Download as pdf or txt
Download as pdf or txt
You are on page 1of 274

Tolunay-W o n g Engineers, Inc.

10710 S. Sam Houston Pkwy W., Suite 100 / Houston, TX 77031 / 713-722-7064 / Fax 713-777-0341
(J Houston, TX J Beaumont, TX J Corpus Christi, TX J Dallas/Ft. Worth, TX J Gonzales, LA J Gainesville, FL)

COVER

SHEET Email
To: Mr. Peter Tam From: Arthur J. Stephens, P.E.
(peter_tam@fwhou.fwc.com) Phone: 713-722-7064
Foster Wheeler USA Corporation Fax: 713-777-0341 / 713-722-0319
Cell: 832-741-2179
Mr. Andres Contreras Email: astephens@tweinc.com
(Andres_Contreras@fwhou.fwc.com)
Cc: John Brown (jdbrown@tweinc.com) Date: March 16, 2011
TWEI #: 10.14.105.003
Pedro Velandia (pivelandia@gmail.com)
Fouad Hammoud (fhammoud@tweinc.com)
Ref: Subcontract No.: 13-123939-02-CH503
Subcontract Name: Geotechnical Engineering Consulting Services; PMRB
TWEI Ref: PMRB-CH-503.6-135
Subj: Settlement Estimates - Priority 1 Borings C-2, C-3, C-6, C-7, C-10, C-11, C-12, C-14, C-15, Subj:
C-17, C-19, C-20, C-23, C-25, and C-40

Introduction

This report presents our settlement estimates based on the data provided for fifteen Priority 1 Test
Borings: C-2, C-3, C-6, C-7, C-10, C-11, C-12, C-14, C-15, C-17, C-19, C-20, C-23, C-25, and C-
40. This report supersedes three previous settlement reports issued by TWEI:

1) Boring C-19 (BFW Package) issued December 23, 2010; and,


2) Boring C-12 (Unit 8500) issued January 11, 2011;
3) Six Priority 1 Borings C-2, C-3, C-6, C-7, C-11, C-17, and C-25 issued January 20, 2011.

Soil parameters used in our settlement analysis for the Priority 1 borings were compiled from
consolidation tests and correlations to index tests. Settlement was not calculated for boring C-40
because existing ground surface elevation is approximately +76 m, which is equal to design final
grade elevation.

In preparing the settlement estimates, we assumed that the in-place total weight of the fill materials
is approximately 120 pcf. If the total unit weight of the fill materials is less than assumed, the
settlement will be less. The locations of the Priority 1 test borings and the planned Units are shown
on Figure 1. The rough grading and final grade elevations for the various Units are shown on
Figures 2 and 3.

T:\HIG\Projects\2010\10.14.105-003\10-14-105.003-268(135)-Priority 1 Settlement Report.doc


Mr. Peter Tam
Mr. Andres Contreras
March 16, 2011
Page 2

Soil Properties

The following outlines the analysis parameters used. These parameters were compared with the
information from previous borings A-8, A-10, A-13, A-14, B-16, B-18, B-21, B-24, and B-28. The
locations of the fifteen Priority 1 borings and the nine previous borings considered in this report are
shown on Figure 1. The recent test boring logs are shown in Appendix A. Boring logs from the
previous site investigation performed by Gomez, Cajiao y Asociados (GCA) are presented in
Appendix B. Consolidation test results from the Priority 1 test borings are included in Appendix C.
Photographs of the locations of the fifteen Priority 1 borings are included in Appendix A. The SPT
blow counts (N-value) corrected to N60 and total unit weights from the test borings are profiled with
depth and shown on Figures 4 through 33.

Soil stratigraphy generally consists of alternating layers of sands, silts and clays of varying
thicknesses extending to the top of the conglomerate (Alluvium), which was encountered at
elevations ranging from 51.6 m to 43.3 m. Soil stratigraphy and consistency/relative density are
detailed on the boring logs and are summarized on the SPT and total unit weight vs. depth profiles
in Figures 4 through 33. Selected Ground surface elevation at the boring locations varied from 76
m to 72 m msl.

The Alluvium layer, as interpreted from the boring logs presented in Appendices A and B, is
comprised of fine to coarse size gravel, sub-rounded, with a primarily sand matrix. Clayey gravel
lenses were also encountered within the Alluvium. Table 1 lists the elevation of the top of the
Alluvium for the Priority 1 and selected CGA borings.

Table 1
Elevations of Alluvium and Competent Soil
Top of Alluvium Top of Competent Soil
Unit Area Borings (m msl) (m msl)

8200 C-2 49.1 55 (med. dense to dense sand)


C-3 51.4 56 (med. dense to v. dense sand)
B-18 45.0 55 (med. dense to dense sand)
B-21 43.5 56 (med. dense to v. dense sand)
B-24 Not Reached (T.D = 18.5m) 56 (med. dense to v. dense sand)
8600 C-6 45.3 --
8700
8900
9000
6300 C-7 43.3 55 (very dense sand)

T:\HIG\Projects\2010\10.14.105-003\10-14-105.003-268(135)-Priority 1 Settlement Report.doc


Mr. Peter Tam
Mr. Andres Contreras
March 16, 2011
Page 3

Top of Alluvium Top of Competent Soil


Unit Area Borings (m msl) (m msl)

8400 C-10 42.0 52 (dense to v. dense sand)


8300
C-11 44.0 52 (m. dense to v. dense sand)
A-10 45.0 52 (m. dense to v. dense sand)
A-13 43.9 54 (dense to v. dense sand)
8500 C-12 51.6 54 (dense to v. dense sand)
9100 C-14 43.2 --
9200
9400
9500
Sulfur C-15 40.8 --
Storage Area
7100 C-17 50.8 --
C-25 45.8 --
A-8 45.0 --
B-16 45.0 --
6100 C-19 49.3 --
9700 C-20 46.5 53 (v. dense sand)
7300 C-23 Not Reached (T.D. = 43.0m) --
6000 C-40 47.6 --
A-14 46.1 --

Competent sands were identified in Units 6300, 8200, 8300, 8400, 8500, and 9700. The elevations
at the top of the competent soil are shown in Table 1. Medium dense to very dense sands were
encountered above the Alluvium in Priority 1 borings C-2, C-3, C-7, C-10, C-11, C-12 and C-20,
and GCA borings A-10, A-13, B-18, B-21, and B-24. The compactness of these sands is evident in
the N60 vs. depth plots on Figures 4, 6, 10, 12, 14, 16, and 26.

During detailed design, the data regarding the elevations of competent soils developed by the
Priority 1 and Priority 2 test borings should be reviewed. It is likely that piling driven in to the
competent soils will be feasible, which will reduce the need to extend the piles into the deeper
alluvium.

Compressible layers comprised of soft to firm consistency, low to high plasticity lean clays (CL)
and fat clays (CH), and loose elastic silts (MH) were identified in the Priority 1 borings. These soil
T:\HIG\Projects\2010\10.14.105-003\10-14-105.003-268(135)-Priority 1 Settlement Report.doc
Mr. Peter Tam
Mr. Andres Contreras
March 16, 2011
Page 4

layers are shown on Figures 4 through 33. Compressible layer composition, thickness, elevation,
and maximum drainage path for each boring are tabulated in Table 2.

Table 2
Compressible Layer Thicknesses
(m)
Thickness Elevation Maximum Drainage Path,
Boring Compressible Material (m) (m) H/2 (m)

C-2 Soft Lean Clay (CL) 2.07 70.7-68.5 1.035


Loose Elastic Silt (MH) 3 61-58 1.5
C-3 Soft to Firm Fat Clay (CH) 2 74-72 5
Firm to Soft Lean Clay (CL) 3 72-69
Loose Elastic Silt (MH) 6 62.4-56.4 3
C-6 Soft Gray Fat Clay (CH) 4 72-68 2
Loose Elastic Silt (MH) 2.7 61.5-58.8 1.35
Firm Lean Clay (CL) 3 58.8-55.8 1.5
Firm Lean Clay (CL) 3.8 49.1-45.3 1.9
C-7 Soft Sandy Lean Clay (CL) 3 73-70 1.5
“FILL”
Loose Elastic Silt (MH) 2 61-59 1
Firm Sandy Lean Clay (CL) 1.5 58.5-57 0.75
C-10 Soft Clay (CL/CH) 2.5 71-68.5 1.25
Firm to Stiff Clay 7 63-56 3.5
Very Stiff Clay 3 45-42 1.5
C-11 Soft to Stiff Lean Clay (CL) 2.9 72.4-69.5 1.45
Very stiff Clay (CL) 1.2 65.8-64.6 0.6
Very Soft Clay (CH) 6.2 64-57.8 3.1
Stiff Lean Clay (CL) 1.4 47.2-45.8 0.7
C-12 Soft Clay (CL/CH) 2.4 73-70.6 1.2
Loose Elastic Silt (MH) 4.5 61.5-57 2.25
C-14 Soft Clay (CH) 4.8 69.8-65 2.4
Loose Elastic Silt (MH) 4.5 47.5-43 2.25

T:\HIG\Projects\2010\10.14.105-003\10-14-105.003-268(135)-Priority 1 Settlement Report.doc


Mr. Peter Tam
Mr. Andres Contreras
March 16, 2011
Page 5

Thickness Elevation Maximum Drainage Path,


Boring Compressible Material (m) (m) H/2 (m)

C-15 Very Soft Clay (CL) 4.6 69.6-65 2.3


Stiff Clay (CL/CH) 5 61.5-56.5 2.5
Stiff Clay (CL) 5.7 45.5-40.8 2.75
C-17 Soft Clay (CL) “FILL” 2.4 73-70.6
4.0
Soft Clay (CL/CH) 1.6 70.6-69
Firm Clay (CL) 7.1 58.2-51.1 3.5
C-19 Very Soft Clay (CL) 3.1 71.6-68.5 1.55
Very Soft Clay (CH) 4 64-60 2
Organic Clay (OH) 0.5 60-59.5 0.25
Soft to Very Soft Clay (CL) 10.3 59.5-49.2 5.15
C-20 Very Soft Clay (CL) 7.5 73-65.5 5.2
Soft to Firm Clay (CH) 7.7 65.5-57.8
Very Stiff Clay (CL) 1.2 47.4-46.5 0.6
C-23 Soft Clay (CL) 1.6 71-69.4 0.8
Soft Clay (CH) 1.5 58-56.5 0.75
Stiff Clay (CL) 3 47.6-44.6 1.5
C-25 Very Soft Silty Clay (CL-ML) 3 73-70 1.5
Loose Elastic Silt (MH) 1.2 47.2-46 0.6
C-40 Very Soft Clay (CL) 3 73.6-70.6 1.5
Firm Fat Clay (CH) 2 65.5-63.5 N/A
Loose Elastic Silt/Organic 6 63.5-57.5 N/A
Clay (MH/OH)
Very Soft Lean Clay (CL) 4.5 57.5-53 N/A
Elastic Silt/Organic Clay 2.1 53-50.9 N/A
(MH/OH)
N/A = Not analyzed

Consolidation test data from borings C-2, C-6, C-10, C-11, C-12, C-14, C-15, C-17, C-19, C-20, C-
23 and C-25 were used to develop soil parameters for compressible soil layers. Consolidation test
results are attached in Appendix C. Soil parameters for settlement analysis were also obtained

T:\HIG\Projects\2010\10.14.105-003\10-14-105.003-268(135)-Priority 1 Settlement Report.doc


Mr. Peter Tam
Mr. Andres Contreras
March 16, 2011
Page 6

using empirical correlations based on the Atterberg limit (ASTM D 4318) and moisture content
(ASTM D 2166) test data shown on the boring logs enclosed in Appendix A.

Settlement Analysis

The settlement analyses were performed using the program FoSSA. This program considers
various layers, differences in soil properties for each layer, and can simulate the effects of staged
embankment loading. For our analysis and based on correspondence with Foster Wheeler, we
assumed two site fill schedules.

A. Fill Schedule No. 1 – Schedule No. 1 assumes rough grading and final filling will be
completed on a unit-by-unit basis.

Stage 1 Fill – initial fill placement and surfacing from El. 72 m/73m to El. 74.5 m over
a period of 70 days.

Stage 2 Fill – EPC contractor will commence final filling to El. 76.0 m 590 days after
completion of Stage 1 (660 days after Stage 1 start). Final fill will be completed 30
days after that (690 days after Stage 1 start).

B. Fill Schedule No. 2 – Schedule No. 2 assumes fill placement for rough grading and final
site grade will be performed across all units simultaneously.

Stage 1 fill and surfacing will be completed from El. 72/73 m to El. 74.5 m over about
390 days.

Stage 2 fill will commence 510 days after completion of Stage 1 (900 days after Stage 1
start) and will be completed to El. 76.0 m 930 days after start of Stage 1.

Fill Schedules 1 and 2 were analyzed for rate of settlement using drainage paths equal to one-half
the layer thicknesses, as shown on Table 2.

Analysis Results and Discussion

The locations of Borings C-2, C-3, C-6, C-7, C-10, C-11, C-12, C-14, C-15, C-17, C-19, C-20, C-
23, C-25 and C-40 are shown on Figure 1. Figure 1 indicates the locations of existing roadways
which bisect 7100 (Material Storage), 8200 (Delayed Coker) and 8400 (Hydrocracker and Naphtha
Hydrotreater). There is also an existing road that borders the west perimeter of Unit 8500. The
total settlement within the vicinity of the existing roadway areas will be less than the balance of the
unit areas. There is also a large stockpile in Unit 8200 where settlement resulting from site grading
will be minimal once the stockpile of fill and construction debris is removed. The existing stockpile
is approximately 10m high and has plan dimensions of about 200 m by 250 m. Priority 2 boring C-

T:\HIG\Projects\2010\10.14.105-003\10-14-105.003-268(135)-Priority 1 Settlement Report.doc


Mr. Peter Tam
Mr. Andres Contreras
March 16, 2011
Page 7

35 was located at the western edge of the stockpile; the driller’s log indicates variegated fill material
comprised of sands/gravels/clays with concrete/asphalt debris to 5 m depth, followed by alternating
clay and sand layers to 32m, underlain by gravel (Alluvium).

The Ecological Lake was probed by Solingral to assess the depth of water and depth to hard bottom.
The survey was conducted in a boat manned by two people using a ¾ inch steel rod marked every
20 cm. The probes were made in a 30 m x 30 m grid pattern. At each point, the rod was lowered to
the lake bottom and then pushed manually through the sludge/muck layer. At some locations the
rod could not be inserted below lake bottom due to the presence of gravel deposits. Cross sections
prepared by Solingral of the lake indicate a water depth of 2 m to 2.4 m and a very thin to non-
existent muck layer on the lake bottom. Survey grid layout and lake profiles were prepared by
Solingral and are presented in Appendix D.

The time rate of settlement results are shown on Figures 34 through 61. These figures illustrate the
time vs. primary consolidation settlement for Units 6100, 7100, 7100, 8200 through 8700, and 8900
through 9500 under the various assumptions shown. Table 3 quantifies the settlement results for
each unit based on Figures 34 through 61. The ability to predict the time rate of consolidation is a
function of small and discrete drainage paths within the soil column and generally settlements occur
at a faster rate than predicted based on the test borings.

Table 3
Estimated Settlement
Time to Attain
2.5 cm
Differential Differential
End of Stage 1 End of Stage 2 Settlement, Stage Settlement After
Unit Fill Settlement Settlement 1-Stage 2 End of Stage 2
Boring Area Schedule (cm) (cm) (cm) (Days)
C-2 8200 1 5 12 7 <300
2 2 12 7 <300
C-3 8200 1 5 23 18 <300
2 5 23 18 <300
C-6 8600 1 35 52 17 <300
8700
2 35 52 17 <300
8900
9000
C-7 -- 1 6 11 5 <300
2 6 11 5 <300

T:\HIG\Projects\2010\10.14.105-003\10-14-105.003-268(135)-Priority 1 Settlement Report.doc


Mr. Peter Tam
Mr. Andres Contreras
March 16, 2011
Page 8

Time to Attain
2.5 cm
Differential Differential
End of Stage 1 End of Stage 2 Settlement, Stage Settlement After
Unit Fill Settlement Settlement 1-Stage 2 End of Stage 2
Boring Area Schedule (cm) (cm) (cm) (Days)
C-10 8300 1 21 32 11 <300
8400
2 21 32 11 <300
C-11 8400 1 16 31 15 <300
2 16 31 15 <300
C-12 8500 1 24 36 12 <300
2 24 36 12 <300
C-14 9100 1 52 75 23 <300
9200
2 52 75 23 <300
9400
9500
C-15 -- 1 30 46 16 <300
2 30 46 16
C-17 7100 1 13 28 15 <300
2 13 28 15 <300
C-19 6100 1 35 57 22 <600
2 35 57 22 <600
C-20 8700 1 27 60 33 <600
2 27 60 33 <600
C-23 7300 1 20 27 7 <300
2 20 27 7 <300
C-25 7100 1 1 2 1 <300
2 1 2 1 <300

Settlement analysis was not performed for boring C-40. The existing ground surface elevation at
boring C-40 is 75.96 m and final design site grade elevation is +76 m; therefore, settlement in the
vicinity of boring C-40 will be negligible. As shown by Figures 34 through 61, the consolidation
settlement resulting from the placement of fill to El. 74.5 m is nearly completed before the second
stage filling begins. The additional settlement which occurs as a result of filling to El. 76.0 m will
generally be differential with respect to the equipment and structures supported on deep

T:\HIG\Projects\2010\10.14.105-003\10-14-105.003-268(135)-Priority 1 Settlement Report.doc


Mr. Peter Tam
Mr. Andres Contreras
March 16, 2011
Page 9

foundations. The anticipated differential settlement as shown on Table 3 and Figures 34 through 61
ranges from about 1 cm to 33 cm. However, as shown on the figures, the additional settlement as a
result of final filling will occur relatively rapidly after completion of the Stage 2 fill, except at Units
6100 (Boring C-19) and 8700 (Boring C-20). Table 3 shows that differential settlement in all but
two units will reach tolerable limits of 1 inch (2.5 cm) or less within 300 days after end of Stage 2
filling. Allowable differential settlement within Units 6100 and 8700 will be achieved after
approximately 600 days, respectively, for Fill Schedule No. 1 and Fill Schedule No. 2.

This provides a scheduling option to reduce post-construction differential settlement between


shallow foundations, equipment, slabs, and equipment or structures supported on deep foundations.
A schedule which begins filling to El. 76.0 early in the unit development sequence and allows as
much time as possible after filling before slabs or shallow foundations are installed will reduce the
differential settlement with respect to equipment and structures supported on deep foundations to
less than 2.5 cm.

In Unit Areas 6100 (Boring C-19) and 8700 (Boring C-20) the increased time to reduce differential
settlement between pile supported equipment and equipment supported on shallow foundations is a
result of soft compressible layers extending from about El. 64.0 to 49.2 m at Boring C-19, and about
El. 73.0 to 57.8 m at Boring C-20. At these locations, it is likely that there are additional thin seams
which will provide shorter drainage paths than assumed, which will reduce the time required to less
than 600 days. In addition, the actual time rate of settlement should be monitored during fill
placement as outlined below.

Quality Assurance and Quality Control

It is critical that the settlement be monitored prior to fill placement through initial fill placement and
during and following completion of final filling. The monitoring of settlement will provide the
basis to evaluate the site response and provide data for assessing when shallow foundations and
slabs could be constructed.

More detailed comments on the importance of the quality assurance and control observations
follow.

The site preparation activities will affect the EPC contractors’ bids. The EPC contractors will
expect that the site preparation is conducted in strict accordance to the plans and specifications. As
a result, the QA/QC data for the site preparation will be important to the follow-on phases of the
project.

In our opinion, the Owner should consider maintaining the overall responsibility for the QA effort
for this project. Routine QC testing activities can be provided by the site preparation contractor.

T:\HIG\Projects\2010\10.14.105-003\10-14-105.003-268(135)-Priority 1 Settlement Report.doc


Mr. Peter Tam
Mr. Andres Contreras
March 16, 2011
Page 10

The following are critical items for each unit area. Separate reports should be prepared for each
major unit.

Confirmation of the site preparation performed prior to fill placement including stripping,
handling of vegetation, placement of geotextiles and geogrids, and settlement plate
installation;

Details for each settlement plate placed including accurate locations, initial elevations prior
to site filling, and frequent settlement observations as the fill materials are placed and
following completion of the filling. These records should include date, elevation of the fill
at the time of the settlement observations, and total plate settlement since fill placement
began. The records should be presented in tabular and graphical plots of time vs. plate
settlement. These records will be critical to provide the basis for evaluating the post-
construction settlement which could occur between equipment and structures supported on
deep foundations and those bearing in fill.

The settlement plate monitoring should continue during the EPC phase and following the
completion of final site grading.

Documentation of on fill material quality (gradation, Atterberg Limits, CBR, etc.) and the
results of field and laboratory compaction testing.

The final QA/AC reports for the site preparation should include details of earthwork
materials, fill placement, and compaction including drawings showing the elevations and
locations of all field density tests performed for each unit area.

In our opinion, the responsibility for this documentation is too important to be left to the site
preparation contractor.

Summary

This report outlines our settlement estimates for Units 6100, 7100, 7300, 8200, 8300, 8400, 8500,
8600, 8700, 8900, 9000, 9100, 9100, 9400 and 9500, and provides general comments regarding the
expected settlement at Borings C-2, C-3, C-6, C-7, C-10, C-11, C-12, C-14, C-15, C-17, C-19, C-
20, C-23 and C-25. Secondary compression was not considered in our analysis but could be a factor
at some units because of the presence of organic clays, decomposed wood and peats of varying
thicknesses observed within the test borings. Secondary compression is a rearrangement or
breakdown of the soil skeleton due to sustained heavy loads (creep) or decomposition of organic
material. The time rate and magnitude of settlement produced by secondary compression is difficult
to quantify and to predict over time. Ecopetrol should consider performing annual elevation survey
at all critical structures supported on shallow foundations to monitor long term settlement.

T:\HIG\Projects\2010\10.14.105-003\10-14-105.003-268(135)-Priority 1 Settlement Report.doc


Mr. Peter Tam
Mr. Andres Contreras
March 16, 2011
Page 11

Our analysis did not assess liquefaction potential. Liquefaction mitigation will be addressed at
completion of the microzonation-liquefaction study currently being performed by Solingral.

We hope this information proves satisfactory and we are looking forward to the opportunity to
discuss our findings with you.

Sincerely,
Tolunay-Wong Engineers, Inc.
TBPE Registration No.: F-000124

Arthur J. Stephens, P.E.


Executive Vice President
Art/jdb/dee
Attachments: Figure 1: Locations of Priority 1 Borings, Previous Borings, and Planned Units
Figure 2: Rough Grading Elevations
Figure 3: Final Grading Elevations
Figures 4-33: N60 and Total Unit Weight Profiles for Fifteen Priority 1 Borings
Figures 34-61: Time vs. Settlement for Fifteen Priority 1 Borings
Appendix A: Logs of Test Borings w/ Photographs C-2, C-3, C-6, C-7, C-10, C-11, C-12, C-14, C-
15, C-17, C-19, C-20, C-23, C-25, and C-40
Appendix B Logs of CGA Borings A-5, A-8, A-10, A-11, A-13, A-14, B-15, B-16, B-18, B-21, B-
24, B-27 and B-28
Appendix C Consolidation Test Results
Appendix E Ecological Lake Survey Report

T:\HIG\Projects\2010\10.14.105-003\10-14-105.003-268(135)-Priority 1 Settlement Report.doc


TWEI

Figures

T:\HIG\Projects\2010\10.14.105-003\10-14-105.003-268(135)-Priority 1 Settlement Report.doc


Figure 2
Figure 3
TWEI Project No. 10.14.105.003

SPT Profile : C‐2, B‐18
75

Fill: Silty Sand w/ Gravel

70
Soft to Firm Clay

Loose to Medium Dense Sand
65

60
Loose Fine Sand
Elevation, m

Loose Elastic Silt
55

Loose to Dense Clayey/ Silty Sand
50

45 Alluvium

40
0 20 40 60 80 100
C‐2 B‐18
N60, Blows per Foot

Figure 4
TWEI Project No. 10.14.105.003

Total Unit Weight : C‐2
75

Fill: Silty Sand w/ Gravel

70 Soft to Firm Clay

65
Loose to Medium Dense Sand

60
Loose Fine Sand
Elevation, m

Loose Elastic Silt
55

Loose to Dense Clayey/ Silty Sand

50

Alluvium

45

40
0 5 10 15 20 25 30
Total Unit Weight, kN/m3

Figure 5
TWEI Project No. 10.14.105.003

SPT Profile : C‐3, B‐21, B‐24
75
Fill: Soft to Firm Clay

70 Soft to Firm Clay

Very Loose to Very Dense Fine Sand/ Silty Sand 


65

60
Loose Elastic Silt/Very Soft Organic Clay
Elevation, m

55
Medium Dense to Very Dense Sand/ Silty Sand

50

Alluvium

45

40
0 20 40 60 80 100
C‐3 B‐21 B‐24

N60, Blows per Foot

Figure 6
TWEI Project No. 10.14.105.003

Total Unit Weight : C‐3
75
Fill: Soft to Firm Clay

70 Soft to Firm Soft Clay

Very Loose to Very Dense Fine Sand/ Silty Sand 


65

60
Loose Elastic Silt/Very Soft Organic Clay
Elevation, m

55
Medium Dense to Very Dense Sand/ Silty Sand

50

Alluvium

45

40
0 5 10 15 20 25 30
Total Unit Weight, kN/m3

Figure 7
TWEI Project No. 10.14.105.003

SPT Profile : C‐6
75

70
Soft Clay

65
Medium Dense to Loose Silty Sand

Firm Clay
60 Loose Elastic Silt
Elevation, m

Very Stiff Lean Clay
55

Very  Dense Sand

50

Firm Clay

45

Medium Dense to Very Dense Alluvium 
40
0 20 40 60 80 100
N60, Blows per Foot

Figure 8
TWEI Project No. 10.14.105.003

Total Unit Weight : C‐6
75

70
Soft Clay

65
Medium Dense to Loose Silty Sand

Firm Clay
60 Loose Elastic Silt
Elevation, m

Very Stiff Lean Clay
55

Very Dense Sand

50
Firm Clay

45

Medium Dense to Very DenseAlluvium 

40
0 5 10 15 20 25 30
Total Unit Weight, kN/m3

Figure 9
TWEI Project No. 10.14.105.003

SPT Profile : C‐7
75

Fill: Silty Clay

70

Loose to Medium Dense Sand w/Silt
65

60 Loose Elastic Silt
Elevation, m

Loose Sand w/Silt
Firm Sandy Lean Clay

55

Loose to Very Dense Sand w/Silt

50

45 Medium Dense Sand w/ Silt

Alluvium
40
0 20 40 60 80 100
N60, Blows per Foot

Figure 10
TWEI Project No. 10.14.105.003

Total Unit Weight : C‐7
75

Fill: Silty Clay

70

Loose to Medium Dense Sand w/Silt
65

60 Loose Elastic Silt
Elevation, m

Loose Sand w/Silt
Firm Sandy Lean Clay

55

Loose to Very Dense Sand w/Silt

50

45 Medium Dense Sand w/ Silt

Alluvium
40
0 5 10 15 20 25 30
Total Unit Weight, kN/m3

Figure 11
TWEI Project No. 10.14.105.003

SPT Profile : C‐10

Fill Material
70 Soft Clay

Medium Dense Sand
65

60 Firm to Stiff Clay

55
Elevation, m

Medium Dense Sand

50
Dense to Very Dense Sand
Dense to Very Dense Sand

45
Stiff to Very Stiff Clay

40

Alluvium

35
0 20 40 60 80 100

N60, Blows per Foot

Figure 12
TWEI Project No. 10.14.105.003

Total Unit Weight : C‐10

Fill Material
70 Soft Clay

Medium Dense Sand
65

60

Firm to Stiff Clay

55
Elevation, m

Medium Dense Sand

50
Dense to Very Dense Sand

45
Stiff to Very Stiff Clay

40

Alluvium

35
0 5 10 15 20 25 30 35
Total Unit Weight, kN/m3

Figure 13
TWEI Project No. 10.14.105.003

SPT Profile : C‐11, A‐10
75
Fill Material

Soft to stiff Clay
70

Loose to Medium Dense Fine Sand

65 Very Stiff Clay

Very Stiff Clay
Dense Fine Sand

60 Very Soft Clay
Elevation, m

55

Loose to Very Dense Sand

50

Stiff Lean Clay
45 Medium dense to Very Dense Sand

Alluvium

40
0 20 40 60 80 100
C‐11 A‐10

N60, Blows per Foot

Figure 14
TWEI Project No. 10.14.105.003

Total Unit Weight : C‐11
75
Fill Material

Soft to stiff Clay
70

Medium Dense Fine Sand

65 Very Stiff Clay

Very Stiff Clay Dense Fine Sand

60 Very Soft Clay
Elevation, m

55

Dense to Very Dense Sand

50

Stiff Lean Clay
45 Medium Dense to Very Dense Sand

Alluvium

40
0 5 10 15 20 25 30
Total Unit Weight, kN/m3

Figure 15
TWEI Project No. 10.14.105.003

SPT P fil C
SPT Profile : C‐12, A‐13
12 A 13
75

Soft Clay
70
Very Loose Silty Sand/Silt w/ Sand 
Very Loose Silty Sand/Silt w/ Sand

65 Medium Dense Sand

60 Loose to Medium Dense Elastic Silt
Elevation, m

Loose to Medium Dense Silty Sand
55
Dense to Very Dense
Dense to Very Dense Sand
Sand

50 Alluvium

45

40
0 20 40 60 80 100
C‐12 A‐13
N60, Blows per Foot

Figure 16
TWEI Project No. 10.14.105.003

Total Unit Weight Profile ‐ C‐12

75

Soft Clay
70
Very loose Silty Sand/ Silt w/ Sand

Medium Dense Sand
65

60
Loose  To Medium Dense Elastic Silt
Elevation, m
evation, m

Loose to Medium Dense Silty Sand
55

Dense to Very Dense Sand
Dense to Very Dense Sand

50
Alluvium

45

40
0 5 10 15 20 25 30
T l U i W i h KN/ 3
Total Unit Weight, KN/m

Figure 17
TWEI Project No. 10.14.105.003

SPT Profile : C‐14

70 Fill Material

Soft Clay

65

Loose to Dense Sand
60

Medium Dense Elastic Silt
55
Elevation, m

Dense to Very Dense Sand
50

Medium Dense Sand

Loose Elastic Silt
45
Stiff Clay

40

Alluvium

35
0 20 40 60 80 100

N60, Blows per Foot

Figure 18
TWEI Project No. 10.14.105.003

Total Unit Weight : C‐14

70 Fill Material

Soft Clay
65

Loose to Dense Sand
60

Medium Dense Elastic Silt
55
Elevation, m

Dense to Very Dense Sand

50
Medium Dense Sand

Loose Elastic Silt
45
Stiff Clay

40

Alluvium

35
0 5 10 15 20 25 30 35
Total Unit Weight, kN/m3

Figure 19
TWEI Project No. 10.14.105.003

SPT Profile : C‐15

70 Fill Material
Very Soft Clay
65
Loose to Medium Dense Sand
60
Firm to Stiff Clay
55 Loose to Medium Dense Sand

50
Dense to Very Dense Sand
45
Firm to Very stiff Clay w/ Gravel
Elevation, m

40

35

30

25
Alluvium
20

15

10
0 20 40 60 80 100

N60, Blows per Foot

Figure 20
TWEI Project No. 10.14.105.003

Total Unit Weight : C‐15

Fill Material
70
Very Soft to Soft Clay
65
Loose to Medium Dense Sand
60
Stiff Clay
55 Loose to Medium Dense Sand

50 Dense to Very Dense Sand

45
Firm to Very stiff Clay w/ Gravel
Elevation, m

40

35

30 Alluvium

25

20

15

10
0 5 10 15 20 25 30
Total Unit Weight, kN/m3

Figure 21
TWEI Project No. 10.14.105.003

SPT Profile : C‐17, B‐16

Fill Material : Silty Clay

70 Soft Silty Clay

65

Loose to Medium Dense Sand

60
Elevation, m

55
Firm Clay

50

Alluvium

45

40
0 20 40 60 80 100
C‐17 B‐16

N60, Blows per Foot

Figure 22
TWEI Project No. 10.14.105.003

Total Unit Weight : C‐17

Fill Material : Silty Clay

70 Soft Silty Clay

65

Loose to Medium Dense Sand

60
Elevation, m

55
Firm Clay

50

Alluvium

45

40
0 5 10 15 20 25 30

Total Unit Weight, kN/m3

Figure 23
TWEI Project No. 10.14.105.003

Total Unit Weight Profile ‐ C‐19

75

Fill: Loose Sandy Silt w/ Gravel

70 Very Soft to Firm Clay

Medium Dense Sand
65

Soft to Very Soft Clay

60

Organic Clay
Elevation, m
vation, m

55

Very Soft to FirmClay
50

45
Alluvium

40
0 5 10 15 20 25 30

Total Unit Weight, kN/m3

Figure 25
TWEI Project No. 10.14.105.003

SPT Profile : C‐20

70

Very Soft Clay

65

60
Very Soft to Soft Clay
Elevation, m

Medium Dense to Dense Sand
55

Alluvium
50

Very Stiff Clay
45

Alluvium

40
0 20 40 60 80 100

N60, Blows per Foot

Figure 26
TWEI Project No. 10.14.105.003

Total Unit Weight : C‐20

70

Very Soft Clay

65

60
Very Soft to Soft Clay
Elevation, m

Medium Dense to Dense Sand
55

50
Alluvium

Very Stiff Clay
45

Alluvium

40
0 5 10 15 20 25 30
Total Unit Weight, kN/m3

Figure 27
TWEI Project No. 10.14.105.003

SPT Profile : C‐23

70 Soft Clay

Loose Sand

65
Dense Sand

Medium Dense Sand
60

Soft Clay
Elevation, m

55

Dense Sand
Dense Sand

50

Stiff Clay
45
Medium Dense Silty Sand

Firm to Stiff Clay
40
0 20 40 60 80 100

N60, Blows per Foot

Figure 28
TWEI Project No. 10.14.105.003

Total Unit Weight : C‐23

70 Soft Clay

Loose Sand

65
Dense Sand

Medium Dense Sand
60

Soft Clay
Elevation, m

55

Dense Sand
Dense Sand

50

Stiff Clay
45
Medium Dense Silty Sand

Firm to Stiff Clay
40
0 5 10 15 20 25 30
Total Unit Weight, kN/m3

Figure 29
TWEI Project No. 10.14.105.003

SPT Profile : C‐25
75

Very Soft Silty Clay

70

Loose to  Very Dense Sand
65

60
Elevation, m

55

50
Loose Elastic Silt
Hard Clay
45

Alluvium

40
0 20 40 60 80 100
N60, Blows per Foot

Figure 30
TWEI Project No. 10.14.105.003

Total Unit Weight : C‐25
75

Very Soft Silty Clay

70

Loose to Very Dense Sand
65

60
Elevation, m

55

50
Loose Elastic Silt
Hard Clay
45

Alluvium

40
0 5 10 15 20 25 30
Total Unit Weight, kN/m3

Figure 31
TWEI Project No. 10.14.105.003

SPT Profile : C‐40, A‐14

75 Fill: Very Loose to Loose Gravel/Clay/Sand

Very Soft Clay
70

Loose to Medium Dense Sand

65
Firm Clay

Loose Elastic Silt
60
Elevation, m

55
Very Soft Clay

Medium Dense Elastic Silt

50 Stiff Sandy Clay
Loose Sand

45

Alluvium

40
0 20 40 60 80 100
C‐40 A‐14

N60, Blows per Foot

Figure 32
TWEI Project No. 10.14.105.003

Total Unit Weight : C‐40

75
Fill: Very Loose to Loose Gravel/Clay/Sand

Very Soft Clay
70

Loose to Medium Dense Sand

65
Firm Clay

60 Loose Elastic Silt
Elevation, m

55 Very Soft Clay

Medium Dense Elastic Silt
50 Stiff Sandy Clay
Loose Sand

45

Alluvium

40
0 5 10 15 20 25 30
Total Unit Weight, kN/m3

Figure 33
TWEI Project No. 10.14.105.003 Settlement ‐ Staged Fill Placement, Schedule No. 1, Maximum Drainage Path = 1.5 m
Boring C‐2

Days
1 10 100 1000 10000
0.00
End Stage 1 Startof Stage 2 End of Stage 2
70 Days 660 Days 690 Days
0.02

0.04
Settlement, m

0.06
Stage 1 ‐ 74.5 m
Stage 2 ‐ 76.0 m

0.08
0 08

0.10

0.12

0.14

Figure 34
TWEI Project No. 10.14.105.003 Settlement ‐ Staged Fill Placement, Schedule No. 2 Max Drainage Path = 1.5 m
Boring C‐2

Startof Stage 2
Days
900 Days
1 10 100 1000 10000
0.00
End of Stage 2
End Stage 1 930 Days
390 Days
0.02

0.04 Stage 1 ‐ 74.5m


Stage 2 ‐ 76.0m
Settlement, m

0.06

0.08
0 08

0.10

0.12

0.14

Figure 35
TWEI Project No. 10.14.105.003 Settlement ‐ Staged Fill Placement, Schedule No. 1m Maximum Drainage Path = 5 m
Boring C‐3

Days
1 10 100 1000 10000
0.00
End Stage 1 Startof Stage 2 End of Stage 2
70 Days 660 Days 690 Days

0.05
Settlement, m

0.10

Stage 1 ‐ 74.5m
Stage 2 ‐ 76.0m

0.15

0.20

0.25

Figure 36
TWEI Project No. 10.14.105.003 Settlement ‐ Staged Fill Placement, Schedule No. 2, Maximum Drainage Path = 5 m
Boring C‐3

Startof Stage 2
Days
900 Days
1 10 100 1000 10000
0.00
End of Stage 2
End Stage 1 930 Days
390 Days

0.05

Stage 1 ‐ 74.5m
Stage 2 ‐ 76.0m
Settlement, m

0.10

0.15

0.20

0.25

Figure 37
TWEI Project No. 10.14.105.003 Settlement ‐ Staged Fill Placement, Schedule No. 1, Maximum Drainage Path = 2 m
Boring C‐6

Days
1 10 100 1000 10000
0.00
End Stage 1 Startof Stage 2 End of Stage 2
70 Days 660 Days 690 Days

0.10

0.20
Settlement, m

0.30 Stage 1 ‐ 74.5m


Stage 2 ‐ 76.0m

0.40

0.50

0.60

Figure 38
TWEI Project No. 10.14.105.003 Settlement ‐ Staged Fill Placement, Schedule No. 2, Maximum Drainage Path = 2 m
Boring C‐6

Startof Stage 2
Days
900 Days
1 10 100 1000 10000
0.00
End of Stage 2
End Stage 1 930 Days
390 Days
0.10

Stage 1 ‐ 74.5m

0.20 Stage 2 ‐ 76.0m


Settlement, m

0.30

0.40

0.50

0.60

Figure 39
TWEI Project No. 10.14.105.003 Settlement ‐ Staged Fill Placement, Schedule No. 1, Maximum Drainage Path = 1.5 m
Boring C‐7

Days
1 10 100 1000 10000
0.00
End Stage 1 Startof Stage 2 End of Stage 2
70 Days 660 Days 690 Days

0.02

0.04
Settlement, m

0.06 Stage 1 ‐ 74.5m


Stage 2 ‐ 76.0m

0.08

0.10

0.12

Figure 40
TWEI Project No. 10.14.105.003 Settlement ‐ Staged Fill Placement, Schedule No. 2, Maximum Drainage Path = 1.5 m
Boring C‐7

Startof Stage 2
Days
900 Days
1 10 100 1000 10000
0.00
End of Stage 2
End Stage 1 930 Days
390 Days
0.02

Stage 1 ‐ 74.5m

0.04 Stage 2 ‐ 76.0m


Settlement, m

0.06

0.08

0.10

0.12

Figure 41
TWEI Project No. 10.14.105.003 Settlement ‐ Staged Fill Placement, Schedule No. 1, Maximum Drainage Path = 3.5 m
Boring C‐10

Days
1 10 100 1000 10000
0.00
End Stage 1 Startof Stage 2 End of Stage 2
70 Days 660 Days 690 Days
0.05

0.10
Settlement, m

0.15

Stage 1 ‐ 74.5m

Stage 2 ‐ 76.0m
0.20
0 20

0.25

0.30

0.35

Figure 42
TWEI Project No. 10.14.105.003 Settlement ‐ Staged Fill Placement, Schedule No. 2, Maximum Drainage Path = 3.5 m
Boring C‐10

Startof Stage 2
Days 900 Days
1 10 100 1000 10000
0.00
End of Stage 2
End Stage 1 930 Days
0.05 390 Days

0.10
Stage 1 ‐ 74.5 m Stage 2 ‐ 76.0 m
Settlement, m

0.15

0.20
0 20

0.25

0.30

0.35

Figure 43
TWEI Project No. 10.14.105.003 Settlement ‐ Staged Fill Placement, Schedule No. 1, Maximum Drainage Path = 3.1 m
Boring C‐11

Days
1 10 100 1000 10000
0.000
End Stage 1 Startof Stage 2 End of Stage 2
70 Days 660 Days 690 Days
0.050

0.100
Settlement, m

0.150

Stage 1 ‐ 74.5m
Stage 2 ‐ 76.0m
0.200
0 200

0.250

0.300

0.350

Figure 44
TWEI Project No. 10.14.105.003 Settlement ‐ Staged Fill Placement, Schedule No. 2, Maximum Drainage Path = 3.1 m
Boring C‐11

Startof Stage 2
Days
900 Days
1 10 100 1000 10000
0.000
End of Stage 2
End Stage 1 930 Days
390 Days
0.050

0.100 Stage 1 ‐ 74.5m


Stage 2 ‐ 76.0m
Settlement, m

0.150

0.200
0 200

0.250

0.300

0.350

Figure 45
TWEI Project No. 10.14.105.003 Settlement ‐ Staged Fill Placement, Schedule No. 1, Maximum Drainage Path = 2.25 m
Boring C‐12

Days
1 10 100 1000 10000
0.00
End Stage 1 Startof Stage 2 End of Stage 2
70 Days 660 Days 690 Days
0.05

0.10
Settlement, m

0.15

Stage 1 ‐ 74.5m
0.20
Stage 2 ‐ 76.0m

0.25

0.30

0.35

0.40

Figure 46
TWEI Project No. 10.14.105.003 Settlement ‐ Staged Fill Placement, Schedule No. 2, Maximum Drainage Path = 2.25 m
Boring C‐12

Startof Stage 2
Days
900 Days
1 10 100 1000 10000
0.00
End of Stage 2
End Stage 1 930 Days
0.05 390 Days

0.10
Stage 1 ‐ 74.5m
Stage 2 ‐ 76.0m
Settlement, m

0.15

0.20

0.25

0.30

0.35

0.40

Figure 47
TWEI Project No. 10.14.105.003 Settlement ‐ Staged Fill Placement, Schedule No. 1, Maximum Drainage Path = 2.4 m
Boring C‐14

Days
1 10 100 1000 10000
0.00
End Stage 1 Startof Stage 2 End of Stage 2
70 Days 660 Days 690 Days
0.10

0.20
Settlement, m

0.30

0.40 Stage 1 ‐ 74.5m Stage 2 ‐ 76.0m

0.50

0.60

0.70

0.80

Figure 48
TWEI Project No. 10.14.105.003 Settlement ‐ Staged Fill Placement, Schedule No. 2, Maximum Drainage Path = 2.4 m
Boring C‐14

Startof Stage 2
Days 900 Days
1 10 100 1000 10000
0.00
End of Stage 2
End Stage 1 930 Days
0.10 390 Days

0.20
Stage 1 ‐ 74.5 m Stage 2 ‐ 76.0 m
Settlement, m

0.30

0.40

0.50

0.60

0.70

0.80

Figure 49
TWEI Project No. 10.14.105.003 Settlement ‐ Staged Fill Placement, Schedule No. 1, Maximum Drainage Path=2.75 m
Boring C‐15

Days
1 10 100 1000 10000
0.00
End Stage 1 Startof Stage 2 End of Stage 2
0.05 70 Days 660 Days 690 Days

0.10

0.15
Settlement, m

0.20

Stage 1 ‐ 74.5m
0.25
Stage 2 ‐ 76.0m

0.30

0.35

0.40

0.45

0.50

Figure 50
TWEI Project No. 10.14.105.003 Settlement ‐ Staged Fill Placement, Schedule No. 2, Maximum Drainage Path= 2.75 m
Boring C‐15

Startof Stage 2
Days 900 Days
1 10 100 1000 10000
0.00
End of Stage 2
End Stage 1 930 Days
0.05
390 Days

0.10

Stage 1 ‐ 74.5 m
0.15
Stage 2 ‐ 76.0 m
Settlement, m

0.20

0.25

0.30

0.35

0.40

0.45

0.50

Figure 51
TWEI Project No. 10.14.105.003 Settlement ‐ Staged Fill Placement, Schedule No. 1, Maximum Drainage Path = 4 m
Boring C‐17

Days
1 10 100 1000 10000
0.000
End Stage 1 Startof Stage 2 End of Stage 2
70 Days 660 Days 690 Days

0.050

0.100
Settlement, m

Stage 1 ‐ 74.5m
0.150
Stage 2 ‐ 76.0m

0.200

0.250

0.300

Figure 52
TWEI Project No. 10.14.105.003 Settlement ‐ Staged Fill Placement, Schedule No. 2, w/ Maximum Drainage Path = 4 m
Boring C‐17

Startof Stage 2
Days
900 Days
1 10 100 1000 10000
0.000
End of Stage 2
End Stage 1 930 Days
390 Days
0.050

Stage 1 ‐ 74.5m
0.100 Stage 2 ‐ 76.0m
Settlement, m

0.150

0.200

0.250

0.300

Figure 53
TWEI Project No. 10.14.105.003 Settlement ‐ Staged Fill Placement, Schedule No. 1, Maximum Drainage Path = 5.15m
Boring C‐19

Days
1 10 100 1000 10000
0.00
End Stage 1 Startof Stage 2 End of Stage 2
70 Days 660 Days 690 Days
0.10

0.20
Settlement, m

0.30

Stage 1 ‐ 74.5m
Stage 2 ‐ 76.0m
0.40
0 40

0.50

0.60

0.70

Figure 54
TWEI Project No. 10.14.105.003 Settlement ‐ Staged Fill Placement, Schedule No. 2, Maximum Drainage Path = 5.15m
Boring C‐19

Startof Stage 2
Days
900 Days
1 10 100 1000 10000
0.00
End of Stage 2
End Stage 1 930 Days
390 Days
0.10

0.20 Stage 1 ‐ 74.5m

Stage 2 ‐ 76.0m
Settlement, m

0.30

0.40
0 40

0.50

0.60

0.70

Figure 55
TWEI Project No. 10.14.105.003 Settlement ‐ Staged Fill Placement, Schedule No. 1,  Maximum Drainage Path = 5.2 m
Boring C‐20

Days
1 10 100 1000 10000
0.00
End Stage 1 Startof Stage 2 End of Stage 2
70 Days 660 Days 690 Days
0.10

0.20
Settlement, m

0.30

Stage 1 ‐ 74.5m Stage 2 ‐ 76.0m

0.40
0 40

0.50

0.60

0.70

Figure 56
TWEI Project No. 10.14.105.003 Settlement ‐ Staged Fill Placement, Schedule No. 2,  Maximum Drainage Path = 5.2 m
Boring C‐20

Startof Stage 2
Days 900 Days
1 10 100 1000 10000
0.00
End of Stage 2
End Stage 1 930 Days
390 Days
0.10

0.20 Stage 1 ‐ 74.5 m

Stage 2 ‐ 76.0 m
Settlement, m

0.30

0.40
0 40

0.50

0.60

0.70

Figure 57
TWEI Project No. 10.14.105.003 Settlement ‐ Staged Fill Placement, Schedule No. 1, Maximum Drainage Path = 1.5 m
Boring C‐23

Days

1 10 100 1000 10000


0.00

End Stage 1 End of Stage 2


Startof Stage 2
70 Days 690 Days
660 Days

0.05

0.10
Settlement, m

0.15

Stage 1 ‐ 74.5m

Stage 2 ‐ 76.0m

0.20

0.25

0.30

0.35

Figure 58
TWEI Project No. 10.14.105.003 Settlement ‐ Staged Fill Placement, Schedule No. 2,  Maximum Drainage Path = 1.5 m
Boring C‐23

Startof Stage 2
Days 900 Days
1 10 100 1000 10000
0.00
End of Stage 2
930 Days
End Stage 1
390 Days
0.05

0.10 Stage 1 ‐ 74.5 m

Stage 2 ‐ 76.0 m
Settlement, m

0.15

0.20

0.25

0.30

0.35

Figure 59
TWEI Project No. 10.14.105.003 Settlement ‐ Staged Fill Placement, Schedule No. 1, Maximum Drainage Path = 1.5 m
Boring C‐25

Days
1 10 100 1000 10000
0.000
End Stage 1 Startof Stage 2 End of Stage 2
70 Days 660 Days 690 Days

0.005
Settlement, m

0.010

Stage 1 ‐ 74.5m
Stage 2 ‐ 76.0m

0.015

0.020

0.025

Figure 60
TWEI Project No. 10.14.105.003 Settlement ‐ Staged Fill Placement, Schedule No. 2, Maximum Drainage Path = 1.5 m
Boring C‐25

Startof Stage 2
Days
900 Days
1 10 100 1000 10000
0.000
End of Stage 2
End Stage 1 930 Days
390 Days

0.005

Stage 1 ‐ 74.5m
Stage 2 ‐ 76.0m
Settlement, m

0.010

0.015

0.020

0.025

Figure 61
TWEI

Appendix A
Logs of Test Borings w/ Photographs
(C-2, C-3, C-6, C-7, C-10, C-11, C-12, C-14, C-15, C-17, C-19, C-20, C-23, C-25,
And C-40)

T:\HIG\Projects\2010\10.14.105-003\10-14-105.003-268(135)-Priority 1 Settlement Report.doc


TWEI

Appendix B
Logs of CGA Borings
(A-8, A-10, A-13, A-14, B-15, B-16, B-18, B-21, B-24, And B-28)

T:\HIG\Projects\2010\10.14.105-003\10-14-105.003-268(135)-Priority 1 Settlement Report.doc


TWEI

Appendix C
Consolidation Test Results

T:\HIG\Projects\2010\10.14.105-003\10-14-105.003-268(135)-Priority 1 Settlement Report.doc


TWEI

Appendix D
Ecological Lake Survey Report

T:\HIG\Projects\2010\10.14.105-003\10-14-105.003-268(135)-Priority 1 Settlement Report.doc

You might also like