Professional Documents
Culture Documents
Daily Housekeeping Checklist
Daily Housekeeping Checklist
FO/HS42/RO
SITE NAME :- Month :-_____________
Daily Housekeeping checklist Observation ok(√) / Not ok(×)
Frequency SR. No.
Observations
10
11
12
13
14
15
1
2
3
4
5
6
7
8
9
1 Is dedicated housekeeping team available under responsible person?
2 Is Tower incharge ensured that concern contractor clean his work place at the end of shift by devoting at least 30 minute on HK.?
3 Is Housekeeping and debris collecting worker are equipped with Proper PPEs (Helmet, safety shoe/ Gumboot, dust mask, goggles, hand gloves,
yellow coloured reflective jacket with Housekeeping person label )
4 Is Housekeeping and debris collecting worker are provided with proper tools (Broom Brush, collecting tray/pan, spade etc.)
5 Is peripheral area of site adequately fenced?
6 Is perimeter area and frontage of site free of dust, concrete spillage, stagnant water etc?
7 Is nomenclature prominently in place such as tower name / number, offices, other facilities, Plant & machineries, pictorial gender marks on
urinals/ toilets, floor/ level number marking in staircase & face of tower etc...?
8 Is awareness training about “Site HK Rules” through Pep-Talk / Tool Box / Training, posters, signage’s.going on?
9 Is safety nets, catch platforms, and chajjas cleaned regularly?
10 Are there separate gate provided for material entry and labour entry?
11 Are walkways and gangways with minimum width of 1.2M maintained and clear of obstruction?
12 Are emergency exit, fire doors, access to fire extinguishers, electrical panels and DB’s , First Aid station etc… unobstructed and in good working
order?
13 Are all cut- outs, floor edges, shafts, voids, staircases, open excavation and trenches etc…hard barricaded?
14 Is adequate illumination provided at work place, stair case, landing passages, lift shafts and maintained general uniform illumination of 50 Lux
across length and breadth of site and access roads?
Daily Activity
Page 1 of 2
GODREJ PROPERTIES LIMITED
42 Are all surplus earth/ debris removed and disposed from site fortnightly?
Inspection Team:
Page 2 of 2