Professional Documents
Culture Documents
5 Contract - Discharge
5 Contract - Discharge
Law: the General Rule is that if a contract is to be discharged by performance, the parties must perform their
obligations fully and precisely; Cutter v Powell; Re Moore & Co and Landauer & Co. [use case that is more
relevant to question]
Exceptions: [mention all exceptions of law but use relevant ones to case]
DEFINITION:Discharge refers to a termination of a contract. After a contract is discharged, the parties are relieved
of their obligations under the contract. There are four ways 🡪 Performance, Breach, Agreement and Frustration.
Performance (Pg 179) – discharging a contract by performing all obligations as stipulated in the contract
Precise Performance – General rule is that if a contract is to be discharged by performance, the parties must
perform their obligations fully and precisely.
Cutter v Powell (1795) – The court held that payment was conditional upon the completion of the voyage;
payment even part payment may not be made.
Re Moore & Co and Landauer & Co (1921) – The court held that the buyer was lawfully entitled to reject the
shipment in boxes of 24 cans instead of the contracted 30 cans based on less than full and precise performance.
E Over the years, the courts have acknowledged that this rule of full and precise performance, if applied
x strictly, may cause unfairness.
c
e If the deviation in performance is microscopic, then the contract is deemed to have been
p performed fully and precisely. What is microscopic depends on the facts of the case.
t De minimis
i rule Acros Ltd v E A Ronaasen & Sons (1933) – The HOL held that although the staves were
o of merchantable quality and could be used to manufacture cement barrels, the contract
n was breached because the staves did not correspond to the description of the goods.
s A contract may in certain circumstance be viewed as several independent obligations.
t These may be deemed as severable sub-contracts, e.g. Employment Contracts.
o Not applicable to expressly specified Lump Sum contracts.
t
h
e
P
r
e
c
i
s
e
P Divisible
e contracts
r
f
o
r
m
a
n
c
e
R
u
l
e
Boone v Eyre (1779) – where a promisor has substantially performed his obligations
under a contract, he can claim the agreed payment, less the amount necessary to make
good the defect.
RDC Concrete Pte Ltd v Sato Kogyo (S) Pte Ltd & Another Appeal (2007)
Renunciation
Situation 2: Where a party, by his words or conduct, renounces all obligations under the
contract, the innocent party is entitled to terminate the contract.
By Products Traders Pte Ltd & Another v JAK Alhadad & Co Pte Ltd (2004) – The test of
whether an intention is sufficiently evinced by conduct is whether the party renunciating has
acted in such a way as to lead a reasonable person to the conclusion that he does not intend
to fulfil his part of the contract. In this case, the Singapore High Court rejected JAK’s
arguments that the plaintiffs had repudiated the contract because the plaintiffs had made it clear
Repudiation
that they still intended to purchase the properties from JAK (thus fulfilling their obligations in the
(Pg 184)
contract) if it could prove that it was in a position to sell.
Conditional Breach
Situation 3(a): Condition/warranty approach – where a party breaches a condition of the
contract, the innocent party is entitled to terminate the contract. The nature of the term depends
on the intention of the parties to so designate it.
Fundamental Breach
Situation 3(b): the Hongkong Fir approach – where the nature and consequences of the
breach are so serious as to “go to the root of the contract”, the innocent party is entitled to
terminate the contract.
Teo Teo Lee v Ong Swee Lan & Others (2002) – In commercial contracts, time is usually
considered of essence to the contract because prices can fluctuate significantly over a short
period. Performance of obligations outside the time limits specified in the contract may amount
to a fundamental breach.
Repudiation must be unequivocal
In all cases of breach, whether actual or anticipatory, the repudiation must be unequivocal
(clear). An honest misapprehension as to one’s obligations under a contact which leads to
non-performance would not amount to repudiation if there is underlying willingness to correct
one’s understanding and fulfill those obligations.
Repudiation Mersey Steel and Iron Co v Naylor Benson & Co (1884) – The HOL held that there was no
(Pg 186) repudiation because Mersey Steel was under a genuine misapprehension that they should
not pay for the shipments.
Wong Poh Oi v Gertrude Guok and Another (1966) – The court held that mere non-payment of
an installment or breach of one term does not necessarily put an end to a contract. Here, the
court found that the plaintiff did not evince an intention not to be bound by the contract. Hence,
the defendant’s purported repudiation was wrongful.
Election
Even when a repudiatory breach is present, the contract is not automatically discharged.
RDC Concrete Pte Ltd v Sato Kogyo (S) Pte Ltd & Another Appeal (2007) – A repudiatory
breach grants the innocent party a right of election as to whether to terminate the contract. He
may choose to accept the repudiation or affirm the contract.
HG Metal Manufacturing Ltd v Nam Tat Hardware Co (2006) – In either case, the innocent
party should communicate unequivocally to the other party his decision.
Clea Shipping Coronation v Bulk Oil International, “The Alaskan Trader” (1984) –
In the absence of “legitimate interest”, the innocent party must accept the anticipatory
breach, treat the contract as discharged and claim the damages.
Risk of Frustration
In affirming the contract, the innocent party places himself at risk that a supervening event may
occur, discharging the contract by frustration.
Avery v Bowen (1855) – It was held that Bowden’s liability for the anticipatory repudiation was
relieved by war which frustrated the contract.
Agreement (Pg 190)
Existing A contract may include a term that it would be discharged upon occurrence of a stipulated event
Agreement or at the expiration of a certain period.
A contract may be discharged by parties entering into a fresh agreement to extinguish the earlier
contract.
When the contract is partially or entire executory, the parties may execute a
mutual release which discharges each party from all their obligations under that
contract.
Mutual
Li Hwee Building Construction Pte Ltd v Advanced Construction & Engineering
Release
Pte Ltd (2002) – The parties may have acted in such a manner as to be
construed as having abandoned the contract, such that the contract is terminated
as a result of the common intention of the parties that it should no longer bind
them.
When one party who has performed all his obligations seeks to discharge the
Unilateral
other party who has not performed all his obligations, then the first party may
Release
execute a release in the form of a deed, so that no consideration is required.
When one party purchases his release with fresh valuable consideration
Accord and
Subsequent provided to the other party, the understanding to do so is the accord and the
Satisfaction
Agreement consideration provided is the satisfaction. This discharges the earlier contract.
Where the contract is altered by a subsequent agreement, supported by fresh
Variation consideration. Depending on the case, the contract may be discharged entirely
or amended by the subsequent agreement.
Where one party, at or without the request of the other party voluntarily grants
the other party an indulgence not to perform an obligation under a contract
without consideration passing, the first party has been given a waiver. Usually
given in respect of specific modes of performance but not usually in respect of
the whole contract, e.g. an employee consistently late. Employer can prevent by
including the clause “no waiver unless in writing” in the employment contract.
Waiver of
Rights
Leivest International Pte Ltd v Top Ten Entertainment Pte Ltd (2006) – When Top
Ten failed to pay the costs and interests on time, Leivest could have terminated
the lease, but chose instead to accept Top Ten’s delayed cheque payment. By its
demand for and acceptance of the costs and rent, Leivest had “waived the
breaches, and it cannot resurrect them”, and Leivest thus could not discharge
the lease agreement.
Davis Contractors Ltd v Fareham Urban District Council (1956) – the House of Lords rejected the appellant’s
claim as the cost increase did not alter the situation so much that the task undertaken was radically different
from what was originally contemplated by the parties. “It is not hardship or inconvenience or material loss itself
which calls the principle of frustration into play. There must be as well such a change in significance of the
obligation that the thing undertaken, would if performed, be a different thing than that contracted for.”