Professional Documents
Culture Documents
10.04a PR RFR P06 21
10.04a PR RFR P06 21
10.04a PR RFR P06 21
Refractory 1/15
PR RFR P06-21 V1.0
Introduction
This document is intended to give production managers a working frame to design their own specific warm-up
or cool down procedure, adapted to each case: type of kiln, extend of repairs done on this kiln, etc…:
Procedure for kiln start-up after a major turnaround, defined for each type of kiln:
Preheating curve and kiln turning schedule
Adjustment to the above guidelines, depending on refractory work completed
Start-up procedure and strategy to reach full production
Record Keeping
Modifications to this Procedure for kiln start-up after shutdowns shorter than 48 hours
Additional information required to customize procedures for a specific kiln
Indicators required for process monitoring
This procedure details the following actions:
Warming up program
Tyre creep
Cooling down program
Warming after kiln breakdown
Result indicators
The indicators which need to be recorded to show progress should be
Number of incidents within 2 weeks after start-up
Number of bricks replaced between 2 major shut-downs
Brick consumption in the burning zone in Kg/T/KK/m of kiln length
Amount of time it takes to reach full production
Objectives
Develop master procedures for heating up the pyro-line in a standard, safe and efficient manner
(minimum transition periods, no aborted start-ups) while assuring the integrity of the equipment and of
the refractory and staying in environmental compliance. The procedures will address the quick
compliance with clinker quality objectives.
Then, each plant would customize these master procedures to the specific characteristics of their
equipment and develop more detailed checklists and SOPs.
Safety aspects
Ensure that the whole start-up process is supervised by an experienced kiln coach, burner or production
engineer.
Complete a thorough inspection to check if all doors are closed without anybody left behind, if all safety
protection devices are in place (pull cords, safety guards, limit switches…), and if analyzers and inerting
systems are in operating conditions.
Ensure that safety SOPs are known from the operators and applied (i.e. start-up of electrical motors, of
fuel feeding systems
Maintain a permanent radio contact between start-up team and kiln control operator.
How to warm up / cool down the kiln
Refractory 2/15
PR RFR P06-21 V1.0
Prerequisites
Proper installation of refractory cannot be over emphasized as it plays a key role in the longevity of the
lining. During a major turnaround it would be good for plants to consider hiring an experienced
refractory installation specialist to supervise the ongoing lining replacement or ensure that the installer is
familiar with the various installation techniques that are available.
Each plant should consult and insist on having a representative from the refractory supplier on hand
during the installation and curing of the material chosen. This process is included in the purchasing
agreement set up by a group buying team established through Lafarge in 1998.
In this procedure you may find references to other information (calculation tools, other procedures, knowledge
documents, etc) which are available from the Refractory domain of the Web Cement Portal (standard &
procedures, job aid sections) or from the BRS database (indicators).
How to warm up / cool down the kiln
Refractory 3/15
PR RFR P06-21 V1.0
Action Steps
A. Kiln warm-up
1. Prepare for kiln warm up: Pre-start checks
Check Kiln feed system
The kiln feed system should be run in a recirculation operation and calibrated, if allowed by the system. If
the system does not allow for a complete run, then a way to determine the readiness of the system should
be developed.
If no recirculation system is in place, then the feed system should be run for few minutes, checking for
proper operation and system leaks.
Test run the dust evacuation system including elevators, screws, pumps etc. Continue to run this system
throughout the warm up.
Action Steps
In order to ensure the complete check, it is recommended to fill an "equipment check sheet" for
every equipment and have it signed.
To adjust ID fan draft, backend gas analyzer must be available and used all along the warming up
program.
How to warm up / cool down the kiln
Refractory 5/15
PR RFR P06-21 V1.0
2. Preheating phase
The objective of preparing the kiln refractory for start-up is to:
Dry the burner pipe lining refractory if not already dried.
1 How to line the burner pipe
Dry the castable installed inside the kiln
Preheat the kiln refractory brick linings up to temperature where feed can be introduced into the kiln
It is essential that plants have a preheating schedule determined prior to the start up. The start-up
program, which mainly determines the kiln temperature increase per unit time and the timing of the
introduction of raw feed, must consider a number of factors such as the type of refractory material,
design of the kiln system, mechanical systems etc.
It is recommended to use a real-time report during the kiln start-up, in order to facilitate the post-
audit phase.
Overheating of the refractory and the kiln shell Poor heat distribution
Duck-nesting of the refractory Longer preheat time due to poor transfer of heat
As a compromise, the kiln should be periodically turned i.e.: rotated a fraction of a turn during the initial
phase until the sintering zone temperature reaches approximately 900 degrees "C" (1650F). After this
phase, the kiln can be rotated continuously in a normal manner through the auxiliary drive.
How to warm up / cool down the kiln
Refractory 7/15
PR RFR P06-21 V1.0
Heating up guidelines
Below you will find general guidelines for heating up the kiln before start-up but you should draw a
specific preheat schedule depending on your kiln characteristics and length of stop.
The following information has been collected from a large number of refractory suppliers used by
Lafarge. This information should be used only as a guideline for proper refractory management. In all
cases the plants should review the intended operating procedures with the refractory suppliers as the
amount of refractory types and materials vary extensively.
Most suppliers of refractory materials recommend for the start up of kilns after major turnarounds
with monolithic linings, a maximum heating-up rate of approximately 25°C /h in the sintering zone up
to a temperature of 900°C. After reaching 900°C, heating up can continue at a rate of 50°C up to
the working temperature.
After a minor shutdown (less than 24 hours) where no major lining is replaced, refractory suppliers
recommend a heating-up rate of 50°C/h.
What is not shown in the graph above is a stepped approach to the heat up schedule. What this
means is that there should be a holding pattern on the temperatures in the kiln system in at least two
separate temperature ranges. The first holding pattern should be made in the initial stages of the
heat up procedure. This means that when the sintering zone temperature reaches approximately
300°C, the temperature should be held constant for approximately 3 hours. This procedure should be
repeated again once the sintering zone temperature reaches approximately 500 to 550°C. This
procedure allows the refractory material to "catch up" with the gas temperature. The heat penetrates
the refractory material as well as the metal casings and reduces the possibility of non-uniform
expansion and tyre creep problems. This procedure can of course be modified based on the amount
of refractory work that has been completed during the shutdown.
How to warm up / cool down the kiln
Refractory 8/15
PR RFR P06-21 V1.0
Thermal shock:
brick split like spallings
in 2 – 3 cm layers
8
10
12
14
16
18
20
22
24
Hours
How to warm up / cool down the kiln
Refractory 9/15
PR RFR P06-21 V1.0
Backend T°
(°C)
1000
900
Continuous rotation 800
1/3 revolution every 10 min
1/3 revolution every 15 min
700
1/3 revolution every 30 min 600
1/3 revolution every 45 min 500
400
300
200
100
0
0
9
12
15
18
21
24
27
30
33
36
Hours
How to warm up / cool down the kiln
Refractory 10/15
PR RFR P06-21 V1.0
Tyre temperature is determined by taking the measurement on each side of the tyre. The recorded
temperature should be the average of the two. Tyre creep could be monitored by a shell scanner if
available and, in addition, should be measured every 2 hours during the critical period when tyre
creep is below 8 mm/rev.
How to warm up / cool down the kiln
Refractory 11/15
PR RFR P06-21 V1.0
The temperature difference between the tyre and the shell must be less than 125°C all times during
the warming up program. (To be checked at the plant with the hypothesis taken for shim calculations)
The minimum tyre slippage per kiln revolution is 8mm.
If the kiln tyre slippage falls below 8mm/rev, hold the kiln heat input until the tyre slippage reaches
8mm/rev. At 8mm / rev, resume the preheating schedule.
If the kiln tyre slippage falls below 5mm / rev decrease kiln heat input until the tyre slippage reaches
5mm / rev. Ensure that the shell and the tyre temperature are rising at the same rate. At 5mm +, hold
the kiln heat input until the slippage reaches 8mm +, at this point, resume preheating schedule.
If there is no measurable slippage, follow the instructions for slippage below 5mm/rev with
aggressive moves on heat decrease. If slippage has not returned in ½ hour, shut down.
If tyre slippage is in excess of 25mm,
shimming of the tyre must be considered.
Excess slippage of the tyre can cause problems
with kiln ovality which may result in shell,
refractory and nose ring damage.
3. Feed on phase
Preheaters / Precalciners :
Raw material feed can be started when the temperature curve in the kiln system approaches operational
conditions or as soon as the precalciner and preheat temperatures profile is ready for feed.
The period between the start of the kiln feed and its arrival at the sintering zone is the most critical with
respect to tire creep because the fuel supply must be increased rapidly to compensate for the heat
absorbed by the processing of the raw material. Close attention must be made at this phase so that slip
is continuously present. If slip of the tire ceases, countermeasures must be taken to correct the situation.
Feed may be introduced into the kiln system prior to arriving at optimal temperature as a measure to
coat the refractory linings. Only small amounts can be introduced so that there is not a deterioration of
the heat gradient.
4. Stabilisation period
This is the time where we are building the protective coating on the bricks.
We should avoid over-heating
Feed-rate should be increased by small increments to maintain the back-end temperature while avoiding
flushing in the burning zone.
5. Post audit
A post audit of the start-up to analyze deviations from the planned schedule should be systematically
done between the production coordinator and the kiln operators.
Reasons for deviations should be identified and recommendations to improve the next kiln start-up
should be drafted and when necessary, incorporated into the SOP. Control room operators’
involvement is essential to the success of proper kiln start ups.
Review Items
Preheat temperatures and oxygen control-actual vs. plan
Timing of preheat-actual vs plan
Specific heat consumption / NOx values
Tire Creep report
Axial and swirl settings
How to warm up / cool down the kiln
Refractory 13/15
PR RFR P06-21 V1.0
Develop the above into a table that shows the variances and explanations for the
variances.
1 See proposal to build a post-audit report in Annex.
How to warm up / cool down the kiln
Refractory 14/15
PR RFR P06-21 V1.0
Brick hanging
Especially for Alumina brick area
Backend T°
(°C)
1000
900
800
700
600
500
400
300
200
100
0
0
8
10
12
14
16
18
20
22
24
Hours
Continuous rotation
1/3 revolution every 10 min
1/3 revolution every 15 min
1/3 revolution every 30 min
1/3 revolution every 45 min
How to warm up / cool down the kiln
Refractory 15/15
PR RFR P06-21 V1.0
Appendix
Post Audit Report for the kiln start-up dated from ____________________
Reference:___________________