Professional Documents
Culture Documents
PLT Methodology
PLT Methodology
For
Submitted by
Skanda Material Testing Laboratory Private Limited
26-150, Sharadanagar
Safilguda, Hyderabad- 500047
Contents
2. Reference 3
3. Equipment 3
4. Procedure 3
5. Load-Settlement Curves 5
7. Submission of Results 6
8. Loads Proposed 7
Page 2 of 7
1. What is the Plate Load Test?
The plate load test is a field test, which is performed to determine the ultimate bearing
capacity of the soil and the probable settlement under a given load. This test is very
popular for the selection and design of foundation.
For performing this test, the plate is placed at the desired depth, then the load is
applied gradually and the settlement for each increment of the load is recorded. At one
point a settlement occurs at a rapid rate, the total load up to that point is calculated
and divided by the area of the plate to determine the ultimate bearing capacity of soil
at that depth. The ultimate bearing capacity is then divided by a safety factor (typically
2.5 – 3) to determine the Safe bearing capacity.
2. Reference
3. Equipment
The following plate load test apparatus is necessary for performing the test.
1. Test plate of size 750x750mm
2. Hydraulic jack & pump
3. Reaction beam
4. Dial gauges – 4 Nos
5. Pressure gauge
6. Loading columns
7. Necessary equipment for the loading platform, like MS sheet to rest sand bags
8. Tripod, Plumb bob, sprit level etc.
4. Procedure
The following procedure is adopted to perform a plate load test :
1. Excavation test pit up to the desired depth (Founding Level in our Case). The pit size
should be at least 5 times the size of the test plate (bp)
2. At the centre of the pit, a small hole or depression is created. The size of the hole is
the same as the size of the steel plate. The bottom level of the hole should
correspond to the level of the actual foundation.
Page 3 of 7
3. A mild steel plate is used as a load-bearing plate of 25 mm thick and size adopted
are 450 mm,600mm and 750 mm. The plate adopted here is square in shape and of
750x750mm size.
4. A load transfer Jack is placed at the centre of the plate. The load is transferred to the
plate through the centrally placed jack.
5. The load transfer is by gravity loading method. The test set up is shown in Figure 1
Page 4 of 7
5. Load-Settlement Curves
Curve I is typical of dense sand or gravel or stiff clay, wherein general shear failure
occurs. The point corresponding to failure is obtained by extrapolating backwards (as
shown in the Figure 2), as a pronounced departure from the straight line relationship
that applies to the initial stages of loading is observed. (This coincides approximately
with the point up to which the range of proportionality extends).
Curve II is typical of loose sand or soft clay, wherein local shear failure occurs.
Continuous steepening of the curve is observed and it is rather difficult to pinpoint
failure; however, the point where the curve becomes suddenly steep is located and
treated as that corresponding to failure.
The size effect has been empirically evolved in the form of the following equation
(Terzaghi and Peck, 1948):
Page 5 of 7
〈 . 〉
= 〈
-- 1
. 〉
Where
S = settlement of the proposed foundation (mm),
Sp (same units) = settlement of the test plate (mm),
b = size of the proposed foundation (m), and
bp = size of the test plate (m).
However, the relationship is simpler for clays, since the modulus value Es, for clays
is reasonably constant:
= -- 2
= 〈
--3
. 〉
7. Submission of Results
The data which is recorded for every incremental load and corresponding settlement
will be recorded . After completion of each test the calculations will be done for each
increment of load and will be submitted.
Page 6 of 7
8. Proposed loads
The following plates are considered for testing
750mm x 750mm
Calculation for 750m x 750mm plate:
Safe Stress on Foundation (qf) = 150 t/m2 ( Assumed)
.
Safe stress on plate (qp) = = 28.125 𝑡/𝑚
.
Ultimate stress on plate with FS of 2.5 = 𝑞 = 2.5𝑥 𝑞 = 2.5𝑥 28.125 = 70.31 𝑡/𝑚
Stress on platform = 1.5 𝑡𝑖𝑚𝑒𝑠 𝑈𝑙𝑡𝑖𝑚𝑎𝑡𝑒 𝑠𝑡𝑟𝑒𝑠𝑠 = 1.5 𝑥 70.31 = 105.47 t/m2
Load on platform= 105.47 x (0.75x0.75) = 59.33 T Say 60.0 tonnes
Page 7 of 7