SUMMARY

RENOVASI DAN PERLUASAN MASJID AR-RAUDAH KIDECO TANAH MERAH


JUMLAH HARGA PLAN
NO U R A I A N REMARKS
(Rp.) %

A PREPARATION WORK Rp 172.429.000,00 6,90%


B EARTHWORK & FOUNDATION WORK Rp 85.549.520,00 3,42%
C STRUCTURE WORK Rp 298.086.856,00 11,92%
D WALL WORK Rp 157.745.360,00 6,31%
E FLOOR WORK Rp 413.814.803,00 16,55%
F CEILING WORK Rp 106.591.004,00 4,26%
G ROOFING WORK Rp 329.617.279,00 13,18%
H DOOR & WINDOW WORK Rp 117.246.800,00 4,69%
I PAINTING WORK Rp 74.139.839,00 2,97%
J SANITATION WORK Rp 48.336.730,00 1,93%
K MISCELLANEOUS WORK Rp 389.479.877,00 15,58%
L ELECTRICAL WORK Rp 307.090.581,63 12,28%

TOTAL PRICE Rp 2.500.127.649,63 100,00%


ROUNDED Rp 2.500.000.000,00
IN WORDS : DUA MILYAR LIMA RATUS JUTA RUPIAH

BoQ AR - RAUDAH Page 1 of 7


Bill of Quantity
RENOVASI DAN PERLUASAN MASJID AR-RAUDAH KIDECO TANAH MERAH
HARGA SATUAN JUMLAH HARGA SATUAN
NO. URAIAN SAT VOLUME JUMLAH KETERANGAN
MATERIAL CONSTRUCTION MATERIAL CONSTRUCTION

A PREPARATION WORK 121.060.000 51.369.000 172.429.000,00


1 General Management ls 1,00 9.500.000 4.000.000 9.500.000 4.000.000 13.500.000,00
2 Temporary Offife and Facilities ls 1,00 29.000.000 12.500.000 29.000.000 12.500.000 41.500.000,00
3 Transportation Site month 6,00 9.500.000 4.000.000 57.000.000 24.000.000 81.000.000,00
4 Safety device ls 1,00 3.250.000 1.250.000 3.250.000 1.250.000 4.500.000,00
5 General for Mob & Demob ls 1,00 4.900.000 2.000.000 4.900.000 2.000.000 6.900.000,00
6 Banner Fence for Site m' 57,00 95.000 42.000 5.415.000 2.394.000 7.809.000,00
7 Dismantle Work (Inside Wall, Wudhu & Fence) month 1,00 6.000.000 2.500.000 6.000.000 2.500.000 8.500.000,00
8 Bouwplank m' 109,00 55.000 25.000 5.995.000 2.725.000 8.720.000,00

B EARTHWORK & FOUNDATION WORK 67.691.780 17.857.740 85.549.520,00


1 Found. Soil Excavation m3 85,14 - 25.000 2.128.500 2.128.500,00
2 Refill Found. Soil m3 25,54 - 42.000 1.072.680 1.072.680,00
3 Compaction Stamper m2 19,23 - 60.000 1.153.800 1.153.800,00
4 Lean Concrete Found. m3 3,49 900.000 185.000 3.141.000 645.650 3.786.650,00
5 Rebar Foundation kg 2.242,06 13.000 2.700 29.146.780 6.053.562 35.200.342,00
6 Form Work Foundation m2 45,32 100.000 23.900 4.532.000 1.083.148 5.615.148,00
7 Concrete Found. K-250 m3 18,16 1.700.000 315.000 30.872.000 5.720.400 36.592.400,00

C STRUCTURE WORK 246.833.910 51.252.946 298.086.856,00


1 Sloof Found. 250/400
A Rebar kg 871,30 13.000 2.700 11.326.900 2.352.510 13.679.410,00
B Form Work m2 84,05 100.000 23.900 8.405.000 2.008.795 10.413.795,00
C Concrete K-250 m3 10,51 1.700.000 315.000 17.867.000 3.310.650 21.177.650,00
2 Sloof Found. 200/300
A Rebar kg 923,92 13.000 2.700 12.010.960 2.494.584 14.505.544,00
B Form Work m2 85,90 100.000 23.900 8.590.000 2.053.010 10.643.010,00
C Concrete K-250 m3 8,59 1.700.000 315.000 14.603.000 2.705.850 17.308.850,00
3 Column. 250/250
A Rebar kg 1.711,76 13.000 2.700 22.252.880 4.621.752 26.874.632,00
B Form Work m2 154,09 100.000 23.900 15.409.000 3.682.751 19.091.751,00
C Concrete K-250 m3 9,63 1.700.000 315.000 16.371.000 3.033.450 19.404.450,00
4 Column. 200/200
A Rebar kg 287,15 13.000 2.700 3.732.950 775.305 4.508.255,00
B Form Work m2 31,72 100.000 23.900 3.172.000 758.108 3.930.108,00
C Concrete K-250 m3 1,59 1.700.000 315.000 2.703.000 500.850 3.203.850,00
5 Column. 15/150 (Practice column)
A Rebar kg 164,93 13.000 2.700 2.144.090 445.311 2.589.401,00
B Form Work m2 15,89 100.000 23.900 1.589.000 379.771 1.968.771,00
C Concrete K-175 m3 0,89 1.172.000 206.000 1.043.080 183.340 1.226.420,00
6 Girder. 250/350
A Rebar kg 1.438,54 13.000 2.700 18.701.020 3.884.058 22.585.078,00
B Form Work m2 170,26 100.000 23.900 17.026.000 4.069.214 21.095.214,00
C Concrete K-250 m3 15,68 1.700.000 315.000 26.656.000 4.939.200 31.595.200,00
7 Girder. 200/300
A Rebar kg 206,49 13.000 2.700 2.684.370 557.523 3.241.893,00

BoQ AR - RAUDAH Page 2 of 7


HARGA SATUAN JUMLAH HARGA SATUAN
NO. URAIAN SAT VOLUME JUMLAH KETERANGAN
MATERIAL CONSTRUCTION MATERIAL CONSTRUCTION
B Form Work m2 34,61 100.000 23.900 3.461.000 827.179 4.288.179,00
C Concrete K-250 m3 2,60 1.700.000 315.000 4.420.000 819.000 5.239.000,00
8 Girder. 150/200
A Rebar kg 331,50 13.000 2.700 4.309.500 895.050 5.204.550,00
B Form Work m2 45,89 100.000 23.900 4.589.000 1.096.771 5.685.771,00
C Concrete K-250 m3 2,50 1.700.000 315.000 4.250.000 787.500 5.037.500,00
9 Ring Balk. 150/200
A Rebar kg 279,50 13.000 2.700 3.633.500 754.650 4.388.150,00
B Form Work m2 19,78 100.000 23.900 1.978.000 472.742 2.450.742,00
C Concrete K-175 m3 1,48 1.172.000 206.000 1.734.560 304.880 2.039.440,00
10 Latei Beam. 150/150
A Rebar kg 431,42 13.000 2.700 5.608.460 1.164.834 6.773.294,00
B Form Work m2 34,92 100.000 23.900 3.492.000 834.588 4.326.588,00
C Concrete K-175 m3 2,62 1.172.000 206.000 3.070.640 539.720 3.610.360,00

D WALL WORK 133.713.230 24.032.130 157.745.360,00


1 Mud brick 0.5 Wall m2 258,63 139.000 24.500 35.949.570 6.336.435 42.286.005,00
2 Plesteran + acian m2 647,99 55.000 10.500 35.639.450 6.803.895 42.443.345,00
3 Ceramics Wall 300/600 (Wudhu & Toilet) m2 144,73 193.000 34.000 27.932.890 4.920.820 32.853.710,00
4 Dinding Batu Alam m2 53,00 516.000 90.000 27.348.000 4.770.000 32.118.000,00
5 Dinding GRC Motif m2 45,32 151.000 26.500 6.843.320 1.200.980 8.044.300,00

E FLOOR WORK 351.792.639 62.022.164 413.814.803,00


1 Soil Fill m3 67,20 71.500 12.600 4.804.800 846.720 5.651.520,00
2 Sand Fill m3 25,33 151.000 26.600 3.824.830 673.778 4.498.608,00
3 Plastic Layer Concrete m2 506,50 19.800 3.500 10.028.700 1.772.750 11.801.450,00
4 Wire Mesh Floor M6 1 Layer m2 506,50 51.600 9.100 26.135.400 4.609.150 30.744.550,00
5 Concrete Floor K-175 m3 51,58 1.172.000 206.000 60.451.760 10.625.480 71.077.240,00
6 Granito Ceramics 600/600 m2 399,64 369.500 65.200 147.666.980 26.056.528 173.723.508,00
7 Granito Ceramics 600/600 (Rough Surface) m2 172,01 369.500 65.200 63.557.695 11.215.052 74.772.747,00
8 Ceramics 300/300 (Rough Surface) m2 45,32 194.700 34.300 8.823.804 1.554.476 10.378.280,00
9 Ceramics Plint h 100 mm m2 136,10 194.700 34.300 26.498.670 4.668.230 31.166.900,00

F CEILING WORK 90.641.284 15.949.720 106.591.004,00


1 Metal Furring Frame + Gypsum Plafond 9 mm m2 521,18 147.800 26.000 77.030.404 13.550.680 90.581.084,00
2 Shadow line Gypsum Plafond m 489,60 27.800 4.900 13.610.880 2.399.040 16.009.920,00

G ROOFING WORK 272.993.395 56.623.884 329.617.279,00


1 Roofing Dak
A Stell Floor Deck m2 432,55 123.900 21.800 53.592.945 9.429.590 63.022.535,00
B Wire Mesh M8 1 Layer m2 432,55 61.900 10.900 26.774.845 4.714.795 31.489.640,00
C Concrete K-250 m3 66,83 1.700.000 315.000 113.611.000 21.051.450 134.662.450,00
D Lapisan Waterproof Damdex m2 432,55 121.500 36.400 52.554.825 15.744.820 68.299.645,00
2 Listplank Roofing Dak
A Rebar kg 703,74 13.000 2.700 9.148.620 1.900.098 11.048.718,00
B Form Work m2 117,09 100.000 23.900 11.709.000 2.798.451 14.507.451,00
C Concrete K-175 m3 4,78 1.172.000 206.000 5.602.160 984.680 6.586.840,00

H DOOR & WINDOW WORK 99.961.500 17.285.300 117.246.800,00


1 DW1 WPC Door & Window + accessories ea 5,00 4.892.400 863.300 24.462.000 4.316.500 28.778.500,00

BoQ AR - RAUDAH Page 3 of 7


HARGA SATUAN JUMLAH HARGA SATUAN
NO. URAIAN SAT VOLUME JUMLAH KETERANGAN
MATERIAL CONSTRUCTION MATERIAL CONSTRUCTION
2 DW2 WPC Door & Window + accessories ea 1,00 4.484.700 791.400 4.484.700 791.400 5.276.100,00
3 DW3 WPC Door & Window + accessories ea 2,00 3.434.900 429.600 6.869.800 859.200 7.729.000,00
4 D1 WPC Door + accessories ea 2,00 1.460.900 257.800 2.921.800 515.600 3.437.400,00
5 D2 WPC Door + accessories ea 4,00 1.298.600 229.100 5.194.400 916.400 6.110.800,00
6 W1 Alumunium Window (Glass 5 mm) + accessories ea 14,00 3.159.100 557.400 44.227.400 7.803.600 52.031.000,00
7 W2 Alumunium Window (Glass 5 mm) + accessories ea 6,00 1.609.300 284.000 9.655.800 1.704.000 11.359.800,00
8 BV Alumunium Bouvenlight + accessories ea 6,00 357.600 63.100 2.145.600 378.600 2.524.200,00

I PAINTING WORK 63.151.379 10.988.460 74.139.839,00


1 Painting Wall Exterior (Weather Shield) m2 616,69 38.900 6.800 23.989.241 4.193.492 28.182.733,00
2 Painting Wall Interior m2 879,79 25.400 4.400 22.346.666 3.871.076 26.217.742,00
3 Painting Ceiling m2 521,18 25.400 4.400 13.237.972 2.293.192 15.531.164,00
4 Coating Batu Alam m2 53,00 67.500 11.900 3.577.500 630.700 4.208.200,00

J SANITATION WORK 41.092.120 7.244.610 48.336.730,00


1 Installation PVC Pipe 1"-1/2" AW + Accesories m 70,90 15.400 2.700 1.091.860 191.430 1.283.290,00
2 Installation PVC Pipe 2,5" AW (Downspout Roofing)+ m 164,20 4.564.760 804.580 5.369.340,00
27.800 4.900
Accessories
3 Installation PVC Pipe 3" AW + Accesories m 20,50 54.800 9.600 1.123.400 196.800 1.320.200,00
4 Installation PVC Pipe 4" AW + Accesories m 12,00 91.300 16.100 1.095.600 193.200 1.288.800,00
5 Closet TOTO CW637J/SW637JP ea 2,00 2.344.500 413.700 4.689.000 827.400 5.516.400,00
6 Jet Shower TOTO TX403SMCRB ea 2,00 516.500 91.100 1.033.000 182.200 1.215.200,00
7 Closet Jongkok TOTO CE7 ea 1,00 357.600 63.100 357.600 63.100 420.700,00
8 Wastafel TOTO LW230J ea 2,00 1.549.700 273.400 3.099.400 546.800 3.646.200,00
9 Urinal TOTO U57M ea 3,00 1.708.700 301.500 5.126.100 904.500 6.030.600,00
10 Urinal partisi TOTO A100 ea 2,00 696.100 122.800 1.392.200 245.600 1.637.800,00
11 Floor Drain, Stainless Steel ea 8,00 119.200 21.000 953.600 168.000 1.121.600,00
12 Roof Drain, Stainless Steel ea 31,00 194.700 34.300 6.035.700 1.063.300 7.099.000,00
13 Cermin Wastafel ea 2,00 476.850 84.150 953.700 168.300 1.122.000,00
14 Valve Toilet, Stainless Steel ea 5,00 139.000 24.500 695.000 122.500 817.500,00
15 Valve Wudhu Toto TX133L ea 19,00 59.600 10.500 1.132.400 199.500 1.331.900,00
16 Septic tank Bio tech, Cap 2000 liter ea 1,00 7.748.800 1.367.400 7.748.800 1.367.400 9.116.200,00

K MISCELLANEOUS WORK 313.859.808 75.620.069 389.479.877,00


1 Ditch Concrete
A Wire Mesh M6 1 Layer m2 109,00 51.600 9.100 5.624.400 991.900 6.616.300,00
B Form Work m2 152,60 100.000 23.900 15.260.000 3.647.140 18.907.140,00
C Concrete K-175 m3 12,54 1.172.000 206.000 14.696.880 2.583.240 17.280.120,00
D Plesteran + acian m2 109,00 59.600 10.500 6.496.400 1.144.500 7.640.900,00
2 Cover Ditch
A Rebar D10 kg 289,47 13.000 2.700 3.763.110 781.569 4.544.679,00
B Angle 50.50.5 kg 917,74 23.800 4.200 21.842.212 3.854.508 25.696.720,00
C Painting Steel m2 17,44 38.900 6.800 678.416 118.592 797.008,00
3 Vertical Ladder
A Galvanis Steel Pipe
Ø 2" m 19,90 17.000 30.000 338.300 597.000 935.300,00
Ø 1.5" m 8,10 122.000 21.000 988.200 170.100 1.158.300,00
B Strip Plate 50 mm, t = 5 mm kg 27,79 23.000 4.200 639.170 116.718 755.888,00
C Panting Steel m2 4,23 38.000 11.000 160.740 46.530 207.270,00
4 Koridor Wudhu (Tambahan blm masuk

BoQ AR - RAUDAH Page 4 of 7


HARGA SATUAN JUMLAH HARGA SATUAN
NO. URAIAN SAT VOLUME JUMLAH KETERANGAN
MATERIAL CONSTRUCTION MATERIAL CONSTRUCTION
A Rebar Structure (Fnd, Sloof & Column) kg 534,17 13.000 2.700 6.944.210 1.442.259 8.386.469,00
B Form Work m2 33,86 100.000 23.900 3.386.000 809.254 4.195.254,00
C Concrete K-175 m3 4,61 1.172.000 351.000 5.402.920 1.618.110 7.021.030,00
D Concrete Floor K-175 m3 2,52 1.172.000 351.000 2.953.440 884.520 3.837.960,00
E Ceramics 600/600 m2 25,16 193.000 570.000 4.855.880 14.341.200 19.197.080,00
F Light Steel Frame m2 51,20 151.000 26.000 7.731.200 1.331.200 9.062.400,00
G Spandek Roofing m2 51,20 178.000 31.000 9.113.600 1.587.200 10.700.800,00
H Column Painting m2 18,48 38.000 11.000 702.240 203.280 905.520,00
5 Kubah GRC motif & painting ls 1,00 39.500.000 6.900.000 39.500.000 6.900.000 46.400.000,00
6 Mimbar Kutbah Bahan Kayu Jati Ukir ls 1,00 11.700.000 2.000.000 11.700.000 2.000.000 13.700.000,00
7 Install Paving Block warna merah bata m2 254,00 131.100 23.000 33.299.400 5.842.000 39.141.400,00
8 Fence (Pagar keliling)
A Found. Soil Excavation m3 38,35 - 25.000 958.750 958.750,00
B Lean Concrete Found. m3 3,49 900.000 185.000 3.141.000 645.650 3.786.650,00
C Masonry Found. m3 23,24 1.000.000 178.000 23.240.000 4.136.720 27.376.720,00
D Rebar Structure (Sloof & Column) kg 1.308,18 13.000 2.700 17.006.340 3.532.086 20.538.426,00
E Form Work m2 140,67 100.000 23.900 14.067.000 3.362.013 17.429.013,00
F Concrete K-175 m3 10,55 1.172.000 206.000 12.364.600 2.173.300 14.537.900,00
G Mud brick 0.5 Wall m2 56,97 139.000 24.500 7.918.830 1.395.765 9.314.595,00
H Plesteran + acian m2 164,90 55.000 10.500 9.069.500 1.731.450 10.800.950,00
I Hollow Frame 50.50 m2 43,40 194.000 34.000 8.419.600 1.475.600 9.895.200,00
J Rack Shoes Work
- Wiremesh M6 m2 18,24 51.600 9.100 941.184 165.984 1.107.168,00
- Wiremesh M8 m2 7,56 61.900 10.900 467.964 82.404 550.368,00
- Form Work m2 28,37 100.000 23.900 2.837.000 678.043 3.515.043,00
- Concrete K-175 m3 1,43 900.000 185.000 1.287.000 264.550 1.551.550,00
- Plesteran + acian m2 50,86 55.000 10.500 2.797.300 534.030 3.331.330,00
K Wall, Column & Rack Shoes Painting Work m2 215,76 38.000 11.000 8.198.880 2.373.360 10.572.240,00
L Hollow Steel Painting Work m2 8,68 38.900 11.000 337.652 95.480 433.132,00
M Plate Satainless Steel Font Ar-Raudah ls 1,00 147.000 25.900 147.000 25.900 172.900,00
N Pintu Pagar m2 10,34 536.000 94.600 5.542.240 978.164 6.520.404,00

L ELECTRICAL WORK 257.156.251 49.934.330 307.090.581,63


1 MASJID
a Downlight Led Inbow 13Watt colour white ea 96,00 77.000 13.000 7.392.000 1.248.000 8.640.000,00
b WT069C 1xTL LED Eco fit 16W include instalation ea 3,00
290.000 51.000 870.000 153.000 1.023.000,00
(koridor wudhu)
Lampu Gantung Diameter 1.5 meter include lampu bulb
c ea 1,00 9.537.000 1.683.000 9.537.000 1.683.000 11.220.000,00
led
d Lampu Gantung Diameter 30 cm include lampu bulb led ea 4,00 774.000 136.000 3.096.000 544.000 3.640.000,00
e Saklar single inbow incude instalation ea 2,00 178.000 31.000 356.000 62.000 418.000,00
f Saklar seri inbow incude instalation ea 7,00 194.000 34.000 1.358.000 238.000 1.596.000,00
g Stop kontak inbow 220V ea 19,00 186.000 32.000 3.534.000 608.000 4.142.000,00
h Stop kontak 3 kaki 220V ea 2,00 210.000 37.000 420.000 74.000 494.000,00

HVAC
a KDK Exhaust fan 25t gq include instalation ea 1,00 449.000 79.000 449.000 79.000 528.000,00
b Kipas angin dinding sekai 20 inch ea 10,00 596.000 105.000 5.960.000 1.050.000 7.010.000,00
AC Daikin FTC25NV14 (Indoor + Outdoor) include
c ea 2,00 3.695.000 652.000 7.390.000 1.304.000 8.694.000,00
instalation
AC Daikin 5 PK standing (Indoor + Outdoor) include
d ea 2,00 23.000.000 4.000.000 46.000.000 8.000.000 54.000.000,00
instalation

BoQ AR - RAUDAH Page 5 of 7


HARGA SATUAN JUMLAH HARGA SATUAN
NO. URAIAN SAT VOLUME JUMLAH KETERANGAN
MATERIAL CONSTRUCTION MATERIAL CONSTRUCTION
e Pembongkaran dan pemasangan AC Daikin 5 PK ea 2,00
350.000 60.000 700.000 120.000 820.000,00
standing eksisting (Indoor + Outdoor)

SOUND SYSTEM
a Mic Wireless Ashley AXT200 ea 1,00 1.900.000 343.000 1.900.000 343.000 2.243.000,00
b Mixer Ashley King 6 Channel ea 1,00 2.000.000 364.000 2.000.000 364.000 2.364.000,00
c ZA-2128M PA Amplifier ea 2,00 4.300.000 771.000 8.600.000 1.542.000 10.142.000,00
d ZS-F2000BM Wide Speaker ea 8,00 1.490.000 262.000 11.920.000 2.096.000 14.016.000,00
e ZH-5050M-AS Horn Speaker 50W with transformer ea 2,00 874.000 154.000 1.748.000 308.000 2.056.000,00
f Jack connector Amphenol ls 1,00 357.000 63.000 357.000 63.000 420.000,00
g Kabel sound system Klotz ls 1,00 5.392.000 951.000 5.392.000 951.000 6.343.000,00
h Instalasi sound system ls 1,00 3.973.000 701.000 3.973.000 701.000 4.674.000,00

ASESSORIS
a Cable NYY 4x25mm2 m 45,00 150.000 26.000 6.750.000 1.170.000 7.920.000,00
b Cable NYY 4x6mm3 m 140,00 45.000 8.000 6.300.000 1.120.000 7.420.000,00
c Cable NYM 3x2.5mm2 m 1.000,00 30.000 9.000 30.000.000 9.000.000 39.000.000,00
d Pipe & Flexible 20mm conduit, T-Dos 20mm, Cross Dos ls 1,00
1.192.000 210.000 1.192.000 210.000 1.402.000,00
20mm, Elbow, klem
e inbow dos ea 30,00 1.900 350 57.000 10.500 67.500,00
f Electrical Vynil 3m, scotch Super 33+ ea 2,00 51.000 9.000 102.000 18.000 120.000,00
g Lasdop ls 1,00 198.000 35.000 198.000 35.000 233.000,00

PANEL
a Panel Masjid include instalation set 1,00 10.000.000 1.500.000 10.000.000 1.500.000 11.500.000,00
b Kabel tray 30cm plus cover m 6,00 449.000 79.000 2.694.000 474.000 3.168.000,00

GROUNDING
a Kabel BC 50mm m 20,00 67.000 11.000 1.340.000 220.000 1.560.000,00
Grounding rod Besi lapis Cu 5/8 x 4000 ( Copper Bonded
b ea 3,00 298.000 52.000 894.000 156.000 1.050.000,00
)
c Grounding Box cover plat and busbar ea 1,00 596.000 105.000 596.000 105.000 701.000,00
d Accessories ( cable lug, clamp cable to rod ) ls 1,00 437.000 77.000 437.000 77.000 514.000,00

2 TEMPAT WUDHU
a Downlight Led Inbow 13Watt colour white ea 24,00 77.000 23.000 1.848.000 552.000 2.400.000,00
b Saklar single inbow incude instalation ea 2,00 178.000 53.000 356.000 106.000 462.000,00
c Saklar seri inbow incude instalation ea 4,00 194.000 58.000 776.000 232.000 1.008.000,00
d Stop kontak outbow cover 220V ea 2,00 186.000 56.000 372.000 112.000 484.000,00

HVAC
a KDK Exhaust fan 25tgq include instalation ea 3,00 449.034 134.710 1.347.101 404.130 1.751.231,63

ASESSORIS
a Cable NYY 1x6mm2 m 30,00 13.100 2.300 393.000 69.000 462.000,00
b Cable NYY 4x4mm2 m 30,00 33.300 5.800 999.000 174.000 1.173.000,00
c Cable NYM 3x2.5mm2 m 250,00 30.000 9.000 7.500.000 2.250.000 9.750.000,00
d Pipe & Flexible 20mm conduit, T-Dos 20mm, Cross Dos ls 1,00
1.192.100 210.300 1.192.100 210.300 1.402.400,00
20mm, Elbow, klem
e inbow dos ea 8,00 1.900 500 15.200 4.000 19.200,00
f Electrical Vynil 3m, scotch Super 33+ ea 1,00 51.600 15.400 51.600 15.400 67.000,00

BoQ AR - RAUDAH Page 6 of 7


HARGA SATUAN JUMLAH HARGA SATUAN
NO. URAIAN SAT VOLUME JUMLAH KETERANGAN
MATERIAL CONSTRUCTION MATERIAL CONSTRUCTION

POMPA
a Rumah Pompa ls 1,00 2.781.600 490.800 2.781.600 490.800 3.272.400,00
b Pompa JP Basic 5 ea 2,00 6.000.000 1.000.000 12.000.000 2.000.000 14.000.000,00
c Ball Vavle 1,25" PVC ea 4,00 158.950 28.050 635.800 112.200 748.000,00
d Watermur 1,25" PVC ea 2,00 19.800 3.500 39.600 7.000 46.600,00
e Ball Vavle 1" PVC ea 3,00 39.700 7.000 119.100 21.000 140.100,00
f Watermur 1" PVC ea 2,00 13.900 2.400 27.800 4.800 32.600,00
g Reducer 1 - 0.5" PVC ea 1,00 3.500 600 3.500 600 4.100,00
h Instaslasi PVC pompa (1,25 - 1" pvc) ls 1,00 909.750 160.500 909.750 160.500 1.070.250,00

PANEL
a Panel Inbow include MCB and instalation set 1,00 14.000.000 2.000.000 14.000.000 2.000.000 16.000.000,00

3 MISCELLANEOUS WORK
a SDP Masjid include instalation set 1,00 23.000.000 4.000.000 23.000.000 4.000.000 27.000.000,00
b Accessories instalasi ls 1,00 2.000.000 400.000 2.000.000 400.000 2.400.000,00

Grounding
a Kabel BC 50mm m 20,00 67.500 20.200 1.350.000 404.000 1.754.000,00
b Grounding rod Besi lapis Cu 5/8 x 4000 ( Copper Bonded ea 3,00 298.000 89.400 894.000 268.200 1.162.200,00
c Grounding Box cover plat and busbar ea 1,00 596.000 178.800 596.000 178.800 774.800,00
d Accessories ( cable lug, clamp cable to rod ) ls 1,00 437.100 131.100 437.100 131.100 568.200,00

JUMLAH HARGA 2.059.947.296 440.180.353 2.500.127.649,63


PEMBULATAN 2.500.000.000,00

BoQ AR - RAUDAH Page 7 of 7