 2.5m - BD review and approves design C1)
C01_7 d/w - 10h/d - No HK
60 03-Nov-22 01-Jan-23 22-Feb-23 22-Apr-23 111
Hols - No B/O periods (was
310.D.RC.P566 ELS for UU Trench Below 2.5m - submit BA8 consent application (excavation + structure) C1)
C01_7 d/w - 10h/d - No HK 28 02-Jan-23 29-Jan-23 23-Apr-23 20-May-23 111
Hols - No B/O periods (was
Method Statement for Plate Load Test for Glide Path Building C C1)
C01_7 d/w - 10h/d - No HK Hols58
- No B/O periods
0 (was30-Oct-22
C1) 26-Dec-22 14-Nov-22 10-Jan-23 15
310.D.TX.A292 Method Statement for Plate Load Test for Glide Path Building C - prepare document C01_7 d/w - 10h/d - No HK 30 30-Oct-22 28-Nov-22 14-Nov-22 13-Dec-22 15
Hols - No B/O periods (was
310.D.TX.A296 Method Statement for Plate Load Test for Glide Path Building C - BD Acknowledgement C1)
C01_7 d/w - 10h/d - No HK 28 29-Nov-22 26-Dec-22 14-Dec-22 10-Jan-23 15
Hols - No B/O periods (was
CAD Glide Path Building C - MEP Submission C1)
C01_7 d/w - 10h/d - No HK Hols210
- No B/O periods
0 (was
18-Mar-22
C1) A 21-Nov-22 09-Sep-22 06-May-23 166
CAD Glide Path Building C - MEP - Drawing Submission C01_7 d/w - 10h/d - No HK Hols210
- No B/O periods
0 (was
18-Mar-22
C1) A 21-Nov-22 09-Sep-22 06-May-23 166

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 231 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L1024 CAD Glide Path Building C - MEP - Drawing Submission - prepare document C01_7 d/w - 10h/d - No HK 21 18-Mar-22 A 23-Aug-22 09-Sep-22 05-Feb-23 166
Hols - No B/O periods (was
310.D.WS.L1588 CAD Glide Path Building C - MEP - Drawing Submission - PM review and accept 1st C1)
C01_7 d/w - 10h/d - No HK 150 26-Apr-22 22-Sep-22 09-Oct-22 07-Mar-23 166
Round Hols - No B/O periods (was
310.D.WS.L1584 CAD Glide Path Building C - MEP - Drawing Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 150 26-May-22 22-Oct-22 08-Nov-22 06-Apr-23 166
Hols - No B/O periods (was
310.D.WS.L1028 CAD Glide Path Building C - MEP - Drawing Submission - PM review and accept 2nd C1)
C01_7 d/w - 10h/d - No HK 150 25-Jun-22 21-Nov-22 08-Dec-22 06-May-23 166
Round Hols - No B/O periods (was
CAD Glide Path Building C - ABWF Submission C1)
C01_7 d/w - 10h/d - No HK Hols119
- No B/O periods
0 (was12-Jul-22
C1) 07-Nov-22 13-Aug-22 09-Dec-22 32
CAD Glide Path Building C - ABWF - Drawing Submission C01_7 d/w - 10h/d - No HK Hols91
- No B/O periods
0 (was12-Jul-22
C1) 10-Oct-22 13-Aug-22 11-Nov-22 32
310.D.WS.L1312 CAD Glide Path Building C - ABWF - prepare document C01_7 d/w - 10h/d - No HK 21 12-Jul-22 01-Aug-22 13-Aug-22 02-Sep-22 32
Hols - No B/O periods (was
310.D.WS.L1908 CAD Glide Path Building C - ABWF - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 28 02-Aug-22 29-Aug-22 03-Sep-22 30-Sep-22 32
Hols - No B/O periods (was
310.D.WS.L1904 CAD Glide Path Building C - ABWF - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 14 30-Aug-22 12-Sep-22 01-Oct-22 14-Oct-22 32
Hols - No B/O periods (was
310.D.WS.L1316 CAD Glide Path Building C - ABWF - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 28 13-Sep-22 10-Oct-22 15-Oct-22 11-Nov-22 32
Hols - No B/O periods (was
CAD Glide Path Building C - ABWF - Material Submission C1)
C01_7 d/w - 10h/d - No HK Hols98
- No B/O periods
0 (was02-Aug-22
C1) 07-Nov-22 10-Sep-22 09-Dec-22 32
310.D.WS.L1328 CAD Glide Path Building C - ABWF - Material Submission - prepare document C01_7 d/w - 10h/d - No HK 21 02-Aug-22 22-Aug-22 10-Sep-22 30-Sep-22 39
Hols - No B/O periods (was
310.D.WS.L1916 CAD Glide Path Building C - ABWF - Material Submission - PM review and accept 1st C1)
C01_7 d/w - 10h/d - No HK 28 23-Aug-22 19-Sep-22 01-Oct-22 28-Oct-22 39
Round Hols - No B/O periods (was
310.D.WS.L1912 CAD Glide Path Building C - ABWF - Material Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 14 20-Sep-22 03-Oct-22 29-Oct-22 11-Nov-22 39
Hols - No B/O periods (was
310.D.WS.L1332 CAD Glide Path Building C - ABWF - Material Submission - PM review and accept 2nd C1)
C01_7 d/w - 10h/d - No HK 28 11-Oct-22 07-Nov-22 12-Nov-22 09-Dec-22 32
Round Hols - No B/O periods (was
Subletting & Procurement C1)
C01_7 d/w - 10h/d - No HK Hols440
- No B/O periods
0 (was
30-Oct-21
C1) A 14-Apr-23 14-Apr-22 06-May-23 22
Subletting C01_7 d/w - 10h/d - No HK Hols181
- No B/O periods
0 (was
30-Oct-21
C1) A 29-Jul-22 14-Apr-22 09-Feb-23 195
310.P.EX.F120 Subletting - Optional Works MEP - Award sub-contract C01_7 d/w - 10h/d - No HK 90 30-Oct-21 A 18-Jan-22 A 13-Aug-22 13-Aug-22
Hols - No B/O periods (was
310.P.EX.F124 Subletting - Optional Works ABWF (Plastering) - Stage 1&2 Preparation,Submission& C1)
C01_7 d/w - 10h/d - No HK 90 03-Jan-22 A 20-Apr-22 19-Jul-22 12-Aug-22 114
Approval,Tender&Award sub-contract Hols - No B/O periods (was
310.P.EX.F164.B01 Subletting - Optional Works ABWF (Painting) - Stage 1&2 Preparation,Submission& C1)
C01_7 d/w - 10h/d - No HK 90 03-Jan-22 A 25-Apr-22 14-Jul-22 12-Aug-22 109
Approval,Tender&Award sub-contract Hols - No B/O periods (was
310.P.EX.F168.B01 Subletting - Optional Works ABWF (Door) - Stage 1&2 Preparation,Submission& C1)
C01_7 d/w - 10h/d - No HK 90 03-Jan-22 A 25-Apr-22 14-Jul-22 12-Aug-22 109
Approval,Tender&Award sub-contract Hols - No B/O periods (was
310.P.EX.F172.B01 Subletting-Optional Wk ABWF (Louver,Window,etc)-Stage 1&2 Preparation,Submission& C1)
C01_7 d/w - 10h/d - No HK 90 03-Jan-22 A 25-Apr-22 14-Jul-22 12-Aug-22 109
Approval,Tender&Award sub-contract Hols - No B/O periods (was
310.P.EX.F176.B01 Subletting - Optional Works ABWF (Steel&Metal)- Stage 1&2 Preparation,Submission& C1)
C01_7 d/w - 10h/d - No HK 90 03-Jan-22 A 25-Apr-22 14-Jul-22 12-Aug-22 109
Approval,Tender&Award sub-contract Hols - No B/O periods (was
310.P.EX.F165.B02 Provision of Record Plan for Demolition Works C1)
C01_7 d/w - 10h/d - No HK 0 27-Mar-22 14-Apr-22 19
Hols - No B/O periods (was
310.P.EX.F164.B02 Subletting - Demolition Works - Stage 1&2 Preparation,Submission& C1)
C01_7 d/w - 10h/d - No HK 60 27-Mar-22 25-May-22 15-Apr-22 13-Jun-22 19
Approval,Tender&Award sub-contract Hols - No B/O periods (was
310.P.EX.F156 Subletting - Optional Works Earthwork - Stage 1&2 Preparation,Submission& C1)
C01_7 d/w - 10h/d - No HK 90 01-May-22 29-Jul-22 12-Nov-22 09-Feb-23 195
Approval,Tender&Award sub-contract Hols - No B/O periods (was
Procurement C1)
C01_7 d/w - 10h/d - No HK Hols277
- No B/O periods
0 (was12-Jul-22
C1) 14-Apr-23 03-Aug-22 06-May-23 22
Major Materials ABWF C01_7 d/w - 10h/d - No HK Hols148
- No B/O periods
0 (was08-Nov-22
C1) 04-Apr-23 10-Dec-22 06-May-23 32
310.P.RC.P222 Glide Path Bldg. C (Procurement ABWF) - louvres,doors,raised floors C01_7 d/w - 10h/d - No HK 14 08-Nov-22 21-Nov-22 10-Dec-22 23-Dec-22 32
panels&Others-Place Order Hols - No B/O periods (was
C1)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 232 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.P.RC.P226 Glide Path Bldg. C (Procurement ABWF) - Manufacturing of Materials C01_7 d/w - 10h/d - No HK 120 22-Nov-22 21-Mar-23 24-Dec-22 22-Apr-23 32
Hols - No B/O periods (was
310.P.RC.P234 Glide Path Bldg. C (Procurement ABWF) - Delivery of Materials C1)
C01_7 d/w - 10h/d - No HK 14 22-Mar-23 04-Apr-23 23-Apr-23 06-May-23 32
Hols - No B/O periods (was
Major Materials MEP C1)
C01_7 d/w - 10h/d - No HK Hols277
- No B/O periods
0 (was12-Jul-22
C1) 14-Apr-23 03-Aug-22 06-May-23 22
310.P.RC.P210 Glide Path Bldg. C (Procurement FS and P&D Major Equipment) -NOVEC 1230, FA& C01_7 d/w - 10h/d - No HK 140 12-Jul-22 28-Nov-22 03-Aug-22 20-Dec-22 22
Others-Place Order for Materials Hols - No B/O periods (was
310.P.RC.P214 Glide Path Bldg. C (Procurement Electrical & MVAC Major Equipment) -AC/fan, LV C1)
C01_7 d/w - 10h/d - No HK 60 01-Aug-22 29-Sep-22 10-Nov-22 08-Jan-23 101
switchboard, genset&Others-Place Order Hols - No B/O periods (was
310.P.RC.P662 Glide Path Bldg. C (Procurement FS and P&D Major Equipment) - NOVEC 1230 system, C1)
C01_7 d/w - 10h/d - No HK 240 11-Aug-22 07-Apr-23 02-Sep-22 29-Apr-23 22
FA& Others-Manufacturing of Materials Hols - No B/O periods (was
310.P.RC.P666 Glide Path Bldg. C (Procurement Electrical & MVAC Major Equipment) - AC/fan, LV C1)
C01_7 d/w - 10h/d - No HK 120 31-Aug-22 28-Dec-22 10-Dec-22 08-Apr-23 101
switchboard, genset &Others Manufacting Hols - No B/O periods (was
310.P.RC.P670 Glide Path Bldg. C (Procurement MEP) - Delivery of Materials C1)
C01_7 d/w - 10h/d - No HK 28 18-Mar-23 14-Apr-23 09-Apr-23 06-May-23 22
Hols - No B/O periods (was
Construction - Glide Path Bldg C C1) 632 3 07-Jun-21 A 21-Jul-23 26-May-22 20-Aug-23 25
Initial Works 298 0 07-Jun-21 A 07-Jun-22 26-May-22 02-Aug-22 47
310.C.RC.P002 Glide Path Bldg C - Site Access WA 3310/4 C01_7 d/w - 10h/d - No HK 0 07-Jun-21 A 26-May-22
Hols - No B/O periods (was
310.C.RC.P004 Glide Path Bldg C - Coordination meeting with AA/CAD to allow advance GI works, secure C1)
C01_7 d/w - 10h/d - No HK 14 22-Jul-21 A 04-Aug-21 A 26-May-22 26-May-22
work permit Hols - No B/O periods (was
310.C.RC.P008 Glide Path Bldg C - Carry out detection to locate existing UU C1)
C11_6 d/w - 10h/d - With 6 09-Dec-21 A 09-Dec-21 A 26-May-22 26-May-22
HK Hols - No B/O periods
310.C.RC.P012 Glide Path Bldg C - Carry out trial pits (was
C11_6C3)
d/w - 10h/d - With 12 28-Mar-22 11-Apr-22 26-May-22 09-Jun-22 46
HK Hols - No B/O periods
310.C.RC.P016 Glide Path Bldg C - Install instrumentations (Qty: 9 nos.) (was
C11_6C3)
d/w - 10h/d - With 7 12-Apr-22 22-Apr-22 10-Jun-22 17-Jun-22 46
HK Hols - No B/O periods
310.C.RC.P020 Glide Path Bldg C - Ground investigation (GI) (No. of rigs: 2 nos) + report (was
C11_6C3)
d/w - 10h/d - With 14 23-Apr-22 10-May-22 18-Jun-22 05-Jul-22 46
HK Hols - No B/O periods
310.C.RC.P024 Glide Path Bldg C - Submit report to PM for review and submit to BD including Form BA14 (was
C01_7C3)
d/w - 10h/d - No HK 28 11-May-22 07-Jun-22 06-Jul-22 02-Aug-22 56
for Completion Hols - No B/O periods (was
Excavation Works C1) 113 0 19-Oct-22 05-Mar-23 20-Oct-22 06-Mar-23 1
310.C.RC.P025 Glide Path Bldg C - submit BA10 notice of commencement of work C01_7 d/w - 10h/d - No HK 7 19-Oct-22 25-Oct-22 20-Oct-22 26-Oct-22 1
Hols - No B/O periods (was
310.C.RC.P028 Glide Path Bldg C -Vertical elements for the water cut-off (assumed perimeter 82m @ C1)
C03_7 d/w - 10h/d - With 20 26-Oct-22 14-Nov-22 27-Oct-22 15-Nov-22 1
600mm sheet pile) HK Hols - No B/O periods
310.C.RC.P032 Glide Path Bldg C - Install dewatering wells and observation wells C03_7 d/w - 10h/d - With 10 09-Nov-22 18-Nov-22 10-Nov-22 19-Nov-22 1
HK Hols - No B/O periods
310.C.RC.P036 Glide Path Bldg C - Pumping test C03_7 d/w - 10h/d - With 28 19-Nov-22 16-Dec-22 20-Nov-22 17-Dec-22 1
HK Hols - No B/O periods
310.C.RC.P040 Glide Path Bldg C - Submit pumping test report to AA for review/comments C03_7 d/w - 10h/d - With 14 17-Dec-22 02-Jan-23 18-Dec-22 03-Jan-23 1
HK Hols - No B/O periods
310.C.RC.P044 Glide Path Bldg C - Revise/amend pumping test report and submit to AA C03_7 d/w - 10h/d - With 7 03-Jan-23 09-Jan-23 04-Jan-23 10-Jan-23 1
HK Hols - No B/O periods
310.C.RC.P048 Glide Path Bldg C - AA submit final pumping test report to BD + BA8 consent application C01_7 d/w - 10h/d - No HK 28 10-Jan-23 06-Feb-23 11-Jan-23 07-Feb-23 1
(excavation) Hols - No B/O periods (was
310.C.RC.P052 Glide Path Bldg C - BD acknowledge and issue consent letter C1)
C01_7 d/w - 10h/d - No HK 0 06-Feb-23 07-Feb-23 1
Hols - No B/O periods (was
310.C.RC.P056 Glide Path Bldg C - Submit BA10 notice of commencement of work C1)
C03_7 d/w - 10h/d - With 7 07-Feb-23 13-Feb-23 08-Feb-23 14-Feb-23 1
HK Hols - No B/O periods

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 233 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.RC.P060 Glide Path Bldg C - Excavation to FL (Soil: 3192 m3 @ 300m3/day C03_7 d/w - 10h/d - With 10 14-Feb-23 23-Feb-23 15-Feb-23 24-Feb-23 1
HK Hols - No B/O periods
310.C.RC.P064 Glide Path Bldg C - Plate load test (Qty: 1 no.) C03_7 d/w - 10h/d - With 10 24-Feb-23 05-Mar-23 25-Feb-23 06-Mar-23 1
HK Hols - No B/O periods
Structural Works C03_7 d/w - 10h/d - With HK Hols
71- No B/O 0periods 06-Mar-23 21-May-23 07-Mar-23 27-Jul-23 64
310.C.RC.P068 Glide Path Bldg C - B1 Level - construction of footing (Concrete: 276 m3) C03_7 d/w - 10h/d - With 9 06-Mar-23 14-Mar-23 07-Mar-23 15-Mar-23 1
HK Hols - No B/O periods
310.C.RC.P072 Glide Path Bldg C - B1 Level - construction of screen walls , bearing walls (Concrete: 216 C03_7 d/w - 10h/d - With 14 15-Mar-23 28-Mar-23 16-Mar-23 29-Mar-23 1
m3) HK Hols - No B/O periods
310.C.RC.P076 Glide Path Bldg C - Ground Level - construction of beam and base slab (Concrete: 168 C03_7 d/w - 10h/d - With 18 29-Mar-23 20-Apr-23 30-Mar-23 21-Apr-23 1
m3) HK Hols - No B/O periods
310.C.RC.P080 Glide Path Bldg C - Construction of concrete stairs + B1 Level mass concrete (Concrete: C03_7 d/w - 10h/d - With 16 21-Apr-23 07-May-23 02-Jun-23 17-Jun-23 40
48 m3) HK Hols - No B/O periods
310.C.RC.P084 Glide Path Bldg C - Waterproofing - roofs (2 layers) and walls (Area: 936 m2) C03_7 d/w - 10h/d - With 30 21-Apr-23 21-May-23 27-Jun-23 27-Jul-23 64
HK Hols - No B/O periods
ABWF Works C03_7 d/w - 10h/d - With HK Hols
48- No B/O 0periods 28-Apr-23 16-Jun-23 29-Apr-23 17-Jun-23 1
310.C.RC.P088 Glide Path Bldg C - Commence ABWF works C03_7 d/w - 10h/d - With 0 28-Apr-23 29-Apr-23 1
HK Hols - No B/O periods
310.C.RC.P092 Glide Path Bldg C - ABWF Internal Works C03_7 d/w - 10h/d - With 48 28-Apr-23 16-Jun-23 29-Apr-23 17-Jun-23 1
HK Hols - No B/O periods
E&M Works C03_7 d/w - 10h/d - With HK Hols
42- No B/O 0periods 06-May-23 17-Jun-23 07-May-23 18-Jun-23 1
310.C.RC.P104 Glide Path Bldg C - Commence MEP works C03_7 d/w - 10h/d - With 0 06-May-23 07-May-23 1
HK Hols - No B/O periods
Drainage Installation C03_7 d/w - 10h/d - With HK Hols
42- No B/O 0periods 06-May-23 17-Jun-23 07-May-23 18-Jun-23 1
310.C.RC.P108 Glide Path Bldg C - Drainage 1st Fix & Installation C03_7 d/w - 10h/d - With 30 06-May-23 05-Jun-23 07-May-23 06-Jun-23 1
HK Hols - No B/O periods
310.C.RC.P109.B01 Glide Path Bldg C - Drainage 2nd Fix & Installation C03_7 d/w - 10h/d - With 30 13-May-23 12-Jun-23 14-May-23 13-Jun-23 1
HK Hols - No B/O periods
310.C.RC.P110.B01 Glide Path Bldg C - Drainage Final Fix & Adjustment C03_7 d/w - 10h/d - With 5 13-Jun-23 17-Jun-23 14-Jun-23 18-Jun-23 1
HK Hols - No B/O periods
Electrical Installation C03_7 d/w - 10h/d - With HK Hols
42- No B/O 0periods 06-May-23 17-Jun-23 07-May-23 18-Jun-23 1
310.C.RC.P111.B01 Glide Path Bldg C - Electrical 1st Fix & Installation C03_7 d/w - 10h/d - With 30 06-May-23 05-Jun-23 07-May-23 06-Jun-23 1
HK Hols - No B/O periods
310.C.RC.P112.B01 Glide Path Bldg C - Electrical 2nd Fix & Installation C03_7 d/w - 10h/d - With 30 13-May-23 12-Jun-23 14-May-23 13-Jun-23 1
HK Hols - No B/O periods
310.C.RC.P113.B01 Glide Path Bldg C - Switchgear Installation C03_7 d/w - 10h/d - With 18 24-May-23 11-Jun-23 27-May-23 13-Jun-23 2
HK Hols - No B/O periods
310.C.RC.P114.B01 Glide Path Bldg C - Power On to All Floors C03_7 d/w - 10h/d - With 0 12-Jun-23 13-Jun-23 1
HK Hols - No B/O periods
310.C.RC.P115.B01 Glide Path Bldg C - Electrical Final Fix & Adjustment C03_7 d/w - 10h/d - With 5 13-Jun-23 17-Jun-23 14-Jun-23 18-Jun-23 1
HK Hols - No B/O periods
Fire Services Installation C03_7 d/w - 10h/d - With HK Hols
42- No B/O 0periods 06-May-23 17-Jun-23 07-May-23 18-Jun-23 1
310.C.RC.P116.B01 Glide Path Bldg C - Fire Services 1st Fix & Installation C03_7 d/w - 10h/d - With 30 06-May-23 05-Jun-23 07-May-23 06-Jun-23 1
HK Hols - No B/O periods
310.C.RC.P117.B01 Glide Path Bldg C - Fire Services 2nd Fix & Installation C03_7 d/w - 10h/d - With 30 13-May-23 12-Jun-23 14-May-23 13-Jun-23 1
HK Hols - No B/O periods
310.C.RC.P118.B01 Glide Path Bldg C - Fire Service Final Fix & Adjustment C03_7 d/w - 10h/d - With 5 13-Jun-23 17-Jun-23 14-Jun-23 18-Jun-23 1
HK Hols - No B/O periods
MVAC Installation C03_7 d/w - 10h/d - With HK Hols
42- No B/O 0periods 06-May-23 17-Jun-23 07-May-23 18-Jun-23 1
310.C.RC.P119.B01 Glide Path Bldg C - MVAC 1st Fix & Installation C03_7 d/w - 10h/d - With 30 06-May-23 05-Jun-23 07-May-23 06-Jun-23 1
HK Hols - No B/O periods

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 234 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.RC.P120.B01 Glide Path Bldg C - MVAC 2nd Fix & Installation C03_7 d/w - 10h/d - With 30 13-May-23 12-Jun-23 14-May-23 13-Jun-23 1
HK Hols - No B/O periods
310.C.RC.P121.B01 Glide Path Bldg C - MVAC Final Fix & Adjustment C03_7 d/w - 10h/d - With 5 13-Jun-23 17-Jun-23 14-Jun-23 18-Jun-23 1
HK Hols - No B/O periods
Airport System C03_7 d/w - 10h/d - With HK Hols
60- No B/O 0periods 06-May-23 07-Jul-23 15-May-23 16-Jul-23 9
310.C.RC.P132 Glide Path Bldg C (Airport System) - VDC, BCS C03_7 d/w - 10h/d - With 60 06-May-23 07-Jul-23 15-May-23 16-Jul-23 9
HK Hols - No B/O periods
External Works (Drainage and UU Works & EVA) 75 3 21-Apr-23 21-Jul-23 21-May-23 20-Aug-23 25
310.C.RC.P152 Glide Path Bldg C (Civil Works) - CLP ducting, sleeving, drawpits C03_7 d/w - 10h/d - With 30 21-Apr-23 21-May-23 27-May-23 26-Jun-23 34
HK Hols - No B/O periods
310.C.RC.P148 Glide Path Bldg C (Civil Works) - Building drainage, manholes, pipe laying and connect to C03_7 d/w - 10h/d - With 30 21-Apr-23 21-May-23 21-May-23 20-Jun-23 29
stormwater manhole HK Hols - No B/O periods
310.C.RC.P730 Glide Path Bldg C (Civil Works) - Comm ducting, sleeving, drawpits C03_7 d/w - 10h/d - With 30 21-Apr-23 21-May-23 27-May-23 26-Jun-23 34
HK Hols - No B/O periods
310.C.RC.P156 Glide Path Bldg C (Civil Works) - Watermain + connection C03_7 d/w - 10h/d - With 45 12-May-23 27-Jun-23 11-Jun-23 27-Jul-23 29
HK Hols - No B/O periods
310.C.RC.P734 Glide Path Bldg C (Civil Works) - CLP cable laying C03_7 d/w - 10h/d - With 30 3 22-May-23 21-Jun-23 27-Jun-23 27-Jul-23 34
HK Hols - No B/O periods
310.T.EX.L448 Glide Path Bldg C (Civil Works) - EVA works C01_7 d/w - 10h/d - No HK 24 28-Jun-23 21-Jul-23 28-Jul-23 20-Aug-23 30
Hols - No B/O periods (was
Testing and Commissioning C1) 92 0 18-Jun-23 07-Oct-23 19-Jun-23 07-Oct-23 0
Testing and Commissioning C01_7 d/w - 10h/d - No HK Hols41
- No B/O periods
0 (was18-Jun-23
C1) 28-Jul-23 19-Jun-23 14-Sep-23 48
310.T.EX.L352 Glide Path Bldg C - Building Services System Test (Electrical, Ventilation, FS System, C01_7 d/w - 10h/d - No HK 21 18-Jun-23 08-Jul-23 19-Jun-23 09-Jul-23 1
Plumbing etc) Hols - No B/O periods (was
310.T.EX.L353.B01 Glide Path Bldg C - Fire Service T&C (Non-FSI) C1)
C01_7 d/w - 10h/d - No HK 21 18-Jun-23 08-Jul-23 25-Aug-23 14-Sep-23 68
Hols - No B/O periods (was
310.C.ES.P780 Glide Path Bldg C - Airport System T&C - VDC, BCS C1)
C01_7 d/w - 10h/d - No HK 21 08-Jul-23 28-Jul-23 17-Jul-23 06-Aug-23 9
Hols - No B/O periods (was
Statutory Inspection C1) 76 0 10-Jul-23 07-Oct-23 10-Jul-23 07-Oct-23 0
Fire Services Department (FSD) C11_6 d/w - 10h/d - With HK Hols
58- No B/O 0periods (was
10-Jul-23
C3) 14-Sep-23 10-Jul-23 14-Sep-23 0
310.T.WS.T976 Glide Path Bldg C - F.S. Inspection Plan (Form FSI / 314 Submission) C11_6 d/w - 10h/d - With 0 10-Jul-23 10-Jul-23 0
HK Hols - No B/O periods
310.T.WS.T980 Glide Path Bldg C - F.S. Inspection Application (Form FSI / 501 & 251 Submission) (was
C11_6C3)
d/w - 10h/d - With 0 07-Aug-23 07-Aug-23 0
HK Hols - No B/O periods
310.T.WS.T984 Glide Path Bldg C - F.S. 1st Inspection (was
C11_6C3)
d/w - 10h/d - With 6 21-Aug-23 26-Aug-23 21-Aug-23 26-Aug-23 0
HK Hols - No B/O periods
310.T.WS.T988 Glide Path Bldg C - FSD Comment (was
C11_6C3)
d/w - 10h/d - With 0 26-Aug-23 26-Aug-23 0
HK Hols - No B/O periods
310.T.WS.T992 Glide Path Bldg C - Rectification & Adjustment (was
C11_6C3)
d/w - 10h/d - With 10 28-Aug-23 07-Sep-23 28-Aug-23 07-Sep-23 0
HK Hols - No B/O periods
310.T.WS.T996 Glide Path Bldg C - F.S. Re-inspection (was
C11_6C3)
d/w - 10h/d - With 6 08-Sep-23 14-Sep-23 08-Sep-23 14-Sep-23 0
HK Hols - No B/O periods
310.T.WS.T1000 Glide Path Bldg C - Issue F.S. Certificate (Form FS172) (was
C11_6C3)
d/w - 10h/d - With 0 14-Sep-23 14-Sep-23 0
HK Hols - No B/O periods
Building Department (BD) (was C3) 18 0 15-Sep-23 07-Oct-23 15-Sep-23 07-Oct-23 0
310.T.WS.T1364 Glide Path Bldg C - BD Inspection Application for Occupation Permit (Form BA13 C11_6 d/w - 10h/d - With 0 15-Sep-23 15-Sep-23 0
Submission) HK Hols - No B/O periods
310.T.WS.T1368 Glide Path Bldg C - BD 1st Inspection (was
C11_6C3)
d/w - 10h/d - With 6 15-Sep-23 21-Sep-23 15-Sep-23 21-Sep-23 0
HK Hols - No B/O periods
310.T.WS.T1372 Glide Path Bldg C - BD Comment (was
C11_6C3)
d/w - 10h/d - With 0 21-Sep-23 21-Sep-23 0
HK Hols - No B/O periods
(was C3)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 235 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.T.WS.T1376 Glide Path Bldg C - Rectification & Adjustment C11_6 d/w - 10h/d - With 6 22-Sep-23 28-Sep-23 22-Sep-23 28-Sep-23 0
HK Hols - No B/O periods
310.T.WS.T1380 Glide Path Bldg C - BD Re-inspection (was
C11_6C3)
d/w - 10h/d - With 6 29-Sep-23 07-Oct-23 29-Sep-23 07-Oct-23 0
HK Hols - No B/O periods
310.T.RC.P151 Glide Path Bldg C (T&C) - Achieved KD-G2(b) - CAD glide path antenna platform & (was
C01_7C3)
d/w - 10h/d - No HK 0 07-Oct-23 07-Oct-23 0
equipment Hols - No B/O periods (was
310.T.WS.T1384 Glide Path Bldg C - Issue Occupation Permit (Form BD104) C1)
C11_6 d/w - 10h/d - With 0 07-Oct-23 07-Oct-23 0
HK Hols - No B/O periods
Demolition of Old Glide Path Bldg. C (was C3) 211 0 26-May-22 07-Feb-23 30-Jun-22 14-Mar-23 30
Demolition Plan For Existing Facilities C01_7 d/w - 10h/d - No HK Hols156
- No B/O periods
0 (was26-May-22
C1) 28-Oct-22 30-Jun-22 02-Dec-22 35
310.D.G3.F240.B01 Demolition Plan for Demolish Existing Facilities - prepare design and submit with ICE C01_7 d/w - 10h/d - No HK 14 26-May-22 08-Jun-22 30-Jun-22 13-Jul-22 35
Hols - No B/O periods (was
310.D.G3.F244.B01 Demolition Plan for Demolish Existing Facilities - PM, AP, RSE reviewing C1)
C01_7 d/w - 10h/d - No HK 28 09-Jun-22 06-Jul-22 14-Jul-22 10-Aug-22 35
Hols - No B/O periods (was
310.D.G3.F248.B01 Demolition Plan for Demolish Existing Facilities - ICC, M&VC review design and issue C1)
C01_7 d/w - 10h/d - No HK 21 07-Jul-22 27-Jul-22 11-Aug-22 31-Aug-22 35
check certificates Hols - No B/O periods (was
310.D.G3.F251.B01 Demolition Plan for Demolish Existing Facilities - address comments and resubmit with C1)
C01_7 d/w - 10h/d - No HK 7 28-Jul-22 03-Aug-22 01-Sep-22 07-Sep-22 35
ICE 2nd Round Hols - No B/O periods (was
310.D.G3.F253.B01 Demolition Plan for Demolish Existing Facilities - PM, AP, RSE reviewing 2nd Round C1)
C01_7 d/w - 10h/d - No HK 21 04-Aug-22 24-Aug-22 08-Sep-22 28-Sep-22 35
Hols - No B/O periods (was
310.D.G3.F257.B01 Demolition Plan for Demolish Existing Facilities - ICC, M&VA review design and issue C1)
C01_7 d/w - 10h/d - No HK 21 25-Aug-22 14-Sep-22 29-Sep-22 19-Oct-22 35
check certificates 2nd Round Hols - No B/O periods (was
310.D.G3.F263.B01 Demolition Plan for Demolish Existing Facilities - BD approve C1)
C01_7 d/w - 10h/d - No HK 30 15-Sep-22 14-Oct-22 20-Oct-22 18-Nov-22 35
Hols - No B/O periods (was
310.D.G3.F267.B01 Demolition Plan for Demolish Existing Facilities - prepare and submit Form BA8 and grant C1)
C01_7 d/w - 10h/d - No HK 7 15-Oct-22 21-Oct-22 19-Nov-22 25-Nov-22 35
consent Hols - No B/O periods (was
310.D.G3.F272.B01 Demolition Plan for Demolish Existing Facilities - prepare and submit Form BA10 to notify C1)
C01_7 d/w - 10h/d - No HK 7 22-Oct-22 28-Oct-22 26-Nov-22 02-Dec-22 35
work commencement Hols - No B/O periods (was
Demolition Works C1) 200 0 09-Jun-22 07-Feb-23 14-Sep-22 14-Mar-23 30
310.C.RC.P169 Ex. Glide Path Bldg C - submit Method Statement to Demolish Existing Facilities C11_6 d/w - 10h/d - With 21 09-Jun-22 04-Jul-22 14-Sep-22 10-Oct-22 81
HK Hols - No B/O periods
310.C.RC.P173 Ex. Glide Path Bldg C - PM review MS (was
C11_6C3)
d/w - 10h/d - With 28 05-Jul-22 05-Aug-22 11-Oct-22 11-Nov-22 81
HK Hols - No B/O periods
310.C.RC.P163 Ex. Glide Path Bldg C - Application of Work Permit for Demolition of Old Glide Path Bldg. (was
C01_7C3)
d/w - 10h/d - No HK 21 06-Aug-22 26-Aug-22 12-Nov-22 02-Dec-22 98
C Hols - No B/O periods (was
310.C.RC.P165 Ex. Glide Path Bldg C - Coordinate with CAD to decommission the existing facilities C1)
C11_6 d/w - 10h/d - With 30 11-Aug-22 15-Sep-22 29-Oct-22 02-Dec-22 65
HK Hols - No B/O periods
310.C.RC.P161 Closure of Existing North Runway (was
C01_7C3)
d/w - 10h/d - No HK 0 01-Sep-22 03-Dec-22 93
Hols - No B/O periods (was
310.C.RC.P177 Ex. Glide Path Bldg C - Decommissioning C1)
C11_6 d/w - 10h/d - With 7 29-Oct-22 05-Nov-22 03-Dec-22 10-Dec-22 30
HK Hols - No B/O periods
310.C.RC.P181 Ex. Glide Path Bldg C - removal of existing CAD facilities (was
C11_6C3)
d/w - 10h/d - With 30 07-Nov-22 10-Dec-22 12-Dec-22 17-Jan-23 30
HK Hols - No B/O periods
310.C.RC.P185 Ex. Glide Path Bldg C - demolish structure (was
C11_6C3)
d/w - 10h/d - With 45 12-Dec-22 07-Feb-23 18-Jan-23 14-Mar-23 30
HK Hols - No B/O periods
CAD Glide Path Building D (was C3) 696 3 07-Jun-21 A 06-Oct-23 09-Jun-22 08-Oct-23 1
Design and Submission - ELS C01_7 d/w - 10h/d - No HK Hols186
- No B/O periods
0 (was
01-Dec-21
C1) A 07-Jun-22 09-Jun-22 19-Oct-22 134
310.D.RC.P56 Glide Path Bldg D - Prepare Design of ELS for Foundation Works C01_7 d/w - 10h/d - No HK 28 01-Dec-21 A 21-Dec-21 A 09-Jun-22 09-Jun-22
Hols - No B/O periods (was
310.D.RC.P60 Glide Path Bldg D - ICE review and issue check certificate C1)
C01_7 d/w - 10h/d - No HK 7 22-Dec-21 A 23-Dec-21 A 09-Jun-22 09-Jun-22
Hols - No B/O periods (was
C1)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 236 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.RC.P64 Glide Path Bldg D - Review by PM, AP, RSE, RGE C01_7 d/w - 10h/d - No HK 28 23-Dec-21 A 20-Jan-22 A 09-Jun-22 09-Jun-22
Hols - No B/O periods (was
310.D.RC.P80 Glide Path Bldg D - BD review and approves design C1)
C01_7 d/w - 10h/d - No HK 60 21-Jan-22 A 25-Apr-22 09-Jun-22 08-Jul-22 74
Hols - No B/O periods (was
310.D.RC.P534 Glide Path Bldg D - submit BA8 consent application (excavation + structure) C1)
C01_7 d/w - 10h/d - No HK 28 11-May-22 07-Jun-22 22-Sep-22 19-Oct-22 134
Hols - No B/O periods (was
Method Statement for Plate Load Test for Glide Path Building D C1)
C01_7 d/w - 10h/d - No HK Hols58
- No B/O periods
0 (was20-Oct-22
C1) 16-Dec-22 09-Nov-22 05-Jan-23 20
310.D.TX.A300 Method Statement for Plate Load Test for Glide Path Building D - prepare document C01_7 d/w - 10h/d - No HK 30 20-Oct-22 18-Nov-22 09-Nov-22 08-Dec-22 20
Hols - No B/O periods (was
310.D.TX.A304 Method Statement for Plate Load Test for Glide Path Building D - BD Acknowledgement C1)
C01_7 d/w - 10h/d - No HK 28 19-Nov-22 16-Dec-22 09-Dec-22 05-Jan-23 20
Hols - No B/O periods (was
CAD Glide Path Building D - MEP Submission C1)
C01_7 d/w - 10h/d - No HK Hols227
- No B/O periods
0 (was
21-Mar-22
C1) A 01-Dec-22 26-Aug-22 02-May-23 152
CAD Glide Path Building D - MEP - Drawing Submission C01_7 d/w - 10h/d - No HK Hols227
- No B/O periods
0 (was
21-Mar-22
C1) A 01-Dec-22 26-Aug-22 02-May-23 152
310.D.WS.L1048 CAD Glide Path Building D - MEP - Drawing Submission - prepare document C01_7 d/w - 10h/d - No HK 150 21-Mar-22 A 02-Sep-22 26-Aug-22 01-Feb-23 152
Hols - No B/O periods (was
310.D.WS.L1612 CAD Glide Path Building D - MEP - Drawing Submission - PM review and accept 1st C1)
C01_7 d/w - 10h/d - No HK 160 26-Apr-22 02-Oct-22 25-Sep-22 03-Mar-23 152
Round Hols - No B/O periods (was
310.D.WS.L1608 CAD Glide Path Building D - MEP - Drawing Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 160 26-May-22 01-Nov-22 25-Oct-22 02-Apr-23 152
Hols - No B/O periods (was
310.D.WS.L1052 CAD Glide Path Building D - MEP - Drawing Submission - PM review and accept 2nd C1)
C01_7 d/w - 10h/d - No HK 160 25-Jun-22 01-Dec-22 24-Nov-22 02-May-23 152
Round Hols - No B/O periods (was
CAD Glide Path Building D - ABWF Submission C1)
C01_7 d/w - 10h/d - No HK Hols119
- No B/O periods
0 (was12-Jul-22
C1) 07-Nov-22 24-Jul-22 19-Nov-22 12
CAD Glide Path Building D - ABWF - Drawing Submission C01_7 d/w - 10h/d - No HK Hols91
- No B/O periods
0 (was12-Jul-22
C1) 10-Oct-22 24-Jul-22 22-Oct-22 12
310.D.WS.L1336 CAD Glide Path Building D - ABWF - prepare document C01_7 d/w - 10h/d - No HK 21 12-Jul-22 01-Aug-22 24-Jul-22 13-Aug-22 12
Hols - No B/O periods (was
310.D.WS.L1924 CAD Glide Path Building D - ABWF - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 28 02-Aug-22 29-Aug-22 14-Aug-22 10-Sep-22 12
Hols - No B/O periods (was
310.D.WS.L1920 CAD Glide Path Building D - ABWF - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 14 30-Aug-22 12-Sep-22 11-Sep-22 24-Sep-22 12
Hols - No B/O periods (was
310.D.WS.L1340 CAD Glide Path Building D - ABWF - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 28 13-Sep-22 10-Oct-22 25-Sep-22 22-Oct-22 12
Hols - No B/O periods (was
CAD Glide Path Building D - ABWF - Material Submission C1)
C01_7 d/w - 10h/d - No HK Hols98
- No B/O periods
0 (was02-Aug-22
C1) 07-Nov-22 21-Aug-22 19-Nov-22 12
310.D.WS.L1352 CAD Glide Path Building D - ABWF - Material Submission - prepare document C01_7 d/w - 10h/d - No HK 21 02-Aug-22 22-Aug-22 21-Aug-22 10-Sep-22 19
Hols - No B/O periods (was
310.D.WS.L1932 CAD Glide Path Building D - ABWF - Material Submission - PM review and accept 1st C1)
C01_7 d/w - 10h/d - No HK 28 23-Aug-22 19-Sep-22 11-Sep-22 08-Oct-22 19
Round Hols - No B/O periods (was
310.D.WS.L1928 CAD Glide Path Building D - ABWF - Material Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 14 20-Sep-22 03-Oct-22 09-Oct-22 22-Oct-22 19
Hols - No B/O periods (was
310.D.WS.L1356 CAD Glide Path Building D - ABWF - Material Submission - PM review and accept 2nd C1)
C01_7 d/w - 10h/d - No HK 28 11-Oct-22 07-Nov-22 23-Oct-22 19-Nov-22 12
Round Hols - No B/O periods (was
Subletting & Procurement C1)
C01_7 d/w - 10h/d - No HK Hols321
- No B/O periods
0 (was19-May-22
C1) 04-Apr-23 09-Jul-22 02-May-23 28
Major Materials ABWF C01_7 d/w - 10h/d - No HK Hols148
- No B/O periods
0 (was08-Nov-22
C1) 04-Apr-23 20-Nov-22 16-Apr-23 12
310.P.RC.P566 Glide Path Bldg. D (Procurement ABWF) - louvres, doors, raised floors panels & C01_7 d/w - 10h/d - No HK 14 08-Nov-22 21-Nov-22 20-Nov-22 03-Dec-22 12
Others-Place Order Hols - No B/O periods (was
310.P.RC.P570 Glide Path Bldg. D (Procurement ABWF) - Manufacturing of Materials C1)
C01_7 d/w - 10h/d - No HK 120 22-Nov-22 21-Mar-23 04-Dec-22 02-Apr-23 12
Hols - No B/O periods (was
310.P.RC.P578 Glide Path Bldg. D (Procurement ABWF) - Delivery of Materials C1)
C01_7 d/w - 10h/d - No HK 14 22-Mar-23 04-Apr-23 03-Apr-23 16-Apr-23 12
Hols - No B/O periods (was
Major Materials MEP C1)
C01_7 d/w - 10h/d - No HK Hols320
- No B/O periods
0 (was19-May-22
C1) 03-Apr-23 09-Jul-22 02-May-23 29
310.P.RC.P558 Glide Path Bldg. D (Procurement Electrical & MVAC Major Equipment) -AC/fan, LV C01_7 d/w - 10h/d - No HK 60 19-May-22 17-Jul-22 07-Oct-22 05-Dec-22 141
switchboard, genset &Others-Place Order Hols - No B/O periods (was
C1)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 237 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.P.RC.P554 Glide Path Bldg. D (Procurement FS and P&D Major Equipment) -NOVEC 1230 system, C01_7 d/w - 10h/d - No HK 140 10-Jun-22 27-Oct-22 09-Jul-22 25-Nov-22 29
FA&Others-Place Order for Materials Hols - No B/O periods (was
310.P.RC.P674 Glide Path Bldg. D (Procurement FS and P&D Major Equipment) - NOVEC 1230 system, C1) C01_7 d/w - 10h/d - No HK 240 10-Jul-22 06-Mar-23 08-Aug-22 04-Apr-23 29
FA system & Others Hols - No B/O periods (was
310.P.RC.P678 Glide Path Bldg. D (Procurement Electrical & MVAC Major Equipment) -AC/fan units, LV C1)
C01_7 d/w - 10h/d - No HK 120 18-Jul-22 14-Nov-22 06-Dec-22 04-Apr-23 141
switchboard, genset & Others Hols - No B/O periods (was
310.P.RC.P682 Glide Path Bldg. D (Procurement MEP) - Delivery of Materials C1)
C01_7 d/w - 10h/d - No HK 28 07-Mar-23 03-Apr-23 05-Apr-23 02-May-23 29
Hols - No B/O periods (was
Construction - Glide Path Bldg D C1) 654 3 07-Jun-21 A 16-Aug-23 13-Aug-22 17-Aug-23 1
Initial Works 298 0 07-Jun-21 A 07-Jun-22 13-Aug-22 19-Oct-22 111
310.C.RC.P204 Glide Path Bldg D - Site Access WA 3310/3 C01_7 d/w - 10h/d - No HK 0 07-Jun-21 A 13-Aug-22
Hols - No B/O periods (was
310.C.RC.P206 Glide Path Bldg D - Coordination meeting with AA/CAD to allow advance GI works, secure C1)
C01_7 d/w - 10h/d - No HK 30 22-Jul-21 A 20-Aug-21 A 13-Aug-22 13-Aug-22
work permit Hols - No B/O periods (was
310.C.RC.P212 Glide Path Bldg D - Carry out detection to locate existing UU C1)
C11_6 d/w - 10h/d - With 6 04-Dec-21 A 16-Dec-21 A 13-Aug-22 13-Aug-22
HK Hols - No B/O periods
310.C.RC.P216 Glide Path Bldg D - Carry out trial pits (was
C11_6C3)
d/w - 10h/d - With 12 28-Mar-22 11-Apr-22 13-Aug-22 26-Aug-22 112
HK Hols - No B/O periods
310.C.RC.P220 Glide Path Bldg D - Install instrumentations (Qty: 9 nos.) (was
C11_6C3)
d/w - 10h/d - With 7 12-Apr-22 22-Apr-22 27-Aug-22 03-Sep-22 112
HK Hols - No B/O periods
310.C.RC.P224 Glide Path Bldg D - Ground investigation (GI) (No. of rigs: 2 nos) + report (was
C11_6C3)
d/w - 10h/d - With 14 23-Apr-22 10-May-22 05-Sep-22 21-Sep-22 112
HK Hols - No B/O periods
310.C.RC.P228 Glide Path Bldg D - Submit report to PM for review and submit to BD including Form BA14 (was
C01_7C3)
d/w - 10h/d - No HK 28 11-May-22 07-Jun-22 22-Sep-22 19-Oct-22 134
for Completion Hols - No B/O periods (was
Excavation Works C1) 109 0 19-Oct-22 28-Feb-23 20-Oct-22 01-Mar-23 1
310.C.RC.P253 Glide Path Bldg D - submit BA10 notice of commencement of work C01_7 d/w - 10h/d - No HK 7 19-Oct-22 25-Oct-22 20-Oct-22 26-Oct-22 1
Hols - No B/O periods (was
310.C.RC.P256 Glide Path Bldg D -Vertical elements for the water cut-off (assumed perimeter 82m @ C1)
C03_7 d/w - 10h/d - With 20 26-Oct-22 14-Nov-22 27-Oct-22 15-Nov-22 1
600mm sheet pile) HK Hols - No B/O periods
310.C.RC.P232 Glide Path Bldg D - Install dewatering wells and observation wells C03_7 d/w - 10h/d - With 12 09-Nov-22 20-Nov-22 10-Nov-22 21-Nov-22 1
HK Hols - No B/O periods
310.C.RC.P236 Glide Path Bldg D - Pumping test C03_7 d/w - 10h/d - With 21 21-Nov-22 11-Dec-22 22-Nov-22 12-Dec-22 1
HK Hols - No B/O periods
310.C.RC.P240 Glide Path Bldg D - Submit pumping test report to AA for review/comments C03_7 d/w - 10h/d - With 14 12-Dec-22 27-Dec-22 13-Dec-22 28-Dec-22 1
HK Hols - No B/O periods
310.C.RC.P244 Glide Path Bldg D - Revise/amend pumping test report and submit to AA C03_7 d/w - 10h/d - With 7 28-Dec-22 04-Jan-23 29-Dec-22 05-Jan-23 1
HK Hols - No B/O periods
310.C.RC.P268 Glide Path Bldg D - AA submit final pumping test report to BD + BA8 consent application C01_7 d/w - 10h/d - No HK 28 05-Jan-23 01-Feb-23 06-Jan-23 02-Feb-23 1
(excavation) Hols - No B/O periods (was
310.C.RC.P272 Glide Path Bldg D - BD acknowledge and issue consent letter C1)
C01_7 d/w - 10h/d - No HK 0 01-Feb-23 02-Feb-23 1
Hols - No B/O periods (was
310.C.RC.P248 Glide Path Bldg D - Submit BA10 notice of commencement of work C1)
C01_7 d/w - 10h/d - No HK 7 02-Feb-23 08-Feb-23 03-Feb-23 09-Feb-23 1
Hols - No B/O periods (was
310.C.RC.P252 Glide Path Bldg D - Excavation to FL (Soil: 3192 m3 @ 300m3/day) C1)
C03_7 d/w - 10h/d - With 10 09-Feb-23 18-Feb-23 10-Feb-23 19-Feb-23 1
HK Hols - No B/O periods
310.C.RC.P260 Glide Path Bldg D - Plate load test (Qty: 1 no.) C03_7 d/w - 10h/d - With 10 19-Feb-23 28-Feb-23 20-Feb-23 01-Mar-23 1
HK Hols - No B/O periods
Structural Works C03_7 d/w - 10h/d - With HK Hols
71- No B/O 0periods 01-Mar-23 16-May-23 02-Mar-23 24-Jul-23 66
310.C.RC.P264 Glide Path Bldg D - B1 Level - construction of footing (Concrete: 276 m3) C03_7 d/w - 10h/d - With 9 01-Mar-23 09-Mar-23 02-Mar-23 10-Mar-23 1
HK Hols - No B/O periods

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 238 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.RC.P276 Glide Path Bldg D - B1 Level - construction of screen walls , bearing walls (Concrete: 216 C03_7 d/w - 10h/d - With 14 10-Mar-23 23-Mar-23 11-Mar-23 24-Mar-23 1
m3) HK Hols - No B/O periods
310.C.RC.P280 Glide Path Bldg D - Ground Level - construction of beam and base slab (Concrete: 168 C03_7 d/w - 10h/d - With 18 24-Mar-23 15-Apr-23 25-Mar-23 16-Apr-23 1
m3) HK Hols - No B/O periods
310.C.RC.P284 Glide Path Bldg D - Construction of concrete stairs + B1 Level mass concrete (Concrete: C03_7 d/w - 10h/d - With 16 16-Apr-23 02-May-23 09-Jul-23 24-Jul-23 80
48 m3) HK Hols - No B/O periods
310.C.RC.P288 Glide Path Bldg D - Waterproofing - roofs (2 layers) and walls (Area: 936 m2) C03_7 d/w - 10h/d - With 30 16-Apr-23 16-May-23 24-Jun-23 24-Jul-23 66
HK Hols - No B/O periods
ABWF Works C03_7 d/w - 10h/d - With HK Hols
60- No B/O 0periods 23-Apr-23 24-Jun-23 25-Apr-23 26-Jun-23 2
310.C.RC.P292 Glide Path Bldg D - Commence ABWF works C03_7 d/w - 10h/d - With 0 23-Apr-23 25-Apr-23 2
HK Hols - No B/O periods
310.C.RC.P296 Glide Path Bldg D - ABWF Internal and External Works C03_7 d/w - 10h/d - With 60 23-Apr-23 24-Jun-23 25-Apr-23 26-Jun-23 2
HK Hols - No B/O periods
E&M Works C03_7 d/w - 10h/d - With HK Hols
53- No B/O 0periods 30-Apr-23 24-Jun-23 03-May-23 26-Jun-23 2
310.C.RC.P308 Glide Path Bldg D - Commence MEP works C03_7 d/w - 10h/d - With 0 30-Apr-23 03-May-23 2
HK Hols - No B/O periods
Drainage Installation C03_7 d/w - 10h/d - With HK Hols
53- No B/O 0periods 30-Apr-23 24-Jun-23 03-May-23 26-Jun-23 2
310.C.RC.P312 Glide Path Bldg D - Drainage 1st Fix & Installation C03_7 d/w - 10h/d - With 30 30-Apr-23 31-May-23 03-May-23 02-Jun-23 2
HK Hols - No B/O periods
310.C.RC.P313.B01 Glide Path Bldg D - Drainage 2nd Fix & Installation C03_7 d/w - 10h/d - With 30 19-May-23 18-Jun-23 21-May-23 20-Jun-23 2
HK Hols - No B/O periods
310.C.RC.P314.B01 Glide Path Bldg D - Drainage Final Fix & Adjustment C03_7 d/w - 10h/d - With 5 19-Jun-23 24-Jun-23 21-Jun-23 26-Jun-23 2
HK Hols - No B/O periods
Electrical Installation C03_7 d/w - 10h/d - With HK Hols
53- No B/O 0periods 30-Apr-23 24-Jun-23 03-May-23 26-Jun-23 2
310.C.RC.P315.B01 Glide Path Bldg D - Electrical 1st Fix & Installation C03_7 d/w - 10h/d - With 30 30-Apr-23 31-May-23 03-May-23 02-Jun-23 2
HK Hols - No B/O periods
310.C.RC.P316.B01 Glide Path Bldg D - Switchgear Installation C03_7 d/w - 10h/d - With 18 19-May-23 06-Jun-23 03-Jun-23 20-Jun-23 14
HK Hols - No B/O periods
310.C.RC.P317.B01 Glide Path Bldg D - Electrical 2nd Fix & Installation C03_7 d/w - 10h/d - With 30 19-May-23 18-Jun-23 21-May-23 20-Jun-23 2
HK Hols - No B/O periods
310.C.RC.P318.B01 Glide Path Bldg D - Power On to All Floors C03_7 d/w - 10h/d - With 0 18-Jun-23 20-Jun-23 2
HK Hols - No B/O periods
310.C.RC.P319.B01 Glide Path Bldg D - Electrical Final Fix & Adjustment C03_7 d/w - 10h/d - With 5 19-Jun-23 24-Jun-23 21-Jun-23 26-Jun-23 2
HK Hols - No B/O periods
Fire Services Installation C03_7 d/w - 10h/d - With HK Hols
53- No B/O 0periods 30-Apr-23 24-Jun-23 03-May-23 26-Jun-23 2
310.C.RC.P320.B01 Glide Path Bldg D - Fire Services 1st Fix & Installation C03_7 d/w - 10h/d - With 30 30-Apr-23 31-May-23 03-May-23 02-Jun-23 2
HK Hols - No B/O periods
310.C.RC.P321.B01 Glide Path Bldg D - Fire Services 2nd Fix & Installation C03_7 d/w - 10h/d - With 30 19-May-23 18-Jun-23 21-May-23 20-Jun-23 2
HK Hols - No B/O periods
310.C.RC.P322.B01 Glide Path Bldg D - Fire Service Final Fix & Adjustment C03_7 d/w - 10h/d - With 5 19-Jun-23 24-Jun-23 21-Jun-23 26-Jun-23 2
HK Hols - No B/O periods
MVAC Installation C03_7 d/w - 10h/d - With HK Hols
53- No B/O 0periods 30-Apr-23 24-Jun-23 03-May-23 26-Jun-23 2
310.C.RC.P323.B01 Glide Path Bldg D - MVAC 1st Fix & Installation C03_7 d/w - 10h/d - With 30 30-Apr-23 31-May-23 03-May-23 02-Jun-23 2
HK Hols - No B/O periods
310.C.RC.P324.B01 Glide Path Bldg D - MVAC 2nd Fix & Installation C03_7 d/w - 10h/d - With 30 19-May-23 18-Jun-23 21-May-23 20-Jun-23 2
HK Hols - No B/O periods
310.C.RC.P325.B01 Glide Path Bldg D - MVAC Final Fix & Adjustment C03_7 d/w - 10h/d - With 5 19-Jun-23 24-Jun-23 21-Jun-23 26-Jun-23 2
HK Hols - No B/O periods
Airport System - Glide Path Building D C03_7 d/w - 10h/d - With HK Hols
60- No B/O 0periods 30-Apr-23 02-Jul-23 27-May-23 27-Jul-23 25
310.C.RC.P336 Glide Path Bldg D (Airport System) - VDC, BCS C03_7 d/w - 10h/d - With 60 30-Apr-23 02-Jul-23 27-May-23 27-Jul-23 25
HK Hols - No B/O periods

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 239 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
External Works (Drainage and UU Works & EVA) 101 3 16-Apr-23 16-Aug-23 17-Apr-23 17-Aug-23 1
310.C.RC.P352 Glide Path Bldg D (Civil Works) - Building drainage, manholes, pipe laying and connect to C03_7 d/w - 10h/d - With 35 16-Apr-23 21-May-23 17-Apr-23 22-May-23 1
stormwater manhole HK Hols - No B/O periods
310.C.RC.P356 Glide Path Bldg D (Civil Works) - CLP ducting, sleeving, drawpits C03_7 d/w - 10h/d - With 30 21-Apr-23 21-May-23 22-Apr-23 22-May-23 1
HK Hols - No B/O periods
310.C.RC.P360 Glide Path Bldg D (Civil Works) - Watermain + connection C03_7 d/w - 10h/d - With 45 24-Apr-23 09-Jun-23 11-May-23 26-Jun-23 16
HK Hols - No B/O periods
310.C.RC.P738 Glide Path Bldg D (Civil Works) - AS and Comm ducting, sleeving, drawpits C03_7 d/w - 10h/d - With 30 22-May-23 21-Jun-23 23-May-23 23-Jun-23 1
HK Hols - No B/O periods
310.C.RC.P742 Glide Path Bldg D (Civil Works) - CLP cable laying C03_7 d/w - 10h/d - With 30 3 23-Jun-23 23-Jul-23 24-Jun-23 24-Jul-23 1
HK Hols - No B/O periods
310.T.EX.L452 Glide Path Bldg D (Civil Works) - EVA works C01_7 d/w - 10h/d - No HK 24 24-Jul-23 16-Aug-23 25-Jul-23 17-Aug-23 1
Hols - No B/O periods (was
Testing and Commissioning C1) 86 0 25-Jun-23 06-Oct-23 27-Jun-23 08-Oct-23 1
Testing and Commissioning C01_7 d/w - 10h/d - No HK Hols29
- No B/O periods
0 (was25-Jun-23
C1) 23-Jul-23 27-Jun-23 14-Sep-23 53
310.T.EX.L432 Glide Path Bldg D - Building Services System Test (Electrical, Ventilation, FS System, C01_7 d/w - 10h/d - No HK 24 25-Jun-23 18-Jul-23 27-Jun-23 20-Jul-23 2
Plumbing etc) Hols - No B/O periods (was
310.T.EX.L433.B01 Glide Path Bldg D - Fire Service T&C (Non-FSI) C1)
C01_7 d/w - 10h/d - No HK 24 25-Jun-23 18-Jul-23 22-Aug-23 14-Sep-23 58
Hols - No B/O periods (was
310.C.ES.P784 Glide Path Bldg D - Airport System T&C - VDC, BCS C1)
C01_7 d/w - 10h/d - No HK 21 03-Jul-23 23-Jul-23 28-Jul-23 17-Aug-23 25
Hols - No B/O periods (was
Statutory Inspection C1) 67 0 19-Jul-23 06-Oct-23 21-Jul-23 08-Oct-23 1
Fire Services Department (FSD) C11_6 d/w - 10h/d - With HK Hols
49- No B/O 0periods (was
19-Jul-23
C3) 13-Sep-23 21-Jul-23 14-Sep-23 1
310.T.WS.T1088 Glide Path Bldg D - F.S. Inspection Plan (Form FSI / 314 Submission) C11_6 d/w - 10h/d - With 0 19-Jul-23 21-Jul-23 2
HK Hols - No B/O periods
310.T.WS.T1092 Glide Path Bldg D - F.S. Inspection Application (Form FSI / 501 & 251 Submission) (was
C11_6C3)
d/w - 10h/d - With 0 02-Aug-23 04-Aug-23 2
HK Hols - No B/O periods
310.T.WS.T1096 Glide Path Bldg D - F.S. 1st Inspection (was
C11_6C3)
d/w - 10h/d - With 6 17-Aug-23 23-Aug-23 18-Aug-23 24-Aug-23 1
HK Hols - No B/O periods
310.T.WS.T1100 Glide Path Bldg D - FSD Comment (was
C11_6C3)
d/w - 10h/d - With 0 23-Aug-23 24-Aug-23 1
HK Hols - No B/O periods
310.T.WS.T1104 Glide Path Bldg D - Rectification & Adjustment (was
C11_6C3)
d/w - 10h/d - With 12 24-Aug-23 06-Sep-23 25-Aug-23 07-Sep-23 1
HK Hols - No B/O periods
310.T.WS.T1108 Glide Path Bldg D - F.S. Re-inspection (was
C11_6C3)
d/w - 10h/d - With 6 07-Sep-23 13-Sep-23 08-Sep-23 14-Sep-23 1
HK Hols - No B/O periods
310.T.WS.T1112 Glide Path Bldg D - Issue F.S. Certificate (Form FS172) (was
C11_6C3)
d/w - 10h/d - With 0 13-Sep-23 14-Sep-23 1
HK Hols - No B/O periods
Building Department (BD) (was C3) 18 0 14-Sep-23 06-Oct-23 15-Sep-23 08-Oct-23 1
310.T.WS.T1388 Glide Path Bldg D - BD Inspection Application for Occupation Permit (Form BA13 C11_6 d/w - 10h/d - With 0 14-Sep-23 15-Sep-23 1
Submission) HK Hols - No B/O periods
310.T.WS.T1392 Glide Path Bldg D - BD 1st Inspection (was
C11_6C3)
d/w - 10h/d - With 6 14-Sep-23 20-Sep-23 15-Sep-23 21-Sep-23 1
HK Hols - No B/O periods
310.T.WS.T1396 Glide Path Bldg D - BD Comment (was
C11_6C3)
d/w - 10h/d - With 0 20-Sep-23 21-Sep-23 1
HK Hols - No B/O periods
310.T.WS.T1400 Glide Path Bldg D - Rectification & Adjustment (was
C11_6C3)
d/w - 10h/d - With 6 21-Sep-23 27-Sep-23 22-Sep-23 28-Sep-23 1
HK Hols - No B/O periods
310.T.WS.T1404 Glide Path Bldg D - BD Re-inspection (was
C11_6C3)
d/w - 10h/d - With 6 28-Sep-23 06-Oct-23 29-Sep-23 07-Oct-23 1
HK Hols - No B/O periods
310.T.RC.P350 Glide Path Bldg D - Achieved KD-G2(b) - CAD glide path antenna platform & equipment (was
C01_7C3)
d/w - 10h/d - No HK 0 06-Oct-23 08-Oct-23 2
Hols - No B/O periods (was
C1)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 240 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.T.WS.T1408 Glide Path Bldg D - Issue Occupation Permit (Form BD104) C11_6 d/w - 10h/d - With 0 06-Oct-23 07-Oct-23 1
HK Hols - No B/O periods
Demolition of Existing Glide Path Bldg. D (was C3) 211 0 26-May-22 07-Feb-23 13-Nov-22 26-Jul-23 137
Demolition Plan for Existing Facilities C01_7 d/w - 10h/d - No HK Hols156
- No B/O periods
0 (was26-May-22
C1) 28-Oct-22 13-Nov-22 17-Apr-23 171
310.D.G3.F239.B01 Demolition Plan for Demolish Existing Facilities - prepare design and submit with ICE C01_7 d/w - 10h/d - No HK 14 26-May-22 08-Jun-22 13-Nov-22 26-Nov-22 171
Hols - No B/O periods (was
310.D.G3.F241.B01 Demolition Plan for Demolish Existing Facilities - PM, AP, RSE reviewing C1)
C01_7 d/w - 10h/d - No HK 28 09-Jun-22 06-Jul-22 27-Nov-22 24-Dec-22 171
Hols - No B/O periods (was
310.D.G3.F243.B01 Demolition Plan for Demolish Existing Facilities - ICC, M&VC review design and issue C1)
C01_7 d/w - 10h/d - No HK 21 07-Jul-22 27-Jul-22 25-Dec-22 14-Jan-23 171
check certificates Hols - No B/O periods (was
310.D.G3.F249.B01 Demolition Plan for Demolish Existing Facilities - address comments and resubmit with C1)
C01_7 d/w - 10h/d - No HK 7 28-Jul-22 03-Aug-22 15-Jan-23 21-Jan-23 171
ICE 2nd Round Hols - No B/O periods (was
310.D.G3.F255.B01 Demolition Plan for Demolish Existing Facilities - PM, AP, RSE reviewing 2nd Round C1)
C01_7 d/w - 10h/d - No HK 21 04-Aug-22 24-Aug-22 22-Jan-23 11-Feb-23 171
Hols - No B/O periods (was
310.D.G3.F256.B01 Demolition Plan for Demolish Existing Facilities - ICC, M&VA review design and issue C1)
C01_7 d/w - 10h/d - No HK 21 25-Aug-22 14-Sep-22 12-Feb-23 04-Mar-23 171
check certificates 2nd Round Hols - No B/O periods (was
310.D.G3.F261.B01 Demolition Plan for Demolish Existing Facilities - BD approve C1)
C01_7 d/w - 10h/d - No HK 30 15-Sep-22 14-Oct-22 05-Mar-23 03-Apr-23 171
Hols - No B/O periods (was
310.D.G3.F265.B01 Demolition Plan for Demolish Existing Facilities - prepare and submit Form BA8 and grant C1)
C01_7 d/w - 10h/d - No HK 7 15-Oct-22 21-Oct-22 04-Apr-23 10-Apr-23 171
consent Hols - No B/O periods (was
310.D.G3.F271.B01 Demolition Plan for Demolish Existing Facilities - prepare and submit Form BA10 to notify C1)
C01_7 d/w - 10h/d - No HK 7 22-Oct-22 28-Oct-22 11-Apr-23 17-Apr-23 171
work commencement Hols - No B/O periods (was
Demolition Works C1) 200 0 09-Jun-22 07-Feb-23 30-Jan-23 26-Jul-23 137
310.C.RC.P658 Ex. Glide Path Bldg D - submit Method Statement to Demolish Existing Facilities C11_6 d/w - 10h/d - With 21 09-Jun-22 04-Jul-22 30-Jan-23 22-Feb-23 192
HK Hols - No B/O periods
310.C.RC.P662 Ex. Glide Path Bldg D - PM review MS (was
C11_6C3)
d/w - 10h/d - With 28 05-Jul-22 05-Aug-22 23-Feb-23 27-Mar-23 192
HK Hols - No B/O periods
310.C.RC.P663 Ex. Glide Path Bldg D - Application of Work Permit for Demolition of Old Glide Path Bldg. (was
C01_7C3)
d/w - 10h/d - No HK 21 06-Aug-22 26-Aug-22 28-Mar-23 17-Apr-23 234
D. Hols - No B/O periods (was
310.C.RC.P678 Ex. Glide Path Bldg D - Coordinate with CAD to decommission the existing facilities C1)
C11_6 d/w - 10h/d - With 30 11-Aug-22 15-Sep-22 09-Mar-23 17-Apr-23 172
HK Hols - No B/O periods
310.C.RC.P674 Closure of Existing North Runway (was
C01_7C3)
d/w - 10h/d - No HK 0 01-Sep-22 18-Apr-23 229
Hols - No B/O periods (was
310.C.RC.P666 Ex. Glide Path Bldg D - Decommissioning C1)
C11_6 d/w - 10h/d - With 7 29-Oct-22 05-Nov-22 18-Apr-23 25-Apr-23 137
HK Hols - No B/O periods
310.C.RC.P670 Ex. Glide Path Bldg D - removal of existing CAD facilities (was
C11_6C3)
d/w - 10h/d - With 30 07-Nov-22 10-Dec-22 26-Apr-23 01-Jun-23 137
HK Hols - No B/O periods
310.C.RC.P682 Ex. Glide Path Bldg D - demolish structure (was
C11_6C3)
d/w - 10h/d - With 45 12-Dec-22 07-Feb-23 02-Jun-23 26-Jul-23 137
HK Hols - No B/O periods
Localizer Building C (was C3) 409 3 26-May-22 07-Oct-23 14-Jun-22 07-Oct-23 0
Design and Submissions C01_7 d/w - 10h/d - No HK Hols35
- No B/O periods
0 (was18-Dec-22
C1) 21-Jan-23 22-Dec-22 25-Jan-23 4
310.D.RC.P530 Localizer Bldg C (BD) - submit BA8 consent application to BD C01_7 d/w - 10h/d - No HK 28 18-Dec-22 14-Jan-23 22-Dec-22 18-Jan-23 4
Hols - No B/O periods (was
310.C.RC.P686 Localizer Bldg C - submit BA10 notice of commencement of work C1)
C01_7 d/w - 10h/d - No HK 7 15-Jan-23 21-Jan-23 19-Jan-23 25-Jan-23 4
Hols - No B/O periods (was
Method Statement for Plate Load Test for Localizer Building C C1)
C01_7 d/w - 10h/d - No HK Hols58
- No B/O periods
0 (was30-Sep-22
C1) 26-Nov-22 25-Oct-22 21-Dec-22 25
310.D.TX.A308 Method Statement for Plate Load Test for Localizer Building C - prepare document C01_7 d/w - 10h/d - No HK 30 30-Sep-22 29-Oct-22 25-Oct-22 23-Nov-22 25
Hols - No B/O periods (was
310.D.TX.A312 Method Statement for Plate Load Test for Localizer Building C - BD Acknowledgement C1)
C01_7 d/w - 10h/d - No HK 28 30-Oct-22 26-Nov-22 24-Nov-22 21-Dec-22 25
Hols - No B/O periods (was
Procurement ABWF C1)
C01_7 d/w - 10h/d - No HK Hols210
- No B/O periods
0 (was21-Aug-22
C1) 18-Mar-23 26-Sep-22 23-Apr-23 36

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 241 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.P.RC.P510 Localizer Bldg C (Procurement ABWF) - Material Submission of louvres,windows,metal C01_7 d/w - 10h/d - No HK 60 21-Aug-22 19-Oct-22 26-Sep-22 24-Nov-22 36
doors,handrails,ironmongeries&Others Hols - No B/O periods (was
310.P.RC.P518 Localizer Bldg C (Procurement ABWF) - PM reviews and accept materials C1)
C01_7 d/w - 10h/d - No HK 30 20-Oct-22 18-Nov-22 25-Nov-22 24-Dec-22 36
Hols - No B/O periods (was
310.P.RC.P522 Localizer Bldg C (Procurement ABWF) - purchase and fabrication and delivery of major C1)
C01_7 d/w - 10h/d - No HK 120 19-Nov-22 18-Mar-23 25-Dec-22 23-Apr-23 36
materials Hols - No B/O periods (was
Procurement MEP C1)
C01_7 d/w - 10h/d - No HK Hols210
- No B/O periods
0 (was30-Aug-22
C1) 27-Mar-23 04-Oct-22 01-May-23 35
310.P.RC.P694 Localizer Bldg C (Procurement MEP) - purchase and fabrication and delivery of major C01_7 d/w - 10h/d - No HK 210 30-Aug-22 27-Mar-23 04-Oct-22 01-May-23 35
materials Hols - No B/O periods (was
Demolition Plan for Existing Facilities C1)
C01_7 d/w - 10h/d - No HK Hols156
- No B/O periods
0 (was26-May-22
C1) 28-Oct-22 14-Jun-22 22-Mar-23 145
310.D.G3.F202 Demolition Plan for Demolish Existing Facilities - prepare design and submit with ICE C01_7 d/w - 10h/d - No HK 14 26-May-22 08-Jun-22 14-Jun-22 27-Jun-22 19
Hols - No B/O periods (was
310.D.G3.F206 Demolition Plan for Demolish Existing Facilities - PM, AP, RSE reviewing C1)
C01_7 d/w - 10h/d - No HK 28 09-Jun-22 06-Jul-22 01-Nov-22 28-Nov-22 145
Hols - No B/O periods (was
310.D.G3.F210 Demolition Plan for Demolish Existing Facilities - ICC, M&VC review design and issue C1)
C01_7 d/w - 10h/d - No HK 21 07-Jul-22 27-Jul-22 29-Nov-22 19-Dec-22 145
check certificates Hols - No B/O periods (was
310.D.G3.F214 Demolition Plan for Demolish Existing Facilities - address comments and resubmit with C1)
C01_7 d/w - 10h/d - No HK 7 28-Jul-22 03-Aug-22 20-Dec-22 26-Dec-22 145
ICE 2nd Round Hols - No B/O periods (was
310.D.G3.F218 Demolition Plan for Demolish Existing Facilities - PM, AP, RSE reviewing 2nd Round C1)
C01_7 d/w - 10h/d - No HK 21 04-Aug-22 24-Aug-22 27-Dec-22 16-Jan-23 145
Hols - No B/O periods (was
310.D.G3.F222 Demolition Plan for Demolish Existing Facilities - ICC, M&VA review design and issue C1)
C01_7 d/w - 10h/d - No HK 21 25-Aug-22 14-Sep-22 17-Jan-23 06-Feb-23 145
check certificates 2nd Round Hols - No B/O periods (was
310.D.G3.F226 Demolition Plan for Demolish Existing Facilities - BD approve C1)
C01_7 d/w - 10h/d - No HK 30 15-Sep-22 14-Oct-22 07-Feb-23 08-Mar-23 145
Hols - No B/O periods (was
310.D.G3.F230 Demolition Plan for Demolish Existing Facilities - prepare and submit Form BA8 and grant C1)
C01_7 d/w - 10h/d - No HK 7 15-Oct-22 21-Oct-22 09-Mar-23 15-Mar-23 145
consent Hols - No B/O periods (was
310.D.G3.F234 Demolition Plan for Demolish Existing Facilities - prepare and submit Form BA10 to notify C1)
C01_7 d/w - 10h/d - No HK 7 22-Oct-22 28-Oct-22 16-Mar-23 22-Mar-23 145
work commencement Hols - No B/O periods (was
Construction C1) 302 3 07-Aug-22 12-Aug-23 11-Aug-22 17-Aug-23 4
Initial Works 111 0 07-Aug-22 17-Dec-22 11-Aug-22 21-Jan-23 28
310.C.RC.P638 Localizer Bldg C - Portion of Zone G4 area handed over C01_7 d/w - 10h/d - No HK 0 07-Aug-22 11-Aug-22 4
Hols - No B/O periods (was
310.C.RC.P642 Localizer Bldg C - Commencement of Work C1)
C01_7 d/w - 10h/d - No HK 0 07-Aug-22 11-Aug-22 4
Hols - No B/O periods (was
310.C.RC.P646 Localizer Bldg C - Carry out GI works, Submit report to PM for review and submit to BD C1)
C03_7 d/w - 10h/d - With 28 07-Aug-22 03-Sep-22 11-Aug-22 07-Sep-22 4
includin Form BA14 for Completion HK Hols - No B/O periods
310.C.RC.P654 Localizer Bldg C - install instrumentation C03_7 d/w - 10h/d - With 4 04-Sep-22 07-Sep-22 18-Jan-23 21-Jan-23 130
HK Hols - No B/O periods
310.C.RC.P650 Localizer Bldg C - Anticipated BD approval period (15 week) C01_7 d/w - 10h/d - No HK 105 04-Sep-22 17-Dec-22 08-Sep-22 21-Dec-22 4
Hols - No B/O periods (was
Excavation C1)
C03_7 d/w - 10h/d - With HK Hols
12- No B/O 0periods 26-Jan-23 06-Feb-23 26-Jan-23 06-Feb-23 0
310.C.RC.P602 Localizer Bldg C - Open cut excavation to founding level C03_7 d/w - 10h/d - With 3 26-Jan-23 28-Jan-23 26-Jan-23 28-Jan-23 0
HK Hols - No B/O periods
310.C.RC.P606 Localizer Bldg C - Plate load test and submit report C03_7 d/w - 10h/d - With 9 29-Jan-23 06-Feb-23 29-Jan-23 06-Feb-23 0
HK Hols - No B/O periods
Structure C03_7 d/w - 10h/d - With HK Hols
42- No B/O 0periods 07-Feb-23 20-Mar-23 07-Feb-23 20-Mar-23 0
310.C.RC.P610 Localizer Bldg C - Construction of footing C03_7 d/w - 10h/d - With 8 07-Feb-23 14-Feb-23 07-Feb-23 14-Feb-23 0
HK Hols - No B/O periods
310.C.RC.P614 Localizer Bldg C - Construction of walls, columns C03_7 d/w - 10h/d - With 14 15-Feb-23 28-Feb-23 15-Feb-23 28-Feb-23 0
HK Hols - No B/O periods

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 242 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.RC.P618 Localizer Bldg C - Construction of roof - beam and roof slab C03_7 d/w - 10h/d - With 20 01-Mar-23 20-Mar-23 01-Mar-23 20-Mar-23 0
HK Hols - No B/O periods
ABWF / E&M C03_7 d/w - 10h/d - With HK Hols
60- No B/O 0periods 21-Mar-23 25-May-23 24-Mar-23 17-Jun-23 22
310.C.RC.P622 Localizer Bldg C - Roof Waterproofing & Roof Finishes C03_7 d/w - 10h/d - With 30 21-Mar-23 24-Apr-23 24-Mar-23 27-Apr-23 3
HK Hols - No B/O periods
310.C.RC.P626 Localizer Bldg C (ABWF) - Internal Works C03_7 d/w - 10h/d - With 30 06-Apr-23 10-May-23 24-Apr-23 24-May-23 14
HK Hols - No B/O periods
310.C.RC.P694 Localizer Bldg C (ABWF) - External Works C03_7 d/w - 10h/d - With 30 25-Apr-23 25-May-23 18-May-23 17-Jun-23 22
HK Hols - No B/O periods
Drainage Installation C03_7 d/w - 10h/d - With HK Hols
30- No B/O 0periods 17-Apr-23 17-May-23 13-May-23 12-Jun-23 25
310.C.RC.P558 Localizer Bldg C - Drainage 1st Fix & Installation C03_7 d/w - 10h/d - With 18 17-Apr-23 05-May-23 13-May-23 31-May-23 25
HK Hols - No B/O periods
310.C.RC.P559.B01 Localizer Bldg C - Drainage 2nd Fix & Installation C03_7 d/w - 10h/d - With 18 24-Apr-23 12-May-23 20-May-23 07-Jun-23 25
HK Hols - No B/O periods
310.C.RC.P560.B01 Localizer Bldg C - Drainage Final Fix & Adjustment C03_7 d/w - 10h/d - With 5 13-May-23 17-May-23 08-Jun-23 12-Jun-23 25
HK Hols - No B/O periods
Electrical Installation C03_7 d/w - 10h/d - With HK Hols
30- No B/O 0periods 17-Apr-23 17-May-23 02-May-23 12-Jun-23 25
310.C.RC.P561.B01 Localizer Bldg C - Electrical 1st Fix & Installation C03_7 d/w - 10h/d - With 18 17-Apr-23 05-May-23 02-May-23 19-May-23 14
HK Hols - No B/O periods
310.C.RC.P563.B01 Localizer Bldg C - Electrical 2nd Fix & Installation C03_7 d/w - 10h/d - With 18 24-Apr-23 12-May-23 20-May-23 07-Jun-23 25
HK Hols - No B/O periods
310.C.RC.P562.B01 Localizer Bldg C - Switchgear Installation C03_7 d/w - 10h/d - With 10 02-May-23 11-May-23 29-May-23 07-Jun-23 26
HK Hols - No B/O periods
310.C.RC.P564.B01 Localizer Bldg C - Power On to All Floors C03_7 d/w - 10h/d - With 0 12-May-23 07-Jun-23 25
HK Hols - No B/O periods
310.C.RC.P565.B01 Localizer Bldg C - Electrical Final Fix & Adjustment C03_7 d/w - 10h/d - With 5 13-May-23 17-May-23 08-Jun-23 12-Jun-23 25
HK Hols - No B/O periods
Fire Services Installation C03_7 d/w - 10h/d - With HK Hols
30- No B/O 0periods 17-Apr-23 17-May-23 02-May-23 12-Jun-23 25
310.C.RC.P566.B01 Localizer Bldg C - Fire Services 1st Fix & Installation C03_7 d/w - 10h/d - With 18 17-Apr-23 05-May-23 02-May-23 19-May-23 14
HK Hols - No B/O periods
310.C.RC.P567.B01 Localizer Bldg C - Fire Services 2nd Fix & Installation C03_7 d/w - 10h/d - With 18 24-Apr-23 12-May-23 20-May-23 07-Jun-23 25
HK Hols - No B/O periods
310.C.RC.P568.B01 Localizer Bldg C - Fire Service Final Fix & Adjustment C03_7 d/w - 10h/d - With 5 13-May-23 17-May-23 08-Jun-23 12-Jun-23 25
HK Hols - No B/O periods
MVAC Installation C03_7 d/w - 10h/d - With HK Hols
30- No B/O 0periods 17-Apr-23 17-May-23 13-May-23 12-Jun-23 25
310.C.RC.P569.B01 Localizer Bldg C - MVAC 1st Fix & Installation C03_7 d/w - 10h/d - With 18 17-Apr-23 05-May-23 13-May-23 31-May-23 25
HK Hols - No B/O periods
310.C.RC.P570.B01 Localizer Bldg C - MVAC 2nd Fix & Installation C03_7 d/w - 10h/d - With 18 24-Apr-23 12-May-23 20-May-23 07-Jun-23 25
HK Hols - No B/O periods
310.C.RC.P571.B01 Localizer Bldg C - MVAC Final Fix & Adjustment C03_7 d/w - 10h/d - With 5 13-May-23 17-May-23 08-Jun-23 12-Jun-23 25
HK Hols - No B/O periods
Airport System C03_7 d/w - 10h/d - With HK Hols
60- No B/O 0periods 24-Mar-23 29-May-23 30-Apr-23 02-Jul-23 32
310.C.RC.P592 Localizer Bldg C (Airport System) - VDC, CCTV C03_7 d/w - 10h/d - With 60 24-Mar-23 29-May-23 30-Apr-23 02-Jul-23 32
HK Hols - No B/O periods
External Works (Drainage and UU Works & EVA) 117 3 21-Mar-23 12-Aug-23 21-Mar-23 17-Aug-23 4
310.C.RC.P589 Localizer Bldg C (Bldg Drainage) - Drainage works, manholes C11_6 d/w - 10h/d - With 45 21-Mar-23 17-May-23 21-Mar-23 17-May-23 0
HK Hols - No B/O periods
310.C.RC.P593 Localizer Bldg C (UU) - Cable ducts, drawpits (Comms, AS) (was
C11_6C3)
d/w - 10h/d - With 21 18-May-23 12-Jun-23 18-May-23 12-Jun-23 0
HK Hols - No B/O periods
310.C.RC.P746 Localizer Bldg C (UU) - Cable ducts, drawpit (CLP) (was
C11_6C3)
d/w - 10h/d - With 21 18-May-23 12-Jun-23 23-May-23 16-Jun-23 4
HK Hols - No B/O periods
(was C3)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 243 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.RC.P750 Localizer Bldg C (UU) - cable laying (CLP) C11_6 d/w - 10h/d - With 30 3 13-Jun-23 19-Jul-23 17-Jun-23 24-Jul-23 4
HK Hols - No B/O periods
310.T.EX.L456 Localizer Bldg C - EVA works (was
C01_7C3)
d/w - 10h/d - No HK 24 20-Jul-23 12-Aug-23 25-Jul-23 17-Aug-23 5
Hols - No B/O periods (was
Testing and Commissioning C1) 128 0 06-May-23 07-Oct-23 20-May-23 07-Oct-23 0
Testing and Commissioning C01_7 d/w - 10h/d - No HK Hols38
- No B/O periods
0 (was30-May-23
C1) 06-Jul-23 13-Jun-23 14-Sep-23 70
310.C.ES.P788 Localizer Bldg C - Airport System T&C - VDC, CCTV C01_7 d/w - 10h/d - No HK 21 30-May-23 19-Jun-23 28-Jul-23 17-Aug-23 59
Hols - No B/O periods (was
310.T.EX.L440 Localizer Bldg C - Building Services System Test (Electrical, Ventilation, FS System, C1)
C01_7 d/w - 10h/d - No HK 24 13-Jun-23 06-Jul-23 13-Jun-23 06-Jul-23 0
Plumbing etc) Hols - No B/O periods (was
310.T.EX.L441.B01 Localizer Bldg C - Fire Service T&C (Non-FSI) C1)
C01_7 d/w - 10h/d - No HK 24 13-Jun-23 06-Jul-23 22-Aug-23 14-Sep-23 70
Hols - No B/O periods (was
Statutory Inspection C1) 128 0 06-May-23 07-Oct-23 20-May-23 07-Oct-23 0
Fire Services Department (FSD) C11_6 d/w - 10h/d - With HK Hols
110- No B/O 0periods (was
06-May-23
C3) 14-Sep-23 20-May-23 14-Sep-23 0
DG Application & Inspection C11_6 d/w - 10h/d - With HK Hols
38- No B/O 0periods (was
06-May-23
C3) 20-Jun-23 20-May-23 06-Jul-23 12
310.T.ES.P548 Localizer Bldg C - DG Inspection Application (Form Submission) C11_6 d/w - 10h/d - With 0 06-May-23 20-May-23 12
HK Hols - No B/O periods
310.T.ES.P552 Localizer Bldg C - DG 1st Inspection (was
C11_6C3)
d/w - 10h/d - With 7 20-May-23 29-May-23 05-Jun-23 12-Jun-23 12
HK Hols - No B/O periods
310.T.ES.P556 Localizer Bldg C - DG FSD Comment (was
C11_6C3)
d/w - 10h/d - With 0 29-May-23 12-Jun-23 12
HK Hols - No B/O periods
310.T.ES.P560 Localizer Bldg C - DG Rectification & Adjustment (was
C11_6C3)
d/w - 10h/d - With 12 30-May-23 12-Jun-23 13-Jun-23 27-Jun-23 12
HK Hols - No B/O periods
310.T.ES.P564 Localizer Bldg C - DG Re-inspection (was
C11_6C3)
d/w - 10h/d - With 7 13-Jun-23 20-Jun-23 28-Jun-23 06-Jul-23 12
HK Hols - No B/O periods
310.T.ES.P568 Localizer Bldg C - Issue DG Certificate (was
C11_6C3)
d/w - 10h/d - With 0 20-Jun-23 06-Jul-23 12
HK Hols - No B/O periods
Fire Services Application & Inspection (was
C11_6C3)
d/w - 10h/d - With HK Hols
60- No B/O 0periods (was
07-Jul-23
C3) 14-Sep-23 07-Jul-23 14-Sep-23 0
310.T.WS.T1116 Localizer Bldg C - F.S. Inspection Plan (Form FSI / 314 Submission) C11_6 d/w - 10h/d - With 0 07-Jul-23 07-Jul-23 0
HK Hols - No B/O periods
310.T.WS.T1120 Localizer Bldg C - F.S. Inspection Application (Form FSI / 501 & 251 Submission) (was
C11_6C3)
d/w - 10h/d - With 0 04-Aug-23 04-Aug-23 0
HK Hols - No B/O periods
310.T.WS.T1124 Localizer Bldg C - F.S. 1st Inspection (was
C11_6C3)
d/w - 10h/d - With 6 18-Aug-23 24-Aug-23 18-Aug-23 24-Aug-23 0
HK Hols - No B/O periods
310.T.WS.T1128 Localizer Bldg C - FSD Comment (was
C11_6C3)
d/w - 10h/d - With 0 24-Aug-23 24-Aug-23 0
HK Hols - No B/O periods
310.T.WS.T1132 Localizer Bldg C - Rectification & Adjustment (was
C11_6C3)
d/w - 10h/d - With 12 25-Aug-23 07-Sep-23 25-Aug-23 07-Sep-23 0
HK Hols - No B/O periods
310.T.WS.T1136 Localizer Bldg C - F.S. Re-inspection (was
C11_6C3)
d/w - 10h/d - With 6 08-Sep-23 14-Sep-23 08-Sep-23 14-Sep-23 0
HK Hols - No B/O periods
310.T.WS.T1140 Localizer Bldg C - Issue F.S. Certificate (Form FS172) (was
C11_6C3)
d/w - 10h/d - With 0 14-Sep-23 14-Sep-23 0
HK Hols - No B/O periods
Environmental Protection Department (EDP) (was
C11_6C3)
d/w - 10h/d - With HK Hols
30- No B/O 0periods (was
06-May-23
C3) 10-Jun-23 31-May-23 06-Jul-23 20
EPD Application & Inspection C11_6 d/w - 10h/d - With HK Hols
30- No B/O 0periods (was
06-May-23
C3) 10-Jun-23 31-May-23 06-Jul-23 20
310.T.ES.P644 Localizer Bldg C - EPD Inspection Application C11_6 d/w - 10h/d - With 0 06-May-23 31-May-23 20
HK Hols - No B/O periods
310.T.ES.P648 Localizer Bldg C - EPD 1st Inspection (was
C11_6C3)
d/w - 10h/d - With 6 20-May-23 27-May-23 14-Jun-23 20-Jun-23 20
HK Hols - No B/O periods
310.T.ES.P652 Localizer Bldg C - EPD Comment (was
C11_6C3)
d/w - 10h/d - With 0 27-May-23 20-Jun-23 20
HK Hols - No B/O periods
(was C3)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 244 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.T.ES.P656 Localizer Bldg C - EPD Rectification & Adjustment C11_6 d/w - 10h/d - With 6 29-May-23 03-Jun-23 21-Jun-23 28-Jun-23 20
HK Hols - No B/O periods
310.T.ES.P660 Localizer Bldg C - EPD Re-inspection (was
C11_6C3)
d/w - 10h/d - With 6 05-Jun-23 10-Jun-23 29-Jun-23 06-Jul-23 20
HK Hols - No B/O periods
310.T.ES.P664 Localizer Bldg C - Issue License (was
C11_6C3)
d/w - 10h/d - With 0 10-Jun-23 06-Jul-23 20
HK Hols - No B/O periods
Building Department (BD) (was C3) 18 0 15-Sep-23 07-Oct-23 15-Sep-23 07-Oct-23 0
310.T.WS.T1412 Localizer Bldg C - BD Inspection Application for Occupation Permit (Form BA13 C11_6 d/w - 10h/d - With 0 15-Sep-23 15-Sep-23 0
Submission) HK Hols - No B/O periods
310.T.WS.T1416 Localizer Bldg C - BD 1st Inspection (was
C11_6C3)
d/w - 10h/d - With 6 15-Sep-23 21-Sep-23 15-Sep-23 21-Sep-23 0
HK Hols - No B/O periods
310.T.WS.T1420 Localizer Bldg C - BD Comment (was
C11_6C3)
d/w - 10h/d - With 0 21-Sep-23 21-Sep-23 0
HK Hols - No B/O periods
310.T.WS.T1424 Localizer Bldg C - Rectification & Adjustment (was
C11_6C3)
d/w - 10h/d - With 6 22-Sep-23 28-Sep-23 22-Sep-23 28-Sep-23 0
HK Hols - No B/O periods
310.T.WS.T1428 Localizer Bldg C - BD Re-inspection (was
C11_6C3)
d/w - 10h/d - With 6 29-Sep-23 07-Oct-23 29-Sep-23 07-Oct-23 0
HK Hols - No B/O periods
310.T.RC.P050 Localizer Bldg C - Achieved KD-G2 (was
C01_7C3)
d/w - 10h/d - No HK 0 07-Oct-23 07-Oct-23 0
Hols - No B/O periods (was
310.T.WS.T1432 Localizer Bldg C - Issue Occupation Permit (Form BD104) C1)
C11_6 d/w - 10h/d - With 0 07-Oct-23 07-Oct-23 0
HK Hols - No B/O periods
Demolition of Existing Localizer Building & Antenna Platforms (was C3) 174 0 09-Jun-22 04-Jan-23 27-Dec-22 02-Jun-23 119
310.C.RC.P698 Ex. Localizer Building - submit Method Statement to Demolish Existing facilities C11_6 d/w - 10h/d - With 21 09-Jun-22 04-Jul-22 27-Dec-22 20-Jan-23 167
HK Hols - No B/O periods
310.C.RC.P702 Ex. Localizer Building - PM review MS (was
C11_6C3)
d/w - 10h/d - With 28 05-Jul-22 05-Aug-22 21-Jan-23 25-Feb-23 167
HK Hols - No B/O periods
310.C.RC.P726 Ex. Localizer Building - Application of Work Permit for Demolition of Existing Building (was
C11_6C3)
d/w - 10h/d - With 21 06-Aug-22 30-Aug-22 27-Feb-23 22-Mar-23 167
HK Hols - No B/O periods
310.C.RC.P718 Ex. Localizer Building - Coordination decommissioning of facilities (was
C11_6C3)
d/w - 10h/d - With 30 11-Aug-22 15-Sep-22 16-Feb-23 22-Mar-23 154
HK Hols - No B/O periods
310.C.RC.P714 Closure of Existing North Runway (was
C01_7C3)
d/w - 10h/d - No HK 0 01-Sep-22* 23-Mar-23 203
Hols - No B/O periods (was
310.C.RC.P706 Ex. Localizer Building - Decommissioning C1)
C11_6 d/w - 10h/d - With 7 29-Oct-22 05-Nov-22 23-Mar-23 30-Mar-23 119
HK Hols - No B/O periods
310.C.RC.P710 Ex. Localizer Building - removal of existing facilities (was
C11_6C3)
d/w - 10h/d - With 21 07-Nov-22 30-Nov-22 31-Mar-23 28-Apr-23 119
HK Hols - No B/O periods
310.C.RC.P722 Ex. Localizer Building - demolish structure (was
C11_6C3)
d/w - 10h/d - With 28 01-Dec-22 04-Jan-23 29-Apr-23 02-Jun-23 119
HK Hols - No B/O periods
Localizer Building D (was C3) 185 0 26-May-22 04-Jan-23 14-Jun-22 26-Jan-23 16
Demolition Plan for Existing Factilities C01_7 d/w - 10h/d - No HK Hols156
- No B/O periods
0 (was26-May-22
C1) 28-Oct-22 14-Jun-22 16-Nov-22 19
310.D.G3.F238.B01 Demolition Plan for Demolish Existing Facilities - prepare design and submit with ICE C01_7 d/w - 10h/d - No HK 14 26-May-22 08-Jun-22 14-Jun-22 27-Jun-22 19
Hols - No B/O periods (was
310.D.G3.F242.B01 Demolition Plan for Demolish Existing Facilities - PM, AP, RSE reviewing C1)
C01_7 d/w - 10h/d - No HK 28 09-Jun-22 06-Jul-22 28-Jun-22 25-Jul-22 19
Hols - No B/O periods (was
310.D.G3.F246.B01 Demolition Plan for Demolish Existing Facilities - ICC, M&VC review design and issue C1)
C01_7 d/w - 10h/d - No HK 21 07-Jul-22 27-Jul-22 26-Jul-22 15-Aug-22 19
check certificates Hols - No B/O periods (was
310.D.G3.F250.B01 Demolition Plan for Demolish Existing Facilities - address comments and resubmit with C1)
C01_7 d/w - 10h/d - No HK 7 28-Jul-22 03-Aug-22 16-Aug-22 22-Aug-22 19
ICE 2nd Round Hols - No B/O periods (was
310.D.G3.F254.B01 Demolition Plan for Demolish Existing Facilities - PM, AP, RSE reviewing 2nd Round C1)
C01_7 d/w - 10h/d - No HK 21 04-Aug-22 24-Aug-22 23-Aug-22 12-Sep-22 19
Hols - No B/O periods (was
C1)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 245 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.G3.F258.B01 Demolition Plan for Demolish Existing Facilities - ICC, M&VA review design and issue C01_7 d/w - 10h/d - No HK 21 25-Aug-22 14-Sep-22 13-Sep-22 03-Oct-22 19
check certificates 2nd Round Hols - No B/O periods (was
310.D.G3.F262.B01 Demolition Plan for Demolish Existing Facilities - BD approve C1)
C01_7 d/w - 10h/d - No HK 30 15-Sep-22 14-Oct-22 04-Oct-22 02-Nov-22 19
Hols - No B/O periods (was
310.D.G3.F266.B01 Demolition Plan for Demolish Existing Facilities - prepare and submit Form BA8 and grant C1)
C01_7 d/w - 10h/d - No HK 7 15-Oct-22 21-Oct-22 03-Nov-22 09-Nov-22 19
consent Hols - No B/O periods (was
310.D.G3.F270.B01 Demolition Plan for Demolish Existing Facilities - prepare and submit Form BA10 to notify C1)
C01_7 d/w - 10h/d - No HK 7 22-Oct-22 28-Oct-22 10-Nov-22 16-Nov-22 19
work commencement Hols - No B/O periods (was
Demolition of Existing Localizer Building & Antenna Platforms C1)
C11_6 d/w - 10h/d - With HK Hols
174- No B/O 0periods (was
09-Jun-22
C3) 04-Jan-23 24-Aug-22 26-Jan-23 16
310.C.RC.P754.B01 Ex. Localizer Building - submit Method Statement to Demolish Existing facilities C11_6 d/w - 10h/d - With 21 09-Jun-22 04-Jul-22 24-Aug-22 17-Sep-22 64
HK Hols - No B/O periods
310.C.RC.P758.B01 Ex. Localizer Building - PM review MS (was
C11_6C3)
d/w - 10h/d - With 28 05-Jul-22 05-Aug-22 19-Sep-22 22-Oct-22 64
HK Hols - No B/O periods
310.C.RC.P782.B01 Ex. Localizer Building - Application of Work Permit for Demolition of Existing Building (was
C11_6C3)
d/w - 10h/d - With 21 06-Aug-22 30-Aug-22 24-Oct-22 16-Nov-22 64
HK Hols - No B/O periods
310.C.RC.P774.B01 Ex. Localizer Building - Coordination decommissioning of facilities (was
C11_6C3)
d/w - 10h/d - With 30 11-Aug-22 15-Sep-22 13-Oct-22 16-Nov-22 51
HK Hols - No B/O periods
310.C.RC.P762.B01 Ex. Localizer Building - Decommissioning (was
C11_6C3)
d/w - 10h/d - With 7 29-Oct-22 05-Nov-22 17-Nov-22 24-Nov-22 16
HK Hols - No B/O periods
310.C.RC.P766.B01 Ex. Localizer Building - removal of existing facilities (was
C11_6C3)
d/w - 10h/d - With 21 07-Nov-22 30-Nov-22 25-Nov-22 19-Dec-22 16
HK Hols - No B/O periods
310.C.RC.P778.B01 Ex. Localizer Building - demolish structure (was
C11_6C3)
d/w - 10h/d - With 28 01-Dec-22 04-Jan-23 20-Dec-22 26-Jan-23 16
HK Hols - No B/O periods
HKPF Building (HKPF Equipment Room C) (was C3) 379 0 02-Jul-22 07-Oct-23 21-Aug-22 07-Oct-23 0
Design C01_7 d/w - 10h/d - No HK Hols35
- No B/O periods
0 (was14-Feb-23
C1) 20-Mar-23 14-Feb-23 20-Mar-23 0
310.D.RC.S030 HKPF Bldg (BD) - submit BA8 consent application to BD C01_7 d/w - 10h/d - No HK 28 14-Feb-23 13-Mar-23 14-Feb-23 13-Mar-23 0
Hols - No B/O periods (was
310.C.RC.S014 HKPF Bldg (Excavation) - submit BA10 notice of commencement of work C1)
C01_7 d/w - 10h/d - No HK 7 14-Mar-23 20-Mar-23 14-Mar-23 20-Mar-23 0
Hols - No B/O periods (was
Method Statement for Plate Load Test for HKPF Building C1)
C01_7 d/w - 10h/d - No HK Hols58
- No B/O periods
0 (was19-Nov-22
C1) 15-Jan-23 18-Dec-22 13-Feb-23 29
310.D.TX.A316 Method Statement for Plate Load Test for HKPF Building - prepare document C01_7 d/w - 10h/d - No HK 30 19-Nov-22 18-Dec-22 18-Dec-22 16-Jan-23 29
Hols - No B/O periods (was
310.D.TX.A320 Method Statement for Plate Load Test for HKPF Building - BD Acknowledgement C1)
C01_7 d/w - 10h/d - No HK 28 19-Dec-22 15-Jan-23 17-Jan-23 13-Feb-23 29
Hols - No B/O periods (was
HKPF - MEP Submission C1)
C01_7 d/w - 10h/d - No HK Hols180
- No B/O periods
0 (was12-Jul-22
C1) 07-Jan-23 17-Dec-22 14-Jun-23 158
HKPF - MEP - Drawing Submission C01_7 d/w - 10h/d - No HK Hols180
- No B/O periods
0 (was12-Jul-22
C1) 07-Jan-23 17-Dec-22 14-Jun-23 158
310.D.WS.L1360 HKPF - MEP - Drawing Submission - prepare document C01_7 d/w - 10h/d - No HK 90 12-Jul-22 09-Oct-22 17-Dec-22 16-Mar-23 158
Hols - No B/O periods (was
310.D.WS.L1636 HKPF - MEP - Drawing Submission - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 90 11-Aug-22 08-Nov-22 16-Jan-23 15-Apr-23 158
Hols - No B/O periods (was
310.D.WS.L1632 HKPF - MEP - Drawing Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 90 10-Sep-22 08-Dec-22 15-Feb-23 15-May-23 158
Hols - No B/O periods (was
310.D.WS.L1364 HKPF - MEP - Drawing Submission - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 90 10-Oct-22 07-Jan-23 17-Mar-23 14-Jun-23 158
Hols - No B/O periods (was
HKPF - ABWF Submission C1)
C01_7 d/w - 10h/d - No HK Hols119
- No B/O periods
0 (was02-Jul-22
C1) 28-Oct-22 14-Sep-22 10-Jan-23 74
HKPF - ABWF - Drawing Submission C01_7 d/w - 10h/d - No HK Hols91
- No B/O periods
0 (was02-Jul-22
C1) 30-Sep-22 14-Sep-22 13-Dec-22 74
310.D.WS.L1384 HKPF - ABWF - prepare document C01_7 d/w - 10h/d - No HK 21 02-Jul-22 22-Jul-22 14-Sep-22 04-Oct-22 74
Hols - No B/O periods (was
310.D.WS.L1940 HKPF - ABWF - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 28 23-Jul-22 19-Aug-22 05-Oct-22 01-Nov-22 74
Hols - No B/O periods (was
C1)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 246 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.D.WS.L1936 HKPF - ABWF - prepare resubmission C01_7 d/w - 10h/d - No HK 14 20-Aug-22 02-Sep-22 02-Nov-22 15-Nov-22 74
Hols - No B/O periods (was
310.D.WS.L1388 HKPF - ABWF - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 28 03-Sep-22 30-Sep-22 16-Nov-22 13-Dec-22 74
Hols - No B/O periods (was
HKPF - ABWF - Material Submission C1)
C01_7 d/w - 10h/d - No HK Hols98
- No B/O periods
0 (was23-Jul-22
C1) 28-Oct-22 12-Oct-22 10-Jan-23 74
310.D.WS.L1392 HKPF - ABWF - Material Submission - prepare document C01_7 d/w - 10h/d - No HK 21 23-Jul-22 12-Aug-22 12-Oct-22 01-Nov-22 81
Hols - No B/O periods (was
310.D.WS.L1948 HKPF - ABWF - Material Submission - PM review and accept C1)
C01_7 d/w - 10h/d - No HK 28 13-Aug-22 09-Sep-22 02-Nov-22 29-Nov-22 81
Hols - No B/O periods (was
310.D.WS.L1944 HKPF - ABWF - Material Submission - prepare document C1)
C01_7 d/w - 10h/d - No HK 14 10-Sep-22 23-Sep-22 30-Nov-22 13-Dec-22 81
Hols - No B/O periods (was
310.D.WS.L1396 HKPF - ABWF - Material Submission - PM review and accept C1)
C01_7 d/w - 10h/d - No HK 28 01-Oct-22 28-Oct-22 14-Dec-22 10-Jan-23 74
Hols - No B/O periods (was
HKPF - Structural Steel Staircase C1)
C01_7 d/w - 10h/d - No HK Hols84
- No B/O periods
0 (was12-Jul-22
C1) 03-Oct-22 25-Oct-22 16-Jan-23 105
HKPF - ABWF - Drawing Submission C01_7 d/w - 10h/d - No HK Hols56
- No B/O periods
0 (was12-Jul-22
C1) 05-Sep-22 25-Oct-22 19-Dec-22 105
310.D.WS.L1544 HKPF - Structural Steel Staircase - prepare document C01_7 d/w - 10h/d - No HK 28 12-Jul-22 08-Aug-22 25-Oct-22 21-Nov-22 105
Hols - No B/O periods (was
310.D.WS.L1548 HKPF - Structural Steel Staircase - PM review and accept C1)
C01_7 d/w - 10h/d - No HK 28 09-Aug-22 05-Sep-22 22-Nov-22 19-Dec-22 105
Hols - No B/O periods (was
HKPF - ABWF - Material Submission C1)
C01_7 d/w - 10h/d - No HK Hols56
- No B/O periods
0 (was09-Aug-22
C1) 03-Oct-22 22-Nov-22 16-Jan-23 105
310.D.WS.L1552 HKPF - Structural Steel Staircase - Material Submission - prepare document C01_7 d/w - 10h/d - No HK 28 09-Aug-22 05-Sep-22 22-Nov-22 19-Dec-22 105
Hols - No B/O periods (was
310.D.WS.L1556 HKPF - Structural Steel Staircase - Material Submission - PM review and accept C1)
C01_7 d/w - 10h/d - No HK 28 06-Sep-22 03-Oct-22 20-Dec-22 16-Jan-23 105
Hols - No B/O periods (was
Procurement - MEP C1)
C01_7 d/w - 10h/d - No HK Hols298
- No B/O periods
0 (was01-Aug-22
C1) 25-May-23 21-Aug-22 14-Jun-23 20
310.P.RC.S014 HKPF Bldg (Procurement Electrical & MVAC Major Equipment) - AC/fan units, LV C01_7 d/w - 10h/d - No HK 50 01-Aug-22 19-Sep-22 21-Aug-22 09-Oct-22 20
switchboard, genset & Others - Place Order Hols - No B/O periods (was
310.P.RC.S010 HKPF Bldg (Procurement FS and P&D Major Equipment) - NOVEC 1230 system, FA C1)
C01_7 d/w - 10h/d - No HK 80 01-Aug-22 19-Oct-22 21-Aug-22 08-Nov-22 20
system&Others-Place Order Hols - No B/O periods (was
310.P.RC.S202 HKPF Bldg (Procurement MEP) - Manufacturing of Materials C1)
C01_7 d/w - 10h/d - No HK 240 31-Aug-22 27-Apr-23 20-Sep-22 17-May-23 20
Hols - No B/O periods (was
310.P.RC.S206 HKPF Bldg (Procurement MEP) - Delivery of Materials C1)
C01_7 d/w - 10h/d - No HK 28 28-Apr-23 25-May-23 18-May-23 14-Jun-23 20
Hols - No B/O periods (was
Procurement - ABWF C1)
C01_7 d/w - 10h/d - No HK Hols148
- No B/O periods
0 (was29-Oct-22
C1) 25-Mar-23 11-Jan-23 07-Jun-23 74
310.P.RC.S022 HKPF Bldg (Procurement ABWF) - louvres,doors,raised floors panels&Others-Place Order C01_7 d/w - 10h/d - No HK 14 29-Oct-22 11-Nov-22 11-Jan-23 24-Jan-23 74
Hols - No B/O periods (was
310.P.RC.S026 HKPF Bldg (Procurement ABWF) - Manufacturing of Materials C1)
C01_7 d/w - 10h/d - No HK 120 12-Nov-22 11-Mar-23 25-Jan-23 24-May-23 74
Hols - No B/O periods (was
310.P.RC.S034 HKPF Bldg (Procurement ABWF) - Delivery of Materials C1)
C01_7 d/w - 10h/d - No HK 14 12-Mar-23 25-Mar-23 25-May-23 07-Jun-23 74
Hols - No B/O periods (was
Procurement - Structural Steel Staircase C1)
C01_7 d/w - 10h/d - No HK Hols192
- No B/O periods
0 (was04-Oct-22
C1) 13-Apr-23 17-Jan-23 27-Jul-23 105
310.P.RC.S210 HKPF Bldg (Procurement Structural Steel Staircase) - Place Order for Materials C01_7 d/w - 10h/d - No HK 28 04-Oct-22 31-Oct-22 17-Jan-23 13-Feb-23 105
Hols - No B/O periods (was
310.P.RC.S214 HKPF Bldg (Procurement Structural Steel Staircase) - Manufacturing of Materials C1)
C01_7 d/w - 10h/d - No HK 150 01-Nov-22 30-Mar-23 14-Feb-23 13-Jul-23 105
Hols - No B/O periods (was
310.P.RC.S218 HKPF Bldg (Procurement Structural Steel Staircase) - Delivery of Materials C1) d/w - 10h/d - No HK
C01_7 14 31-Mar-23 13-Apr-23 14-Jul-23 27-Jul-23 105
Hols - No B/O periods (was
Construction C1) 273 0 05-Sep-22 08-Aug-23 05-Sep-22 20-Aug-23 10
Site Preparation and Establishment 130 0 05-Sep-22 13-Feb-23 05-Sep-22 13-Feb-23 0
310.C.RC.S046 HKPF Bldg - Portion of Zone G1 area handed over at +6.5mPD C01_7 d/w - 10h/d - No HK 0 05-Sep-22 05-Sep-22 0
Hols - No B/O periods (was
C1)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 247 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.RC.S054 HKPF Bldg - Commencement of Work C01_7 d/w - 10h/d - No HK 0 06-Sep-22 06-Sep-22 0
Hols - No B/O periods (was
310.C.RC.S066 HKPF Bldg - install instrumentation C1)
C03_7 d/w - 10h/d - With 4 06-Sep-22 09-Sep-22 21-Oct-22 24-Oct-22 42
HK Hols - No B/O periods
310.C.RC.S058 HKPF Bldg - Carry out GI works, Submit report to PM for review and submit to BD includin C03_7 d/w - 10h/d - With 18 06-Sep-22 24-Sep-22 06-Sep-22 24-Sep-22 0
Form BA14 for Completion HK Hols - No B/O periods
310.C.RC.S059 HKPF Bldg - PM review report C03_7 d/w - 10h/d - With 28 25-Sep-22 24-Oct-22 25-Sep-22 24-Oct-22 0
HK Hols - No B/O periods
310.C.RC.S062 HKPF Bldg - submit Geotechnical Assessment Report to BD C03_7 d/w - 10h/d - With 105 25-Oct-22 13-Feb-23 25-Oct-22 13-Feb-23 0
HK Hols - No B/O periods
Structural Work C03_7 d/w - 10h/d - With HK Hols
88- No B/O 0periods 21-Mar-23 24-Jun-23 21-Mar-23 20-Aug-23 56
310.C.RC.S082 HKPF Bldg (Excavation) - Open cut excavation from +6.5mPD to + 6.30mPD C03_7 d/w - 10h/d - With 3 21-Mar-23 23-Mar-23 21-Mar-23 23-Mar-23 0
HK Hols - No B/O periods
310.C.RC.S086 HKPF Bldg (Footing) - Plate load test and submit report C03_7 d/w - 10h/d - With 10 24-Mar-23 02-Apr-23 24-Mar-23 02-Apr-23 0
HK Hols - No B/O periods
310.C.RC.S090 HKPF Bldg (Footing/Ground) - Construction of footing C03_7 d/w - 10h/d - With 9 03-Apr-23 16-Apr-23 03-Apr-23 16-Apr-23 0
HK Hols - No B/O periods
310.C.RC.S094 HKPF Bldg (First Floor) - Construction of walls, columns, beam, slab C03_7 d/w - 10h/d - With 21 17-Apr-23 08-May-23 17-Apr-23 08-May-23 0
HK Hols - No B/O periods
310.C.RC.S098 HKPF Bldg (Roof Floor) - Construction of walls, columns, beam, slab + plinth C03_7 d/w - 10h/d - With 21 09-May-23 30-May-23 09-May-23 30-May-23 0
HK Hols - No B/O periods
310.C.RC.S100 HKPF Bldg (Roof Floor) - Construction of roof - Waterproofing & Roof Finishes C03_7 d/w - 10h/d - With 14 31-May-23 13-Jun-23 02-Jun-23 15-Jun-23 2
HK Hols - No B/O periods
310.C.RC.S204 HKPF Bldg - Installation of Staircase C03_7 d/w - 10h/d - With 24 31-May-23 24-Jun-23 28-Jul-23 20-Aug-23 56
HK Hols - No B/O periods
ABWF / E&M Works C03_7 d/w - 10h/d - With HK Hols
42- No B/O 0periods 31-May-23 13-Jul-23 08-Jun-23 16-Jul-23 3
310.C.RC.S108 HKPF Bldg - ABWF Internal Works C03_7 d/w - 10h/d - With 30 31-May-23 30-Jun-23 08-Jun-23 09-Jul-23 8
HK Hols - No B/O periods
310.C.RC.S112 HKPF Bldg - ABWF External Works C03_7 d/w - 10h/d - With 28 14-Jun-23 13-Jul-23 16-Jun-23 15-Jul-23 2
HK Hols - No B/O periods
Drainage Installation C03_7 d/w - 10h/d - With HK Hols
30- No B/O 0periods 07-Jun-23 08-Jul-23 15-Jun-23 16-Jul-23 8
310.C.RC.S124 HKPF Bldg - Drainage 1st Fix & Installation C03_7 d/w - 10h/d - With 18 07-Jun-23 25-Jun-23 15-Jun-23 04-Jul-23 8
HK Hols - No B/O periods
310.C.RC.S125.B01 HKPF Bldg - Drainage 2nd Fix & Installation C03_7 d/w - 10h/d - With 18 14-Jun-23 03-Jul-23 23-Jun-23 11-Jul-23 8
HK Hols - No B/O periods
310.C.RC.S126.B01 HKPF Bldg - Drainage Final Fix & Adjustment C03_7 d/w - 10h/d - With 5 04-Jul-23 08-Jul-23 12-Jul-23 16-Jul-23 8
HK Hols - No B/O periods
Electrical Installation C03_7 d/w - 10h/d - With HK Hols
30- No B/O 0periods 07-Jun-23 08-Jul-23 15-Jun-23 16-Jul-23 8
310.C.RC.S127.B01 HKPF Bldg - Electrical 1st Fix & Installation C03_7 d/w - 10h/d - With 18 07-Jun-23 25-Jun-23 15-Jun-23 04-Jul-23 8
HK Hols - No B/O periods
310.C.RC.S129.B01 HKPF Bldg - Electrical 2nd Fix & Installation C03_7 d/w - 10h/d - With 18 14-Jun-23 03-Jul-23 23-Jun-23 11-Jul-23 8
HK Hols - No B/O periods
310.C.RC.S128.B01 HKPF Bldg - Switchgear Installation C03_7 d/w - 10h/d - With 10 21-Jun-23 02-Jul-23 02-Jul-23 11-Jul-23 9
HK Hols - No B/O periods
310.C.RC.S130.B01 HKPF Bldg - Power On to All Floors C03_7 d/w - 10h/d - With 0 03-Jul-23 11-Jul-23 8
HK Hols - No B/O periods
310.C.RC.S131.B01 HKPF Bldg - Electrical Final Fix & Adjustment C03_7 d/w - 10h/d - With 5 04-Jul-23 08-Jul-23 12-Jul-23 16-Jul-23 8
HK Hols - No B/O periods
Fire Services Installation C03_7 d/w - 10h/d - With HK Hols
30- No B/O 0periods 07-Jun-23 08-Jul-23 15-Jun-23 16-Jul-23 8
310.C.RC.S132.B01 HKPF Bldg - Fire Services 1st Fix & Installation C03_7 d/w - 10h/d - With 18 07-Jun-23 25-Jun-23 15-Jun-23 04-Jul-23 8
HK Hols - No B/O periods

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 248 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.RC.S133.B01 HKPF Bldg - Fire Services 2nd Fix & Installation C03_7 d/w - 10h/d - With 18 14-Jun-23 03-Jul-23 23-Jun-23 11-Jul-23 8
HK Hols - No B/O periods
310.C.RC.S134.B01 HKPF Bldg - Fire Service Final Fix & Adjustment C03_7 d/w - 10h/d - With 5 04-Jul-23 08-Jul-23 12-Jul-23 16-Jul-23 8
HK Hols - No B/O periods
MVAC Installation C03_7 d/w - 10h/d - With HK Hols
30- No B/O 0periods 07-Jun-23 08-Jul-23 15-Jun-23 16-Jul-23 8
310.C.RC.S135.B01 HKPF Bldg - MVAC 1st Fix & Installation C03_7 d/w - 10h/d - With 18 07-Jun-23 25-Jun-23 15-Jun-23 04-Jul-23 8
HK Hols - No B/O periods
310.C.RC.S136.B01 HKPF Bldg - MVAC 2nd Fix & Installation C03_7 d/w - 10h/d - With 18 14-Jun-23 03-Jul-23 23-Jun-23 11-Jul-23 8
HK Hols - No B/O periods
310.C.RC.S137.B01 HKPF Bldg - MVAC Final Fix & Adjustment C03_7 d/w - 10h/d - With 5 04-Jul-23 08-Jul-23 12-Jul-23 16-Jul-23 8
HK Hols - No B/O periods
Airport System C03_7 d/w - 10h/d - With HK Hols
30- No B/O 0periods 31-May-23 30-Jun-23 01-Jun-23 02-Jul-23 1
310.C.RC.P591 HKPF Bldg (Airport System) - VDC, CCTV C03_7 d/w - 10h/d - With 30 31-May-23 30-Jun-23 01-Jun-23 02-Jul-23 1
HK Hols - No B/O periods
External Works (Drainage and UU Works & EVA) 76 0 09-May-23 08-Aug-23 09-May-23 20-Aug-23 10
310.C.RC.S185 HKPF Bldg (Civil) - Drainage (stormwater), manholes C11_6 d/w - 10h/d - With 28 09-May-23 10-Jun-23 09-May-23 10-Jun-23 0
HK Hols - No B/O periods
310.C.RC.S200 HKPF Bldg (Civil) - AS, power and Comms cable ducts and sleeve (was
C11_6C3)
d/w - 10h/d - With 28 12-Jun-23 15-Jul-23 12-Jun-23 15-Jul-23 0
HK Hols - No B/O periods
310.T.EX.L460 HKPF Bldg - EVA works (was
C01_7C3)
d/w - 10h/d - No HK 24 16-Jul-23 08-Aug-23 28-Jul-23 20-Aug-23 12
Hols - No B/O periods (was
Testing and Commissioning C1) 82 0 01-Jul-23 07-Oct-23 03-Jul-23 07-Oct-23 0
Testing and Commissioning C01_7 d/w - 10h/d - No HK Hols36
- No B/O periods
0 (was01-Jul-23
C1) 05-Aug-23 03-Jul-23 14-Sep-23 40
310.C.ES.P792 HKPF Bldg - Airport System T&C - VDC, CCTV C01_7 d/w - 10h/d - No HK 21 01-Jul-23 21-Jul-23 03-Jul-23 23-Jul-23 2
Hols - No B/O periods (was
310.T.EX.L420.B01 HKPF Bldg - Fire Service T&C (Non-FSI) C1)
C01_7 d/w - 10h/d - No HK 21 09-Jul-23 29-Jul-23 25-Aug-23 14-Sep-23 47
Hols - No B/O periods (was
310.T.EX.L416 HKPF Bldg - Building Services System Test (Electrical, Ventilation, FS System, Plumbing C1)
C01_7 d/w - 10h/d - No HK 21 16-Jul-23 05-Aug-23 17-Jul-23 06-Aug-23 1
etc) Hols - No B/O periods (was
Statutory Inspection C1) 65 0 22-Jul-23 07-Oct-23 24-Jul-23 07-Oct-23 0
Fire Services Department (FSD) C11_6 d/w - 10h/d - With HK Hols
47- No B/O 0periods (was
22-Jul-23
C3) 14-Sep-23 24-Jul-23 14-Sep-23 0
310.T.WS.T1060 HKPF Bldg - F.S. Inspection Plan (Form FSI / 314 Submission) C11_6 d/w - 10h/d - With 0 22-Jul-23 24-Jul-23 1
HK Hols - No B/O periods
310.T.WS.T1064 HKPF Bldg - F.S. Inspection Application (Form FSI / 501 & 251 Submission) (was
C11_6C3)
d/w - 10h/d - With 0 07-Aug-23 07-Aug-23 0
HK Hols - No B/O periods
310.T.WS.T1068 HKPF Bldg - F.S. 1st Inspection (was
C11_6C3)
d/w - 10h/d - With 6 21-Aug-23 26-Aug-23 21-Aug-23 26-Aug-23 0
HK Hols - No B/O periods
310.T.WS.T1072 HKPF Bldg - FSD Comment (was
C11_6C3)
d/w - 10h/d - With 0 26-Aug-23 26-Aug-23 0
HK Hols - No B/O periods
310.T.WS.T1076 HKPF Bldg - Rectification & Adjustment (was
C11_6C3)
d/w - 10h/d - With 10 28-Aug-23 07-Sep-23 28-Aug-23 07-Sep-23 0
HK Hols - No B/O periods
310.T.WS.T1080 HKPF Bldg - F.S. Re-inspection (was
C11_6C3)
d/w - 10h/d - With 6 08-Sep-23 14-Sep-23 08-Sep-23 14-Sep-23 0
HK Hols - No B/O periods
310.T.WS.T1084 HKPF Bldg - Issue F.S. Certificate (Form FS172) (was
C11_6C3)
d/w - 10h/d - With 0 14-Sep-23 14-Sep-23 0
HK Hols - No B/O periods
Building Department (BD) (was C3) 18 0 15-Sep-23 07-Oct-23 15-Sep-23 07-Oct-23 0
310.T.WS.T1436 HKPF Bldg - BD Inspection Application for Occupation Permit (Form BA13 Submission) C11_6 d/w - 10h/d - With 0 15-Sep-23 15-Sep-23 0
HK Hols - No B/O periods
310.T.WS.T1440 HKPF Bldg - BD 1st Inspection (was
C11_6C3)
d/w - 10h/d - With 6 15-Sep-23 21-Sep-23 15-Sep-23 21-Sep-23 0
HK Hols - No B/O periods
(was C3)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 249 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.T.WS.T1444 HKPF Bldg - BD Comment C11_6 d/w - 10h/d - With 0 21-Sep-23 21-Sep-23 0
HK Hols - No B/O periods
310.T.WS.T1448 HKPF Bldg - Rectification & Adjustment (was
C11_6C3)
d/w - 10h/d - With 6 22-Sep-23 28-Sep-23 22-Sep-23 28-Sep-23 0
HK Hols - No B/O periods
310.T.WS.T1452 HKPF Bldg - BD Re-inspection (was
C11_6C3)
d/w - 10h/d - With 6 29-Sep-23 07-Oct-23 29-Sep-23 07-Oct-23 0
HK Hols - No B/O periods
310.T.RC.S141 HKPF Bldg - Achieved KD-G2 (was
C01_7C3)
d/w - 10h/d - No HK 0 07-Oct-23 07-Oct-23 0
Hols - No B/O periods (was
310.T.WS.T1456 HKPF Bldg - Issue Occupation Permit (Form BD104) C1)
C11_6 d/w - 10h/d - With 0 07-Oct-23 07-Oct-23 0
HK Hols - No B/O periods
WSA - Vehicle Search Bay and C&ED Control Kiosk (was C3) 487 9 04-May-22 17-Dec-23 04-Jul-22 18-Dec-23 1
Design & Submission C01_7 d/w - 10h/d - No HK Hols117
- No B/O periods
0 (was04-May-22
C1) 28-Aug-22 15-Aug-22 08-May-23 253
WSA - Vehicle Search Bay, C&ED - MEP Submission C01_7 d/w - 10h/d - No HK Hols98
- No B/O periods
0 (was23-May-22
C1) 28-Aug-22 31-Jan-23 08-May-23 253
WSA - Vehicle Search Bay, C&ED - MEP - Drawing Submission C01_7 d/w - 10h/d - No HK Hols98
- No B/O periods
0 (was23-May-22
C1) 28-Aug-22 31-Jan-23 08-May-23 253
310.D.WS.L1952 WSA - Vehicle Search Bay, C&ED - MEP - Drawing Submission - prepare document C01_7 d/w - 10h/d - No HK 28 23-May-22 19-Jun-22 31-Jan-23 27-Feb-23 253
Hols - No B/O periods (was
310.D.WS.L1996 WSA - Vehicle Search Bay, C&ED - MEP - Drawing Submission - PM review and accept C1)
C01_7 d/w - 10h/d - No HK 28 20-Jun-22 17-Jul-22 28-Feb-23 27-Mar-23 253
1st Round Hols - No B/O periods (was
310.D.WS.L1992 WSA - Vehicle Search Bay, C&ED - MEP - Drawing Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 14 18-Jul-22 31-Jul-22 28-Mar-23 10-Apr-23 253
Hols - No B/O periods (was
310.D.WS.L1956 WSA - Vehicle Search Bay, C&ED - MEP - Drawing Submission - PM review and accept C1) d/w - 10h/d - No HK
C01_7 28 01-Aug-22 28-Aug-22 11-Apr-23 08-May-23 253
2nd Round Hols - No B/O periods (was
WSA - Vehicle Search Bay, C&ED - ABWF Submission C1)
C01_7 d/w - 10h/d - No HK Hols98
- No B/O periods
0 (was04-May-22
C1) 09-Aug-22 15-Aug-22 20-Nov-22 103
WSA - Vehicle Search Bay, C&ED - ABWF - Drawing Submission C01_7 d/w - 10h/d - No HK Hols98
- No B/O periods
0 (was04-May-22
C1) 09-Aug-22 15-Aug-22 20-Nov-22 103
310.D.WS.L1976 WSA - Vehicle Search Bay, C&ED - ABWF - prepare document C01_7 d/w - 10h/d - No HK 21 04-May-22 24-May-22 15-Aug-22 04-Sep-22 103
Hols - No B/O periods (was
310.D.WS.L2020 WSA - Vehicle Search Bay, C&ED - ABWF - PM review and accept 1st Round C1)
C01_7 d/w - 10h/d - No HK 28 25-May-22 21-Jun-22 05-Sep-22 02-Oct-22 103
Hols - No B/O periods (was
310.D.WS.L2016 WSA - Vehicle Search Bay, C&ED - ABWF - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 21 22-Jun-22 12-Jul-22 03-Oct-22 23-Oct-22 103
Hols - No B/O periods (was
310.D.WS.L1980 WSA - Vehicle Search Bay, C&ED - ABWF - PM review and accept 2nd Round C1)
C01_7 d/w - 10h/d - No HK 28 13-Jul-22 09-Aug-22 24-Oct-22 20-Nov-22 103
Hols - No B/O periods (was
WSA - Vehicle Search Bay, C&ED - ABWF - Material Submission C1)
C01_7 d/w - 10h/d - No HK Hols98
- No B/O periods
0 (was04-May-22
C1) 09-Aug-22 15-Aug-22 20-Nov-22 103
310.D.WS.L1984 WSA - Vehicle Search Bay, C&ED - ABWF - Material Submission - prepare document C01_7 d/w - 10h/d - No HK 21 04-May-22 24-May-22 15-Aug-22 04-Sep-22 103
Hols - No B/O periods (was
310.D.WS.L2028 WSA - Vehicle Search Bay, C&ED - ABWF - Material Submission - PM review and accept C1)
C01_7 d/w - 10h/d - No HK 28 25-May-22 21-Jun-22 05-Sep-22 02-Oct-22 103
1st Round Hols - No B/O periods (was
310.D.WS.L2024 WSA - Vehicle Search Bay, C&ED - ABWF - Material Submission - prepare resubmission C1)
C01_7 d/w - 10h/d - No HK 21 22-Jun-22 12-Jul-22 03-Oct-22 23-Oct-22 103
Hols - No B/O periods (was
310.D.WS.L1988 WSA - Vehicle Search Bay, C&ED - ABWF - Material Submission - PM review and accept C1)
C01_7 d/w - 10h/d - No HK 28 13-Jul-22 09-Aug-22 24-Oct-22 20-Nov-22 103
Hols - No B/O periods (was
Procurement C1)
C01_7 d/w - 10h/d - No HK Hols243
- No B/O periods
0 (was07-May-22
C1) 04-Jan-23 27-Oct-22 08-May-23 124
Major Materials ABWF C01_7 d/w - 10h/d - No HK Hols148
- No B/O periods
0 (was10-Aug-22
C1) 04-Jan-23 21-Nov-22 17-Apr-23 103
310.P.ES.P134 WSA - Vehicle Search Bay, C&ED (Procurement ABWF) - Place Order for Materials C01_7 d/w - 10h/d - No HK 14 10-Aug-22 23-Aug-22 21-Nov-22 04-Dec-22 103
Hols - No B/O periods (was
310.P.ES.P146 WSA - Vehicle Search Bay, C&ED (Procurement ABWF) - Manufacturing of Materials C1)
C01_7 d/w - 10h/d - No HK 120 24-Aug-22 21-Dec-22 05-Dec-22 03-Apr-23 103
Hols - No B/O periods (was
310.P.ES.P150 WSA - Vehicle Search Bay, C&ED (Procurement ABWF) - Delivery of Materials C1)
C01_7 d/w - 10h/d - No HK 14 22-Dec-22 04-Jan-23 04-Apr-23 17-Apr-23 103
Hols - No B/O periods (was
Major Materials MEP C1)
C01_7 d/w - 10h/d - No HK Hols194
- No B/O periods
0 (was07-May-22
C1) 16-Nov-22 27-Oct-22 08-May-23 173

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 250 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.P.ES.P138 WSA - Vehicle Search Bay, C&ED (Procurement MEP) - Place Order for Materials C01_7 d/w - 10h/d - No HK 60 07-May-22 05-Jul-22 27-Oct-22 25-Dec-22 173
Hols - No B/O periods (was
310.P.ES.P154 WSA - Vehicle Search Bay, C&ED (Procurement MEP) - Manufacturing of Materials C1)
C01_7 d/w - 10h/d - No HK 150 06-Jun-22 02-Nov-22 26-Nov-22 24-Apr-23 173
Hols - No B/O periods (was
310.P.ES.P162 WSA - Vehicle Search Bay, C&ED (Procurement MEP) - Delivery of Materials C1)
C01_7 d/w - 10h/d - No HK 14 03-Nov-22 16-Nov-22 25-Apr-23 08-May-23 173
Hols - No B/O periods (was
Initial Work and Site Preparation C1) 12 0 04-Jul-22 16-Jul-22 04-Jul-22 22-Aug-22 31
310.C.WS.S404 WSA - Vehicle Search Bay, C&ED Ctrl Kiosk - Site access WA3310/12 C01_7 d/w - 10h/d - No HK 0 04-Jul-22* 04-Jul-22 0
Hols - No B/O periods (was
310.C.WS.S420 WSA - Vehicle Search Bay, C&ED Ctrl Kiosk - Hoarding C1)
C11_6 d/w - 10h/d - With 5 04-Jul-22 08-Jul-22 09-Aug-22 13-Aug-22 31
HK Hols - No B/O periods
310.C.WS.S408 WSA - Vehicle Search Bay, C&ED Ctrl Kiosk - Carry out site survey (was
C11_6C3)
d/w - 10h/d - With 1 08-Jul-22 08-Jul-22 13-Aug-22 13-Aug-22 31
HK Hols - No B/O periods
310.C.WS.S412 WSA - Vehicle Search Bay, C&ED Ctrl Kiosk - Install monitoring point (was
C11_6C3)
d/w - 10h/d - With 1 09-Jul-22 09-Jul-22 15-Aug-22 15-Aug-22 31
HK Hols - No B/O periods
310.C.WS.S416 WSA - Vehicle Search Bay, C&ED Ctrl Kiosk - UU detection and trial pit (was
C11_6C3)
d/w - 10h/d - With 6 11-Jul-22 16-Jul-22 16-Aug-22 22-Aug-22 31
HK Hols - No B/O periods
Structural Works (was C3) 96 0 18-Jul-22 09-Nov-22 19-Jul-22 04-Apr-23 120
310.C.WS.S432 WSA - Vehicle Search Bay & Traffic Control Kiosk - Obtain BA8 consent C01_7 d/w - 10h/d - No HK 28 18-Jul-22 14-Aug-22 19-Jul-22 15-Aug-22 1
Hols - No B/O periods (was
310.C.WS.S428 WSA - Vehicle Search Bay & Traffic Control Kiosk - BA10 notice of commencement of C1)
C01_7 d/w - 10h/d - No HK 7 15-Aug-22 21-Aug-22 16-Aug-22 22-Aug-22 1
works Hols - No B/O periods (was
310.C.WS.S424 WSA - Vehicle Search Bay & Traffic Control Kiosk -- SI works and submit report to PM C1)
C11_6 d/w - 10h/d - With 10 22-Aug-22 01-Sep-22 23-Aug-22 02-Sep-22 1
HK Hols - No B/O periods
Vehicle Search Bay, C&ED Control Kiosk (was
C11_6C3)
d/w - 10h/d - With HK Hols
21- No B/O 0periods (was
17-Oct-22
C3) 09-Nov-22 11-Mar-23 04-Apr-23 120
310.C.WS.S468 WSA - Vehicle Search Bay/C&ED Kiosk - Foundation/footing C11_6 d/w - 10h/d - With 7 17-Oct-22 24-Oct-22 11-Mar-23 18-Mar-23 120
HK Hols - No B/O periods
310.C.WS.S472 WSA - Vehicle Search Bay/C&ED Kiosk - Structural Works (was
C11_6C3)
d/w - 10h/d - With 14 25-Oct-22 09-Nov-22 20-Mar-23 04-Apr-23 120
HK Hols - No B/O periods
ABWF (was
C11_6C3)
d/w - 10h/d - With HK Hols
119- No B/O 0periods (was
11-Feb-23
C3) 10-Jul-23 04-Apr-23 07-Sep-23 51
310.C.EX.W2312 WSA - Vehicle Search Bay, C&ED - Structure completed C11_6 d/w - 10h/d - With 0 11-Feb-23 04-Apr-23 44
HK Hols - No B/O periods
310.C.EX.W2276 WSA - Vehicle Search Bay, C&ED - Partition Wall & Door Subframe (was
C11_6C3)
d/w - 10h/d - With 45 13-Feb-23 06-Apr-23 18-Apr-23 10-Jun-23 51
HK Hols - No B/O periods
310.C.EX.W2280 WSA - Vehicle Search Bay, C&ED - Plastering & Screeding (was
C11_6C3)
d/w - 10h/d - With 45 24-Feb-23 21-Apr-23 29-Apr-23 23-Jun-23 51
HK Hols - No B/O periods
310.C.EX.W2284 WSA - Vehicle Search Bay, C&ED - Tiling & Stonework (was
C11_6C3)
d/w - 10h/d - With 45 08-Mar-23 04-May-23 12-May-23 06-Jul-23 51
HK Hols - No B/O periods
310.C.EX.W2288 WSA - Vehicle Search Bay, C&ED - Suspended Ceiling Framework (was
C11_6C3)
d/w - 10h/d - With 45 20-Mar-23 16-May-23 24-May-23 18-Jul-23 51
HK Hols - No B/O periods
310.C.EX.W2292 WSA - Vehicle Search Bay, C&ED - Sanitary Ware & Fixtures (was
C11_6C3)
d/w - 10h/d - With 45 31-Mar-23 29-May-23 06-Jun-23 29-Jul-23 51
HK Hols - No B/O periods
310.C.EX.W2296 WSA - Vehicle Search Bay, C&ED - Door Sets & Ironmongery (was
C11_6C3)
d/w - 10h/d - With 45 17-Apr-23 09-Jun-23 17-Jun-23 10-Aug-23 51
HK Hols - No B/O periods
310.C.EX.W2300 WSA - Vehicle Search Bay, C&ED - Glazing (was
C11_6C3)
d/w - 10h/d - With 45 28-Apr-23 21-Jun-23 30-Jun-23 22-Aug-23 51
HK Hols - No B/O periods
310.C.EX.W2304 WSA - Vehicle Search Bay, C&ED - Ceiling Panels & Finishes (was
C11_6C3)
d/w - 10h/d - With 45 11-May-23 05-Jul-23 13-Jul-23 02-Sep-23 51
HK Hols - No B/O periods
310.C.EX.W2308 WSA - Vehicle Search Bay, C&ED - Painting, Graphics & Signage (was
C11_6C3)
d/w - 10h/d - With 45 16-May-23 10-Jul-23 18-Jul-23 07-Sep-23 51
HK Hols - No B/O periods
MEP Installation Works (was
C11_6C3)
d/w - 10h/d - With HK Hols
130- No B/O 0periods (was
13-Mar-23
C3) 19-Aug-23 09-May-23 18-Nov-23 75

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 251 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
Plumbing & Drainage Installation C11_6 d/w - 10h/d - With HK Hols
130- No B/O 0periods (was
13-Mar-23
C3) 19-Aug-23 09-May-23 12-Oct-23 44
310.C.EX.W2368 WSA - Vehicle Search Bay, C&ED - Plumbing & Drainage 1st Fix & Installation C11_6 d/w - 10h/d - With 60 13-Mar-23 27-May-23 09-May-23 20-Jul-23 44
HK Hols - No B/O periods
310.C.EX.W2372 WSA - Vehicle Search Bay, C&ED - Plumbing & Drainage 2nd Fix & Installation (was
C11_6C3)
d/w - 10h/d - With 60 14-Apr-23 26-Jun-23 07-Jun-23 17-Aug-23 44
HK Hols - No B/O periods
310.C.EX.W2380 WSA - Vehicle Search Bay, C&ED - Plumbing & Drainage Final Fix & Adjustment (was
C11_6C3)
d/w - 10h/d - With 12 07-Aug-23 19-Aug-23 27-Sep-23 12-Oct-23 44
HK Hols - No B/O periods
Electrical Installation (was
C11_6C3)
d/w - 10h/d - With HK Hols
130- No B/O 0periods (was
13-Mar-23
C3) 19-Aug-23 15-Jun-23 18-Nov-23 75
310.C.EX.W2384 WSA - Vehicle Search Bay, C&ED - Electrical 1st Fix & Installation C11_6 d/w - 10h/d - With 60 13-Mar-23 27-May-23 15-Jun-23 25-Aug-23 75
HK Hols - No B/O periods
310.C.EX.W2388 WSA - Vehicle Search Bay, C&ED - Electrical 2nd Fix & Installation (was
C11_6C3)
d/w - 10h/d - With 60 14-Apr-23 26-Jun-23 15-Jul-23 22-Sep-23 75
HK Hols - No B/O periods
310.C.EX.W2404 WSA - Vehicle Search Bay, C&ED - Electrical Final Fix & Adjustment (was
C11_6C3)
d/w - 10h/d - With 12 07-Aug-23 19-Aug-23 06-Nov-23 18-Nov-23 75
HK Hols - No B/O periods
Fire Services Installation (was
C11_6C3)
d/w - 10h/d - With HK Hols
130- No B/O 0periods (was
13-Mar-23
C3) 19-Aug-23 20-May-23 25-Oct-23 54
310.C.EX.W2408 WSA - Vehicle Search Bay, C&ED - Fire Services 1st Fix & Installation C11_6 d/w - 10h/d - With 60 13-Mar-23 27-May-23 20-May-23 01-Aug-23 54
HK Hols - No B/O periods
310.C.EX.W2412 WSA - Vehicle Search Bay, C&ED - Fire Services 2nd Fix & Installation (was
C11_6C3)
d/w - 10h/d - With 60 14-Apr-23 26-Jun-23 19-Jun-23 29-Aug-23 54
HK Hols - No B/O periods
310.C.EX.W2420 WSA - Vehicle Search Bay, C&ED - Fire Services Final Fix & Adjustment (was
C11_6C3)
d/w - 10h/d - With 12 07-Aug-23 19-Aug-23 11-Oct-23 25-Oct-23 54
HK Hols - No B/O periods
MVAC Installation (was
C11_6C3)
d/w - 10h/d - With HK Hols
130- No B/O 0periods (was
13-Mar-23
C3) 19-Aug-23 20-May-23 25-Oct-23 54
310.C.EX.W2424 WSA - Vehicle Search Bay, C&ED - MVAC 1st Fix & Installation C11_6 d/w - 10h/d - With 60 13-Mar-23 27-May-23 20-May-23 01-Aug-23 54
HK Hols - No B/O periods
310.C.EX.W2428 WSA - Vehicle Search Bay, C&ED - MVAC 2nd Fix & Installation (was
C11_6C3)
d/w - 10h/d - With 60 14-Apr-23 26-Jun-23 19-Jun-23 29-Aug-23 54
HK Hols - No B/O periods
310.C.EX.W2432 WSA - Vehicle Search Bay, C&ED - MVAC Final Fix & Adjustment (was
C11_6C3)
d/w - 10h/d - With 12 07-Aug-23 19-Aug-23 11-Oct-23 25-Oct-23 54
HK Hols - No B/O periods
External Works (was
C11_6C3)
d/w - 10h/d - With HK Hols
120- No B/O 0periods (was
12-May-23
C3) 04-Oct-23 14-Jul-23 04-Dec-23 51
External Building Finishes C11_6 d/w - 10h/d - With HK Hols
99- No B/O 0periods (was
12-May-23
C3) 07-Sep-23 14-Jul-23 04-Dec-23 72
310.C.ES.P812 WSA - Vehicle Search Bay, C&ED - External building finishes C11_6 d/w - 10h/d - With 48 12-May-23 10-Jul-23 14-Jul-23 07-Sep-23 51
HK Hols - No B/O periods
310.C.ES.P808 WSA - Vehicle Search Bay, C&ED - Hard and soft landscape works (was
C11_6C3)
d/w - 10h/d - With 21 15-Aug-23 07-Sep-23 10-Nov-23 04-Dec-23 72
HK Hols - No B/O periods
Drainage and UU (was
C11_6C3)
d/w - 10h/d - With HK Hols
78- No B/O 0periods (was
12-May-23
C3) 14-Aug-23 14-Jul-23 09-Nov-23 72
310.C.ES.P816 WSA - Vehicle Search Bay, C&ED - Building drainage and watermain works C11_6 d/w - 10h/d - With 48 12-May-23 10-Jul-23 14-Jul-23 07-Sep-23 51
HK Hols - No B/O periods
310.C.ES.P820 WSA - Vehicle Search Bay, C&ED - AS Cable ducts + drawpits (was
C11_6C3)
d/w - 10h/d - With 24 11-Jul-23 07-Aug-23 12-Oct-23 09-Nov-23 78
HK Hols - No B/O periods
310.C.ES.P824 WSA - Vehicle Search Bay, C&ED - EL cable ducting + drawpits (was
C11_6C3)
d/w - 10h/d - With 24 11-Jul-23 07-Aug-23 08-Sep-23 07-Oct-23 51
HK Hols - No B/O periods
310.C.ES.P828 WSA - Vehicle Search Bay, C&ED - CLP Cable ducts + drawpits (was
C11_6C3)
d/w - 10h/d - With 30 11-Jul-23 14-Aug-23 05-Oct-23 09-Nov-23 72
HK Hols - No B/O periods
EVA Construction (was
C11_6C3)
d/w - 10h/d - With HK Hols
48- No B/O 0periods (was
08-Aug-23
C3) 04-Oct-23 09-Oct-23 04-Dec-23 51
310.C.WS.C124 WSA - Vehicle Search Bay, C&ED - Site Formation Works and Road Works for EVA C11_6 d/w - 10h/d - With 48 08-Aug-23 04-Oct-23 09-Oct-23 04-Dec-23 51
HK Hols - No B/O periods
Testing and Commissioning (was C3) 145 9 27-Jun-23 17-Dec-23 18-Aug-23 18-Dec-23 1
Preliminary Testing and Commissioning C11_6 d/w - 10h/d - With HK Hols
34- No B/O 0periods (was
27-Jun-23
C3) 05-Aug-23 18-Aug-23 04-Nov-23 75
Preliminary T&C - Plumbing and Drainage C11_6 d/w - 10h/d - With HK Hols
34- No B/O 0periods (was
27-Jun-23
C3) 05-Aug-23 18-Aug-23 26-Sep-23 44
310.C.EX.W2244 WSA - Vehicle Search Bay, C&ED - Plumbing & Drainage Preliminary Inspection & C11_6 d/w - 10h/d - With 24 27-Jun-23 25-Jul-23 18-Aug-23 14-Sep-23 44
Adjustment HK Hols - No B/O periods
(was C3)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 252 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.EX.W2248 WSA - Vehicle Search Bay, C&ED - Plumbing & Drainage Preliminary Testing & C11_6 d/w - 10h/d - With 24 10-Jul-23 05-Aug-23 30-Aug-23 26-Sep-23 44
Commissioning HK Hols - No B/O periods
Preliminary T&C - Electrical (was
C11_6C3)
d/w - 10h/d - With HK Hols
34- No B/O 0periods (was
27-Jun-23
C3) 05-Aug-23 23-Sep-23 04-Nov-23 75
310.C.EX.W2252 WSA - Vehicle Search Bay, C&ED - Electrical Preliminary Inspection & Adjustment C11_6 d/w - 10h/d - With 24 27-Jun-23 25-Jul-23 23-Sep-23 24-Oct-23 75
HK Hols - No B/O periods
310.C.EX.W2256 WSA - Vehicle Search Bay, C&ED - Electrical Preliminary Testing & Commissioning (was
C11_6C3)
d/w - 10h/d - With 24 10-Jul-23 05-Aug-23 07-Oct-23 04-Nov-23 75
HK Hols - No B/O periods
Preliminary T&C - Fire Services (was
C11_6C3)
d/w - 10h/d - With HK Hols
34- No B/O 0periods (was
27-Jun-23
C3) 05-Aug-23 30-Aug-23 10-Oct-23 54
310.C.EX.W2260 WSA - Vehicle Search Bay, C&ED - Fire Services Preliminary Inspection & Adjustment C11_6 d/w - 10h/d - With 24 27-Jun-23 25-Jul-23 30-Aug-23 26-Sep-23 54
HK Hols - No B/O periods
310.C.EX.W2264 WSA - Vehicle Search Bay, C&ED - Fire Services Preliminary Testing & Commissioning (was
C11_6C3)
d/w - 10h/d - With 24 10-Jul-23 05-Aug-23 11-Sep-23 10-Oct-23 54
HK Hols - No B/O periods
Preliminary T&C - MVAC (was
C11_6C3)
d/w - 10h/d - With HK Hols
34- No B/O 0periods (was
27-Jun-23
C3) 05-Aug-23 30-Aug-23 10-Oct-23 54
310.C.EX.W2268 WSA - Vehicle Search Bay, C&ED - MVAC Preliminary Inspection & Adjustment C11_6 d/w - 10h/d - With 24 27-Jun-23 25-Jul-23 30-Aug-23 26-Sep-23 54
HK Hols - No B/O periods
310.C.EX.W2272 WSA - Vehicle Search Bay, C&ED - MVAC Preliminary Testing & Commissioning (was
C11_6C3)
d/w - 10h/d - With 24 10-Jul-23 05-Aug-23 11-Sep-23 10-Oct-23 54
HK Hols - No B/O periods
Testing and Commissioning (was
C01_7C3)
d/w - 10h/d - No HK Hols120
- No B/O periods
9 (was20-Aug-23
C1) 17-Dec-23 13-Oct-23 18-Dec-23 1
310.T.EX.L480 WSA - Vehicle Search Bay and C&ED Control Kiosk - FS System Test C01_7 d/w - 10h/d - No HK 24 2 20-Aug-23 12-Sep-23 26-Oct-23 18-Nov-23 67
Hols - No B/O periods (was
310.T.EX.L484 WSA - Vehicle Search Bay and C&ED Control Kiosk - Ventilation System Test C1)
C01_7 d/w - 10h/d - No HK 24 2 20-Aug-23 12-Sep-23 26-Oct-23 18-Nov-23 67
Hols - No B/O periods (was
310.T.EX.L492 WSA - Vehicle Search Bay and C&ED Control Kiosk - Plumbing System Test C1)
C01_7 d/w - 10h/d - No HK 24 2 20-Aug-23 12-Sep-23 13-Oct-23 05-Nov-23 54
Hols - No B/O periods (was
310.T.EX.L488 WSA - Vehicle Search Bay and C&ED Control Kiosk - Systems Integration Test C1)
C01_7 d/w - 10h/d - No HK 30 3 18-Nov-23 17-Dec-23 19-Nov-23 18-Dec-23 1
Hols - No B/O periods (was
HKO Facilities C1) 663 9 22-Jul-21 A 11-Oct-23 27-Mar-22 15-Oct-23 3
Subletting & Procurement C01_7 d/w - 10h/d - No HK Hols181
- No B/O periods
0 (was
30-Oct-21
C1) A 29-Jul-22 28-Jan-23 27-Apr-23 272
Subletting C01_7 d/w - 10h/d - No HK Hols181
- No B/O periods
0 (was
30-Oct-21
C1) A 29-Jul-22 28-Jan-23 27-Apr-23 272
310.P.EX.F128 Subletting - Optional Works MEP - Award sub-contract C01_7 d/w - 10h/d - No HK 90 30-Oct-21 A 18-Jan-22 A 27-Apr-23 27-Apr-23
Hols - No B/O periods (was
310.P.EX.F140 Subletting - Optional Works Earthwork - Stage 1&2 Preparation,Submission& C1)
C01_7 d/w - 10h/d - No HK 90 01-May-22 29-Jul-22 28-Jan-23 27-Apr-23 272
Approval,Tender&Award sub-contract Hols - No B/O periods (was
Submissions C1) 250 0 22-Jul-21 A 24-May-22 27-Mar-22 14-Jun-22 17
Coordination 195 0 22-Jul-21 A 29-Mar-22 27-Mar-22 29-Mar-22 0
310.C.RC.R002 HKO Anemometer - coordination with AA for site access and exemption C11_6 d/w - 10h/d - With 45 22-Jul-21 A 11-Sep-21 A 27-Mar-22 27-Mar-22
HK Hols - No B/O periods
310.C.RC.R002.1.B01 HKO Anemometer - coordination & confirmation of construction details with BD Approval (was
C01_7C3)
d/w - 10h/d - No HK 80 10-Nov-21 A 29-Mar-22 27-Mar-22 29-Mar-22 0
Hols - No B/O periods (was
Method Statement Submission C1)
C01_7 d/w - 10h/d - No HK Hols56
- No B/O periods
0 (was30-Mar-22
C1) 24-May-22 20-Apr-22 14-Jun-22 21
Method Statement - Cabling C01_7 d/w - 10h/d - No HK Hols56
- No B/O periods
0 (was30-Mar-22
C1) 24-May-22 20-Apr-22 14-Jun-22 21
310.D.RC.S031.B01 HKO Anemometer - Method Statement - Cabling Works - prepare document C01_7 d/w - 10h/d - No HK 28 30-Mar-22 26-Apr-22 20-Apr-22 17-May-22 21
Hols - No B/O periods (was
310.D.RC.S032.B01 HKO Anemometer - Method Statement - Cabling Works - PM review and accept C1)
C01_7 d/w - 10h/d - No HK 28 27-Apr-22 24-May-22 18-May-22 14-Jun-22 21
Hols - No B/O periods (was
BA Submission C1)
C01_7 d/w - 10h/d - No HK Hols28
- No B/O periods
0 (was
16-Feb-22
C1) A 02-Apr-22 27-Mar-22 02-Apr-22 0
310.D.RC.S30 HKO Anemometer - submit BA8 consent application to BD C01_7 d/w - 10h/d - No HK 28 16-Feb-22 A 24-Mar-22 A 27-Mar-22 27-Mar-22
Hols - No B/O periods (was
310.C.RC.S208 HKO Anemometer - submit BA10 notice of commencement of work C1)
C01_7 d/w - 10h/d - No HK 7 27-Mar-22 02-Apr-22 27-Mar-22 02-Apr-22 0
Hols - No B/O periods (was
C1)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 253 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
HKO Equipment (Anemometer) 633 3 11-Sep-21 A 07-Oct-23 27-Mar-22 14-Oct-23 6
HKO Area 279 2 11-Sep-21 A 31-Jul-22 27-Mar-22 31-Jul-22 0
Work Permit 244 0 11-Sep-21 A 18-Jun-22 27-Mar-22 09-Jul-22 17
310.C.RC.R042.B01 HKO Anemometer - Application of Work Permit (Cable detection on Footing footprint) C01_7 d/w - 10h/d - No HK 21 11-Sep-21 A 15-Oct-21 A 27-Mar-22 27-Mar-22
Hols - No B/O periods (was
310.C.RC.R42 HKO Anemometer - Application of Work Permit (Cable Detection on cable drawpit / cable C1)
C01_7 d/w - 10h/d - No HK 21 15-Dec-21 A 15-Jan-22 A 27-Mar-22 27-Mar-22
ducts) Hols - No B/O periods (was
310.C.RC.R043.B01 HKO Anemometer - Application of Work Permit (Cabling Works) C1)
C11_6 d/w - 10h/d - With 21 25-May-22 18-Jun-22 15-Jun-22 09-Jul-22 17
HK Hols - No B/O periods
Installation Works (was C3) 174 2 13-Sep-21 A 31-Jul-22 27-Mar-22 31-Jul-22 0
310.C.RC.R018 HKO Anemometer - Grant Site Access C11_6 d/w - 10h/d - With 0 13-Sep-21 A 27-Mar-22
HK Hols - No B/O periods
Initial Works (was C3) 56 0 30-Dec-21 A 11-Apr-22 27-Mar-22 21-Apr-22 6
310.C.RC.R006.B01 HKO Anemometer - Cable Detection under Footing (NOTAM) C23_4d/w - NOTAM 3 30-Dec-21 A 30-Dec-21 A 27-Mar-22 27-Mar-22
(M,W,Th,Su-01:30-07:30) -
310.C.RC.R007.B01 HKO Anemometer - Trial pit at Anemometer 4 & 5 Footing (NOTAM) No HK d/w
C01_7 Hols- -10h/d
With B/O
- No HK 4 19-Jan-22 A 20-Jan-22 A 27-Mar-22 27-Mar-22
Hols - No B/O periods (was
310.C.RC.R006 HKO Anemometer - Inspection of manhole condition survey and trial pit excavation C1)
C11_6 d/w - 10h/d - With 16 24-Jan-22 A 11-Apr-22 02-Apr-22 21-Apr-22 6
HK Hols - No B/O periods
310.C.RC.R022.B01 HKO Anemometer - Installation of Settlement points (NOTAM) (was C3) - NOTAM
C23_4d/w 8 21-Mar-22 A 25-Mar-22 A 27-Mar-22 27-Mar-22
(M,W,Th,Su-01:30-07:30) -
HKO Anemometer Footing No HK Hols- -NOTAM
C23_4d/w With B/O(M,W,Th,Su-01:30-07:30)
32 0 - No HK
03-Apr-22
Hols - With B/O07-Jul-22
Periods & Flight03-Apr-22
Checks 31-Jul-22 13
310.C.RC.R010 HKO Anemometer - Excavation and Construction of Footing for Anemometer 4&5 C23_4d/w - NOTAM 18 03-Apr-22 13-Jun-22 03-Apr-22 13-Jun-22 0
(NOTAM) (M,W,Th,Su-01:30-07:30) -
310.C.RC.R011.B01 HKO Anemometer - Footing - Submission of Form BA14 for Completion of Works No HK Hols- -NOTAM
C23_4d/w With B/O 14 15-Jun-22 07-Jul-22 07-Jul-22 31-Jul-22 13
(M,W,Th,Su-01:30-07:30) -
HKO Drawpit & Duct No HK Hols- -NOTAM
C23_4d/w With B/O(M,W,Th,Su-01:30-07:30)
14 0 - No HK
15-Jun-22
Hols - With B/O07-Jul-22
Periods & Flight15-Jun-22
Checks 07-Jul-22 0
310.C.RC.R013 HKO Anemometer - Excavation and Construction of Temporary cable draw pit and cable C23_4d/w - NOTAM 14 15-Jun-22 07-Jul-22 15-Jun-22 07-Jul-22 0
duct for power and comms (NOTAM) (M,W,Th,Su-01:30-07:30) -
HKO Pillar Box, Comms & Power Cabling No HK Hols- -NOTAM
C23_4d/w With B/O(M,W,Th,Su-01:30-07:30)
10 2 - No HK
10-Jul-22
Hols - With B/O25-Jul-22
Periods & Flight10-Jul-22
Checks 25-Jul-22 0
310.C.RC.R013.B01 HKO Anemometer - Cabling works_Communication System (NOTAM) C23_4d/w - NOTAM 10 1 10-Jul-22 25-Jul-22 10-Jul-22 25-Jul-22 0
(M,W,Th,Su-01:30-07:30) -
310.C.RC.R015.B01 HKO Anemometer - Cabling works_Power System (NOTAM) No HK Hols- -NOTAM
C23_4d/w With B/O 10 1 10-Jul-22 25-Jul-22 10-Jul-22 25-Jul-22 0
(M,W,Th,Su-01:30-07:30) -
HKO Inspection & Handover No HK d/w
C01_7 Hols- -10h/d
With B/O
- No HK Hols 7- No B/O periods
0 (was25-Jul-22
C1) 31-Jul-22 25-Jul-22 31-Jul-22 0
310.C.RC.R014 HKO Anemometer - Testing & Commissioning, Inspection & Handover with relevant C01_7 d/w - 10h/d - No HK 7 25-Jul-22 31-Jul-22 25-Jul-22 31-Jul-22 0
authorities Hols - No B/O periods (was
310.C.RC.R026 HKO Anemometer - Achieved KD-G1 C1)
C01_7 d/w - 10h/d - No HK 0 31-Jul-22 31-Jul-22 0
Hols - No B/O periods (was
Between ATCX & BATCX C1)
C11_6 d/w - 10h/d - With HK Hols
35- No B/O 1periods (was
01-Aug-22
C3) 09-Sep-22 02-Sep-23 14-Oct-23 325
310.C.RC.R38 Between ATCX and BATCX - Cable Detection, Trial Pits C11_6 d/w - 10h/d - With 14 01-Aug-22 16-Aug-22 02-Sep-23 18-Sep-23 325
HK Hols - No B/O periods
310.C.RC.R46 Between ATCX and BATCX - Cabling Works_Power System (was
C11_6C3)
d/w - 10h/d - With 15 1 17-Aug-22 02-Sep-22 19-Sep-23 07-Oct-23 325
HK Hols - No B/O periods
310.C.RC.R47.B02 Between ATCX and BATCX - T&C and Inspection & handover with relevant authorities (was
C11_6C3)
d/w - 10h/d - With 6 03-Sep-22 09-Sep-22 09-Oct-23 14-Oct-23 325
HK Hols - No B/O periods
HKO Anemometer Parallel Run & Remaining Works (was C3) 354 0 01-Aug-22 07-Oct-23 01-Aug-22 08-Oct-23 0
310.C.RC.R050.B01 HKO Anemometer - Installation of New HKO Equipment (by others) C01_7 d/w - 10h/d - No HK 28 01-Aug-22 28-Aug-22 01-Aug-22 28-Aug-22 0
Hols - No B/O periods (was
310.C.RC.R058.B01 HKO Anemometer - Construct New Glide Path Antenna Counterpoise, Submit BA14 and C1)
C11_6 d/w - 10h/d - With 45 15-Aug-23 07-Oct-23 15-Aug-23 07-Oct-23 0
H/O inspection with relevant authorities HK Hols - No B/O periods
(was C3)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 254 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.RC.R030.B01 HKO Anemometer - Complete Parallel Run with existing Anemometer (365 days) C01_7 d/w - 10h/d - No HK 0 28-Aug-23 28-Aug-23 0
Hols - No B/O periods (was
310.C.RC.R054.B01 HKO Anemometer - Remove Existing Anemometer C1)
C11_6 d/w - 10h/d - With 12 29-Aug-23 11-Sep-23 29-Aug-23 11-Sep-23 0
HK Hols - No B/O periods
310.C.RC.R158.B01 HKO Anemometer - Achieved KD-G2 (was
C01_7C3)
d/w - 10h/d - No HK 0 07-Oct-23 08-Oct-23 1
Hols - No B/O periods (was
HKO Equipment (Ceilometer) C1) 140 3 25-Apr-23 11-Oct-23 28-Apr-23 14-Oct-23 3
310.C.RC.R032 HKO Equipment (Ceilometer) - Footing C11_6 d/w - 10h/d - With 45 25-Apr-23 17-Jun-23 28-Apr-23 21-Jun-23 3
HK Hols - No B/O periods
310.C.RC.R012.B01 HKO Equipment (Ceilometer) - Footing - Submission of Form BA14 for Completion of (was C3) - NOTAM
C23_4d/w 14 18-Jun-23 10-Jul-23 09-Aug-23 31-Aug-23 30
Works (M,W,Th,Su-01:30-07:30) -
310.C.RC.R040 HKO Equipment (Ceilometer) - Cable ducts & draw pit No HK d/w
C11_6 Hols- -10h/d
With B/O
- With 30 19-Jun-23 25-Jul-23 23-Jun-23 28-Jul-23 3
HK Hols - No B/O periods
310.C.RC.R033 HKO Equipment (Ceilometer) - Cabling (was
C11_6C3)
d/w - 10h/d - With 30 3 26-Jul-23 29-Aug-23 29-Jul-23 01-Sep-23 3
HK Hols - No B/O periods
310.C.RC.R035 HKO Equipment (Ceilometer) - T&C and Inspection & handover with relevant authorities (was
C11_6C3)
d/w - 10h/d - With 35 30-Aug-23 11-Oct-23 02-Sep-23 14-Oct-23 3
HK Hols - No B/O periods
HKO Equipment (Forward Scatterer, RVR Transmissometer, RVR Receivers) (was C3) 140 3 25-Apr-23 11-Oct-23 28-Apr-23 15-Oct-23 3
310.C.RC.R034 HKO Equipment (Forward Scatterer, RVR Transmissometer, RVR Receivers) - Footing C11_6 d/w - 10h/d - With 45 25-Apr-23 17-Jun-23 28-Apr-23 21-Jun-23 3
HK Hols - No B/O periods
310.C.RC.R035.B01 HKO Equipment (Forward Scatterer, RVR Transmissometer, RVR Receivers) - Footing - (was C3) - NOTAM
C23_4d/w 14 18-Jun-23 10-Jul-23 20-Aug-23 11-Sep-23 36
Submission of Form BA14 for Comp of Wk (M,W,Th,Su-01:30-07:30) -
310.C.RC.R041 HKO Equipment (Forward Scatterer, RVR Transmissometer, RVR Receivers) - Cable No HK d/w
C11_6 Hols- -10h/d
With B/O
- With 30 19-Jun-23 25-Jul-23 03-Jul-23 05-Aug-23 10
ducts & draw pits HK Hols - No B/O periods
310.C.RC.R037 HKO Equipment (Forward Scatterer, RVR Transmissometer, RVR Receivers) - cabling (was
C11_6C3)
d/w - 10h/d - With 30 3 26-Jul-23 29-Aug-23 07-Aug-23 09-Sep-23 10
HK Hols - No B/O periods
310.C.RC.R038 HKO Equipment (Forward Scatterer, RVR Transmissometer, RVR Receivers) - T&C & (was
C11_6C3)
d/w - 10h/d - With 28 30-Aug-23 03-Oct-23 11-Sep-23 14-Oct-23 10
handover inspect with relevant authorities HK Hols - No B/O periods
310.C.RC.R036 Achieved KD-G3 -Complete all civil works for CAD Facilities, HKO Facilities (was
C01_7C3)
d/w - 10h/d - No HK 0 11-Oct-23 15-Oct-23 4
Hols - No B/O periods (was
CAD Facilities C1)
C11_6 d/w - 10h/d - With HK Hols
52- No B/O 2periods (was
13-Jun-23
C3) 14-Aug-23 07-Aug-23 07-Oct-23 45
Antenna C11_6 d/w - 10h/d - With HK Hols
52- No B/O 2periods (was
13-Jun-23
C3) 14-Aug-23 07-Aug-23 07-Oct-23 45
310.C.RC.P594 Localizer Bldg C and D Antenna - foundation platform + duct C11_6 d/w - 10h/d - With 30 2 13-Jun-23 19-Jul-23 07-Aug-23 09-Sep-23 45
HK Hols - No B/O periods
310.C.RC.P595.B02 Localizer Bldg C and D Antenna - cabling works (was
C11_6C3)
d/w - 10h/d - With 12 20-Jul-23 02-Aug-23 11-Sep-23 23-Sep-23 45
HK Hols - No B/O periods
310.C.RC.P596 Localizer Bldg C and D Antenna - installation & function test & handover with relevant (was
C11_6C3)
d/w - 10h/d - With 10 03-Aug-23 14-Aug-23 25-Sep-23 07-Oct-23 45
authorities HK Hols - No B/O periods
Appendix C2a - Communication Rooms (was C3) 354 0 20-Oct-22 27-Dec-23 28-Nov-22 31-Dec-23 3
Communication Room CR358 (New Air Traffic Control Tower) 187 0 20-Oct-22 08-Jun-23 28-Nov-22 23-Nov-23 139
310.C.TC.W104 CR358 - Application of Work Permit for Works at Communication Room C01_7 d/w - 10h/d - No HK 21 20-Oct-22 09-Nov-22 06-Apr-23 26-Apr-23 168
Hols - No B/O periods (was
310.C.TC.W100 CR358 - Access Date C1)
C01_7 d/w - 10h/d - No HK 0 28-Nov-22* 28-Nov-22 0
Hols - No B/O periods (was
310.C.TC.W115 CR358 - Communication cabling works i.e. trunking and cable laying [NOTAM] C1)
C23_4d/w - NOTAM 48 30-Nov-22 24-Apr-23 27-Apr-23 10-Aug-23 50
(M,W,Th,Su-01:30-07:30) -
310.C.TC.W118 CR358 - T&C - local connection test [NOTAM] No HK Hols- -NOTAM
C23_4d/w With B/O 14 26-Apr-23 08-Jun-23 20-Sep-23 23-Nov-23 72
(M,W,Th,Su-01:30-07:30) -
Communication Room CR306 (Aircraft Fuel Dispenser Staging and Staff Facilities) No HK Hols - With B/O 137 0 08-Jan-23 28-Jun-23 27-Mar-23 25-Nov-23 125
310.C.TC.W150 CR306 - Application of Work Permit for Works at Communication Room C01_7 d/w - 10h/d - No HK 21 08-Jan-23 28-Jan-23 08-Aug-23 28-Aug-23 212
Hols - No B/O periods (was
C1)
Remaining Work Data Date: 27-Mar-22 Programme Rev. B02
Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 255 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone
Programme for Contract 3310 - North Runway
Modification Works (Rev. B02)
Activity ID Activity Name Calendar OD TRA Start Finish Late Start Late Finish Total 2021 2022 2023 2024
Float J J AS OND J F A J J AS O ND J F A J J AS OND J F M AM J J A S
310.C.TC.W103 CR306 - Access Date C01_7 d/w - 10h/d - No HK 0 27-Mar-23* 27-Mar-23 0
Hols - No B/O periods (was
310.C.TC.W121 CR306 - cabling works i.e. trunking and cable laying (ACS, ALWS, CCTV, AANET, C1)
C11_6 d/w - 10h/d - With 60 27-Mar-23 10-Jun-23 29-Aug-23 09-Nov-23 125
SCADA, VDC) HK Hols - No B/O periods
310.C.TC.W124 CR306 - T&C - local connection test and trouble shooting (was
C11_6C3)
d/w - 10h/d - With 14 12-Jun-23 28-Jun-23 10-Nov-23 25-Nov-23 125
HK Hols - No B/O periods
Data Center (was C3) 115 0 09-Mar-23 29-Jul-23 01-May-23 25-Nov-23 99
310.C.TC.W154 Data Center - Application of Work Permit for Works C01_7 d/w - 10h/d - No HK 21 09-Mar-23 29-Mar-23 08-Aug-23 28-Aug-23 152
Hols - No B/O periods (was
310.C.TC.W106 Data Center - Access Date C1)
C01_7 d/w - 10h/d - No HK 0 01-May-23* 01-May-23 0
Hols - No B/O periods (was
310.C.TC.W127 Data Center - cabling works i.e. trunking and cable laying (SCADA) C1)
C11_6 d/w - 10h/d - With 60 02-May-23 13-Jul-23 29-Aug-23 09-Nov-23 99
HK Hols - No B/O periods
310.C.TC.W130 Data Center - T&C - local connection test and trouble shooting (was
C11_6C3)
d/w - 10h/d - With 14 14-Jul-23 29-Jul-23 10-Nov-23 25-Nov-23 99
HK Hols - No B/O periods
Communication Room CR3088 (Electrical Substation 5) (was C3) 110 0 18-May-23 26-Sep-23 03-Jul-23 25-Nov-23 49
310.C.TC.W158 CR3088 - Application of Work Permit for Works at Communication Room C01_7 d/w - 10h/d - No HK 21 18-May-23 07-Jun-23 08-Aug-23 28-Aug-23 82
Hols - No B/O periods (was
310.C.TC.W109 CR3088 - Access Date C1)
C01_7 d/w - 10h/d - No HK 0 03-Jul-23* 03-Jul-23 0
Hols - No B/O periods (was
310.C.TC.W133 CR3088 - cabling works i.e. trunking and cable laying (ALWS, CCTV, AANET, VDC) C1)
C11_6 d/w - 10h/d - With 60 03-Jul-23 09-Sep-23 29-Aug-23 09-Nov-23 49
HK Hols - No B/O periods
310.C.TC.W136 CR3088 - T&C - local connection test and trouble shooting (was
C11_6C3)
d/w - 10h/d - With 14 11-Sep-23 26-Sep-23 10-Nov-23 25-Nov-23 49
HK Hols - No B/O periods
Communication Room CR78 (Backup IAC) (was C3) 144 0 02-Jun-23 23-Nov-23 28-Jun-23 23-Nov-23 0
310.C.TC.W146 CR78 - Application of Work Permit for Works at Communication Room C01_7 d/w - 10h/d - No HK 21 02-Jun-23 22-Jun-23 28-Jun-23 18-Jul-23 26
Hols - No B/O periods (was
310.C.TC.W112 CR78 - Access Date C1)
C01_7 d/w - 10h/d - No HK 0 17-Jul-23* 17-Jul-23 0
Hols - No B/O periods (was
310.C.TC.W139 CR78 - Communication cabling works i.e. trunking and cable laying [NOTAM] (SCADA) C1)
C23_4d/w - NOTAM 36 19-Jul-23 18-Sep-23 19-Jul-23 18-Sep-23 0
(M,W,Th,Su-01:30-07:30) -
310.C.TC.W142 CR78 - T&C - local connection test and trouble shooting [NOTAM] No HK Hols- -NOTAM
C23_4d/w With B/O 14 20-Sep-23 23-Nov-23 20-Sep-23 23-Nov-23 0
(M,W,Th,Su-01:30-07:30) -
Testing and Commissioning - Integration Test of Communication Link No HK Hols - With B/O 37 0 13-Nov-23 27-Dec-23 25-Nov-23 31-Dec-23 3
310.T.TC.W013 Start after Completion of EVT cabling works (electrical and comms) C11_6 d/w - 10h/d - With 0 13-Nov-23 27-Nov-23 12
HK Hols - No B/O periods
310.T.TC.W010 Completion of Comms ducting works, cable laying, trunking and cable termination (was
C11_6C3)
d/w - 10h/d - With 0 23-Nov-23 25-Nov-23 3
HK Hols - No B/O periods
310.T.TC.W016 T&C - system integration test, connectivity test, packet loss test, function test and (was
C11_6C3)
d/w - 10h/d - With 21 23-Nov-23 16-Dec-23 27-Nov-23 20-Dec-23 3
Inspection HK Hols - No B/O periods
310.T.TC.W019 T&C - PM acceptance & handover inspection with relevant authorities (was
C11_6C3)
d/w - 10h/d - With 7 18-Dec-23 27-Dec-23 21-Dec-23 30-Dec-23 3
HK Hols - No B/O periods
310.T.TC.W022 Achieved KD-6 (Stage 6) - Complete cabling bet. comms rms in ATCT, Backup ATCT, (was
C01_7C3)
d/w - 10h/d - No HK 0 27-Dec-23 31-Dec-23 4
New ATCT through EVT + T&C Hols - No B/O periods (was
C1)

Remaining Work Data Date: 27-Mar-22 Programme Rev. B02


Project ID: 3310-CWPG-B02 Date Revision Checked Approved
Critical Remaining Work Printed: 03-May-22 09:45
Milestone Programme Layout: 3310 - PMP 29-Sep-21 A03 Submission - accepted on 12 Nov ...
Crit Milestone Page 256 of 256 TASK filter: Non-LOE. 18-Feb-22 B01 Submission - not accepted
Actual Work 03-May-22 B02 Submitted
Actual Milestone